{"document":{"slug":"rec-20260821-5220","title":"Comments of Advanced Energy United in response to PJM Interconnection, L.L.C.’s 07/31/2026 filing","issued":"2026-08-21","accession":"20260821-5220","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Advanced Energy United","kind":"comments","file":"sources/filings/text/20260821-5220_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5220","tier":"record","sha256":"49711740e92162c6097a3010716ac9d2788197f3219ead2dc64f9a2f5cf2e642","pages":30,"tokens":8650,"emptyPages":[],"textThemes":["adequacy","flex","cost","colo"]},"pages":[{"page":1,"startToken":0,"endToken":292,"text":"1 \nUNITED STATES OF AMERICA  \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n) \nPJM Interconnection, L.L.C    \n \n) \n \nDocket No. ER26-3380-000   \n \n) \n \n  \n \n \n \n \n \n \n \n \n \n \nCOMMENTS OF ADVANCED ENERGY UNITED  \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission”) \nRules of Practice and Procedures,1 Advanced Energy United2 (“United”) submits these \ncomments in response to PJM Interconnection, L.L.C.’s (“PJM”) revisions to the PJM Open \nAccess Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load \nServing Entities (“RAA”) to establish the Reliability Backstop Procurement (“RBP”).3 United \ngenerally supports PJM’s July 31, 2026, filing as the best available solution to address the \npressing challenge of rapid load growth and slow resource entry in a manner that avoids putting \neven greater cost burden on existing customers not contributing to the resource adequacy \nshortfall. However, RBP is far from an ideal outcome, and must be implemented in a manner that \navoids perverse and distortionary outcomes that could undermine the investment landscape in \nPJM. Advanced Energy United’s comments below point to areas that need clarification and/or \ncommitment from PJM, both in the context of RBP itself and to improve the region’s resource \nadequacy outlook moving forward.  \n \n1 18 C.F.R. § 385.211 \n2 Advanced Energy United is a national association of businesses that are making the energy we use secure, clean, \nand affordable. Advanced Energy United is the only industry association in the United States that represents the full \nrange of advanced energy technologies and services, both grid-scale and distributed. Advanced energy includes \nenergy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and more. \n3 PJM Interconnection, L.L.C. “Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from Large Loads” Docket No. ER26-3380-000 (filed July 31, 2026) (“Transmittal Letter”)."},{"page":2,"startToken":292,"endToken":565,"text":"2 \nI. \nINTRODUCTION \nPJM is navigating a genuinely difficult situation, and the RBP reflects real effort to \ndesign a workable response under significant time pressure. United and its members have been \nactive participants throughout the stakeholder process leading to this filing, and the RBP \nframework and related Interim Resource Adequacy Service (“IRAS”) proposal as proposed \nreflect meaningful refinement from the concepts PJM initially floated through the Critical Issue \nFast Path processes earlier this year and in 2025. For these reasons and because of the urgency of \ntaking action, United does not oppose the RBP mechanism PJM has proposed.  \nUnited’s support, however, is not without reservation. The comments below identify \nspecific areas where PJM’s proposal falls short of its own stated objectives, or where PJM’s own \nreasoning for excluding otherwise-qualified resources does not withstand scrutiny. United urges \nthe Commission to direct PJM to act on these issues promptly, for two related reasons. First, \nseveral of the barriers discussed below—particularly with respect to Surplus Interconnection \nService and demand-side resources—unnecessarily constrain the pool of fast-to-deploy capacity \navailable to the RBP, and addressing them would materially improve PJM’s chances of actually \nfilling the shortfall the RBP is designed to address. Second, and more broadly, these same \nbarriers bear directly on the success of PJM’s separate Build Your Own New Capacity \n(“BYONC”) initiative and on the durability of investment confidence in PJM generally; \nresolving them now will pay dividends well beyond this single procurement. United emphasizes \nthat RBP was conceived, and must remain, a one-time, bounded response to the specific shortfall \nidentified in the 2028/2029 Base Residual Auction, not a template PJM may invoke unilaterally"},{"page":3,"startToken":565,"endToken":847,"text":"3 \neach time a future auction falls short. United’s comments accordingly conclude with specific \nrecommendations to ensure the mechanism does not outlive its stated purpose. \nII. \nCOMMENTS \nA. RBP Includes Important Elements that will Contribute to its Success \nPJM should be commended for several elements of the RBP design that will support full \nparticipation by qualified resources and promote fair outcomes for developers navigating the \nprocurement’s compressed timeline. \nFirst, United supports the shortfall-charge exception for resources unable to meet their \nexpected commercial operation date solely due to Network Upgrades, where the resource \ndemonstrates readiness through test energy and seeks interim deliverability.4 Network Upgrade \ncosts and schedules represent one of the largest sources of risk facing new capacity development \nin PJM today. A meaningful share of the resources best positioned to participate in the RBP are \ncurrently at some stage of the interconnection process, and without this exception, those \nresources would bear shortfall-charge risk for delays entirely outside their control, a result that \nwould needlessly shrink the pool of supply available to the RBP at the exact moment PJM most \nneeds it to be as large as possible.  \nUnited cautions, however, that this exception addresses only one element of the risk that \nprojects still in the queue face: it excuses the shortfall charge itself, but developers must still \nprice uncertain Network Upgrade costs and schedules into their RBP bids, and continue to bear \nreal cost and schedule risk for as long as their projects remain queued. This exception is a \nnecessary and well-designed accommodation, but it is not a substitute for PJM continuing to \nprioritize a faster, more predictable interconnection process and to resolve Network Upgrade cost \n \n4 Transmittal Letter at 60."},{"page":4,"startToken":847,"endToken":1128,"text":"4 \nand schedule uncertainty that persists even after a generator interconnection agreement is signed. \nBoth the Commission and PJM should remain actively engaged on these challenges well beyond \nthe scope of this proceeding. \nSecond, United also welcomes PJM’s decision to allow new load to use Surplus \nInterconnection Service (“SIS”) capacity to reduce its own RBP obligation as Qualifying RBP \noffset UCAP.5 Recognizing SIS-derived capacity as legitimate, usable supply for these purposes \nis the right outcome. United notes, however, that this recognition does not currently extend to \nallowing SIS-based resources to sell directly into the RBP, an asymmetry United addresses \nseparately. Nor does it resolve barriers to full utilization of SIS to deliver new capacity to the \nPJM region, an issue that United urges PJM to resolve expeditiously outside of the RBP \nproceeding, as discussed below. \nThird, United appreciates PJM’s inclusion of Demand Response and DER Aggregation \nResources as eligible sources of Qualifying RBP Offset UCAP MW, including their use as a \nbridge for new load pending availability of generation or storage capacity not yet in service.6 \nUnited welcomes this bridge function as one use case among several, but does not read it as \nlimiting the role Demand Response and DER Aggregation Resources can or should play; these \nresources provide durable capacity, energy, and congestion relief value independent of whether \nnew generation or storage is also under development, and PJM’s Tariff should recognize that \nstanding value rather than treating demand-side participation as merely transitional. Demand-\nside resources are flexible, comparatively affordable, and capable of being deployed quickly \nrelative to new-build generation, and their inclusion here is a meaningful step, even as United \n \n5 Id at 36. \n6 Id at 40."},{"page":5,"startToken":1128,"endToken":1385,"text":"5 \nrequests additional flexibility regarding their eligibility to participate as RBP Resources, as \ndiscussed below.  \nFourth, United supports the narrow opt-out PJM has proposed for Electric Distributor \nzones/areas with a qualifying peak-shaving adjustment.7 However, as discussed below, this \nprovision requires clarification to ensure it functions as intended alongside PJM’s separate \nInterim Resource Adequacy Service (“IRAS”) filing.  \nPJM has made genuine progress toward a workable backstop mechanism, and it is against \nthat backdrop that United respectfully identifies, in the comments below, the specific \nclarifications and commitments needed to ensure RBP achieves its intended purpose without \ncreating new barriers to the very resources best positioned to help. \nB. Some Elements of RBP Require Clarification or Further Commitment \n \nPJM indicated that it would accept discrete revisions from the Commission “where such \nmodification and/or severance is consistent with PJM’s overarching objectives in this filing.”8 In \nthis context, United respectfully offers the following opportunities to enhance the RBP, provided \nthat they can be implemented such that they do not “give[…] rise to complications” or cause \ndelay of the RBP and/or BRA for the 2029/2030 delivery year.9 The discrete recommendations \nbelow aim to increase supply in the RBP and improve PJM’s overall resource adequacy outlook. \nTo the extent any of these recommendations would delay implementation of RBP, United \nrecognizes the urgency of the procurement and accepts the current design, though imperfect, as \ngood enough. United strongly urges, however, that PJM and the Commission commit to further \n \n7 Id at 44-45. \n8 Id at 3. \n9 Id."},{"page":6,"startToken":1385,"endToken":1718,"text":"6 \nreforms across all the areas identified below to improve outcomes beyond the RBP, and to ensure \nthat the RBP remains a one-time emergency measure. \ni. \nPeak Shaving Adjustment Opt-Outs Should be Clarified \nAs noted above, United supports PJM’s proposal to allow Electric Distributor zones/areas \nwith a qualifying peak shaving adjustment to opt out of a portion of their RBP obligation.10 This \nopt-out recognizes that load which has already taken concrete steps to reduce its own \ncontribution to peak demand should not be treated the same as load that has done nothing to \naddress the shortfall it is helping to cause, and it gives Electric Distributors a meaningful \nincentive to pursue peak shaving arrangements going forward. \nThat incentive, however, depends entirely on the opt-out actually relieving the load in \nquestion of backstop-related obligations, and PJM’s filing leaves that question unresolved. In its \nRBP filing, PJM states that “even if the Electric Distributor zone/area qualifies for and receives \nan opt-out from the RBP, the load in that zone/area may be subject to load reduction under the \nforthcoming proposal to implement a IRAS.”11 PJM's now-filed IRAS proposal confirms this \nconcern rather than resolving it. Under the proposed Eligible New Large Load Amount formula, \na Large Load's exposure to IRAS curtailment is reduced only by its BYONC arrangements and \nAllocated RBP UCAP MW; Peak Shaving Adjustment values, though separately tracked in the \nLarge Load Registry, play no role in that calculation.12 Read in the most concerning light, this \nmeans a load that successfully qualifies for the RBP opt-out could nonetheless find itself subject \nto IRAS curtailment on the same basis as load that made no effort to reduce its footprint at all, a \n \n10 Id at 44-45. \n11 Id, at 46. \n12 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Aug. 13, \n2026); id. at 37 (Large Load Registry data field for Peak Shaving Adjustment value, tracked but not used in the \neligibility calculation)."},{"page":7,"startToken":1718,"endToken":2035,"text":"7 \nresult that would undermine the very incentive the opt-out is meant to create. Clear, \nunambiguous rules on this point are essential, both to actually entice Electric Distributors and \nlarge loads to pursue peak shaving adjustments in the first place, and to give those that do the \nconfidence they will not face unexpected penalties or curtailment exposure down the line once \nIRAS is filed. If Electric Distributors and their large-load customers cannot be confident that a \npeak shaving adjustment actually reduces their exposure, whether through avoided RBP charges \nor reduced curtailment priority under IRAS, many will have little reason to pursue the \narrangement in the first place. \nUnited recommends that the Commission direct PJM to amend the Eligible New Large \nLoad Amount formula in the IRAS proceeding, Docket No. ER26-3515-000, to credit Peak \nShaving Adjustment values on the same basis as BYONC and Allocated RBP UCAP MW, or to \nexplain on the record why a load managing its footprint through a state-sponsored peak shaving \nprogram should be treated identically to one that has not. Absent such a change, the RBP opt-out \nrisks functioning as a paper protection rather than a substantive one, since PJM’s own IRAS \nmechanics now confirm that a load's peak shaving efforts provide no relief from curtailment \nexposure. While Tariff changes are not needed in the instant filing, United respectfully requests \nthat PJM clarify that Peak Shaving Adjustment will be taken into account when calculating IRAS \nexposure, even if the zone/area still has some remaining curtailment risk. \nC. Unpredictable ELCC Values Carry Excessive Risk for Developers \nELCC values for solar, storage, and other accredited resources are set by PJM based on \nsystem-wide fleet mix and grid conditions that no individual developer can control, predict, or \nhedge over a fifteen-year commitment. PJM’s proposal only partially addresses the risk this \nuncertainty produces in the context of the RBP. Specifically, PJM allows developers to bid into"},{"page":8,"startToken":2035,"endToken":2418,"text":"8 \nthe RBP based on their own expectations of a resource’s future Effective Load Carrying \nCapability (“ELCC”), including the ability to offer above the forecasted class rating, up to a \ndefined cap, where a developer believes its resource’s accreditation value is likely to improve \nover the term.13 PJM also avoids applying shortfall charges to resources whose ELCC declines \nbelow their committed RBP UCAP once they achieve commercial operation.14 This treatment is \na reasonable accommodation as far as it goes, but it does not go far enough: RBP resources \nremain subject to unhedgeable ELCC risk in the revenue settlement for supply.  \nBecause that risk is effectively unhedgeable at the individual resource level, rational \ndevelopers will either choose not to participate in RBP or price a substantial risk premium into \ntheir RBP offers to protect against it. This premium will exceed the actual expected cost of \nELCC variability and raise the cost of the RBP regardless of whether the risk materializes. A \nbetter approach, consistent with proposals other stakeholders have put forward, would separate \nthis risk into its two component parts rather than assigning both to the developer.15 The portion \nof ELCC decline that PJM can already forecast, based on known and projected fleet buildout, \nshould be published as an official long-term forecast covering the full RBP term, so that \ndevelopers can price that expected trajectory into their bids at face value, without needing to \nguess at it or pad for it. The portion that cannot be forecast, meaning the variance above or below \nthat expected trajectory driven by factors outside any single developer’s control, should instead \n \n13 Proposed Tariff, Attachment DD, § 18.5(e)(i) (Transmittal Letter at 55) (requiring RBP Sell Offers to state UCAP \nMW based on the resource’s current ELCC Class Rating or unit-specific estimate, with sellers permitted to offer up \nto 120% of that rating to reflect projected future improvement, at the seller’s own risk if the projection proves too \noptimistic). \n14 Transmittal Letter at 87. \n15 See PJM Stakeholder Proposal of REV Renewables, LS Power, Middle River Power, and Geronimo Power, PJM \nReliability Backstop Procurement Design (submitted June 30, 2026) (“Proposing Companies' Alternative Proposal \nvs. PJM Proposal”) https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-\nitem-02k---rev-renewables--ls-power---mrp---geronimo---rbp---executive-summary.pdf"},{"page":9,"startToken":2418,"endToken":2766,"text":"9 \nbe absorbed by RPM, where ELCC variability already manifests annually for every resource in \nthe fleet as a matter of course. Shifting that unhedgeable component to RPM, so long as an RBP \nresource’s underlying installed capacity remains unchanged, would allow ratepayers to bear the \nactual cost of ELCC variability as it occurs, rather than an inflated risk premium embedded in \nevery RBP bid whether or not that variability ever materializes. The practical result should be \nlower, more competitive RBP offers at equivalent or lower total cost to load. \nAddressing this risk is not simply a matter of fairness to developers, it bears directly on \nwhether the RBP achieves its stated reliability purpose. An inflated risk premium does not just \nraise the price load pays for capacity that clears, it risks excluding resources from clearing at all. \nBecause PJM’s proposed maximum willingness to pay is fixed as a MW-weighted average \nlevelized cost across all selected offers, resources forced to bid in an unhedgeable ELCC risk \npremium are more likely to price above that cap, or above where competing offers clear, and be \npassed over in the selection process entirely. Every resource priced out of the RBP on that basis \nis capacity that does not get procured toward the Final RBP Target, increasing the chance that \nthe target is not reached. These resources also bring reliability value beyond their raw UCAP \ncontribution. For example, storage paired with solar helps shift midday generation into the \nevening hours when PJM’s system is most at risk, and a resource mix that includes solar and \nstorage alongside gas reduces PJM’s exposure to the kind of correlated, fuel-supply-driven \nfailures that have caused widespread forced outages among gas generation during past extreme \ncold weather events.16 Excluding or discouraging these resources through avoidable pricing risk \n \n16 See “Winter Storm Elliott: Event Analysis and Recommendation Report” PJM Interconnection, L.L.C. at Page 49 \n(July 17,2023) (Of the total 49,959 MW forced outages 33,404 or 71% was natural gas facilities.) \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2023/20230717-winter-storm-elliott-\nevent-analysis-and-recommendation-report.pdf."},{"page":10,"startToken":2766,"endToken":3002,"text":"10 \nnot only harms individual developers, it narrows the diversity and resilience of the resource mix \nthe RBP is meant to secure. \nUnited further notes that ELCC uncertainty is compounded for DER Aggregation \nResources by factors distinct from those affecting utility-scale solar and storage. The \naccreditation methodology PJM applies to behind-the-meter aggregated resources depends not \nonly on fleet-wide modeling assumptions, but also on PJM’s still-evolving rules for how \ndistributed resources are modeled, dispatched, and measured, including ongoing changes to \nmetering, telemetry, and baseline methodologies that can independently shift a DER \naggregation’s accredited value from one delivery year to the next. Any commitment PJM makes \nto enhance ELCC forecasting and accreditation stability should expressly cover DER \nAggregation Resources, not solely utility-scale resource classes, so that aggregators bidding into \nthe RBP or future capacity procurements can price their offers based on a published, transparent \nforecast rather than guessing at both fleet-wide ELCC dynamics and PJM’s own methodological \nevolution simultaneously. \nUnited requests, at a minimum, that PJM commit to enhancing its ELCC forecasting and \naccreditation process in the near term to promote greater stability and predictability for all \ncapacity resources, whether bidding into RBP, the RPM, and/or pursuing other long-term \ncommitments. Doing so would benefit not only the RBP procurement itself, but investment \nconfidence in PJM’s capacity market more broadly, which is ultimately essential to supporting \ndurable resource adequacy outcomes across the region. Absent such action, PJM risks"},{"page":11,"startToken":3002,"endToken":3382,"text":"11 \nperpetuating an uncertain investment environment that has contributed to the region’s failure to \nbring on new resources to address its growing reliability shortfall. \nD. Exclusion of Surplus Interconnection Service from RBP is a missed opportunity  \n \nPJM recognized SIS as a tool to address “the need for more Capacity on the PJM \nTransmission System from resources that can be brought online quickly” when it proposed \nreforms to its SIS process in 2024, approved by FERC in 2025, to “encourage and facilitate the \nuse of Surplus Interconnection Service from existing and planned generating units on PJM’s \nsystem.”17 Despite significant progress, barriers to full utilization of SIS remain, and this filing \nmisses an opportunity to capitalize on SIS as a pathway to accelerate capacity additions. \nPJM’s proposal draws a sharp line between the criteria for capacity that may offset a \nload’s RBP obligation and the criteria for capacity eligible to be sold into the RBP as an RBP \nResource, and Surplus Interconnection Service capacity falls on the favorable side of that line for \none purpose and the unfavorable side for the other: new load may use SIS-derived capacity to \nreduce its own RBP obligation,18 but a resource relying on SIS is expressly barred from selling \ninto the RBP as an RBP Resource.19 PJM’s stated rationale for the exclusion turns principally on \nthe difficulty of cleanly attributing UCAP between an existing host resource and a surplus \naddition, which PJM states “creat[es] uncertainty and the need for sensitivities or estimates” in \nboth the incremental capacity determination and RBP settlement.20 PJM’s reasoning treats SIS-\nbased capacity as real and valuable enough to net against a load’s RBP obligation, yet not \nreliable enough to sell into the RBP, even though the underlying physical capacity is identical \n \n17 PJM Interconnection, L.L.C. “Proposed Tariff Amendments for Surplus Interconnection Service” Docket No. \nER25-778-000 (filed Dec 20, 2024), Transmittal Letter at 6. \n18 Transmittal Letter at 36. (Proposed Tariff, Attachment DD, § 18.2(a)(iii)) \n19Id at 53 (“[R]esources relying on Surplus Interconnection Service to bring new UCAP MW on the PJM system do \nnot qualify as RBP Resources, because these resources do not have any independent rights to the PJM system.”). \n20 Croop Affidavit at P 20 (Transmittal Letter at 53-54)."},{"page":12,"startToken":3382,"endToken":3715,"text":"12 \neither way.21 United is concerned by PJM’s decision to leave valuable SIS capacity on the \nsidelines, and urges the Commission and PJM to act quickly to increase SIS opportunities, for \ntwo reasons. \nFirst, SIS is a uniquely fast-to-deploy resource, and allowing SIS-based capacity to \ncontribute to addressing PJM’s resource adequacy challenges should be a priority independent of \nthe RBP. SIS was designed specifically to bring new capacity online faster than a full \ninterconnection study process would otherwise allow, by making use of interconnection rights an \nexisting resource is not fully utilizing.22 At a moment when PJM has determined that a 6,831.3 \nMW UCAP shortfall requires an unprecedented 15-year backstop procurement mechanism,23 \nPJM should simultaneously be doing everything it can to ensure that one of the fastest-to-market \nsources of new capacity is actually facilitating new capacity additions in practice. \nSecond, and relatedly, this is not the only barrier limiting the full use of SIS to deliver \nnew capacity to PJM. Current market participation rules do not provide a meaningful pathway in \npractice for SIS based resources to bring new capacity onto the system. A surplus resource that \nwishes to participate in PJM’s markets must either hybridize with the original interconnection \ncustomer, which generally requires unwinding existing commercial obligations; or abandon its \nSIS-based interconnection status and instead pursue a full interconnection study to obtain its own \nincremental Capacity Interconnection Rights and Maximum Facility Output, co-located with the \nexisting host resource.24 PJM's own affidavit confirms that this is true for the RBP specifically as \n \n21 Compare Proposed Tariff, Attachment DD, § 18.2(a)(iii) (Transmittal Letter at 36), with Croop Aff. ¶ 20 \n(Transmittal Letter at 53–54). \n22 Croop Affidavit at P 17. \n23 Id at P 4. \n24 Id at P18 (“[T]hese sited projects would still have an opportunity to offer into the RBP and co-locate with the \nexisting resource and be studied by PJM for increased CIRs and MFO at the facility through the interconnection \nprocess.”)."},{"page":13,"startToken":3715,"endToken":4001,"text":"13 \nwell: a surplus resource's only path to participate in the RBP is this same full interconnection \nprocess, not its existing SIS arrangement.25 In other words, current market participation rules \neffectively restrict meaningful capacity participation, in the RBP or otherwise, by SIS resources, \nundermining the speed-to-market advantage that makes these resources valuable in the first \nplace. To take the common example of storage added to an existing solar site, SIS only grants \ncapacity interconnection rights (“CIRs”) if the storage merges into the solar plant as a single \nhybrid resource. However, this pathway typically requires unwinding existing PPA, tax equity, \nand lender agreements, which is rarely feasible on an operating asset. If storage instead \ninterconnects independently as a co-located resource, it must participate in PJM markets as \nenergy-only—forfeiting all capacity accreditation and preventing SIS from serving as a tool to \nexpedite accredited capacity entry in PJM. United recommends that PJM address this barrier \nboth within the RBP and more broadly across its capacity market participation rules.  \nWithin the RBP, United recommends that the Commission direct PJM to allow the \nincremental UCAP created by an SIS-based addition, meaning the difference between the \nresulting hybrid resource's UCAP and what the host resource's UCAP would have been on a \nstandalone basis, to qualify for the RBP.  This approach directly resolves PJM’s stated concern \nregarding unclear UCAP attribution between the existing resource and the surplus addition,26 \nbecause it does not require PJM to determine how much of the hybrid resource’s total UCAP \nbelongs to which component. It instead isolates and credits only the new value created by the \nsurplus addition, a discrete and calculable quantity, while leaving the host resource’s pre-\n \n25 Id. \n26 Id at P 20."},{"page":14,"startToken":4001,"endToken":4294,"text":"14 \nexisting UCAP contribution untouched and outside the RBP altogether. This should be a discrete \nand surgical adjustment to RBP eligibility. \nSeparate and apart from RBP, United requests that PJM commit to expand opportunities \nfor SIS-based resources in PJM's capacity market, so that this same fast-to-deploy source of \ncapacity is not permanently forced to choose between hybridization or a full interconnection \nstudy as its only options to deliver new capacity to PJM. Specifically, United requests that PJM \ncommit to a broader stakeholder review that would consider the following solutions: \n• Settle UCAP into two accounts. Keep CIRs pooled under a single GIA—no allocation \nor division required—but settle the resulting UCAP between two capacity market \nparticipant accounts, one for solar and one for the battery. Because a hybrid resource \nbehind one set of CIRs generates more combined UCAP than the same two assets would \nunder any divided-CIR approach, this option preserves the most total UCAP while still \ngiving each owner an independently recognized, bankable capacity position. One \nreasonable way to handle UCAP allocations would be to allocate the existing resource \nwhatever it would have gotten without the hybrid addition and then to allocate the \nremaining UCAP to the addition. Capacity market revenues, PAI obligations, and PAI \nliability would flow to each account according to this split. \n• Independent E&AS participation. Allow the component parts of a hybrid resource to \nparticipate independently in Energy & Ancillary Services markets. PJM has already \nindicated interest in exploring this pathway in its “Hybrid Resources Market Model \nSelection” Problem Statement / Issue Charge.27 Capacity market revenue still has to be \n \n27  PJM, Issue Charge: Hybrid Resources Market Model Selection (Aug. 2026), available at https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-2---hybrid-resources-\nmarket-model-selection---issue-charge.pdf."},{"page":15,"startToken":4294,"endToken":4574,"text":"15 \ndisaggregated ex post between the two owners in many cases, but this model has attracted \nsignificant developer interest.  \n• CIR transfer between components. Enable CIR transfers between the components of a \nco-located resource, so each party can hold, finance, and transfer its own share. \nSuppliers—not a fixed ELCC proportional formula—should determine how CIRs are \nallocated between them. This would resemble the CIR transfer process that is available to \ndeactivating generators, i.e., this would enable CIR transfers for resources that are \npartially giving up capacity resource status. It would be appropriate to require that any \ntransfer only be allowed if it resulted in a net increase in system UCAP. \nPursuing these reforms to SIS will not deliver more capacity through the RBP, but it will make \nadditional capacity available in upcoming BRAs and via bring your own new capacity \narrangements, and thus help to resolve tight resource adequacy conditions that are expected to \npersist beyond the RBP. The Commission can encourage progress from PJM to fully realize its \ngoal to “encourage and facilitate the use of Surplus Interconnection Service” as a tool to bring \nmore capacity onto its system quickly28; and, if progress is not made, take further action to \nensure a fully functional SIS process in PJM. \nE. Restrictions to DR/DER Participation will Limit RBP Participation of \nAffordable, Fast-to-Deploy Resources \n \nDemand-side resources and demand response are among the most affordable and flexible \nsolutions to address PJM’s resource adequacy shortfall, capable of being deployed on timescales \nof three to twenty-four months, alongside generation resources that may target later commercial \n \n28 “Proposed Tariff Amendments for Surplus Interconnection Service” Docket No. ER25-778-000 Transmittal Letter \nat 6. (December 20, 2024)"},{"page":16,"startToken":4574,"endToken":4874,"text":"16 \noperation dates.29  PJM has offered some promising opportunities to deploy more of these \nresources in the instant filing, but has simultaneously erected unnecessary barriers. As with \nSurplus Interconnection Service, PJM applies materially different eligibility standards to \nDemand Response and DER Aggregation Resources depending on whether they are offsetting a \nload’s own RBP obligation or competing to sell into the RBP as RBP Resources. While both \npathways suffer deficiencies, they can be remedied through surgical changes that will expand DR \nand DER availability and help to close PJM’s resource adequacy gap. \na. Qualifying RBP Offset MW Rules for DR and DERs \nShould be Clarified \n \nTo offset an RBP obligation, DR/DER can provide Qualifying RBP Offset MW either as \na new supply resource or through direct enrollment of a new load as an Annual Demand \nResponse or DER Capacity Aggregation Resource. United supports these pathways. However, \nthe latter is described as a bridge mechanism pending the availability of generation or storage \ncapacity not yet in service.30 United does not oppose the option for DR/DER to serve as a bridge \nmechanism, but also urges against artificially constraining Demand Response and DER \nAggregation Resources to serve as temporary solutions. Demand-side resources and demand \nresponse deliver standing capacity, energy, and transmission congestion relief benefits that \npersist independent of whether  new generation or storage capacity comes online; they are not \nmerely a placeholder for supply that has not yet materialized. PJM’s Tariff and this proceeding \nshould recognize Demand Response and DER Aggregation Resources as a durable, permanent \n \n29 Voltus, Inc., Submission to the PJM Board, Critical Issue Fast Path Stage 4, Reliability Backstop Procurement / \nConnect & Manage, at 1 (June 2026). https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260630/20260630-item-02l---voltus---cm-and-rbp---executive-summary.pdf  \n30 Transmittal Letter at 40."},{"page":17,"startToken":4874,"endToken":5185,"text":"17 \ncomponent of the resource mix addressing PJM’s shortfall, not solely as an interim measure to be \nphased out or superseded once other capacity arrives.  \nA related ambiguity in the offset pathway itself warrants clarification. Proposed Tariff, \nAttachment DD, § 18.2(c) offers Qualifying RBP Offset UCAP MW status through three \nevidentiary pathways, but it is unclear whether behind-the-meter generation or storage backing a \ndemand response arrangement may rely on the signed bilateral contract pathway in § 18.2(c)(i), \navailable on equal terms to front-of-the-meter resources, or whether it is instead confined to the \ndemand response pathway in § 18.2(c)(iii), which imposes two requirements not applicable \nunder (c)(i): that the resource offset the new load's full MW quantity rather than a partial share, \nand that it be in place by the 2028/2029 Delivery Year Second Incremental Auction or the load \npurchase replacement offset capacity. United requests that PJM clarify that behind-the-meter \ngeneration and storage backing a demand response arrangement is not categorically confined to \nthe more restrictive pathway in § 18.2(c)(iii) solely because of its behind-the-meter \nconfiguration, consistent with PJM's function as a technology-neutral procurement mechanism.31  \nThe offset provision also raises a threshold eligibility question distinct from the \nevidentiary ambiguity above. Proposed Tariff, Attachment DD, § 18.2(a) appears to limit \nQualifying RBP Offset UCAP MW eligibility for demand-side resources to Planned Demand \nResponse or Planned DER Capacity Aggregation Resource as described in RAA Schedule 6 and \nSchedule 6.2, potentially excluding reactivations of previously active sites and new capacity at \nexisting sites, categories that generation and storage resources are expressly permitted to rely on \nunder § 18.2(b), and that were included as offset-eligible for demand-side resources in every \nversion of PJM's proposal discussed during the stakeholder process. United requests that PJM \n \n31 Proposed Tariff, Attachment DD, § 18.2(c)(i), (iii)."},{"page":18,"startToken":5185,"endToken":5508,"text":"18 \namend § 18.2(a) to align demand-side offset eligibility with the treatment already afforded to \ngeneration and storage under § 18.2(b), consistent with the stakeholder consensus reached on this \nissue.32 \nb. DR and DER Participating as RBP Supply face \nUnnecessary Barriers to Entry  \n \nTo participate in RBP, DR and DER must meet eligibility requirements that will render \nmost, if not all, such resources unable to participate in practice. To qualify as an RBP Resource, \na Demand Response or DER Aggregation Resource must have executed participation contracts \ncovering the full fifteen year term, with every location identified, in place at the time of the RBP \nSell Offer itself.33 PJM states this heightened requirement is necessary “to provide assurance that \nthe supply will be available for the 15-year term,” in contrast to Qualifying RBP Offset UCAP \nMW, where commitment terms are simply “managed by the commercial contract between the \nbuyer and seller.”34 PJM’s own reasoning treats demand-side resources as flexible and reliable \nenough to satisfy a load’s offset obligation on privately negotiated terms, yet not reliable enough \nto sell into the RBP without locking in a full fifteen year, fully site-identified commitment before \never submitting an offer.35 United does not oppose heightened requirements under the RBP, nor \ndo we seek preferential treatment for DR/DER assets relative to other RPB resources. However, \nPJM’s proposal introduces three avoidable barriers to full participation by DR and DERs in the \nRBP itself that can be easily remedied to unlock additional supply through RBP. \nFirst, the proposed Tariff requires that every site in that portfolio must be identified and \nunder contract for the full term at the time of the offer.36 For generation and storage resources, by \n \n32 Proposed Tariff, Attachment DD, § 18.2(a), (b). \n33 Transmittal Letter at 54. \n34 Id at 55. \n35 Id at 40. \n36 Proposed Tariff, Attachment DD, §§ 18.5(c)(ii), 18.5(d)(i)."},{"page":19,"startToken":5508,"endToken":5812,"text":"19 \ncontrast, PJM requires a critical path construction schedule, evidence of site control, financing \nand permitting plans, and, critically, “[s]igned memoranda or other documentary evidence that \nthe developer has or will procure the major equipment necessary,” not a completed, executed \nequipment purchase contract.37 This reflects PJM's own recognition that final investment \ncommitments are prudently made only once a revenue stream, meaning a successful auction \nresult, is in place. PJM's own affidavit confirms that Demand Response and DER Aggregation \nResources face no such accommodation, explaining that they “need to have contracts for the \nRBP term (i.e., up to 15 years) with the identified sites that are offering as RBP Resources.”38 \nThe barrier PJM has constructed is a timing and term-length one: every site that will ever back \nthe commitment must be locked in before the resource can even bid, for a term length that few \ndemand-side commercial agreements are structured to support. PJM’s failure to explore \nalternative approaches to satisfying its stated deliverability-certainty objective, including a \ndefined enrollment ramp-up plan supported by a credible compliance mechanism, rather than \nrequiring a fully built and contracted portfolio as a precondition to bidding at all, is a missed \nopportunity of the RBP. \nSecond and more consequential, PJM’s proposal lacks any mechanism allowing a \nDemand Response or DER Aggregation Resource to substitute a departing site or customer for a \nnew one over the course of a fifteen-year commitment. Section 18.6 of the proposed Tariff, \nwhich governs RBP Resource obligations over the life of a commitment, addresses numerous \nchanges or challenges that could impact generation and storage resources, including shortfall \n \n37 Proposed Tariff, Attachment DD, § 18.5(f)(i) (generation and storage evidentiary requirements) (emphasis added). \n38 Proposed Tariff, Attachment DD, § 18.5(f)(i) (Demand Response and DER Aggregation Resource evidentiary \nrequirements) (emphasis added)."},{"page":20,"startToken":5812,"endToken":6119,"text":"20 \ncharges,39 rescission for prolonged non-performance,40 and the treatment of a commitment upon \nchange of ownership of the underlying resource.41 However, it contains no analogous provision \npermitting a DER Aggregator or Curtailment Service Provider to replace an individual site \nwhose participation ends, whether because a customer relocates, closes, or simply does not \nrenew, with a new, equivalent site. Where an ownership change in a generation or storage asset \nis expressly accommodated because the physical resource persists, a demand-side portfolio has \nno equivalent accommodation despite facing a materially higher likelihood, over a fifteen-year \nterm, that at least some constituent sites will turn over. Allowing this flexibility would not \nrelieve DER Aggregators or Curtailment Service Providers of any delivery or performance \nobligations under RBP, but would meaningfully expand willingness and ability of such resources \nto participate in RBP in the first place. Existing RPM deficiency charges already discipline an \naggregator against over-committing volume it cannot deliver, since any underdelivery exposes \nthe aggregator to those penalties independent of RBP; a substitution mechanism would not \nweaken that existing discipline, only allow a portfolio to remain whole as individual sites turn \nover. Absent a substitution mechanism, an RBP Resource in this position has no cure path other \nthan exposure to daily shortfall charges under Section 18.6(d) for a portion of its portfolio it no \nlonger controls. \nThese barriers fall with particular force on residential DER aggregators, whose portfolios \nconsist of hundreds or thousands of individually enrolled households rather than a handful of \ncommercial or industrial facilities. For a residential virtual power plant operator, requiring every \nparticipating site to be identified and under contract for a full fifteen-year term at the time of the \n \n39 Proposed Tariff, Attachment DD, § 18.6(d). \n40 Proposed Tariff, Attachment DD, § 18.6(e). \n41 Proposed Tariff, Attachment DD, § 18.6(f)."},{"page":21,"startToken":6119,"endToken":6403,"text":"21 \nRBP Sell Offer is not merely burdensome; it is operationally incompatible with the way these \nresources are built and maintained. Residential DER portfolios experience predictable, ongoing \ncustomer turnover as homeowners relocate, sell their homes, or choose not to renew participation \nagreements, at rates that are well understood and manageable at the portfolio level but that \nguarantee individual site changes over any multi-year horizon. A residential aggregator with a \ndiversified portfolio of several thousand homes can deliver highly reliable aggregate capacity \neven as individual customers cycle in and out, precisely because the portfolio’s statistical depth \nmakes its aggregate performance far less sensitive to any single customer’s status than a \ncommitment backed by one or two large facilities. PJM’s proposed eligibility criteria do not \naccount for this distinction, and by treating a portfolio of thousands of residential sites identically \nto a single generation facility, PJM has effectively foreclosed participation by one of the fastest-\ngrowing and most scalable sources of dispatchable capacity available to address the shortfall. \nThird, the gating criteria applicable to Demand Response and DER Aggregation \nResource sell offers require, prior to selection, executed customer agreements identifying \nspecific locations, customer names, and per-site curtailment or injection capability,42 together \nwith either a procurement plan for, or evidence of already deployed, metering, telemetry, load \ncontrol, and related equipment.43 United does not object to requiring a credible plan for this \ninfrastructure as a condition of eligibility, but requests that PJM confirm on the record that a \nprocurement plan, rather than infrastructure already installed and operational at the time of the \noffer, is sufficient to satisfy this requirement, consistent with the plain language of the proposed \n \n42 Transmittal Letter at 74-75.  \n43 Id at 75."},{"page":22,"startToken":6403,"endToken":6704,"text":"22 \nTariff provision itself.44 Absent that confirmation, developers may face pressure to build out \ncostly infrastructure at their own risk, despite having no assurance their offer will be selected. \nUnited recommends that the Commission direct PJM to: (i) explore shorter or laddered \ncommitment terms for Demand Response and DER Aggregation Resource sellers, consistent \nwith the lighter-touch, procurement-plan-based approach already applied to generation and \nstorage at the same stage of development, in lieu of a uniform fifteen year requirement; (ii) adopt \na site substitution mechanism allowing an RBP Resource to replace a departing site with a new, \nequivalent capacity site without triggering shortfall charges under Section 18.6(d), consistent \nwith the accommodation already made for generation and storage ownership changes under \nSection 18.6(f); and (iii) confirm that the equipment and metering requirements in Section \n18.5(f)(i) may be satisfied by a credible deployment plan rather than requiring infrastructure to \nbe fully installed prior to bid submission:  (iv) confirm that behind-the-meter generation and \nstorage backing a demand response arrangement may rely on the bilateral contract pathway in \nSection 18.2(c)(i) on the same terms as front-of-the-meter resources; and (v) amend Section \n18.2(a) to align demand-side offset eligibility with the treatment already afforded to generation \nand storage under Section 18.2(b), consistent with the stakeholder consensus reached on this \nissue.  \nBeyond RBP, PJM should commit to reforms that optimize DR and DER participation in \nits markets, including but not limited to addressing metering and data access barriers, introducing \nadditional DR and DER products with different durations and commitments, and improving \ncommunication during emergencies to enable optimal performance. As fast-to-deploy resources, \n \n44 Proposed Tariff, Attachment DD, § 18.5(f)(i)(11) (requiring “[a]n equipment procurement plan or evidence of \ndeployed” infrastructure) (emphasis added)."},{"page":23,"startToken":6704,"endToken":6992,"text":"23 \nDR and DERs offer promising tools to address PJM’s current capacity shortfall and deliver \nbenefits to all customers, but market rules and participation barriers must be addressed to allow \nfull participation and ensure optimal performance. \n \nIII. \nPJM MUST BE HELD ACCOUNTABLE FOR ENSURING THAT RBP \nREMAINS A ONE-TIME MECHANISM  \nA. RBP is Specifically Designed as a One-Time Mechanism \nPJM’s own filing provides the clearest evidence that RBP is meant to be a bounded, non-\nrecurring response to the shortfall identified in the 2028/2029 Base Residual Auction, and PJM \nshould be held to that characterization going forward. United understands that PJM has \nrepresented RBP as a one-time mechanism and takes PJM at its word on that point. United \nnonetheless requests assurance that steps will be taken to ensure this characterization holds in \npractice, so that RBP does not become a recurring tool PJM invokes each time a future auction \nreveals a shortfall. \nMost notably, PJM defends its choice of a pay-as-bid clearing structure, rather than the \nuniform clearing price design PJM otherwise favors across its markets,45 specifically on the \nground that the RBP “is not designed to be a durable or repeatable procurement,” such that “its \npricing outcomes are less likely to serve as incentive market signals.”46 PJM further explains that \nbecause RBP resources will differ in contract duration, commercial operation date, and ELCC \naccreditation over the term, they do not constitute a single homogeneous product suited to \nuniform pricing, a rationale that only holds together if RBP is understood as a one-time, purpose-\n \n45 Croop Affidavit at P 21 (“PJM generally supports a single-clearing-price market design and continues to view \nuniform clearing prices as the most efficient market outcome.”). \n46 Id at P 23."},{"page":24,"startToken":6992,"endToken":7303,"text":"24 \nbuilt mechanism rather than an ongoing feature of PJM’s capacity procurement architecture.47 \nHaving justified a significant departure from its preferred market design specifically because \nRBP is one-time and non-repeatable, PJM should not be permitted to invoke RBP, or a \nsubstantially similar mechanism, as a recurring tool each time a future Base Residual Auction \nreveals a shortfall. \nUnited recommends that the Commission condition its approval of this filing on an \nexplicit acknowledgment that RBP is a one-time mechanism addressed specifically to resolve the \nshortfall identified in the 2028/2029 Base Residual Auction, and not a template PJM may invoke \nunilaterally in response to future shortfalls without a fresh stakeholder process and a new Section \n205 filing subject to the Commission’s full review. Such a condition would simply hold PJM to \nthe premise on which it has already built its own pay-as-bid justification, and would ensure that \nany future backstop procurement, should one prove necessary, is developed with the benefit of a \nnew stakeholder process reflecting conditions and lessons learned at that time, rather than treated \nas a foregone conclusion based on this proceeding. \nB. RBP Must be Followed by a Commitment to Durable Reforms \nRBP treats the symptom of PJM’s current resource adequacy gap rather than its cause. \nThe 6,831.3 MW shortfall identified in the 2028/2029 Base Residual Auction is itself the product \nof deeper structural issues. PJM itself has acknowledged that its capacity market is no longer fit \nfor purpose, and requires holistic reform.48 New entry has been further hampered by persistent \ninterconnection queue delays, evolving supply chain constraints, and permitting timelines, \nbarriers documented in United’s own analysis, which found that PJM had the largest \n \n47 Id at P 25. \n48 PJM, Powering Reliability Through Market Design (May 6, 2026), available at https://www.pjm.com/-\n/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-\ndesign.pdf."},{"page":25,"startToken":7303,"endToken":7660,"text":"25 \ninterconnection backlog of any U.S. grid operator at the end of 2023, that gas turbine wait times \nof five to seven years are now delaying new capacity into 2030–2032, and that 46 GW of PJM-\napproved projects remain unbuilt due to supply chain, siting, and permitting constraints.49 While \nPJM’s interconnection queue has begun processing new requests, the timeline for those projects \nto reach commercial operation is still many years out. Other factors have further stymied \ndevelopment in the region, including highly variable and uncertain ELCC values and lack of \nparticipation options available to the growing range of DR and DER technologies and solutions \navailable today. RBP, as a one-time backstop, addresses the immediate shortfall these dynamics \nhave produced, but does nothing to correct the underlying market structure and infrastructure \nchallenges that produced it in the first place. \nUnited commends PJM’s engagement, through the Critical Issue Fast Path process and \notherwise, with the broader question of how to improve long term investment signals in PJM’s \ncapacity market.50 United is encouraged by PJM’s commitment to holistic market reforms as part \nof its “Powering Reliability Through Market Design” effort.51 Absent such reform, PJM risks \nfinding itself in the same position again: a future Base Residual Auction resulting in a shortfall \nthat RPM’s existing structure was not designed to prevent, with RBP, or a mechanism like it, \noffered again as the only available remedy. \nPJM should also prioritize the more immediate, lower-lift improvements identified \nelsewhere in these comments, including the ELCC risk allocation, Surplus Interconnection \n \n49 “The Next Decade in PJM: A Path to Reliability and Affordability,” Synapse Energy Economics, Inc., prepared \nfor Advanced Energy United, at 2–3 (Feb. 2026). \n50 Croop Affidavit at P 5 (describing RBP as designed to work “in part with ... a return to market fundamentals to \nsupport the expected load growth over the next decade”). \n51”Powering Reliability Through Market Design : Addressing Rising Demand and Constrained Supply, and \nStimulating Investment To Support Durable Reliability” Walter Graf, PJM Interconnection L.L.C. (May 20, 2026) \nfound at:  https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20260520/20260520-\npowering-reliability-through-market-design"},{"page":26,"startToken":7660,"endToken":7945,"text":"26 \nService reforms, network upgrade cost and schedule uncertainty, and Demand Response and \nDER Aggregation Resource participation barriers. These changes do not require a fundamental \nRPM redesign, but they would expand the capacity pool available in the interim, reducing the \nrisk that PJM may resort to a second one-time backstop before durable reform is complete.  \nThe Commission should make clear that it expects PJM to make progress across these \nissues in the near term; at minimum, the Commission should explicitly state that it will \ncategorically reject any future iteration of RBP if PJM cannot demonstrate that it has taken \nmeaningful steps to avoid the need for a future RBP. \nIV. \nRETAIL COST ALLOCATION - SUPPORTING STATE/LARGE LOAD \nCOORDINATION \n \nThe fairness premise underlying PJM’s proposed cost allocation framework, that large \nloads should bear the cost of the capacity procured on their account, depends on state and \nRelevant Electric Retail Regulatory Authority (“RERRA”) action that PJM’s proposal cannot \nitself guarantee.52 PJM’s allocation stops at the LSE level, using a state or RERRA-determined \nRBP Obligation where one is reported, or a default Peak Load Contribution ratio share where it \nis not.53 Whether the cost that lands on an LSE is then actually passed through to the large load \ncausing it, or spread across an LSE’s broader retail base, is a retail ratemaking question entirely \noutside PJM’s proposal and, as PJM itself acknowledges, outside the Commission’s \njurisdiction.54 \nUnited accordingly welcomes the June 30, 2026 letter from the Virginia State \nCorporation Commission and the Data Center Coalition, in which the parties committed to \njointly develop model state retail tariff provisions addressing RBP retail cost allocation by \n \n52 Transmittal Letter at 96-99. \n53 Id.  \n54 Id at 96."},{"page":27,"startToken":7945,"endToken":8273,"text":"27 \nJanuary 1, 2028, and model retail emergency load reduction and interruptible service tariffs by \nFebruary 1, 2027.55 This kind of state-level collaborative process is precisely the vehicle needed \nto close the gap between PJM’s wholesale allocation and actual cost recovery from the large \nloads driving the shortfall, since PJM’s wholesale-to-LSE allocation does not by itself guarantee \nthat the customers causing the cost are the ones who ultimately pay it.  \nUnited supports a state level collaborative approach both because it appropriately \nrespects the jurisdictional line between wholesale market design and retail ratemaking, and \nbecause it offers the most realistic path to fulfilling the commitment that all governors across the \nPJM states made in the January 16, 2026 Statement of Principles to use their authorities to \nallocate RBP costs to data centers and protect residential customers.56 United therefore does not \nask the Commission to mandate a particular retail rate design in this proceeding, nor to compel \nstate action beyond the Commission’s jurisdiction. That does not mean that there is no role for \nPJM or the Commission in ensuring fair outcomes at the state level. Specifically, PJM could \ncommit to monitoring and supporting the development of state-level rate design mechanisms of \nthis kind across its footprint, and report progress to the Commission and stakeholders on the \nextent to which RERRAs in each state have adopted RBP-reporting or comparable retail-level \ncost allocation mechanisms as RBP implementation proceeds. Such monitoring would preserve \nthe cooperative-federalism structure PJM’s proposal is built on, while ensuring that the absence \nof state action in any given jurisdiction does not go unnoticed until costs have already been \n \n55 Letter from Chair Kelsey Bagot, Virginia State Corporation Commission, and Josh Levi, Data Center Coalition, to \nPaula Conboy and David Mills, PJM Interconnection, L.L.C. (June 30, 2026) (Transmittal Letter at 11–12, nn. 27–\n34). \n56 Statement of Principles Regarding PJM, National Energy Dominance Council, at 2 (Jan. 16, 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm."},{"page":28,"startToken":8273,"endToken":8540,"text":"28 \ndiffused across residential and small-commercial ratepayers who were not responsible for \ncausing the shortfall in the first place. \nThe gap between this proceeding's cost-allocation premise and its actual retail-level effect \nis not merely theoretical. As discussed above, PJM’s now-filed Interim Resource Adequacy \nService proposal confirms that a Large Load’s Peak Shaving Adjustment, one of the concrete \nsteps a load can take to manage its footprint and reduce its cost exposure, plays no role in \nreducing that load’s exposure to IRAS curtailment.57 That outcome is a direct illustration of the \nrisk that a mechanism intended to reward large loads that take affirmative steps to reduce their \nimpact on the system can fail to deliver that benefit in practice, absent careful coordination \nacross PJM’s parallel proceedings. United’s request that PJM commit to monitoring and \nreporting on state-level implementation applies with equal force to ensuring consistency between \nRBP’s cost-allocation and opt-out provisions and IRAS’s curtailment mechanics. \n \nV. \nCONCLUSION \nUnited accepts PJM’s proposed Reliability Backstop Procurement as a necessary tool to \naddress the extraordinary challenges facing the region, and offers the clarifications and \ncommitments identified in these comments as opportunities to improve the ability of the RBP to \nclose PJM’s identified resource adequacy shortfall. United respectfully requests that the \nCommission direct PJM to address these issues on the timeline necessary to preserve the \nSeptember 29, 2026, effective date PJM has requested, consistent with PJM’s own invitation for \nthe Commission to modify or clarify specific provisions of its proposal. United appreciates the \n \n57 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Aug. 13, \n2026)."},{"page":29,"startToken":8540,"endToken":8608,"text":"29 \nCommission’s consideration of these comments and looks forward to continuing to work with \nPJM and other stakeholders as this proceeding moves forward. \n \nRespectfully submitted, \n \n \n \n \n \n \n \n/s/   Mike Haugh                             \n \n \n  \nCaitlin Marquis, Managing Director   \nMike Haugh, Director  \nJon Gordon, Senior Director \nKelsey Koenig, Associate \nAdvanced Energy United   \n1801 Pennsylvania Ave. N.W., Suite 410    \nWashington, D.C. 20006    \ncmarquis@advancedenergyunited.org   \nmhaugh@advancedenergyunited.org \njgordon@advancedenergyunited.org  \nkkoenig@advancedenergyunited.org"},{"page":30,"startToken":8608,"endToken":8650,"text":"30 \n \n \nCERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \nDated this 21st day of August 2026. \n \n \n \n \n \n \n \n/s/ Mike Haugh"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":293},{"p":2,"at":3,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":175,"startToken":293,"endToken":590},{"p":3,"at":175,"title":"II. COMMENTS","method":"printed heading","endPage":3,"endAt":190,"startToken":590,"endToken":592},{"p":3,"at":190,"title":"A. RBP Includes Important Elements that will Contribute to its Success","method":"printed heading","endPage":5,"endAt":779,"startToken":592,"endToken":1235},{"p":5,"at":779,"title":"B. Some Elements of RBP Require Clarification or Further Commitment","method":"printed heading","endPage":7,"endAt":1601,"startToken":1235,"endToken":1969},{"p":7,"at":1601,"title":"C. Unpredictable ELCC Values Carry Excessive Risk for Developers","method":"printed heading","endPage":11,"endAt":172,"startToken":1969,"endToken":3026},{"p":11,"at":172,"title":"D. Exclusion of Surplus Interconnection Service from RBP is a missed opportunity","method":"printed heading","endPage":15,"endAt":1328,"startToken":3026,"endToken":4504},{"p":15,"at":1328,"title":"E. Restrictions to DR/DER Participation will Limit RBP Participation of","method":"printed heading","endPage":23,"endAt":248,"startToken":4504,"endToken":6740},{"p":23,"at":248,"title":"III. PJM MUST BE HELD ACCOUNTABLE FOR ENSURING THAT RBP","method":"printed heading","endPage":23,"endAt":337,"startToken":6740,"endToken":6754},{"p":23,"at":337,"title":"A. RBP is Specifically Designed as a One-Time Mechanism","method":"printed heading","endPage":24,"endAt":1216,"startToken":6754,"endToken":7176},{"p":24,"at":1216,"title":"B. RBP Must be Followed by a Commitment to Durable Reforms","method":"printed heading","endPage":26,"endAt":694,"startToken":7176,"endToken":7769},{"p":26,"at":694,"title":"IV. RETAIL COST ALLOCATION - SUPPORTING STATE/LARGE LOAD","method":"printed heading","endPage":28,"endAt":1067,"startToken":7769,"endToken":8428},{"p":28,"at":1067,"title":"V. CONCLUSION","method":"printed heading","endPage":30,"endAt":8,"startToken":8428,"endToken":8609},{"p":30,"at":8,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":30,"endAt":276,"startToken":8609,"endToken":8650}]}