{"document":{"slug":"rec-20260821-5231","title":"Post-Technical Conference Comments of American Electric Power Company, Inc. re the Commission’s technical conference on governance and stakeholder reforms…","issued":"2026-08-21","accession":"20260821-5231","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"American Electric Power Service Corporation","kind":"comments","file":"sources/filings/text/20260821-5231_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5231","tier":"record","sha256":"e9fdd0f1eca471fabde715cc32724e47c9c31859923fa489c5db6e6572f0bd11","pages":32,"tokens":9489,"emptyPages":[],"textThemes":["adequacy","cost","study"]},"pages":[{"page":1,"startToken":0,"endToken":250,"text":"#5144811v2 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Governance and Stakeholder Reforms\nDocket No. AD26-7-000\n \nPOST-TECHNICAL CONFERENCE COMMENTS OF \nAMERICAN ELECTRIC POWER COMPANY, INC. \nAmerican Electric Power Company, Inc. (“AEP”) appreciates the opportunity to provide \nthese comments to the Federal Energy Regulatory Commission (“Commission” or “FERC”) \nfollowing the Commission’s technical conference on governance and stakeholder reforms for PJM \nInterconnection, L.L.C. (“PJM”). These comments build on AEP’s statement filed in advance of \nthe technical conference.1 \nINTRODUCTION AND SUMMARY \nThe Commission’s technical conference confirmed Chairman Swett’s conclusion that \nPJM’s “status quo is unacceptable.”2 Commissioner See framed the problem at the outset: “PJM’s \nunique stakeholder process and system of voting” has produced “stalemates”—not “results”—on \n“some of the most consequential questions PJM is grappling with,” causing everyone to “los[e] \nconfidence[.]”3 Stakeholders echoed those observations throughout the technical conference and \nin pre-conference filings. \n \n \n1 PJM Governance and Stakeholder Reforms, Docket No. AD26-7-000, Statement of Stacey Burbure, \nAmerican Electric Power Company, Inc., Panel 1 (filed July 15, 2026) (“AEP Statement”). Unless \notherwise noted, all materials cited in these comments were submitted in FERC Docket No. AD26-7-000. \n2 FERC, Chairman Laura Swett’s Comments at PJM’s Annual Meeting in Baltimore, MD (May 12, 2026), \nhttps://www.ferc.gov/news-events/news/chairman-laura-swetts-comments-pjms-annual-meeting-\nbaltimore-md-0. \n3 FERC, Commission-Led Technical Conference on PJM Governance and Stakeholder Reforms at 21:16–\n21:38, YOUTUBE (July 23, 2026) (“Technical Conference”) (statement of Comm’r Lindsay See), \nhttps://www.youtube.com/watch?v=OAGH1c-KENM."},{"page":2,"startToken":250,"endToken":511,"text":"2 \nParticipants broadly shared AEP’s diagnosis of PJM’s ills. There is broad recognition that \nPJM must act more quickly and decisively. PJM’s governance and stakeholder processes must be \nmodernized so that responsibility, authority, and accountability are aligned to produce timely, \ntechnically sound decisions that maintain reliability, support affordability, and accelerate \ninfrastructure development. The PJM governance process must enable economic growth, and most \nimportantly, bring new generation online quickly to meet the generational opportunity before us.4 \nThere is also a near-universal understanding that reform must reconcile the genuine tension \nbetween Board independence and meaningful stakeholder and state participation. And there is \nwidespread agreement that PJM and the Commission should pursue concrete reforms that solve \nidentifiable problems rather than focusing on process for process’s sake. \nAEP’s overarching position is results-driven: Ensuring PJM customers are served reliably \nand affordably; developing generation and transmission according to customer-driven timelines; \nand supporting PJM’s ability to evaluate integrated solutions without procedural paralysis. As \nDeputy Secretary of Energy James Danly put it, the “number one priority” in governance reform \nmust be “fix[ing] the problems that are inhibiting . . . getting as much supply online as quickly as \npossible, and doing so while protecting ratepayers.”5 Confronting these reliability, affordability, \nresource adequacy, and infrastructure-development challenges requires faster and more integrated \ndecision-making. The current governance model was not designed for the speed, complexity, or \nscale of today’s load growth, generation and transmission development needs, and market-design \nchallenges. \n \n \n4 See, e.g., AEP Statement at 3-4. \n5 Technical Conference at 46:09–46:26 (statement of Dep. Sec’y of Energy James Danly)."},{"page":3,"startToken":511,"endToken":767,"text":"3 \nThe record also strongly supports AEP’s proposed solutions. First, the stakeholder process \nmust be realigned to an advisory model that has the right people at the table, including the states, \nand can provide actionable support to the Board in fulfilling its role. Second, the Board must be \nfunctionally independent and capable of leading nimbly on the most difficult issues facing the \nregion. \nThese comments proceed in four parts: \nPart I explains why these governance reforms are inseparable from PJM’s most urgent \nsubstantive challenge: getting generation online in time to serve new load. \nPart II highlights how the record from the July 23, 2026, technical conference confirms \nthe need for governance reform in PJM. \nPart III discusses how to provide PJM’s Board and management clear authority and \naccountability through a true advisory stakeholder model and a reexamination of Federal \nPower Act (“FPA”) Section 205 filing rights over core functional matters.  \nPart IV addresses reforms to allow greater state involvement, highlighting the need to \nalign filing rights with legal responsibilities while preserving FERC’s role and the rights \nof transmission owners. AEP specifically recommends that PJM adopt a limited, collective \nstate filing mechanism for resource adequacy issues and consider a “jump-ball” \nframework. \nFinally, the appendix to these comments responds to the specific questions the Commission posed \nin its July 30, 2026, notice requesting post-conference comments.  \nTaken together, the AEP recommendations will modernize PJM’s governance so that \nresponsibility, authority, and accountability are aligned to produce timely, technically sound \ndecisions that allow PJM to address this century’s most critical challenges."},{"page":4,"startToken":767,"endToken":1039,"text":"4 \nCOMMENTS \nI. \nPJM Must Swiftly Implement Solutions to Help Address Its Most Significant \nChallenge: Getting Generation Online in Time to Meet New Load \nPJM’s most urgent challenge is getting needed generation online quickly enough to meet \nrapidly growing load. But PJM cannot solve that problem if integrated solutions are forced through \na governance structure that divides responsibility across fragmented committees and distinct filing \nauthorities. The same governance defects that prevent PJM from evaluating integrated proposals \nlike AEP’s Accelerated Load, Infrastructure, Generation and Network Planning (“ALIGN”) \nconcept also prevent PJM from implementing solutions to get generation online promptly. Indeed, \nthe persistent governance problems in PJM directly contribute to its current resource adequacy \nchallenges: while the region has long seen the current problems coming, potential solutions \nlanguished for years in deadlocked stakeholder processes. Governance reform thus is not separate \nfrom generator interconnection or resource adequacy concerns; it is the mechanism needed to \nmove necessary reforms from concept to implemented solution. \nThe relevant measure of reform should be whether it helps new resources reach commercial \noperation in time to serve customer demand—not whether PJM has merely improved on certain \ngovernance, queue administration, or study throughput metrics. PJM’s current committee structure \ncan take an integrated generation solution and divide it into separate pieces—separating out \ngenerator interconnection, load interconnection, transmission planning, market design, \ndeliverability, and cost allocation—before PJM, stakeholders, or the Board can evaluate whether \nthe package solves the underlying reliability problem. That fragmentation does not align with the \nintegrated nature of the challenge: generation cannot meet new load unless the project, the network \nupgrades, deliverability, and load-service arrangements are synchronized. A committee-by-"},{"page":5,"startToken":1039,"endToken":1287,"text":"5 \ncommittee process can delay, narrow, or defeat a proposal before the merits of the integrated \nsolution are ever considered. \nCommissioner Rosner captured the interdependent nature of the region’s challenges, \nobserving that “transmission is needed to interconnect new resources. We can have the fastest \nqueue in the world, but if there’s not a grid to plug it in, there’s nothing we can do fast.”6 Divided \nSection 205 filing rights compound the problem. Even if a solution survives stakeholder review, \nimplementation may require coordinated changes to the Tariff, Operating Agreement, Reliability \nAssurance Agreement, manuals, and transmission-planning protocols—creating multiple \nprocedural gates controlled by different actors with different incentives. The practical consequence \nis delayed generation: when each component of an integrated proposal is subject to separate \ncommittee review and separate filing authority, PJM cannot reliably move from identifying a need \nto implementing a solution on the timeline necessitated by customers, states, and the system. \nThis problem ties directly to AEP’s governance recommendations in these Comments:   \n An advisory stakeholder model would preserve technical input without allowing \nthe stakeholder process to become a veto point;  \n Reexamined Section 205 rights would allow reforms related to core functional \nmatters to be brought to the Commission efficiently;  \n A more meaningful role for states—with appropriate protections for transmission \nowners’ Section 205 rights—would ensure that decision-making authority within \nPJM aligns with the entities responsible for reliability, affordability, and economic \ndevelopment; and  \n \n \n6 Technical Conference at 18:43–18:54 (statement of Comm’r David Rosner)."},{"page":6,"startToken":1287,"endToken":1598,"text":"6 \n A more engaged, qualified, and accountable Board would be better situated to \nprovide dynamic leadership and ensure timely action.  \nTogether, these reforms would give PJM the tools to act on the region’s most pressing needs. \nPJM should adopt a near-term action framework that coordinates generator \ninterconnection, transmission planning, and load-service review for projects needed to serve new \ndemand. That framework should include clear eligibility criteria, synchronized study timelines, \nand Board-level accountability for whether expedited pathways are in fact producing commercial-\noperation results. The governance reforms AEP recommends will help achieve this objective. \nWithout an advisory process that avoids veto-driven stalemate, clearer filing authority over core \nfunctional issues, a meaningful and defined role for states, and an informed and accountable \nBoard—PJM will continue to identify urgent generation needs faster than it can implement the \nintegrated solutions necessary to meet them. \nII. \nThe Technical Conference Record Demonstrates the Need for Reform \nThe record here demonstrates that stakeholders are broadly aligned in three key areas: First, \ngovernance reform is necessary to allow PJM to act more efficiently and effectively. Second, \ngovernance reform must navigate the genuine tension between Board independence and \nstakeholder participation. Third, any governance changes should be solutions-oriented, facilitating \ndecisive action to address the region’s most significant challenges rather than focusing on process \nfor its own sake. Although there are outer limits to what governance reform alone can accomplish \nto address PJM’s current ills, as Commissioner Chang put it, the simple question on the table is: \n“How can we help PJM make decisions more swiftly?”7 \n \n \n7 Technical Conference at 27:37–32:44 (statement of Comm’r Judy Chang) (“[A]s for solutions, PJM \ncannot do this alone. . . . I say this because I want to make clear not every problem at PJM will be fixed \nthrough changes of the governance structure. And certainly, we will talk about today the stakeholder"},{"page":7,"startToken":1598,"endToken":1936,"text":"7 \nA. \nStakeholders Agree PJM Must Act More Quickly and Decisively \nEveryone, including PJM, agrees that PJM’s current governance system is not delivering \nfast and decisive decision-making. PJM admitted not only that “matters of significance can stall” \nin its stakeholder process, but that its most consequential matters often are the ones that do.8 That \nis in no small part because, as PJM also conceded, the sector-weighted voting structure allows any \ntwo of five sectors to block action.9 Critical issues that have fallen victim to PJM’s process \nimpediments range from resource adequacy and the capacity market to large load integration.10 \nPJM, to its credit, did not shy away from recognizing the severe consequences: In this period of \nrapid load growth, these governance failures can “degrade[] reliability, increase[] costs, [and \nreduce] investment certainty in our markets . . . .”11 Preventing such outcomes is PJM’s core \nresponsibility, not an optional undertaking. Therefore, PJM’s conclusion that governance reform \nmust strengthen its ability to act is table stakes.12 \nPJM’s Critical Issue Fast Path process on large load additions illustrates the point. \nAlthough stakeholders participated “active[ly]” and considered numerous competing reform \npackages, none reached the sector-weighted threshold required for member approval.13 AEP agrees \n \n \nprocess, decision-making process . . . but these process related challenges even if we can fix it quickly, we \nwon’t fix some of the technical and market issues. I want to set the stage and make sure that our expectation \nof change, we set the proper expectations for change.”). \n8 Comments from PJM Interconnection, L.L.C. at 3-6 & tbl. 2 (filed July 16, 2026) (“PJM Comments”). \n9 Id. \n10 Id. at 3-5 & tbl. 2. \n11 Id. at 5. \n12 Id. at 6-7. \n13 Id. at 5-6 & tbl. 4. PJM also highlighted its Reserve Certainty Senior Task Force as another example of \n“the process’s inability to move through a technically complex, yet important issue,” noting that the task \nforce currently is targeting a Members Committee vote three years after it was formed, after more than forty \nmeetings. Id. at 5."},{"page":8,"startToken":1936,"endToken":2361,"text":"8 \nwith PJM that stakeholders receive no trophy for “participation alone,” especially when “timely \naction on matters of significance” is essential to the 60+ million Americans relying on the RTO.14  \nState representatives and independent observers reinforced this point. Pat Wood III—\nformer FERC and Public Utility Commission of Texas Chairman and current Executive Chairman \nof the Hunt Energy Network—called for a “more nimble, transparent process,” recommending that \nPJM transition its stakeholder process to an advisory role and establish direct channels for states \nto bring issues to the Board.15 State representatives from across the PJM footprint—including the \nOrganization of PJM States, Inc. (“OPSI”); the Public Utilities Commission of Ohio’s Office of \nthe Federal Energy Advocate; Kelsey Bagot of the Virginia State Corporation Commission; Jacob \nFinkel of the Office of the Governor of Pennsylvania (on behalf of the PJM Governors’ \nCollaborative); and Suzanne Jaworowski of the Office of the Governor of Indiana—each \nhighlighted PJM’s failure to take timely action on critical issues and supported reforms to improve \nstate input, strengthen Board accountability, and enhance PJM’s ability to respond to reliability \nand affordability concerns.16 \n \n \n14 Id. at 6. \n15 Recommendations for PJM Governance and Stakeholder Process Reform from Pat Wood III (filed July \n16, 2026) (“Wood Statement”). \n16 See Pre-Conference Comments of the Organization of PJM States, Inc. at 8 (filed July 21, 2026) (“OPSI \nComments”) (“[F]ar too often the PJM stakeholder process becomes a vehicle for repetition and \ndelay . . . .”); Comments of the Public Utilities Commission of Ohio’s Office of the Federal Energy \nAdvocate at 6 (filed July 21, 2026) (“Ohio FEA Comments”) (“[S]omething is not working if PJM’s \nstakeholder process is not reaching consensus or able to determine a course of action on pressing issues in \na timely manner.”); Pre-Conference Comments of Kelsey A. Bagot, Chair, Virginia State Corporation \nCommission at 1 (filed July 21, 2026) (“Bagot Statement”) (arguing “the PJM stakeholder process has \nfailed to drive meaningful and timely outcomes for the most critical of issues facing PJM”); Pre-Technical \nConference Statement of Jacob Finkel, Office of Governor Josh Shapiro, Deputy Secretary of Policy at 10 \n(filed July 16, 2026) (“Finkel Statement”) (“[D]urable solutions are impossible without better alignment of \nauthority with accountability, which means a more independent Board, a more nimble stakeholder process \ndirected at the right type of engagement, and greater involvement from the states in PJM’s decision-making \nprocesses. Such durable solutions are needed, and needed quickly.”); Written Statement of Suzanne \nJaworowski, Secretary of Energy and Natural Resources, State of Indiana Office of Governor Mike Braun"},{"page":9,"startToken":2361,"endToken":2740,"text":"9 \nEven market participants that resisted major structural change recognized the need for \nfaster and more disciplined execution. For instance, Vistra urged PJM to set timelines and \nstreamline stakeholder processes, American Municipal Power (“AMP”) called for better issue \nprioritization and workload management, and Constellation identified stronger and more decisive \nPJM leadership as the single most important reform.17 Large load interests agreed that current \nprocesses fall short, with Google criticizing PJM’s lack of visible leadership during the large-load-\nintegration process, and the PJM Industrial Customer Coalition calling for better tools to give the \nBoard actionable information on time-sensitive issues.18  \nStakeholders disagree on much, but they reached a broad consensus here: PJM’s current \ngovernance structure fails to facilitate the effective, timely action the region needs, and it must \nchange. \n \n \nat 2 (filed July 15, 2026) (“Jaworowski Statement”) (“Sector-weighted voting has value, but the current \ndesign no longer strikes the right balance between consensus and timely action.”). \n17 See Pre-Conference Statement of J. Arnold Quinn, Senior Vice President, Regulatory Policy, Vistra Corp. \nat 10 (filed July 15, 2026) (“Vistra Statement”) (“Significant streamlining and simplification of the PJM \nstakeholder process would improve both focus and speed. As it stands, the process is needlessly complex, \ntime-consuming, and lacks clear objectives or timelines.”); Pre-Technical Conference Statement of Steven \nLieberman on Behalf of American Municipal Power, Inc. at 2 (filed July 15, 2026) (“AMP Statement”) \n(arguing “the speed of decision-making is largely determined by PJM’s prioritization of issues and meeting \nschedules”); Pre-Conference Statement of Mason Emnett on Behalf of Constellation Energy Generation, \nLLC at 2 (filed July 16, 2026) (“Constellation Statement”) (“When PJM has delayed action, it has been \nbecause its leadership has decided not to proceed, not because of any lack of authority.”). \n18 See Pre-Filed Statement of Brian D. George on Behalf of Google LLC at 3 (filed July 15, 2026) (“Google \nStatement”) (“It is not unreasonable to posit that with a narrowed and targeted focus, additional efforts to \nbuild consensus, including, critically, from PJM leadership, and transparency from the Board regarding \ntheir desired outcomes from the stakeholder body, and a little more time, consensus could have been \nachieved [on large load additions].”); Pre-Filed Statement of Susan Bruce, Counsel to PJM Industrial \nCustomer Coalition at 6 (filed July 15, 2026) (“PJMICC Statement”)."},{"page":10,"startToken":2740,"endToken":3098,"text":"10 \nB. \nThe Record Reflects a Need to Carefully Calibrate the Board’s and \nStakeholders’ Roles \nThe technical conference confirmed that governance reform must balance two key \ninterests: Ensuring PJM is truly independent to achieve its important objectives as an RTO while \nproviding a meaningful opportunity for stakeholders and states to participate in PJM decision-\nmaking processes. Several parties—including PJM, OPSI and various other state representatives, \nthe PSEG Companies, and Google—called for greater Board authority and independence. They \noffered proposals ranging from expanded or unconditioned Section 205 filing rights for PJM and \nadvisory stakeholder voting to revised Board qualifications and reforms to reduce the potential for \nstakeholder stalemates that can block timely filings.19 Others, meanwhile, cautioned against \nreforms that could diminish or limit the stakeholder process. For instance, the PJM Power \nProviders Group, AMP, Constellation, LS Power, Vistra, the Independent Market Monitor, and \nKent Chandler—R Street Institute fellow and former Kentucky Public Service Commission \nChairman—generally favored more targeted reforms focused on execution, transparency, state \nengagement, and workflow prioritization rather than wholesale restructuring.20  \nAs described below, fostering functional independence for PJM and providing stakeholders \na robust role are not mutually exclusive; they are mutually reinforcing. A well-functioning \n \n \n19 See, e.g., PJM Comments at 6-9; OPSI Comments at 1-2; Wood Statement; Bagot Statement at 1-2; \nFinkel Statement at 2-7; Jaworowski Statement at 2-3; Pre-Technical Conference Comments of the PSEG \nCompanies at 4 (filed July 15, 2026) (“PSEG Comments”); Google Statement. \n20 See Pre-Conference Comments of the PJM Power Providers Group (P3) (filed July 15, 2026) (“P3 \nComments”); AMP Statement; Constellation Statement at 1-2; Pre-Technical Conference Comments of \nMarjorie Philips, LS Power Development, LLC (filed July 16, 2026); Vistra Statement; Comments of the \nIndependent Market Monitor for PJM at 1-3 (filed July 20, 2026) (“IMM Comments”); Technical \nConference at 4:12:10–4:13:19 (American Municipal Power), 5:47:35–5:50:49 (PJM Power Providers \nGroup), 2:07:14–2:08:37 (LS Power), and 4:54:40–4:56:18 (Kent Chandler); Submitted Statement of Kent \nChandler, Senior Fellow, Energy and Environmental Policy, R Street Institute (filed July 15, 2026) \n(“Chandler Statement”)."},{"page":11,"startToken":3098,"endToken":3348,"text":"11 \nstakeholder participation model can deliver timely, transparent, and well-developed input to the \nBoard, improving action and outcomes. The stakeholder process, however, cannot endure as a tool \nfor a small minority of interests to block progress. This critical moment requires leadership to \ncalibrate PJM’s governance structure to advance reforms that balance independence and \nstakeholder participation in a way that promotes engagement and enables solving the pressing \nproblems facing the region. \nC. \nGovernance Changes Must Emphasize Concrete Reforms, Not Process for \nProcess’s Sake \nThe record supports focusing on reforms that solve identifiable problems: delay, lack of \naccountability, insufficient state involvement, unclear Board decision-making, and inadequate \nprioritization of urgent issues. PJM itself proposed concrete process improvements, including an \nadditional expedited process for high-priority reliability, market, and planning issues; enforceable \n“time gates” for stakeholder processes; conducting more business in writing where appropriate; \nfewer duplicative meetings; clearer issue prioritization; and better use of technology to improve \ntransparency and reduce repetition.21 Other participants also offered actionable reform proposals. \nFor instance, former FERC Chairman Pat Wood III proposed an advisory stakeholder model, \nbinding consultative authority for OPSI, and a complementary state committee, while the PSEG \nCompanies proposed Section 205 reforms, changing voting structures or moving to an advisory \nstakeholder process, and Board accountability reviews.22 Other commenters supported enhanced \nstate roles paired with greater Board independence;23 firmer Section 205 authority for the Board, \n \n \n21 PJM Comments at 9-10. \n22 See Wood Statement; PSEG Comments at 6-7. \n23 See Finkel Statement; Jaworowski Statement at 1-2."},{"page":12,"startToken":3348,"endToken":3641,"text":"12 \ninformed by stakeholder input;24 a funded PJM States Committee modeled on the New England \nStates Committee on Electricity (“NESCOE”);25 “jump-ball” filing rights and a dedicated state \nsector;26 or requiring the Board to provide written explanations of its decisions and better \nmechanisms for time-sensitive issues.27 \nIn weighing these and other proposals, PJM and the Commission should distinguish added \nprocedural churn from meaningful governance reform. Additional stakeholder meetings, \neducational sessions, or informal coordination will not be enough to address the serious shortfalls \nin PJM governance practices unless they are paired with results-oriented reforms, such as \nenforceable timelines, clear decision points, defined Board authority, and accountability for \noutcomes. The reforms AEP recommends are designed to meet that standard. \nIII. \nPJM’s Board and Management Must Have Clear Authority to Address Reliability, \nAffordability, Resource Adequacy, and Infrastructure Challenges; Stakeholders \nMust Have a Meaningful and Effective Role in Promoting the Best Outcomes \nPJM’s Board and management must be empowered to address the reliability, affordability, \nand resource adequacy challenges confronting the region effectively. To do so, PJM’s governance \nstructure must be calibrated to ensure that the Board can lead decisively and nimbly, while \nproviding stakeholders a structure for their voices to be heard in a manner that assists the Board in \nachieving the best outcomes. AEP believes that (1) Section 205 filing rights for core functional \nmatters should be reallocated; (2) PJM should shift to a purely advisory stakeholder process; and \n \n \n24 See Bagot Statement at 2. \n25 See Opening Statement of Abraham Silverman at 2-3 (filed July 15, 2026) (“Silverman Statement”). \n26 See Overview of Potential Changes to PJM Governance, Delaware Division of the Public Advocate, \nJameson Tweedie, Public Advocate for Delaware (filed July 20, 2026) (“Tweedie Comments”). \n27 See PJMICC Statement at 5-6."},{"page":13,"startToken":3641,"endToken":4023,"text":"13 \n(3) PJM should adopt other changes that improve the Board’s functionality and its interaction with \nstakeholders.  \nA. \nPJM Must Reexamine Section 205 Filing Rights for Core Functional Matters \nPJM’s current division of Section 205 filing rights can impede timely action, particularly \nwhere an integrated reform requires changes to more than one governing document. In \napportioning Section 205 rights, PJM and the Commission should distinguish between rights over \ncorporate governance of the RTO and rights over core functional matters, such as energy markets, \nregional transmission planning, resource adequacy, and interconnection reform. The Members \nCommittee’s Section 205 authority over core functional matters too often operates as a barrier to \ntimely and technically sound action.28 Such authority should instead reside with the PJM Board. \nAs PJM explained, it holds unconditioned Section 205 rights in some core areas, principally \nthe capacity market, but its ability to file changes to the energy and ancillary services markets and \nto the Regional Transmission Expansion Plan process is “conditioned on Members Committee \napproval,” such that, absent such approval, “PJM may be required to proceed under the more \nrestrictive requirements of section 206.”29 PJM candidly characterized this division as “in many \ncases[] an accident of history” and noted that its peer RTOs “do not have such conditioning of \ntheir 205 rights.”30 PJM therefore asked the Commission to consider whether PJM should have \n \n \n28 See PJM Comments at 3-6; AEP Statement, App’x at 7-8. \n29 PJM Comments at 6. \n30 Id. at 7-8. Indeed, it is not clear whether the Commission, in approving PJM’s structure, appreciated the \neffects of this approach. Cf. Bangor Hydro-Electric Co., 96 FERC ¶ 61,063 at 61,259 (2001) (explaining \nthat an independent RTO “must have the sole authority to make changes to Market Rules and any other \nchanges it deems necessary without being required to seek approval from” a market participant committee); \nN.Y. Indep. Sys. Operator, Inc., 96 FERC ¶ 61,059 at 61,186-87 (2001) (rejecting NYISO’s proposal for an \nRTO in which decision-making would be “shared by a non-stakeholder Board of Directors and [a] \nstakeholder Management Committee,” with the Board having the right to make unilateral Section 205 \nfilings only “in exigent circumstances” because an “RTO must limit the authority of committees of the type \nNYISO employs to an advisory role”)."},{"page":14,"startToken":4023,"endToken":4288,"text":"14 \n“unconditioned section 205 filing rights across all its core operational, market and transmission \nplanning responsibilities, subject to Board oversight and informed by stakeholder engagement.”31 \nThe problem is especially acute for provisions addressed in both the Tariff and the \nOperating Agreement. Energy market provisions, for example, appear in substantively identical \nform in both documents, so reform requires approval under both the Board’s and the Members \nCommittee’s filing authorities.32 The practical effect is that an integrated solution like AEP’s \nALIGN concept may require changes to multiple governing documents subject to distinct approval \nrequirements33—and too often process defeats substance. AEP therefore supports reforms that \nallow PJM’s Board and management to advance functional reforms efficiently while preserving \nstakeholder input through an advisory process. Consistent with the discussion below, transmission \nowners must retain their appropriate rights and responsibilities under the Consolidated \nTransmission Owners Agreement and related governing documents.34 \nB. \nPJM Must Convert the Stakeholder Process Into a True Advisory Model \nPJM should create an advisory stakeholder structure that provides meaningful, actionable \nadvice to PJM management and the Board while eliminating the procedural features that too often \nallow stakeholders to block needed reforms. Today, the Members Committee approves actions and \nrecommendations by a two-thirds sector-weighted vote.35 Because there are five sectors, any two \nsectors can combine to veto proposals—even where the Board needs timely advice on reliability, \n \n \n31 PJM Comments at 8. \n32 Compare PJM Open Access Transmission Tariff Attach. K-Appendix with PJM Operating Agreement \nSched. 1. \n33 AEP Statement at 5-6. \n34 See infra Part IV.B. \n35 PJM Operating Agreement § 8.4."},{"page":15,"startToken":4288,"endToken":4608,"text":"15 \nplanning, or market-design reforms.36 As AEP’s pre-conference statement explained, the two-\nthirds requirement applies not only to amendments to the Operating Agreement, over which the \nMembers Committee holds Section 205 filing rights, but also to any recommendation to the \nBoard.37 The result is that the Members Committee’s advice “is far too often no advice at all.”38 \nStakeholder engagement remains essential, but stakeholder voting should not dictate \noutcomes when stakeholders are performing an advisory function. Peter Lake, former Senior \nDirector of Power on the White House National Energy Dominance Council, made the point \ndirectly at the technical conference: stakeholders “need a voice in the stakeholder process, but it \ncannot be a veto. We must accelerate gen and load interconnect in PJM.”39 Under a true advisory \nmodel, stakeholders would retain robust opportunities to offer proposals, test alternatives, identify \nconsensus, and create a record for Board consideration. PJM management would develop \nproposals after stakeholder engagement, and the Board would decide whether to proceed—\nweighing stakeholder input and accepting accountability for the final decision.40 \nCritically, the advisory structure must be flexible enough to allow subject-matter \ncommittees to evaluate discrete technical issues while also enabling integrated proposals—such as \nAEP’s ALIGN concept—to be considered as a whole rather than being broken up across \ndisconnected committees.41 Moving to a purely advisory model would improve PJM’s \neffectiveness and speed in decision-making while strengthening—not diminishing—stakeholder \n \n \n36 See AEP Statement, App’x at 2, 6; see also PJM Comments at 4-5 & tbl. 3. \n37 AEP Statement, App’x at 2. \n38 Id. \n39 Technical Conference at 1:03:14–1:03:24 (statement of Peter Lake, Sr. Dir., White House Nat’l Energy \nDominance Council). \n40 See AEP Statement, App’x at 6-7. \n41 See AEP Statement at 4-6 (describing ALIGN as a concept that would plan committed load, generation, \nand transmission as a coordinated portfolio, augmenting rather than replacing PJM’s existing processes)."},{"page":16,"startToken":4608,"endToken":4908,"text":"16 \nparticipation, by focusing on surfacing useful advice and insights and avoiding procedural \nstalemates. This is not a novel construct: The Midcontinent Independent System Operator \n(“MISO”), the Southwest Power Pool (“SPP”), and ISO New England (“ISO-NE”) each employ \nadvisory stakeholder processes in which final authority rests with an independent board informed \nby robust stakeholder input.42 \nC. \nPJM Must Limit Its Ex Parte Restrictions to Improve Board Transparency, \nAccessibility, and Stakeholder Engagement \nPJM’s broad-ranging challenges—including accelerating load growth, resource adequacy \nconcerns, transmission expansion, interconnection reform, and rising expectations from states, \ncustomers, and federal policymakers—require more frequent and meaningful communication \nbetween the PJM Board and affected stakeholders. The current rules restricting informal \ncommunications, however, unnecessarily limit the Board’s ability to understand the real-world \nimplications of its governance, market, planning, and reliability decisions. They significantly \nconstrain informal engagement between stakeholders and individual Board members outside of \nformal stakeholder proceedings.43 Although safeguards against improper influence are important, \nPJM’s current restrictions are broader than necessary and prevent the Board from hearing directly \nfrom those most affected by issues of regional significance—including reliability, transmission \nplanning, and interconnection reform.  \nPJM’s approach is more restrictive than the governance practices of its peer RTOs, and no \nother RTO or ISO imposes such severe restrictions on Board-stakeholder communication.44 \n \n \n42 See MISO Transmission Owners Agreement, App’x F (“MISO Bylaws”), Art. VI § 6.1 (Advisory \nCommittee); SPP Bylaws §§ 4.1, 5.1; ISO-NE Participants Agreement § 8.1. \n43 See PJM Interconnection, L.L.C., Board of Managers Code of Conduct 3 (rev. Mar. 2026) (“Board Code \nof Conduct”), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/bom-code.ashx. \n44 See Christopher A. Parent et al., Governance Structure and Practices in the FERC-Jurisdictional \nISOs/RTOs, Exeter Assocs., Inc. (Feb. 2021) (“NESCOE Report”) (discussing PJM’s ex parte restrictions"},{"page":17,"startToken":4908,"endToken":5207,"text":"17 \nMISO’s corporate-governance framework expressly contemplates that directors may communicate \nwith stakeholders, requiring only that a director who receives an unsolicited communication on \ncompany business report its substance to the CEO and the full Board.45 SPP similarly provides \nstakeholders with substantial opportunities to engage with its Board through open governance \nprocesses, including Board participation in the work of SPP’s organizational groups.46 These \nexamples show that PJM can permit direct stakeholder communication with the Board while \nmaintaining transparency, avoiding improper influence, and preserving the integrity of Board \ndecision-making. \nThe disconnect between the Board and stakeholders created by PJM’s ex parte restrictions \ndoes not fit the Board’s role. PJM is a public utility, not a regulator; its Board should be an active \npartner in confronting the challenges the region faces, and its policies should not foster the \nmisimpression that the Board is providing another layer of regulator-like oversight. Direct \nengagement would help ensure that the Board receives a broad range of practical, operational, \ncommercial, and policy perspectives before making decisions that will shape the region’s future. \nAppropriate safeguards can preserve impartiality without insulating the Board from useful \nstakeholder input.47 \n \n \nand not identifying any ex parte restrictions for other RTOs or ISOs), https://nescoe.com/wp-\ncontent/uploads/2021/02/ISO-RTOGovernanceStructureandPractices_19Feb2021.pdf. \n45 \nSee \nMISO, \nPrinciples \nof \nCorporate \nGovernance \n§ \nV.E \n(May \n16, \n2025), \nhttps://cdn.misoenergy.org/MISO%20Principles%20of%20Corporate%20Governance110859.pdf; \nNESCOE Report at 4-11 to 4-12 (describing MISO board members’ expected attendance at monthly \nAdvisory Committee meetings and MISO’s encouragement of “additional communication between its \nBoard and stakeholders”). \n46 See SPP Bylaws § 4.1(a)-(b); NESCOE Report at ES-7 tbl. ES-5 (reflecting that SPP board meetings, \nagendas, minutes, and materials are open to the public). \n47 AEP Statement at 8 & App’x at 12-13."},{"page":18,"startToken":5207,"endToken":5538,"text":"18 \nIndeed, PJM’s ex parte rules are a product of the Board’s own Code of Conduct, which the \nBoard’s Governance Committee can amend without Members Committee or other stakeholder \napproval.48 This is a step the Board can and should take immediately. AEP recommends that PJM \namend its Board Code of Conduct and related governance practices to allow productive Board-\nstakeholder engagement, subject to appropriate transparency safeguards. Specifically, PJM should: \n(1) permit direct communication between stakeholders and individual Board members, consistent \nwith the practices of peer RTOs; (2) encourage substantive stakeholder discussions in connection \nwith open Board or committee meetings; (3) provide summaries of significant stakeholder \noutreach where appropriate; (4) revise restrictions on sector meetings so that they are narrowly \ntailored to prevent improper ex parte influence without unnecessarily limiting productive \nengagement; and (5) conduct Board meetings in an open and publicly accessible manner whenever \npracticable, reserving executive sessions for confidential, personnel, litigation, or other legally \nprotected matters. \n \n \n48 See Board Code of Conduct at 3; PJM Interconnection, L.L.C., Board Managers: Master Charter and \nCommittee Charters 6-7 (rev. May 2026) (explaining that the Board’s Governance Committee “shall . . . \n[p]eriodically review . . . the PJM Board Code of Conduct” and “[a]pprove revisions to . . . the Board Code \nof Conduct . . . .”), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/board-committees-\ncharter-2026.pdf. Because the Board Code of Conduct is not on file with the Commission, revisions do not \nrequire Commission approval. In addition to amending the Board Code of Conduct, the section of PJM \nManual 34 on Board Communications also may require revisions. PJM Interconnection, L.L.C., PJM \nManual 34: PJM Stakeholder Process § 15.4 (rev. 22, Sept. 25, 2025), https://www.pjm.com/-\n/media/DotCom/documents/manuals/m34.pdf. Changes to this manual generally require a two-thirds vote \nof the Members Committee. Id. § 1. However, under the terms of the Operating Agreement, PJM may assert \nauthority to revise the relevant manual directly if stakeholder support cannot be achieved. See id. § 11.15."},{"page":19,"startToken":5538,"endToken":5948,"text":"19 \nD. \nPJM Must Implement Additional Targeted Board Reforms to Improve \nExpertise, Engagement, and Accountability \nAs detailed in AEP’s pre-conference statement, PJM should adopt several additional, \ntargeted Board reforms drawn from the practices of other RTOs and ISOs.49 Without repeating its \nprior comments, AEP reiterates its recommendations of the following reforms to strengthen the \nBoard’s ability to address reliability, affordability, resource adequacy, and infrastructure \nchallenges swiftly, while preserving the Board’s independence: \n1. PJM should make its President and CEO a voting member of the Board. The \nPresident and CEO is responsible for implementing Board decisions and managing \nPJM’s operations and therefore should be fully involved in Board decision-making. \nThe CEOs of MISO, SPP, and NYISO already serve as voting members of their \nrespective boards, subject to appropriate recusal limits.50  \n2. PJM Board meetings should be open by default. PJM’s Board meetings are not open \nto the public or stakeholders, leaving very little transparency into how some of the most \nconsequential decisions are made. For example, following the Critical Issue Fast Path \nstakeholder process for the reliability backstop procurement, the PJM Board developed \nits own proposal and submitted it to FERC. Stakeholders do not know how the Board \nreached its final decision, what tradeoffs it made, and why certain features were \nselected. AEP strongly supports the Board’s decisive adoption of its own proposal \nfollowing robust stakeholder input. However, future processes should be more \ntransparent, which in turn will promote better future engagement and enhance the \nlegitimacy of the PJM Board’s decisions. To promote transparency, the Board should \nprovide public access to meetings not involving confidential topics (e.g., personnel, \nsecurity).51 \n3. PJM should adopt an in-region preference for Board candidates. Given the \nimportance of regional knowledge to reliability, affordability, and economic-\ndevelopment decisions, AEP recommends a preference for Board candidates who \nreside within the PJM footprint or have significant professional experience with the \nregion’s electric system. Both ISO-NE and NYISO maintain such preferences.52 \n \n \n49 These reforms—which draw on the governance practices of other RTOs and ISOs—are addressed in \ndetail in the AEP Statement, App’x at 9-13. \n50 See AEP Statement, App’x at 9-10 (citing PJM Operating Agreement § 7.1; MISO Bylaws Art. IV § 4.1, \nArt. V § 5.4; SPP Bylaws § 4.2.1; NYISO Bylaws Art. III § 3(a)). \n51 See Chandler Statement at 3-4. \n52 See AEP Statement, App’x at 10-11 (citing ISO-NE Participants Agreement § 9.2.2; NYISO Bylaws Art. \nIII § 2)."},{"page":20,"startToken":5948,"endToken":6325,"text":"20 \n4. PJM should shorten its cooling-off period for prospective Board members. Reducing \nthe cooling-off period for Board members from two years to one would improve the \npool of qualified candidates with current industry experience while maintaining Board \nindependence. This change would be consistent with MISO’s 2017 reform and with the \npractices of ISO-NE and SPP, which have no cooling-off periods.53  \n5. PJM should limit incumbent Board control over nominations. Reducing the role \nincumbent Board members play in the Nominating Committee process would avoid \nstatus-quo bias and improve accountability to PJM members. CAISO and ERCOT \nprovide no formal role for incumbent directors in their nomination processes.54  \nThese reforms are targeted adjustments, not a wholesale restructuring. Each preserves \nBoard independence while improving the Board’s expertise, information flow, accountability, and \nresponsiveness—qualities the technical conference record shows the region urgently needs. \nE. \nThe Commission Should Not Impose a Novel “Public Interest” Requirement \nSome participants have suggested that PJM’s governing documents be amended to require \nthe Board to act in the “public interest.” This proposal, however well intentioned, misconceives \nPJM’s role as an RTO (not a regulator) charged with providing nondiscriminatory open access to \nthe regional transmission system, operating the grid reliably, and administering efficient wholesale \nmarkets that serve customers at least cost.55 A generalized “public interest” obligation would run \ncounter to the overriding goal in this proceeding of facilitating nimble and decisive Board action \nby creating an undefined standard that the Board would have to interpret on the front end and that \ncould create litigation risk on the back end. Meanwhile, the public interest is already protected—\n \n \n53 See id. at 11 (citing PJM Operating Agreement § 7.2; Midcontinent Indep. Sys. Operator, Inc., Docket \nNo. ER17-686-000, Transmittal Letter at 8-9 (filed Dec. 28, 2016); ISO-NE Participants Agreement § 9.3.1; \nISO-NE Code of Conduct § 2.2; SPP Bylaws § 4.2.3). \n54 See id. at 12 (citing PJM Operating Agreement § 7.1; CAISO Board Selection Policy § 4.2; Tex. Utils. \nCode § 39.1513(a), (d)). \n55 See 18 C.F.R. § 35.34(j)-(k) (prescribing an RTO’s minimum characteristics and functions); Reg’l \nTransmission Orgs., Order No. 2000, FERC Stats. & Regs. ¶ 31,089 (1999), order on reh’g, Order No. \n2000-A, FERC Stats. & Regs. ¶ 31,092 (2000)."},{"page":21,"startToken":6325,"endToken":6560,"text":"21 \nthe FPA obliges the Commission to ensure that RTO rates are just, reasonable, and \nnondiscriminatory.  \nIV. \nPJM Must Implement Reforms that Allow Greater State Input \nAEP supports targeted reforms to PJM’s governance framework that improve the ability of \nresponsible entities to bring concrete, actionable proposals to the Commission under Section 205. \nAny expansion of filing rights should be balanced and carefully defined—preserving the existing \nSection 205 rights of transmission owners while recognizing the central and evolving role of states \nin resource adequacy, affordability, economic development, and public policy matters. The \nCommission should encourage governance reforms that promote timely action, transparency, and \naccountability without undermining the legal responsibilities and investment obligations of \ntransmission owners. \nA. \nGeneral Principles: Filing Rights Must Align with Legal Responsibility and \nReforms Must Enable Timely Action While Preserving FERC’s Role \nSection 205 filing rights should rest with, or be made available to, entities that have direct \nresponsibility for serving customers, maintaining reliability, making long-term infrastructure \ninvestments, and implementing public policy requirements. PJM’s current governance \nframework—including the allocation of Section 205 rights—was developed in a different \noperating environment, one characterized by slower load growth, surplus generation, and \nincremental infrastructure needs.56 As that operating environment has changed, PJM’s governance \nmust be updated to align filing authority with legal responsibility regarding today’s reliability, \nresource adequacy, transmission-expansion, and affordability challenges.  \n \n \n56 See PJM Comments at 2-3, 7; AEP Statement at 9."},{"page":22,"startToken":6560,"endToken":6848,"text":"22 \nAs states bear increasing responsibility for resource adequacy policy, economic \ndevelopment strategy, transmission siting, and customer affordability, they should have a defined \nmechanism to advance regional tariff reforms within their collective jurisdiction. OPSI explained \nthe point forcefully: state officials “remain accountable for outcomes they have little power to \nformally shape,” and need “a more formal means of presenting their proposals to the Commission \non a level playing field with PJM and the [transmission owners].”57 At the same time, transmission \nowners must retain meaningful filing rights, because they remain responsible for owning, \noperating, maintaining, and investing in jurisdictional transmission facilities and for complying \nwith applicable FERC and reliability obligations. \nAnother important reform principle is that PJM’s governance should not require unanimity \nor extended stakeholder deadlock before needed reliability, market, or transmission reforms can \nmove forward. Expanding access to Section 205 filing mechanisms can provide a constructive path \nto facilitate innovative solutions while preserving the Commission’s role as the independent \nregulator charged with determining whether a proposal is just and reasonable. As PJM emphasized, \neven where a proposal is filed under Section 205, “stakeholders, of course, may continue to provide \nfeedback or challenge the proposal before the Commission,” which “is ultimately responsible for \ndetermining whether a proposed Tariff change is just and reasonable.”58 A reformed filing-rights \nframework should improve transparency by making disagreements visible to the Commission and \nallowing proposals to be tested in an open record. The ultimate objective should be a governance \n \n \n57 OPSI Comments at 1-2; see also Finkel Statement at 1 (describing a “fundamental gap” between those \naccountable for reliability and affordability—the states and the Board—and the private Members with \nauthority over many of the solutions). \n58 PJM Comments at 7."},{"page":23,"startToken":6848,"endToken":7122,"text":"23 \nstructure that empowers responsible entities to act, encourages collaboration, and gives the \nCommission a clear record on which to resolve competing proposals. \nB. \nPJM Should Adopt a Limited, Collective State Filing Mechanism for \nResource Adequacy Issues While Preserving Transmission Owners’ Section \n205 Rights \nAEP supports providing states with a defined and limited ability to initiate Section 205 \nfilings on matters within their collective jurisdiction—namely, resource adequacy. That authority \nshould be exercised through an established regional process, such as OPSI or another collectively \ngoverned state body, rather than through unilateral filings by individual states. A collective \nmechanism would recognize the important role states play in protecting consumers and advancing \npolicy objectives while reducing the risk of fragmented or conflicting individual state filings. \nSeveral participants advanced complementary versions of this idea. For instance, OPSI proposed \nthat, where its members agree on resource adequacy or transmission cost allocation reforms, PJM \nor the transmission owners should be required to provide that solution to FERC “in a way that \nFERC can accept it.”59 And Abraham Silverman, research scholar at Johns Hopkins University \nand principal at SilverGreen Energy Consulting, proposed a funded PJM States Committee, \nmodeled on NESCOE, with co-filing rights over at least the resource adequacy portions of the PJM \nTariff.60  \nAEP believes a collective state filing mechanism could provide significant value as PJM \nworks to address novel resource adequacy challenges. However, any such collective state filing \nmechanism must be limited to proposals related to resource adequacy issues that are appropriately \nwithin states’ collective authority, and must not displace or dilute transmission owner filing rights \n \n \n59 OPSI Comments at 1. \n60 Silverman Statement at 2-3."},{"page":24,"startToken":7122,"endToken":7408,"text":"24 \nover transmission rates, planning responsibilities, cost allocation, or the facilities transmission \nowners own and operate. \nTransmission owners must retain their existing Section 205 rights over matters affecting \ntransmission rates, revenue requirements, cost allocation, planning responsibilities, transmission \nowner agreements, and the facilities they own and operate.61 These rights are not merely \nprocedural; they are essential to enabling transmission owners to fulfill their obligations to \nmaintain reliability, invest in the transmission system, comply with FERC and NERC \nrequirements, and protect customers. As the Commission made clear in Order No. 2000, “a \ntransmission owner must have independent authority to set the level of its portion of the revenue \nrequirement to be collected by the RTO.”62 Governance reform must not shift authority away from \nthe entities that bear the legal, operational, and financial responsibility for transmission service \nand system performance. Preserving transmission owner filing rights also ensures that the \nCommission receives fully developed alternatives when PJM’s stakeholder processes fail to yield \ntimely or adequate reforms. \nC. \nPJM Should Consider a “Jump-Ball” Section 205 Filing Framework \nThe Commission should encourage PJM and its stakeholders to consider a “jump-ball” \nfiling framework that allows competing Section 205 proposals to be presented to the Commission \nin appropriate circumstances. Such a framework could apply when PJM, the transmission owners, \nor a supermajority of states advance competing proposals on issues implicating their respective \nresponsibilities and stakeholder consensus cannot be reached. A jump-ball process follows an \n \n \n61 See PJM Open Access Transmission Tariff § 9.1 (reserving to Transmission Owners the “exclusive and \nunilateral” right to file changes relating to the establishment and recovery of their transmission revenue \nrequirements and transmission rate design). \n62 Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 31,076."},{"page":25,"startToken":7408,"endToken":7732,"text":"25 \nestablished model: ISO-NE’s governing documents already allow a New England Power Pool \n(“NEPOOL”)-supported alternative to be filed alongside the ISO’s own proposal, with the \nCommission free to adopt either proposal that it finds just and reasonable.63 \nA jump-ball approach would allow the Commission to evaluate competing just-and-\nreasonable proposals in a single proceeding, rather than forcing stakeholders through a more \nburdensome Section 206 complaint process. It would promote efficiency—instead of protracted \ndebates at PJM about which specific proposal should be presented to the Commission, multiple \ncompeting proposals could be developed in parallel. It also would improve accountability and \nencourage negotiation, because parties would know that the Commission may evaluate an \nalternative proposal on the merits. State officials specifically endorsed such a mechanism for \nmatters within state jurisdiction.64 Any jump-ball mechanism must include clear eligibility \nstandards, voting thresholds, issue limitations, and safeguards to avoid duplicative or strategic \nfilings. \nCONCLUSION \nPJM’s stakeholders—from transmission owners and generators to states and consumer \nadvocates—are committed to serving customers across the region reliably and at just and \nreasonable rates. But too often, PJM’s governance structure has inhibited, rather than facilitated, \nthat essential work. The technical conference record confirms the need for reform and points the \nway toward concrete solutions. PJM should adopt the reforms described above: a true advisory \n \n \n63 See ISO-NE Participants Agreement § 11.1.5 (providing that, where the Participants Committee approves \nan alternative Market Rule proposal by at least 60% of the aggregate sector voting shares, ISO-NE must \ndescribe that alternative in its Section 205 filing and the Commission “may adopt any or all” of either \nproposal as it finds “just and reasonable and preferable”). \n64 See Bagot Statement at 2 (describing longstanding state advocacy for “jump-ball” Section 205 rights over \nresource adequacy and transmission cost allocation); Tweedie Comments at 1-2 (proposing that, upon \nsupermajority support of a state committee, PJM file the states’ proposal as an alternate “jump-ball” filing)."},{"page":26,"startToken":7732,"endToken":7846,"text":"26 \nstakeholder model; a reexamination of Section 205 filing rights over core functional matters; a \nlimited, collective state filing mechanism that preserves transmission owners’ rights; consideration \nof a “jump-ball” mechanism; and targeted reforms to improve Board transparency, accessibility, \nexpertise, and accountability. These reforms would align legal responsibility, authority, and \naccountability so that PJM can make the timely, technically sound decisions the region urgently \nrequires and implement a near-term action framework that will bring generation online in time to \nserve new load. \n \n \nRespectfully submitted, \n \n \n/s/ John C. Crespo \n \n \nJohn C. Crespo \nSenior Legal Counsel \nAmerican Electric Power Service Corporation\n1 Riverside Plaza \nColumbus, OH 43215 \nTelephone: (614) 716-3727 \nE-mail: jccrespo@aep.com  \nAugust 21, 2026"},{"page":27,"startToken":7846,"endToken":8167,"text":"27 \nAppendix \nPJM Governance and Stakeholder Reforms – Docket No. AD26-7-000 \nAEP Responses to Post Technical Conference Questions \n \nPJM Board Independence \n \nQuestions/Comments \nYes \nNo \n1) \nShould Board members’ terms be extended to five or more years? \nYes \n \n \nComments: AEP supports a term for Board members up to and including 5 years, with a \nlimit of no more than two consecutive terms.  This term change should be implemented \nonly if the broader reforms also establish clear Board qualification requirements and a \nresidency preference to ensure the Board has the appropriate experience, expertise, and \nregional representation. \n2) \nShould there be a maximum number of years that a Board member may \nserve (e.g., 10 years)? \n \nNo \n \nComments: An arbitrary maximum number of years of service is not needed, subject to \nthe limitation that a Board member should serve no more than ten years consecutively \n(i.e., two consecutive 5-year terms).   \n3) \nShould the Board member qualification rules be revised to provide a \npreference for some Board members that reside in the PJM region? \nYes \n \n \nComments: Yes, there should be a preference for Board members to have both \npermanent residence in the PJM region and meaningful professional experience related \nto PJM, ensuring that residency reflects substantive knowledge and experience with the \nregion rather than simply maintaining an apartment or other place of residence.    \n4) \nShould the conflict-of-interest rules be revised to reduce the cooling off \nperiod for Board members from two years to one year? \nYes \n \n \nComments: Yes, the conflict-of-interest rules have likely prevented PJM from attracting \nqualified candidates. Reducing the cooling off period for Board members from two years \nto one year could help broaden the pool of qualified, potential PJM Board candidates. \n5) \nShould restrictions on Board communications be relaxed to enable more \ncommunication between the Board and stakeholders? \nYes \n \n \nComments: Yes, AEP recommends permitting direct communication between \nstakeholders and individual Board members consistent with the governance practices \nemployed by peer RTOs."},{"page":28,"startToken":8167,"endToken":8458,"text":"28 \n \nQuestions/Comments \nYes \nNo \n6) \nIn order to increase transparency, should Board votes be made public or \nthe Board be required to explain its reasoning?  \nYes \n \n \nComments: Board meetings and Board votes should be public to promote transparency \nand accountability. When the Board departs from or rejects the recommendations of the \nstakeholder process, it should publicly explain the rationale for its decision.  \n7) \nIn order to increase transparency, should some Board meetings be open or \navailable to the public? \nYes \n \n \nComments:  Yes, AEP recommends conducting Board meetings in an open and publicly \naccessible manner whenever practicable, with only limited executive sessions for matters \ninvolving confidential, personnel, litigation, or other legally protected information. \n8) \nShould PJM’s governing documents be revised to explicitly state that the \nresponsibility of PJM and its Board is to serve the public interest? \n \nNo  \n \nComments: AEP would not support adding a broad, standalone requirement to PJM’s \ngoverning documents that PJM and its Board must serve the “public interest.” While \nAEP recognizes the importance of considering broader public interests in PJM’s \ndecision-making, the term can be subjective and could create uncertainty or additional \ncomplexity in Board deliberations. AEP believes PJM’s existing mission and governance \nframework, together with FERC’s established oversight, provide an appropriate basis for \nbalancing reliability, affordability, and the diverse interests of PJM stakeholders. \n9) \nShould state representatives have at least one voting member on the \nNominating Committee? \nYes \n \n \nComments: Yes, state representatives should have at least one voting member on the \nNominating Committee.  \n10) Should PJM adopt public performance metrics and tie management \ncompensation to their achievement? \nYes \n \n \nComments: Yes, the Board should undertake a process of identifying measurable goals \nfor PJM leadership. The goals should be implemented and made public prior to each new \nyear."},{"page":29,"startToken":8458,"endToken":8839,"text":"29 \nSection 205 Filing Rights \n \nQuestions/Comments \nYes \nNo \n11) \nShould the stakeholder process be advisory, i.e., stakeholder votes only \ninform the Board? \nYes \n \n \nComments: Yes, the stakeholder process should be advisory and inform, rather than \ndirect, the Board. The process should provide the Board with the benefit of diverse \nstakeholder perspectives, technical expertise, and thoughtful analysis while preserving \nthe Board’s responsibility to exercise independent judgment. The Board should \ncarefully consider stakeholder recommendations but retain the authority to make \ndecisions in the best interests of PJM’s reliability, affordability, and overall \neffectiveness. Where the Board reaches a different conclusion from the stakeholder \nprocess, it should provide a clear explanation of the rationale for its decision. \n12) \nShould PJM have section 205 filing rights over the energy market and \nancillary services unencumbered by the requirement to obtain approval \nof two-thirds of the Members Committee? \nYes \n \n \nComments: Yes, PJM should have Section 205 filing rights over core functional matters \nsuch as energy and ancillaries markets, regional transmission planning, resource \nadequacy, and interconnection reform. \n13) \nShould PJM have section 205 filing rights over Regional Transmission \nExpansion Planning (RTEP) unencumbered by the requirement to \nobtain approval of two-thirds of the Members Committee? \nYes \n \n \nComments:  Yes, PJM should have 205 filings rights over regional transmission \nplanning. Providing PJM with appropriate filing authority would allow the organization \nto more effectively implement regional planning reforms and respond to evolving \nreliability and system needs. This authority should be paired with appropriate \nstakeholder input and Board oversight, while preserving FERC’s ultimate authority to \nreview and approve proposed changes. \n14) \nShould the Organization of PJM States Inc (OPSI) have “jump ball” \nrights over resource adequacy and transmission cost allocation filings \nwhen a supermajority of OPSI agrees on an alternative proposal? \nYes \n \n \nComments: Yes, AEP supports a limited “jump ball” framework for resource adequacy \nfilings where there is broad state consensus. Such a framework could promote \ncollaboration, strengthen state and stakeholder engagement, and allow FERC to evaluate \ncompeting proposals in a single proceeding under the just and reasonable standard. \nHowever, any such right should be subject to clear safeguards. It should be available \nonly where the alternative proposal reflects support from a supermajority of PJM states \n(10 or greater states), not merely a narrow supermajority, and it should not be used to"},{"page":30,"startToken":8839,"endToken":9112,"text":"30 \n \nQuestions/Comments \nYes \nNo \nshift the costs of one state’s public policy choices to neighboring states.  For example, \nin 2020/21, only 11 PJM states had a renewable or clean energy standard, raising the \nproblem of cost shifts to states without those standards from public policy projects. \n15) \nShould the Members Committee have “jump ball” filing rights over the \nportions of the tariff where PJM has 205 filing rights when a \nsupermajority of stakeholders approves an alternative proposal? \nYes \n \n \nComments: Yes, PJM should evaluate adopting a “jump ball” filing process similar to \nother regional transmission organizations. When PJM, Transmission Owners, or a \nsupermajority of states disagree on a proposed tariff revision, FERC should have the \nopportunity to evaluate competing Section 205 proposals in a single proceeding. A jump \nball framework promotes collaboration, strengthens stakeholder engagement, and allows \nFERC to select the proposal that best satisfies the just and reasonable standard. \n \nStakeholder Process \n \nQuestions/Comments \nYes \nNo \n16) Should the approval threshold in the Members Committee be lowered \nfrom two-thirds sector-weighted voting? \nYes \n \n \nComments: AEP’s preferred approach is for the stakeholder process to be advisory over \nmatters where PJM has 205 filing rights.  As noted above, PJM’s filing rights should be \nexpanded to include core functional matters.  The Members Committee’s authority over \ncorporate governance of the RTO should be distinguished from rights over core \nfunctional matters.  The Members Committee may retain its existing two-thirds sector-\nweighted voting for corporate governance matters. \n17) Should the voting rules barring affiliate votes, which apply to senior \nstanding committees, also apply to lower-level committees? \nYes \n \n \nComments: AEP’s preferred approach is for the stakeholder process to be advisory."},{"page":31,"startToken":9112,"endToken":9425,"text":"31 \nState Participation \n \nQuestions/Comments \nYes No \n18) In addition to OPSI, should there be a second state representative group \nconsisting of governors’ representatives and/or state legislators’ \nrepresentatives? \nYes  \n \nComments: Yes, there could be a second state representative group. However, each \ngroup must have well-defined roles, responsibilities and membership. Also, each group \nmust have accountability alongside their defined responsibility.  \n19) Should state representatives have a formal voting role in the stakeholder \nprocess (limited to certain topics, such as resource adequacy and regional \ntransmission cost allocation) in addition to the consumer advocate votes?  \nYes  \n \nComments: Yes, provided that the stakeholder process is advisory. Any new state role \nshould be well-defined and rights and responsibilities should align with accountability.  \n20) Should PJM be required to consult with OPSI prior to making a section \n205 filing related to resource adequacy and transmission cost allocation? \nYes  \n \nComments: Yes. AEP supports a formal consultation right for the states with respect to \nSection 205 filings on matters within state jurisdiction, with the exception of certain \ntransmission cost allocation issues. The consultation process should provide states with a \nmeaningful opportunity to review and provide input before a filing is submitted, while \npreserving the Board’s ability to act within appropriate timelines. \nPJM Transmission Owners already have Section 205 filing rights, and any state \nconsultation process should recognize and preserve those existing rights. Consultation \nwith OPSI should also occur today as a matter of course on matters affecting state \ninterests and does not require a change to PJM’s governing documents. More broadly, \nthe process should apply to whatever entity or body is ultimately established to represent \nthe collective interests of the states before PJM, whether that remains OPSI or is \nreplaced by a new state body. \nThe consultation process should be clearly defined and structured to promote \ntransparency and meaningful state input without creating unnecessary delays or \nambiguity regarding filing authority."},{"page":32,"startToken":9425,"endToken":9489,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that on this 21st day of August, 2026, I have served a copy of the \nforegoing document on the official service list compiled by the Office of the Secretary for the \nabove-referenced proceeding. \n \n/s/ LaChon Turner \nLaChon Turner \nParalegal \nAmerican Electric Power Service Corporation \n801 Pennsylvania Ave NW \nSuite 735 \nWashington, DC 20004 \n(202) 383-3465 \nlturner@aep.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":13,"startToken":0,"endToken":769},{"p":4,"at":13,"title":"I. PJM Must Swiftly Implement Solutions to Help Address Its Most Significant","method":"printed heading","endPage":6,"endAt":1022,"startToken":769,"endToken":1428},{"p":6,"at":1022,"title":"II. The Technical Conference Record Demonstrates the Need for Reform","method":"printed heading","endPage":7,"endAt":3,"startToken":1428,"endToken":1599},{"p":7,"at":3,"title":"A. Stakeholders Agree PJM Must Act More Quickly and Decisively","method":"printed heading","endPage":10,"endAt":4,"startToken":1599,"endToken":2741},{"p":10,"at":4,"title":"B. The Record Reflects a Need to Carefully Calibrate the Board’s and","method":"printed heading","endPage":11,"endAt":507,"startToken":2741,"endToken":3168},{"p":11,"at":507,"title":"C. Governance Changes Must Emphasize Concrete Reforms, Not Process for","method":"printed heading","endPage":12,"endAt":860,"startToken":3168,"endToken":3468},{"p":12,"at":860,"title":"III. PJM’s Board and Management Must Have Clear Authority to Address Reliability,","method":"printed heading","endPage":13,"endAt":120,"startToken":3468,"endToken":3658},{"p":13,"at":120,"title":"A. PJM Must Reexamine Section 205 Filing Rights for Core Functional Matters","method":"printed heading","endPage":14,"endAt":1107,"startToken":3658,"endToken":4171},{"p":14,"at":1107,"title":"B. PJM Must Convert the Stakeholder Process Into a True Advisory Model","method":"printed heading","endPage":16,"endAt":403,"startToken":4171,"endToken":4664},{"p":16,"at":403,"title":"C. PJM Must Limit Its Ex Parte Restrictions to Improve Board Transparency,","method":"printed heading","endPage":19,"endAt":4,"startToken":4664,"endToken":5539},{"p":19,"at":4,"title":"D. PJM Must Implement Additional Targeted Board Reforms to Improve","method":"printed heading","endPage":20,"endAt":1003,"startToken":5539,"endToken":6089},{"p":20,"at":1003,"title":"E. The Commission Should Not Impose a Novel “Public Interest” Requirement","method":"printed heading","endPage":21,"endAt":108,"startToken":6089,"endToken":6341},{"p":21,"at":108,"title":"IV. PJM Must Implement Reforms that Allow Greater State Input","method":"printed heading","endPage":21,"endAt":858,"startToken":6341,"endToken":6440},{"p":21,"at":858,"title":"A. General Principles: Filing Rights Must Align with Legal Responsibility and","method":"printed heading","endPage":23,"endAt":166,"startToken":6440,"endToken":6871},{"p":23,"at":166,"title":"B. PJM Should Adopt a Limited, Collective State Filing Mechanism for","method":"printed heading","endPage":24,"endAt":1194,"startToken":6871,"endToken":7286},{"p":24,"at":1194,"title":"C. PJM Should Consider a “Jump-Ball” Section 205 Filing Framework","method":"printed heading","endPage":25,"endAt":1100,"startToken":7286,"endToken":7560},{"p":25,"at":1100,"title":"CONCLUSION","method":"printed heading","endPage":32,"endAt":0,"startToken":7560,"endToken":9425},{"p":32,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":32,"endAt":419,"startToken":9425,"endToken":9489}]}