{"document":{"slug":"rec-20260821-5243","title":"Comments of Equinix Inc. on the PJM Interconnection, LLC filing re Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from…","issued":"2026-08-21","accession":"20260821-5243","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"EQUINIX INC.","kind":"comments","file":"sources/filings/text/20260821-5243_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5243","tier":"record","sha256":"907abeb182beec32585ebd6e4a939c0b996c5eacbf5538ab649a1f7f120c9c67","pages":20,"tokens":6502,"emptyPages":[],"textThemes":["credit","adequacy","cost","flex"]},"pages":[{"page":1,"startToken":0,"endToken":274,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n) \n \nPJM Interconnection, L.L.C.  \n \n) \nDocket No. ER26-3380-000 \n \n \n) \n \n \nCOMMENTS OF EQUINIX INC. ON THE \nPJM INTERCONNECTION, LLC FILING REGARDING ITS \nRELIABILITY BACKSTOP PROCUREMENT TO ADDRESS  \nRESOURCE ADEQUACY CONCERNS STEMMING FROM LARGE LOADS \n \nEquinix Inc. (“Equinix”) is pleased to have this opportunity to contribute its comments in \nresponse to the filing by PJM Interconnection, L.L.C. (“PJM”) entitled “Reliability Backstop \nProcurement to Address Resource Adequacy Concerns Stemming From Large Loads” (the “RBP \nFiling”), which PJM submitted on July 31, 2026.1  We respectfully provide these comments for \nconsideration by the Federal Energy Regulatory Commission (“Commission” or “FERC”) \npursuant to Rules 211 and 214 of its Rules of Practice and Procedure, 18 C.F.R. §§ 385.211, \n385.214, and the Commission’s notice issued in this docket.2  \nI. SUMMARY \nEquinix supports the adoption of the RBP on the timeline proposed by PJM. It is an \nurgent and necessary mechanism which, if applied as intended as a one-time backstop, can help \n \n1 PJM Interconnection, L.L.C., “Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from New Load Adjustments,” Docket No. ER26-3380-000, Transmittal Letter (July 31, 2026) \n(“Transmittal”). Capitalized terms not defined herein have the meanings given in the Transmittal, the PJM Open \nAccess Transmission Tariff (“PJM Tariff”), or the PJM Reliability Assurance Agreement among Load Serving \nEntities (“RAA”). \n2 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, Combined Notice of Filings, 91 Fed. Reg. 50,827 \n(Aug. 6, 2026) (establishing a comment date of August 21, 2026). Equinix filed a timely doc-less motion to \nintervene in this proceeding on Thursday, August 6, 2026."},{"page":2,"startToken":274,"endToken":637,"text":"2 \nsupport much-needed near-term stability for both market and reliability conditions. However, \nEquinix believes FERC direction is required to achieve several key objectives: to enable  the \nbilateral procurement that all parties agree is the preferred path; to ensure the RPB is to truly \nfunction as a backstop, and not the default mechanism; to ensure the RBP is truly a one-time \nstabilization measure and not a recurring feature of the PJM market; and to avoid unnecessarily \nexacerbating the energy affordability concerns that have driven the extremely high degree of \npolitical and public attention on energy rates.  \nEquinix asks that FERC take the following actions: \n1) Direct PJM, before the RBP bid submission window opens, to publish clear and \ncomplete requirements for demonstrating Qualifying RBP Offset UCAP MW, \nincluding the evidence PJM will accept and the process by which large loads may \nsubmit that evidence directly; \n2) Direct PJM to provide affected loads sufficient transparency into the Large Load \nAdjustment data underlying RBP cost allocation, subject to appropriate \nconfidentiality protections, together with a process to correct demonstrable errors \nor duplication;  \n3) Modify the proposed buyer-side RBP Collateral provisions so that collateral is \ncalibrated to reasonably foreseeable forward exposure and the forms of credit \nsupport available under Attachment Q are permitted. PJM expressly consented to \nCommission modification or severance of its Section 205 proposal pursuant to \nNRG Power Marketing, LLC v. FERC.3 The Commission therefore can make this \ndiscrete modification without rejecting or delaying the RBP. As proposed, the \n$1.5 million/MW requirement and restriction to cash or letters of credit would \nunnecessarily and significantly worsen energy affordability issues;  \n4) Make clear that acceptance of the RBP is an extraordinary, one-time response and \nencourage PJM to continue work on durable reforms that allow needed resources \nto be studied, interconnected, permitted, and placed in service on timelines \nconsistent with identified reliability needs; and \n5) Require PJM to initiate the process of identifying and evaluating tariff-codified \nmechanisms that can be deployed to address significant and potentially long-\nlasting supply-demand gaps. \n \n \n \n3 Transmittal at 3-4 (consenting to Commission modification or severance pursuant to NRG Power Marketing, LLC \nv. FERC, 862 F.3d 108 (D.C. Cir. 2017))."},{"page":3,"startToken":637,"endToken":955,"text":"3 \nII. BACKGROUND AND INTEREST OF EQUINIX \nEquinix, based in Redwood City, California, is one of the oldest and largest data center \ndevelopers in the world, with data centers across six continents, over 35 countries, and more than \n70 metropolitan areas. Private enterprises, network operators, cloud providers, governmental \nentities and nonprofits house computing equipment and interconnect with one another within \nEquinix’s International Business Exchange (“IBX”) data centers. Many of Equinix’s customers \nutilize the computing equipment in our data centers and the interconnection services we provide \nto enable critical services, such as emergency response, grid operations, medical information, \nand national security. Each individual IBX facility may house as many as 400 co-located \ncustomers. Our IBX data centers range between a few megawatts up to approximately 100 MW, \nand average in the mid-30 MWs. Equinix also develops, owns and operates larger xScale data \ncenters, which can exceed 750 MW. Our xScale data centers serve customers requiring a \nsignificant dedicated proportion, or even the entirety, of these larger facilities. The data centers \nEquinix develops, owns and operates are long-lived assets developed against investment \nhorizons measured in decades rather than quarters.  \nEquinix has operated in the PJM Region for decades. Its facilities include the very first \ncommercial data center in Data Center Alley in Northern Virginia, as well as numerous data \ncenters in the Chicago area, New Jersey, and Northern Virginia. Equinix takes retail electric \nservice from Electric Distributors and Load Serving Entities across the PJM Region and, in retail \nchoice jurisdictions, procures its supply through competitive retail suppliers. Depending on how \nEquinix’s procurement of new capacity is credited, Equinix may therefore bear charges resulting \nfrom the RBP as states and Relevant Electric Retail Regulatory Authorities (“RERRAs”) further \nallocate them, and could be directly affected by any IRAS load-reduction obligation. Equinix has \nno financial interest in the outcome of the RBP as a seller; its interest is entirely on the load side."},{"page":4,"startToken":955,"endToken":1221,"text":"4 \nEquinix has always held itself to a high standard of care for the communities it operates \nin. Recognizing that more is needed to meet the current moment, Equinix recently memorialized \nits practices explicitly through its U.S. Community Principles.4  These principles include \nEquinix’s commitment to power responsibility, ensuring it “pays the full cost of its grid \ninfrastructure needs so costs are not passed to consumers.”5 Equinix does not regard the \nreliability consequences of large load growth as someone else’s problem to solve, and it has \ncommitted capital to the long-term arrangements needed for new generating capacity and energy \ninfrastructure. \nEquinix’s interest in this proceeding is accordingly not in a lower capacity price next \nyear. It is in the long-term stability, predictability, and durability of the rules that govern \nreliability and market conditions, including resource adequacy, across the PJM Region. As a load \nthat intends to sign long-term supply commitments, Equinix needs to know what those \ncommitments will provide, what risks will remain, and how to best address those remaining \nrisks. That is the lens through which Equinix offers the comments that follow. \nIII.  \nINTRODUCTION \nEquinix supports PJM’s RBP approach as a one-time response to a severe resource \nadequacy shortfall posing a near-term threat to reliability. Equinix urges the Commission to \naccept the RBP on PJM’s proposed timeline while making limited, discrete modifications and \nclarifications that will make bilateral procurement more workable and avoid unnecessary \nfinancing costs. Those change can be made without delaying the procurement window or \ndisturbing the core design of PJM’s proposal. \n \n4 Available at https://equinixtogether.com/community-principles/.  \n5 Id."},{"page":5,"startToken":1221,"endToken":1582,"text":"5 \nEquinix asks the Commission to exercise particularly keen oversight to ensure that the \nRBP achieves its objective as a backstop, and does not become not the default procurement \nmechanism for new capacity. As PJM describes its intent, the RBP “will only procure the \ncapacity necessary to cover any remaining shortfall from the 2028/2029 BRA after PJM has \naccounted for new capacity being brought by new load.”6 The premise of the design of both the \nRBP and the closely-related Interim Resource Adequacy Service (“IRAS”) program7—as well as \nthe focus of the National Energy Dominance Council / PJM Governors’ Principles8 that \nprompted these new programs—is that large loads that bring their own new capacity should \nneither be procured for, nor charged for capacity procured for loads that failed to procure for \nthemselves. Equinix agrees with that premise without reservation, has signed on to the Ratepayer \nProtection Pledge,9 and has issued its own U.S. Community Principles10 that hold itself to an \neven higher standard of care for its communities, consistent with its nearly 30-year strong track \nrecord. In short, Equinix is among the companies developing new large loads that intends to \ncover that load with its own new capacity procurement. The premise only operates, however, if \nnew large loads can reasonably act on it with confidence.  \nEquinix therefore does not ask the Commission to hold the RBP back. It asks the \nCommission to condition its acceptance on the following points, none of which would require \nany delay in the implementation of the RBP: \n1) Equivalency. Whatever capacity qualifies as Qualifying RBP Offset UCAP MW \n \n6  Transmittal at 26. \n7  The IRAS is under consideration in Docket No. ER26-03515. \n8  Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026) (“NEDC/PJM \nGovernors’ Principles”) (urging PJM to “allocate the cost of any new capacity procured through the aforementioned \nReliability Backstop Auction to load serving entities (LSEs) with new data centers that have not self-procured new \ncapacity or agreed to be curtailable”), available at https://www.energy.gov/documents/statement-principles-\nregarding-pjm. \n9 Available at https://www.whitehouse.gov/ratepayer-protection-pledge/.  \n10 Op. cit. fn. 3 and associated text."},{"page":6,"startToken":1582,"endToken":2007,"text":"6 \nunder proposed section 18.2 must also qualify to relieve the associated load of \nreduction obligations under IRAS. Equinix recognizes that the Commission is limited \nin this docket to addressing issues raised within the IRAS docket, although PJM has \nthroughout its Transmittal Letter acknowledged the interaction of the two programs. \nTo the extent that PJM believes its proposed requirements for Qualifying RBP Offset \nUCAP MW would fail to meet the requirements of IRAS, however, that should be \nmade clear in this docket, and the Commission should consider whether the \nQualifying RBP Offset UCAP MW definition should be adjusted to address those \nconcerns so as to avoid conflicting or incompatible criteria.  \n2) Clarity, in time to be useful. The RBP bid submission window is scheduled to close \nthree weeks after it opens.11 PJM should be directed to publish, before that window \nopens, the specific evidentiary showing it will accept to verify Qualifying RBP Offset \nUCAP MW, including permissible treatment of commercially sensitive information \nand the process for direct submissions by large loads. \n3) Allocation transparency. Direct PJM to provide affected loads access, subject to \nappropriate confidentiality protections, to the zonal Large Load Adjustment data on \nwhich their RBP cost allocation will rest and a defined process to correct \ndemonstrable errors or duplication.12 \n4) Buyer-side collateral. Modify the proposed RBP Collateral provisions so that the \nRBP Credit Rate is calibrated to reasonably foreseeable forward exposure and the \nforms of credit support accepted under Tariff, Attachment Q are available. PJM has \nexpressly consented to Commission modification or severance of discrete aspects of \nits Section 205 proposal, so this change can be made without rejecting or delaying the \nRBP.13 \nSeparately, Equinix encourages the Commission to make clear that acceptance of the \nRBP is a response to extraordinary near-term conditions, not an endorsement of recurring \nbackstop procurements as a substitute for durable market, interconnection, transmission and \nother required reforms. PJM and its stakeholders should continue that longer-term work on a \nconsidered schedule rather than waiting for the next emergency. \n \n11  Transmittal at 32 (Qualifying RBP Offset UCAP MW “may be reported to PJM during the bid submission \nwindow, which will close three weeks after the window opening”); id. at 27 (targeting commencement of the \nprocurement window on September 30, 2026). \n12 Transmittal at 32 (Qualifying RBP Offset UCAP MW “may be reported to PJM during the bid submission \nwindow, which will close three weeks after the window opening”); id. at 27 (targeting commencement of the \nprocurement window on September 30, 2026). \n13 Op cit. fn. 3."},{"page":7,"startToken":2007,"endToken":2318,"text":"7 \nThese limited requests would preserve PJM's proposed procurement timeline while \nensuring it is reasonably feasible for load to undertake the bilateral procurement PJM intends and \nexpects to minimize the scope and total cost of the RBP. These requests would also serve to \nreduce or eliminate avoidable costs that otherwise would be passed through to customers, \nexacerbating energy affordability concerns. \nIV.  \nCOMMENTS \nA. \nThe RBP Is an Appropriate One-Time Response, but the Commission Should \nNot Assume Current Conditions are a One-Time Aberration. \nAs PJM’s RBP transmittal letter observes, the Commission has long recognized that \nwhere market-design measures alone prove insufficient, it “is willing to consider specific \nproposals to provide an appropriate last resort process such as an RTO/ISO administered auction \nto create a long-term commitment which can support cost-effective financing where the problem \nis projected to be a long-term one.”14 Equinix agrees that the present circumstances fit that \ndescription. Two consecutive auctions have cleared short at the cap; PJM represents that all \nevidence points to the December 2026 auction clearing short as well. Equinix accordingly \nsupports the RBP as a one-time mechanism, and supports PJM’s decision to design a tailored \ninstrument rather than invoke the Reliability Backstop Auction provisions that have sat unused in \nAttachment DD, section 16 for twenty years.15 The existing provisions were built for a different \nproblem. \nEquinix asks the Commission, however, not to lull itself—or the region—into the belief \nthat acceptance of the RBP would restore a “Pax PJM” in which supply and demand track one \n \n14  PJM Interconnection, L.L.C., 107 FERC ¶ 61,112, at P 21 (2004), order on reh’g, 110 FERC ¶ 61,053 (2005), \nquoted in Transmittal at 27. \n15  Transmittal at 29 (noting that the existing Reliability Backstop Auction in Tariff, Attachment DD, section 16 \n“was proposed over 20 years ago but has never once been used”)."},{"page":8,"startToken":2318,"endToken":2681,"text":"8 \nanother closely and the annual auction will do the rest. The conditions that produced the current \nshortfalls are structural. Supply did grow between the two auctions—by a net 1,294.4 MW ICAP \nbetween the 2027/2028 and 2028/2029 BRAs—but, as PJM puts it, “the addition of new supply \nhas not kept pace with rapid large load demand growth.”16 Replacement supply arrives on \ninterconnection, permitting, and construction timelines that no procurement mechanism can \ncompress below physical limits, while PJM’s own twenty-year forecast continues to project \nsignificant long-term load growth.17 The gap between those two rates is what produced the \n2027/2028 and 2028/2029 results, and nothing in the RBP changes either rate.  \nMorever, significant increases in demand and significant shortfalls in supply availability \nmay well occur as a result of multiple factors. While the current supply-demand gap is, \ninarguably, predominantly driven by data center growth, other causes of supply-demand \nimbalance could yield similarly untenable BRA results, as discussed further herein. A more \nthoughtful, advanced preparation that is thoroughly vetted through unrushed stakeholder and \nFERC review processes is needed to address the likelihood of significant supply-demand gaps in \nthe future. \nB. \nBilateral Procurement Is the Most Economic and Most Just and Reasonable \nPath: the Commission Should Ensure the RBP Does Not Displaces It. \n1. \nRBP Cost Allocation Should Align with Load Procurement of its Own \nNew Capacity. \nThe Commission’s long-held cost causation principle requires that “all approved rates \nreflect to some degree the costs actually caused by the customer who must pay them.”18 PJM \n \n16  Transmittal at 7 & n.16 (citing 2028/2029 Base Residual Auction Report, PJM Interconnection, L.L.C., 8 (July \n14, 2026)). \n17  Transmittal at 6-7 & n.15 (describing PJM’s updated 20-year load forecast and continued significant long-term \nload growth). \n18  Ill. Com. Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009)(citing KN Energy, Inc. v. FERC, 968 F.2d 1295, \n1300 (D.C. Cir. 1992); Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 708 (D.C. Cir. 2000); \nPacific Gas & Elec. Co. v. FERC, No. 03-1025, 373 F.3d 1315, 1320-21 (D.C. Cir. 2004))."},{"page":9,"startToken":2681,"endToken":3025,"text":"9 \ninvokes that principle in support of its allocation methodology, and correctly observes that \ndecrementing a zone’s allocation by Qualifying RBP Offset UCAP MW “guards against \nassigning costs to those who will not benefit from the addition of the new capacity procured \nthrough the RBP.”19 Equinix agrees. The difficulty is that the decrement will operate at the level \nof the Electric Distributor zone/area, and the further allocation within the zone is left to states \nand RERRAs under mechanisms that, in most jurisdictions, do not yet exist. New Jersey presents \none example of how that allocation can be properly structured with its recent Data Center Fair \nShare Act,20 and as PJM notes in its transmittal letter Virginia’s State Corporations Commission \nand the Data Center Coalition are collaborating on model tariff language that will hopefully also \nhelp address these questions.21 \nFurther allocation within each zone is left to states and RERRAs, as necessitated by the \nsplit in jurisdiction between wholesale and retail markets. As a result, the wholesale decrement \nalone cannot guarantee that the individual load responsible for qualifying bilateral procurement \nreceives the corresponding retail benefit.  \nEquinix does not ask the Commission to dictate retail allocation. It does ask PJM to \nprovide states and RERRAs the information needed to implement retail mechanisms consistent \nwith the RBP's design and cost-causation rationale. In particular, PJM should identify the \nQualifying RBP Offset UCAP MW reflected in each zone's decrement and work with state \nauthorities so those data can be used in retail proceedings. That coordination is important if the \nRBP is to encourage bilateral procurement while protecting customers that did not cause the need \n \n19  Transmittal at 102 (“By reducing allocated load further based on Qualifying RBP Offset UCAP MW, the \nproposed methodology guards against assigning costs to those who will not benefit from the addition of the new \ncapacity procured through the RBP.”). \n20 Data Center Fair Share Act, P.L. 2026, c, 32; S. 731, 222nd Leg., Reg. Sess. (N.J. 2026)(the “NJ Data Center Fair \nShare Act”). \n21 Transmittal at 10."},{"page":10,"startToken":3025,"endToken":3343,"text":"10 \nfor backstop procurement. \nIt is one thing to say that cost causation need not be perfect; it is another to socialize, \nwithin a rate class, the costs of either 1) speculation by others onto the members of that class \nwho behaved responsibly, or 2) large load adjustment calculations that are insufficiently tethered \nto reasonable assumptions and calculations. It is certainly true, as PJM asserts, that retail cost \nallocation measures are outside of PJM’s wholesale market jurisdiction.22  It is equally true, as \nPJM observes,  \n“[S]erving emerging large loads while meeting the mandates of the PJM state utility \ncommissions will ‘require proactive collaboration among states, industry, and PJM \nto develop standardized regulatory tools and model retail tariff structures that \nindividual state commissions may consider as they address the integration of new \nlarge electric loads.’”23 \nPJM is launching two tidal waves through its proposed market design changes, waves that would \ninevitably flow across the jurisdictional divide and impact the retail markets. The clearly \nforeseeable impacts of wholesale market changes on retail market conditions require further \naction. At the very least, consistent with the Transmittal’s acknowledgment of the need for \n“proactive collaboration,” PJM could convene state actors with relevant jurisdiction to \ncoordinate efforts.  This “proactive collaboration” could help ensure wholesale and retail market \nelements flange up with minimal unintended adverse consequences, and better realize the shared \nintent of the NCED/PJM Governors’ Principles and of PJM’s RBP filing to 1) incent large loads \nto bilateral procurement and 2) minimize energy affordability impacts.  \n \n22 See, e.g., Transmittal at 14-16. \n23 Transmittal at 11 (quoting Letter of Chair of Virginia State Corporation Commission, Kelsey Bagot and President \nand CEO of Data Center Coalition, Josh Levi to Ms. Paula Conboy, Chair of PJM Board of Managers, and Mr. \nDavid Mills, President and CEO of PJM Interconnection, L.L.C., at 1 (June 30, 2026), available at \nhttps://perma.cc/S7C6-C86H)"},{"page":11,"startToken":3343,"endToken":3855,"text":"11 \n2. \nBilateral Procurement Requires Clear, Usable Implementation Rules. \nEquinix asks the Commission to recognize that the RBP’s central design premise—that \nload will bring its own capacity—places a responsibility on load, and that load can only be \nreasonably expected to discharge that responsibility if four conditions are met: \n• First, PJM must clearly identify when and how Qualifying RBP Offset UCAP MW \nwill reduce the RBP procurement attributable to a zone and provide states and \nRERRAs information sufficient to trace that decrement to the procurement that \ncreated it. Load must be assured that new bilateral capacity procurement will protect \nit from RBP cost allocation. That assurance must be reliable at the level of the \nindividual load, not merely at the level of the zone.  \n• Second, load must be assured that the same new capacity procurement credited \nagainst RPB cost allocation will protect it from IRAS curtailment. As noted above, \nwhile the Commission is limited in what it can do with respect to IRAS in this docket, \nit can ensure that the definitions applicable to RBP do not conflict with those \napplicable to IRAS. As a practical matter, a load facing an unquantified probability of \ncurtailment cannot justify the cost of procuring new capacity: if it may be curtailed \nwhether or not it self-supplies, it has insufficient reason to bilateral procurement. The \ntwo instruments must be read together because, from a load perspective, there is very \nlittle purpose to considering them separately; protection from RBP cost allocation \npales in comparison to the risk of significant, lengthy and/or repeated curtailment that \ncould challenge continued reliability of the information systems our emergency \nresponse, financial, medical, security and other sectors- and even grid operations- \nhave come to rely upon. \n• Third, PJM should coordinate with the states and RERRAs responsible for retail \nallocation so they have the information necessary to implement the RBP's cost-\ncausation design, and consider a convening to ensure wholesale and retail rate designs \nwork as seamlessly together as possible. Again, Equinix does not ask the Commission \nto prescribe a retail rate or allocation methodology; it asks that the wholesale \nconstruct provide a usable factual foundation for the authorities that must make those \nretail decisions.  \n• Fourth, crediting terms must be defined clearly enough to permit effective, \nmanageable procurement by load, including the evidence that must be shown to \nensure that credit is awarded. The proposed Tariff sets out the elements at a high \nlevel—a signed bilateral contract of at least five Delivery Years, documentation of an \nexpected online date no later than June 1, 2032, and evidence matching the capacity \nto load.24 What it does not supply is the form and detailed content requirements of that \nshowing, including what documents PJM will accept, what redactions are permitted, \n \n24  Tariff, Attachment DD, section 18.2(c) (as proposed); Transmittal at 39 (bilateral contracts of at least five \nDelivery Years, documented expected online date no later than June 1, 2032, matched to load with an executed \nelectric service agreement or transmission service agreement for the 2027/2028 or 2028/2029 Delivery Years)."},{"page":12,"startToken":3855,"endToken":4301,"text":"12 \nwhat happens when a contract is contingent, and how a load whose Electric \nDistributor declines to report on its behalf can make the showing directly. PJM has \ncommitted to accept reports from “large loads” among others,25 which Equinix \nappreciates. PJM should be directed to publish the accompanying evidentiary \nspecification before the procurement window opens. Moreover, a load that has \nsatisfied PJM’s evidentiary standard once should not be required to satisfy a different \nstandard, on different evidence, for the other half of the same interconnected policy: \nas noted above, the criteria, and the evidence required to establish those criteria, must \nbe the same for both the RBP and the IRAS to support significant bilateral \ncontracting.26  Equinix anticipates raising this issue as appropriate in the IRAS \nproceeding.  \n4. \nThe Peak Shaving, Five year Minimum Term, and Fixed RBP Credit \nLevel Features Properly Support Bilateral Procurement. \nPeak shaving. Equinix applauds PJM’s recognition, in the second proposed opt-out, that \nto the extent load participates in a state-codified peak shaving adjustment program, it has already \naddressed that extent of its capacity needs and should not be procured for again.27 That \nrecognition is sound and should be preserved in the RBP. The Transmittal separately notes that a \nzone/area receiving that opt-out may still be subject to load reduction under IRAS.28  While that \nissue is not formally before the Commission in this docket, other than the reference in the \nTransmittal letter itself, Equinix flags it because 1) the reference threatens to undermine the use \nof the Peak Shaving programs to achieve the objectives of the RPB, and 2) the interaction \nbetween a federal curtailment construct and state-codified peak-shaving programs raises distinct \n \n25  Transmittal at 43 (PJM “will also accept reports and evidence of Qualifying RBP Offset UCAP MW provided \nduring the RBP bid submission window by other jurisdictional, as well as non-jurisdictional entities, including, but \nnot limited to, Transmission Owners, LSEs, interconnecting customers, large loads, and state regulatory agencies.”). \n26 To be clear, Equinix does not ask that the RBP’s seller-side eligibility rules be conformed to the offset rules. PJM \nhas given reasoned explanations for holding RBP Resources to more stringent standards than Qualifying RBP Offset \nUCAP MW—those resources take a fifteen-year commitment and a must-offer obligation, and PJM is entitled to \ninsist on a higher showing of viability. The potential asymmetry Equinix objects to is the one between the two load-\nside constructs, where no such justification has been offered, and where conflicting requirements could undermine \nthe objectives of both programs. \n27 Transmittal at 45 (citing NJ Data Center Fair Share Act ); Tariff, Attachment DD, section 18.1(d) (as proposed). \n28 Transmittal at 45."},{"page":13,"startToken":4301,"endToken":4610,"text":"13 \njurisdictional and policy questions, which Equinix anticipates addressing in the IRAS \nproceeding.  \nFive-year minimum term. Equinix supports PJM’s selection of a five-Delivery-Year \nminimum term for the bilateral contracts and bilateral procurement arrangements that may \ngenerate Qualifying RBP Offset UCAP MW.29 The balance PJM strikes is the right one: a five-\nyear floor is long enough to demonstrate that the capacity has been well-established, is not \ntransitory, and is likely to be available to support resource adequacy needs even after the initial \ncontracting term is over. It is also short enough to avoid foreclosing commercially reasonable \nstructures, as well as avoiding excess costs and financing burdens, all of which would serve to \ndeter bilateral contracting. A longer minimum would have excluded a meaningful share of the \nvery bilateral procurement the RBP is designed to encourage. \nFixing the RBP credited value at the time of procurement. Equinix likewise supports \nPJM’s proposal to determine the UCAP value of Qualifying RBP Offset UCAP MW using the \napplicable ELCC Class Ratings for the 2028/2029 Delivery Year BRA, or unit-specific UCAP \nvalues where no class rating exists, rather than re-rating that capacity annually over the life of the \narrangement.30 Load contracting today cannot price accreditation risk fifteen years forward, and \na floating credit would transfer to load a modeling risk it has no ability to manage. Fixing the \ncapacity value at the time of procurement solely for purposes of crediting against the RBP and its \ncost allocation (and not for operational reliability reasons) is therefore just, reasonable, and an \nimportant feature of making long-term bilateral commitments feasible. Equinix therefore urges \nthe Commission to preserve this element in the RBP. Equinix anticipates addressing the \n \n29  Transmittal at 39-40; Tariff, Attachment DD, sections 18.2(c)(i)-(ii) (as proposed). \n30  Transmittal at 32; Tariff, Attachment DD, section 18.2(d) (as proposed)."},{"page":14,"startToken":4610,"endToken":4987,"text":"14 \ntreatment of accreditation under IRAS in the separate IRAS proceeding. \nC.  \nThe Commission Should Modify the Proposed Buyer-Side RBP Collateral \nRequirement to Avoid Excessive and Unduly Restrictive Requirements. \nPJM proposes to require each LSE allocated RBP cost responsibility to post RBP \nCollateral equal to an RBP Credit Rate—set initially at $1.5 million—multiplied by the RBP \nUCAP MW committed.31 As proposed, RBP Collateral could take only two forms: a cash deposit \nor a letter of credit.32 PJM explains that the $1.5 million figure was chosen to hold collateral \ncovering “approximately 50% of the notional value of all RBP commitments” from day one.33 \nEquinix respectfully submits that this requirement as currently framed is not just and reasonable, \nfor three reasons. \nThe Commission can remedy these defects without rejecting or delaying the RBP. PJM \nexpressly consented to Commission modification or severance of its proposal. That consent is \nespecially important here: the buyer-side collateral provisions are discrete from the \nprocurement's core design, and modifying them would leave the RBP otherwise intact while \navoiding an unnecessary financing burden.34 \nFirst, the calibration is disproportionate and internally inconsistent. Sellers—who bear \ngenuine development, supply chain, and permitting risk and have the most control over those \nrisks, and whose non-performance is the failure mode PJM says most threatens the region— \nwould be required to post 20% of three Delivery Years of offer value.35 Buyers, whose obligation \n \n31  Tariff, Attachment DD, section 18.8(b)(i)(A) (as proposed); Transmittal at 116. \n32  Tariff, Definitions – RBP Collateral (as proposed) (“either (1) a cash deposit, including any interest thereon, or \n(2) a letter of credit issued for the benefit of PJM or PJM Settlement”); Transmittal at 108 n.260, 110. \n33  Transmittal at 117 (explaining that $1.5 million per MW “ensures that PJM holds sufficient collateral to cover \napproximately 50% of the notional value of all RBP commitments,” calculated as 15 years × 365 days × $555/MW-\nday = $3,038,625). \n34  Op cit. fn. 3. \n35  Tariff, Attachment DD, section 18.8(a)(iv) (as proposed); Transmittal at 112 (seller credit requirement equal to \nthe sum of 20% of the RBP Sell Offer Price × RBP UCAP MW for each of the first three Delivery Years offered)."},{"page":15,"startToken":4987,"endToken":5321,"text":"15 \nis to pay a known, tariffed, declining schedule of charges, would be required to post roughly half \nof a fifteen-year notional value. A requirement calibrated to a rolling forward exposure \nwindow—one to three years of RBP Charges, measured on the same principle PJM applies to \nsellers—would mitigate the same non-payment risk at a small fraction of the cost. \nSecond, the analogy to Financial Transmission Rights does not hold. PJM justifies \nrestricting RBP Collateral to cash or letters of credit by reference to “the credit requirements \nimposed on inherently riskier Financial Transmission Rights.”36 FTR exposure is volatile, \nmarked to changing congestion outcomes, and can move sharply within a Delivery Year. RBP \nCharges are the opposite: fixed by a Commission-approved contract for differences, known in \nadvance, reduced by the establishment of new capacity that is reasonably likely to continue in \nexistence so long as the market is available to pay, and payable on a schedule that only shrinks. \nThat risk profile is well within the range PJM manages every day under Attachment Q, which \naccommodates unsecured credit based on creditworthiness and corporate guaranties.37 Equinix \nasks the Commission to direct PJM to accept, for RBP purposes, the forms of credit support it \naccepts under Attachment Q, including unsecured credit for LSEs that satisfy PJM’s existing \ncreditworthiness standards. \nThird, the requirement works against the ratepayer protection rationale offered to support \nit. PJM invokes the Ratepayer Protection Pledge in support of buyer-side collateral.38 But \ncollateral- especially cash and letters of credit- is not free. An LSE that must post cash or \npurchase a letter of credit covering half the notional value of a fifteen-year commitment will \n \n36  Transmittal at 109-10 (analogizing to “the credit requirements imposed on inherently riskier Financial \nTransmission Rights”). \n37  Tariff, Attachment Q (PJM Credit Risk Management Policy). PJM expressly declined to house the RBP credit \nrules in Attachment Q. See Transmittal at 108-09. \n38  Transmittal at 109-10 (invoking the Ratepayer Protection Pledge as support for the buyer-side collateral \nrequirement)."},{"page":16,"startToken":5321,"endToken":5696,"text":"16 \nalmost certainly have to finance that posting, and the cost of that financing will appear in retail \nrates. On the region-wide Final RBP Target, the aggregate posting contemplated by a $1.5 \nmillion per MW rate runs to billions of dollars of tied-up capital. Requiring load to pre-fund half \nof a fifteen-year obligation on day one, in the two most expensive forms of assurance available, \nwould by itself materially increase the rates that the Pledge was adopted to protect. Equinix urges \nthe Commission to direct PJM to recalibrate the RBP Credit Rate to a rolling forward-exposure \nmeasure and to broaden the permissible forms of RBP Collateral. \nD. \nThe RBP Should Remain a One-Time Backstop While PJM Addresses the \nStructural Constraints That Produced the Shortfall. \nThe RBP will, if accepted, create a second capacity construct that operates alongside the \nReliability Pricing Model (“RPM”) for fifteen Delivery Years. RBP Resources would be paid on \na pay-as-bid basis under a contract for differences, subject to a maximum willingness to pay of \n$555/MW-day UCAP39 and without direct market power screens or mitigation;40 and each \ncommitted RBP Resource must offer its committed MW into every RPM Auction through \n2042/2043 as a $0/MW-day price taker.41 Equinix understands why PJM made each of these \nchoices, and does not ask the Commission to reject them in this proceeding. \nThe Commission should be clear-eyed about what a bifurcated market means if it \npersists. A block of supply equal to as much as the entire observed shortfall will sit outside price \nformation for fifteen years while remaining inside the reliability requirement. Whatever the \n \n39  Transmittal at 61-62; Tariff, Attachment DD, section 18.5(f) (as proposed). \n40  Id. at 65-66 (describing the pay-as-bid structure and the absence of a “marginal unit” in any meaningful sense); \nid. at 66 (“No direct market power screens or mitigation are being proposed for the RBP.”). \n41  Tariff, Attachment DD, section 18.6(a) (as proposed); Transmittal at 56 (a committed RBP Resource “must offer \nits available capacity, up to the total quantity of committed RBP UCAP MW, into the RPM Auctions as a price \ntaker, i.e., $0/MW-day UCAP . . . continuing each subsequent Delivery Year through the end of the fixed, 15-year \nterm”)."},{"page":17,"startToken":5696,"endToken":5989,"text":"17 \nmerits of that approach as an emergency response, its longer-run effects on entry signals, \ncustomer costs, and resource incentives warrant deliberate evaluation outside the compressed \nschedule of this filing. \nThe broader lesson is that the RBP addresses an immediate procurement gap neither \neliminates the underlying constraints on bringing new supply to load, nor paves the way for the \nmechanisms needed to address future significant supply-demand gaps before they disrupt the \nmarket and in more considered fashion. PJM developed this proposal under acute time pressure \nand expressly asked the Commission to modify or sever aspects of the filing as needed to permit \ntimely acceptance. That flexibility is appropriate for the present filing, but it should not become \nthe region's default method of addressing future supply-demand imbalances.  \nFuture imbalances could arise from many sources, including additional load growth, \ngeneration retirements, the unexpected loss of major resources, electrification, or delays in \ninterconnection, transmission, permitting, supply chains, and construction. It would be prudent to \nassume there may very well be a next time, if not many future reoccurrences of similar supply-\ndemand imbalances to those that resulted in this and the IRAS proceedings. PJM has already \nbegun a broader inquiry into durable market design, and should be commended for doing so, \nespecially with respect to its thoughtful and insightful white paper.42 Equinix supports that work \nand believes it should include the practical reforms necessary for new resources - including \nresources procured bilaterally by large loads - to be studied, interconnected, permitted, and \nplaced in service on timelines that can actually address identified reliability needs. \n \n42 PJM Interconnection, L.L.C., Powering Reliability Through Market Design: Addressing Rising Demand and \nConstrained Supply, and Stimulating Investment to Support Durable Reliability (May 9, 2026), available at  \nhttps://perma.cc/3W8Z-M4TQ."},{"page":18,"startToken":5989,"endToken":6328,"text":"18 \nAccordingly, Equinix asks the Commission to make clear that acceptance of this RBP is \nnot precedent for recurring emergency procurements and direct PJM to initiate the process of \nidentifying and evaluating tariff-codified mechanisms that can be deployed to address significant \nand potentially long-lasting supply-demand gaps, so that the next response is a rule rather than a \nrush. This step would not present any cause for delay of the RBP. \nV. \nCONCLUSION \nEquinix supports the Reliability Backstop Procurement as a one-time mechanism and \nurges the Commission to accept it so that the procurement window may open as scheduled. \nEquinix respectfully requests, however, that in accepting the RBP, the Commission take the \nfollowing discrete actions: \n1) Direct PJM, before the RBP bid submission window opens, to publish clear guidance \nas to the evidence it will accept in support of Qualifying RBP Offset UCAP MW, \nincluding the process for direct submissions by large loads; \n2) Direct PJM to provide affected loads, subject to appropriate confidentiality \nprotections, access to the RBP target adjustment data relevant to RBP cost allocation \nand a process to correct demonstrable errors or duplication; \n3) Modify the buyer-side RBP Collateral provisions so that collateral is calibrated to \nreasonably foreseeable forward exposure and the forms of credit support accepted \nunder Tariff, Attachment Q are available. PJM expressly consented to Commission \nmodification or severance of its Section 205 proposal, so the Commission can make \nthis discrete change without rejecting or delaying the RBP;  \n4) Make clear that acceptance of the RBP is an extraordinary, one-time response and \nencourage PJM to continue work on durable reforms that allow needed resources to \nbe studied, interconnected, permitted, and placed in service on timelines consistent \nwith identified reliability needs; and \n5) Require PJM to initiate the process of identifying and evaluating tariff-codified \nmechanisms that can be deployed to address significant and potentially long-lasting \nsupply-demand gaps. \nEquinix does not ask the Commission in this docket to resolve how bilateral procurement should \nbe treated under IRAS. Equinix does, however, flag that PJM's objective of encouraging large"},{"page":19,"startToken":6328,"endToken":6408,"text":"19 \nloads to bring new capacity will depend on coherent and consistent treatment of those \ninvestments across its related reforms, and Equinix expects to address that issue directly in the \nIRAS proceeding. \n \nEquinix again appreciates the opportunity to submit these comments. We look forward to \nfurther participation in this and related dockets. \n \nRespectfully submitted, \n/s/ Arthur Haubenstock \nArthur Haubenstock \nSr. Counsel, Global Regulatory \nEquinix Inc. \n700 “K” Street, N.W., Suite 600 \nWashington DC, 20001 \n(202) 322-9073 \nahaubenstock@equinix.com"},{"page":20,"startToken":6408,"endToken":6502,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have on this date caused a copy of the foregoing document to be served on each person included \non the official service list maintained for this proceeding by the Commission’s Secretary, by electronic mail or such other means \nas a party may have requested, in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.2010.  \n \nDated this the 21st day of August 2026, at Washington, D.C. \n \n \n/s/ Arthur Haubenstock \n \nArthur Haubenstock \nSr. Counsel, Global Regulatory \nEquinix Inc."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":952,"startToken":0,"endToken":137},{"p":1,"at":952,"title":"I. SUMMARY","method":"printed heading","endPage":3,"endAt":3,"startToken":137,"endToken":638},{"p":3,"at":3,"title":"II. BACKGROUND AND INTEREST OF EQUINIX","method":"printed heading","endPage":4,"endAt":1208,"startToken":638,"endToken":1140},{"p":4,"at":1208,"title":"III. INTRODUCTION","method":"printed heading","endPage":7,"endAt":412,"startToken":1140,"endToken":2067},{"p":7,"at":412,"title":"IV. COMMENTS","method":"printed heading","endPage":7,"endAt":428,"startToken":2067,"endToken":2069},{"p":7,"at":428,"title":"A. The RBP Is an Appropriate One-Time Response, but the Commission Should","method":"printed heading","endPage":8,"endAt":1290,"startToken":2069,"endToken":2514},{"p":8,"at":1290,"title":"B. Bilateral Procurement Is the Most Economic and Most Just and Reasonable","method":"printed heading","endPage":14,"endAt":76,"startToken":2514,"endToken":4621},{"p":14,"at":76,"title":"C. The Commission Should Modify the Proposed Buyer-Side RBP Collateral","method":"printed heading","endPage":16,"endAt":655,"startToken":4621,"endToken":5428},{"p":16,"at":655,"title":"D. The RBP Should Remain a One-Time Backstop While PJM Addresses the","method":"printed heading","endPage":18,"endAt":451,"startToken":5428,"endToken":6059},{"p":18,"at":451,"title":"V. CONCLUSION","method":"printed heading","endPage":20,"endAt":0,"startToken":6059,"endToken":6408},{"p":20,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":20,"endAt":572,"startToken":6408,"endToken":6502}]}