{"document":{"slug":"rec-20260821-5263","title":"Comments of Southern Maryland Electric Cooperative, Inc. re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement filing","issued":"2026-08-21","accession":"20260821-5263","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Southern Maryland Electric Cooperative, Inc.","kind":"comments","file":"sources/filings/text/20260821-5263_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5263","tier":"record","sha256":"efd4eb7e2497d8f1638a9410479487b5404b8d91892bfc03f5619762cc671137","pages":10,"tokens":3229,"emptyPages":[],"textThemes":["credit","cost","adequacy","registry"]},"pages":[{"page":1,"startToken":0,"endToken":262,"text":"1 \n \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.                               ) \nDocket No. ER26-3380-000 \n \nCOMMENTS OF SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. \n \nPursuant to the Combined Notice of Filings #1 issued by the Federal Energy Regulatory \nCommission (“Commission”) on August 3, 2026, Southern Maryland Electric Cooperative, Inc. \n(“SMECO”)1 respectfully submits these comments regarding the filing that PJM Interconnection, \nL.L.C. (“PJM”) submitted in the above-captioned docket on July 31, 2026 (the “RBP Filing”).2  \nPJM proposes revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the \nReliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a one-time \n“Reliability Backstop Procurement” (“RBP”) of new capacity, the costs of which PJM proposes \nto recover through a new charge (the “RBP Charge”) assessed against a subset of Load Serving \nEntities (“LSEs”) in the PJM Region.    \nSMECO acknowledges that additional capacity is needed to address the shortfall reflected \nin the 2028/2029 Delivery Year (“DY”) Base Residual Auction (“BRA”) and PJM's decision to \npursue that capacity through a one-time backstop mechanism, the RBP.   SMECO’s comments \nfocus on the roles the RBP Filing assigns to Electric Distributors in making those determinations, \nand certain aspects of the RBP credit and collateral requirements proposed in the RBP Filing.  \n \n1 On August 4, 2026,SMECO submitted, and the Commission accepted, a (Doc-less) Motion to Intervene in this \nproceeding: https://elibrary.ferc.gov/eLibrary/filedownload?fileid=857BC7F7-7CD8-CD58-9E7A-9FCDA3B00000  \n2Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, \nTransmittal Letter of PJM Interconnection, L.L.C., Docket No. ER26-3380-000 (July 31, 2026) (“RBP Filing”):"},{"page":2,"startToken":262,"endToken":600,"text":"2 \n \nI. INTRODUCTION AND SUMMARY  \nPJM's RBP proposal responds to an actual reliability concern – namely, that the 2028/2029 \nDY BRA cleared 6,831.3 MW short of the PJM Region Reliability Requirement.  This shortfall, \nas PJM notes, was driven in part by the rapid interconnection of large loads, including data \ncenters.3  SMECO agrees that this shortfall must be addressed.   \nHowever, SMECO has comments in two areas.  First, PJM’s proposal assigns Electric \nDistributors a series of functions that exceed the metering and data-reporting functions Electric \nDistributors have historically performed for PJM under the PJM Operating Agreement (“OA”). \nSecond, as to RBP credit, PJM proposes vastly different RBP collateral requirements as  \nbetween RBP load versus RBP supply. SMECO serves a service territory that has attracted data \ncenter interest, and as such, has an interest in seeing a rational PJM RBP credit policy established.  \nII. BACKGROUND \nPJM filed the RBP Filing on July 31, 2026, requesting that the Commission act by \nSeptember 29, 2026 -- sixty days after filing -- so that PJM may commence the RBP on September \n30, 2026.4  PJM proposes to set an “Initial RBP Target” equal to the 6,831.3 MW UCAP shortfall \nreflected in the 2028/2029 DY BRA (excluding Fixed Resource Requirement load and supply), \nand to decrement that Initial RBP Target by two categories of MWs to arrive at a “Final RBP \nTarget”: (1) “Qualifying RBP Offset UCAP MW,” meaning new capacity, matched with new load, \nthat PJM verifies was not previously counted as either an RPM commitment or an FRR resource; \nand (2) “Opt-Out UCAP MW,” a narrow opt-out available in limited circumstances.5 PJM \nproposes to procure that Final RBP Target quantity through the RBP. \n \n3RBP Filing at 21 (“6,831.3 MW UCAP”); see also id. at 1 (describing the shortfall as “primarily driven by the \nunprecedented addition of large loads, most notably data centers”). \n4RBP Filing at 3, Footnote 5 and at 27. \n5RBP Filing at 31, 35, 44 (proposed Tariff, Attachment DD, sections 18.1, 18.2)."},{"page":3,"startToken":600,"endToken":927,"text":"3 \n \nPJM proposes to allocate the resulting daily RBP Charges first to Electric Distributor \nzones/areas, pro rata, based on each zone/area's share of the region-wide Final RBP Target -- = \nadjusted to reflect zone-specific Qualifying RBP Offset UCAP MW.6  Within each zone/area, PJM \nproposes that cost allocation to individual LSEs “be based on ‘the state and/or RERRA-determined \nallocation of cleared RBP UCAP MW to LSEs within each Electric Distributor's zone/area, as \nreported [to PJM] by each Electric Distributor.’”7    \nThis state/RERRA-determined allocation is referred to as the “RBP Obligation” or \n“RBO.”8  LSEs allocated RBP cost responsibility -- an RBO -- must post collateral (“RBP \nCollateral”) in an amount equal to a uniform “RBP Credit Rate” -- proposed by PJM to be at $1.5 \nmillion per MW -- multiplied by the LSE's allocated RBP UCAP MW.9  An LSE with an RBO \nmust post this RBP Collateral no later than forty-five days before the start of the relevant DY -- \njust fifteen days after the underlying RBO allocation on which the collateral requirement depends \nis reported (i.e., the RBO must be reported no later than sixty days before the DY).10 \n \nIII. COMMENTS \nA.  \nPJM’s RBP Filing Assigns Electric Distributors a Role Inconsistent with Their \nIntended Function in PJM \nThe term “Electric Distributor” refers to a Member “sector” under the PJM OA, defined \nprincipally by reference to a Member's ownership or lease of distribution facilities serving load in \nthe PJM Region, including cooperative and joint municipal systems.11  Historically, the functions \nElectric Distributors perform for PJM under the OA and RAA have centered on metering and load-\n \n6RBP Filing at 96-97 (proposed Tariff, Attachment DD, section 18.3(a)). \n7RBP Filing at 97-98 (quoting proposed Tariff, Attachment DD, section 18.3(b)(iii)). \n8RBP Filing at 98 (quoting proposed Tariff, Definitions -- RBP Obligation). \n9RBP Filing at 114-118 (proposed Tariff, Attachment DD, section 18.8(b)). \n10RBP Filing at 120. \n11See generally OA, Definitions -- Electric Distributor."},{"page":4,"startToken":927,"endToken":1318,"text":"4 \n \ndata reporting -- classic “meter reading” roles such as reporting hourly net energy flows for \nsettlement purposes.12  Even OA section 11.3.3 (h), which requires that an Electric Distributor \n“[p]rovide to the Office of the Interconnection all System, accounting, customer tracking, load \nforecasting (including all load to be served from its System) and other data necessary or \nappropriate to implement or administer this Agreement, and the Reliability Assurance Agreement” \ndoes not result in an Electric Distributor performing the following  expansive set of Tasks: \n1. \nSponsor of reductions to the zone's RBP target (opt-outs)13: Electric \nDistributors serve as the applicant and evidentiary sponsor -- the opt-out \nrequest itself must come from the Electric Distributor, with supporting \ndocumentation. \n2. \nReporting capacity offsets: Electric Distributors, along with other entities, \nprovide evidentiary support for Qualifying RBP Offset UCAP MW claimed \nwithin their zone/area, which is capped at that zone/area's Load Adjustment \namount of summer 2028 demand.14 That is, Electric Distributors must \nprovide reports and evidence of Qualifying RBP Offset UCAP MW in each \nof their respective zones/areas.15  \n3. \nBridge between state decisions, LSEs, and PJM: Electric Distributors \nmust report the state/RERRA-determined allocation (i.e., the RBO)16; \nabsent a report, PJM falls back to a Peak Load Contribution share of Daily \nUnforced Capacity Obligation. \n4. \nRBO Cost allocation: Electric Distributors' reports feed both the zone-\nlevel allocation of the Final RBP Target and the LSE-level daily formula17, \nwith PJMSettlement as the Counterparty responsible for collecting from \nLSEs.18 \n5. \nSupporting DER and Demand Resource participation: Electric \nDistributors must develop and provide distribution-impact studies for RBP \n \n12See, e.g., OA, Schedule 1, section 3.6 (Metering Reconciliation); PJM Manual 28: Operating Agreement Accounting \n(describing the role of “fully metered” Electric Distribution Companies in reporting hourly net energy flows for \nsettlement purposes). \n13 RBP Filing at 33, 44-46, Section III.B.3 \"Opt-out\".  \n14 RBP Filing at 42-43; Section III.B.2.e: \"Electric Distributors and other entities provide evidentiary support for \nQualifying RBP Offset UCAP MW\".  The RBP Filing at 32 indicates that the cap is set at the Load Adjustment for \neach Electric Distributor zone/area amount of summer 2028 demand. \n15 RBP Filing at 42-43, emphasis added, footnotes omitted. \n16 RBP Filing at 97-99, \n17 RBP Filing at 96-99.. \n18 RBP Filing at footnote 236."},{"page":5,"startToken":1318,"endToken":1796,"text":"5 \n \nDER Aggregation Resources.19 An RBP DER Capacity Aggregation \nResource \nmust \naddress \n“applicable \nElectric \nDistributor \ninterconnection/distribution impact study requirements,” and an RBP \nDemand Resource must satisfy “Electric Distributor coordination \nrequirements for metering, telemetry, and baseline measurement \ninfrastructure.”20 \n6. \nSupplying inputs that affect LSE collateral: under the Tariff provision \nfor \"Determining an LSE's RBP credit requirement,\" the Electric \nDistributor's RBO report -- as submitted, and scaled if it does not sum to the \nzone/area's Final RBP Target -- sets an LSE's RBP UCAP MW; absent an \nRBO, PJM instead uses each LSE's pro-rata share of the zone/area's Daily \nUnforced Capacity Obligation.21 \nFor example, with regards to RBO Cost allocation “Task #4”, the RBP Filing asks Electric \nDistributors to report “the state and/or RERRA-determined allocation of RBP UCAP MW to \n[LSEs] within each Electric Distributor’s zone/area” --  i.e., the RBO.22  But the RBO an Electric \nDistributor reports is not a metered quantity; rather, it is a state or RERRA’s own determination \nof which customers are “large loads”23, for which the Electric Distributor must “certify” to PJM, \nfixing how much each LSE in the zone will be assessed the RBP Charge.   \nNeither PJM’s Filing nor the OA, so far as SMECO is aware, gives an Electric Distributor \nthis role: OA section 11.324 sets forth data-reporting and other operational obligations for Electric \n \n19 RBP Filing at 75; footnote 199. \n20RBP Filing at 75 (quoting proposed Tariff, Attachment DD, section 18.5(f)(i)(12)-(13)). \n21RBP Filing at 118-119.  \n22RBP Filing at 97-98. \n23RBP Filing at 98. \n24 OA 11.3.3 Electric Distributors. In addition to any of the foregoing responsibilities that may be applicable, each \nMember that is an Electric Distributor, whether or not that Member votes in the Members Committee in the Electric \nDistributor sector or meets the eligibility requirements for any other sector of the Members Committee, shall:  \n(a) Accept, comply with or be compatible with all standards applicable within the PJM Region with respect to system \ndesign, equipment ratings, operating practices and maintenance practices as set forth in the PJM Manuals, or be subject \nto an interconnected Member’s requirements relating to the foregoing, so that sufficient electrical equipment, control \ncapability, information and communication are available to the Office of the Interconnection for planning and \noperation of the PJM Region;  \n(b) Assure the continued compatibility of its local system energy management system monitoring and \ntelecommunications systems to satisfy the technical requirements of interacting automatically or manually with the \nOffice of the Interconnection as it directs the operation of the PJM Region;  \n(c) Maintain or arrange for a portion of its connected load to be subject to control by automatic underfrequency, under-\nvoltage, or other load-shedding devices at least equal to the levels established pursuant to the Reliability Assurance \nAgreement, or be subject to another Member’s control for these purposes;"},{"page":6,"startToken":1796,"endToken":2389,"text":"6 \n \nDistributor Members, but it does not contemplate a Member determining or certifying to PJM an \nallocation of a FERC-jurisdictional “RBP Charge” among other Members’ customers, including \nhelping assemble the “sufficient evidence” PJM requires to support any Qualifying RBP Offset \nUCAP MW claimed within its zone/area.25  These tasks become harder still where it is the LSE, \nnot the Electric Distributor, that holds the underlying large-load data. \nRegarding Electric Distributor “Task #5” from the list above, PJM’s RBP Filing requires \nthat the RBP DER Aggregation or Demand Resource seller demonstrate it has coordinated with \nthe Electric Distributor to meet requirements.26 The RBP Filing itself never defines these \nrequirements; the Electric Distributor is thus placed in a gatekeeper role over how these types of \ncapacity resources can submit an RBP Sell Offer; presumably this is as soon as September 30, \n2026 – the earliest planned opening date of the RBP sell-offer window.  But this function also \n \n(d) Provide or arrange for sufficient reactive capability and voltage control facilities to conform to Good Utility \nPractice and (i) to meet the reactive requirements of its system and customers and (ii) to maintain adequate voltage \nlevels and the stability required by the bulk power supply facilities of the PJM Region;  \n(e) Shed connected load, share Generation Capacity Resources and take such other coordination actions as may be \nnecessary in accordance with the directions of the Office of the Interconnection in Emergencies;  \n(f) Maintain or arrange for a portion of its Generation Capacity Resources at least equal to the level established \npursuant to the Reliability Assurance Agreement to have the ability to go from a shutdown condition to an operating \ncondition and start delivering power without assistance from the power system;  \n(g) Provide or arrange through another Member for the services of a 24-hour local control center to coordinate with \nthe Office of the Interconnection, each such control center to be furnished with appropriate telemetry equipment as \nspecified in the PJM Manuals, and to be staffed by system operators trained and delegated sufficient authority to take \nany action necessary to assure that the system for which the operator is responsible is operated in a stable and reliable \nmanner.  In addition to meeting any training standards and requirements specified in this Agreement, local control \ncenter staff shall be required to meet applicable training standards and requirements in PJM Manual 40, Control Center \nRequirements, including the PJM System Operator Training Requirements in Attachment C;  \n(h) Provide to the Office of the Interconnection all System, accounting, customer tracking, load forecasting (including \nall load to be served from its System) and other data necessary or appropriate to implement or administer this \nAgreement, and the Reliability Assurance Agreement; and (i) Comply with the underfrequency relay obligations and \ncharges specified in Operating Agreement, Schedule 7. \n25RBP Filing at 97: “Cost responsibility allocated to a zone/area may be further adjusted where PJM receives sufficient \nevidence demonstrating that new capacity has been brought by load to the relevant Electric Distributor’s zone/area in \nthe form of Qualifying RBP Offset UCAP MW. A zone/area of an Electric Distributor that qualifies for one of the \nopt-outs set forth in proposed Tariff, Attachment DD, section 18.1(d), would also have RBP Charges reduced by the \nMW quantity of the opt-out.” (citing proposed Tariff, Attachment DD, section 18.2(c)). \n26RBP Filing at 75: “the seller must demonstrate that it has coordinated with the Electric Distributor to ensure the \nresource will meet applicable requirements” (citing proposed Tariff, Attachment DD, section 18.5(f)(i)(11)-(12))."},{"page":7,"startToken":2389,"endToken":2735,"text":"7 \n \nconflicts with the “metering and reporting role” that OA section 11.3 assigns to Electric \nDistributors.  \nB. RBP Credit and Collateral Issues.  \nPJM’s proposed Tariff, Attachment DD, section 18.8 imposes a credit requirement on \nLSEs.  Per the Affidavit of PJM witness Danielle Croop27, PJM's proposed initial allocation of \nRBP UCAP MW to each Electric Distributor zone/area is based on the Load Adjustments in PJM \nTable B9b of the 2026 PJM Load Forecast, applied against the region-wide Initial RBP Target of \n6,831.3 MW. 28    PJM proposes an RBP LSE Credit Rate \"initially at $1.5 million\" per MW.29 \nApplied to the 6,831.3 MW of RBP target capacity, approximately $10.25 billion (6,831.3 MW × \n$1,500,000/MW = $10,246,950,000) would need to be posted by LSEs as collateral no later than \n45 days ahead of the start of the 2028/2029 Delivery Year. PJM derived the $1.5 million buy-side \ncredit requirement as a full 15-year, $555 MW-day contract payment (discounted at 9.5%), \nyielding an RBP LSE required posting  ~ 7.5 years equivalent buy-side collateral.    \nPJM proposes that the Electric Distributor’s RBO allocation be reported at no later than \nsixty days before the start of the DY; PJM proposes to require the affected LSE to post the resulting \ncollateral just fifteen days later, at forty-five days before the DY begins.30  That leaves just a \nfifteen-day window to arrange collateral for an obligation whose amount it could not have \npredicted in advance, using a $1.5 million/MW RBP Credit Rate”31   Thus, once an LSE knows \nthe outcome of the state/RERRA reporting process administered by the Electric Distributor, but it \nthen only has two weeks to post significant RPM buy-side collateral. \n \n27 Affidavit Danielle Croop, PJM at page 12 (paragraph 46) (“Croop Affidavit”).  \n28 Croop Affidavit at paragraph 4. \n29 RBP Filing at 116-117; proposed Tariff, Attachment DD, § 18.8(b)(i)(A). \n30RBP Filing at 120. \n31RBP Filing at 116 (quoting proposed Tariff, Attachment DD, section 18.8(b)(i)(A))."},{"page":8,"startToken":2735,"endToken":3124,"text":"8 \n \nIf the Electric Distributor uploads RBP Obligation MW for the LSEs in its zone/area that \ndo not sum to the zone’s fixed Final RBP Target MW, per the RBP Filing PJM simply scales up \neach reported MW-value – and individual LSE collateral obligations – to fit the fixed Final RBP \nTarget MW.32 And if the Electric Distributor reports no RBO at all for its zone/area, PJM instead \ncalculates the LSE’s RBP Collateral using the LSE’s pro-rata share of the zone/area’s Daily \nUnforced Capacity Obligation, a value tied to historical peak load rather than any state/RERRA \ndetermination.33  At the same time, on the sell-side RBP resources have a three (3)-year, and only \n20% * RBP price of $555 MW-day collateral, posting requirement equal to $101,647/MW \ndiscounted at PJM’s 9.5% discount rate.  As such, RBP LSEs have a 14.5x collateral posting \nrequirement of RBP supply resources.   \nMoreover, if an RBP-procured generator fails to deliver or is delayed, the RBP load it \nserves is exposed to higher risk of load curtailment.  An RBP load that wants to hedge that risk by \nbuying replacement capacity cannot do so,  practically speaking; a 20% shortfall penalty times \n$555 MW-day is only $111 MW-day, which is insufficient compensation to purchase new \ncapacity.  Further, if an RBP resource misses its commercial operation date (“COD”) because of \nnetwork-upgrade delays are excused from shortfall penalty charges -- no RBP shortfall charge is \ncollected to compensate the load sitting exposed to “IRAS” or other elevated curtailment risk in \nthe meantime.34   \n \n \n32RBP Filing at 119. “For LSEs serving load in an Electric Distributor zone/area in which RBOs have been reported, \nthe LSE will be required to post RBP Collateral for its RBO MW (i.e., its allocated RBP UCAP MW amount). \nConsistent with the proposed cost allocation rules, PJM proposes that “the RBP Obligation MW [will] equal[] the \nRBP Obligation MW submitted for the Load Serving Entity by the Electric Distributor and scaled, as necessary, in \nthe event that the RBP Obligation MW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP \nTarget MW for the zone/area” (footnotes omitted). \n33Proposed Tariff, Attachment DD, section 18.8(b)(i)(B)(1) \n34 See: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260610/20260610-item-03h---\nsmeco-presentation.pdf"},{"page":9,"startToken":3124,"endToken":3181,"text":"9 \n \nIV. CONCLUSION \nSMECO respectfully requests that the Commission consider SMECO’s comments on \nPJM’s RBP Filing. \nRespectfully submitted, \nDamon L. Krieger \nSenior Vice President, Legal and Strategy, and  \nGeneral Counsel \nSouthern Maryland Electric Cooperative, Inc.  \n15035 Burnt Store Road \nP.O. Box 1937 \nHughesville, MD  20637-1937 \n301.274.4323  \nDamon.Krieger@SMECO.coop  \n \nDated: August 21, 2026."},{"page":10,"startToken":3181,"endToken":3229,"text":"10 \n \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served a copy of the foregoing document upon each \nparty on the official service list compiled by the Secretary of the Federal Energy Regulatory \nCommission in this proceeding. \n \n \n \n \nDated: August 21, 2026. \n \n \n \n \n \n \n \n /s/ _____ \nJohn S. Rohrbach"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":263},{"p":2,"at":5,"title":"I. INTRODUCTION AND SUMMARY","method":"printed heading","endPage":2,"endAt":940,"startToken":263,"endToken":405},{"p":2,"at":940,"title":"II. BACKGROUND","method":"printed heading","endPage":3,"endAt":1174,"startToken":405,"endToken":793},{"p":3,"at":1174,"title":"III. COMMENTS","method":"printed heading","endPage":3,"endAt":1189,"startToken":793,"endToken":795},{"p":3,"at":1189,"title":"A. PJM’s RBP Filing Assigns Electric Distributors a Role Inconsistent with Their","method":"printed heading","endPage":7,"endAt":112,"startToken":795,"endToken":2406},{"p":7,"at":112,"title":"B. RBP Credit and Collateral Issues.","method":"printed heading","endPage":9,"endAt":5,"startToken":2406,"endToken":3125},{"p":9,"at":5,"title":"IV. CONCLUSION","method":"printed heading","endPage":10,"endAt":8,"startToken":3125,"endToken":3182},{"p":10,"at":8,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":325,"startToken":3182,"endToken":3229}]}