{"document":{"slug":"rec-20260821-5264","title":"Comments of Exelon Corporation in response to FERC's Notice re PJM Governance and Stakeholder Reforms","issued":"2026-08-21","accession":"20260821-5264","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Exelon Corporation","kind":"comments","file":"sources/filings/text/20260821-5264_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5264","tier":"record","sha256":"d56a72c3fa25c4941cb7816bc9bf727cb35a705a3d9fb69523c66ed4e3f633d5","pages":29,"tokens":6474,"emptyPages":[],"textThemes":["adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":226,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Governance and Stakeholder \nReforms \n) \n) \n) \n) \n \nDocket No. AD26-7-000 \n \nCOMMENTS OF EXELON CORPORATION \n \nExelon Corporation and its affiliates1 (collectively, “Exelon”) welcome the opportunity to \ncomment in response to the Notice Requesting Post-Technical Conference Comments2 issued by the \nFederal Energy Regulatory Commission (“Commission”) in the above-captioned docket. \nI. \nINTRODUCTION AND COMMENTS \nExelon appreciates the Commission’s attention to issues related to the governance structure of \nPJM Interconnection, L.L.C. (“PJM”) at this important time of change in the electricity industry. The \nefficacy of the PJM governance framework and stakeholder process has been a simmering issue for \nyears but has come to a head over the looming resource adequacy crisis paired with the inability to \nmove rapidly to interconnect new large loads while maintaining reliability and affordability. Forecasted \nresource adequacy concerns are especially acute in PJM, the region where Exelon’s utility operating \ncompanies provide electric service to over 10 million customers across five states and the District of \nColumbia.  These circumstances present at a time when electricity has never been more important to \n \n1 Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth \nEdison Company of Indiana, Inc., Delmarva Power and Light Company, PECO Energy Company, and Potomac Electric \nPower Company. \n2 Notice Requesting Post-Technical Conference Comments, Docket No. AD26-7-000 (July 30, 2026) (“Notice”)."},{"page":2,"startToken":226,"endToken":538,"text":"2 \n \nthe US economy, to national security, and to the nation as it seeks to capitalize on strategic growth \nopportunities related to data center and artificial intelligence demands, expanded manufacturing \ncapacity, and electrification of end-use energy applications that are increasingly becoming the practice \nand expectation of our customers. This is not a time for anyone to persist with a poorly performing \ngovernance structure.  \nThe Commission, in initiating the instant docket, has properly identified pains stemming from \nPJM’s current governance framework. PJM’s rigid, hierarchical committee structure—which affords \nmembers binding affiliate voting rights at lower-level standing committees and binding sector-\nweighted voting rights at senior standing committees—is no longer fit for purpose. Time after time, the \nstakeholder process voting results reflect that efforts to reach a two-thirds supermajority required to \npass solutions under this paradigm mostly result in gridlock, thereby derailing advancements needed to \naddress today’s challenges. Perhaps equally important, gridlock leaves states feeling uncomfortable \nwith outcomes, and investors tepid about the durability of the commercial environment in the region. It \nis also worth noting that the data consistently shows low voter turnout even when votes concern highly \ncritical issues. For instance, most recently, only approximately 70 members—representing less than \n15% of more than 500 qualified voting members—voted in the Reliability Backstop \nProcurement/Connect and Manage critical issues fast path effort.3  \nTo address the governance challenges facing PJM, Exelon’s view is informed by the guiding \nprinciple that it is critical to focus on development of solutions that are responsive to specific identified \nproblems. Solutions that are reactive to general grievances about challenging processes, but that do not \nhave ties to specific aims, will not meet the moment. Moreover, not all problems facing the region can \n \n3 See MC Voting Results from the Special Members Committee – Reliability Backstop Procurement dated 6/30/26 -- \nhttps://www.pjm.com/committees-and-groups/committees/mc"},{"page":3,"startToken":538,"endToken":872,"text":"3 \n \nbe addressed through governance reforms, especially important resource adequacy and affordability \nchallenges depend on actions outside of the PJM market to resolve.  \nTo this end, Exelon uses two primary objectives as a waypoint for potential reforms. First, the \nneed to enhance independent decision-making by PJM. The PJM Board of Managers (“Board”) should \nbe empowered to make decisions untethered from the need to obtain approval from the Members \nCommittee, including being granted the filing rights to do so. This extends to the transmission planning \nprotocols as well as the energy and ancillary services markets, as the Board has today for the capacity \nmarket. Furthermore, the terms of Board members should be extended and they should have more open \nlines of communication with the membership to enable receipt of a wider range of perspectives filtered \nthrough fewer intermediaries and overly structured meetings. \nExelon’s second objective is to modify the stakeholder process to more fully recognize the \nbroader political context in which PJM operates. PJM has always included a diverse makeup of states, \nbut today’s energy landscape is more political than it has ever been and pressing issues increasingly \nstraddle the state-federal jurisdictional divide. States need a greater role in PJM, recognizing the \ninherently political nature of many decisions and the need to align PJM processes with state policies \nand, in turn, to make sure that states’ decisions (e.g., permitting) support PJM outcomes. There is a \nneed for coordinated action between PJM and the states, and buy-in from the states to achieve PJM’s \nobjectives. PJM cannot act without cognizance of, or in opposition to, the states if it hopes to be \nsuccessful.  \nWith this in mind, Exelon supports giving states a greater role in PJM. Exactly what form such a \nrole takes should be a matter of discussion and could include representation of state interests on the \nPJM Nominating Committee, on the Board, and/or mandatory consultation processes between state \nrepresentatives and the Board. We would be open to incorporating best practices from other Regional"},{"page":4,"startToken":872,"endToken":1196,"text":"4 \n \nTransmission Organizations (“RTOs”)/Independent System Operators (“ISOs”) and how they integrate \nstate policymakers into governance. However, any expanded role for the states in the PJM governance \nprocess should not impinge on efforts to enhance the independence of the Board. Said another way, any \nreform should not subordinate the Board to the states. An RTO must remain independent for its region \nto attract significant, needed, long-term capital investments. This can be achieved by ensuring that \nPJM’s policies are developed to be both considerate of and resilient to today’s fast-moving, short-\nduration political dynamic. \nAs PJM stakeholders chart a path forward for PJM’s governance framework, Exelon emphasizes \nthat governance reforms cannot solve all problems. PJM faces challenges with its markets and with \ntransmission planning that will require solutions beyond the reach of improved RTO governance, and \nin large part beyond any regional power market improvements that could flow from such changes. \nRather, state and federal actions are likely required to address generation planning, siting, permitting, \nsupply chain, and financing challenges. These comments do not offer prescriptions to address the need \nfor increased entry of new supply; rather, we note that while improved governance is a worthy goal, \nseeking it should not become a distraction from other pressing threats to reliability and affordability in \nthe footprint that will need to be addressed separately, and by a different set of stakeholders and using \ndifferent tools.  \nExelon remains committed to continuing to work with our states, federal policymakers, and PJM \non governance reform for the region. We look forward to partnering with other stakeholders to retain \nexisting structures that work, advance needed reforms, and drive compatibility of reforms with the \ndiverse views of states in the PJM region. We recognize and appreciate that what takes place at the \nCommission and at PJM must also accommodate and, indeed, facilitate actions states may take to \nsupport their own policies and priorities. To date, Exelon has tried to focus external stakeholder"},{"page":5,"startToken":1196,"endToken":1249,"text":"5 \n \nengagement on governance by asking what problems need to be fixed and pushing towards reforms that \n(1) enable independent decision making by PJM and (2) ensure PJM decisions are made with better \nawareness of political contexts. Exelon continues to pursue these objectives and urges the Commission \nto advance them through this proceeding."},{"page":6,"startToken":1249,"endToken":1546,"text":"6 \n \nII. \nRESPONSES TO QUESTIONS IN NOTICE \nA. \nQuestion 1 – Board Member Terms  \n \nYes \nNo \nShould Board members’ terms be extended to five or more years? \nx \n \n \nExelon’s view is that Board members’ terms should be longer than the current three-year \nduration. The structure of PJM is extremely complex and the issues facing the region are multi-faceted. \nThus, it takes time to come up to speed once a Board member is elected and installed. Then, when \nissues arise, it can take years to develop solutions through the stakeholder process, have them approved \nby the Commission, and then be implemented with time for stakeholders and market participants to \nrespond and gain experience with new rules. Ideally, Board members would have terms of adequate \nduration to support both the education and initiation process and to serve for long enough to have a \nmeaningful amount of continuity in oversight as PJM staff and the stakeholder process develop and \nimplement improvements to markets, planning, and operational rules.   \nIn addition to serving longer terms—and only if Board terms are extended—Exelon offers that \nBoard members should only be able to serve at most three five year terms and must be younger than 75 \nyears old to be eligible for election or re-election consistent with existing obligations. Maintaining \nthese standards of conduct while extending individual term limits would enhance Board independence, \nrecognizing that Board members would undertake votes with less concern about how those votes would \nimpact their ability to be renominated. Especially as PJM faces increased political pressure and Board \nactions have been subject to unprecedented levels of scrutiny, not facing continual renomination will \nfree Board members to act with the highest level of independence in line with what they think is the \nbest course of action for the PJM region."},{"page":7,"startToken":1546,"endToken":1804,"text":"7 \n \nB. \nQuestion 2 – Board Service Limits \n \nYes \nNo \nShould there be a maximum number of years that a Board member \nmay serve (e.g., 10 years)? \nx \n \n \nExelon’s view is that Board members should be limited in the maximum number of years they \nmay serve. An appropriate maximum likely depends on whether Board members are eligible to be \nrenominated for more than one term that is extended beyond the current three-year period (see answer \nto Question 1). If Board members are not eligible for renomination, an appropriate single term would \nbe seven years. This duration balances the considerations of 1) allowing Board members to come up to \nspeed on PJM and oversee a number of meaningful reform efforts with 2) the fact that there is risk with \nplacing too much weight on the one-time decision of the Nominating Committee. As with any \ncorporate hiring process, experience has shown that not every Board member ultimately proves to be \nthe right fit. If Board members are eligible for renomination and terms are not extended, this balance \nmay be struck by allowing one or two renominations (for a total of six or nine total years of service). If \nBoard members are eligible for renomination and terms are extended, the balance will depend on the \nnew length of the term. In any case, Exelon’s view is that fifteen years of service is a reasonable upper \nbound on total number of years of Board service, which would arithmetically limit allowed \nrenominations to two so long as the term length is five years."},{"page":8,"startToken":1804,"endToken":1971,"text":"8 \n \nC. \nQuestion 3 – Footprint Residence Preference \n \nYes \nNo \nShould the Board member qualification rules be revised to provide \na preference for some Board members that reside in the PJM \nregion? \nx \n \n \nExelon would support a residency preference for Board members. Residence in PJM may have \nseveral benefits for Board members, including that it may increase likelihood of prior experience with \nthe RTO, may increase Board members skin-in-the game with respect to outcomes in the region, and \nmay make it easier for stakeholders to engage actively with Board members. However, Exelon does not \nsupport a mandate of residence in the PJM region so as not to overly constrain the pool of Board \ncandidates. There are already challenges identifying qualified and interested Board members (even \nwithout the preference or requirement); it would be ill advised to exacerbate such challenges. We \nwould not wish to overly constrain PJM’s ability to recruit qualified candidates that can bring a \ndiversity of valuable experience, including experience from other regions, to the Board."},{"page":9,"startToken":1971,"endToken":2163,"text":"9 \n \nD. \nQuestion 4 – Cooling Off Period  \n \nYes \nNo \nShould the conflict-of-interest rules be revised to reduce the \ncooling off period for Board members from two years to one year? \nx \n \n \nExelon supports shortening the current two-year cooling off period to instead be one year. We \nunderstand the value of a cooling off period as a general matter, creating space between the time when \na Board member may be affiliated with a PJM member and that member’s interest, and when she or he \nmay serve on the Board and need to shift their perspective to the broader interests of the region. \nHowever, it is also important to, within reason, maximize the pool of quality, qualified candidates to \nserve on the Board. The current two-year cooling off period is unnecessarily restrictive and a one-year \ncooling off period may be a more appropriate duration to balance the interests. Note that this position is \nconsistent with the implementation of a preference, but not requirement, for Board member residence \nin the PJM footprint—ultimately, the objective is to improve and expand the range of individuals that \nthe Nominating Committee may consider to serve on the Board."},{"page":10,"startToken":2163,"endToken":2438,"text":"10 \n \nE. \nQuestion 5 – Ex Parte Restrictions  \n \nYes \nNo \nShould restrictions on Board communications be relaxed to enable \nmore communication between the Board and stakeholders? \nx \n \n \nExelon supports relaxation of restrictions to enable more communication between the Board and \nstakeholders. Especially if PJM’s governance structures are reformed in alignment with Exelon’s \nrecommended reforms—including a shift to an advisory polling with enhanced section 205 rights for \nthe Board—it will be more important than ever that the Board is able to effectively gather direct, \ncandid, and unfiltered information from stakeholders. The Board may benefit from having more \nfrequent and informal communication channels with stakeholders as it makes important forward-\nlooking operational, strategic, and market-design decisions. It should not be required to rely only on \ncommunications through overly structured meetings with stakeholders (e.g., Liaison Committee \nmeetings) and summaries filtered through PJM staff, however fair they may be. This would prevent \nsituations where nuanced, non-conforming, or minority viewpoints are lost or reframed through the \nperspective of others. It may also allow for the Board to provide feedback to stakeholders earlier in the \ncommittee development process, allowing for Board guidance on paths forward that are aligned with \nthe Board’s vision and most likely to garner the Board’s support. Of course, increased access needs to \nbe balanced and cannot be unconstrained. Board members do not serve PJM on a full-time basis and \ncannot hear an unlimited number of stakeholder perspectives. There would need to be practical limits \non the amount of time that each Board member should be available and mechanisms put in place to \nensure that no one stakeholder or sector is able to monopolize Board bandwidth."},{"page":11,"startToken":2438,"endToken":2658,"text":"11 \n \nF. \nQuestion 6 – Board Vote Transparency  \n \nYes \nNo \nIn order to increase transparency, should Board votes be made \npublic or the Board be required to explain its reasoning? \n \nx \n \nExelon does not support publication of Board votes or requirements for Board members to \nexplain their votes. Thematically, Exelon supports PJM reforms to empower the Board and to increase \nindependence, particularly in a period of heightened attention regarding developments in PJM. \nRequiring the Board to make public each of its votes would expose Board members to increased \nscrutiny and pressure at a time when they should be encouraged to take positions aligned with their \nbest, unbiased judgement and insulated from blowback from market participants. The Board functions \nas a collective decision-making body and, as such, transparency is adequately served by disclosing the \nBoard’s final action rather than the votes of individual members. The ability of the Board to act behind \nclosed doors aligns with how most corporate boards function and allows appropriate levels of \ndeliberative privilege and confidentiality. Moreover, it is Exelon’s view that governance changes \nshould be focused on ensuring that the Board has more time to focus on the issues and engage \nmeaningfully with stakeholders, a goal that is not advanced by requiring Board members to spend \nprecious time documenting the reasoning for each vote that they take."},{"page":12,"startToken":2658,"endToken":2846,"text":"12 \n \nG. \nQuestion 7 – Public Board Meetings \n \nYes \nNo \nIn order to increase transparency, should some Board meetings be \nopen or available to the public? \n \nx \n \nExelon does not support making meetings of the Board available to the public. Similar to the \nreasoning for not supporting publication and explanation of voting, this would not advance the \nobjective of Board independence. Instead, it would likely lead the Board to hold curated, selectively-\nscoped public meetings that, over concerns about optics and politics, would not involve meaningful, \nopen dialogue or the taking of controversial votes. The Board would then do the bulk of its business in \nprivate executive sessions. Not only would these meetings be a drain on scarce Board time that is best \nspent on other activities, but they would also be unsatisfying to those who advocate for the value of \npublic Board meetings to enhance transparency, thereby creating even more dissatisfaction with PJM \ngovernance. The Commission should seek reforms that provide more, not fewer, opportunities for the \nBoard to engage in the deliberative process. In Exelon’s view, public Board meetings do not advance, \nand may undermine, that goal."},{"page":13,"startToken":2846,"endToken":3013,"text":"13 \n \nH. \nQuestion 8 – Public Interest Principle  \n \nYes \nNo \nShould PJM’s governing documents be revised to explicitly state \nthat the responsibility of PJM and its Board is to serve the public \ninterest? \nx  \n \n \nExelon would support revisions to PJM’s governing documents to explicitly state that PJM and \nits Board are responsible to serve the public interest, as long as it is solely intended to memorialize, and \nnot expand, requirements within the Federal Power Act (“FPA”). PJM is a public utility under the FPA, \nhaving received rights and obligations under that act from its public utility members. It already has \nappropriate legal and operational obligations for an entity regulated by the Commission to work in the \npublic interest, primarily by ensuring grid reliability, providing non-discriminatory transmission access, \nand running markets and planning mechanisms that produce just and reasonable wholesale electricity \nrates.  Thus, depending on how the language is worded, it could be acceptable to include a public \ninterest principle in the operating agreement as embedded in the FPA."},{"page":14,"startToken":3013,"endToken":3233,"text":"14 \n \nI. \nQuestion 9 – State Nominating Committee Representation  \n \nYes \nNo \nShould state representatives have at least one voting member on the \nNominating Committee? \nx \n \n \nExelon supports a change to the Nominating Committee makeup that would give state \nrepresentatives one vote. Providing states a vote would expand the perspectives represented on the \nNominating Committee and ensure that perspective is included in the selection of Board members, in \nequal weight with the sectors currently represented on the Nominating Committee. Having this \nperspective and input from the states would serve to increase the confidence that the states have in how \nthe Nominating Committee operates and makes its decisions, ultimately building trust in the Board on \nthe part of the states and facilitating alignment between PJM processes and state action. Of course, the \nstate representatives on the Nominating Committee would be expected to adhere to the same strict code \nof conduct and confidentiality rules as all other Nominating Committee members during and after their \nperiod of service. It would be up to the various relevant state entities to determine who to put forward \nas the Nominating Committee participant. Finally, Exelon does not support having more than one state \nrepresentative voting member on the Nominating Committee, as that could create imbalance in how \nvarious interests are represented on the Nominating Committee and ultimately the Board."},{"page":15,"startToken":3233,"endToken":3516,"text":"15 \n \nJ. \nQuestion 10 – Performance Metrics  \n \nYes \nNo \nShould PJM adopt public performance metrics and tie management \ncompensation to their achievement? \n \nx \n \nExelon does not support establishment of public performance metrics that are tied to PJM \nmanagement compensation. Such a change would create several problems. First, as a general matter, \nthere is concern that, per Goodhart’s Law, any time a measure (here: metric) becomes a target, it ceases \nto be a good measure. It would be undesirable to reorient PJM management’s personal incentive \nstructure towards narrow—even if well intentioned—objectives. The result could likely be that \nachieving those metrics could become the overriding priority, potentially 1) prioritizing short-term \noutcomes at the expense of balance and long-term perspective that is necessary to achieve the broader \nmission of PJM, and/or 2) giving precedence and attention only to those issues tied to performance \nmetrics, leaving other important but unincentivized issues by the wayside. Second, the PJM process \nand, indeed, the overall electric utility industry structure, is likely not conducive to tying work product \nin one period to actual outcomes—whether they be regulatory, reliability, price/affordability, etc. — in \nthe same period. Owing to the long timescales of the utility industry, outcomes are often a significant \nlagging indicator to actions, often by years. Judging the quality of management performance, especially \nat an RTO, is only something that can be done over time. Third, PJM management is already facing \nunprecedented levels of scrutiny in an environment where it can be hard to identify high-caliber \npersonnel alternatives. Layering publicly-reported performance assessments on top of already \nsignificant pressure would not be constructive to management retention and, if it caused attrition of top \nstaff, could actually reduce outcome quality."},{"page":16,"startToken":3516,"endToken":3811,"text":"16 \n \nK. \nQuestion 11 – Advisory Stakeholder Process  \n \nYes \nNo \nShould the stakeholder process be advisory, i.e., stakeholder votes \nonly inform the Board? \nx \n \n \nExelon supports transitioning the PJM stakeholder process to be advisory. This would be a \nchange from the current binding endorsements process, and would entail a move to advisory polling for \noperations, planning, and market rules as well as for tariff changes and other activities. Our view is that \nthis—paired with the necessary shift in section 205 rights—is likely the most impactful available \ngovernance reform and would be a significant way to address the concern expressed by Commission \nChair Swett that PJM’s governance structure is unacceptable and the region may be “too big to \nfunction.” This perspective is aligned with the view advanced by the PJM Transmission Owners that \nthe “PJM’s stakeholder process, which culminates in PJM Members Committee votes, has been widely \nacknowledged as an often fractious, difficult and time-consuming exercise. Intended to promote \ncollaboration and compromise, it has in practice instead led to stasis, with many self-interested parties \neffectively exercising veto power over critical issues.”4 Instead, advisory polling would maintain the \nbenefits associated with the existing large, coordinated regional grid that provides backbone reliability \nto 67 million customers across a wide 13 states and the District of Columbia. \nBinding member endorsement voting has limited PJM’s ability to act independently, nimbly, and \neffectively. The current binding structure has constrained PJM’s ability to modify its governing \ndocuments, either leading to inferior, compromised rule proposals or, in some cases, no ability to \npresent proposals to the Commission at all. By its current process, PJM and its members are forced into \n \n4 Duquesne Light Co., Amendments to the Consolidated Transmission Owners Agreement, Docket No. ER24-2336-000, at 8 \n(filed June 21, 2024)."},{"page":17,"startToken":3811,"endToken":4157,"text":"17 \n \nendless negotiations to secure majority consensus, leading to watered-down rules and stifled \ninnovation.5 Furthermore, the binding stakeholder process has proven to be slow, creating occasions for \nindividual opportunistic stakeholders to delay resolution, in some cases for years, and ultimately \nproduces ineffectual outcomes. In the worst cases, the products of the existing binding process may be \nso compromised as to not achieve their objectives, potentially leading to the costs of running the \nstakeholder process—in time and other resources—without any benefits to customers or the market. \nEspecially in an operating environment that demands decisive, timely action to maintain reliability and \naddress affordability, the current structure is not tailored to the needs of a modern RTO.  \nAdvisory stakeholder polling is successfully used in MISO, CAISO, SPP, and ISO-NE. It serves \nas a tool for gathering information on the positions of the RTO membership on proposals being \nconsidered by RTO staff and the Board. Stakeholder polling can enhance transparency regarding the \nposition of various stakeholders, while allowing a shift away from the sector-weighting structure that \ncan lead to stilted results and inflexibility in the ability of decisionmakers to make judgements based on \nmore than mechanistic vote-counting. Furthermore, an advisory stakeholder framework would preserve \na stronger, formal voice for state regulators by allowing them to provide their perspective and have it \nconsidered, either by participating in polls or otherwise, in a manner that does not constrain the state \nperspective to being considered as just another vote.  \nIn addition to bringing PJM into line with best practices across other RTO/ISOs, a shift to \nadvisory polling would better align PJM’s governance with Commission policy. The Commission has \nhistorically prioritized the idea that RTOs/ISOs should be independent. Polling of members, that is \nstrictly advisory, ensures the ultimate decision-making power rests with the RTO/ISO Board, with \n \n5  See e.g., id. at Ex. C, Declaration of Pulin Shah, ¶¶ 11–14 (discussing the PJM stakeholder process impeding PJM from \nmoving forward with storage as a transmission asset, preventing PJM from leveraging this potentially valuable, flexible, and \ncost-saving transmission option)."},{"page":18,"startToken":4157,"endToken":4383,"text":"18 \n \nsupport from expert staff. This would protect PJM from being deadlocked or dictated to by special \ninterest groups or competing member companies. Leveraging advisory polling would allow the \nindependent Board to gain the views of the members while properly empowering them to override \nbiased stakeholder consensus when necessary to ensure fair market operations.  \nAdvisory polling would particularly benefit PJM because it would strongly contribute to \nmaintaining RTO independence and neutrality given PJM’s makeup and its range of stakeholders that is \nbroader, more diverse in terms of represented interests and business structures, more politically \nheterogenous, and more topologically complex than other RTO/ISO regions. This reform would have the \nadded benefit of addressing concerns, that have been expressed by the Commission and states regarding \nthe need to prevent special interest groups, incumbent transmission and generation utilities, financial \nmarketers, industrial customers and consumer advocates from capturing the regulatory process and \nvetoing market reforms that threaten their parochial business interests. An advisory framework would \nmake it impossible for coalitions to vote down proposed reforms out of protective self-interest, resulting \nin rules that often protect the narrow interests of members at the expense of the regional grid as a whole. \nIt would allow the Board to exercise its independence to bypass gridlock and make timely, objective, \nsystematic, strategic decisions in the interest of broad grid reliability and market efficiency."},{"page":19,"startToken":4383,"endToken":4703,"text":"19 \n \nL. \nQuestion 12 – PJM 205 Rights Over Energy and Ancillary Service Markets \n \nYes \nNo \nShould PJM have section 205 filing rights over the energy market \nand ancillary services unencumbered by the requirement to obtain \napproval of two-thirds of the Members Committee? \nx \n \n \nExelon supports PJM having section 205 rights over the energy and ancillary services markets, \nunencumbered by the requirement to obtain any approval from the Members Committee. This would \nalign with the section 205 rights that PJM currently has for the capacity market. This conclusion \nfollows, in part, from similar reasoning that leads Exelon to support a change to an advisory \nstakeholder process: the current binding endorsement voting approach gives stakeholders outsized \nauthority over section 205 filings to the Commission. Moreover, and beyond the practical challenges \nthat have flowed from the current process that binds the Board to the actions of the Members \nCommittee, the Members Committee should not have anything resembling 205 rights in the first \ninstance. These rights appropriately lie with PJM as the Commission-jurisdictional public utility, \nunencumbered by the obligation to act in accordance with action of the Members Committee, a third \nparty. Under the FPA, only a public utility has section 205 rights to file to change its tariff without \nshowing that its existing provision is unlawful, and PJM is that public utility. The Members Committee \nis not.  \nThis shifting of rights to the Board and away from the Members Committee restores the RTO’s \nproper rights and responsibilities. Under the current arrangement, in many instances PJM is prohibited \nfrom acting to modify its rules and processes without approval of the Members Committee; that is the \ndefinitional opposite of independence. It puts PJM in a position subservient to the Members Committee \nand in an inferior legal posture. PJM cannot act under section 205 to change its tariff without approval \nfrom the Members Committee, a body that may not act consistent with PJM’s interests, and may"},{"page":20,"startToken":4703,"endToken":4825,"text":"20 \n \nobstruct changes to maintain reliability and advance market efficiency. Instead, perversely, in many \ninstances PJM may only change its own tariff by filing a complaint under section 206 against itself. \nRestoring section 205 rights to the proper party (i.e., PJM) and advancing the necessary and \ncorresponding shift to an advisory stakeholder structure puts the ultimate accountability and \nresponsibility for federal regulatory filings with PJM, rather than wrongly transferring them to private \nmarket participants. Then, the Commission is put in the proper role of adjudicating the merit of those \nfilings and whether they are just and reasonable and not unduly discriminatory, rather than only having \nthe chance to review those limited, delayed, watered-down filings that the PJM stakeholder process \ncurrently produces."},{"page":21,"startToken":4825,"endToken":5032,"text":"21 \n \nM. \nQuestion 13 - PJM 205 Rights Over Planning Protocols  \n \nYes \nNo \nShould PJM have section 205 filing rights over Regional \nTransmission Expansion Planning (RTEP) unencumbered by the \nrequirement to obtain approval of two-thirds of the Members \nCommittee? \nx \n \n \nExelon supports PJM having section 205 rights over the RTEP process unencumbered by the \nrequirement to obtain any approval from the Members committee, as PJM has over the capacity market \nand as we support it having over the energy and ancillary service markets. Our reasoning in support of \nthis position is consistent with that provided in response to Question 12. As the PJM Transmission \nOwners have stated, “PJM, as embodied in the PJM Board and staff, is the “public utility” under the \nFPA and is thus the only appropriate counterparty to the Transmission Owners in terms of transferred \nrights and commitments under the FPA.”6 We note that any enhancement of section 205 rights over the \nRTEP process would be subject to negotiation of appropriate corresponding amendments to the CTOA \nsatisfactory to both PJM and the PJM Transmission Owners. Indeed, PJM and the PJM Transmission \nOwners attempted to implement just such a change in June 2024 in Docket Nos. ER24-2336, EL24-\n119, and ER24-2338. \n \n \n \n6 Id. at 21."},{"page":22,"startToken":5032,"endToken":5194,"text":"22 \n \nN. \nQuestion 14 – Jump Ball Rights for OPSI \n \nYes \nNo \nShould the Organization of PJM States Inc (OPSI) have “jump \nball” rights over resource adequacy and transmission cost \nallocation filings when a supermajority of OPSI agrees on an \nalternative proposal? \n \nx \n \nExelon does not support the creation of “jump ball” rights for OPSI or for any other party, \nincluding the Members Committee, for any issues, including resource adequacy and/or transmission \ncost allocation. Under the FPA, only a public utility like PJM may have section 205 rights.7 It would \ntherefore be inappropriate to grant section 205 rights to any non-utility party, including OPSI or the \nMembers Committee.  \n \n \n7 Commonwealth of Mass., Dep’t of Pub. Utils. v. United States, 729 F.2d 886, 888-89 (1st Cir. 1984) (Breyer, J.) and Atl. \nCity Elec. Co. v. FERC, 295 F.3d 1, 9-10 (D.C. Cir. 2002) and Atlantic City Electric Co. v. FERC, 329 F.3d 856, 859 (D.C. \nCir. 2003)."},{"page":23,"startToken":5194,"endToken":5312,"text":"23 \n \nO. \nQuestion 15 – Members Committee Jump Ball Rights \n \nYes \nNo \nShould the Members Committee have “jump ball” filing rights over \nthe portions of the tariff where PJM has 205 filing rights when a \nsupermajority of stakeholders approves an alternative proposal? \n \nx \n \nExelon does not support the Members Committee having “jump ball” filing rights over any \nportions of the tariff, regardless of any stakeholder voting thresholds. For the same reason that Exelon \ndoes not support providing “jump ball” filing rights to OPSI, as described in the answer to Question 14, \nExelon opposes providing a “jump ball” filing rights to the Members Committee. Only a public utility, \nnot the Members Committee, may have section 205 rights.8  \n \n \n8 Id."},{"page":24,"startToken":5312,"endToken":5499,"text":"24 \n \nP. \nQuestion 16 – Sector Weighted Voting Threshold \n \nYes \nNo \nShould the approval threshold in the Members Committee be \nlowered from two-thirds sector-weighted voting? \n \nx \n \nExelon does not support lowering the Members Committee sector-weighted voting threshold \nfrom two-thirds. This is not the solution to what ails the Members Committee process. While it is \ncorrect that the current sector-weighted voting thresholds have been a significant barrier to advancing \nreforms through the PJM stakeholder process, lowering the threshold could do as much to allow poorly \nconceived proposals to pass as much as it could reduce the likelihood that well-developed proposals are \nstymied. The right answer, consistent with Exelon’s position expressed elsewhere in these comments, \nis to focus on empowering PJM staff and the Board by granting the Board expanded section 205 rights \nand shifting the stakeholder process to be advisory. If that critical reform is implemented, then any \nweighting of votes or polls by the Members Committee would become unnecessary and voting reports \ncould be used to analyze members’ positions through a more expansive and diverse set of filters rather \nthan reducing everything to simply a member’s sector affiliation."},{"page":25,"startToken":5499,"endToken":5725,"text":"25 \n \nQ. \nQuestion 17 – Affiliate Voting in Lower-Level Committees \n \nYes \nNo \nShould the voting rules barring affiliate votes, which apply to \nsenior standing committees, also apply to lower-level committees? \n \nx \n \nExelon does not support extending the rules barring affiliate voting to the lower-level \ncommittees. The original motivation for the implementation of affiliate voting at lower-level \ncommittees was to foster innovation and ideation in discussions in those committees. We believe that \naffiliate voting still holds the potential to advance this objective, and to maintain the standing \ncommittees as open workshops for ideas as PJM stakeholders seek to address challenging issues. In this \ncontext, lower-level committees focus on highly technical operational and market mechanics. The \naffiliate structure allows companies that have more diverse business interests to express differentiated \npositions on behalf of those interests where there may be distinctions on technical issues. In the current \ncontext, it is also noteworthy that the affiliate voting bar at the senior committee level acts as a \nsafeguard against affiliate abuse. Furthermore, should the stakeholder process shift to being advisory in \nnature, the importance of affiliate voting would diminish—allowed or not—as all votes would be \ninformative to the ultimate decisions of the Board. Because the overall change to an advisory \nstakeholder structure is the more impactful change, changes to affiliate voting rules in the lower-level \ncommittees is of lesser consequence."},{"page":26,"startToken":5725,"endToken":5882,"text":"26 \n \nR. \nQuestion 18 – Governors and/or State Legislators’ Representative Group \n \nYes \nNo \nIn addition to OPSI, should there be a second state representative \ngroup consisting of governors’ representatives and/or state \nlegislators’ representatives? \nx \n \n \nExelon is supportive of creating an additional group, or groups, that allow for representation of \nstate Governors and/or state legislators. This is consistent with Exelon’s overarching view that it is \nappropriate to enhance the role of the states in the PJM governance structure, owing to the fact that \ndecisions have become more political and there are more critical issues that overlap federal and state \njurisdiction, so there is a need to more closely align state perspectives and PJM action. While OPSI \nplays a valuable role, we recognize that OPSI may not represent the full range of perspectives of \npolicymakers in the states, and therefore there may be room for an additional group, or groups, to \nensure representation of those broader perspectives."},{"page":27,"startToken":5882,"endToken":6143,"text":"27 \n \nS. \nQuestion 19 – State Representative Voting \n \nYes \nNo \nShould state representatives have a formal voting role in the \nstakeholder process (limited to certain topics, such as resource \nadequacy and regional transmission cost allocation) in addition to \nthe consumer advocate votes?   \nx \n \n \nShould they want it, Exelon supports the option for representatives of state interests to have a \nformal voting role in the stakeholder process, which be cast in addition to consumer advocate votes. \nThis position is consistent with our general view of the appropriateness of enhancing the role of the \nstates in the PJM governance structure. Allowing for such voting, if this is a mechanism among others \nthat state representatives view as appropriate and constructive, will allow them to formally express \ntheir position on issues of interest, along with the votes of other stakeholders. Granted, Exelon also \nsupports shifting the PJM stakeholder process to be advisory (i.e., stakeholder votes only inform the \nBoard), so in our view the process that the states would be voting in would inform but not bind the \nBoard. This would have distinct advantages, however, when adding state representative voting, \nincluding 1) there would not be a need to determine how to integrate state representative votes into \ncurrent binding sector-weighted structures and 2) by not constraining state representative votes to a \nspecific treatment within a broader structure (e.g., sector-weighted voting), the Board would be free to \nconsider state representative votes as they assess as appropriate and in a manner that may give such \nvotes higher significance related to certain issues (e.g., resource adequacy)."},{"page":28,"startToken":6143,"endToken":6350,"text":"28 \n \nT. \nQuestion 20 – OPSI Consultation on Resource Adequacy and Transmission Cost \nAllocation Filings  \n \nYes \nNo \nShould PJM be required to consult with OPSI prior to making a \nsection 205 filing related to resource adequacy and transmission \ncost allocation? \nx \n \n \nExelon supports consultation between PJM and OPSI prior to PJM making section 205 filings on \neither resource adequacy or transmission cost allocation. Regarding the latter, it must be recognized \nthat PJM does not have section 205 filing rights, as they were retained by the PJM Transmission \nOwners, so such consultation would be with the PJM Transmission Owners and not PJM. PJM makes \ntransmission cost allocation 205 filings on behalf of the PJM Transmission Owners and the PJM \nTransmission Owners consult with the Members Committee pursuant to CTOA Section 7.3.2. \nAdditionally, the PJM Transmission Owners typically consult with OPSI prior to making 205 filings.  \nAlthough OPSI already has the ability and does participate in stakeholder processes as well as \nconducting consultation with PJM and the PJM Transmission Owners, Exelon supports greater \nengagement by OPSI as well as opportunities for both the state commissions and the executive \nbranches of each state to be involved with mechanisms that allow each state to speak with one voice \nthrough OPSI."},{"page":29,"startToken":6350,"endToken":6474,"text":"29 \n \nIII. \nCONCLUSION \nExelon respectfully submits these comments for the Commission’s consideration as it continues \nto lead and drive towards solutions to deliver for American customers, including by improving \ngovernance structures in PJM. As the Commission considers these and other comments submitted in \nthis record, Exelon will remain a partner in developing and maintaining infrastructure that supports \naffordability, reliability, resilience, national security, economic growth, and other public policy goals.  \n \nRespectfully submitted, \n \n/s/ Bradley Perkins \nBradley Perkins  \nVice President and Deputy General Counsel \nExelon Corporation  \n10 S. Dearborn \nChicago IL 60603 \nPhone: (312) 394-2632 \nEmail: bradley.perkins@exeloncorp.com \n/s/ William Sauer \n William Sauer \nVice President, Regulatory Affairs \nExelon Corporation \n701 9th Street, N.W. \nWashington, DC 20068 \nTelephone: 202-868-7499 \nEmail: William.Sauer@exeloncorp.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":473,"startToken":0,"endToken":56},{"p":1,"at":473,"title":"I. INTRODUCTION AND COMMENTS","method":"printed heading","endPage":6,"endAt":5,"startToken":56,"endToken":1250},{"p":6,"at":5,"title":"II. RESPONSES TO QUESTIONS IN NOTICE","method":"printed heading","endPage":6,"endAt":44,"startToken":1250,"endToken":1256},{"p":6,"at":44,"title":"A. Question 1 – Board Member Terms","method":"printed heading","endPage":7,"endAt":5,"startToken":1256,"endToken":1547},{"p":7,"at":5,"title":"B. Question 2 – Board Service Limits","method":"printed heading","endPage":8,"endAt":5,"startToken":1547,"endToken":1805},{"p":8,"at":5,"title":"C. Question 3 – Footprint Residence Preference","method":"printed heading","endPage":9,"endAt":5,"startToken":1805,"endToken":1972},{"p":9,"at":5,"title":"D. Question 4 – Cooling Off Period","method":"printed heading","endPage":10,"endAt":6,"startToken":1972,"endToken":2164},{"p":10,"at":6,"title":"E. Question 5 – Ex Parte Restrictions","method":"printed heading","endPage":11,"endAt":6,"startToken":2164,"endToken":2439},{"p":11,"at":6,"title":"F. Question 6 – Board Vote Transparency","method":"printed heading","endPage":12,"endAt":6,"startToken":2439,"endToken":2659},{"p":12,"at":6,"title":"G. Question 7 – Public Board Meetings","method":"printed heading","endPage":13,"endAt":6,"startToken":2659,"endToken":2847},{"p":13,"at":6,"title":"H. Question 8 – Public Interest Principle","method":"printed heading","endPage":14,"endAt":6,"startToken":2847,"endToken":3014},{"p":14,"at":6,"title":"I. Question 9 – State Nominating Committee Representation","method":"printed heading","endPage":29,"endAt":6,"startToken":3014,"endToken":6351},{"p":29,"at":6,"title":"III. CONCLUSION","method":"printed heading","endPage":29,"endAt":945,"startToken":6351,"endToken":6474}]}