{"document":{"slug":"rec-20260821-5266","title":"Limited Protest of Constellation Energy Generation, LLC re PJM Interconnection, L.L.C.’s 07/31/2026 filing","issued":"2026-08-21","accession":"20260821-5266","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Constellation Energy Generation, LLC","kind":"protest","file":"sources/filings/text/20260821-5266_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5266","tier":"record","sha256":"b435d43e3cac6d68ca5d2b1049a2a3ef604bdf8022b75a0fe38117d90dae280e","pages":71,"tokens":18939,"emptyPages":[33,34],"textThemes":["adequacy","cost","credit","colo"]},"pages":[{"page":1,"startToken":0,"endToken":276,"text":"UNITED STATES OF AMERICA \n \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \n \n \n) \nPJM Interconnection, L.L.C. \n \n \n) \n \nDocket No. ER26-3380-000 \n \n \n \n \n \n \n \n) \n \nLIMITED PROTEST OF CONSTELLATION ENERGY GENERATION, LLC \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“FERC” or \n“Commission”) Rules of Practice and Procedure,1 Constellation Energy Generation, LLC \n(“Constellation”) hereby submits this limited protest of the revisions PJM Interconnection, L.L.C. \n(“PJM”) submitted on July 31, 2026, to the PJM Open Access Transmission Tariff (“Tariff”) and \nthe Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish the \nReliability Backstop Procurement (“RBP”).2 \nConstellation has serious concerns with several elements of the RBP, including its new-\nresource limitations, pay-as-bid procurement structure, and cost-allocation consequences.  Given \nthe need for prompt action, however, this limited protest seeks four targeted modifications and/or \nclarifications.  The first and most important is for the Commission to reject PJM’s proposal that \n“Available RBP UCAP” 3 participate in Reliability Pricing Model (“RPM”) Auctions as a price \ntaker for the duration of the RBP commitment.4  PJM suggests that RBP resources must be offered \n \n1  18 C.F.R. § 385.211. \n2  PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming \nfrom Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (the “PJM Proposal”).  Capitalized terms used \nbut not otherwise defined herein have the meaning as defined in the Tariff, the RAA, or the PJM Proposal, as \napplicable.  \n3  “Available RBP UCAP” means committed RBP UCAP that, for the applicable Delivery Year, is accredited, has \nsatisfied the applicable commercial-operation or registration requirements, is deliverable where required, and is \navailable to provide capacity. \n4  See PJM Proposal at 56."},{"page":2,"startToken":276,"endToken":656,"text":"2 \ninto RPM as a price-taker to ensure load does not “double pay” for capacity.  PJM’s proposal will \ndo more harm than good, however, because it will undermine RPM’s ability to send accurate \nresource adequacy price signals in the future.5  As explained in Section I and the accompanying \nAffidavit of Roy J. Shanker, Ph.D., included here as Appendix A, PJM’s proposed requirement is \nnot a just and reasonable means of addressing PJM’s asserted duplicate-procurement concern.  \nInstead, Section I herein outlines why the Commission should direct PJM to exclude Available \nRBP UCAP from RPM price formation with a matched exclusion of RBP-Related Load.6  Such \nan annual isolation mechanism that adjusts both RBP supply and the matched quantity of RBP-\nRelated Load while preserving the RBP resources’ compensation and physical obligations is \nreflected in the Tariff language contained in Appendix B to this limited protest. 7  This modest \nadjustment to PJM’s proposal will allow the RBP to procure the megawatts needed to address \nPJM’s immediate resource adequacy shortfall, while preserving RPM’s effectiveness for price \nformation in support of long-term resource adequacy. \nSections II through IV describe three additional changes that FERC must make to render \nthe filing just and reasonable: (1) the deletion of the “new Maximum Facility Output” requirement \nin Tariff section 18.5(b)(i) and inclusion of qualifying Energy Resources in section 18.5(b)(iii); \n(2) the addition of a meaningful cure period for Qualifying RBP Offset UCAP MW submissions; \nand (3) clarification and revision of certain credit and collateral provisions. \n \n5  Id. at 57. \n6  “RBP-Related Load” means the portion of the incremental-load cohort used to establish or allocate the RBP that \nPJM includes in the planning parameters for the applicable RPM Auction. \n7  The proposed, illustrative language in Appendix B regarding the isolation mechanism is provided to assist the \nCommission in exercising its authority (to which PJM consented) to modify the proposed Tariff pursuant to the FPA \nand NRG Power Marketing in order to resolve the issues raised in this limited protest.  See, e.g., PJM Proposal at 3-4 \nand 130-131.  No severance is recommended and effectuating Appendix B may be done and meshed with the other \nparts of the Tariff without causing delay in the commencement of the RBP in September 2026."},{"page":3,"startToken":656,"endToken":963,"text":"3 \nAccordingly, consistent with NRG Power Marketing, LLC v. FERC,8 the Commission \nshould accept the RBP subject to the exercise of its authority to modify the proposed Tariff \nlanguage in order to effectuate the four targeted Tariff and RAA modifications set forth herein and \nin Appendix B. \nI. \nLIMITED PROTEST OF REQUIREMENT THAT AVAILABLE RBP UCAP \nMUST OFFER INTO RPM AS A PRICE TAKER \nA. \nIntroduction and Summary \nThe capacity challenge facing the PJM Region is serious.9  While PJM’s filing includes \nseveral imperfections, Constellation does not oppose PJM’s use of a one-time RBP to address the \nshortfall in the 2028/2029 Base Residual Auction (“BRA”), reduced as applicable for accepted \noffsets and opt-outs.10 \nAlthough PJM frames the RBP as a one-time stopgap measure, the zero-offer obligation \nwill affect repeated RPM Auctions for as long as fifteen years.11  The RBP may address an \nimmediate procurement need, but without modification it can weaken the market’s ability to attract \nand retain the capacity PJM will need in later years.  PJM’s price-taker requirement is unsupported \nand potentially harmful because it impairs RPM as a credible price-forming market.  Such \ndegradation to RPM could result in resources deferring market entry or capital expenditures, \nexporting to other markets, or accelerating retirements—undermining the express resource \nadequacy purpose of PJM’s RBP proposal.12  \n \n8  NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017).  \n9  This limited protest does not challenge PJM’s decision to procure needed capacity or to impose enforceable physical \nperformance obligations on selected resources. \n10  See PJM Proposal at 7–9. \n11  See id. at 5, 7.  \n12 PJM itself has said RPM pricing below the value placed on capacity by other regions incents generators to export \nto neighboring regions.  See PJM Interconnection, L.L.C, 2027/2028 Base Residual Auction Reserve Target Shortfall"},{"page":4,"startToken":963,"endToken":1312,"text":"4 \nAs Dr. Roy Shanker—an economist with more than 50 years of electric-industry \nexperience and approximately 30 years of competitive-market-design experience, including \nparticipation in PJM market design since RPM’s inception—explains: When Available RBP \nUCAP precedes or exceeds the RBP-Related Load reflected in an RPM Auction, the mandatory \nzero-offer rule can cause RPM to signal excess supply to the residual market.13  Distorting the \nRPM price signal threatens increased retirement risk, incents resources to export to other \nmarkets,14 and delays market entry and capital investment—leaving PJM short yet again when \ndelayed load arrives.15  The risk of delayed load is real and looming, so ensuring RPM sends \ncorrect price signals, rather than promoting the exit of existing generation, is of critical importance \nto reliability. \nPJM has not addressed the foreseeable mismatch between supply and load timing.  PJM \nhas supported the physical retention and compensation of RBP resources, but it has not shown \nthat requiring those resources to offer at zero in RPM auctions will support resource adequacy in \nPJM beyond covering the most immediate shortfall.  That omission is the heart of this limited \nprotest, and the solution lies in conditioning approval of PJM’s FPA 205 filing on the annual \nisolation mechanism that excludes the RBP resources and a matched quantity of RBP Load from \nRPM Auctions as set forth in Section I.D. \n \nReport 12 (Feb. 9, 2026), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-\n2028/2027-2028-bra-reserve-target-shortfall-report.pdf.  \n13  See Shanker Aff. ¶¶ 9, 14 \n14 See, e.g., Cordova Energy Company LLC, 194 FERC 61,108 (2026) (authorizing a 611.2 MW natural-gas fueled, \ncombined-cycle electric generating facility located in PJM to sell its capacity to an affiliate in MISO during the \n2028/2029 Delivery Year after already receiving approvals for similar sales during the 2027/2028 Delivery Year); \nDairyland Power Coop., 194 FERC ¶ 61,133, at P 5 (2026) (explaining that Dairyland acquired PJM units for the \npurpose of exporting energy and capacity to fulfill Dairyland’s capacity obligations to its distribution cooperative \nmembers located in MISO). \n15  See Shanker Aff. ¶¶ 13–16."},{"page":5,"startToken":1312,"endToken":1628,"text":"5 \nThe PJM proposal aims to implement the Statement of Principles Regarding PJM issued \non January 16, 2026, by the National Energy Dominance Council and the 13 governors of the PJM \nstates.16  The NEDC/PJM Governors’ Principles called both for prompt procurement and a return \nto market fundamentals.17  But mandatory zero offers for separately compensated RBP capacity \nfrustrates that objective by causing RPM to signal excess supply when Available RBP UCAP \nexceeds RBP-Related Load that actually materializes.  The RBP proposed by PJM is not a return \nto market fundamentals but rather a retreat from them. \nIt is wholly inconsistent with market fundamentals for the main capacity market, RPM, to \nfalsely signal excess supply on the heels of a supplemental procurement due to a serious resource \nadequacy shortfall.  As Dr. Shanker explains, PJM’s proposed treatment of that capacity \nundermines the same resource-adequacy objective PJM aims to solve with the RBP.18 \nB. \nPJM Has Not Shown That Mandatory Zero Offers Are Just and Reasonable \nPJM has shown why RBP resources should be retained for resource adequacy and why \nselected sellers should receive their accepted RBP compensation.  PJM has not shown why a zero \nprice is the appropriate representation of those resources in the supply stack when RPM is intended \nto establish the marginal value of capacity.  \nWhether an RBP resource should count toward reliability, whether it should receive its \npromised compensation, and whether its mandatory offer should affect the market price paid to \nnon-RBP resources are distinct questions.  PJM’s filing conflates them in the name of guarding \nload against facing risk of double payment for capacity.  A mandatory $0/MW-day offer is not the \n \n16  PJM Proposal at 2 (citing National Energy Dominance Council, Statement of Principles Regarding PJM (Jan. 16, \n2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm) \n(“NEDC/PJM \nGovernors’ \nPrinciples”). \n17  NEDC/PJM Governors’ Principles at 1. \n18  See Shanker Aff. ¶¶ 14–15."},{"page":6,"startToken":1628,"endToken":1879,"text":"6 \nreasonable or just way to address that risk because such mandate does more harm than good by \nsignaling excess supply if anticipated load is delayed or does not show up, thereby encouraging \ndeparture of existing generation—recreating the very reliability problems that spurred the RBP in \nthe first place.  This problem can be eliminated, and load still protected from double payment, if \ninstead PJM removes RBP supply while also removing the actual new load that the RBP resources \nwere procured to supply.  That way, if anticipated load is delayed, the market will not signal excess \nsupply and encourage retirement of the existing fleet. \nAs Dr. Shanker explains, RPM price signals guide both new-entry and resource-retention \ndecisions.19  When a large block of capacity procured under long-term, out-of-market \ncommitments is required to offer at zero, prospective entrants may defer merchant investment in \nanticipation of lower-risk contractual opportunities, while existing resources may accelerate exit \nor decline to commit additional capital. \nThose responses can occur substantially faster than replacement generation can be \ndeveloped.  An inappropriate signal today can therefore leave the competitive fleet smaller when \nforecast load ultimately arrives. 20  Indeed, Constellation suspects this phenomenon (lack of new \nentry and instead waiting for out-of-market compensation) was reflected in the last RPM auction, \nas the instant filing providing for an out-of-market auction opportunity was widely-discussed and \nexpected. \nPJM’s own contemporaneous analysis corroborates Dr. Shanker.  PJM describes a \n“credibility trap” in which scarcity triggers price caps, emergency backstop procurements, or other \n \n19  Id. \n20  Id."},{"page":7,"startToken":1879,"endToken":2209,"text":"7 \nadministrative interventions.  Investors then discount the durability of the revenue signal, capital \nremains on the sidelines, and the shortage persists.21  \nPJM states that the RBP should not subsume the broader review of market fundamentals \nand that the RBP should permit PJM to return to competitive resource-adequacy markets as soon \nas possible.22  Yet, the mandatory zero-offer requirement moves in the opposite direction by \nallowing the financial terms of a separate backstop procurement to determine the price signal \nreceived for the next 15 years by the residual competitive market, which could undermine the \nresource adequacy objective of that market. \nThe challenged proposal is not transitory merely because PJM calls the RBP a “one-time” \nprocurement.  The Initial RBP Target is 6,831.3 MW UCAP before accepted offsets and opt-outs. \nAs selected resources become operational and accredited, PJM will require their committed, \navailable RBP UCAP to offer at $0/MW-day in each applicable RPM Auction through the end of \nthe applicable commitment (i.e., up to 15 years).  The procurement can create a potentially multi-\ngigawatt block of mandatory zero-priced capacity in repeated RPM Auctions over many years. \nPJM supplies no sensitivity analysis evaluating whether its mandatory zero-offer rule will \npreserve appropriate entry and retention signals under plausible variations in timely load \nrealization, resource commercial-operation dates, annual accreditation, resource exit or retirement, \nor updated Incremental Auction parameters.  Nor does PJM analyze the later resource-adequacy \neffect if delayed load arrives after the auction signal has induced exit or deferred entry.  PJM’s \n \n21  PJM Interconnection, L.L.C., Powering Reliability Through Market Design: Addressing Rising Demand and \nConstrained Supply, and Stimulating Investment to Support Durable Reliability 5–6, 26, 29–30 (May 6, 2026), \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-\nthrough-market-design.pdf. \n22  PJM Interconnection, L.L.C., Critical Issue Fast Path–Reliability Backstop Procurement PJM Proposal 1(June 30, \n2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02a---\npjm-reliability-backstop-procurement-proposal---paper.pdf (“PJM Paper”)."},{"page":8,"startToken":2209,"endToken":2508,"text":"8 \nsection 205 showing therefore does not address the central price-formation and resource-adequacy \nconsequences of the rule it proposes. \nC. \nThe Risk Is Most Acute When Available RBP UCAP Precedes or Exceeds \nTimely RBP-Related Load \nThe price-formation and reliability risks are most acute when Available RBP UCAP \nexceeds the RBP-Related Load included in the Planning Parameters for the applicable RPM \nAuction.  That mismatch does not require long-term load growth to disappear—a delay alone is \nsufficient.  Even if all forecast load ultimately connects, a multi-year delay can cause RPM to \nsignal reduced need for resource retention and new entry before the load arrives. \nDr. Shanker uses a simplified example in which the full Initial RBP Target is available in \nthe relevant auction but load is delayed.23  This delayed-load example shows the resulting \nproblem.24  Assume, for illustration, that approximately 6.8 GW of RBP capacity becomes \navailable and must enter RPM at a zero price, but only 3 GW of RBP-Related Load is reflected in \nthe applicable auction parameters due to large load delays.  RPM would then reflect 3.8 GW of \nunmatched zero-offer RBP supply without the corresponding RBP-Related Load.  That clearing \noutcome can signal reduced need for retention or entry in the RPM market.  If the remaining load \narrives several years later, some existing capacity may already have retired (or otherwise exited \nPJM), and prospective new entry may have stayed on the sidelines.  Because retirement/exit can \noccur faster than replacement capacity can be developed, PJM may again face a shortfall and \npressure for another out-of-market procurement.25 \n \n23  In operation, the quantity of Available RBP UCAP subject to the isolation mechanism would vary by Delivery \nYear based on commercial-operation timing, accreditation, and availability, as described above. \n24  Shanker Aff. ¶¶ 13–14. \n25  Id. ¶¶ 14–16."},{"page":9,"startToken":2508,"endToken":2862,"text":"9 \nPJM’s implementation design confirms that the relevant supply and demand quantities will \nvary across auctions.  Available RBP UCAP may ramp across several Delivery Years, while PJM \nwill continue to update its load forecasts through later RPM Auctions.  PJM’s August 10 example, \nfor instance, shows an illustrative 6,800 MW portfolio providing 3,900 MW in 2028/2029, 6,750 \nMW in 2029/2030, 6,800 MW in 2030/2031, and 6,850 MW in 2031/2032.  PJM’s example is \nillustrative rather than predictive, but it confirms that the filed selection architecture permits RBP \nquantities to vary materially across Delivery Years and that RBP supply may exceed the target in \na particular year.26  \nIncremental Auctions do not cure this problem.  They update the competitive market \naround the RBP commitments; they do not true up or unwind the underlying backstop \nprocurement.  If PJM lowers the load reflected in the planning parameters (even temporarily) while \nAvailable RBP UCAP remains subject to the zero-offer requirement, the forecast correction is \nborne by the existing resources participating in the RPM market rather than by the out-of-market \nprocurement based on the earlier forecast.27 \nThe supply-load timing risk is not merely conceptual.  ERCOT has reported approximately \n8,900 MW of large load approved for energization, of which more than 5,000 MW had not yet \nenergized, while significant new generation and storage capacity was being added.28  While \nERCOT’s market design differs materially from PJM’s, this example illustrates an underlying \nfactual risk:  large-load projects and new supply do not necessarily become operational on the \n \n26  See PJM Interconnection, L.L.C and Charles River Associates, Reliability Backstop Procurement Execution \nPresentation, 44–45 (Aug. 10, 2026).  Slides 44-45 show 3,900 MW in 2028/2029, 6,750 MW in 2029/2030, 6,800 \nMW in 2030/2031, and 6,850 MW in 2031/2032, and explain that full, indivisible offers may exceed the remaining \ntarget). \n27  Shanker Aff. ¶ 17. \n28  Electric Reliability Council of Texas, Large Load Interconnection Status Update, Large Load Integration Team 8–\n9 (June 19, 2026), https://www.ercot.com/files/docs/2026/06/18/June-19-LLWG-Report.pptx."},{"page":10,"startToken":2862,"endToken":3200,"text":"10 \nsame schedule.  Based on the ERCOT example, it is not a hypothetical that new supply may enter \nservice prior to when the corresponding large load enters service.  PJM’s RBP design should not \nassume otherwise. \nPJM’s own recent downward revisions to its near-term load growth forecasts confirms that \nlarge-load forecasts are not static and that the amount reflected in successive RPM Auctions can \nchange materially.  The downward revision for peak annual load in 2027 was trimmed by 3,735 \nMW.29  The point is not that PJM’s long-term load growth will necessarily fail to appear.  The \npoint is that the timing of supply and load can diverge long enough for a temporary RBP supply \nsurplus to produce durable entry, exit, and retirement consequences in RPM.30 \nWhen timely RBP-Related Load is below Available RBP UCAP, mandatory zero-offer \nRBP supply can cause RPM to signal excess supply to the RPM market before the forecast load \nhas arrived, even as PJM expects delayed load to require additional capacity.  That signal bears \ndirectly on entry, retention, and capital-investment decisions and can leave PJM short precisely \nwhen PJM continues to forecast substantial future demand.  \nD. \nAnnual RBP Isolation and a Matched Demand Adjustment Will Preserve the \nCompetitive Integrity of RPM While Avoiding Duplicate Procurement \nTo prevent the adverse impacts described above, while still protecting customers from \ndouble payment for capacity, Dr. Shanker recommends isolation through an annual, auction-\nspecific mechanism.  Dr. Shanker recommends removing the separately procured RBP supply and \n \n29  PJM Interconnection, L.L.C., PJM’s Updated 20-Year Forecast Continues to See Significant Long-Term Load \nGrowth (Jan. 14, 2026), https://insidelines.pjm.com/pjms-updated-20-year-forecast-continues-to-see-significant-\nlong-term-load-growth/.  \n30  Goldman Sachs reports that historically approximately 72% of data centers scheduled for activation within the \nfollowing four quarters came online on time and forecasts on-time realization of approximately 60% over the next \nyear and approximately 50% over the next two years.  See Goldman Sachs, US Data Center Power Demand Projected \nto Double by 2027 (May 20, 2026), https://www.goldmansachs.com/insights/articles/us-data-center-power-demand-\nprojected-to-double-by-2027."},{"page":11,"startToken":3200,"endToken":3458,"text":"11 \nthe corresponding RBP-related demand from RPM price formation.31  This isolation mechanism \neliminates the threat of any double payment and removes the deleterious impact on RPM.  The \nTariff language in Appendix B implements Dr. Shanker’s core isolation recommendation through \nan annual, auction-specific mechanism. \nThe revisions in Appendix B translate that economic recommendation into the filed RBP \ndesign by accounting for annual accreditation, availability, commercial-operation timing, and the \nconduct of both Base Residual Auctions and Incremental Auctions.  For each Delivery Year and \neach applicable RPM Auction, PJM should: (1) exclude Available RBP UCAP from the RPM \nprice-forming supply stack; and (2) reduce the applicable RPM reliability requirement by the lesser \nof Available RBP UCAP and RBP-Related Load included in the Planning Parameters for that \nauction, with both quantities expressed in UCAP terms.32 \nThe adjustment concerns price formation only.  The revisions in Appendix B preserve the \nRBP resources’ physical and performance obligations and the two-sided economics of the RBP \nsettlement. \nPJM argues that zero-price participation is necessary because responsible LSEs already are \npaying for RBP capacity and another resource might otherwise be procured via RPM if the RBP \nresources are not entered as price-takers, resulting in a double payment for capacity by load.33  \nThat concern assumes RBP supply is removed while the entire associated demand requirement \nremains in RPM.  Constellation’s proposal does not do that.  For the matched quantity—the lesser \nof Available RBP UCAP and RBP-Related Load—the mechanism adjusts both supply and \n \n31  Shanker Aff. ¶¶ 25–30. \n32  Id. ¶ 25. \n33  PJM Proposal at 57."},{"page":12,"startToken":3458,"endToken":3784,"text":"12 \ndemand.  RPM therefore does not procure replacement capacity for load already covered through \nthe RBP.34 \nDr. Shanker also explains why all RBP resources must be excluded, as price-taker offers \ncannot readily be prorated among individual large-load projects.  RBP resources are not physically \nmatched to particular loads, and individual generating units cannot be divided among varying \nlevels of realized load without creating another administrative allocation mechanism.35  The more \nworkable design is to isolate all the RBP supply while adjusting demand by the amount of timely \nRBP-Related Load. \nWhere Available RBP UCAP exceeds timely RBP-Related Load, Constellation recognizes \nthat isolation may temporarily preserve more total physical capacity than the updated RPM \nrequirement alone would procure.  Constellation proposes that result as a safeguard against \nallowing a potentially temporary, forecast-created mismatch to trigger exit and deferred \ninvestment before the load arrives.  The relevant comparison is intertemporal: temporary additional \ncapacity versus premature exit, later replacement, another capacity shortfall, and another backstop \nprocurement. \nPJM itself evaluated carving RBP supply and demand out of RPM.36  It anticipated that the \ncapacity-cost outcomes of the zero-offer and carve-out approaches would be largely the same and \nthat neither would materially change costs to the remaining RPM load.  PJM rejected isolation \n \n34  Even excluding the RBP supply and associated load as proposed here does not completely neutralize the out-of-\nmarket effects on RPM, as RPM is deprived of the RBP resources that would sit at the top of the supply stack, \nproviding upward pressure on RPM price signals.  See ISO New England Inc., 138 FERC ¶ 61,027 at PP 72–75 (2012); \nsee also ISO New England Inc., 135 FERC ¶ 61,029 at PP 230, 232 (2011).  By this measure, the isolation methodology \nis a conservative solution, yet is significantly more effective at reducing any out-of-market pricing impact as compared \nto the mandatory zero offer proposal, and without creating any risk of double payment.  \n35  Shanker Aff. ¶ 29. \n36  PJM Paper at 11."},{"page":13,"startToken":3784,"endToken":4053,"text":"13 \nprincipally because it believed the approach would differentiate large load from other load and \nrequire additional changes to RPM.37 \nThat concession substantially narrows the dispute.  The RBP already creates a separately \ncompensated supply cohort associated with a separately identified increment of forecast load for \nterms lasting as long as fifteen years.  Isolating that cohort from RPM price formation better \npreserves the competitive integrity of the residual market than requiring it to participate at zero in \nevery applicable RPM Auction. \nRBP isolation and the matched demand adjustment therefore preserve the RBP \nprocurement and the physical availability of RBP resources without representing separately \ncompensated capacity as though its competitive RPM offer were zero. \nII. \nTHE PHRASE “MAXIMUM FACILITY OUTPUT” IN TARIFF SECTION \n18.5(b)(i) SHOULD BE DELETED, AND ENERGY RESOURCES SHOULD BE \nINCLUDED IN SECTION 18.5(b)(iii). \nThe Commission should condition acceptance of PJM’s Proposal on (A) revising proposed \nTariff section 18.5(b)(i) from “new Installed Capacity and new Maximum Facility Output” to “new \nInstalled Capacity” and (B) revising proposed Tariff section 18.5(b)(iii)(2) to include an Energy \nResource seeking new Capacity Interconnection Rights.  As drafted, section 18.5(b) excludes an \nexisting Energy Resource that has Maximum Facility Output but no Capacity Interconnection \nRights and is seeking new Capacity Interconnection Rights through an Interconnection Request, \neven if the resource otherwise satisfies the RBP eligibility criteria. \nTo qualify as an RBP Resource, a generation resource must meet the requirements of \nsections 18.5(a) and 18.5(b) of the proposed Tariff.  Such generation resources must have a \n \n37  Id."},{"page":14,"startToken":4053,"endToken":4335,"text":"14 \ncommercial operation date prior to June 1, 2032, not otherwise have an RPM commitment for a \nfuture delivery year, and be: \n(i) Composed of new Installed Capacity and new Maximum Facility Output; \n(ii) Supported by new Capacity Interconnection Rights (if located in the \nPJM Region) or Capacity Interconnection Rights transferred from a \ndeactivated resource or a resource that announced deactivation as of April \n10, 2026; and \n(iii) Consist of (1) new build; (2) incremental capacity created by an uprate \nof an existing Generation Capacity Resource’s or Energy Storage \nResource’s installed capacity and associated level of Capacity \nInterconnection Rights; or (3) repowering of a generation resource that had \ndeactivated, or announced deactivation, on or before April 10, 2026.38 \nAn existing Energy Resource necessarily has Maximum Facility Output; obtaining new \nCapacity Interconnection Rights does not create a new Maximum Facility Output.  The relevant \nattribute from a resource adequacy perspective is the new Capacity Interconnection Rights.  \nExcluding an otherwise eligible resource solely because its Maximum Facility Output is not “new” \nand because it is currently not a capacity resource but is seeking to obtain new Capacity \nInterconnection Rights is unjust and unreasonable where the resource will provide new capacity, \nsatisfy the applicable commercial-operation requirements, and bear its share of any required \nNetwork Upgrade costs associated with securing its new Capacity Interconnection Rights. \nAccordingly, the Commission should exercise its authority to modify the proposed Tariff \nlanguage to delete the phrase “and new Maximum Facility Output” in proposed Tariff section \n18.5(b)(i) and add Energy Resources seeking new Capacity Interconnection Rights as a category \nof resource eligible under section 18.5(b)(iii)(2). \n \n38  See PJM Proposal, attach. A § 18.5(b)."},{"page":15,"startToken":4335,"endToken":4634,"text":"15 \nIII. \nQUALIFYING RBP OFFSET UCAP MW SUBMISSIONS SHOULD RECEIVE A \nMEANINGFUL CURE PERIOD \nConstellation requests clarification that PJM will provide a submitting entity five calendar \ndays from notice to cure a deficiency in a Qualifying RBP Offset UCAP MW submission, provided \nthat the cure is completed before the close of the bid submission window of the Reliability \nBackstop Procurement.  If PJM does not confirm that interpretation, the Commission should \ncondition acceptance on Tariff revisions expressly providing that cure opportunity. \nNew Section 18.2(c) requires entities to report the Qualifying RBP Offset UCAP MW \nduring the RBP bid submission window with accompanying listed evidence, but does not explicitly \nprovide for a cure period upon a finding of deficiency by PJM.39  PJM has indicated in stakeholder \nworkshops that it would initiate discussions with any parties where there are questions regarding \nthe submission of evidence of Qualifying RBP Offset UCAP MW.  Further, PJM’s recently-\nproposed draft Manual 18 Attachment F confirms that PJM contemplates that there will be some \nlevel of communication with participants regarding clarification of evidence submitted by \nparticipants seeking to establish Qualifying RBP Offset UCAP MW.40  However, given the impact \nof Qualifying RBP Offset UCAP MW on the RBP’s total procurement target and the procurement \nassignment and allocation of charges to specific EDC zones/areas, a more formal and explicit cure \nprocess is warranted. \nRBP Sell Offers receive a five-calendar-day cure opportunity after notice of a deficiency.41  \nQualifying RBP Offset UCAP MW submissions should receive the same substantive protection. \nThe Commission should therefore exercise its authority to modify the proposed Tariff language to \n \n39  See id.  \n40  PJM Interconnection, L.L.C., Draft Manual Language for Reliability Backstop Procurement (Aug. 10, 2026), \n20260810-draft-manual-language-for-reliability-backstop-procurement.pdf.  \n41  See PJM Proposal, attach. A § 18.5(f)(i)."},{"page":16,"startToken":4634,"endToken":4943,"text":"16 \nprovide for five calendar days from notice to cure a curable deficiency, subject to completion \nbefore the close of the bid submission window of the Reliability Backstop Procurement.  This \ntreatment will prevent minor, curable errors from unnecessarily increasing the procurement target \nor shifting cost responsibility. \nIV. \nLIMITED PROTEST OF CERTAIN CREDIT AND COLLATERAL PROVISIONS \nThe Commission should exercise its authority to modify the proposed Tariff language to \nclarify two aspects of the credit and collateral provisions in the proposed Tariff. \nFirst, the Commission should clarify that, for purposes of proposed Tariff section 18.8, \nreference to “the first Delivery Year” means the 2028/2029 Delivery Year.  As written, the phrase \nis ambiguous and does not provide affected Load Serving Entities sufficient certainty regarding \nthe date on which the initial collateral obligation attaches. \nSecond, in section 18.3(b)(iii) of the proposed Tariff, the Commission should replace the \nphrase “no later than sixty (60) days prior to the 2028/2029 Delivery Year” with “no later than \nthree-hundred sixty-five (365) days prior to the 2028/2029 Delivery Year.”  This would allow \nmarket participants to have a clear understanding of how the initial allocation determination under \nsection 18.3 will be effectuated, and perhaps equally important, how any default amounts that \nresult from the failure of expected large loads to materialize will also be allocated.  This timeline \nwould give the states over a year to conduct proceedings to finalize these determinations and the \nentire market will benefit from increased certainty.  PJM’s proposed schedule gives the State \nCommissions over two years to determine their proposed cost allocation and only fifteen days \nbetween the allocation determination and the collateral deadline. That period is not reasonably \npracticable and creates an unnecessary risk of credit default and resulting cost reallocation.  The \nrevisions to the Tariff proposed here provide those with collateral obligations a reasonable"},{"page":17,"startToken":4943,"endToken":5245,"text":"17 \nopportunity to quantify their final exposure, obtain necessary internal approvals, arrange \npotentially substantial collateral, and make the required posting. \nAccordingly, the Commission should therefore condition acceptance of PJM’s Proposal on \nreplacing the phrase “no later than sixty (60) days prior to the 2028/2029 Delivery Year” with “no \nlater than three-hundred sixty-five (365) days prior to the 2028/2029 Delivery Year” in revised \nTariff section 18.3(b)(iii). \nV. \nTHE MODIFICATIONS PROPOSED HEREIN COMPLY WITH NRG POWER \nMARKETING \nUnder NRG Power Marketing, the Commission may condition acceptance of a section 205 \nfiling where the filing utility has consented to the modification and the condition does not \ntransform the proposal into an entirely different rate design. \nThe modifications of the Tariff and RAA provisions proposed herein are consistent with \nNRG Power Marketing.  PJM expressly consents to Commission modification or severance of \nindividual Tariff and RAA provisions where the modification is consistent with the filing’s \noverarching objectives.42  PJM also asks the Commission to prescribe any replacement rule with \nsufficient specificity for immediate implementation, states that a compliance filing implementing \nprescribed changes would constitute further consent, and distinguishes this proposal from the \nstakeholder compromise at issue in NRG Power Marketing.43  PJM’s consent therefore satisfies \nthe threshold requirement for conditional acceptance. \n \n42  See PJM Proposal at 3 (“PJM provides notice that it consents to the Commission’s exercise of authority to modify \nand/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under section \n205 of the FPA and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent \nwith PJM’s overarching objectives in this filing”).  \n43  See PJM Proposal at 3–4, 131–33; NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114–16 (D.C. Cir. 2017)."},{"page":18,"startToken":5245,"endToken":5494,"text":"18 \nThe requested modifications to the Tariff here do not create an “entirely different rate \ndesign.”44  The isolation condition preserves the RBP solicitation, target determination, offsets and \nopt-outs, seller eligibility, selection process, resource-specific compensation, commitment terms, \ncost allocation, credit requirements, and physical performance obligations.  It modifies the \nrepresentation and settlement of RBP capacity in subsequent RPM Auctions to preserve \ncompetitive price formation and RPM’s resource-adequacy function. \nAs explained in Section I.D, PJM itself evaluated the same basic supply-and-demand \ncarve-out, confirming that the requested condition falls within the range of design alternatives \nconsidered during development of the RBP.45  The proposed modification therefore is neither \nforeign to the filed design nor beyond the range of alternatives of which stakeholders had notice.  \nAppendix B provides the framework for the Commission to use in the exercise of its authority to \nmodify the proposed Tariff to implement the annual formula, continuing resource obligations, \nsettlement treatment, and locational requirements. \nThe remaining requested revisions are narrower still and do not alter the RBP’s core \nprocurement, compensation, allocation, or performance design.  The Commission may therefore \ncondition acceptance without leaving PJM discretion to devise a materially different replacement \nrate. \nVI. \nCONCLUSION \nFor the foregoing reasons, the Commission should accept the RBP subject to the \nCommission exercising its authority to modify the proposed Tariff to effectuate the revisions \ndescribed herein and in Appendix B.  The annual RBP isolation mechanism and matched demand \n \n44  NRG Power Mktg., 862 F.3d at 115. \n45  PJM Paper at 11."},{"page":19,"startToken":5494,"endToken":5719,"text":"19 \nadjustment preserve the competitive integrity and resource-adequacy function of RPM, address \nPJM’s asserted duplicate-procurement concern, and preserve the RBP resources’ promised \ncompensation and physical obligations. \nThe Commission should also exercise of its authority to modify the proposed Tariff \nlanguage to: (1) delete the phrase “new Maximum Facility Output” in Tariff section 18.5(b)(i) and \ninclude qualifying Energy Resources in section 18.5(b)(iii); (2) provide a five-calendar-day cure \nopportunity for curable deficiencies in Qualifying RBP Offset UCAP MW submissions; and (3) \nclarify and revise the credit and collateral provisions in proposed Tariff sections 18.3 and 18.8. \n \nRespectfully submitted, \n \nDated: August 21, 2026 \n \n/s/ \nCarrie Hill Allen \nSr. Vice President & Deputy General \nCounsel \nJohn M. White \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \njohn.white@constellation.com \n \nChristopher A. Wilson \nVice President, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \nKenneth W. Irvin \nAlexandra K. Calabro \nSidley Austin LLP \n1501 K Street, N.W. \nWashington, DC 20005 \nPhone: (202) 736-8256 \nkirvin@sidley.com \nalexandra.calabro@sidley.com \n \nTerence T. Healey \nSidley Austin LLP \n60 State Street, 37th Floor \nBoston, MA 02109 \nPhone: (617) 223-0306 \nthealey@sidley.com \n \nCounsel for Constellation Energy Generation, \nLLC"},{"page":20,"startToken":5719,"endToken":5776,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, D.C. this 21 day of August 2026. \n/s/ \nAlexandra K. Calabro  \nSidley Austin LLP \n1501 K Street, N.W. \nWashington, DC 20005"},{"page":21,"startToken":5776,"endToken":5778,"text":"Appendix A"},{"page":22,"startToken":5778,"endToken":6038,"text":"UNITED STATES OF AMERICA \nBEFORE \nTHE FEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \n) \n) \nDocket No. ER26-3380-000 \n \nAFFIDAVIT OF ROY J. SHANKER, PH.D., IN SUPPORT OF \nCONSTELLATION ENERGY GENERATION, LLC’S \nLIMITED PROTEST \nI. \nQualifications and Purpose of Affidavit \n1. \nMy name is Roy J. Shanker.  My address is P.O. Box 1480, Pebble Beach, \nCalifornia, 93953.  I have a bachelor’s degree from Swarthmore College and both a master’s \ndegree and a doctorate degree from Carnegie Mellon University. \n2. \nMy resume, Attachment A hereto, summarizes my experience in numerous \nregulatory proceedings before state commissions and the Federal Energy Regulatory Commission \n(“FERC” or “Commission”). As detailed therein, I have over 50 years of experience covering a \nbroad range of issues in the electric utility/power generation/energy sectors for a broad range of \nclients. I have been involved in competitive market design for approximately 30 years, and \nspecifically for PJM from the inception of the market. I contributed to some of the fundamental \ndesign elements for the capacity market and its evolution over the years. \n3. \nThe purpose of my affidavit is to assist the Commission with its decision-making \nprocess as it evaluates PJM’s proposal in this docket as filed on July 31, 2026.1 I specifically \naddress the interaction of the Reliability Backstop Procurement (“RBP”) and the subsequent offer \nrequirements proposed for such capacity in future Reliability Planning Model (“RPM”) auctions. \n \n1  PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (the “PJM Proposal”)."},{"page":23,"startToken":6038,"endToken":6352,"text":"2 \nI was retained by Constellation Energy Generation, LLC to offer an independent opinion \nregarding these issues. \nII. \nBackground \n4. \nIn May of this year PJM released a white paper entitled Powering Reliability \nThrough Market Design.2  In this paper PJM candidly discussed what it calls the “credibility trap” \n– the idea that properly functioning markets need to be able to signal scarcity, but investors have \nlittle confidence that the market will actually produce the appropriate price signal due to political \ninterference.  As PJM noted: \nThe result is what might be called a credibility trap: high scarcity prices that are \neconomically necessary to signal the need for investment become, in this \nenvironment, the trigger for governmental intervention that undermines the \ncredibility of those same prices. When prices spike and unhedged load is \nimmediately exposed, policymakers face intense pressure to intervene through \nprice caps, emergency backstop procurements, or other administrative actions that \nsignal to investors that the revenue they are counting on to recover their costs may \nnot materialize. Investors, anticipating further intervention, discount the durability \nof the price signal. Capital stays on the sidelines; the shortage persists.3 \n5. \nThis concern is more relevant than ever.  PJM’s recently concluded Base Residual \nAuction (“BRA”) for the 2028/29 Delivery Year cleared over approximately 6.8 GW (6,831.3 \nMW)4 short of the reliability requirement.  The BRA for the 2027/28 Delivery Year, conducted \nlast year, cleared similarly short.  These unprecedented shortfalls are a clear signal of scarcity, \nthough market clearing prices have been administratively capped at well below the price needed \n \n2  PJM Interconnection, L.L.C., Powering Reliability Through Market Design: Addressing Rising Demand and \nConstrained Supply, and Stimulating Investment to Support Durable Reliability (May 6, 2026), \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-\nthrough-market-design.pdf (“PJM White Paper”). \n3  Id. at 5–6. \n4  PJM Proposal at 7."},{"page":24,"startToken":6352,"endToken":6710,"text":"3 \nto attract new supply.  PJM itself recognizes the conflict between capped prices and encouraging \nnew market entry for capacity.5  Meanwhile, the problem only appears to be getting worse.  PJM \nestimates 32 GW (virtually all attributable to large loads) of growth in peak load from 2024 to \n2030, and supply, at least to date, has failed to keep up.6 \n6. \nAgainst this backdrop, in this proceeding PJM has proposed a one-time,7 out-of-\nmarket intervention, the RBP, which aims to procure new capacity to fill the gap as established by \nthe 2028/29 BRA.  Capacity procured through the RBP auction would assume a long-term capacity \nobligation for a term of up to 15 years at a “pay-as-bid” price.8 \n7. \nWhile the RBP proposal is complex and has many different features worth \ndiscussing, I focus my affidavit chiefly on one element of the proposal: the requirement that all \ncapacity resources committed through the RBP central procurement must offer that capacity into \nfuture RPM Auctions at a $0/MW-day price for the entire term of the RBP commitment (i.e., up \nto 15 years).9  Getting this aspect of the proposal right is critical to address the “credibility trap” \nproblem PJM has correctly identified and to promote resource adequacy both near- and long-term. \nIt is a vital element to PJM’s self-proclaimed intent of returning to a market-based paradigm.10 \nIII. \nPJM Must Isolate the Impact of the RBP Central Procurement \n8. \nFor all its faults and imperfections, RPM has delivered on its central mission—\nresource adequacy.  But now, facing some of the most difficult challenges in its history, the future \n \n5  PJM White Paper at 5–6, 26. \n6  PJM Proposal at 6. \n7  Id. at 6–7. \n8  Id. at 7–8, 42. \n9  Id. at attach. A § 6.6(j) (“An RBP Resource committed through the Reliability Backstop Procurement must offer \nall available committed RBP UCAP MW as a price-taker (i.e., $0/MW-day) into the applicable RPM Auctions \npursuant to the capacity must offer requirements and exceptions set forth in Tariff, Attachment DD, sections 6.6 and \n6.6A.”). \n10  PJM Proposal at 6."},{"page":25,"startToken":6710,"endToken":7009,"text":"4 \nof RPM is at stake.  The RBP represents a point of inflection that may determine the success or \nfailure of PJM’s resource adequacy construct going forward. \n9. \nWhile PJM has correctly identified the “credibility trap” issue, the RBP proposal \ndoes not inspire confidence that PJM is ready and able to tackle the problem and escape the trap.  \nIndeed, the representation of new supply from the RBP as “price takers” in RPM is one of the most \nsignificant and farthest-reaching of any market intervention by PJM to date.  As proposed, this \nprice-taking offer requirement will have a material, one-sided bias to reduce future capacity prices \nbelow the necessary levels required to attract new entry and retain needed existing supply. This \ntype of market intervention will further damage confidence in the robustness of RPM going \nforward, limiting its ability to attract and retain the supply needed to reliably serve PJM’s rapidly \nexpanding load. It would be the antithesis of “returning PJM to market fundamentals.” \n10. \nThe current challenge facing PJM and its stakeholders is twofold: First, how do we \nmaintain reliability when facing a perceived supply shortage? And second, how do we preserve a \nviable competitive market for Capacity Resources? \n11. \nAs I note above PJM’s proposed RBP will fail to achieve these objectives.  PJM’s \nproposal, if left unchanged, (a) will drive near-term exit of resources that will be needed if load \ngrowth materializes and (b) would be a one-sided intervention that depresses the market below \nwhere it would otherwise clear under a competitive outcome, further entrenching the “credibility \ntrap” problem and leading to stagnation, shortfall, and ultimately market failure. \n12. \nI propose, below, a change to the RBP design to reduce its impact on the broader \ncompetitive capacity market structure, thereby preserving proper investment signals and ultimately \nresource adequacy."},{"page":26,"startToken":7009,"endToken":7248,"text":"5 \n13. \nThe key problem with PJM’s proposal is best illustrated with an example.  Assume \nthe RBP procures approximately 6,800 MW of new capacity.  Under PJM’s proposal this capacity \nwould then be required to offer into RPM Auctions for the entire RBP commitment period at a \nprice of $0/MW-day.  But now assume that only 3,000 MW of RBP-related load materializes on \nschedule as forecasted. \nFigure 1. \n \n14. \nAs shown in Figure 1, the addition of the full 6.8 GW of supply at $0, combined \nwith a demand curve only reflecting a portion (3 GW) of the previously expected load, results in \na material surplus of supply.  The resulting price signal will indicate to investors that there is no \nneed for new entry, and, in fact, that many existing resources should retire or seek other markets.  \nFurther investment in new resources will be chilled, and many aging thermal capacity resources \nare likely to exit the market. \n15. \nClearly that is not the right price signal.  If the rest of that originally-expected load \nlater materializes, the market will be even worse off than it is today.  The market will be short \nbecause the low prices encouraged additional existing resources to exit while also not supporting \nnew entry. This scenario is represented below in Figure 2, where the expected load eventually \narrives, but supply is deficient due to the increase in exits and inadequate new entry. The result,"},{"page":27,"startToken":7248,"endToken":7504,"text":"6 \nbased on recent behavior, is that PJM is likely to once again face political pressure to intervene \nadministratively to maintain reliability.  And developers of new capacity will build the expectation \nof future interventions into their decision-making framework.  Investment will be further chilled \nby repeated market intervention, and the “credibility trap” cycle will continue. \nFigure 2. \n \n16. \nThis risk of load delay is not merely hypothetical.  We have already seen real-life \nexamples of forecasted data center load failing to materialize as scheduled.11  Goldman Sachs \nResearch reports that despite surging AI-driven demand, grid constraints and project attrition mean \nthat only 50% to 72% of planned U.S. data center capacity will likely materialize on time.12 There \nis no reason to assume that such delays will not persist over the next few years at least. \n17. \nThis reality underscores the need to consider the impact of the RBP on the \ncompetitive capacity market’s clearing mechanism going forward.  The basic link between the \nRBP capacity and the competitive market is that (i) the targeted out-of-market RBP procurement \n \n11  ERCOT has reported approximately 8,900 MW of large load approved for energization, of which more than \n5,000 MW had not yet energized.  Electric Reliability Council of Texas, Large Load Interconnection Status Update, \nLarge Load Integration Team 8–9 (June 19, 2026), https://www.ercot.com/files/docs/2026/06/18/June-19-LLWG-\nReport.pptx.   \n12  See US Data Center Power Demand Projected to Double by 2027, Goldman Sachs (May 20, 2026), \nhttps://www.goldmansachs.com/insights/articles/us-data-center-power-demand-projected-to-double-by-2027."},{"page":28,"startToken":7504,"endToken":7853,"text":"7 \nquantity is fixed, (ii) this quantity remains fixed regardless of whether or not and when the forecast \ndemand is realized, and (iii) as proposed, subsequently, that RBP capacity quantity will be entered \ninto the competitive RPM process as price takers regardless of the level of load. \n18. \nNotably, PJM has indicated via its August 13, 2026 IRAS Filing that it will exclude \nthe representation of new large loads in the RPM demand curve in the future unless and until such \nloads bring their own new capacity supply or an allocated portion of the RBP supply.13 \n19. \nWhile the purpose of this Affidavit is not to address the IRAS Filing, and I take no \nposition here on the IRAS Filing generally, this aspect of PJM’s IRAS proposal is worth \nhighlighting given how it informs elements within the RBP proposal. \n20. \nIn the RBP filing PJM proposes that all RBP supply be represented as price takers \nin RPM Auctions. It ignores whether the underlying load is realized or not or when it is realized. \nThus, RBP supply can exceed the linked demand and lower market prices for other existing supply \nvia the out-of-market actions. \n21. \nWhile PJM includes RBP generation regardless of whether the associated load is \nrealized in the capacity auction, it takes the opposite approach with respect to when it includes \nnew large load in the capacity auction in the IRAS proposal.  Specifically, in the IRAS proposal, \nPJM only includes new large load in the capacity auction when it can be offset by either new \ngeneration (BYONC) or an allocation of RBP capacity. In other words, PJM only includes this \nbalanced amount of New Large Load and generation (which may be partially made up of RBP \ngeneration) in the RPM auctions. Any additional load is not represented in these auctions. This is \n \n13  See PJM Proposal at n.9; see also PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to \nEstablish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. \nER26-3515-000 (filed Aug. 13, 2026) (“IRAS Filing”)."},{"page":29,"startToken":7853,"endToken":8173,"text":"8 \ndone, as PJM states to “prevent[s] artificial price shifts, [thus] resulting in an effectively price-\nneutral outcome for the rest of the market.”14 \n22. \nPJM ignores that its logic in the IRAS Filing must mean there can, at times, be \nunrealized (delayed or cancelled) load. This will result in “extra” RBP generation, which, in turn, \nwill depress prices due to the “artificial shifts.” This outcome occurs whenever the RBP load has \nnot yet arrived or is delayed. When this happens the excess RBP supply will depress RPM prices \nand will not be price neutral for the existing market supply. Out-of-market actions will distort \nprices and exacerbate the “credibility trap” in just the manner that PJM has so well described.  \n23. \nDespite this rationale in the IRAS filing, and without any explanation or mitigation, \nPJM is apparently satisfied in the instant filing to require all RBP capacity to offer into RPM as \nprice takers, with no guarantee that the forecasted load forming the basis for the procurement will \nactually materialize as scheduled. \nIV. \nRecommendation \n24. \nThe preferred approach for any market design would be to adopt a design that works \nwithout the need for ad-hoc interventions and stick with that design—both when prices rise and \nwhen they fall.  The dislocation caused by the combination of large new loads, regulatory and \npolitical intervention, and the continued erosion of true market-based pricing makes that solution \nvery unlikely. But if PJM must intervene now with an ad-hoc intervention such as the RBP out-\nof-market procurement, a top priority of the intervention should be to preserve resource adequacy \nby maintaining the competitive integrity of the overall market going forward to the greatest extent \npossible.  Without that focus it is very likely that PJM will see increased exits of existing resources \n(which will only exacerbate resource adequacy issues in the region) and be right back at the \n \n14  IRAS Filing at 58."},{"page":30,"startToken":8173,"endToken":8504,"text":"9 \ndrawing board in a few short years, and even sooner if the RBP does not clear the needed quantity \nof capacity. \n25. \nTo that end, my recommendation is to modify the RBP proposal to include a \nmechanism that will appropriately isolate the effect of the RBP and maintain appropriate \ninvestment signals for the remainder of the capacity market.  There is a very simple way to \naccomplish this objective. Rather than requiring all RBP supply to offer into RPM at $0/MW-day, \nPJM should remove all RBP supply and RBP-related demand from the RPM Auctions going \nforward.  Specifically, PJM should exclude from RPM Auctions both (a) the cleared RBP capacity \nand (b) the lower of (i) the actual large load that is in the applicable auction Planning Parameters \nand (ii) an amount of load equal to the RBP generation. \n26. \nThis representation is as neutral as possible with respect to price formation for the \n“rest” of the market, and allows PJM to return to market fundamentals, market-based procurement, \nand rates and avoid unnecessary exits of existing resources. With this adjustment in place the rest \nof the market sees the “right” representation of supply and demand. And in this manner the market \ncan adjust going forward independently of PJM’s “one-time” RBP purchases. In turn, regardless \nof the rate of arrival of the 6,800 MW of demand (the forecasted deficiency), there will be no price \ndistortion for the rest of the market. The RBP capacity will operate as intended, as a separate out-\nof-market procurement to assure reliability.  \n27. \nWhen seen in light of PJM’s removal of future large loads, my recommendation to \nsimply remove both the RBP supply and the lower of (i) the actual large load that is in the \napplicable auction Planning Parameters and (ii) an amount of load equal to the RBP generation \nbecomes almost obvious in terms of logical consistency. Failing to make the adjustment discussed \nherein leaves the PJM proposal fundamentally discriminatory against existing suppliers who"},{"page":31,"startToken":8504,"endToken":8842,"text":"10 \nwill face the distorted market signal when the RBP deficiency load either is delayed or fails to \narrive completely. \n28. \nIn this context it is illogical to not remove all out-of-market RBP supply and \nthe associated demand. Doing so removes the asymmetry and any associated price distortion. \nWith this proposal the RBP procurement exists and continues to address reliability. But my \nrecommended adjustment prevents delays in the arrival of the forecast demand or the failure of the \nforecast demand (the 6,800 MW) to enter at all from artificially shifting prices. The rest of the \nmarket therefore sees accurate price signals. \n29. \nIt is important to understand that this must be achieved by isolating this RBP load \nand generation. This is because the RBP generation is not readily divisible, e.g. it cannot be \nreasonably pro-rated for participation vis-a-vis any specific load. It must be either in or out. There \nis not a simple way to pro-rate a half of such a unit’s participation in the context of varying levels \nof realized load. Thus, the correct approach is to simply remove both the out-of-market supply and \nthe realized portion of the load it was intended to serve. Modifying the demand curve by the same \n(reliability adjusted) amount in either direction does not distort prices. There is no reason to retain \nthe one-way bias that PJM has built into the representation of the RBP supply when the bias and \nprice distortion can be so easily fixed. \n30. \nAs a practical matter my recommendation is very simple to implement. PJM will \nhave to clearly identify the supply identified in the RBP procurement in the very near future. PJM \nwill also be tracking the actual realization of the 6,800 MW deficiency. This direct empirical \ninformation is easily represented in RPM Auction parameters and offering generation. The new \nlarge load registry PJM is instituting in the IRAS Filing has exactly the detailed information to \naccomplish this objective. Similarly, via the criteria for the submission of the RBP for sale, PJM’s"},{"page":32,"startToken":8842,"endToken":8915,"text":"11 \nproposal elicits all the necessary information to identify and remove the RBP supply from the RPM \nAuctions.  \n31. \nSimilarly, my proposal stands independent of any other details of the operation of \nthe RBP procurement process, either as proposed or as potentially modified. If there is to be such \na procurement, this type of isolation is necessary to protect the markets and stands independently \nas a required feature. \n32. \nThis concludes my affidavit."},{"page":33,"startToken":8915,"endToken":8915,"text":""},{"page":34,"startToken":8915,"endToken":8915,"text":""},{"page":35,"startToken":8915,"endToken":9057,"text":"Roy J. Shanker  \n \nPage 1 \n \n \n \n \n \n \n \nAttachment A \n \n \n \nQUALIFICATIONS \nAND  \nEXPERIENCE OF \n \nDR. ROY J. SHANKER \n \n \n \nEDUCATION: \n \nSwarthmore College, Swarthmore, PA  \nA.B., Physics, 1970 \n \nCarnegie-Mellon University, Pittsburgh, PA \nGraduate School of Industrial Administration  \nMSIA Industrial Administration, 1972 \nPh.D., Industrial Administration, 1975 \n           \nDoctoral research in the development of new non-parametric multivariate \ntechniques for data analysis, with applications in business, marketing and \nfinance.  \n \nEXPERIENCE: \n \n1981 -         \nIndependent Consultant \nPresent        \nP.O. Box 1480 \n \n \nPebble Beach, CA 93953 \n \nProviding management and economic consulting services in \nnatural resource-related industries, primarily electric \nand natural gas utilities. \n \n1979-81        Hagler, Bailly & Company \n               \n2301 M Street, N.W. \n               \nWashington, D.C. \n           \nPrincipal and a founding partner of the firm; director of electric utility \npractice area.  The firm conducted economic, financial, and technical \nmanagement consulting analyses in the natural resource area. \n \n1976-79        Resource Planning Associates, Inc. \n               \n1901 L Street, N.W."},{"page":36,"startToken":9057,"endToken":9325,"text":"Roy J. Shanker \nPage 2 \n               \nWashington, D.C. \n           \nPrincipal of the firm; management consultant on resource problems, \ndirector of the Washington, D.C. utility practice.  Direct supervisor of \napproximately 20 people. \n \n1973-76        Institute for Defense Analysis \n               \nProfessional Staff \n               \n400 Army-Navy Drive \n               \nArlington, VA \n           \n           \nMember of 25 person doctoral level research staff \n           \nconducting economic and operations research analyses of military and \nresource problems. \n \n \nRELEVANT EXPERIENCE: \n2025 \n \n271—On behalf of Vistra Corporation. Before the Federal Energy \nRegulatory Commission Docket EL25-49-000. Affidavit addressing \nproperties of co-location of generation and new load and the proper \ncomparison of the impacts of such arrangements versus behind the meter \ngeneration of in general, Network Load.  \n2024  \n \n270—On behalf of PJM Power Providers. EL24-148-000.  Testimony \nregarding reliability must run designation and price formation for energy \nand capacity in the context of the development of the PJM Reliability \nPricing Model.  \n \n269—On behalf of Constellation Energy Generation LLC, Before the \nFederal Energy Regulatory Commission Dockets No. ER24-2172-000 \nAffidavit addressing the proper comparison of impacts of co-located load \nbehind a generator to Network Load or behind the meter generation in the \nPJM Interconnection markets. Conclusions addressing the specific \nbusiness configuration of interest. \n \n268—On behalf of Constellation Energy Generation LLC, Before the \nFederal Energy Regulatory Commission Dockets No. El24-2888 et al. \nAffidavit addressing the proper comparison of impacts of co-located load \nbehind a generator to Network Load or behind the meter generation in the \nPJM Interconnection markets. Conclusions addressing the specific \nbusiness configuration of interest.  \n267—On behalf of Kiewit Power Constructors. AAA CASE NO. 01-23-\n0000-2706. Analyses of the proper comparison of alternatives to estimate"},{"page":37,"startToken":9325,"endToken":9590,"text":"Roy J. Shanker \nPage 3 \ndamages related to the performance of an electric generator during Winter \nStorm Elliott.   \n \n \n2023 \n \n266—On behalf of the PJM Power Providers. Before the Federal Energy \nRegulatory Commission. Docket No. EL 23-19-000 and Docket ER23-729 \nAffidavit regarding the calculation of the Capacity Emergency Transfer \nObjective and model properties and how they interact with the Reliability \nRequirements for a Locational Deliverability Area. Explanation of the role \nof offer options in degrading information in the Capacity Auctions.  \n \n265—On Dr. Shanker’s own behalf. Before the Federal Energy \nRegulatory Commission, Docket EL23-13. Answer ing statements to \nintervenors regarding Dr. Shanker’s complaint.  \n \n2022 \n \n264—On Dr. Shanker’s own behalf. Before the Federal Energy \nRegulatory Commission, Docket EL23-13. An FPA Section 206 complaint \nfor violating its Tariff via over accreditation of certain Variable Capacity \nResoruces.  \n \n263—On Dr. Shanker’s own behalf. Before the Federal Energy \nRegulatory Commission, Docket RM22-14. Comments and reply \ncomments regarding the Notice of Proposed Rulemaking Improvements to \nGenerator Interconnection Procedures and Agreements. \n \n \n262—On behalf of the Energy Trading Institute. Before the Federal \nEnergy Regulatory Commission, Docket No. ER22-797. Affidavit in \nsupport of PJM LLC proposals for modifications to the Auction Revenue \nRights/Financial Transmission Rights Market. Preparation of extensive \ngeneral regulatory and PJM history regarding the formation of such rights \nover time.  \n2021 \n \n261—On behalf of the PJM Power Producers Group (P3) before the \nFederal Energy Regulatory Commission Docket No. ER21-2582-000. \nAffidavit addressing PJM’s proposed modification of the Minimum Offer \nPrice Rule and problems related to the economic justification of the \nproposed narrowing of the applicability of the rule."},{"page":38,"startToken":9590,"endToken":9921,"text":"Roy J. Shanker \nPage 4 \n260—On behalf of LS Power Associates L.P. before the Federal Energy \nRegulatory Commission Docket No. ER21-2043. Affidavit discussing \nPJM’s revised Effective Load Carrying Capability proposal, its limitations \nand associated PJM responses to previous comments regarding its initial \nproposal.  \n \n259—On behalf of Indicated Suppliers before the Federal Energy \nRegulatory Commission in Dockets No. EL19-47-000 and EL19-63-000 \ncomments regarding the PJM proposed modification to its Market Seller \nOffer Cap in the Reliability Planning Model Base Residual Auction for \nCapacity Resources.  \n \n258—Written post conference comments in Federal Energy Commission \nDocket No. AD21-10. Discussion of the appropriate scope and range of \nactions for the Commission with respect to the PJM Minimun Offer Price \nRate. Similar considerations of the legal scope of the Commission under \nthe Federal Power Act.  \n \n257—Invited Speaker before the Federal Energy Energy Regulatory \nCommission Docket No. AD21-10. Comments before the Commissioners \nrelated to the role of subsidies and their impact in terms of the \ndetermination of satisfaction of just and reasonable rates under the Federal \nPower Act.  \n \n256—On behalf of LS Power Associates L.P. before the Federal Enegy \nRegulatory Commission Docket No. ER21-278-001. Affidavit discussing \nPJM’s Effective Load Carrying Capability proposal, its limitations and \nassociated PJM responses to the Commission’s deficiency notice.  \n \n2020 \n \n256—On behalf of Cricket Valley Energy Center and Empire Generating \nCompany before the Federal Energy Commission Docket EL21-7. \nAffidavit addressing the appropriate design of offer price floors in the \nNYISO Capacity market and associated mitigation and extension of the \nrelated rules to the entire state.  \n \n255—Invited speaker and written submission before the Federal Energy \nRegulatory Commission Docket AD20-14. Comments about the legal \nissues under the Federal Power Act relevant to the implementation of \ncarbon pricing within the wholesale regional transmission organizations.  \n \n254—On behalf of Shell Energy North America before the Federal Energy \nRegulatory Commission, Docket EL20-49. Affidavit addressing bilateral \ntrading of FTRs, associated agreements and the interaction with PJM’s \nFTR Center reporting and Tariff."},{"page":39,"startToken":9921,"endToken":10234,"text":"Roy J. Shanker \nPage 5 \n \n2019  \n \n253—On behalf of White Oak Power Constructors before the United \nStates District Court for the Eastern District of Virginia (Richmond \nDivision). Expert report on proper calculation of damages and costs \nassociated with the delay in commercial operations of a new electric \npower generation facility.  \n \n252—On behalf of the Public Service Companies before the Federal \nEnergy Regulatory Commission, Docket ER19-1486. Affidavit regarding \nthe PJM proposed operating reserve demand curve and other \nmodifications to the reserve products market. Comments on missing \nelements within the proposal.  \n \n251—On behalf of  Indicated Parties, (Calpine, Vestra, and Electric Power \nSupply Association) before the Federal Energy Regulatory Commission. \nDocket EL19-63. Affidavit regarding the complaint of the Joint Consumer \nAdvocates regarding PJM’s market seller offer cap, the potential exercise \nof market power in the capacity market and appropriate market design \nadjustments under the Capacity Performance paradigm.  \n \n250—On behalf of  Indicated Parties, (Calpine, Vestra, and Electric Power \nSupply Association) before the Federal Energy Regulatory Commission. \nDocket EL19-47. Affidavit regarding the appropriate adjustment of \npenalties and the Market Seller Offer Cap within the PJM Capacity \nPerformance paradigm.  \n \n249—Supreme Court of the United States. Brief of Energy Economists as \nAmici Curiae in Support Of Petitioners, Nos. 18-868 & 18-879. \nDiscussion of the impact of subsidies in electric energy market structures \nand the relationship of the instant cases where a Writ of Certiorari is being \nsought to previous Supreme Court precedent regarding state actions that \neffect Federal Energy Regulatory Commission jurisdictional rates.  \n \n2018 \n \n248—On behalf of PJM Power Providers (P3). Federal Energy Regulatory \nCommission. Docket EL18-178. Affidavit addressing the appropriate \nmechanisms to address state/public policy subsidies in the PJM Reliability \nPlanning Model capacity construct. Related comments with respect to a \n“Clean” Minimum Price Offer Rule.  \n \n247—On behalf of Calpine Corporation, Eastern Generating and CPV \nPower Holdings. Federal Energy Regulatory Commission. Docket No."},{"page":40,"startToken":10234,"endToken":10543,"text":"Roy J. Shanker \nPage 6 \nEL18-169. Affidavit addressing the the establishment of a “clean” \nMinimum Offer Price Rule for capacity offers in the PJM markets.  \n \n246—On behalf of DC Energy LLC and Vitol Inc. Federal Energy \nRegulatory Commission. Docket No. ER18-1334. Affidavit on the CAISO \nproposals to limit source and sink pairs in its annual and monthly CRR \nauctions, as well as comments addressing appropriate coordination of \ntransmission outage and constraint information.  \n \n245—On behalf of the PJM Power Providers. Federal Energy Regulatory \nCommission Docket No. ER18-1314-000. Affidavit on the PJM proposed \nmitigation alternatives for addressing out of market subsidies either by \nRepricing or a modified Minimum Offer Price Rule.  \n \n244—On behalf of Joint Commentors. Federal Energy Regulatory \nCommission Docket EL18-34. Participation in the preparation of \ncomments addressing PJM’s proposed fast start pricing modifications and \nrelated price formation issues.  \n \n243—On behalf of the PJM Power Providers Group. Federal Energy \nRegulatory Commission Dockets EL17-32 and EL17-36. Pre-Technical \nConference Comments and participant technical conference regarding \nseasonal capacity products and specific related reliability and forecasting \nquestions from Commission Staff. \n \n(2018) Non-public reports regarding potential market manipulation within \nISO NE markets.  \n \n2017 \n \n242—On behalf of the PSEG Companies. Federal Energy Regulatory \nCommission Docket No. ER13-535-000. Affidavit regarding \nimplementation of Court of Appeals remand to FERC of the PJM capacity \nmarket Minimum Offer Price Rule.  \n241-- In the United States Court of Appeals for the Second Circuit. Case \nNo. 17-2654.Co-writer/sponsor of the Brief of Energy Economists as \nAmici Curiae in Support of Plaintiffs-Appealants-Reversal. Comments \nregarding the impacts of subsidies on the operation of organized electric \nmarkets. \n \n240—In the United States Court of Appeals for the Seventh Circuit. No. \n17-2433.Co-writer/sponsor of the Brief of Energy Economists as Amici  \nCuriae in Support of Plaintiffs-Appealants. Comments regarding the \nimpacts of subsidies on the operation of organized electric markets."},{"page":41,"startToken":10543,"endToken":10805,"text":"Roy J. Shanker \nPage 7 \n239—Invited speaker Federal Energy Regulatory Commission technical \nsession, Docket AD17-11. Comments on the appropriate incorporation of \nstate policies in wholesale electric markets. Submission of post technical \nsession comments.  \n \n238—On behalf of PJM Power Providers. Federal Energy Regulatory \nCommission Dockets EL17-36 and EL17-32  addressing the current \nCapacity Performance design and criticisms related to the exclusion of \nan inferior seasonal capacity product. Explanation of how PJM \nestablishes its adequacy targets and whether or not the asserted \ncriticisms were valid. \n \n2016 \n \n237- On behalf of DC Energy, Vitol, Intertia Power, Saracen Energy East. \nFederal Energy Regulatory Commission Dockets EL16-6, ER16-121. \nSubmission of post technical session statement regarding PJM FTR \nmarket “netting” proposal. \n \n236-On behalf of DC Energy, Vitol, Intertia Power, Saracen Energy East. \nFederal Energy Regulatory Commission Dockets EL16-6, ER16-121. \nParticipant in two Technical Session Panels addressing PJM FTR market \ndesign and deficiency in the pending proposal to remove netting in the \nmarket settlement.  \n \n2015  \n \n235- On behalf of the Electric Power Supply Associaton. Federal Energy \nRegulatory Commission Dockets EL15-70, 71, 72, 82. Affidavit regarding \nMISO capacity market design and also addressing use of opportunity costs \nin offers. \n \n234-On behalf of the Electric Power Supply Associaton. Federal Energy \nRegulatory Commission Dockets EL15-70, 71, 72, 82. Discussant in \ntechnical session addressing the establishment of opportunity costs as the \nbasis for capacity reference pricing in the MISO Planning Resource \nAuctions. \n \n233-On behalf of Dominion Virginia Power. Federal Energy Regulatory \nCommission Docket ER15-1966. Affidavit regarding changing economic \nincentives for suppliers associated with the modification of PJM’s \ncalculation of Lost Opportunity Costs."},{"page":42,"startToken":10805,"endToken":11126,"text":"Roy J. Shanker \nPage 8 \n232-On behalf of “Indicated Suppliers” Federal Energy Regulatory \nCommission Docket No. EL15-64-000. Testimony addressing the \nappropriateness of proposed changes to the NYISO buyer side mitigation \nexemptions.  \n \n231-On behalf of Hydro Quebec, Energy Services U.S. Federal Energy \nRegulatory Commission Docket No. ER15-623. Affidavit addressing the \nconsistent treatment of energy imports under PJM’s Capacity Performance \nproposal.  \n \n230-Before the Supreme Court of the United States, No. 14-995, On \nPetition for a Writ of Certiorari to the United States Court of Appeals for \nthe Third Circuit. Brief of electrical engineers, scientists and economists \nas amici curiae in support of petitioners. Metropolitan Edison et al. versus \nPennsylvania Public Utility Commission et al., http://www.americanbar.\norg/content/dam/aba/publications/supreme_court_preview/briefs_2015_20\n16/14-840_Borlick_et_al.pdf. \n \n2014 \n \n229-On behalf of Benton County Wind Farm. United States District Court \nSouthern District of Indiana, Indianapolis Division, Civil Action No. 1:13-\ncv-1984-SEB-TAB. Expert Reports addressing custom and practice in \nelectric power purchase agreements. \n \n228-On behalf of FirstEnergy Services. FERC Docket EL14-55. Affidavit \nrelated to the appropriate characterization of Demand Response in \nCapacity Markets reflecting performance as the reduction of retail energy \nconsumption.  \n \n227-Federal Energy Regulatory Commission. Docket RM10-17. On my \nown behalf, a statement regarding the ability of the PJM capacity and \nenergy markets to clear in the transition from any determination that \ndemand response would be excluded jurisdictionally from wholesale \nmarkets. This could in turn result in a more appropriate representation of \nretail demand response.  \n \n226-Illinois Commerce Commission. Matter: No. 13-0657. On behalf of \nCommonwealth Edison Company. Testimony regarding the operation of \nthe PJM regional transmission expansion planning process in general and \nparticularly with regards to the preservation of long-term transmission \nrights (Stage 1A Auction Revenue Rights), and the consequences that \noccur when such mandated rights are infeasible.  \n \n225-Federal Energy Regulatory Commission. Docket ER14-1579. On \nbehalf of H-P Energy. Affidavit explaining importance of property rights"},{"page":43,"startToken":11126,"endToken":11412,"text":"Roy J. Shanker \nPage 9 \nand associated contracts within the PJM transmission planning process, \nparticularly as they pertain to Upgrade Construction Service Agreements.  \n \n2013 \n \n224-Federal Energy Regulatory Commission. Docket No. ER14-456. On \nbehalf of NextEra Energy to analyze a proposed modification to the PJM \nTariff allowing for “easily resolved constraints” to be address by \ntransmission upgrades without any analyses of benefits.  \n \n223-Federal Energy Regulatory Commission. Docket No. ER14-504. \nAffidavit on behalf of PJM Power Producers addressing the interaction \nbetween the PJM adequacy planning processes and the formulation of \nsaturation constraints on Limited and Extended Summer Demand \nResponse products. \n \n222-Federal Energy Regulatory Commission. Docket AD13-7. Invited \nspeaker on the Commission’s technical session regarding capacity markets \nin RTO’s. Comments addressed basic principles of market design, market \nfeatures, and consequences of market failures and deviations from design \nprinciples.  \n \n221-Federal Energy Regulatory Commission. Docket No. EL13-62 on \nbehalf of TC Ravenswood LLC. Two affidavits addressing the treatment \nof reliability support services agreements and associated capacity in the \nNYISO capacity market design.  \n \n2012 \n \n220-Federal Energy Regulatory Commission. Docket No. ER12-715-003. \nOn behalf of First Energy Services Company. An affidavit and testimony \naddressing the appropriateness of the application of a proposed new MISO \ntariff provision after the fact to a withdrawing MISO member.  \n \n219-Federal Energy Regulatory Commission. Docket ER13-335. On \nbehalf of Hydro Quebec U.S. Affidavit addressing appropriate application \nof ISO-NE Market Rule 1/ Tariff with respect to the qualification of  new \nexternal capacity to participate in the Forward Capacity Market. \n \n218-Federal Energy Regulatory Commission. Docket IN12-4. On behalf \nof Deutsche Bank Energy Trading. Affidavit regarding a review of \nspecific transactions, related congestion revenue rights, and deficiencies in \nCAISO tariff implementation during periods when market software \nproduces multiple feasible pricing solutions."},{"page":44,"startToken":11412,"endToken":11723,"text":"Roy J. Shanker \nPage 10 \n217-Federal Energy Regulatory Commission. Docket No. ER12-715-003. \nOn behalf of FirstEnergy Services Company.  Affidavit regarding \nimplementation of the MISO Tariff with respect to the determination of \nappropriate exit fees and charges related to certain transmission facilities.  \n \n216-Federal Energy Regulatory Commission. Docket No. IN12-11. On \nbehalf of Rumford Paper Company. Affidavit regarding free riding \nbehavior in the design of demand response programs, and its relationship \nto accusations of market manipulation.  \n \n215-Federal Energy Regulatory Commission. Docket No. IN12-10. On \nbehalf of Lincoln Paper and Tissue LLC. Affidavit regarding relationship \nof demand response behavior and value established in Order 745 to \nclaimed market impacts associated with accusations of market \nmanipulation.  \n \n214-Federal Energy Regulatory Commission. Docket No. AD12-16-000. \nOn behalf of PJM Power Providers, testimony regarding deliverability of \ncapacity between the MISO and PJM RTO’s and associated basic \nadequacy planning concepts. \n \n213-United States Court Of Appeals, District of Columbia Circuit. Electric \nPower Supply Asociation, et al (Petitioners) v. Federal Energy Regulatory \nCommission et al (Respondents) Nos. 11-1486. Amici Curiae brief \nregarding the appropriate pricing of demand reduction services in \nwholesale markets vis a vis the FERC determinations in Order 745.  \n \n212-United States Supreme Court. Metropolitan Edison Company and \nPennsyvalnia electric Company (Petitioners), Pennsylvania Public Utility \nCommission (Respondent) (No. 12-4) Amici Curiae brief regarding the \nnature of physical losses in electric transmission and relationship to proper \nmarginal cost pricing of electric power and the marginal cost of \ntransmission service.  \n \n2011 \n \n211-Federal Energy Regulatory Commission Docket No. ER12-513-000. \nOn behalf of PJM Power Providers, testimony regarding the establishment \nof system wide values for the net cost of new entry related to \nmodifications of the Reliability Planning Model.  \n \n210-Federal Energy Regulatory Commission Docket No. EL11-56-000, on \nbehalf of First Energy Services. Affidavit regarding the appropriateness of \nproposed transmission cost allocation of Multi-Value Projects to an \nexiting member of the Midwest Independent System Operator."},{"page":45,"startToken":11723,"endToken":12030,"text":"Roy J. Shanker \nPage 11 \n209-Federal Energy Regulatory Commission Docket No. ER11-4081-000, \non behalf of “Capacity Suppliers”. Affidavit addressing correct market \ndesign elements for Midwest Independent System Operator proposed \nresource adequacy market. \n \n208-Public Utility Commission of Ohio, Case Nos. 11-346-EL-SSO,11-\n348-EL-SSO,Nos. 11-349-EL-AAM, 11-350-EL-AAM, on behalf of First \nEnergy Services. Testimony regarding the interaction between the \ncapacity default rates for retail access under the PJM Fixed Resource \nRequirement and the PJM Reliability Planning Model valuations.  \n \n207-Federal Energy Regulatory Commission Dockets No. ER11-2875, \nEL11-20, Staff Technical Conference on behalf of PJM Power Providers,  \naddressing self supply and the Fixed Resource Requirement elements of \nPJM’s capacity market design.  \n \n206-New Jersey Board of Public Utilities, Docket Number EO11050309 \non behalf of PSEG Companies. Affidavit addressing the implications of \nmarkets and market design elements, and regulatory actions on the relative \nrisk and trade-offs between capital versus energy intensive generation \ninvestments.  \n \n205-Federal Energy Regulatory Commission Docket No. ER11-2875. \nAffidavit and supplemental statement on behalf of PJM Power Providers \naddressing flaws in the PJM tariff’s Minimum Offer Price Rule regarding \nnew capacity entry and recommendations for tariff revisions.  \n \n204-Federal Energy Regulatory Commission Docket No. EL11-20. \nAffidavit on behalf of PJM Power Providers addressing flaws in the PJM \ntariff’s Minimum Offer Price Rule regarding new capacity entry.  \n \n203-Federal Energy Regulatory Commission  Docket Nos. ER04-449. \nAffidavit and supplemental statement on behalf of New York Suppliers \naddressing the appropriate criteria for the establishment of a new capacity \nzone in the NYISO markets.  \n \n2010 \n \n202-New Jersey State Assembly and Senate. Statements on behalf of the \nCompetitive Supplier Coalition addressing market power and reliability \nimpacts of proposed legislation, Assembly Bill 3442 and Senate Bill 2381. \n \n201-Federal Energy Reglatory Commission. Docket ER11-2183. Affidavit \non behalf of First Energy Services Company addressing default capacity \ncharges for Fixed Resource Requirement participants in the PJM \nReliability Pricing Model capacity market design."},{"page":46,"startToken":12030,"endToken":12344,"text":"Roy J. Shanker \nPage 12 \n \n200-Federal Energy Regulatory Commission. Docket ER11-2059 \nAffidavit on behalf of First Energy Services Company addressing \ndeficiencies and computational problems in the  proposed “exit charges” \nfor transmission owners leaving the MISO RTO related to long term \ntransmission rights.  \n \n199-Federal Energy Regulatory Commission Docket RM10-17. Invited \npanelist addressing metrics for cost effectiveness of demand response and \nassociated cost allocations and implications for monopsony power.  \n \n198-Federal Energy Regualtory Commission Consolidated Dockets ER10-\n787-000, EL10-50-000, and EL10-57-000. Two affidavits on behalf of the \nNew England Power Generators Association regarding ISO-NE modified \nproposals for alternative price rule mitigation and zonal \ndefinitions/functions of locational capacity markets. \n \n197-Federal Energy Regulatory Commission Docket No. ER10-2220-000. \nAffidavit on behalf of the Independent Energy Producers of New York. \nAddressing rest of state mitigation thresholds and procedures for adjusting \nthresholds for frequently mitigated units and reliability must run units.  \n \n196-Federal Energy Regulatory Commission Docket PA10-1. Affidavit on \nbehalf of Entergy Services related to development of security constrained \nunit commitment software and its performance.  \n \n195-Federal Energy Regulatory Commission Docket No. ER09-1063-004. \nTestimony on behalf of the PJM Power Providers Group (P3) regarding \nthe proposed shortage pricing mechanism to be implemented in the PJM \nenergy market. Reply comments related to a similar proposal by the \nindependent market monitor.  \n \n194-PJM RTO. Statement regarding the impact of the exercise of buyer \nmarket power in the PJM RPM/Capacity market. Panel discussant on the \nissue at the associated Long Term Capacity Market Issues Sympossium.  \n \n193-Federal Energy Regulatory Commission Docket No. ER10-787-000. \nAffidavit on behalf of New England Power Generators Association \naddressing proper design of the alternative price rules (APR) for the ISO-\nNE Forward Capacity Auctions. Second affidavit offered in reply. \nSupplemental affidavit also submitted \n \n192-Federal Energy Regulatory Commission Docket No. RM10-17-000. \nAffidavit on behalf of New England Power Generators Association \naddressing proper pricing for demand response compensation in organized \nwholesale regional transmissiom organizations."},{"page":47,"startToken":12344,"endToken":12615,"text":"Roy J. Shanker \nPage 13 \n \n191-Federal Energy Regulatory Commission Docket No. RM10-17-000, \nAffidavit on my on behalf regarding inconsistent representations made \nbetween filings in this docket and contemporaneous materials presented in \nthe PJM stakeholder process.  \n \n2009 \n \n190-Federal Energy Regulatory Commission Docket No. ER09-1682. \nTwo affidavits on behalf of an un-named party regarding confidential \ntreatment of market data coupled with specific market participant bidding, \nand associated issues.  \n \n189-American Arbitration Assoication, Case No. 75-198-Y-00042-09 \nJMLE, on behalf of Rathdrum Power LLC. Report on the operation of \nspecific pricing provision of a tolling power purchase agreement.  \n \n188-Federal Energy Regulatory Commission. Docket No. IN06-3-003. \nAnalyses on behalf of Energy Transfer Partners L.P. regarding trading \nactivity in physical and financial natural gas markets.  \n \n187-Federal Energy Regulatory Commission. Docket No. ER08-1281-\n000. Analyses on behalf of Fortis Energy Trading related to the impacts of \nloop flow on trading activities and pricing.  \n \n186-American Arbitration Association. Report on behalf of PEPCO \nEnergy Services regarding several trading transactions related to the \npurchase and sale of Installed Capacity under the PJM Reliability Pricing \nModel.  \n \n185-Federal Energy Regulatory Commission Docket No. EL-0-47. \nAnalyses on behalf of HQ Energy services (U.S.) regarding pricing and \nsale of energy associated with capacity imports into ISO-NE.  \n \n184-Federal Energy Regulatory Commission Docket No.  ER04-449 019, \nAffidavit on behalf of HQ Energy Services (U.S.) regarding the \nimplementation of the consensus deliverability plan for the NYISO, and \nassociated reliability impacts of imports.  \n \n183-Federal Energy Regulatory Commission Docket ER09-412-000, \nER05-1410-010, EL05-148-010. Affidavit and Reply Affidavit on behalf \nof PSEG Companies addressing proposed changes to the PJM Reliability \nPricing Model and rebuttal related to other parties’ filings.  \n \n2008"},{"page":48,"startToken":12615,"endToken":12896,"text":"Roy J. Shanker \nPage 14 \n182-Pennsylvania Public Service Commission. En Banc Public Hearing on \n\"Current and Future Wholesale Electricity Markets\", comments regarding \nthe design of PJM wholesale market pricing and state restructuring. \n \n181-Maine Public Utility Commission. Docket No. 2008-156. Testimony \non behalf of a consortium of energy producers and suppliers addressing \nthe potential withdrawal of Maine from ISO New England and associated \nmarket and supplier response.  \n \n180-Federal Energy Regulatory Commission. Docket No. EL08-67-000. \nAffidavit on behalf of Duke Energy Ohio and Reliant Energy regarding \ncriticisms of the PJM reliability pricing model (RPM) transitional \nauctions.  \n \n179-Federal Energy Regulatory Commission. Docket AD08-4, on behalf \nof the PJM Power Providers. Statement and participation in technical \nsession regarding the design and operation of capacity markets, the status \nof the PJM RPM market and comments regarding additional market \ndesign proposals.  \n \n178-Federal Energy Regulatory Commission. Docket ER06-456-006, \nTestimony on behalf of East Coast Power and Long Island Power \nAuthority regarding appropriate cost allocation procedures for merchant \ntransmission facilities within PJM.  \n \n2007 \n \n177-FERC Docket No. EL07-39-000. Testimony on behalf of Mirant \nCompanies and Entergy Nuclear Power Marketing regarding the operation \nof the NYISO In-City Capacity market and the associated rules and \nproposed rule modifications.  \n \n176-FERC Dockets: RM07-19-000 and AD07-7-000, filing on behalf of \nthe PJM Power Providers addressing conservation and scarcity pricing \nissues identified in the Commission’s ANOPR on Competition.  \n \n175-FERC Docket No. EL07-67-000. Testimony and reply comments on \nbehalf of Hydro Quebec U.S. regarding the operation of the NYISO TCC \nmarket and appropriate bidding and competitive practices in the TCC and \nEnergy markets.  \n \n174-FERC Docket Nos. EL06-45-003. Testimony on behalf of El Paso \nElectric regarding the appropriate interpretation of a bilateral transmission \nand exchange agreement.  \n \n2006"},{"page":49,"startToken":12896,"endToken":13168,"text":"Roy J. Shanker \nPage 15 \n \n173-United States Bankruptcy Court for the Southern District of New \nYork. Case No. 01-16034 (AJG). Report on Behalf of EPMI regarding the \nproperties and operation of a power purchase agreement. \n \n172-FERC Docket No. EL05-148-000. Testimony regarding the proposed \nReliability Pricing Model settlement submitted for the PJM RTO.  \n \n171-FERC Docket No. ER06-1474-000, FERC. Testimony on behalf othe \nPSEG Companies regarding the PJM proposed new policy for including \n“market efficiency” transmission upgrades in the regional transmission \nexpansion plan.  \n \n170-FERC Docket No. EL05-148-000,  FERC. Participation in \nCommission technical sessions regarding the PJM proposed Reliability \nPricing Model.  \n \n169-FERC Docket No. EL05-148-000,  FERC. Comments filed on behalf \nof six PJM market participants concerning the proposed rules for \nparticipation in the PJM Reliability Pricing Model Installed Capacity \nmarket, and related rules for opting out of the RPM market.  \n \n168-FERC Docket No. ER06-407-000. Testimony on behalf of GSG, \nregarding interconnection issues for new wind generation facilities within \nPJM.  \n \n2005 \n \n167-FERC Docket No. EL05-121-000, Testimony on behalf of several \nPJM Transmission Owners (Responsible Pricing Alliance)  regarding \nalternative regional rate designs for transmission service and associated \nmarket design issues.  \n \n166-FERC Technical Conference of June 16, 2005. (Docket Nos. PL05-7-\n000, EL03-236-000, ER04-539-000). Invited participant. Statement \nregarding the operation of the PJM Capacity market and the proposed new \nReliability Pricing Model Market design.  \n \n165-American Arbitration Association Nos. 16-198-00206-03 16-198-\n002070.On behalf of PG&E Energy Trading. Analyses related to the \noperation and interpretation of power purchase and sale/tolling agreements \nand electrical interconnection requirements.  \n \n164-Arbitration on behalf of Black Hills Power, Inc. Expert testimony \nrelated to a power purchase and sale and energy exchange agreement, as"},{"page":50,"startToken":13168,"endToken":13442,"text":"Roy J. Shanker \nPage 16 \nwell as FERC criteria related to the applicable code and standards of \nconduct.  \n \n2004 \n \n163-Federal Energy Regulatory Commission Docket No. EL03-236-003.     \nTestimony on behalf of Mirant companies relating to PJM proposal for \ncompensation of frequently mitigated generation facilities.  \n \n162-Federal Energy Regulatory Commission. Docket No. ER03-563-030. \nTestimony on behalf of Calpine Energy Services regarding the \ndevelopment of a locational Installed Capacity market and associated \ngenerator service obligations for ISO-NE. Supplemental testimony filed \n2005.  \n \n161-Federal Energy Regulatory Commission.  Docket No. EL04-135-000. \nTestimony on behalf on the Unified Plan Supporters regarding \nimplications of using a flow based rate design to allocate embedded costs.  \n \n160-Federal Energy Regulatory Commission. Docket No. ER04-1229-\n000. Testimony on behalf of EME Companies regarding the allocation and \nrecovery of administrative charges in the NYISO markets.  \n \n159-Federal Energy Regulatory Commission. Dockets No. EL01-19-000, \nNo. EL01-19-001, No. EL02-16-000, EL02-16-000. Testimony on behalf \nof PSE&G Energy Resources and Trade regarding pricing in the New \nYork Independent System Operator energy markets. \n \n158-Federal Energy Regulatory Commission. Invited panelist regarding \nperformance based regulation (PBR)  and wholesale market design. \nComments related to the potential role of PBR in transmission expansion, \nand its interaction with market mechanisms for new transmission.  \n \n157-Federal Energy Regulatory Commission. Docket No. ER04-539-000 \nTestimony on behalf of EME Companies regarding proposed market \nmitigation in the energy and capacity markets of the Northern Illinois \nControl Area.  \n \n156-Federal Energy Regulatory Commission. Standardization of \nGenerator Interconnection Agreements and Procedures Docket No. RM02-\n1-001, Order 2003-A, Affidavit on Behalf of PSEG Companies regarding \nthe modifications on rehearing to interconnection crediting procedures.  \n \n \n155-Federal Energy Regulatory Commission. Dockets ER03-236-\n000,ER04-364-000,ER04-367-000,ER04-375-000. Testimony on behalf of"},{"page":51,"startToken":13442,"endToken":13735,"text":"Roy J. Shanker \nPage 17 \nthe EME Companies regarding proposed market mitigation measures in \nthe Northern Illinois Control Area of PJM.  \n \n154-Federal Energy Regulatory Commission. Dockets PL04-2-000, EL03-\n236-000. Invited panelist, testimony related to local market power and the \nappropriate levels of compensation for reliability must run resources.  \n \n2003 \n \n153-American Arbitration Association. 16 Y 198 00204 03. Report on \nbehalf of Trigen-Cineregy Solutions regarding an energy services \nagreement related to a cogeneration facility.  \n \n152-Federal Energy Regulatory Commission. Docket No. EL03-236-000. \nTestimony on behalf of EME Companies regarding the PJM proposed \ntariff changes addressing mitigation of local market power and the \nimplementation of a related auction process.  \n \n151-Federal Energy Regulatory Commission. Docket No. PA03-12-000. \nTestimony on behalf of Pepco Holdings Incorporated regarding \ntransmission congestion and related issues in market design in general, \nand specifically addressing congestion on the Delmarva Peninsula.  \n \n150-Federal Energy Regulatory Commission. Docket Nos. ER03-262-007, \nAffidavit on behalf of EME Companies regarding the cost benefit analysis \nof the operation of an expanded PJM including Commonwealth Edison.  \n \n149-Supreme Court of the State of New York, Index No. 601505/01. \nReport on behalf of Trigen-Syracuse Energy Corporation regarding energy \ntrading and sales agreements and the operation of the New York \nIndependent System Operator.  \n \n148-Federal Energy Regulatory Commission. Docket No. ER03-262-000. \nAffidavit on behalf of the EME Companies regarding the issues associated \nwith the integration of the Commonwealth Edison Company into PJM.  \n \n147-Federal Energy Regulatory Commission. Docket No. ER03-690-000. \nAffidavit on behalf of Hydro Quebec US regarding New York ISO market \nrules at external generator proxy buses when such buses are deemed non-\ncompetitive.  \n \n146-Federal Energy Regulatory Commission. Docket RT01-2-006,007. \nAffidavit on behalf of the PSEG Companies regarding the PJM Regional \nTransmission Expansion Planning Protocol, and proper incentives and \nstructure for merchant transmission expansion."},{"page":52,"startToken":13735,"endToken":14028,"text":"Roy J. Shanker \nPage 18 \n145-Federal Energy Regulatory Commission. Docket No. ER03-406-000. \nAffidavit on behalf of seven PJM Stakeholders addressing the \nappropriateness of the proposed new Auction Revenue Rights/Financial \nTransmission Rights process to be implemented by the PJM ISO.  \n \n144-Federal Energy Regulatory Commission. Docket No. ER01-2998-\n002. Testimony on behalf of Pacific Gas and Electric Company related to \nthe cause and allocation of transmission congestion charges.  \n \n143-Federal Energy Regulatory Commission. Docket No. RM01-12-000. \nOn behalf of six different companies including both independent \ngenerators, integrated utilities and distribution companies comments on \nthe proposed resource adequacy requirements of the Standard Market \nDesign.  \n \n142-United States Bankruptcy Court, Northern District of California, San \nFrancisco Division, Case No. 01-30923 DM. On behalf of Pacific Gas and \nElectric Dr. Shanker presented testimony addressing issues related to \ntransmission congestion, and the proposed FERC SMD and California \nMD02 market design proposals.  \n \n2002 \n \n141-Arbitration. Testimony on behalf of AES Ironwood regarding the \noperation of a tolling agreement and its interaction with PJM market rules.  \n \n140-Federal Energy Regulatory Commission. Docket No. RM01-12-000. \nDr. Shanker was asked by the three Northeast ISO’s to present a summary \nof his resource adequacy proposal developed in the Joint Capacity \nAdequacy Group. This was part of the Standard Market Design NOPR \nprocess.  \n \n139-Federal Energy Regulatory Commission. Docket No. ER02-456-000. \nTestimony on behalf of Electric Gen LLC addressing comparability of a \ncontract among affiliates with respect to non-price terms and conditions.  \n \n138-Circuit Court for Baltimore City. Case 24-C-01-000234. Testimony \non behalf of Baltimore Refuse Energy Systems Company regarding the \nappropriate implementation and pricing of a power purchase agreement \nand related Installed Capacity credits.  \n \n137-Federal Energy Regulatory Commission. Docket No. RM01-12-000. \nComments on the characteristics of capacity adequacy markets and \nalternative market design systems for implementing capacity adequacy \nmarkets."},{"page":53,"startToken":14028,"endToken":14308,"text":"Roy J. Shanker \nPage 19 \n2001 \n \n136-Federal Energy Regulatory Commission.  Docket ER02-456-000. \nTestimony on behalf of Electric Gen LLC regarding the terms and \nconditions of a power sales agreement between PG&E and  Electric \nGenerating Company LLC.   \n \n135-Delaware Public Service Commission. Docket 01-194. On behalf of \nConectiv et al. Testimony relating to the proper calculation of Locational \nMarginal Prices in the PJM market design, and the function of Fixed \nTransmission Rights.  \n \n134-Federal Energy Regulatory Commission. Docket No. IN01-7-000 On \nbehalf of Exelon Corporation . Testimony relating to the function of Fixed \nTransmission Rights, and associated business strategies in the PJM market \nsystem.  \n  \n133-Federal Energy Regulatory Commission. Docket No. RM01-12-000. \nComments on the basic elements of RTO market design and the required \nmarket elements.  \n \n132-Federal Energy Regulatory Commission. Docket No. RT01-99-000. \nOn behalf of the One RTO Coalition. Affadavit on the computational \nfeasibility of large scale regional transmission organizations and related \nissues in the PJM and NYISO market design.  \n \n131-Arbitration. On behalf of Hydro Quebec. Testimony related to the \neligibility of power sales to qualify as Installed Capacitywithin the New \nYork Independent system operator.  \n \n130-Virginia State Corporation Commission. Case No. PUE000584. On \nbehalf of the Virginia Independent Power Producers. Testimony related to \nthe proposed restructuring of Dominion Power and its impact on private \npower contracts.  \n \n129-United States District Court, Northern District of Ohio, Eastern \nDivision, Case: 1:00CV1729. On behalf of Federal Energy Sales, Inc. \nTestimony related to damages in disputed electric energy trading \ntransactions.  \n \n128-Federal Energy Regulatory Commission. Docket Number ER01-\n2076-000. Testimony on behalf of Aquila Energy Marketing Corp and \nEdison Mission Marketing and Trading, Inc. relating to the \nimplementation of an Automated Mitigation Procedure by the New York \nISO."},{"page":54,"startToken":14308,"endToken":14581,"text":"Roy J. Shanker \nPage 20 \n2000 \n \n127-New York Independent System Operator Board. Statement on behalf \nof Hydro Quebec, U.S. regarding the implications and impacts of the \nimposition of a price cap on an operating market system.  \n \n126-Federal Energy Regulatory Administration. Docket No. EL00-24-000. \nTestimony on behalf of Dayton Power and Light Company regarding the \nproper characterization and computation of regulation and imbalance \ncharges.  \n \n125-American Arbitration Association File 71-198-00309-99. Report on \nbehalf of Orange and Rockland Utilities, Inc. regarding the estimation of \ndamages associated with the termination of a power marketing agreement.  \n \n124-Circuit Court, 15th Judicial Circuit, Palm Beach County, Florida. On \nbehalf of Okeelanta and Osceola Power Limted Partnerships et. al. \nAnalyses related to commercial operation provisions of a power purchase \nagreement.  \n \n1999 \n \n123-Federal Energy Regulatory Commission. Docket No. ER00-1-000. \nTestimony on behalf of TransEnergie U.S. related to market power \nassociated with merchant transmission facilities. Also related analyses \nregarding market based tariff design for merchant transmission facilities.  \n \n122-Federal Energy Regulatory Commission. Docket RM99-2-000. \nAnalyses on behalf of Edison Mission Energy relating to the Regional \nTransmission Organization Notice of Proposed Rulemaking.  \n \n121-Federal Energy Regulatory Commission. Docket No. ER99-3508-\n000. On behalf of PG&E Energy Trading, analyses associated with the \nproposed implementation and cutover plan for the New York Independent \nSystem Operator.  \n \n120-Federal Energy Regulatory Commission. Docket No. EL99-46-000. \nComments on behalf of the Electric Power Supply Association relating to \nthe Capacity Benefit Margin.  \n \n119-New York Public Service Commission, Case 97-F-1563. Testimony \non behalf of Athens Generating Company describing the impacts on \npricing and transmission of a new generation facility within the New York \nPower Pool under the new proposed ISO tariff."},{"page":55,"startToken":14581,"endToken":14829,"text":"Roy J. Shanker \nPage 21 \n118-JAMS Arbitration Case No. 1220019318 On behalf of Fellows \nGeneration Company. Testimony related to the development of the \nindependent power and qualifying facility industry and related industry \npractices with respect to transactions between cogeneration facilities and \nthermal hosts. \n \n117-Court of Common Pleas, Philadelphia County, Pennsylvania. \nAnalyses on behalf of Chase Manhattan Bank and Grays Ferry \nCogeneration Partnership related to power purchase agreements and \nelectric utility restructuring.  \n \n1998 \n \n116-Virginia State Corporation Commission. Case No. PUE 980463. \nTestimony on behalf of Appomattax Cogeneration related to the proper \nimplementation of avoided cost methodology.  \n \n115-Virginia State Corporation Commission. Case No. PUE980462 \nTestimony on behalf of Virginia Independent Power Producers related to \nan applicaton for a certificate for new generation facilities.  \n \n114-Federal Energy Regulatory Commission. Analyses related to a \nnumber of dockets reflecting amendments to the PJM ISO tariff and \nReliability Assurance Agreement. \n \n113-U.S. District Court, Western Oklahoma. CIV96-1595-L. Testimony \nrelated to anti-competitive elements of utility rate design and promotional \nactions.  \n \n112-Federal Energy Regulatory Commission Dockets No. EL94-45-001 \nand QF88-84-006. Analyses related to historic measurement of spot prices \nfor as available energy.  \n \n111-Circuit Court, Fourth Judicial Circuit, Duval County, Florida. \nAnalyses related to the proper implementation of a a power purchase \nagreement and associated calculations of capacity payments. (Testimony \n1999)  \n \n1997 \n \n110-United States District Court for the Eastern District of Virginia, CA \nNo. 3:97CV 231. Analyses of the business and market behavior of \nVirginia Power with respect to the implementation of wholesale electric \npower purchase agreements."},{"page":56,"startToken":14829,"endToken":15111,"text":"Roy J. Shanker \nPage 22 \n109-United States District Court, Southern District of Florida, Case No. \n96-594-CIV, Analyses related to anti-competitive practices by an electric \nutility and related contract matters regarding the appropriate calculation of \nenergy payments. \n \n108-Virginia State Corporation Commission. Case No. PUE960296. \nTestimony related to the restructuring proposal of Virginia Power and \nassociated stranded cost issues.  \n \n107-Federal Energy Regulatory Commission. Dockets No. ER97-1523-\n000 and OA97-470-000, Analyses related to the restructuring of the New \nYork Power Pool and the implementation of locational marginal cost \npricing.  \n \n106-Federal Energy Regulatory Commission Dockets No. OA97-261-000 \nand ER97-1082-000 Analyses and testimony related to the restructuring of \nthe PJM Power Pool and the implementation of locational marginal cost \npricing.  \n \n105-Missouri Public Service Commission. Case No. ET-97-113. \nTestimony related to the proper definition and rate design for standby, \nsupplemental and maintenance service for Qualifying facilities.  \n \n104-American Arbitration Association. Case 79 Y 199 00070 95. \nTestimony and analyses related to the proper conditions necessary for the \ncurtailment of Qualifying Facilities and the associated calculations of \nnegative avoided costs.  \n \n103-Virginia State Corporation Commission. Case Number PUE960117 \nTestimony related to proper implementation of the differential revenue \nrequirements methodology for the calculation of avoided costs.  \n \n102-New York Public Service Commission. Case 96-E-0897, Analyses \nrelated to the restructuring of Consolidated Edison Company of New York \nand New York Power Pool proposed Independent System Operator and \nrelated transmission tariffs.  \n \n1996 \n \n101-Florida Public Service Commission. Docket No. 950110-EI. \nTestimony related to the correct calculation of avoided costs using the \nValue of Deferral methodology and its implementation.  \n \n100-Federal Energy Regulatory Commission Dockets No. EL94-45-001 \nand QF88-84-006.  Testimony and Analyses related to the estimation of \nhistoric market rates for electricity in the Virginia Power service territory."},{"page":57,"startToken":15111,"endToken":15396,"text":"Roy J. Shanker \nPage 23 \n \n99-Circuit Court of the City of Richmond Case No. LA-2266-4. Analyses \nrelated to the incurrence of actual and estimated damages associated with \nthe outages of an electric generation facility.  \n \n98-New Hampshire Public Utility Commission, Docket No. DR96-149. \nAnalyses related to the requirements of light loading for the curtailment of \nQualifying Facilities,  and the compliance of a utility with such \nrequirements.  \n \n97-State of New York Supreme Court, Index No. 94-1125. Testimony \nrelated to system planning criteria and their relationship to contract \nperformance specifications for a purchased power facility. \n \n96-United States District Court for the Western District of Pennsylvania, \nCivil Action No.  95-0658.  Analyses related to anti-competitive actions of \nan electric utility with respect to a power purchase agreement.  \n \n95-United States District Court for the Northern District of Alabama, \nSouthern Division. Civil Action Number CV-96-PT 0097-S. Affadavit on \nbehalf of TVA and LG&E Power regarding displacement in wholesale \npower transactions.  \n \n1995 \n \n94-American Arbitration Association. Arbitration No. 14 198 012795 \nH/K. Report concerning the correct measurement of savings resulting from \na commercial  building cogeneration system and associated contract \ncompensation issues. \n \n93-Circuit Court City of Richmond. Law No. LX-2859-1. Analyses related \nto IPP contract structure and interpretation regarding plant compensation \nunder different operating conditions.  \n \n92-Federal Energy Regulatory Commission. Case EL95-28-000. Affidavit \nconcerning the provisions of the FERC regulations related to the Public \nUtility Regulatory Policies Act of 1978,  and relationship of estimated \navoided cost to traditional rate based recovery of utility investment.  \n \n91-New York Public Service Commission, Case 95-E-0172, Testimony on \nthe correct design of standby, maintenance and supplemental  service rates \nfor qualifying facilities. \n \n90-Florida Public Service Commission, Docket No. 941101-EQ. \nTestimony related to the proper analyses and procedures related to the"},{"page":58,"startToken":15396,"endToken":15663,"text":"Roy J. Shanker \nPage 24 \ncurtailment of purchases from Qualifying Facilities under Florida and \nFERC regulations.  \n \n89-Federal Energy Regulatory Commission, Dockets ER95-267-000 and \nEL95-25-000. Testimony related to the proper evaluation of generation \nexpansion alternatives. \n \n1994 \n \n88-American Arbitration Association, Case Number 11 Y198 00352 94 \nAnalyses related to contract provisions for milestones and commercial \noperation date and associated termination and damages related to the \nconstruction  of a NUG facility. \n \n87-United States District Court, Middle District Florida, Case No. 94-303 \nCiv-Orl-18. Analyses related to contract pricing interpretation other \ncontract matters in a power purchase agreement  between a qualifying \nfacility and Florida Power Corporation. \n \n86-Florida Public Service Commission Docket 94037-EQ. Analyses \nrelated to a contract dispute between Orlando Power Generation and \nFlorida Power Corporation. \n \n85-Florida Public Service Commission Docket 941101-EQ.  Testimony \nand analyses of the proper procedures for the determination and \nmeasurement for the need to curtail purchases from qualifying facilities.  \n \n84-New York Public Service Commission Case 93-E-0272, Testimony \nregarding PURPA policy considerations and the status of services \nprovided to the generation and consuming elements of a qualifying \nfacility. \n \n83-Circuit Court for the City of Richmond. Case Number LW 730-4. \nAnalyses of the historic avoided costs of Virginia Power, related \nprocedures and fixed fuel transportation rate design.  \n \n82-New York Public Service Commission, Case 93-E-0958 Analyses of \nStand-by, Supplementary and Maintenance Rates of Niagara Mohawk \nPower Corporation for Qualifying Facilities . \n \n81-New York Public Service Commission, Case 94-E-0098. Analyses of \ncost of service and rate design  of Niagara Mohawk Power Corporation.  \n \n80-American Arbitration Association, Case 55-198-0198-93, Arbitrator in \ncontract dispute regarding the commercial operation date of a qualifying \nsmall power generation facility."},{"page":59,"startToken":15663,"endToken":15934,"text":"Roy J. Shanker \nPage 25 \n \n1993 \n \n79-U.S. District Court, Southern District of New York Case 92 Civ 5755. \nAnalyses of contract provisions and associated commercial terms and \nconditions of power purchase agreements between an independent power \nproducer and Orange and Rockland Utilities.  \n \n78-State Corporation Commission, Virginia. Case No. PUE920041. \nTestimony related to the appropriate evaluation of historic avoided costs in \nVirginia and the inclusion of gross receipt taxes.  \n \n77-Federal Energy Regulatory Commission. Docket ER93-323-000. \nEvaluations and analyses related to the financial and regulatory status of a \ncogeneration facility.  \n \n76-Federal Energy Regulatory Commission. Docket EL93-45-000; Docket \nQF83-248-002. Analyses related to the qualifying status of cogeneration \nfacility.  \n \n75-Circuit Court of the Eleventh Judicial Circuit, Dade County, Florida.  \nCase No. 92-08605-CA-06.  Analyses related to compliance with electric \nand thermal energy purchase agreements. Damage analyses and testimony.  \n \n74-Board of Regulatory Commissioners, State of New Jersey. Docket EM \n91010067. Testimony regarding the revised GPU/Duquesne 500 MW \npower sales agreement and associated transmission line. \n \n73-State of North Carolina Utilities Commission. Docket No. E-100 Sub \n67. Testimony in the consideration of rate making standards pursuant to \nSection 712 of the Energy Policy Act of 1992.  \n \n72-State of New York Public Service Commission. Cases 88-E-081 and \n92-E-0814. Testimony regarding appropriate procedures for the \ndetermination of the need for curtailment of qualifying facilities and \nassociated proper production cost modeling and measurement.  \n \n71-Pennsylvania Public Utility Commission. Docket No. A-110300f051. \nTestimony regarding the prudence of the revised GPU/Duquesne 500 MW \npower sales agreement and associated transmission line. \n \n1992 \n \n70-Pennsylvania Public Service Commission. Dockets No. P-870235,C-\n913318,P-910515,C-913764. Testimony regarding the calculation of \navoided costs for GPU/Penelec."},{"page":60,"startToken":15934,"endToken":16199,"text":"Roy J. Shanker \nPage 26 \n \n69-Public Service Commission of Maryland. Case No. 8413,8346. \nTestimony on the appropriate avoided costs for Pepco, and appropriate \nprocedures for contract negotiation.  \n \n1991 \n68-Board of Regulatory Commissioners, State of New Jersey. Docket EM-\n91010067. Testimony regarding the planned purchase of 500 MW by GPU \nfrom Duquesne Light Company.  \n \n67-Public Service Commission of Wisconsin. Docket 05-EP-6. State \nAdvance Plan. Testimony on the calculation of avoided costs and the \nstructuring of payments to qualifying facilities. \n \n66-State Corporation Commission, Virginia. Case No. PUE910033. \nTestimony on class rate of return and rate design for delivery point \nservice. Northern Virginia Electric Cooperative. \n \n65-State Corporation Commission, Virginia. Case No. PUE910048 \nTestimony on proper data and modeling procedures to be used in the \nevaluation of the annual Virginia Power fuel factor. \n \n64-State Corporation Commission, Virginia. Case No. PUE910035. \nEvaluation of the differential revenue requirements method for the \ncalculation of avoided costs. \n \n63-Public Service Commission of Maryland. Case Number 8241 Phase II. \nTestimony related to the proper determination of avoided costs for \nBaltimore Gas and Electric.  \n \n62-Public Service Commission of Maryland. Case Number 8315. \nEvaluation of the system expansion planning methodology and the \nassociated impacts on marginal costs and rate design, PEPCO.  \n \n1990 \n \n61-Public Utility Commission, State of California, Application 90-12-064. \nAnalyses related to the contractual obligations between San Diego Gas \nand Electric and a proposed QF. \n \n60-Montana Public Service Commission. Docket 90.1.1 Testimony and \nanalyses related to natural gas transportation, services and rates.  \n \n59-State Corporation Commission, Virginia. Case No. PUE890075. \nTestimony on the calculation of full avoided costs via the differential \nrevenue requirements methodology."},{"page":61,"startToken":16199,"endToken":16441,"text":"Roy J. Shanker \nPage 27 \n \n58-District of Columbia Public Service Commission. Formal Case 834 \nPhase II. Analyses and development of demand side management \nprograms and least cost planning for Washington Gas Light.  \n \n57-State Corporation Commission, Virginia. Case No. PUE890076. \nAnalyses related to administratively set avoided costs. Determination of \noptimal expansion plans for Virginia Power.  \n \n56-State Corporation Commission, Virginia. Case No. PUE900052. \nAnalyses supporting arbitration of a power purchase agreement with \nVirginia Power. Determination of expansion plan and avoided costs.  \n \n55-Public Service Commission of Maryland. Case Number 8251. \nAnalyses of system expansion planning models and marginal cost rate \ndesign for PEPCO.  \n \n54-State Corporation Commission, Virginia. Case No. PUE900054. \nEvaluation of fuel factor application and short term avoided costs.  \n \n53-Federal Energy Regulatory Commission. Northeast Utilities Service \nCompany Docket Nos. EC90-10-000, ER90-143-000, ER90-144-\n000,ER90-145-000 and El90-9-000. Analyses of the implications of \nNortheast Utilities and Public Service Company of New Hampshire \nmerger on electric supply and pricing.  \n \n52-Public Service Commission of Maryland. Re: Southern Maryland \nElectric Cooperative Inc. Contract with Advanced Power Systems, Inc. \nand PEPCO.  \n \n51-Puerto Rico Electric Power Authority, Office of the Governor of \nPuerto Rico. Independent evaluation for PREPA of avoided costs and the \nevaluation of competing QF's.  \n \n50-State Corporation Commission, Virginia. Case No. PUE890041. \nTestimony on the proper determination of avoided costs with respect to \nOld Dominion Electric Cooperative. \n \n1989 \n \n \n49-Oklahoma Corporation Commission.  Case Number  PUD-000586.  \nAnalyses related to system planning and calculation of avoided costs for \nPublic Service of Oklahoma."},{"page":62,"startToken":16441,"endToken":16672,"text":"Roy J. Shanker \nPage 28 \n48-Virginia State Corporation Commission.  Case  Number PUE890007.  \nTestimony relating to the proper determination of avoided costs to the \ncertification evaluation of new generation facilities. \n \n47-Federal Energy Regulatory Commission.  Docket RP85-50. Analyses \nof the gas transportation rates, terms and conditions filed by Florida Gas \nTransmission. \n \n46-Circuit Court of the Fifth Judicial Circuit, Dade County, Florida.  Case \nNo. 88-48187.  Analyses related to compliance with electric and thermal \nenergy purchase agreements. \n \n45-Florida Public Service Commission.  Docket 880004-EU. Analysis of \nstate wide expansion planning procedures and associated avoided unit. \n \n1988 \n \n44-Virginia State Corporation Commission.  Case No. PUE870081.  \nTestimony on the implementation of the differential revenue requirements \navoided costmethodology recommended by the SCC Task Force. \n \n43-Virginia State Corporation Commission.  Case No. PUE880014.  \nTestimony on the design and level of standby, maintenance and \nsupplemental power rates for qualifying facilities. \n \n42-Virginia State Corporation Commission.  Case No. PUE99038.  \nTestimony on the natural gas transportation rate design and service \nprovisions. \n \n41-Montana Public Service Commission.  Docket 87.8.38. Testimony on \nNatural Gas Transmission Rate Design and Service Provisions. \n \n40-Oklahoma Corporation Commission.  Cause Pud No. 00345. \nTestimony on estimation and level of avoided cost payments for \nqualifying facilities. \n \n39-Florida Public Service Commission.  Docket No.8700197-EI.  \nTestimony on the methodology for establishing non-firm load service \nlevels. \n \n38-Arizona Corporation Commission.  Docket No. U-1551-86-300.  \nAnalysis of cost-of-service studies and related terms and conditions for \nmaterial gas transportation rates. \n \n1987"},{"page":63,"startToken":16672,"endToken":16917,"text":"Roy J. Shanker \nPage 29 \n37-Virginia State Corporation Commission.  Case No. PUE870028.  \nAnalysis of Virginia Power fuel factorapplication and relationship to \navoided costs. \n \n36-District of Columbia Public Service Commission.  Formal Case No. \n834 Phase II.  Analysis of the theory and empirical basis for establishing \ncost effectiveness of natural gas conservation programs. \n \n35-Virginia State Corporation Commission.  Case No. PUE860058.  \nTestimony on the relationship of small power producers and cogenerators \nto the need for power and new generation facilities. \n \n34-Virginia State Corporation Commission.  Case No. PUE870025.  \nTestimony addressing the proper design of rates for standby, maintenance \nand supplement power sales to cogenerators. \n \n33-Florida Public Service Commission.  Docket No. 860004 EU.  \nTestimony in the 1986 annual planning hearing on proper system \nexpansion planning procedures. \n \n1986 \n \n32-Florida Public Service Commission.  Docket No. 860001 EI-E.  \nTestimony on the proper methodology for the estimation of avoided O&M \ncosts. \n \n31-Florida Public Service Commission.  Docket No. 860786-EI.  \nTestimony on the proper economic analysis for the evaluation of self-\nservice wheeling. \n \n30-U.S. Bankruptcy Court, District of Ohio.  Testimony on capabilities to \ndevelop and operate wood-fired qualifying facility. \n \n29-Public Utility Commission, New Hampshire Docket No. DR-86-41.  \nTestimony on pricing and contract terms for power purchase agreement \nbetween utility and QFs. (Settlement Negotiations) \n \n28-Florida Public Service Commission, Docket No. 850673-EU. \nTestimony on generic issues related to the design of standby rates for \nqualifying facilities. \n \n27-Virginia State Corporation Commission.  Case No. 860024. Generic \nhearing on natural gas transportation rate design and tariff terms and \nconditions."},{"page":64,"startToken":16917,"endToken":17167,"text":"Roy J. Shanker \nPage 30 \n26-Virginia State Corporation Commission. Commonwealth Gas Pipeline \nCorporation.  Case No. 850052. Testimony on natural gas transportation \nrate design and tariff terms and conditions. \n \n25-Bonneville Power Administration.  Case No. VI86. Testimony on the \nproposed Variable Industrial Power Rate for Aluminum Smelters. \n \n24-Virginia Power.  Case No. PUE860011.  Testimony on the proper ex \npost facto valuation of avoided power costs for qualifying facilities. \n \n23-Florida Public Service Commission.  Docket No. 850004 EU.  \nTestimony on proper analytic procedures for developing a statewide \ngeneration expansion plan and associated avoided unit. \n \n1985 \n \n22-Virginia Natural Gas.  Docket No. 85-0036.  Testimony and cost of \nservice procedures and rate design for natural gas transportation service. \n \n21-Arkansas Louisiana Gas.  Louisiana Docket No. U-16534. Testimony \non proper cost of service procedures and rate design for natural gas \nservice. \n \n20-Connecticut Light and Power.  Docket No. 85-08-08.  \nAssist in the development of testimony for industrial natural gas \ntransportation rates. \n \n19-Oklahoma Gas and Electric.  Cause 29727.  Testimony and system \noperations and the development of avoided cost measurements as the basis \nfor rates to qualifying facilities. \n \n18-Florida Public Service Commission.  Docket No. 840399EU.  \nTestimony on self-service wheeling and business arrangements for \nqualifying facilities. \n \n17-Virginia Electric and Power Company.  General Rate application No. \nPUE840071.  Testimony on proper rate design procedures and \ncomputations for development of supplemental, maintenance and standby \nservice for cogenerators. \n \n16-Virginia Electric and Power Company.  Fuel Factor \nProceeding No. PUE850001.  Testimony on the proper use of the \nPROMOD model and associated procedures in setting avoided cost energy \nrates for cogenerators."},{"page":65,"startToken":17167,"endToken":17422,"text":"Roy J. Shanker \nPage 31 \n15-New York State Public Service Commission.  Case No. 28962.  \nDevelopment of the use of multi-area PROMOD models to estimate \navoided energy costs for six private utilities in New York State. \n  \n14-Vermont Rate Hearings on Payments to Small Power Producers.  Case \nNo. 4933.  Testimony on proper assumptions, procedures and analysis for \nthe development of avoided cost rates. \n \n1984 \n \n13-Northern Virginia Electric Cooperative.  Case No. PUE840041.  \nTestimony on class cost-of-serviceprocedures, class rate of return and rate \ndesign. \n \n12-BPA 1985 Wholesale Rate Proceedings.  Analysis of Power 1985 Rate \nDirectives.  Testimony on theory and implementation of marginal cost rate \ndesign. \n \n11-Virginia Electric Power Company.  Application to Revise Rate \nSchedule 19 -- Power Purchases from Cogeneration and Small Power \nProduction Qualifying Facilities.  Case No. PUE830067.  Testimony on \nproper PROMOD  modeling procedures for power purchases and \nproperties of PROMOD model. \n \n10-Northern Virginia Electric Cooperative.  Case No. PUE840041.  \nTestimony on class cost-of-service procedures, class rate of return and rate \ndesign. \n \n9-BPA 1985 Wholesale Rate Proceedings.  Analysis of Power 1985 Rate \nDirectives.  Testimony on the theory and implementation of marginal cost \nrate design, financial performance of BPA; interactions between rate \ndesign, demand, system expansion and operation. \n \n1983 \n \n8-Northern Virginia Electric Cooperative.  Case No. PUE830040.  \nTestimony on class cost-of-service procedures, class rate of return and rate \ndesign. \n \n7-Vermont Rate Hearings to Small Power Producers.  No.4804.  \nTestimony on proper use and application of production costing analyses to \nthe estimation of avoided costs. \n \n6-BPA Wholesale Rate Proceedings.  Testimony on the theory and \nimplementation of marginal cost rate design; financial performance of"},{"page":66,"startToken":17422,"endToken":17567,"text":"Roy J. Shanker \nPage 32 \nBPA; interactions between rate design, demand, system expansion and \noperation. \n \n5-Idaho Power Company, PUC-U-1006-185.  Analysis of system \nplanning/production costing model play of hydro regulation and associated \nenergy costs. \n \n1982 \n \n4-Generic Conservation Proceedings, New York State.  Case No. 18223.  \nTestimony on the economic criteria for the evaluation of conservation \nactivities; impacts on utility financial performance and rate design. \n \n3-PEPCO, Washington Gas Light.  DCPSC-743.  Financial evaluation of \nconservation activities; procedures for cost classification, allocation; rate \ndesign. \n \n2-PEPCO, Maryland PSC Case Nos. 7597-I, 7597-II, and 7652. \nTestimony on class rates of return, cost classification and allocation, \npower pool operations and sales. \n \n1981 \n \n1-Pacific Gas and Electric.  California PSC Case No. 60153.  Testimony \non rate design; class cost-of-service and rate of return. \n \nPrevious testimony before the District of Columbia \nPublic Service Commission, Maryland PSC, New York Public Service \nCommission, FERC; Economic Regulatory Administration"},{"page":67,"startToken":17567,"endToken":17569,"text":"Appendix B"},{"page":68,"startToken":17569,"endToken":17925,"text":"1 \n \n18.10 Annual RBP Isolation and Matched Demand Adjustment \n(a) Applicability \nFor each Delivery Year during the Reliability Backstop Procurement commitment period, and \nfor each Base Residual Auction and Incremental Auction conducted after the Office of the \nInterconnection commits RBP UCAP MW through the Reliability Backstop Procurement, the \nOffice of the Interconnection shall apply the RBP isolation and matched demand adjustment set \nforth in this section. \n(b) Determination of Available RBP UCAP MW \nBefore posting the Planning Parameters for each applicable RPM Auction, the Office of the \nInterconnection shall determine Available RBP UCAP MW for the applicable Delivery Year on \na resource-specific and aggregate basis. The determination shall account for the RBP Resource’s \ncommitted RBP UCAP MW, applicable Accredited UCAP, expected commercial-operation or \nregistration status, deliverability, any notice submitted pursuant to Tariff, Attachment DD, \nsection 5.5, approved replacement capacity, and any rescission pursuant to Tariff, Attachment \nDD, section 18.6(e). \nThe Office of the Interconnection shall determine Available RBP UCAP MW for the PJM \nRegion and by Zone and modeled Locational Deliverability Area. \n(c) Determination of RBP-Related Load UCAP MW \nBefore posting the Planning Parameters for each applicable RPM Auction, the Office of the \nInterconnection shall determine the portion of the incremental-load cohort used to establish or \nallocate the Reliability Backstop Procurement that is included in the Planning Parameters for the \napplicable RPM Auction. The Office of the Interconnection shall convert such load to UCAP \nMW using the Forecast Pool Requirement and the existing methodologies used to determine the \napplicable PJM Region and LDA Reliability Requirements. \nThe determination shall exclude load associated with Qualifying RBP Offset UCAP MW, \napproved opt-outs, FRR Entities, and load not included in the applicable RPM Auction Planning \nParameters. Load shall not be counted more than once under this section or under any other \nTariff provision providing for exclusion or matched treatment of New Large Load. \n(d) RTO-Wide RBP Demand Adjustment \nFor each applicable RPM Auction, the RBP Demand Adjustment for the PJM Region shall equal \nthe lesser of: \n1. Available RBP UCAP MW; and  \n2. RBP-Related Load UCAP MW included in the Planning Parameters for such RPM \nAuction."},{"page":69,"startToken":17925,"endToken":18285,"text":"2 \n \nSolely for purposes of clearing and price formation in the applicable RPM Auction, the Office of \nthe Interconnection shall reduce the PJM Region Reliability Requirement by the RBP Demand \nAdjustment. \n(e) Exclusion of Available RBP UCAP MW \nAvailable RBP UCAP MW shall not be included in any Sell Offer, price-forming supply curve, \nor optimization used to determine the Capacity Resource Clearing Price in an applicable RPM \nAuction. Available RBP UCAP MW shall not clear such RPM Auction and shall not receive \nRPM Auction capacity credits. \nAny UCAP MW of an RBP Resource above its committed RBP UCAP MW may participate in \nRPM Auctions pursuant to otherwise applicable Tariff and RAA requirements. \nTo the extent Available RBP UCAP MW exceeds RBP-Related Load UCAP MW, such excess \nshall remain excluded from RPM Auction price formation and shall not produce an additional \nreduction in any RPM reliability requirement. \n(f) Incremental Auctions \nFor each Incremental Auction, the Office of the Interconnection shall recalculate Available RBP \nUCAP MW, RBP-Related Load UCAP MW, and the RBP Demand Adjustment using the \nupdated Planning Parameters for the applicable Delivery Year. The RBP-Adjusted Reliability \nRequirement used in the Incremental Auction shall reflect the recalculated RBP Demand \nAdjustment and all RPM commitments established in prior RPM Auctions for the same Delivery \nYear. Available RBP UCAP MW shall not be included as an RPM commitment established in a \nprior auction. \n(g) Locational Treatment \nThe Office of the Interconnection shall allocate the RBP Demand Adjustment among Zones \nbased on the location of RBP-Related Load included in the applicable Planning Parameters. \nFor each modeled LDA, the reduction in the LDA Reliability Requirement shall not exceed: \n1. RBP-Related Load UCAP MW located in such LDA; or  \n2. Available RBP UCAP MW located in, or determined under the same CETO and CETL \nassumptions used in the applicable RPM Auction to be deliverable to, such LDA.  \nThe Office of the Interconnection shall not count the same RBP Demand Adjustment more than \nonce among nested LDAs and their parent LDAs. Any portion of the RTO-wide RBP Demand \nAdjustment that cannot support an LDA adjustment under this subsection shall not reduce the \nreliability requirement for that LDA."},{"page":70,"startToken":18285,"endToken":18693,"text":"3 \n(h) Publication\nWith the Planning Parameters for each applicable RPM Auction, the Office of the \nInterconnection shall post the aggregate Available RBP UCAP MW, RBP-Related Load UCAP \nMW, RBP Demand Adjustment, and resulting RBP-Adjusted Reliability Requirements for the \nPJM Region and each affected Zone and LDA. Resource- or customer-specific confidential \ninformation may be omitted from the public posting but shall be made available to the Market \nMonitoring Unit. \n(i) Effect Limited to RPM Price Formation\nThe exclusion of Available RBP UCAP MW under this section shall not relieve an RBP \nResource of any accreditation, deliverability, registration, testing, outage-reporting, energy-\nmarket must-offer, Capacity Performance, replacement-capacity, Non-Performance Charge, \ndeficiency-charge, RBP shortfall, or other physical or performance obligation applicable to the \ncommitted RBP UCAP MW. \nRecommended new and revised defined terms \n“Available RBP UCAP MW” shall mean, for an RPM Auction for a Delivery Year, the \naggregate UCAP MW of RBP Resources committed for such Delivery Year that the Office of the \nInterconnection determines, using the accreditation, commercial-operation or registration, \ndeliverability, and availability standards that otherwise would apply in determining the quantity \nof such resources eligible to participate in that RPM Auction, are expected to be available to \nprovide capacity during such Delivery Year; provided that Available RBP UCAP MW shall not \nexceed the RBP UCAP MW committed for such Delivery Year and shall exclude any \ncommitment rescinded pursuant to Tariff, Attachment DD, section 18.6(e). \n“RBP-Related Load UCAP MW” shall mean, for an RPM Auction for a Delivery Year, \nexclusive of any load associated with Qualifying RBP Offset UCAP MW, an approved opt-out, \nan FRR Entity, or load otherwise excluded from the applicable RPM Auction Planning \nParameters, the sum of all Large Loads across the PJM region in the load forecast for the \nrelevant Delivery Year minus the sum of all Large Loads across the PJM region that were \nforecasted to be on the system for the 2026/27 delivery year using the load forecast that was used \nfor the 2028/29 Base Residual Auction. Peak-load megawatts shall be converted to UCAP MW \nusing the Forecast Pool Requirement and the applicable existing zonal and LDA methodologies \nfor such Delivery Year. \n“RBP Demand Adjustment” shall mean, for an RPM Auction for a Delivery Year, the lesser of \nAvailable RBP UCAP MW and RBP-Related Load UCAP MW, as determined and allocated to \nthe PJM Region, Zones, and affected Locational Deliverability Areas in accordance with Tariff, \nAttachment DD, section 18.10."},{"page":71,"startToken":18693,"endToken":18939,"text":"4 \n \n“RBP-Adjusted Reliability Requirement” shall mean, solely for purposes of clearing and price \nformation in an RPM Auction, the applicable PJM Region Reliability Requirement or LDA \nReliability Requirement, as applicable, reduced by the RBP Demand Adjustment determined \npursuant to Tariff, Attachment DD, section 18.10. The RBP-Adjusted Reliability Requirement \nshall not modify the applicable reliability criterion, Forecast Pool Requirement, or physical \nresource-adequacy requirement. \n“Daily RBP Settlement Quantity” shall mean, for an RBP Resource and Operating Day, the \nlesser of the RBP Resource’s daily committed RBP UCAP MW and daily owned UCAP MW. \n“RBP Market Revenue Offset” shall mean, for a Delivery Year and Electric Distributor \nzone/area, the daily dollar value of the final RBP Demand Adjustment allocated to such \nzone/area multiplied by the applicable Final Zonal Capacity Price, subject to interim calculation \nand true-up as set forth in Tariff, Attachment DD, section 18.5(g). \n“RBP Settlement Credits” shall mean the daily dollar amount payable to an RBP Resource \npursuant to Tariff, Attachment DD, section 18.5(g), before application of any RBP shortfall \ncharge, Non-Performance Charge, deficiency charge, or other applicable charge. \n“RBP Charges” shall mean the daily positive or negative net amount determined pursuant to \nTariff, Attachment DD, sections 18.3 and 18.5(g), consisting of RBP Settlement Credits allocated \nto an Electric Distributor zone/area, less the RBP Market Revenue Offset applicable to such \nzone/area, together with any other adjustment expressly included pursuant to Tariff, Attachment \nDD, section 18."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":294,"startToken":0,"endToken":704},{"p":3,"at":294,"title":"I. LIMITED PROTEST OF REQUIREMENT THAT AVAILABLE RBP UCAP","method":"printed heading","endPage":3,"endAt":392,"startToken":704,"endToken":721},{"p":3,"at":392,"title":"A. Introduction and Summary","method":"printed heading","endPage":5,"endAt":974,"startToken":721,"endToken":1464},{"p":5,"at":974,"title":"B. PJM Has Not Shown That Mandatory Zero Offers Are Just and Reasonable","method":"printed heading","endPage":8,"endAt":140,"startToken":1464,"endToken":2228},{"p":8,"at":140,"title":"C. The Risk Is Most Acute When Available RBP UCAP Precedes or Exceeds","method":"printed heading","endPage":10,"endAt":1197,"startToken":2228,"endToken":3052},{"p":10,"at":1197,"title":"D. Annual RBP Isolation and a Matched Demand Adjustment Will Preserve the","method":"printed heading","endPage":13,"endAt":795,"startToken":3052,"endToken":3897},{"p":13,"at":795,"title":"II. THE PHRASE “MAXIMUM FACILITY OUTPUT” IN TARIFF SECTION","method":"printed heading","endPage":15,"endAt":4,"startToken":3897,"endToken":4336},{"p":15,"at":4,"title":"III. QUALIFYING RBP OFFSET UCAP MW SUBMISSIONS SHOULD RECEIVE A","method":"printed heading","endPage":16,"endAt":327,"startToken":4336,"endToken":4680},{"p":16,"at":327,"title":"IV. LIMITED PROTEST OF CERTAIN CREDIT AND COLLATERAL PROVISIONS","method":"printed heading","endPage":17,"endAt":479,"startToken":4680,"endToken":5013},{"p":17,"at":479,"title":"V. THE MODIFICATIONS PROPOSED HEREIN COMPLY WITH NRG POWER","method":"printed heading","endPage":18,"endAt":1447,"startToken":5013,"endToken":5438},{"p":18,"at":1447,"title":"VI. CONCLUSION","method":"printed heading","endPage":20,"endAt":0,"startToken":5438,"endToken":5719},{"p":20,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":22,"endAt":250,"startToken":5719,"endToken":5812},{"p":22,"at":250,"title":"I. Qualifications and Purpose of Affidavit","method":"printed heading","endPage":23,"endAt":116,"startToken":5812,"endToken":6055},{"p":23,"at":116,"title":"II. Background","method":"printed heading","endPage":24,"endAt":1367,"startToken":6055,"endToken":6582},{"p":24,"at":1367,"title":"III. PJM Must Isolate the Impact of the RBP Central Procurement","method":"printed heading","endPage":29,"endAt":1060,"startToken":6582,"endToken":8027},{"p":29,"at":1060,"title":"IV. Recommendation","method":"printed heading","endPage":35,"endAt":41,"startToken":8027,"endToken":8920},{"p":35,"at":41,"title":"Attachment A","method":"printed heading","endPage":71,"endAt":1662,"startToken":8920,"endToken":18939}]}