{"document":{"slug":"rec-20260821-5270","title":"Post-Conference Statement of Constellation Energy Generation, LLC addressing issues raised at the Commissioner-led technical conference held on 07/23/2026…","issued":"2026-08-21","accession":"20260821-5270","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Constellation Energy Generation, LLC","kind":"testimony","file":"sources/filings/text/20260821-5270_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5270","tier":"record","sha256":"22be024ef2d91a4d6ec4aa34f963164859978278b9a8f3a44a4ecc2fa340cc10","pages":22,"tokens":7016,"emptyPages":[],"textThemes":["adequacy","retail"]},"pages":[{"page":1,"startToken":0,"endToken":261,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \n \nPJM Governance and Stakeholder Reforms \n) \n) \nDocket No. AD26-7-000 \n \n \n \n \nPOST-CONFERENCE STATEMENT OF  \nCONSTELLATION ENERGY GENERATION, LLC \n \nPursuant to the Commission’s July 30, 2026 notice in the above-captioned proceeding,1 \nConstellation Energy Generation, LLC (Constellation) submits these comments addressing issues \nraised at the Commissioner-led technical conference held on July 23, 2026, and responding to the \nCommission’s issues list found in the appendix of the Notice.    \nI. \nINTRODUCTION AND SUMMARY   \nConstellation commends the Commission for proactively addressing issues with the PJM \nstakeholder process.  While we caution against overhauling a governance process that, despite its \nchallenges, has led to the successful implementation of many market enhancements over the years, \nresulting in a regional market that saves consumers approximately $5 billion annually,2 there are \nnonetheless a number of reforms that can be made to improve the efficiency of the existing \nstakeholder process.  As explained in responses to the Commission’s questions, Constellation does \nnot support altering section 205 filing right authority or reforms that may result in undue political \ninfluence on market rules.  Most of the unrest in PJM over the last decade has involved issues \nrelated to resource adequacy, generator retirements and replacements, and capacity market rules \nchanges—matters over which PJM already has section 205 filing rights and is able to take action \n \n1 PJM Governance and Stakeholder Reforms, Notice Requesting Post-Conference Comment, Docket No. AD26-7-\n000 (July 30, 2026) (Notice).  \n2 The Value of PJM, PJM Interconnection, L.L.C. (Jan. 21, 2026), https://www.pjm.com/-/media/DotCom/about-\npjm/the-value-of-pjm.pdf."},{"page":2,"startToken":261,"endToken":573,"text":"2 \n \nunder section 205 even when the Membership disagrees.  Instead, Constellation urges the \nCommission to focus on reforms that are tailored to the problems the region is trying to solve, \nincluding the suggestions we offer herein (with a more detailed path forward in the appendix).   \nII. \nQUESTION RESPONSES \nA. PJM Board Independence \n1. Should Board members’ terms be extended to five or more years? \n \nYes.  Board terms should be lengthened to five years with two full terms possible, and \nsubstantive criteria should be considered for removing Board members.  Terms exceeding five \nyears may be too long of a commitment period for Board member candidates and could \ninadvertently limit Board member candidates.  Further discussion on this matter should be pursued. \n2. Should there be a maximum number of years that a Board member may serve (e.g., 10 \nyears)? \n \nYes.  See our response to Question 1.  Constellation generally agrees that a maximum number \nof years is reasonable and welcomes discussion on determining the most appropriate number of \nyears any Board member may serve.  For example, a limit of two, five-year terms—for a ten-year \ncap—could make sense.3   \n3. Should the Board member qualification rules be revised to provide a preference for some \nBoard members that reside in the PJM region?  \nYes.  The key focus on Board qualifications should remain (as it has in the past) on relevant \nexperience and expertise.  If strictly applied, a residency requirement risks diminishing the number \nof otherwise qualified Board candidates.  Nonetheless, the deeper appreciation of a region that \ncould be gained through living there (and being directly impacted by decisions made by the Board) \ncould be beneficial.  Constellation recommends a requirement that one PJM Board member reside \n \n3 We would suggest not counting years served replacing a Board member who is leaving the Board prior to the end \nof her/his term against the ten-year cap."},{"page":3,"startToken":573,"endToken":863,"text":"3 \n \nwithin the PJM footprint.  Having a one-member residency requirement is consistent with other \nBoard membership qualification quantities in Section 7.2 of the Operating Agreement that can be \nsatisfied with one qualified member (e.g., “one [member] shall have expertise and experience in \nthe operation or concerns of transmission dependent utilities, one [member] shall have expertise \nand experience in the operation or planning of transmission systems, and one [member] shall have \nexpertise and experience in the area of commercial markets and trading and associated risk \nmanagement”).4 \n4. Should the conflict-of-interest rules be revised to reduce the cooling off period for Board \nmembers from two years to one year? \n \nYes.  The two-year cooling off period may unduly limit the pool of candidates—who are \notherwise qualified—from Board participation.  A one-year cooling off period may be more \nappropriate and would be generally consistent with the Commission’s own cooling off period for \nformer Commissioners and senior Commission staff.5  \n5. Should restrictions on Board communications be relaxed to enable more communication \nbetween the Board and stakeholders? \n \nYes.  Additional opportunities for Board and stakeholder communications should be pursued \nas long as such additional communication opportunities are fair for all stakeholders and Board \nindependence is preserved.  \n6. In order to increase transparency, should Board votes be made public or the Board be \nrequired to explain its reasoning?  \nYes.  While disclosing individual Board member votes would chill robust Board discussion of \nissues and should remain non-public, the Board should be required to provide a written explanation \nsupporting its decisions and how the decision will achieve a just, reasonable and not unduly \n \n4 Operating Agreement, Section 7.2 (emphasis added). \n5 See 18 U.S.C. § 207(c); 5 C.F.R. § 2641.204."},{"page":4,"startToken":863,"endToken":1172,"text":"4 \n \ndiscriminatory or preferential outcome.  In addition, such explanation should include a discussion \nof why it rejected other views. \n7. In order to increase transparency, should some Board meetings be open or available to \nthe public? \nNo.  The PJM Board is a decision-making body, unlike the boards of some other RTOs/ISOs \nthat advise on decisions being made by the RTO/ISO leadership.  The PJM Board therefore needs \nan independent opportunity to deliberate, and requiring all deliberation to occur in a public arena \nwould chill effective Board meeting discussions.  Non-public Board meetings are necessary for \nefficient discussion of often very technical matters to support well-informed policy decisions.  To \nthe extent additional information on Board decisions is desired, this can be addressed through a \nBoard memo as described in our response to Question 6.  Additionally, the Board should consider \nmaking all relevant, non-confidential material presented by PJM staff, the market monitor, and \nother participants at Board meetings public contemporaneously with the meeting.  If additional \nBoard interaction with stakeholders is pursued, as suggested in our response to Question 5, it must \nbe fair for all stakeholders, preserve Board independence, and should be in addition to the existing, \nseparate Board meetings.   \n8. Should PJM’s governing documents be revised to explicitly state that the responsibility \nof PJM and its Board is to serve the public interest? \nNo.  PJM is already required to provide service consistent with the public interest by Federal \nPower Act (FPA), 16 U.S.C. § 824d(a), and it would be redundant and encourage disputes to \nattempt to restate that obligation in PJM’s governing documents using different words.     \n9. Should state representatives have at least one voting member on the Nominating \nCommittee? \nNo.  States can and should make their views known about selection of potential Board members \nby taking advantage of existing opportunities to engage.  This could include coordinating efforts"},{"page":5,"startToken":1172,"endToken":1463,"text":"5 \n \nby developing a list of suggested nominees, perhaps through OPSI or through the formation of \nnomination advisory group consisting of state-designated representatives.  Some suggest that the \nBoard member selection is “slanted” and “deep[ly] biased” and seek to have specific interests \ndominate the Nominating Committee.6  Those suggestions are not correct.  A number of prior \nparticipants in the Nominating Committee, including two current Constellation employees, signed \nan affidavit being submitted contemporaneously in this proceeding explaining the robust and fair \nnature of the Nominating Committees’ work.   \n10. Should PJM adopt public performance metrics and tie management compensation to \ntheir achievement? \nYes.  To the extent the Board already has or adopts performance metrics for senior PJM \nmanagement, those metrics should be made public. \n11. Should the stakeholder process be advisory, i.e., stakeholder votes only inform the \nBoard? \nNo.  The stakeholder process should not be made advisory-only and should remain as is for the \nreasons discussed below.7   \nPJM’s Section 205 Filing Rights Should Remain As Is \nPJM has authority to file changes to rules related to resource adequacy issues under section \n205.  Section 205 filings related to energy and ancillary market matters (Operating Agreement, \nSchedule 1) and to regional transmission planning matters (Operating Agreement, Schedule 6) are \nconditioned on PJM first obtaining Members Committee approval, and PJM has complained that \n“PJM may be required to proceed under more restrictive requirements of section 206 [if it does \n \n6 See, e.g., Pre-Technical Conference Statement of Jacob Finkel, Office of Governor Josh Shapiro, Deputy Secretary \nof Policy, Docket No. AD26-7-000, at 9 (July 16, 2026). \n7 We interpret the suggestion of an “advisory” stakeholder process to mean that PJM would have filing rights under \nsection 205 even if it would consider stakeholder input."},{"page":6,"startToken":1463,"endToken":1836,"text":"6 \n \nnot obtain Member Committee approval].”8  To avoid the “more restrictive” requirements of \nsection 206, PJM seeks discretion to file under section 205 for energy and ancillary service market \nand regional transmission planning matters even if the PJM Members disagree.9  As discussed in \nthe following sub-sections, PJM has no need for such authority, which could be more damaging \nthan helpful.  Moreover, PJM lacks a legal basis to abrogate the long-standing allocation of section \n205 filing rights.10   \nPJM’s Concern Is a Red-Herring and Is Unsupported \nVirtually all discussions of significance related to PJM in recent years focus on resource \nadequacy issues, where PJM already has section 205 authority.  For example, of the six principles \ninvolving PJM in the Statement of Principles Regarding PJM signed by the National Energy \nDominance Counsel and all thirteen PJM state governors, PJM already has section 205 filing rights \nover all six principles.11  PJM’s concern (particularly with respect to filing authority over the \nenergy and ancillary service markets) seem particularly out of place against this backdrop.  As \nConstellation’s Mason Emnett explained in a pre-conference statement filed in this proceeding:  \n[M]ost of the unrest in PJM over the last decade has involved issues \nrelated \nto \nresource \nadequacy, \ngenerator \nretirements \nand \nreplacements, and capacity market rules changes—matters over \nwhich PJM already has section 205 filing rights and is able to take \naction under section 205 even when the Membership disagrees. \nWhen PJM has delayed action, it has been because its leadership has \ndecided not to proceed, not because of any lack of authority. In the \n \n8 Comments from PJM Interconnection, L.L.C., Docket No. AD26-7-000, at 6 (July 16, 2026) (PJM Pre-Conference \nComments). \n9 Id. at 6-7; see also FERC Mediation Term Sheet, PJM Interconnection, L.L.C., Term 1 (Aug. 10, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20260819/20260819-item-08---1-\nferc-mediation-term-sheet.pdf.  \n10 As Constellation owns and operates generation assets, its focus in this discussion is on PJM authority over energy \nand ancillary services markets. \n11 Statement of Principles Regarding PJM, National Energy Dominance Council (Jan. 16, 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm.  The seventh principle, regarding cost \nallocation, involves only the PJM state governors and not PJM."},{"page":7,"startToken":1836,"endToken":2153,"text":"7 \n \nsame vein, PJM’s lack of section 205 rights over energy market \nissues has not deterred PJM’s action under section 206 when its \nleadership decided to proceed without Membership endorsement.12 \nThere is no evidence contradicting Mr. Emnett’s statement, and PJM’s concerns are \noverstated and unsupported.  For example, in its pre-conference comments, PJM lists nine \ninstances in recent years of a “failed” stakeholder vote.13  However, PJM’s recitation of recent \nstakeholder history deserves some scrutiny.  Of the nine “failed” stakeholder votes only one of the \nnine (i.e., 11%) did not involve a resource adequacy-related matter (over which PJM already has \nsection 205 filing authority).14  In other words, the stakeholder vote is already advisory for eight \nof the items listed, so PJM could file under section 205 regardless of the voting outcome.  For the \none item not covered under PJM’s section 205 rights, reserve requirement revisions, a majority \n(although not a required super-majority) of Members did support PJM’s proposal.  And a separate \nproposal on reserve deployment revisions was endorsed by acclamation.   \nPJM raised a single instance where it believes the lack of unfettered section 205 filing \nrights has undermined its ability to make needed reform (i.e., certain reserves markets \nimprovements).15  While Constellation fully supports reserve market improvements, we are \nconcerned, based on PJM’s track record with respect to resource adequacy (described below), \nwhether PJM would actually exercise its authority in a manner that alleviates, rather than \ncontributes to, the “credibility gap” discussed in PJM’s recent paper.  With respect to the issue of \nreserve market reforms referenced by PJM, Constellation notes that PJM failed to vigorously \npursue it in the designated senior task force, which contributed to its delay progressing through the \n \n12 Pre-Conference Statement of Mason Emnett on Behalf of Constellation Energy Generation, LLC, Docket \nNo. AD26-7-000, at 2 (July 16, 2026). \n13 PJM Pre-Conference Comments at 3-4. \n14 Id. at 4. \n15 Id."},{"page":8,"startToken":2153,"endToken":2588,"text":"8 \n \nstakeholder process.  It is PJM’s failure to timely articulate the needs and goals of the reserve \nstakeholder process, rather than Member voting, that is responsible for delay of these much-needed \nreforms.  If PJM believes this reserves change is critical, then it should not have allowed the \nstakeholder process to languish as it did and PJM should not be allowed to point to this process—\nwhere it contributed significantly to the delay—as justifying its claim for section 205 filing rights.   \nIn addition, rather than pursue complete abrogation of the Members’ long-standing section \n205 filing rights, PJM could pursue reform via other means.  Specifically, PJM can file a well-\nsupported proposal under section 206 of FPA.  Section 206 of the FPA is the long-established \nmeans for those lacking section 205 filing rights to seek recourse, and courts unsurprisingly agree \nthat section 206 provides an adequate remedy.16  PJM arguments that section 206 is “more \nrestrictive” compared to section 205 are not relevant under the FPA if there is no underlying right \nto file under section 205.  As the Commission found in a recent decision responding to a similar \nPJM complaint about section 206 filings, “the fact that PJM may benefit from what it views as a \nmore timely and efficient process under FPA section 205 compared to section 206 does not render \nthe [transmission planning] Protocol’s existing location in the OA to be unjust and \nunreasonable.”17  PJM has demonstrated skill at filing under section 206, particularly in response \nto an urgent situation,18 so it is unclear there is a problem at all.  Simply put, PJM has not \ndemonstrated that there is any meaningful issue that it cannot already address. \n \n16 See, e.g., Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520, 542 (D.C. Cir. 2010) (in the event of “an unjust \noutcome, San Diego may petition the Commission to order appropriate changes . . .  under section 206”).  \n17 Duquesne Light Co., 189 FERC ¶ 61,181, at P 106 (2024), order on reh’g, 192 FERC ¶ 61,051 (2025), aff’d sub \nnom. PJM Transmission Owners v. FERC, Nos. 25-1064, 25-1100, 2026 U.S. App. LEXIS 16255 (D.C. Cir. June 5, \n2026). \n18 See, e.g., PJM Interconnection, L.L.C., 178 FERC ¶ 61,104 (PJM filing to change transmission constraint penalty \nfactor contained within the Operating Agreement so as to avoid unjust and unreasonable energy market rates for \nconsumers on the Northern Neck peninsula in the Dominion Transmission Zone), order on reh’g, 179 FERC \n¶ 61,161 (2022), aff’d sub nom. Citadel FNGE Ltd. v. FERC, 77 F.4th 842 (D.C. Cir. 2023)."},{"page":9,"startToken":2588,"endToken":2936,"text":"9 \n \nThe Members’ Retention of Section 205 Filing Rights Was Heavily Negotiated and Cannot Be \nSet Aside Because PJM Wants Control \nNor can the Members Committee section 205 filing rights be abrogated simply because \nPJM wants control.  The allocation of those rights, as set forth in Sections 8.8 and 10.4 of the \nOperating Agreement, is entitled to Mobile-Sierra protection,19 meaning that by operation of law \nthe filing rights can only be abrogated upon a finding of “unequivocal public necessity” or \n“extraordinary circumstances.”20   \nSection 8.8 grants the Members Committee the authority to “amend any portion of this \nAgreement, including the Schedules hereto, or create new Schedules, and file any such \namendments or new Schedules with FERC.”21  This includes Schedule 1, which governs the energy \nand ancillary services markets.  Section 10.4 sets forth PJM’s duties and responsibilities, including \n“[filing] on behalf of the Members any amendments to this Agreement or the Schedules hereto, \nany new Schedules hereto, and mak[ing] any other regulatory filings on behalf of the Members or \nthe LLC necessary to implement this Agreement.”22  Thus, while the Members entered into an \nagreement that requires PJM to run the energy markets and to submit filings under section 205, \nPJM can only submit those filings on behalf of the Members, not on its own behalf. \nThe allocation of section 205 filing rights falls squarely within “contract rates” afforded \nMobile-Sierra protection.23  As Atlantic City Electric Company states, public utilities may only \ncede their section 205 filing rights “voluntarily,” that is “by contract” under the Mobile-Sierra \n \n19 United Gas Pipe Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332 (1956); FPC v. Sierra Pac. Power Co., 350 \nU.S. 348 (1956). \n20 Morgan Stanley Cap. Grp. Inc. v. Pub. Util. Dist. No. 1, 554 U.S. 527, 534, 551 (2008) (quoting Permian Basin \nArea Rate Cases, 390 U.S. 747, 822 (1968)). \n21 Operating Agreement, Section 8.8(ii). \n22 Operating Agreement, Section 10.4(xiii). \n23 NRG Power Mktg., LLC v. Me. PUC, 558 U.S. 165, 176 (2010)."},{"page":10,"startToken":2936,"endToken":3354,"text":"10 \n \ndoctrine,24 and the Commission has approved Mobile-Sierra’s application to such allocations of \nfiling rights between transmission owners and independent system operators across markets.25  \nIn addition, Sections 8.8 and 10.4 are the product of arm’s-length negotiations rather than \nnegotiations “aimed at protecting a common interest” among competitors.26  Sophisticated parties \nfreely negotiated these terms nearly thirty years ago in order to put in place an Independent System \nOperator for the PJM Power Pool.  From January through May 1997, transmission owners and a \n“large group of interested stakeholders”—including “two major independent power producers” \nand “two major power marketers”—“met continuously” with “the assistance of a professional \nfacilitator” to “resolve or narrow differences” and “forge consensus where possible” on issues of \n“ISO governance, reliability, transmission service and the structure of the energy market.”27  The \npowers of the Members Committee were among those provisions where “compromise” was \nachieved.28  The Supporting Companies Filing of the PJM Governing Documents stated that the \n“proposal to utilize sector voting” for the Members Committee “is the product of compromise with \nother stakeholders, even though it is not [their] preferred approach.”29   \n \n24 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 11 (D.C. Cir. 2002). \n25 See Pennsylvania-New Jersey-Maryland Interconnection, 105 FERC ¶ 61,294, at PP 32-33 (2003); PJM \nInterconnection, L.L.C., 108 FERC ¶ 61,318, at P 66 (2004) (finding that Mobile-Sierra application to the allocation \nof all filing rights between PJM and PJM Transmission Owners applies to “all transmission owner filings”); ISO \nNew England Inc., 106 FERC ¶ 61,280, at P 127 (2004) (approving application of Mobile-Sierra to allocation of \nfiling rights to transmission owners); Midwest Indep. Transmission Sys. Operator, Inc., 110 FERC ¶ 61,380, at \nPP 19, 25-26 (2005) (approving application of Mobile-Sierra to allocation of filing rights). \n26 PJM Interconnection, L.L.C., 142 FERC ¶ 61,214, at P 189 (2013). \n27 Filing of the PJM Supporting Companies, Docket Nos. ER97-3189-000, et al., Transmittal at 1-2, 6 (June 2, 1997) \n(Filing of PJM Governing Documents). \n28 Id., Transmittal at 6. \n29 Id., Attachment B at 3 n.1 (Compliance with Criteria for an Independent System Operator); see Pennsylvania-New \nJersey-Maryland Interconnection, 81 FERC ¶ 61,257, at 62,261-70 (1997) (conditionally accepting the Supporting \nCompanies proposal to restructure PJM as an ISO and form the PJM Operating Agreement, Transmission Owners \nAgreement, Tariff, and Reliability Assurance Agreement), reh’g denied, 92 FERC ¶ 61,282 (2000), modified sub \nnom. Atl. City Elec. Co., 295 F.3d 1."},{"page":11,"startToken":3354,"endToken":3765,"text":"11 \n \nMoreover, while Sections 8.8 and 10.4 apply to all Members, they preserve the existing rights \nof public utilities and do not “delimit, qualify, or restrict”30 the ability of any other market \nparticipant.  The “division of responsibility” between PJM and its Members “affect[s], \npredominantly[,] the contracting parties alone.”31  New Members have the same rights as the \noriginal parties.  Non-market generators and transmission owners retain their individual section \n205 filing rights, and all parties retain section 205 filing rights via the Members Committee, where \n“each major segment of the industry is assured a say” and “no one sector can force the Members \nCommittee to act, and no one sector can block the Members Committee from acting.”32  Indeed, \nthe Commission previously found that similar allocation of filing rights “adequately safeguarded \nthe interests of the region as a whole.”33 \nRelatedly, some argue that governance structures in other RTOs/ISOs that permit the RTO/ISO \nto file energy and ancillary services market rule changes under section 205 should apply in PJM.34  \nBut even if other RTOs/ISOs may have section 205 authority that PJM does not, that precedent is \nnot binding on PJM.  “The Commission has long recognized regional differences in each of the \nRTOs/ISOs and has specifically allowed for regional differences in RTOs’ governance structure.”35  \nThese differences make sense given “other RTOs/ISOs have different governance structures that \n \n30 PJM Interconnection, L.L.C., 142 FERC ¶ 61,214, at P 186. \n31 ISO New England Inc., 106 FERC ¶ 61,280, at P 130. \n32 PJM Governing Documents, Attachment B at 3. \n33 Midwest Indep. Transmission Sys. Operator, Inc., 110 FERC ¶ 61,380, at P 19. \n34 See, e.g., PJM Pre-Conference Comments at 8; Commission-Led Technical Conference on PJM Governance and \nStakeholder Reforms, Docket No. AD26-7-000, at 2:25:21 - 2:27:36 (July 23, 2026), https://www.ferc.gov/news-\nevents/events/PJM-Governance-Stakeholder-Reforms (Tech. Conf. Video) (PJM President and CEO, David Mills, \ndiscussing section 205 rights over the energy and ancillary services markets). \n35 Duquesne Light Co., 189 FERC ¶ 61,181, at P 108 (citing Order Nos. 1000 and 2000); see, e.g., Midcontinent \nIndep. Sys. Operator, Inc., 162 FERC ¶ 61,176, at P 57 (2018) (“[T]he Commission has consistently rejected a one-\nsize-fits-all approach in the various RTOs/ISOs due, in large part, to significant differences between each region and \nthat there can be more than one just and reasonable rate.”)."},{"page":12,"startToken":3765,"endToken":4225,"text":"12 \n \nwere arrived at through negotiations and tradeoffs that balance the rights and obligations of diverse \nstakeholders.”36  The division of filing rights in PJM reflect the stakeholder tradeoffs that were \nnegotiated in PJM to balance the rights and obligations among PJM stakeholders and the \nagreements struck among stakeholders in other regions does not reflect the PJM balance. \nInvestor Concerns Are Likely to Rise if PJM Authority Is Increased \nThe Commission should refrain from fundamentally overhauling filing rights in PJM, \nespecially at this critical time when significant investment is needed to meet tightening system \nconditions; simply put, a governance overhaul that includes additional PJM filing rights could \nundermine investor confidence in PJM at a time when their investment is most needed.  Investor \nconfidence and willingness to invest in assets in PJM is shaped by (among other things) PJM \nmarket outcomes and expectations in the rules that shape those market outcomes into the future.  \nActions by PJM that are counter to competitive market results undermine investor confidence in \nthe markets and the desire by competitors (and their owners) to invest.  The bottom line is that \nPJM has failed to appropriately consider investor impact in exercising the section 205 authority \nover resource adequacy matters it already has.  This is inconsistent with the Commission’s and \nAdministration’s desire to instill investor confidence and incent new infrastructure in PJM.37  And, \nagainst this backdrop, it is particularly difficult to justify increasing PJM’s filing authority. \n \n36 Duquesne Light Co., 189 FERC ¶ 61,181, at P 108. \n37 Chairman Laura Swett, Chairman Laura Swett’s Comments at PJM’s Annual Meeting in Baltimore, MD, FERC \n(May 12, 2026), https://www.ferc.gov/news-events/news/chairman-laura-swetts-comments-pjms-annual-meeting-\nbaltimore-md-0 (“[W]e cannot disrupt finalized commercial agreements.  At FERC, I have no appetite to \ncompromise investor confidence when those investors are driving the buildout of the generation that PJM \ndesperately needs.”); Tech. Conf. Video at 45:30-46:50 (the Honorable James P. Danly discussing the need to right \nthe capacity market with immediate resolution: “We are facing demand signals like we’ve never seen before. . . .  \nDon’t lose sight of the fact that we actually have to fix the problems that are inhibiting the biggest problem we have \nwhich is getting as much supply online as quickly as possible and doing so while protecting ratepayers. . . .  PJM’s \nBoard and as an institution needs to recommit itself to the market functions it was originally designed to oversee and \nexecute.”), 55:40-55:52 (Peter Lake: “[I]f were gonna have a market we’ve got to let it work.”), 56:55-57:27 (Peter \nLake: “[T]his is the only industry in the world that can stare in the face of trillions of dollars of expected investment \nand argue amongst each other so effectively as to scare off that investment.”)."},{"page":13,"startToken":4225,"endToken":4645,"text":"13 \n \nFor example, in February 2025, PJM filed—without Member Committee authorization—a \ncollar mechanism to apply in the capacity market during delivery years 2026/27 and 2027/28.  PJM \nmade this filing pursuant to existing authority to file under section 205 with respect to resource \nadequacy matters.38  A little over a year later, PJM filed to extend the collar to also cover the \n2028/29 and 2029/30 delivery years, again filing under section 205, based on its existing authority \nand without Member Committee authorization.39  The signal to investors from these repeated \nexercises of PJM’s section 205 filing rights is that market supply/demand fundamentals cannot be \ncounted on in PJM to support new investment; in other words, investors have learned to expect \nPJM to curb actual market results whenever supply becomes tight compared to demand in PJM,40 \nand they must factor that PJM intervention expectation when deciding whether to invest through \nmarket mechanisms.  As a result, in part, of PJM’s repeated artificial reductions in capacity market \nprices, investors will hesitate to bring new investment through the capacity market.  Indeed only \n524.7 MWs of new resources entered in PJM’s most recent capacity market auction, although some \nof the reticence was undoubtedly caused by the knowledge that the Reliability Backstop \nProcurement (RBP) was around the corner.41  Instead, investors will require something more (e.g., \na long-term, out-of-market contract such as those available under the RBP) before they will invest \nin the region, and this out-of-market contracting will be more costly in the long run compared to \n \n38 Proposal for Revised Price Cap and Price Floor for the 2026/2027 and 2027/2028 Delivery Years of PJM \nInterconnection, L.L.C., Docket No. ER25-1357, at 6 (Feb. 20, 2025) (Initial Collar Filing).  \n39 Proposal to Extend the Price Cap and Price Floor for the 2028/2029 and 2029/2030 Delivery Years of PJM \nInterconnection, L.L.C., Docket No. ER26-1556, at 6 (Feb. 27, 2026) (Collar Extension). \n40 Recent price trends in the oil industry provide a simple example of how supply/demand fundamentals would \ntypically affect price-outcome expectations.  World oil market prices have increased, as restrictions on oil shipments \n(i.e., supply) through the Strait of Hormuz and uncertainty related to such shipments has increased.  Conversely, oil \nprices have decreased as shipment certainty has increased.   \n41 2028/2029 Base Residual Auction Report, PJM Interconnection, L.L.C., 3, 7-8 (July 14, 2026), \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results-\nreport.pdf."},{"page":14,"startToken":4645,"endToken":5018,"text":"14 \n \nthe market-driven approach.   Given PJM’s repeated interventions in market outcomes, in order for \nPJM to restore market integrity and investor confidence, it will have to intentionally and \nconsistently embrace competitive markets that reflect market fundamentals.  With the current RBP \nproposal, Constellation is concerned that more of the inefficient out-of-market intervention likely \nwill be required. \nPJM has filed numerous other changes recently to resource adequacy market rules under its \nexisting section 205 authority that similarly undermine market outcomes and investor confidence \nincluding: the DPL-South market rerun;42 the treatment of Brandon Shores and Wagner as price \ntakers in capacity auctions despite not providing a Capacity Performance product;43 and PJM’s \nproposal to treat RBP resources as price takers.44   \nDuring the technical conference, PJM’s Senior Director of Stakeholder Affairs, David Anders, \nexplained that when PJM was initially formed, the asset owners did not have confidence in PJM, \nso they intentionally kept the transmission planning and energy and ancillary services markets \nmatters in the Operating Agreement so Members could retain oversight.45  Given PJM’s extensive \nmarket-undermining use of the section 205 authority it already has, Constellation, a significant \nasset owner in PJM, has little confidence in how PJM has used its existing section 205 authority \n \n42 See PJM Power Providers Grp. v. FERC, 96 F.4th 390 (3d Cir. 2024). \n43 See H.A. Wagner LLC, 187 FERC ¶ 61,176 (2024), order on contested settlement, 191 FERC ¶ 61,098, order on \nreh’g, 192 FERC ¶ 61,189 (2025), appeal pending, Petition for Review, Maryland Office of People’s Counsel v. \nFERC, No. 26-1050 (D.C. Cir. Mar. 2, 2026). \n44 See Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads of \nPJM Interconnection, L.L.C., Docket No. ER26-3380-000, at 56-60, 129-30 (July 31, 2026); Limited Protest of \nConstellation Energy Generation, LLC, Docket No. ER26-3880-000 (Aug. 21, 2026). \n45 Tech. Conf. Video at 6:00:10 – 6:01:20 (David Anders PJM history discussion noting that “there was a certain \nlevel of confidence that [asset owners] didn’t have at the time” in “turning over their assets to this new fledgling \norganization” which led them retaining certain PJM responsibilities under the Operating Agreement so they could \nmaintain some control over decisions affecting their assets)."},{"page":15,"startToken":5018,"endToken":5383,"text":"15 \n \nand does not support an expansion of PJM’s filing authority.  The Commission should be similarly \nconcerned.  \n12. Should PJM have section 205 filing rights over the energy market and ancillary \nservices unencumbered by the requirement to obtain approval of two-thirds of the \nMembers Committee? \nNo.  See our response to Question 11.  \n13. Should PJM have section 205 filing rights over Regional Transmission Expansion \nPlanning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of \nthe Members Committee? \nNo.  See our response to Question 11.  However, Constellation acknowledges that extending \nsection 205 filing rights to PJM for non-market matters raises issues that are different than filing \nrights over market matters. \n14. Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over \nresource adequacy and transmission cost allocation filings when a supermajority of \nOPSI agrees on an alternative proposal? \nNo.  States and organizations representing state interests seeking changes to PJM’s Tariff, \nmarket rules, or other governing documents have long-established rights to pursue such changes \nunder the FPA,46 and state entities have proven well-capable of exercising these rights.47  However, \nit would be inconsistent with the FPA for the states to have such rights, jump ball or otherwise.48  \nIn addition, as elaborated above in response to Question 11, even if some RTO/ISO allows a jump \nball right for certain membership organizations, those RTO/ISO rules are not dispositive for PJM.   \n \n46 16 U.S.C. § 824e. \n47 See, e.g., PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 (2025) (Governor Josh Shapiro and the \nCommonwealth of Pennsylvania price cap complaint that led PJM to submit its section 205 price collar filing); \nIndep. Mkt. Monitor for PJM v. PJM Interconnection, L.L.C., 174 FERC ¶ 61,212 (2021), order on reh’g, 178 FERC \n¶ 61,121 (2022) (granting consolidated complaints filed by several PJM state consumer organizations and denying \nrehearing thereof), aff’d sub nom. Vistra Corp. v. FERC, 80 F.4th 302 (D.C. Cir. 2023). \n48 See Joseph Kelliher, States Cannot Be Granted Filing Rights Under Section 205 of the Federal Power Act, Utility \nDive (July 27, 2026), https://www.utilitydive.com/news/states-ferc-filing-rights-section-205-pjm/826170/; 16 U.S.C. \n§ 824d."},{"page":16,"startToken":5383,"endToken":5674,"text":"16 \n \n15. Should the Members Committee have “jump ball” filing rights over the portions of the \ntariff where PJM has 205 filing rights when a supermajority of stakeholders approves \nan alternative proposal? \nNo.  Constellation supports retention of existing rights rather than the addition of “jump ball” \nrights.  In addition, as elaborated above in response to Question 11, even if some RTO/ISO allows \na jump ball right for certain membership organizations those RTO/ISO rules are not dispositive for \nPJM.   \nB. Stakeholder Process \n16. Should the approval threshold in the Members Committee be lowered from two-thirds \nsector-weighted voting? \nYes.  If the PJM Members Committee agrees to such a change, reducing the voting threshold \nto a majority vote could support the Commission’s goal of facilitating section 205 filings without \nupending PJM’s existing governance structure as some have suggested.   \n17. Should the voting rules barring affiliate votes, which apply to senior standing \ncommittees, also apply to lower-level committees? \n \nNo.  Affiliate voting is an important component for balancing interests within the PJM voting \nstructure.  Discussion at the lower level committees—where affiliate voting is relied on—are \nusually more technical and detailed in nature and having the diversity of interests makes for a more \nrobust vetting of issues.  At the senior level committees (Markets and Reliability and Members \nCommittees) each Member has only one vote, consolidating the interests to the primary voting \nmember on matters that have already been largely shaped at the lower committee. \nC. State Participation \n18. In addition to OPSI, should there be a second state representative group consisting of \ngovernors’ representatives and/or state legislators’ representatives? \nYes.  However, Constellation sees two potential approaches for enhancing governor \nrepresentation: (1) the “right-sizing” of OPSI, including increased staffing levels so it can cover"},{"page":17,"startToken":5674,"endToken":5964,"text":"17 \n \nits existing constituents as well as an OPSI-enhanced role in representing governors’ and \nlegislators’ interests; or (2) creating and funding a separate entity representing PJM governors and \nlegislators.    \nIn addition to providing these additional resources, protocols should be established for PJM to \nmeet regularly with state commissioners and/or commission staff to seek input on important \nmarket and transmission issues, rule changes, and other concerns, including both staff-to-staff and \nleadership-to-leadership meetings.  Also, clear processes for state commissions to request and \nreceive technical information and support on matters related to wholesale markets and/or \ninfrastructure planning and their interactions with state regulation and retail rates should be \nestablished. \n19. Should state representatives have a formal voting role in the stakeholder process \n(limited to certain topics, such as resource adequacy and regional transmission cost \nallocation) in addition to the consumer advocate votes?   \nNo.  Consumer interests are already represented through the state-designated consumer \nadvocates.  The relationship between state commissions and PJM was developed in a 2005 \nMemorandum of Understanding between PJM and OPSI which stated that while commissioners \nand their staff participate, deliberate, give input, and engage at all levels of the PJM stakeholder \nprocess they do not vote on any issue.49  Since then, state commissions and representatives have \nparticipated in the stakeholder process and have done so very effectively.  For example, the current \nVariable Resource Requirement curve that was endorsed by Members and approved by the \nCommission was based on a joint proposal between PJM and the office of the Vice Chair of the \n \n49 Memorandum of Understanding Between PJM Interconnection, L.L.C. and the Organization of PJM States, Inc., \nPJM Interconnection, L.L.C. (June 1, 2005), https://www.pjm.com/-/media/DotCom/documents/agreements/opsi-\npjm-memorandum.ashx."},{"page":18,"startToken":5964,"endToken":6337,"text":"18 \n \nPennsylvania Public Utilities Commission,50 and at OPSI’s request, PJM facilitated the Clean \nAttribute Procurement Senior Task Force in 2022 and 2023.51  \nStates are sovereign regulators and policy makers with the ability to make policy decisions that \nare outside of PJM jurisdiction.  That said, states can and have played an important, non-voting, \nrole in the PJM stakeholder process; including, for example, the initiation of the Sub-Annual \nCapacity Market Senior Task Force, spearheaded by the office of Pennsylvania Governor Josh \nShapiro.52  In addition, state commissions and representatives have a variety of opportunities to \ninteract with PJM staff and the PJM Board that are not available to voting Members, some of which \nare discussed in the 2005 Memorandum of Understanding.  To the extent that those opportunities \nneed to be enhanced or expanded, such as assigning a PJM Board member to act as a liaison with \neach state, Constellation welcomes further discussion on this matter.  However, providing the states \nwith an additional voting role at PJM would elevate their status compared to existing PJM voting \nMembers, including the state consumer advocates who have a critical role in representing retail \nratepayers.  Amending the Operating Agreement to include state commissions or representatives \nundermines that current, balanced governing structure at PJM that ensures that no Member has \nundue influence while recognizing and supporting the state’s important, non-voting role in the PJM \nstakeholder process and community.   \n \n50 See 2025 Periodic Review of Variable Resource Requirement Curve Shape and Key Parameters of PJM \nInterconnection, L.L.C., Docket No. ER26-455-000, at 7-8 (Nov. 7, 2025) (describing the Joint PJM/PA Public \nUtility Commission, Vice Chair Barrow proposal that received super-majority support from stakeholders and was \nadopted by the PJM Board without modification), accepted by PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, on \nreh’g, 196 FERC ¶ 61,007 (2026). \n51 Clean Attribute Procurement Senior Task Force, PJM Interconnection, L.L.C., https://www.pjm.com/committees-\nand-groups/closed-groups/capstf. \n52 Sub-Annual Capacity Market Senior Task Force, PJM Interconnection, L.L.C., https://www.pjm.com/committees-\nand-groups/task-forces/sacmstf (originating from Issue Charge, PJM Interconnection, L.L.C. (July 16, 2025), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2025/20250723/20250723-item-05---3-\nrevised-sub-annual-auction-issue-charge---clean.pdf)."},{"page":19,"startToken":6337,"endToken":6593,"text":"19 \n \n20. Should PJM be required to consult with OPSI prior to making a section 205 filing \nrelated to resource adequacy and transmission cost allocation? \nNo.  Such a consultation could give OPSI undue influence over PJM and thereby undermine \nPJM independence.53  \nIII. \nCONCLUSION \nConstellation appreciates the Commission’s leadership in addressing potential governance \nreforms and looks forward to participating in further discussion during the Dispute Resolution \nProceeding this September.  As discussed above, investor confidence in PJM has never been more \ncritical.  As the Commission considers potential reforms, it is imperative that such reforms \nimprove, not weaken, confidence in PJM’s markets when significant investment is needed to meet \ntightening system conditions.   \nRespectfully submitted, \n    /s/ Christopher A. Wilson \nCarrie Hill Allen  \nSr. Vice President & Deputy General  \nCounsel  \nConstellation Energy Generation, LLC  \n250 Massachusetts Ave. NW, Suite 760  \nWashington, D.C. 20001  \ncarrie.allen@constellation.com \n \nSara Gordon \nManager, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n1310 Point Street \nBaltimore, MD 21231 \nsara.gordon@constellation.com \nChristopher A. Wilson \nVice President, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \nFERCe-filings1@constellation.com \n \nMichael P. McLaughlin \nDirector, Federal Regulatory Affairs  \nConstellation Energy Generation, LLC \n1310 Point Street \nBaltimore, MD 21231 \nFERCe-filings1@constellation.com \n \n \nDated: August 21, 2026 \n \n53 See PJM Transmission Owners, 2026 U.S. App. LEXIS 16255, at *13-14 (proposed transmission owner right to \narbitrate PJM’s proposed section 205 filings “was not just and reasonable because it diminished PJM’s \nindependence” and “gives the Transmission Owners undue influence over Tariff modifications”)."},{"page":20,"startToken":6593,"endToken":6897,"text":"APPENDIX  \nPJM GOVERNANCE SETTLEMENT FRAMEWORK \n1. PJM Board  \na. Board Seat Duration \ni. Extend Board member term to five years, with two full terms (plus any time \nserved replacing an early-exiting Board member) possible; and \nii. Offer current Board the opportunity to extend their term to a five-year term, \nstill ensuring terms are staggered. \nb. Board Member Qualifications—(Operating Agreement, Section 7.2)1—New \nrequirements that: \ni. One member to reside within PJM – conforming changes within Operating \nAgreement Section 7.2 may be required to implement this change, \nincluding potentially shortening the two-year “stay-out” so as to increase \nthe Board member applicant pool; and \nii. One member has energy regulatory experience. \nc. Increased Transparency in Board Determinations – Board to provide a written \nexplanation supporting its decisions and how the decision will achieve a just, \nreasonable and not unduly discriminatory or preferential outcome along with an \nexplanation for why it rejected other views. \nd. Nominating Committee Role (Operating Agreement, Section 7.1) – states to make \ntheir views known about potential Board members by developing a list of \nsuggested nominees, perhaps through OPSI or through the formation of \nnomination advisory group consisting of state-designated representatives. \n2. State Focused Reforms \na. OPSI “Right-Sizing” \ni. OPSI funding/staffing levels to be increased so OPSI can effectively \nrepresent states at PJM and in stakeholder processes.   \nii. Governors’ interests to also be represented under the OPSI “umbrella” or \nalternatively to establish a stand-alone organization to facilitate \nparticipation by state elected officials. \nb. PJM/OPSI Engagement Protocols   \ni. Establish protocols for meeting regularly with state commissioners and/or \ncommission staff to seek input on important market and transmission \nissues, rule changes, and other concerns, including both staff-to-staff and \nleadership-to-leadership meetings. \n \n1 See PJM Board Member Qualifications Matrix, https://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/nc/postings/nc-board-member-qualifications-oa-section-7-2.pdf."},{"page":21,"startToken":6897,"endToken":6958,"text":"2 \n \nii. Establish a clear process for state commissions to request and receive \ntechnical information and support on matters related to wholesale markets \nand/or infrastructure planning and their interactions with state regulation \nand retail rates. \nc. State/Board Member Communications – Each state commission to have a Board \nmember assigned for periodic conversations on state priorities and other pressing \nPJM matters."},{"page":22,"startToken":6958,"endToken":7016,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 21st day of August 2026 served a copy of the foregoing \nupon all parties on the service list in this proceeding in accordance with Rule 2010 of the \nCommission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010. \n \n/s/ Sara Gordon \nConstellation Energy Generation, LLC"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":579,"startToken":0,"endToken":73},{"p":1,"at":579,"title":"I. INTRODUCTION AND SUMMARY","method":"printed heading","endPage":2,"endAt":289,"startToken":73,"endToken":306},{"p":2,"at":289,"title":"II. QUESTION RESPONSES","method":"printed heading","endPage":2,"endAt":314,"startToken":306,"endToken":309},{"p":2,"at":314,"title":"A. PJM Board Independence","method":"printed heading","endPage":16,"endAt":513,"startToken":309,"endToken":5463},{"p":16,"at":513,"title":"B. Stakeholder Process","method":"printed heading","endPage":16,"endAt":1612,"startToken":5463,"endToken":5625},{"p":16,"at":1612,"title":"C. State Participation","method":"printed heading","endPage":19,"endAt":267,"startToken":5625,"endToken":6379},{"p":19,"at":267,"title":"III. CONCLUSION","method":"printed heading","endPage":22,"endAt":0,"startToken":6379,"endToken":6958},{"p":22,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":22,"endAt":334,"startToken":6958,"endToken":7016}]}