{"document":{"slug":"rec-20260821-5273","title":"Limited Protest of the NRG Companies re PJM Interconnection, L.L.C.’s 07/31/2026 filing proposing a Reliability Backstop Procurement","issued":"2026-08-21","accession":"20260821-5273","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"NRG Business Marketing LLCAspen Gen Funding, LLCDirect Energy Business, LLC ,Doswell, LLC ,Energy Plus Holdings LLC ,Enerwise Global Technologies, LLC dba CPower ,Green Mountain Energy Company ,Helix Ironwood, LLC ,Independence Energy Group LLC ,LSP University Park, LLC ,Midwest Generation LLC ,NRG Curtailment Solutions, Inc. ,Reliant Energy Northeast LLC ,Riverside Generating Company, LLC ,Stream Energy Pennsylvania, LLC ,University Park Energy, LLC ,XOOM Energy, LLC ,","kind":"protest","file":"sources/filings/text/20260821-5273_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5273","tier":"record","sha256":"9b9cb875485a1836c6c32f32c6c750aaa080fad9fea9f825009a040d25e06139","pages":50,"tokens":14460,"emptyPages":[50],"textThemes":["adequacy","study"]},"pages":[{"page":1,"startToken":0,"endToken":355,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3380-000\nLIMITED PROTEST OF THE NRG COMPANIES \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (the “Commission”)1 and in accordance with the Commission’s notice \nissued August 3, 2026,2 the NRG Companies3 hereby submit this limited protest to the July 31, \n2026, filing by PJM Interconnection, L.L.C. (“PJM”)4 proposing a Reliability Backstop \nProcurement (the “RBP”), a one-time procurement of new capacity to cover shortfalls in the Base \nResidual Auctions for the 2027/2028 Delivery Year (the “2027/2028 BRA”) and 2028/2029 \nDelivery Year (the “2028/2029 BRA”).5  The NRG Companies are supportive of the RBP concept \nand are filing this limited protest with respect to two discrete and severable elements of the July 31 \nFiling that are not just and reasonable and should be modified.  For the reasons set forth herein and \n \n1  \n18 C.F.R. § 385.211 (2025). \n2  \nCombined Notice of Filings #1, Docket Nos. EC26-106-000, et al. (Aug. 3, 2026) (unreported). \n3  \nThe NRG Companies include the following subsidiaries of NRG Energy, Inc. (“NRG”): NRG \nBusiness Marketing LLC, Aspen Gen Funding, LLC, Direct Energy Business, LLC, Doswell Limited \nPartnership, Energy Plus Holdings LLC, Enerwise Global Technologies, LLC dba CPower, Green \nMountain Energy Company, Helix Ironwood, LLC, Independence Energy Group LLC, LSP University \nPark, LLC, Midwest Generation LLC, NRG Curtailment Solutions, Inc., Reliant Energy Northeast LLC, \nRiverside Generating Company, LLC, Stream Energy Pennsylvania, LLC, University Park Energy, LLC \nand XOOM Energy, LLC.  The NRG Companies have separately moved to intervene in this proceeding.  \nSee (doc-less) Motion to Intervene of NRG Business Marketing LLC, et al., Docket No. ER26-3380-000 \n(filed Aug. 21, 2026). \n4  \nCapitalized terms not defined herein have the meaning set forth in PJM’s Open Access \nTransmission Tariff (the “PJM Tariff”) or the Reliability Assurance Agreement Among Load Serving \nEntities in the PJM Region (the “RAA”). \n5  \nReliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large \nLoads, Docket No. ER26-3380-000 (July 31, 2026) (the “July 31 Filing”)."},{"page":2,"startToken":355,"endToken":618,"text":"2 \nin the affidavit of John R. Morris, Ph.D., provided in Attachment A hereto (the “Morris Affidavit”) \nand the affidavit of Thomas E. Atkins provided in Attachment B hereto (the “Atkins Affidavit”), \nthe NRG Companies respectfully urge the Commission to accept the July 31 Filing subject to the \nmodifications proposed herein. \nI. \n \nBACKGROUND \nAs indicated in the July 31 Filing, both the 2027/2028 BRA and the 2028/2029 BRA \ncleared at the market price cap of $325/MW-day and over 6 GW short of the applicable PJM \nRegional Reliability Requirement.6  In the July 31 Filing, PJM proposes the RBP to procure \ncapacity outside the Reliability Pricing Model (“RPM”) construct to a target based on the shortfall \nin the 2028/2029 BRA for commitment periods of up to 15 years ending, in all cases, with the \n2042/2043 Delivery Year.7  PJM describes the RBP as “a critical safety net designed to address \ncurrent resource adequacy shortfalls”8 and explains that the 15-year term is informed by the \nstatement of principles agreed between and among governors of PJM states and the National \nEnergy Dominance Council,9 “which seeks ‘[r]evenue [c]ertainty to [n]ew [g]eneration’ through \n‘15-year price certainty for new capacity resources.’”10 \n \n6  \nSee id., Transmittal Letter at 7-8. \n7  \nSee id. at 8. \n8  \nId. at 26. \n9  \nD. Burgum, et al., Statement of Principles Regarding PJM (Jan. 15, 2026) (“Statement of \nPrinciples”), https://www.energy.gov/documents/statement-principles-regarding-pjm. \n10  \nJuly 31 Filing, Transmittal Letter at 48 (alteration in original) (quoting Statement of Principles \nat 1)."},{"page":3,"startToken":618,"endToken":894,"text":"3 \nThe RBP will be a pay-as-bid auction conducted for three weeks following Commission \nacceptance of the July 31 Filing.11  PJM proposes a soft cap, or “maximum willingness to pay,”12 \nof $555/MW-day applied to all selected offers on a MW-weighted average basis over all Delivery \nYears of the RBP.13  This figure represents the cap that would have applied under the Variable \nResource Requirement (“VRR”) curve for the 2028/2029 BRA but for the separate price collar.14   \nRBP commitments will be settled as contracts-for-differences with the seller’s offer price \nas the strike price and the RPM Auction clearing price as the market price.15  Subject to a narrow \nexception, a supplier with an RBP commitment is required to submit price-taker offers into RPM \nAuctions for the Delivery Years covered by its RBP commitment.16  PJM states that this \nrequirement is meant to ensure that “load does not double pay for capacity.”17 \nII. \n \nPROTEST \nAs noted, the NRG Companies generally support PJM’s RBP proposal as a necessary “stop-\ngap solution[]”18 to fill the reliability gap.  Nonetheless, there are two elements of that proposal \nthat are not just and reasonable and that must be modified to ensure that the RBP serves its intended \npurpose and does not create further market distortions that will, in turn, necessitate further one-off \nsolutions.  First, the soft cap is set at a level that does not adequately reflect current costs of adding \n \n11  \nSee id. at 65. \n12  \nId. at 61. \n13  \nSee id. \n14  \nSee id. at 62. \n15  \nSee id. at 79-80. \n16  \nSee id. at 56. \n17  \nId. at 57. \n18  \nId. at 5."},{"page":4,"startToken":894,"endToken":1237,"text":"4 \nnew resources to the system and that will, therefore, greatly increase the risk that the RBP fails to \nfulfill its role as “a critical safety net designed to address current resource adequacy shortfalls.”19  \nSecond, the price-taker requirement for offers into RPM Auctions from resources with RBP \ncommitments should be eliminated, and an offer floor should be imposed if and to the extent that \nthe associated load does not materialize in order to prevent systematic price distortion. \nImportantly, the proposed modifications do not present concerns under NRG Power \nMarketing, LLC v. FERC,20 because PJM has “consent[ed] to the Commission’s exercise of \nauthority to modify and/or sever any element of the proposed [PJM] Tariff and RAA \nlanguage . . . [,] where such modification and/or severance is consistent with PJM’s overarching \nobjectives in this filing.”21  As PJM notes, the July 31 Filing “is not a stakeholder compromise \npackage,”22 so these modifications will not upset the terms of a proposal that was “the subject of \nextensive negotiation and compromise among PJM’s stakeholders.”23  And the NRG Companies’ \nproposed modifications, while important, are “minor deviations” from PJM’s proposal,24 that will \nnot have the Commission “transform[ing] [PJM’s] proposal into an entirely new rate of FERC’s \nown making.”25  \n \n19  \nId. at 26. \n20  \n862 F.3d 108 (D.C. Cir. 2017) (“NRG-PML”). \n21  \nJuly 31 Filing, Transmittal Letter at 3. \n22  \nId. at 132. \n23  \nHecate Energy LLC v. FERC, 126 F.4th 660, 667 (D.C. Cir. 2025). \n24  \nNRG-PML, 862 F.3d at 115 (quoting Western Res., Inc. v. FERC, 9 F.3d 1568, 1579 (D.C. Cir. \n1993)). \n25  \nId. at 110.  See also City of Winnfield v. FERC, 744 F.2d 871, 875-76 (D.C. Cir. 1984) (suggesting \nthat a utility acquiescing to a Commission proposal that “involved the Commission’s own original notion \nof a new form of rate” could “remove[] the Commission from an essentially passive and reactive role \nenvisioned by § 205 and place[] it in a more active role of the sort it occupies under § 206”)."},{"page":5,"startToken":1237,"endToken":1620,"text":"5 \nPJM requests that if the Commission requires modifications, it “expressly prescribe the \nrevised rate or rule in its order.”26  In keeping with that request, the NRG Companies have proposed \nspecific modifications to the RBP proposal that the Commission could expressly prescribe as \nconditions to its acceptance of the July 31 Filing. \nA. \nAny Soft Cap Should Be Set at a Level Reflecting Current Costs of Resources Whose \nCapacity Could Be Procured through the RBP \nPJM fails to carry its burden to demonstrate that setting the RBP soft cap at $555/MW-day \nis just and reasonable.  PJM asserts that its “proposal to limit the maximum willingness to pay is \nnecessary,” because “[t]he RBP is not disciplined by direct buy bids that explicitly express \nwillingness to pay.”27  According to PJM, “it is not reasonable to assume that load should be \nobligated to pay an unlimited amount for supply.”28  The $555/MW-hour figure was calculated \nbased on outdated estimates of the cost of new entry (“CONE”) and the energy and ancillary \nservices revenues for the reference combustion turbine (“CT”) in PJM’s most recent quadrennial \nreview.  As such, it is not representative of the current CONE for such a unit, much less of the \ncosts of other resources whose capacity could be procured through the RBP, including resources \nwhose technology or circumstances do not match those of the reference CT. \nAs an initial matter, while the NRG Companies understand the “consumer protection \nconsiderations”29 that have prompted PJM’s decision to impose a cap, it bears emphasis that the \nCommission’s statutory mission under the Federal Power Act is not just to protect consumers from \n \n26  \nJuly 31 Filing, Transmittal Letter at 131. \n27  \nId. at 63.  The suggestion that PJM’s proposed soft cap represents load’s “willingness to pay,” id., \nis, at best, dubious.  The soft cap was not calculated based on any value of lost load study or other analysis \nintended to assess load’s actual willingness to pay for capacity being procured through the RBP.  See Morris \nAffidavit at ¶ 12.  Rather, it would simply be an administratively determined limit on what PJM will pay. \n28  \nJuly 31 Filing, Attachment C, Affidavit of Danielle Croop on Behalf of PJM Interconnection, \nL.L.C. at ¶ 26 (the “Croop Affidavit”). \n29  \nId., Transmittal Letter at 62."},{"page":6,"startToken":1620,"endToken":1927,"text":"6 \nexcessive rates but “to encourage the orderly development of plentiful supplies of electricity . . . at \nreasonable prices.”30  As Dr. Morris observes, running the RBP with any cap necessarily increases \nthe risk that the RBP will clear short, because if the cap binds, PJM will not procure the full RBP \ntarget.31  As he puts it, the assumption implicit in the soft cap proposal is that “it is just and \nreasonable to sacrifice reliability in exchange for lower RBP Prices.”32  With the last two BRAs \nhaving failed to procure adequate, much less plentiful, supplies of capacity, the NRG Companies \ndo not believe such a sacrifice is justified, particularly when, as Dr. Morris notes, “[m]arket power \nis not a concern with the prices in the [RBP].”33  The top priority here should be allowing the RBP \nto fulfill its purpose of covering the shortfall.   \nFurther, the assumed tradeoff between reliability and cost does not exist.  It is true that the \ncap, if it binds, will sacrifice reliability for lower RBP prices.  But, as Dr. Morris explains, the \ninterplay between the RBP and the RPM Auctions is such that, over time, consumers will have \nsacrificed reliability in exchange for higher, not lower, prices overall.34  If the soft cap binds and \nthe RBP clears short, there will be less capacity available for future RPM Auctions (or other \ncapacity constructs to incent current capacity to stay in the market), which will increase the single \nclearing prices paid to all capacity cleared in those auctions.35  Dr. Morris observes that the \nincreased costs resulting from higher clearing prices in those future RPM Auctions – which will \n \n30  \nNAACP v. FPC, 425 U.S. 662, 670 (1976). \n31  \nSee Morris Affidavit at ¶ 10. \n32  \nId. at ¶ 13. \n33  \nId. at ¶ 23. \n34  \nSee id. at ¶ 14. \n35  \nSee id. at ¶ 16."},{"page":7,"startToken":1927,"endToken":2293,"text":"7 \nimpact all consumers, not just the large loads for which the RBP is meant to procure capacity – are \nlikely to dwarf the added cost of acquiring more capacity through the RBP.36 \nEven assuming arguendo that some cap is appropriate, PJM fails to explain why a soft cap \nbased on CONE for the reference CT in the last quadrennial review is a just and reasonable level \nfor this soft cap.  The best it can offer is that the longer commitment term provides benefits to \nsuppliers such that “it is reasonable to conclude that PJM’s willingness to pay for a 15-year \ncommitment should not exceed the amount that load would be willing to pay for a single-year \ncommitment under the RPM framework for the targeted Delivery Year.”37  But the RBP is not a \nBRA.  A BRA is a single clearing-price auction for a uniform commodity with a downward sloping \ndemand curve designed to send price signals “guiding resource entry and exit.”38  In contrast, the \nRBP is a one-time, pay-as-bid auction being conducted solely for the purpose of procuring enough \nnew capacity to cover the shortfall from the last two BRAs.39  Indeed, PJM itself highlights the \ndistinct nature of the RBP, including the fact that it is “not . . . procuring a uniform commodity”40 \nand that it has no “‘marginal unit’ in any meaningful sense of the term . . . .”41   \nThe NRG Companies do not disagree with the implicit assumption that, all other things \nbeing equal, a supplier should be willing to accept a lower price for a commitment of up to 15 \nyears than it would be for the one-year commitment obtained through an RPM Auction.  The \n \n36  \nSee id.  \n37  \nJuly 31 Filing, Transmittal Letter at 64. \n38  \nPJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at 70 (2025). \n39  \nSee July 31 Filing, Transmittal Letter at 25-26 (“The RBP is designed to be a one-time mechanism \nfor procuring new capacity (i.e., UCAP MW only) to address the PJM Region shortfall observed in the \nBRA for the 2027/2028 and 2028/2029 Delivery Years caused by the rapid load growth in the PJM \nRegion.”). \n40  \nId. at 65. \n41  \nId. at 66."},{"page":8,"startToken":2293,"endToken":2601,"text":"8 \nproblem is that, as is often the case, all other things are not equal.  There are a number of material \nrisks concerning both the costs associated of new construction as well as the risks and costs of \nproviding service out 15 Delivery Years, including, but not limited to, indeterminate network \nupgrade costs that may be allocated to a new project, costs and risks associated with uncertainty \nabout potential changes in Effective Load Carrying Capability, fuel delivery costs, and energy and \nancillary services prices.  Indeed, Dr. Morris explains that the $450/MW-day energy and ancillary \nservices offset underlying the $555/MW-day soft cap exacerbates the risk surrounding future \nenergy and ancillary services prices, as this level is substantially higher than past offsets and the \naverage of the offsets over the previous nine BRAs, which would be $225.49/MW-day.42 \nThere is no logical reason why the prices paid to individual suppliers in the RBP should be \nsubject to a cap based on CONE for a CT when the capacity shortfall could be covered with any \nnumber of resources, including resources using different technologies or having other \ncharacteristics that cause their costs to significantly exceed those of the reference CT.  None of \nthat variation is captured in the price of the reference CT, which is only “a representative, \ntheoretical new plant.”43  As the Commission has observed, a “reference unit is hypothetical, and \nthe actual new entrant may be different . . . .”44  That the costs of new entry can vary dramatically \nbased on technology and location is illustrated by the range of default MOPR Offer Floor Prices \n \n42  \nSee Morris Affidavit at ¶ 21. \n43  \nPJM Interconnection, L.L.C., 194 FERC ¶ 61,049 at P 2 (the “Quadrennial Order”), on reh’g, 196 \nFERC ¶ 61,007 (2026). \n44  \nISO New England Inc., 175 FERC ¶ 61,172 at P 127 (2021)."},{"page":9,"startToken":2601,"endToken":2951,"text":"9 \nfor the 2028/2029 BRA, which ranged from $68.69/MW-day (UCAP) for a CT in the APS zone to \n$3,135.04/MW-day (UCAP) for a solar project in the PECO zone.45  \nNRG’s real-world experience confirms that actual costs can and do differ significantly from \nthe $555/MW-day calculated based on the reference CT’s CONE.  Mr. Atkins, NRG’s Vice \nPresident of Development, explains that NRG has several development projects that are \nsufficiently advanced to participate in the RBP.  One of these projects, which would be located in \na historically import-constrained zone and would provide significant locational benefits, has costs, \nnet of expected energy and ancillary services revenues, that are substantially greater than the \ncurrent proposed cap.46  Given the costs and size of this project, it would be hard to justify the time \nand expense of even offering it into the RBP if it is conducted with a soft cap of $555/MW-day.47 \nFinally, even as a measure of the reference CT’s CONE, the CONE value underlying the \n$555/MW-day is outdated. As PJM has recognized, “capital costs have escalated sharply” in recent \nyears.48  The $555/MW-day cap is based on a gross CONE estimate of $776/MW-day calculated \nin a CONE study concluded over a year ago.49  As Dr. Morris and Mr. Atkins observe, capital costs \nhave continued to escalate sharply since that time.50 \n \n45  \nSee PJM, Default New Entry MOPR Offer Prices (Mar. 16, 2026), https://www.pjm.com/-/media/\nDotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-default-new-entry-mopr-offer-prices. \nxlsx. \n46  \nSee Atkins Affidavit at ¶ 16. \n47  \nSee id. \n48  \nPJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained \nSupply, and Stimulating Investment To Support Durable Reliability at 4 (May 6, 2026) (“Powering \nReliability”), \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/2026\n0506-powering-reliability-through-market-design.pdf. \n49  \nSee 2025 Periodic Review of Variable Resource Requirement Curve Shape and Key Parameters at \n5-7, Docket No. ER26-455-000 (filed Nov. 7, 2025) (discussing the CONE study process), accepted, \nQuadrennial Order, 194 FERC ¶ 61,049. \n50  \nSee Morris Affidavit at ¶¶ 18-19; Atkins Affidavit at ¶¶ 13-15."},{"page":10,"startToken":2951,"endToken":3268,"text":"10 \nIf the Commission is not going to eliminate the soft cap, the NRG Companies would urge \nthe Commission to reset it at a level reflecting a more current estimate of the reference CT’s CONE \nand an energy and ancillary services offset that better accounts for the risks around future energy \nand ancillary services prices.  Dr. Morris calculated such a cap price using an updated CONE of \n$900/MW-day51 and the average of the energy and ancillary services offsets for the nine BRAs \nprior to the 2028/2029 BRA ($225/MW-day).52  This calculation yields a soft cap of $866/MW-\nday.53  If the RBP is going to be run with a soft cap, the NRG Companies urge that the soft cap be \nreset at $866/MW-day, which will reduce the risk that the RBP clears short. \nB. \nThe Commission Should Impose a Price Floor on Offers for Resources with RBP \nCommitments to the Extent the Load Prompting the RBP Does Not Materialize \nAs Dr. Morris explains, the proposed requirement that resources with RBP commitments \noffer as price-takers into RPM Auctions for the associated Delivery Years “is antithetical to \ncreating a normal capacity market.”54  PJM itself has recognized the “credibility trap” where “[t]he \nsignal that is required to attract investment is the same signal that triggers the intervention that \nundermines it.”55  After interventions that produced “unsustainably low price levels for three \ndelivery years,”56 Dr. Morris states, “the market is waiting for PJM – and implicitly, the \nCommission – to make credible moves that they will not allow capacity prices to crash to levels \nthat make new investments likely unprofitable over the life of the assets.”57  In this environment, \n \n51  \nSee Morris Affidavit at ¶ 19. \n52  \nSee id. at ¶¶ 21-22. \n53  \nSee id. at ¶ 22. \n54  \nSee id. at ¶ 25. \n55  \nPowering Reliability at 24. \n56  \nMorris Affidavit at ¶ 29. \n57  \nId. at ¶ 31."},{"page":11,"startToken":3268,"endToken":3556,"text":"11 \nthe price-taker offer requirement “send[s] the wrong signals [to] potential investors of PJM \ngeneration capacity.”58   \nTo be clear, a requirement that resources with RBP commitments offer as price-takers is \nnot necessary to ensure that load does not pay twice for the same capacity.  Dr. Morris describes \nan alternative approach that would achieve the same result without such a requirement.59  Under \nthis approach, commitments would be structured so that any RBP capacity that does not clear in \nan RPM Auction has its strike price reset to zero for that RPM Auction and all future RPM Auctions \nfor the remainder of the commitment period.60  The RBP supplier would have a compelling \nincentive to ensure that its capacity clears the RPM Auctions, but it would still be a voluntary \nchoice.61 \nEven if the price-taker offer requirement is retained, the Commission should direct PJM to \nestablish a narrow exception to this requirement that would apply when the forecasted load for \nwhich PJM is procuring through the RBP does not materialize.  In the July 31 Filing, PJM proposed \nmeasures to protect load in the event new capacity procured through the RBP does not materialize62 \nand to protect cooperatives and municipal utilities “if a particular large load included in the forecast \nwere to fail to materialize.”63  What is missing is any comparable measure to preserve the integrity \nof future RPM Auctions if the forecasted large load does not materialize.  The Commission should \ndirect PJM to impose an offer floor on RBP resources if and to the extent the forecasted large loads \n \n58  \nId.  \n59  \nSee id. at ¶ 27. \n60  \nSee id. \n61  \nSee id. \n62  \nSee July 31 Filing, Transmittal Letter at 60-61. \n63  \nId. at 45."},{"page":12,"startToken":3556,"endToken":3911,"text":"12 \nnecessitating the RBP do not actually appear.  The NRG Companies propose that such a floor be \nset at $175/MW-day (UCAP), which was the floor price applied as part of the price collar in the \nRPM Auctions for the 2026/2027, 2027/2028, 2028/2029 and 2029/2030 Delivery Years.64 \nAs noted above, PJM has proposed that resources with RBP commitments be required to \nsubmit price-taker offers (i.e., offers priced at $0/MW-day) into RPM Auctions for the Delivery \nYears of their RBP commitments in order to “ensure[] that load does not double pay for capacity.”65  \nIf the forecasted load for which the RBP is procuring capacity materializes as expected, the price-\ntaker offer requirement will approximate the outcome in which both the RBP load and RBP supply \nare excluded from future RPM Auctions.  If the large loads do not materialize, however, the price-\ntaker offer requirement will depress prices in the RPM Auctions, and this “stop-gap solution[]”66 \nto the shortfall in two BRAs could be another in a series of interventions that undermine the \nviability of PJM’s capacity market.  To prevent such an outcome, the NRG Companies propose \nthat an offer floor of $175/MW-day (UCAP) apply to offers from resources with RBP \ncommitments equal to the forecasted load does not materialize, if and to the extent such a situation \noccurs.  While a floor set at each resource’s actual cost, which would likely be higher than \n$175/MW-day, would also be justifiable, the NRG Companies propose using the previously \naccepted $175/MW-day for the sake of simplicity and uniformity. \n \n64  \nSee PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 (“PJM I”) (accepting price collar, including \n$175/MW-day (ICAP) price floor, for the RPM Auctions for the 2026/2027 and 2027/2028 Delivery \nYears), on reh’g, 192 FERC ¶ 61,258 (2025) (“PJM II”); PJM Interconnection, L.L.C., 195 FERC ¶ 61,076 \n(2026) (“PJM III”) (accepting price collar, including $175/MW-day (ICAP) price floor, for the RPM \nAuctions for the 2028/2029 and 2029/2030 Delivery Years). \n65  \nJuly 31 Filing, Transmittal Letter at 57. \n66  \nId. at 5."},{"page":13,"startToken":3911,"endToken":4234,"text":"13 \nIn accepting $175/MW-day (UCAP) as part of the price collar, the Commission found that \nit “reasonably narrows potential auction outcomes to maintain investor confidence.”67  The \nCommission also agreed with PJM that the price floor “help[ed] to broadly assure investors in \ncapacity supply that in cases where PJM finds it appropriate to intervene in its capacity market in \nextraordinary circumstances, those interventions will not be one-sided.”68  That is, the price floor \nmakes clear that, “in extraordinary circumstances like these, PJM will not leave investors \ndisproportionately exposed to the downside risk of lower market prices and reduced capacity \nrevenues.”69  By its terms, the RBP is an extraordinary intervention:  it is a “one-time, \nsupplementary mechanism to procure additional supply to meet the resource adequacy needs of \nthe PJM Region”70 outside the RPM construct.  With multiple gigawatts of resources being \nawarded commitments of up to 15 years and being required to be offered on a price-taker basis for \nthe duration of those commitments, investors will naturally be concerned about the potential \nimpact that this intervention will have on clearing prices in future RPM Auctions if the \n“unprecedented addition of large loads . . . in the PJM Region”71 does not actually come to pass \nand need assurance that this “intervention[] will not be one-sided.”72  The proposed offer floor \nwould provide such assurance, will have limited applicability (i.e., only in a volume equal to the \nforegone load), and will apply to a quantity no greater than that procured in the RBP. \n \n67  \nPJM I, 191 FERC ¶ 61,066 at P 55.  See also PJM III, 195 FERC ¶ 61,076 at P 51 (finding extension \nof the price collar appropriate “to narrow the range of potential price outcomes”). \n68  \nPJM II, 192 FERC ¶ 61,258 at P 31. \n69  \nId. \n70  \nJuly 31 Filing, Transmittal Letter at 7. \n71  \nId. at 1. \n72  \nPJM II, 192 FERC ¶ 61,258 at P 31."},{"page":14,"startToken":4234,"endToken":4393,"text":"14 \nIII. \n \nCONCLUSION \nFor the reasons set forth herein, the NRG Companies respectfully request that the \nCommission condition its acceptance of the July 31 Filing on the modifications proposed herein. \nRespectfully submitted, \nNRG BUSINESS MARKETING LLC \nASPEN GEN FUNDING, LLC \nDIRECT ENERGY BUSINESS, LLC \nDOSWELL, LLC \nENERGY PLUS HOLDINGS LLC \nENERWISE GLOBAL TECHNOLOGIES, LLC DBA CPOWER \nGREEN MOUNTAIN ENERGY COMPANY \nHELIX IRONWOOD, LLC \nINDEPENDENCE ENERGY GROUP LLC \nLSP UNIVERSITY PARK, LLC \nMIDWEST GENERATION LLC \nNRG CURTAILMENT SOLUTIONS, INC. \nRELIANT ENERGY NORTHEAST LLC \nRIVERSIDE GENERATING COMPANY, LLC \nSTREAM ENERGY PENNSYLVANIA, LLC \nUNIVERSITY PARK ENERGY, LLC \nXOOM ENERGY, LLC \nBy: \n  /s/ David G. Tewksbury \n \nDavid G. Tewksbury \nStephanie S. Lim \nMCDERMOTT WILL & SCHULTE LLP \nThe McDermott Building \n500 North Capitol St., NW \nWashington, DC  20001 \nCortney Madea Slager \nVice President & Assistant General Counsel \nJennifer S. Hsia \nAssistant General Counsel \nBrianna Anderson \nRegulatory Counsel \nNRG Energy, Inc. \n804 Carnegie Center \nPrinceton, NJ  08540 \nCounsel for the NRG Companies \nDated:  August 21, 2026"},{"page":15,"startToken":4393,"endToken":4450,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day caused the foregoing document to be served upon each \nperson designated on the official service list compiled by the Secretary of the Federal Energy \nRegulatory Commission in this proceeding. \nDated at Washington, D.C., this 21st day of August 2026. \n  /s/ David Tewksbury \n \n \nDavid G. Tewksbury"},{"page":16,"startToken":4450,"endToken":4455,"text":"Attachment A \nThe Morris Affidavit"},{"page":17,"startToken":4455,"endToken":4489,"text":"Attachment A \n \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \nDOCKET NO. ER26-3380-000 \n \n \n \n \nON BEHALF OF \n \nNRG ENERGY, INC. \n \n \n \n \n \nAugust 21, 2026 \n \n \n \n \n \n \n \n \nAFFIDAVIT OF \nJOHN R. MORRIS"},{"page":18,"startToken":4489,"endToken":4700,"text":"Attachment A \n \n \nPage 2 of 17 \n \n \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C. \nDOCKET NO. ER26-3380-000 \n \nAFFIDAVIT  \nOF  \nJOHN R. MORRIS \n \n1. My name is John R. Morris, and my business address is 2121 K Street, Northwest, \nWashington, DC.  I am currently employed as a Managing Director at Secretariat \nAdvisors LLC.  I was retained by NRG Energy, Inc. (“NRG”) to opine on issues related \nto the price cap and must offer conditions of the Reliability Backstop Procurement \n(“RBP”) proposal that PJM filed with the Commission on July 31, 2026 (“RBP \nProposal”).  \n2. I received a bachelor’s degree in economics from Georgetown University and a \nmaster’s degree and a Ph.D. in economics from the University of Washington.  My \nprimary field is industrial organization, which is the study of company behavior in \ncompetitive, oligopolistic, and monopolistic markets.  This field also covers the \nbusiness regulation of companies through the antitrust laws and the price and entry \nregulation of electric and natural gas utilities.  \n3. I have been studying and consulting in the energy industry since joining the Federal \nTrade Commission in 1985.  At the Federal Trade Commission, I served as a staff \neconomist, a Commissioner Advisor, and as the Assistant to the Deputy Director for"},{"page":19,"startToken":4700,"endToken":4962,"text":"Attachment A \n \n \nPage 3 of 17 \n \n \n \n \n \nAntitrust.  As a staff economist, I focused much of my time on investigations of the \nnatural gas industry and became familiar with rate-setting principles in that industry \nat both the federal and state levels.  \n4. Since joining what is now Secretariat in 1992, I have consulted on many matters \ninvolving electric and natural gas companies, examined issues relating to utility rates, \nexamined issues concerning undue discrimination by operators of natural gas and \nelectric power transmission facilities, calculated damages, and calculated amounts of \nalleged unjust enrichment.  I have worked for a wide range of clients including many \ngovernmental entities—e.g., the Antitrust Division of the U.S. Department of Justice, \nthe Federal Trade Commission, the City of San Antonio, the City of San Diego, and \nthe New Jersey Board of Public Utilities—and many major corporations—e.g., \nAmerican Electric Power Corporation, Berkshire Hathaway Energy, Energy Transfer \nPartners, Exelon Corporation, Public Service Enterprise Group Incorporated, Tampa \nElectric Company, TC Energy Corporation, and WEC Energy Group. The Federal \nEnergy Regulatory Commission (“the Commission” or “FERC”), state public utility \ncommissions, and federal courts have accepted me as an expert witness on energy \nmatters.  \n5. I have conducted a wide range of professional activities during my career.  I have \nspoken before the Commission, the U.S. Department of Justice, and the Federal \nTrade Commission.  I have published articles in journals such as the Antitrust Bulletin, \nthe Journal of Regulatory Economics, the Electricity Journal, and Public Utilities \nFortnightly.  Formerly I was the chairman of the Antitrust Committee of the Energy"},{"page":20,"startToken":4962,"endToken":5226,"text":"Attachment A \n \n \nPage 4 of 17 \n \n \n \n \n \nBar Association.  I have previously taught economics at the University of Washington, \nIndiana University, and Stanford University (Washington, DC, campus).  A complete \nlisting of my experience, publications, and testimony is contained in my resume, \npresented in Attachment A2. \n6. I have been studying the PJM market for about 30 years.  My research has included \nstudies into the functioning of PJM markets, the resulting rates, and the competitive \neffects of mergers and acquisitions.  This breadth of research gives me an historical \nperspective of how the PJM market has evolved over the years.  My opinions below \nare based upon this historical perspective as well as my examination of the RBP \nProposal. \n7. Although the RBP Proposal has many elements, the following are the essential \nelements for my affidavit.  PJM will conduct a RBP to acquire up to 6,831.3 MW \nUnforced Capacity (“UCAP”).  (RBP Proposal at 31.)  This amount will be decreased \nto the extent that qualifying bilateral contracts matching new capacity to large loads \nare identified before the RBP.  The net amount will be the RBP Target.  The RBP will \nbe a pay-as-bid solicitation, so each contract would have a different price.  The RBP \nProposal has a “Soft Cap” of $555/MW-day, so that the average procurement price \n(“RBP Price”) cannot be above this average.  The capacity that is accepted in the \nprocurement will be the “RBP Capacity.” \n8. I support the concept of the RBP.  From the original construct of the capacity market, \nit was envisioned that, when PJM does not procure sufficient capacity via its capacity"},{"page":21,"startToken":5226,"endToken":5543,"text":"Attachment A \n \n \nPage 5 of 17 \n \n \n \n \n \nauctions, it would be able to procure capacity directly to ensure system reliability.  \nThat was one of the main reasons to have a three-year forward auction: it would give \nPJM time to solicit contracts for new capacity before the delivery year if the auction \ndid not clear sufficient capacity for reliability. \n9. In this affidavit I discuss two aspects of the RBP Proposal.  First, I will discuss the \nSoft Cap.  We can all hope that PJM will be able to procure the full “Final RBP Target” \n(up to 6,800 MW) at an average price below the Soft Cap so that it is not binding.  But \nif the Soft Cap is binding, then PJM will procure less than this amount.  As discussed \nin more detail below, failing to procure the full Final RBP Target of capacity is likely \nto raise prices in subsequent Base Residual Auctions (“BRAs”) and hence raise \nprices to residential customers in PJM.  Therefore, I recommend that the Commission \neither eliminate the Soft Cap or raise it to a level reflecting more recent costs facing \nthe industry for procurement and construction of new supply resources.  Second, I \ndiscuss the requirement that for 15 years all the capacity procured in the RBP be \noffered into the BRAs at zero prices.  Although this has some appeal, other more \nmarket-oriented solutions can achieve just and reasonable prices without a \nrequirement that makes it more difficult to achieve the goal of returning PJM capacity \nprices to market fundamentals.  Although my preference would be that the \nCommission not mandate zero-priced offers in the BRAs for the RBP resources and \ninstead give incentives to clear the capacity, I would recommend that, at a minimum, \nthe Commission establish an offer floor for RBP resources that would apply if and to \nthe extent that the large loads prompting the need for the RBP do not materialize."},{"page":22,"startToken":5543,"endToken":5850,"text":"Attachment A \n \n \nPage 6 of 17 \n \n \n \n \n \nI. \nThe “Soft” Price Cap of $555/MW-Day Can Only Serve to Raise Costs to \nResidential Customers \n10. The Soft Cap is pitched in the RBP Proposal as a just and reasonable limit on the \nwillingness to pay for new capacity.  (RBP Proposal, at 62.)  We can all hope that \nsufficient capacity at low enough prices is available so that the Soft Cap will not \nbecome binding.  But if the Soft Cap is binding—that is, PJM does not purchase the \nfull RBP Target because the Soft Cap requires PJM to reject offers from willing \nsellers—then the main effect of the Soft Cap is to raise capacity prices in general, \nand indirectly to residential customers.  Accordingly, I recommend that the \nCommission does not accept the proposed Soft Cap; or, at a minimum, the \nCommission raises the Soft Cap to reflect increases in costs and uncertainty for new \nconstruction since PJM’s last Cost of New Entry (“CONE”) study. \n11. The Soft Cap is a mechanism by which PJM will procure capacity only if the quantity-\nweighted average prices of the accepted pay-as-bid prices are less than $555/MW-\nday.  (RBP Proposal, at 63.)  This is a “soft” price cap because it does not limit every \naccepted price to be equal or less than $555/MW-day, but PJM can pay more than \n$555/MW-day for one or more contracts if the prices for other RBP contracts are \nsufficiently low so that the overall average of purchases is less than or equal to \n$555/MW-day. \n12. Although the RBP Proposal couches the Soft Cap as a “willingness to pay” (RBP \nProposal, at 61–64.), it is not based on any studies of the actual willingness to pay.  \nFor energy, the willingness to pay is measured in the Value of Loss Load (VOLL).  I"},{"page":23,"startToken":5850,"endToken":6163,"text":"Attachment A \n \n \nPage 7 of 17 \n \n \n \n \n \nhave seen estimates of VOLL as high as $17,000/MWh, and those estimates were \nfor 20 years ago.  In the instant case, the question is what is the incremental \nprobability of having to shed load when PJM is 6,800 MW short of what is necessary \nto ensure a load shed even only once every 10 years.  The RBP Proposal does not \ncalculate, and does not claim, that the load would be willing to pay more than \n$555/MW-day for 15 years of capacity and additional reliability.  Moreover, as \ndiscussed below, load will be willing to pay more than the average of $555/MW-day \nfor incremental capacity for the likelihood of lower capacity prices in future BRAs.     \n13. In other words, in a mechanism designed to procure capacity to ensure reliability, \nPJM is claiming that it is just and reasonable to sacrifice reliability in exchange for \nlower RBP Prices.  BRAs are already intended to provide a mechanism to attract and \nretain the resources needed to maintain reliability; however, the BRA process has \nprice caps and recognizes that at times it may not procure sufficient capacity and it \nwill be necessary for PJM to run a supplemental procurement process.  Given that \nPJM is already short and into the backstop process, placing a price cap on the RBP \nprocess says that PJM, and implicitly the Commission, are willing to force operators \nto shed load when capacity would be available but for the caps.  There is no backstop \nto the backstop.  \n14. In this case, however, such a trade-off between prices and reliability is misplaced \nbecause total capacity costs to Load Serving Entities (“LSEs”) and consumers would \nlikely be less over time if supply is brought into balance with demand than if the Soft \nCap is adopted by the Commission and shortages persist.  The reason is that the Soft"},{"page":24,"startToken":6163,"endToken":6456,"text":"Attachment A \n \n \nPage 8 of 17 \n \n \n \n \n \nCap comes into play only if PJM procures less capacity for at least one auction.  \nAlthough there would be no effect for delivery years in which the BRA has already \noccurred—for example, the 2028/2029 delivery year—effects would likely occur in \nsome future delivery years.   \n15. To provide an example, I use the prices used in the RBP Proposal; specifically, I \nassume that an offer for $800/MW-day is rejected because the price is too high and \nthe maximum acceptable price is $720/MW-day given all the other offers to sell \ncapacity.  (RBP Proposal at 63.)  For ease of exposition, I assume that PJM would \nnot acquire 1,000 MW of capacity because of the Soft Cap. \n16. Not acquiring capacity means that less capacity would be available in some future \nBRAs.  Given the demand slope parameters for the BRA for the 2028/2029 delivery \nyear, not clearing 1,000 MW of capacity under normal market conditions would raise \nmarket prices by $76.43/MW-day.  Based on a reliability requirement of 145,000 MW \nper day, that amounts to an annual difference in payments of $4 billion per year.  In \ncomparison, the added cost of acquiring capacity at $800/MW-day is only $29 million \nper year.  To the extent that the additional capacity is truly needed to meet reliability \nrequirements, it is economically rational that paying a little more for capacity the \nconsumers in PJM would likely pay substantially less for capacity until the market \nsettles toward prices consistent with the long-run price of capacity. \n17. The value of $555/MW-day, although couched as consistent with the PJM Tariff (RBP \nProposal, at 61–62), is an outdated number.  It is based upon a Brattle Report,"},{"page":25,"startToken":6456,"endToken":6726,"text":"Attachment A \n \n \nPage 9 of 17 \n \n \n \n \n \nreleased in April 2025.  (Newell, Thompson, Zhou, et al., Brattle 2025 CONE Report \nfor PJM, Informing Parameters for PJM’s RPM Auctions for Delivery Year 2028/29 \nthrough \n2031/32, \n§ \nII \n(Apr. \n9, \n2025), \nhttps://www.brattle.com/wp-\ncontent/uploads/2025/04/Brattle-2025-CONE-Report-for-PJM.pdf \n(“Brattle \n2025 \nCONE Report”).)  This report led to a Gross CONE value of $776/MW-day for the \nBRA for the 2028/2029 delivery year, and an Energy and Ancillary Service (“EAS”) \noffset of $450/MW-day.  (PJM, 2028/2029 RPM Base Residual Auction Planning \nParameters, \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-\ninfo/2028-2029/2028-2029-planning-period-parameters-for-base-residual-\nauction.xlsx.)  Using these figures, the cap is $555/MW-day (equal to 1.15 x \n$776/MW-day – 0.75 x $450/MW-day).   \n18. Both Brattle and PJM acknowledge the generation costs are increasing.  For \nexample, the Brattle 2025 CONE Report states that: “Supply shortages and volatile \nprice premiums may last for several years until supply chains can develop sufficient \ncapacity to support demand.”  (Brattle 2025 CONE Report, at 2.)  PJM has \nacknowledged, “[c]apital costs have escalated sharply” in recent years.  (PJM, \nPowering Reliability Through Market Design, May 6, 2026, at 4.)  Accordingly, it is \nreasonable to increase the $555/MW-day Soft Cap to reflect increases in costs. \n19. Updating this figure to 2026 costs would increase the Soft Cap to $697/MW-day.  The \nBrattle 2025 CONE Report indicates that the CONE for the reference combustion \nturbine have increased about 47% over three years, or about 13% each year.  Hence, \nadding another year would increase costs by about another 13%.  As for the math,"},{"page":26,"startToken":6726,"endToken":7003,"text":"Attachment A \n \n \nPage 10 of 17 \n \n \n \n \n \n1+47% multiplied by 1+13% gives 1+66%; that is, a 13% increase in costs on top of \na 47% cost increase results in a 66% cost increase compared to the starting \nperiod.  This increase is consistent with reports that construction costs for gas-fired \ngeneration have increased 66% in the past three years.  (Josh Saul, Cost to Build a \nNatural Gas-Fired Power Plant Surges 66%, BNEF Says, EnergyNow Media, April \n23, 2026, https://energynow.com/2026/04/cost-to-build-a-natural-gas-fired-power-\nplant-surges-66-bnef-says/.)  In addition, the RBP contracts are for at most 15 years, \nwhereas the CONE calculation is based upon 20 years.  The shorter period would \nincrease annualized costs by about another 3%.  Combining these changes would \nproduce a total cost increase of about 16%.    This would increase the Gross CONE \nto $900/MW-day, and the BRA price cap to $697/MW-day.     \n20. Another factor is that the PJM CONE estimate assumes only $22 million for \ninterconnection costs.  This is based upon an average of completed interconnections.  \n(Brattle 2025 CONE Study, at  43.)  In my experience reviewing many interconnection \nstudies and agreements, many developers essentially wait until transmission \nupgrades are made so that they are able to reduce their interconnection costs.  But \nthat will not be the case with the RBP; the capacity will need to come online as soon \nas possible.  Interconnection costs can easily be double or triple the average figure.  \nThis can greatly increase the cost of entry, and it is a risk that many new \ndevelopments will have.  A higher Soft Cap would help to account for this and other \nuncertainties that developers will face to satisfy RBP obligations."},{"page":27,"startToken":7003,"endToken":7316,"text":"Attachment A \n \n \nPage 11 of 17 \n \n \n \n \n \n21. Another major uncertainty over 15 years is the EAS offset of $450/MW-day underlying \nthe proposed $555/MW-day Soft Cap.  This is the highest EAS offset in 10 years, and \nperhaps ever.  The average EAS offset over the prior nine BRAs is only $225.49/MW-\nday, not significantly different from the average of the three prior BRAs, of \n$228.79/MW-day.  The lowest EAS offset during this period was only $91.67/MW-\nday.  Moreover, as more solar facilities and batteries enter the system, the net margin \nin the reference technology, a natural gas-fired combustion turbine, has a strong \nchance of falling significantly over 15 years.  This creates substantial risks for \ngeneration that is making a fixed capacity price commitment for 15 years. \n22. Accounting for the historical EAS value of $225/MW-day would produce a Soft Cap \nof $866/MW-day.  This is equal to the measure of $697/MW-day discussed above, \nadding back in 0.75 x $450/MW-day (unique EAS offset for the 2028/2029 delivery \nyear), and subtracting 0.75 x $225/MW-day (historical average EAS offset).  At a \nminimum I recommend that the Commission raise the Soft Cap to $866/MW-day.  \nHaving a cap significantly below $866/MW-day creates the risk that developers will \nnot submit economically efficient offers because they believe that there is no feasible \nway for their projects to be accepted in the RBP. \n23. Market power is not a concern with the prices in the auction.  As Danielle Croop \nstates, with a pay-as-bid auction format the price of a contract does not affect the \nprice of other contracts.  (Croop Aff., at Par. 33.)  In such a situation, each project is \nindependent in pricing and that eliminates the incentive to withhold a project to raise \nthe prices on other projects.  In addition, these contracts involve the construction of"},{"page":28,"startToken":7316,"endToken":7537,"text":"Attachment A \n \n \nPage 12 of 17 \n \n \n \n \n \nnew capacity, and the Commission has previously found that “absent entry barriers, \nlong-term capacity markets are inherently competitive because new market entrants \ncan build alternative generating supply.”  (Market-Based Rates for Wholesale Sales \nof Electric Energy, Capacity and Ancillary Services by Public Utilities, 119 FERC ¶ \n61,295, Order No. 694, P 122 (2007).)  And here there clearly are no barriers to entry.  \nA survey by Charles River Associates found that 87 organizations with over 136 GW \nof supplies would be interested in participating in a procurement auction.  (Charles \nRiver Associates, PJM Reliability Backstop RFI Summary, May 27, 2026, at 5.)  If the \naverage price of accepted projects were over $555/MW-day, the Commission can be \nassured that the reason for the higher than hoped for average was due to the actual \ncost of installing generation in PJM and not companies attempting to exercise market \npower. \n24. In short, letting the market work and revealing the true cost of installing generation in \nPJM is the policy that is most likely to minimize capacity costs for most consumers in \nPJM.  This is consistent with NEDC/PJM Governors’ Principles that PJM should \nreturn to market fundamentals.  (Statement of Principles Regarding PJM, National \nEnergy \nDominance \nCouncil, \n1 \n(Jan. \n16, \n2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm  \n(“NEDC/PJM Governors’ Principles”).)"},{"page":29,"startToken":7537,"endToken":7831,"text":"Attachment A \n \n \nPage 13 of 17 \n \n \n \n \n \nII. \nA Zero Must Offer Price Is Inconsistent with Returning PJM to Market \nFundamentals \n25. The RBP Proposal also has a requirement that the RBP Capacity must offer that \ncapacity into the BRAs at a price of zero to ensure that it clears the auctions.  In their \nprotest, the NRG Companies propose an offer floor of $175/MW-day (UCAP)—the \nsame price as the floor incorporated into the price collar applied in the capacity \nauctions for the 2026/2027, 2027/2028, 2028/2029 and 2029/2030 Delivery Years—\napply to the extent the forecast load prompting the RBP does not materialize.  For \nthe reasons discussed below, requiring capacity to be offered into the BRAs at zero \nis antithetical to creating a normal capacity market.  Accordingly, I recommend that \nthe Commission adopt alternative measures to protect the buyers and consumers in \nPJM. \n26. A must offer requirement is reasonable given that the purpose of the RBP is to \nprocure capacity to serve PJM for 15 years.  (RBP Proposal, 56–57.)  It is also \nreasonable to require that the capacity be offered into PJM and not to be allowed to \nsell RBP Capacity into markets outside of PJM.  (RBP Proposal, at 57.)  Finally, it is \nreasonable that load will receive the benefit of the capacity it will pay for under the \nRBP, if all the capacity procured is truly needed to meet the reliability requirement.  \n(RBP Proposal, at 57.)   \n27. Markets evolve and 15 years is a long time.  Instead of specifying a zero offer price \nfor the full 15 years, contracts could be structured so that any uncleared capacity has \nits strike price set to zero for that BRA and all future BRAs until the end of the contract."},{"page":30,"startToken":7831,"endToken":8116,"text":"Attachment A \n \n \nPage 14 of 17 \n \n \n \n \n \nThat would provide a strong incentive to clear the capacity and provide equal \nprotection to the buyer.  The buyer would never “double pay” for capacity because \nthe seller would be forced to “pay” for the capacity that the buyer would implicitly \nacquire from the BRA.  To avoid losing the secure income stream the seller might \nwillingly offer the capacity with a price-taking offer, but that would be a voluntary \nchoice of the seller. \n28. NRG proposes placing a price floor of $175/MW-day on the seller’s capacity offers to \nensure a just and reasonable outcome in BRA auctions should the load that \nnecessitated the RBP procurement not materialize.  I support the concept of a floor \non capacity prices in PJM in general today and on offers if not on auction prices.  \nSuch a floor will would lead to lower capacity prices over time, not higher prices, as \nthe floor provides greater certainty on cost recovery and hence less risks for the \nowners of new generation. \n29. Although this is not the forum to reform PJM’s capacity market, some perspective on \nthe necessity of the procurement is reasonable.  The main function of the BRAs is to \nacquire sufficient generation capacity to provide electricity reliably.  With its \nperformance capacity proposal, PJM proposed and the Commission accepted a \nsystem that provided for new capacity that was replacing retiring capacity and \nmatching load growth.  The RTO capacity prices under that system ranged from \n$76.53/MW-day to $164.77/MWh, with an average of $120.33/MW-day.  Some \nthought these prices were “too high” and sought rule changes to reduce capacity \nprices.  They were successful, and capacity prices crashed to the range of"},{"page":31,"startToken":8116,"endToken":8401,"text":"Attachment A \n \n \nPage 15 of 17 \n \n \n \n \n \n$28.92/MW-day to $50/MW-day, an average of $37.68/MW-day, for the 2022/2023 \nthrough the 2024/2025 delivery years.  These prices were too low to maintain capacity \nin the market.  Although it is difficult to identify exactly how much capacity retired \nbecause of the low prices, I estimate it to be about 10,000 MW.  The effect has been \nsubstantially higher RTO prices to the range of $269/MW-day to $333/MW-day in the \npast four auctions.  And the only reason that BRA prices were not higher in the last \nthree auctions is that the Commission adopted a “collar” that capped the prices to \naround $330/MW-day in exchange for a floor of $175/MW-day.  In short, attempts to \nlower prices resulted in prices being substantially above the levels that they would \nhave been but for the actions that resulted in unsustainably low price levels for three \ndelivery years.  \n30. PJM recognizes that it now has a “credibility trap.”  Because of intervention at \nreasonable capacity price levels that crashed those prices to unsustainably low \nlevels, “[i]nvestors, anticipating further intervention, discount the durability of the \n[current high] price signal. Capital stays on the sidelines; the shortage persists.”  \n(Powering Reliability, at 5-6.) \n31. Short of significant structural change, like adopting the California system for resource \nadequacy, the market is waiting for PJM—and implicitly, the Commission—to make \ncredible moves that they will not allow capacity prices to crash to levels that make \nnew investments likely unprofitable over the life of the assets.  Steps to force even \nmore generation capacity to offer into auctions zero prices are sending the wrong \nsignals potential investors of PJM generation capacity."},{"page":32,"startToken":8401,"endToken":8690,"text":"Attachment A \n \n \nPage 16 of 17 \n \n \n \n \n \n32. We know that PJM virtually always needs capacity prices at sufficiently high levels to \nfinance new generation capacity.  Even with a 60-year life of capacity, a market with \nabout 180,000 MW of installed capacity (“ICAP”) needs to replace 3,000 MW of \ncapacity each year just to maintain the current fleet size.  And 3% demand growth \neach year would produce a need for an additional 5,400 MW of capacity.   \n33. The net CONE value in the last auction was $316/MW-day.  Given this value and the \ndire need for new capacity in PJM, a price floor of $175/MW-day, or about 55% of the \nNet CONE value, appears the minimum just and reasonable value to give investors \nmore confidence in capacity prices in PJM. \n34. Placing a capacity price floor and allowing generation owners greater flexibility in \nsubmitting offers would be consistent with the desires of the National Energy \nDominance Counsel and the PJM Governors to return to a normal functioning market \nas soon as possible.  Not enough dispatchable capacity is in the PJM interconnection \nqueue to provide for future reliability.  Commitments to price floors are necessary to \nprovide investors with the incentives to invest in PJM.  \n35. The NRG proposed offer floor of $175/MW-day, to be implemented only if the \nexpected demand levels do not materialize, is a more modest proposal.  It helps to \nprotect the market only under the circumstance that this RBP is not necessary for \nreliability.  The protection is limited because it would not prevent capacity prices from \nfalling below $175/MW-day if PJM has vastly overestimated demand.  At most it \nwould establish a flat section in the capacity offer curve at $175/MW-day.  Moreover,"},{"page":33,"startToken":8690,"endToken":8811,"text":"Attachment A \n \n \nPage 17 of 17 \n \n \n \n \n \nalthough it is desirable for load not to “double pay” for capacity, it is not just and \nreasonable for PJM to acquire capacity that the market does not need and force \ngeneration owners to receive unsustainably low capacity prices.  Removing the \nexcess capacity from the BRAs by an offer price floor of $175/MW-day is a more \nmodest step to achieve just and reasonable prices in the subsequent BRAs. \n36. This concludes my affidavit. \n \n \n \nVERIFICATION \n \n \nPursuant to 28 U.S.C. §1746, I state under penalty of perjury that the foregoing is true \nand correct to the best of my information, knowledge, and belief. \n \nExecuted this 21st day of August, 2026 \n \n \n___________________________________________ \nDr. John R. Morris"},{"page":34,"startToken":8811,"endToken":9156,"text":"Qualifications of Dr. Morris \n \nAttachment A2 \n \n \nPage 1 of 10 \n \n \n \n \n \n \n \nEXPERIENCE AND QUALIFICATIONS OF \nDr. John R. Morris \n \nOVERVIEW \nDr. Morris, a recognized expert in studying competition and price formation in energy \nindustries, currently is a Managing Director at Secretariat Advisors LLC (formerly \nEconomists Incorporated).  He began his research of competition in energy industries in \n1985 while working for the Federal Trade Commission.  Since joining Economists \nIncorporated in 1992, he has consulted on many mergers and acquisitions involving \nenergy companies, examined competitive issues relating to rates, and studied issues in \nstate restructuring proceedings. He has published articles on competition and energy \nmatters, and he has spoken on numerous occasions concerning competition in natural gas, \nelectric power and other industries.  He has been accepted as an expert witness on energy \nmatters before the Federal Energy Regulatory Commission, state regulatory \ncommissions, and in federal and state courts. \n \nEDUCATION \nPh.D., University of Washington, August 1985 Dissertation: Intellectual Property: \nCreating, Pricing, Copying • M.A., University of Washington, December 1983 • A.B., \nGeorgetown University, May 1981 \n \nPRESENT POSITION \nDr. Morris is a Managing Director at Secretariat Advisors LLC, an economic consulting \nfirm located at 2121 K Street, NW, Suite 1100, Washington, DC  20037.  (202-223-4700) \nSecretariat Advisors studies competition and regulation in many industries in the United \nStates and in other countries.  It is a leading firm in studying the competitive effects of \nmergers and acquisitions, damages, construction costs, and construction delay. \n \nPREVIOUS EXPERIENCE \nPrincipal, Economists Incorporated, December 2002 – July 2021 •  Senior Vice \nPresident, Economists Incorporated, December 2001 – December 2002 • Vice President, \nEconomists Incorporated, December 1995 – December 2001 • Senior Economist, \nEconomists Incorporated, June 1992 – December 1995 • Economic Tutorial Leader, \nStanford University (Stanford in Washington), April 1993 – June 1995 • Visiting \nAssistant Professor, Department of Business Economics and Public Policy, School of \nBusiness, Indiana University, September 1991 – May 1992 • Assistant to the Director for \nAntitrust, Bureau of Economics, Federal Trade Commission, November 1989 – August \n1991 • Economic Advisor, Office of Commissioner Machol, Federal Trade Commission, \nDecember 1988 – October 1989 • Economist, Division of Antitrust, Bureau of \nEconomics, Federal Trade Commission, October 1985 – December 1988"},{"page":35,"startToken":9156,"endToken":9541,"text":"Qualifications of Dr. Morris \n \nPage 2 of 10 \n \n \n \n \n \n \n \n \n \nMEMBERSHIPS \nMember, International Association of Energy Economics • Associate, Energy Bar \nAssociation • Member, American Economic Association • Member, Western Economic \nAssociation International • Associate, American Bar Association \n \nAWARDS & HONORS \nAward for Excellence in Law Enforcement, Federal Trade Commission, 1988 • Graduate \nSchool Scholarship, University of Washington, 1984 • Graduated Cum Laude \nGeorgetown University, 1981 • Senior Comprehensive Passed with Distinction, \nGeorgetown University, 1981 \n \nTESTIMONY BEFORE THE FEDERAL ENERGY REGULATORY \nCOMMISSION \nAffidavit, Maryland Energy Administration et al. v. Baltimore Gas and Electric Company \net al., Docket No. EL26-87-000 (2026) • Report & Affidavit, NRG East Generation \nHoldings et al., Docket No. EC25-102-000 (2025) • Report & Affidavit, Vandolah Power \nCompany L.L.C. and Florida Power & Light Company, Docket No. EC25-101-000 \n(2025) • Prepared Answering Testimony, Deposition, and Hearing, Public Utilities \nCommission of the State of California v. Sellers of Long-Term Contracts to the \nCalifornia Department of Water Resources, Docket Nos EL02-60-017 and EL02-60-18 \n(2025) • Milford Gen Lead, LLC, FERC Docket No. ER24-3102-000 (2024) • Prepared \nDirect Testimony, Algonquin Gas Transmission, LLC, Docket No. RP24-781 (2024) • \nPrepared Testimony, Louisiana Public Service Commission et al., v. System Energy \nResources, Inc., et al., Docket No. EL21-56 (2024) •  Affidavit, Elliott Associates, L.P., \net al., Docket No. EC23-112 (2023) • Affidavit, Tampa Electric Company, ER10-1437 \n(2023) • Affidavits (2), NextEra Energy Resources, LLC, et al., Docket No.  EC23-36-\n000 (2022, 2023) • Affidavits, Building for the Future Through Electric Regional \nTransmission Planning and Cost Allocation and Generator Interconnection, Docket No. \nRM21-17-000 (2022) • Affidavit, NRG Energy, Inc., Docket No. EC20-96-000 (2020) • \nAffidavit, Energy Texas, Inc., EC20-85-000 (2020) • Affidavit, Tampa Electric \nCompany, ER10-1437-011 (2020) •  Affidavits, American Transmission System, Inc., \nDocket No. ER20-1740-000 (2020) • Affidavits, NRG Wholesale Generation LP and \nEntergy Mississippi, LLC Docket No. EC19-63-000 (2019) • Affidavits, Louisville Gas \nand Electric Co. and Kentucky Utilities Co., Docket Nos. EC98-2-001, ER18-2162-000 \n(2018) • Affidavit, Upper Peninsula Power Company, Docket No. ER10-1901-011 (2018) \n• Affidavit, NRG Cottonwood Tenant LLC, ER18-1160-001 (2018) • Affidavit, PSEG \nEnergy Resources & Trade LLC, ER10-1789-005 (2018) • Affidavit, Southern Indiana \nGas and Electric Co. d/b/a Vectren Energy Delivery of Indiana, Inc., ER10-1338-002 \n(2017) • Affidavit, PSEG Keys Energy Center LLC, ER17-2426-000 (2017) • Affidavit, \nTampa Electric Company, ER10-1437-006 (2017) • Prepared Answering Testimony, \nDeposition, and Hearing, People of the State of California, ex rel; Bill Lockyer, Attorney \nGeneral of the State of California v. British Columbia Power Exchange, et al., EL02-71-"},{"page":36,"startToken":9541,"endToken":10018,"text":"Qualifications of Dr. Morris \n \nPage 3 of 10 \n \n \n \n \n \n \n \n \n \n000 (2017) • Affidavit, Public Service Electric and Gas Company et al., ER10-1789-004 \n(2016) • Affidavit, Alabama Power Company, et al., ER17-514-00 (2016) • Affidavits \n(3), Alabama Power Company, et al., EL15-39-000 (2016) • Affidavit, Combined Locks \nEnergy Center, LLC, et al. , ER10-3042-004 (2015) • Affidavit, Alabama Power \nCompany, et al., EL15-39-000 (2015) • Affidavit, PJM Interconnection, L.L.C., ER15-\n623-000 (2015) • Affidavit, Southern Indiana Gas and Electric Co. d/b/a Vectren Energy \nDelivery of Indiana, Inc., ER10-1338-000 (2014) • Affidavit, Quantum Choctaw Power, \nLLC et al., ER12-458-007 (2014) • Affidavit, NRG Power Marketing LLC, et al., ER10-\n2265-004 et al. (2014) • Affidavit, TransCanada Entities, ER10-2870-004 et al. (2014) • \nAffidavit, Tampa Electric Company, ER10-1437-002 (2014) • Affidavit, Kendall Green \nEnergy LLC, ER14-1363-003 (2014) • Affidavit, Quantum Lake Power, LP, ER13-1489-\n000 (2014) • Affidavit, NRG Power Marketing LLC, et al. ER10-2265-002 (2014) • \nAffidavit, NRG Yield, Inc., et al., EC14-101-000 (2014) • Affidavit, Community Wind \nFarm 1 et al., ER14-1668-000 (2014) • Seaway Crude Pipeline Company LLC, OR15-6-\n000 (2014) • Affidavit, Public Service Electric and Gas Company et al., ER10-1789-003 \n(2013) • Affidavits, NRG Energy Holdings, Inc., Edison Mission Energy, EC14-14-000 \n(2013) • Affidavit, Silver Merger Sub, Inc., et al., EC13-128-000 (2013) • Prepared \nAnswering Testimony, Deposition, and Hearing, Puget Sound Energy, Inc., et al., EL01-\n10-085 (2012) • Affidavit, Wisconsin Public Service Corporation, et al., ER10-1894-004 \n(2012) • Affidavit, PSEG New Haven LLC, ER12-1250-000 (2012) • Affidavit, \nEnterprise Product Partners L.P. and Enbridge, Inc., OR12-4-000 (2012) • Affidavit, \nSouthern Indiana Gas and Electric Co., ER10-1338-001 (2011) • Affidavit, TransCanada \nPower Marketing Ltd. et al., ER10-2780-001 (2011) • Affidavit, Tampa Electric \nCompany, ER10-1476-001 (2011) • Affidavit, Cedar Creek Wind Energy, LLC, ER11-\n2577-000 (2010) • Affidavit, Public Service Electric and Gas Company et al., ER97-837-\n014 (2010) • Affidavit, Morris Energy Group, LLC v. PSEG Energy Resources & Trade \nLLC; PSEG Fossil LLC; and PSEG Power LLC, EL10-79-000 (2010) • Affidavit, UGI \nStorage Company and UGI Central Penn Gas, Inc., CP10-23-000 (2010) • Prepared \nAnswering Testimony, People of the State of California, ex rel; Bill Lockyer, Attorney \nGeneral of the State of California v. Powerex Corp., et al., EL02-71-000 (2009) • \nAffidavit, Integrys Energy Services, Inc. v. New Brunswick Power Generation \nCorporation, EL09-32-002 (2009) • Affidavit, People of the State of California, ex rel; \nEdmund G. Brown Jr. Attorney General of the State of California v. Powerex Corp., et \nal., EL09-56-000 (2009) • Affidavit, San Diego Gas & Electric Company v. Sellers of \nEnergy and Ancillary Services, EL00-95-000 (2009) • Affidavit, Troy Energy, LLC, et \nal., ER02-25-010 (2009) • Affidavit, Combined Locks Energy Center, LLC, et al., ER01-\n2659-015 (2009) • Prepared Direct Testimony and Deposition, Energy Transfer Partners, \net al., IN06-3-003 (2009) • Prepared Direct Testimony and Hearing, Mobil Pipe Line \nCompany, OR07-21-000 (2009) • Idaho Power Company, ER06-787-002 (2009) • \nAffidavit, Southern Indiana Gas and Electric Co. d/b/a Vectren Energy Delivery of \nIndiana, Inc. ER96-2734-007 (2008) • Affidavit, Choctaw Gas Generation, LLC, et al. \nER08-1332-002 • Affidavit, TransCanada Energy Sales Ltd., ER09-328-001 (2008) •"},{"page":37,"startToken":10018,"endToken":10458,"text":"Qualifications of Dr. Morris \n \nPage 4 of 10 \n \n \n \n \n \n \n \n \n \nPrepared Direct Testimony and Deposition, Oasis Pipeline L.P., et al., IN06-3-004 (2008) \n• Affidavit, Tampa Electric Company, ER99-2342-012 (2008) • Affidavit, ANP \nBellingham Energy Company, LLC, et al., ER00-2117-005 (2008) • Affidavit, SUEZ \nEnergy Marketing, NA, et al., ER06-169-003 (2008) • Affidavit, TransCanada Energy \nMarketing ULC, et al., ER07-1274-001 (2008) • Affidavit, Georgia-Pacific Brewton \nLLC, et al., ER08-1126-000 (2008) • Affidavit, Montgomery L’Energia Power Partners \nLP, ER08-864-000 (2008) • Affidavit (with Joseph P. Kalt), Energy Transfer Partners, et \nal., IN06-3-002 (2008) • Affidavit, Energy Transfer Partners, et al., IN06-3-002 (2008) • \nAffidavit, TransCanada Maine Wind Development Inc., ER08-685-000 (2008) • \nAffidavit, O’Connor & Hewitt, LTD, RP08-30-000 (2007) • Affidavit (with Joseph P. \nKalt), Energy Transfer Partners, et al., IN06-3-000 (2007) • Affidavit, Energy Transfer \nPartners, et al., IN06-3-000 (2007) • Affidavit, The People of the State of Illinois, ex rel. \nIllinois Attorney General Lisa Madigan v. Exelon Generation Co., LLC, et al., EL07-47-\n000 (2007) • Affidavit, Baltimore Gas and Electric Company, ER07-576-000 (2007) • \nAffidavit, Trans-Allegheny Interstate Line Company, ER07-562-000 (2007) • Affidavit, \nTransCanada Energy Marketing Ltd., et al., ER07-331-000 (2006) • Affidavit, Tampa \nElectric Company, ER99-2342-000, ER07-173-000 (2006) • Affidavit, Koch Supply & \nTrading, LP, ER07-100-000 (2006) • WPS Resources Corporation and Peoples Energy \nCorporation, EC06-152-000 (2006) • Affidavit, Sabine Cogen, LP, ER06-744-000 (2006) \n• Affidavit, Air Liquide Large Industries U.S. LP, ER06-743-000 (2006) • Affidavit, \nANP Bellingham Energy Company, LLC., et al., ER00-2117-000 (2005) • Affidavit, \nDuke Energy Corporation and Cinergy Corp., EC05-103-000  (2005) • Affidavit, El Paso \nMarketing, L.P., et al., ER95-428-000  (2005) • Affidavit, TransCanada Energy Ltd., et \nal., ER95-692-000  (2005) • Affidavit, Granite Ridge Energy, LLC, ER00-1147-000, \nER05-287-001  (2005) • Affidavit, TransCanada Power (Castleton) LLC, ER05-743-000  \n(2005) • Affidavit, Tampa Electric Company, et al., ER99-2342-003 (2005) • Affidavit, \nWisconsin Public Service Corporation, WPS Energy Services, Inc., and WPS Power \nDevelopment, Inc., ER96-1088-035 and Wisconsin Public Service Corporation, ER95-\n1528-010 (2005) • Affidavit, Wisconsin River Power Company, ER05-453-000 (2005) • \nAffidavit, Upper Peninsula Power Company, ER05-89-001 (2005) • Affidavit, Southern \nIndiana Gas and Electric Company, ER96-2734-003 (2004) • Affidavit, Tampa Electric \nCompany, et al., ER99-2342-003 (2004) • Affidavits, TransCanada Hydro Northeast, \nInc., et al., EC05-12-000, ER05-111-000 (2004) • Affidavits, Dominion Energy New \nEngland, Inc., et al., EC05-4-000, ER05-34-000 (2004) • Affidavit, Wisconsin Public \nService Corporation, WPS Energy Services, Inc., and WPS Power Development, Inc., \nER96-1088-033 and Wisconsin Public Service Corporation, ER95-1528-008 (2004) • \nAffidavit, NorthPoint Energy Solutions Inc. ER04-1244-000 (2004) • Affidavit, Union \nPower Partners, L.P., ER01-930-004 (2004) • Affidavit, Panda Gila River, L.P., ER01-\n931-004 (2004) • Affidavit, Dominion Energy Kewaunee, Inc., ER04-318-000 (2003) • \nAffidavit, TPS GP, Inc., TPG LP, Inc., Panda GS V, LLC & Panda GS VI, LLC, EC03-\n90-000 (2003) • Affidavit, Berkshire Power Company, L.L.C. et al., ER99-3502-001 \n(2002) • Affidavit, El Paso Merchant Energy, L.P., ER95-428-024 (2002) • Affidavit,"},{"page":38,"startToken":10458,"endToken":10939,"text":"Qualifications of Dr. Morris \n \nPage 5 of 10 \n \n \n \n \n \n \n \n \n \nTampa Electric Company, ER99-2342-001 (2002) • Affidavit, Hardee Power Partners \nLimited, ER99-2341-001 (2002) • Affidavit, TECO-PANDA Generating Company, L.P., \nER02-1000-000 (2002) • Affidavit, Commonwealth Chesapeake Company, LLC, ER99-\n415-004 (2002) • Affidavit, Wisconsin Public Service Corporation, WPS Energy \nServices, Inc., and WPS Power Development, Inc., ER96-1088-031 and Wisconsin \nPublic Service Corporation, ER95-1528-006 (2001) • Affidavit, TPS McAdams, LLC and \nTPS Dell, LLC, ER02-507-000 and ER02-510-000 (2001) • Affidavits, Prepared Direct \nTestimony, and Hearing, CPUC v. El Paso Natural Gas Company, et al., RP00-241-000 \n(2000-2001), Affidavit, El Paso Energy Corporation and The Coastal Corporation, EC00-\n73-000, (2000) • Affidavit, El Paso Energy Corporation and Sonat Inc., EC99-73-000 \n(1999) • Prepared Testimony, San Diego Gas & Electric Company and Enova Energy, \nInc., EC97-12-000 (1997) • Prepared Testimony and Hearing, Wisconsin Electric Power \nCo., Northern States Power Co. (Minnesota), Northern States Power Co. (Wisconsin), \nand Cenerprise, Inc., EC95-16-000 (1996)  \n \nTESTIMONY BEFORE STATE REGULATORY COMMISSIONS \nPrepared Direct Testimony, Hearing, and Affidavit, Monroe Energy et al. v. Laurel Pipe \nLine Company, L.P., Pennsylvania Public Utilities Commission Docket No. C-2025-\n3053018 (2025) • Affidavit, Joint Petition of NRG East Generation Holdings LLC and \nLightning Power, LLC, for a Declaratory Ruling Eschewing Further Review of Proposed \nTransaction, or, in the Alternative, an Order Authorizing the Transaction Pursuant to \nSections 70 and 83 of the New York Public Service Law, New York Public Service \nCommission Case 25-M-0358 (2025) • Affidavit, Investigation of Resource Adequacy \nAlternatives, New Jersey Board of Public Utilities Docket No. EO20030203 (2020) • \nPrepared Answering Testimony, Supplemental Testimony, and Cross-Examination, In the \nMatter of Eligibility Criteria for Energy Service Companies, Case 15-M-0127, New York \nPublic Service Commission (2017) • Prepared Direct Testimony, In re: Petition for \nDetermination of Cost Effective Generation Alternative to Meet Need Prior to 2018, by \nDuke Energy Florida, Inc., FPSC Docket No. 140111-EI (2014) • Affidavit and Prepared \nTestimony, In The Matter of the Petition of Public Service Electric and Gas Company for \nApproval of an Increase in Electric and Gas Rates and for Changes in the Tariffs for \nElectric and Gas Service, B.P.U.N.J. No. 14 Electric and B.P.U.N.J. No. 14 Gas Pursuant \nto N.J.S.A. 48:2-21 and N.J.S.A. 48:2-21.1 and for Approval of a Gas Weather \nNormalization Clause; A Pension Expense Tracker; and for Other Appropriate Relief, \nBPU Docket No. GR09050422, New Jersey Board of Public Utilities (2010) • Prepared \nDirect Testimony, Application of Wisconsin Power and Light Company for Issuance of a \nCertificate of Public Convenience and Necessity for Construction and Placement in \nOperation of an Approximately 300 MW Coal-Fired Baseload Facility and an \nApplication for Approval of Fixed Financial Parameters and Capital Cost Rate-Making \nPrinciples for the Baseload Facility, Docket No. 6680-CE-170, Public Service \nCommission of Wisconsin (2008) • Prepared Rebuttal Testimony and Hearing, In the \nMatter of the Joint Petition of Public Service Electric and Gas Company and Exelon"},{"page":39,"startToken":10939,"endToken":11405,"text":"Qualifications of Dr. Morris \n \nPage 6 of 10 \n \n \n \n \n \n \n \n \n \nCorporation for Approval of a Change in Control of Public Service Electric and Gas \nCompany, and Related Authorizations, BPU Docket No. EM05020106, OAL Docket No. \nPUC-01874-05, New Jersey Board of Public Utilities (2005, 2006) • Affidavit, \nApplication of Duke Energy Corporation for Authorization to Enter Into a Business \nCombination Transaction with Cinergy Corp., Docket No. 2005-210-E, Public Service \nCommission Of South Carolina (2005) • Prepared Rebuttal Testimony and Hearing, Joint \nApplication of PECO Energy Company and Public Service Electric and Gas Company \nfor Approval of the Merger of Public Service Enterprise Group Incorporated with and \ninto Exelon Corporation, Docket No. A-110550F0160, Pennsylvania Public Utility \nCommission (2005) • Prepared Direct Testimony and Hearing, Application of \nWashington Gas Light Company for amendments to Rate Schedule No. 9, Firm Delivery \nGas Supplier Agreement of its Gas Tariff, Docket No. PUE-2004-00085 (2005) • \nPrepared Direct Testimony, Application of Wisconsin Public Service Corporation for a \nCertificate of Public Convenience and Necessity for Construction of A Large Electric \nGenerating Plant with Associated Facilities, known as Weston 4, at Its Existing Weston \nGenerating Station Located in Marathon County, Docket No. 6690-CE-187, Public \nService Commission of Wisconsin (2004) • Prepared Direct Testimony, Metromedia \nEnergy, Inc. - Regarding Washington Gas Light Company's Plan to Return Customers to \nSales Service Effective December 1, 2003, Docket No. PUE-2003-00536 (2004) • Report \n(with Mark Frankena) and Testimony, Analysis of Competitive Implications: An \ninvestigations into whether electric industry restructuring and competition in the \nprovision of retail electric service is in the public interest, Louisiana Public Service \nCommission Docket No. U-21453, U-20925 (SC), U-22092 (SC) (Subdocket A) (2000) • \nReport and Hearing, Atlantic City Electric Company: Audit of Restructuring, New Jersey \nBoard of Public Utilities, Docket No. EA97060395 (1998) • Prepared Testimony and \nHearing, Proceeding on Motion of the Commission to Redesign Niagara Mohawk Power \nCorporation’s Current SC-7 Service Classification and Implement a New SC-7-A Service \nClassification, Case 94-E-0172, New York Public Service Commission (1995)   \n \nTESTIMONY BEFORE FEDERAL COURTS \nReport, Deposition and Bench Trial, Entergy Arkansas, LLC, vs. Ted J. Thomas, in his \nofficial capacity as Chairman of the Arkansas Public Service Commission et al., Civil \nAction No. 4:20-cv-01088-KGB, U.S. Dist. Court, Dist. of Eastern Arkansas (2022, \n2023) • Reports and Deposition, Duke Energy Carolinas, LLC, vs. NTE Carolinas II, \nLLC, NTE Carolinas II Holdings, LLC, NTE Energy LLC, NTE Southeast Electric \nCompany, LLC, NTE Energy Services Co., LLC, and Castillo Investment Holdings II, \nLLC, vs. Duke Energy Progress, LLC and Duke Energy Corporation, Civil Action No. \n3:19-cv-515, U.S. Dist. Court,  (2022) • Report, Deposition, and Bench Trial, FTC v. \nArch Coal, Inc., et al., Civil Action 04-0534 (JDB), U.S. Dist. Court, Dist. of Western \nNorth Carolina (2004) • Report, Deposition and Jury Trial, Trigen v. OG&E, CIV-96-\n1595L, U.S. Dist. Court, Western Dist. of Oklahoma (1998)"},{"page":40,"startToken":11405,"endToken":11853,"text":"Qualifications of Dr. Morris \n \nPage 7 of 10 \n \n \n \n \n \n \n \n \n \nTESTIMONY BEFORE STATE COURTS \nReport, Deposition, and Trial, CPS Energy v. Houston Pipe Line Company, LP and Oasis \nPipeline, LP, Cause No. 2021-CI-05138, District Court of Bexar County, Texas, 407th \nand 166th Judicial Districts (2023-6) • Affidavit, Retail Energy Supply Association, et al. \nv. Public Service Commission of the State of New York, et al., Index No. 870-16, State \nof New York, Supreme Court, County of Albany (2016) • Affidavit, City Public Service \nBoard of San Antonio vs. Public Utility Commission of Texas, et al., No. 97-02917, \nDistrict Court of Travis County, Texas, 200th Judicial District (1997) \n \nOTHER TESTIMONY \nReport, Metromedia Energy, Inc. v. Mirant Americas Energy Marketing, RE: 18 198 Y \n18484 03 (2005) • Report and Deposition, King Provision Corporation v. Burger King \nCorporation and Grand Metropolitan PLC, 90-05718-CA, 4th Cir., Duval Co., Florida \n(1992) •  Deposition, West Texas Transmission L.P. v. Enron Corp. et al., SA 88 CA \n0638, W.D. Texas, San Antonio Division (1988) \n \nPUBLICATIONS \n“Alternative Measures of ‘Representative Market Prices’ for FERC Delivered Price \nTests,” Energy Law Journal 42 (2021): 191-235 • “Should market power still be a \nconcern in the U.S. electric power industry?” with Jéssica Dutra and Tristan SnowCobb, \nElectricity Journal 33 (May 2020): 106725-28 • “Geographic Market Delineation in LMP \nElectric Power Markets,” with Megan Accordino, Electricity Journal 23(3) (April 2010): \n49-60 • “The Likely Effect of the Proposed Exelon-PSEG Merger on Wholesale \nElectricity Prices,” with Dan Oska, Electricity Journal 21(1) (Jan./Feb. 2008): 45-54 • \n“FERC MBR Screens: The Good, the Bad, and the Ugly,” Public Utilities Fortnightly \n143(7) (July 2005): 37-42 • “Finding Market Power in Power Markets,” International \nJournal of the Economics of Business, 7(2) (July 2000): 167-178 • “Why Applicants \nShould Use Computer Simulation Models to Comply with the FERC’s New Merger \nPolicy,” with Mark Frankena, Public Utilities Fortnightly, 135(3) (February 1, 1997): 22-\n26 • Electric Utility Mergers, with Mark Frankena and Bruce Owen, Chapters 1, 4, & 5, \n1994 • “International Trade and Antitrust: Comments,” University of Cincinnati Law \nReview, 61(3) (1993): 945-953 • “Upstream Vertical Integration with Automatic Price \nAdjustments,” Journal of Regulatory Economics 4 (1992): 279-287 • “Should the U.S. \nDepartment of Justice deviate from the 5% price test for market definition on a case-by-\ncase basis?”  with Gale Mosteller, International Merger Law, April 1992 • “Defining \nMarkets for Merger Analysis,” with Gale Mosteller, Antitrust Bulletin 36 (Fall 1991):  \n599-640 • “Analyzing Agreements Among Competitors:  What Does the Future Hold?” \nwith Jim Langenfeld, Antitrust Bulletin 36 (Fall 1991):  651-679 • “In Defense of \nAntitrust,” with Jim Langenfeld, Regulation 14(2) (Spring 1991):  (Letters) 2-4 • \n“Enforcement of Property Rights and the Provision of Public Good Attributes,” \nInformation Economics and Policy 3 (1988):  91-108"},{"page":41,"startToken":11853,"endToken":12299,"text":"Qualifications of Dr. Morris \n \nPage 8 of 10 \n \n \n \n \n \n \n \n \n \nWORKING PAPERS \n“Advertising Restrictions as Rent Increasing Costs,” FTC Bureau of Economics Working \nPaper No. 196, May 1992 • “Rent Increasing Costs:  The Antitrust Implications from a \nParadox in Value Theory,” FTC Bureau of Economics Working Paper No. 182, \nNovember 1990 • “The Relationship Between Industrial Sales Prices and Concentration \nof Natural Gas Pipelines,” FTC Bureau of Economics Working Paper No. 168, \nNovember 1988 • “Deregulation by Vertical Integration?”  FTC Bureau of Economics \nWorking Paper No. 166, November 1988 \n \nPRESENTATIONS & PROFESSIONAL ACTIVITIES \n“Finding ‘representative market prices’ for calculating concentration in electric power \nmarkets,” presentation to staff of the Federal Energy Regulatory Commission, March 4, \n2020 • Comments to the Antitrust Division of the U.S. Department of Justice and the \nFederal Trade Commission Concerning U.S. Department of Justice and the Federal Trade \nCommission Draft Vertical Merger Guidelines Released for Public Comment on January \n10, 2020, Feb. 25, 2020 (with Lona Fowdur) • Comments (with 7 others), Notice of \nInquiry: Modifications to Commission Requirements for Review of Transactions under \nSection 203 of the Federal Power Act and Market-Based Rate Applications under Section \n205 of the Federal Power Act, Docket No. RM16-21-000, Federal Energy Regulatory \nCommission, November 28, 2016 • Report, PJM Interconnection, L.L.C., Docket No. \nER15-623-000, Federal Energy Regulatory Commission, January 20, 2015 • Comments, \nNotice of Inquiry: Analysis of Horizontal Market Power under the Federal Power Act, \nDocket No. RM11-14-000, Federal Energy Regulatory Commission, May 23, 2011 • \nComments, Position Limits for Derivatives, RIN 3038–AD15 and 3038–AD16, \nCommodity Futures Trading Commission, March 28, 2011 • Comments, Guidance on \nSimultaneous Transmission Import Limit Studies, AD10-2-000, Federal Energy \nRegulatory Commission, February 12, 2010 • “Geographic Market Delineation in LMP \nElectric Power Markets,” presentation before representatives of the Federal Energy \nRegulatory Commission, U.S. Department of Justice, and U.S. Federal Trade \nCommission, January 27, 2010 • Comments, Notices of Intent to determine that 15 \nnatural gas financial basis contracts traded on the Intercontinental Exchange, Inc. are \nSignificant Price Discovery Contracts, Commodity Futures Trading Commission, \nOctober 26, 2009 • “Efficacy of Vertical Integration in Energy Industries with \nApplications to Proposed Standards of Conduct for Transmission Providers,” submitted \nto FERC by Santee Cooper in Docket No. RM07-1-000 (2007) • Chair, Antitrust \nCommittee, Energy Bar Association, 2004–2005 • “Competition in the Natural Gas \nIndustry: An Antitrust Perspective, presentation to staff of the Federal Energy Regulatory \nCommission,” March 28, 2005 • Vice Chair, Antitrust Committee, Energy Bar \nAssociation, 2003–2004 • “Weston 4 Effect on Wholesale Competition in WUMS,” \nsubmitted to the Public Service Commission of Wisconsin by Wisconsin Public Service \nCorporation in Docket No. 6690-CE-187, September 26, 2003 • “Computer Models In \nThe Electric Power Industry,” presented to staff of the Federal Trade Commission,"},{"page":42,"startToken":12299,"endToken":12787,"text":"Qualifications of Dr. Morris \n \nPage 9 of 10 \n \n \n \n \n \n \n \n \n \nWashington, DC, June 11, 2002 • “TECO EnergySource Market Share Analysis,” \nsubmitted to FERC by TECO EnergySource, Inc. in Docket No. ER96-1563-017, \nSeptember 10, 2001 • “Finding Market Power in Power Markets,” presented to staff of \nthe Federal Trade Commission, Washington, DC, June 20, 2001 • “A Study of Marketing \nAffiliate and Other Affiliate Holdings of Firm Capacity on Interstate Natural Gas \nPipelines and the Effects on Natural Gas Markets,” April 30, 2001, submitted to FERC \nby the Interstate Natural Gas Association of America in Docket No. PL00-1-003 • “Why \nWe Should Use Computer Models to Unveil Market Power,” presented at the Sixth \nDOE–NARUC National Electricity Forum, Brown Convention Center, Houston, TX, \nSeptember 16, 1998 • Comments, Agency Information Collection and Dissemination \nActivities: Comment Request, U.S. Department of Energy, Energy Information \nAdministration, August 28, 1998 • Comments, Revised filing Requirements Under Part \n33 of the Commission’s Regulations, Federal Energy Regulatory Commission Docket No. \nRM98-4-000, August 21, 1998 • “Use of Computer Simulation Models to Unveil Market \nPower,” presented to staff of the Federal Trade Commission, Federal Energy Regulatory \nCommission and U.S. Department of Justice, Federal Trade Commission, Washington, \nDC, April 10, 1998 • “Use of Computer Simulation Models to Unveil Market Power: The \nPrimergy Case,” presented to the Bureau of Economics, Federal Trade Commission, \nWashington, DC , December 8, 1997 • “Use of Computer Simulation Models to Unveil \nMarket Power,” presented at the 29th Annual Conference of the Institute of Public \nUtilities, Williamsburg, Virginia, December 3, 1997 • “Mergers and Market Power,” \npresented at the National Association of State Utility Consumer Advocates Mid-Year \nMeeting, Charleston, South Carolina, June 9, 1997 • “Market Power Analysis: An \nEconomic Perspective,” (with Mark Frankena), presented at the Strategic Research \nInstitute Conference on The Legal Challenges of Restructuring, Arlington, Virginia, \nApril 16, 1997 • “Mergers and Market Power,” presented at the Edison Electric Institute \nWorkshop on FERC Merger Policy Guidelines, Arlington, Virginia, April 1, 1997 • \n“New Approaches to Controlling Distribution Company Market Power,” presented at the \nNew York Energy Efficiency Council Conference on Innovative Solutions to a Changing \nEnergy Market, New York Athletic Club, February 7, 1997 • Description of the Western \nPower Model, with Mark Frankena, Exhibit 8 to Prepared Testimony Before the Nevada \nPublic Service Commission, January 31, 1997 • Reviewer, American Bar Association, \nSection of Antitrust Law, Manual on the Economics of Antitrust Law, 14th Supplement, \n1995 • Referee, Quarterly Journal of Business and Economics, 1994—1995 • Reviewer, \nAmerican Bar Association, Section of Antitrust Law, Manual on the Economics of \nAntitrust Law, 10th Supplement, 1993 • Expert Witness, Federal American Inn of Court, \nWashington, DC, Winter 1993 • “Advertising Restrictions as Rent Increasing Costs,” \npresented at a Contemporary Policy Issues Session of the Western Economics \nAssociation’s 67th Annual Conference, July 1992 • “Let’s Make Merger Policy ‘Fully \nConsonant With Economic Theory,’” presented at a Contemporary Policy Issues Session \nof the Western Economics Association’s 67th Annual Conference, July 1992 • \n“Advertising Restrictions as Rent Increasing Costs,” Seminar, Department of Business"},{"page":43,"startToken":12787,"endToken":13065,"text":"Qualifications of Dr. Morris \n \nPage 10 of 10 \n \n \n \n \n \n \n \n \n \nEconomics, Indiana University, October 1991 • “International Trade and Antitrust: \nComments,” presented at a Contemporary Policy Issues Session of the Western \nEconomics Association’s 66th Annual Conference, July 1991 • Discussant, Western \nEconomics Association’s 66th Annual Conference, July 1991 • Horizontal Restraints \nCases at the Federal Trade Commission: From American Medical Association through \nthe Present,” with Jim Langenfeld, presented at the 60th Annual Conference of the \nSouthern Economics Association, November 1990 • “Defining Markets for Merger \nAnalysis,” with Gale Mosteller, presented at a Contemporary Policy Issues Session of the \nWestern Economics Association’s 65th Annual Conference, cosponsored by the Antitrust \nBulletin and the Antitrust and Trade Regulation Section of the Federal Bar Association, \nJuly 1990 • “Analyzing Agreements Among Competitors:  What Does the Future Hold?” \nwith Jim Langenfeld, presented at a Contemporary Policy Issues Session of the Western \nEconomics Association’s 65th Annual Conference, cosponsored by the Antitrust Bulletin \nand the Antitrust and Trade Regulation Section of the Federal Bar Association, July 1990 \n• “The Relationship Between Industrial Sales Prices and Concentration of Natural Gas \nPipelines,” Seminar, Office of Economic Policy, Federal Energy Regulatory \nCommission, Summer 1989 • “The Relationship Between Industrial Sales Prices and \nConcentration of Natural Gas Pipelines,” Seminar, Economic Analysis Group, Antitrust \nDivision, U.S. Department of Justice, February 1989 • “Deregulation by Vertical \nIntegration?”  Seminar, Department of Business Economics, Indiana University, January \n1989 • Discussant, Industrial Organization Society Session, Annual Meeting of the \nAmerican Economics Association, December 1988 • “Concentration and Price in the \nNatural Gas Industry,” Seminar, Federal Trade Commission, July 1988 • “Relevant \nMeasures of Concentration for Antitrust Policy,” presented at an Industrial Organization \nSociety Session of the 57th Annual Conference of the Southern Economics Association, \nNovember 1987"},{"page":44,"startToken":13065,"endToken":13070,"text":"Attachment B \nThe Atkins Affidavit"},{"page":45,"startToken":13070,"endToken":13315,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3380-000 \nAFFIDAVIT OF THOMAS E. ATKINS \n1. \nMy name is Thomas E. Atkins.  My business address is 804 Carnegie Center, Princeton, \nNew Jersey, 08540.   \n2. \nI am the Vice President of Development with NRG Energy, Inc. (“NRG”).  In this capacity, \nI am responsible for NRG’s utility scale dispatchable generation development projects, \nincluding a number of development projects in the PJM Interconnection, L.L.C. (“PJM”) \nregion.  In this role, I lead a team of developers responsible for identifying economic \nprojects supporting future grid needs.  Once identified, my team leads the development \neffort including siting, concept design, licensing, permitting and ultimately financing.   \n3. \nI received my Bachelor of Science degree from Cornell University and hold a  Professional \nEngineer’s license from the State of New York.  Prior to joining NRG in 2014, I developed \nnumerous dispatchable electric generating facilities including projects within multiple \nRegional Transmission Organizations, as well as several replacement projects as Chief \nEngineer for the Virgin Islands Water and Power Authority.  I have over 40 years of \nexperience in the electric power industry. \n4. \nI am submitting this affidavit in support of certain of NRG subsidiaries’ limited protest to \na filing in which PJM is proposing rules for its Reliability Backstop Procurement (“RBP”).  \nSpecifically, my affidavit addresses the proposed soft cap of $555/MW-day and explains \nwhy that cap does not reflect the current costs of resources."},{"page":46,"startToken":13315,"endToken":13577,"text":"2 \nI. \nBACKGROUND \nA. \nNRG \n5. \nNRG is a Delaware corporation and an integrated wholesale power generation and retail \nelectricity company.  NRG’s common stock is publicly traded on the New York Stock \nExchange under the symbol “NRG.” \n6. \nThrough various subsidiaries, NRG owns or controls over 9 GW of generation in the PJM \nfootprint and also owns generation in adjacent markets that can be imported into the PJM \nmarket.  NRG actively participates in the organized markets administered by PJM, \nincluding the PJM capacity market.  Through various other subsidiaries, NRG is also an \nactive retail power marketer in the PJM region and engages in wholesale transactions to \nsupport its retail power marketing activities.  NRG’s subsidiaries conduct their retail \nmarketing activities in this region under the brand names NRG Home, Direct Energy, \nGreen Mountain Energy, Gateway Energy Services, Stream Energy and XOOM Energy \nand pursuant to retail marketing licenses issued by applicable state commissions. \n7. \nNRG is actively developing a number of dispatchable generation projects in the PJM \nregion, including both upgrading existing equipment and building new facilities at our \ncurrent brownfield sites.  Several of these projects are in a sufficiently advanced stage of \ndevelopment to qualify for participation in the RBP. \nB. \nThe Proposed RBP \n8. \nAs described in greater detail in PJM’s July 31, 2026, filing in this proceeding, the RBP is \na one-time procurement of new capacity to address shortfalls in PJM’s last two Base \nResidual Auctions (“BRAs”), specifically, the BRAs for the 2027/2028 and the 2028/2029 \nDelivery Years.  As proposed, the RBP would procure capacity commitments from new"},{"page":47,"startToken":13577,"endToken":13848,"text":"3 \nsupply resources for up to 15 Delivery Years ending with the 2042/2043 Delivery Year.  \nThe aim will be to procure an amount equal to the 6,831.3 MW shortfall in the 2028/2029 \nBRA, less qualifying new capacity serving new load and load associated with certain \ncooperatives and municipals that opt out of the RBP. \n9. \nAmong other things, PJM has proposed a soft cap, characterized as a “maximum \nwillingness to pay,” for the RBP of $555/MW-day (UCAP).  This represents the effective \ncap that would have applied in the 2028/2029 BRA but for the separate price collar.  This \n$555/MW-day cap is soft in the sense that a supplier’s offer can exceed $555/MW-day \nprovided the levelized procurement cost of all selected RBP offers, on a MW-weighted \naverage basis, does not exceed $555/MW-day. \n10. \nAccording to PJM, $555/MW-day is the price at “Point 1” on the Variable Resource \nRequirement (“VRR”) curve approved for the 2028/2029 BRA as part of the most recent \nquadrennial review of Reliability Pricing Model auction parameters.1  In the quadrennial \nreview proceeding, PJM described its calculation of the Point 1 price as follows:2 \n \n11. \nThe gross CONE value of $613/MW-day (ICAP) (or $776/MW-day (UCAP)) is intended \nto represent the cost of new entry for a combustion turbine (“CT”), as estimated through a \n \n1  \n2025 Periodic Review of Variable Resource Requirement Curve Shape and Key Parameters, \nDocket No. ER26-455-000 (filed Nov. 7, 2025). \n2  \nMotion for Leave to Answer and Answer of PJM Interconnection, L.L.C. at 14, Docket No. ER26-\n455-000 (filed Jan. 2, 2026)."},{"page":48,"startToken":13848,"endToken":14162,"text":"4 \nstudy conducted by the Brattle Group and Sargent & Lundy and submitted as part of PJM’s \nquadrennial review filing in November 2025.3  The study itself was issued in April 2025. \nII. \nThe Soft Cap is Based on an Outdated CONE Value for a CT and Fails Adequately \nto Reflect Costs of Building New Generation in the PJM Region \n12. \nAs PJM noted in a May 2026 report, “capital costs have escalated sharply in recent years.”4  \nIn fact, as PJM explained: \nInstalled costs for new natural gas combined cycle plants now regularly \nexceed $2,200 per kilowatt for projects with commercial dates in the late \n2020s and early 2030s, and costs for more distant commercial dates are \nhigher still. This represents a substantial increase over the administrative \ncost of new entry (CONE) estimates that PJM uses to calibrate its capacity \nmarket demand curve . . . .5 \n13. \nIn a separate affidavit also being submitted in support of NRG’s limited protest, Dr. John \nR. Morris states that even since the CONE study for the most recent quadrennial update \nfiling was prepared, costs have continued to escalate the CONE value  and the proposed \nsoft cap of $555/MW-day does not reflect the dramatic cost increases in power generation \nequipment.  \n14. \nNRG has witnessed these increased costs in its development efforts. A 2025 paper issued \nby GridLab, Energy Futures Group and Halcyon reflects the “significant and persistent \nincrease in the capital costs of new gas combustion turbine and combined cycle gas turbine \npower plants in the United States” and that the “trend marks a stark departure from \n \n3  \nPJM Interconnection, L.L.C., 2025 Periodic Review of Variable Resource Requirement Curve \nShape  and Key Parameters, Docket No. ER26-455-000 (Nov. 7, 2025).  \n4  \nPJM, Powering Reliability Through Market Design at 4 (May 6, 2026), https://www.pjm.com/-/\nmedia/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-\nmarket-design.pdf. \n5  \nId."},{"page":49,"startToken":14162,"endToken":14460,"text":"5 \nhistorical cost assumptions and public cost projections.”6  In 2026, Bloomberg issued a \nreport showing that the “costs to build natural gas-fired power plants in the US increased \n66% between 2023 and 2025.”7 \n15. \n$555/MW-day is low relative to the costs NRG is seeing as a generation developer.  At the \noutset, I would note that even if it were not out of date, the $555/MW-day figure would \nonly be tied to the costs of a new CT and would not be representative of the costs of projects \nusing other technologies or having other characteristics different from those of the \nreference unit.  For example, NRG currently has several projects under development in the \nPJM footprint using technologies other than simple cycle CT’s that are far enough along \nin the development process to offer into the RBP.   \n16. \nHowever, all of NRG’s development projects that qualify for the RBP are significantly \nchallenged by the $555/MW-day soft cap.  One of these projects has a capacity in excess \nof 800 MW and a CONE, less expected energy and ancillary services revenues, \nsubstantially greater than the $555/MW-day soft cap. This is a well-formed project that \nwould, among other things, be located in what has historically been an import-constrained \nzone.  But it is hard to justify the time and expense associated with offering it into the RBP, \nnotwithstanding the fact that the soft cap allows offers above $555/MW-day.   \n* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * \n17. \nThis concludes my affidavit. \n \n \n6 The New Reality of Power Generation: An Analysis of Increasing Gas Turbine Costs in the U.S., GridLab, \nEnergy Futures Group & Halcyon, at 4 (Sept. 2025), https://gridlab.org/portfolio-item/gas-tubine-cost-\nreport/ \n7 Cost to Build a Natural Gas-Fired Power Plant Surges 66%, BNEF Says, (Apr. 2026), \nhttps://energynow.com/2026/04/cost-to-build-a-natural-gas-fired-power-plant-surges-66-bnef-says/"},{"page":50,"startToken":14460,"endToken":14460,"text":""}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":329,"startToken":0,"endToken":407},{"p":2,"at":329,"title":"I. BACKGROUND","method":"printed heading","endPage":2,"endAt":1322,"startToken":407,"endToken":580},{"p":2,"at":1322,"title":"D. Burgum, et al., Statement of Principles Regarding PJM (Jan. 15, 2026) (“Statement of","method":"printed heading","endPage":3,"endAt":931,"startToken":580,"endToken":774},{"p":3,"at":931,"title":"II. PROTEST","method":"printed heading","endPage":5,"endAt":340,"startToken":774,"endToken":1290},{"p":5,"at":340,"title":"A. Any Soft Cap Should Be Set at a Level Reflecting Current Costs of Resources Whose","method":"printed heading","endPage":10,"endAt":754,"startToken":1290,"endToken":3089},{"p":10,"at":754,"title":"B. The Commission Should Impose a Price Floor on Offers for Resources with RBP","method":"printed heading","endPage":14,"endAt":4,"startToken":3089,"endToken":4235},{"p":14,"at":4,"title":"III. CONCLUSION","method":"printed heading","endPage":15,"endAt":0,"startToken":4235,"endToken":4393},{"p":15,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":16,"endAt":0,"startToken":4393,"endToken":4450},{"p":16,"at":0,"title":"Attachment A","method":"printed heading","endPage":17,"endAt":0,"startToken":4450,"endToken":4455},{"p":17,"at":0,"title":"Attachment A","method":"printed heading","endPage":18,"endAt":0,"startToken":4455,"endToken":4489},{"p":18,"at":0,"title":"Attachment A","method":"printed heading","endPage":19,"endAt":0,"startToken":4489,"endToken":4700},{"p":19,"at":0,"title":"Attachment A","method":"printed heading","endPage":20,"endAt":0,"startToken":4700,"endToken":4962},{"p":20,"at":0,"title":"Attachment A","method":"printed heading","endPage":21,"endAt":0,"startToken":4962,"endToken":5226},{"p":21,"at":0,"title":"Attachment A","method":"printed heading","endPage":22,"endAt":0,"startToken":5226,"endToken":5543},{"p":22,"at":0,"title":"Attachment A","method":"printed heading","endPage":22,"endAt":42,"startToken":5543,"endToken":5549},{"p":22,"at":42,"title":"I. The “Soft” Price Cap of $555/MW-Day Can Only Serve to Raise Costs to","method":"printed heading","endPage":23,"endAt":0,"startToken":5549,"endToken":5850},{"p":23,"at":0,"title":"Attachment A","method":"printed heading","endPage":24,"endAt":0,"startToken":5850,"endToken":6163},{"p":24,"at":0,"title":"Attachment A","method":"printed heading","endPage":25,"endAt":0,"startToken":6163,"endToken":6456},{"p":25,"at":0,"title":"Attachment A","method":"printed heading","endPage":26,"endAt":0,"startToken":6456,"endToken":6726},{"p":26,"at":0,"title":"Attachment A","method":"printed heading","endPage":27,"endAt":0,"startToken":6726,"endToken":7003},{"p":27,"at":0,"title":"Attachment A","method":"printed heading","endPage":28,"endAt":0,"startToken":7003,"endToken":7316},{"p":28,"at":0,"title":"Attachment A","method":"printed heading","endPage":29,"endAt":0,"startToken":7316,"endToken":7537},{"p":29,"at":0,"title":"Attachment A","method":"printed heading","endPage":30,"endAt":0,"startToken":7537,"endToken":7831},{"p":30,"at":0,"title":"Attachment A","method":"printed heading","endPage":31,"endAt":0,"startToken":7831,"endToken":8116},{"p":31,"at":0,"title":"Attachment A","method":"printed heading","endPage":32,"endAt":0,"startToken":8116,"endToken":8401},{"p":32,"at":0,"title":"Attachment A","method":"printed heading","endPage":33,"endAt":0,"startToken":8401,"endToken":8690},{"p":33,"at":0,"title":"Attachment A","method":"printed heading","endPage":44,"endAt":0,"startToken":8690,"endToken":13065},{"p":44,"at":0,"title":"Attachment B","method":"printed heading","endPage":46,"endAt":3,"startToken":13065,"endToken":13316},{"p":46,"at":3,"title":"I. BACKGROUND","method":"printed heading","endPage":46,"endAt":1335,"startToken":13316,"endToken":13515},{"p":46,"at":1335,"title":"B. The Proposed RBP","method":"printed heading","endPage":48,"endAt":182,"startToken":13515,"endToken":13879},{"p":48,"at":182,"title":"II. The Soft Cap is Based on an Outdated CONE Value for a CT and Fails Adequately","method":"printed heading","endPage":50,"endAt":0,"startToken":13879,"endToken":14460}]}