{"document":{"slug":"rec-20260821-5276","title":"Comments and Protest of FirstEnergy Service Company re PJM Interconnection, L.L.C.'s 07/31/2026 filing proposing to establish a Reliability Backstop…","issued":"2026-08-21","accession":"20260821-5276","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"FirstEnergy Service Company","kind":"protest","file":"sources/filings/text/20260821-5276_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5276","tier":"record","sha256":"7b550dfa48ee3eca7cebd50530e622fe80bbe9af697a6094f0859e632604d117","pages":23,"tokens":6533,"emptyPages":[],"textThemes":["credit","cost","adequacy","retail"]},"pages":[{"page":1,"startToken":0,"endToken":324,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION  \nPJM Interconnection, L.L.C.   \n    ) \n \nDocket No. ER26-3380-000\nCOMMENTS AND PROTEST OF  \nFIRSTENERGY SERVICE COMPANY \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or “Commission”),1 FirstEnergy Service Company \n(“FirstEnergy”) respectfully submits these comments and protest of the filing submitted by \nPJM Interconnection, L.L.C. (“PJM”) on July 31, 2026, proposing to establish a Reliability \nBackstop Procurement (“RBP”) mechanism.2\nFirstEnergy agrees that new generation is needed.  Unfortunately, fundamental \nelements of PJM’s RBP proposal are fatally flawed and as a result these elements cannot \nbe approved consistent with Section 205 of the Federal Power Act (“FPA”).  Section 205 \nof the FPA provides that the Commission can accept PJM’s RBP proposal only if it is just \nand reasonable and not unduly discriminatory or preferential.3  The filing utility—PJM—\nbears the burden of proof to demonstrate its proposal meets these FPA requirements.4  The \nCommission may accept PJM’s proposal only if there is sufficient evidence in the record \nto show PJM has carried its Section 205 burden of proof.5  The Commission will reject any \n1\n18 C.F.R. § 385.211 (2025). \n2\nPJM Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from \nLarge Loads, Docket No. ER26-3380-000 (“July 31 RBP Proposal”). \n3\n16 U.S.C. § 824d(a)-(b). \n4\nConstellation Mystic Power, LLC v. FERC,  45 F.4th 1028, 1035 (D.C. Cir. 2022); NorthWestern \nCorp. v. FERC, 884 F.3d 1176, 1182-83 (D.C. Cir. 2018) (“Northwestern Corp.”); Midcontinent Indep. Sys. \nOperator, Inc., 194 FERC ¶ 61,050, at P 23 (2026); Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC \n¶ 61,236, at P 7 (2018). \n5\nNorthwestern Corp., 884 F.3d at 1182-84; City of Winnfield v. FERC, 744 F.2d 871, 876-77 (D.C. \nCir. 1984); NorthWestern Corp., 147 FERC ¶ 61,049, at P 48 (2014)."},{"page":2,"startToken":324,"endToken":702,"text":"2 \nproposal that falls outside the zone of reasonableness—i.e., does not result in just and \nreasonable rates in accordance with Section 205.6  Moreover, even if a rate falls within the \nzone of reasonableness, it may nevertheless violate Section 205 due to being unduly \ndiscriminatory or preferential.7\nIn these comments and protest, FirstEnergy demonstrates that PJM’s filing does not \nmeet the FPA Section 205 just and reasonable standard because: \n1. PJM did not follow the Statement of Principles policy directive for \ndetermining how much new capacity to purchase, or how to allocate the \ncosts;8\n2. PJM's load-side collateral requirements are unsupported and not \nnecessary;   \n3. PJM's levelized contract framework – which permits suppliers to “front \nload” the capacity contracts – creates unnecessary affordability risks; \n4. PJM’s proposed cost allocation can result in costs not going to new data \ncenters as required by the Statement of Principles and also fails to \ncomply with fundamental cost allocation criteria; \n5. PJM’s Reliability Backstop Procurement should be limited to resources \nthat most effectively address reliability needs;  \n6. PJM's proposed implementation schedule is compressed unreasonably; \n7. PJM’s proposed “opt-out” mechanism allows for unreasonable cost \nshifting; \n8. FERC should direct PJM to strengthen supplier performance and credit \nrequirements; and \n9. FERC should direct PJM to clarify that its proposed gating criteria \nrequire binding contractual commitments for eligible demand response \nresources. \nIn addition to the above, FirstEnergy respectfully submits that FERC should require \nthat, when PJM refiles tariff amendments that comply with the Statement of Principles, \n6\nIndep. Power Producers of N.Y., Inc. v. FERC, 2022 U.S. App. LEXIS 22081, at * 6, 2022 WL \n3210362, at *2 (D.C. Cir. Aug. 9, 2022) (citing Me. Pub. Utils. Comm'n v. FERC, 520 F.3d 464, 471 (D.C. \nCir. 2008), rev’d on other grounds, 558 U.S. 165 (2010); FCC v. Prometheus Radio Project, 592 U.S. 414, \n423 (2021)). \n7\nAla. Elec. Co-op., Inc. v. FERC, 684 F.2d 20, 27 (D.C. Cir. 1982) (citing U.S. v. Ill. Cent. R.R., 263 \nU.S. 515, 524 (1924)). \n8\nStatement of Principles Regarding PJM, National Energy Dominance Council (Jan. 16, 2026),\navailable at https://www.energy.gov/documents/statement-principles-regarding-pjm[https://perma.cc/35HJ-\nW56E](the “Statement” or “Statement of Principles”)."},{"page":3,"startToken":702,"endToken":1013,"text":"3 \nPJM should provide certain clarifications about the qualifications and criteria for Demand \nResponse to participate in the backstop procurement. \nCOMMENTS AND PROTEST \n1. \nPJM Did Not Follow the Statement of Principles Policy \nDirective For Determining How Much New Capacity to \nPurchase, or How to Allocate the Costs. \nThe Statement of Principles directs PJM to conduct a reliability backstop auction \nto procure new capacity resources, with the procurement to provide a 15-year term of price \ncertainty.9  The Statement also directs that the costs are to be allocated to load-serving \nentities with new data centers that have not self-procured new capacity or agreed to be \ncurtailable.10  PJM’s proposal makes no effort to comply with this directive.  Instead, PJM \nproposes to allocate costs based on forecasts that were submitted in 2025.  PJM does not \nidentify the data centers that are included in such forecasts, nor does it make any effort to \nensure that the costs that are so allocated go only to new data centers that have not self-\nsupplied or agreed to be curtailable.  As such, PJM cannot demonstrate that the costs will \ngo to new data centers. \nPJM cannot justify its failure to adhere to the Statement’s policy guidance.  The \nStatement was issued on January 16, 2026 and PJM’s filing was submitted on July 31, \n2026.  PJM had six and one-half months to identify the new data centers that are within \nscope, and to hold stakeholder discussions for how to allocate the costs at the wholesale \nand retail level.  PJM did not do so.  Instead, PJM conducted extensive stakeholder \nprocesses in an effort to justify its preferred policy direction, and then refused to implement \n9\nStatement of Principles, Bullet 1.  Notably, PJM’s proposal does not comply even with this \nstraightforward directive as it contemplates that resources may contract for terms of less than 15 years. \n10\nId., Bullet 3."},{"page":4,"startToken":1013,"endToken":1299,"text":"4 \nthe stakeholder-endorsed backstop procurement proposal that came out of that process.11\nIn other words, PJM ran out the clock with stakeholder processes instead of utilizing the \nallotted time to solicit the data that would be necessary for PJM to allocate the backstop \nprocurement costs as directed by the Statement of Principles. \nPJM cannot take refuge in its broad authority to amend the terms of the existing \nReliability Assurance Agreement.12  It’s correct to say that Section 16.4 of the RAA gives \nthe PJM Board broad rights to amend the agreement.  And it’s also correct to say that \nSection 16.4 of Attachment DD of the PJM Open Access Transmission Tariff (“OATT”) \ndescribes a “reliability backstop auction.”13  But PJM’s authorization to amend the RAA\nand the OATT is subject to certain inherent limiting principles.  PJM cannot, for example, \ncreate an entirely new power product and impose the costs on wholesale or retail customers \nsimply because it wants to or simply because in its best judgement its corporate principles \nwill be served. \nImportantly, PJM was not “starting from scratch.”  As noted, the current OATT \ndescribes a “reliability backstop” product.  The Statement of Principles reflects policy \nguidance and direction from a slate of bipartisan state governors and the White House.  \nAnd the PJM stakeholder process included a “Joint Proposal” by a group of Electric \n11\nSee PJM Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop Procurement \nand Connect and Manage, available at https://www.pjm.com/-/media/DotCom/about-pjm/who-we-\nare/public-disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement-\nand-connect-and-manage.pdf. \n12\nAvailable at https://www.pjm.com/pjmfiles/directory/merged-tariffs/raa.pdf.  \n13\nAvailable at https://www.pjm.com/pjmfiles/directory/merged-tariffs/oatt.pdf, at pp. 6285-87."},{"page":5,"startToken":1299,"endToken":1593,"text":"5 \nDistribution Companies and Data Center Customers for how to implement the Statement\nand allocate the costs.14\nPJM’s proposal is not consistent with any of the above.  Instead, and as noted above \nand throughout this Protest, PJM has submitted tariff amendments that are inconsistent in \nmaterial terms with the Statement of Principles and a proposal that was approved by the \noverwhelming majority of stakeholders.  Even worse, PJM’s tariff amendments call for the \ncosts of its backstop procurement to attach before LSEs (and their respective stakeholders) \nwill have any meaningful opportunity to avoid such costs by exercising their right to exit.  \nThat is, PJM proposes to conduct a procurement that it admits it has designed in such a \nmanner that the cost likely will be close to the “notational value” (or cap) of $555/MWD, \nor approximately $20.7 billion over the 15-year term of the contracts, and for the \nprocurement to be conducted and the costs to attach before LSEs and their stakeholders \ncan exercise their right to avoid such costs by exiting.   \nThere is no scenario where this outcome can be construed as “just and reasonable.”  \nEven if the Commission were inclined to approve the proposal—which given the above \nwould raise serious doubt about the legal durability of such approval—to do so would bring \neven more uncertainty as LSEs, the PJM states, and other important stakeholders could be \nforced to resort to extraordinary legal measures to prevent such costs from attaching before \nthe appellate process could address the merits of the Commission’s action. \nGiven the manifest deficiencies in PJM’s filing, and the significant financial and \nlegal risk in going forward, the Commission should: (i) rule that PJM has not met its \n14\nAvailable at 20260630-item-02f---joint-edcs-and-data-center-coalition---rbp---executive-\nsummary.pdf."},{"page":6,"startToken":1593,"endToken":1872,"text":"6 \nstatutory “just and reasonable” burden for going forward, and (ii) provide guidance for \nPJM and the stakeholders going forward.  Moreover, in light of the amount of time that has \npassed since the January 16, 2026 issuance of the Statement of Principles, and the \nCommission’s experience with obtaining a broadly-supported outcome for PJM capacity \nissues,15 the Commission should give serious consideration to commencing an FPA Section \n206 proceeding and then facilitating settlement negotiations. \nSpeaking to the going-forward process: creation of the Reliability Pricing Model \n(“RPM”) is the analogue for navigating significant policy changes for the PJM capacity \nproduct.  As the Commission is aware, over twenty years ago, PJM submitted amendments \nto its tariff to implement its vision for funding the capacity cost of physical generation.16\nThen, as now, the proposed tariff amendments were poorly designed and faced significant \nopposition from utilities, customers, and state regulators.  The Commission rejected PJM’s \nfiling and instituted an FPA Section 20617 proceeding.  There were many months of \nsettlement negotiations and, ultimately, the majority of PJM’s stakeholders were able to \nagree, or “not oppose” the RPM construct.18  This background illustrates the arbitrary \nnature of PJM’s current proposal:  less than 20% of the stakeholders voted for PJM’s RBP \nproposal,19 whereas almost 60% of the stakeholders voted in favor of a Joint Electric \n15\nSee FERC Docket Nos. ER05-1410, EL05-148, PJM Interconnection, L.L.C., Order Denying \nRehearing and Approving Settlement Subject to Conditions, 117 FERC ¶ 61,331 (2006). \n16\nSee id.\n17\n16 U.S.C. § 824e. \n18\nPJM Interconnection, 117 FERC ¶ 61,331. \n19\nSee 6/30/26 PJM Members Committee, Supplemental Voting Results, available at mc-voting-\nresults---agenda-item-3l---pjm-rbp-proposal.pdf."},{"page":7,"startToken":1872,"endToken":2167,"text":"7 \nDistribution Company/Data Center Coalition proposal.20  The Commission should follow \nthe RPM playbook: reject PJM’s filing, institute an FPA Section 206 proceeding, and \nestablish settlement proceedings. \n \n2.  \nPJM’s \nProposed \nLSE \nCollateral \nRequirements \nAre \nUnnecessary and Excessive. \nPJM proposes to impose a new and onerous collateral obligation on each LSE \nallocated RBP Charges.21  Under the Proposed Tariff, the cumulative LSE credit \nrequirement would initially equal $1.5 million multiplied by the total MW of committed \nRBP Unforced Capacity (“UCAP”) allocated to the LSE.22  PJM has failed to meet its \nburden under section 205 to demonstrate that its proposed LSE credit requirement is just \nand reasonable and not unduly discriminatory and the Commission must therefore reject \nPJM’s unprecedented load-side collateral requirements.   \nPJM fails to demonstrate why it is necessary to require LSEs to post additional \ncollateral. Retail customers, hopefully the new data centers described in the Statement of \nPrinciples, ultimately will take these costs.23  Because retail customers ultimately will pay \nthe RBP costs, there is no justification for imposing new and onerous collateral \n20\nSee 6/30/26 PJM Members Committee, Supplemental Voting Results, available at mc-voting-\nresults---agenda-item-3o---joint-edcs-and-data-center-coalition-rbp-proposal.pdf. \n21\nSee July 31 RBP Proposal at 108-123. \n22\nProposed Tariff, Attachment DD at Section 18.8(b)(i)(A). \n23\nSee, e.g., Qualifying Facility Rates & Requirements Implementation Issues Under the Pub. Util. \nRegul. Pol’ys Act of 1978, 172 FERC ¶ 61,041, at P 40 (2020) (recognizing that “electric utilities with \nfranchised service territories that make sales at retail are often effectively guaranteed the recovery of their \nenergy costs in their retail rates by their state regulatory authorities—provided that such costs are prudently \nincurred.”); Pa. Power Co. v. Pub. Util. Comm’n, 932 A.2d 300 (Pa. Commw. Ct. 2007)."},{"page":8,"startToken":2167,"endToken":2587,"text":"8 \nrequirements on LSEs that will likely result in hundreds of millions of dollars in additional \ncollateral, the costs of which will ultimately be borne by retail ratepayers.24 \nPURPA must-purchase arrangements supporting Qualifying Facility development \nare the closest long-term contractual analogue to the sort of commitment that LSEs will be \nrequired to assume as a result of PJM’s RBP.25  Under PURPA contracts, however, the \npurchasing entities generally have been subject to low or no collateral requirements \nbecause of their ability to recover costs from retail customers.26  Imposing identical rates, \nterms and conditions on entities that are not similarly situated is no less discriminatory than \ntreating similar situated entities differently.27  PJM’s proposal is therefore unduly \ndiscriminatory and must be rejected. \nEven if some additional collateral was appropriate, PJM must be able to show that \nits proposed collateral requirements are reasonably tailored to the actual credit risk \npresented by specific LSEs, or substantially similar classes of LSEs.  PJM’s proposal is \nunjust and unreasonable because it automatically treats such entities as presenting the same \nnonpayment risk as LSEs without comparable cost-recovery mechanisms.  It does not \n24 With respect to FirstEnergy affiliate service territories, FirstEnergy estimates that the collateral \nrequirements will be approximately $363.7 million in total, representing $169 million in the FirstEnergy \nOhio area, $20.5 million in the Penn Power area and $174.2 million in the Potomac Edison territory. \n25\nPublic Utility Regulatory Policies Act of 1978 (“PURPA”), Pub. L. No. 95-617, 92 Stat. 3117 \n(1978), codified in relevant part at 16 U.S.C. § 824a-3. \n26\nSee, e.g., North Carolina Electric Membership Corp., Standard Power Purchase Agreement for \nQualifying \nFacilities \n(Facilities \n≤ \n100 \nkW) \n(May \n21, \n2026), \navailable \nat\nhttps://e1.nmcdn.io/assets/ncemcs2/wp-content/uploads/2026/05/NCEMC-Standard-PPA_20260521.pdf; \nOrder Establishing Standard Rates and Contract Terms for Qualifying Facilities, Dkt. No. E-100, Sub 194 \n(N.C. Util. Comm’n Sept. 30, 2024) (approving standard offer PUPRA PPA without utility collateral \nrequirements); In re Joint Utils. Application for Approval of Proposed Schedules & Standard Power \nPurchase Agreement for Qualifying Facilities up to 10 MW, Docket No. UM 2299, Order No. 24-070 (Or. \nP.U.C. Mar. 12, 2024) (approving form of standard QF PPA without utility collateral requirements). \n27\nSee, e.g., Ark. Elec. Energy Consumers v. FERC, 290 F.3d 362, 368 (D.C. Cir. 2002); Complex \nConsol. Edison Co. of New York v. FERC, 165 F.3d 992, 1013 (D.C. Cir. 1999); Ala. Elec. Co-op. v. FERC, \n684 F.2d at 27-28."},{"page":9,"startToken":2587,"endToken":2889,"text":"9 \nexplain whether or how regulated cost recovery affects LSE default risk, and it does not \nidentify evidence that LSEs with such recovery mechanisms require collateral equal to \napproximately half of a 15-year notional payment stream.   \nThese deficiencies alone require rejection of PJM’s collateral proposal.  However, \nPJM’s collateral proposal suffers from additional flaws: \n\nPJM fails to provide sufficient justification for the $1.5 million per MW figure. \nPJM does not identify an expected probability of default, a loss-given-default \nassumption, a historical LSE default experience, a liquidation or replacement \nperiod, or any other quantitative measure connecting the proposed $1.5 million \nper committed RBP MW requirement to a reasonably anticipated loss. \n\nPJM acknowledges that LSEs and other market participants already are subject \nto existing collateral requirements, but fails to identify the particular limitation \nin Attachment Q that prevents it from addressing a reasonably measured RBP \nexposure through those existing requirements.   \n\nPJM provides no details specifying how quickly excess collateral must be \nreturned.  PJM’s proposal to retain absolute discretion to make such \ndeterminations is unjust and unreasonable as it fails to protect LSEs from over-\ncollateralization. \n\nIf seller collateral remains available when an RBP Seller defaults, PJM should \nbe required to draw upon that collateral and use the proceeds to provide the \ncorresponding shortfall credits to the affected LSEs.  Nothing in PJM’s proposal \nexplains why the use of available seller collateral should be discretionary, or \nwhy the proposed tariff provisions are silent regarding the amount, timing, and \nallocation of any proceeds recovered from such collateral. \nIn an age of increasing affordability concerns, PJM’s proposal will harm retail \ncustomers, because those customers will ultimately bear the costs of these credit \nrequirements.  Absent more compelling justifications than those contained in the current \nRBP Proposal, the Commission cannot accept PJM’s proposal as within the zone of \nreasonableness."},{"page":10,"startToken":2889,"endToken":3203,"text":"10 \n3.\nPJM’s Levelized Contract Framework—Which Permits \nSuppliers to “Front Load” the Capacity Contracts—Creates \nUnnecessary Affordability Risks. \nPJM proposes to clear offers in the RBP Auction based on a levelized cost \napproach.  PJM bears the burden to show it is just and reasonable.  It cannot, and its \napproach creates the risk of excessive affordability concerns for retail ratepayers.   \nSpecifically, PJM proposes that the levelized cost of all selected RBP offers will \nnot exceed a maximum “willingness to pay” of $555/MW-day, on a MW-weighted average \nbasis over all of the Delivery Years of the RBP.28  As PJM acknowledges, this means sellers \ncan offer substantially different price offers between Delivery Years, so long as the total \nMW-weighted average of all RBP offers over all of the Delivery Years of the RBP does \nnot exceed $555-day.29\nThe predictable consequence of this flexibility is that sellers will front-load their \ncosts into the initial years of their contracts, significantly increasing bill impacts in the near \nterm.  A seller, for example, could charge $1,000/MW-day for the first several years of the \ncontract, and then balance that out with sub-market prices in the latter years.  The result is \nthat customers will be forced to bear what could be extremely large increases in capacity \ncosts during the initial Delivery Years of the RBP.  All during a period when there is \nincreasing concern, including concern by members of this Commission,30 about \naffordability.  Absent a persuasive justification for this levelized offer structure—and there \nis none—the Commission should reject it. \n28\nJuly 31 RBP Proposal at 61-64; Proposed Tariff, Attachment DD at Section 18.5(f). \n29\nJuly 31 RBP Proposal at 62-63. \n30\nSee, e.g., United States House of Representatives, Committee on Energy & Commerce, 2/3/2026 \nHearing:  Oversight of FERC: Advancing Affordable and Reliable Energy for All Americans, comments of \nCommission members."},{"page":11,"startToken":3203,"endToken":3443,"text":"11 \nA “levelized” cost structure is not needed.  The Statement of Principles calls for \nPJM to provide for price certainty for a 15-year term.31  There is significant investment in \nnew generation in areas outside of PJM by vertically-integrated utilities where cost \nrecovery generally is on a straight-line fixed value basis.  And the country’s experience \nwith PURPA contracts reflects that, generally, nonincumbent utility investors are willing \nto construct new generation on a straight-line fixed value basis.  Doubtless, these factors \ninfluenced the Statement of Principles policy directive that PJM was to provide price \ncertainty for a 15-year term. \nAs a “levelized” cost structure is not needed, and as permitting it could lead to \nunacceptable affordability issues, PJM has not carried its FPA Section 205 “just and \nreasonable” burden for going forward.  Accordingly, the Commission should reject PJM’s \nproposed amendments. \n4.\nPJM Has Failed to Demonstrate That Its Cost Allocation \nProposal Is Just and Reasonable. \nPJM proposes that RBP costs will be allocated to LSEs within the territories of \nElectric Distributors.32  Each Electric Distributor’s territory’s share of RBP costs will be \nits pro rata share of the difference between the forecasted load adjustments for the \n2026/2027 and 2028/2029 capacity auction cycles.33  Each Electric Distributor’s territory’s \nshare will then be allocated to LSEs within that territory.34   \n31\nStatement of Principles, Bullet 1. \n32\nSee July 31 RBP Proposal at 96-97. \n33\nId. at 96-97. \n34\nId. at 97-98."},{"page":12,"startToken":3443,"endToken":3770,"text":"12 \nThis proposal is at odds with FPA Section 205 as well as fundamental principles of \ncost allocation.  First, PJM’s cost allocation proposal is not meaningfully targeted to ensure \nthe customers ultimately allocated the costs of the RBP will be entities causing the need \nfor the procurement of new generation—i.e. new data center customers, in accordance with \nthe Statement of Principles.  Rather than proposing an allocation methodology specifically \ntargeted to new data centers, PJM instead proposes allocating the costs based on forecasted \nLoad Adjustments for the 2026/2026 and 2028/2029 Delivery Years.  These forecasted \nLoad Adjustments are not, however, limited to new data centers.  Instead, they include \nfacilities with existing contracts and possibly even those already under construction, as \nwell as potentially native non-data load customers as well.  In short, PJM is proposing to \nallocate the costs of the new generation needed for tomorrow’s data centers to yesterday’s \ncustomers.  PJM fails to explain its departure from the Statement of Principles, and \ntherefore fails to meet its burden under FPA Section 205 to demonstrate its cost allocation \nproposal is just and reasonable. \nPJM’s proposal is also inconsistent with the Commission’s fundamental cost \nallocation principles, particularly the requirement that costs be assigned “roughly \ncommensurate” with the benefits received by customers.35  PJM’s proposed methodology \nto allocate costs to LSEs based on a single forecasting comparison, along with arbitrary \ndiscounts to data center loads, bears no meaningful relationship to reasonably-anticipated \nnew data center load.  To the contrary, PJM’s proposal would allocate costs primarily based \n35\nSee, e.g., Building for the Future Through Electric Regional Transmission Planning and Cost \nAllocation, Order No. 1920-A, 189 FERC ¶ 61,126 at P 157 (Nov. 25, 2024) (Order No. 1920 mandates \n“consistent with long-established Commission and court precedent, that transmission customers within a \ntransmission planning region need only pay costs that are ‘roughly commensurate’ with the benefits that \ntransmission providers estimate they will receive from a regional transmission facility.”) (citations omitted)."},{"page":13,"startToken":3770,"endToken":4118,"text":"13 \non LSEs with existing data center customers, rather than the new data center customers that \nare primarily driving the need for the RBP.  This disconnect between cost causers and \nbeneficiaries and the RBP costs to be allocated will be magnified by PJM’s decision that \nthe allocation will remain fixed for a fifteen-year period.  While cost allocation does not \nrequire absolute precision,  it does require an “articulable and plausible reason” to believe \nthat the benefits received will be at least “roughly commensurate” with the costs.36  There \nis, however, no way to know what load conditions will look like in five years, much less \nfifteen.  Thus, there is no plausible reason to believe that PJM’s zonal cost allocation \napproach will ensure even a rough match between the costs and the beneficiaries of \ncapacity procured in the RBP.37\nPJM’s cost allocation proposal also violates the filed rate doctrine because it will \nundermine preexisting commercial relationships by attempting to allocate costs to data \ncenters who possibly have already signed FERC-jurisdictional contracts based on a pre-\nRBP understanding of the market.  As discussed above, PJM’s proposed allocation \nmethodology could include data center facilities that already have binding commitments, \nincluding contracts between the data center customer and associated EDCs/LSEs.  Those \ncontracts, to the extent they have been filed and accepted by the Commission, constitute \nthe filed rate for those entities with respect to their energy supply obligations.  PJM’s \nproposal does not even recognize, much less attempt to justify, the need or reasonableness \n36\nSee Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009).  See also Transmission \nPlanning & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, 136 FERC \n¶ 61,051 at P 622 (2011). \n37\nThis allocation mismatch is further compounded by PJM’s proposal to require non-defaulting LSEs \nto assume an additional payment obligation solely because another LSE failed to satisfy its allocated RBP \nCharges.  See Proposed Tariff, Attachment DD at Section 18.9(a).  The default of one LSE should not provide \nan independent basis for increasing the RBP costs assigned to another."},{"page":14,"startToken":4118,"endToken":4422,"text":"14 \nof allocating these entities what would essentially constitute additional costs for the same \nservice. \nPJM’s cost allocation proposal also fails to meet the requirements of FPA Section \n205 because the proposed LSE allocation methodologies are dependent in substantial part \non whether and how certain state or other retail regulators choose to exercise their own \nauthority and discretion.  There is no way to determine whether such allocations would be \njust and reasonable because such determination is left entirely to the discretion of state and \nother retail regulators.  The justness and reasonableness of a public utility’s proposal cannot \nbe established based on speculative future action, particularly action by third-parties that \nneither PJM nor the Commission has the authority to control.38\nFinally, PJM’s cost allocation proposal runs afoul of the “rule of reason” requiring \nthat sufficient detail regarding FERC-jurisdictional services be included in a public utility’s \ntariff.  For example, in the affidavit accompanying PJM’s filing, PJM provides a chart with \nexamples of possible RBP cost allocations.39  In this chart, FirstEnergy affiliate Potomac \nEdison is listed as an “Electric Distributor Zone/Area,” subject to cost allocation.  \nHowever, the reference to Potomac Edison is unclear because there are multiple \nFirstEnergy affiliates operating under that banner across three different States.  This \nambiguity suggests that FirstEnergy will have to decide how to sub-allocate the RBP costs \namong these entities, yet the PJM proposal does not even acknowledge, let alone provide \ndetails regarding the implementation of, this sub-allocation.  The Commission cannot \n38\nSee, e.g., N.Y. State Pub. Serv. Comm’n v. FERC, 104 F.4th 886 (D.C. Cir. 2024); N.Y. Indep. Sys. \nOperator, Inc., 183 FERC ¶ 61,130 (2023); Kan. Corp. Comm’n v. FERC, 881 F.3d 924 (D.C. Cir. 2018). \n39\nSee Attachment C, Affidavit of Ms. Danielle Croop at P 46 (“Croop Affidavit”)."},{"page":15,"startToken":4422,"endToken":4690,"text":"15 \napprove a rate filing that is so vague and subject to numerous implementation details that \nhave yet to be even contemplated let alone developed. \n5.\nPJM’s Reliability Backstop Procurement Should Be Limited to \nResources That Most Effectively Address Reliability Needs. \nPJM proposes to permit a broad range of resources to participate in the RBP, \nincluding new generation resources, energy storage resources, demand response resources, \nand distributed energy resources.40  PJM justifies the RBP as an extraordinary measure \nnecessary to address the approximately 6,831 MW capacity shortfall identified in the \n2028/2029 Base Residual Auction and to preserve resource adequacy within the PJM \nRegion.41  Because the stated purpose of the procurement is to address an identified \nreliability need, the Commission should ensure that the procurement is structured to \nprioritize the resources that most effectively advance that need. \nWhile demand response, storage, and distributed energy resources may provide \nvalue under certain circumstances, not all eligible resource types provide the same level of \nreliability benefits or operational certainty.  Because the stated purpose of the RBP is to \naddress a reliability shortfall, the Commission should ensure that the procurement \nappropriately prioritizes resources that provide firm and dependable capacity.  New \ndispatchable generation resources are capable of producing energy when needed and \ntherefore provide a more direct means of addressing the resource adequacy concerns that \nPJM identifies as the basis for the proposal. \nWorth noting here is that the North American Electric Reliability Corporation \n(“NERC”)—which is responsible for developing, applying and enforcing mandatory \n40\nJuly 31 RBP Proposal at 42 n.112. \n41\nJuly 31 RBP Proposal at 31, 68."},{"page":16,"startToken":4690,"endToken":4968,"text":"16 \nreliability standards—has identified that “conventional generators,” such as nuclear, coal \nand natural gas generators, provide much of the essential reliability services that support \nreliable operation of the grid today.42  NERC further reports that wind and solar resources \nlack the spinning mass, that is, the traditional excitation systems, that provide for voltage \ncontrol and stability to support the transmission grid.43  NERC explains that generators that \ncan be controlled, that is, dispatched on demand, provide system inertia, dynamic reactive \nsupport, and frequency response for stable grid operation.44  In an era that is dominated by \naffordability concerns, it would be reasonable to conclude that scarce customer dollars \nshould be directed to resources that provide or reflect the dispatchable characteristics that \nare necessary for reliability. \nThis issue is particularly important given the magnitude of the procurement and the \nfifteen-year commitments associated with selected resources.45  PJM expressly states that \nthe procurement process is designed to select the “least-cost set of resources” that satisfies \nthe procurement target while remaining within the applicable willingness-to-pay \nconstraint.46  Although cost discipline is important, a procurement justified on reliability \ngrounds should not focus exclusively on minimizing costs without sufficient consideration \nof the relative reliability value provided by different resource types. \nFirstEnergy therefore urges the Commission to ensure that the RBP is narrowly \ntailored to procure the resources that most effectively address reliability needs.  At a \n42\n NERC, 2024 Long-Term Reliability Assessment, at p. 29, available at \nhttps://www.nerc.com/globalassets/our-work/assessments/2024-ltra_corrected_july_2025.pdf. \n43\nId. at pp. 29-30. \n44\nId. at p .22. \n45\nJuly 31 RBP Proposal at 76-78. \n46\nJuly 31 RBP Proposal at 78."},{"page":17,"startToken":4968,"endToken":5190,"text":"17 \nminimum, the Commission should require PJM to demonstrate that the proposed \nframework appropriately prioritizes firm and dependable capacity resources and does not \nresult in the procurement of resources that provide less reliability value than reasonably \navailable dispatchable alternatives. \n6.\nPJM’s Proposed Implementation Schedule Is Unreasonably \nCompressed. \nPJM proposes to commence the Reliability Backstop Procurement on September \n30, 2026 and requests that the Commission act on the filing by September 29, 2026.47\nPJM’s proposed schedule would therefore permit the procurement to begin immediately \nfollowing Commission approval.  While FirstEnergy appreciates the need for prompt \naction, PJM’s proposed implementation schedule provides insufficient time for affected \nLSEs, Electric Distributors, state regulators, and retail customers to evaluate the \nconsequences of the proposal and take steps to mitigate resulting obligations.  The RBP is \nnot a minor modification to PJM’s capacity construct, but an entirely new procurement \nmechanism.  The RBP will create substantial long-term payment obligations, impose \nunprecedented collateral requirements, and rely upon state-specific cost-allocation \ndeterminations that, in many jurisdictions, have not yet been developed.48  For these \nreasons, PJM has failed to demonstrate that the compressed timeline is just and reasonable. \nPJM acknowledges that implementation of its proposal requires substantial \ncoordination among PJM, Electric Distributors, states, Regional Electric Reliability \n47\nJuly 31 RBP Proposal at 2-3, 130. \n48\nJuly 31 RBP Proposal at 96-99, 103-105, 116-117."},{"page":18,"startToken":5190,"endToken":5462,"text":"18 \nRegulatory Authorities (“RERRAs”), and load-serving entities.49  Yet, the proposal would \nmove forward before all of these entities have had a reasonable opportunity to determine \nwhether and how, they will implement the proposal. \nThe compressed schedule is particularly problematic given the magnitude of the \nfinancial obligations at issue.  As discussed above, PJM proposes to require LSEs allocated \nRBP costs to post hundreds of millions of dollars collateral.  FirstEnergy’s affiliates alone \nestimate the collateral costs for their retail customers could be in excess of $350 million.  \nBefore such obligations are imposed, affected entities should have a reasonable opportunity \nto assess the proposal, evaluate potential mitigation measures, and coordinate with state \nregulators regarding cost recovery and compliance.  Moreover, unlike prior significant \nmarket reforms—most notably RMM, which is discussed in more detail above—affected \nparties have no meaningful opportunity to avoid these costs.  Once the procurement occurs \nand long-term commitments are established, LSEs will become subject to the resulting \nallocation framework and associated collateral requirements. \nHere, PJM has failed to demonstrate that its compressed implementation schedule \nis just and reasonable.  Although PJM cites the 2028/2029 Delivery Year resource \nadequacy shortfall as the basis for the proposal, PJM has not shown that delaying \ncommencement of the procurement for a reasonable period would undermine the stated \nobjectives of the RBP.  Indeed, PJM’s tariff contemplates a RBP-like procurement only \noccurring after three years of resource adequacy shortfalls, while only two have occurred \nto date. \n49\nFor example, PJM's cost-allocation framework depends on states and/or RERRAs developing and \ncommunicating allocations of RBP obligations among LSEs within each service territory. July 31 RBP \nProposal at 98-99."},{"page":19,"startToken":5462,"endToken":5770,"text":"19 \nPJM doubtless will assert that the Statement of Principles requires the Commission \nto act now.  But the simple fact is that PJM ran six and one-half months off of the clock in \nstakeholder processes, only to reject the consensus position advanced by the majority of \nElectric Distribution Companies and customer representatives that emerged from that \nstakeholder process.50  Having run the clock, and been entirely unwilling to work with its \nstakeholders, it would be unjust and unreasonable to wave PJM through the regulatory \nprocess because of an impending deadline.  PJM is proposing to lock up obligations of as \nmuch as—in its own words—$20.7 billion of its stakeholders’ dollars.  If more time is \nneeded to get it right, then more time should be afforded. \n7.\nPJM’s Proposed “Opt-Out” Mechanism Will Allow \nUnreasonable Cost Shifting Among Load Customers. \nWith regard to Electric Distributors, PJM proposes to reduce the Initial RBP Target \nbased on requests from certain Electric Distributors, such as municipal utilities and \ncooperatives, to “opt out.”51  Thus, an Electric Distributor whose territory qualifies for an \n“opt out” relating to capacity procurement will not have any cost responsibility assigned to \nit.  Such an “opt out” is unduly discriminatory under FPA Section 205 and therefore cannot \nbe approved.  Large load in those territories eligible for the “opt out” is no less real than \nlarge load in any other territory, and PJM provides no reasonable basis for treating such \nloads differently under the RBP.  The proposed ”opt out” is also inconsistent with cost-\ncausation principles because it will result in customers in other territories subsidizing \n50\nSee PJM Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop Procurement \nand Connect and Manage, available at https://www.pjm.com/-/media/DotCom/about-pjm/who-we-\nare/public-disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement-\nand-connect-and-manage.pdf. \n51\nJuly 31 RBP Proposal at 31-33, 44-46."},{"page":20,"startToken":5770,"endToken":6037,"text":"20 \ncustomers in the territories receiving an “opt out.”  There is no lawful basis for requiring a \ndata center located outside of a cooperative’s service territory to subsidize generation \nprocured to serve a data center located within a cooperative's service territory.   \n8. \nPJM Should Strengthen Supplier Performance and Credit \nRequirements. \nThe Commission should ensure that customers are adequately protected against \nsupplier non-performance over the fifteen-year commitment term.  While PJM proposes \nnumerous measures intended to reduce development risk and increase the likelihood that \nselected resources achieve commercial operation, those protections are directed primarily \ntoward construction risk and the risk that a resource fails to come online in the first \ninstance.52  For example, PJM proposes to assess an RBP UCAP MW shortfall charge when \na committed resource fails to achieve commercial operation and provide committed \ncapacity.53  PJM further proposes that a resource’s commitment may ultimately be \nrescinded if the resource fails to provide any committed RBP UCAP MW after three \nconsecutive Delivery Years.54  These provisions help address development risk, but they \nagain do not fully protect customers against the possibility that a resource satisfies its initial \ncommercial operation obligations and subsequently underperforms during the balance of \nits fifteen-year commitment term. \nThis concern is particularly significant because the RBP would provide selected \nsuppliers with long-term, customer-supported revenue streams extending for up to fifteen \nyears.55  LSEs, and ultimately retail customers, will remain responsible for funding those \n52\nJuly 31 RBP Proposal at 60-61, 80-81, 116-118 \n53\nJuly 31 RBP Proposal at 60-61. \n54\nJuly 31 RBP Proposal at 60-61. \n55\nJuly 31 RBP Proposal at 61-64, 76-78."},{"page":21,"startToken":6037,"endToken":6280,"text":"21 \ncommitments throughout the contract term.  Yet PJM has not demonstrated that the \nproposed performance assurance framework provides commensurate protection against the \nlong-term risks associated with supplier underperformance after commercial operation has \nbeen achieved.  The asymmetry is particularly striking because PJM proposes substantial, \nand unnecessary, collateral requirements to protect suppliers against the risk of customer \nnon-payment.   \nIf the Commission permits PJM to proceed with the RBP, it should require PJM to \nstrengthen protections available to customers following commercial operation.  Such \nprotections could include enhanced performance assurance requirements, ongoing credit \nsupport, or other mechanisms designed to ensure that resources receiving long-term RBP \ncommitments remain accountable to customers throughout the entire commitment period.  \nGiven the magnitude of the proposed procurement and the duration of the associated \ncommitments, customers should receive protections that are commensurate with the risks \nand obligations they are being asked to bear. \n9. \nPJM Must Clarify How Its Gating Criteria Apply to Demand \nResponse Resources. \nPJM must clarify how its proposed gating criteria apply to demand response \nresources.  As drafted, the proposal appears to require only a contract or agreement \nevidencing a “plan or evidence of deployed enabling infrastructure,” not a contract or \nagreement demonstrating a clear and binding commitment to provide the MWs sold into \nthe RBP.56\nThat ambiguity is significant.  If demand response resources may satisfy the gating \ncriteria based merely on a “plan,” rather than a binding commitment for the underlying \n56\nJuly 31 RBP Proposal at 74-75."},{"page":22,"startToken":6280,"endToken":6457,"text":"22 \ndemand response capability, the proposal risks treating speculative resources as equivalent \nto committed resources.  Such a result would defeat the purpose of the RBP and require \ndata centers to pay for capacity that has not genuinely been procured. The Commission \nshould require PJM to clarify that eligible demand response resources must be supported \nby binding contractual commitments.  Absent such a requirement, PJM has failed to \ndemonstrate that the proposal is just and reasonable. \nCONCLUSION \nFirstEnergy respectfully requests that the Commission consider the foregoing \ncomments and protest in its consideration of PJM’s RBP Proposal, reject PJM’s filing, \ninstitute an FPA Section 206 proceeding, and establish settlement proceedings. \nRespectfully submitted, \n/s/ Michael Kunselman \nMorgan E. Parke \nMichael Kunselman \nVice President, Associate General Counsel  \nJonathan Namazi \nDaniel T. Lloyd \nDavis Wright Tremaine LLP \nSenior Counsel \n1301 K Street, NW \nFirstEnergy Service Company \nSuite 500 East \n341 White Pond Drive \nWashington, DC 20005 \nAkron, OH 44320 \n \nTel: (202) 973-4295 \nTel: (330) 620-9585  \nmichaelkunselman@dwt.com  \nTel: (330) 384-5947  \njonathannamazi@dwt.com \n  mparke@firstenergycorp.com  \n  dlloyd@firstenergycorp.com \nAugust 21, 2026"},{"page":23,"startToken":6457,"endToken":6533,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have caused the foregoing document to be served upon all the parties \nlisted on the official service list for the above-referenced proceeding, pursuant to the requirements \nof Rule 2010 of the Commission’s Rules of Practice and Procedure.  \nDated at Washington, D.C. this 21st day of August, 2026.  \n/s/ Daniel Klein \nDaniel Klein  \nDavis Wright Tremaine LLP  \n1301 K Street NW \nSuite 500 East \nWashington, D.C. 20005"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":22,"endAt":499,"startToken":0,"endToken":6354},{"p":22,"at":499,"title":"CONCLUSION","method":"printed heading","endPage":23,"endAt":0,"startToken":6354,"endToken":6457},{"p":23,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":23,"endAt":465,"startToken":6457,"endToken":6533}]}