{"document":{"slug":"rec-20260821-5283","title":"Limited Protest of American Electric Power Service Corporation to PJM Interconnection, LLC’s proposed revisions to the Open Access Transmission Tariff and…","issued":"2026-08-21","accession":"20260821-5283","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"American Electric Power Service Corporation","kind":"protest","file":"sources/filings/text/20260821-5283_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5283","tier":"record","sha256":"584b5448d461bac011b096c27068a211fcd1665cfce7b1fe0bb103f79169ec11","pages":38,"tokens":11408,"emptyPages":[],"textThemes":["credit","cost","adequacy","registry"]},"pages":[{"page":1,"startToken":0,"endToken":233,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, LLC  \n) \n \nDocket No. ER26-3380-000  \n \nLIMITED PROTEST OF  \nAMERICAN ELECTRIC POWER SERVICE CORPORATION \n \n \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission (“Commission”) \nRules of Practice and Procedure,1 American Electric Power Service Corporation, on behalf of its \naffiliates Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power \nCompany, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP \nAppalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., \nAEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP \nWest Virginia Transmission Company, Inc. (collectively, “AEP”), hereby submits this protest to \nPJM Interconnection, LLC’s (“PJM”) proposed revisions to its Open Access Transmission Tariff \n(“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to \nestablish a Reliability Backstop Procurement (“RBP”) to Address Resource Adequacy Concerns \nStemming from Large Loads.2 \nI. \nEXECUTIVE SUMMARY \n \nThe resource adequacy crisis in PJM is undisputed.  PJM is confronting the most significant \ngeneration need in its history.  Demand from national security needs, advanced manufacturing, \ndata centers, and electrification is accelerating faster than PJM’s current interconnection processes \n \n1  \n18 C.F.R. §§ 385.211, 385.214 (2025).   \n2  \nReliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from New Load \nAdjustments, Docket No. ER26-3380 (filed July 31, 2026) (“RBP Proposal”).  AEP filed a doc-less motion to \nintervene in the captioned docket on August 5, 2026."},{"page":2,"startToken":233,"endToken":549,"text":"2 \n \nand market mechanisms allow the region to plan and build the infrastructure needed to reliably \nsupport such unprecedented load growth.  Given the urgency of the problem, PJM rightfully \nproposes to move with extraordinary speed to commit significant capital to new generating \ncapacity.  AEP has urged PJM to aggressively address both the current resource adequacy crisis \nand the existing structures that gave rise to the shortfall, and supports measures to address the PJM \nregion’s capacity shortfall.  Notwithstanding AEP’s support for swift and decisive action, the \namount of capital required for this effort and the associated potential impact on wholesale and \nretail rates render the details of implementation critically important.  With that in mind, several \nimportant elements of the RBP Proposal must be reformed to ensure that the RBP produces just \nand reasonable outcomes for customers.  Consequently, AEP urges the Commission to exercise \ncaution, subject the RBP Proposal’s details to meaningful scrutiny, and make use of the broad \ndiscretion PJM has afforded the Commission through its willingness to make the components of \nthe RBP design “severable” for purposes of NRG.3 \n \nDespite AEP’s overall support for the RBP concept as a near-term measure to address the \nregion’s resource adequacy crisis, certain changes are needed.  Specifically, the Commission \nshould:  (1) either reject PJM’s proposed Transmission Owner4 exit provisions or direct PJM to \nmodify them to limit any continuing RBP financial obligation of a departing Transmission Owner \nto the RBP Charges already allocated to that Transmission Owner’s zone under the Commission-\naccepted RBP Charge cost allocation methodology, and confirm that any new provisions do not \ndisturb the Commission’s established precedent governing Regional Transmission Operator \n \n3  \nSee RBP Proposal at 3.  NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) (NRG). \n4  \nCapitalized terms not otherwise defined herein shall have the meaning ascribed to them in the PJM Tariff \nand the RBP Proposal, as applicable."},{"page":3,"startToken":549,"endToken":759,"text":"3 \n \n(“RTO”) exit obligations; (2) direct PJM to revise its proposed cost allocation methodology to \nclarify that:  (a) Electric Distributors bear no financial liability for RBP Charges solely by virtue \nof their administrative role to report Load Serving Entities’ (“LSEs’”) RBP Obligations; and (b) \ncollateral obligations attach to LSEs allocated RBP Charges; and (3) direct PJM to acknowledge \nand correct on compliance the drafting error in RAA, Schedule 8.1.D, Section D.1.1 that would, \nas written, fail to achieve PJM’s stated intent with respect to Fixed Resource Requirement (“FRR”) \nEntities. \nII. \nCORRESPONDENCE AND COMMUNICATIONS \n \nCorrespondence regarding this filing should be sent to the following individuals, who \nshould be placed on the official service list in this proceeding:5 \n \nJohn C. Crespo \nSenior Legal Counsel \nAmerican Electric Power Service Corporation \n1 Riverside Plaza \nColumbus, Ohio 43215 \n(614) 716-3727 \njccrespo@aep.com \n \nChristopher R. Jones \nWilliam R. Derasmo \nEmily Beard  \nTROUTMAN PEPPER LOCKE LLP \n401 9th Street, NW Suite 1000 \nWashington, DC \n(202) 662-2181 \nchris.jones@troutman.com \nwilliam.derasmo@troutman.com \nemily.beard@troutman.com  \n \n \n \n \n \n \n5  \nAEP respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) to allow more than two individuals to be \ndesignated for service on the official service list in this proceeding."},{"page":4,"startToken":759,"endToken":1120,"text":"4 \n \nIII. \nBACKGROUND \nTo address the near-term reliability concerns exposed by PJM’s 2028/2029 Base Residual \nAuction (“BRA”), which cleared short of PJM’s target reserve margin by 6,831.3 MW at the \nCommission-approved price cap of $325/MW-day, PJM proposes to conduct a one-time RBP for \nprocuring new capacity from September 30, 2026 to October 21, 2026.6  The proposed rules \ngoverning the RBP are set forth in PJM’s Tariff and PJM’s RAA and are designed to allow PJM \nto procure the capacity needed to meet the shortfall from the 2028/2029 BRA.7  The January 16, \n2026 National Energy Dominance Council/PJM Governors’ Principles urged PJM to procure new \ncapacity through a backstop auction commencing no later than September 2026, provide 15-year \nprice certainty for new capacity resources, and allocate the costs of that capacity to LSEs with new \ndata centers that have not self-procured new capacity or agreed to be curtailable.8  PJM explains \nthat the initial RBP procurement target (“Initial Target”) for the RBP will be set at 6,831.3 MW, \nsubject to reduction after PJM has accounted for certain self-supplied new capacity and opt-outs.9  \nNoting that PJM members have expressed a strong preference for bringing new capacity to \nthe PJM system voluntarily rather than contracting through PJM, PJM has facilitated a bilateral \nmatching process to connect new capacity with new load.  The process began with an RFP on June \n \n6  \n RBP Proposal at 25-27; see also PJM INSIDE LINES, PJM Capacity Auction Procures 138,318 MW of \nGeneration Resources as Work Continues to Address Growing Electricity Demand (July 14, 2026), \nhttps://insidelines.pjm.com/pjm-capacity-auction-procures-138318-mw-of-generation-resources-as-work-continues-\nto-address-growing-electricity-demand/. \n7  \n RBP Proposal at 26; id. at 3–6 (describing the forthcoming IRAS filing and broader holistic review); see \nalso PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and \nStimulating \nInvestment \nto \nSupport \nDurable \nReliability \n(May \n20, \n2026), \nhttps://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mrc/2026/20260520/20260520-powering-reliability-through-\nmarket-design.  \n8  \nDEP’T OF ENERGY, Statement of Principles Regarding PJM (Jan. 15, 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm. \n9  \nRBP Proposal at 26.  FRR Entities are excluded from the RBP.  Id. at 31."},{"page":5,"startToken":1120,"endToken":1481,"text":"5 \n \n9, 2026, and initial matches were expected in or around August 2026.10  Participation is voluntary \nand non-binding, and PJM is not a party to the resulting arrangements.  In addition to accounting \nfor opt-outs, PJM will reduce the Initial Target by capacity obtained through this bilateral matching \nprocess or other voluntary agreements for new capacity (“Qualifying RBP Offset MW”),11 if \nreported to PJM within the RBP procurement window by October 21, 2026.12  This reduced \ncapacity procurement target (“Final Target”) will then form the basis for the RBP procurement.   \nPJM explains that offers in the RBP will be for a fixed 15-year Delivery Year term and are \nexpected to commence commercial operation in the 2028/2029 Delivery Year.13  RBP capacity \nwill be paid-as-bid and subject to a must-offer requirement for the term of its commitment.14  The \ntotal cost of the RBP could amount to up to $20 billion over the 15-year term, and $1.63 billion \nannually.15  Following the conclusion of the RBP, PJM states that it will post a report that provides \na transparent overview of the aggregate MWs that were procured as well as a weighted average of \nthe RBP Charges as soon as practicable.16  PJM concedes that there is a possibility that it may clear \na set of resources that does not match the Final Target.17 \nPJM explains that, because the Final Target will be based on a region-wide shortfall, it is \nnot proposing to match specific supply to specific demand or apply locational constraints in the \n \n10  \nId. at 30-31. \n11  \nPJM explains that the Initial Target will only be decremented by a quantity of capacity that was not already \ncounted as supply for the 2027/2028 Delivery Year and that serves load that was counted in the forecasted demand \nfor the period from 2027 through the beginning of the 2028/2029 Delivery Year.  Id. at 37.   \n12  \nId. at 31.  \n13  \nId. at 48.   \n14  \nId. at 42, 58-59.   \n15  \nThis estimate is based on the following calculation: 6.8 GW (procurement target) × $555/MW-day \n(maximum willingness to pay) × 15 years (commitment term). \n16  \nId. \n17  \nId. at 80."},{"page":6,"startToken":1481,"endToken":1750,"text":"6 \n \nRBP.18  PJM states that, unlike the Reliability Pricing Model (“RPM”), whose annual three-year \nforward framework allowed PJM to model the necessary locational parameters, PJM does not have \nthe information needed to determine such parameters for 15-year term capacity commitments.19  \nAccording to PJM, “including locational parameters based on today’s conditions would . . . lead \nto either over-procurement or under-procurement in given zones based on nothing more than \nspeculation . . . .” and “ignore the role of PJM[] . . . to ensure delivery of capacity resources to load \nthroughout PJM.”20  PJM does not propose direct market power screens or mitigation for the RBP, \ncontending that the pay-as-bid structure with a maximum willingness to pay $555/MW-day limits \nthe effectiveness of direct market screens or mitigation.21  RBP Sell Offers are considered binding, \nand RBP capacity that is subject to a Sell Offer is not permitted to exit the RBP to enter bilateral \narrangements unless the project is not committed in the RBP following the conclusion of the \nprocurement process.22   \nEach committed RBP Resource will individually settle as a contract-for-differences \n(“CfD”).23  This settlement structure turns on a committed RBP Resource’s individualized strike \nprice.  A committed RBP Resource must offer all committed RBP Unforced Capacity (“UCAP”) \nMW as a price-taker in the RPM, unless a qualifying exception applies.  The market price for the \nRBP Resource is specifically defined as the resource’s unit-specific weighted average resource \nclearing price (“WARCP”) for all RPM Auctions in which the RBP Resource participated for the \n \n18  \nId. at 33.   \n19  \nId. at 33-34. \n20  \nId. at 34.   \n21  \nId. at 66-71. \n22  \nId. at 49. \n23  \nId. at 79-80."},{"page":7,"startToken":1750,"endToken":2062,"text":"7 \n \nrelevant Delivery Year.24  If the strike price is higher than the market price, the RBP Buyer must \npay the difference between the strike price and the market price.25  If the strike price is lower than \nthe market price, the RBP Resource must pay back the difference between the two.  PJM contends \nthat this settlement structure protects RBP Buyers from paying RBP Resources a windfall, while \nprotecting RBP Resources from settling below market prices.  The total MW eligible to settle as a \nCfD is the lesser of the RBP Resource’s daily committed RBP UCAP MWs, daily owned UCAP \nMWs, and daily cleared RPM UCAP MWs.26  In other words, RBP Buyers do not pay if the RBP \nSellers’ capacity does not clear RPM also, an effort to further prevent over procurement.   \nPJM proposes a three-tiered cost allocation system for RBP Charges, first allocating costs \nto Electric Distributor zones/areas, followed by LSEs, and then ultimately to retail customers.  For \nthe last two steps, PJM’s cost allocation methodology relies on coordination between Electric \nDistributor zones/areas, state regulatory authorities, and state regulatory processes.  First, before \nallocating RBP Charges, PJM allocates cost responsibility to the relevant Electric Distributor \nzones/areas.  To do so, PJM proposes to determine each relevant Electric Distributor zone/area’s \npro rata responsibility for the Initial Target based on forecasted load growth from the 2026/2027 \nDelivery Year to the 2028/2029 Delivery Year, incorporating certain load adjustments from the \n2026 PJM Load Forecast.27  PJM then proposes to adjust each Electric Distributor zone/area’s \nallocation to reflect reductions based on its ability to procure Qualifying Offset MWs or \nsuccessfully support an opt-out.28  After calculating the Final Target, PJM will reallocate RBP \n \n24  \nId. at 80.   \n25  \nId.  \n26  \nId. at 81. \n27  \nSee RBP Proposal, Attachment C, Affidavit of Danielle Croop ¶¶ 42-43 (“Croop Affidavit”).    \n28  \nId. ¶ 44."},{"page":8,"startToken":2062,"endToken":2361,"text":"8 \n \nCharges based on each Electric Distributor zone/area’s adjusted pro rata share of the Final Target.29  \nAfter receiving its allocation of RBP Charges, each Electric Distributor will coordinate with states \nand/or the Relevant Electric Retail Regulatory Authority (“RERRA”) to determine the allocation \nof RBP Charges attributable to an LSE in its zone/area (“RBP Obligation”) and report the RBP \nObligation to PJM.30  PJM will then use the RBP Obligation to assess RBP Charges to each LSE.  \nIf no RBP Obligation is reported, PJM will assign RBP Charges to LSEs using PJM’s method for \nallocating capacity costs pursuant to RAA, Schedule 8.31  Finally, states and RERRAs may decide \nhow to further allocate RBP Charges to the appropriate retail customers.32 \nRBP Buyers and Sellers must meet a variety of requirements to become eligible to \nparticipate in the RBP, including collateral requirements that apply in addition to and separate \nfrom existing collateral requirements.33  RBP Buyers are required to post collateral to mitigate the \nrisk of potential defaults from non-payment of RBP Charges.  This requirement begins at an \namount sufficient to mitigate the long-term risk of the RBP commitment.34  As with cost allocation, \nPJM first determines the overall credit requirement needed to address the risk associated with RBP \ncommitments throughout the RBP 15-year term on a region-wide basis, assigning a $/MW rate \napplicable to all RBP capacity.35  In determining the credit requirement, PJM will multiply the \ntotal capacity committed in the RBP by the RBP Credit Rate, which is initially set at $1.5 million.36  \n \n29  \nId.  \n30  \nId. ¶¶ 51-52; RBP Proposal at 98.  \n31  \nCroop Affidavit ¶ 52; RBP Proposal at 98-99. \n32  \nRBP Proposal at 100.   \n33  \nId. at 109. \n34  \nId. at 111.  \n35  \nId. at 115.   \n36  \nId. at 116."},{"page":9,"startToken":2361,"endToken":2714,"text":"9 \n \nEach LSE is then required to post, at least 45 days before the start of the Delivery Year, collateral \nequal to the product of $1.5 million and its allocated RBP Obligation.37  An RBP Buyer’s credit \nrequirement is designed to go down over time, as the LSE’s RBP Obligation decreases.38 \nPJM also proposes rules setting forth the responsibilities of “various parties” in the event \na Transmission Owner exits from PJM.39  PJM explains its goal to establish clear and enforceable \nrules to ensure that RBP Resources would be made whole for the entire term of the 15-year \ncommitment.40  PJM thus proposes that a departing Transmission Owner with RBP commitments \nin its zone will have two options prior to exit:  depart with net load or net generation. \n• Departing with load: If a Transmission Owner exits PJM with the net load in its region, \nbefore exiting, the Transmission Owner must either execute a binding agreement(s) that \nwould maintain appropriate rates, terms, and conditions, and preserve the RBP \ncommitments with the owners of the RBP Resources or pay (on an accelerated basis) all \nfuture RBP Charges it would have owed.41 \n• Departing with generation: If a Transmission Owner exits with net generation (i.e., RBP \nResources) in its territory, the departing Transmission Owner must either ensure its RBP-\ncontracted generation continues to serve PJM through a pseudo-tie (and agree to cover all \nrelated costs) or, if that is not possible:   (1) pay its remaining RBP obligations in full (on \nan accelerated basis) before exiting; or (2) execute a binding agreement(s) that would \n \n37  \nId. at 120. \n38  \nId. at 120-121. \n39  \nId. at 90. \n40  \nId. at 91. \n41  \nId. at 94-95.  The revenue collected will be credited to the remaining loads in PJM responsible for paying \nRBP Charges.  Id. at 95.  PJM states that, while the exiting Transmission Owner would initially be responsible to pay \nthe costs necessary to ensure no RBP Resource becomes a stranded asset, nothing in the RBP Proposal would preclude \na Transmission Owner from seeking to recover the costs from the relevant large loads.  Id."},{"page":10,"startToken":2714,"endToken":3043,"text":"10 \n \nmaintain appropriate rates, terms, and conditions of the RBP commitments, thus stepping \ninto PJM’s role in the RBP context.42 \nIn the event the Commission deems necessary, PJM consents to the Commission’s exercise \nof authority to modify and/or sever any element of the proposed Tariff or RAA language to the \nextent necessary and permitted under section 205 of the Federal Power Act (“FPA”) and NRG,43 \nwhere such modification and/or severance is consistent with PJM’s overarching objectives in this \nfiling.44 \nIV. \nPROTEST \nA. \nPJM’s Proposed Transmission Owner Exit Provisions are Unjust and \nUnreasonable \nThe RBP Proposal, absent the modifications requested herein, could meaningfully and \nunfairly expand the negotiated terms of exit embedded in the Consolidated Transmission Owner’s \nAgreement (“TO Agreement”), Operating Agreement (“OA”) and RAA.  If and to the extent the \nCommission approves the RBP, AEP does not object to the notion that departing loads continue \nto pay for the RBP Charges assigned to them as a result of this one-time event, but objects to the \nimposition of an exit fee that obligates departing load to pay for charges that are unrelated to its \nfair allocation of RBP commitments. \nAEP has publicly announced that it is evaluating whether continued membership in PJM \nwill be in the best interest of its customers in the long run.  It is common knowledge that PJM’s \n \n42  \nId. at 92-94.  PJM states that the exact amount that an exiting Transmission Owner would owe would be \ndetermined through a separate filing with the Commission.  Id. at 94.  Thereafter, PJM states that it would pay the \ncollected revenues from the Transmission Owner to the impacted RBP Resources as payments become due.  Id. \n43 \nNRG, 862 F.3d 108. \n44  \nRBP Proposal at 3.  PJM cautions that if severance or modification gives rise to complications, it may delay \nthe opening of the RBP procurement window, causing downstream impacts such as the need to delay the BRA for the \n2029/2030 Delivery Year.  Id."},{"page":11,"startToken":3043,"endToken":3373,"text":"11 \n \ngoverning documents do not contain an exit fee, and Commission precedent confirms that a \ndeparting member’s obligation with regard to generating capacity charges extend only through the \nlast RPM auction in which that departing member’s load was included.  With that in mind, the \nRBP Proposal’s exit provisions stand to broaden what the Commission has deemed necessary for \ndeparting load to honor cost commitments.  Principles of cost causation require PJM to \ndemonstrate a reasonable nexus between the capacity procured in the RBP and the reliability need \nfor which customers are being charged.  As drafted, the RBP Proposal would impose a financial \nobligation on a departing Transmission Owner based not on the RBP Charges allocated to an \nElectric Distributor zone/area pursuant to PJM’s proposed RBP cost allocation methodology, but \non where PJM happens to procure or locate new RBP resources.  In this respect, the RBP Proposal \nflouts cost causation principles by imposing an exit fee that could far exceed the RBP Charges \nallocated to a departing Transmission Owner’s zone.45   \nFor these reasons and as explained further below, the Commission should reject the \nproposed Transmission Owner exit provisions or, at minimum, require PJM to revise them before \nacceptance.  Any revised exit provisions should be consistent with these principles:  (1) a departing \nTransmission Owner’s responsibility for RBP Charges is limited to the RBP Charges otherwise \nassigned to its zone/area under the Commission-accepted RBP cost allocation; (2) PJM may not \nrequire a departing Transmission Owner to assume or guarantee, payment of obligations associated \nwith RBP Resources beyond that limited responsibility, nor require acceleration of any payment \nobligation; (3) any proposed RTO replacement arrangement or continuity agreement must be \ncalculated by reference to the withdrawing Transmission Owner’s allocated RBP Charges, not by \n \n45  \nSee K N Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992) (finding that cost causation requires \nthat all approved rates reflect to some degree the costs actually caused by the customer who pays them)."},{"page":12,"startToken":3373,"endToken":3654,"text":"12 \n \nartificial reference to RBP Resources physically located in the relevant zone; (4) a Transmission \nOwner’s responsibility for RBP Charges should remain eligible for the RBP Settlement Credits \nand RPM Auction Credits that would apply as cost offsets if the same load remained in PJM; and \n(5) the exit fee attributable to a departing Transmission Owner’s responsibility for RBP Charges \nshould be reasonably capable of being calculated with the information known based on the results \nof the RBP. \n1. \nThe Proposed Exit Terms Lack Sufficient Clarity and Detail \nThe RBP Proposal’s proposed allocation of RBP Charges to departing Transmission \nOwners, first of all, lacks needed detail in light of the enormity of the financial burden it stands to \nimpose.  Moreover, even the language that is sufficiently clear creates an unjust and unreasonable \nobligation on a withdrawing member. \nSpecifically, section 18.7 of the proposed Tariff language lacks administrable standards \nand is underdeveloped for the following reasons:   \n• Section 18.7 (a) first mentions voluntary agreements that a departing Transmission Owner \n“may” enter into with RBP Resources in the applicable zone under the standard that they \n“preserve[] the RBP commitments . . . with the owners of RBP Resources . . . .”46  It is not \nclear what this standard requires, including whether that agreement is intended to preserve \nthat unit’s obligations to PJM, or whether the RBP Resource could agree to serve as a \ncapacity resource to the departing Transmission Owner.   \n• PJM also has not explained or justified its request to have unfettered discretion to merely \nelect not to “retain” an RBP Resource that can be pseudo-tied back to PJM, as provided in \n \n46  \nRBP Proposal, Attachment B, Clean Tariff Records, Attachment DD, § 18.7(a) (“Proposed Tariff”)."},{"page":13,"startToken":3654,"endToken":3947,"text":"13 \n \nsection 18.7(a).47  Pursuant to the second paragraph of section 18.7(a), PJM wants the right \nto “elect” not to retain such a resource that could be pseudo-tied and foist a financial \nobligation on the departing member to take on 100 percent of the RBP Resource’s \nremaining revenue requirement for the 15-year term.48   \n• Section 18.7(b) in turn is also fatally vague.  It provides that a departing Transmission \nOwner exiting with net load that has been allocated RBP Charges for RBP Resources not \nlocated in its zone should enter into bilateral contracts with RBP resource not located in \nits Zone—i.e., with resources remaining in PJM—under the vague notion that such an \nagreement would “preserve[] the RBP commitments.”49  Since a departing Transmission \nOwner will have no relationship with any such unit, it is not clear what sort of contract may \nsatisfy this requirement.   \n2. \nThe Proposed Exit Terms are Unjust and Unreasonable Because the \nRBP Charges of Departing Zones Are Not Reduced By \nCorresponding RPM Revenues or Other Offsets \nPJM’s proposed exit provisions are also unjust and unreasonable because they:  (1) appear \nto require a departing Electric Distributor zone/area to assume liability for the gross cost of RBP \nResources without preserving the offsets and settlement protections that would apply if the same \nload remained in PJM; and (2) do not protect departing Transmission Owners from assuming RBP \nCharges in the event that RBP Resource capacity becomes surplus in PJM.  Under PJM’s proposed \nCfD structure, RBP Buyers pay RBP Charges based not simply on the full quantity of RBP MW \nacquired, but rather on an adjusted value that reflects a corresponding settlement value from PJM.  \n \n47  \nId. \n48  \nId. \n49  \nId. § 18.7(b)."},{"page":14,"startToken":3947,"endToken":4262,"text":"14 \n \nUnder PJM’s proposed exit structure, however, departing load appears to be required to fund the \nfull RBP strike price without the adjustment afforded to remaining members.   \nThe RBP Charge is intended to be netted against the resource’s RPM market value through \nthe offsetting the RBP Settlement Credit, which is based on the lesser of three MW values:  (1) \ndaily committed RBP UCAP MWs, (2) daily owned UCAP MWs, and (3) daily cleared RPM \nUCAP MWs.50  That offset is central to PJM’s own explanation of the RBP as a supplement to, \nnot a replacement for, RPM.51  However, PJM’s proposed Transmission Owner withdrawal \nprovisions only provide that a Transmission Owner departing with net load that has been allocated \nRBP Charges for RBP Resources—if it does not enter into agreements that maintain appropriate \nrates, terms and conditions that preserve the RBP commitments with the owners of such RBP \nResources—must pay all forward obligations on an accelerated basis through the remaining term \nof the RBP commitment.52  This proposed term does not make clear that a Transmission Owner \ndeparting with net load and responsible for funding RBP commitments throughout their 15-year \ncommitment term would be afforded the offset price for an RBP Resource that it would receive if \nit stayed in PJM.  \nIn the example provided by PJM, the RBP Resource may clear substantially more MWs in \nthe RBP than in the RPM, but is still eligible to receive RBP Settlement Credits that reduce the \nRBP Charge assessed.53  If a Transmission Owner’s post-exit obligation is calculated based only \non the gross RBP Charge, while disregarding the quantity of RBP MW that clears both the RBP \nand RPM, the exit fee allocated to an exiting Transmission Owner would be calculated without \n \n50  \nRBP Proposal at 81. \n51  \nSee id. at 7.  \n52  \nProposed Tariff, Attachment DD § 18.7(b). \n53  \nRBP Proposal at 85."},{"page":15,"startToken":4262,"endToken":4571,"text":"15 \n \naccounting for the offsets that would otherwise accrue had it stayed in PJM.  Consequently, \ndeparting Transmission Owners and their load remain exposed to a substantial portion of the RBP \nCharges with no corresponding opportunity to receive an offset to the RBP Charge, thus forcing \nthe departing Transmission Owner and its customers to pay more than similarly situated load that \nstays in PJM.  This result is unjust, unreasonable, and unduly discriminatory, and is not tied to cost \ncausation. \nThis outcome is asymmetrical and inconsistent with PJM’s stated premise that RPM \nremains the foundational capacity market and that the RBP merely addresses incremental resource \nadequacy concerns.  If a Transmission Owner departing with load is required to fund the entire \nRBP payment obligation for an RBP Resource, principles of cost causation require that departing \nload should receive a corresponding RPM Auction Credit or RBP Settlement Credit tied to the full \namount of capacity for which it is paying.  Otherwise, the RBP would function less as a \nsupplemental reliability mechanism and more as an additional capacity procurement obligation \nrequiring load to pay a higher RBP Charge for the RBP Resources in its zone than it would have \notherwise been assessed had the load stayed in PJM.  The Commission should direct PJM to \nexplain why this outcome fairly represents a Transmission Owner’s responsibility for its RBP \nCharges. \nPJM should also be required to demonstrate why it proposes to limit the RBP Settlement \nCredit to overlapping RPM-cleared MW only for load remaining in PJM, and how that limitation \nproduces a just and reasonable allocation of RBP Charges and benefits for departing Transmission \nOwners or Electric Distributor zones/areas.  This design increases the risk that a departing \nTransmission Owner will be allocated an unreasonable share of RBP Charges following its \nwithdrawal from PJM.  The examples put forth in the RBP Proposal illustrate that the economic"},{"page":16,"startToken":4571,"endToken":4878,"text":"16 \n \nvalue of the CfD is limited to the quantity of MW that clears in both RPM and the RBP.54  This \nlimitation becomes particularly significant in the event that future load reductions, market changes, \nor an Electric Distributor or Transmission Owner exit result in RBP Resources becoming surplus \nto PJM’s capacity needs.  For example—and as a result of PJM’s decision not to implement \nlocational parameters in the RBP—if a Transmission Owner leaves PJM with the net load that \nformed the basis for its allocation of RBP Charges, the RBP Resources procured on its behalf that \nare located outside of the zone/area may no longer be needed in PJM.  Under such circumstances, \nRPM clearing levels may decline, thereby reducing or eliminating the quantity of MW eligible for \nCfD settlement and associated RBP Settlement Credits or RPM Auction Credits, while customers \nin the exiting zones/areas remain responsible for the underlying RBP Charges.  The RBP Proposal \ntherefore creates the possibility that departing load will continue paying for RBP Resources long \nafter the market no longer recognizes equivalent capacity value through RPM. \nThis is especially concerning with respect to PJM’s proposed long-term cost responsibility \nframework.  If an Electric Distributor or Transmission Owner remains responsible for RBP \nCharges after an exit, PJM has not demonstrated that corresponding RPM revenues or CfD \nsettlement benefits, including RPM Auction Credits and RBP Settlement Credits, will remain \navailable throughout the 15-year commitment.  The RBP Proposal therefore risks creating an \nunfairly fixed financial obligation under which customers remain responsible for unabated RBP \nCharges, even as the quantity of RBP MW eligible to receive RPM Auction Credits declines over \ntime.  At a minimum, PJM should clarify how withdrawing Transmission Owners will be protected \nfrom paying for RBP Resources whose capacity has become surplus to PJM’s needs and no longer \n \n54  \nId. at 84-86."},{"page":17,"startToken":4878,"endToken":5241,"text":"17 \n \nreceives corresponding RPM value either because of the Transmission Owner’s withdrawal or \nother changes in conditions impacting resource adequacy in PJM. \n3. \nAny Imposed Exit Terms Should Be Consistent with Cost Causation \nAnd Should be Capable of Determination in Advance of Withdrawal \nIn addition to the issues addressed above, the RBP Proposal reflects a disconnect between \na departing load’s responsibility for RBP Charges upon withdrawal and PJM’s proposed exit \ncharges without explanation regarding how the proposed exit fee is tied to the departing load’s \ninitial allocation of RBP Charges.  The starting point for this analysis is PJM’s decision to propose \nan RBP process with no locational deliverability requirement.55  The RBP Proposal expressly \nassumes that new generation anywhere in PJM is deliverable to any load in PJM.  Under its \nproposal, PJM could acquire all 6,831.3 MW of new supply in New Jersey, or North Carolina, or \neven suburban Chicago.  More to the point for AEP, PJM could decide to acquire all—or at least \na disproportionate share of — the new capacity in Ohio.  This is a stark departure from the RPM’s \ndesign, which does include locational elements, and relies on Capacity Emergency Transfer \nObjectives (“CETO”) and Capacity Emergency Transfer Limits (“CETL”) modeling to ensure that \ncleared capacity can address the reliability needs of constrained areas.56  As a result, customers \nmay be required to fund RBP Resources that are not deliverable to their zone, while resources that \nare necessary to address local reliability needs may not be procured at all.  The RBP Proposal \n \n55  \nId. at 33.  \n56  \nPJM’s claim that it cannot predict future CETO or CETL values with precision does not eliminate the need \nto establish a reasonable relationship between the resources procured and the reliability benefits for which customers \nare charged.  At minimum, PJM should be required to explain how it will evaluate whether RBP Resources remain \nreasonably connected to the reliability needs of a zone that continues to bear RBP Charges, including after an Electric \nDistributor or Transmission Owner exits PJM.  Absent such a showing, the proposed cost responsibility framework \nrisks obligating customers to pay for capacity that is incapable of addressing their underlying reliability needs."},{"page":18,"startToken":5241,"endToken":5549,"text":"18 \n \ntherefore raises a fundamental question regarding whether the RBP can reasonably achieve its \nstated reliability objective without accounting for known transmission limitations. \nSetting aside whether this approach will ensure reliability for the entire PJM region (which \nshares the costs of the RBP), the lack of a locational element undermines PJM’s proposed exit \nprovisions.  If a transmission owning member of PJM exercises its contractual right to leave, its \nobligations for RBP Charges cannot be more than if that member decided to stay.  As proposed, a \nTransmission Owner remaining in PJM would pay RBP Charges according to PJM’s proposed \ncost allocation methodology (if accepted), while a departing Transmission Owner could be \nrequired to assume responsibility for RBP commitments tied to the RBP Resources in its zone/area, \nregardless of whether those commitments correspond to the RBP Charges allocated to that \nzone/area.  Indeed, under PJM’s proposal, a departing Transmission Owner would essentially have \nto indemnify each RBP Resource in its zone for the remainder of its RBP capacity commitment, \neven though—due to the lack of a locational element in the RBP—said RBP Resources may not \nbe at all tied to that Transmission Owner.   \nBased on the exclusion of locational parameters from the RBP’s design, the location of \nselected RBP Resources may bear little relationship to the RBP Charges allocated to any particular \nzone/area.  Thus, if PJM procures a substantial amount of RBP capacity in one zone/area, the \nTransmission Owner for that zone/area could face exit-related obligations materially greater than \nthose imposed by the RBP Charges otherwise allocated to that zone/area.  PJM’s potentially \npunitive proposal threatens to place an undue burden on departing Transmission Owners solely by \nvirtue of where RBP Resources are located.  This outcome would create an undue barrier to a \nTransmission Owner’s ability to exercise its long-held contractual right to leave."},{"page":19,"startToken":5549,"endToken":5869,"text":"19 \n \nSuch an outcome would not comport with the principles of cost causation, nor would it \nprovide meaningful notice to Transmission Owners of the financial consequences of RTO \nwithdrawal.  Furthermore, it would potentially impose a disproportionate financial burden and \nexpand the contractual requirements on Transmission Owners seeking to withdraw from PJM.  \nStated differently, PJM’s proposed exit framework could transform each LSE’s allocated RBP \nCharge into an unduly burdensome exit fee for a departing Transmission Owner.  The Commission \nshould reject the proposed exit provisions and require PJM to limit a departing Transmission \nOwner’s liability to the RBP Charges allocated to its zone under PJM’s proposed cost allocation \nmethodology, as accepted by the Commission.  Modifying PJM’s proposal in this manner would \nstill insulate existing PJM members from RBP-related cost shifts upon a member’s departure while \navoiding the creation of obligations that are not tied to an Electric Distributor zone/area’s allocated \nRBP Charges. \nAt a minimum, any RBP exit fee must be defined through an objective formula that can be \ncalculated using the information known once the RBP results are final.  The cost of exiting an RTO \nmust be clear and transparent so that a Transmission Owner can act in the best interests of its \ncustomers.  As stated above, the formula should begin with the departing Transmission Owner’s \nzone or area-level’s allocation of RBP Charges established under a Commission-accepted cost \nallocation for RBP Charges, as adjusted for any Qualifying RBP Offset MW, opt-outs, or other \naccepted reductions.  That amount should then be converted into a fixed, annual payment \nobligation for each remaining Delivery Year of the RBP commitment term, based on the RBP \nCharges that would otherwise have been assessed to the load remaining in PJM.  The RBP exit fee \nshould be reduced by any RBP Settlement Credits, RPM Auction Credits, refunds, offsets, or other \ncredits that would have applied had the load remained in PJM, and it should not include any"},{"page":20,"startToken":5869,"endToken":6167,"text":"20 \n \nadditional obligation tied to the identity or physical location of RBP Resources selected by PJM.  \nWith respect to any amounts not reasonably capable of being estimated as of the date of \ncalculation, the Tariff should include an obligation for those credits or other amounts to be paid \nover time as they are realized.  This approach would preserve PJM’s stated objective of preventing \ncost shifts to remaining load while giving departing Transmission Owners, customers, and state \nregulators a transparent and reasonably calculable measure of the financial consequences of \nwithdrawal. \n4. \nIf An RBP Exit Fee is Accepted, the Commission Should Respect and \nConfirm Existing Exit Standards For RTO Withdrawal \nTo the extent the Commission accepts any exit obligation for RBP Charges, it must make \nclear that its ruling is limited to those charges and does not undermine existing precedent governing \nexisting PJM withdrawal obligations.  The Commission has already addressed the contractual \nobligations that apply when a PJM member exits, and nothing in this proceeding should expand \nthose obligations beyond the specific Tariff language adopted for RBP Charges.  AEP’s concerns \nwith the RBP withdrawal obligations addressed above underscore a broader need for the \nCommission to clarify how the proposed RBP framework will impact departing Transmission \nOwner’s responsibilities upon withdrawal now, before PJM creates new long-term obligations that \ncould affect future RTO transition decisions.  Such clarification will allow Transmission Owners, \ncustomers, and state regulators the ability to evaluate the consequences of any potential RTO \ntransition before long-term obligations are created.  The relationship between any new RBP exit \nrequirements and PJM’s existing exit framework must be clearly defined such that PJM’s members \nand their customers and state regulators have adequate notice of how a member’s contractual \nobligations for departure will change should the Commission approve the RBP.  This topic is thus"},{"page":21,"startToken":6167,"endToken":6681,"text":"21 \n \nripe for consideration in this proceeding because the terms of the RBP Proposal, if accepted, stand \nto expand Transmission Owners’ contractual obligations upon departure from PJM. \na. \nThe Current Terms for Departing PJM \nPJM is fundamentally a membership organization and membership, by law, is strictly \nvoluntary.57  The Commission can neither compel entry into an RTO nor enjoin a utility’s exit if \nthe standard for departure has been satisfied.58  Each transmission owning member of PJM has a \ncontractual right to leave.  The first part of the Commission’s section 205 role in a utility’s \ndeparture from an RTO (excluding of course its review of RTO replacement arrangements) is \nsolely to ensure that the departing utility satisfies the “contractual obligations” applicable to it \nunder its RTO’s governing documents upon withdrawal.59  The Commission has squarely rejected \nthe notion that, absent specific contractual commitments, RTO exit is subject to a broader and \nmore amorphous “hold harmless” standard and, in the case of PJM, there is no “exit fee.”60   \nIn PJM today, the “contractual obligations” that must be satisfied for departure are clear.  \nSection 3.4 of the TO Agreement provides that any party that withdraws from the TO Agreement \n \n57  \nSee, e.g., Reg’l Transmission Organizations, Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 30,994 (1999) \n(cross-referenced at 89 FERC ¶ 61,285) (adopting “an open collaborative process that relies on voluntary regional \nparticipation to design RTOs”), order on reh’g, Order No. 2000-A, FERC Stats. & Regs. ¶ 31,092 (2000) (cross-\nreferenced at 90 FERC ¶ 61,201), petitions for review dismissed sub nom. Public Utility Dist. No. 1 of Snohomish \nCounty, Wash. v. FERC, 272 F.3d 607 (D.C. Cir. 2001); Louisville Gas & Elec. Co., 114 FERC ¶ 61,282 at P 29 \n(2006) (“LG&E”) (“[P]articipation in an RTO is voluntary.”); see also Atl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. \nCir. 2002) (“Atlantic City”) (finding that the Commission has no authority to regulate RTO membership as a change-\nin-control transaction under section 203 of the Federal Power Act). \n58  \nDuquesne Light Co., 122 FERC ¶ 61,039 at P 48 (2008) (“Duquesne I”) (“[M]ovement from one \nCommission-approved RTO to another is not barred by Order No. 2000.  As we recognized in LG&E, companies that \nvoluntarily join RTOs should have the ability to withdraw from an RTO as long as the replacement rates that are \nestablished are just and reasonable.”). \n59  \nLG&E, 114 FERC ¶ 61,282 at P 27; Duquesne I, 122 FERC ¶ 61,039 at PP 28-29. \n60  \nMw. Indep. Transmission Sys. Operator, Inc., 124 FERC ¶ 61,219 at P 222 (2008) (“Duquesne II”). (“Under \nthe TO Agreement, in this regard, there is no exit fee requirement nor is there a hold harmless provision.  Considered \nin this context, we find that any weight that Reliant may have assigned to an asserted hold harmless guarantee has no \nreasonable basis in the TO Agreement itself and therefore, for all the reasons explained by the Commission in the \nJanuary 17 Order, cannot be a basis for obligating Duquesne.”)."},{"page":22,"startToken":6681,"endToken":6968,"text":"22 \n \n“shall remain liable for any and all obligations under [the TO] Agreement that such Party incurred, \nthat were incurred on behalf of such Party, or that arose hereunder prior to the date upon which \nsuch Party’s withdrawal, transfer, or assignment became effective.”61  One of the most significant \napplications of this rule is the liability of a departing member for Transmission Expansion Costs \nincurred by PJM under Schedule 12 of the PJM Tariff.  The Commission explored this issue in \ndetail in the Duquesne proceedings.  In Duquesne I, the Commission made a number of \ndeterminations about Duquesne’s proposed exit demonstration, but found that Duquesne had not \nsufficiently addressed the “. . . full extent of its remaining transmission function obligations, as \nrequired by section 3.4 of the TO Agreement.”62  Specifically, the Commission found that “. . . \nDuquesne had not adequately addressed its financial liability to PJM with respect to its allocated \nshare of [Regional Transmission Expansion Plan (“RTEP”)] project costs.”63  Accordingly, the \nCommission required Duquesne to address these obligations in a compliance filing, and accepted \nadditional record development on this question. \nAfter considerable briefing on the matter, the Commission concluded that section 3.4 of \nthe TO Agreement obligates a departing Transmission Owner to pay the costs of Regional \nFacilities and Necessary Lower Voltage Facilities allocated to it under PJM Tariff Schedule 12 \nand its appendix through the end of the calendar year of its exit but does not subject the departing \nTransmission Owner to future-period costs related to those facilities.64  The Commission \ndetermined that the departing member would owe the entirety of the Lower Voltage Facility costs \n \n61  \nTO Agreement § 3.4. \n62  \nSee Duquesne II, 124 FERC ¶ 61,219 at P 16. \n63  \nId. \n64  \nId."},{"page":23,"startToken":6968,"endToken":7262,"text":"23 \n \ndirectly assigned to it.65  The Commission justified these findings on the basis that PJM’s \nassignment of Lower Voltage Facility costs “is fixed” at the time of the cost assignment, while \ncost assignments for Regional Facilities and Necessary Lower Voltage Facilities “are not fixed \nduring the RTEP process” and are instead reallocated annually pursuant to Schedule 12.66   \nThe Commission explained that the Schedule 12 appendix (today, Schedule 12 – Appendix \nA) assigns RTEP costs “on an evolving, superseding basis”67 and that, pursuant to Schedule 12: \na new transmission owner joining PJM would become subject to these \ncharges . . .   regardless of when the projects were approved and regardless \nof who these projects may have previously benefitted.  And a departing \ntransmission owner leaving PJM would, pursuant to this language, no \nlonger be subject to these charges; it would not have a zonal annual peak \nload as it would no longer be a zone in PJM.68   \n \nThe Commission also pointed to the lack of any mechanism under Schedule 12 for PJM \n“to allocate future-period project costs to a former transmission owner based on the fictional \nassumption that this former transmission owner’s zone can or should remain a part of PJM for \nfuture-year schedule 12 purposes.”69  To that end, “[j]ust as PJM would not be permitted to \nexclude, from its schedule 12 appendix, load data applicable to the entry of a new transmission \nowner’s zone, it would not be allowed to continue to include a former transmission owner’s \nzone.”70  \nIn reaching that decision, the Commission expressly rejected several arguments that would \nhave imposed significant regional transmission costs on departing Transmission Owners.  First, \n \n65  \nId. P 168. \n66  \nId.  \n67  \nId. P 165. \n68  \nSee id. P 164. \n69  \nId. P 167. \n70  \nId."},{"page":24,"startToken":7262,"endToken":7547,"text":"24 \n \nthe Commission dismissed the notion that “an RTEP report, once filed with the Commission, \nbecomes binding on all zones then existing in PJM, presumably until all such project costs have \nbeen submitted for filing and recovered by PJM.”71  As the Commission noted, “PJM has chosen \nan allocation method for the higher voltage projects included in its RTEP that treats these costs as \nsystem-wide costs that are imposed on any new transmission owners that may join PJM and, \nsimilarly, may not be imposed on departing members.”72   \nSecond, the Commission rejected the argument that its holding in a prior proceeding \nconcerning the Midcontinent Independent System Operator (“MISO”) Transmission Owners \nAgreement had any relevance to the question of a departing PJM Transmission Owner’s RTEP \ncost liability.73  The Commission noted that although it had previously held in the context of the \nMISO Transmission Owners Agreement that “[i]n principle, a transmission owner should not be \nable to avoid previously allocated costs by withdrawing from the [RTO],” the Commission’s \nfinding in that proceeding “was based on existing tariff provisions pertaining to financial \nobligations of withdrawing transmission owners, as reflected in the [MISO] Transmission Owners \nAgreement.”74  While the Commission “agree[d] that it might be just and reasonable for PJM to \nadopt a similar requirement, in the future,” the Commission noted it was “required here to interpret \nPJM’s tariff as currently drafted.”75  PJM never “adopt[ed] a similar requirement.” TO Agreement \nsection 3.4 has not changed since the Commission decided Duquesne II in 2008. \n \n71  \nId. P 171. \n72  \nId. \n73  \nId. P 173. \n74  \nSee id. (citing Mw. Indep. Transmission Sys. Operator, Inc., 118 FERC ¶ 61,209 at P 193 (2007)). \n75  \nId."},{"page":25,"startToken":7547,"endToken":7856,"text":"25 \n \nThird, the Commission was not swayed by an argument that it was required to hold a \ndeparting Transmission Owner “liable for regional RTEP costs shown to have reliability benefits” \nfor that Transmission Owner’s zone.76  The Commission noted that Schedule 12 did not require \nthat any “determinations of benefits to individual zones . . . be made,” and high-voltage facilities \ncosts were “allocated during the year incurred to all transmission zones then-existing in PJM.”77 \nFinally, the Commission dismissed the notion that a departing Transmission Owner \n“should be required to pay, as a condition of its withdrawal, an exit fee that reflects its share of \nexisting PJM financial expenditures and commitments.”78  The Commission reiterated its prior \nfinding that “[t]he TO Agreement . . .  does not require [a transmission owner] to pay an exit fee \nas a condition to its withdrawal.”79 \nAs it relates to generating capacity obligations, Section 5.1.1 of the RAA allows an LSE to \nwithdraw from the RAA effective, inter alia, “upon completion of its obligations hereunder” and \nafter giving prior written notice to the PJM Office of the Interconnection.80  As a general matter, \nthe withdrawing LSE’s obligations under the RAA “shall be completed as of the end of the last \nmonth for which such Party’s obligations have been set at the time said notice is received.”81  The \nRAA directs that a withdrawing LSE pay a Locational Reliability Charge for each PJM zone in \nwhich it serves load during a Delivery Year.82  As the Commission explained in Duquesne I, this \nmeans the departing LSE must pay for all capacity PJM acquired on the LSE’s behalf, up to and \n \n76  \nId. P 172. \n77  \nId. \n78  \nId. P 176. \n79 \nId. \n80  \nRAA § 5.1.1. \n81  \nId. § 5.1.2. \n82  \nId. §§ 5.1.3(a), 7.2, 7.2A, 11.1-11.3."},{"page":26,"startToken":7856,"endToken":8322,"text":"26 \n \nincluding all RPM auctions (PJM’s capacity auctions) in which the LSE’s load forecasts are \nincluded.83   \nConsequently, under Duquesne I and II, when an LSE exits PJM, it is only required to pay \nfor capacity PJM has acquired for it up through the last capacity auction in which the LSE’s load \nforecasts were included.  In Duquesne I, the Commission concluded that these provisions required \nDuquesne to pay (in the form of Locational Reliability Charges) for all capacity PJM acquired on \nits behalf up through and including RPM auctions in which its load forecasts were included.84  The \nCommission also directed PJM “to support reasonable arrangements to permit Duquesne to utilize \nthat capacity in satisfying its reliability obligations to the Midwest ISO or to any other reliability \norganization.”85   \nPursuant to the RAA, a withdrawing load-serving entity must also settle all “202(c) \ncharges” allocated to it.86  These charges pertain to the costs incurred by certain generation owners \nin compliance with orders of the Secretary of Energy under FPA section 202(c) to keep otherwise \nretiring generators operating under declared emergency conditions.  Section 7.2A of the RAA \ndirects each RAA Party to “pay, as to the loads it serves during a Delivery Year, a 202(c) charge” \n \n83  \nDuquesne I, 122 FERC ¶ 61,039 at PP 83, 93. \n84  \nId. P 92. \n85  \nId. P 93. \n86  \nRAA §§ 5.1.3(a), 7.2A.  Specifically, section 7.2A of the RAA provides: “Each Party shall pay, as to the \nloads it serves during a Delivery Year, a 202(c) charge for each resource that is (1) directed to maintain operations for \nresource adequacy purposes for the PJM Region and is not expressly limited to resolve resource adequacy issues in \nspecific Locational Deliverability Area(s) or Zone(s) by order of the Secretary of Energy pursuant to Federal Power \nAct section 202(c) on or after May 30, 2025, and (2) subject to an agreement between the parties identified in such \n202(c) order setting forth a rate for compensation using the formula rate methodology and processes based on the \nDeactivation Avoidable Cost Credit set forth in Tariff, Part V, sections 114, 115, 116, 118, 118A with refinements to \nensure recovery of incurred costs, which may include, but are not limited to, maintenance and necessary repairs, and \nwhere any refinements to such formula rate are acknowledged and reviewed by the Independent Market Monitor.  The \nforegoing 202(c) charge to each Load Serving Entity shall be equal to the monthly aforementioned rate multiplied by \neach Load Serving Entity’s pro rata share of the sum of the total Daily Unforced Capacity Obligations across all Zones \nin the PJM Region for all days within the calendar month covered by the relevant Federal Power Act section 202(c) \norder.”"},{"page":27,"startToken":8322,"endToken":8630,"text":"27 \n \nfor certain resources.87  This provision was recently added to the RAA and allocates the costs \nincurred by generating units directed to remain operational pursuant to emergency orders issued \nby the U.S. Secretary of Energy under FPA section 202(c).88   \nb. \nThe Commission Should Be Clear That Any Treatment of RBP \nCharges Does Not Undermine The Commission’s Precedents \nOn Other PJM Contractual Exit Commitments  \nAs explained above, PJM is a voluntary membership organization, and the ability of a \nmember to withdraw upon satisfying its contractual obligations is central to the continued viability \nof the RTO model and to public utilities’ ability to make long-term decisions in the best interests \nof their customers.  Those rights depend on clear, enforceable contractual commitments, not after-\nthe-fact efforts to expand withdrawal obligations through generalized claims of cost shifting or \nadministrative convenience.  The RBP Proposal is PJM’s first attempt to add a new long-term \nfinancial obligation that would have to be addressed in connection with a Transmission Owner’s \nwithdrawal.  If the Commission concludes that some limited RBP-related exit obligation is \nnecessary to prevent RBP Charges from being shifted to remaining load, it should make equally \nclear that any such ruling is confined to the specific Tariff language governing RBP Charges and \ndoes not disturb the Commission’s existing precedent regarding other PJM contractual exit \ncommitments.  The Commission should not allow this proceeding to become a vehicle for \nrevisiting or diluting the settled principles recognized in Duquesne I and II and related orders, \nincluding the absence of any general PJM exit fee and the requirement that withdrawal obligations \nbe grounded in the governing agreements as actually written.  \n \n87  \nId. § 7.2A (emphasis added). \n88  \nPJM Interconnection, L.L.C., 193 FERC ¶ 61,192 at P 1 (2025) (citing 16 U.S.C. § 824a(c)), order on reh’g, \n195 FERC ¶ 61,002 (2026))."},{"page":28,"startToken":8630,"endToken":8901,"text":"28 \n \nThe Commission should furthermore expressly reaffirm that any expansion of a \nTransmission Owner’s responsibility for charges upon withdrawal accepted in this proceeding is \nlimited to RBP Charges and does not otherwise expand a departing Transmission Owner’s \nobligations under the TO Agreement, RAA, or PJM Tariff beyond their existing terms, and does \nnot authorize PJM to impose new withdrawal conditions unrelated to the specific RBP Charges \nallocated pursuant to the cost allocation methodology approved by the Commission in this \nproceeding.  The Commission should provide that clarity now, before the RBP Proposal imposes \nnew 15-year obligations that could materially affect future RTO transition decisions by \nTransmission Owners and customers, by requiring that PJM modify its proposal to create a \ndefined, transparent RBP exit fee and by reconfirming the contractual obligations applicable to \nTransmission Owners withdrawing from PJM, consistent with its past precedents. \nB. \nPJM’s Proposed Cost Allocation Methodology Is Not Just and Reasonable \nAnd Requires Further Development \n \nGiven the amount of customer funding the RBP Proposal could require, ensuring a just and \nreasonable and not unduly discriminatory cost allocation of RBP Charges is of paramount \nimportance.  As proposed, the cost allocation terms included in the RBP Proposal leave key \nquestions unanswered.  First, PJM’s proposed location-based cost allocation methodology is at \nodds with its decision not to include locational parameters in the RBP.  Second, PJM’s use of a \nsingle load forecast as the basis for 15-years of cost allocation is unreasonable absent some \nallowance for adjustment to allocation over time.  Third, the proposed provisions require further \ndevelopment to ensure that Electric Distributors are not left responsible for an unreasonable \nallocation of RBP Charges."},{"page":29,"startToken":8901,"endToken":9257,"text":"29 \n \n1. \nPJM’s Static Load-Forecast Cost Allocation Is Unjust and \nUnreasonable Because It Disconnects Long-Term RBP Charges From \nActual Load Responsibility \n \nPJM proposes to allocate RBP Charges by first imputing the current 6,831.3 MW shortfall \nto each Electric Distributor zone/area based in part on that zone/area’s forecasted load growth from \nthe 2026/2027 Delivery Year to the 2028/2029 Delivery Year.89  PJM’s proposal to use the \nforecasted load growth between those Delivery Years to allocate a financial obligation that will \nrun through the 2042/2043 Delivery Year creates a number of problems.  First, PJM’s proposal to \nallocate costs based on zonal responsibility for its current reliability shortfall is at odds with its \nconcession that there will be no locational element to the RBP.  PJM’s theory that its load forecast \nis a reliable proxy for where in the PJM region the resource adequacy shortfall exists, paired with \nits decision not to include a locational element to capacity procurement, creates a fundamental \ndisconnect between the product procured and the allocation of RBP Charges for the product.  For \nexample, load in western PJM may end up paying for significant new generation investments in \neastern PJM that ultimately do not benefit that western load, or vice versa. \n \nSecond, the temporal mismatch created by the RBP Proposal is independently \nunreasonable.  PJM proposes to allocate a 15-year stream of RBP Charges through the 2042/2043 \nDelivery Year using a single snapshot of relative load growth between the 2026/2027 and \n2028/2029 Delivery Years, even though load growth patterns are highly likely to shift materially \nover that period as large-load projects, interconnection timelines, retirements, and customer \ncommitments change.  PJM acknowledges that it cannot project CETO and CETL 15 years out \nbecause it lacks the information needed to determine those locational parameters.  PJM cannot \n \n89  \n In her affidavit, Ms. Croop explains that the allocation of RBP MWs to each Electric Distributor zone/area \nwill be based on the forecasted load growth from the 2026/2027 Delivery Year to the 2028/2029 Delivery Year and \nincorporate the Load Adjustments from the 2026 PJM Load Forecast.  See Croop Affidavit ¶ 43."},{"page":30,"startToken":9257,"endToken":9578,"text":"30 \n \ninvoke that uncertainty to avoid locational procurement while simultaneously locking in cost \nallocation for the full commitment term based on a near-term forecast that it cannot reasonably \nexpect to remain representative. \n \n \nFor these reasons, the cost allocation methodology contemplated by the RBP Proposal is \nunjust, unreasonable and unduly discriminatory.  The Commission should reject the proposed \nmethodology or, at minimum, direct that PJM implement the necessary corrections and \nclarifications described in this Protest to ensure that the RBP functions as designed.  This includes, \nat minimum, a requirement that PJM revise the RBP Proposal to include a mechanism to revisit \ncost allocation for RBP Charges as the actual load and reliability landscape evolves. \n2. \nPJM’s Cost Allocation Provisions Must be Further Clarified to Avoid \nPlacing Unreasonable Burdens on Electric Distributors \n \nThe proposed provisions governing cost allocation to LSEs—i.e., the parties taking \ntransmission service on behalf of the large load customer in question—require further development \nto ensure that Electric Distributors are not left responsible for an undue allocation of RBP Charges.  \nUnlike PJM’s allocation of RBP Charges to Electric Distributor areas/zones, which will be set to \na fixed amount and assigned by PJM, the proposed allocation of RBP Charges to LSEs is much \nless definitive, thereby exposing Electric Distributors to risk for assuming unwarranted RBP costs. \n \nAccording to the RBP Proposal, after PJM allocates RBP Charges to each Electric \nDistributor zone/area, those RBP Charges will be further allocated to each LSE based on the LSE’s \npro-rata share of the zone’s RBP Obligation.  This allocation depends entirely on actions by parties \nthat neither PJM nor the Electric Distributor can compel.  Although PJM’s proposal nominally \nplaces payment obligations on LSEs rather than Electric Distributors, the practical reality is more \ncomplex.  The Electric Distributor is the entity responsible for a host of administrative functions \nthat will impact on how costs are allocated among LSEs according to their pro-rata share of their"},{"page":31,"startToken":9578,"endToken":9911,"text":"31 \n \nRBP Obligations.  Should this fail, PJM proposes that it will allocate costs among LSEs in the \nzone using each LSE’s load ratio share of the Daily Unforced Capacity Obligation for the zone as \ndetermined in Schedule 8 of the RAA.  Importantly, PJM’s proposal also does not mention which \nparty bears responsibility if LSEs decide not to pay their allocated share of RBP Charges or if their \nload commitments shift over time, or if an LSE disputes their previously-allocated share of RBP \nCharges.  Given that the Electric Distributors zones/areas are assigned a fixed amount of RBP \nCharges that will be expressly defined by the Tariff, the ambiguities regarding LSEs’ \nresponsibilities for RBP Charges leave Electric Distributors at a significant disadvantage for \nbearing costs that, by design, should be allocated fairly among responsible LSEs before ultimately \nbeing allocated to load.  This outcome would be consistent with both the design of the RBP and \nthe Trump Administration’s Ratepayer Protection Pledge.90 \n \nTo remedy these deficiencies, the Commission should direct PJM to clarify that the full \n15-year RBP financial obligation follows the LSE serving the large-load or data center customer \nwhose load growth gives rise to the RBP responsibility, not the Electric Distributor for the \nzone/area in which that customer happens to be located.  If the purpose of the RBP is to ensure \nthat new large loads and data centers bear the incremental capacity costs associated with their \nservice, then the legally enforceable obligation should be assigned at the outset to the LSE serving \nthat load and should remain with that service obligation for the full RBP commitment term.  The \nTariff should also provide that, if the large-load or data center customer later switches suppliers, \nthe corresponding RBP obligation transfers to the successor LSE serving that same load.  That \nstructure would prevent residual liability from falling on an Electric Distributor merely because \n \n90  \nTHE WHITE HOUSE, Ratepayer Protection Pledge Proclamation (Mar. 4, 2026) \nhttps://www.whitehouse.gov/presidential-actions/2026/03/ratepayer-protection-pledge-proclamation/ (“Ratepayer \nProtection Pledge”)."},{"page":32,"startToken":9911,"endToken":10244,"text":"32 \n \nthe load is located in its zone/area, while ensuring that the entities serving and receiving revenues \nfrom the load remain responsible for the capacity costs caused by that load.   \n \nThis approach is consistent with PJM’s asserted cost-causation rationale and with the \nRatepayer Protection Pledge’s premise that large loads and data centers—not other customers and \nnot the Electric Distributor as a default guarantor—should be responsible for the incremental \ncapacity costs required to serve them.  At a minimum, the Commission should direct PJM to:  (1) \nexpressly state in the Tariff that an Electric Distributor shall have no financial obligation for RBP \nCharges solely by virtue of defining the zone/area or by reason of a failure to report RBP \nObligation MW, and that the obligation to report is ministerial in character—not a condition whose \nnon-fulfillment exposes the Electric Distributor to financial liability for the zone/area’s allocated \ncharges; and (2) provide that Electric Distributors are not held financially liable in a circumstance \nwhere an LSE fails to pay its share of, or otherwise disputes its allocation of RBP Charges.   \nC. \nPJM Must Clarify That RBP Collateral Obligations Apply to Load Serving \nEntities, Not Electric Distributors, Because Credit Responsibility Should \nFollow the Entity Responsible for RBP Charges \nPJM proposes to require that those LSEs allocated responsibility for RBP Charges for a \ngiven Delivery Year must post credit associated with that obligation.  PJM must clarify that \ncollateral obligations attach only to LSEs allocated responsibility for RBP Charges, not to Electric \nDistributors acting solely in an administrative or delivery-service role.  PJM expressly states that \nRBP Buyer collateral is intended to protect against the risk that an entity responsible for RBP \nCharges fails to pay those charges.  This collateral obligation should therefore follow the entity \nultimately responsible for the RBP Charge.  Given that LSEs are the parties taking transmission \nservice on behalf of the large loads that have caused the need for the RBP, the burden to acquire \ncollateral should reside with the LSE."},{"page":33,"startToken":10244,"endToken":10550,"text":"33 \n \nThe Commission should direct PJM to clarify that the obligation to post RBP Collateral \napplies exclusively to LSEs allocated responsibility for RBP Charges and does not attach to an \nElectric Distributor solely because the applicable load is located within its distribution service \nterritory.  PJM explains that RBP Buyer collateral is intended to mitigate the risk of non-payment \nof RBP Charges and that only LSEs allocated responsibility for RBP Charges generally will have \na credit requirement.  The RBP Proposal therefore appears to recognize that collateral should \nfollow financial responsibility for RBP Charges.  Given the substantial magnitude and long \nduration of the proposed collateral requirements, however, the Tariff should expressly state that \nElectric Distributors have no obligation to post RBP Collateral unless they are serving the \nunderlying load in their capacity as an LSE.  Failure to provide such clarification creates \nunnecessary uncertainty regarding which market participants ultimately bear the financial \nobligations associated with the RBP framework. \nThis clarification is also necessary to ensure consistency with the cost-causation principles \nthat PJM invokes throughout the filing.  PJM’s proposed cost allocation methodology is premised \non assigning RBP Charges to the LSEs serving the load that gives rise to the resource adequacy \nneed underlying the RBP.  It would therefore be inconsistent and unreasonable to require an \nElectric Distributor, whose role in the RBP framework is limited to delivery service and \nadministrative reporting of allocations, to provide collateral backing obligations incurred by \ncompetitive suppliers serving that load.  This concern is particularly acute in the AEP Ohio Electric \nDistributor zone/area, where essentially all large-load and data center customers driving forecasted \nload growth are shopping customers served by competitive retail suppliers acting as LSEs.  \nRequiring AEP Ohio to post collateral for obligations attributable to those suppliers would \nimproperly shift credit risk from the entities serving and benefiting from the load to an Electric"},{"page":34,"startToken":10550,"endToken":10843,"text":"34 \n \nDistributor that neither controls generation supply decisions nor receives the revenues associated \nwith serving that load.  Such a result would be inconsistent with cost-causation principles and \nshould be expressly foreclosed in the Tariff. \nThe Commission should therefore direct PJM to modify the RBP Tariff language to \nexpressly state that, “RBP Collateral shall be required only of those Load Serving Entities allocated \nresponsibility for RBP Charges pursuant to Attachment DD.  An Electric Distributor shall have no \nobligation to post RBP Collateral solely by virtue of serving as the Electric Distributor for a zone \nor area, except to the extent the Electric Distributor is also acting as the Load Serving Entity for \nthe applicable load.” \nD. \nPJM’s Proposal Contains an Error Regarding Fixed Resource Requirement \nEntities That Must Be Addressed \n \nThe RBP Proposal contains an error that, if the Commission accepts the RBP Proposal, the \nCommission should direct PJM to amend on compliance.  In RAA, Schedule 8, Article 1, Section \nD 1.1, PJM proposes language stating that “An FRR Entity may not use an Existing Generation \nCapacity Resource not owned by such FRR Entity as of June 1, 2027 or any resource committed \nthrough the Reliability Backstop Procurement to satisfy its Capacity FRR Plan.”91  This mistake, \nlacking the ability to use both owned or contracted resources, if accepted, would represent a critical \nerror in the filed rate as applied to FRR Entities.  In conversations with PJM since the RBP \nProposal was submitted, PJM has conceded to AEP that this mistake was a simple drafting error.  \nConsequently, PJM must acknowledge this error on the record of this proceeding and commit to \nfixing it in a compliance filing. \n \n91  \nRBP Proposal, Attachment B, Clean Tariff Records, RAA, Art. 1 § D 1.1 (emphasis added)."},{"page":35,"startToken":10843,"endToken":11105,"text":"35 \n \nV. \nCONCLUSION \nAEP recognizes that PJM faces a genuine and pressing resource adequacy challenge and \ndoes not oppose a carefully tailored one-time backstop procurement designed to address the \n2028/2029 BRA shortfall.  That said, the extraordinary speed, cost, and duration of the RBP \nProposal require the Commission to scrutinize the proposed terms carefully before customers are \nexposed to billions of dollars in long-term financial commitments.  As explained in this Protest, \nthe RBP Proposal contains provisions that are unjust, unreasonable, and unduly discriminatory.  \nAEP therefore respectfully requests that the Commission reject those provisions of the RBP \nProposal or, at minimum, condition any acceptance of the RBP Proposal on the modifications and \nclarifications described above.  \nSpecifically, the Commission should: \n1. Reject or direct PJM to substantially revise the RBP Proposal’s Transmission Owner exit \nprovisions to:  (a) ensure that a departing Transmission Owner’s financial obligation for \nRBP Charges is limited to the charges allocated to its zone under PJM’s Commission-\naccepted RBP cost allocation methodology, subject to reduction by any RBP Settlement \nCredits, RPM Auction Credits, refunds, offsets, or other credits that would have applied \nhad the load remained in PJM; and (b) make the cost of exiting PJM transparent and readily \nascertainable through an objective, pre-determinable formula; \n2. Reaffirm the Commission’s established precedent governing RTO exit obligations, and \nexpressly confirm that any RBP exit obligation accepted in this proceeding is confined to \nRBP Charges and does not disturb, expand, or supersede the contractual exit framework \nestablished in Duquesne I and II and related orders, including the absence of any general \nPJM exit fee;"},{"page":36,"startToken":11105,"endToken":11295,"text":"36 \n \n3. Reject or direct PJM to modify the proposed RBP cost allocation methodology by:  (a) \nexpressly stating that Electric Distributors bear no financial liability for RBP Charges \nsolely by virtue of their administrative role in reporting LSE RBP Obligations; (b) \nproviding that collateral obligations attach exclusively to LSEs allocated responsibility for \nRBP Charges and not to Electric Distributors acting in a delivery-service or reporting \ncapacity; and (c) adopting a mechanism to revisit cost allocation over the 15-year RBP \ncommitment term as actual load and reliability conditions evolve; and  \n4. Direct PJM to correct the identified drafting error in RAA, Schedule 8.1.D, Section \nD.1.1 affecting FRR Entities on compliance, and to acknowledge that error on the record \nof this proceeding. \nThese conditions are necessary to ensure that any one-time backstop procurement approved \nby the Commission addresses PJM’s asserted reliability need without imposing unjust, \nunreasonable, unduly discriminatory, or insufficiently reviewed long-term costs on AEP, its \naffiliates, and their customers. \n \n \n \n \n \n        Respectfully submitted, \n \n \n/s/ John C. Crespo \nJohn C. Crespo \nSenior Legal Counsel \nAmerican Electric Power Service Corporation \n1 Riverside Plaza \nColumbus, Ohio 43215 \n(614) 716-3727 \njccrespo@aep.com"},{"page":37,"startToken":11295,"endToken":11345,"text":"37 \n \n/s/ Christopher R. Jones \nChristopher R. Jones \nWilliam R. Derasmo \nEmily Beard  \nTROUTMAN PEPPER LOCKE LLP \n401 9th Street, NW Suite 1000 \nWashington, DC \n(202) 662-2181 \nchris.jones@troutman.com \nwilliam.derasmo@troutman.com \nemily.beard@troutman.com  \n \nCounsel for American Electric Power Service \nCorporation \n \n \n \n \nDated: August 21, 2026"},{"page":38,"startToken":11345,"endToken":11408,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that on this 21st day of August 2026, I have caused a copy of the \nforegoing document to be served electronically on each person listed on the Secretary’s official \nservice list in the above-referenced proceeding. \n \n/s/ Emily Beard \nEmily Beard \nTROUTMAN PEPPER LOCKE \n401 9th Street, NW Suite 1000 \nWashington, DC \n(202) 274-1949 \nemily.beard@troutman.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1133,"startToken":0,"endToken":144},{"p":1,"at":1133,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":3,"endAt":605,"startToken":144,"endToken":642},{"p":3,"at":605,"title":"II. CORRESPONDENCE AND COMMUNICATIONS","method":"printed heading","endPage":4,"endAt":5,"startToken":642,"endToken":760},{"p":4,"at":5,"title":"III. BACKGROUND","method":"printed heading","endPage":10,"endAt":520,"startToken":760,"endToken":2798},{"p":10,"at":520,"title":"IV. PROTEST","method":"printed heading","endPage":10,"endAt":534,"startToken":2798,"endToken":2800},{"p":10,"at":534,"title":"A. PJM’s Proposed Transmission Owner Exit Provisions are Unjust and","method":"printed heading","endPage":28,"endAt":994,"startToken":2800,"endToken":8771},{"p":28,"at":994,"title":"B. PJM’s Proposed Cost Allocation Methodology Is Not Just and Reasonable","method":"printed heading","endPage":32,"endAt":1164,"startToken":8771,"endToken":10093},{"p":32,"at":1164,"title":"C. PJM Must Clarify That RBP Collateral Obligations Apply to Load Serving","method":"printed heading","endPage":34,"endAt":759,"startToken":10093,"endToken":10664},{"p":34,"at":759,"title":"D. PJM’s Proposal Contains an Error Regarding Fixed Resource Requirement","method":"printed heading","endPage":35,"endAt":6,"startToken":10664,"endToken":10844},{"p":35,"at":6,"title":"V. CONCLUSION","method":"printed heading","endPage":38,"endAt":0,"startToken":10844,"endToken":11345},{"p":38,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":38,"endAt":402,"startToken":11345,"endToken":11408}]}