{"document":{"slug":"rec-20260821-5289","title":"Motion to Intervene and Protest of the Retail Energy Supply Association re PJM Interconnection, LLC's proposed revisions to the Open Access Transmission Tariff","issued":"2026-08-21","accession":"20260821-5289","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"The Retail Energy Supply Association","kind":"protest","file":"sources/filings/text/20260821-5289_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5289","tier":"record","sha256":"354bbae6e30592f1fa2b77052ec3ca118a566a8a990461fb612b2166bb529041","pages":11,"tokens":2913,"emptyPages":[],"textThemes":["cost","adequacy","credit"]},"pages":[{"page":1,"startToken":0,"endToken":285,"text":"4900-3540-9097.1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C.  \n) \n Docket No. ER26-3380-000 \nMOTION TO INTERVENE AND PROTEST OF \nTHE RETAIL ENERGY SUPPLY ASSOCIATION \nPursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission’s \n(“Commission’s”) Rules of Practice and Procedure, 18 C.F.R. §§ 385.211 and 385.214, the \nRetail Energy Supply Association (“RESA”)1 hereby files this Motion to Intervene and Protest in \nthe above-referenced proceeding, in which PJM Interconnection, LLC (“PJM”) seeks to modify \nthe Reliability Assurance Agreement (“RAA”) of its Open Access Transmission Tariff (“Tariff”) \nto establish a Reliability Backstop Procurement (“RBP”) process to procure new capacity to \naddress resource adequacy issues in PJM (“RBP Proposal”).     \nRESA files this Protest to express the need for market certainty, stability and clarity and \nthe importance of the granular allocation of costs using principles of cost causation.   As \ndescribed below, significant changes to the PJM market design can cause harm if implemented to \nupset settled expectations of Market Participants and if a change in market design creates rate \nshock. In addition, RESA opposes PJM’s default methodology that would allocate costs \n1\nThe comments expressed in this filing represent the position of the Retail Energy Supply Association \n(RESA) as an organization but may not represent the views of any particular member of the Association.  Founded \nin 1990, RESA is a broad and diverse group of more than twenty retail energy suppliers dedicated to promoting \nefficient, sustainable and customer-oriented competitive retail energy markets.  RESA members operate throughout \nthe United States delivering value-added electricity and natural gas service at retail to residential, commercial and \nindustrial energy customers.  More information on RESA can be found at www.resausa.org."},{"page":2,"startToken":285,"endToken":505,"text":"2 \n4900-3540-9097.1 \nassociated with the capacity procurement in accordance with RAA Schedule 8.  In support of this \nMotion to Intervene and Protest, RESA submits as follows: \nI. \nMOTION TO INTERVENE \nA. \nCorrespondence and Communications \nCorrespondence and communications regarding this matter should be addressed to the  \nfollowing person(s), and the same should also be designated for service on the Commission’s  \nofficial list for this proceeding: \nElizabeth W. Whittle  \nCharles Iannello \nNixon Peabody LLP \nInterstate Gas Supply, LLC \n799 Ninth Street, N.W. \n6100 Emerald Parkway \nSuite 500 \nDublin, OH 43016 \n \nWashington, DC 20001 \n217-899-2537 \n202-585-8338  \ncharlie.iannello@igs.com\newhittle@nixonpeabody.com\nB. \nRESA \nRESA is a non-profit trade association of independent corporations that are involved in the \ncompetitive supply of electricity and natural gas to end-use consumers.  RESA and its members \nare actively involved in retail electricity and natural gas markets throughout the United States in \nstates that have implemented markets that allow entities other than the incumbent electric or natural \ngas utility to provide commodity electric and gas service. RESA members are Load Serving \nEntities (“LSEs”) active in the following RTO/ISOs: PJM, ISO New England, Inc. (“ISO-NE”), \nMidcontinent Independent System Operator, Inc. (“MISO”), New York Independent System \nOperator, Inc. (“NYISO”), and California Independent System Operator, Inc. (“CAISO”).  RESA \nmembers possess market-based rate authority from the Commission."},{"page":3,"startToken":505,"endToken":798,"text":"3 \n4900-3540-9097.1 \nC. \nMotion to Intervene  \nOn July 31, 2026, PJM made a filing to modify the RAA provisions of its Tariff to impose \nan RBP on a one-time basis to acquire additional capacity due to shortages for 2027/2028 and \n2028/2029 Reliability Pricing Model Auctions.  RESA, with members who are active in PJM \nmarkets, have an interest in this proceeding that cannot be represented by any other party, moves \nto intervene. \nII. \nGENERAL COMMENTS \n RESA asks that the Commission take note of the need for market certainty and stability \nand the importance of granular cost allocations consistent with cost causation principles.2  In light \nof today’s ever increasing capacity prices, rate shock caused by mis-allocated costs will cause \nsignificant harm to those entities who are not causing the costs to increase.   \nRESA members purchase services in the RTO/ISO markets such as energy, capacity and \nancillary services, but they offer more than just electricity service to their customers.  Competitive \nretail suppliers may provide  retail energy to end-use customers at contracted fixed or variable \nprices which are tied to wholesale electricity prices.  Retail suppliers may offer demand response \nservices – assisting customers in reducing peak demand and receiving benefits for reducing \nconsumption at peak times.  Retail suppliers may offer energy efficiency services to assist \ncustomers in reducing their electricity consumption.  Retail suppliers may offer electricity with a \ncertain component of renewable energy – or all renewable energy.  There is no one model – \n2  \nCost causation requires “all approved rates reflect to some degree the costs actually caused by the customer \nwho must pay them.”  K N Energy v FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); Midwest ISO Transmission \nOwners v FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004)."},{"page":4,"startToken":798,"endToken":1120,"text":"4 \n4900-3540-9097.1 \ncompetitive wholesale markets and the introduction of retail choice in states such as Ohio, Illinois, \nPennsylvania, New Jersey, Delaware and Maryland, have allowed significant innovation, which \nhas reduced consumption of energy, lowered prices, and provided valuable services to consumers.   \nCompetitive retail suppliers operate in an environment of risk.  Retail suppliers are unlike \ntraditional utilities in several important ways.  For example, retail suppliers are not cost-based \nregulated by state public utility commissions (although they comply with a myriad of state \nrequirements to be authorized to provide energy-related products and services to retail customers).  \nRetail suppliers do not have a mechanism to defer costs, like traditional utilities, and thus bear the \nrisk of wholesale market volatility and uncertainty.  Retail suppliers do not have a specified service \narea.  They contract with customers bilaterally.  Generally, these contracts are long-term – of a \nduration of one to five years. As a result, when a contract expires, it may or may not be renewed.  \nThus, a customer today may not be a customer tomorrow.  As a result, charges allocated to a utility \nservice area or load zone must be properly allocated to the appropriate retail end use customer, \neven if the customer has changed suppliers or returned to default service (i.e. the customer is served \nby different LSEs).   \nTo offer valuable and innovative services at competitive prices, retail suppliers \nparticipating in competitive wholesale markets require market certainty, transparency and stability.  \nMarket certainty, transparency and stability allow retail suppliers to offer products and services \nthat they know they can deliver during the term of the applicable contract.  The importance of \nhaving confidence in the competitive wholesale market cannot be overstated.  As with products \nand services offered by retail suppliers, the contracts vary by company, by service, by customer \ntype, by term and other conditions.  If competitive retail suppliers are participating in default \nservice programs, those programs often require winning suppliers to agree to a standard form"},{"page":5,"startToken":1120,"endToken":1414,"text":"5 \n4900-3540-9097.1 \ncontract, which may or may not address unanticipated market changes, including changes to \ncapacity cost allocations caused by RBP.   \nThis RBP filing, and the related Interim Resource Adequacy Service (“IRAS”), filed by \nPJM in Docket No. ER26-3515, may fundamentally alter the risks and credit exposure of all \ncustomers in a utility service area depending on how RBP or related costs are allocated among \nthem.  It is critical for all Market Participants to have market certainty, stability and transparency \nin this critical time as PJM addresses the need for additional capacity.  \n III. \nPROTEST \nA. The Commission should Deny PJM’s Default Allocation Proposal and Require \nPJM to Use Sub-Accounts to Allocate Costs to Large Load  \nRESA supports PJM's RBP Proposal to the extent that it assigns RBP costs and collateral \nobligations to the LSE serving the Large Load Customers that cause those costs. PJM’s proposal \nto facilitate the allocation of costs to cost causers, however, is undermined to the extent that PJM’s \nproposed default methodology applies. Under PJM’s RBP, if an Electric Distributor does not report \nReliability Backstop Obligations (“RBO”) for the Large Load Customers in its zone, PJM will \ninstead allocate RBP costs to all load in that zone based on each LSE’s existing Peak Load \nContribution assignments.  The result is that the cost of capacity procured specifically to serve \nnew, not-yet-interconnected Large Load through the RBP would be borne by residential, \ncommercial, and traditional industrial customers who did not cause those costs and who receive \nno corresponding benefit.  \nThis is not a remote contingency.  As PJM acknowledges, neither the Commission nor PJM \ncan dictate how RBP costs are allocated among the customers and LSEs behind each Electric \nDistributor. Ensuring allocation of RBP costs to cost causers will require each Relevant Electric"},{"page":6,"startToken":1414,"endToken":1730,"text":"6 \n4900-3540-9097.1 \nRetail Regulatory Authority (“RERRA”) and each Electric Distributor across the PJM footprint to \nimplement regulations, tariff provisions, registry processes, and data exchanges necessary to \nidentify Large Load Customers and assign RBO to their LSEs. Changes necessary to implement \nRBO may even require a change in state law or be dependent on PJM implementing the necessary \nchanges to implement RBO.  While the commitments made today will not be paid until the \n2028/2029 Delivery Year, this is a significantly compressed schedule for the States and RERRAs \nto execute the necessary changes to implement RBO.  If the necessary changes are not \nimplemented in time, the default allocation attaches automatically, and capacity costs associated \nwith Large Load Customers are spread across non-cost causing residential, commercial and \ntraditional industrial customers. In other words, the most consequential cost allocation outcome in \nthis proceeding would be determined not by a reasoned Commission judgment about cost \ncausation, but by the pace of administrative implementation in individual states, RERRAs and \nElectric Distributor service territories. \nPJM touts its cost allocation proposal as supporting the Statement of Principles Regarding \nPJM issued on January 16, 2026, by the National Energy Dominance Council and the 13 governors \nof the PJM states (“NEDC/PJM Governors’ Principles”)3\nThus, a cost allocation methodology that provides PJM states and/or RERRAs with the \nability to determine the specific RBOs that should be assigned to LSEs, as well as to cost \nallocate to end-use customers in their respective states in accordance with their laws and \npolicies, supports the NEDC/PJM Governors’ Principles, which include the principle that \nthe cost of new capacity should be allocated to data centers who have caused the need for \nadditional capacity in the PJM Region.4\n3 Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm \n4 PJM RBP Proposal Filing Letter at 106-107."},{"page":7,"startToken":1730,"endToken":2036,"text":"7 \n4900-3540-9097.1 \nHowever, if for any reason, the states, RERRAs, and Electric Distributors are unable to \ntimely implement the necessary changes to implement RBO, the NEDC/PJM Governor’ Principles \nwould be gravely violated by the socialization of RBP costs against all captive customers.  There \nis a mechanism to prevent any unjustified cost allocations to LSEs – PJM should establish as a \ndefault methodology the obligation to create a sub-account to the LSE serving the Large Load \nwhere those costs can be appropriately assigned.  For these reasons, RESA respectfully requests \nthe Commission reject PJM’s default zonal cost allocation proposal and require PJM to establish \nan LSE sub-account associated with the Large Load in the PJM system where the costs can be \ndirectly assigned.   \nB.\nIf the Commission Accepts PJM’s Default Allocation Proposal, PJM Should be \nOrdered to Take Additional Steps to Protect Residential, Commercial and \nTraditional Industrial Customers from Cost Shifts  \nIf the Commission accepts PJM’s Tariff proposal to, as a default, allocate RBP costs to \nLSEs based on the sum of their customers’ Peak Load Contributions, states, RERRAs and Electric \nDistributors will be under significant pressure to timely implement RBO.   Accordingly, RESA \nrespectfully requests that the Commission facilitate discussions among and between the states, \nRERRAs, Electric Distributors and interested Market Participants to assist in implementing the \nRBP Proposal and RBO.   \nRESA hereby emphasizes the urgency of state action and collaboration between the states \nand PJM in implementing RBO. If the RBP Proposal is accepted substantially as filed, every PJM \nstate — and particularly those open to retail competition — will need to move immediately to \nidentify Large Load Customers and to assign RBP costs and collateral obligations to those \ncustomers and their LSEs.  RESA intends to participate in those proceedings, and the Commission \nshould recognize in any order approving the RBP that the reasonableness of the cost allocation"},{"page":8,"startToken":2036,"endToken":2331,"text":"8 \n4900-3540-9097.1 \noutcome depends entirely on the implementation of the necessary changes by states, RERRAs and \nElectric Distributors to complete implementation of RBO before obligations attach to all LSEs \nserving load in a zone. \nIf PJM’s default allocation proposal is accepted as filed, and the Commission declines to \nimplement RESA’s suggestion to create an LSE sub-account for Large Load as noted in Section \nIV.A above, then the Commission should require PJM to take additional steps to protect customers \nand LSEs before the default RPB cost allocation is triggered.  First, PJM should be required to \npublish, well in advance of each cost allocation determination, which zones lack a qualifying \nframework for identifying Large Load Customers and assigning Reliability Backstop Obligations.  \nStates, RERRAs, LSEs, and customers need notice of that exposure before the RBP costs are \nallocated, not after. Second, if the Commission nonetheless permits a default allocation, the Tariff \nshould make clear that it is a last resort of strictly limited duration and that it establishes no \nprecedent for allocating costs caused by Large Load to customers other than Large Load. \nC. \nThe Commission Should Require Certain Commitments and Advance \nDisclosure from PJM to Reduce Risk and Provide Greater Certainty to \nLSEs.   \nPJM’s RBP injects significant uncertainty to competitive wholesale markets to the \ndetriment of wholesale and retail customers. In the short amount of time to analyze this filing, \nRESA has identified a number of concerns that are identified below. \nFirst, PJM should publish RBO determinations and resulting cost allocations expeditiously.  \nRetail suppliers such as RESA members are currently submitting bids into default service supply \nsolicitations to provide service to retail customers for long-term obligations of between one and \nfive years.  Price certainty and the RBO is critical information in responding to these procurements"},{"page":9,"startToken":2331,"endToken":2654,"text":"9 \n4900-3540-9097.1 \nfor future Delivery Years.  The central RBP auction is proposed to run from September 30 through \nOctober 21, 2026, while the facilitated bilateral matchmaking process is expected to continue for \nanother six to nine months.  Thus, RESA asks that the Commission require PJM to publish \nReliability Backstop Obligation determinations and cost allocations sufficiently in advance of \nthose solicitations for suppliers to reflect them in their offers.   \nSecond, PJM offers no guarantee regarding timing of resettlement of RBP charges.  RESA \nasks the Commission to confirm that RBP charges will not be subject to retroactive resettlement \noutside PJM's standard resettlement window. Retail suppliers cannot recover charges retroactively \nimposed after a contract has been priced and served, and the magnitude of the obligations at issue \nhere makes that exposure materially different from ordinary settlement variance. \nThird, RESA further notes that excluding Large Load growth from future Reliability \nPricing Model auction demand until that load is covered by new supply is directionally consistent \nwith cost causation and may reduce capacity costs for all LSEs and the customers they serve. To \nrealize that benefit, however, RESA asks that PJM be directed to re-release the 2029/2030 Base \nResidual Auction planning parameters promptly upon any change to the load forecast so suppliers \ncan reflect a demand adjustment of this significance in their estimate of future capacity costs \nprocured through the RPM. \nFourth, PJM’s proposal appears to lack specificity around how RBP costs will be assigned \nto LSE’s serving Large Load Customers as those customers switch from one LSE to another \nthroughout the period the RBP will be in effect.  For example, each state that permits retail access \nhas rules and guidelines governing switching LSEs.  Under the RBP, how will PJM be notified of \nthe transfer of the Large Load and how will appropriate collateral be collected from the transferee \nLSE and returned to the transfer LSE?  Will PJM deadlines interfere with the switch and leave the"},{"page":10,"startToken":2654,"endToken":2861,"text":"10 \n4900-3540-9097.1 \ntransfer LSE with the Large Load?  These issues must be addressed in the PJM Tariff. \nFinally, while PJM’s proposal provides detailed steps to address LSE default on RBP \nobligations, the proposal lacks details related to Large Load Customer load not materializing or \ndecommissioning.  RESA supports the portion of the proposal intended to protect traditional \ncustomers if a Large Load Customer ceases operations after its load clears the RBP and requests \nthat the Commission require PJM to address that scenario more completely.  For example, PJM’s \nproposal does not resolve whether the remaining fifteen-year cost obligation would be socialized \nto other customers in the zone, satisfied by drawing on an LSE's collateral, or reallocated. That \nambiguity exposes non-cost causing customers and their LSEs to an open-ended liability and, as a \npractical matter, is itself an impediment to the Large Load interconnection the RBP is intended to \nfacilitate. \nWHEREFORE, RESA respectfully requests that RESA’s Motion to Intervene is granted \nand its Protest considered by the Commission in this proceeding.  \nRespectfully submitted, \nElizabeth W. Whittle \nElizabeth W. Whittle \nCounsel for \nThe Retail Energy Supply Association \nOf Counsel: \nNixon Peabody, LLP \n799 9th Street, N.W. \nSuite 500 \nWashington, DC 20001 \n202-585-8338 \newhittle@nixonpeabody.com\nDated: August 21, 2026"},{"page":11,"startToken":2861,"endToken":2913,"text":"11 \n4900-3540-9097.1 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document, via email, on each \nperson listed on the Official Service List compiled by the Secretary in this proceeding. \nDated in Washington, DC this 21st day of August 2026. \nElizabeth W. Whittle\nElizabeth W. Whittle"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":177,"startToken":0,"endToken":312},{"p":2,"at":177,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":2,"endAt":202,"startToken":312,"endToken":316},{"p":2,"at":202,"title":"A. Correspondence and Communications","method":"printed heading","endPage":2,"endAt":723,"startToken":316,"endToken":388},{"p":2,"at":723,"title":"B. RESA","method":"printed heading","endPage":3,"endAt":21,"startToken":388,"endToken":508},{"p":3,"at":21,"title":"C. Motion to Intervene","method":"printed heading","endPage":3,"endAt":434,"startToken":508,"endToken":579},{"p":3,"at":434,"title":"II. GENERAL COMMENTS","method":"printed heading","endPage":5,"endAt":608,"startToken":579,"endToken":1213},{"p":5,"at":608,"title":"III. PROTEST","method":"printed heading","endPage":5,"endAt":624,"startToken":1213,"endToken":1215},{"p":5,"at":624,"title":"A. The Commission should Deny PJM’s Default Allocation Proposal and Require","method":"printed heading","endPage":7,"endAt":799,"startToken":1215,"endToken":1852},{"p":7,"at":799,"title":"B. If the Commission Accepts PJM’s Default Allocation Proposal, PJM Should be","method":"printed heading","endPage":8,"endAt":1189,"startToken":1852,"endToken":2218},{"p":8,"at":1189,"title":"C. The Commission Should Require Certain Commitments and Advance","method":"printed heading","endPage":11,"endAt":22,"startToken":2218,"endToken":2864},{"p":11,"at":22,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":321,"startToken":2864,"endToken":2913}]}