{"document":{"slug":"rec-20260821-5295","title":"Post-Technical Conference Comments of Vistra Corp. re PJM Governance and Stakeholder Reforms","issued":"2026-08-21","accession":"20260821-5295","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Vistra Corp.","kind":"comments","file":"sources/filings/text/20260821-5295_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5295","tier":"record","sha256":"c96d6a8f18abc7ad478a3d69f5ce55bec646887579568f510b959f9b294284a1","pages":8,"tokens":2679,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":264,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Governance and Stakeholder Reforms \n) \n) \n) \nDocket No. \n \nAD26-7-000 \n \nPOST-TECHNICAL CONFERENCE COMMENTS OF VISTRA CORP. \n \nPursuant to the Federal Energy Regulatory Commission’s (FERC or Commission) July \n30, 2026 Notice Requesting Post-Technical Conference Comments, Vistra Corp. (Vistra) submits \nlimited comments1 and full responses to the question in the Notice’s Appendix. \nVistra is the second-largest independent power producer in the United States, owning and \noperating a diverse fleet of generation facilities totaling approximately 44,000 megawatts (MWs) \nof capacity in markets across the country.  Vistra is one of the largest independent power \nproducers in PJM (with approximately 15,000 MW of generation), serves millions of retail \ncustomers as a competitive power supplier, and is an active participant in all aspects of the PJM \nstakeholder process.  Thus, while Vistra participates in the PJM stakeholder process via the \nGeneration Owner sector, Vistra is also directly cognizant of the impacts PJM policies have on \nretail customers.  Vistra plans to participate constructively in the interest-based discussions \nconvened by the Commission’s Dispute Resolution Service, with the goal of reaching consensus \non impactful governance reforms that will improve PJM’s process and allow PJM and its \nstakeholders to return their focus to the critical market reforms that will sustain investment and \nresource adequacy well into the future. \nI. \nCOMMENTS \nAlthough the Technical Conference record is largely comprised of answers to specific \n \n1 Vistra’s positions on key issues in the PJM Governance conversation are included in the Pre-Technical \nConference Statement of J. Arnold Quinn, Senior Vice President of Regulatory Policy filed in this Docket."},{"page":2,"startToken":264,"endToken":642,"text":"2 \n \nquestions, the issues being discussed all, at their core, relate to the core objectives of RTO/ISO \ngovernance: independence and responsiveness.  These are not competing objectives. Rather, they \nare companion principles the Commission has required of RTOs and ISOs since Order No. 2000, \nand reaffirmed and elaborated on in Order No. 719.2  Order No. 2000 defines independence as \nRTOs/ISOs having a decision-making process independent from any market participant or class \nof market participants and reaffirms the principle that “[a]n RTO needs to be independent in both \nreality and perception.”3  In Order No. 719, the Commission found that RTOs and ISOs must \ndemonstrate responsiveness by “provid[ing] an avenue for customers and other stakeholders to \npresent their views on RTO and ISO decision-making, and to have those views considered” and, \ncritically, “ensure that no single stakeholder group can dominate.”4   The Commission should \nreject any position that treats independence and responsiveness as a zero-sum game, including \nproposals that would strengthen the Board’s hand only by weakening its obligation to hear from \nstakeholders, or that would elevate one stakeholder group over others. \nWith respect to responsiveness, moving to a purely advisory stakeholder process, as PJM \nasks, will reduce PJM’s responsiveness to stakeholders writ large.  Stakeholder views are \ninherently weakened when an RTO/ISO can simply take them or leave them.  Moving to an \nadvisory model also opens the door to capture by stakeholders who formally or functionally have \nthe ability to influence the RTO behind the scenes.  It follows that responsiveness does not mean \nresponsiveness to just one category of stakeholder.  PJM's independence (and the appearance of \n \n2 Regional Transmission Organizations, Order No. 2000, 89 FERC ¶ 61,285, at pp. 193–194 (1999), order \non reh’g, Order No. 2000-A, 90 FERC ¶ 61,201 (2000), aff'd sub nom. Pub. Util. Dist. No. 1 of Snohomish County, \nWashington v. FERC, 272 F.3d 607 (D.C. Cir. 2001)  \n3 Id. \n4 Wholesale Competitive Electricity Markets, Order No. 719 at PP 503, 507, 73 Fed. Reg. 64,100 (Oct. 28, \n2008), FERC Stats. & Regs. ¶ 31,281 (2008), order on reh’g, Order No. 719-A, 74 Fed. Reg. 65,626 (Dec. 11, 2009), \nFERC Stats. & Regs. ¶ 31,292 (2009), order on reh’g, Order No. 719-B, 129 FERC ¶ 61,252 (2009)."},{"page":3,"startToken":642,"endToken":966,"text":"3 \n \nindependence) is placed at risk any time one class of participants is elevated over others, whether \nstates, transmission owners, or any commercial sector.  Any governance reforms should ensure \nbalanced input across all sectors. \nVistra believes common sense reforms to the day-to-day functioning of the PJM \nstakeholder process should be the focus of any discussions.  We are heartened by the near-\nuniversal agreement among commenters, including PJM itself, that PJM should develop long-\nterm plans, prioritize initiatives, and discipline the mechanics of the stakeholder process.  Vistra \napplauds PJM’s recent publication of a five-year strategy5 as a first step to implementing the kind \nof consensus-based, practical reforms that will improve the stakeholder process across the board.  \nAs noted in our pre-conference comments and our comments during the conference, Vistra \nbelieves better prioritization and reform to stakeholder voting will allow stakeholders to timely \naddress the most pressing challenges and will limit the need to use the Critical Issue Fast Path \nprocess that inappropriately requires the PJM Board to engage in detailed market design work.  \nConsistent with its goal of being a constructive participant in these ongoing discussions, Vistra \nremains open to discussions about the allocation of Section 205 filing rights among PJM and the \nMembers Committee, provided any such changes are agreed to by stakeholders themselves. The \nCommission's authority to unilaterally force the reallocation of Section 205 \n rights is limited,6 and any attempt to direct such a reallocation absent stakeholder \nconsensus is likely to trigger protracted litigation, which will only serve to divert PJM's, \nstakeholders’, and the Commission’s attention and resources away from the more pressing work \nof ensuring resource adequacy and reliability through competitive markets at the lowest \n \n5 Shaping a Powerful Change: PJM Five-Year Strategy (August 19, 2026). \n6  See Atlantic City Elec. Co v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002) (“[N]nothing in section 206 sanctions \ndenying [public utilities] their right to unilaterally file rate and term changes.”)"},{"page":4,"startToken":966,"endToken":1365,"text":"4 \n \nreasonable cost over time.   \nII. \n APPENDIX QUESTIONS \nPJM Board Independence \nNo. \nQuestion / Comment \nYes \nNo \n1 \nShould Board members’ terms be extended \nto five or more years? \nX \n \nComments:  Vistra believes that it could be helpful to extend Board members’ terms to up \nto five years.  That term would enhance continuity and build member experience over \ntime.  However, we would be concerned with terms significantly longer than five years \nbecause it could reduce accountability. \n2 \nShould there be a maximum number of years \nthat a Board member may serve (e.g., 10 \nyears)? \nX \n \nComments: Vistra interprets this question to ask whether a Board member should be \nterm-limited.  We believe that the ability to serve two five-year terms is reasonable, if the \nBoard member is re-nominated and re-elected after their first term.  However, more than \ntwo terms could create stagnation in Board membership and limit the ability for new \nmembers to bring fresh experience and perspective. \n3 \nShould the Board member qualification rules \nbe revised to provide a preference for some \nBoard members that reside in the PJM \nregion? \nX \n \nComments: Vistra thinks adding a preference for some Board members that reside in the \nPJM region is a reasonable change to address concerns raised by some stakeholders.  \nHowever, we do not believe that residence in the PJM region should be a requirement for \nBoard membership.  That approach would significantly limit the pool of potential Board \nmembers and exclude candidates that have valuable experience at other RTOs/ISOs. \n4 \nShould the conflict-of-interest rules be \nrevised to reduce the cooling off period for \nBoard members from two years to one year? \nX \n \nComments: Vistra believes that reducing the cooling off period from two years to one \nyear strikes an appropriate balance between maintaining Board independence from any \nPJM stakeholder with broadening the pool of Board candidates. \n5 \nShould restrictions on Board \ncommunications be relaxed to enable more \ncommunication between the Board and \nstakeholders? \nX \n \nComments: Currently, the PJM Board meets with high-level representatives in each \nSector once per year, and Board members are prohibited from privately speaking about \nany matter that is before, or may come before, the Board.  Vistra believes that both \npolicies unnecessarily limit the Board’s ability to hear from stakeholders.  The Board \nshould meet with Sector representatives several times per year, and not only with senior \nmarket participant officials.  Furthermore, the ex parte limitation, especially with respect"},{"page":5,"startToken":1365,"endToken":1815,"text":"5 \n \nto matters that may come before the Board in the future, prevent the Board from \nunderstanding the context of matters they will consider.  Analogizing to the \nCommission’s ex parte rules, this prohibition is the equivalent of barring pre-filing \nmeetings, which are nearly universally seen as beneficial to Commissioners and \nstakeholders. \n6 \nShould Board votes be made public or the \nBoard be required to explain its reasoning? \n \nX \nComments: It is certainly critical that the overall decisions of the Board be public, \nincluding the high-level reasoning behind those positions, as seen in the current Board \nLetter approach.  However, requiring that individual Board member votes and reasoning \nto be public is unnecessary because it is the cumulative action of the Board, rather than \nindividual positions of Board members, that is relevant to PJM policy. \n7 \nShould some Board meetings be open or \navailable to the public? \nX \n \nComments: Opening some Board meetings to the public would also be a common-sense \nway to increase transparency, but closed-doors business meetings are also important to \nallow candid discussions, particularly between the Board and PJM management and \ntechnical experts.  For example, the ISO-New England Board has an annual open meeting \nwhere it discusses certain regional strategies and takes public comment. \n8 \nShould PJM governing documents explicitly \nstate responsibility to serve the public \ninterest? \nX \n \nComments: Vistra does not object to including a reference to the public interest in PJM’s \ngoverning documents, to the extent it is consistent with PJM’s statutory obligations.  \nPJM, as a public utility, is governed by the Federal Power Act’s mandate to provide \njurisdictional services on terms that are just, reasonable, and not unduly discriminatory or \npreferential.  Federal Power Act (section 201) also recognizes that the provision of \ntransmitting and selling electric energy for ultimate distribution to the public is affected \nwith a public interest and that the regulation of those activities is necessary in the public \ninterest.   \n9 \nShould state representatives have at least one \nvoting member on the Nominating \nCommittee? \nX \n \nComments: Vistra believes that having state representation on the Nominating Committee \nis a straightforward way to increase state participation in PJM governance.  However, \nVistra cautions against including more than one state representative; no group should \nhave an outsized role in the Nominating Committee process.  \n10 \nShould PJM adopt public performance \nmetrics and tie management compensation to \ntheir achievement? \n \nX \nComments: Performance metrics are an important component of strategic organization \nmanagement.  However,  Vistra does not believe those metrics should be public.  Rather, \nsuch metrics should be utilized by the board to ensure performance of, and accountability \nfrom, PJM management.  Performance metrics also must not be so restrictive as to limit \nmanagement’s flexibility to be responsive to changing circumstances and need."},{"page":6,"startToken":1815,"endToken":2196,"text":"6 \n \nSection 205 Filing Rights \nNo. \nQuestion / Comment \nYes \nNo \n11 \nShould the stakeholder process be advisory? \n \nX \nComments: Advisory stakeholder processes make RTO/ISO Boards less responsive to \nstakeholders and create a situation where one stakeholder group can develop outsized \ninfluence over the RTO/ISO.  For example, certain stakeholder groups have inherent \nleverage over RTOs/ISOs (e.g, , Transmission Owners, whose membership is the \nfoundation of the regional organization.)  Without a binding stakeholder process to \nensure all stakeholders have a meaningful voice, inherent advantages can unduly \ninfluence Board decision-making. \n12 \nShould PJM have unencumbered section 205 \nfiling rights over energy and ancillary \nservices? \n \nX \nComments: As noted in Vistra’s pre-conference comments, unencumbered filing rights \nwould reduce PJM’s responsiveness to stakeholders. \n13 \nShould PJM have unencumbered section 205 \nfiling rights over RTEP? \n \nX \nComments:  Unencumbered filing rights would reduce PJM’s responsiveness to \nstakeholders. \n14 \nShould OPSI have jump ball rights over \ncertain filings? \n \nX \nComments:  Jump ball rights can be a useful tool to increase RTO/ISO responsiveness \nand accountability to stakeholders.  However, no one stakeholder group should have \nsole jump ball rights.  That structure would provide one organization with outsize \ninfluence over what is filed.  The ISO-NE example is instructive: jump ball rights are \nheld by the stakeholder body as a whole, which drives consensus building and ensures \nthat no one group has undue influence in the process. \n15 \nShould the Members Committee have jump \nball filing rights over tariffs where PJM has \n205 rights? \nX \n \nComments:  Vistra would be open to the Members Committee having jump ball filing \nrights over tariff where PJM has 205 rights.  If PJM’s 205 filing rights are expanded to \ninclude the energy and ancillary services markets, Vistra believes the Members \nCommittee should have jump ball if that approach is the product of voluntary \nstakeholder consensus.  In ISO-New England, the jump ball process has historically \ndriven stakeholder consensus and organizational accountability.  However, a key reason \nthat process functions well in ISO-NE is because it is supported by dedicated \nstakeholder process infrastructure administered by NEPOOL, which enables \nstakeholders to independently reach consensus. Any consideration of a similar \nmechanism for PJM would need to ensure that all stakeholders are represented in the \nalternative filing process and build comparable supporting infrastructure. \n \nStakeholder Process \nNo. \nQuestion / Comment \nYes \nNo"},{"page":7,"startToken":2196,"endToken":2633,"text":"7 \n \n16 \nShould the approval threshold in the \nMembers Committee be lowered from two-\nthirds sector-weighted voting? \n \nX \nComments: Requiring more than a simple majority vote of stakeholders is key to \npreventing any one sector from dominating the voting on a proposed market reform.   \nHowever, Vistra would support lowering the two-thirds requirement to a threshold \nbetween a simple majority and supermajority.  For example, a 60% sector weighted \nvoting threshold would be a high enough bar to prevent one group from dominating but \nreduce the ability of a single group or sector  to veto a proposal.  \n17 \nShould affiliate vote restrictions apply to \nlower-level committees? \nX \n \nComments: Consistent voting structures across committees would prevent the \ninefficiencies of initiatives that pass at lower committees failing at higher committees \nand being sent back. \n \nState Participation \nNo. \nQuestion / Comment \nYes \nNo \n18 \nShould there be a second state representative \ngroup? \n \nX \nComments:   Vistra supports expanding OPSI to be an organization that reflects a \nbroader spectrum of state voices and has the resources to robustly participate in the \nstakeholder process.  Providing more resources to OPSI could allow it to expand its \nmembership to include governors’ offices or other state representatives and increase its \nstaffing and expertise to engage in PJM’s complex and technical process. \n19 \nShould state representatives have a formal \nvoting role in the stakeholder process? \n \nX \nComments:  Providing states with a formal voting role in the stakeholder process \nwould be logistically complex and has the potential to dilute, rather than elevate, state \nvoices.  PJM state representatives are diverse both within a state (e.g., governors’ \noffices and state utility Commissions, which may have different perspectives on the \nsame issue) and among PJM states, which are heterogenous in many respects \n(including in their status as net sellers or net buyers of electricity and in state \nenvironmental and economic policies).  Clarity on individual state perspectives could \nbe reduced by boiling these interests down to voting positions.  Further, states already \nhave a significant voice in the stakeholder process through their advocacy and \ninfluence with individual stakeholders and in the larger stakeholder process.  Moreover, \nstate utility commissions act as regulators, not jurisdictional wholesale market \nparticipants or (unlike consumer advocates) direct representatives of retail customers. \n20 \nShould PJM be required to consult with \nOPSI before certain section 205 filings? \nX \n \nComments:  PJM must be mindful of elevating any one stakeholder group over others, \nbut a consultation requirement before certain section 205 filings could be a helpful way \nfor PJM to hear from states on issues like transmission cost allocation while not \nblurring state/federal jurisdictional lines by providing states with separate section 205 \nfiling rights."},{"page":8,"startToken":2633,"endToken":2679,"text":"8 \n \n \n \nIII. \nCONCLUSION \nVistra appreciates the opportunity to provide these post-technical conference comments \nand looks forward to productive engagement with PJM and the stakeholder community. \n \n \n \n \nRespectfully submitted, \n \nJ. Arnold Quinn  \nVistra Corp.  \n325 7th Street, N.W.  \nSuite 520  \nWashington, D.C. 20004  \n \nAugust 21, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1546,"startToken":0,"endToken":218},{"p":1,"at":1546,"title":"I. COMMENTS","method":"printed heading","endPage":4,"endAt":35,"startToken":218,"endToken":971},{"p":4,"at":35,"title":"II. APPENDIX QUESTIONS","method":"printed heading","endPage":8,"endAt":9,"startToken":971,"endToken":2634},{"p":8,"at":9,"title":"III. CONCLUSION","method":"printed heading","endPage":8,"endAt":344,"startToken":2634,"endToken":2679}]}