{"document":{"slug":"rec-20260821-5299","title":"Limited Protest of Vistra Corp. re PJM Interconnection, L.L.C.’s proposed Reliability Backstop Procurement mechanism","issued":"2026-08-21","accession":"20260821-5299","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Vistra Corp.","kind":"protest","file":"sources/filings/text/20260821-5299_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5299","tier":"record","sha256":"6195277c3dd4d4c0a855ac54708107308884c7da4de864c787b932a28bb3a940","pages":8,"tokens":2379,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":299,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nDocket No. ER26-3380-000\nLIMITED PROTEST OF VISTRA CORP. \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 Vistra Corp. (“Vistra”) submits this limited protest of \nPJM Interconnection, L.L.C.’s (“PJM”) proposed Reliability Backstop Procurement (“RBP”) \nmechanism.  This proceeding is the latest in PJM’s efforts to address the resource adequacy \nchallenges it faces as supply struggles to keep up with forecasted demand.  Vistra generally \nsupports the proposal to use a backstop mechanism to address near-term the resource adequacy \nneeds in the PJM system, even as Vistra believes it is critically important to ensure that the \n“ordinary” tools for ensuring resource adequacy, including the Reliability Pricing Model (“RPM”), \nremain the principal mechanisms by which PJM meets that critically important goal.  Short-term \nfixes have a tendency to beget further short-term fixes.  Vistra urges PJM—and the Commission—\nto ensure that RBP does not follow that well-trod path.      \nIn that vein, Vistra appreciates PJM’s efforts to narrowly tailor the RBP to the immediate \nresource adequacy need in front of it.  During the stakeholder process, PJM narrowed the \nprocurement target from 15 GW to 6.8 GW,2 which brings the procurement amount in line with \n1 18 C.F.R. § 385.211 (2026). \n2 Compare PJM Interconnection, L.L.C., Critical Issue Fast Path – Reliability Backstop Procurement PJM \nProposal, \nat \n4 \nn.4, \n(Apr. \n16, \n2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260416/20260416-item-05---pjm-reliability-backstop-procurement-proposal---paper.pdf (proposing an \ninitial target of ~15 GW), with PJM Interconnection, L.L.C., Transmittal, Docket No. ER26-3380-000, at 31 (filed \nJul. 31, 2026) (“Transmittal”) (setting the Initial RBP Target as 6,831.3 MW UCAP)."},{"page":2,"startToken":299,"endToken":574,"text":"-2- \nthe observed shortfall.  By targeting the observed shortfall, PJM has mitigated the risk of capacity \noverprocurement, which could otherwise lead to harmful long term market impacts, including the \npremature retirements of needed resources, which would ultimately exacerbate the very reliability \nchallenge RBP is intended to remedy.  PJM’s targeted approach will help ensure the reliability of \nthe PJM system without sacrificing affordability or unduly undermining the RPM and other tools \nthat should form the basis of a durable approach to ensuring resource adequacy at just and \nreasonable rates. \nI.\nLIMITED PROTEST \nNotwithstanding Vistra’s general support of the proposal, Vistra submits this limited \nprotest to address certain discrete issues and ensure that the RBP proposal is consistent with cost \ncausation principles and is not unduly discriminatory.  PJM explicitly “consent[ed] to the \nCommission’s exercise of authority to modify and/or sever any element of the proposed Tariff and \nRAA language to the extent necessary and permitted under section 205 of the FPA and NRG Power \nMarketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s \noverarching objectives in this filing.”3\nFirst, PJM’s proposal to allocate RBP costs to all load-serving entities (“LSEs”)—for a \nlocked-in fifteen-year period—regardless of whether they contributed to the current resource \nadequacy shortfall is unjust, unreasonable, and unduly discriminatory.  PJM proposes to assign \nRBP costs to each Electric Distributor zone based on the zone’s share of the regional MW target, \nthen to LSEs within the zone based on a state-determined allocation methodology.  If a state does \nnot set a methodology, PJM will default to allocating costs based on a LSE’s peak load \n3 Transmittal at 3."},{"page":3,"startToken":574,"endToken":1088,"text":"-3- \ncontribution.4  But a LSE’s peak load contribution has no inherent relationship with its contribution \nto the need for the RBP.  While a state may well propose a methodology that addresses Vistra’s \nconcerns, there is no requirement that they do so, and PJM’s default methodology is fundamentally \nflawed. \nThe just and reasonable standard in the Federal Power Act (“FPA”) requires that costs be \nallocated in a manner that is “roughly commensurate” with benefits.5  As applied here, that \nprinciple means that the costs of incremental investments needed to ensure reliable service should \nbe borne by the parties that cause the need for those investments.6  And the Commission may not \napprove a scheme requiring a party to pay for facilities from which it derives “benefits that are \ntrivial in relation to the costs.”7\nThe resource adequacy shortfall that caused PJM to pursue the RBP is the result of certain \nLSEs agreeing to serve load in excess of their available supply.  It is the cumulative effect of those \nshortfalls that led to PJM’s resource adequacy deficit.  By the same token, LSEs with sufficient \nsupply to cover their load obligation did not cause the need for RBP.  Although PJM contends that \nthe resource adequacy shortfall is simply the subsequent product of growth among new large \n4 Transmittal at 98-99 (citing id., Attach. B (Revisions to the PJM Open Access Transmission Tariff and PJM \nReliability Assurance Agreement) at attach. DD, § 18.3(b)(iii) (“Proposed Tariff”)). \n5 See Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1260-62 (D.C. Cir. 2018); Long Island Power Auth. v. \nFERC, 27 F.4th 705, 714-15 (D.C. Cir. 2022) (quoting Ill. Com. Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009) \n(“Illinois Commerce I”)); Neb. Pub. Power Dist. v. FERC, 957 F.3d 932, 939-41 (8th Cir. 2020); Coal. of MISO \nTransmission Customers v. FERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022); see also BNP Paribas Energy Trading GP \nv. FERC, 743 F.3d 264, 267-68 (D.C. Cir. 2014) (“The Natural Gas Act requires that rates be just and reasonable and \nnot unduly discriminatory.  The Commission has ‘added flesh to these statutory bones’ through adoption of the ‘cost \ncausation’ principle . . . . The flip side of this principle is that the Commission generally may not single out a party \nfor the full cost of a project, or even most of it, when the benefits of the project are diffuse.”); K N Energy, Inc. v. \nFERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992).  \n6 See BNP Paribas Energy Trading, 743 F.3d at 267; Battle Creek Gas Co. v. Fed. Power Comm’n, 281 F.2d 42, \n46-48 (D.C. Cir. 1960); El Paso Elec. Co. v. FERC, 76 F.4th 352, 357-58, 361 (5th Cir. 2023) (“El Paso II”).  \n7 See Pub. Serv. Elec. & Gas Co. v. FERC, 989 F.3d 10, 18-19 (D.C. Cir. 2021); Illinois Commerce I, 576 F.3d \nat 477; Ill. Com. Comm’n v. FERC, 756 F.3d 556, 561-62, 564 (7th Cir. 2014) (“Illinois Commerce II”)."},{"page":4,"startToken":1088,"endToken":1437,"text":"-4- \nloads,8 neither the RPM nor the physics of the bulk power system distinguishes among retail \ncustomers.9  The shortfall is simply the result of certain LSEs committing to serve more demand \nthan they have supply.  Allocating the cost of covering the cumulative shortfall to LSEs that had \nno shortfall and, thus, did not contribute to it would be patently inconsistent with cost causation.10\nNor do such entities meaningfully benefit from RBP because they already procured the capacity \nthey need.  To the extent those entities enjoy any benefits from RBP, they are trivial in relation to \nthe costs that RBP promises to impose.   \nSecond, PJM’s proposal is unduly discriminatory because it excludes Fixed Resource \nRequirement (“FRR”) entities from RBP cost allocation based on the very cost causation principle \ndescribed above, while not applying the principle to other entities to which it equally applies.11\nPJM proposes to exclude FRR entities principally because they have already paid for sufficient \ncapacity to meet their needs, such that “[a]llocating RBP Charges to FRR load would, in essence, \nrequire that they pay twice for capacity it has already procured.”12  Vistra takes no issue with that \ntreatment of FRR entities in isolation.  But, as explained above, the same principle—excluding \nentities that procured sufficient capacity from RBP cost allocation—applies equally to competitive \nretail suppliers that similarly have procured sufficient generation to meet their load needs.  \nAs a result, it would be textbook undue discrimination to exclude FRR entities from RBP \nbecause they have already paid for the capacity they need while not excluding competitive retail \nsuppliers that have done the same.  Entities are “similarly situated” where there are “no differences \n8 See Transmittal at 6-8, 19. \n9 Cf. BNP Paribas Energy Trading, 743 F.3d at 268-69 (establishing that “the cost causation principle itself \nmanifests a kind of equity” such that all load is economically marginal). \n10 See El Paso II, 76 F.4th at 362; S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, (D.C. Cir. 2014). \n11 Transmittal at 31-32.   \n12 Id. n.92."},{"page":5,"startToken":1437,"endToken":1780,"text":"-5- \nmaterial to the inquiry at hand.”13  Here, the inquiry at hand is whether an entity bears \nresponsibility for the resource adequacy shortfall the RBP is designed to cure.  On that question, \nthere is no difference between FRR entities and competitive retail suppliers with balanced books.  \nBoth have secured capacity to cover their load.  Neither entity contributed to the shortfall, so \nneither should be swept into the auction mechanism designed to remedy it.   \nPJM offers no reasoned basis for treating these entities differently.  Nor can it.  The fact \nthat FRR entities opt out of the RPM does not justify the differential treatment.  RBP is designed \nto cure PJM’s resource adequacy shortfall.  The material questions at hand, then, is who caused \nthat shortfall and who benefits from additional procurement?  On those questions, FRR entities \nand competitive suppliers with balanced supply and demand books are similarly situated.  The \nmechanism by which each entity accomplished the goal of covering its own capacity needs is \nirrelevant to the question of who should pay for the procurement necessary to cover the shortfall.  \nNeither FRR entities nor competitive suppliers with sufficient supply to serve their demand \ncontributed to the shortfall, so neither should be required to pay to remedy it. \nTo ensure RBP is just and reasonable and not unduly discriminatory, the Commission \nshould not permit PJM to impose RBP costs on competitive retail suppliers that already have \nbalanced books.  This result is also in line with the PJM Governors’ principles that PJM repeatedly \ninvokes.  Those principles direct that RBP costs be allocated “to LSEs with new data centers that \nhave not self-procured new capacity or agreed to be curtailable,” with “any remaining costs . . . \n13 See ISO New England Inc., 162 FERC ¶ 61,205, at P 44 (2018) (quoting  N.Y. Indep. Sys. Operator, Inc., 162 \nFERC ¶ 61,124, at P 10, n.30 (2018) (“To say that entities are similarly situated does not mean that there are no \ndifferences between them; rather, it means that there are no differences that are material to the inquiry at hand.”))."},{"page":6,"startToken":1780,"endToken":2107,"text":"-6- \nallocated to LSEs based on their remaining net short positions.”14  A competitive supplier with a \nbalanced book, by definition, has no net short position.   \nFinally, Vistra is also concerned with PJM’s fixed approach for allocating RBP costs.  The \nproposed Tariff language provides that each “zone/area’s assigned share of the Final RBP Target \nMW shall remain constant throughout the fixed 15-year term.”15  If there is anything that the last \nfive years have shown conclusively in PJM, it’s that load growth can be hard to anticipate in \nadvance.  Over the 15 years following the RBP, load will grow more than expected in some places \nand less than expected in others, but the RBP cost allocation will be frozen in time.  That static \napproach all but guarantees that costs will not be allocated in a manner that is roughly \ncommensurate with benefits.  Although PJM claims that the 15-year contract term will provide \nfinancing certainty, it is not clear why the zonal allocation needs to be frozen to accomplish that \ngoal.  The principal concern for financiers should be that project costs can be recovered, not the \nultimate retail customers from which that is derived.   \nNeither of these issues requires the Commission to reject RBP altogether.  Rather, the \nCommission can and should require PJM to modify its proposal by allocating RBP costs to LSEs \nbased on their net short positions.  PJM explicitly consented to the Commission’s modification of \nthe proposed Tariff as permitted under section 205 of the FPA and NRG.  These are discrete issues \nthat require necessary modification, consistent with NRG, and preserve the overarching goal of \nPJM’ filing. 16\n14 Statement of Principles Regarding PJM, National Energy Dominance Council, at 1 (Jan. 15, 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm.  \n15 Proposed Tariff, attach. DD, §18.3(b)(ii). \n16 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) (explaining that the Commission can make \nminor modifications with the utility’s consent.)."},{"page":7,"startToken":2107,"endToken":2314,"text":"-7- \nII.\nCONCLUSION \nAs this Commission considers PJM’s proposal, it is important not to miss the forest for the \ntrees.  RBP is intended to be a one-time, narrowly tailored solution to incentivize new resource \nadditions to meet short-term load growth.17  This is not PJM’s first stop-gap measure.  The cascade \nof “one-time” interventions in PJM’s capacity market risks creating a negative feedback loop that \ndivorces the market from economic fundamentals, jeopardizing its ability to attract much-needed \ninfrastructure investment.  While there are important near-term challenges to address, in the long \nterm, price signals based on market fundamentals are critical to ensuring resource adequacy and \naffordability.  Without market signals based on accurate supply and demand dynamics, PJM will \ncontinue to struggle to incentivize and retain sufficient generation to meet demand.   \nRespectfully submitted, \n/s/ J. Arnold Quinn\nJ. Arnold Quinn\nSVP of Regulatory Policy \nAndrew Weinstein\nVice President, FERC Market Policy\nVistra Corp.\n325 7th Street NW\nSuite 400\nWashington, DC 20004\narnie.quinn@vistracorp.com\nandrew.weinstein@vistracorp.com\nNicholas M. Gladd\nSarah Greenberg\nWilson Sonsini Goodrich & Rosati\n1700 K Street NW\nFifth Floor\nWashington, DC 20006\n(617) 598-7871\nngladd@wsgr.com\nsgreenberg@wsgr.com\nCounsel for Vistra Corp.\nDated:  August 21, 2026\n17 Transmittal at 1,7, 25."},{"page":8,"startToken":2314,"endToken":2379,"text":"CERTIFICATE OF SERVICE\nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings.\nDated: August 21, 2026\nSan Francisco, CA\n/s/ Jenae Sharp\nJenae Sharp\nWilson Sonsini Goodrich & Rosati\nOne Market Plaza, \nSpear Tower #3300\nSan Francisco, CA 94105\n(650) 722-6123\njmsharp@wsgr.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":608,"startToken":0,"endToken":387},{"p":2,"at":608,"title":"I. LIMITED PROTEST","method":"printed heading","endPage":7,"endAt":5,"startToken":387,"endToken":2108},{"p":7,"at":5,"title":"II. CONCLUSION","method":"printed heading","endPage":8,"endAt":0,"startToken":2108,"endToken":2314},{"p":8,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":8,"endAt":411,"startToken":2314,"endToken":2379}]}