{"document":{"slug":"rec-20260821-5303","title":"Post-Conference Comments of the Electric Power Supply Association re the Chairman- and Commissioner-led technical conference held on 07/23/2026 re PJM…","issued":"2026-08-21","accession":"20260821-5303","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Electric Power Supply Association","kind":"comments","file":"sources/filings/text/20260821-5303_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5303","tier":"record","sha256":"5323479872357db74b9b36315802d2a4ee47ae3565b9374a873b7dcfdf12bd64","pages":25,"tokens":7278,"emptyPages":[25],"textThemes":["retail"]},"pages":[{"page":1,"startToken":0,"endToken":269,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Governance and Stakeholder \nReforms\n) \n)\nDocket No. AD26-7-000\nPOST-CONFERENCE COMMENTS OF  \nTHE ELECTRIC POWER SUPPLY ASSOCIATION \nIn accordance with the July 30, 2026 notice issued by the Federal Energy \nRegulatory Commission (“FERC” or the “Commission”),1 the Electric Power Supply \nAssociation (“EPSA”)2 submits these post-conference comments following up on the \nChairman- and Commissioner-led technical conference held on July 23, 2026 (the \n“Technical Conference”), to discuss the governance and stakeholder processes of PJM \nInterconnection, L.L.C. (“PJM”).  EPSA appreciates the Commission’s efforts to address \nthese matters and this opportunity for input on the important issues discussed at the \nTechnical Conference.  EPSA is submitting these comments to address two questions \nposed by the Commission about the allocation of filing rights under Section 205 of the \nFederal Power Act (the “FPA”),3 and to underscore the critical importance of ensuring \nthat any attempted reallocation of such rights is fully in accordance with the statutory \nframework of the FPA.  EPSA also supports and incorporates by reference the \n \n1  \nPJM Governance & Stakeholder Reforms, Docket No. AD26-7-000 (July 30, 2026) \n(unreported) (the “July 30 Notice”). \n2 \nEPSA is the national trade association representing competitive power suppliers in the \nU.S.  EPSA members provide reliable and competitively priced electricity from environmentally \nresponsible facilities using a diverse mix of fuels and technologies.  EPSA seeks to bring the \nbenefits of competition to all power customers.  This filing represents the position of EPSA as an \norganization, but not necessarily the views of any particular member with respect to any issue. \n3  \n16 U.S.C. § 824d (2024)."},{"page":2,"startToken":269,"endToken":581,"text":"2 \nresponses to the specific questions set forth in the July 30 Notice that are being filed by \nThe PJM Power Providers Group. \nEPSA is particularly concerned by suggestions that Section 205 filing rights could \nbe transferred or delegated to states or a state entity like the Organization of PJM \nStates Inc (“OPSI”), which are not public utilities.  EPSA is also concerned about \nsuggestions that the Commission ought to upset the bargain struck when PJM was \nformed, under which consent from its members, including power suppliers, was required \nunder PJM’s Amended and Restated Operating Agreement (the “Operating Agreement”) \nfor Section 205 filings with respect to certain matters.  Specifically, while PJM may be \ndissatisfied with the need for member approval for Section 205 filings with respect to \nrules for the energy and ancillary services markets,4 there is no basis for the \nCommission to disrupt the agreement that was the basis for PJM’s formation or to \notherwise give PJM the ability to usurp the filing rights of the suppliers that have real \n“skin in the game” and who will be relied on to make needed investments in the coming \nyears. \nI. \nCOMMENTS \nA. \nThe FPA Bars OPSI and Other State Entities From Having Section 205 \nFiling Rights \nSection 205 reserves to public utilities the right to file rate changes and is \ntherefore “intended for the benefit of the utility,”5 with the Commission only “play[ing] ‘an \n \n4  \nSee Comments from PJM Interconnection, L.L.C. at 6, Docket No. AD26-7-000 (filed \nJuly 16, 2026) (the “PJM Pre-Technical Conference Comments”).  While the July 30 Notice also \nquestions whether PJM should have Section 205 rights with respect to Regional Transmission \nExpansion Planning (“RTEP”), these comments focus on PJM’s filing rights with respect to the \nenergy and ancillary services markets. \n5  \nCity of Winnfield v. FERC, 744 F.2d 871, 875 (D.C. Cir. 1984)."},{"page":3,"startToken":581,"endToken":1052,"text":"3 \nessentially passive and reactive’ role under section 205.”6  As explained in the affidavit \nof the Honorable Joseph T. Kelliher, former Chairman and Commissioner of the \nCommission, provided in Attachment A (the “Kelliher Affidavit”), state entities like OPSI \ncannot make filings under Section 205, given that such entities are simply not “public \nutilities” under the statute.7  In fact, the Commission previously acknowledged as much \nwhen it found that “[t]he FPA grants Section 205 filing rights to public utilities only, and \nthe Regional State Committee will not be a public utility.”8  Moreover, it is well \nestablished that neither the Commission nor a state authority can force a public utility to \n“cede [its] right under section 205 of the Act to file changes in rate design with the \nCommission,”9 or compel the public utility to make a rate filing that it does not want.10 \nIt bears emphasis that, while Atlantic City recognized a public utility’s right to \n \n6  \nAtlantic City Elec. Co. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002) (“Atlantic City”) (citation \nomitted)).   \n7  \nSee Kelliher Affidavit at PP 11-12; 16 U.S.C. § 824(e) (2024) (defining a “public utility” as \n“any person who owns or operates facilities subject to the jurisdiction of the Commission”). \n8  \nISO New England Inc., 106 FERC ¶ 61,280 at P 79, on reh’g, 109 FERC ¶ 61,147 \n(2004), petitions for review denied, Me. Pub. Utils. Comm’n v. FERC, 454 F.3d 278 (D.C. Cir. \n2006).  See also Midwest Indep. Transmission Sys. Operator, Inc., 122 FERC ¶ 61,283 at P 64 \n(2008) (“Section 205 grants filing rights to jurisdictional public utilities, not state agencies or \ncommissions.”). \n9  \nAtlantic City, 295 F.3d at 11.  See also Atlantic City Elec. Co. v. FERC, 329 F.3d 856, \n858 (D.C. Cir. 2003) (“Atlantic City II”) (same).  Cf. Building for the Future Through Elec. Reg’l \nTransmission Planning and Cost Allocation, Order No. 1920-B, 191 FERC ¶ 61,026 at P 52 \n(recognizing that public utilities have filing rights under Section 205 of the FPA, but explaining \nsuch Section 205 rights were not implicated because the Commission was acting under Section \n206 in requiring transmission providers to make compliance filings providing state entities’ \nproposals for cost allocation “to assist in building the record for the Commission’s exercise of its \nown authority to determine and fix the just and reasonable rate”). \n10  \nSee Massachusetts Dep’t of Pub. Utils. v. FERC, 729 F.2d 886, 888 (1st Cir. 1984) \n(“Mass DPU”) (permitting a state to require a public utility to make a filing under Section 205 \nwould “allow a state to do what FERC itself cannot, namely, to change an interstate rate \npractice that FERC has not found unreasonable” (emphasis in original)).  See also Kelliher \nAffidavit at PP 13-17 (discussing Mass DPU)."},{"page":4,"startToken":1052,"endToken":1355,"text":"4 \n“choose to voluntarily give up, by contract, some of their rate-filing freedom under \nsection 205,”11 this falls far short of blessing an attempt to grant or transfer Section 205 \nrights to non-public utilities in contravention of the plain language of the statute.12  The \npractical application of such shared rights demonstrates the potential legal pitfalls.  First, \nimagine a situation where OPSI is permitted to make Section 205 filings even where \nPJM is not seeking a change in its rates.  As Mr. Kelliher explains, this would effectively \ngive OPSI the right to force changes to rates that are not unjust or unreasonable, which \nthe Commission itself is prohibited from doing.13  Alternatively, imagine a situation where \nPJM files its desired Section 205 proposal but then a competing OPSI proposal is also \nfiled under Section 205.  In such a case, PJM’s and OPSI’s proposals would \ntheoretically be placed on an even footing before the Commission, and the Commission \ncould select the proposal of the non-public utility, OPSI, over that of the public utility, \nPJM, even if the public utility’s proposal were just and reasonable, contrary to the well-\nestablished principle that the Commission may reject rate changes proposed under \nSection 205 of the FPA “only if it finds that the changes . . . are not ‘just and \nreasonable.’”14  This would directly violate PJM’s rights under Section 205 of the FPA:  \nas the court recognized in Mass DPU, “[t]o accept Massachusetts’ claim that [Section] \n205 includes ‘regulator-compelled’ utility-proposed changes would prevent the utility \nfrom choosing among reasonable rate-practice alternatives.”15   \n \n11  \nAtlantic City, 295 F.3d at 10 (emphasis added). \n12  \nSee Kelliher Affidavit at PP 20-23. \n13  \nSee id. at PP 13-14 (discussing holding in Mass DPU). \n14  \nAtlantic City, 295 F.3d at 9. \n15  \nMass DPU, 729 F.2d at 888."},{"page":5,"startToken":1355,"endToken":1650,"text":"5 \nFinally, Mr. Kelliher points out that, even without Section 205 filing rights, state \nentities have options available to them to address rates they believe are unjust and \nunreasonable.  Indeed, consistent with the statutory scheme of the FPA, states have \nhistorically filed, and continue to file, complaints with the Commission under Section 206 \nof the FPA,16 but “what OPSI is asking for is functionally the ability to obtain relief that is \nonly available under Section 206 while shedding the burden associated with Section \n206 that all other complainants – and the Commission itself – are required to bear.”17 \nB. \nThe Bargain Struck in the Operating Agreement Should be Upheld \nOn December 31, 1996, nine of the ten members of the Pennsylvania-New \nJersey-Maryland Interconnection made a filing with the Commission to comply with \nOrder No. 888, explaining that their filing “was the product of intense dialogue and \ncollaboration,” but that “[i]t was not possible for the participants to agree on a \ncomprehensive restructuring of PJM, including an [independent system operator \n(“ISO”)],” by the date of the filing and committing to make a further filing.18  On June 2, \n1997, the Supporting Companies fulfilled that commitment by making another filing to \nestablish PJM as an ISO, which resulted from “further negotiations with stakeholders,” \nwhere the “Supporting Companies worked with a large group of interested stakeholders \n \n16  \nSee Kelliher Affidavit at P 19. \n17  \nId. \n18  \nBrief of the Supporting Companies at 2, Docket Nos. ER97-1082-000, et al. (filed Dec. \n31, 1996) (filed by Atlantic City Electric Company, Baltimore Gas and Electric Company, \nDelmarva Power & Light Company, Pennsylvania Power & Light Company, Potomac Electric \nPower Company, Public Service Electric and Gas Company, Jersey Central Power & Light \nCompany, Metropolitan Edison Company and Pennsylvania Electric Company (collectively, the \n“Supporting Companies”))."},{"page":6,"startToken":1650,"endToken":1981,"text":"6 \nin an effort to obtain as much consensus as possible.”19  Among other things, this filing \nincluded the Operating Agreement setting forth “revised governance provisions [that] \nare a direct result of discussions among the Supporting Companies and other \nstakeholders.”20  One of the “[k]ey features” of the Operating Agreement21 was the \n“[c]lear delineation of the respective roles of the PJM Board, the Office of the \nInterconnection, and the Members Committee,” where the Members Committee’s \nresponsibilities included “amend[ing] or terminat[ing] the Operating Agreement. . . .”22 \nIn conditionally accepting the Operating Agreement, the Commission did not \nrequire any changes to the filing rights limitations set forth therein.23  There is no basis \nfor the Commission or PJM to now seek to undo this foundational structure that \ninformed members’ willingness to establish and join PJM.  Even aside from the fact that \nthe Operating Agreement is a voluntary agreement among sophisticated parties that \nshould be entitled to protection under the Mobile-Sierra public interest standard of \nreview,24 disrupting that agreement by giving PJM unilateral Section 205 filing rights \nwould effectively recreate the situation that led to Atlantic City and Atlantic City II.  That \nis, the public utilities that actually own the assets used to supply the energy and \n \n19  \nAmended & Restated Operating Agreement, Transmittal Letter at 1, Docket No. ER97-\n3189-000, et al. (filed June 2, 1997). \n20  \nId. at 3. \n21  \nId. at 7. \n22  \nId. at 9. \n23  \nSee Pennsylvania-N.J.-Md. Interconnection, 81 FERC ¶ 61,257 (1997) (the “PJM ISO \nOrder”), clarified, 82 FERC ¶ 61,068 (1998), on reh'g, 92 FERC ¶ 61, 282 (2000).  The PJM ISO \nOrder did require modifications to the filing rights proposed in the Transmission Owners \nAgreement, see 81 FERC ¶ 61,257 at 62,279, leading to the decisions in Atlantic City and \nAtlantic City II.  \n24  \nSee United Gas Pipe Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332 (1956); FPC v. \nSierra Pac. Power Co., 350 U.S. 348 (1956)."},{"page":7,"startToken":1981,"endToken":2304,"text":"7 \nancillary services markets would be completely deprived of their rights under \nSection 205.  This result is clearly forbidden:  As the D.C. Circuit made abundantly clear \nin Atlantic City and reiterated in Atlantic City II, “[w]hen FERC attempts to deprive the \nutilities of their rights ‘to initiate rate design changes with respect to services provided \nby their own assets[,]’  FERC has exceeded its jurisdiction.”25  Moreover, the \nCommission itself has previously recognized that, “[u]nder section 205 of the FPA, a \nsingle utility or a group of utilities is not permitted to file to change a rate applicable to \nanother utility, unless there is an agreement to that effect,”26 but that is precisely what \nwould happen if the Commission were to disregard the balance struck in the Operating \nAgreement and grant PJM unilateral Section 205 filing rights over suppliers’ objections. \nIn short, the statutory scheme of the FPA makes clear that the Commission \ncannot use its authority under Section 206 of the FPA to effectively strip public utilities of \ntheir Section 205 filing rights over energy and ancillary services markets and transfer \nsuch rights to PJM by, for example, finding that the inclusion of energy and ancillary \nservices market rules in Schedule Nos. 1 and 2 to the Operating Agreement is unjust \nand unreasonable, and requiring those rules to be moved to the PJM Open Access \nTransmission Tariff (the “PJM Tariff”), where PJM has unilateral Section 205 filing rights. \nEven assuming arguendo, however, that the Commission had the authority to \ntake such an action under Section 206, there are sound policy reasons to refrain from \ndoing so.  In particular, EPSA notes that PJM previously filed a complaint seeking to \n \n25  \nAtlantic City II, 329 F.3d at 859 (alteration in original) (quoting Atlantic City, 295 F.3d at \n10). \n26  \nPJM Interconnection, L.L.C., 109 FERC ¶ 61,012 at P 22 (2004), on reh’g, 110 FERC \n¶ 61,234 (2005)."},{"page":8,"startToken":2304,"endToken":2710,"text":"8 \nmove the RTEP procedures out of the Operating Agreement to the PJM Tariff so that \nPJM would have Section 205 filing rights with respect to the RTEP.  The Commission \ninitially denied the complaint and then, on rehearing, dismissed it on procedural \ngrounds.27  It is nonetheless instructive that, in Duquesne I, the Commission reminded \nPJM that neither the rules of other regional transmission organizations (“RTOs”) or \nISOs28 nor any purported increased efficiencies29 would satisfy PJM’s burden under \nSection 206 of the FPA to make such a change to the Operating Agreement.  \nNotwithstanding the Commission’s subsequent dismissal in Duquesne II, those findings \ncorrectly state the legal standard applicable under Section 206 of the FPA and would \napply to any attempt to modify the Operating Agreement to give PJM Section 205 filing \nrights over the energy and ancillary services markets.  In addition, as a policy matter, \ndepriving PJM members of their Section 205 rights with respect to those markets would \nsignal a disregard for supplier concerns, sending precisely the wrong message at this \ncritical juncture when the investment community is looking for signs that PJM will \nprovide the necessary stability and consistency for investments and that the value of \n \n27  \nDuquesne Light Co., 189 FERC ¶ 61,181 at P 105 (2024) (“Duquesne I”), on reh’g, 192 \nFERC ¶ 61,051 (2025) (“Duquesne II”). \n28  \nSee Duquesne I, 189 FERC ¶ 61,181 at P 108 (explaining that there are “regional \ndifferences in RTOs’ governance structure,” and that such differences “were arrived at through \nnegotiations and tradeoffs that balance the rights and obligations of diverse stakeholders” \n(footnotes omitted)).  See also Regional Transmission Orgs., Order No. 2000, 89 FERC \n¶ 61,285, 1999 WL 33505505 at *94 (1999) (recognizing that “RTOs will take many different \nforms that reflect the needs and different starting points of each region,” and that “[i]t is unlikely \nthat a single approach to governance will work for the different types of RTOs that are likely to \nemerge”), on reh’g, Order No. 2000-A, 90 FERC ¶ 61,201 (2000). \n29  \nSee Duquesne I, 189 FERC ¶ 61,181 at P 105 (stating that “the extent to which PJM \nmay be able to more efficiently or effectively propose changes to . . . rules under some \nalternative structure governing the circumstances under which PJM can make FPA section 205 \nfilings” does not establish that the existing limitations on PJM’s filing rights as set forth in the \nOperating Agreement are unjust, unreasonable or unduly discriminatory”)."},{"page":9,"startToken":2710,"endToken":2822,"text":"9 \nany investments will not be eroded by future rule changes. \nII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, EPSA respectfully requests that the \nCommission take these comments under consideration in taking any further action with \nrespect to PJM’s governance and stakeholder processes. \nRespectfully submitted, \nELECTRIC POWER SUPPLY ASSOCIATION \nBy: \n  /s/ David G. Tewksbury \n \n \nDavid G. Tewksbury \nStephanie S. Lim \nMCDERMOTT WILL & SCHULTE LLP \nThe McDermott Building \n500 North Capitol Street, NW \nWashington, DC  20001 \nNancy Bagot \nSenior Vice President \nSharon Royka Theodore \nVice President, Regulatory Affairs \nElectric Power Supply Association \n1401 New York Ave, NW, Suite 950 \nWashington, DC  20005 \nOn behalf of the  \nElectric Power Supply Association \nDated:  August 21, 2026"},{"page":10,"startToken":2822,"endToken":2827,"text":"ATTACHMENT A \nTHE KELLIHER AFFIDAVIT"},{"page":11,"startToken":2827,"endToken":2863,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \n \n \n \n) \nPJM Governance and Stakeholder Reforms   \n) \nDocket No. AD26-7 \n \n \n \n \n \n \n \n) \n \n \n \n \nOn Behalf of  \n \nThe Electric Power Supply Association \n \n \n \n \n \nAugust 21, 2026 \n \n \n \n \n \n \n \n \n \n \nAffidavit \nOf \nThe Hon. Joseph T. Kelliher"},{"page":12,"startToken":2863,"endToken":3132,"text":"2 \n \nIntroduction \n \n1. My name is Joseph T. Kelliher.  I am the principal of Joseph Kelliher Consulting, an advisory \nand consulting business. \n2. My Affidavit supports the Post-Conference Comments of the Electric Power Supply \nAssociation in the PJM Interconnection, L.L.C. (“PJM”) Governance and Stakeholder \nReforms proceeding initiated by the Federal Energy Regulatory Commission (“Commission” \nor “FERC”) earlier this year.  In this Affidavit I review Sections 205 and 206 of the Federal \nPower Act, previous Commission approvals and rejections of state requests for Section 205 \nfiling rights, relevant legal precedent, and discuss whether the Commission has the legal \nauthority to grant requests by the Organization of PJM States, Inc. (“OPSI”) and states for \nSection 205 filing rights.  My conclusion is the Commission is barred from granting states \ndirect or indirect Section 205 filing rights by the Federal Power Act. \nBackground and Qualifications \n3. My opinions are based on my forty years of experience with energy policy matters, on both \nthe giving and receiving end of energy policymaking.  That experience includes service as \nCommission Chairman and Commissioner (2003-09); Executive Vice President-Federal \nRegulatory Affairs with NextEra Energy, Inc. (2009-20), the largest U.S. electricity company, \nwhich through its subsidiaries is a member of every regional transmission organization \n(“RTO”), either as a generator, marketer, or transmission owner; Senior Policy Advisor to the \nU.S. Secretary of Energy (2001-03) during the California and Western Power Crisis and \ndevelopment of the National Energy Strategy; and Majority Counsel for the House \nCommerce Committee (1995-2000), responsible for electricity legislation and Commission \noversight.  During my service as FERC Chairman and Commissioner, I voted to authorize the"},{"page":13,"startToken":3132,"endToken":3563,"text":"3 \n \nestablishment of multiple RTOs, including Southwest Power Pool, Inc. (“SPP”), and ISO-\nNew England Inc. (“ISO-NE”).  The Commission issued Order No. 719 during my \nchairmanship, which was designed to improve RTO responsiveness to state commissions and \nstakeholders.1  I also voted on a number of orders where the Commission considered state \nrequests for direct or indirect Section 205 filing rights, voting to grant the SPP regional state \ncommittee indirect Section 205 filing rights in 20042 and voting to reject the Organization of \nMISO States’ (“OMS”) request for direct Section 205 filing rights in 2008.3  I voted more \nthan 7,000 times during my FERC service, and my vote to grant indirect Section 205 filing \nrights to the SPP regional state committee is one I came to regret.  As Commission Chairman, \nI proposed joint boards with the states to consider policy questions that involved both federal \nand state jurisdiction, which evolved into federal-state collaboratives that continue today.   \n4. I reserve the right to modify or supplement this Affidavit.   \nState Efforts to Secure Federal Power Act Section 205 Filing Rights with Respect to \nPJM’s Rules \n \n5. OPSI and some PJM states have requested that the Commission grant OPSI and PJM states \nSection 205 filing rights.4  The OPSI comments are the most fulsome, while the other state \ncommenters offer only a sentence or two in passing.5  OPSI makes much of that fact that it is \n \n1 Wholesale Competition in Regions with Organized Elec. Mkts., 125 FERC ¶ 61,071 (2008) (“Order No. 719”), \norder on reh’g, 128 FERC ¶ 61,059 (“Order No. 719-A”), order on reh’g, 129 FERC ¶ 61,252 (2009) (“Order No. \n719-B”). \n2 Southwest Power Pool, Inc., 106 FERC ¶ 61,110 (“SPP I”) (Wood, Chairman, concurring) (Kelliher, Comm’r, \nconcurring), order on reh’g, 109 FERC ¶ 61,010 (2004) (“SPP II”). \n3 Midwest Indep. Transmission Sys. Operator, Inc., 122 FERC ¶ 61,283 at P 64 (2008) (denying OMS request for \ndirect Section 205 filing rights on the grounds that “Section 205 grants filing rights to jurisdictional public utilities, \nnot state agencies or commissions”). \n4 PJM Governance and Stakeholder Reforms, Pre-Conference Comments of the Organization of PJM States, Inc., \nDocket No. AD26-7-000 (filed July 21, 2026) (“OPSI Comments”); PJM Governance and Stakeholder Reforms, \nPre-Technical Conference Comments of the Pennsylvania Public Utility Commission, Docket No. AD26-7-000 \n(filed July 22, 2026) (“Pennsylvania PUC Comments”); PJM Governance and Stakeholder Reforms, Comments of \nthe Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate, Docket No. AD26-7-000 (filed \nJuly 21, 2026) (“Ohio FEA Comments”). \n5 Pennsylvania PUC Comments at 1; Ohio FEA Comments at 5."},{"page":14,"startToken":3563,"endToken":3932,"text":"4 \n \nnot asking that PJM and PJM public utility transmission owners be divested of their Section \n205 filing rights,6 something that is not in the world of the possible in any event after Atlantic \nCity Electric Co. v. FERC (“Atlantic City”).7  Instead, OPSI “simply” requests that PJM and \nall PJM public utility transmission owners voluntarily bind themselves to make Section 205 \nfilings at the behest of OPSI and state commissions.8  This would be true even when the \npublic utility opposes the filing and believes it to be unjust and unreasonable, or has no desire \nto change the existing tariff.  This is no small thing.  To be clear, the Commission has not \npreviously granted Section 205 filing rights over public utility transmission owners in SPP, \nISO-NE, and Midcontinent Independent System Operator, Inc. f/k/a Midwest Independent \nTransmission System Operator, Inc. (“MISO”) to individual state commissions,9 and the \ndirect and indirect extension of Section 205 filing rights to state commissions, as a group, is \nlegally problematic. \n6. States have requested two types of Section 205 filing rights in the past: direct and indirect.  \nDirect filing rights would allow states to make Section 205 filings to change the tariff rates, \nterms and conditions of state-regulated public utilities on their own motion.  Indirect filing \nrights are where an RTO or public utility is required by the Commission to make Section 205 \nfilings at the behest of a regional state committee or state.  While some voices in PJM seem \nto be calling for states to be vested with direct Section 205 filing rights, as discussed below, \nthat is barred by the Federal Power Act, which the Commission to its credit has \n \n6 OPSI Comments at 12-13 (“OPSI is not asking that [PJM and PJM public utilities] give up any of their filing \nauthority under FPA Section 205.”) (emphasis in original) (footnote omitted). \n7 295 F.3d 1 (D.C. Cir. 2002). \n8 OPSI Comments at 9-17. \n9 The Commission did approve Entergy’s proposal for an Entergy regional state committee to have indirect Section \n205 filing rights but did not share Entergy’s filing rights with individual state commissions.  Entergy Ark., Inc., 133 \nFERC ¶ 61,211 at P 15 (2010) (“Entergy”)."},{"page":15,"startToken":3932,"endToken":4347,"text":"5 \n \nacknowledged in the past.10  To the extent that OPSI or others are nonetheless asserting that \n“states should have filing rights,” this is actually a muted call for the Commission to ignore \nor Congress to amend the Federal Power Act.   \n7. The OPSI proposal requests indirect Section 205 filing rights, where PJM and PJM public \nutility transmission owners would be compelled to make Section 205 filings on OPSI’s \nbehalf.  This would effectively turn PJM and PJM public utility transmission owners into a \nsleeve for the state exercise of Section 205 filing rights, whereby PJM and the PJM public \nutility transmission owners would be forced to lend their Section 205 filing rights to the \nstates.  As discussed below, giving states such indirect Section 205 filing rights is also barred \nby the Federal Power Act.  While OPSI focuses on resource adequacy and transmission cost \nallocation reforms,11 the limitations of the Federal Power Act apply with equal force to all \nrates filed under Section 205.  Moreover, some advocates for state filing rights assert that all \nthe states are asking for is the ability to make a joint filing with PJM when the states and \nPJM are in agreement, but if that were truly the case, there is no reason to do anything, since \nthat is functionally equivalent to states filing supporting comments on a PJM Section 205 \nfiling.  However, it would be naïve to discount the possibility that PJM or individual public \nutilities could feel pressured to agree to make such “voluntary” joint filings because of \nthreats by states to withdraw from PJM or by the prospect of retaliation by state \ncommissions.  Personally, I do not see much difference between a Section 205 filing that a \n \n10 ISO New Eng. Inc., 106 FERC ¶ 61,280 at P 79 (“ISO-NE I”) (denying the New England Conference of Public \nUtility Commissioners’ (“NECPUC”)  request for concurrent Section 205 filing rights because “[t]he FPA grants \nSection 205 filing rights to public utilities only, and the Regional State Committee will not be a public utility.”), on \nreh’g, 109 FERC ¶ 61,147 (2004) (“ISO-NE II”), petitions for review denied, Me. Pub. Utils. Comm’n v. FERC, 454 \nF.3d 278 (D.C. Cir. 2006) (“Maine PUC”); Midwest Indep. Transmission Sys. Operator, Inc., 122 FERC ¶ 61,283 at \nP 64 (2008) (denying OMS request for direct Section 205 filing rights on the grounds that “Section 205 grants filing \nrights to jurisdictional public utilities, not state agencies or commissions”). \n11 OPSI Comments at 1."},{"page":16,"startToken":4347,"endToken":4702,"text":"6 \n \nstate has compelled a public utility to file on its behalf and one the state has filed directly.  \nBoth are Section 205 filings made by a non-public utility and both are barred by the Federal \nPower Act. \n8. To be clear, I do not question the motives of state commissions that are seeking Section 205 \nfiling rights.  OPSI expresses frustration that retail regulators are unable to control wholesale \ncosts that flow through to retail consumers.12  But its grievance properly lies with the \nCommerce Clause, the Supremacy Clause, and Supreme Court decisions tracing back 100 \nyears, including judicial doctrines such as the filed rate doctrine, not the PJM Tariff or \nOperating Agreement. \n9. OPSI also goes so far as to suggest that PJM and/or PJM transmission owners would be \nrequired to share their filing rights with all state commissions.13  Even aside from legal \nconsiderations, this raises practical concerns because it assumes away the prospect that PJM \nstates might disagree.  Would PJM only be compelled to make an alternative filing at the \nbehest of the states if there is unanimous support among the states?14  If not, is a \nsupermajority required or does a simple majority suffice?  Are indirect Section 205 filing \nrights reserved to the majority of PJM states and would the minority be divested of those \nrights?  Would PJM have to make two or more alternative filings on behalf of the states if \nPJM states fracture into different camps?  In the event of broad disagreement among the \nstates, would the disagreeing states all be able to make individual Section 205 filings on \nbehalf of PJM that are contradictory in nature, along perhaps with a filing from PJM itself?  \n \n12 OPSI Comments at 9. \n13 Id. at 13 (“OPSI is simply requesting that [PJM and PJM public utility transmission owners] add a condition to \nthese [Section 205 filing] rights, voluntarily, to make a filing on behalf of the states”). \n14 The Entergy regional state committee only had the authority to compel Entergy to make a Section 205 filing upon \nunanimous consent of its members.  Entergy, 133 FERC ¶ 61,211 at P 5."},{"page":17,"startToken":4702,"endToken":5022,"text":"7 \n \nIf multiple alternative proposals are just and reasonable, how would the Commission choose \namong them?  Would a “tie” go to the public utility or a non-public utility?  Frankly, it is hard \nto see that any of these outcomes are consistent with the purpose of the PJM Governance and \nStakeholder Reform proceeding: improving PJM decisionmaking and its ability to address \noperational and market needs in a timely and efficient manner. \n10. Some advocates for granting states Section 205 filing rights envision that the states and PJM \nwill always agree with the proposed filing, so where is the harm?  But in that scenario, what \nis the point?  As I noted previously, if PJM and the states agree on a Section 205 filing, PJM \ncan make the filing and the states can file supportive comments, as they can do today.  When \nconsidering granting Section 205 filing rights to state commissions or a committee of state \ncommissions, the Commission should assume the opposite, namely that the public utility, \nwhether it be PJM or an individual PJM public utility, opposes the state proposal and believes \nit is unjust and unreasonable.  Should a public utility be compelled to make a Section 205 \nfiling at the behest of the states that it believes is unjust and unreasonable?   \nFederal Power Act Sections 205 and 206 \n \n \nSection 205 \n11. The rationale offered by OPSI for sharing the Section 205 filing rights of PJM and PJM \npublic utility transmission owners with the states is that “PJM’s governance structure and \nstakeholder process were developed for a different era.”15  It may be a different era, but it is \nstill the same Federal Power Act.  There are two ways tariff rates, terms and conditions can \nbe changed under the Federal Power Act.  The first approach, the path the states would like to \navail themselves of, is Section 205 of the Federal Power Act, which states that: \n \n15 OPSI Comments at 1."},{"page":18,"startToken":5022,"endToken":5409,"text":"8 \n \nevery public utility shall file with the Commission ... schedules showing all \nrates and ... practices ... and ... contracts which ... relate to such rates .... [N]o \nchange shall be made ... except after sixty days’ notice ....  Such notice shall be \ngiven by filing with the Commission ... new schedules ....  Whenever any such \nnew schedule is filed the Commission shall have authority ... to enter upon a \nhearing concerning the lawfulness [of the changes] ...; and, pending such \nhearing and the decision thereon, the Commission ... may suspend the ... [new] \nschedule ... [for no longer than] five months ....  If ... an order [has not been] \nmade at [the end of] ... five months, [the changes] ... shall go into effect ..., but \nin case of a proposed increased rate or charge, the Commission ... [may require \na refund of any] portion of such increased rate[ ] ... as by its decision shall be \nfound not justified.  At any hearing involving [a rate increase], the burden [of \nproving an increase] just and reasonable shall be upon the public utility .... \n \n16 U.S.C. §§ 824d(c)-(e). \n12. What stands out is that Section 205 filing rights are reserved to “public utilities,” a term \ndefined to mean “any person who owns or operates facilities subject to the jurisdiction of the \nCommission,”16 which in turn is “the transmission of electric energy in interstate commerce \nand the sale of such energy at wholesale in interstate commerce.”17  A “public utility” must be \na “person” and “person” is defined by the Federal Power Act to mean an individual or \ncorporation.18  To belabor the obvious, OPSI and state commissions do not own or operate \nfacilities subject to FERC jurisdiction, nor are OPSI and state commissions “individuals” or \n“corporations.”  That would seem to answer the question of whether a regional state \ncommittee or state commissions can be directly vested with Section 205 filing rights: it is \nbarred by the Federal Power Act, which reserves these rights to public utilities, and only \npublic utilities.  The Commission has consistently acknowledged that in the past.19  If the \ndefinition of “public utility” left any room for doubt (and it does not), that would be \n \n16 Federal Power Act § 201(e), 16 U.S.C. § 824(e). \n17 Id., § 201(a), 16 U.S.C. § 824(a). \n18 Id., § 3(4), 16 U.S.C. § 796(4). \n19 See supra note 11."},{"page":19,"startToken":5409,"endToken":5733,"text":"9 \n \neliminated by Section 201(f), which expressly excludes from the application of Part II of the \nFederal Power Act any “State or any political subdivision of a State….”20 \n13. The courts have also held that states cannot exercise indirect Section 205 filing rights.  This \nquestion was asked and answered more than forty years ago in Massachusetts Department of \nPublic Utilities v. FERC (“Mass. DPU”).21  In Mass. DPU a state commission ordered the \nWestern Massachusetts Electric Company, a public utility under the FPA, to make a Section \n205 filing to change a rate-setting practice objectionable to the state commission.  The public \nutility dutifully made the filing, but FERC rejected it, finding that Section 205 “governs \nchanges that the utility itself proposes, not those that a state regulator requires it to \npropose.”22  As future Supreme Court Justice Breyer summarized the FERC rejection: “If \nMassachusetts objects to the rule, says FERC, it should file a complaint in accordance with \n[Section 206].”23  The court agreed with FERC.  Under Breyer’s reasoning, Section 205 \nfilings are limited to when a public utility seeks to change its tariff for reasons of its own, not \nwhen a public utility desires no changes, but a state commission does.  As Breyer put it, \nSection 205 “governs changes that the utility itself proposes, not those that a state regulator \nrequires it to propose.”24 \n14. As the court in Mass. DPU noted, “the net effect of accepting Massachusetts’ argument is to \nallow a state to do what FERC itself cannot, namely, to change an interstate rate practice that \nFERC has not found unreasonable.”25  That is exactly what OPSI is grasping for in its \nrecommendations.  Accordingly, the Commission should reject any proposals for PJM and \n \n20 Federal Power Act § 201(f), 16 U.S.C. § 824(f). \n21 729 F.2d 886 (1st Cir. 1984).  \n22 Id. at 886. \n23 Id. \n24 Id. \n25 Id. at 888 (emphasis in original)."},{"page":20,"startToken":5733,"endToken":6054,"text":"10 \n \nPJM public utility transmission owners to share their Section 205 filing rights with the states, \nand instead invite states to file Section 206 complaints proposing tariff changes, consistent \nwith Mass. DPU. \n15. The Mass. DPU court was troubled by the prospect of allowing a state to sidestep its burden \nunder Section 206 through the device of commanding a public utility to make a Section 205 \nover its objections, effectively seizing the Section 205 filing rights for the state.  Allowing a \nstate to require a public utility file a Section 205 tariff change is an end run around the \nFederal Power Act.  That was true in 1984 and remains true in 2026.  OPSI seems to have the \nsame objective of proposing tariff changes while dodging their burden under Section 206. \n16. The OPSI recommendations essentially exhume the approach rejected in Mass. DPU more \nthan forty years ago.  The passage of time has not made this idea any more meritorious.  \nOPSI desires that state commissions be able to “present[] their proposals to the Commission \non a level playing field with PJM and [Transmission Owners].”26  But that is simply not \npermissible under the Federal Power Act.  The Act limits Section 205 filings to public \nutilities: PJM is a public utility, jurisdictional transmission owners are public utilities, \nregional state committees and state commissions plainly are not and to the extent they want \nto seek rate changes, they must do so as complainants under Section 206. \n17. If OPSI is instead asking that the Commission delegate to OPSI the power to compel PJM \nand PJM public utility transmission owners to make Section 205 filings, that approach also \nfails because the courts have repeatedly held FERC has no power to force public utilities to \nmake Section 205 filings,27 and FERC cannot delegate to the states more power than the \n \n26 OPSI Comments at 2 (emphasis added). \n27 Atlantic City, 295 F.3d at 10."},{"page":21,"startToken":6054,"endToken":6541,"text":"11 \n \nCommission itself possesses.  In fact, the Commission has no authority to delegate any of its \nFederal Power Act authority to states.28 \nSection 206 \n18. The other approach to change tariff rates, terms and conditions is Section 206 of the Federal \nPower Act.  States are very familiar with this path and have trodden it many times over the \ndecades since 1935.  Section 206 states that: \n[w]henever the Commission, after a hearing had upon its own motion or upon \ncomplaint, shall find that any rate ... or ... any rule, ... practice, or contract \naffecting such rate ... is ... unjust, unreasonable, unduly discriminatory or \npreferential, the Commission shall determine the just and reasonable rate, ... \npractice, or contract to be thereafter observed and in force, and shall fix the same \nby order. \n \n16 U.S.C. § 824e(a). \n19. While OPSI decries that there is no formal process for states to change PJM’s tariff,29 that is \nsimply not true.  The means exists: Section 206.  Under Section 206, states are free to file \ncomplaints seeking changes to the PJM tariff and have done so many times in the past.  In \nfact, there are currently nine Section 206 complaints pending at the Commission filed by \nstate entities.30  However, state complainants, like any other complainant and the Commission \n \n28 U.S. Telecom Ass'n v. FCC, 359 F.3d 554 (D.C. Cir. 2004). \n29 OPSI Comments at 1-2, 9-11, 13. \n30 Pa. Pub. Util. Comm’n v. PJM Interconnection, L.L.C., Complaint of the Pennsylvania Public Utility Commission, \nDocket No. EL26-98-000 (filed Aug. 17, 2026); Md. Energy Admin. v. Baltimore Gas & Elec. Co., Complaint by the \nMaryland State Agencies, Docket No. EL26-87-000 (filed July 2, 2026); Conn. Dept. of Energy v. ISO New Eng. \nInc., Complaint of Connecticut State Agencies Challenging RTO Adder Costs and Requesting Termination, Docket \nNo. EL26-79-000 (filed June 11, 2026); La. Pub. Serv. Comm’n v. Entergy Corp., Complaint on Behalf of the \nLouisiana Public Service Commission, Docket No. EL26-73-000 (filed May 19, 2026); Me. Off. of the Pub. Advoc. \nv. Eversource Energy Serv. Co., Complaint Against Eversource Energy Service Company, Docket No. EL26-66-000 \n(filed May 12, 2026); Md. Off. of People’s Couns. v. PJM Interconnection, LLC, Complaint Requesting Fast Track \nProcessing of the Maryland Office of People’s Counsel, Docket No. EL26-63-000 (filed May 7, 2026); N.D. Pub. \nServ. Comm’n v. Midcontinent Indep. Sys. Operator, Inc., Complaint of the Concerned Commissions and Requests \nfor Expedited Action and Fast Track Processing, Docket No. EL25-109-000 (filed July 30, 2025); Joint Consumer \nAdvocs. v. PJM Interconnection, L.L.C., Complaint of Joint Consumer Advocates and Request for Fast Track \nProcessing, Docket No. EL25-76-000 (filed Apr. 14, 2025); Off. of the Ohio Consumers’ Couns. v. PJM \nInterconnection, L.L.C., Complaint of the Office of the Ohio Consumers’ Counsel to Protect Ohio Consumers Under \nthe PJM Tariff from the Failures of Multiple Agencies to Regulate Hundreds of Millions of Dollars in Monopoly"},{"page":22,"startToken":6541,"endToken":6883,"text":"12 \n \nitself when acting under Section 206, bear the burden of demonstrating the current rate, rule, \npractice, or contract is unjust and unreasonable or unduly discriminatory or preferential.  The \ninspiration for state proposals for sharing Section 205 filing rights could be a belief that this \nburden is inconvenient and they would prefer to set it aside.  But since a state cannot exercise \ndirect or indirect Section 205 filing rights, the only means it has to change tariff rates, terms \nand conditions is through a Section 206 complaint, the same means states have used for \ndecades.  Looking at the OPSI proposal through the lens of the Federal Power Act, what \nOPSI is asking for is functionally the ability to obtain relief that is only available under \nSection 206 while shedding the burden associated with Section 206 that all other \ncomplainants – and the Commission itself – are required to bear. \nAtlantic City Does Not Support Sharing of Section 205 Filing Rights with the States \n20. It is telling that OPSI makes little effort to persuade the Commission that its \nrecommendations are consistent with the Federal Power Act.  In particular, it offers no \nargument its proposals are allowed under Section 205.  Inexplicably, OPSI declares its \nrecommendations are consistent with Atlantic City,31 pointing to a stray sentence in the \ndecision, namely: “Of course, utilities may choose to voluntarily give up, by contract, some \nof their rate-filing freedom under section 205.”32  This attempt is at best misleading.  First, the \nonly sharing of Section 205 filing rights discussed in Atlantic City was the allocation of \nSection 205 filing rights between PJM, a public utility, and PJM public utility members.33  \nThe court was not troubled at the sharing of Section 205 filing rights between public utilities, \n \nElectric Transmission Charges for “Supplemental Projects” Planned by AEP, AES, Duke, and FirstEnergy and \nRequest for Fast-Track Processing, Docket No. EL23-105-000 (filed Sept. 28, 2023). \n31 OPSI Comments at 12. \n32 Id. (quoting Atlantic City, 295 F.3d at 10 (emphasis added)). \n33 Atlantic City, 279 F.3d at 9, 11."},{"page":23,"startToken":6883,"endToken":7207,"text":"13 \n \nespecially where one public utility would be operating the assets of other public utilities.  \nThat does not mean, however, that the court embraced the idea of sharing Section 205 filing \nrights with entities that are not public utilities. \n21. Second, the quote is misrepresented as implying Atlantic City blesses the notion of sharing \nSection 205 filing rights with state entities.  But that is not what the quote says.  The quote \ndoes not refer to public utilities giving their filing rights to someone else, but only to public \nutilities “giv[ing] up … some of their rate-filing freedom under section 205.”  “What “rate-\nfiling freedom” was the court envisioning?  Not the sharing of Section 205 filing rights to a \nnon-public utility, to be sure.  It was a public utility relinquishing its right to make unilateral \nchanges in rates for a time as part of a fixed rate contract.34  OPSI’s interpretation would \nrewrite the sentence to read “Of course, utilities may choose to voluntarily give, by contract, \nsome of their rate-filing rights to a non-public utility under section 205.” \n22. In my view, the OPSI recommendations are squarely inconsistent with Atlantic City.  The \ncentral holding of Atlantic City is that “the power to initiate rate changes [under Section 205] \nrests with the utility and cannot be appropriated by FERC.”35 That is true whether FERC \nseeks to appropriate a public utility’s Section 205 filing rights for itself or for the use of a \nregional state committee and state commissions, as OPSI seeks.  In harsh language the \nAtlantic City court concluded “FERC thereby eliminated the very thing that the statute was \ndesigned to protect – the ability of the utility owner to ‘set the rates it will charge prospective \ncustomers, and change them at will,’ subject to review by the Commission.”36  \n \n34 Id. at 11. \n35 Id. at 10. \n36 Id. (quoting City of Cleveland v. FPC, 525 F.2d 845, 855 (D.C. Cir. 1976))."},{"page":24,"startToken":7207,"endToken":7278,"text":"14 \n \n23. The OPSI recommendations would eliminate the ability of PJM and its public utility \ntransmission owner members to “set the rates [they] will charge” and “change them at will,” \nsubject to Commission review.  Instead, these public utilities may be compelled to file \nSection 205 tariff changes they actively oppose and believe unjust and unreasonable at the \nbehest of states, in violation of their clear rights under the Federal Power Act."},{"page":25,"startToken":7278,"endToken":7278,"text":""}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1158,"startToken":0,"endToken":458},{"p":2,"at":1158,"title":"I. COMMENTS","method":"printed heading","endPage":5,"endAt":621,"startToken":458,"endToken":1453},{"p":5,"at":621,"title":"B. The Bargain Struck in the Operating Agreement Should be Upheld","method":"printed heading","endPage":9,"endAt":63,"startToken":1453,"endToken":2721},{"p":9,"at":63,"title":"II. CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2721,"endToken":2822},{"p":10,"at":0,"title":"ATTACHMENT A","method":"printed heading","endPage":12,"endAt":5,"startToken":2822,"endToken":2864},{"p":12,"at":5,"title":"Introduction","method":"printed heading","endPage":25,"endAt":0,"startToken":2864,"endToken":7278}]}