{"document":{"slug":"rec-20260821-5307","title":"Protest of Northern Virginia Electric Cooperative, Inc. to the PJM Reliability Backstop Procurement Proposal","issued":"2026-08-21","accession":"20260821-5307","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Northern Virginia Electric Cooperative, Inc.","kind":"protest","file":"sources/filings/text/20260821-5307_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5307","tier":"record","sha256":"26b0d3d0a6397eb5fe3d701212f03ad28d947a8b753987ae16ba448dd4cee528","pages":28,"tokens":8871,"emptyPages":[],"textThemes":["credit","adequacy","cost","registry"]},"pages":[{"page":1,"startToken":0,"endToken":274,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \n \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3380-000 \n \n) \n \n \nPROTEST OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC. \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or the “Commission”),1 Northern Virginia Electric \nCooperative, Inc. (“NOVEC”) respectfully submits this protest to aspects of the July 31, 2026, \nfiling by PJM Interconnection, L.L.C. (“PJM”) to revise its Open Access Transmission Tariff \n(“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to \nestablish the Reliability Backstop Procurement (“RBP”).2 For the reasons set forth herein, the \nCommission should reject the RBP as unjust and unreasonable. If the Commission does not \nreject the RBP, it should require revisions on compliance to eliminate or substantially reduce the \nnearly $2 billion collateral requirement that the RBP Proposal would impose on NOVEC, and to \neliminate the resulting subsidization of the PJM capacity market by NOVEC and a relatively \nsmall number of the other Load Serving Entities (“LSEs”) that would be primarily responsible \nfor providing financial security for the contracts that PJM would enter into with RBP Resources. \nI. \nINTRODUCTION \nNOVEC recognizes the importance of bringing online more new capacity quickly to \nensure system reliability and the fair assignment of associated costs. Even before the recent \n \n1 18 C.F.R. § 385.211. NOVEC filed a doc-less motion to intervene in this proceeding on August 10, 2026. NOVEC, \n(doc-less) Motion to Intervene, Docket No. ER26-3380-000 (Aug 10, 2026) (Accession No. 20260810-5101). \n2 PJM Interconnection, L.L.C., Reliability Backstop Procurement, Docket No. ER26-3380-000 (July 31, 2026) \n(Accession No. 20260731-5214) (“RBP Proposal”)."},{"page":2,"startToken":274,"endToken":587,"text":"2 \n \nexponential nationwide expansion of data centers and other large loads, significant numbers of \ndata centers had already been locating in NOVEC’s service territory.  \nNOVEC has a longstanding practice of taking steps to appropriately assign costs to large-\nload customers. NOVEC developed and received state regulatory approval for, and then began \nutilizing, a data-center-specific rate class that has been in place since the 1990’s. Additionally, \nNOVEC has directly assigned more than $1.7 billion in costs directly to data-center customers to \nhelp ensure they pay upfront for their dedicated substations and other infrastructure. NOVEC is \nalso concerned about supply-demand imbalances and the resulting cost increases impacting \ncustomers large and small throughout the region. \nAs a result, NOVEC was encouraged by, and participated in, the PJM stakeholder process \nthat utilized PJM’s Critical Issue Fast Path (“CIFP”) to address the issue of large-load additions. \nThat stakeholder process successfully culminated in a coalition proposal that received more than \ntwo-thirds member endorsement in a sector-weighted vote. That consensus proposal “would have \ncreated greater stability and certainty while shielding homes and businesses from bearing the \ncosts of serving large loads.”3 The coalition proposal was a bottom-up structure that relied on a \nvoluntary subscription model to maintain LSEs’ authority to negotiate with large-load customers \nand only take on obligations for which it had signed contracts or otherwise secured a pathway for \ndirectly assigning the resulting costs to the data center causing the costs. Despite the strong \nstakeholder support, PJM rejected the consensus proposal and instead filed its RBP Proposal, a \ntop-down approach that is fundamentally flawed and was not fully vetted through the stakeholder \nprocess. Notably, the details and full implications of the mandatory credit and collateral \nrequirements were never explained. \n \n3 East Kentucky Power Cooperative, Letter of EKPC President and CEO Don Mosier, Docket No. ER26-3380-000, \nat 2 (filed Aug. 11, 2026) (Accession No. 20260811-4003) (“EKPC Letter”)."},{"page":3,"startToken":587,"endToken":938,"text":"3 \n \nThe as-filed RBP Proposal is not just and reasonable. The accelerated schedule prevents \nthe RBP from achieving the aims of mutually agreed-upon cost-causation principles. The cost \nallocation of the RBP violates the Commission’s cost-causation principle because it does not \nrecognize that neither load growth of large-load customers, nor load growth in general, are the \nsole cause of the capacity shortfall. PJM’s proposal is also not just or reasonable because it \nunreasonably causes entities like NOVEC to secure and subsidize the capacity market as RBP \nbuyers. Although the RBP allows RBP buyers to offset their obligations, the time allotted to do \nso is unreasonably short and the RBP requires that customers procure more MWs than they \nwould otherwise be responsible for, design choices that should be rejected. Having put this \nburden on NOVEC and other RBP buyers, PJM is also proposing to impose collateral \nrequirements on them that are excessive, onerous, and not commensurate with the actual RBP \nCharges that need to be collateralized. \nThe Commission should reject the filing as unjust and unreasonable. If the Commission \ndoes not reject the filing, it should accept PJM’s invitation4 to require changes to the RBP to \nrectify the flaws discussed below, including extending the effective date to allow for the RBP to \nhave a chance of success, revising the cost-allocation structure to recognize the benefits derived \nfrom RBP Resources by non-RBP buyers, adjusting the amount of MWs needed to offset RBP \ncost responsibility, requiring additional paths to mitigation, and reducing the collateral \nrequirements as discussed below. At a minimum, the Commission should issue a deficiency \nletter and require PJM to better explain both its rejection of the coalition proposal and clarify \nPJM’s as-filed RBP design.  \n \n4 RBP Proposal at 3 (“…PJM provides notice that it consents to the Commission’s exercise of authority to modify \nand/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under \nsection 205 of the FPA and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is \nconsistent with PJM’s overarching objectives in this filing.”) (internal citation omitted)."},{"page":4,"startToken":938,"endToken":1310,"text":"4 \n \nII. \nPROTEST \nA. \nThere is a material mismatch in the timing required by PJM’s proposed RBP \nobligation and the decisions of state regulators on allocation process requirements \nas PJM laid them out prior to the auction.  \nRecognizing that the justness and reasonableness of the RBP hinges on the ability of the \nLSEs to directly assign the RBP costs imposed on them to large loads that the LSEs serve, PJM \nstates that the success of the RBP relies on state participation to “refine, for purposes of cost \nallocation, which retail loads — including which ‘large loads,’ as each state defines such loads \n— should be allocated the costs of resources procured through the RBP.”5 The success, then, of \nthe RBP relies on the coordination of a multidimensional amalgam of state regulatory \ncommissions, legislatures, governors, local governments, and utilities across thirteen states and \nthe District of Columbia. Notwithstanding that Herculean challenge, PJM plans for the \nprocurement phase of the RBP to conclude less than six weeks from today’s comment date \n(specifically, within three weeks of September 30, 2026).6 In principle, NOVEC supports PJM’s \nefforts to quickly address its lack of capacity and the allocation of costs, as appropriate, directly \nto large loads but is concerned that the pace of the RBP process as PJM has proposed it will not \nafford NOVEC and others the necessary time for either RBP-obligation mitigation or completion \nof necessary regulatory proceedings to assign costs fairly and accurately to the cost-causing \ncustomers, to develop customer-level allocation rules, to make necessary modifications to billing \nand settlement processes, to address phased, delayed, reduced, or canceled load, and to \nimplement appropriate audit and control procedures for substantial obligations lasting up to 15 \n \n5 RBP Proposal at 11 (citing Statement of Principles Regarding PJM, National Energy Dominance Council, at 2 \n(Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm (“NEDC/PJM Governors’ \nPrinciples”)). \n6 RBP Proposal at 3, n.5 (“To the extent the RBP framework is accepted by September 29, 2026, and absent \nsignificant revisions or developments, PJM intends to open the procurement window on September 30, 2026.”); id., \nAttachment A at § 18.4 (“The Reliability Backstop Procurement offer submission window for RBP Sell Offers shall \nopen for three weeks in 2026.”)."},{"page":5,"startToken":1310,"endToken":1646,"text":"5 \n \nyears. NOVEC is a prime example of this conundrum because its nature, as a not-for-profit \nelectric cooperative, is to set up allocations before assuming obligations, but PJM is mandating \nthat it assume a large obligation that it has no way to opt out of. \n \nPJM’s timeline raises additional concerns that adversely affect the market. The success of \nthe RBP depends on generators offering in sufficient quantities and at competitive prices. With \nonly three weeks to make informed decisions based on the final, effective version of the RBP, \nsome participants may not be able to prepare offers in time to participate. Indeed, PJM has \nrequested FERC approval by September 29 so it can begin the RBP auction on September 30, \nwhich means that participants are expected to make decisions with impacts that last the better \npart of two decades in a span of a few weeks and without knowing what the actual rules or \napproved state regulator allocations will be. The companies with the wherewithal to prepare \noffers on an expedited basis and accept the uncertainty risk are likely to be staffed sufficiently to \ngamble on whatever the RBP might turn out to be without detracting from their established \nsources of revenue and have significant market share of PJM’s existing generation. From the \ncustomer’s perspective, there is a risk that a paucity of true competition will result in much of the \nRBP Resources receiving guaranteed payments at the cap of $555/MW-day when, if more time \nwere afforded, more participants might think through ways to offer at lower rates and still be \nprofitable. Not many developers will have proposed generation sitting on the shelf ready to \ndeploy into the RBP auction within such a short window. PJM’s expedited process thus risks \nunnecessarily increasing costs on the customers who will be supporting RBP Resources and \nundermines the purpose of the RBP. \n \nThe expedited process also effectively forecloses NOVEC’s ability to procure Qualifying \nRBP Offset UCAP MW. As PJM explains in the transmittal letter, Qualifying RBP Offset UCAP"},{"page":6,"startToken":1646,"endToken":1969,"text":"6 \n \nMW “is new capacity voluntarily brought on to the PJM system by new load… [and] [w]here \nElectric Distributors…report Qualifying RBP Offset UCAP MW to PJM with the requisite \nsupporting evidence, PJM may reduce the region-wide Initial RBP Target by the quantity of \nQualifying RBP Offset UCAP MW, where appropriate.”7 In addition to reducing the region-wide \nRBP Target, “the pro-rata allocation of RBP UCAP MW to each Electric Distributor’s zone/area, \nand the Final RBP Target, will be further adjusted to reflect reductions for Qualifying RBP \nOffset UCAP MW and UCAP MW representing successfully supported opt-outs from RBP in \neach zone/area.”8 Thus, RBP buyers can benefit in two ways from Qualifying Offset UCAP \nMW: by a reduction to the Initial Load Adjustment MW, and by reducing the Final RBP Target, \nthus reducing the pro-rata share of RBP UCAP MW from that Final RBP Target allocated to \neach Electric Distributor’s zone.  \n \nThe ability to procure Qualifying RBP Offset UCAP MW is important to managing RBP \ncosts for all RBP buyers, but particularly for NOVEC given the size of its obligation and the \nneed to address the appropriate allocation and recovery of these new and substantial RBP costs \nfrom the cost-causing data centers. Despite that importance, RBP buyers have only the imminent \nand brief RBP bid-submission window in which to procure new generation.9 Just as supply-side \nparticipants are likely to encounter difficulties preparing offers for the RBP, NOVEC and other \nbuyers will experience difficulty securing new generation by the third week of October. PJM’s \nproposed schedule provides RBP buyers an exceptionally limited period to identify and procure \nqualifying capacity. The result is an offset mechanism that may exist under the Tariff but cannot \nreasonably be utilized at the scale required. \n \n7 RBP Proposal at 35.  \n8 Id., Attachment C, Affidavit of Ms. Danielle Croop at P 44 (“Croop Affidavit”).  \n9 See RBP Proposal, Attachment A at § 18.2(c)."},{"page":7,"startToken":1969,"endToken":2261,"text":"7 \n \nNOVEC in particular is prejudiced because the Initial Load Adjustment MW that it \nwould need to offset to eliminate its obligation in the RBP auction is so high (1,619.2 MW) that \nNOVEC is unlikely to be able to secure bilateral contracts with new generators for anything \napproaching that amount. The only other Electric Distributor who exceeds NOVEC’s initial \nallocation is in a retail-choice state where the LSEs it serves take on the obligation.10 As a rural, \nnot-for-profit cooperative and a transmission-dependent distribution utility, NOVEC faces a \nprocurement challenge that is unusual both in magnitude and structure. A prudent procurement \nof more than 1,600 MW cannot reasonably be completed within the period PJM proposes. A \nprocurement of this magnitude would likely require multiple counterparties and transactions, \neach involving counterparty and credit diligence, commercial and risk analysis, contract \nnegotiations, internal approvals, and potentially regulatory review. A conventional physical \nbilateral capacity transaction may require approximately two to four months once qualifying \ncapacity has been identified, while more complex structured transactions, including power \npurchase agreements or tolling arrangements, may require four to twelve months or more to \nnegotiate. PJM’s proposed schedule does not provide a commercially reasonable opportunity to \nundertake those activities, particularly for an Electric Distributor seeking capacity on the scale \nrequired here. \nThe compressed procurement period is especially problematic because the universe of \nresources capable of qualifying as RBP offsets is itself constrained. The applicable qualification \nwindow limits the capacity that can serve as an offset, and PJM’s schedule provides no realistic \nopportunity to develop new generation specifically for that purpose. RBP buyers therefore are \nnot entering an unrestricted capacity market with sufficient time to develop alternatives. They are \n \n10 RBP Proposal, Attachment C, Croop Affidavit at P 46."},{"page":8,"startToken":2261,"endToken":2614,"text":"8 \n \ncompeting within a limited pool of qualifying resources under an unusually compressed \ndeadline. \nThe consequences of the compressed schedule extend beyond NOVEC. It is worth noting \nthat NOVEC will not be the only Electric Distributor harmed by the constraints on NOVEC’s \nability to assess and obtain Qualifying RBP Offset UCAP MW. In her affidavit, Ms. Croop \nwalks through an example that shows how one Electric Distributor obtaining Qualifying RBP \nOffset UCAP MW reduces the final allocation of RBP UCAP MW for all RBP buyers.11 That is, \nwhen one RBP buyers procures some Qualifying RBP Offset UCAP MW, that act also reduces \nthe final amount of RBP MW allocated to other RBP buyers as well.12 Thus, an Electric \nDistributor’s ability to obtain qualifying offsets affects the residual RBP allocation borne by \nother RBP buyers. PJM’s compressed timetable therefore does not merely impair an individual \nparticipant’s opportunity to mitigate its own costs. It can affect the ultimate allocation of RBP \nobligations across multiple participants.  \nNOVEC is also concerned that, given the limited timeframe to choose between \nparticipating in the RBP auction or signing a bilateral contract, the compressed schedule and \nlimited pool of qualifying resources may materially disadvantage RBP buyers in bilateral \nnegotiations. Potential counterparties will know that RBP buyers face a fixed and imminent \ndeadline to obtain qualifying capacity and that the alternative is exposure to an RBP allocation. \nThose circumstances reduce the ability of RBP buyers to solicit competing offers, develop \nalternative transaction structures, and negotiate from a commercially reasonable position, \n \n11 Id. PP 47-50. \n12 This is because, per the example in Croop’s affidavit, when an Electric Distributor procures generation to be \nQualifying RBP Offset UCAP MW, it reduces both the MW load adjustment column and the Final Allocation of \nRBP UCAP MW column such that all Electric Distributor areas are allocated fewer RBP MWs. In Croop’s example, \nODEC procuring 130 MW entitles them to 122.2 MW, but also reduces (in combination with REC’s 673.8 MW) \nNOVEC’s allocation to 1,271.6 MW from 1,302.6 MW. See id., Attachment C, Croop Affidavit at PP 47-50."},{"page":9,"startToken":2614,"endToken":2903,"text":"9 \n \npotentially resulting in higher bilateral prices or less favorable contractual terms. PJM cannot \nreasonably rely on Qualifying RBP Offset UCAP MW as a meaningful mechanism for \nmitigating RBP obligations while establishing a schedule that prevents affected Electric \nDistributors from having a commercially reasonable opportunity to use that mechanism. The \nproblem is particularly acute where, as here, PJM proposes to impose substantial long-term \nfinancial obligations based, in part, on whether an Electric Distributor succeeds in procuring \nqualifying offsets during this abbreviated period.  \nThe Commission should therefore reject PJM’s proposed implementation schedule or \nrequire PJM to provide RBP buyers sufficient time to conduct a commercially reasonable \nprocurement of Qualifying RBP Offset UCAP MW before their final RBP obligations are \nestablished. At a minimum, the schedule should provide no less than four months for \nconventional bilateral capacity transactions after the universe of qualifying resources and \napplicable offset requirements are sufficiently known, with additional time where structured \ntransactions are necessary. Without such an opportunity, the offset mechanism does not provide \na meaningful means of mitigating RBP exposure, and PJM’s resulting allocation may reflect the \nconstraints of its accelerated implementation schedule rather than the amount of capacity RBP \nbuyers reasonably could procure.  \nB. \nThe RBP violates the Commission’s cost-causation principle because it does not \nrecognize the structural causes of the capacity shortfall beyond load growth and \nimproperly assigns all RBP costs based only on projected load growth of large-load \ncustomers. \n \nSection 205 requires rates to be just and reasonable.13 That standard incorporates “a ‘cost-\ncausation principle’—the rates charged for electricity should reflect the costs of providing it.”14 \n \n13 16 U.S.C. § 824d(a).  \n14 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018)."},{"page":10,"startToken":2903,"endToken":3268,"text":"10 \n \nThe cost-causation principle “add[s] flesh to the[] bare statutory bones” of the just and \nreasonable standard.15 But while cost allocation is not a matter for the “slide-rule”16 and does not \nrequire “exacting precision,”17 the cost-causation principle does require the Commission to have \n“an articulable and plausible reason” to believe that the benefits are roughly commensurate with \nthe costs.18 A rate that assigns all the costs to a cause only partly responsible for the costs does \nnot satisfy the cost-causation principle because as a “kind of equity,” the principle matches \nburden with benefit.19 \n \nThe RBP violates the Commission’s cost-causation principle because it assigns the costs \nof the RBP Charge and the collateral requirements to one cause without recognition of other \nsignificant causes of the capacity shortfall, and because it results in an improper subsidy of \nPJM’s Reliability Pricing Model (“RPM”) auction by RBP buyers for the benefit of other Market \nParticipants that are not RBP buyers. \n \nThe RBP process is a one-time mechanism designed to address resource-adequacy \nchallenges arising from the capacity shortfall that occurred in the 2028/2029 Base Residual \nAuction (“BRA”).20 Ms. Croop explains that the “RBP will function as a safety net to address the \nshortfall MW from the 2028/2029 BRA that has not been addressed by new load bringing their \nown new capacity through bilateral agreements or otherwise.”21  \nThe RBP attributes the shortfall to load growth.22 PJM argues that, despite the addition of \n1,294.4 MW ICAP between the 2027/2028 and 2028/2029 BRA, the shortfall has grown.23 \n \n15 K N Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992).  \n16 United Distribution Cos. v. FERC, 88 F.3d 1105, 1167 (D.C. Cir. 1996). \n17 Coalition of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1017 (D.C. Cir. 2022). \n18 Illinois Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009). \n19 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).  \n20 RBP Proposal at 25-26.  \n21 Id., Attachment C, Croop Affidavit at P 5.  \n22 RBP Proposal at 6-7.  \n23 Id."},{"page":11,"startToken":3268,"endToken":3573,"text":"11 \n \nPJM’s proposed RBP cost-allocation mechanism assigns costs only to those Electric Distribution \nzones where load growth is forecasted, as measured by load adjustments between 2026 and \n2028.24 This allocation is particularly problematic because it remains fixed for the entire 15-year \nRBP commitment term. If forecasted large load is delayed, reduced, canceled, or never \nmaterialized, the RBP obligation assigned based on that forecast could remain with the Electric \nDistributor and ultimately be borne by its remaining retail customers. PJM has not adequately \nexplained how a fixed allocation continues to reflect cost causation when the load on which it \nwas based materially changes or fails to materialize. \n \nA central flaw of this paradigm is that the shortfall’s cause is not solely large-load \ncustomer growth. Even PJM recognizes that “it is well-documented and recognized that supply \nand demand in the PJM Region have converged, as a significant portion of PJM’s thermal \ngeneration fleet have retired while replacement resources are arriving at a slower pace….”25 PJM \nacknowledges that: “Together, these factors have strained the RPM Auction’s ability to procure \nsufficient capacity to meet the PJM Region Reliability Requirement in recent capacity \nauctions.”26 Thus, as PJM itself explains, the shortfall in the capacity market arose not only from \nlarge-load growth but also from a reduction in supply and the inability to bring new generation \nonline. \n \nThose retirements did not occur in a vacuum, nor did they occur suddenly. Many of them \nwere precipitated by the policies of states whose Electric Distributors will not be bearing costs \nassociated with the RBP as PJM has proposed it. The reduction in supply is a PJM-wide \nphenomenon that PJM had been warning stakeholders and the Commission about long before the \n \n24 RBP Proposal, Attachment C, Croop Affidavit at PP 41, 43.  \n25 RBP Proposal at 28.  \n26 Id. (emphasis added)."},{"page":12,"startToken":3573,"endToken":3920,"text":"12 \n \nunexpected surge in load growth. As early as PJM’s February 24, 2023, report Energy Transition \nin PJM: Resource Retirements, Replacements & Risks, PJM noted that significant amounts of \ngeneration had retired and was slated to retire.27 Between 2012 and 2022, 47.2 GW ICAP \nretired.28 Figure 1 of the 4R Report highlights that PJM was projecting 40 GW of retirements by \n2030, composed of “12 GW of announced retirements, 25 GW of potential policy-driven \nretirements and 3 GW of potential economic retirements. Combined, this represents 21% of \nPJM’s current installed capacity.”29 The Independent Market Monitor for PJM echoed those \nconcerns in its 2023 State of the Market Report for PJM, commenting that “an estimated total of \nbetween 24,000 MW and 58,000 MW of thermal resources are at risk of retirement, including \n4,285 MW of announced retirements, 19,635 MW of retirements as a result of state and federal \nenvironmental regulations, and 33,744 MW of retirements for economic reasons, based on \nexpected forward prices.”30 So PJM’s recognition 1,294.4 MW ICAP added between the \n2027/2028 and 2028/2029 BRA fails to also recognize the removal of 47,200 MW ICAP over a \nlittle more than the past decade. \n \nThe renewables that replaced the retiring thermal generation could replace the energy, but \nnot the capacity, and the interconnection queue could not proceed efficiently enough to bring \nnew generation online.31 The shortfall is, to a significant degree, as much the product of state \npolicy choices as it is large-load growth. As Commissioner Christie articulated in the \ntransmission context: \n \n27 Energy Transition in PJM: Resource Retirements, Replacements & Risks at 6-7 (dated Feb. 24, 2023) (Available \nat: https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2023/energy-transition-in-pjm-\nresource-retirements-replacements-and-risks.ashx) (“4R Report”). \n28 Id. at 6.  \n29 Id. at 5 (internal citations omitted). \n30 IMM, 2023 State of the Market Report for PJM Volume I at 1 (March 14, 2024) \n(https://www.monitoringanalytics.com/reports/pjm_state_of_the_market/2023.shtml) (“2023 State of the Market”). \n31 Id. at 2."},{"page":13,"startToken":3920,"endToken":4332,"text":"13 \n \nLet me emphasize that the State of Maryland, within its sovereign police \npowers, clearly has the authority to mandate any particular mix of \ngenerating resources it prefers. Maryland's new climate law is well within \nits inherent authority to enact. Such policies are for Marylanders to choose, \nnot RTOs or FERC. But if the resulting transmission projects under protest \nin this RTEP filing are caused more by Maryland's policy choices than by \norganic load growth and economic resource retirements, then a salient \nquestion that may be asked is whether these transmission projects are more \naccurately categorized as public policy projects, essentially the same as the \ntransmission upgrades caused by New Jersey's offshore wind projects? \n \nAnd if they are more accurately categorized as public policy projects, \nshould such projects be regionally cost-allocated, potentially to consumers \nin Pennsylvania, West Virginia, Ohio, et al.? For example, the State of \nIllinois has a law similar to Maryland's that PJM has already estimated will \ncause $2 billion in transmission upgrades, costs that will be allocated to \nconsumers in other states under PJM's existing cost-allocation formula.32 \n \nIt is an equally salient question as to how the RBP is just and reasonable when it attributes, \ncontrary to even PJM’s admission, all the costs associated with the shortfall to large-load growth \nduring a PJM-wide phenomenon of supply constriction. \n \nThe RBP is not just and reasonable because it does not match cost and causation. Large-\nload growth is a cause, certainly, but not the only cause. The truth is that causation also is \nattributable to the diffuse effect of state environmental policies and the interconnection queue. \nThe fact that the problem ballooned to this extent is because of the fundamental dysfunction of \nthe PJM RPM, which has been unable to respond effectively to either an increase in demand or a \ndecrease in supply. Although characterized as a reaction to load growth, the RBP is, in reality, \nanother iteration of the “perpetual tweaking”33 needed to keep the PJM RPM wheezing along, in \nthe same tradition as the Minimum Offer Price Rule34 and the price collar.35 \n \n32 PJM Interconnection, L.L.C., 185 FERC ¶ 61,107, PP 7-8 (2023) (Christie, Comm’r, concurring). \n33 Mark C. Christie, It’s Time to Reconsider Single-Clearing Price Mechanisms in U.S. Energy Markets, 44 Energy \nL.J. 1, 26 (2023).  \n34 Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC ¶ 61,236 (2018). \n35 PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 (2025)."},{"page":14,"startToken":4332,"endToken":4639,"text":"14 \n \n \nPJM has acknowledged that the RPM is ill-suited for it purpose, and indeed has not \nallowed the RPM to work as it’s designed. Rather than allow the RPM to clear at a price \nintended to spur the entry of new generation, PJM entered a settlement agreement to “cap [] \npower plant capacity prices.”36 Mr. Mosier is correct that suppressing the market signals to enter \nthe market undermines investor confidence in the markets – “credibility trap” is PJM’s phrase for \nit.37 There is also likely merit to his assertion that “the ability to obtain 15-year price certainty in \na backstop procurement likely chilled new entry in PJM’s most recent capacity auction.”38 \nNOVEC should also point out that there is a mechanism in the PJM RPM -- the Reliability \nBackstop Auction -- specifically to address consecutive capacity shortfalls which PJM is also \npreempting in favor of yet another temporary “fix.”39 \n \nIf NOVEC (or others) cannot assign these costs directly to large loads, then the results \nshould be viewed through the lens of whether the actual cost allocation is just and reasonable, \nand not whether a hypothetical allocation occurred. Viewed through that lens, the proposal does \nnot satisfy the cost-causation principle because it does not match even one iota of the burden of \nthe shortfall to the rest of PJM, notwithstanding the policy-driven retirements of generation that \ncontributed to the shortfall. Unless the Commission revises the effective date or PJM voluntarily \nagrees to, the Commission should reject the RBP as a violation of the cost-causation principle. \n \n36 EKPC Letter at 2.  \n37 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and \nStimulating Investment to Support Durable Reliability at 5-6 (May 6, 2026) (https://www.pjm.com/-\n/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-\ndesign.pdf).  \n38 EKPC Letter at 2.  \n39 RBP Proposal at 123-125."},{"page":15,"startToken":4639,"endToken":4954,"text":"15 \n \nC. \nThe RBP improperly concentrates the incremental costs of RBP Resources on RBP \nbuyers while allowing the resulting capacity-market benefits to accrue more \nbroadly. \nPJM’s proposed RBP framework does not adequately account for the market-wide benefits \nthat RBP Resources may provide. RBP buyers would bear the incremental RBP Charges and \nassociated credit obligations attributable to the RBP Resources allocated to them. Yet those \nresources would participate in the same RPM Auctions that establish capacity prices paid by load \nthroughout the relevant capacity market. To the extent RBP Resources increase available supply \nand reduce RPM clearing prices, those benefits are not confined to the LSEs assigned RBP cost \nresponsibility. They accrue to other capacity purchasers as well. \nThe RBP framework requires RBP Resources to offer their committed capacity into the \nRPM Auctions as price takers at $0. PJM explains that this requirement is appropriate because the \nRBP Resources are already being paid for by the responsible LSEs and because it ensures that an \nRBP Resource clears the RPM Auction, thereby avoiding the potential for load to pay twice for \nthe same capacity. NOVEC does not dispute the objective of preventing duplicative payment \nobligations, but PJM’s solution has an important cost-allocation consequence that its proposal does \nnot adequately address requiring RBP-supported capacity to offer at $0 can affect RPM clearing \noutcomes for market participants that bear no corresponding share of the incremental RBP costs. \nThe significance of that requirement follows from the operation of RPM. Adding RBP \nResources at a mandatory $0 offer increases the quantity of capacity offered at the bottom of the \nsupply curve. Depending on market conditions, locational constraints, and the position of the \nmarginal resource, those offers can reduce the RPM clearing price that otherwise would have \nresulted. Where that occurs, the resulting reduction in capacity prices benefits capacity purchasers \ngenerally, not merely the RBP buyers that financially support the RBP Resources."},{"page":16,"startToken":4954,"endToken":5230,"text":"16 \n \nThe incremental financial obligations associated with those resources, however, remain \nconcentrated on the LSEs assigned RBP cost responsibility. Those LSEs must fund applicable \nRBP Charges and support those obligations through PJM’s proposed collateral requirements, while \nother market participants may receive lower capacity prices resulting from the same resources \nwithout bearing a corresponding share of those incremental costs. \nThe RBP’s contract-for-differences settlement structure compounds this mismatch. RBP \nResources receive RPM revenues that offset their RBP commitment payments. If the mandatory \n$0 offers of RBP Resources contribute to a lower RPM clearing price, those resources receive less \nRPM revenue and the corresponding RBP settlement obligation increases. RBP buyers therefore \nmay bear a larger RBP Charge at the same time that the lower RPM price produces savings for \ncapacity purchasers more broadly. In that circumstance, the same market effect that benefits non-\nRBP buyers increases the incremental obligation imposed on RBP buyers. \nThis allocation raises concerns under the Commission’s cost-causation principles. \nAlthough cost allocation need not correspond precisely to benefits received, the Commission has \nrequired costs to bear a reasonable relationship to the burdens imposed and benefits received and \nhas recognized that substantial departures from that principle can create inappropriate cross-\nsubsidization. PJM has not adequately demonstrated why the incremental costs and substantial \ncredit obligations associated with RBP Resources should be concentrated on designated RBP \nbuyers without accounting for material capacity-market benefits those resources may provide to \nother PJM load. \nAt a minimum, the Commission should require PJM to demonstrate that its proposed \nallocation of RBP costs is roughly commensurate with the benefits attributable to the RBP \nResources. If PJM’s mandatory $0 offer requirement produces material market-wide capacity-"},{"page":17,"startToken":5230,"endToken":5602,"text":"17 \n \nprice benefits, PJM should explain why those benefits do not warrant broader allocation of at least \nsome portion of the incremental RBP costs or another mechanism that recognizes the value \nreceived by non-RBP buyers. \nThe potential effect of such offers on RPM clearing prices is not merely theoretical. In \nconsidering the operation of PJM’s capacity market in another context, the Third Circuit \nrecognized that artificially low capacity offers can “crowd out other capacity that is priced at a \nhigher, cost-based rate” and thereby produce a lower clearing price.40 NOVEC does not contend \nthat RBP Resources are similarly situated to the state-supported resources at issue in New Jersey \nBPU. The relevant point is narrower: PJM’s requirement that RBP Resources offer at $0 can affect \nthe RPM clearing price, and any resulting price reduction benefits capacity purchasers beyond the \nLSEs required to bear the incremental costs of supporting those resources. \nD. \nThe RBP framework is not just and reasonable because it requires too many MW to \noffset the RBP Target and encourages free riding.  \n \nThe RBP framework is unjust and unreasonable because the Qualifying RBP Offset \nUCAP MW to offset each Electric Distributor’s zone is too high relative to their pro rata share \nof the Initial RBP Target. The initial allocation of the RBP UCAP MW is based on each Electric \nDistributor’s zone’s share of the Initial RBP Target of 6,831.3 MW.41 NOVEC, for example, is \nassigned 1,302.6 MW.42 Even though NOVEC’s “share” of the shortfall is 1,302.6 MW, PJM’s \nproposal would require NOVEC to procure approximately 1,619 MW to fully offset 1,302.6 \nMW.43 If the Initial RBP Target of 6,831.3 MW is the goal to offset, it is unjust and unreasonable \nto force RBP buyers to procure an excess of that target MW amount. The excess MW provide \n \n40 New Jersey Board of Public Utilities v. FERC, 744 F.3d 74, 85 (3d Cir. 2014). \n41 RBP Proposal, Attachment C, Croop Affidavit at P 46.  \n42 Id. \n43 Id. P 47 (“Note: The qualifying RBP Offset UCAP MW is represented by load*FPR for the 2028/2029 BRA \n(0.9401). This is representative of the self-supply obligation.”)."},{"page":18,"startToken":5602,"endToken":5988,"text":"18 \n \nadditional value to the PJM capacity market for which the RBP buyer is not compensated. \nSimilarly, the RBP reduces other buyers’ obligations when a single buyer procures Qualifying \nRBP Offset UCAP MW, which creates a perverse incentive for buyers willing to risk assignment \nof the RBP Charges to do nothing with the hope that other RBP buyers enter bilateral \narrangements and reduce the Final RBP Target.  \nE. \nThe RBP is not just and reasonable because it relies on load forecasts that were \nprepared without knowledge or consideration of PJM’s newly proposed RBP \nparadigm. \n \nThe RBP is intended to address the shortfall that occurred in the 2028/2029 BRA, but it \nassigns responsibility to that shortfall using the load adjustments from 2026 to 2028 submitted by \nLSEs. NOVEC has reservations about the use of the load adjustments “to ultimately determine \nthe initial allocated pro-rata share to each relevant Electric Distributor zone/area.”44 PJM has not \nexplained why this snapshot in time is appropriate beyond references to Schedule 8 of the RAA, \nwhich does not suffice.45 The load adjustments set forth in PJM Table B9b from the 2026 PJM \nLoad Forecast are something of a black box.46  \n \nThe problem with relying on the load adjustments is, even if they are “firm,” all the load \nindicated interest based on economic circumstances that no longer exist.47 The RBP will raise \ncosts of data center loads, which will either prompt marginal data center projects to withdraw or \ncause data centers to relocate to areas that are not assessed RBP Charges so that they can avoid \nthese additional costs. If loads had known about the RBP, their plans would be different, they \n \n44 RBP Proposal, Attachment C, Croop Affidavit at P 43.  \n45 Id.  \n46 2026 PJM Load Forecast Report Data Tables, PJM Interconnection, L.L.C., Tab Table B9b (Feb. 2026), \nhttps://www.pjm.com/-/media/DotCom/planning/res-adeq/load-forecast/2026-load-report-tables.xlsx \n[https://perma.cc/SST2-EGUZ]; 2026 PJM Load Forecast Report, PJM Interconnection, L.L.C., 5-6 (Jan. 14, 2026), \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf \n[https://perma.cc/J24E-7CV7] (describing Table B9b results). \n47 See Coscia Affidavit at P 22 (explaining that no participant in the load forecast process knew that the figures \nwould be used in an RBP process)."},{"page":19,"startToken":5988,"endToken":6342,"text":"19 \n \nwould have made different representations to their LSEs, and the load adjustments would be \ndifferent. As a consequence of the increased costs, PJM will reduce the actual load that \nmaterializes. In order to account for this effect, the Commission should either reject the filing or \nreduce the amount of RBP MWs that are allocated to NOVEC and other RBP buyers.  \nF. \nThe RBP’s collateral requirements on RBP buyers are unjust and unreasonable \nbecause it is unduly burdensome, excessive, and has not been shown to be necessary. \n \nPJM “is proposing to require that those LSEs allocated RBP cost responsibility for a \ngiven Delivery Year must post credit associated with such obligation.”48 PJM argues that this \ncredit obligation is just and reasonable because “it is designed [to prevent] those LSEs not \nallocated cost responsibility for RBP Resources from having to pay for such resources” \nnotwithstanding the benefit those LSEs derive from the new generation themselves.49 The RBP \ncredit requirement “is a function of two inputs: the RBP Credit Rate and RBP UCAP MW \ncommitted.”50 The RBP UCAP MW input is the total amount of RBP UCAP MW committed \nthrough the RBP, as adjusted for resources that do not come online.51 \n \nPJM is proposing to set the RBP Credit Rate at $1.5 million per MW initially, but it can \nbe reduced to reflect a reduction in the total RBP UCAP MW or when total posted RBP \nCollateral exceeds the total RBP Charges obligation.52 PJM states that it set the credit rate at $1.5 \nmillion based on an estimate of “the contractual value associated with a 1-MW RBP commitment \nusing conservative assumptions, including a 15-year commitment term application of the RBP \nprice throughout that commitment period.”53 Assuming the RBP clearing price is at the price cap \nof $555/MW-day, PJM estimated the contractual value of a 1-MW RBP commitment at $3.04 \n \n48 RBP Proposal at 114.  \n49 Id. at 114 (emphasis in original).  \n50 Id. at 115.  \n51 Id. at 115-116.  \n52 Id. at 116.  \n53 Id., Attachment D, Affidavit of Ms. Gwen Kellyat P 25 (“Kelly Affidavit”)."},{"page":20,"startToken":6342,"endToken":6681,"text":"20 \n \nmillion.54 PJM then reduced the $3.04 million to $1.5 million so that PJM would hold “sufficient \ncollateral to cover approximately 50% of the notional value of all RBP commitments….”55 \n \nAs set forth in Mr. Rollins’ affidavit, NOVEC estimates that its collateral requirement \nunder PJM’s proposed regime would be approximately $1.95 billion.56 The collateral \nrequirement is an extraordinary imposition on NOVEC. Indeed, the collateral requirement \nexceeds NOVEC’s total assets.57 NOVEC is uncertain whether it would even be able to secure \n$2 billion in collateral.58 As Mr. Rollins explains, the collateral requirement will disrupt \nNOVEC’s ordinary business operations.59 The Commission should not approve a collateral \nrequirement that is an impossibility, a hindrance to an entity’s ability to operate, and an injustice. \n \nThe need to reject or modify the collateral obligation is heightened by the calculation’s \nobvious defects. PJM “conservatively” requires the collateral obligation of the buyers to span the \nentire 15-year period.60 This expansive requirement simply is not necessary, as the risk could be \nsignificantly mitigated by a shorter period, such as three years. As Mr. Rollins discusses, the \nmost significant obstacle to NOVEC fulfilling its RBP obligations is, ironically, the size of the \nRBP collateral obligation itself and not the RBP Charges.61 Indeed, PJM does not believe that a \n15-year collateral obligation on sellers is appropriate, noting that it limited the sellers’ collateral \nobligation to three years to avoid making the collateral requirement “onerous.”62 NOVEC does \nnot see why it is just and reasonable for buyers to suffer under what even PJM deems an \n \n54 Id. P 25. \n55 RBP Proposal at 116.  \n56 Rollins Affidavit at 2.  \n57 Id. at 3; see also Coscia Affidavit at PP 13, 58-61. \n58 Rollins Affidavit at 3. \n59 Id. at 3-4. \n60 See Coscia Affidavit at PP 48-50; id. P 51 (“The observation that matters is that the filed requirement exceeds the \nexposure at every path in the range.”). \n61 See generally Rollins Affidavit.  \n62 RBP Proposal at 109-110."},{"page":21,"startToken":6681,"endToken":7138,"text":"21 \n \n“onerous” requirement while sellers are limited to a three-year period – as if the potential \nimpossibility of a $2-billion collateral obligation was not onerous enough.  \n \nMs. Kelly states in her affidavit for PJM that the collateral requirement assumes that the \nRBP clearing price is at the price cap of $555/MW-day,63 and PJM sets forth the calculation as \nan “application of a simple formula based on the RBP Charge obligation over 15 years, i.e., the \ncommitment term, and a conservative assumption that all RBP commitments are — on average \n— at the maximum willingness to pay, i.e.,15 years * 365 days * $555/MW-Day = \n$3,038,625.”64 There are two problems with this calculation. First, it assumes that the clearing \nprices of the RBP are $555/MW-day, which is not guaranteed — if the price clears lower than \nthat, the proposed Tariff revisions still fix the RBP Credit Rate at $1.5 million, even though \nPJM’s own methodology could support a lower price.65  \n \nSecond, the calculation assumes that the RBP buyers have to collateralize the entire \n$555/MW-day. In actuality, the RBP Charges will be the RBP clearing-price average (which can \nbe less than $555/MW-day) net of revenues from the capacity auction.66 Effectively, RBP buyers \nare providing collateral to ensure that everyone in PJM pays the capacity costs associated with \nthe RBP Resources. RBP buyers themselves already provide PJM collateral to ensure that they \npay their capacity rates under Attachment Q, and so do all other capacity buyers.67 PJM is \n \n63 Id., Attachment D, Kelly Affidavit at P 25. \n64 RBP Proposal at 116-117; see also Coscia Affidavit at P 39.  \n65 Coscia Affidavit at P 38 (“The RBP settles as a contract for differences. In each Delivery Year the cooperative \npays the difference between the RBP price and the RPM clearing price for that year, multiplied by its allocated RBP \nUCAP MW. It does not pay the RBP price. Where RPM clears above the RBP price the payment runs in the \nopposite direction.”); id. P 46 (“If the RBP clears below $555.00 the exposure falls and the ratio of collateral to \nexposure rises, so this assumption is conservative against the conclusion I reach.”).  \n66 Id. P 40 (“Because the Credit Rate makes no reference to RPM, the requirement bears no stable relationship to \nwhat the cooperative will owe. Where RPM clears close to the RBP price the difference approaches zero while the \ncollateral does not move. Where RPM clears far below it the difference widens and the collateral is unchanged \nagain. A requirement calibrated to exposure would vary with the second price; this one is fixed against the first.”). \n67 Id. P 26 (noting that PJM already holds collateral from NOVEC)."},{"page":22,"startToken":7138,"endToken":7522,"text":"22 \n \nrequiring duplicative collateral — at the most, RBP buyers should only have to provide collateral \nfor the incremental cost of the RBP clearing price above the weighted RPM clearing price for the \nrelevant delivery year. That is the only cost that RBP buyers will actually have to pay, and thus \nthe only payments that need to be collateralized.68  \n \nIt is unnecessary to require that 50% of the total payments be held as collateral. Although \nPJM contends that this provides “commensurate” protection against non-payment,69 NOVEC has \ndemonstrated that the actual RBP Charges will be less than $555/MW-day. The total amount \nheld as collateral could exceed the ultimate payments made by the RBP buyers.70 The collateral \namount should not exceed a level that is commensurate with actual RBP obligations. PJM asserts \nthat to test the reasonableness of the $1.5 million per MW figure, PJM used a 9.5% discount rate \ndeveloped by consultants from The Brattle Group based on the average weighted cost of capital \nfor participants in the RPM.71 PJM’s reliance on calculations from a Brattle report does not \nsubstantiate PJM’s assertion that its figure is just and reasonable. For one, it was developed for \nanother purpose and does not necessarily translate to a risk of non-payment. The figure is \ndesigned for ordinary generators, not generators who will have a guaranteed revenue stream for \n15 years. Those generators face much lower risk and do not need as high a return. \n \nThe Tariff is ambiguous as to when the collateral obligation will be reduced and does not \nappear to properly reduce it over time. Ms. Kelly states that “PJM concluded that the remaining \npayment exposure naturally declines as remaining, forward RBP payment obligations are \nsatisfied and as committed RBP Resources are removed from the portfolio through rescinded \n \n68 Id. P 41 (“A collateral requirement is ordinarily derived from an identified position, a price at which that position \nwould be replaced, and a period over which the exposure is held before replacement is complete.”). \n69 RBP Proposal, Attachment D, Kelly Affidavit at P 24.  \n70 Indeed, Mr. Coscia shows that the collateral could be as much as 9 times the amount of exposure it is securing. \nCoscia Affidavit at P 49.  \n71 RBP Proposal, Attachment D, Kelly Affidavit at PP 27-28."},{"page":23,"startToken":7522,"endToken":7845,"text":"23 \n \ncommitments or other changes affecting the remaining payment obligations.”72 PJM is vague \nabout whether such reductions will occur — Ms. Kelly testifies that PJM’s Tariff provision \n“permit[s]” reductions to the RBP credit rate when “changes in the underlying RBP commitment \nportfolio demonstrate that previously required collateral exceeds the remaining expected \npayment exposure.”73 According to the proposed Tariff, “the RBP Credit Rate shall equal $1.5 \nmillion, as may be reduced, for reasons including a change in the total committed RBP UCAP \nMW, when total posted RBP Collateral is greater than the total remaining RBP Charges \nobligations, over time by the Office of the Interconnection to an amount sufficient to cover the \ntotal existing RBP Charges obligations….”74 It is not just and reasonable to grant PJM the \ndiscretion to determine whether RBP buyers should be required to post more collateral than the \ntotal existing RBP Charges obligations, especially given that their calculation already overstates \nthe likely RBP Charges.  \n \nThe circumstances in which the collateral obligation is reduced are too few. The RBP \nCredit Rate should be reduced to account for the remaining term over which RBP Charges will \nbe paid. If 50% of the total RBP Charges is the standard (and it should be lower for the reasons \ndiscussed in prior paragraphs), then it should be 50% or less of the remaining RBP Charges in \neach year. If PJM believes that 50% of the total payment obligations at the start of the 15-year \nterm is sufficient, then the same percentage of the total remaining payment obligations should be \nthe cap for each year.  \n \nIf the Commission does not reject the filing, then it should require revisions on \ncompliance to reduce the collateral obligation so that it corresponds to the actual risk imposed on \n \n72 RBP Proposal, Attachment D, Kelly Affidavit at P 29.  \n73 Id. P 30.  \n74 RBP Proposal, Attachment A at § 18.8(b)(i)(A) (emphasis added)."},{"page":24,"startToken":7845,"endToken":8144,"text":"24 \n \nPJM’s markets. The Commission should require PJM to allow other methods to demonstrate \ncreditworthiness besides posting the full collateral or a letter of credit. NOVEC maintains an \ninvestment-grade credit rating and has met its obligations to PJM. Given NOVEC’s investment-\ngrade credit rating, financial condition, and established record of satisfying its PJM obligations, \nPJM should permit NOVEC to satisfy all or a substantial portion of the requirement through \nunsecured credit or another demonstration of creditworthiness rather than requiring cash \ncollateral or a letter of credit for the full notional amount. If the Commission does not allow \nalternative demonstrations of creditworthiness, the Commission should correct PJM’s defective \ncollateral calculations. The Commission should require the collateral calculation to reflect the \nactual clearing price of the RBP auction. Instead of providing for an “onerous” 15-year term, the \nCommission should limit the period collateralized to three years, just as PJM proposes to do for \ngenerators. Additionally, the Commission should also limit the collateral amount to the expected \nincremental amount between the RBP clearing price and the expected capacity-market revenue to \navoid duplicative collateral requirements. \nIII. \nSTAKEHOLDER PROCESS \n \nRather than attempt to salvage the RBP Proposal, the Commission should exercise its \nauthority under NRG to implement the voluntary subscription model the stakeholders approved \nas part of the CIFP process. PJM’s CIFP process is intended to expedite resolution of issues \ncritical to PJM. As such, while decisions from it are ultimately the Board’s to make, PJM \nmembers and other stakeholders play a key advisory role by signaling solutions they agree with \nthrough a four-stage proposal-development and voting process. Indeed, members have been \ncriticized in past iterations of the CIFP for not coming to clear consensus. Members sent the \nBoard a clear message in this CIFP by supporting one proposal from more than a dozen"},{"page":25,"startToken":8144,"endToken":8450,"text":"25 \n \nconsidered. That proposal included an interconnected package of reforms that were carefully \nbalanced to address the issue while maintaining mitigation options for LSEs, all headlined by a \nversion of the RBP auction that would have required LSEs to “subscribe” to obligations, i.e. they \nhad control to mitigate their forecasted growth by committing to curtail it instead of accepting a \ncapacity obligation and resulting costs. NOVEC supported that proposal and still does. \n \nThe Board clearly appreciated members’ message by adopting portions of the proposal \nthat it found favorable but rejecting those it did not, including the key tool for LSEs to mitigate \ntheir potential obligations in the auction: the subscription-based auction. By pulling out that \ncomponent of the proposal, PJM effectively stripped LSEs of their control over accepting RBP \nobligations. In NOVEC’s view, that control was critical to the success of the RBP process, which \nshould embody a bottom-up, rather than a top-down approach. The bottom-up process gives truly \ninterested developers the option to subscribe to pay the RBP costs rather than accept an \ninterruptible form of service which PJM has proposed in Docket No. ER26-3515 (the Interim \nResource Adequacy Service or “IRAS”). Contrary to the PJM Board’s determination, the \nvoluntary subscription framework would provide sufficient assurance that capacity equal to the \nidentified near-term shortfall would actually be procured.75 Paired with IRAS, committed load is \nadequately incentivized to participate to avoid an interruptible service—their business models \nrely on reliable service. \n \nAlthough NOVEC rejects the premise that the voluntary subscription process would fail, \neven if it procured less than the total shortfall, that should not be considered a failure when \nconsidered in the context of the package of reforms the stakeholders proposed. The IRAS \neffectively mitigates any reliability harm, and if load prefers to avoid IRAS through bringing its \n \n75 RBP Proposal at 21."},{"page":26,"startToken":8450,"endToken":8737,"text":"26 \n \nown generation rather than participating in the RBP, it makes sense to allow that option. Either \nway, PJM obtains the generation it needs, and the large load is better situated to make that \ndetermination. More to the point, the subscription process avoids many of the issues discussed \nabove because it allows LSEs to make arrangements directly with willing participants. FERC \nshould order PJM to revise its RBP auction structure to be subscription-based with the load \ngrowth that is not subscribed being subject to curtailment by default, as contemplated by the \nstakeholder proposal. \nIV. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the \nCommission reject the RBP Filing. If the Commission does not reject the filing, it should accept \nPJM’s invitation76 to require changes to the RBP to rectify the mistakes discussed above, \nincluding extending the effective date to allow for the RBP to have a chance of success, revising \nthe cost-allocation structure to recognize the benefits derived from RBP Resources by non-RBP \nbuyers, adjusting the amount of MW needed to offset RBP cost responsibility, shifting the \nauction to a subscription-based model, and reducing the collateral requirements as discussed \nabove. At a minimum, the Commission should issue a deficiency letter and require PJM to better \nexplain both its rejection of the coalition proposal and the as-filed RBP’s design. \n \n \n \n76 Id. at 3 (“…PJM provides notice that it consents to the Commission’s exercise of authority to modify and/or sever \nany element of the proposed Tariff and RAA language to the extent necessary and permitted under section 205 of \nthe FPA and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent with \nPJM’s overarching objectives in this filing.”) (internal citation omitted)."},{"page":27,"startToken":8737,"endToken":8793,"text":"27 \n \n \nRespectfully submitted, \n \n  //s// Alan I. Robbins \n \nAlan I. Robbins \nDebra D. Roby \nThomas B. Steiger III \nWashington Energy Law LLP \n900 17th Street. N.W., Suite 500-A  \nWashington, D.C. 20006 \nTel: (202) 326-9313 \nEmail: arobbins@washingtonenergylaw.com \ndroby@washingtonenergylaw.com \ntsteiger@washingtonenergylaw.com \n \nCounsel to Northern Virginia Electric Cooperative, Inc. \n \n \n \n \nDated: August 21, 2026."},{"page":28,"startToken":8793,"endToken":8871,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Federal Energy \nRegulatory Commission in this proceeding. \nDated at Washington, D.C. this 21st day of August, 2026. \n \n  //s// Jessika Dziechciowska  \nJessika Dziechciowska \nEnergy Practice Analyst \nWashington Energy Law LLP \n900 17th Street, N.W., Suite 500-A \nWashington, D.C. 20006 \nTel: (202) 326-9308  \nEmail: jdziechciowska@washingtonenergylaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1312,"startToken":0,"endToken":191},{"p":1,"at":1312,"title":"I. INTRODUCTION","method":"printed heading","endPage":4,"endAt":5,"startToken":191,"endToken":939},{"p":4,"at":5,"title":"II. PROTEST","method":"printed heading","endPage":4,"endAt":19,"startToken":939,"endToken":941},{"p":4,"at":19,"title":"A. There is a material mismatch in the timing required by PJM’s proposed RBP","method":"printed heading","endPage":9,"endAt":1453,"startToken":941,"endToken":2812},{"p":9,"at":1453,"title":"B. The RBP violates the Commission’s cost-causation principle because it does not","method":"printed heading","endPage":15,"endAt":6,"startToken":2812,"endToken":4640},{"p":15,"at":6,"title":"C. The RBP improperly concentrates the incremental costs of RBP Resources on RBP","method":"printed heading","endPage":17,"endAt":973,"startToken":4640,"endToken":5380},{"p":17,"at":973,"title":"D. The RBP framework is not just and reasonable because it requires too many MW to","method":"printed heading","endPage":18,"endAt":417,"startToken":5380,"endToken":5669},{"p":18,"at":417,"title":"E. The RBP is not just and reasonable because it relies on load forecasts that were","method":"printed heading","endPage":19,"endAt":371,"startToken":5669,"endToken":6049},{"p":19,"at":371,"title":"F. The RBP’s collateral requirements on RBP buyers are unjust and unreasonable","method":"printed heading","endPage":24,"endAt":1290,"startToken":6049,"endToken":8026},{"p":24,"at":1290,"title":"III. STAKEHOLDER PROCESS","method":"printed heading","endPage":26,"endAt":597,"startToken":8026,"endToken":8543},{"p":26,"at":597,"title":"IV. CONCLUSION","method":"printed heading","endPage":28,"endAt":0,"startToken":8543,"endToken":8793},{"p":28,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":28,"endAt":536,"startToken":8793,"endToken":8871}]}