{"document":{"slug":"rec-20260821-5313","title":"Motion to Intervene and Request for Clarification, or in the Alternative, Limited Protest of Tract Holding Company I, LLC re PJM Interconnection, L.L.C.’s…","issued":"2026-08-21","accession":"20260821-5313","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Tract Holding Company I, LLC","kind":"protest","file":"sources/filings/text/20260821-5313_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5313","tier":"record","sha256":"268ea02e5deadf2772640a05fe017f3ca86e74748fb4c26d45a6100016ae230f","pages":12,"tokens":3458,"emptyPages":[],"textThemes":["flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":323,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3380-000 \nMOTION TO INTERVENE AND REQUEST FOR CLARIFICATION,  \nOR IN THE ALTERNATIVE, LIMITED PROTEST OF  \nTRACT HOLDING COMPANY I, LLC \nPursuant to Rules 211, 212, and 214 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”),1 Tract Holding Company I, LLC \n(“Tract”) hereby submits this motion to intervene and request for clarification of, or in the \nalternative, limited protest to, PJM Interconnection, L.L.C.’s (“PJM”) proposed Reliability \nBackstop Procurement (“RBP”) framework, filed in the above-captioned proceeding on July 31, \n2026,2 pursuant to Section 205 of the Federal Power Act (“FPA”).3 \nFor the reasons set forth below, Tract respectfully requests that PJM clarify the scope of \n“executed electric service agreement[s] or transmission service agreement[s]” that new load may \npresent as evidence of Qualifying RBP Offset UCAP MW.4 Absent such clarification, the \nCommission should find that PJM has failed to satisfy its burden under Section 205 of the FPA \nand should sever and reject the relevant portion of PJM’s proposed tariff revisions as unduly \ndiscriminatory or preferential, and direct modifications consistent with the Commission’s \nauthority under NRG Power Marketing, LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017).5 \n \n1 18 C.F.R. §§ 385.211, 385.212, 385.214. \n2 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (“PJM RBP Filing”). \n3 16 U.S.C. § 824d. \n4 PJM RBP Filing at 39-40; Proposed PJM Tariff, Attachment DD, §§ 18.2(c)(i)-(iii). \n5 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017). Whereas here, PJM has consented to any \nmodifications to the RBP filing, the D.C. Circuit “has held that . . . the Commission has ‘authority to propose"},{"page":2,"startToken":323,"endToken":606,"text":"2 \n \nI. \nMOTION TO INTERVENE \nTract respectfully moves to intervene in this proceeding.6 Tract, through its affiliates, \nacquires land and develops shovel-ready development sites for data centers in the PJM region—\npre-positioning power, fiber, zoning and entitlements, and will be directly subject to PJM’s RBP \nprocess should the Commission accept PJM’s filing. Tract therefore has a substantial and direct \ninterest in the outcome of this proceeding that cannot be adequately represented by any other party. \nAccordingly, Tract requests that the Commission grant this motion, consistent with the public \ninterest. \nII. \nCOMMUNICATIONS \nPlease address all notices and communications regarding this proceeding to the following \npersons who are also designated for service in this proceeding. \nOrijit Ghoshal \nVice President, Government and \nRegulatory Affairs  \nAllison Girvin \nVice President and Corporate Counsel  \n3200 E Cherry Creek South Drive \nSuite 700  \nDenver, CO 80209  \nTel: 406-202-4519 \norijit.ghoshal@tract.com              \nallison.girvin@tractcapital.com   \nTyler O’Connor \nKathy Lowrey \nCrowell & Moring LLP \n600 Fifth St NW \nWashington, D.C. 20001 \nTel: 202-624-2704 \nklowrey@crowell.com  \ntoconnor@crowell.com \n \n \n \n \n \nIII. \nBACKGROUND  \nThe instant proceeding concerns proposed revisions to the PJM Tariff and Reliability \nAssurance Agreement to institute the RBP, a “one-time, supplementary mechanism to procure \n \nmodifications to a utility’s [FPA section 205] proposal.’” See, e.g., N.Y. Indep. Sys. Operator, Inc., 188 FERC ¶ \n61,051, at P 22 n.36 (2024) (alteration in original) (citing NRG Power Mktg., 862 F.3d at 114-15); see Midcontinent \nIndep. Sys. Operator, Inc., 180 FERC ¶ 61,141, at P 26 n.29 (2022), order on reh’g, 182 FERC ¶ 61,096 (2023); \nISO New Eng. Inc., 175 FERC ¶ 61,172, at P 16 n.20 (2021).  \n6 18 C.F.R. § 385.214."},{"page":3,"startToken":606,"endToken":921,"text":"3 \n \nadditional supply to meet the resource adequacy needs of the PJM Region.”7 Following the \n2027/2028 base residual auction clearing 5.6% short of PJM’s target reserve margin, on January \n16, 2026, the PJM Board initiated a Critical Issue Fast Path Process (“CIFP”) to address PJM’s \nresource adequacy challenges.8 \nFollowing the conclusion of the CIFP, on July 31, 2026, PJM submitted the instant filing \nto establish what it characterizes as a “critical safety net designed to address current resource \nadequacy shortfalls” observed in the base residual auctions for the 2028/2029 delivery year.9 \nAccording to PJM, the RBP “will only procure the capacity necessary to cover any remaining \nshortfall from the 2028/2029 BRA after PJM has accounted for new capacity being brought by \nnew load or that otherwise qualify for a limited opt-out from the RBP.”10 Tract generally supports \nand commends PJM addressing the BRA shortfall by requiring loads to either curtail, bring their \nown capacity, or enter the RBP. \nUnder PJM’s proposal, “new capacity voluntarily brought on to the PJM system by new \nload” that satisfies the criteria set forth in proposed tariff section 18.2 may be credited as \nQualifying RBP Offset UCAP MW, thereby reducing the Initial RBP Target.11 In addition, new \nload that participates as Annual Demand Resources or DER Capacity Aggregation Resources may \nalso reduce the Initial RBP Target.12 These new capacity and curtailment offset options are \nrequired under the Statement of Principles Regarding PJM issued on January 16, 2026, by the \n \n7 PJM RBP Filing at 7. \n8 David E. Mills, PJM Board Chair, Board Decisional Letter on Critical Issue Fast Path - Large Load Additions, \nPJM Board (Jan. 16, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-load-additions.pdf.  \n9 PJM RBP Filing at 26. \n10 Id. \n11 See id. at 35, 39. \n12 Id. at 40."},{"page":4,"startToken":921,"endToken":1245,"text":"4 \n \nNational Energy Dominance Council (“NEDC”) and the 13 governors of the PJM states.13 \nHowever, proposed section 18.2(c) requires that new load present an “executed electric service \nagreement or transmission service agreement” demonstrating that such load will achieve \ncommercial operation within the applicable delivery year in order for the Qualifying RBP Offset \nUCAP MW or Annual Demand Resources or DER Capacity Aggregation Resources to decrement \nthe Initial RBP Target.14 This evidentiary requirement warrants clarification. \nIV. \nREQUEST FOR CLARIFICATION \nA. \nPJM Should Clarify the Scope of Agreements Load Can Provide As Evidence \nof Qualifying RBP Offset UCAP MW and Annual Demand Resources or \nDER Capacity Aggregation Resources. \nTract respectfully requests that PJM clarify that the undefined terms “electric service \nagreement and transmission service agreement” encompass executed agreements with load serving \nentities or transmission owners that evidence a binding commitment by new load to achieve \ncommercial operation by or during the relevant delivery year. As currently drafted, the proposed \ntariff language is not clear whether functionally equivalent agreements that serve the same \nevidentiary purpose as electric and transmission service agreements would satisfy the Qualifying \nRBP Offset UCAP MW or Annual Demand Resources or DER Capacity Aggregation Resources \neligibility requirements set forth in section 18.2(c). Absent such clarification, PJM risks \nunderstating the volume of legitimately committed new load that will achieve commercial \noperation by or during the relevant delivery year and that satisfies the requirements for Qualifying \nRBP Offset UCAP MWs or Annual Demand Resources or DER Capacity Aggregation Resources, \nthereby inflating the Final RBP Target beyond that necessary to address any actual resource \n \n13 Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm (urging PJM to allow loads to not be \nallocated RBP costs if they “self-procured new capacity or agreed to be curtailable”). \n14 PJM RBP Filing at 39-40; Proposed PJM Tariff, Attachment DD, §§ 18.2(c)(i)-(iii)."},{"page":5,"startToken":1245,"endToken":1551,"text":"5 \n \nadequacy shortfall. This result would be inconsistent with the NEDC’s and Governors’ Principles \nand outside the control of the load who may be subject to EDC tariffs and rules that do not \ncontemplate the named agreements. \nAs drafted, the requirement for load to provide an executed electric or transmission service \nagreement serves an evidentiary function: to “indicat[e] that the load will be coming online” in the \nrelevant delivery year.15 The requirement screens out speculative load and ensures that only load \nthat has assumed binding obligations sufficient to demonstrate it will achieve commercial \noperation within the applicable timeframe may be credited as Qualifying RBP Offset UCAP MW \nor Annual Demand Resources or DER Capacity Aggregation Resources. While electric service \nand transmission service agreements satisfy that standard, other executed agreements—including \ntransmission security agreements and construction letters of authorization—impose binding \ncommitments equally probative of genuine load commitment. That some EDCs either do not \nutilize those agreements or do not require loads coming online in the 2028/2029 delivery year to \nexecute them so far in advance does not make such loads any less likely to reach commercial \noperation. Of course, such loads must demonstrate some evidence of commitment to come online, \nand the Commission should find that transmission security agreements and construction letters of \nauthorization suffice. \nThe Commission has recently accepted executed transmission security agreements filed by \nCommonwealth Edison Company (“ComEd”) and PECO Energy Company (“PECO”), two \ntransmission owners in PJM.16 ComEd and PECO utilize these agreements to govern the terms \n \n15 PJM RBP Filing at 39-40; Proposed PJM Tariff, Attachment DD, §§ 18.2(c)(i)-(ii). \n16 See, e.g., Commonwealth Edison Company, 196 FERC ¶ 61,040 (2026); Commonwealth Edison Company, 196 \nFERC ¶ 61,042 (2026); PECO Energy Company, 195 FERC ¶ 61,074 (2026); PECO Energy Company, 193 FERC ¶ \n61,148 (2025)."},{"page":6,"startToken":1551,"endToken":1847,"text":"6 \n \nunder which they provide retail electric delivery services to large load customers that will not take \ntransmission service under PJM’s tariff.17 As the Commission explained in its order accepting \nComEd’s executed transmission security agreement with Tract’s affiliate, Grundy County Power \nNR I, LLC (“GCP”), the agreement imposes binding financial commitments designed to ensure \nthe data center achieves commercial operation on schedule: \nComEd states that the Transmission Security Agreement establishes protections in \nthe event of GCP’s failure to timely construct the Data Center and related facilities, \nfailure of such facilities to reach commercial operation by the commercial operation \ndate, \nfailure \nto \nremain \nin \noperation \nthroughout \nthe \nterm \nof \nthe Transmission Security Agreement, or failure to operate in conformance with \nthe agreed upon load phasing schedule (Load and Phasing Schedule) for a given \nyear.18 \nSimilarly, the construction letter of authorization that Tract’s other affiliate has executed \nwith Virginia Electric and Power Company (“Dominion”), authorizes Dominion to commence \nengineering, procurement, and installation of the facilities and associated equipment required to \nprovide electrical service to its forthcoming data center project and imposes binding obligations \non the executing party including equipment deposits and payments owed for delay or project \ncancellation. That neither ComEd nor Dominion have tendered electric service agreements or \ntransmission service agreements for these two projects that are otherwise contractually committed \nto achieve commercial operation during the 2028/2029 delivery year should not preclude the \nprojects from securing their own capacity and thereby satisfying the evidentiary requirements for \nQualifying RBP Offset UCAP MW and Annual Demand Resources or DER Capacity Aggregation \nResources. Even those electric distribution companies that execute electric service agreements \n \n17 PECO Energy Company, 193 FERC ¶ 61,148 at P 2 (2025). \n18 Commonwealth Edison Company, 194 FERC ¶ 61,181 at P 3 (2026)."},{"page":7,"startToken":1847,"endToken":2178,"text":"7 \n \nwith large loads often do not tender them until 12 months in advance of energization.19 Requiring \nlarge loads to demonstrate evidence of such agreements now—rather than transmission security \nagreements or construction letters of authorization agreements—would functionally prevent large \nloads with commercial operation dates in the 2028/2029 delivery year from meeting the \nrequirements for Qualifying RBP Offset UCAP MW or Annual Demand Resources or DER \nCapacity Aggregation Resources, in violation of the NEDC’s and Governors’ Principle to allow \nloads that procure their own capacity or agree to curtail to avoid being double-counted in the \nauction. \nLike electric and transmission service agreements, both transmission security agreements \nand construction letters of authorization impose binding commitments on developers and EDCs20 \nto bring a project online within a defined timeframe and impose material financial consequences \non a developer that fails to satisfy its obligations. PJM should therefore afford sufficient flexibility \nin evaluating the agreements that new load may present as evidence of Qualifying RBP Offset \nUCAP MW or Annual Demand Resources or DER Capacity Aggregation Resources—including \ntransmission security agreements, construction letters of authorization, and functionally equivalent \ninstruments—to ensure that the RBP process accurately accounts for all genuinely committed new \nload that is properly matched with new supply. The Commission has accepted proposals that afford \nprecisely such flexibility in other contexts.21 \n \n19 Application of Virginia Electric and Power Company for Approval of its Large-Load Connection Queue Process \nStandards, Case No. PUR-2026-00011, at 74 (Va. State Corp. Comm’n Apr. 15, 2026) (explaining the Dominion \n“offers Electric Service Agreements to customers approximately one year before energization of service”). \n20 For instance, Dominion’s construction letter of authorization authorizes Dominion to install the facilities \nnecessary to provide electric service. \n21 Midcontinent Independent System Operator, Inc., 192 FERC ¶ 61,064 at P 208 (2025) (accepting MISO’s \nproposal to allow applicants to provide “other agreements” to satisfy a showing of an executed agreement with load \nand explaining it “provides considerable flexibility . . . to satisfy this requirement”)."},{"page":8,"startToken":2178,"endToken":2517,"text":"8 \n \nAbsent clarification from PJM, a narrow interpretation of “electric service agreement and \ntransmission service agreement” risks producing the very outcome PJM sought to avoid: load \npaying to procure capacity in the RBP that could otherwise be served by its own capacity or \nthrough curtailment.22 Such a result would directly contravene the stated purpose of the RBP—to \ninstitute “a one-time mechanism that will only procure the capacity necessary to cover any \nremaining shortfall from the 2028/2029 BRA after PJM has accounted for new capacity being \nbrought by new load or that otherwise qualify for a limited opt-out from the RBP.”23 \nV. \nLIMITED PROTEST \nA. \nTo The Extent Not Clarified As Argued Above, PJM’s RBP Filing Is Unduly \nDiscriminatory Because It Excludes Similarly Situated New Loads From \nEligibility For Qualifying RBP Offset UCAP MW and Annual Demand \nResources or DER Capacity Aggregation Resources. \nThe Commission has long held that a rate, term, or condition is unduly discriminatory \nwhere it treats similarly situated customers differently absent a legitimate basis for doing so.24 \nShould PJM decline to provide the requested clarification, the Commission should reject the RBP \nfiling as unduly discriminatory or preferential under Section 205 of the FPA.25  \nBy restricting the types of executed agreements new loads may present to obtain eligibility \nfor Qualifying RBP Offset UCAP MW and Annual Demand Resources or DER Capacity \nAggregation Resources, PJM’s proposal draws an impermissible distinction among similarly \n \n22 PJM RBP Filing at 37-38.  \n23 Id. at 26 (emphasis added).  \n24 See El Paso Nat. Gas Co. Aera Energy, LLC, 104 FERC ¶ 61,045 at P 115 (2003), reh’g denied, 106 FERC ¶ \n61,233 (2004) (“Discrimination is undue when there is a difference in rates or services among similarly situated \ncustomers that is not justified by some legitimate factor.”). \n25 See 16 U.S.C. § 824d(b); See Sw. Power Pool, Inc., 193 FERC ¶ 61,171 at P 91 (2025) (the applicant “bear[s] the \nburden of demonstrating that proposed tariff revisions are . . . not unduly discriminatory or preferential.”)."},{"page":9,"startToken":2517,"endToken":2822,"text":"9 \n \nsituated customers.26 As explained above, new load customers that have executed transmission \nsecurity agreements, construction letters of authorization, or similar agreements have undertaken \nbinding contractual and financial commitments functionally equivalent to those assumed under \nstandard electric service or transmission service agreements. In each case, the customer has \ndemonstrated a genuine, non-speculative commitment to achieve commercial operation within a \ndefined timeframe; the sole relevant distinction lies in the particular contractual instrument through \nwhich that commitment has been formalized. PJM’s proposal permits the latter category of \ncustomers to qualify for RBP offset eligibility while denying the former any opportunity to do so, \nwithout any reasoned justification for the disparate treatment.27 \nThis discrimination is particularly impactful in this instance because large load customers, \nsuch as data centers, by virtue of their scale and operational characteristics, are often subject to \nnon-standard contractual instruments before being tendered electric or transmission service \nagreements. As explained above, electric distribution companies are increasingly requiring data \ncenters to execute bespoke instruments—such as transmission security agreements and \nconstruction letters of authorization—which impose substantial financial commitments at least as \nprobative of genuine load commitment as a standard electric or transmission service agreement. \nPJM’s proposal thus creates a discriminatory preference for customers whose agreements bear a \n \n26 See Transmission Agency of N. Cal. v. FERC, 628 F.3d 538, 551 (D.C. Cir. 2010) (explaining that the \nCommission cannot treat similarly situated entities differently (citing Sacramento Mun. Util. Dist. v. FERC, 474 \nF.3d 797, 802 (D.C. Cir. 2007)). \n27 See, e.g., id.; N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018) (“To say that entities are \nsimilarly situated does not mean that there are no differences between them; rather, it means that there are no \ndifferences that are material to the inquiry at hand.”)."},{"page":10,"startToken":2822,"endToken":3266,"text":"10 \n \nparticular label, while penalizing those who have undertaken equivalent binding commitments to \ndemonstrate their load is real, committed, and coming online within the relevant delivery years.28 \nGiven that PJM has acknowledged the requirements of Section 18.2(c) are intended to \ndemonstrate that interconnecting load will achieve commercial operation within the applicable \ndelivery year, the Commission should condition acceptance of the RBP filing on PJM’s submission \nof revised tariff language permitting PJM to evaluate whether any executed agreement evidences \na genuine, binding commitment to achieve commercial operation within the applicable delivery \nyear.29 For example, PJM could adopt the following revisions, shown in red, to proposed tariff \nsection 18.2(c)(i)-(iii): \n(i) Signed bilateral contracts for Qualifying RBP Offset UCAP MW for at least five \nDelivery Years with a commercial operation date prior to the start of the 2032/2033 \nDelivery Year, and matched with load that has an executed electric service agreement, or \ntransmission service agreement or any other binding agreement, indicating that the load \nwill be coming online in the 2027/2028 or 2028/2029 Delivery Year; \n \n(ii) Self-Supply generation that is in a Relevant Electric Retail Regulatory Authority \n(“RERRA”)-approved or accepted integrated resource plan with either associated \ngeneration in the PJM interconnection queue or signed bilateral contracts for Qualifying \nRBP Offset UCAP MW for at least five Delivery Years with a commercial operation date \nprior to the start of the 2032/2033 Delivery Year, and matched with load that has an \nexecuted electric service agreement, or transmission service agreement or any other \nbinding agreement, indicating that the load will be coming online in the 2027/2028 or \n2028/2029 Delivery Year; or   \n \n(iii) Signed commitment between a Curtailment Service Provider or DER Aggregator and \nnew load(s) that has an executed electric service agreement, or transmission service \nagreement or any other binding agreement, indicating that the new load(s) will, in a MW \nquantity equal to MW quantity of the new load(s), either (a) participate as Annual Demand \nResources or DER Capacity Aggregation Resources starting in the 2028/2029 Delivery \nYear Second Incremental Auction and continuing through the 2032/2033 Delivery Year, \nor (b) purchase replacement Qualifying RBP Offset UCAP MW that are eligible generation \nor storage resources.  \n \n28 See PacifiCorp, 171 FERC ¶ 61,112 at PP 100-102 (2020) (rejecting a proposal where similarly situated \ncustomers were required to make different showings of commercial readiness). \n29 Commission may take such action because PJM has consented to the Commission’s exercise of authority to \nmodify or sever elements of the RBP filing. See NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017)."},{"page":11,"startToken":3266,"endToken":3405,"text":"11 \n \n \nAbsent such modification, PJM’s proposal will arbitrarily foreclose Qualifying RBP Offset \nUCAP MW and Annual Demand Resources or DER Capacity Aggregation Resources eligibility \nfor an entire class of similarly situated new load customers—a result that is neither just nor \nreasonable, nor consistent with the prohibition against undue discrimination under the FPA. \nVI. \nCONCLUSION \nFor the foregoing reasons, Tract respectfully requests that PJM provide the clarification \nrequested herein, or, in the alternative, that the Commission sever and reject the relevant portion \nof PJM’s RBP filing as unduly discriminatory and direct PJM to submit revised tariff language on \ncompliance consistent with this filing. \n \n \nRespectfully submitted, \n \n \n \n \n \n \nAugust 21, 2026 \n/s/ Tyler O’Connor_ \nTyler O’Connor \nKathryn Douglass \nKathy Lowrey \nCrowell & Moring LLP \n600 Fifth St NW \nWashington, D.C. 20001 \n202-624-2500 \ntoconnor@crowell.com \n \nCounsel for Tract Holding Company I, \nLLC"},{"page":12,"startToken":3405,"endToken":3458,"text":"12 \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that on this 21st day of August, 2026, a copy of the foregoing document \nhas been electronically served upon each person designated on the official service list in this \nproceeding. \n \n/s/ Kathy Lowrey_ \nKathy Lowrey \n600 Fifth St NW \nWashington, D.C. 20001 \nklowrey@crowell.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":324},{"p":2,"at":5,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":2,"endAt":618,"startToken":324,"endToken":413},{"p":2,"at":618,"title":"II. COMMUNICATIONS","method":"printed heading","endPage":2,"endAt":1241,"startToken":413,"endToken":496},{"p":2,"at":1241,"title":"III. BACKGROUND","method":"printed heading","endPage":4,"endAt":539,"startToken":496,"endToken":999},{"p":4,"at":539,"title":"IV. REQUEST FOR CLARIFICATION","method":"printed heading","endPage":4,"endAt":571,"startToken":999,"endToken":1003},{"p":4,"at":571,"title":"A. PJM Should Clarify the Scope of Agreements Load Can Provide As Evidence","method":"printed heading","endPage":8,"endAt":647,"startToken":1003,"endToken":2282},{"p":8,"at":647,"title":"V. LIMITED PROTEST","method":"printed heading","endPage":8,"endAt":668,"startToken":2282,"endToken":2285},{"p":8,"at":668,"title":"A. To The Extent Not Clarified As Argued Above, PJM’s RBP Filing Is Unduly","method":"printed heading","endPage":11,"endAt":375,"startToken":2285,"endToken":3319},{"p":11,"at":375,"title":"VI. CONCLUSION","method":"printed heading","endPage":12,"endAt":6,"startToken":3319,"endToken":3406},{"p":12,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":12,"endAt":327,"startToken":3406,"endToken":3458}]}