{"document":{"slug":"rec-20260821-5314","title":"Comments of Old Dominion Electric Cooperative re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement filing","issued":"2026-08-21","accession":"20260821-5314","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Old Dominion Electric Cooperative","kind":"comments","file":"sources/filings/text/20260821-5314_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5314","tier":"record","sha256":"490090c36f58dd0a0db9b89f337a915fe81f2f3d2b105f34de24574067b24d06","pages":18,"tokens":5042,"emptyPages":[],"textThemes":["credit","adequacy","cost","registry"]},"pages":[{"page":1,"startToken":0,"endToken":279,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3380-000 \nCOMMENTS OF OLD DOMINION ELECTRIC COOPERATIVE \nI.\nINTRODUCTION \nOn July 31, 2026, as supplemented on August 14, 2026, PJM Interconnection, L.L.C. \n(“PJM”) submitted revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the \nReliability Assurance Agreement Among Load Serving Entities (“RAA”) for a proposed \nReliability Backstop Procurement (“RBP”). The RBP, as described by PJM, is a one-time \nmechanism to address the capacity shortfall caused by large loads. The proposed RBP would \nprocure capacity needed to meet the reliability requirement shortfall for the 2028/2029 Delivery \nYear, to the extent new loads coming online in the 2027/2028 or 2028/2029 Delivery Years do not \nvoluntarily procure sufficient new capacity to address the shortfall or otherwise qualify for the \nlimited RBP opt-out.1 PJM requests Commission acceptance and an effective date for RBP of no \nlater than September 29, 2026, so that PJM can commence RBP procurement on September 30, \n2026.2\nODEC respects PJM’s critical role in ensuring resource adequacy and facilitating reliable \ninterconnection of large loads. In that regard, ODEC does not take issue with PJM’s assessment \nof the problem – there is an impending reliability problem of insufficient capacity that must be \naddressed immediately, for the 2028/2029 Delivery Year.3 However, as discussed in these \n1 PJM Transmittal Letter at 26. \n2 Id. at 27. \n3 See id. at 7 (“the addition of new supply has not kept pace with rapid large load demand growth, thus \ngiving rise to the significant tightening of the capacity market in recent years and the subsequent resource \nadequacy shortfalls.”)"},{"page":2,"startToken":279,"endToken":567,"text":"2 \ncomments, PJM’s proposed solution raises concerns regarding whether costs and risks will be \nsufficiently aligned with the large loads that drive the need for the procurement. Rather than accept \nPJM’s RBP as filed, the Commission should instead take PJM up on its offer for the Commission \nto adopt revisions to specific elements of the RBP and adopt an alternative that received significant \nstakeholder support. Specifically, the Commission should direct PJM to adopt the “subscription \nmodel” proposed by Joint EDCs and the Data Center Coalition and approved by the PJM \nstakeholders by a super-majority vote.4 \nFurther, the Commission should revise the proposed RBP to adopt a revision to provide \nunrestricted opt-out for municipally owned utilities and electric cooperatives. At the very least, \nPJM should be required to confirm that electric cooperatives such as ODEC are eligible for the \nopt-out mechanism and revise the opt-out provisions as necessary to reflect such clarification.  \nFinally, ODEC has identified an inconsistency between PJM’s statement in the RBP \ntransmittal letter and its proposed Tariff provisions with respect to allocation of RBP Charges in \nthe event of default by LSEs. PJM should confirm that the Tariff is what it intends for RBP Default \nAllocation. \nPursuant to the Combined Notice of Filings #1 issued August 3, 2026, ODEC submits these \ncomments on PJM’s RBP proposal. In support of its request for the Commission to remedy PJM’s \nRBP, ODEC states as follows: \n4 The Joint EDCs and Data Center Coalition Reliability Backstop Procurement Package proposal is \navailable in materials posted by PJM for the June 30, 2026, PJM Members Committee meeting, \nhttps://www.pjm.com/committees-and-groups/committees/mc (last visited August 18, 2026). For \nconvenience, a copy of the proposal is attached to this pleading."},{"page":3,"startToken":567,"endToken":887,"text":"3 \nII.\nCOMMENTS \nA. The subscription model better aligns procurement obligations with cost-causation \nprinciples. \nPJM’s RBP will require LSEs to meet significant collateral requirements, cover the cost of \ncapacity allocated to them per the allocation of RBP Charges, and bear responsibility for defaults.5\nEach of these components of PJM’s proposal will create significant financial and other obligations \nfor LSEs, including the costs to administer or implement the new obligations, as well as potential \nimpacts on LSEs’ ability to shoulder these costs while continuing in their other obligations. PJM \nacknowledges the region is in the predicament due primarily to the influx of large loads without \nadequate or timely investment in new generation to serve those large loads.6\nPJM’s proposal places substantial responsibility for these risks on LSEs who neither caused \nthe underlying problems of large loads with insufficient capacity, nor caused these costs to be \nincurred. LSEs will bear the cost of RBP Collateral – which must be in the form of cash or a letter \nof credit deemed acceptable to PJM or PJMSettlement – that is in addition to and separate from \ncollateral they already must post for the RPM auctions and bilateral transactions. Moreover, the \namount of such collateral is unknown at this time and will not be known until after the cost \nresponsibility for RBP capacity has been determined for the Delivery Year. We can expect that the \nRBP Collateral requirement for individual LSEs who will be allocated cost responsibility for RBP \nCharges will be significant. As PJM explains, the risk of non-performance for RBP resources is \ngreater than the risk for resources in the RPM Auctions and, therefore, PJM has created RBP \nCollateral requirements that reflect the inherently riskier nature of RBP resources. ODEC is \nconcerned that this risk will not be borne by those who cause the risk (RBP Sellers, large loads). \n5 See PJM Transmittal Letter at 50. \n6 See PJM Transmittal Letter at 1."},{"page":4,"startToken":887,"endToken":1263,"text":"4 \nIt will instead be shifted to LSEs. While PJM contends its imposition of the risk of default on LSEs \nis consistent with the Ratepayer Protection Pledge, that simply is not the case. The Ratepayer \nProtection Pledge calls for large loads to cover the costs of new capacity and for costs not to \nbecome stranded or socialized. The Ratepayer Protection Pledge does not contemplate LSEs \nserving as the primary backstop for costs and risks that originate with large-load growth.  \nPJM contends that it has no choice but to shift all the cost and risk to LSEs, because PJM’s \njurisdiction stops at the Electric Distributor/LSE and we must depend on the states to take it from \nthere. ODEC agrees that states have an important role in ensuring large loads pay their fair share \nand other ratepayers are not forced to subsidize the costs associated with large loads. However, \nusing LSEs as the default payer, with no assurance of the level of costs or that those costs will be \nallocated to large loads, does not adhere to principles of cost causation. Retail customers from \nevery rate class may end up paying these costs if the states do not adopt measures to ensure the \nLSEs have the regulatory mechanisms to allocate these costs to those who cause them.   \nPJM’s RBP relies on rules that do not exist, to define the large loads to whom these costs \nwill be allocated and the mechanisms for doing so. It is unreasonable to expect that the states, even \nwith their best intentions and resources, will be able to resolve these determinations in time for the \nRBP that PJM intends to commence on September 30, so that LSEs have any of the assurance they \nwill not shoulder the stranded costs of default and/or RBP Charges, as well as RBP Collateral. \nPJM’s Board had another option to consider, which would have provided a mechanism to \naddress the shortfall in the short term without unreasonably shifting all cost and risk to LSEs. As \nPJM briefly mentioned in its filing, the Joint EDC and Data Center Coalition (“Coalition”) \nproposed a subscription-based model for RBP. In summary, the subscription model would have \nLSEs secure bilateral contracts or other arrangements to meet the large load capacity obligations,"},{"page":5,"startToken":1263,"endToken":1584,"text":"5 \nthen opt to participate in a central procurement by indicating to PJM the MW quantity that PJM \nshould procure on their behalf through the RBP. Those LSEs would be responsible for satisfying \nthe credit or collateral requirements associated with any capacity committed on their behalf \nthrough the RBP and would not be permitted to participate in RBP if they fail to do so. Thus, the \nLSE would remain responsible for protecting other LSEs and PJM market participants from \nassuming obligations associated with a default. However, unlike PJM’s RBP proposal, the \nCoalition RBP proposal gives LSEs the opportunity to determine how best to meet the capacity \nneeds of their customers, including through bilateral arrangements and contracts outside of RBP \nto protect LSEs and their customers. The Coalition RBP proposal also avoids the use of a large \nload forecast to procure long-term capacity commitments that is a component of PJM’s RBP \nproposal. PJM acknowledges the need to improve load forecasting and has efforts underway to do \nso.7 However, there is a significant risk that PJM will over-procure capacity because the RBP \nTargets will be based on load forecasts that were not developed with this urgent and long-term \ncommitment in mind and may be outdated or contain duplicative requests. Additionally, PJM’s \napproach does not provide any mechanisms to lock-in the capacity commitments made on behalf \nof the large load for the possible 15 year term of the RBP. Thus, even if the large load does \nmaterialize as forecasted, there are no assurances it will stay online for the full 15 years. The \nCoalition RBP proposal’s subscription-based approach would allow LSEs who represent or serve \nlarge load end-users, to make capacity commitments based on contracts and communications with \nlarge loads. \nThere was significant stakeholder support for the Coalition subscription-based proposal. \nAs PJM reported, the Coalition RBP proposal was the only one of the 13 different RBP proposals \n7 PJM Transmittal Letter at 25."},{"page":6,"startToken":1584,"endToken":1957,"text":"6 \nthat received greater than two-thirds sector-weighted member support. The PJM Board opted not \nto adopt the core difference between the Coalition Proposal and the PJM RBP; the subscription \nmodel. PJM’s RBP will impose costs and risks on LSEs that the LSEs did not cause. Therefore, \nthe Commission should direct PJM to adopt the subscription aspect of the Coalition RBP Proposal \nif the Commission deems it is permitted to do so under FPA section 205.8\nB. The Commission should direct PJM to revise its Opt-Out or at the very least \nclarify eligibility for the Opt-Out. \nPJM proposes a RBP Opt-Out that would provide for a reduction in the Initial RBP Target \nfor calculating the Final RBP Target, where an Electric Distributors’ zone or area has rates that \nare not regulated by the states and the Electric Distributor is unable to address cost allocation \nassociated with capacity procured in the RBP.9 In order to request the Opt-Out, an Electric \nDistributor must not only identify the quantity of load that will be opted-out in the Initial RBP \nTarget, but also provide “supporting documentation demonstrating an inability to address cost \nallocations associated with capacity procured in the backstop” as well as written support for the \nopt-out from the state governor, RERRA and interconnection customer(s).10 In the event the \nCommission does not adopt the subscription model for RBP discussed above, then the Commission \nshould direct PJM to revise its Opt-Out. \nPJM explains in its filing that the Opt-Out is in response to concerns raised by cooperatives \nthat cooperatives who are Electric Distributors in a retail choice state are not state regulated and \n8 PJM has consented to “the Commission’s exercise of authority to modify and/or sever any element of \nthe proposed Tariff and RAA language ot he extent necessary and permitted under section 205 of the FPA \nand NRG Power Marketing, LLC v. FERC . . .” PJM Transmittal Letter at 3. ODEC expects that PJM \nwould not find the subscription model consistent with PJM’s RBP, even if FERC deems it is permitted to \ndirect such a revision while accepting PJM’s filing. In that instance, the Commission should reject PJM’s \nfiling as unjust and unreasonable. \n9 PJM Proposed Tariff Section 18.1(d). \n10 Id."},{"page":7,"startToken":1957,"endToken":2275,"text":"7 \nnot otherwise serving as the LSE for generation to load, would not have a state regulatory authority \nto address the allocation of RBP costs to other large loads or zones within the state.11 As discussed \nabove, ODEC has significant concerns that as an electric cooperative that will be subject to RBP \nCharges, ODEC and its member distribution cooperatives will be left to bear the costs for RBP \nCharges, defaults, and RBP Collateral without assurance that it will be able to allocate those costs \nto large loads who cause the costs to be incurred. \nODEC appreciates PJM’s effort to address concerns raised by electric cooperatives and \nmunicipal utilities regarding mandatory participation in RBP. As PJM explains, the opt-out \nprovision was developed in response to concerns that certain entities could be required to bear the \ncosts of capacity procured for large loads that ultimately fail to materialize. PJM further explains \nthat cooperatives and municipal utilities may face unique challenges because they are not always \nsubject to traditional state rate regulation. \nODEC believes, however, that the underlying purpose of the opt-out is broader than \naddressing a narrow regulatory gap. The concern raised by cooperatives was fundamentally one of \nrisk allocation: ensuring that smaller, community-focused utilities are not required to assume \nprocurement obligations and associated financial risks that may be outside of their control. Rate \nregulation status may be one factor relevant to that concern, but it is not the concern itself. In \nODEC’s view, PJM’s discussion appears to rely on the premise that electric cooperatives and \nmunicipal utilities generally are not subject to rate regulation. While that may be true in some \njurisdictions, it is not universally the case. For example, Virginia’s electric cooperatives operate \nunder a regulatory framework that includes oversight of rates and services by the Virginia State \nCorporation Commission. The existence of such oversight demonstrates that the distinction is not \n11 PJM Transmittal Letter at 45."},{"page":8,"startToken":2275,"endToken":2601,"text":"8 \nas simple as whether an entity is or is not rate regulated. More importantly, the procurement and \ncost-allocation risks that motivated the opt-out can exist regardless of the specific form of \nregulatory oversight applicable to a utility. \nODEC therefore believes the opt-out was intended to provide a reasonable safeguard for \nsmaller utilities, including electric cooperatives and municipal utilities, that could face \ndisproportionate exposure to Reliability Backstop Procurement obligations. Interpreting the \nprovision solely through the lens of traditional state rate regulation risks narrowing the opt-out \nbeyond the concern it was designed to address. The Commission should instead evaluate the opt-\nout consistent with its broader purpose of protecting smaller utilities from undue procurement risk \nwhile preserving flexibility for those entities best positioned to manage that risk. \nElectric cooperatives and municipals have every reason to ensure sufficient capacity and \nthat costs are allocated to the large loads who cause those costs to be incurred. PJM’s willingness \nto provide the opt-out demonstrates that PJM agrees or at least does not oppose the ability of \nelectric cooperatives to secure sufficient capacity outside of the RBP. Therefore, if the \nCommission accepts PJM’s RBP, it should condition such acceptance on a compliance filing by \nPJM to remove the restrictions on the opt-out and instead provide an unrestricted opt-out for \nelectric cooperatives and municipal utilities. This change is consistent with the goal of PJM’s Opt-\nOut provision and, therefore, can be required per PJM’s advanced consent to the Commission’s \nauthority to modify the proposed Tariff and RAA language.12 Specifically, the Commission should \ndirect PJM to submit a compliance filing to revise the RBP Opt-Out, as follows: \n(d) Opt-Out \nWhen calculating the Final RBP Target, the Initial RBP Target shall also be decremented \nwhere the Electric Distributor’s zone/area has rates that are not regulated by the states and is unable \nto address cost allocation associated with capacity procured in the backstop includes load that is \n12 PJM Transmittal Letter at 3."},{"page":9,"startToken":2601,"endToken":3002,"text":"9 \nserved by an electric cooperative or a joint municipal agency, upon request by the Electric \nDistributor to opt-out a portion or all of its associated portion of the Initial RBP Target. Such \nrequest by the Electric Distributor shall specify the associated MW quantity of load in the \nzone/area that will be opted-out of the Initial RBP Target and be accompanied by supporting \ndocumentation demonstrating an inability to address cost allocation associated with capacity \nprocured in the backstop, along with written support for such opt-out from the relevant state \ngovernor, RERRA, and interconnection customer(s). The Initial RBP Target shall be further \ndecremented, if requested by an Electric Distributor, by up to the associated MW quantity of load \nthat participates in a peak shaving adjustment program where such Electric Distributor’s zone/area \naddresses their capacity needs through peak shaving adjustment programs that are codified in state \nlaw and that also meet the requirements of Tariff, Attachment DD-2. \nAdditionally, PJM should clarify that for purposes of the Opt-Out, generation and \ntransmission electric cooperatives qualify for the opt-out, as opposed to only their distribution \ncooperative members. ODEC is the LSE for its member cooperatives. ODEC is also presumably \nthe entity that will receive the RBP Charge and RBP Collateral obligations. Therefore, ODEC \nshould be permitted to request the RBP Opt-Out. ODEC is not subject to rate regulation by state \ncommissions but is instead subject to rate regulation at FERC. However, its member distribution \ncooperatives in Virginia are subject to state regulation by the Virginia State Corporation \nCommission. The PJM RAA defines Electric Distributor as follows: \n“Electric Distributor” shall mean a Member that 1) owns or leases with rights \nequivalent to ownership of electric distribution facilities that are used to provide \nelectric distribution service to electric load within the PJM Region; or 2) is a \ngeneration and transmission cooperative or a joint municipal agency that has a \nmember that owns electric distribution facilities used to provide electric distribution \nservice to electric load within the PJM Region. \nBased on the definition of Electric Distributor, ODEC is an Electric Distributor because \nODEC is a generation and transmission cooperative that has members that own electric distribution \nfacilities used to provide electric distribution service to electric load in the PJM Region. PJM \nshould clarify that ODEC and other similarly situated generation and transmission cooperatives \nqualify for the Opt-Out, even if their distribution cooperative members are state regulated."},{"page":10,"startToken":3002,"endToken":3307,"text":"10 \nC. PJM should resolve an inconsistency in its filing. \nPJM states in its transmittal letter that if an LSE defaults and fails to pay an RBP Charge, \n“PJM will allocate the defaulted amount to all remaining LSEs that have been assigned \nresponsibility for RBP Charges in the Electric Distributor zone/area based on each LSE’s pro-rata \nshare of the total RBP Charges, as allocated based on either the Reliability Backstop Obligation \nor PJM’s back-up cost allocation methodology.”13 However, the proposed Tariff states that the \ndefaulted amount “will be allocated to all remaining Load Serving Entities responsible for paying \nRBP Charges based on their pro rata share of the total RBP Charges for all such Load Serving \nEntities. . .”14 The difference between these two can be significant, because allocating default \namounts to only the zone as opposed to all LSEs in the PJM Region could result in LSEs in the \ndefault zone bearing a larger portion of the default amounts. ODEC presumes that PJM’s Tariff \nwould control, but PJM should confirm its intent to allocate default amounts to all LSEs in the \nregion with responsibility for RBP Charges. \nIII.\nCONCLUSION \nWHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider \nthese comments in its determination of the PJM RBP proposal and if the Commission accepts the \nfiling, require PJM to submit a compliance filing to (1) adopt the “subscription model” proposed \nby Joint EDCs and the Data Center Coalition; (2) in the event the Commission does not adopt the \nsubscription model, then revise PJM’s proposed RBP to provide an unrestricted opt-out for \nmunicipally-owned utilities and electric cooperatives and confirm that electric cooperatives such \nas ODEC are eligible for the opt-out mechanism and revise the opt-out provisions as necessary to \n13 PJM Transmittal Letter at 90 (emphasis added). \n14 Proposed Tariff Section 18.9."},{"page":11,"startToken":3307,"endToken":3366,"text":"11 \nreflect such clarification; and (4) confirm that the Tariff reflects PJM’s intention for the RBP \nDefault Allocation. \nRespectfully submitted, \n /s/ Adrienne E. Clair \nAdrienne E. Clair \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C. 20006-1167 \n(202) 585-6900 \n(202) 585-6969 (fax) \naclair@thompsoncoburn.com  \nAttorney for Old Dominion Electric \nCooperative \nDated: August 21, 2026"},{"page":12,"startToken":3366,"endToken":3408,"text":"CERTIFICATE OF SERVICE \nI hereby certify that on this 21st day of August 2026, I have caused a copy of the foregoing \nto be served upon each party designated on the Commission’s Official Service List for this \nproceeding. \n /s/Adrienne E. Clair"},{"page":13,"startToken":3408,"endToken":3736,"text":"1 \n \n \nJoint EDCs & Data Center Coalition (“Coalition”) \nReliability Backstop Procurement Package \nExecutive Summary \nJoint EDCs = Buckeye Power, Dominion Energy, Duke Energy Ohio, Duke Energy Kentucky, \nDuquesne Light Company, East Kentucky Power Cooperative, Exelon, Old Dominion \nElectric Cooperative, PPL Electric Utilities Corp., Southern Maryland Electric Cooperative \n \nThe Coalition supports and include PJM’s bilateral matching phase in our package. The \nprocess provides opportunities for large loads and suppliers to directly contract to add \nneeded capacity to the RTO system while allowing for negotiated terms and conditions to \nbe decided among the parties. A strong bilateral contracting phase will improve the \nlikelihood of success of the central procurement proposed by the Coalition.  \nThe Coalition supports PJM implementing a centralized procurement to address the \ncapacity needs of Large Loads, a Reliability Backstop Procurement (RBP), centered on two \ncore principles: \n1. Establishing a subscription-based procurement target which recognizes the \nbenefit of Large Loads continuing to secure bilateral contracts that manage risk \nwithin contract terms outside of PJM’s markets, and \n2. Ensuring that RBP costs and credit/collateral obligations are assigned to the \nappropriate cost-causing parties at the time RBP commitments are made. \nA Load Serving Entity (LSE) is the entity legally or contractually obligated to supply a Large \nLoad’s capacity and energy needs. LSEs, therefore, should be responsible for both \ndetermining the procurement target for the Large Loads they serve and bearing associated \nfinancial and credit obligations associated with those loads.  \nThe Coalition’s proposal is grounded in PJM’s existing legal and operational framework. \nUnder PJM’s governing documents, LSEs that rely on PJM markets must be parties to the \nReliability Assurance Agreement (RAA) and are responsible for financial obligations arising \nfrom RPM capacity auctions. LSEs work with the loads they serve to determine how best to \nsatisfy capacity obligations, including making resource build, demand response, and \nbilateral contracting decisions.  A central RBP must accommodate the ability of the LSE to \ndetermine how best to meet the capacity needs of its customers, including respecting \nATTACHMENT"},{"page":14,"startToken":3736,"endToken":4133,"text":"2 \n \nRERRA directives for how those needs should be satisfied.  Any RBP should respect LSE \ndecisions that may transfer cost and financial risk outside of the PJM market by allowing \nthe LSEs to opt-into the procurement.  There simply is insufficient time to ensure all \nbilateral contracting that that can be completed before PJM intends to conduct the RBP. \nThe Coalition proposes that the LSEs who wish to participate in the central procurement (or \nLarge Loads themselves if they so desire) would indicate the MW quantity PJM should \nprocure on their behalf through the RBP. This may be referred to as a subscription model. \nThe decision to subscribe is based on the legal arrangement between the LSE and the \nrelevant Large Load. In subscribing, the LSE commits to satisfying the credit/collateral \nrequirements at the time the RBP commits supply resources and through the duration of \nthe RBP resource commitment period.  An LSE that cannot satisfy the credit requirements \ndescribed below is not permitted to subscribe MW to be procured through the RBP.  This \nprotects other LSEs and PJM market participants more broadly from assuming obligations \nshould a default of an RBP obligation occur of the RBP obligation were to occur.  This \napproach also should accommodate Large Load switching to new LSEs, with their \nsubscribed RBP commitment following them to their new LSE. \nThe registry-based subscription model proposed by the Coalition simultaneously \naddresses concerns related to over procurement, cost allocation and cost shifting.  \n \nLL LSE Registry \nTo establish the procurement target, the Coalition proposes the creation of a Large Load \nRegistry, maintained by PJM, through which either the Large Load or its designated LSE \nwould report: \n• The MW quantity of Large Load assigned to a specific LSE (or assigned directly to \nthe Large Load should it be able and willing directly to take on the obligation) in a \nspecific zone, and \n• Identity of the Large Load (not necessarily meter level data at time of \nprocurement) \nBelow is a flow chart conceptualizing how the information would flow to determine the RBP \nprocurement target via LSE subscription. \nAt the start of each Delivery Year, the registry would confidentially capture the Large Load \nmeter level information (or other unique identifier information as appropriate under state \nlaw) to facilitate appropriate billing and collateral tracking to accommodate Large Load \nswitching LSEs in retail choice states and any Large Load corporate ownership changes.  \nATTACHMENT"},{"page":15,"startToken":4133,"endToken":4473,"text":"3 \n \n \nSettlement  \nThe RBP commitment is fixed at the time of the procurement. LSEs who subscribed receive \ntheir MW allocation of committed resources.  Although the MW quantity may vary over time \nto account for the varying in-service dates of the resources committed, the obligation to \npay for the committed resources is fixed at the time of procurement.  This obligation can be \ntransferred to a different LSE should the Large Load change suppliers, subject to any PJM \ncredit requirements associated with such transfers. \nDuring the Delivery Year, LSEs could use PJM subaccounts to enable PJM billing to separate \ncosts for individual Large Loads to best enable the LSE to allocate costs to the right retail \nentity via Tariff or contract, limiting the potential for cost shifts to unrelated retail \ncustomers. \nUnder this subscription model, RBP obligations would be settled separately from RPM but \nstructured to net appropriately for the correct LSE and avoid double payment for \noverlapping capacity obligations with the same MWs of load being represented in both RPM \nand RBP.  \nBelow is a flow chart conceptualizing how, after the information flows to establish the \nprocurement target, PJM would bill for the RBP obligation.  Note the credit requirement \nproposed below attaches to the LSE at the time of the RBP commitment, and adjusts over \ntime. This is not depicted in the flow chart. \n \nCredit Requirement \nSubscribing LSEs (or Large Loads if they directly subscribed) are required to post collateral \nto ensure that, in the event of a subscribing LSE RBP commitment buyer default, other LSE \nsubscribers and other PJM market participants are largely insulated from the costs of \nassuming the obligation.  The Coalition proposes that a credit requirement be established \nthat ensures that any emerging buyer default exposure is recognized early, funded \ncontinuously, and contained entirely within the LSE buyer who subscribed to the RBP MWs \n(or received the transferred RBP obligation) over time. \n \nRBP Clearing Constraints \nThe Coalition proposes two clearing constraints for the RBP: (1) a maximum volume-\nweighted average procurement price, and (2) locational commitment requirement. \nATTACHMENT"},{"page":16,"startToken":4473,"endToken":4753,"text":"4 \n \nMaximum Volume Weighted Average Procurement Price \nThe RBP must appropriately compensate resources for taking on RBP commitments, \nincluding the risk associated with taking on those commitments. However, there must be \nreasonable boundaries placed on the overall costs arising from this procurement. Since \nthe auction is not structured to allow load to submit buy-bids indicating their true \nwillingness to pay, the auction clearing must contain an upper limit on LSE cost exposure \nto further derisk the potential for and impact of cost-shifting.  \nThe Coalition proposes a maximum volume-weighted average procurement price cap using \nPoint A of the VRR curve applicable for the 2028/29 Delivery Year, which is approximately \n$555/MW-day.  This is based on (maximum of (1.15 * Gross CONE minus 75% of the EAS \noffset and 0.2 *Gross CONE)).  PJM would commit the resources by ranking the offers by \nvolume-weighted price (in $/MW-day, averaged across the contract term based on the \nresource’s in-service date) and accepting each offer sequentially until the procurement \ntarget is met or price cap is breached. \nExample: Target = 1,000 MW.  \nO1: 250 MW @ $475  \nO2: 250 MW @ $500 \nO3: 250 MW @ $525  \nO4: 250 MW @ $600 \nAll accepted if weighted avg ≤ $555.  \nIf O1 instead was priced at $500, O4 is excluded. \nUnder this clearing constraint approach, the procurement may fall short of the nominal \ntarget if accepting additional supply would violate the average volume-weighted price \nmaximum.  However, this approach acknowledges that resource offers, factoring in the \nuncertainty inherent in the RBP requirements and timing, may result in offers that exceed \n$555/MW-day.  Higher and lower committed offers are acceptable as long as the total \nprocurement average cost is ≤$555/MW-day. \n \n \n \n \nATTACHMENT"},{"page":17,"startToken":4753,"endToken":5007,"text":"5 \n \nLocational Commitment Requirement \nThe amount of RBP capacity procured within rest-of-RTO for delivery into the combined \nMAAC and DOM LDAs cannot exceed a maximum threshold. The Coalition suggests a 500 \nMW value may be appropriate for this constraint, subject to further analysis and \ncoordination with PJM to determine the appropriate MW value for this constraint.  The \npurpose of this locational commitment constraint is to mitigate a scenario where supply \nresources procured through the RBP are located far from the large load it is intended to \nserve, potentially reducing the real-time reliability benefits to that area associated with the \nnew resource. In other words, the Large Load could be located in the MAAC and DOM LDAs \nyet all the RBP committed supply could be in the western part of PJM. This would result in \nsome MAAC and DOM LDA price separation in RPM auctions, exposing all load in those \nLDAs to higher prices. It also could result in increased RTEP costs over time as PJM \nplanning identifies needs to address transmission reliability constraints. \n \nCurrent Tariff Provisions for Reliability Backstop Mechanism \nThe current PJM Tariff provisions for Reliability Backstop Mechanism will be adjusted to not \napply until the 2030/31 Delivery Year such that any triggering of it would occur no earlier \nthan after PJM has cleared three consecutive BRAs where the threshold for the backstop \nhas been met. (ie., the 2020/31 DY BRA clearing short would be the first Delivery Year that \nwould be counted to determine if the threshold were met). \n \n \n \n \n \n \n \n \n \n \nATTACHMENT"},{"page":18,"startToken":5007,"endToken":5042,"text":"6 \n \nThe example below is intended to illustrate conceptually how the registry could be \nused to facilitate the RBP.  This example is illustrative, and for simplicity the MW \nvalues are small for computational ease.\n \nATTACHMENT"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":184,"startToken":0,"endToken":25},{"p":1,"at":184,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":3,"startToken":25,"endToken":568},{"p":3,"at":3,"title":"II. COMMENTS","method":"printed heading","endPage":3,"endAt":17,"startToken":568,"endToken":570},{"p":3,"at":17,"title":"A. The subscription model better aligns procurement obligations with cost-causation","method":"printed heading","endPage":6,"endAt":457,"startToken":570,"endToken":1660},{"p":6,"at":457,"title":"B. The Commission should direct PJM to revise its Opt-Out or at the very least","method":"printed heading","endPage":10,"endAt":4,"startToken":1660,"endToken":3003},{"p":10,"at":4,"title":"C. PJM should resolve an inconsistency in its filing.","method":"printed heading","endPage":10,"endAt":1155,"startToken":3003,"endToken":3191},{"p":10,"at":1155,"title":"III. CONCLUSION","method":"printed heading","endPage":12,"endAt":0,"startToken":3191,"endToken":3366},{"p":12,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":99,"startToken":3366,"endToken":3419},{"p":13,"at":99,"title":"Executive Summary","method":"printed heading","endPage":18,"endAt":228,"startToken":3419,"endToken":5042}]}