{"document":{"slug":"rec-20260821-5322","title":"Protest of East Kentucky Power Cooperative, Inc. to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal","issued":"2026-08-21","accession":"20260821-5322","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"East Kentucky Power Cooperative, Inc.","kind":"protest","file":"sources/filings/text/20260821-5322_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5322","tier":"record","sha256":"1bfba97402f4c05e9a4374241249d3fb28a59bc25ef99abc7a48f6f9dd75d04a","pages":120,"tokens":51089,"emptyPages":[],"textThemes":["credit","adequacy","cost","registry"]},"pages":[{"page":1,"startToken":0,"endToken":285,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n) \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3380-000 \n \n \n) \n \nPROTEST OF \nEAST KENTUCKY POWER COOPERATIVE, INC.  \n \nPursuant to Rule 211 of the Commission’s Rules of Practice and Procedure1 and the \nCommission’s August 3, 2026 “Combined Notice of Filings #1,” East Kentucky Power \nCooperative, Inc. (“EKPC”)2 hereby protests the July 31, 2026 filing3 of PJM Interconnection, \nL.L.C. (“PJM”) proposing revisions to its Open Access Transmission Tariff (“Tariff”) and \nReliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish the \nReliability Backstop Procurement (“RBP”). PJM proposes the RBP to be a one-time procurement \nof new capacity resources intended to address previously identified resource adequacy challenges \nthat have arisen as a result of insufficient capacity commitments in the 2027/2028 and 2028/2029 \nReliability Pricing Model (“RPM”) Capacity Market Auctions (“RBP Proposal”).   EKPC shares \nthe concern that PJM is attempting to address; however, this is not the right fix.  The PJM RBP \nProposal is unjust and unreasonable, improperly expands the role of an Electric Distributor in PJM, \nand is inconsistent with the boundaries of federal and state jurisdiction.  Despite its claims to the \ncontrary, PJM’s RBP Proposal also fails to address concerns raised by the Commission and the \nGovernors of the 13 PJM states regarding the impacts of large loads, specifically ratepayer \nprotection. Indeed, EKPC is significantly concerned about the potential cost shifting that could \n \n1 18 C.F.R. § 385.211 (2026). \n2 EKPC filed a doc-less motion to intervene in this proceeding on August 7, 2026. \n3 PJM Interconnection L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource \nAdequacy Concerns Stemming from Large Loads,” (filed July 31, 2026) (“PJM RBP Filing”)."},{"page":2,"startToken":285,"endToken":590,"text":"2 \noccur, and possibly even defaults that may result from, the inability of any Load Serving Entity \n(“LSE”) to know with certainty its ultimate cost exposure, which may be exacerbated should the \nrealization of the large load itself be affected by the potential exposure to these costs. The \nCommission should therefore reject PJM’s proposed Tariff revisions. \nI. \nBackground \nA. RBP Overview \nAs proposed by PJM, the RBP is a one-time capacity procurement targeting an Unforced \nCapacity (“UCAP”) shortfall identified in the 2027/2028 and 2028/2029 RPM Capacity Market \nAuctions. PJM claims that “[t]o mitigate the potential reliability risks associated with resource \nadequacy shortfalls, PJM is proposing this RBP as a supplementary mechanism to procure \nadditional supply to meet the resource adequacy needs of the PJM Region.”4 PJM asserts that \n“[t]he RBP proposal is a just and reasonable means to address the influx of large loads while \nmaintaining resource adequacy, reliability, and affordability in a manner that respects the divide \nbetween state and federal authorities and avoids disrupting existing commercial arrangements.”5 \nFundamentally, according to PJM, the RBP has the “goal of obtaining commitments of \nnew RBP UCAP MW from eligible resources, called RBP Resources, for a fixed term of up to 15 \nyears, starting with the 2028/2029 Delivery Year and ending with the 2042/2043 Delivery Year.”6  \nThe RBP intends to accomplish this goal by conducting a one-time auction to procure new capacity \nequal to the identified “RBP Target.” The RBP Target is equal to the “Initial RBP Target,” which \nis the region-wide 2028/2029 Delivery Year reliability shortfall observed in the July 2026 Base \nResidual Auction (“BRA”) for Delivery Year 2028/2029, i.e., 6,831.3 MW UCAP, minus \n \n4 PJM RBP Filing at 7.  \n5 PJM RBP Filing at 2.  \n6 PJM RBP Filing at 8."},{"page":3,"startToken":590,"endToken":879,"text":"3 \nQualifying RBP Offset UCAP MW and Opt-Out UCAP MW.7 Qualifying RBP Offset UCAP MW \nis “new capacity voluntarily brought on to the PJM system by new load” that must meet certain \nspecified criteria.8 And Opt-Out UCAP MW will reflect the associated MW quantity of load in the \nzone/area that will be opted-out of the Initial RBP Target. To qualify for this opt-out, the request \nmust be supported by documentation demonstrating an inability to address cost allocation \nassociated with capacity procured in the backstop, along with written support for such opt-out from \nthe relevant state governor, Relevant Electric Retail Regulatory Authority (“RERRA”), and \ninterconnection customers.9 PJM is also proposing another narrow opt-out to permit Electric \nDistributors to decrement the Initial RBP Target by up to the associated MW quantity of load that \nparticipates in a peak shaving adjustment program codified in state law.10 Notably, Fixed Resource \nRequirement (“FRR”) Entities as of the 2028/2029 Delivery Year also will be excluded from the \nRBP. \nImportantly, PJM is not proposing to match specific supply to specific demand.11 In other \nwords, PJM is not utilizing a register or other means to ensure specific LSEs serving large loads \nthroughout the 15-year duration are appropriately charged the costs associated with the \nprocurement or credited with the RBP MW secured on their behalf (to offset any potential for \ncurtailments under the Interim Resource Adequacy Service (“IRAS”) PJM has proposed in Docket \n \n7 PJM RBP Filing at 31.  \n8 PJM RBP Filing at 35. \n9 Proposed Tariff, Attachment DD, Section 18.1(d).  \n10 PJM BRP Filing at 45. \n11 PJM RBP Filing at 33; PJM RBP Filing, Attachment C, “Affidavit of Ms. Danielle Croop,” at P 7 (“Croop \nAffidavit”)."},{"page":4,"startToken":879,"endToken":1198,"text":"4 \nNo. ER26-3515.)12 This is a duration 15-times greater than the commitment secured through any \nof the other markets PJM administers.  \nNor is PJM applying any locational constraints in determining which resources to select \nfor 15-year commitments.  PJM claims that “locational parameters based on today’s conditions \nwould inevitably skew the results and lead to either over-procurement or under-procurement in \ngiven zones based on nothing more than speculation as to the state of the system ten and fifteen \nyears from now.”13 As PJM asserts, “inclusion of a speculative 15-year forward locational capacity \nrequirement at this point in time would simply ignore the role of PJM’s interconnection and \nplanning process as the means to ensure deliverability of capacity resources to load throughout the \nPJM Region.”14 \nAccording to PJM, the RBP is designed to attract new supplies of capacity.15 Under PJM’s \nproposal, resources procured through the RBP must demonstrate a high degree of certainty of \nachieving commercial operation within the next few years and be available to provide capacity \nuntil the end of a fixed, 15-year term.16 Sellers eligible to participate in the RBP, i.e., RBP \nResources or Market Participants selling RBP UCAP MW of RBP Resources, must: “(1) meet \ncollateral requirements prior to participating in the RBP; (2) support eligibility to provide capacity; \n(3) provide capacity; (4) cover penalties for any capacity shortfalls; and (5) bear responsibility for \ndefaults.”17 Similarly, buyers, i.e., LSEs, must: “(1) meet collateral requirements immediately \n \n12 PJM Interconnection, L.L.C., “Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy \nand a Large Load Registry to Address System Reliability,” Docket No. ER26-3515-000 (filed Aug. 13, 2026).  \n13 PJM RBP Filing at 34.  \n14 PJM RBP Filing at 34.  \n15 PJM RBP Filing at 51; Croop Affidavit at P 9. \n16 PJM RBP Filing at 51; Croop Affidavit at P 15. \n17 PJM RBP Filing at 49-51."},{"page":5,"startToken":1198,"endToken":1511,"text":"5 \nprior to each relevant Delivery Year; (2) cover the cost of RBP UCAP MW in accordance with the \nallocation of RBP Charges in each Delivery Year covered by the 15-year resource commitments; \nand (3) bear responsibility for defaults.”18 \nThe RBP will use a pay-as-bid clearing structure with a MW-weighted average levelized \nprocurement cost cap of $555/MW-day UCAP, which is based on Point 1 of the Variable Resource \nRequirement (“VRR”) curve for the 2028/2029 BRA.19 Resources selected through the RBP are \ncommitted for a fixed 15-year term, commencing with the 2028/2029 Delivery Year and extending \nthrough the 2042/2043 Delivery Year.20 PJMSettlement acts as the counterparty to RBP \ncommitments, and RBP Resources must offer as price takers ($0/MW-day) in RPM Capacity \nMarket auctions. PJM proposes to commit resources in the RBP using a pay-as-bid approach, \nwhich PJM explains is more appropriate for a one-time backstop procurement than the single-\nclear-price approach used in the RPM Capacity Market.21  \nAs proposed by PJM, cost allocation under the RBP flows first to Electric Distributor \nzones/areas based on Load Adjustments per RAA Schedule 8, then to LSEs based on state- or \nRERRA-determined RBP Obligations (“RBOs”). In the absence of reported RBOs, PJM’s backup \nmethodology uses Daily Unforced Capacity Obligation ratios. Costs will be allocated to PJM zones \nbased on their pro rata share of the procurement target and then allocated to utilities and other \nLSEs within the zones. As explained by PJM, it “is proposing to allocate daily RBP Charges to \nrelevant Electric Distributor zones/areas, pro rata, based on the zone/area’s assigned share of the \ntotal, region-wide Final RBP Target MW, floored at zero,” incorporating certain Load \n \n18 PJM RBP Filing at 51.  \n19 PJM RBP Filing at 61-62.  \n20 PJM RBP Filing at 8.  \n21 PJM RBP Filing at 65; Croop Affidavit at PP 22-25."},{"page":6,"startToken":1511,"endToken":1846,"text":"6 \nAdjustments.22 Costs allocated to a zone/area may be further adjusted where a zone/area is \nrecognized by PJM as having Qualifying RBP Offset UCAP MW or Opt-Out UCAP MW that \nqualifies for an opt-out.23 PJM is proposing that cost allocation to LSEs within an Electric \nDistributor’s zone/area be based on “the state and/or RERRA-determined allocation of cleared \nRBP UCAP MW to LSEs within each Electric Distributor’s zone/area, as reported by each Electric \nDistributor to [PJM].”24 However, should there be no state- or RERRA-determined RBO allocation \nmethodology, PJM will require the Electric Distributor to further assign the costs that PJM \nassigned to the zone/area to the LSEs in that zone/area according to their Daily Unforced Capacity \nObligation (which commonly is referred to as their “Peak Load Contribution” or “PLC”).   \nPJM’s cost allocation proposal relies heavily on the role of Electric Distributors, requiring \nthem to report to PJM, “the state and/or RERRA-determined allocations of RBP UCAP MW to \nLSEs in their zone(s)/area(s).”25  Without PJM providing the linkage between RBP MW procured \nto specific LSEs, the Electric Distributor must determine how any zone/area offset or opt-out MW \nPJM accepted affects individual LSE obligations. PJM provides no details in the proposed Tariff \nor RAA revisions for how the Electric Distributor must execute upon this responsibility. If an RBO \nis not reported by an Electric Distributor to PJM, the cost allocation will default to applying a \nback-up cost allocation methodology based on “PJM’s status quo method for allocating capacity \ncosts pursuant to RAA, Schedule 8.”26 Overall, PJM claims that its proposed cost allocation \nmethod “recognizes and respects” the division of responsibilities between PJM and states.27  PJM \n \n22 PJM RBP Filing at 97.  \n23 Croop Affidavit at PP 43-46.  \n24 PJM RBP Filing at 97-98 (quoting Proposed Tariff, Attachment DD, Section 18.3(b)(iii)). \n25 PJM RBP Filing at 98.  \n26 PJM RBP Filing at 98-99.  \n27 PJM RBP Filing at 99."},{"page":7,"startToken":1846,"endToken":2207,"text":"7 \nalso claims, without adequate support, that its proposal is consistent with the Ratepayer Protection \nPledge.28 \nPJM proposes to align an LSE’s RBP credit requirement with its cost allocation. Therefore, \nthe extensive role PJM has proposed for Electric Distributors also impacts credit requirements and \nthe collateral an LSE will be required to post. As PJM explains, “for LSEs serving load in an \nElectric Distributor zone/area in which no RBOs have been reported, an LSE’s ‘allocated RBP \nUCAP MW shall equal the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity \nObligation for the zone/area as determined in RAA, Schedule 8.’”29 If an LSE is serving load in \nan “Electric Distributor zone/area in which RBOs have been reported, the LSE will be required to \npost RBP Collateral for its RBO MW (i.e., its allocated RBP UCAP MW amount).”30 PJM has \nproposed that collateral must be posted 45 days before the starts of the Delivery Year, which is \nintended to give Electric Distributors sufficient time to specify the RBO MW for the applicable \nzone/area.31 If an LSE were to default on RBP Charges, any defaulted amount is allocated among \nthe LSEs with RBP Charges “based on [the LSE’s] proportional share.”32 However, the amount to \nbe reallocated will be offset by collateral posted by the defaulting LSE.33 In the event that an RBP \nResource defaults on the payment of RBP shortfall charges, the LSE which anticipated receiving \n \n28See \nTHE \nWHITE \nHOUSE, \nRatepayer \nProtection \nPledge, \n(Mar. \n4, \n2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/. As of August 18, 2026, more than 300 \norganizations across every stakeholder in the power system has signed on to the Ratepayer Protection Pledge, \nincluding Governors of 23 states and more than 250 utilities and cooperatives, including EKPC (see \nhttps://www.whitehouse.gov/ratepayer-protection-pledge/#commitments for a list of entities that have signed the \nPledge).  \n29 PJM RBP Filing at 118 (quoting Proposed Tariff, Attachment DD, Section 18.8(b)(i)(B)(1)). \n30 PJM RBP Filing at 119. \n31 PJM RBP Filing at 120.  \n32 PJM RBP Filing at 122.  \n33 PJM RBP Filing at 122."},{"page":8,"startToken":2207,"endToken":2523,"text":"8 \ncredits will not receive such credits unless there is posted collateral that PJM could provide to the \nLSE.34 \nPJM has also proposed to restrict an FRR entity’s use of bilateral contracts to satisfy its \nFRR obligation. PJM’s proposed language in RAA Section 8.1.D.1.1 states that “[a]n FRR Entity \nmay not use an Existing Generation Capacity Resource not owned by such FRR Entity as of June \n1, 2027 or any resource committed through the Reliability Backstop Procurement to satisfy its \nCapacity FRR Plan.”35 With this proposal, PJM has created ambiguity with respect to the role of \nbilateral contracts for FRR entities while still allowing the potential for existing resources to be \nremoved from the RPM Capacity Market.  \nA. The Stakeholder Process and Coalition RBP Proposal \nPJM claims that “the RBP reflects the input of stakeholders, as well as PJM’s judgment \nand analyses in shaping the specific means to implement the Principles document.”36 During the \nstakeholder process intended to consider options to address the identified capacity shortfall, PJM \nconsidered 13 proposals that were voted on June 30, 2026, through the Critical Issue Fast Path \n(“CIFP”) process. Of those proposals, only the Coalition RBP Proposal, discussed in more detail \nbelow, received the required two-thirds sector-weighted member support. The PJM Board, in its \nJuly 27, 2026 decisional letter, rejected this voluntary, stakeholder-supported proposal and instead \ndirected PJM to file the mandatory procurement framework at issue here.37 PJM acknowledges \nthat only the Coalition RBP Proposal received the required two-thirds sector-weighted member \n \n34 PJM RBP Filing at 122-123.  \n35 Proposed RAA, Schedule 8.1.D.1.1 (emphasis added). \n36 PJM RBP Filing at 9.  \n37 See Paula Conboy, PJM Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop Procurement and \nConnect and Manage, (July 27, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement-and-connect-and-\nmanage.pdf."},{"page":9,"startToken":2523,"endToken":3016,"text":"9 \nsupport.38 The Coalition RBP Proposal represented the consensus of PJM’s diverse stakeholder \nbody, including the LSEs that will bear the financial consequences of the RBP. At the same time \nthe Commission is questioning whether the PJM membership can come to a consensus on \nproposals to address the most pressing challenge facing the PJM region, the membership did, in \nfact, come to agreement.39  \nThe Commission should give significant weight to the fact that the stakeholder body—\nwhich includes the LSEs that will bear the costs—did not support a mandatory procurement, \nespecially one that did not identify or track with specificity who would bear the costs of, or who \nreceives the RBP MW credit resulting from, the procurement. With respect to the Coalition RBP \nProposal, a coalition of entities, including EKPC,40 put forward a proposed registry-based \nsubscription model that would have allowed large loads and their LSEs to secure bilateral contracts \nto manage the risks associated with large loads.41 In the subscription-based model, LSEs would \n \n38 See PJM RBP Filing at 20 (citing PJM Members Committee, MC Voting Results for RBP Proposals Agenda Items \n3L \nthrough \n3X \n(June \n30, \n2026), \nhttps://www.pjm.com/committees-and-groups/committees/mc \n[https://perma.cc/5CSQ-DP4K] (scroll to “Meeting Materials” and search for 2026, click on link for “6.30.2026 \nSpecial Meeting,” scroll to MC Voting Results – Agenda Items 3L to 3X and click on each to view the PDF)). \n39 The Commission has an open docket addressing PJM governance and the stakeholder process, and the Commission \nrecently held a Commission-led technical conference to discuss these issues. See PJM Governance and Stakeholder \nReforms, Docket No. AD26-7-000, “Notice of Commission-Led Technical Conference” (May 12, 2026). And, starting \nSeptember 1, 2026, the Commission’s Director of Dispute Resolution Services “will convene a forum to facilitate \ninterest-based discussions on proposed reforms to PJM’s governance and stakeholder processes” intended “to gather \nfeedback from PJM members and stakeholders, identify areas of consensus and divergence, and evaluate actionable \nreforms to inform a future filing.” See PJM Governance and Stakeholder Reforms, Docket No. AD26-6-000, “Notice \nRegarding Dispute Resolution Procedures” (Aug. 10, 2026). As noted by Chairman Swett, “PJM is facing a grave \nlegitimacy crisis, frustrations are mounting, the collaborative spirit that underpinned the market’s formation is \nfracturing, and some transmission owners are openly discussing leaving the RTO altogether. Put plainly, market \nparticipants have lost confidence in PJM’s decision-making abilities.” PJM Governance and Stakeholder Reforms, \nDocket No. AD26-7-000, Transcript, 8:25-9:6.   \n40 Along with EKPC, the Coalition also included Buckeye Power, Dominion Energy, Duke Energy Ohio, Duke Energy \nKentucky, Duquesne Light Company, Exelon, Old Dominion Electric Cooperative, PPL Electric Utilities Corp., \nSouthern Maryland Electric Cooperative, and the Data Center Coalition. \n41 PJM Critical Issue Fast Path – Reliability Backstop Procurement / Connect & Manage, Joint EDCs & Data Center \nCoalition \nReliability \nBackstop \nProcurement \nPackage \n(June \n30, \n2026), \nhttps://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02f---joint-edcs-and-data-center-\ncoalition---rbp---executive-summary.pdfbp---executive-summary.pdf"},{"page":10,"startToken":3016,"endToken":3477,"text":"10 \nopt into the procurement on behalf of their large load customers, bear associated credit and \ncollateral obligations, and prevent cost-shifting to unrelated retail customers.  Importantly, those \nelements worked together to create a just and reasonable proposal.  Despite PJM’s claims that \ncertain elements were adopted from the Coalition RBP Proposal,42 they were altered and applied \nto a fundamentally different approach, and thus will have a significantly different effect than they \nwould under the Coalition RBP Proposal.43  \nFor the reasons explained herein, EKPC urges the Commission to reject the PJM RBP \nProposal as unjust, unreasonable, and unduly discriminatory.44 EKPC also urges the Commission \nto clarify the revision proposed to FRR will not preclude the ability of any entity electing to utilize \nthe FRR alternative in the future to satisfy its PJM capacity obligations to rely upon existing \nbilateral contracts in its long-standing supply portfolio.   \nII. \nProtest \nPJM claims that the RBP is “a critical safety net designed to address current resource \nadequacy shortfalls.”45 EKPC shares PJM’s concern about resource adequacy and the reliability \nchallenges facing the PJM region, and EKPC supports measures that maintain resource adequacy \n \n42 PJM RBP Filing at 22 (“[T]he PJM Board adopted various concepts from the Coalition RBP Proposal that received \na sector-weighted majority of stakeholder support. Specifically, the proposed (1) maximum volume weighted average \nof all selected RBP Sell Offers, (2) credit requirement for Load Serving Entities, and (3) opt-out from the RBP Initial \nProcurement Target all had their roots in the Coalition RBP Proposal.”). \n43 The Coalition proposed a Large Load Registry maintained by PJM, through which the Large Load or its designated \nLSE would report the MW quantity of Large Load assigned to a specific LSE in a specific zone and the identity of the \nLarge Load (not necessarily meter-level data at time of procurement). At the start of each Delivery Year, the registry \nwould capture Large Load meter-level information to facilitate billing and collateral tracking, accommodate LSE \nswitching in retail choice states, and address corporate ownership changes. The Coalition RBP Proposal’s cost \nallocation method was based on assigning costs and collateral obligations to the cost-causing parties at the time the \nbilateral commitments are made. The Coalition RBP Proposal fixed the RBP commitment at the time of procurement. \nWhile MW quantities could vary over time based on varying in-service dates of committed resources, the obligation \nto pay is fixed at procurement. RBP obligations would be settled separately from RPM Capacity Market but structured \nto net appropriately to avoid double payment for overlapping capacity obligations. \n44 The Commission should reject PJM’s suggestion that the Commission make changes to the as-filed Proposal to \nremedy the fact that the RBP Proposal is unjust, unreasonable, and unduly discriminatory. \n45 PJM RBP Filing at 26."},{"page":11,"startToken":3477,"endToken":3828,"text":"11 \nand recognizes the urgency of PJM’s reliability concerns. But as filed, the PJM RBP Proposal will \nfail to achieve its objectives in a manner consistent with the requirements of the Federal Power \nAct (“FPA”). The PJM RBP Proposal assigns long-term costs and collateral obligations through a \nframework that lacks the specificity necessary to be just and reasonable. In particular, PJM’s RBP \nProposal does not sufficiently identify the LSE responsible for causing the capacity shortage, \nensure that any offsets or opt-outs follow the entity that secured them, or protect LSEs whose \nexisting resource portfolios already support their expected load obligations from incurring \nadditional costs. PJM’s RBP Proposal may attempt to address a legitimate reliability need. But \nsimply attempting to address a legitimate need is not enough to make the RBP Proposal just and \nreasonable, especially where the resulting costs are not reasonably tied to cost causation, and the \ncost allocation and credit and collateral obligations are not knowable, hedgeable, or administrable. \nThese uncertainties, in turn, will frustrate PJM’s stated purpose and serve to actually increase the \ndefault risk that has broader implications for the PJM region. That risk extends to entities like \nEKPC whose supply portfolio contains sufficient resources to serve the load underlying PJM’s \nforecast that was the basis for its calculation of the shortfall the RBP is attempting to address.46  \nFor example, in his Affidavit,47 Mr. Bednarczyk explains that the PJM RBP Proposal is not \njust and reasonable because, as proposed, the RBP “creates cost, credit, collateral, and risk-\nallocation obligations that do not consistently satisfy the principles of transparency, traceability, \nand cost causation.”48  He also provides an analysis as to why the RBP’s cost-and-risk allocation \n46 See PJM Interconnection, L.L.C., Presentation to Post-CIFP Workshop, Reliability Backstop Procurement \nExecution, \nat \n11 \n(Aug. \n10, \n2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260810/20260810-pjm-and-cra-reliability-backstop-procurement-presentation.pdf (showing Table B9b \nfrom the 2026 PJM Load Forecast, which shows EKPC’s initial share of RBP Charges and Allocation to be “0”). \n47 Attachment 1, Affidavit of Adam Bednarczyk (“Bednarczyk Affidavit”). \n48 Bednarczyk Affidavit at P 7."},{"page":12,"startToken":3828,"endToken":4120,"text":"12 \nmechanism fails because a “generalized showing of regional reliability need” is insufficient to \nsupport the “particular RBP rate design” under FPA section 205,49 and the zonal or Electric \nDistributor cost allocation process does not ensure the assignment of RBP obligations to the \nspecific LSE responsible for supplying the large load. Moreover, he explains why Electric \nDistributors are not the same as RAA load-serving parties, and therefore, the conventional role for \nElectric Distributors does not appropriately extend to assigning wholesale cost responsibility.50 \nMr. Bednarczyk explains how the RBP converts what should be a targeted, incremental large-load \ncost-causation problem into a generalized load-ratio obligation that penalizes self-supply LSEs \nthat acted prudently and rewards policies that incentivize inadequate resource planning.51 \nAdditionally, the RBP as proposed “does not directly assign RBP obligations to the LSE \nresponsible for serving the large load that creates the procurement need.”52 This may create an \nincentive, as Mr. Bednarczyk explains, that will “encourage parties to focus on allocation \noutcomes rather than on actions that reduce the reliability impacts of adding large loads without \ncorresponding resources or curtailment arrangements.”53  \nThe Affidavit of Mr. Carl Coscia further elaborates on the concerns with PJM’s credit and \ncollateral elements of the RBP proposal. The credit and collateral requirements also fail to satisfy \nthe Commission’s just and reasonable standard.54 The proposed collateral requirements do not \nsecure a measured exposure,55 and an LSE cannot calculate its collateral posting requirements \n49 Bednarczyk Affidavit at P 7. \n50 Bednarczyk Affidavit at P 42. \n51 Bednarczyk Affidavit at PP 7, 9, 12, 18.  \n52 Bednarczyk Affidavit at P 12. \n53 Bednarczyk Affidavit at P 12. \n54 Attachment 2, Affidavit of Carl F. Coscia (“Coscia Affidavit”). \n55 Coscia Affidavit at PP 7, 120."},{"page":13,"startToken":4120,"endToken":4459,"text":"13 \nbased on the Tariff language proposed.56 Also, PJM proposes to reduce the applicable collateral \nrequirements over time, but does not propose a schedule or precise method for doing so.57 And if \nthere is no reduction, the posted collateral amount may exceed exposure by the 2036/2037 delivery \nyear.58 Moreover, that approximately $10.2 billion “becomes due at a single moment, from a single \nclass of participants, in two instruments,” creates a systemic liquidity risk, which could be \nmanaged by proper sequencing, but is not managed by the RBP proposal.59 \nPJM also performed its own exposure analysis before filing and then departed from it. In \nthe Credit and Securitization Overview presented March 4, 2026, PJM modeled the procurement \nas a fixed-for-float swap and produced a potential future exposure curve that begins at zero, peaks \nbelow $1.2 million per MW within roughly the first third of the term, and then amortizes to zero \nby expiration.60 PJM then filed a flat $1.5 million per MW Credit Rate.61 This is not a case in \nwhich PJM lacked analysis regarding credit exposure; it is a case in which PJM had analysis and \ndid not use it. \nThe RBP Proposal also creates an unjustified distinction among entities that have taken \nsimilar resource adequacy actions with respect to the exclusion of FRR entities but not RPM self-\nsupply entities.62 As proposed, PJM allows an FRR entity that satisfies its resource adequacy \nobligations through qualifying owned and some portion of existing resources to be “insulated from \n \n56 Coscia Affidavit at PP 7, 108. \n57 Coscia Affidavit at PP 109-121. \n58 Coscia Affidavit at PP 116. \n59 Coscia Affidavit at PP 136-153. \n60 PJM Interconnection, L.L.C., Presentation to Reliability Backstop Procurement Workshop, Credit and \nSecuritization \nOverview, \nat \n12 \n(Mar. \n4, \n2026), \nhttps://www.pjm.com/-/media/DotCom/committees-\ngroups/workshops/rbpw/2026/20260304/20260304-item-03---credit-and-securitization-overview---pjm-\npresentation.pdf (“PJM March 4 Credit Overview Presentation”). \n61 PJM RBP Filing at 116-117.  \n62 Bednarczyk Affidavit at PP 59-60."},{"page":14,"startToken":4459,"endToken":4747,"text":"14 \nRBP exposure.”63 In contrast, an RPM Capacity Market LSE that has likewise prudently planned \nto serve its load does not receive comparable treatment under the proposed RBP cost-allocation \nframework.64 As explained in Mr. Bednarczyk’s Affidavit, this raises comparability concerns65 \nand results in undue discrimination between similarly situated participants in the PJM market. \nMoreover, the ambiguity PJM has introduced with respect to what qualifies as an existing resource \nfor an FRR entity creates additional market design concerns, particularly for entities that rely \nheavily on long-term, bilateral contracts.66 \nThe PJM RBP Proposal creates unmitigable financial and reliability risk for LSEs that \nprudently planned for their load or otherwise did not cause the residual RBP procurement need. It \nalso creates a potential significant burden for those LSEs that may not have sufficiently planned \nand may have anticipated costs from RBP associated with only their contribution to the need. If \nthe weight of the imposed burden causes defaults, that increases risk for the entire market. The \nfinancial and reliability risks and burdens imposed on all market participants will inhibit growth \nand ultimately discourage investment in the PJM region. Moreover, and most strikingly, the RBP \nProposal also undermines the Administration’s and PJM state Governor’ ratepayer-protection \nobjectives because it has the potential to shift large-load-driven costs to customers and LSEs that \ndid not create the need for those costs. Indeed, the default allocation provision explicitly would \nassign costs to all LSEs in a zone/area without regard to whether those affected zones/aeras serve \na new large load.  Therefore, the Commission should reject the RBP Proposal.  \n \n63 Bednarczyk Affidavit at P 60. \n64 Bednarczyk Affidavit at P 60. \n65 Bednarczyk Affidavit at P 60. \n66 Bednarczyk Affidavit at P 63."},{"page":15,"startToken":4747,"endToken":5086,"text":"15 \nA. \nThe PJM RBP Proposal is Not Just and Reasonable.  \na. PJM’s RBP Proposal is Unjust and Unreasonable Because the Resulting \nRate Impact is Uncertain.  \nUnder section 205 of the FPA, rates must be “just and reasonable.”67 Section 205(c) of the \nFPA “requires rate filings to recite ‘the … practices … affecting such rates and charges.’” The \nCommission’s regulations also require rate schedules to set forth “clearly and specifically … the \nclassifications, practices, rules and regulations affecting such rates, charges, classifications, \nservices … ”68 The PJM RBP Proposal does not provide sufficiently bounded and causation-based \ninputs for determining which LSE is responsible for RBP charges. The PJM RBP Proposal does \nnot explain how qualifying offsets or opt-outs follow the responsible LSE such that its allocation \nappropriately can be calibrated or reduced to zero. Nor does it make clear when collateral \nobligations attach. Relying on the Electric Distributor and RERRA to make determinations or \notherwise effectuate downstream processes does not replace the need to ensure the appropriate \nwholesale entity is allocated the costs. Therefore, the cost allocation put forward as part of the PJM \nRBP Proposal fails to meet this standard, and is not just and reasonable.  \nThe Commission has rejected proposed cost allocations when the proposals, like the PJM \nRBP Proposal here, lack specificity or do not allow impacted customers to be able to estimate the \ncost impact. In California Power Exchange Corp., for example, the Commission rejected the cost \nallocation plan of the California Power Exchange Corporation (“PX”) for its Block-Forward \nMarket because the plan “lack[ed] specificity with regard to items which will not be directly \nassigned” and “ha[d] not linked the allocation methodologies to particular costs to be allocated.”69 \n \n67 16 U.S.C. § 824d (2018). \n68 18 C.F.R. § 35.1(a). See also City of Cleveland v. FERC, 773 F.2d 1,368, 1,376 (D.C. Cir. 1985) (citing 18 C.F.R. \n§§ 35.1(a), 35.2(b)). \n69 Cal. Power Exch. Corp., 88 FERC ¶ 61,249, 61,795 (1999)."},{"page":16,"startToken":5086,"endToken":5344,"text":"16 \nPX argued that it was “impossible to be more explicit about the methodologies for allocating \nspecific costs” because the Block-Forward Market was “in [its] infancy,” but the Commission was \n“not persuaded by PX’s unsupported claim” and directed the PX to “clarify and support which cost \nallocation methodology is applicable to each particular cost category.”70 As with the PX cost \nallocation proposal, the cost allocation proposed in the PJM RBP Proposal lacks specificity and \ndoes not provide sufficiently bounded and causation-based inputs for determining which LSE is \nresponsible for RBP charges. Therefore, the Commission should similarly reject the PJM RBP \nProposal.  \nSimilarly, in Tri-State, the Commission issued a show cause order finding Tri-State \nGeneration and Transmission Association Inc.’s (“Tri-State”) Contract Termination Payment \n(“CTP”) calculations were impermissibly vague.71 The Commission held that Tri-State’s Open \nAccess Transmission Tariff, Bylaws, and Rate Schedules (“Tri-State Tariff”) was “impermissibly \nvague because it lack[ed] detailed procedures governing when and how a utility member may \nobtain a CTP methodology calculation.”72 The Commission found that since the CTP methodology \nrelied on information proprietary to Tri-State, “utility members cannot estimate their own CTP \npayments or reasonably predict the impacts of a membership withdrawal.”73 The Commission \nreasoned that the failure to provide “clear and transparent procedures” makes it “difficult, if not \nimpossible, for Tri-State’s members to make a reasoned assessment as to whether to terminate \ntheir membership.”74   \n \n70 Id. \n71 Tri-State Generation & Transmission Ass’n, 175 FERC ¶ 61,229 (2021). \n72 Id. at P 12. \n73 Id. \n74 Id. at P 13."},{"page":17,"startToken":5344,"endToken":5712,"text":"17 \nAs was the case in Tri-State, PJM has failed to provide “clear and transparent procedures” \nto allow an LSE to determine the amount of costs it may be allocated under the PJM RBP Proposal. \nAs Mr. Bednarczyk explains, the RBP cost allocation process proposed by PJM “does not provide \na transparent means for an LSE to assess its wholesale RBP exposure, evaluate the benefits of \nqualifying offsets or opt-outs, understand its related credit obligations, or determine whether its \nactions will make it reliability neutral.”75 Pursuant to the PJM RBP Proposal, only certain LSEs in \nthe zone/area may be charged, or all LSEs in a zone/area will be charged.76 But, the responsible \nLSE is not known with sufficient specificity based on the PJM RBP Proposal. It both depends on \nthe Electric Distributor RBO allocation determinations, possibly informed by the RERRA, and the \nDelivery Year to Delivery Year changes to large load growth over the 15-year duration. PJM has \nnot proposed to lock in the allocation in the first Delivery Year in which the costs will be allocated. \nLSEs will be assigned costs each Delivery Year over the 15-year duration.  Moreover, PJM does \nnot propose to insulate any LSE that provided Qualifying RBP Offset UCAP MW or accepted \nOpt-Out to decrement the procurement target from costs associated from the RBP procurement. \nThe RBP Proposal is silent in this regard.  Most concerning, PJM’s proposal for a default allocation \nmethodology, should the Electric Distributor not report an RBO, is that all LSEs in the zone/area \nwill be held accountable to pay the costs PJM assigns to the zone/area, regardless of whether they \nserve any large load or contributed to the need for backstop procurement.  The uncertainty of being \nassigned costs, as well as the magnitude of the costs that may be assigned, should the large loads \nnot materialize in each zone/area as PJM anticipated in establishing the procurement target, will \nitself impact whether large loads materialize as forecasted.77  It is nearly impossible for an LSE, \n \n75 Bednarczyk Affidavit at P 14. \n76 PJM RBP Filing at 96-100; Croop Affidavit at 41 (costs are allocated based on RBO).  \n77 Bednarczyk Affidavit at PP 52-53."},{"page":18,"startToken":5712,"endToken":6044,"text":"18 \nbased on the information available to it in PJM’s RBP Proposal, to determine the amount of costs \nit may be allocated. Therefore, the Commission should reject the RBP Proposal. \nThe PJM RBP Proposal is also distinguishable from Commission-approved formula rates \nin which the resulting rate may not be known with exact precision at the time of filing or in future \nyears as the formula rate is implemented.  But the PJM RBP Proposal lacks the important \nguardrails that make formula rates acceptable. For example, the D.C. Circuit has noted that “the \nCommission’s acceptance of formula rates is premised on the rate design’s ‘fixed, predictable \nnature,’ which both allows a utility to recover costs that may fluctuate over time and prevents a \nutility from utilizing excessive discretion in determining the ultimate amounts charged to \ncustomers.”78 The D.C. Circuit acknowledged that “there is undoubtedly some irreducible \nminimum of detail needed for a valid formula rate.”79 However, the court emphasized that “the \namount of the detail in a formula rate is not the dispositive consideration.”80 The key question is \nnot whether a rate filing falls short “of some absolute prescribed standard literally set forth in the \nstatute and regulations,” but “of the minimum specificity that the Commission could reasonably \nrequire.”81 \nHere, PJM’s proposed cost allocation is neither fixed nor predictable. The problem is not \nmerely that the final dollar amount to be allocated may be calculated later; formula rates often \ninvolve later inputs and the Commission has found that may be just and reasonable. The PJM RBP \nProposal does not adequately define who is responsible for the charges (which affects how much \n \n78 Pub. Utils. Comm’n of Cal. v. FERC, 254 F.3d 250, 254 (D.C. Cir. 2001) (citing Ocean State Power II, 69 FERC \n61,146, 61,552 (1994)) (“PUC”).    \n79 PUC, 254 F.3d at 255 (citing City of Cleveland v. FERC, 773 F.2d 1368, 1376–77 (D.C. Cir. 1985)). \n80 Id. \n81 Id."},{"page":19,"startToken":6044,"endToken":6373,"text":"19 \nof the zone/area assigned costs any individual LSE may receive) or how the charges are tied to \nincremental cost causation. \nPJM’s RBP Proposal also lacks critical details regarding how changes that could impact \ncost allocation will be accounted for. For example, EKPC presumes that PJM will not bill for the \ncosts associated with generators that do not come online and therefore have not satisfied their \nrequirements to be eligible for payment. But, that is not specified anywhere in the PJM RBP \nProposal.  EKPC also presumes that the zone/area allocation will change Delivery Year to Delivery \nYear because large loads are projected to continue growing. PJM’s proposal is silent as to how \nload growth between Delivery Years over the 15-year horizon of the RBP obligation will be \nhandled.  Certainly, under the proposed default allocation methodology, LSE obligations would \nchange Delivery Year to Delivery Year.  It is unclear how LSEs could discern their obligation, and \nit is unclear how PJM would manage the credit obligation in such situations.82 PJM appears to \nassume, based on its proposed credit provisions, that the obligation is fixed in the first Delivery \nYear during which costs would be assigned, and can only decrement at some point, without \nexplaining how, in the future. \nPJM assumes that a RERRA can determine a cost allocation methodology that fixes the \nconcerns caused by PJM’s decision to allocate costs to zone/areas and not directly to LSEs causing \nthe need for the RBP procurement.  However, PJM has not explained the impact on a cost \nallocation if a zone crosses state boundaries. States or RERRAs must be able to ensure that costs \nare appropriately allocated to the correct entities. But, that assumes that the costs are correctly \nallocated in the first instance at the PJM level. If a zone/area crosses state or RERRA boundaries \n(for example, the Dominion Energy zone, which is in both Virginia and North Carolina), under the \n \n82 See Coscia Affidavit at P 47."},{"page":20,"startToken":6373,"endToken":6725,"text":"20 \nPJM RBP Proposal, a state may not be able to fully assign the costs to the correct entities because \nit will not know who is responsible for the charges (since PJM is not tracking that large load \ninformation), and the state will only be able to determine the cost allocation and assignment to the \ncustomers in its state. It is also unclear whether PJM is properly using the information from Table \nB9b from the 2026 PJM Load Forecast to ensure Electric Distributor zone/areas receive correct \nallocations from PJM.83 For example, North Carolina Electric Membership Corporation \n(“NCEMC”) is located in the Dominion Energy zone. But, the NCEMC area is not currently \nreflected as “0” in PJM’s Initial Allocation to Electric Distributor zone/area table. Therefore, as \ninitially presented by PJM, NCEMC could be subject to some kind of cost allocation if the cross-\nstate cost allocation is not appropriately determined.  \nMoreover, PJM’s proposal to use a default allocation based on Daily Unforced Capacity \nObligation if the more targeted allocation process does not produce an LSE-specific result is also \nunjust and unreasonable. When a state or RERRA has not determined an RBO for LSEs within a \nzone/area, PJM defaults to allocating costs based on each LSE’s Daily Unforced Capacity \nObligation ratio share. This backup methodology socializes RBP costs across all load within the \nzone – including LSEs serving customer bases that contributed nothing to the capacity shortfall. \nThis violates the fundamental principle that “costs must be allocated to entities that cause them.”84 \nAs explained in the Bednarczyk Affidavit, the “Daily Unforced Capacity Obligation is a broad \ncapacity allocation metric,” and “it does not identify the LSEs that created the residual \nprocurement need.”85 Reliance on a preexisting cost allocation methodology that may have been \n \n83 See PJM Interconnection, L.L.C., Presentation to Post-CIFP Workshop, Reliability Backstop Procurement \nExecution, \nat \n10, \n(Aug. \n10, \n2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260810/20260810-pjm-and-cra-reliability-backstop-procurement-presentation.pdf. \n84 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254. at 1260 (D.C. Cir. 2018). \n85 Bednarczyk Affidavit at P 17."},{"page":21,"startToken":6725,"endToken":7056,"text":"21 \napproved as just and reasonable in a different context does not provide justification to use it as the \ndefault methodology in this case. And hoping that the Electric Distributor or state/RERRA \ndetermines an appropriate allocation methodology such that PJM’s proposed default methodology \nmay be avoided is clearly insufficient too. \nThe Commission must support its rate design decisions with “substantial evidence.”86 PJM \nhas offered no evidence that allocating costs based on total zonal load obligations bears any \nreasonable relationship to the load growth that caused the shortfall. LSEs with no or minimal large \nload growth may nonetheless be allocated disproportionate costs due to improper accounting of \nthe offsets and opt-outs or the use of the default allocation methodology. The vagueness inherent \nin PJM’s proposal virtually assures this. PJM’s proposal provides no clear nexus between cost \ncausation and cost allocation. For example, even where an LSE such as EKPC has not been shown \nto cause or contribute to the RBP procurement target, PJM’s RBP Proposal will leave EKPC \nexposed to other LSEs’ payment default risk, and potential associated collateral requirement risk, \nbecause PJM has proposed mechanisms that do not reliably assign costs to the LSEs that caused \nthe incremental need. PJM’s RBP Proposal is unjust and unreasonable.  \nb. The Proposed Collateral Requirements are Unjust and Unreasonable. \nPJM’s proposed collateral requirements further exacerbate the unjustness and \nunreasonableness of PJM’s RBP Proposal’s cost allocation because an LSE’s RBP credit \nrequirement will be aligned with its cost allocation.87 If an LSE’s cost allocation cannot be \ndetermined with specificity based on PJM’s RBP Proposal, its credit requirement will also be \n \n86 See, e.g., Elec. Consumers Res. Council v. FERC, 407 F.3d 1232, 1233 (D.C. Cir. 2005) (“Upon applying the usual \nAPA standard, we conclude that the Commission’s approval of the rate design is supported by substantial evidence in \nthe record and is not otherwise arbitrary and capricious.”). \n87 PJM RBP Filing at 118. See also Bednarczyk Affidavit at P 26."},{"page":22,"startToken":7056,"endToken":7358,"text":"22 \nuncertain. A collateral requirement may only be just and reasonable if it stems from “clear and \nconsistent credit policies.”88 Under PJM’s RBP Proposal, PJM will first calculate an aggregate \ncollateral requirement.89 Then, PJM will allocate that collateral requirement to individual LSEs.90 \nAn LSE should not have to post substantial RBP collateral for an obligation that PJM has \nnot properly linked to exposure. As Mr. Coscia notes, there is a timing gap evident in the load \nrequirement that demonstrates that this requirement is not tied to exposure.91 Mr. Coscia explains \nthat “[c]ommitments bind when results post on December 2, 2026,” and the first Delivery Year’s \nexposure is known at the moment the commitment binds because the “2028/2029 [BRA] has \nalready cleared at $325.00/MW-day.”92 Then, “[t]he 2029/2030 results post on December 22, \n2026.”93 Therefore, within three weeks of commitment (i.e., December 2, 2026), “two Delivery \nYears are priced, and on the adjusted target of approximately 6,000 MW the exposure they \nrepresent is approximately $1.0 billion, taking the 2029/2030 year at the $333.44 proxy” defined \nin Mr. Coscia’s Affidavit. This is exposure that has been quantified, yet PJM requires no collateral \nat all until roughly April 17, 2028.94 Rather, PJM requires “approximately $9.1 billion on the same \ntarget against an exposure it has never quantified, beginning at the point when a substantial part of \nthe position has become knowable and is no longer in doubt.”95 \n \n88 Credit Reforms in Organized Wholesale Electric Markets, 133 FERC ¶ 61,060, P 2 (2010), order on reh’g, 134 \nFERC ¶ 61,126 (2011).  \n89 PJM RBP Filing at 118.  \n90 PJM RBP Filing at 115. \n91 Coscia Affidavit at P 204.  \n92 Id. \n93 Id. \n94 Id. \n95 Id."},{"page":23,"startToken":7358,"endToken":7690,"text":"23 \nMoreover, it is clear from PJM’s proposal with respect to collateral requirements for sellers \nthat neither the seller’s collateral requirement nor the LSE/buyer collateral requirement was \nderived from measured exposure. The two requirements imply contradictory RPM price paths. As \nexplained by Mr. Coscia, the RBP Proposal’s proposed seller collateral is adequate only if RPM \naverages at or above $532.80/MW-day, and above $564 across the thirteen unpriced and \nuncollared years.96 But, the LSE figure corresponds to the exposure only if RPM averages at or \nbelow $281.03.97 No single price path satisfies both. This shows that neither figure was derived \nfrom measured exposure and are irreconcilably in conflict – the exact opposite of just and \nreasonable. \nIn addition, the same obligation is also collateralized twice. The RBP Charge is secured in \nadvance by the Credit Rate, and once the Delivery Year begins and RBP Charges are billed, those \nsame charges enter the LSE’s Peak Market Activity through the ordinary operation of Attachment \nQ and are secured again. Proposed Section 18.8(b) does not net the two collateral requirements.98 \nMoreover, an LSE should not have to post a collateral requirement based on a default \nallocation rather than the LSE’s own load-serving obligation and its inability or failure to provide \nQualifying RBP Offset UCAP MW or Opt-Out UCAP MW.99 Nor should an LSE have to post \ncollateral for an obligation that may be resolved later through an Electric Distributor or \nstate/RERRA cost allocation determination. Requiring an LSE to post collateral based on any of \nthe foregoing is unjust and unreasonable. \n \n96 Coscia Affidavit at P 203. \n97 Coscia Affidavit at P 203. \n98 Coscia Affidavit at P 98. \n99 Coscia Affidavit at P 51 (“[S]ection 18.8(b)(i)(B)(2) provides that the LSE ‘may be required to post’ collateral based \non ‘the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined \nin RAA, Schedule 8.’”)."},{"page":24,"startToken":7690,"endToken":8024,"text":"24 \n Section 18.8, as proposed, requires an LSE to post collateral prior to the start of a delivery \nyear.  However, it is not just and reasonable to require an LSE to post collateral before PJM has \ncalculated the zone/area initial allocation, applied all recognized offsets and opt-outs, finalized the \nzone/area LSE-specific cost allocation, and provided sufficient transparency for the LSE to \nunderstand and, if warranted, challenge the obligation. The LSE credit requirement alone is $1.5 \nmillion per committed RBP MW.100 This means LSEs could collectively face credit requirements \nexceeding $10 billion.101 Applying the credit requirement ahead of those steps most certainly will \nresult in a significant credit burden being placed on LSEs that had no role in creating the reliability \nshortfall. What is worse, those LSEs may lack the financial capacity to absorb such obligations, \nleaving other LSEs in PJM to face allocations caused by an LSE defaulting on its payment \nobligations. \nPJM’s own analysis underscores that this is not a theoretical concern. Before filing, PJM \nidentified 105 LSEs, only 24 of which were investment grade with 81 sub-investment grade, and \nreported that 46 percent of LSEs had tangible net worth below $5 million and 30 percent below $1 \nmillion.102 PJM stated before filing that those figures indicated limited financial capacity. \nNonetheless, PJM selected a collateral rate that would impose substantial liquidity pressure on that \nsame population. \nThis risk of picking up a collateral obligation is particularly acute for smaller LSEs that do \nnot serve a large load. Absent separate collateral support from a large load customer under a supply \nagreement, the required collateral could be significant relative to the LSE’s financial resources and \ncould impose material financial harm. The disproportion is evident on either measure of the \n \n100 PJM RBP Filing, Attachment D, “Affidavit of Ms. Gwen Kelly” at P 33. \n101 See Coscia Affidavit at PP 7, 62-71.  \n102 Coscia Affidavit at PP 138, 192. See also PJM March 4 Credit Overview Presentation at 7."},{"page":25,"startToken":8024,"endToken":8335,"text":"25 \nobligation secured. The RBP settles as a contract for differences, meaning that in each Delivery \nYear, load pays the difference between the RBP price and the RPM clearing price, not the RBP \nprice itself.103 Measured against the maximum gross annual commitment value before any offset \nfor RPM revenues – approximately $1.38 billion at the $555 maximum willingness to pay and the \nInitial RBP Target – the proposed collateral requirement of approximately $10.2 billion is \napproximately 740% of one year’s gross commitment value.104 But that gross figure is not the \namount billed to load. At the 2028/2029 Base Residual Auction clearing price of $325.00/MW-\nday, the amount billed to load in the first Delivery Year is approximately $573 million, against \nwhich the collateral requirement is approximately 1,790%.105 PJM has thus sized collateral as \nthough load owed the full contract price, when the Tariff obligates load to pay only a difference \nbetween two prices. \nThat burden is particularly stark in the zones receiving the largest allocations. Under PJM’s \nown allocation, the NVEC zone is assigned 1,302.6 RBP UCAP MW, translating into \napproximately $1.954 billion of collateral at the proposed $1.5 million Credit Rate.106 For the \ncooperative serving that zone, the requirement exceeds total assets of roughly $1.716 billion, total \nequity and margins of approximately $920 million, and cash and temporary investments of only \nabout $243 million.107 Even at a carrying cost of just 100 basis points, maintaining that collateral \nwould consume roughly 94% of a year’s operating margins, with the burden rising substantially at \nhigher financing costs.108 If a requirement of this magnitude strains the balance sheet of an \n \n103 Coscia Affidavit at P 67.  \n104 Id. \n105 Id. \n106 Coscia Affidavit at P 140.  \n107 Coscia Affidavit at P 141. \n108 Coscia Affidavit at P 142."},{"page":26,"startToken":8335,"endToken":8606,"text":"26 \ninvestment-grade, member-owned cooperative operating without a parental guarantee, PJM’s own \ndata raise serious concerns about its impact on the broader LSE population, 77% of which PJM \nclassified as sub-investment grade and 46% of which have tangible net worth below $5 million.109 \nNeither figure bears any relation to PJM’s own practice. PJM’s collateral across every \nmarket it operates and every class of participant in them has run between approximately nine and \nthirteen percent of annual market activity. The proposed requirement is therefore between \napproximately fifty-seven and eighty-five times that intensity measured against gross commitment \nvalue, and between approximately 138 and 206 times measured against the amount actually billed \nto load. The magnitude of this proposed collateral requirement “stands apart from anything in \nPJM's experience.”110 An unprecedented collateral requirement with such significant uncertainty \ncannot be just and reasonable.  \nWhile PJM consents in advance to the Commission modifying or severing any element of \nthe proposed Tariff and RAA language,111 there is an insufficient basis for the Commission to \nprovide a substitute collateral requirement that is justifiable and reasonable. PJM’s consent \nsupplies authority to modify; it does not supply a record to modify on. As Mr. Coscia explains, the \nappropriate requirement cannot be determined from the filed formula alone, the analysis on which \nany rate would rest was never performed, and the present record does not contain the participant-\nspecific financial and liquidity information needed to perform it.112 Selecting a substitute figure on \n \n109 PJM March 4 Credit Overview Presentation at 7. \n110 Coscia Affidavit at P 61. \n111 PJM RBP Filing at 3. \n112 Coscia Affidavit at PP 209-210."},{"page":27,"startToken":8606,"endToken":8961,"text":"27 \nthis record would repeat the defect rather than cure it. There is no support for the Commission to \nmake such a determination off.113 \nThe RBP Proposal collateral requirements are also unjust and unreasonable because the \nrequirement is not distributed evenly but instead is concentrated among LSEs that receive RBP \nObligations.114 This creates systemic liquidity risk among the entities required to post collateral at \nthe proposed levels. In an example prepared by Mr. Coscia, the Northern Virginia Electric \nCooperative (“NOVEC”) Zone illustrates this risk.115 Based on PJM’s RBP Proposal, NOVEC’s \ninitial allocation (RBP UCAP MW) is 1302.6 MW, and a Zonal Collateral Obligation at $1.5 \nmillion per MW results in a $1.954 billion collateral requirement.116 The cooperative serving this \nzone has $1.716 billion of total assets, $243.2 million of cash and temporary investments, and \n$34.4 million of cash collateral already posted to PJM, which continues to be required.117 \nConsidering the most favorable assumptions available, the cost to maintain a letter of credit in \nthese circumstances could be approximately $19.5 million annually (or much more, as explained \nby Mr. Coscia) and that cost would have to be borne by the cooperatives’ customers.118 This \nexample is illustrative of the systemic risk but “is not the limit of the problem.”119  \nThe concentration problem also extends to the instruments PJM expects LSEs to use. As \nof July 30, 2026, PJM held approximately $6.87 billion in letters of credit issued by 43 institutions, \n \n113 PJM distinguishes NRG Power Marketing LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) on the grounds that the \nRBP Proposal was Board-authorized and not stakeholder-endorsed. See PJM RBP Filing at 3, n.8. However, here, the \nPJM Board rejected a stakeholder-endorsed proposal that received the only sector-weighted supermajority, the \nCoalition RBP Proposal.  \n114 Coscia Affidavit at P 139. \n115 Mr. Coscia prepared this example based on publicly available data in a federal regulatory filing.  \n116 Coscia Affidavit at PP 140-41. \n117 Coscia Affidavit at P 141. \n118 Coscia Affidavit at PP 142-43.  \n119 Coscia Affidavit at P 144."},{"page":28,"startToken":8961,"endToken":9268,"text":"28 \nwith the ten largest accounting for approximately 65 percent and two individual institutions each \nexceeding 10 percent.120 Satisfying the RBP requirement predominantly through letters of credit \nwould more than double PJM’s letter-of-credit exposure, drawn substantially from the same \ninstitutions. \nIt is important to note that if the collateral obligation cannot be met, as proposed by PJM, \nit would not be extinguished.121 Instead, Tariff Section 18.9(a) reallocates the defaulted charge pro \nrata to the remaining LSEs, and Operating Agreement (“OA”) Section 15.2.2 extends what remains \nto Members in the residual tier with no RBP allocation at all, like EKPC. Therefore, an entity like \nEKPC, which is not anticipating any RBP Obligation in its zone/area,122 is still at risk and no party \nis posting collateral against that exposure. This astonishing misalignment of collateral obligations \nand cost causation severely runs afoul of the Ratepayer Protection Pledge and is plainly \nunreasonable and unjust. \nc. PJM’s Proposal with respect to Decrementing the Procurement Target and \nCrediting Offsets Is Unjust and Unreasonable. \nPJM’s proposed RBP uses “decrementing” in two primary contexts. First, the Initial RBP \nTarget is decremented pre-procurement by Qualifying RBP Offset UCAP MW and opt-out MW \nto arrive at the Final RBP Target.123 Second, post-procurement, committed RBP UCAP MW may \nbe effectively reduced through generation rescission for failure to materialize, changes in ELCC-\nbased accreditation, or Transmission Owner exit scenarios, each of which carries distinct financial \n \n120 Coscia Affidavit at P 146 (citing PJM Interconnection, L.L.C., Presentation to Risk Management Committee, \nCredit \nRisk \nMetrics, \n4 \n(Aug. \n18, \n2026), \nhttps://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/rmc/2026/20260818/20260818-informational-only---credit-metrics---august-2026.pdf). \n121 See Coscia Affidavit at P 153. \n122 Coscia Affidavit at PP 169-70. \n123 PJM RBP Filing at 35; Proposed Tariff Section 18.1(b)."},{"page":29,"startToken":9268,"endToken":9574,"text":"29 \nand credit consequences.124 PJM’s RBP Proposal does not, however, adequately distinguish \nbetween reducing the aggregate procurement target for any of those reasons and shielding LSEs \nwhose qualifying supply offsets reduced the procurement target amount. There is no provision in \nthe proposal that requires such LSEs to be insulated from RBP charges. A reduction in the regional \nor zonal procurement target is not equivalent to an LSE-specific cost-allocation credit.  As noted \nby Mr. Bednarczyk, “reducing the aggregate procurement target is not the same as protecting the \nLSE that supplied or sponsored the offset from RBP Charges, collateral obligations, or default-\nallocation risk,” and therefore, “[t]he tariff should clearly state whether, and how, a recognized \noffset follows the associated LSE or load when PJM calculates LSE-specific RBO MW, RBP \nCharges, and collateral requirements.”125  \nAdditionally, PJM’s failure to explicitly shield LSEs from cost assignment is especially \nproblematic for LSEs who did not contribute to the need for the RBP procurement. There is no \nprovision that insulates them from RBP charges either. And given the duration of the obligations \nimposed by the RBP – obligations that could last as long as 15 years – the risk is more significant \nthan a standard double payment. As Mr. Bednarczyk highlights, “an LSE that has already planned \nprudently and secured adequate resources could nonetheless incur a second long-term obligation \nthat provides little or no additional reliability benefit. That outcome weakens incentives for \nproactive resource planning, socializes the benefits of prudent mitigation, and leaves the planning \nLSE exposed to residual charges, collateral obligations, and default-allocation risk.”126  \nPJM is allowing decrementing of the procurement target only for providing qualifying new \ngeneration supply, while failing to provide comparable recognition for existing owned resources, \n \n124 PJM RBP Filing at 55, 60-61, 94-95. \n125 Bednarczyk Affidavit at P 27. \n126 Bednarczyk Affidavit at P 34."},{"page":30,"startToken":9574,"endToken":9917,"text":"30 \nlong-term bilateral contracts, or other forward actions that may already support an LSE’s \nincremental load obligations.127 That restriction ignores prudent planning and ignores the \nCommission’s cost-causation principles.  \nTo be just and reasonable and not unduly discriminatory or preferential under FPA section \n205,128 rates must reflect the cost causation principle that “all approved rates reflect to some degree \nthe costs actually caused by the customer who must pay them.”129 The Commission analyzes \ncompliance with the cost causation principle “by comparing the costs assessed against a party to \nthe burdens imposed or benefits drawn by that party.”130 Courts have held that to “the extent that \na utility benefits from the costs of new facilities, it may be said to have ‘caused’ a part of those \ncosts to be incurred, as without the expectation of its contributions the facilities might not have \nbeen built, or might have been delayed.”131 The courts have emphasized that the Commission must \nhave an “articulable and plausible reason to believe that the benefits are at least roughly \ncommensurate with” the allocation of the costs.”132 And it is the Commission’s fundamental \nmission to ensure that rates satisfy that standard.133 \nPJM’s RBP Proposal with respect to decrementing fails to meet this cost causation \nrequirement in numerous ways. For example, even where PJM recognizes Qualifying RBP Offset \nUCAP MW, the proposed Tariff revisions do not clearly require the corresponding benefit to \nreduce the RBO MW, RBP charge, or collateral exposure of the LSE or load that supplied the \n \n127 PJM RBP Filing at 35-36.  \n128 16 U.S.C. § 824d (2018). \n129 KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992). \n130 Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004). \n131 Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009). \n132 Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009). \n133 See, e.g., FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 277 (2016)."},{"page":31,"startToken":9917,"endToken":10231,"text":"31 \noffset. Under either the Electric Distributor (with state/RERRA support) allocation determinations, \nor the PJM default allocation mechanism, an LSE that supplied qualifying offsets or already has \nsufficient existing capacity resources may still pay RBP costs and be required to post collateral \nbecause it is not guaranteed it will receive the benefit of any offsetting decrement. As explained \nby Mr. Bednarczyk, “[i]f the benefit of a Qualifying RBP Offset UCAP MW is applied only at a \nzonal or Electric Distributor level and is not traced to the LSE that undertook the mitigation action, \nthe proposal weakens the incentive for voluntary forward procurement and load-management \nmeasures.”134 Without a rule requiring offsets and existing-supply recognition to follow the \nresponsible LSE or load, the RBP unfairly socializes the benefit of prudent resource planning while \nleaving those LSEs that adequately covered their load obligations exposed to residual charges and \ncollateral. That result violates the Commission’s cost-causation principles because costs may be \nassigned to loads that did not cause the need for those costs. Therefore, the PJM RBP Proposal is \nalso unjust and unreasonable for yet another reason.  \nd. PJM’s RBP Proposal is Not Just and Reasonable Because it Lacks a \nLocational Requirement.   \nPJM seeks approval of a 15-year, region-wide backstop procurement but has not shown \nthat the procured capacity will be deliverable to, or operationally useful for, the loads identified as \ndriving the need for the procurement and responsible for its costs. Under FPA section 205, that \nshowing is an important element of establishing that the proposal is just and reasonable. The fact \nthat a procurement adds capacity somewhere in the PJM region does not, by itself, demonstrate \nthat it will address the specific reliability concern identified by PJM or that the allocation of costs \nis reasonably aligned with expected benefits. The filing does not provide sufficient support on \n \n134 Bednarczyk Affidavit at P 38."},{"page":32,"startToken":10231,"endToken":10506,"text":"32 \nthese points. PJM proposes to allow resources that satisfy the eligibility criteria to locate anywhere \nin the PJM region without regard to the Capacity Emergency Transfer Objective/Capacity \nEmergency Transfer Limit analysis that underlies the RPM Capacity Market Locational \nDeliverability Areas (“LDAs”). However, the existence of LDAs under Tariff Attachment DD \nreflects that there are load pockets and constrained areas in PJM where transmission import \ncapability limits the operational value of remote capacity. Capacity that is not deliverable to \nconstrained load areas may not solve the reliability need that PJM invokes to justify the RBP, even \nthough LSEs and customers may still be charged for it. \nPJM’s explanation that it does not project and calculate locational parameters 15 years into \nthe future does not satisfy its burden under FPA section 205. The question is not whether PJM can \nforecast every future constraint with precision; it is whether PJM has provided substantial evidence \nthat a non-locational, region-wide procurement is a just and reasonable means of addressing the \nstated reliability need. PJM has not done so. Ms. Croop acknowledges that PJM “does not project \nand calculate” locational parameters “15-years out” and therefore cannot apply locational \nconstraints in the RBP.135 However, that asserted forecasting limitation does not justify eliminating \nlocational analysis altogether, particularly where PJM already recognizes persistent constraints \nthrough existing LDA constructs and where the Coalition RBP Proposal included an element \ndesigned to account for the locational benefits of offered capacity resources. \nPJM’s own 2028/2029 BRA Report confirms that locational scarcity is not speculative. In \nthe uncapped auction results reported shortly before PJM filed, the auction cleared at \n \n135 Croop Affidavit at P 8."},{"page":33,"startToken":10506,"endToken":10818,"text":"33 \n$554.72/MW-day except for ComEd, which cleared at $776.69/MW-day.136 The prior delivery \nyear similarly showed Dominion clearing separately.137 The reason no LDA appeared constrained \nin the filed auction results was not that location had ceased to matter; it was that the collar and \noverall shortage produced a flat result. PJM should not be permitted to rely on a capped auction \nresult to prove that location is irrelevant when its own uncapped run of that auction showed the \nopposite. \nThe same locational disconnect is particularly harmful when viewed with PJM’s \ncompanion IRAS proposal in Docket No. ER26-3515. IRAS would curtail large loads when the \nregion is short, and curtailment necessarily turns on local system conditions. A resource \nelectrically remote from the constrained pocket does not relieve the local condition that triggers \ncurtailment there. Thus, an LSE could pay RBP charges and post collateral for 15 years and still \nface curtailment because the RBP resource procured with those payments is not deliverable to the \nlocation where the need arises. That is a concrete injury, not a theoretical objection. \nNor does PJM’s forecasting objection withstand scrutiny. PJM says a 15-year locational \nrequirement would be speculative, but the proposal fixes the quantity at 6,831.3 MW for 15 years, \nfixes each zone’s share based on the 2026 Load Forecast, and fixes the conversion factor at 0.9401 \nunder proposed section 18.3(a).138 Even that conversion factor did not remain stable for three \nweeks: after filing, PJM asked stakeholders to endorse a 0.9232 conversion factor for the next \n \n136 PJM Interconnection, L.L.C., 2028/2029 Base Residual Auction Report, at 17 (July 14, 2026) available at: \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results-\nreport.pdf (“2028/2029 BRA Report”).  \n137 2028/2029 BRA Report at 17.  \n138 Croop Affidavit at PP 46-47."},{"page":34,"startToken":10818,"endToken":11115,"text":"34 \ndelivery year.139 If a 15-year horizon is too speculative to site supply, it is too speculative to freeze \nwho pays and in what amount. \nWithout a locational requirement or comparable deliverability showing, the RBP may \nprocure capacity that is concentrated in areas that do not address localized reliability needs. That \noutcome would leave the Commission approving a charge for capacity that may not mitigate the \nlocational RPM Capacity Market impacts, reliability risks, or operational constraints that PJM cites \nas the basis for the proposal. Worse, if RBP resources are electrically distant from constrained load \npockets, PJM may later need to rely on out-of-market actions or additional Regional Transmission \nExpansion Plan transmission projects to make those resources useful to the load that allegedly \ncaused the need. In that circumstance, unrelated LSEs and customers could be required to pay \ntwice: first through RBP charges for capacity that is not deliverable where needed, and later \nthrough transmission-related cost allocation to address the transmission constraints the RBP failed \nto account for. That result is inconsistent with the Commission’s cost-causation principles and \nwould expose the Commission to approving a rate design that imposes substantial long-term costs \nwithout substantial evidence that the procurement will produce commensurate reliability benefits. \nPJM’s RBP Proposal therefore fails to establish the required nexus among the identified reliability \nneed, the location and deliverability of procured resources, and the LSEs and customers assigned \nthe resulting costs. For these reasons, the Commission should find PJM’s RBP Proposal unjust and \nunreasonable. \n \n139 PJM Interconnection, L.L.C., Presentation to Markets & Reliability Committee, Installed Reserve Margin (IRM), \nForecast Pool Requirement (FPR), and Effective Load Carrying Capability (ELCC) for 2029/2030 BRA, at 11 (Aug. \n19, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20260819/20260819-\nitem-03---2029-2030-bra-irm-fpr---presentation."},{"page":35,"startToken":11115,"endToken":11410,"text":"35 \nB. \nThe Role of Electric Distributors, States, and RERRAs in PJM’s RBP \nProposal Is Improper, Administratively Incomplete, and Not a Substitute for \na Just and Reasonable Rate Design. \nElectric Distributors’ Commission-approved function in the PJM market is limited. An \nElectric Distributor’s function largely consists of managing meter-data and administrative, \ntechnical functions. The previously determined role of an Electric Distributor is limited and \nfundamentally different than assigning wholesale cost responsibility for a long-term backstop \nprocurement.  \nIn its RBP Proposal, PJM assigns to Electric Distributors the performance of functions that \ngo well beyond ordinary meter-data or administrative responsibilities.140 Electric Distributors are \nassigned responsibility for requesting the MW quantity of load in the zone/area that will be \ndecremented from the Initial RBP Target and opted-out of the Final RBP Target. Electric \nDistributors must specify the MW quantity of load to be decremented where the Electric \nDistributor’s zone/area has rates that are not regulated by the states and is unable to address cost \nallocation associated with capacity procured in the backstop. As part of such a request, Electric \nDistributors must include “written support for such opt-out from the relevant state governor, \nRERRA, and interconnection customer(s).”141 Electric Distributors may also request the Initial \nRBP Target be further decremented by up to the associated MW quantity of load that participates \nin a peak shaving adjustment program codified in state law.142  \n PJM’s RBP Proposal requires Electric Distributors to effectively set allocation inputs for \na Commission-jurisdictional charge. The allocation of these inputs impacts cost allocation and \ncredit requirements. PJM’s RBP Proposal also requires Electric Distributors to coordinate state or \n \n140 See Bednarczyk Affidavit at P 42 (summarizing the traditional role of Electric Distributors).  \n141 See Proposed Tariff, Attachment DD, Section 18.3(b)(iii). \n142 Id."},{"page":36,"startToken":11410,"endToken":11718,"text":"36 \nRERRA determinations, and it delegates the allocation of certain costs even though it may not be \nknown – by PJM or the Electric Distributor – which LSEs serve the relevant large loads that should \nbe held accountable to pay the RBP costs. In doing so, PJM shifts a significant responsibility and \nconsiderable degree of discretion to Electric Distributors. \nPJM relies on OA Section 11.3 to support its proposed role for Electric Distributors. \nHowever, that OA section did not envision the Electric Distributor playing a rate-making role. OA \nSection 11.3 sets out a specific set of tasks for Electric Distributors in the PJM market. These \ninclude mostly technical tasks such as metering reading, providing for and arranging reactive \ncapability and voltage control facilities, coordinating load shedding with the PJM Office of \nInterconnection in emergencies, maintaining and arranging control center services,  and engaging \nin the tasks specifically enumerated in the OA.143 That provision also requires Electric Distributors \nto “[p]rovide to the Office of the Interconnection all System, accounting, customer tracking, load \nforecasting (including all load to be served from its System) and other data necessary or \nappropriate to implement or administer this [OA], and the [RAA].”144 But that “catch all” provision \ndoes not justify imposing on Electric Distributors a new rate-design and cost-allocation function. \nThis is particularly true where many entities that PJM appears to treat as “Electric Distributors” \n(or similarly situated distribution-level entities) may not be PJM Members or may not have \ncontractual privity with PJM. \nUnder PJM’s RBP Proposal, PJM will first assign RBP costs to zones, but the Electric \nDistributor is then given the responsibility for translating those costs into LSE-level RBO MW. \nThat step is not merely administrative; it is the step that determines which LSEs bear the \n \n143 See OA, Section 11.3.3. \n144 OA, Section 11.3.3(h)."},{"page":37,"startToken":11718,"endToken":12059,"text":"37 \nCommission-jurisdictional charge and associated collateral obligation. Under PJM’s RBP \nProposal, each Electric Distributor is required to report to PJM the state- and/or RERRA-\ndetermined allocations of RBP UCAP MW to LSEs in the Electric Distributors zone/area or the \n“RBO.”145 The RBP Charge assessed daily to an LSE in the relevant zone will equal the LSE’s \ndaily reported RBO MW in the zone/area divided by the total daily RBO MW in the zone, and \nmultiplied by the total, daily RBP Charges allocated to the zone/area.146 Thus, the allocation \ndetermination sets the rate paid. The fewer the number of LSEs assigned costs, the greater an \nindividual LSE’s proportional assignment of zone/area allocation may be.  Conversely, the larger \nthe number of LSEs assigned costs, the lower the individual LSE’s proportional assignment of the \nzone/area allocation may be. \nPJM proposes that the Electric Distributors would allocate the costs by LSEs’ PLC (Peak \nLoad Contribution) if no allocation is reported by the Electric Distributor with allocated RBP \nUCAP MW. The intent is to allocate costs to the LSEs serving large loads. But this is an impossible \ntask in the RBP as PJM has proposed. PJM is not tracking which large loads were in the forecast \nused to set the procurement target. Therefore, there is currently no way for an Electric Distributor \nto know which LSE should be charged.  \nPJM cannot make an otherwise insufficient federal rate design just and reasonable by \nrequiring Electric Distributors, states, or RERRAs to supply the missing cost-causation analysis.147 \nIf PJM cannot identify the responsible LSE (the entity that is the PJM wholesale customer) with \nsufficient specificity, shifting that task downstream to an Electric Distributor does not solve a cost \n \n145 PJM RBP Filing at 98. \n146 Id. \n147 See La. Pub. Serv. Comm’n v. FERC, 337 F.3d 1066, 1077 (D.C. Cir. 2003) (“FERC may not brandish a state’s \nprior approval of a set of existing rates as if it were independently sufficient to satisfy the Commission’s own \nregulatory obligations.”)."},{"page":38,"startToken":12059,"endToken":12403,"text":"38 \nallocation problem that ultimately sits with PJM.148 And because PJM cannot identify the \nresponsible LSE, the costs cannot be allocated in a way that is consistent with the Commission’s \ncost causation policy.149 As noted above, the Commission’s cost causation policy requires that \nthose who cause costs to be incurred should pay for those costs, and, conversely, that those who \nbenefit from costs should pay a portion of the costs that is roughly commensurate with the benefits \nreceived.150 PJM has not made a sufficient showing that the proposed allocations will assign costs \nin all circumstances to the LSEs that caused the costs to be incurred, or that LSEs that benefit from \nthe costs will pay an amount that is roughly commensurate with the allocated costs. Rather, under \nPJM’s RBP Proposal, the Electric Distributor must apply judgment and gather information (or \nspeculate about such information if no such information is available) from customers and work \nwith the state and/or RERRAs to determine an allocation methodology. This is far beyond the \nscope of the OA’s intended role of an Electric Distributor. There is no precedent to support an \nElectric Distributor having such a role. Nor is there any indication in PJM’s original filing or the \nCommission’s approval of the OA that it intended Electric Distributors to be able to have such an \nexpanded role. Therefore, PJM’s RBP Proposal has not been shown to be just and reasonable yet \nagain. \nMoreover, this is vastly different from the role the Electric Distributor plays in determining \nPLC associated with each LSE in its zone/area for purposes of PJM charging RPM Capacity \nMarket costs to LSEs. In that circumstance, the Electric Distributor performs a meter-reading \nfunction to calculate all of the end-use, consumer loads served by an LSE contribution at peak, \nand then the RPM Capacity Market clearing prices (combination of BRA and Incremental \n \n148 See Bednarczyk Affidavit at PP 45-46. \n149 See Bednarczyk Affidavit at P 46. \n150 See, e.g., Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009)."},{"page":39,"startToken":12403,"endToken":12764,"text":"39 \nAuctions for a Delivery Year) are applied. Simply stated, this is a mathematical, mechanical \nexercise: in the RPM Capacity Market, the price to be assigned is known and the PLC determines \nthe quantity against which the price is applied. All loads pay for capacity in the RPM Capacity \nMarket. In contrast, here the Electric Distributor effectively is tasked with determining the rate \neach LSE pays for the RBP.  The rate may vary both by the allocation of the procurement target \nPJM assigns to each zone area after decrementing the procurement target,151 and further by the \nnumber of LSEs receiving a portion of the allocation based on the state/RERRA determination. \nAnd in cases in which all loads in a zone are required to pay on a Daily Unforced Capacity \nobligation basis (the default allocation methodology PJM proposes to use should an Electric \nDistributor not have an allocation method), this will spread costs across all LSEs in the zone. This \nexpansive role assigned to Electric Distributors in PJM’s RBP Proposal thus contravenes the \nRatepayer Protection Pledge and violates the Commission’s cost causation policy. \nAs PJM acknowledges, the Commission has previously held that an Electric Distributor \nserves as “the party with the distribution and metering facilities defining a zone/area and \nresponsible for reporting load information to PJM.”152 EKPC does not dispute that Electric \nDistributors have a role to play in the PJM market. However, reporting PLC load data to PJM, \nwhich is the role the Commission has previously recognized,153 is far different than being charged \nwith implementing a cost allocation which has the functional effect of determining the rate of a \nCommission-jurisdictional product. PJM’s attempt to present this role proposed here for an \n \n151 See Bednarczyk Affidavit at PP 26-35 (explaining, in part the impacts of PJM’s proposed decrementing). See also \nProposed Tariff Sections 18.1 and 18.2 (recognize Qualifying RBP Offset UCAP MW for purposes of reducing the \naggregate procurement target). \n152 PJM RBP Filing at 101 (quoting PJM Interconnection, L.L.C., 188 FERC ¶ 61,200, P 40 (2024)). \n153 See PJM Interconnection, L.L.C., 188 FERC ¶ 61,200, P 40, n.65 (2024)."},{"page":40,"startToken":12764,"endToken":13097,"text":"40 \nElectric Distributor to be the same as the role for an Electric Distributor with respect to supporting \nthe PLC calculation should be rejected. \nThe Commission lacks jurisdiction to impose such obligations on Electric Distributors \ndirectly. Additionally, Electric Distributors are defined by the OA as \na Member that: 1) owns or leases with rights equivalent to \nownership electric distribution facilities that are used to provide \nelectric distribution service to electric load within the PJM Region; \nor 2) is a generation and transmission cooperative or a joint \nmunicipal agency that has a member that owns electric distribution \nfacilities used to provide electric distribution service to electric load \nwithin the PJM Region.154 \nThey may or may not also engage in Commission-jurisdictional activities, i.e., wholesale sales and \ntransmission of electric energy in interstate commerce. Accordingly, in the absence of further \ninformation, there is no way to know whether they are “public utilities” over which the \nCommission may exercise plenary jurisdiction under Part II of the FPA.155 And if they are not \n“public utilities,” then the Commission may not exercise such authority over them. Indeed, many \nentities that engage solely in electric distribution activities are expressly exempt from the \nCommission’s “public utility” regulatory authority by virtue of FPA section 201(f).156 In any event, \nany argument that they may have agreed to take on this role based on vague, catch-all language in \nthe Operating Agreement should be rejected. \nAdditionally, under FPA section 201(b), the Commission is explicitly precluded from \nexercising jurisdiction over “facilities used in local distribution or only for the transmission of \nelectric energy in intrastate commerce.”157 The FPA limits the Commission’s jurisdiction to \n \n154 OA Definitions.  \n155 16 U.S.C. § 824(e). \n156 See 16 U.S.C. § 824(f).  \n157 16 U.S.C. § 824(b)(1). See also Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 695 (D.C. Cir. \n2000) aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002)."},{"page":41,"startToken":13097,"endToken":13443,"text":"41 \nwholesale sales in interstate commerce, which includes only those rules or practices that “directly \naffect the wholesale rate.”158 The Commission does not have the authority to directly regulate retail \nsales “no matter how direct, or dramatic, its impact on wholesale rates.”159  \nWhile determination of PLCs for capacity is a meter reading function that may be \nappropriately delegated to an Electric Distributor, allocating RBP costs will require the exercise \nof discretion. This will require Electric Distributors to have knowledge of, or speculate in the \nabsence of knowledge of, which LSE is serving large load and whether that load has resources that \nallowed the RBP target to be decremented. The load forecast that the RBP Target is based upon, \nwhile including information from the Electric Distributor, also will be adjusted by PJM applying \nits “independent judgement.”160  As a result, for several zone/areas there is no direct linkage to \nspecific end-use consumers in that forecast that an Electric Distributor may apply. Therefore, the \nElectric Distributor is making an allocation decision based on knowledge outside of its control. \nSuch an allocation cannot be just and reasonable.  \nC. \nPJM’s RBP Proposal is Inconsistent with the Boundaries of Federal and State \nJurisdiction. \nPJM claims that the RBP Proposal is “the result of a carefully considered effort to respect \nthe line between federal and state jurisdiction while simultaneously embracing PJM’s significant \nrole in (1) meeting the region’s resource adequacy needs and (2) supporting the reliable and orderly \ninterconnection of large loads in the region.”161 But PJM’s RBP Proposal is inconsistent with the \n \n158 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 277-78 (2016). \n159 Id. at 279-80. \n160 See PJM Interconnection, L.L.C., PJM Manual 19: Load Forecasting and Analysis, at Attachment B: Load Forecast \nAdjustment Guidelines (effective June 30, 2026); PJM Interconnection, L.L.C., Presentation to Load Analysis \nSubcommittee, Load Adjustment Requests Summary for 2026 Load Forecast – Preliminary, (Nov. 24, 2025), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2025/20251124/20251124-item-03---\nlarge-load-adjustment-requests-summary.pdf.  \n161 PJM RBP Filing at 10."},{"page":42,"startToken":13443,"endToken":13762,"text":"42 \nboundaries of federal and state jurisdiction because it inappropriately places obligations on Electric \nDistributors and states or RERRAs. PJM’s cost allocation methodology relies on states and \nRERRAs to determine appropriate RBOs in order to allocate RBP to LSEs within each Electric \nDistributor zone/area. This “cooperative federalism” approach improperly delegates a critical \ncomponent of rate design to entities that may not be parties to this proceeding and whose actions \nare not subject to Commission review.  \nPJM relies on the Commission’s determination in its order accepting Midcontinent \nIndependent System Operator, Inc.’s (“MISO”) Revised Expedited Resource Addition Study \n(“ERAS”) Proposal.162 In the ERAS proceeding, the Commission found that RERRA participation \nin the ERAS process was permissible and not an improper delegation of federal authority to the \nstates.163 The delegation of ratemaking authority that PJM has proposed here is distinguishable \nfrom the RERRA participation in the MISO ERAS process. The RERRA’s role in the MISO ERAS \nprocess was “limited to assessing and verifying non-speculative interconnection requests.”164 This \nis much more limited than the RERRA’s role in the PJM RBP Proposal where states or RERRAs \nare determining cost allocations to LSEs – which is within the Commission’s primary regulatory \nauthority.  \nAdditionally, federal agencies cannot delegate “decision-making authority … to outside \nentities – private or sovereign – absent affirmative evidence of authority to do so.”165 The \nCommission found that the MISO ERAS proposal was distinguishable from U.S. Telecom because \n \n162 PJM RBP Filing at 105 (citing Midcontinent Indep. Sys. Operator, Inc., 192 FERC ¶ 61,064, at P 99 (2025), order \naddressing arguments raised on reh’g, 194 FERC ¶ 61,050 (2026)). \n163 Midcontinent Indep. Sys. Operator, Inc., 192 FERC ¶ 61,064, at P 99 (2025) (“MISO ERAS Order”), order \naddressing arguments raised on reh’g, 194 FERC ¶ 61,050 (2026). \n164 MISO ERAS Order at P 101. \n165 U.S. Telecom Ass’n v. FCC, 359 F.3d 554, 566 (D.C. Cir. 2004)."},{"page":43,"startToken":13762,"endToken":14094,"text":"43 \n“it does not subdelegate the Commission’s authority but simply creates a role for RERRAs in a \nCommission-jurisdictional process.”166 Here, PJM is not “simply” creating a role for RERRAs. \nRather, PJM’s RBP Proposal gives significant decision-making authority and discretion to states \nor RERRAs through Electric Distributors by delegating the Commission’s authority over \njurisdictional rates. \nPJM’s RBP Proposal requires Electric Distributors to determine how to allocate RBO \namong the LSEs in a zone, which in turn requires states or RERRAs to play a role in establishing \na Commission-jurisdictional rate. This is also true of the credit requirement associated with the \nprocurement obligation. Collateral determination responsibilities should be reserved for entities \nregulated by the Commission.167 Entities imposing credit requirements or obligations are “public \nutilities” regulated by the Commission because these entities engage in practices that directly affect \nrates, terms and conditions, and therefore they should be subject to Commission regulation.168 But \nPJM’s RBP Proposal skirts that regulation by assigning the role of establishing credit requirements \nto non-jurisdictional entities by virtue of requiring the Electric Distributor to determine the LSE \nRBO. Technically, PJM will implement the credit requirement, but it will do so based on the \nElectric Distributor determinations. Therefore, PJM’s proposed delegation is inappropriate and \ninconsistent with the requirements of the FPA. \nMoreover, not all electric distribution companies (or similar distribution-level utilities that \nmight qualify as “Electric Distributors”) are Members of PJM. There are multiple transmission \n \n166 MISO ERAS Order at P 101.  \n167 See generally Credit Reforms in Organized Wholesale Electric Markets, 133 FERC ¶ 61,060 (2010), order on \nreh’g, 134 FERC ¶ 61,126 (2011) (rulemaking order regarding risk and credit procedures in Commission-jurisdictional \nmarkets). See also Policy Statement on Credit-Related Issues for Electric OATT Transmission Providers, Independent \nSystem Operators and Regional Transmission Organizations, 109 FERC ¶ 61,186, P 1 (2004) (“credit policies of \nregulated utilities have always been a component of the Commission’s regulatory agenda”). \n168 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 277-78 (2016)."},{"page":44,"startToken":14094,"endToken":14409,"text":"44 \ndependent cooperatives and municipalities throughout the PJM region. Therefore, an attempt to \ndelegate such a role to distribution-level utilities creates jurisdictional overreach by bringing such \nentities into a Commission-jurisdictional ratemaking role.   \nIn an attempt to present the RBO as “flexible” and consistent with the boundaries of federal \nand state jurisdiction over cost allocation, PJM is proposing that “cost allocation to LSEs within \nan Electric Distributor’s zone/area be based on ‘the state and/or RERRA-determined allocation of \ncleared RBP UCAP MW to LSEs within each Electric Distributor’s zone/area, as reported by each \nElectric Distributor to [PJM].’”169 Basing the cost allocation on a state or RERRA determined \nallocation of RBP UCAP MW to LSEs within each zone/area is inconsistent with the intended role \nof states/RERRAs with respect to rates under the Commission’s jurisdiction. It would be \nappropriate and indeed consistent with retail jurisdiction for states and RERRAs to develop and \ncharge retail rates that are based upon Commission-jurisdictional rates. However, here, because \nthe states/RERRAs must determine the cost allocations in the first instance, they are determining \nCommission-jurisdictional rates. As explained by Mr. Bednarczyk, “the market-design concern is \nthat PJM has not first established a sufficiently specific wholesale framework that identifies the \nresponsible LSE, records the relevant large-load obligation, tracks offsets and mitigation measures \nassociated with that obligation, and maintains a clear connection between cost responsibility and \ncost causation.”170 PJM is effectively improperly pushing its rate-making role onto other entities \nand impermissibly blurring the line between federal and state jurisdiction.  This delegation is not \n \n169 PJM RBP Filing at 97-98.  \n170 Bednarczyk Affidavit at P 46. Additionally, as explained by Mr. Bednarczyk, the Coalition RBP Proposal \n“established responsibility first and then used retail or administrative processes to implement that responsibility,” \nwhich would be an appropriate market design that incorporated Electric Distributor, state, and RERRA processes. \nBednarczyk Affidavit at P 45."},{"page":45,"startToken":14409,"endToken":14754,"text":"45 \nappropriate,171 and at a minimum, it is not clear that Electric Distributors agreed to such a role by \nexecuting the OA. Delegating this role to Electric Distributors does not make PJM’s RBP Proposal \nconsistent with the boundaries of federal and state jurisdiction. \nPJM’s RBP Proposal also has not been shown to be just and reasonable because it leaves \nout much of the implementation details. For example, if PJM’s RBP Proposal is accepted, will \nElectric Distributors then become Commission-jurisdictional? And, how will PJM’s RBP Proposal \nbe implemented in zones where not all of the load is served by Electric Distributors? Rather than \nleave open the possibility of this jurisdictional overreach, the Commission should reject PJM’s \nRBP Proposal. \nD. \nPJM’s Proposed FRR Exemption and Treatment of RPM Capacity Market \nSelf-Supply Are Unduly Discriminatory. \nPJM’s RBP Proposal’s treatment of FRR entities and the use of existing resources to satisfy \nFRR plans creates comparability concerns and unduly discriminates against RPM Capacity Market \nLSEs in several ways. First, as proposed, PJM allows an FRR entity that satisfies its resource \nadequacy obligations through qualifying owned and some portion of existing resources to be \n“insulated from RBP exposure”172 In contrast, an RPM Capacity Market LSE that has likewise \nprudently planned to serve its load does not receive comparable treatment under the proposed RBP \ncost-allocation framework.173 PJM’s RBP Proposal allows FRR entities to use existing resources \n \n171 See, e.g., Entergy Servs., Inc., 120 FERC P 61,020, at P 28 (2007) (“The Commission’s ratemaking obligations \nunder the FPA cannot be delegated to a state commission.  Similarly, as a general matter, a state commission cannot \nset Commission-jurisdictional rates nor direct the filing of Commission-jurisdictional rates. Likewise, the \nCommission cannot delegate to jurisdictional utilities its obligation to ensure the justness and reasonableness of \njurisdictional rates. Yet, that is what [the Utility] effectively asks us to do, i.e., to delegate to state commissions and \nto [the Utility] itself the determination of the reasonableness of [the Utility’s] Commission-jurisdictional rates.”). \n172 Bednarczyk Affidavit at P 60. \n173 Bednarczyk Affidavit at P 60."},{"page":46,"startToken":14754,"endToken":15161,"text":"46 \nto meet their FRR plans so long as those resources are locked in by June 1, 2027,174 while RPM \nCapacity Market LSEs with owned or contracted resources may not receive comparable protection \nfrom RBP cost assignment. PJM’s proffered explanation is that “FRR load has already paid for \nresource adequacy through the FRR Plan. Allocating RBP Charges to FRR load, in essence, \nrequire that they pay twice for capacity it has already procured.”175 But PJM offers no explanation \nas to why LSEs that similarly have existing resources paid for by the load they serve should be \nexposed to RBP costs. As explained by Mr. Bednarczyk, \nAn FRR entity that satisfies its resource adequacy obligation \nthrough qualifying owned resources, and at least some categories of \nexisting resources, is effectively insulated from RBP exposure. By \ncontrast, an RPM LSE that has prudently developed, retained, or \ncontracted for sufficient resources to serve all or part of its \nincremental load does not appear to receive comparable treatment \nunder the RBP cost-allocation framework. If PJM recognizes \nresource adequacy actions taken under the FRR construct for \npurposes of avoiding RBP exposure, principles of comparability and \ncost causation suggest that it should similarly recognize owned \nresources, \nbilateral \ncontracts, \nand \ncomparable \nresource \ncommitments maintained by RPM LSEs when determining RBO \nMW, RBP Charges, and collateral obligations.176 \nRPM Capacity Market LSEs that have sufficient capacity, whether owned or contracted for, are \nsimilarly situated to FRR entities, because both have sufficient capacity. Therefore, neither has \ncaused any costs to be incurred or gained any benefits from the RBP. Yet as proposed, only RPM \nCapacity Market LSEs have exposure under RBP. This is inconsistent with the Commission’s cost-\ncausation principles. And, this distinction, without justification, is unduly discriminatory.177 As \n \n174 Proposed RAA, Schedule 8.1.D.1.1.  \n175 PJM RBP Filing at 31-32, n.92.  \n176 Bednarczyk Affidavit at P 60. \n177 City of Anaheim, Opinion No. 483, 113 FERC ¶ 61,091, P 130 (2005) (“Discrimination is undue when there is a \ndifference in rates or services among similarly situated customers that is not justified by some legitimate factor.”); \nPacifiCorp Elec. Operations, 54 FERC ¶ 61,296, 61,855 (“undue discrimination can occur only when two similarly \nsituated customers are treated differently, and there is no justification for the differing treatment”); Puget Sound \nEnergy, Inc. v. All Jurisdictional Sellers of Energy, Opinion No. 537, 151 FERC ¶ 61,173, P 43, n.105 (quoting Energy"},{"page":47,"startToken":15161,"endToken":15526,"text":"47 \nexplained by Mr. Bednarczyk, “an LSE’s choice between the RPM construct and the FRR \nalternative should not determine whether its resource position receives recognition under the \nRBP.”178 Instead, the focus should be on whether an LSE has mitigated or eliminated the \nincremental reliability need.179 \nE. \nPJM’s Proposed FRR Exemption Creates Ambiguity and Disadvantages \nEntities that May Elect FRR in the Future. \nPJM’s RBP Proposal is unclear with respect to the extent to which a future FRR entity may \nrely on existing resources, including bilateral contracts associated with existing resources, to \nsatisfy FRR obligations. PJM’s proposed language creates ambiguity about whether an FRR entity \nmay use capacity resources it does not own to satisfy its FRR plan, despite other RAA provisions \nallowing bilateral contracts.180 PJM’s proposed language in RAA Section 8.1.D.1.1 states that \n“[a]n FRR Entity may not use an Existing Generation Capacity Resource not owned by such FRR \nEntity as of June 1, 2027 or any resource committed through the Reliability Backstop Procurement \nto satisfy its Capacity FRR Plan.”181 Thus, according to PJM’s proposal, an FRR entity is limited \nto relying upon its “owned” (not purchased via bilateral contract with the generation owner) \ncapacity. Yet elsewhere in the RAA,182 bilateral contracts are clearly permitted.  \nPJM’s proposed language was not explained in its RBP Filing Transmittal Letter, so its \npurpose and likely impacts have not been presented to the Commission. But it appears to be an \n \nTransfer, 120 FERC ¶ 61,086, P 169), rev’d on other grounds, 157 FERC ¶ 61,026 (2016) (“It is well established that \na finding of undue discrimination requires a showing that ‘(1) two classes of customers are treated differently; and (2) \nthe two classes of customers are similarly situated.’”); Midwest Indep. Transmission Sys. Operator, Inc., 155 FERC ¶ \n61,082, P 31 (2016) (“there is no undue discrimination or preference because we have identified appropriate reasons \nfor it”).  \n178 Bednarczyk Affidavit at P 62. \n179 Bednarczyk Affidavit at P 62. \n180 Bednarczyk Affidavit at P 63. See RAA, Schedule 8.1.D.4. \n181 Proposed RAA, Schedule 8.1.D.1. (emphasis added). \n182 See RAA, Schedule 8.1.D.4."},{"page":48,"startToken":15526,"endToken":15902,"text":"48 \neffort to ensure that FRR Entities do not enter into bilateral agreements with resources that have \nbeen committed to serve load under the RPM Capacity Market and further challenge the resource \nadequacy of entities who rely on the RPM Capacity Market.  However, as drafted the provision \nwould privilege ownership over bilateral (contract) supply arrangements for satisfying FRR plans.  \nHowever, LSEs may have long-standing bilateral contracts. To the extent that this language would \nrestrict an entity newly electing the FRR alternative from being able to rely upon a long-standing \nbilateral contract to satisfy its FRR plan, it is an unjust and unreasonable provision.  This revision \nwould unnecessarily constrain the ability of other entities to consider use of the FRR alternative in \nthe future if their full portfolio of resources could not be used to satisfy an FRR plan. The revision \nis unexplained by PJM, is unjustified for the reasons discussed herein, and therefore has not been \nshown to be just and reasonable and should be rejected by the Commission. \nF. \nPJM’s Proposal Is Inconsistent with Ratepayer Protection and the \nAdministration’s Policy Objectives Because It May Shift Large-Load-Driven \nCosts to LSEs and Customers That Did Not Cause Them to Be Incurred. \nPJM wraps its RBP Proposal in the claim that it addresses concerns raised by the \nAdministration, the Commission, and PJM states with respect to large loads and ratepayer \nprotection.183 But advancing the policy goal of rate payer protection184 depends on assigning \nreliability-related costs to the entities whose incremental large load growth creates the need for \nthose costs, in a manner consistent with the Commission’s cost-causation principles. Thus, \nadvancing the goal of ratepayer protection necessarily depends on the ability to assign costs to \n \n183 \nSee \nTHE \nWHITE \nHOUSE, \nRatepayer \nProtection \nPledge, \n(Mar. \n4, \n2026),  \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/. As of August 18, 2026, more than 300 \norganizations across every stakeholder in the power system have signed on to the Ratepayer Protection Pledge, \nincluding Governors of 23 states and more than 250 utilities and cooperatives, including EKPC (see \nhttps://www.whitehouse.gov/ratepayer-protection-pledge/#commitments for a list of entities that have signed the \nPledge). \n184 See National Energy Dominance Counsel, Statement of Principles Regarding PJM (Jan. 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm)."},{"page":49,"startToken":15902,"endToken":16102,"text":"49 \nentities that either cause the costs to be incurred or benefit from the RBP in a manner roughly \ncommensurate with the costs assigned. \nPJM’s RBP Proposal is inconsistent with the objectives expressed by the Administration, \nthe Commission, and the PJM Governors because, as proposed, the RBP will inevitably allocate \ncosts to LSEs that prudently managed their resource positions and did not contribute to the need \nfor the RBP and therefore, do not benefit from the costs arising under the RBP. PJM’s RBP \nProposal allows for this improper cost allocation in multiple ways, as recounted above. First, \nPJM’s RBP Proposal fails to account for existing resources in an LSE’s supply portfolio. The RBP \nProposal also fails to ensure that applicable offsets and opt-outs decrement any obligation of LSEs \nwho supplied them. Additionally, relying on Electric Distributors and state or RERRA cost \nallocation methods, or defaulting to a cost allocation method adopted and approved for a very \ndifferent purpose (i.e., the RPM Capacity Market), may shift costs away from the entities that have \ncaused the costs. This is inconsistent with the Commission’s cost causation principles and \nproduces an unjust and unreasonable result. Therefore, the Commission should reject PJM’s RBP \nProposal."},{"page":50,"startToken":16102,"endToken":16280,"text":"50 \nIII.\nConclusion\nWherefore, East Kentucky Power Cooperative, Inc. respectfully requests that the\nCommission reject the PJM RBP Proposal because the PJM RBP Proposal is unjust and \nunreasonable, improperly expands the role of an Electric Distributor in PJM, and is inconsistent \nwith the boundaries of federal and state jurisdiction. PJM’s RBP Proposal also fails to address \nconcerns raised by the Commission and the governors of the 13 PJM states regarding the impacts \nof large loads, specifically ratepayer protection. \nRespectfully submitted, \nDenise R. Foster Cronin \nChief Compliance Officer and Senior Vice \nPresident \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTel.: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \nOn Behalf of \nEast Kentucky Power Cooperative, Inc. \n/s/ Daniel E. Frank \nDaniel E. Frank \nAllison E. S. Salvia  \nKelly A. Cuthbertson \nAdriana J. Santana \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTel.: 202-383-0100 \nEmail: danielfrank@eversheds-sutherland.com \nallisonsalvia@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \nanasantana@eversheds-sutherland.com \nCounsel for \nEast Kentucky Power Cooperative, Inc. \nDated: August 21, 2026"},{"page":51,"startToken":16280,"endToken":16286,"text":"Attachment 1 \nAffidavit of Adam Bednarczyk"},{"page":52,"startToken":16286,"endToken":16604,"text":"DAYMARK ENERGY ADVISORS |370 MAIN STREET, SUITE 325 |  WORCESTER, MA 01608 \nTEL: (617) 778-5515 | DAYMARKEA.COM \n \nAFFIDAVIT OF ADAM BEDNARCZYK \nPrepared for East Kentucky Power Cooperative, Inc. in connection with PJM Interconnection, \nL.L.C.’s Reliability Backstop Procurement filing \n \nAFFIDAVIT \nI. Introduction and Qualifications \n1. My name is Adam Bednarczyk. I am a Lead Consultant with Daymark Energy Advisors. I work with \nmarket participants, regulators, utilities, and developers to provide actionable insights regarding power \nmarket design, FERC policy, and transmission economics. I submit this affidavit on behalf of East \nKentucky Power Cooperative, Inc. (“EKPC”) in connection with PJM Interconnection, L.L.C.’s proposed \nReliability Backstop Procurement (“RBP”). \n2. I have approximately 17 years of experience at the Federal Energy Regulatory Commission (“FERC” \nor the “Commission”) in roles of progressive responsibility. \n3. During my tenure at FERC, I served in the Office of Energy Market Regulation, the Office of Policy and \nInnovation, and the Office of Enforcement. Most germane here, I advised senior agency management \nand Commissioners on matters arising under the Federal Power Act, including wholesale energy, \ncapacity, and ancillary services market rules in the Eastern RTOs and ISOs. My experience includes \nSection 205 and Section 206 proceedings, tariff compliance, rulemaking implementation, natural gas-\nelectric coordination, fuel security, market power mitigation, market-based rate authority, and affiliate \nsales restrictions. \n4. Based on that experience, I am familiar with how Commission staff evaluate whether a proposed \nRTO or ISO tariff change is supported by the filing utility’s Section 205 showing, whether the filed \nprovisions are sufficiently specific and administrable, and whether the resulting rate design is reasonably \naligned with cost causation, market incentives, and comparability among similarly situated market \nparticipants. \n5. My affidavit examines whether the specific design elements of PJM’s proposed Reliability Backstop \nProcurement (“RBP”) appropriately align procurement obligations, cost responsibility, collateral \nrequirements, and associated risks with the entities whose incremental load growth creates the need for"},{"page":53,"startToken":16604,"endToken":17030,"text":"Adam Bednarczyk Affidavit \n2 \n \nadditional capacity. I address market-design, cost-causation, incentive, hedgeability, collateral, and \nadministrability issues arising under proposed Tariff sections 18.1, 18.2, 18.3, 18.4, 18.5, 18.8, and 18.9, \nas well as proposed RAA Articles 7.2B and 7.2C. My review focuses not on whether PJM has identified a \nlegitimate reliability concern, but on whether the specific rate design and allocation provisions filed \nunder Section 205 are sufficiently transparent, traceable, administrable, and consistent with cost-\ncausation principles. \nII. Summary of Opinions \n6. PJM has identified a real and urgent resource adequacy challenge, and nothing in my testimony \nsuggests that PJM should be prohibited from addressing that challenge. Rather, my testimony examines \nwhether the specific mechanisms PJM selected to procure capacity, recognize offsets, allocate costs, \nimpose collateral requirements, and assign related risks appropriately align those obligations with the \nentities whose incremental demand creates the need for the procurement. These questions are \nparticularly important because the proposal contemplates long-term financial commitments and credit \nobligations that may remain in place for as many as fifteen Delivery Years. \n7. In my opinion, the Commission should not treat a generalized showing of regional reliability need as \nsufficient to support the particular RBP rate design filed under Section 205. PJM must demonstrate that \nthe specific tariff provisions governing RBP offsets, cost allocation, resource commitments, collateral \nrequirements, RBP Charges, RBP Obligations (“RBO MW”), and Electric Distributor reporting satisfy the \nstandards of a just and reasonable rate design. The proposal creates cost, credit, collateral, and risk-\nallocation obligations that do not consistently satisfy the principles of transparency, traceability, and cost \ncausation. In particular, the proposal does not consistently identify the entities responsible for the \nincremental reliability need, track mitigation measures taken by those entities, or ensure that resulting \ncosts, credits, collateral obligations, and associated risks remain aligned with the parties whose actions \ncreate, increase, or mitigate the need for backstop procurement. \nIII. Background \n8. PJM’s proposed Reliability Backstop Procurement (“RBP”) is a one-time, PJM-administered capacity \nprocurement intended to address the 6,831 MW resource adequacy shortfall identified in the 2028/2029 \nBase Residual Auction. Under the proposal, PJM would procure new capacity resources through a \ncompetitive process and provide successful resources with commitments of up to fifteen Delivery Years. \nThe procurement target would be reduced by certain qualifying new capacity arrangements and limited \nopt-outs, but PJM would not require a direct matching of specific resources to specific loads. The costs of \nthe procurement would be allocated first to Electric Distributor zones and areas based on load-growth-"},{"page":54,"startToken":17030,"endToken":17434,"text":"Adam Bednarczyk Affidavit \n3 \n \nrelated allocation factors and then further allocated to Load Serving Entities through a combination of \nstate-, RERRA-, or Electric Distributor-reported assignments, with a default PJM allocation mechanism if \nno such assignments are provided. PJM’s proposal therefore combines a centralized procurement \nmechanism with a largely downstream allocation process for costs and obligations, placing substantial \nreliance on subsequent state, RERRA, and Electric Distributor actions to identify the ultimate \nbeneficiaries and cost-responsible parties. \n9. PJM’s proposal reflects a market-design choice to address the identified resource adequacy shortfall \nthrough a centralized procurement mechanism combined with a multi-layered allocation framework. \nUnder the filing, qualifying offsets and opt-outs may reduce the overall procurement target, while \nresponsibility for the resulting obligations is assigned through Electric Distributor zones and areas and \nultimately translated into Load Serving Entity (“LSE”)-level obligations through Electric Distributor, state, \nRERRA, or default PJM allocation processes. The proposal also includes associated settlement, collateral, \nand default-allocation provisions intended to support the financial administration of the procurement. \nAccordingly, evaluating the proposal requires consideration not only of how PJM procures resources, but \nalso of how procurement obligations, offsets, cost responsibility, collateral requirements, and associated \nrisks are assigned and tracked after the procurement occurs. The remainder of my affidavit evaluates \nwhether those mechanisms provide a sufficiently transparent, traceable, and administrable framework \nfor ensuring that responsibility for the procurement remains aligned with the parties whose actions \ncreate, increase, or mitigate the underlying reliability need. \nIV. Reliability Neutrality and Large-Load Growth \n10. The Commission can apply an affirmative principle that improves reliability while preserving cost-\ncausation discipline: new large loads should be expected to remain reliability neutral, or as close to \nreliability neutral as reasonably practicable, before their incremental demand imposes long-term costs \non customers that did not create the need. \n11. A reliability neutral design principle is not an anti-growth or anti-data-center concept; it is a \ngovernance and cost-allocation principle. It recognizes that large loads may produce economic benefits \nand that PJM may need additional resources to serve them reliably. At the same time, it requires PJM to \nlink, as directly as practicable, the incremental reliability consequences of serving those loads to the LSEs \nthat supply them. \n12. The RBP proposal does not adequately implement this principle. A load-serving entity, or a self-\nsupplying large-load customer, should know that bringing capacity, demand response, curtailability, or \nanother recognized mitigation measure will reduce its own RBP exposure. PJM's proposed zonal and"},{"page":55,"startToken":17434,"endToken":17899,"text":"Adam Bednarczyk Affidavit \n4 \n \nElectric Distributor allocation framework does not directly assign RBP obligations to the LSE responsible \nfor serving the large load that creates the procurement need. As a result, the proposal may encourage \nparties to focus on allocation outcomes rather than on actions that reduce the reliability impacts of \nadding large loads without corresponding resources or curtailment arrangements. \n13. PJM's allocation framework does not provide sufficient LSE-specific information for an LSE to \ndetermine, before completion of the Electric Distributor process, whether it will be assigned RBP costs. \nNor does the filing include a registry or MW opt-in mechanism that would allow an LSE or self-supplying \nlarge load to identify responsibility at the outset, associate qualifying mitigation measures with that \nresponsibility, and determine whether its actions satisfy a reliability-neutral standard. \n14. Proposed Tariff section 18.1(b) provides that the Final RBP Target equals the Initial RBP Target less \nthe total PJM-wide Qualifying RBP Offset UCAP MW and the unforced capacity obligation value of load \nthat successfully opts out under section 18.1(d). Proposed section 18.3 similarly reduces the Electric \nDistributor zone/area calculation for qualifying offsets and opt-outs before calculating that zone's or \narea's share of the Final RBP Target MW. These provisions reduce a PJM-wide or zone-specific \nprocurement target, but they do not expressly provide that the LSE supplying the offset or associated \nwith the opt-out receives a corresponding reduction in its own RBO MW, RBP Charges, or collateral \nrequirements. Instead, the Electric Distributor allocates the remaining obligation through the RAA \nframework. That process does not provide a transparent means for an LSE to assess its wholesale RBP \nexposure, evaluate the benefits of qualifying offsets or opt-outs, understand its related credit \nobligations, or determine whether its actions will make it reliability neutral. \n15. The significance of a registry extends beyond administrative tracking. The Coalition proposal that \nEKPC co-sponsored was designed to establish an opt-in mechanism under which an LSE or associated \nlarge-load customer could identify the RBP MW for which it accepted responsibility and allow those MW \nto be tracked and cost responsibility assigned to the correct LSE. The Coalition proposal did not itself \nrequire tracking of qualifying offsets by the LSE. Rather, in combination with a separate Connect and \nManage framework, the registry would have linked procurement responsibility, cost allocation, collateral \nrequirements, and operational consequences. \n16. By contrast, PJM's filed proposal largely treats procurement, cost allocation, and the forthcoming \nIRAS process as separate constructs. PJM states that the RBP does not depend on the IRAS framework. \nThat separation breaks the direct connection between the entity creating the incremental reliability \nneed and the consequences of failing to mitigate that need. Unlike the Coalition proposal, the filing does \nnot establish a unified framework that carries responsibility from procurement through settlement and"},{"page":56,"startToken":17899,"endToken":18369,"text":"Adam Bednarczyk Affidavit \n5 \n \noperational consequences. As a result, it does not provide the same transparent and traceable path for \nensuring that large-load customers and their suppliers remain reliability neutral. \nV. Cost Causation and Section 205 Burden \n17. Proposed Tariff section 18.3 is the central cost-allocation provision. Section 18.3(a) allocates the \nInitial RBP Target MW to each Electric Distributor zone or area based on that zone's or area's pro rata \nshare of the increase in forecasted Load Adjustments between the 2026/2027 and 2028/2029 Delivery \nYears. Section 18.3(b) then allocates daily RBP Charges to LSEs based on each LSE's assigned RBO MW. \nCritically, section 18.3(b)(iii) provides that, if no RBO MW are reported, \"PJM will allocate the RBP \nCharges for that zone/area to all load in the zone/area using each LSE's ratio share of the Daily Unforced \nCapacity Obligation for the zone/area as determined in RAA, Schedule 8.\"1 That default raises a \nsignificant just-and-reasonable concern because Daily Unforced Capacity Obligation is a broad capacity-\nallocation metric. By itself, it does not identify the LSEs that created the residual procurement need, nor \ndoes it provide a mechanism to ensure that recognized offsets, opt-outs, or mitigation actions reduce \nthe exposure of the LSE that supplied them. \n18. Section 18.3 therefore risks transforming an incremental large-load cost-causation issue into a \ngeneralized load-ratio allocation. A simple example illustrates the concern. Assume one LSE's new large \nload creates an incremental need for RBP procurement, while another LSE in the same zone experiences \nonly ordinary load growth and has already secured sufficient owned or contracted resources to meet its \nobligations. Under a default zonal or load-ratio allocation, the second LSE could still bear a portion of the \ncosts caused by the first. In that circumstance, the filed rate would not distinguish between an LSE that \ncreated, or failed to mitigate, the incremental procurement need and an LSE that prudently planned for \nits resource requirements. By blurring that distinction, the proposal weakens the forward-planning \nincentives that PJM asserts the RBP is intended to create. \n19. This concern is consistent with principles the Commission has accepted in other PJM market-design \ncontexts. PJM credit and collateral requirements have generally been tied to measurable participant-\nspecific exposure and structured to reduce mutualized default risk. Similarly, PJM capacity-market \nreforms have sought to align accreditation, testing requirements, must-offer obligations, and \nperformance consequences with actual resource-adequacy value. Those same principles underscore the \nimportance of the alternative framework reflected in the Coalition proposal that EKPC co-sponsored. \nUnder that approach, obligations would be identified when procurement responsibility is established, \ntied to a party that affirmatively accepts responsibility, and paired with a mechanism that associates \n \n1 PJM Interconnection, L.L.C., Proposed Open Access Transmission Tariff, Attachment DD § 18.3(b)(iii)."},{"page":57,"startToken":18369,"endToken":18806,"text":"Adam Bednarczyk Affidavit \n6 \n \nqualifying offsets with the entity that supplied them. PJM's filed proposal does not provide the same \nlevel of upfront traceability. \n20. The Coalition proposal that EKPC co-sponsored addresses many of these concerns through a registry \nor MW opt-in framework. Under that approach, the large-load-driven need, the LSE or supplier \nassociated with that need, the MWs for which that party accepted responsibility, and the qualifying \nresources or mitigation measures used to reduce that responsibility would all be identified at the time of \nprocurement. That framework differs materially from PJM's proposal, which reduces the procurement \ntarget through offsets and opt-outs but does not comparably ensure that the resulting credit follows the \nresponsible LSE into the cost-allocation, settlement, and collateral calculations. \n21. In my view, the absence of a transparent registry or opt-in mechanism is significant because it \neliminates a practical tool for linking RBP MW and related cost recovery responsibility to the LSE serving \nthe large load. The Coalition proposal treated the registry as a means of identifying the responsible LSE \nand tracking the RBP MW to that entity. The registry, together with the Connect and Manage framework  \nco-sponsored by EKPC would have provided a transparent mechanism linking procurement responsibility, \ncost responsibility, settlement outcomes, and operational consequences. \n22. PJM has since proposed registry-related elements through its separate IRAS filing. In this RBP filing, \nhowever, PJM expressly treats the RBP and IRAS frameworks as independent constructs. As a result, the \nfiling does not establish a unified framework that carries responsibility from procurement through cost \nallocation, settlement, collateral requirements, and operational reliability obligations. The proposal \ntherefore does not provide the same direct and transparent connection between the entity creating the \nincremental reliability need and the consequences of failing to mitigate that need. \nVI. Cost and Risk Allocation Effects Created by the RBP \n23. The proposed RBP would create a new administrative procurement opportunity for new generation \ndevelopers, including independent power producers. A long-term RBP commitment may be valuable \nbecause it provides revenue certainty and a risk profile that differs from traditional RPM participation or \nbilateral contracting. That distinction matters because the RBP's long-term contract structure may shield \nselected generators from certain RPM market risks, while performance, load-realization, and stranded-\ncost risks do not disappear. Instead, the tariff shifts those risks to the LSEs and large-load customers \nexpected to bear RBP Charges. Because the proposed allocation framework does not fully ring-fence \nthose costs and risks to the entities that created the procurement need, LSEs that do not require RBP \nresources to serve large loads may nonetheless assume long-term financial obligations, even in the \nabsence of a payment default."},{"page":58,"startToken":18806,"endToken":19269,"text":"Adam Bednarczyk Affidavit \n7 \n \n24. Proposed Tariff sections 18.4 and 18.5 are central to this concern because they establish the terms \nunder which new RBP Resources may be selected and compensated. Section 18.4 offers commitments \n\"for a fixed period of fifteen (15) Delivery Years,\" while section 18.5(g) provides that each committed \nRBP Resource \"shall be individually settled as a contract for difference.\" These provisions create a \nvaluable administrative procurement pathway that is distinct from traditional RPM participation. The \nconcern is not that new resources receive backstop compensation. Rather, if PJM creates a payment \nstream with a different and potentially more favorable risk profile for selected resources, the tariff \nshould also clearly identify who bears the associated performance, revenue-sufficiency, load-realization, \nand stranded-cost risks. Unless the cost-allocation and collateral provisions are equally specific and \ntraceable, the RBP may procure supply through one set of rules while allocating the resulting costs and \nrisks through another set of rules that does not clearly identify the responsible LSE or load. \n25. Existing resources receive materially different treatment. An LSE that prudently has planned, built, or \ncontracted for resources to meet future load obligations generally cannot access the RBP revenue \nstream. That distinction may be reasonable if PJM intends to reserve RBP compensation for new \nbackstop resources. It becomes problematic, however, if the tariff fails to recognize those same existing \nresource commitments when determining which LSEs caused, mitigated, or avoided the residual need \nfor RBP procurement. \n26. A related but distinct concern involves the LSEs that procured, developed, or retained those \nresources. For vertically integrated utilities, cooperatives, and other self-supply LSEs, the key question is \nwhether their resource-adequacy actions reduce their own RBP exposure. Proposed Tariff sections 18.1 \nand 18.2 appear to recognize Qualifying RBP Offset UCAP MW for purposes of reducing the aggregate \nprocurement target. However, the tariff must distinguish between reducing a zonal or system-wide \nprocurement target and reducing the obligation of the LSE that supplied the offset. If an offset reduces \nonly the aggregate target and does not follow the LSE or load responsible for the mitigation, the tariff \nmay still assign RBP costs and collateral requirements, and impose risks on an entity that prudently acted \nto reduce the need for procurement. \n27. My concern with proposed section 18.2 is not simply that it may exclude certain categories of \npotential Qualifying RBP Offset UCAP MW. Rather, the more fundamental issue is that reducing the \naggregate procurement target is not the same as protecting the LSE that supplied or sponsored the \noffset from RBP Charges, collateral obligations, or default-allocation risk. The tariff should clearly state \nwhether, and how, a recognized offset follows the associated LSE or load when PJM calculates LSE-\nspecific RBO MW, RBP Charges, and collateral requirements."},{"page":59,"startToken":19269,"endToken":19740,"text":"Adam Bednarczyk Affidavit \n8 \n \n28. The distinction can be illustrated through a simple example. Assume LSE A serves a new 500 MW \nlarge load that contributes to the need for Reliability Backstop Procurement capacity. LSE B serves \nexisting native load and has already developed or contracted sufficient resources to support its \nforecasted load growth. Further assume that LSE B sponsors a qualifying offset that PJM recognizes \nunder proposed sections 18.1 and 18.2, thereby reducing the overall procurement target. \n29. Section 18.2 defines Qualifying RBP Offset UCAP MW as capacity that has not previously supported a \ncapacity commitment or been committed in an FRR Plan and that is supported by specified evidence, \nincluding certain bilateral contracts, RERRA-approved or accepted self-supply generation, or demand-\nside commitments. Yet PJM's proposal does not expressly provide that the offset secured by LSE B will \nreduce LSE B's own RBO MW, cost assignment, or related collateral obligation. Instead, the offset \nappears to reduce the aggregate or zonal procurement target, after which either the Electric Distributor \ndetermines the downstream allocation or PJM defaults to a zonal allocation methodology. \n30. The problem becomes most apparent under the default-allocation approach. LSE B is not necessarily \ninsulated from RBP Charges or collateral obligations merely because its actions reduced the procurement \ntarget. Because the tariff does not clearly provide that the offset will flow through to LSE B's own \nobligation before costs and collateral are assigned, LSE B may remain exposed to RBP costs and credit \nobligations despite having taken the very actions that reduced the need for procurement. \n31. An even more direct example illustrates the concern. Assume an LSE has a 1,000 MW resource \nportfolio and serves 900 MW of existing load. The LSE then adds a 100 MW large load that is fully \ncovered by its existing owned resources or bilateral contracts. Under a reliability-neutral framework, that \nLSE has not created an incremental need for additional backstop procurement. Yet PJM's proposal does \nnot clearly ensure that the LSE's existing resource position will eliminate its RBP exposure. If the LSE \nnevertheless receives an RBP cost allocation, it effectively pays twice: first for the resources it already \nsecured to serve the load and again for a long-term RBP obligation imposed through PJM's allocation \nprocess. \n32. The incentive issue is particularly important because the Coalition proposal, in combination with a \nConnect and Manage framework, would have tied procurement obligations to corresponding operational \nconsequences. Under that combined approach, a large load that failed to bring sufficient capacity, self-\nsupply resources, bilateral contracts would remain subject to curtailment per the proposed Connect and \nManage provisions. The possibility of curtailment served as a practical forcing mechanism that \nencouraged reliability-neutral behavior. PJM's RBP filing does not establish the same connection \nbetween procurement responsibility and operational consequences. As filed, an LSE may face"},{"page":60,"startToken":19740,"endToken":20195,"text":"Adam Bednarczyk Affidavit \n9 \n \nuncertainty regarding its ultimate cost exposure while lacking a clear and predictable mechanism \nthrough which reliability-neutral actions eliminate that exposure. \n33. This outcome creates both a cost-causation problem and an incentive problem. An LSE may have \nsufficient owned resources, bilateral capacity contracts, demand response, curtailment commitments, or \nother qualifying portfolio assets to satisfy its load obligations, including all or part of the large load that \nPJM seeks to address through the RBP. If PJM does not ensure that those LSE-specific resource positions \nreduce that LSE's own RBO MW, charges, and collateral requirements, the proposal risks requiring the \nLSE to pay twice for capacity: once through resources or contracts it already secured and again through \nan RBP allocation. \n34. The concern extends beyond ordinary double payment. The RBP may impose obligations lasting as \nlong as fifteen years, together with substantial collateral and credit requirements. As a result, an LSE that \nhas already planned prudently and secured adequate resources could nonetheless incur a second long-\nterm obligation that provides little or no additional reliability benefit. That outcome weakens incentives \nfor proactive resource planning, socializes the benefits of prudent mitigation, and leaves the planning \nLSE exposed to residual charges, collateral obligations, and default-allocation risk. \n35. This concern extends beyond self-supply LSEs. Any LSE considering bilateral contracts, demand \nresponse, curtailment commitments, or self-supply resources faces uncertainty if the tariff does not \nclearly provide that the resulting credit will reduce that LSE's own RBO MW, RBP Charges, and collateral \nexposure. The issue is particularly significant for self-supply LSEs because they may already have \nsubstantial resource commitments in place that mitigate or eliminate the need for RBP procurement, yet \nthe proposal does not clearly ensure that those commitments will be recognized throughout the \nprocurement, allocation, settlement, and collateral framework. \nVII. \nEffects on LSEs, Electric Distributors, and States \n36. For purposes of this affidavit, I use the term “LSE” to mean a load-serving entity that bears \nwholesale obligations under the PJM governing documents. The RAA defines a Load Serving Entity as an \nentity serving end users in the PJM Region that has authority or an obligation under state or local law, \nregulation, or franchise to sell electric energy to those end users, and includes certain end-use \ncustomers that manage their own supply. This category includes self-supply LSEs, such as vertically \nintegrated utilities and cooperatives, as well as LSEs that serve load through market purchases or \nbilateral arrangements. The concerns raised by the RBP are not identical for every LSE. Self-supply LSEs \nface particular risk if the tariff does not recognize their owned or contracted resource positions. More \nbroadly, all LSEs face risk under proposed Tariff section 18.3 and proposed RAA Articles 7.2B and 7.2C if"},{"page":61,"startToken":20195,"endToken":20673,"text":"Adam Bednarczyk Affidavit \n10 \n \nPJM ultimately relies on its default allocation mechanism, which assigns RBP Charges to all LSEs within a \nzone or area based on Daily Unforced Capacity Obligation MW when no Electric Distributor allocation is \nreported. That approach risks assigning costs through a broad load-ratio methodology rather than \ntracing them to the incremental reliability need that gave rise to the procurement. \n37. For LSEs serving new large loads, the RBP may create perverse incentives. PJM appears to intend that \nlarge-load customers and their serving LSEs bring qualifying capacity or accept curtailment to mitigate \nthe need for backstop procurement. That incentive, however, is effective only if the LSE can determine in \nadvance that those actions will reduce its own RBP obligation. The Coalition proposal addressed this \nissue through a mandatory Connect and Manage framework that coupled procurement responsibility \nwith operational consequences. By contrast, PJM's current proposal relies in part on the separate and \nvoluntary IRAS framework and does not provide the same clear forcing mechanism. \n38. If the benefit of a Qualifying RBP Offset UCAP MW is applied only at a zonal or Electric Distributor \nlevel and is not traced to the LSE that undertook the mitigation action, the proposal weakens the \nincentive for voluntary forward procurement and load-management measures. Under those \ncircumstances, an LSE may not know whether self-supply, bilateral contracts, demand response, or \ncurtailment commitments will reduce its own RBP exposure. That uncertainty may encourage reliance on \nex post allocation outcomes rather than proactive actions that reduce future resource-adequacy needs. \n39. LSEs serving existing native load face a different concern. This issue relates specifically to PJM's \nproposed default allocation methodology rather than to the self-supply example discussed above. If \nPJM's section 18.3 process does not result in an Electric Distributor or state/RERRA allocation mechanism \nthat identifies the responsible LSEs, PJM may allocate residual RBP obligations across LSEs in the zone \nusing Daily Unforced Capacity Obligation MW or another load-ratio proxy. In that circumstance, an LSE \nmay bear costs associated with large loads served by other LSEs in the same zone despite having taken \nno action that contributed to the procurement need. \n40. For example, assume LSE B has a 1,000 MW resource portfolio and serves 900 MW of existing load. If \na new 100 MW large load is also served from that existing portfolio, LSE B has not created an \nincremental resource shortfall requiring RBP procurement. If PJM nevertheless allocates RBP costs to LSE \nB through a zonal load-ratio mechanism rather than recognizing that LSE B's resource position already \ncovers the incremental load, LSE B could incur RBP charges despite having acted in a reliability-neutral \nmanner. That outcome would not send an efficient planning signal because the LSE already procured the \nresources necessary to serve the load and may have no practical means of avoiding the costs assigned \nthrough the default mechanism."},{"page":62,"startToken":20673,"endToken":21140,"text":"Adam Bednarczyk Affidavit \n11 \n \n41. Proposed RAA Articles 7.2B and 7.2C raise a separate administrability concern because they establish \nthe framework through which Electric Distributors communicate and report RBO MW for purposes of \nallocating RBP Charges and credits. Article 7.2B provides that when an Electric Distributor reports RBO \nMW for each LSE within its zone or area, PJM will allocate RBP Charges and shortfall credits in \naccordance with that notification. If no such notification is provided, PJM will allocate those charges and \ncredits based on each LSE's share of Daily Unforced Capacity Obligation MW. Article 7.2C further requires \nElectric Distributors to provide PJM, no later than 36 hours before each Operating Day, any RBO MW \nassociated with each RAA party serving load in the applicable zone or area. \n42. Electric Distributors are not the same entities as RAA load-serving parties, and their traditional role is \ngenerally associated with metering, customer data, and distribution system functions rather than \nassigning wholesale cost responsibility. If PJM intends Electric Distributors to identify or communicate \nRBO MW, coordinate with state or RERRA allocation processes, and translate those determinations into \nwholesale settlement consequences, the federal tariff should clearly specify the mechanics of that \nprocess and explain how it produces just and reasonable wholesale charges. \n43. PJM's attempt to analogize these responsibilities to obligations imposed on Transmission Owners in \nother proceedings does not resolve that concern. Transmission Owners and Electric Distributors perform \ndifferent functions and are separately defined under the PJM governing documents. A requirement that \na Transmission Owner identify network upgrades associated with serving large-load customers is directly \nrelated to the Transmission Owner's facilities and planning responsibilities. By contrast, the proposed \nRBP requires Electric Distributors to provide or convey allocation inputs that determine LSE-specific \nwholesale obligations and collateral requirements. Even if PJM is correct that the information sought is \n\"in connection with\" or \"directly affects\" wholesale rates, that observation does not explain why Electric \nDistributors are the appropriate entities to provide the information or why a wholesale cost-allocation \nframework should depend on that process. \n44. The Coalition proposal demonstrates that a more traceable and administrable alternative is \navailable. Under that framework, PJM would identify responsibility at the wholesale level through a \nregistry and subscription process that associated specific RBP MW with specific LSEs and loads before \nassigning costs, credits, offsets, and collateral requirements. The Coalition RBP proposal did not impose \ncurtailment consequences. Rather, in combination with a Connect and Manage framework, the registry \ncould have enabled the transparent implementation of curtailment actions by PJM, TO, EDC, and LSE. \n45. By contrast, PJM's proposal relies heavily on downstream Electric Distributor, state, and RERRA \nprocesses to determine how obligations ultimately flow to individual LSEs. This distinction is important \nbecause the Coalition proposal established responsibility first and then used retail or administrative"},{"page":63,"startToken":21140,"endToken":21578,"text":"Adam Bednarczyk Affidavit \n12 \n \nprocesses to implement that responsibility. PJM's proposal reverses that sequence by relying on \ndownstream processes to determine critical wholesale allocation outcomes. \n46. This distinction does not suggest that states or RERRAs lack an appropriate role in addressing retail \nallocation or retail-rate consequences. Rather, the market-design concern is that PJM has not first \nestablished a sufficiently specific wholesale framework that identifies the responsible LSE, records the \nrelevant large-load obligation, tracks offsets and mitigation measures associated with that obligation, \nand maintains a clear connection between cost responsibility and cost causation. Had PJM performed \nthose wholesale functions first, downstream state, RERRA, and Electric Distributor processes could \noperate in a more administrative capacity and would be less likely to shift costs to entities that did not \ncreate or fail to mitigate the incremental procurement need. \nVIII. Hedgeability, Traceability, and Collateral Risk \n47. Proposed Tariff section 18.8 amplifies the same cost-allocation concerns because it imposes \ncollateral obligations on LSEs based on their RBP exposure. Section 18.8 applies its credit provisions to \n“LSEs allocated costs for RBP UCAP MW procured through the Reliability Backstop Procurement, as \ndetermined in accordance with Tariff, Attachment DD, section 18.3,” and makes clear that RBP credit \nrequirements are “separate from and additional to” credit requirements associated with RPM Auctions, \nbilateral transactions, and other PJM market activity. Collateral requirements are just and reasonable \nonly when the underlying obligation is sufficiently knowable, measurable, and attributable to the \nresponsible party before collateral is required. Here, however, an LSE’s RBO MW and resulting RBP \nCharges may depend on subsequent Electric Distributor reporting, state or RERRA allocation \ndeterminations, PJM’s treatment of offsets and opt-outs, and the potential application of default Daily \nUnforced Capacity Obligation allocations. Under those circumstances, an LSE may be unable to \ndetermine its exposure with sufficient certainty to plan for future payment obligations or collateral \nrequirements. \n48. The insufficiency of the proposal stems from the fact that sections 18.1 and 18.2 reduce the \nprocurement target without clearly establishing how offsets and opt-outs affect LSE-specific cost and \ncollateral exposure. For example, if LSE A serves a new large load that contributes to the need for RBP \nprocurement while LSE B develops or contracts for resources that qualify as a Qualifying RBP Offset \nUCAP MW, the tariff does not clearly provide whether that offset reduces only the zonal procurement \ntarget or also reduces LSE B’s own RBO MW, RBP Charges, and collateral obligations. Without that \ninformation, an LSE cannot determine its actual exposure, evaluate the value of mitigation options, or \neffectively hedge the resulting obligation. The issue is therefore not merely whether offsets are"},{"page":64,"startToken":21578,"endToken":22043,"text":"Adam Bednarczyk Affidavit \n13 \n \nrecognized, but whether the tariff ensures that the benefit of those offsets follows the LSE that supplied \nthem. \n49. Collateral secures an obligation, but it does not make that obligation more transparent, traceable, or \nhedgeable. Section 18.8 reflects, and therefore inherits, the allocation framework established elsewhere \nin the RBP proposal. Section 18.8(b)(i)(B)(1) would require certain LSEs to post or maintain RBP Collateral \nequal to “$1.5 million x the allocated RBP Obligation MW.”2 Section 18.8(b)(i)(B)(2) further provides that, \nwhere no RBP Obligations are reported for an Electric Distributor zone or area, PJM may require LSEs to \npost collateral based on their pro rata share of Daily Unforced Capacity Obligation MW. \n50. Collateral secures an obligation, but it does not establish whether the underlying obligation satisfies \ncost-causation principles. If section 18.3 allocates costs through a broad zonal default mechanism, fails to \nfully account for recognized offsets and opt-outs, or does not credit an LSE’s owned or contracted \nresources against that LSE’s own RBO MW, section 18.8 requires the LSE to post collateral against those \nsame potentially misallocated obligations. \n51. The consequences can be significant. Consider an LSE with 1,000 MW of owned or contracted \nresources serving 900 MW of existing load plus a 100 MW large load. If that portfolio already covers the \nfull 1,000 MW requirement, the LSE has not created an incremental need for backstop procurement. Yet \nif PJM allocates RBP costs through a zonal default mechanism rather than recognizing that resource \nposition, the LSE may be required both to pay for capacity it already procured and to post collateral \nsupporting a separate long-term RBP obligation. In that circumstance, the collateral requirement \nincreases the financial consequences of the allocation framework without improving the connection \nbetween cost responsibility and the actions that created the procurement need. The LSE may therefore \nface collateral obligations that it neither reasonably anticipated nor could effectively hedge. \n52. The relevant RBP risk extends beyond ordinary counterparty default risk. The RBP is a large, one-\ntime procurement that may commit substantial quantities of capacity based on forecasts of future load \ngrowth. Those forecasts will inevitably differ from actual outcomes. Some forecasted loads may be \ndelayed, reduced, relocated, or abandoned, while others may develop differently than anticipated. Large \ndata centers and other large-load customers may be financially strong and unlikely to default on short-\nterm payment obligations, yet still create significant load-realization risk if future business conditions, \ntechnology changes, economic developments, or shifts in demand reduce or eliminate the need for the \nprojected load after PJM has already entered into long-term procurement commitments. \n \n2 PJM Interconnection, L.L.C., Proposed Open Access Transmission Tariff, Attachment DD § 18.8(b)(i)(B)(1)."},{"page":65,"startToken":22043,"endToken":22483,"text":"Adam Bednarczyk Affidavit \n14 \n \n53. That risk is both temporal and concentrated. It does not scale in proportion to ordinary forecasting \nerror because a small number of very large load decisions can create substantial procurement, \ndeliverability, and stranded-cost consequences within particular PJM zones or areas. Those impacts may \nalso shift over time as the location and timing of large-load development evolve. \n54. Because RBO MW assignments and corresponding RBP Charges may remain uncertain or change \nover time, an LSE may have no practical way to determine in advance the direct costs or collateral \nobligations for which it will ultimately be responsible. That uncertainty can itself increase default risk. An \nLSE that receives an unexpected RBP obligation or collateral requirement may not be able to satisfy it. If \nthat occurs, the resulting costs may flow through the same residual or default-allocation mechanisms to \nother LSEs, including entities that neither served the large load nor contributed to the procurement \nneed. In that respect, the uncertainty embedded in the allocation framework risks creating the same \ntype of mutualized exposure that collateral requirements are ordinarily designed to prevent. \n55. The relevant question is whether the collateral framework effectively ring-fences the costs and risks \nassociated with large-load-driven procurement to the loads, or the suppliers serving those loads, that \ncreate the exposure. \n56. Unlike the Coalition proposal, which would have assigned obligations at the time procurement \ncommitments were established through a registry-based framework, PJM’s proposal leaves RBO MW \nassignments, offsets, opt-outs, and collateral exposure to be determined through subsequent allocation \nprocesses. That approach reduces transparency and predictability for affected LSEs. Without a \nmechanism that links procurement commitments to identifiable obligations from the outset, collateral \nmay secure obligations that market participants cannot readily identify, trace to the underlying reliability \nneed, or effectively hedge. \n57. In my opinion, section 18.8 does not fully address the credit-risk concerns created by the broader \nRBP allocation framework. The provision requires collateral for RBO obligations that may not be known \nuntil PJM determines LSE-specific RBO MW, applies Qualifying RBP Offset UCAP MW and opt-out \nreductions, completes the section 18.3 allocation process, and reports the resulting obligations. This \npoint is particularly important because the tariff appears to use offsets and opt-outs to reduce the \naggregate procurement target without clearly stating that those same reductions will apply to the \naffected LSE’s own cost and collateral obligations. \n58. Until those determinations occur, an LSE cannot reliably determine either the amount or the basis of \nits obligation. Collateral posted under those circumstances secures a contingent and uncertain exposure \nrather than a clearly defined obligation. As a result, the provision may increase rather than reduce"},{"page":66,"startToken":22483,"endToken":22913,"text":"Adam Bednarczyk Affidavit \n15 \n \nuncertainty, may complicate efforts to hedge future obligations, and may ultimately shift risk to other \nLSEs, including entities that do not serve large loads as PJM defines them. \nIX. FRR and RPM Self-Supply Asymmetry \n59. The RBP also treats FRR entities and RPM self-supply entities differently in ways that raise \ncomparability concerns. PJM proposes to exclude “Fixed Resource Requirement (‘FRR’) Entities as of the \n2028/2029 Delivery Year” from the Reliability Backstop Procurement, including both the Initial and Final \nRBP Targets, while continuing to hold an Electric Distributor zone or area responsible for RBP UCAP MW \nif that zone or area later becomes an FRR Service Area. PJM’s proposed RAA revisions further provide \nthat, beginning with the 2028/2029 Delivery Year and thereafter, an FRR Capacity Plan must consist \nsolely of Capacity Performance Resources and Seasonal Capacity Performance Resources, and that an \nFRR Entity may not use certain existing generation resources or any resource committed through the RBP \nto satisfy its FRR Capacity Plan. \n60. When those provisions are read together with RAA Schedule 8.1, which requires an FRR Capacity \nPlan to include sufficient capacity to serve all load in the FRR Service Area, including load growth, an \nimportant comparability issue emerges. An FRR entity that satisfies its resource adequacy obligation \nthrough qualifying owned resources, and at least some categories of existing resources, is effectively \ninsulated from RBP exposure. By contrast, an RPM LSE that has prudently developed, retained, or \ncontracted for sufficient resources to serve all or part of its incremental load does not appear to receive \ncomparable treatment under the RBP cost-allocation framework. If PJM recognizes resource adequacy \nactions taken under the FRR construct for purposes of avoiding RBP exposure, principles of comparability \nand cost causation suggest that it should similarly recognize owned resources, bilateral contracts, and \ncomparable resource commitments maintained by RPM LSEs when determining RBO MW, RBP Charges, \nand collateral obligations. As filed, the proposal appears to exempt FRR entities from the RBP framework \nwhile providing no equivalent mechanism to credit RPM LSEs that have undertaken similar resource \nadequacy actions. \n61. I am not suggesting that existing resources should receive RBP compensation. The issue is instead \nwhether existing owned resources, bilateral contracts, and other resource adequacy commitments \nshould be recognized when determining whether an LSE created the residual need for RBP procurement \nand whether that LSE should bear RBP-related costs and obligations. PJM can reasonably limit RBP \npayments to new backstop resources while still recognizing existing resources, or comparable \ncontractual arrangements, for purposes of cost allocation, collateral assignment, and reliability-neutrality \ndeterminations."},{"page":67,"startToken":22913,"endToken":23357,"text":"Adam Bednarczyk Affidavit \n16 \n \n62. More fundamentally, an LSE’s choice between the RPM construct and the FRR alternative should not \ndetermine whether its resource position receives recognition under the RBP. An LSE that elects RPM but \nsecures sufficient resources to support its incremental load stands in a comparable position to an FRR \nentity that satisfies its obligations through its FRR Capacity Plan. The relevant question is whether the \nLSE has taken actions that mitigate or eliminate the incremental reliability need, not which resource \nadequacy construct it uses to satisfy its RAA obligations. \n63. PJM’s proposed revisions also appear unclear regarding the extent to which a future FRR entity may \nrely on existing resources, including bilateral contracts associated with existing resources, to satisfy FRR \nobligations. To the extent those provisions conflict with other RAA provisions governing FRR resource \neligibility, or are interpreted to restrict reliance on existing bilateral arrangements, they could create \nadditional market-design concerns. That issue is particularly important for LSEs whose resource \nadequacy strategies rely heavily on long-term bilateral contracts. \n64. Ultimately, comparable treatment matters because the RBP is intended to address incremental \nreliability need, not to favor one resource adequacy construct over another. If two LSEs have each \nsecured sufficient resources to support their incremental load and satisfy reliability-neutrality objectives, \nthe fact that one participates through FRR and the other through RPM should not, by itself, determine \nwhether one avoids RBP obligations while the other remains exposed to RBP costs, collateral \nrequirements, and related risks. \nX. Application to EKPC \n65. I understand that EKPC is not identified in PJM’s allocation table as directly responsible for RBP \ncosts associated with the large-load adjustments underlying the proposed procurement. That fact is \nimportant, but it does not eliminate EKPC’s exposure under the filed proposal. EKPC’s concern is not that \nit will necessarily receive a direct Electric Distributor assignment or a direct allocation under PJM’s \ndefault cost allocation methodology. Rather, EKPC’s concern is that the proposal may impose RBP costs \nand collateral obligations on other LSEs in a manner that is not closely tied to cost causation, thereby \nincreasing the likelihood that those obligations become unmanageable and ultimately result in defaults. \n66. That concern is particularly relevant because proposed Tariff section 18.9(a) provides that, if an LSE \ndefaults and fails to pay an RBP Charge, “the defaulted amount will be allocated to all remaining Load \nServing Entities responsible for paying RBP Charges based on their pro-rata share of the total RBP \nCharges for all such Load Serving Entities,”3 subject to any available RBP Collateral posted by the \n \n3 PJM Interconnection, L.L.C., Proposed Open Access Transmission Tariff, Attachment DD § 18.9(a)."},{"page":68,"startToken":23357,"endToken":23816,"text":"Adam Bednarczyk Affidavit \n17 \n \ndefaulting LSE. As a result, even if EKPC is not expected to receive an initial RBP allocation associated \nwith the identified large-load growth, EKPC may nevertheless face exposure through the proposal’s \ndefault-allocation framework if other LSEs assigned RBP obligations are unable to satisfy them. \n67. From EKPC’s perspective, the market-design concern therefore arises one step removed from the \ninitial allocation. The risk is not primarily that EKPC will be identified as causing the need for Reliability \nBackstop Procurement. Rather, the risk is that PJM’s allocation, offset, collateral, and responsibility-\ntracking mechanisms may fail to align costs and risks with the entities that created the procurement \nneed. If those entities are assigned obligations that are difficult to predict, hedge, finance, or recover, \nresulting defaults may transfer costs to other market participants, including EKPC, through the residual \nallocation provisions. \n68. This exposure is a market-design concern independent of whether EKPC receives a direct initial \nassignment. A tariff framework that does not identify responsible LSEs at the outset, track recognized \noffsets and opt-ins to those LSEs, and maintain default-allocation rules tied as closely as practicable to \ncost causation can shift the financial consequences of large-load-driven procurement to entities that did \nnot create the underlying need. I do not offer a legal conclusion regarding the ultimate tariff standard. \nMy point is that, as a matter of market design, the filed framework leaves residual cost and collateral \nrisks that are not fully traceable to the entities responsible for the incremental procurement need and, \nas a result, may ultimately expose other LSEs, including EKPC, to those risks. \nXI. Conclusion \n69. In my opinion, PJM has identified a serious reliability challenge, but the proposed RBP does not \nsatisfy PJM's Section 205 burden as filed. My concern is not a general disagreement with PJM's policy \nobjectives. Rather, the specific design choices reflected in proposed Tariff sections 18.1, 18.2, 18.3, 18.4, \n18.5, and 18.8, together with proposed RAA Articles 7.2B and 7.2C, do not adequately align \nresponsibility for the procurement with responsibility for the resulting costs, credit exposure, and \ncollateral obligations. The proposal may impose long-term costs and collateral requirements on LSEs that \ndid not create the residual procurement need, may fail to recognize or protect LSEs that prudently \naddressed resource adequacy through self-supply, bilateral contracting, or other mitigation measures, \nand relies on Electric Distributor, state, and RERRA processes to resolve allocation questions that should \nbe addressed more directly and transparently in the federal tariff. \n70. For these reasons, I conclude that the proposal does not adequately align RBP costs, credits, \nreporting obligations, and collateral requirements with the reliability-neutrality principle that should \ngovern new large-load growth. The proposed tariff does not consistently satisfy the principles of"},{"page":69,"startToken":23816,"endToken":23950,"text":"Adam Bednarczyk Affidavit \n18 \n \ntransparency, traceability, and cost causation. It does not consistently identify the entities responsible for \nthe incremental reliability need, track the actions taken to mitigate that need, or ensure that resulting \ncosts, credits, collateral obligations, and risks remain aligned with those entities. The proposal also \nseparates procurement from the operational mechanisms that would otherwise encourage reliability-\nneutral behavior. Unlike the Coalition proposal supported by EKPC, the filing does not establish a unified \nframework that identifies the responsible load, records mitigating actions, assigns resulting obligations, \nand links reliability consequences to the failure to bring sufficient resources. As a result, the proposal \nweakens the connection between the parties that create or mitigate the need for backstop procurement \nand the parties that ultimately bear the associated costs and risks. \n71. This completes my affidavit."},{"page":70,"startToken":23950,"endToken":23984,"text":"VERIFICATION OF AFFIDAVIT\nPursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the foregoing\nAffidavit is true and correct.\nExecuted August 21, 2026. \nBy: _____________________________ \nAdam Bednarczyk"},{"page":71,"startToken":23984,"endToken":23991,"text":"Attachment 2 \nAffidavit of Carl F. Coscia"},{"page":72,"startToken":23991,"endToken":24591,"text":"1 \n \nAFFIDAVIT OF CARL F. COSCIA, Ph.D. \nOn behalf of East Kentucky Power Cooperative, Inc. \nPJM Interconnection, L.L.C., FERC Docket No. ER26-3380-000 \nPrepared by Toller Energy  ·  21 August 2026 \n \nI.  INTRODUCTION AND QUALIFICATIONS \n1. \nMy name is Carl F. Coscia. I am the Principal of Toller Energy, an independent energy consulting \nfirm. My business address is Wynnewood, Pennsylvania 19096. I have been retained by Eversheds \nSutherland (US) LLP on behalf of East Kentucky Power Cooperative, Inc. to evaluate the credit \nand collateral provisions of the Reliability Backstop Procurement proposed by PJM \nInterconnection, L.L.C.1 The opinions expressed in this affidavit are my own. No part of my \ncompensation is contingent on the outcome of this proceeding. \n2. \nI hold a Ph.D. in Economics from the University of Minnesota, and a B.S. in Economics and a \nB.A. in Mathematics from the University of Kansas. I have more than twenty-five years of \nexperience in wholesale power and commodity markets, concentrated in credit risk, market design \nand regulatory proceedings, and have provided testimony, affidavits or economic analysis in more \nthan forty proceedings before the Federal Energy Regulatory Commission, the Commodity \nFutures Trading Commission, and other regulatory and self-regulatory bodies. \n3. \nFrom September 2022 to March 2026 I served as Chief Risk Officer of PJM Interconnection, \nL.L.C., where I led the corporate risk function across the energy, capacity and financial \ntransmission rights markets. The credit provisions of Attachment Q to the Open Access \nTransmission Tariff fell within my responsibility, as did the Key Risk Metrics reported to the Risk \nManagement Committee and relied on in this affidavit. I led PJM’s work with stakeholders on \nPeak Market Activity, Know Your Customer, minimum capitalization and RPM credit support, \nand PJM’s management of the collateral consequences of Winter Storm Elliott and Winter Storm \nFern. I administered the credit policy from which the provisions at issue in this proceeding depart. \n4. \nBased on that experience I am familiar with how collateral requirements in the organized markets \nare derived from measured exposure, administered as that exposure changes, and released as it \ndeclines, and with the liquidity consequences of collateral calls for the participants subject to \nthem. Before joining PJM I held senior risk and commercial roles at EnBW AG, Hartree Partners, \nLP, Constellation Energy and TXU, and earlier served as a Branch Chief in the Office of \nEnforcement at the Federal Energy Regulatory Commission and at The Brattle Group. At \nConstellation I was the primary author of the company’s comments in the Commission’s credit \nreform rulemaking, Order No. 741, which is cited in this affidavit. \n5. \nIn preparing this affidavit I have reviewed the July 31, 2026 filing in this docket and the affidavits \nsubmitted with it, the provisions of the Open Access Transmission Tariff, the Operating \nAgreement and the Reliability Assurance Agreement to which those provisions refer, the materials \npresented to PJM stakeholders during the development of the proposal, PJM’s Key Risk Metrics \nand Credit Metrics reporting to the Risk Management Committee, PJM’s audited financial \nstatements, the reports of the Independent Market Monitor, and the public financial reports of the \nentities discussed. Materials on which I rely are cited where used. \n \n1 I have also been retained by Northern Virginia Electric Cooperative (“NOVEC”) in this docket and have submitted \na separate affidavit on its behalf addressing the application of the proposed provisions to that cooperative and to the \nNOVEC zone/area. Section XI of this affidavit uses the NOVEC zone/area as an illustration because it carries the \nlargest single-zone allocation to a cooperative under PJM's own figures."},{"page":73,"startToken":24591,"endToken":25246,"text":"2 \n \nII.  PURPOSE AND SUMMARY OF OPINIONS \n6. \nI have been asked by counsel to review the credit and collateral provisions of the Reliability \nBackstop Procurement proposed by PJM Interconnection, L.L.C. on July 31, 2026 in Docket No. \nER26-3380-000, and to address five questions: (i) whether the proposed RBP Credit Rate is \nderived on terms standard to commercial collateral arrangements, which require an identified \nmeasure of exposure, a tenor over which that exposure is held, and a liquidation value at which the \ndefaulted position would be replaced; (ii) whether the proposed requirement meets the standard for \ncollateral, namely to protect the non-defaulting party from loss; (iii) whether a Load Serving \nEntity subject to an RBP Charge can determine, from the filed rate, the amount it will be required \nto post; (iv) whether the requirement itself creates systemic liquidity risk among the entities \nobligated to post it; and (v) how a default is socialized under the proposed provisions, and what \nfollows from that allocation. My opinions address proposed Tariff, Attachment DD, sections 18.8 \nand 18.9, and the provisions on which those sections depend. \n7. \nMy opinions are as follows. \n(a)  The requirement is without precedent in PJM. At the Initial RBP Target, the LSE collateral \nrequirement is approximately $10.2 billion. PJM’s monthly Key Risk Metrics reporting \nshows total collateral held from all Members, against every market it operates, averaging \napproximately $6.2 billion in 2024 and $7.0 billion in 2025. It rose in 2026 as measured \nexposure rose, peaking at approximately $13.1 billion in February 2026 and standing at \napproximately $10.9 billion on July 30, 2026. \n(b)  The requirement is not derived on standard commercial terms. Collateral is sized to the \ncost of replacing defaulted performance, which requires identifying the position to be \nreplaced, the price at which it would be replaced, and the period over which the exposure is \nheld. Section 18.8 identifies none of the three. \n(c)  The requirement is a financing calculation rather than a measure of exposure. The RBP \nsettles as a contract for differences, and the gross strike stream is never billed to load. PJM \nderived the $1.5 million Credit Rate as approximately fifty percent of the gross fifteen-year \ncontractual value of $3.04 million per MW. \n(d)  The requirement does not protect the non-defaulting party from loss in the manner \nPJM’s own credit policy contemplates. Attachment Q, Section I states that PJM must have \nauthority to monitor and manage credit risk on an ongoing basis and to act promptly, in order \nto protect the PJM Markets and PJM Members from losses. Section 18.8 provides no \nongoing measurement and no recalculation as exposure changes. \n(e)  The quantity of MW to which the Credit Rate applies cannot be determined from the \ntariff. Section 18.8(b)(i)(A) keys the requirement to committed MW reduced only for \nrescissions, notwithstanding that commercial operation dates are permitted through June 1, \n2032, while section 18.8(b)(i)(B)(1) scales each LSE’s posting to the Final RBP Target, a \nquantity that diverges from committed MW if the procurement clears short as PJM states it \nmay. \n(f)  The reduction of the requirement over the term is undefined. Attachment Q provides that \ncollateral no longer required “shall be returned at the request of a Participant” within two \nBusiness Days, and Attachment Q, Section VI.B.3 sets out a mandatory, participant-initiated \nschedule reducing RPM auction credit across five stated milestones. Section 18.8(b)(i)(A) \nprovides only that the Credit Rate “may be reduced” by the Office of the Interconnection “to \nan amount sufficient,” without methodology, schedule or request mechanism. \n(g)  The cost of carrying the requirement is material and is not recovered. The requirement \nimposes a material financing cost on load-serving entities that no provision of the proposed \ntariff recovers, and that appears in no figure PJM has presented. Its magnitude depends on"},{"page":74,"startToken":25246,"endToken":25814,"text":"3 \n \nthe form of collateral elected and on the entity’s own credit terms. At the Initial RBP Target, \nthe annual cost ranges from approximately $102 million at 100 basis points to approximately \n$307 million at 300 basis points, against approximately $573 million billed to load in the \nfirst Delivery Year. Expressed per unit, the cost is approximately $41.10 to $123.29 per \nMW-day, or approximately seven to twenty-two percent of the $555 maximum willingness \nto pay. \n(h)  The requirement creates systemic liquidity risk among the entities obligated to post it. \nApproximately $10.2 billion becomes due on a single date, in a form limited to cash or \nletters of credit. On PJM’s illustrative figures the Electric Distributor zone/area PJM \ndesignates NVEC — served by Northern Virginia Electric Cooperative, and referred to in \nthis affidavit as the NOVEC zone — carries an initial allocation of 1,302.6 UCAP MW, \ncorresponding to collateral of approximately $1.95 billion. The requirement falls without \nregard to the balance sheet of the entity obligated to post it. \n(i)  The socialization of a default increases the obligation of the remaining LSEs and reaches \nmembers with no allocation. Section 18.9(a) reallocates a defaulted RBP Charge pro rata \namong the remaining LSEs paying RBP Charges. Under Operating Agreement, section \n15.2.2, the residual exposure extends to PJM Members generally. \n8. \nI do not address the reliability need for the procurement, the absence of a locational requirement, \nthe role assigned to Electric Distributors, or the jurisdictional questions raised by that role. My \nopinions on the sizing of the credit requirement do not depend on the resolution of any of those \nissues. \n9. \nThe principle underlying my opinions is not complex. A security deposit is sized to the damage a \ntenant might do, not to the rent due over the life of the lease. A landlord who demanded six \nmonths’ rent as a deposit on a twelve-month lease would be asked what damage he expected. That \nis approximately what the Credit Rate demands, measured against the gross value of the RBP \ncommitment on PJM’s own derivation. Measured against the exposure the collateral actually \nsecures, it demands considerably more. The filing does not identify the corresponding measured \nexposure. \nPART ONE — FRAMEWORK \nIII.  THE ROLE OF COLLATERAL \n10. \nThis section establishes the standards that govern collateral and margining in commercial and \norganized markets. Those standards are not matters of individual judgment. They are set out in \npublished guidance issued by the Committee on Payments and Market Infrastructures of the Bank \nfor International Settlements together with the International Organization of Securities \nCommissions, adopted by the Financial Stability Board as one of twelve key standards essential to \nfinancial stability, and, for the organized wholesale electric markets specifically, in the orders and \ncredit policy of this Commission. PJM’s own Attachment Q is constructed on the same \narchitecture. I set out those standards here so that the proposed RBP credit requirement can be \nmeasured against them in the sections that follow. \n11. \nCollateral secures replacement cost, not the contract. It is a risk instrument, not a revenue \ninstrument. The governing international standard defines the exposure being secured as \nreplacement-cost risk — “the risk of loss of unrealised gains on unsettled transactions with a \ncounterparty,” where “the resulting exposure is the cost of replacing the original transaction at \ncurrent market prices.” CPSS-IOSCO, Principles for Financial Market Infrastructures (April 2012) \n(“PFMI”) ¶ 2.5."},{"page":75,"startToken":25814,"endToken":26470,"text":"4 \n \n12. \nCollateral is accordingly held “to cover current and potential future exposures.” PFMI ¶ 1.13. \nPrinciple 4 requires that credit exposures be effectively measured, monitored and managed, and \nPrinciple 6 requires that a margin system be “risk-based and regularly reviewed.” \n13. \nPrice. Loss is contract price less replacement price. Because replacement price moves with the \nmarket, margin levels must be “commensurate with the risks and particular attributes of each \nproduct, portfolio, and market” the infrastructure serves. PFMI, Principle 6, Key Consideration 1. \nExposure is therefore recalculated rather than fixed. \n14. \nLiquidation. The exposure period runs from default to replacement. PFMI Principle 6, Key \nConsideration 3 requires initial margin models “sufficient to cover its potential future exposure to \nparticipants in the interval between the last margin collection and the close out of positions \nfollowing a participant default,” using “a conservative estimate of the time horizons for the \neffective hedging or close out of the particular types of products cleared.” The driver is the close-\nout horizon, not the remaining term of the contract. \n15. \nSizing therefore requires answering three questions: what position is being replaced, at what price, \nand over what period. That is the structure of PFMI Principle 6, and it is the structure of the \nCommission’s own credit policy, which identifies the function of collateral as preventing the \nsocialization of a default across the membership. Policy Statement on Electric Creditworthiness, \n109 FERC ¶ 61,186, P 17 (2004); Credit Reforms in Organized Wholesale Electric Markets, Order \nNo. 741-A, 134 FERC ¶ 61,126, n.3 (2011). I refer to these below as the three elements. \n16. \nRequirements are recalculated as exposure moves and released as it declines. PFMI Principle 6, \nKey Consideration 4 requires marking positions to market and collecting variation margin “at least \ndaily to limit the build-up of current exposures,” together with the authority and operational \ncapacity to make intraday calls. PFMI Principle 6, Key Consideration 7 requires that the margin \nsystem be regularly reviewed and validated. \n17. \nPJM’s own credit policy is constructed on these principles. The general credit requirement is sized \nto Peak Market Activity, computed from a participant’s own observed billing history; unsecured \ncredit allowances are keyed to creditworthiness and tangible net worth; and requirements are \nrecalculated on an ongoing basis. Attachment Q, Section V.A provides that collateral no longer \nrequired “shall be returned at the request of a Participant no later than two Business Days” \nfollowing PJMSettlement’s determination; that a Participant may substitute one approved form of \ncollateral for another absent a default; and that interest on cash accrues to the benefit of the \nParticipant. \n18. \nWhere PJM faces forward price exposure, it measures that exposure directly. The FTR Credit \nRequirement is calculated on a portfolio basis as initial margin, less Auction Revenue Right \nCredits, less Mark-to-Auction Value, less realized gains and losses, subject to a floor. Initial \nmargin for FTR Obligations is “determined utilizing a historical simulation value-at-risk \nmethodology that calculates the size and value at risk of the applicable FTR portfolio,” aggregated \nby straight sum for long-term positions and by a combination of straight sum and weighted root \nsum of squares for balance-of-period positions. The model “will employ a confidence interval of \n99 percent” — the same standard PFMI Principle 6, Key Consideration 3 requires. Historical \nvalues are adjusted forward where PJM’s economic planning model indicates that transmission \nupgrades will reduce congestion, and PJM may recalculate at any time and must do so no less \nfrequently than after each annual FTR auction. \n19. \nFor planned resources in the capacity market, PJM sizes the requirement to Net Cost of New Entry \nfor the applicable region or Locational Deliverability Area, subject to a floor, and reduces it as \nconstruction risk is retired. Attachment Q, Section VI.B.3 provides that the RPM Auction Credit \nrequirement “shall be reduced” on a stated schedule of five construction milestones, each initiated \nby written request of the Market Participant and supported by defined evidence."},{"page":76,"startToken":26470,"endToken":27145,"text":"5 \n \n20. \nThe concern with access is not incidental to the Commission’s regulation of RTOs. It is the reason \nthe Commission required them. In Order No. 2000 the Commission codified the minimum \ncharacteristics and functions an entity must satisfy to be an RTO, with the stated goal of promoting \n“efficiency in wholesale electricity markets” and ensuring “that electricity consumers pay the \nlowest price possible for reliable service.” Regional Transmission Orgs., Order No. 2000, 89 \nFERC ¶ 61,285, order on reh’g, Order No. 2000-A, 90 FERC ¶ 61,201 (2000). The rule was \ndirected at removing the remaining impediments to competition in wholesale power markets, and \nthe Commission grounded it in the observation that efficient and competitive markets develop only \nwhere participants have confidence that the system is administered fairly. A collateral requirement \nimposed by an RTO is a condition of access to the market that RTO was formed to operate. It is \nmeasured against that purpose. \n21. \nThe Commission has also stated the limiting principle on the other side. In establishing credit \npolicy, “the role of an RTO is to balance the competing goals of minimizing risk to non-defaulting \nmarket participants while, at the same time, ensuring that the credit or collateral requirements are \nnot so stringent that they unnecessarily inhibit access to the marketplace.” Sw. Power Pool, Inc., \n126 FERC ¶ 61,153, at P 19 (2009) (citing Sw. Power Pool, Inc., 114 FERC ¶ 61,222, at P 1 \n(2006), and Midwest Indep. Transmission Sys. Operator, Inc., 115 FERC ¶ 61,296, at P 16 \n(2006)). \n22. \nThe Commission has applied that standard to reject a proposed RTO credit provision. In the same \norder it found a revision defining default as occurring upon a missed invoice date, rather than at \nthe end of the cure period, “may be so stringent as to unnecessarily inhibit access to the \nmarketplace,” and rejected it. Id. at P 21. The Commission did so notwithstanding that the \nprovision had emerged from the RTO’s stakeholder process, holding that “the Commission cannot \naccept any proposal from the stakeholder process that is unduly burdensome or unduly \ndiscriminatory.” Id. The Commission credited the concern that a single default could trigger cross-\ndefault provisions in customers’ other agreements, and placed on the RTO the burden of showing \nthat such provisions could be avoided. Id. and n.23. \n23. \nThe same standard appears in PFMI Principle 18, which requires “objective, risk-based, and \npublicly disclosed criteria for participation, which permit fair and open access.” \n24. \nA participant must also be able to determine what the requirement will cost it. PFMI Principle 23 \nrequires that an infrastructure “provide sufficient information to enable participants to have an \naccurate understanding of the risks, fees, and other material costs they incur by participating,” and \nthat “all relevant rules and key procedures should be publicly disclosed.” \n25. \nCommercial practice outside the organized markets follows the same architecture — rating-based \nunsecured thresholds, variation margin recalculated as exposure moves, negotiable forms of \nsupport, and termination payments measured by replacement cost rather than remaining notional. \n26. \nWhere a central counterparty intermediates, an uncovered default mutualizes to the membership, \nand the defaulting participant’s own margin absorbs the loss first. PFMI ¶¶ 1.13, 3.4.24. \nPJMSettlement occupies that position in the PJM markets, and Attachment Q, Section I states the \npurpose accordingly: PJM “must have the authority to monitor and manage credit risk on an \nongoing basis, and to act promptly to mitigate or reduce any unsecured credit risk, in order to \nprotect the PJM Markets and PJM Members from losses.” \nIV.  PARTIES AND EXPOSURES UNDER THE RBP \n27. \nThis section identifies who bears what under the RBP. That question is prior to any judgment \nabout whether the credit requirement is correctly sized, because collateral secures a party against a \nloss, and one cannot evaluate the amount without first knowing whose loss it is and who is \nprotected from it. A commercial arrangement of this kind involves four distinct roles: the party \nthat posts collateral, the party that pays, the party that receives the benefit, and the party that"},{"page":77,"startToken":27145,"endToken":27731,"text":"6 \n \nabsorbs a default. In an ordinary bilateral contract these align. Under the proposed provisions they \ndo not. I set out the structure here and address its consequences in the opinions that follow. \nA.  Parties with obligations \n28. \nRBP Sellers submit Sell Offers, receive commitments for a fixed fifteen-year term, and post \ncollateral under section 18.8(a) equal to 20% of the offer price times committed UCAP MW times \n365 days, for the first three Delivery Years. \n29. \nA seller that fails to achieve commercial operation is subject to RBP shortfall charges under \nsection 18.6(d), assessed daily on the full committed UCAP at a rate of 20% of the commitment \nprice, for up to three years. A resource delayed solely by Network Upgrades is excepted if it \ndemonstrates readiness through test energy and seeks interim deliverability. \n30. \nUnder section 18.6(e), if committed MW fail to come online for three Delivery Years the \ncommitment is rescinded for the remainder of the fifteen-year term. The resource is then neither \ncompensated nor subject to further shortfall charges. Seller exposure is therefore bounded at three \nyears of shortfall charges, and the seller’s collateral is sized to that same quantity. That \nadministrative cap on the seller’s assessed liability is distinct from the economic replacement \nexposure experienced by load when the capacity does not arrive, which I address at paragraphs 90 \nto 95. \n31. \nLoad Serving Entities allocated RBP Charges pay the contract-for-differences settlement for the \nfull fifteen-year term and post collateral under section 18.8(b) at $1.5 million per RBP UCAP \nMW. Only LSEs in zones with a non-zero Load Adjustment are allocated RBP Charges. \n32. \nPJMSettlement is counterparty to the transactions. \nB.  Parties without obligations \n33. \nElectric Distributors determine the allocation of RBP Obligation MW among LSEs within their \nzone or area. Proposed Reliability Assurance Agreement, section 7.2C. They incur no payment \nobligation and post no collateral. \nC.  The residual tier \n34. \nUnder Operating Agreement section 15.2.2, where a Member defaults on its payment obligations \nthe other PJM Members may be required to pay a share of the defaulted amounts. That exposure \nextends to Members with no Load Adjustment and no RBP Charge allocation. \nD.  How a default travels \n35. \nOn an LSE default, section 18.9(a) provides that the defaulted RBP Charge “will be allocated to \nall remaining Load Serving Entities responsible for paying RBP Charges based on their pro-rata \nshare,” and that such amounts “may be offset by the RBP Collateral posted by the defaulting Load \nServing Entity.” Reallocation is mandatory; application of the defaulter’s collateral is permissive. \n36. \nOn a seller default, section 18.9(b) provides that where an RBP Resource defaults on payment of \nshortfall charges, “the corresponding credits will not be allocated to the Load Serving Entities that \nwould otherwise receive the RBP shortfall credits.” Load bears the loss directly. \n37. \nThe two provisions are asymmetric in effect. A load default is recovered from other load. A seller \ndefault leaves load uncompensated, and after rescission under section 18.6(e) load receives \nnothing for the remaining twelve years of a fifteen-year commitment. \n38. \nUnder section 18.6(f), a commitment follows the resource on a change of ownership and continues \nthrough the end of the fixed term. The identity and financial condition of the party performing the \ncommitment may therefore change during the term while the commitment itself does not. I address \nthe treatment of seller credit over the term in Section VII."},{"page":78,"startToken":27731,"endToken":28466,"text":"7 \n \nE.  Which party is harmed by which failure \n39. \nThe RBP has three distinct failure modes, and they harm different parties at different times. The \nfirst is a failure by a Load Serving Entity to post the required collateral on the stated date, which is \na liquidity event occurring forty-five days before the Delivery Year begins. The second is a failure \nby a Load Serving Entity to pay an RBP Charge, which is a credit event arising during the \nDelivery Year. The third is non-delivery by an RBP Seller, which is a physical event. The first two \nare both financial but are not the same: they are triggered by different conditions, arise on different \ndates, and are secured differently. Collateral secures the second. It does not secure the first, \nbecause the first is a failure to provide the collateral itself. Collateral is ordinarily sized to the loss \nit prevents, so these distinctions are prior to any judgment about the amount of either requirement. \n40. \nA payment failure by an LSE does not affect whether capacity is delivered. The committed \nresource remains committed and the procurement proceeds. What occurs is a reallocation. Under \nsection 18.9(a) the defaulted RBP Charge is allocated among the remaining Load Serving Entities \nresponsible for paying RBP Charges; because RBP Charges are assessed against every zone/area \nholding a share of the RBP Target, that population is footprint-wide rather than confined to the \nzone in which the default occurred. Under Operating Agreement section 15.2.2 any residual \nreaches the wider membership. The parties harmed are therefore other load. Within a zone/area, \nthe Electric Distributor assigns RBP Obligation MW in the first instance to the Load Serving \nEntities serving the Large Loads whose forecast growth generated the Load Adjustment; where it \ndoes not, section 18.8(b)(i)(B)(2) reaches load on Peak Load Contribution, which is native load. \nThe Large Loads are not themselves parties to the RBP and bear no share of the reallocation under \nsection 18.9(a). \n41. \nNon-delivery by an RBP Seller has the opposite incidence. The capacity for which the \nprocurement was conducted does not arrive, and the reliability the RBP was designed to secure is \nnot obtained. That harm falls on the loads the procurement was designed to serve. PJM has \ndescribed a framework under which RBP supply matched to specific Large Loads would be \ncredited as a Bring Your Own Capacity showing for Interim Resource Adequacy Service \npurposes, but the filed provisions establish no mechanism by which an RBP commitment is \nmatched to a particular Large Load or Load Serving Entity, and I express no view on how such a \ncredit would be determined. The harm falls on load generally, both through the resource adequacy \nshortfall and financially: under section 18.9(b) load does not receive the shortfall credits, and after \nrescission under section 18.6(e) load receives nothing for the remaining twelve years of a fifteen-\nyear commitment. \n42. \nNeither the tariff nor the filing quantifies the second of those harms. Shortfall charges under \nsection 18.6(d) are assessed for up to three years at a rate fixed by reference to the commitment \nprice; they are not a measure of the cost of replacing the capacity that did not arrive. PJM \nidentified the same gap in its own analysis, stating that a default in year three of a fifteen-year \ncontract leaves twelve years of capital cost uncovered, and that the current tariff does not calculate \nliquidated damages. I address the consequences of that gap in Sections VII and IX. \nF.  Application to EKPC \n43. \nPJM’s illustrative allocation shows EKPC with a Load Adjustment of zero and no allocation of the \nRBP Target. EKPC would therefore not be allocated RBP Charges on those figures, and would not \npost RBP Collateral. EKPC nonetheless remains within the residual tier under Operating \nAgreement section 15.2.2. EKPC is the Load Serving Entity for its member-owner distribution \ncooperatives, and an obligation allocated to those cooperatives’ load would be borne by EKPC. \nThe quantity that sets each Load Serving Entity’s collateral requirement is submitted by its \nElectric Distributor. That entity incurs no payment obligation, posts no collateral, and need not \nitself be a PJM Member. The party that determines the size of the requirement is therefore not the \nparty subject to it, and PJM’s credit provisions reach only the latter."},{"page":79,"startToken":28466,"endToken":29053,"text":"8 \n \nV.  THE PROPOSED CREDIT CONSTRUCT \n44. \nThis section describes the proposed provisions without evaluating them. I quote the operative \nlanguage, and PJM’s own stated derivation of the figures, because the questions posed to me turn \non what the tariff says and on how PJM arrived at the amounts rather than on how they have been \ncharacterized. \nA.  Seller collateral \n45. \nSection 18.8(a) requires each RBP Resource seeking to submit a Sell Offer to post collateral equal \nto the sum, over the first three Delivery Years, of 20% of the RBP Sell Offer price times the \noffered UCAP MW times 365. Collateral is posted at or before bid submission, in cash or letter of \ncredit. It is returned within five business days for offers that do not clear, and for committed \nresources only after the resource achieves commercial operation and a subsequent one-year look-\nback. \nB.  The cumulative buyer requirement \n46. \nSection 18.8(b)(i)(A) provides that “the cumulative RBP credit requirement for Load Serving \nEntities for a given Delivery Year shall be equivalent to the product of the RBP Credit Rate \nmultiplied by RBP UCAP MW committed.” \n47. \nThe RBP Credit Rate “shall equal $1.5 million, as may be reduced, for reasons including a change \nin the total committed RBP UCAP MW, when total posted RBP Collateral is greater than the total \nremaining RBP Charges obligations, over time by the Office of the Interconnection to an amount \nsufficient to cover the total existing RBP Charges obligations.” \n48. \nThe quantity to which the rate applies is “the amount of RBP UCAP MW that receives a \ncommitment through the Reliability Backstop Procurement minus each commitment of RBP \nUCAP MW that is rescinded pursuant to Tariff, Attachment DD, section 18.6(e).” Rescission is \nthe only stated reduction. Commercial operation dates are permitted through June 1, 2032. \nC.  The individual LSE posting \n49. \nSection 18.8(b)(i)(B)(1) requires each LSE with an RBP Obligation, “prior to forty-five (45) days \nbefore the start of the Delivery Year,” to “post, or maintain an existing, RBP Collateral equal to \n$1.5 million x the allocated RBP Obligation MW.” The obligation recurs in advance of each \nDelivery Year of the fifteen-year term. \n50. \nThe allocated RBP Obligation MW is the quantity “submitted for the Load Serving Entity by the \nElectric Distributor and scaled, as necessary, in the event that the RBP Obligation MW values \nuploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW for the \nzone/area.” \n51. \nWhere no RBP Obligations are reported by the Electric Distributor in a zone in which the LSE \nserves load, section 18.8(b)(i)(B)(2) provides that the LSE “may be required to post” collateral \nbased on “the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for \nthe zone/area as determined in RAA, Schedule 8.” \n52. \nUnder both subsections, PJM “may evaluate such Load Serving Entity for unreasonable credit risk \nunder the Unreasonable Credit Risk provisions of Tariff, Attachment Q, Section II, and require \nadditional RBP Collateral as appropriate.” \nD.  Acceptable forms \n53. \nRBP Collateral is defined as “either (1) a cash deposit, including any interest thereon, or (2) a \nletter of credit issued for the benefit of PJM or PJMSettlement, in an amount and form determined \nby and acceptable to PJM or PJMSettlement as credit support.” Surety bonds, which PJM accepts \nelsewhere subject to per-issuer limits, are not included. No unsecured credit allowance is provided."},{"page":80,"startToken":29053,"endToken":29614,"text":"9 \n \nE.  PJM’s stated derivation \n54. \nPJM states that it is proposing to address RBP credit “through rules outside of its Credit Risk \nManagement Policy,” and that the LSE requirement is intended to mitigate potential defaults from \nnon-payment of RBP Charges. PJM states that its “current credit tools do not contemplate the \nlong-term nature of RBP and the risk of future non-payment that results.” PJM Interconnection, \nL.L.C., “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming \nfrom New Load Adjustments” Docket No. ER26-3380-000 (filed July 31, 2026) (“PJM RBP \nFiling”), Attachment D, Affidavit of Gwen Kelly, ¶ 19 (“Kelly Aff.”). \n55. \nFor sellers, PJM states the requirement formulaically as the sum over the first three Delivery Years \nof 0.2 × RBP Sell Offer Price × UCAP MW × 365. Kelly illustrates with a 100 MW commitment \nat $555/MW-day: a shortfall charge of $4,051,500 in each of the 2028/2029, 2029/2030 and \n2030/2031 Delivery Years, and a credit requirement of $12,154,500. Kelly Aff. ¶ 18. \n56. \nFor load, PJM states that it sought “collateral that provides commensurate protection against non-\npayment while avoiding full collateralization of the entire 15-year contractual commitment.” Kelly \nAff. ¶ 24. \n57. \nPJM derived the $1.5 million figure from the gross contractual value of the commitment. It \n“estimated the contractual value associated with a 1-MW RBP commitment using conservative \nassumptions, including a 15-year commitment term application of the RBP price throughout that \ncommitment period,” yielding “approximately $3.04 million, assuming the RBP clearing price at \nthe price cap of $555/MW.” It then “concluded that an initial credit rate of $1.5 million per \ncommitted RBP MW would collateralize approximately 50% of the estimated contractual value \nassociated with the commitment.” Kelly Aff. ¶¶ 25–26. \n58. \nPJM separately checked that figure by discounted cash flow. Taking a 1-MW fifteen-year \ncommitment at $555/MW-day, each year’s payment is $202,575, discounted to September 2026 at \n9.5%: $172,841 for 2028/2029, $157,850 for 2029/2030, through $48,514 for 2042/2043. “All the \nNPV added together is $1,481,569.” Kelly Aff. ¶ 27. \n59. \nPJM states that the 9.5% discount rate “is the capacity market Weighted Average Cost of Capital \ndeveloped by The Brattle Group as part of PJM’s 2025 periodic review of the Cost of New Entry \nof Capacity Resources into the PJM Region,” and that “Given Brattle’s thorough analysis in \narriving at 9.5%, it represents a well-supported discount rate.” Kelly Aff. ¶ 28. \n60. \nPJM illustrates the resulting requirement for a 100 MW allocation as $1,500,000 × 100 MW = \n$150,000,000. Kelly Aff. ¶ 33. \nPART TWO — THE CREDIT REQUIREMENT  \nVI.  OPINION 1 — The magnitude has no precedent in PJM \n61. \nThis opinion addresses magnitude. The Commission’s standard has two sides: an RTO must \nminimize the risk that a default is socialized among non-defaulting participants, while “ensuring \nthat the credit or collateral requirements are not so stringent that they unnecessarily inhibit access \nto the marketplace.” Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at P 19 (2009). Magnitude is the \nmeasure of the second. In what follows I compare the proposed requirement to the collateral PJM \nactually holds, to the relationship PJM maintains between collateral and market activity, and to the \nannual charge the requirement secures. On each comparison the proposed requirement stands apart \nfrom anything in PJM’s experience."},{"page":81,"startToken":29614,"endToken":30348,"text":"10 \n \n62. \nAt the Initial RBP Target of 6,831.3 UCAP MW, the LSE collateral requirement is approximately \n$10.2 billion. On the illustrative Final RBP Target of 6,075.7 MW it is approximately $9.1 billion. \nPJM’s own illustration of a 100 MW allocation is $150,000,000. Kelly Aff. ¶ 33. \n63. \nPJM’s monthly Key Risk Metrics reporting shows the total collateral PJM holds from all \nMembers, against every market it operates, at approximately $6.2 billion on average in 2024 and \n$7.0 billion in 2025. Collateral rose materially in 2026 as measured exposure rose — PJM reports \nthat three of the highest billing weeks in its history occurred that year — reaching approximately \n$13.1 billion in February 2026, the highest balance PJM has ever held, and standing at \napproximately $10.9 billion on July 30, 2026. \n64. \nThe proposed requirement for a single procurement of 6,831.3 UCAP MW is therefore \napproximately 78% of the largest collateral balance PJM has ever held, and approximately 96% of \nthe average balance held during 2026 to date. Against the 2024 and 2025 averages it is 165% and \n146% respectively. \n65. \nMethodology. The series is constructed from PJM’s monthly Key Risk Metrics reporting to the \nRisk Management Committee. Figures are stated as approximate and rounded to the nearest $0.1 \nbillion. I present them as approximate deliberately. At this magnitude the precision of any single \nmonth is not material to the conclusion, which rests on the ratio between the collateral PJM holds \nand the market activity that collateral secures. Attachment A. \n66. \nThe relationship PJM maintains between collateral and market activity is stable. Measured against \nsettlements processed, collateral ran approximately 12% in 2024 and 9% in 2025. Measured \nagainst the Independent Market Monitor’s total cost of wholesale power, it ran approximately 11% \nin calendar 2025 and 13% over the twelve months ended June 2026. Two differently constructed \nmeasures place PJM’s collateral coverage in a band of roughly 9% to 13% of annual market \nactivity. I use that band below. \n67. \nThe requirement is secured at a multiple of the value it secures. At the $555 maximum willingness \nto pay and the Initial RBP Target of 6,831.3 UCAP MW, the maximum gross annual commitment \nvalue — before any offset for RPM revenues — is approximately $1.38 billion, against a collateral \nrequirement of approximately $10.2 billion. The collateral is therefore approximately 740% of one \nyear's gross commitment value. That gross figure is not, however, the amount billed to load. As set \nout in Section VII.B, the RBP settles as a contract for differences, and at the 2028/2029 Base \nResidual Auction clearing price of $325.00/MW-day the amount billed in the first Delivery Year is \napproximately $573 million. Measured against that amount, the collateral requirement is \napproximately 1,790%. The comparison to PJM's existing markets should be made on a consistent \nbasis: the band of roughly 9% to 13% set out above measures collateral against amounts actually \nsettled and billed, and measured the same way the RBP requirement is on the order of 140 to 200 \ntimes the collateral intensity PJM applies to the markets it operates today. Measured instead \nagainst the gross annual commitment value — a basis more favorable to PJM, because it credits \nthe requirement with securing a stream that is never billed — the multiple is on the order of fifty-\nfive to eighty-five times. I use the latter figure below. The comparison is not one of scale alone. \nThe collateral PJM holds today secures every market it operates and every class of participant in \nthem — energy, capacity, transmission and financial transmission rights, across sellers, buyers and \ntraders alike. The proposed RBP requirement secures one product, owed by one class of \nparticipant, posted on one date. A requirement approaching in magnitude the entire collateral \nbalance PJM has ever held across all of its markets, raised from a subset of the participants in one \nof them, is a different kind of obligation and not merely a larger one. \n68. \nThe aggregate requirement resolves into zonal allocations of substantial size. On PJM’s illustrative \nfigures, the initial allocation produces LSE collateral of approximately $2.29 billion for \nAEPOHIO, $1.95 billion for NVEC, $1.33 billion for COMED, $1.23 billion for PPL and $1.11 \nbillion for DOM. Attachment B sets out the calculation for each Electric Distributor zone and area."},{"page":82,"startToken":30348,"endToken":31057,"text":"11 \n \n69. \nThe Commission has rejected a proposed RTO credit provision on the ground that it “may be so \nstringent as to unnecessarily inhibit access to the marketplace.” Sw. Power Pool, Inc., 126 FERC ¶ \n61,153, at at P 21 (2009).  The provision rejected there imposed no monetary requirement at all; it \nchanged only the moment at which a payment default was deemed to occur, from the end of the \ncure period to the invoice due date. \n70. \nThe proposed requirement is materially larger than PJM’s historical collateral requirements. It has \nno precedent in PJM in magnitude, and the filing identifies no organized market in which a \ncomparable requirement has been imposed on load. The aggregate figure also understates the \nburden on particular entities, because the requirement is allocated by zone and falls without regard \nto the balance sheet of the LSE obligated to post. I address that below. \nVII.  WHETHER THE REQUIREMENT SECURES A MEASURED EXPOSURE \n71. \nThis section evaluates whether the proposed collateral secures a measured risk position, and \nwhether the amount is sufficient or deficient under plausible future price outcomes. The standards \nset out in Section III require that collateral be sized to replacement cost, which is a function of the \nprice at which the position would be replaced and the period over which the exposure is held; that \nthe requirement be recalculated as exposure moves and released as it declines; and that a \nparticipant be able to determine what the requirement will cost it. I apply those elements here. \nA.  The requirement is absent during the period of greatest uncertainty \n72. \nCommitments bind when results are posted on December 2, 2026. Buyer collateral is not due until \nforty-five days before the start of the 2028/2029 Delivery Year, approximately April 17, 2028. For \nroughly seventeen months no LSE collateral secures the obligation. The obligation is not merely \nfixed during that period; its first year is already measurable. The 2028/2029 Base Residual \nAuction cleared in July 2026 at $325.00/MW-day, so at the moment the RBP commitment binds \nthe first Delivery Year’s contract-for-differences exposure is known at $230/MW-day, or $83,950 \nper MW-year. Nor does the position remain single-year for long. The 2029/2030 Base Residual \nAuction results post on December 22, 2026, twenty days after RBP commitments bind, so within \nthree weeks two Delivery Years are priced; by the April 2028 posting date they will have been \nknown for approximately sixteen months. PJM requires no collateral against a quantified exposure \nfor seventeen months, and the requirement it does impose is fixed without reference to prices that \nbecome observable almost immediately. \n73. \nThat interval is when the identity of the obligated party is least certain. RBP Obligation MW are \nreported to PJM by the Electric Distributor. If a large load fails to materialize, or fails to contract \nwith a Load Serving Entity, the load on which the obligation was premised does not appear. \n74. \nThe tariff allocates that shortfall in two tiers. Under section 18.8(b)(i)(B)(1), RBP Obligation MW \nreported by the Electric Distributor are “scaled, as necessary, in the event that the RBP Obligation \nMW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW \nfor the zone/area.” Because the zonal target is fixed, an obligation that is not reported for one LSE \nis scaled onto the LSEs that are reported — in the first instance, the LSEs serving the other large \nloads in that zone. Under section 18.8(b)(i)(B)(2), where no RBP Obligations are reported at all, \nthe requirement is determined by “the Load Serving Entity’s pro-rata share of the Daily Unforced \nCapacity Obligation for the zone/area,” which allocates by total capacity obligation and therefore \nreaches native load. \n75. \nPJM’s proposal does not address this period of risk. The exposure of a large load and its LSE that \nfail to materialize does not disappear; it is scaled onto the remaining large-load LSEs in the zone, \nand where none remain, onto native load. Those parties bear both the reassigned collateral \nrequirement and, under section 18.9(a), the reallocated RBP Charges, “based on their pro-rata \nshare of the total RBP Charges for all such Load Serving Entities.”"},{"page":83,"startToken":31057,"endToken":31757,"text":"12 \n \nB.  The requirement is not measured against the contract it secures \n76. \nThe RBP settles as a contract for differences. Under section 18.5(g)(ii), an RBP Resource offers \ninto RPM as a price taker, clears, and receives the RPM clearing price. The RBP Charge pays the \nresource the difference between that RPM clearing price and its RBP commitment price, so that \nthe resource receives its commitment price in total. The amount billed to load is therefore the \ndifference between the RBP price and the RPM clearing price. The gross RBP price is never \nbilled. \n77. \nPJM nonetheless derived the Credit Rate from the gross price. It “estimated the contractual value \nassociated with a 1-MW RBP commitment using conservative assumptions, including a 15-year \ncommitment term application of the RBP price throughout that commitment period,” arriving at \napproximately $3.04 million, and set the Credit Rate at “approximately 50% of the estimated \ncontractual value.” Kelly Aff. ¶¶ 25–26. Its discounted cash flow check applied the same gross \nfigure — $202,575 per year, discounted at 9.5% to September 2026, summing to $1,481,569. \nKelly Aff. ¶ 27. \n78. \nThe exposure can be measured directly for the one Delivery Year in which the RPM price is \nknown. The 2028/2029 Base Residual Auction cleared at $325.00/MW-day UCAP. At an RBP \nprice of $555 — the figure PJM itself assumes — the differential is $230/MW-day, or $83,950 per \nMW-year. Were that price to persist for fifteen years, the total exposure would be $1,259,250 per \nMW, already below the $1.5 million Credit Rate. \n79. \nThe following comparison is deliberately undiscounted: it equates the Credit Rate to the nominal \nsum of future differentials, without crediting the time value of exposures arising up to fifteen years \nforward. Future RPM prices are not known, and the filing contains no forecast of them. The \nstandards require that potential future exposure be estimated. PJM has performed such an estimate. \nAs set out in Section XIII, it modeled the procurement as a fixed-for-float swap and estimated \npotential future exposure at a 95 percent confidence level across the fifteen-year term, obtaining a \nprofile that rises, reaches a maximum, and declines to zero at expiry. That estimate does not \nappear in the filing, and the Credit Rate does not reflect it. The filing itself neither produces a \nforward price path nor marks the most recent clearing price forward as an estimate of the \nremaining term, as PJM does for FTR portfolios under the Mark-to-Auction methodology in \nAttachment Q. \n80. \nFor the $1.5 million Credit Rate to correspond to the actual exposure, RPM would have to clear at \napproximately $277.89/MW-day or below in each of the fourteen Delivery Years after 2028/2029, \ngiven that year’s known clearing price of $325.00. On a flat assumption across all fifteen years, \nthe required price is $281.03. Both are below the price already realized. \n81. \nThe filing identifies no basis for expecting prices at that level. Other statements in the filing \ncontemplate continuing capacity shortfalls. PJM states that the 2029/2030 auction may clear short \nnotwithstanding the RBP. It also proposes at section 16.2 to reinstate the existing Tariff provisions \nestablishing a Reliability Backstop Auction — a mechanism distinct from the RBP proposed here \n— beginning with the 2032/2033 Delivery Year, so that from that point forward a clearing \nshortfall against the Reliability Requirement in three consecutive Delivery Years would again \ninitiate a backstop procurement. In the interim PJM proposes to suspend the trigger on the ground \nthat further shortfall reports would be “substantively repetitive.” PJM therefore contemplates that \nshortfalls could continue, and provides for the existing backstop mechanism to resume once the \nRBP commitments are in place. The administrative price collar is a feature of the RPM capacity \nmarket rather than of the RBP, and it applies through the 2029/2030 Base Residual Auction only. \nBecause the RBP Charge is the difference between the RBP price and the RPM clearing price, the \ncollar constrains that difference while it is in force. For the remaining thirteen Delivery Years of \nthe RBP term the RPM price is uncollared, and the differential is not bounded by it."},{"page":84,"startToken":31757,"endToken":32438,"text":"13 \n \n82. \nPJM’s own analysis indicates where uncollared prices would settle. PJM simulated that, absent the \nprice cap, the 2028/2029 auction would have cleared at $554.72/MW-day RTO-wide, and at \n$776.69 in the ComEd Locational Deliverability Area. PJM Interconnection, L.L.C., 2028/2029 \nBase Residual Auction Report at 17 (July 14, 2026) (Appendix, BRA Clearing Simulation Without \nCap and Floor). The RBP maximum willingness to pay is $555.00. \n83. \nIf prices approach that level once the collar lapses, the contract-for-differences exposure \napproaches zero. At $554.72 the differential is $0.28/MW-day and the fifteen-year exposure is \n$1,533 per MW, against $1.5 million of posted collateral. On a blended path — the 2028/2029 \nDelivery Year at its known clearing price of $325.00, the 2029/2030 Delivery Year at the $333.44 \ncollar proxy used elsewhere in this affidavit, and the remaining thirteen at $554.72 — the exposure \nis approximately $166,000 per MW, and the collateral would exceed it roughly nine times over. \nAttachment E. \n84. \nWhere the RPM price exceeds the RBP commitment price, the contract for differences reverses \nand the resource owes the difference to load. The collateral then secures no exposure at all. \n85. \nThe characterization of the Credit Rate as approximately half of contractual value depends on \nwhether contractual value is stated on a nominal or a present-value basis. PJM derives $1.5 million \nper MW as approximately fifty percent of a gross fifteen-year contractual value of approximately \n$3.04 million per MW, that being the nominal sum of fifteen annual payments of $202,575. But \nPJM also discounts that same stream at its own 9.5% after-tax weighted average cost of capital, \nobtaining a present value of approximately $1.48 million per MW. The two measures are of course \nmathematically consistent with one another, being the nominal and present-value expressions of \nthe same stream. The point is which one the Credit Rate is measured against. Against nominal \nvalue the Credit Rate is approximately fifty percent, as PJM describes it at Kelly Aff. ¶¶ 24 and \n26. Against PJM’s own discounted value of the same stream it is approximately 101 percent — \nfull collateralization of the entire fifteen-year gross obligation. \n86. \nThat comparison uses PJM’s own measure of the obligation, the gross contractual value. As set out \nabove, the amount actually billed to load is the contract-for-differences differential rather than the \ngross stream. Measured against that differential, the requirement is larger still. The Credit Rate \ntherefore represents full collateralization of a stream that is never billed, and a multiple of the \nexposure that is billed. \nC.  The requirement departs from every methodology PJM applies elsewhere \n87. \nThe proposed LSE requirement does not use the exposure-measurement and recalculation features \ndescribed in Section III. It is not sized to a replacement cost, because PJM measures the gross \ncontractual value rather than the contract-for-differences exposure. It applies no close-out period. \nIt is not recalculated as exposure moves, and it is released only at PJM’s discretion. It provides no \nunsecured credit allowance and accepts only two forms of collateral. \n88. \nIt also departs from each methodology PJM applies in its existing markets. For general market \nactivity, PJM sizes the requirement to Peak Market Activity computed from a participant’s own \nobserved billings. For forward price exposure in FTRs, PJM applies a historical simulation value-\nat-risk model at a 99% confidence interval, adjusted by Mark-to-Auction value and recalculated no \nless frequently than after each annual auction. For planned generation in RPM, PJM sizes the \nrequirement to Net Cost of New Entry subject to a floor and releases it across five defined \nconstruction milestones. The RBP uses none of these. The filing offers no explanation for the \ndeparture beyond the observation that its “current credit tools do not contemplate the long-term \nnature of RBP.” Kelly Aff. ¶ 19. \n89. \nPJM’s initial proposal in the stakeholder process would have secured the LSE obligation on a basis \ncomparable to Peak Market Activity, covering approximately three to four weeks of billed \nobligations. PJM, Reliability Backstop Procurement Design, Reliability Backstop CIFP (June 10–"},{"page":85,"startToken":32438,"endToken":33119,"text":"14 \n \n11, 2026) (“Design Presentation”), at slide 35.2 At the RBP price of $555/MW-day, four weeks of \nthe gross obligation is approximately $15,600 per MW; measured against the contract-for-\ndifferences exposure at the 2028/2029 clearing price, it is approximately $6,500 per MW. The \nfiled Credit Rate of $1.5 million is between ninety-six and two hundred thirty-two times those \nfigures. The Joint EDC and Data Center Coalition proposal contemplated that a credit obligation \nwould attach when the LSE subscribed MW into the procurement, although the timing of \ncollection was not specified. No proposal advanced during the stakeholder process, including \nPJM’s own, established a collateral requirement of the magnitude filed for the interval between \ncommitment and the first Delivery Year. \nD.  The seller requirement is deficient by the same standard \n90. \nThe seller requirement is derived from an administrative penalty rate — 20% of the offer price, the \nsame rate as the shortfall charge under section 18.6(d) — rather than from the cost to load of \nreplacing capacity that does not arrive. In an ordinary commercial arrangement the non-\nperforming supplier makes the buyer whole for the prudently incurred cost of replacement. Here \nthe replacement cost is the contract-for-differences differential. \n91. \nThe analysis that follows adopts PJM’s own assumption that the RBP clears at the price cap of \n$555/MW-day. Kelly Aff. ¶¶ 18, 25, 27. \n92. \nFor the 2028/2029 Delivery Year the differential is known: the Base Residual Auction cleared at \n$325.00/MW-day, and the exposure is $83,950 per MW. For 2029/2030, whose auction had not \nbeen held when this filing was made, I use as a proxy the 2027/2028 Base Residual Auction \nclearing price of $333.44/MW-day, giving $80,869 per MW. The two-year total is $164,819. PJM \nhas not published the ELCC of the reference resource so the effective cap is not known. I selected \nthe 2027/2028 auction as a proxy on the following grounds. First, the accreditation basis is the \nclosest match available for a CT technology. Second, both Delivery Years are subject to the same \nprice collar. Third, both are expected to clear short of the Reliability Requirement. The proxy is \ntherefore an observed collared outcome under comparable accreditation and comparable supply \nconditions, rather than a forecast. Lastly, it is conservative in the direction that matters here. The \n2029/2030 class rating is below the rating underlying the 2027/2028 auction, and a lower \naccredited rating corresponds to a higher cap expressed per megawatt of unforced capacity. If the \n2029/2030 auction clears above $333.44/MW-day, the differential between the RBP price and the \nRPM price narrows, the exposure falls, and every ratio in this affidavit that depends on the proxy \nunderstates the disproportion I identify. The 2029/2030 Base Residual Auction results post on \nDecember 22, 2026, and will replace the proxy with an observed price before any collateral is \nposted under section 18.8(b). \n93. \nSeller collateral at that price is $121,545 per MW. It covers 73.7% of those first two Delivery \nYears, and falls $43,274 short before any uncertain year is reached. \n94. \nThe first two Delivery Years therefore exhaust the seller collateral and leave a deficit before any \nuncertain year is reached. For the seller collateral to cover the modeled exposure over the full \nterm, the contract for differences would have to reverse sufficiently during the remaining thirteen \nDelivery Years to offset approximately $43,274 per MW of that first-two-year exposure. That \nrequires an average RPM clearing price of approximately $564.12/MW-day, or $9.12/MW-day \nabove the RBP price, across the 2030/2031 through 2042/2043 Delivery Years. In that \n \n2 Presentation available at: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260611/20260611-item-04a---pjm-reliability-backstop-procurement-design-presentation.pdf. Additional \nrelated materials including PJM’s CFIP Proposal is available here: https://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-rbp/2026/20260611/20260611-item-04a---pjm-reliability-backstop-\nprocurement-paper.pdf. And PJM’s post-meeting materials are available here: https://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-rbp/2026/20260611/20260611-item-04a---pjm-reliability-backstop-\nproposal---post-meeting-materials.pdf"},{"page":86,"startToken":33119,"endToken":33779,"text":"15 \n \ncircumstance the contract for differences reverses and the resource pays load rather than the \nreverse. \n95. \nThe two requirements — the LSE collateral requirement and the seller collateral requirement — \nrest on opposite assumptions about the same variable. On PJM’s own price assumption, the \nseller’s collateral is adequate only if RPM clears at or above approximately $532.80/MW-day on \naverage. The LSE’s collateral corresponds to the exposure only if RPM clears at an average of \napproximately $281.03 or below. The two implied prices differ by $251.77/MW-day. PJM states \nneither assumption, and no single average RPM price can satisfy both conditions. Attachment E. \nE.  Neither requirement is measured against the party that bears it \n96. \nNothing in section 18.8(a) revalues the seller’s collateral for the credit of the entity performing at \nthe time. The requirement is a formula — the greater of $20 or twenty percent of the bid or \nclearing price, multiplied by committed UCAP MW, by 365, by three — keyed to the commitment \nprice fixed at selection. It does not vary with the seller’s rating, tangible net worth or any other \nmeasure of creditworthiness, and it is not recalculated when the resource changes hands. As set out \nat paragraph 38, section 18.6(f) provides that a commitment follows the resource on a change of \nownership, so an entity acquiring a committed resource in a later Delivery Year posts the amount \nfixed at selection, whatever its own financial condition. Attachment Q evaluates creditworthiness \non an ongoing basis and permits PJM to require additional security as a participant’s condition \nchanges; section 18.8(a) contains no equivalent. \n97. \nThe LSE requirement is not measured against the party that bears it either, and it does not account \nfor the collateral that party already provides. An LSE’s existing financial security under \nAttachment Q is determined by its Peak Market Activity, which is derived from its historical \nactivity across the PJM Markets and therefore already reflects its RPM charges. The RBP Charge \nis the difference between the RBP price and the RPM clearing price. When RPM clears high, an \nLSE’s RPM charges rise, its Peak Market Activity rises with them, and the RBP differential falls; \nwhen RPM clears low, the reverse occurs. The two exposures move in opposite directions against \nthe same variable. \n98. \nSection 18.8(b) nonetheless requires the RBP posting in addition to, and without reference to, \nfinancial security already held under Attachment Q. It does not net the two, does not reduce either \nwhen the other rises, and does not extend the unsecured credit allowance that Attachment Q \napplies to Peak Market Activity. An LSE therefore posts the full Credit Rate against an exposure \nthat declines precisely when the collateral supporting its other PJM obligations increases. Part of \nthe same obligation is in consequence collateralized twice. The RBP Charge is secured in advance \nby the Credit Rate, and once the Delivery Year begins and RBP Charges are billed, those same \ncharges enter the LSE’s Peak Market Activity through the ordinary operation of Attachment Q and \nare secured again by the financial security that Peak Market Activity requires. The filing does not \naddress the relationship between the two requirements. \nVIII.  THE QUANTITY OF MW TO WHICH THE CREDIT RATE APPLIES IS \nINDETERMINATE \n99. \nThis section addresses the third question posed to me: whether a Load Serving Entity subject to an \nRBP Charge can determine, from the filed rate, the amount it will be required to post. The Credit \nRate is a price per MW. The amount an LSE must post is therefore the product of that rate and a \nquantity of MW. Section 18.8 specifies three different quantities and does not state which governs \nwhen they diverge. \nA.  The three quantities \n100. \nThe first is committed MW. Section 18.8(b)(i)(A) provides that the cumulative requirement “shall \nbe equivalent to the product of the RBP Credit Rate multiplied by RBP UCAP MW committed,”"},{"page":87,"startToken":33779,"endToken":34455,"text":"16 \n \ndefined as “the amount of RBP UCAP MW that receives a commitment through the Reliability \nBackstop Procurement minus each commitment of RBP UCAP MW that is rescinded pursuant to \nTariff, Attachment DD, section 18.6(e).” \n101. \nThe second is the Final RBP Target. Section 18.8(b)(i)(B)(1) requires each LSE to post “$1.5 \nmillion x the allocated RBP Obligation MW,” where that quantity is “submitted for the Load \nServing Entity by the Electric Distributor and scaled, as necessary, in the event that the RBP \nObligation MW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP \nTarget MW for the zone/area.” \n102. \nThe third is the Daily Unforced Capacity Obligation. Section 18.8(b)(i)(B)(2) provides that where \nno RBP Obligations are reported for a zone, the requirement is based on “the Load Serving \nEntity’s pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined \nin RAA, Schedule 8.” That quantity is a function of the LSE’s peak load contribution and bears no \nrelationship to the RBP commitment. \nB.  Committed MW and the Final RBP Target will not be the same \n103. \nPJM states expressly that the two will diverge, and in both directions. Section 18.5(f) provides that \n“RBP Resources shall not be partially cleared,” and that “[i]n the event that the Reliability \nBackstop Procurement cannot meet the Final RBP Target, the Reliability Backstop Procurement \nshall clear short of the Final RBP Target.” The same section permits PJM to “commit an RBP Sell \nOffer with an offered quantity that exceeds the remaining Final RBP Target to the extent such \nsolution provides greater economic efficiency.” \n104. \nPJM explains the reason: “Because the RBP is procuring new capacity and not simply fungible \nUCAP MW … there exists the possibility that PJM may clear a set of resources with a cumulative \nRBP UCAP MW total that does not exactly match the Final RBP Target.” \n105. \nThe divergence is material. On the illustrative Final RBP Target of 6,075.7 UCAP MW, the \nrequirement scaled to that target is approximately $9.11 billion. Were the procurement to clear \nfive percent short, the requirement computed on committed MW would be approximately $8.66 \nbillion — a difference of approximately $456 million. Were it to clear five percent over, the \ndifference would be the same amount in the opposite direction. Nothing in section 18.8 states \nwhich figure controls. \nC.  Committed MW is not in-service MW \n106. \nThe only reduction to committed MW is rescission under section 18.6(e), which requires that MW \n“fail to come online for three Delivery Years.” Commercial operation dates are permitted as late as \nJune 1, 2032, and RBP Sell Offers may be selected for first Delivery Years through 2032/2033. \nDemand Resources and Distributed Energy Resources may also participate, with their own in-\nservice dates, so the composition of committed MW varies across the term as well as its quantity. \n107. \nA resource committed for a first Delivery Year of 2032/2033 is therefore included in committed \nMW from the 2028/2029 Delivery Year, when it is neither in service nor generating any RBP \nCharge. A resource that fails to appear in 2028/2029 remains in committed MW until rescission \ntakes effect after the 2030/2031 Delivery Year. In the first Delivery Year of the term, the quantity \nto which the Credit Rate applies may bear no relationship to the capacity actually delivering or to \nthe charges actually billed. \nD.  Consequence \n108. \nAn LSE cannot compute the collateral it would be required to post from the tariff. It does not \nknow whether the governing quantity is committed MW, the zonal Final RBP Target, or its share \nof the Daily Unforced Capacity Obligation; it does not know the extent to which committed MW \nwill exceed or fall short of the Final Target until procurement results are posted; and it cannot \ndetermine from any of the three what capacity will actually be in service in the Delivery Year for"},{"page":88,"startToken":34455,"endToken":35105,"text":"17 \n \nwhich it is posting. The standards set out in Section III require that a participant be able to have \n“an accurate understanding of the risks, fees, and other material costs” it incurs. PFMI, Principle \n23. \nIX.  THE REDUCTION OF THE REQUIREMENT OVER THE TERM IS UNDEFINED \n109. \nThis section addresses the release of collateral as exposure declines. The standards set out in \nSection III call for recalculation as exposure moves and release as it declines. For purposes of this \nsection only, I accept PJM’s own measure of the obligation — the gross fifteen-year contractual \nvalue — notwithstanding that, as set out above, the amount actually billed to load is the contract-\nfor-differences differential and not the gross stream. Even on the measure PJM selected, and even \naccepting that the requirement is intended to decline, the filing does not define how or when that \ndecline occurs. \nA.  How PJM releases collateral elsewhere \n110. \nFor collateral generally, release is mandatory and participant-initiated. Attachment Q, Section V \nprovides that Collateral which may no longer be required to be maintained under provisions of the \nAgreements “shall be returned at the request of a Participant, no later than two (2) Business Days \nfollowing determination by PJM within a commercially reasonable period of time that such \nCollateral is not required.” The same section permits a Participant, absent an Event of Default, to \nsubstitute one approved form of Collateral for another of equal value. \n111. \nFor planned generation in the capacity market, release follows a stated schedule. Attachment Q, \nSection VI.B.3 provides that the RPM Auction Credit requirement “shall be reduced periodically, \nafter the Market Participant has provided PJM a written request for each reduction, accompanied \nby documentation sufficient for PJM to verify attainment of required milestones.” The schedule \nspecifies five milestones and the percentage released at each: fifty percent on the effective date of \nan executed interconnection service agreement, fifteen percent at financial close, five percent at \nfull notice to proceed and commencement of construction, five percent on delivery of main power \ngenerating equipment, and twenty-five percent at commencement of interconnection service. Each \nmilestone other than the first and last requires a sworn certification by an independent engineer. \n112. \nThat provision was made effective on March 10, 2026 in Docket No. ER26-980-000, \napproximately five months before the filing in this proceeding. \nB.  How the RBP releases collateral \n113. \nSection 18.8(b)(i)(A) provides that the Credit Rate “shall equal $1.5 million, as may be reduced, \nfor reasons including a change in the total committed RBP UCAP MW, when total posted RBP \nCollateral is greater than the total remaining RBP Charges obligations, over time by the Office of \nthe Interconnection to an amount sufficient to cover the total existing RBP Charges obligations.” \n114. \nThe provision is permissive rather than mandatory; it is exercised by the Office of the \nInterconnection rather than requested by the participant; and it specifies no methodology, no \nschedule, no evidentiary standard, and no time by which a reduction must occur once the stated \ncondition is met. Neither “over time” nor “an amount sufficient” is defined. No mechanism exists \nby which an LSE may request a reduction or contest a determination that none is due. The \ntransmittal supplies none of these. It states that PJM “proposes to reduce this RPM Credit Rate \nvalue to correspond with decreasing risk over time,” and quotes its witness for the proposition that \nthe provision permits reductions “when changes in the underlying RBP commitment portfolio \ndemonstrate that previously required collateral exceeds the remaining expected payment \nexposure.” Transmittal at 117–18; Kelly Aff. ¶ 30. Neither identifies a formula, a schedule, a \ntriggering calculation, or a time by which a reduction must follow the condition being met. \n115. \nPJM has nonetheless represented that the requirement will decline. Its witness states that the \nrequirement “will start at an amount sufficient to mitigate the long-term risk of the RBP"},{"page":89,"startToken":35105,"endToken":35761,"text":"18 \n \ncommitment at the beginning of the commitment term and decrease over time as the term winds \ndown,” and that an LSE’s requirement should “generally only go down over time.” PJM RBP \nFiling at 111, 120; Kelly Aff. ¶¶ 30–31. The tariff does not require it. \nC.  Absent reduction, the requirement exceeds the obligation it secures \n116. \nAt the maximum willingness to pay, the gross obligation is $202,575 per MW-year. The Credit \nRate of $1.5 million equals 7.4 years of that obligation. Measured against the gross remaining \nobligation — again, PJM’s own measure — the posted amount is below the remaining obligation \nfor the first eight Delivery Years and above it thereafter, reaching 106% in the 2036/2037 Delivery \nYear and 740% in the final year of the term. \n117. \nThat is the most favorable measure available to PJM. Measured against the amount actually billed, \nthe crossover occurs earlier and the terminal ratio is higher. The deficiency identified in this \nsection does not depend on which measure is correct. \n118. \nThe estimation of potential future exposure is the method the standards set out in Section III \nprescribe for a long-dated obligation of this kind, and it is the method PJM applied to this \nconstruct. As set out in Section XIII, PJM modeled the procurement as a fixed-for-float swap and \nestimated potential future exposure across the fifteen-year term — the same measure it applies to \nFTR portfolios under Attachment Q, and the measure the standards identify. PJM Interconnection, \nL.L.C., Credit & Securitization Overview, Reliability Backstop Procurement Workshop, at slide \n12 (Mar. 4, 2026) (“March 4 Credit Overview”).3 That estimate begins at zero, rises through the \nearly Delivery Years, reaches a maximum within roughly the first third of the term, and declines to \nzero at expiry. PJM stated the reason: value uncertainty increases with tenor, while quantity \nexposure decreases as Delivery Years elapse. \n119. \nThat shape is consistent with what is presently observable. The RBP Charge is a differential \nbetween the RBP price and the RPM clearing price, and for the first two Delivery Years that \ndifferential is measurable rather than forecast. The 2028/2029 Base Residual Auction cleared at \n$325.00/MW-day, producing a differential of $230.00/MW-day, or $83,950 per MW-year. The \n2029/2030 Delivery Year is subject to the price collar, and at the applicable proxy of \n$333.44/MW-day the differential is $221.56/MW-day, or $80,869 per MW-year. Exposure in the \nnear term is therefore both small and measurable. It is in the later Delivery Years, for which no \nprice is observable, that the range of outcomes widens, and it is in those same years that the \nquantity remaining to be settled contracts. \n120. \nA requirement that does not vary cannot track an exposure that does. The Credit Rate stands at its \nmaximum in the first Delivery Year, when the exposure is approximately $83,950 per MW and is \nmeasurable rather than estimated — a ratio of approximately eighteen to one. Across the first two \nDelivery Years, cumulative exposure is approximately $164,800 per MW against a posting of $1.5 \nmillion per MW, a ratio of approximately nine to one. Both of those years will be priced before \nany collateral is posted: the 2029/2030 Base Residual Auction results post on December 22, 2026, \nand the requirement takes no account of them. The Credit Rate stands at its maximum again in the \nfinal Delivery Year, when a single year of settlement remains. PJM itself applied that \nmethodology to the RBP during the stakeholder process. March 4 Credit Overview at slide 12. It \nwas applied to this construct, it produced an exposure profile that varies across the term and \namortizes to zero, and section 18.8(b) does not reflect it. The filing does not address the \ndifference. \n \n3 Presentation available at: https://www.pjm.com/-/media/DotCom/committees-\ngroups/workshops/rbpw/2026/20260304/20260304-item-03---credit-and-securitization-overview---pjm-\npresentation.pdf"},{"page":90,"startToken":35761,"endToken":36405,"text":"19 \n \nD.  Consequence \n121. \nAn LSE cannot determine its posting for any Delivery Year after the first. PJM adopted a \nmandatory, participant-initiated, milestone-based release mechanism for sellers in the capacity \nmarket five months before this filing, and a mandatory two-business-day return obligation for \ncollateral generally. It proposed neither for load in the RBP. Having selected the gross contractual \nvalue as the measure of the obligation, PJM did not then specify the mechanism by which the \nrequirement tracks that value as it declines. \nX.  THE COST OF CARRYING THE REQUIREMENT IS MATERIAL AND IS NOT \nRECOVERED \n122. \nThis section addresses the cost to a Load Serving Entity of holding the required collateral. That \ncost is not a charge under the tariff and appears in no figure PJM has presented. It is nonetheless a \nreal cost, it is borne by load, and it is a direct consequence of the amount and form of collateral \nPJM has proposed. \n123. \nThe analysis in this section rests on an assumption that I state expressly. It assumes that the Load \nServing Entity is able to fund the required amount — from balance sheet cash, from committed \ncredit capacity, or by incurring debt — and it measures only the cost of doing so. It does not \naddress whether an entity of a given size can obtain funding of the required magnitude at all, and it \ndoes not attempt to quantify the effect on an entity’s credit standing of assuming an obligation of \nthis size. Those questions are distinct from the carrying cost and I address them separately in \nSection XI, where I examine the financial capacity of one investment-grade Load Serving Entity \nagainst the allocation PJM’s illustrative figures would assign to it. The figures in this section are \ntherefore a lower bound: they represent the cost to an entity for which funding is available on the \nterms assumed. \nA.  Only two forms of collateral are permitted \n124. \nRBP Collateral is defined as “either (1) a cash deposit, including any interest thereon, or (2) a \nletter of credit issued for the benefit of PJM or PJMSettlement.” Surety bonds are excluded, \nalthough PJM accepts them elsewhere subject to per-issuer limits, and section 18.8 provides no \nunsecured credit allowance. An LSE therefore has two options, and the cost of the requirement is \nthe cost of whichever it elects. \nB.  Cash \n125. \nAn LSE posting cash must fund the amount. The cost is its own cost of funds, less whatever return \nthe deposit earns. Attachment Q provides that interest on cash accrues to the benefit of the \nParticipant, without specifying a rate. PJM’s audited financial statements for 2025 indicate a \ncredited return of approximately 3.8%, below the effective federal funds rate for the same period, \nand interest is credited to a member account periodically rather than continuously. \n126. \nAn LSE that posts cash therefore bears the difference between its cost of funds and that credited \nreturn. For an investment-grade load-serving entity with a cost of funds in the range of 5% to 6% \n— the range addressed at paragraph 130 — the net cost of posting cash is therefore approximately \n120 to 220 basis points on the amount posted. A lower-rated entity would bear a higher cost. I do \nnot use the 9.5% after-tax weighted average cost of capital PJM applied in deriving the Credit \nRate. As explained at paragraphs 129 through 132, that figure describes the cost of capital for \nmerchant generation investment, not the cost of funds of the load-serving entities required to post \nthe collateral. \nC.  Letter of credit \n127. \nA letter of credit does not require the LSE to fund the amount, but it consumes committed credit \ncapacity and is priced accordingly, as a spread over a reference rate together with a facility fee. \nThe cost is a function of the issuing bank’s pricing and the borrower’s credit, and the filing places"},{"page":91,"startToken":36405,"endToken":37150,"text":"20 \n \nno evidence of either on the record. I therefore state the cost as a range rather than a single figure. \nAt 100 basis points the annual cost is approximately $15,000 per RBP UCAP MW; at 200 basis \npoints, approximately $30,000; and at 300 basis points, approximately $45,000. A letter of credit \nfee is not the same quantity as a corporate bond yield, and I do not equate them. I use these values \nas sensitivities rather than as estimates of the price any particular load-serving entity would obtain. \n128. \nI do not state a single blended cost across the two forms. PJM presently observes a mix of \napproximately thirty-five percent cash and sixty-five percent letters of credit across its markets, \nbut that mix is observed against a total collateral balance that has never exceeded approximately \n$13.1 billion across every market and every participant, and against a period in which PJM's own \nreporting records the extension of unsecured credit alongside it. I do not assume that this historical \nmix would remain unchanged under a single incremental requirement of approximately $10.2 \nbillion imposed on one class of participants on one date, and I do not rely on it. \nD.  The rate PJM selected is not the rate applicable to load \n129. \nPJM applied a discount rate of 9.5% in deriving the Credit Rate, stating that it “is the capacity \nmarket Weighted Average Cost of Capital developed by The Brattle Group [ ] as part of PJM’s \n2025 periodic review of the Cost of New Entry of Capacity Resources into the PJM Region.” \nKelly Aff. ¶ 28. That figure is an after-tax weighted average cost of capital for merchant \ngeneration investment. It describes the cost of capital of the party selling into the procurement, not \nthe party paying for it. The filing offers no rationale for its application to load-serving entities. I \nexpress no view on whether 9.5% was an appropriate input to PJM’s own valuation exercise. My \npoint is narrower: that figure is not evidence of the financing cost a Load Serving Entity incurs to \npost cash or obtain a letter of credit, and the filing offers no other evidence of that cost. \n130. \nPJM has separately represented that approximately seventy-seven percent of load is served by \ninvestment-grade entities. Published market data establish the cost of funds available to corporate \nborrowers across the rating spectrum, and none of it approaches 9.5% for a population of that \ndescription. As of August 12, 2026, the ICE BofA index effective yields were: BBB, the lowest \ninvestment-grade tier, 5.58 percent; BB, the highest non-investment-grade tier, 5.98 percent; \nsingle-B, 7.25 percent; and CCC and lower, 14.51 percent. PJM’s seventy-seven percent figure is \nload weighted; the entity-count measure PJM presented separately, addressed at paragraph 138 \nbelow, identifies 24 of 105 Load Serving Entities as investment grade. The rating distribution of \nthe remainder is not stated, so I present scenarios rather than a single blended figure. A population \nthat is seventy-seven percent BBB with the remainder at BB implies approximately 5.67 percent; \nwith the remainder at single-B, approximately 5.96 percent; and with the remainder entirely at \nCCC and lower, approximately 7.63 percent. To reach 9.5 percent, approximately forty-four \npercent of the population would have to be rated CCC or below if the remainder were BBB, or \napproximately thirty-one percent if the remainder were single-B. The distribution of those yields is \nitself instructive: the interval between the lowest investment-grade tier and the highest non-\ninvestment-grade tier was forty basis points on that date, and between the highest non-investment-\ngrade tier and single-B, 127 basis points, while the interval between single-B and CCC and lower \nwas 726 basis points. Credit is not priced as a single category above and below the investment-\ngrade boundary, and the rate PJM selected lies materially above the BBB, BB and single-B index \nyields and below the CCC-and-lower index. Attachment C. \n131. \nThis distinction has a further consequence. A predominantly investment-grade population is one to \nwhich Attachment Q’s unsecured credit allowance would ordinarily extend, keyed to \ncreditworthiness and tangible net worth — a mechanism section 18.8 omits entirely. \nE.  In aggregate \n132. \nAt the Initial RBP Target, the aggregate annual cost of carrying the requirement ranges from \napproximately $102 million at 100 basis points to approximately $307 million at 300 basis points. \nMeasured against the approximately $573 million billed to load in the first Delivery Year, that is"},{"page":92,"startToken":37150,"endToken":37869,"text":"21 \n \nbetween approximately eighteen and fifty-four percent of the amount billed. Each 100 basis points \non the $1.5 million Credit Rate is $15,000 per MW-year, or approximately $41.10 per MW-day. \nOn the sensitivities used above the per-unit cost is approximately $41.10 per MW-day at 100 basis \npoints, $61.64 at 150, $82.19 at 200 and $123.29 at 300 — which, measured against the $555 \nmaximum willingness to pay rather than against the amount billed, is between approximately \nseven and twenty-two percent of that cap, additional to it and recovered nowhere in the proposed \ntariff. The two ranges differ because the denominators differ: the first states carrying cost as a \nproportion of what load is billed, the second as a proportion of the ceiling PJM has represented as \nthe limit of what load will pay. The per-MW-day figure does not depend on the size of the \nprocurement: because both the collateral and the MW-days scale with committed UCAP MW, the \nquantity cancels. \nF.  The cost is not recovered and is not disclosed \n133. \nNo provision of the proposed tariff recovers this cost. It does not appear in the maximum \nwillingness to pay, in the RBP Charge, or in any figure PJM has presented to the Commission. A \nLoad Serving Entity must either absorb that cost or recover it through its applicable retail or \ncontractual arrangements, and where an LSE or the large load it serves fails to appear, the \nrequirement is reassigned under section 18.8(b)(i)(B) to the remaining large-load LSEs in the zone \nand, where none remain, to native load. \n134. \nAs set out above, the Commission established Regional Transmission Organizations to promote \nefficiency in wholesale electricity markets and to ensure that consumers pay the lowest price \npossible for reliable service, and has held that credit and collateral requirements must not be “so \nstringent that they unnecessarily inhibit access to the marketplace.” PJM has presented the $555 \nmaximum willingness to pay as the limit of what load will pay under this procurement. On PJM’s \nown figures and the forms of collateral its tariff permits, the cost of carrying the required collateral \nis additional to that limit, and on the sensitivities set out above amounts to approximately $102 \nmillion to $307 million each year, or approximately eighteen to fifty-four percent of the amount \nbilled to load in the first Delivery Year. The filing does not identify that cost. The analysis in this \naffidavit indicates that a requirement sized on standard collateral practice would be substantially \nsmaller for load-serving entities, and larger for RBP Sellers. \nXI.  THE REQUIREMENT CREATES SYSTEMIC LIQUIDITY RISK AMONG THE ENTITIES \nOBLIGATED TO POST IT \n135. \nThis section addresses whether the requirement can be met — in the forms the tariff permits and \non the date it specifies. I approach that question at two levels. The first is aggregate: whether \napproximately $10.2 billion can be raised at one moment, from one class of participants, in two \ninstruments, drawn from a limited group of issuing institutions. The second is particular: whether \nthe obligation allocated to a given zone is within the financial capacity of the parties serving it. \nThe second question is not incidental to the first. A requirement of this design becomes entity-\nspecific at the point where the required posting approaches or exceeds the obligor’s available \nliquidity and committed credit capacity, and the tariff performs no test of that at any stage. I use \nthe NOVEC zone as the illustration because PJM’s own allocation and the obligated entity’s own \nreported financials are both on the public record. The standard is the one set out in Section III: \ncredit requirements must not be so stringent that they unnecessarily inhibit access to the \nmarketplace, and the Commission has identified cascading default as the consequence it guards \nagainst. \nA.  The requirement falls at one moment, in two instruments \n136. \nSection 18.8(b)(i)(B)(1) requires each Load Serving Entity with an RBP Obligation to post forty-\nfive days before the start of the Delivery Year. Every obligated LSE across the footprint posts on \nthe same date; nothing in section 18.8 staggers the requirement, phases it, or permits it to be \nsequenced. RBP Collateral is defined as either a cash deposit or a letter of credit. Surety bonds are"},{"page":93,"startToken":37869,"endToken":38312,"text":"22 \n \nexcluded, although PJM accepts them elsewhere and held approximately $606 million of them on \nJuly 30, 2026. No unsecured credit allowance is provided and no corporate guaranty is permitted. \nApproximately $10.2 billion therefore becomes due at a single moment, from a single class of \nparticipants, in two instruments. \nB.  The obligation is concentrated and is not adjusted for the financial capacity of the obligor \n137. \nAs set out in Attachment B, five zones each carry an obligation exceeding $1 billion — AEPOHIO \nat approximately $2.29 billion, NVEC at $1.95 billion, COMED at $1.33 billion, PPL at $1.23 \nbillion and DOM at $1.11 billion — together approximately $7.9 billion, or 77 percent of the \ninitial requirement. Each zone’s share is determined by the Electric Distributor’s submission of \nRBP Obligation MW, scaled as necessary to the fixed zonal target. Nothing in that derivation \nrefers to the financial capacity of the entity required to post, and nothing in section 18.8 tests it at \nany stage. \n138. \nPJM has measured the credit quality of the population required to post. In the Credit and \nSecuritization Overview presented on March 4, 2026, PJM identified 105 Load Serving Entities, \nof which 24 were investment grade and 81 were sub-investment grade. It reported that 46 percent \nhad tangible net worth below $5 million and 30 percent below $1 million, that these figures \nindicated “limited financial flexibility,” and that investment-grade entities had “provided corporate \nguarantees.” PJM therefore had a measurement of the financial capacity of the obligated \npopulation before the requirement was filed. \n139. \nFor scale, $10.2 billion is equivalent to approximately $97.6 million for each of the 105 Load \nServing Entities PJM identified if distributed evenly across that population, in which 48 entities \nreport tangible net worth below $5 million. The actual requirement is not distributed evenly; it is \nconcentrated among the Load Serving Entities that receive RBP obligations. The allocation to the \nNOVEC zone alone is approximately nineteen percent of the entire initial requirement and \napproximately twenty times the average share, and it falls on a single distribution cooperative. \nC.  The NOVEC zone \n140. \nThe consequence is visible in the largest cooperative-served zone. Northern Virginia Electric \nCooperative is the Electric Distributor for that zone/area and the Load Serving Entity for the load \nwithin it. Virginia’s retail choice provisions do not reach the customers of a distribution \ncooperative, so no other Load Serving Entity serves load there. It therefore both makes the RBP \nObligation MW assignment under proposed Reliability Assurance Agreement, section 7.2C and \nbears the resulting RBP Charge and collateral obligation under Tariff, Attachment DD, section \n18.8(b)."},{"page":94,"startToken":38312,"endToken":38901,"text":"23 \n \nTable 1. The NOVEC zone obligation against the reported financial position of the cooperative serving \nit \n($ millions except where noted) \n \nAmount \nNVEC initial allocation (RBP UCAP MW) \n1,302.6 \nZonal collateral obligation at $1.5 million per MW \n1,954 \nTotal assets, FY2025 \n1,716 \nTotal liabilities, FY2025 \n797 \nTotal margins and equities, FY2025 \n920 \nOperating revenue, FY2025 \n1,475 \nPatronage capital and margins, FY2025 \n44.7 \nObligation as % of total assets \n114% \nObligation as % of margins and equities \n212% \nObligation as % of annual revenue \n132% \nAnnual cost of the obligation at 100 bps \n19.5 \nAnnual cost at 200 bps \n39.1 \nAnnual cost at 300 bps \n58.6 \nSources: Croop Aff. ¶ 46 (initial allocation); Proposed Tariff, Attachment DD, § 18.8(b)(i)(A) (Credit Rate); \nNorthern Virginia Electric Cooperative, Financial and Operating Report Electric Distribution, U.S. Dep’t \nof Agriculture, Rural Utilities Service, Borrower Designation VA0055, period ended December 2025 \n(prepared with audited data), Parts A, C, I, O and Q. \n141. \nThe obligation allocated to that single zone is approximately $1.95 billion. The cooperative \nserving it reports total assets of approximately $1.716 billion and total margins and equities of \napproximately $919.7 million. The collateral required for the zone exceeds the entire asset base of \nthe entity whose customers give rise to it, and exceeds its equity by a factor of more than two. It \nexceeds the cooperative’s total long-term debt of approximately $69.2 million by a factor of \napproximately twenty-eight, and its cash and temporary investments of approximately $243.2 \nmillion by a factor of approximately eight. It also exceeds the approximately $34.4 million of cash \ncollateral the cooperative reports as posted to PJM by a factor of approximately fifty-seven. That \n$34.4 million secures the cooperative’s existing obligations under Attachment Q and continues to \nbe required; the RBP requirement is incremental to it, so total credit support would rise to \napproximately $1.988 billion. \n142. \nThe cooperative is rated investment grade and stands on its own balance sheet. I do not assume \nthat its present credit standing establishes that approximately $1.95 billion of incremental credit \nsupport would be available on the terms that standing reflects, because the terms available to an \nentity after it assumes an obligation of this size are not necessarily the terms available to it before. \nTaking the most favorable assumption available — that its credit standing is maintained and that a \nletter of credit can be obtained at 100 basis points — the annual cost would be approximately \n$19.5 million. The cooperative reported patronage capital and operating margins of approximately \n$20.8 million for FY2025, a figure already stated after its existing interest expense of \napproximately $0.8 million. The carrying cost of the required collateral would therefore have to be \nabsorbed out of that residual margin, and at 100 basis points alone it consumes approximately 94 \npercent of it. At 150 basis points it would be approximately $29.3 million, or roughly 141 percent \nof that figure; at 200 basis points, approximately $39.1 million, or roughly 188 percent; and at 300 \nbasis points, approximately $58.6 million, or roughly 281 percent. Each figure is between \napproximately twenty-five and seventy-five times the cooperative’s entire existing annual interest \nexpense of approximately $0.8 million, and would be incremental to it. Each is an annual cost that \ncould recur while the requirement remains outstanding; section 18.8 provides no mandatory \nreduction schedule. The significance of that conclusion is not confined to this cooperative. It is"},{"page":95,"startToken":38901,"endToken":39577,"text":"24 \n \ninvestment grade, and unlike the entities PJM describes as having provided corporate guarantees it \nis member-owned and stands on its own balance sheet rather than a guarantor’s. If a requirement \nof this magnitude cannot be borne by an obligor of that credit quality, PJM’s classification of the \nremaining eighty-one Load Serving Entities as sub-investment grade does not describe a lesser \nproblem. \n143. \nThe customers on whom that cost would ultimately fall cannot select another supplier. Virginia’s \nlarge-customer retail choice provision permits individual nonresidential customers whose \nnoncoincident peak demand exceeded five megawatts to purchase electric energy from a licensed \ncompetitive supplier, but by its terms it reaches only customers “of a Phase I or Phase II Utility, as \nthose terms are defined in subdivision A 1 of § 56-585.1” — Appalachian Power Company and \nVirginia Electric and Power Company. Va. Code § 56-577(A)(3). A distribution cooperative is \nneither. Neither the large loads whose forecast growth produced the NOVEC zone allocation nor \nthe native load that would bear the cost in their absence has any general right to purchase \ngeneration from a competitive supplier. \n144. \nThe zone is the illustration and not the limit of the problem. If the largest and most visible \nallocation in the procurement was not tested against the financial capacity of the entity serving it, \nthe filing identifies no requirement that any allocation be tested at all. \nD.  Letter of credit capacity is concentrated \n145. \nAs of July 30, 2026 PJM held approximately $6.87 billion in letters of credit issued by 43 \ninstitutions, of which the ten largest accounted for approximately 65 percent of the total and two \nindividually exceeded 10 percent. PJM Interconnection, L.L.C., Credit Risk Metrics, Risk \nManagement Committee, at slide 4 (Aug. 18, 2026).4 Satisfying the RBP requirement \npredominantly by letter of credit would more than double the letter of credit exposure PJM holds, \ndrawn from substantially the same group of institutions. \n146. \nPJM monitors and reports monthly on the letters of credit posted by issuing banks. That reporting \nincludes the concentration by volume among the largest issuers. It is provided to keep Members \ninformed of how PJM is managing the credit risk it holds through third parties. PJM has broad \ndiscretion to decline a letter of credit from a bank on concentration grounds. The membership \nprudently supported that discretion in the comprehensive credit policy overhaul PJM filed in 2020, \nbecause it allows PJM to manage not only a Member’s direct credit risk but also the manner in \nwhich the Member chooses to mitigate the risk it presents to the broader membership. No analysis \nappears on the record addressing whether the RBP requirement can be satisfied without creating \nconcentration risk among the banks that would issue the letters of credit. PJM measures that \nconcentration every month because it bears directly on the quality of the collateral PJM holds. The \nfiled requirement would roughly double the letter of credit portfolio, drawn from substantially the \nsame institutions, and the filing does not measure it at all. \nE.  The failure mode is correlated, and PJM has handled the same structure differently \n147. \nThe exposures created by the requirement are correlated rather than independent. All obligated \nLoad Serving Entities post on the same date, in the same two instruments, drawn from the same \nlimited group of issuing institutions, against an obligation whose quantity a Load Serving Entity \nhas only limited means to affect. The assignment is made by the Electric Distributor under \nproposed Reliability Assurance Agreement, section 7.2C, and may be reassigned by it; and the \nprocurement target itself may be reduced before the procurement closes on evidence of the kind \nPJM identified during the stakeholder process. Neither is a means by which a Load Serving Entity \nholding an assigned obligation can reduce that obligation once the commitment binds, which is the \nperiod during which the collateral is required. Under section 18.9(a), a default is reallocated pro \n \n4 Presentation available at: https://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/rmc/2026/20260818/20260818-informational-only---credit-metrics---august-2026.pdf"},{"page":96,"startToken":39577,"endToken":40280,"text":"25 \n \nrata to the remaining LSEs — entities that by construction have just funded or renewed their own \npostings, from the same sources, on the same date. The reallocation therefore arrives at the point in \nthe annual cycle when the remaining LSEs have committed liquidity or bank capacity to their own \nannual postings. \n148. \nPJM has faced a structurally comparable situation. Following Winter Storm Elliott, PJM assessed \napproximately $1.8 billion in non-performance charges. Most of the affected units had already \nbeen liquidated into high real-time energy prices during the event, creating balance sheet and \nliquidity stress. The non-performance charges, and the collateral required to secure them, therefore \nfell on participants whose liquidity had already been depleted. The structure is similar to that of \nthe RBP, except that under the RBP it is the demand side that faces the collateral call. See PJM \nInterconnection, L.L.C., 185 FERC ¶ 61,204 (2023) (order approving offer of settlement resolving \nfifteen complaints concerning Winter Storm Elliott Non-Performance Charges) (“Elliott \nSettlement Order”). \n149. \nPJM did not demand the full amount at a single moment. It sought authority to extend the period \nfor payment of non-performance charges from three months to nine months to reduce the risk of \ndefaults, and the tools available under Attachment Q permitted it to evaluate participants \nindividually and to exercise judgment about timing rather than treating every participant \nidentically on a single date. The charges were ultimately resolved by settlement at approximately \n$1.2 billion against approximately $1.8 billion assessed. See PJM Interconnection, L.L.C., 183 \nFERC ¶ 61,001 (2023) (permitting Members to elect an extended nine-month payment term for \nNon-Performance Charges); PJM Interconnection, L.L.C., 185 FERC ¶ 61,204 (2023) (approving \na uniform 31.7 percent reduction in Non-Performance Charges across all market participants) \n(“Elliott Settlement Order”). Defaults did occur; at least one resource owner sought bankruptcy \nprotection after receiving charges its filings described as a multiple of the affected plants’ annual \nrevenue. What did not occur was a collateral call that itself became a source of stress. \n150. \nSection 18.8 contains no equivalent. It states a date and an amount. It provides no phase-in, no \nschedule, no discretion to sequence, and no mechanism through which a Load Serving Entity \nunable to satisfy the requirement on the stated date may propose an alternative. The consequence \nof failing to satisfy the requirement on the stated date is the default machinery in the governing \ndocuments. I note the absence of sequencing discretion because it describes what the filed \nprovision does, not because supplying that discretion would answer the questions addressed in this \naffidavit. A schedule for posting an amount that is not measured against the exposure it secures \nwould change when the requirement falls due; it would not change its magnitude, its basis, or the \npopulation on which it lands. \nF.  Conclusion \n151. \nIn my opinion the filing does not establish that the proposed requirement can be met by the \npopulation required to post it. It does not analyze the aggregate letter of credit capacity available to \nthe obligated population, the effect of a simultaneous call on entities that cannot reduce their \nexposure by managing their positions, or the consequences in any zone where the obligation \nexceeds the financial capacity of the parties serving it. The NOVEC zone shows that the question \nis not hypothetical: an obligation of approximately $1.95 billion is allocated to a footprint served \nby a cooperative reporting approximately $1.716 billion in total assets, whose customers have no \ngeneral right to select an alternative Load Serving Entity that would bear the cost and collateral \nexposure in its place. \n152. \nWhere an obligation of that kind cannot be met, the proposed provisions do not extinguish it. \nSection 18.9(a) reallocates the defaulted charge pro rata to the remaining Load Serving Entities, \nand Operating Agreement section 15.2.2 extends what remains to Members with no allocation at \nall. The same features that make the requirement difficult to satisfy — its concentration, its single \ndate, and the absence of any adjustment for the financial capacity of the obligor — also determine \nwhere the loss travels when it is not satisfied. That is the subject of the following section."},{"page":97,"startToken":40280,"endToken":40964,"text":"26 \n \nXII.  THE SOCIALIZATION OF A DEFAULT INCREASES THE OBLIGATION OF THE \nREMAINING LSEs AND REACHES MEMBERS WITH NO ALLOCATION \n153. \nThis section addresses where a loss goes. The Commission has identified the prevention of \nsocialization as the function collateral performs: where collateral posted by a defaulting party is \ninsufficient, the remaining exposure and costs are socialized across the membership. The standards \nset out in Section III order those two things — the defaulting participant’s own margin absorbs the \nloss first, and mutualization is what remains after it is exhausted. Section 18.9(a) does not \nexpressly establish that sequence. The proposed provisions also contain two distinct reallocation \nmechanisms, operating on different triggers and different scopes, and the tariff does not \ndistinguish them. \nA.  Section 18.9(a) does not expressly require collateral to be applied before reallocation \n154. \nSection 18.9(a) provides that a defaulted RBP Charge “will be allocated to all remaining Load \nServing Entities responsible for paying RBP Charges based on their pro-rata share,” and that such \namounts “may be offset by the RBP Collateral posted by the defaulting Load Serving Entity.” \nReallocation to non-defaulting parties is stated as mandatory. Application of the defaulting party’s \nown collateral is stated as permissive. \n155. \nThat differs from the sequence the standards describe and from the sequence PJM applies \nelsewhere. Under Attachment Q, collateral posted against an obligation is applied to that \nobligation upon default, and mutualization under Operating Agreement, section 15.2.2 is the \nresidual. Section 18.8 collects $1.5 million per MW from load, and section 18.9(a) does not \ncommit PJM to apply it to the loss against which it was collected. \n156. \nI do not suggest that PJM would decline to apply the collateral. The point is that the tariff does not \nrequire it. The collateral posting is mandatory, while section 18.9(a) states its application to a \ndefaulted RBP Charge in permissive terms. If PJM intends that the collateral be applied first, the \nfiled text does not state it. \nB.  Two reallocation mechanisms of different scope \n157. \nThe proposed provisions reallocate an obligation in two circumstances, and the scope differs. \nWhere a large load does not materialize or ceases operation, the obligation is reassigned within the \nzone. Where an allocated Load Serving Entity fails to pay, section 18.9(a) reallocates the defaulted \ncharge to “all remaining Load Serving Entities responsible for paying RBP Charges,” language \nthat on its face reaches the entire footprint rather than the zone. The tariff does not state that the \ntwo operate on different scopes, and nothing in section 18.9 confines the payment-default \nreallocation to the zone in which the default occurs. \nC.  Where the load does not appear, the obligation reaches native load \n158. \nPJM described the treatment of a load that does not appear during the stakeholder process. In \nmaterials presented to the Reliability Backstop Critical Issue Fast Path on June 10–11, 2026, PJM \nstated that where a load does not materialize or shuts down before the end of the RBP term, the \ncorresponding large load obligation must be reassigned, and identified three options: the Electric \nDistributor may assign the obligation to another Load Serving Entity; if it does not, and other Load \nServing Entities in the zone/area hold assignments, the obligation is allocated pro rata among those \nremaining entities by zonal share; and if the Electric Distributor makes no assignments in the \nzone/area, “the costs will be reallocated across all load in the zone on a pro rata basis using the \nObligation Peak Load Contribution MW (the same methodology used to allocate RPM costs).” \nDesign Presentation,  at slide 30. PJM stated in the same materials that if states have not \nestablished frameworks to allocate costs to new data center loads, “it is unclear to which \ncustomers those costs would be assigned,” and that as a backstop PJM will allocate to all load in \nthe zone, “including non-large loads,” using existing Peak Load Contribution assignments. Id. at \nslide 27. PJM’s stakeholder materials refer to the quantity assigned to a Load Serving Entity as the"},{"page":98,"startToken":40964,"endToken":41734,"text":"27 \n \nLarge Load Contribution or “LLC” Obligation MW; the PJM Board’s July 27, 2026 decisional \nletter refers to the same quantity as the Reliability Backstop Obligation or “RBO,” described there \nas a new defined term exclusively for the RBP; and the proposed tariff language refers to it as the \nRBP Obligation MW submitted for a Load Serving Entity by the Electric Distributor. The quantity \nis the same in each. I use the tariff term. \n159. \nThe filed tariff assigns the allocation function to the Electric Distributor and specifies the outcome \nwhere it is not performed. Section 18.8(b)(i)(B)(1) provides that the RBP Obligation MW values \nuploaded by the Electric Distributor are “scaled, as necessary, in the event that the RBP Obligation \nMW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW \nfor the zone/area.” Because the zonal quantity is fixed, an obligation not reported for one Load \nServing Entity is not extinguished; it is scaled onto the others. Section 18.8(b)(i)(B)(2) addresses a \nLoad Serving Entity for which the Electric Distributor reports no obligation at all, providing that \nsuch an entity “may be required to post” collateral determined by its “pro-rata share of the Daily \nUnforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8” — that is, on \nPeak Load Contribution. Section 18.3(a) fixes the zonal allocation for the full fifteen-year term. \n160. \nThe structure is a two-step one: the Electric Distributor assigns, and where it does not, the cost \nfalls on all load in the zone/area on Peak Load Contribution. PJM has described the assignment \nstep as similar to the existing Peak Load Contribution and Network Service Peak Load processes, \nand Electric Distributors perform an analogous function today. The difference lies in what is \nassigned. Those processes allocate charges that follow measured load: if the load falls, the \nallocated quantity falls with it. The RBP Obligation MW allocates a fixed quantity for fifteen \nyears, set on a forecast, which does not decline if the forecast load does not appear. The tariff \nstates no standard governing how the Electric Distributor is to make the assignment, and no \nmechanism by which a Load Serving Entity may determine in advance whether it will hold one. \nWhat the tariff does specify is where the quantity comes to rest if the assignment is not made: on \nall load in the zone/area, including load that is not large load. In the NVEC zone/area the two steps \nreach the same entity. Northern Virginia Electric Cooperative performs the assignment as Electric \nDistributor and is the Load Serving Entity on which the cost falls if it does not, and there is no \nother Load Serving Entity in that zone/area to which the obligation could be assigned. \n161. \nThe quantities that fix each zone’s share were not prepared for this purpose. The Load \nAdjustments underlying the RBP Target derive from large load additions reported through PJM’s \nload forecasting process and taken from Table B-9b of the 2026 Load Forecast, as the difference \nbetween forecast summer 2028 and summer 2026 peak load. Those submissions were made to \ninform a planning forecast. They carried no cost consequence for the submitting entity, and were \nnot accompanied by verification procedures directed to their use in allocating a fifteen-year \npayment and collateral obligation. Section 18.3(a) then fixes the resulting allocation for the full \nfifteen-year term on that single vintage. \nD.  The NOVEC zone \n162. \nThe consequence is measurable, and its distribution across customer classes is not uniform. As set \nout in the preceding section, the NOVEC zone carries an initial allocation of 1,302.6 UCAP MW \nand a collateral obligation of approximately $1.95 billion. Northern Virginia Electric Cooperative \nserves that zone and reports energy sales of approximately 14.649 billion kilowatt-hours for the \nyear ended December 31, 2025, against a coincident peak demand of approximately 2,360 MW — \na system load factor of approximately 71 percent. That system figure conceals two classes with \nmaterially different characteristics. The cooperative reports that data centers represent more than \n65 percent of its energy sales. I use 65 percent in the calculations that follow, which is therefore a \nlower bound. Data center load typically operates at a load factor of 85 to 95 percent; residential \nand small commercial load operates at approximately 40 to 55 percent, and load factors for the \nresidential class are observable from default service and basic generation service supply auctions. \nThe conclusion does not depend on the precise figures. What the difference in load factor"},{"page":99,"startToken":41734,"endToken":42497,"text":"28 \n \nestablishes is that a charge collected on peak load contribution rather than on energy falls on the \ntwo classes in materially different proportion to the energy each consumes, and that the direction \nof the disparity is against the class that consumes less. Selecting the low end of the data center \nrange and the high end of the residential range understates that disparity, and I do so below. \n163. \nThat difference matters because RBP Charges are allocated on a demand basis rather than an \nenergy basis. Where obligations are not assigned to the Large Loads that produced them, the \nquantity falls to Peak Load Contribution — the Obligation Peak Load Contribution MW that PJM \nstates is “the same methodology used to allocate RPM costs.” The two classes therefore bear the \nobligation in proportion to their contribution to peak, not to their consumption of energy. On the \nload factors stated above, non-data-center load accounts for approximately 35 percent of energy \nbut approximately 45 to 53 percent of peak load contribution. \n164. \nThe effect is to shift the burden toward the lower-load-factor class. At the 2028/2029 Base \nResidual Auction clearing price of $325.00/MW-day and an RBP price of $555, the contract-for-\ndifferences differential is $230/MW-day, or $83,950 per MW-year, and the first-year charge \nallocated to the zone is approximately $109 million. Allocated on peak load contribution, that \ncharge falls at approximately $11.63 to $13.62 per megawatt-hour on non-data-center load, against \napproximately $6.45 to $7.53 per megawatt-hour on the data center load whose forecast growth \nproduced the allocation. The uniform energy-basis figure, approximately $8.96 per megawatt-\nhour, understates the former and overstates the latter. The conclusion does not depend on the \nparticular load factors selected; it holds across the full range set out in Attachment D. \n165. \nThe cost of carrying the collateral is allocated the same way and compounds the same disparity. At \n150 basis points — a midpoint of the sensitivity range set out in Section X, stated here for \nillustration — the annual carrying cost for the zone is approximately $29 million, of which \napproximately $14 million falls on non-data-center load — approximately $3.38 per megawatt-\nhour, against approximately $1.88 per megawatt-hour for data centers. Taken together, the charge \nand the cost of the collateral securing it fall at approximately $16 per megawatt-hour, or 1.6 cents \nper kilowatt-hour, on native load, against approximately $8.88 per megawatt-hour on data centers. \nThe cooperative reports a monthly average residential cost of $113.74 for 1,000 kilowatt-hours; \nthe incremental burden on that bill is approximately fourteen percent. These figures are borne by \nthe customers of a distribution cooperative reporting total assets of approximately $1.716 billion \nand patronage capital and margins of approximately $44.7 million, who have no general right to \npurchase generation from a competitive supplier. I do not suggest that outcome is the expected \none. I state it because the tariff makes it available, because it arises under the allocation \nmethodology PJM itself specifies, and because PJM has acknowledged that it does not know to \nwhich customers the costs would be assigned. Passing the cost through does not resolve the matter. \nWhether the cooperative assigns it to the Large Loads it serves or recovers it from native load, the \nallocation from PJM is unchanged. Those loads did not face a charge of this kind before the RBP \nwas proposed, and a cost of this magnitude may bear on whether a given development proceeds. If \nit does not proceed, the allocation does not follow it: the RBP Obligation MW for the zone/area is \nfixed under section 18.3(a) for the full fifteen-year term on the basis of the load forecast used to \nset it, and it is not revised if the forecast load does not materialize. The cooperative would remain \nresponsible for an allocation calculated on load that did not arrive. The cooperative was in any \nevent already before its state commission on the question of assigning large-load costs: on July 17, \n2026 it announced a filing to update the rate classes applicable to large-load customers so that \ncosts attributable to serving those customers are assigned to them rather than shifted to smaller \nusers, with a further step to follow involving updated load forecasts and a power supply \nsolicitation. \nE.  The NOVEC zone does not satisfy the conditions for the opt-out \n166. \nPJM identified this problem during the stakeholder process and included an opt-out addressing that \nconcern. Explaining the opt-out at section 18.1(d), PJM states that cooperatives raised the concern"},{"page":100,"startToken":42497,"endToken":43190,"text":"29 \n \nthat an Electric Distributor in a retail choice state, not regulated by the state and not otherwise \nserving as the LSE for generation to the load, “would be forced to have its customers absorb the \ncosts of an ‘overbuy’ if a particular large load included in the forecast were to fail to materialize,” \nand that unlike a state-regulated investor-owned utility, cooperatives and municipal utilities “are \nnot governed by a state regulatory authority that would be responsible for addressing the potential \nreallocation of RBP costs.” PJM describes this as a limited regulatory gap faced by cooperatives \nand municipal utilities “whose rates are not regulated by the states.” \n167. \nThe opt-out is available only on that condition. The retail rates of Virginia distribution \ncooperatives are regulated by the Virginia State Corporation Commission. A distribution \ncooperative is a utility consumer services cooperative under Chapter 9.1 of Title 56 of the Code of \nVirginia, and its regulated utility services are subject to the jurisdiction of the Commission in the \nsame manner and to the same extent as those provided by other persons under the laws of the \nCommonwealth. Va. Code §§ 56-231.33, 56-231.34; see also Va. Code § 56-585.3; 20 Va. Admin. \nCode § 5-200-21 (rules governing streamlined and general rate proceedings for electric \ncooperatives subject to the Commission’s rate jurisdiction). Each of the cooperative’s filed rate \nschedules provides that service is available “subject to the Terms and Conditions of the \nCooperative filed with the State Corporation Commission of Virginia.” Northern Virginia Electric \nCooperative, Schedule HV-2, Large Power Dedicated Facilities Contract Service, Regulated \nRates. The cooperative states on the same basis that the Commission “approves rates, fees and all \nterms and conditions of service of the Cooperative.” The cooperative serving the NOVEC zone is \ntherefore ineligible for the opt-out, notwithstanding that it faces precisely the exposure PJM \ndescribed: an obligation fixed for fifteen years on a forecast of large load additions, which under \nsection 18.8(b)(i)(B)(2) reaches its native load if that load does not materialize. The zone carrying \nthe second largest allocation in the procurement, and the only zone in which the obligation \nexceeds the reported assets of the entity serving it, cannot use the remedy PJM built for the \nproblem PJM identified. \nF.  The residual reaches Members with no allocation \n168. \nOperating Agreement, section 15.2.2 provides that where a Member defaults on its payment \nobligations, the other PJM Members may be required to pay a share of the defaulted amounts. That \nprovision is not limited to Members allocated RBP Charges. \n169. \nEast Kentucky Power Cooperative is in that position. PJM’s illustrative allocation shows EKPC \nwith a Load Adjustment of zero and no allocation of the RBP Target. On those figures EKPC \nwould be allocated no RBP Charges and would post no RBP Collateral. It nonetheless remains a \nPJM Member and remains within the residual tier. The assessment under section 15.2.2 is made to \nEKPC as the PJM Member. \n170. \nA Member in that position receives no capacity from the procurement, pays no RBP Charge, and \nposts no collateral, yet bears exposure to a default under it. No collateral is posted against that \nexposure by any party, because the requirement in section 18.8 reaches only Load Serving Entities \nwith an allocated obligation. I do not suggest that a Member in EKPC’s position should be \nrequired to post collateral. The observation is that the requirement PJM has designed does not \nreach the exposure such a Member bears. \nG.  The seller side runs the same direction \n171. \nSection 18.9(b) provides that where an RBP Resource defaults on payment of shortfall charges, \n“the corresponding credits will not be allocated to the Load Serving Entities that would otherwise \nreceive the RBP shortfall credits.” There is no reallocation among sellers and no provision \napplying the seller’s collateral to make load whole. \n172. \nThe seller’s assessed liability is limited to the three-year shortfall period, while the economic \nconsequence to load can continue after the commitment is rescinded. Under section 18.6(e), a \ncommitment that fails to come online for three Delivery Years is rescinded for the remainder of"},{"page":101,"startToken":43190,"endToken":43822,"text":"30 \n \nthe term; the resource is thereafter neither compensated nor charged, and its collateral is released. \nLoad receives nothing for the remaining twelve years of a fifteen-year commitment. \n173. \nThe two provisions produce the same result from opposite facts. A load default is recovered from \nother load. A seller default is also borne by load. Under the two default paths identified in the \nfiling, any unrecovered loss ultimately reaches load or the residual PJM membership. \nH.  Conclusion \n174. \nIn my opinion the proposed provisions do not prevent the socialization of a default. They establish \nthe paths by which residual losses are reallocated. The collateral posting is mandatory, while \nsection 18.9(a) states its application to a defaulted RBP Charge in permissive terms. Where \nforecast Large Load does not materialize, the obligation remains within the zone and, under the \nfinal allocation step PJM describes, may ultimately be allocated to native load by Peak Load \nContribution. An LSE payment default is addressed separately under section 18.9(a), which \nreallocates the defaulted charge among all remaining Load Serving Entities responsible for paying \nRBP Charges. Because RBP Charges are assessed against every zone/area holding a share of the \nRBP Target, that reallocation reaches the footprint and is not confined to the zone in which the \ndefault occurs. The remedy PJM designed for the cooperative overbuy problem is conditioned so \nas to exclude cooperatives whose rates are state-regulated. And the residual extends to Members \nwho take nothing from the procurement and post nothing against it. \nXIII.  THE FILED CREDIT CONSTRUCTS WERE NOT EXAMINED IN THEIR FINAL FORM \n175. \nThis section addresses the process by which the credit provisions developed. I raise it because \ncredit and collateral were material design issues throughout the stakeholder process, because \nmaterially different approaches were proposed by PJM and other stakeholders, and because the \nmethodologies ultimately filed were not examined in their final form. The Commission has held \nthat credit requirements emerging from an RTO stakeholder process must still be reviewed for \nwhether they are unduly burdensome. Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at PP 20-21 \n(2009). The relevant question for my analysis is what opportunity existed for stakeholders to \nexamine the magnitude, mechanics and liquidity consequences of the credit requirements \nultimately proposed. \nA.  PJM proposed using its existing credit framework for LSEs \n176. \nPJM addressed LSE credit requirements in its stakeholder materials on at least two occasions. In \nthe Design Presentation, PJM stated that upon notification by the Load Serving Entity of known \nchanges to its load, “the credit, and collateral requirements for LSEs are expected to be managed \nby the current credit processes,” and that those processes “include, but are not limited to, credit \nevaluation, peak market activity (PMA) recalculation and use of other mitigation tools, such as \nposting of credit support and/or unreasonable credit risk collateral calls (UCRs).” The same \nlanguage appears in PJM’s Stage 4 proposal paper of June 30, 2026. \n177. \nThat was a description of PJM’s existing credit framework applied to a new charge. It contained \nno fixed rate per megawatt, no aggregate requirement, no single posting date, and no stated \ndeparture from Peak Market Activity. As discussed above, Peak Market Activity based on \nhistorical billing would not by itself have captured the prospective exposure created by a new \nfifteen-year RBP obligation, and that limitation was raised during the stakeholder process. But the \napproach PJM described retained the principal elements of its existing credit framework: credit \nevaluation, recalculation of expected exposure through PMA, and the use of additional mitigation \ntools where the calculated exposure was not adequately secured. Nothing in the June 10–11 or \nJune 30 materials identified a Credit Rate of $1.5 million per RBP UCAP MW or an aggregate \nLSE collateral requirement of approximately $10.2 billion."},{"page":102,"startToken":43822,"endToken":44495,"text":"31 \n \nB.  Other stakeholder proposals addressed buyer credit differently \n178. \nCredit and collateral were not absent from the stakeholder debate. Other proposals addressed the \nissue directly and proposed materially different approaches. The Joint EDC and Data Center \nCoalition proposal, which ultimately received the greatest sector-weighted support, tied \nprocurement to the ability of the subscribing LSE or Large Load to satisfy the applicable credit \nrequirement at the time PJM committed supply resources. An LSE unable to satisfy that \nrequirement could not subscribe MW into the procurement. The Joint Consumer Advocates \nlikewise identified credit and collateral as an issue in the procurement. \n179. \nThe Coalition described the objective of its credit methodology in exposure terms. It proposed a \nrequirement intended to ensure that “any emerging buyer default exposure is recognized early, \nfunded continuously, and contained entirely within the LSE buyer” that subscribed to or received \nthe RBP obligation. It also contemplated that the credit requirement would attach when the RBP \ncommitment was made and “adjust[] over time.” That approach therefore contemplated both \nmeasurement of emerging exposure and adjustment of the requirement as that exposure changed. \n180. \nThe Joint Consumer Advocates likewise identified demand-side credit and collateral as a \nnecessary element of the RBP design, but proposed a different structure. Their June 30 executive \nsummary stated that demand-side credit and collateral “should be established before \nprocurement,” rather than assigned later. Their final recommendations to the Board again called \nfor PJM to “[e]stablish demand-side credit and collateral prior to procurement.” They recorded \nPJM staff’s position on that issue as “collateral timing/assignment is later,” and identified as a \nsource of stranded cost risk the absence of any opportunity to require Large Loads to commit to \npay their RBP obligations and to post collateral with the Electric Distributor. Joint Consumer \nAdvocates, Stage 4 of PJM CIFP Stakeholder Process Regarding Large Load Additions and \nReliability Backstop Procurement and Connect & Manage, Executive Summary to the PJM Board \nof Managers (June 30, 2026), at 2, 4, 5. \n181. \nThe significance of these proposals for my analysis is not that the Commission should have \npreferred one stakeholder proposal over another. It is that the stakeholder process had identified \nbuyer credit as a material RBP design issue and produced materially different approaches to \naddressing it. PJM proposed use of its existing credit framework, including credit evaluation and \nrecalculation of exposure. The Coalition proposed that emerging buyer-default exposure be \nrecognized early, funded continuously and contained within the subscribing buyer, with the \nrequirement adjusting over time. The Joint Consumer Advocates proposed establishing demand-\nside collateral before procurement. None of those approaches proposed the fixed $1.5 million per \nMW requirement ultimately filed. \nC.  The seller requirement was materially revised in the final stakeholder proposal \n182. \nSeller credit was also changing late in the process. In the June 10–11 Design Presentation, PJM \nproposed seller credit equal to Max($20, 0.2 × bid price) × MW UCAP committed × 365 × a year \nmultiplier, defined as the ratio of the net present value of the multi-year penalty cash flow to the \nnominal value of one year. PJM stated that a fifteen-year tenor at a 9.5% discount rate “equates to \n~seven years.” Its worked example applied a multiplier of 7.31, producing approximately $21.4 \nmillion for a 100 MW commitment at $400/MW-day, or approximately $214,000 per MW. \n183. \nPJM materially revised that construct in its final June 30 proposal. The Stage 4 proposal paper \nstates the seller requirement as “Max ($20, 0.2 x bid/clearing price) x MW UCAP committed x \n365 x 3 (years),” and explains that PJM was “proposing to require credit support equivalent to \nthree years of the RBP shortfall charges.” Compared on a common basis, at the maximum \nwillingness to pay of $555/MW-day the June 10–11 formulation with its 7.31 multiplier produces \napproximately $296,166 per MW, while the June 30 formulation produces $121,545 per MW — a \nreduction of approximately 59 percent. Section 18.8(a) as filed adopts the June 30 formulation \nwithout further change."},{"page":103,"startToken":44495,"endToken":45152,"text":"32 \n \n184. \nThe timing is relevant. The material revision to seller credit was disclosed in PJM’s final June 30 \nstakeholder proposal, after which no further stakeholder meetings were held. Stakeholders \ntherefore received the revised seller methodology before the filing, but had no subsequent \nstakeholder meeting at which to examine it. The RBP proposal was filed on July 31, 2026, thirty-\none days after the final stakeholder proposal. \nD.  The LSE requirement changed after the final stakeholder proposal \n185. \nThe treatment of LSE credit followed a different sequence. PJM’s final June 30 proposal \ncontinued to state that LSE credit and collateral requirements were expected to be managed \nthrough existing credit processes, including credit evaluation, Peak Market Activity recalculation \nand other mitigation tools. The fixed $1.5 million per RBP UCAP MW requirement does not \nappear in those materials. \n186. \nThe July 31 filing replaced that approach. Section 18.8(b) establishes a fixed Credit Rate of $1.5 \nmillion per RBP UCAP MW, which PJM derived from approximately fifty percent of the gross \nfifteen-year contractual value. At the Initial RBP Target, that produces an aggregate LSE collateral \nrequirement of approximately $10.2 billion. The methodology therefore first appeared after the \nfinal stakeholder proposal and in the filing itself. \n187. \nThe change was not an increase in the amount of collateral produced by the methodology \npresented to stakeholders. The filed construct instead departed from the criteria PJM had identified \nfor determining LSE credit under its existing process. The $1.5 million per MW Credit Rate does \nnot depend on the credit quality of the LSE, a recalculation of Peak Market Activity or expected \nexposure, or the use of other mitigation tools to address an identified deficiency. It applies the \nsame fixed rate per megawatt before unsecured credit to every LSE subject to section 18.8(b), \nregardless of those considerations. \n188. \nBoth credit constructs were therefore moving late in the process, as were other elements of the \nproposal. The Joint Consumer Advocates recorded that PJM staff had revised substantial elements \nof the Reliability Backstop Procurement and Connect and Manage proposals at least three times in \nthe month preceding June 30, 2026, including on the evening before the original deadline for \nstakeholders to submit their own Stage 4 proposals. Id. at 2 n.6. The material change to seller \ncredit was disclosed in PJM’s final June 30 proposal, but there was no subsequent stakeholder \nmeeting at which it could be examined. The material change to LSE credit occurred after that final \nproposal and first appeared in the July 31 filing. At the same time, the stakeholder process had \nproduced other approaches to buyer credit that were substantively different from both PJM’s June \n30 approach and the methodology ultimately filed. Neither filed construct therefore received \nstakeholder examination in its final form, and the specific $1.5 million per MW LSE methodology \nwas not presented for stakeholder examination before the filing. \nE.  The filed methodologies departed from the exposure-based criteria considered during the process \n189. \nThe sequence is relevant to the substance of the methodologies ultimately filed. The approaches \npresented during the stakeholder process differed in important respects, but collectively they \nreflected several criteria ordinarily associated with managing credit exposure, and PJM’s own \nanalysis presented to the process applied those criteria directly. PJM’s June 30 proposal retained \ncredit evaluation, PMA recalculation and additional mitigation tools. The Coalition proposal \nexpressly called for emerging buyer-default exposure to be recognized early, funded continuously \nand contained within the responsible buyer, with the requirement adjusting over time. The Joint \nConsumer Advocates emphasized establishing the credit and collateral requirement before the \nprocurement occurred. \n190. \nPJM also presented an exposure-based analysis of the construct to the stakeholder process. In the \nMarch 4 Credit Overview, PJM stated that the Reliability Back-Stop Auction “introduces 15-year \ncontractual durations, which current PJM credit rules were not designed to mitigate,” and that \nAttachment Q “is primarily built for short-term settlement cycle and one-year capacity"},{"page":104,"startToken":45152,"endToken":45878,"text":"33 \n \nobligations.” It identified the resulting vulnerability as a “liquidity squeeze,” comprising a “sizable \ncollateral requirement,” constraints on liquidity, and “cost of capital.” It also stated that “[c]urrent \ntariff does not calculate liquidated damages.” \n191. \nThat presentation modeled the procurement as a fixed-for-float swap and estimated potential \nfuture exposure across the fifteen-year term. PJM defined potential future exposure as the \nmaximum exposure of economic value to a counterparty at a future point in time, at a stated \nconfidence level such as 95 percent. PJM did not present a flat profile. The estimate begins at zero, \nrises through the early Delivery Years, reaches a maximum within roughly the first third of the \nterm, and declines to zero at expiry. PJM stated the reason: “The value uncertainty goes higher \ndeeper into the future, while quantity exposure decreases as time goes by. This makes PFE peaks \nat 1/3 of life.” PJM’s estimate is denominated in millions of dollars per MW, and at no point \nacross the fifteen-year term does the exposure PJM depicted reach $1.2 million per MW. By \ncontrast, section 18.8 establishes a fixed $1.5 million per MW Credit Rate rather than a \nrequirement that follows that modeled exposure profile. The filed requirement therefore exceeds \nthe maximum exposure PJM itself modeled at every point in the term, and exceeds it by a wide \nmargin in the opening and closing years, when PJM’s own estimate approaches zero. PJM had \nbefore the stakeholder process an estimate of buyer-side exposure that varies across the term and \namortizes to zero. \n192. \nThe same presentation set out the credit profile of the population that would be required to post. \nAs described at ¶ 138 above, PJM identified 105 Load Serving Entities, of which 24 were \ninvestment grade and 81 sub-investment grade, with 46 percent below $5 million in tangible net \nworth and 30 percent below $1 million, and noted that investment-grade LSEs had “provided \ncorporate guarantees.” PJM therefore also had before the process a measurement of the credit \nquality of the entities on which the requirement would fall, and of the mitigation already in place. \n193. \nSection 18.8(b) as filed adopts none of those criteria for determining the initial LSE requirement. \nIt does not measure the LSE’s expected RBP settlement exposure; it does not establish the initial \nrequirement through Peak Market Activity or another exposure calculation; it does not vary the \nCredit Rate according to participant credit quality; and it does not establish a methodology for \ndetermining when additional or alternative mitigation is required. Instead, the initial requirement is \ndetermined by multiplying a fixed $1.5 million Credit Rate by the applicable quantity of RBP \nUCAP MW. Nor does the filed construct reflect the exposure profile PJM itself modeled, or the \ncredit quality PJM itself measured. Potential future exposure as PJM estimated it rises and then \ndeclines to zero across the term; the Credit Rate is a single figure that does not decline at all. And \nthe same $1.5 million per MW Credit Rate applies to each Load Serving Entity that receives an \nRBP obligation, without regard to the credit classification PJM assigned to that entity. \nF.  PJM considered adjustment mechanisms for sellers that were not included for load \n194. \nThe June Design Presentation also demonstrates that PJM considered mechanisms for adjusting \nseller collateral over the term. It presented a year-by-year seller credit requirement schedule, \nincluding a column labeled “RBP Credit Req. Desired (NPV),” defined as “collateral required if \nthe NPV is recalculated through out the contract term,” declining from approximately $21.4 \nmillion to $819,568 for the 100 MW commitment used in the example — approximately $214,000 \nto $8,196 per MW. PJM stated that the step down in collateral would be “contingent on credit \nvaluation per Att. Q,” and that the credit requirement “may be reduced to reflect the remaining \nyears while taking into account the credit quality of the Market Participant.” \n195. \nPJM therefore considered for sellers both periodic recalculation of the remaining obligation and \nadjustment for participant credit quality. Neither mechanism appears in the filed LSE construct. \nSection 18.8(b) provides no schedule for recalculation, no defined reduction methodology, and no \nunsecured credit allowance keyed to creditworthiness. As discussed in Section IX, it provides only \nthat the Credit Rate “may be reduced” by the Office of the Interconnection over time."},{"page":105,"startToken":45878,"endToken":46510,"text":"34 \n \nG.  PJM states that the filed proposal was not stakeholder-endorsed \n196. \nPJM describes the status of the proposal expressly. Distinguishing NRG Power Marketing, LLC v. \nFERC in its transmittal, PJM states that “the proposal submitted in this filing was authorized by \nthe PJM Board and was not the result of a stakeholder-endorsed proposal.” \n197. \nThe absence of stakeholder endorsement does not itself determine whether a credit requirement is \nreasonable. The Commission has rejected a credit provision that had been developed through an \nRTO stakeholder process and approved by its Board, holding that it “cannot accept any proposal \nfrom the stakeholder process that is unduly burdensome or unduly discriminatory.” Sw. Power \nPool, Inc., 126 FERC ¶ 61,153, at PP 20-21 (2009) (quoting Sw. Power Pool, Inc., 114 FERC ¶ \n61,222, at P 19 (2006)). The Commission rejected the provision as “not consistent with or superior \nto the pro forma OATT” and as potentially “so stringent as to unnecessarily inhibit access to the \nmarketplace,” notwithstanding that the revisions were the product of the SPP stakeholder process \nand had been approved by the SPP Board of Directors. Id. The relevance of the process here is \nnarrower. Stakeholder review provides an opportunity for the entities subject to a credit \nrequirement to identify its operational, financing and liquidity consequences and to test the \nmethodology used to measure the exposure before it is implemented. \nH.  Conclusion \n198. \nIn my opinion, neither of the credit constructs ultimately filed received stakeholder examination in \nits final form. Seller credit was materially revised in PJM’s final June 30 proposal, after which no \nfurther stakeholder meetings were held. The fixed $1.5 million per MW LSE requirement was not \nincluded in that final proposal and first appeared in the July 31 filing. \n199. \nThis is significant because the stakeholder process had not ignored credit risk. PJM and other \nstakeholders had proposed different means of addressing it. Those approaches included credit \nevaluation, recalculation or continuing measurement of exposure, adjustment of the requirement \nover time, additional mitigation when needed, and establishment of buyer credit before \nprocurement. The filed LSE methodology did not select among those approaches. It instead \nestablished a fixed Credit Rate derived from the gross contractual value and omitted the exposure-\nbased criteria that had been identified during the stakeholder process. \n200. \nFor a credit construct of this magnitude, those differences are material. The stakeholder process \nprovided no opportunity to examine the $1.5 million per MW methodology against the matters \naddressed in this affidavit: its relationship to measured exposure; the quantity to which the Credit \nRate applies; the availability and cost of permitted collateral; the mechanism by which collateral is \nreduced as exposure declines; the financial capacity of the entities required to post it; the \nconsequences of a simultaneous collateral call; and the allocation of loss following default. The \nfiled $1.5 million per MW methodology therefore was not subjected to stakeholder examination \nagainst those considerations before the filing. \nXIV.  CONCLUSION \n201. \nI believe the matters set out above point to a straightforward characterization of what section 18.8 \ndoes. PJM took the gross contractual value of a fifteen-year commitment, halved it, and called the \nresult collateral. Nearly every difficulty addressed in this affidavit follows from that single step. \n202. \nCollateral, as PJM administers it everywhere else in its markets, requires three things: an identified \nposition that would have to be replaced on default, a price at which it would be replaced, and a \nperiod over which the exposure is held before replacement is complete. Attachment Q is built on \nthose elements. RPM auction credit, FTR credit and Peak Market Activity are each measured \nagainst them, recalculated as conditions change, and released as the exposure declines. Section \n18.8 identifies none of the three. It states a rate and a date."},{"page":106,"startToken":46510,"endToken":47278,"text":"35 \n \n203. \nThe seller requirement confirms the diagnosis rather than qualifying it. Both sides of the RBP face \nthe same quantity and the same two prices. The obligation is denominated in the same RBP UCAP \nMW, and the amount that moves between them in any Delivery Year is the difference between the \nRBP price and the RPM clearing price for that year. The economic consequence being analyzed on \neach side therefore depends on the same two prices and the same committed quantity. Symmetry \nin the exposure does not produce symmetry in the collateral. Section 18.8(a) requires a seller to \npost approximately $121,545 per MW, while section 18.8(b) requires load to post $1.5 million per \nMW against the same quantity and the same prices — roughly twelve times as much. Measured \nagainst the two Delivery Years whose differential is known within twenty days of commitment, \nthe seller posts less than the exposure and load posts about nine times it. As set out in Section VII, \nthe two requirements also imply contradictory RPM price paths: the seller figure is adequate only \nif RPM clears at or above approximately $532.80/MW-day on average, and above approximately \n$564.12 across the thirteen years that remain unpriced, while the load figure corresponds to the \nexposure only if RPM clears at or below approximately $281.03. No single price path satisfies \nboth. Two requirements derived from one measured exposure would not diverge in this way. \nThese did not begin from one. \n204. \nThe timing of the load requirement is the clearest demonstration that it is not calibrated to \nexposure. Commitments bind when results post on December 2, 2026. The 2028/2029 Base \nResidual Auction has already cleared at $325.00/MW-day, so the first Delivery Year's exposure is \nknown at the moment the commitment binds. The 2029/2030 results post on December 22, 2026, \ntwenty days later. Within three weeks of commitment, therefore, two Delivery Years are priced, \nand on the adjusted target of approximately 6,000 MW the exposure they represent is \napproximately $1.0 billion, taking the 2029/2030 year at the $333.44 proxy discussed above. \nAgainst that quantified exposure PJM requires no collateral at all for approximately seventeen \nmonths, until roughly April 17, 2028. It instead requires approximately $9.1 billion on the same \ntarget against an exposure it has never quantified, beginning at the point when a substantial part of \nthe position has become knowable and is no longer in doubt. A requirement that is absent where \nthe exposure is measurable and largest where it is unmeasured is not a risk instrument. \n205. \nThe remaining difficulties are consequences rather than independent defects. Because the \nrequirement is not tied to a measured exposure, there is no quantity against which to apply it, and \nthe tariff supplies three that do not agree. Because the filed methodology does not measure the \nexposure, it provides no exposure-based basis for reducing the requirement as that exposure \ndeclines, and section 18.8(b)(i)(A) provides only that the Credit Rate “may be reduced.” Because \nthe amount is not sized to a risk, the cost of carrying it — approximately $102 million to $307 \nmillion a year against approximately $573 million billed to load in the first Delivery Year — \nappears in no figure PJM has presented and is recovered by no provision of the tariff. And because \nit falls on a single date, in two instruments, drawn from the same limited group of issuing \ninstitutions, without regard to the balance sheet of the entity obligated to post, it creates the \ncorrelated exposure that a credit policy exists to prevent. \n206. \nThe point I made at the outset holds at the end of it. A security deposit is sized to the damage a \ntenant might do, not to the rent due over the life of the lease. A landlord who demanded six \nmonths’ rent on a twelve-month lease would be asked what damage he expected, and would be \nexpected to answer. PJM has not identified the damage. \n207. \nNone of this suggests that the RBP requires no credit support. It plainly does. Section 18.9(a) \nsocializes a defaulted RBP Charge pro rata across the remaining Load Serving Entities, and under \nOperating Agreement, section 15.2.2 the residual reaches Members holding no allocation at all. A \nrequirement set too low leaves native load bearing the cost of another party’s default. That is the \nharm collateral exists to prevent, and it is the harm the Commission identified in the Policy \nStatement on Electric Creditworthiness as the function of collateral to avoid."},{"page":107,"startToken":47278,"endToken":47746,"text":"36 \n \n208. \nBut the error runs in both directions, and that is what makes the matter difficult rather than simple. \nA requirement set too high inhibits access to the market the RTO was formed to operate, and \nwhere it is large enough relative to the balance sheets on which it falls, it creates the systemic \nexposure it was meant to prevent. The Commission has held that “the role of an RTO is to balance \nthe competing goals of minimizing risk to non-defaulting market participants while, at the same \ntime, ensuring that the credit or collateral requirements are not so stringent that they unnecessarily \ninhibit access to the marketplace,” and has rejected a credit provision on that ground \nnotwithstanding that it emerged from an RTO stakeholder process and was approved by that \nRTO’s board. Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at PP 19, 21 (2009). The NOVEC zone \nillustrates that the second error is not hypothetical here: an allocation of approximately $1.95 \nbillion falls on a distribution cooperative reporting total assets of approximately $1.716 billion and \ncash and temporary investments of approximately $243.2 million. \n209. \nThat two-sided character bears directly on what can be done with the filing. The appropriate \nrequirement cannot be determined from the filed formula alone. It requires the exposure to be \nmeasured — the position, the replacement price, the close-out horizon — and it requires the \nresulting number to be tested against the financial capacity of the entities that would post it. That \nsecond step cannot be performed on this record. The balance sheets of the obligated Load Serving \nEntities are not before the Commission. Neither is the letter of credit capacity available to them, \nthe cost at which they could raise cash, or the effect of a simultaneous call on their existing \nfacilities. Those are the facts on which any sound construct depends, and they reside with the \nparties rather than with PJM or the Commission. \n210. \nThe stakeholder process ordinarily provides an opportunity for that examination. As set out in \nSection XIII, credit and collateral were considered during that process, but the specific $1.5 \nmillion per MW methodology first appeared in the July 31 filing and therefore was not subjected \nto stakeholder examination before filing. It was not tested there against the elements set out in \nSection III, against the quantity to which it applies, against the cost of the permitted forms of \ncollateral, or against the capacity of the entities on which it falls. In my opinion the deficiency in \nthe filed construct is not a matter of calibration that could be corrected by adjusting the rate. It is \nthat the analysis on which any rate would rest was not performed, and the present record does not \ncontain the participant-specific financial and liquidity information needed to perform it."},{"page":108,"startToken":47746,"endToken":47765,"text":"ATTACHMENTS TO THE AFFIDAVIT OF CARL F. COSCIA, Ph.D. \nPJM Interconnection, L.L.C., FERC Docket No. ER26-3380-000"},{"page":109,"startToken":47765,"endToken":48280,"text":"Attachment A — PJM Collateral Held and Collateral Intensity \nReferenced at ¶ 65. \nSource and method. PJM reports credit and collateral metrics to the Risk Management Committee. Materials are public at pjm.com/committees-and-\ngroups/committees/rmc, filterable by year. \nThe document title changed during the period covered. Through 2024 and 2025 the deck was posted as \"Informational Only — Key Risk Metrics,\" with the file named \nfor the meeting date. Beginning in 2026 it is posted as \"Informational Only — Credit Metrics — [Month] [Year],\" named for the month of data rather than the meeting. \nThe deck's own title slide reads \"Credit Risk Metrics\" throughout. \nThe series is monthly, but the RMC does not meet every month, and PJM posts any intervening months at the next meeting. At the August 18, 2026 meeting PJM \nposted four decks at once, covering May, June, July and August 2026. The table below is therefore indexed to the month of the data, with the meeting at which each \ndeck was posted recorded separately. \nTotal collateral held, and its division among cash, letters of credit and surety bonds, appears on slide 4 (\"Collateral Summary (Total PJM)\"). Total Unsecured Credit \nAllowance appears on slide 2 (\"Full Portfolio Metrics\"). Letter of credit issuer concentration appears on slides 4 and 5. Each deck reports as of a date shortly before the \nmeeting or, from 2026, as of the month named in the title. \nRMC meeting dates in the period: 2024 — Jan 23, Feb 29, Mar 19, Apr 24, May 21, Jun 26, Jul 23, Aug 20, Sep 24, Oct 29, Nov 25, Dec 17. 2025 — Feb 19, Mar 18, Apr \n22, May 20, Jun 17, Aug 19, Sep 26, Oct 22, Dec 2. 2026 — Feb 18, Mar 24, Apr 21, Aug 18. \nWhere a month's total is stated on the slide, the stated figure is used; where it is not, the value is read from the chart on the same slide and calibrated against the \npublished figures appearing on it. Figures read from the chart rather than stated are marked with an asterisk. Figures are approximate and rounded to the nearest $0.1 \nbillion. \nObservations relied on. The affidavit relies on the observations below rather than on the full monthly record. Annual figures are averages of the month-end balances \nreported in the series; month-end figures are as printed on slide 4 of the deck for that month. \nObservation \nAs of \nSource deck \nTotal ($B) \nCash ($B) \nLC ($B) \nSurety ($B) \nIllustrative mid-series \nobservation \nJun 27, 2024 \nRMC Jul 23, 2024 \n5.97 \n2.23 \n3.47 \n0.271 \nCY2024 average \nmonthly, 2024 \nseries \n6.2 \n \n \n \nCY2025 average \nmonthly, 2025 \nseries \n7.0 \n \n \n \nMonth-end \nJan 29, 2026 \nRMC Feb 18, 2026 \n10.24 \n3.23 \n6.60 \n0.407 \nMaximum recorded — Winter \nStorm Fern \nFeb 26, 2026 \nRMC Mar 24, 2026 \n13.12 \n3.82 \n8.76 \n0.531 \nMonth-end \nMar 26, 2026 \nRMC Apr 21, 2026 \n9.51 \n2.67 \n6.30 \n0.538 \nMost recent before filing \nJul 30, 2026 \nCredit Metrics — Aug 2026, RMC Aug 18, \n2026 \n10.9 \n3.4 \n6.87 \n0.606"},{"page":110,"startToken":48280,"endToken":48775,"text":"Components reconcile to the printed totals in every month for which they are reported. \nThe balance is volatile and event-driven. Across three consecutive month-ends the total moved from $10.24 billion to $13.12 billion and back to $9.51 billion, a range \nof approximately 38 percent. PJM attributes the increase to a single weather event, stating on the February slide that \"[h]igher credit requirements related to Winter \nStorm Fern led to a substantial increase in collateral.\" The chart on that slide shows the balance rising from approximately $6.8 billion in September 2025. PJM's \ncollateral requirement across its markets therefore responds to measured changes in exposure and falls when the exposure recedes. The proposed RBP Credit Rate is \nfixed at $1.5 million per RBP UCAP MW and does not vary with any measured exposure at any point in the fifteen-year term. \nConsistency with the audited statements. PJM's audited financial statements disclose credit deposits of $2.4 billion and letters of credit of approximately $4.5 billion at \nDecember 31, 2025, totalling approximately $6.9 billion excluding surety bonds. The average of the month-end balances reported to the Risk Management Committee \nfor 2025 is approximately $7.0 billion. The two are consistent, and the reported series is bracketed at the year end by an audited disclosure. \nThe maximum is a stress observation. The maximum balance PJM has recorded across all of its markets and all classes of participant, $13.12 billion, was reached under \nstorm conditions and had receded to $9.51 billion within a month. The proposed RBP requirement of approximately $10.2 billion at the Initial RBP Target, or \napproximately $9.1 billion at the illustrative Final RBP Target, is of the same order as the entire collateral balance PJM held from all of its approximately 1,116 members \nacross every market it operates, and would be a standing requirement rather than a response to an event. \nCollateral intensity \nNumerator throughout: the average of the month-end total collateral balances reported to the Risk Management Committee over the period. Using an average rather \nthan a point-in-time balance places the numerator and the denominator on the same basis, the denominator being a full-year flow. Denominators as noted per row. \nThe collateral figures and the resulting intensities are approximations. The numerator for the twelve months ended June 2026 is the average of the month-end balances \nreported for 2026 to date rather than for the full twelve-month window, the month-end balances for the second half of 2025 not being separately stated in the decks \nobtained. \nMeasure \nPeriod \nDenominator \nDenominator source \nCollateral ($B) \nIntensity \nSettlements processed \nCY 2024 \n$51,713M \nPJM 2025 Financial Report, \nBillings for Services \n6.2 \n12.0% \nSettlements processed \nCY 2025 \n$80,479M \nPJM 2025 Financial Report, \nBillings for Services \n7.0 \n8.7% \nTotal cost of wholesale \npower \nCY 2025 \n$66.78B \nIndependent Market \nMonitor, Market Monitor \nReport, PJM Members \nCommittee (July 27, 2026), \nat 11 (derived) \n7.0 \n10.5%"},{"page":111,"startToken":48775,"endToken":49273,"text":"Measure \nPeriod \nDenominator \nDenominator source \nCollateral ($B) \nIntensity \nTotal cost of wholesale \npower \n12 mo. ended Jun 2026 \n$83.05B \nIndependent Market \nMonitor, Market Monitor \nReport, PJM Members \nCommittee (July 27, 2026), \nat 11 and 15 (derived) \n10.7 \n12.9% \n \nPJM identifies settlements processed under the Tariff, Operating Agreement and Reliability Assurance Agreement as a non-GAAP measure. The 2026 period is not \ncovered by an annual report and the denominator for that row is therefore taken from the Independent Market Monitor's report. Band applied in the affidavit: \napproximately 9% to 13% of annual market activity. \nIndependent Market Monitor figures. The Market Monitor does not publish a calendar-year or trailing-twelve-month total; both figures above are derived from the \nreported year-to-date and monthly series. Monitoring Analytics, LLC, Market Monitor Report, presented to the PJM Members Committee Information Webinar (July 27, \n2026), at 11 (“Total Cost of Wholesale Power – YTD 2025/2026,” category table: January–June 2025 total cost $30,071M against 394,842 GWh of real-time load; \nJanuary–June 2026 total cost $46,340M against 404,710 GWh) and at 15 (“Total Cost of Wholesale Power – July 2025 through June 2026 Monthly,” Total Cost and Total \nReal Time Load rows), available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20260727-web/item-02---marketing-monitoring-\nreport---presentation.pdf. Calendar 2025 is the January–June 2025 column at 11 plus the July through December 2025 monthly columns at 15 ($36.71 billion against \n416,051 GWh), giving $66.78 billion against 810,893 GWh, or $82.35 per MWh. The twelve months ended June 2026 is the July through December 2025 monthly \ncolumns at 15 plus the January–June 2026 column at 11, giving $83.05 billion against 820,761 GWh, or $101.19 per MWh. The monthly columns reconcile exactly to the \nreported year-to-date figures. Real-time load is the denominator the Market Monitor itself applies: $46,340 million divided by 404,710 GWh is $114.50 per MWh, the \ntotal reported at 11. \nCollateral did not scale with the market. Settlements processed rose 55.6 percent between 2024 and 2025, from $51.713 billion to $80.479 billion. Collateral intensity \nover the same period fell from approximately 12.0 percent to approximately 8.7 percent. \nA comparator from the audited statements. At December 31, 2025 the estimated fair value of the FTR portfolio under PJM's mark-to-auction model was $2.4 billion, \nagainst which PJM held $2.9 billion of collateral — approximately 121 percent of the marked value of the position secured. The proposed RBP requirement of \napproximately $10.2 billion stands against approximately $573 million billed to load in the first Delivery Year, or approximately 1,790 percent. \nPeak balance. The maximum total collateral balance recorded across the series is approximately $13.1 billion, held against every PJM market and every class of \nparticipant. The proposed RBP requirement of approximately $10.2 billion would be owed by one class of participant, in respect of one product, on one date."},{"page":112,"startToken":49273,"endToken":49673,"text":"Attachment B — LSE Collateral Requirement by Electric Distributor Zone/Area \nReferenced at ¶¶ 68 and 137. \nInitial RBP Target of 6,831.3 UCAP MW allocated on the pro-rata shares derived from the difference between Total Adjustments to Summer Peak Load for summer 2028 \nand summer 2026 (2026 Load Forecast, Table B-9b), at the proposed Credit Rate of $1.5 million per RBP UCAP MW. \nZone \nZone/Area \n2026 (MW) \n2028 (MW) \nDifference \n(MW) \nShare \nAllocated \nMW \nCollateral \n($B) \nBGE \nBGE \n18.0 \n43.0 \n25.0 \n0.28% \n18.9 \n0.028 \nPECO \nPECO \n17.0 \n281.0 \n264.0 \n2.92% \n199.6 \n0.299 \nPL \nPPL \n189.0 \n1,274.0 \n1,085.0 \n12.01% \n820.5 \n1.231 \nPS \nPSEG \n308.0 \n628.0 \n320.0 \n3.54% \n242.0 \n0.363 \nAEP \nAEPOHIO \n1,743.8 \n3,763.0 \n2,019.2 \n22.35% \n1,527.0 \n2.291 \nAPS \nPE \n165.0 \n319.0 \n154.0 \n1.70% \n116.5 \n0.175 \nATSI \nPP \n0.0 \n17.8 \n17.8 \n0.20% \n13.5 \n0.020 \nATSI \nOHIO \n132.0 \n281.2 \n149.2 \n1.65% \n112.8 \n0.169 \nCOMED \nCOMED \n885.0 \n2,058.0 \n1,173.0 \n12.99% \n887.1 \n1.331 \nDAYTON \nDAY \n0.0 \n277.0 \n277.0 \n3.07% \n209.5 \n0.314 \nDOM \nDOM \n4,386.2 \n5,368.8 \n982.6 \n10.88% \n743.1 \n1.115 \nDOM \nNVEC \n1,995.4 \n3,717.8 \n1,722.4 \n19.07% \n1,302.6 \n1.954 \nDOM \nODEC \n384.9 \n555.1 \n170.2 \n1.88% \n128.7 \n0.193 \nDOM \nREC \n299.5 \n973.3 \n673.8 \n7.46% \n509.6 \n0.764 \nTotal \nRTO \n10,523.8 \n19,557.0 \n9,033.2 \n100.00% \n6,831.3 \n10.247 \n \nFive zone/areas each carry an obligation exceeding $1 billion — AEPOHIO, NVEC, COMED, PPL and DOM — together approximately $7.9 billion, or 77.4 percent of the \ninitial requirement. \nNote. PJM's Reliability Backstop Procurement Design presentation of June 10–11, 2026, at slide 11, states the REC difference as 167.8 MW. The difference between the \nvalues in the adjoining columns is 673.8 MW, and PJM's stated share for REC of 7.5 percent is consistent with 673.8 MW rather than with 167.8 MW. The figure above \nuses 673.8 MW."},{"page":113,"startToken":49673,"endToken":49792,"text":"Attachment C — Cost of Funds Across the Rating Distribution \nReferenced at ¶ 130. \nICE BofA index effective yields as of August 12, 2026. \nRating tier \nEffective yield \nBBB (lowest investment grade) \n5.58% \nBB (highest non-investment grade) \n5.98% \nSingle-B \n7.25% \nCCC and lower \n14.51% \n \nBlended cost, 77 percent investment grade \nScenario \nIG portion \nRemainder \nImplied blended rate \n1 \n77% at BBB \n23% at BB \n5.67% \n2 \n77% at BBB \n23% at single-B \n5.96% \n3 \n77% at BBB \n23% at CCC and lower \n7.63% \n \nDistribution required to reach the 9.5% discount rate PJM applied \nAssumption for the remainder \nShare required at CCC and lower \nRemainder at BBB \n43.9% \nRemainder at single-B \n31.0%"},{"page":114,"startToken":49792,"endToken":50099,"text":"Attachment D — Load Factor Sensitivity, NVEC Zone/Area \nReferenced at ¶¶ 162 and 164. \nEnergy sales of approximately 12.2 billion kWh for the year ended December 31, 2024; data centers taken at 65 percent of energy sales; first-Delivery-Year RBP Charge \nallocated to the zone of approximately $109 million at the 2028/2029 clearing price of $325.00/MW-day against an RBP price of $555.00/MW-day. Class peaks are \ncomputed as class energy divided by the product of 8,760 hours and the stated load factor. Uniform energy-basis charge: $8.93 per MWh. \nNon-DC load factor \nDC load factor \nNon-DC class peak (MW) \nDC class peak \n(MW) \nNon-DC share of \nsummed class \npeaks \nNon-DC $/MWh \nDC $/MWh \n40% \n85% \n1,219 \n1,065 \n53.4% \n13.62 \n6.41 \n40% \n90% \n1,219 \n1,006 \n54.8% \n13.98 \n6.22 \n40% \n95% \n1,219 \n953 \n56.1% \n14.33 \n6.03 \n45% \n85% \n1,083 \n1,065 \n50.4% \n12.87 \n6.81 \n45% \n90% \n1,083 \n1,006 \n51.9% \n13.24 \n6.62 \n45% \n95% \n1,083 \n953 \n53.2% \n13.58 \n6.43 \n50% \n85% \n975 \n1,065 \n47.8% \n12.20 \n7.18 \n50% \n90% \n975 \n1,006 \n49.2% \n12.56 \n6.98 \n50% \n95% \n975 \n953 \n50.6% \n12.91 \n6.79 \n55% \n85% \n886 \n1,065 \n45.4% \n11.59 \n7.50 \n55% \n90% \n886 \n1,006 \n46.8% \n11.96 \n7.31 \n55% \n95% \n886 \n953 \n48.2% \n12.30 \n7.12 \n \nAcross every cell, the non-data-center class bears a higher charge per megawatt-hour than the data center class, and a higher charge than the uniform energy-basis \nfigure. The disparity is narrowest at the combination least favorable to the conclusion — non-DC at 55 percent and DC at 85 percent — and is approximately 1.55 to 1 \neven there."},{"page":115,"startToken":50099,"endToken":50490,"text":"Attachment E — Derivation of the Implied Average RPM Prices \nReferenced at ¶¶ 82, 83, 94 and 95. \nRBP price of $555.00/MW-day. Annual differential per MW equals (555 − P) × 365, where P is the RPM clearing price in $/MW-day. Undiscounted, consistent with ¶ 79. \nLSE side. The $1.5 million Credit Rate corresponds to the cumulative fifteen-year contract-for-differences exposure only if: \n(555 − P) × 365 × 15 = $1,500,000 → 555 − P = $273.97 → P = $281.03/MW-day \nSeller side, full term. Seller collateral of $121,545 per MW equals 0.2 × $555 × 365 × 3. It covers the cumulative fifteen-year exposure only if: \n(555 − P) × 365 × 15 = $121,545 → 555 − P = $22.20 → P = $532.80/MW-day \nSeller side, remaining thirteen years. The first two Delivery Years are priced or proxied: 2028/2029 at $325.00 (differential $230.00/MW-day, $83,950 per MW) and \n2029/2030 proxied at $333.44 (differential $221.56/MW-day, $80,869 per MW), a two-year total of $164,819 against $121,545 posted, a deficit of $43,274. Recovering \nthat deficit requires the contract for differences to reverse across the remaining thirteen Delivery Years: \n(P − 555) × 365 × 13 = $43,274 → P − 555 = $9.12 → P = $564.12/MW-day \nThe two requirements are consistent only if the average RPM clearing price is simultaneously at or below $281.03 and at or above $564.12. The difference between the \nimplied prices is $283.09/MW-day, or $251.77 measured against the full-term seller figure of $532.80. \n \nExposure at the uncapped price PJM simulated. PJM has estimated that, absent the price collar, the 2028/2029 Base Residual Auction would have cleared at \n$554.72/MW-day RTO-wide. Against the RBP price of $555.00, the annual differential at that clearing price is $0.28/MW-day: \n(555 − 554.72) × 365 × 15 = $1,533 per MW, against $1,500,000 of collateral. \nBlended path. Taking the two Delivery Years that are priced or proxied at their stated values and the remaining thirteen at the uncapped simulation: \nDY 2028/2029 at $325.00: $83,950 per MW \nDY 2029/2030 at $333.44: $80,869 per MW \nDY 2030/2031 through 2042/2043 at $554.72: $0.28 × 365 × 13 = $1,329 per MW \nFifteen-year total: $166,148 per MW. Collateral of $1,500,000 per MW is approximately 9.0 times that amount."},{"page":116,"startToken":50490,"endToken":50545,"text":"Locational note. PJM’s simulation places the uncapped ComEd Locational Deliverability Area price at $776.69/MW-day, which exceeds the RBP price by $221.69. At any \nclearing price above $555.00 the contract for differences reverses and the payment runs from the resource to load, so no exposure arises for load in that Delivery Year."},{"page":117,"startToken":50545,"endToken":50791,"text":"Table 1 — NVEC Zone/Area Obligation Against Reported Financial Position \nReferenced at ¶¶ 140 to 142. \nThe dollar amounts, ratios and multiples in the tables below are approximations. \nItem \nAmount \nNVEC initial allocation \n1,302.6 UCAP MW \nShare of Initial RBP Target \n19.07% \nCollateral at $1.5 million per MW \n$1.954 billion \nTotal assets (FY2025) \n$1.716 billion \nTotal equities and margins (FY2025) \n$919.7 million \nTotal long-term debt (FY2025) \n$69.2 million \nCash collateral posted to PJM (FY2025) \n$34.4 million \nPatronage capital and margins (FY2025) \n$44.7 million \nAnnual interest expense (FY2025) \n$0.8 million \nPeak demand, coincident (FY2025) \n2,360 MW \nEnergy sales (FY2025) \n14.649 billion kWh \nCash and temporary investments (FY2025) \n$243.2 million \nTotal current and accrued assets (FY2025) \n$575.4 million \nPatronage capital on the books (FY2025) \n$824.0 million \nCapital credits retired (FY2025) \n$17.9 million \nCost of purchased power (FY2025) \n$1,310.1 million \nConsumers served (FY2025) \n184,104 \n \nRatio \nMultiple \nCollateral to total assets \n1.14× \nCollateral to equities and margins \n2.12× \nCollateral to total long-term debt \n28× \nCollateral to cash collateral posted to PJM \n57× \nAllocated MW to system peak demand \n55% \nCollateral to cash and temporary investments \n8.0× \nCollateral to total current and accrued assets \n3.4× \nCollateral to patronage capital on the books \n2.4× \nCollateral to FY2025 operating revenue \n132% \nCollateral per consumer served \n$10,614 \n \nAnnual carrying cost of the required collateral \nCosts and multiples are approximations."},{"page":118,"startToken":50791,"endToken":51006,"text":"Rate \nAnnual cost \nAs a multiple of FY2025 patronage capital \nand operating margins \nAs a multiple of FY2025 interest expense \n100 bp \n$19.5 million \n0.94× \n25× \n150 bp \n$29.3 million \n1.41× \n37× \n200 bp \n$39.1 million \n1.88× \n50× \n300 bp \n$58.6 million \n2.81× \n75× \nSource for the cooperative’s financial and operating figures: Northern Virginia Electric Cooperative, Financial and Operating Report Electric Distribution, U.S. Department \nof Agriculture, Rural Utilities Service, Borrower Designation VA0055, period ended December 2025 (prepared with audited data). Total assets, Part C line 29; total \nmargins and equities, Part C line 36; patronage capital, Part C line 31; total long-term debt, Part C line 43; cash and temporary investments, Part C lines 15 and 18; total \ncurrent and accrued assets, Part C line 26; interest expense, Part A lines 16 and 18; patronage capital and margins, Part A line 29; cost of purchased power, Part A line 3; \ncash collateral posted to PJM, Part Q Section I item 4; capital credits retired, Part I; consumers served, Part O line 10; energy sales, Part O line 11; coincident peak, Part O \nline 20. The report is prepared on the unconsolidated regulatory basis of the Rural Utilities Service and is not consolidated with the cooperative’s subsidiaries."},{"page":119,"startToken":51006,"endToken":51041,"text":"VERIFICATION OF AFFIDAVIT\nPursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the \nforegoing Affidavit is true and correct.\nExecuted August 21, 2026.\nBy: _____________________________\n       Carl F. Coscia"},{"page":120,"startToken":51041,"endToken":51089,"text":"Certificate of Service \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, DC this 21st day of August, 2026. \n/s/ Kelly A. Cuthbertson \n \nKelly A. Cuthbertson"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":362,"startToken":0,"endToken":341},{"p":2,"at":362,"title":"I. Background","method":"printed heading","endPage":2,"endAt":378,"startToken":341,"endToken":343},{"p":2,"at":378,"title":"A. RBP Overview","method":"printed heading","endPage":8,"endAt":730,"startToken":343,"endToken":2331},{"p":8,"at":730,"title":"A. The Stakeholder Process and Coalition RBP Proposal","method":"printed heading","endPage":10,"endAt":979,"startToken":2331,"endToken":3162},{"p":10,"at":979,"title":"II. Protest","method":"printed heading","endPage":15,"endAt":4,"startToken":3162,"endToken":4748},{"p":15,"at":4,"title":"A. The PJM RBP Proposal is Not Just and Reasonable.","method":"printed heading","endPage":35,"endAt":4,"startToken":4748,"endToken":11116},{"p":35,"at":4,"title":"B. The Role of Electric Distributors, States, and RERRAs in PJM’s RBP","method":"printed heading","endPage":41,"endAt":1210,"startToken":11116,"endToken":13284},{"p":41,"at":1210,"title":"C. PJM’s RBP Proposal is Inconsistent with the Boundaries of Federal and State","method":"printed heading","endPage":45,"endAt":760,"startToken":13284,"endToken":14527},{"p":45,"at":760,"title":"D. PJM’s Proposed FRR Exemption and Treatment of RPM Capacity Market","method":"printed heading","endPage":47,"endAt":307,"startToken":14527,"endToken":15208},{"p":47,"at":307,"title":"E. PJM’s Proposed FRR Exemption Creates Ambiguity and Disadvantages","method":"printed heading","endPage":48,"endAt":1077,"startToken":15208,"endToken":15695},{"p":48,"at":1077,"title":"F. PJM’s Proposal Is Inconsistent with Ratepayer Protection and the","method":"printed heading","endPage":50,"endAt":4,"startToken":15695,"endToken":16103},{"p":50,"at":4,"title":"III. Conclusion","method":"printed heading","endPage":52,"endAt":300,"startToken":16103,"endToken":16327},{"p":52,"at":300,"title":"I. Introduction and Qualifications","method":"printed heading","endPage":53,"endAt":577,"startToken":16327,"endToken":16689},{"p":53,"at":577,"title":"II. Summary of Opinions","method":"printed heading","endPage":53,"endAt":2300,"startToken":16689,"endToken":16925},{"p":53,"at":2300,"title":"III. Background","method":"printed heading","endPage":54,"endAt":1894,"startToken":16925,"endToken":17269},{"p":54,"at":1894,"title":"IV. Reliability Neutrality and Large-Load Growth","method":"printed heading","endPage":56,"endAt":220,"startToken":17269,"endToken":17929},{"p":56,"at":220,"title":"V. Cost Causation and Section 205 Burden","method":"printed heading","endPage":57,"endAt":2064,"startToken":17929,"endToken":18661},{"p":57,"at":2064,"title":"VI. Cost and Risk Allocation Effects Created by the RBP","method":"printed heading","endPage":60,"endAt":2125,"startToken":18661,"endToken":20037},{"p":60,"at":2125,"title":"VII. Effects on LSEs, Electric Distributors, and States","method":"printed heading","endPage":63,"endAt":994,"startToken":20037,"endToken":21275},{"p":63,"at":994,"title":"VIII. Hedgeability, Traceability, and Collateral Risk","method":"printed heading","endPage":66,"endAt":215,"startToken":21275,"endToken":22515},{"p":66,"at":215,"title":"IX. FRR and RPM Self-Supply Asymmetry","method":"printed heading","endPage":67,"endAt":1741,"startToken":22515,"endToken":23160},{"p":67,"at":1741,"title":"X. Application to EKPC","method":"printed heading","endPage":68,"endAt":1810,"startToken":23160,"endToken":23622},{"p":68,"at":1810,"title":"XI. Conclusion","method":"printed heading","endPage":72,"endAt":201,"startToken":23622,"endToken":24023},{"p":72,"at":201,"title":"I. INTRODUCTION AND QUALIFICATIONS","method":"printed heading","endPage":73,"endAt":5,"startToken":24023,"endToken":24592},{"p":73,"at":5,"title":"II. PURPOSE AND SUMMARY OF OPINIONS","method":"printed heading","endPage":74,"endAt":2322,"startToken":24592,"endToken":25620},{"p":74,"at":2322,"title":"III. THE ROLE OF COLLATERAL","method":"printed heading","endPage":76,"endAt":3793,"startToken":25620,"endToken":27057},{"p":76,"at":3793,"title":"IV. PARTIES AND EXPOSURES UNDER THE RBP","method":"printed heading","endPage":77,"endAt":203,"startToken":27057,"endToken":27178},{"p":77,"at":203,"title":"A. Parties with obligations","method":"printed heading","endPage":77,"endAt":1769,"startToken":27178,"endToken":27429},{"p":77,"at":1769,"title":"B. Parties without obligations","method":"printed heading","endPage":77,"endAt":2029,"startToken":27429,"endToken":27466},{"p":77,"at":2029,"title":"C. The residual tier","method":"printed heading","endPage":77,"endAt":2319,"startToken":27466,"endToken":27515},{"p":77,"at":2319,"title":"D. How a default travels","method":"printed heading","endPage":78,"endAt":5,"startToken":27515,"endToken":27732},{"p":78,"at":5,"title":"E. Which party is harmed by which failure","method":"printed heading","endPage":78,"endAt":3580,"startToken":27732,"endToken":28330},{"p":78,"at":3580,"title":"F. Application to EKPC","method":"printed heading","endPage":79,"endAt":5,"startToken":28330,"endToken":28467},{"p":79,"at":5,"title":"V. THE PROPOSED CREDIT CONSTRUCT","method":"printed heading","endPage":79,"endAt":351,"startToken":28467,"endToken":28523},{"p":79,"at":351,"title":"A. Seller collateral","method":"printed heading","endPage":79,"endAt":874,"startToken":28523,"endToken":28613},{"p":79,"at":874,"title":"B. The cumulative buyer requirement","method":"printed heading","endPage":79,"endAt":1866,"startToken":28613,"endToken":28776},{"p":79,"at":1866,"title":"C. The individual LSE posting","method":"printed heading","endPage":79,"endAt":3120,"startToken":28776,"endToken":28986},{"p":79,"at":3120,"title":"D. Acceptable forms","method":"printed heading","endPage":80,"endAt":5,"startToken":28986,"endToken":29054},{"p":80,"at":5,"title":"E. PJM’s stated derivation","method":"printed heading","endPage":80,"endAt":2749,"startToken":29054,"endToken":29495},{"p":80,"at":2749,"title":"VI. OPINION 1 — The magnitude has no precedent in PJM","method":"printed heading","endPage":82,"endAt":903,"startToken":29495,"endToken":30497},{"p":82,"at":903,"title":"VII. WHETHER THE REQUIREMENT SECURES A MEASURED EXPOSURE","method":"printed heading","endPage":82,"endAt":1555,"startToken":30497,"endToken":30601},{"p":82,"at":1555,"title":"A. The requirement is absent during the period of greatest uncertainty","method":"printed heading","endPage":83,"endAt":6,"startToken":30601,"endToken":31058},{"p":83,"at":6,"title":"B. The requirement is not measured against the contract it secures","method":"printed heading","endPage":84,"endAt":2711,"startToken":31058,"endToken":32192},{"p":84,"at":2711,"title":"C. The requirement departs from every methodology PJM applies elsewhere","method":"printed heading","endPage":85,"endAt":797,"startToken":32192,"endToken":32562},{"p":85,"at":797,"title":"D. The seller requirement is deficient by the same standard","method":"printed heading","endPage":86,"endAt":681,"startToken":32562,"endToken":33224},{"p":86,"at":681,"title":"E. Neither requirement is measured against the party that bears it","method":"printed heading","endPage":86,"endAt":3325,"startToken":33224,"endToken":33652},{"p":86,"at":3325,"title":"VIII. THE QUANTITY OF MW TO WHICH THE CREDIT RATE APPLIES IS","method":"printed heading","endPage":86,"endAt":3824,"startToken":33652,"endToken":33741},{"p":86,"at":3824,"title":"A. The three quantities","method":"printed heading","endPage":87,"endAt":1071,"startToken":33741,"endToken":33964},{"p":87,"at":1071,"title":"B. Committed MW and the Final RBP Target will not be the same","method":"printed heading","endPage":87,"endAt":2436,"startToken":33964,"endToken":34190},{"p":87,"at":2436,"title":"C. Committed MW is not in-service MW","method":"printed heading","endPage":87,"endAt":3484,"startToken":34190,"endToken":34367},{"p":87,"at":3484,"title":"D. Consequence","method":"printed heading","endPage":88,"endAt":214,"startToken":34367,"endToken":34491},{"p":88,"at":214,"title":"IX. THE REDUCTION OF THE REQUIREMENT OVER THE TERM IS UNDEFINED","method":"printed heading","endPage":88,"endAt":899,"startToken":34491,"endToken":34599},{"p":88,"at":899,"title":"A. How PJM releases collateral elsewhere","method":"printed heading","endPage":88,"endAt":2550,"startToken":34599,"endToken":34841},{"p":88,"at":2550,"title":"B. How the RBP releases collateral","method":"printed heading","endPage":89,"endAt":262,"startToken":34841,"endToken":35151},{"p":89,"at":262,"title":"C. Absent reduction, the requirement exceeds the obligation it secures","method":"printed heading","endPage":90,"endAt":6,"startToken":35151,"endToken":35762},{"p":90,"at":6,"title":"D. Consequence","method":"printed heading","endPage":90,"endAt":553,"startToken":35762,"endToken":35843},{"p":90,"at":553,"title":"X. THE COST OF CARRYING THE REQUIREMENT IS MATERIAL AND IS NOT","method":"printed heading","endPage":90,"endAt":1872,"startToken":35843,"endToken":36070},{"p":90,"at":1872,"title":"A. Only two forms of collateral are permitted","method":"printed heading","endPage":90,"endAt":2347,"startToken":36070,"endToken":36148},{"p":90,"at":2347,"title":"B. Cash","method":"printed heading","endPage":90,"endAt":3549,"startToken":36148,"endToken":36347},{"p":90,"at":3549,"title":"C. Letter of credit","method":"printed heading","endPage":91,"endAt":1183,"startToken":36347,"endToken":36606},{"p":91,"at":1183,"title":"D. The rate PJM selected is not the rate applicable to load","method":"printed heading","endPage":91,"endAt":4296,"startToken":36606,"endToken":37100},{"p":91,"at":4296,"title":"E. In aggregate","method":"printed heading","endPage":92,"endAt":982,"startToken":37100,"endToken":37316},{"p":92,"at":982,"title":"F. The cost is not recovered and is not disclosed","method":"printed heading","endPage":92,"endAt":2620,"startToken":37316,"endToken":37581},{"p":92,"at":2620,"title":"XI. THE REQUIREMENT CREATES SYSTEMIC LIQUIDITY RISK AMONG THE ENTITIES","method":"printed heading","endPage":92,"endAt":3904,"startToken":37581,"endToken":37786},{"p":92,"at":3904,"title":"A. The requirement falls at one moment, in two instruments","method":"printed heading","endPage":93,"endAt":327,"startToken":37786,"endToken":37919},{"p":93,"at":327,"title":"B. The obligation is concentrated and is not adjusted for the financial capacity of the obligor","method":"printed heading","endPage":93,"endAt":2233,"startToken":37919,"endToken":38220},{"p":93,"at":2233,"title":"C. The NOVEC zone","method":"printed heading","endPage":95,"endAt":1496,"startToken":38220,"endToken":39131},{"p":95,"at":1496,"title":"D. Letter of credit capacity is concentrated","method":"printed heading","endPage":95,"endAt":3210,"startToken":39131,"endToken":39405},{"p":95,"at":3210,"title":"E. The failure mode is correlated, and PJM has handled the same structure differently","method":"printed heading","endPage":96,"endAt":3078,"startToken":39405,"endToken":40050},{"p":96,"at":3078,"title":"F. Conclusion","method":"printed heading","endPage":97,"endAt":6,"startToken":40050,"endToken":40281},{"p":97,"at":6,"title":"XII. THE SOCIALIZATION OF A DEFAULT INCREASES THE OBLIGATION OF THE","method":"printed heading","endPage":97,"endAt":834,"startToken":40281,"endToken":40402},{"p":97,"at":834,"title":"A. Section 18.9(a) does not expressly require collateral to be applied before reallocation","method":"printed heading","endPage":97,"endAt":2144,"startToken":40402,"endToken":40618},{"p":97,"at":2144,"title":"B. Two reallocation mechanisms of different scope","method":"printed heading","endPage":97,"endAt":2845,"startToken":40618,"endToken":40727},{"p":97,"at":2845,"title":"C. Where the load does not appear, the obligation reaches native load","method":"printed heading","endPage":98,"endAt":3510,"startToken":40727,"endToken":41546},{"p":98,"at":3510,"title":"D. The NOVEC zone","method":"printed heading","endPage":99,"endAt":4460,"startToken":41546,"endToken":42454},{"p":99,"at":4460,"title":"E. The NOVEC zone does not satisfy the conditions for the opt-out","method":"printed heading","endPage":100,"endAt":2432,"startToken":42454,"endToken":42873},{"p":100,"at":2432,"title":"F. The residual reaches Members with no allocation","method":"printed heading","endPage":100,"endAt":3675,"startToken":42873,"endToken":43081},{"p":100,"at":3675,"title":"G. The seller side runs the same direction","method":"printed heading","endPage":101,"endAt":482,"startToken":43081,"endToken":43265},{"p":101,"at":482,"title":"H. Conclusion","method":"printed heading","endPage":101,"endAt":1627,"startToken":43265,"endToken":43443},{"p":101,"at":1627,"title":"XIII. THE FILED CREDIT CONSTRUCTS WERE NOT EXAMINED IN THEIR FINAL FORM","method":"printed heading","endPage":101,"endAt":2477,"startToken":43443,"endToken":43567},{"p":101,"at":2477,"title":"A. PJM proposed using its existing credit framework for LSEs","method":"printed heading","endPage":102,"endAt":6,"startToken":43567,"endToken":43823},{"p":102,"at":6,"title":"B. Other stakeholder proposals addressed buyer credit differently","method":"printed heading","endPage":102,"endAt":3064,"startToken":43823,"endToken":44263},{"p":102,"at":3064,"title":"C. The seller requirement was materially revised in the final stakeholder proposal","method":"printed heading","endPage":103,"endAt":441,"startToken":44263,"endToken":44562},{"p":103,"at":441,"title":"D. The LSE requirement changed after the final stakeholder proposal","method":"printed heading","endPage":103,"endAt":3123,"startToken":44562,"endToken":44981},{"p":103,"at":3123,"title":"E. The filed methodologies departed from the exposure-based criteria considered during the process","method":"printed heading","endPage":104,"endAt":3278,"startToken":44981,"endToken":45678},{"p":104,"at":3278,"title":"F. PJM considered adjustment mechanisms for sellers that were not included for load","method":"printed heading","endPage":105,"endAt":6,"startToken":45678,"endToken":45879},{"p":105,"at":6,"title":"G. PJM states that the filed proposal was not stakeholder-endorsed","method":"printed heading","endPage":105,"endAt":1478,"startToken":45879,"endToken":46107},{"p":105,"at":1478,"title":"H. Conclusion","method":"printed heading","endPage":105,"endAt":3255,"startToken":46107,"endToken":46368},{"p":105,"at":3255,"title":"XIV. CONCLUSION","method":"printed heading","endPage":120,"endAt":0,"startToken":46368,"endToken":51041},{"p":120,"at":0,"title":"Certificate of Service","method":"printed heading","endPage":120,"endAt":303,"startToken":51041,"endToken":51089}]}