{"document":{"slug":"rec-20260824-5126","title":"Post-Technical Conference Comments of Google LLC to address FERC's 07/30/2026 Notice re PJM Governance and Stakeholder Reforms","issued":"2026-08-24","accession":"20260824-5126","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Google LLC","kind":"comments","file":"sources/filings/text/20260824-5126_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260824-5126","tier":"record","sha256":"1c35e68611367c5a06f676b48410d6ace1bfb062177a0e27206c1457edb64beb","pages":9,"tokens":2437,"emptyPages":[],"textThemes":["adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":216,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n \nPJM Governance and Stakeholder Reforms​ ​\n)​\n​\n        Docket No. AD26-7-000 \n \n \nPOST TECHNICAL CONFERENCE COMMENTS OF  \nGOOGLE LLC \n \n \nI.​\nIntroduction \n \nGoogle, LLC (\"Google\") appreciates the leadership of the Federal Energy Regulatory \nCommission (“FERC” or “Commission”) to address Governance and Stakeholder Reforms in \nPJM, and submits these post-technical conference comments in response to the Commission's \nJuly 30, 2026, Notice Requesting Post-Conference Comments.1  Brian D. George serves as \nSenior Lead, U.S. Energy Markets for Google, establishing and executing the company's energy \nstrategy to ensure access to adequate power supply and infrastructure required to serve data \ncenter facilities across RTO and ISO regions, including PJM.  Mr. George participated as a \npanelist during Panel 2 of the Commission's July 23, 2026, Technical Conference in this docket. \nAlthough Google is not a PJM member and does not hold voting rights in PJM's \nstakeholder process, Google was deeply engaged in both of PJM's recent Critical Issue Fast Path \n(\"CIFP\") stakeholder processes: Large Load Additions (\"CIFP-LLA\") and the Reliability \nBackstop Procurement and Connect-and-Manage reforms (\"CIFP-RBP/C&M\"). Google \nparticipated in nearly every meeting and worked actively to form cross-sector coalitions, \nincluding one with four state governors (Pennsylvania, Maryland, New Jersey, and Virginia), and \n1 See Notice Requesting Post-Conference Comment, Docket No. AD26-7-000 (Jul. 30, 2026). \n1"},{"page":2,"startToken":216,"endToken":515,"text":"transmission owners to develop, refine, and advance multi-issue reform packages in the \nCIFP-LLA. \nThe timeliness of FERC’s technical conference was framed by Chairman Laura Swett's \ncall to PJM to \"right the ship\" and Deputy Secretary of Energy James Danly's frank assessment \nthat the market is \"a mess.”2  This uncertainty is underscored by the recent capacity auctions, \nwhich have resulted in a critical 6,381 MW resource deficit for the 2028/29 Delivery \nYear—currently the largest deficit among all U.S. ISOs and RTOs. \nGoogle's perspectives are informed by its significant investment in the region and the \nprinciples of the Ratepayer Protection Pledge (“Pledge”)—which Google and six other leading \ntechnology companies signed in March 2026.3  The Pledge reinforces the fundamental principle \nthat the costs and risks of new generation and regional network expansions required to serve \nlarge loads should be appropriately borne by those loads themselves, and not passed on to other \nconsumers.  To achieve this, Google continues to advocate for a workable \"Bring Your Own New \nCapacity\" (\"BYONC\") framework to incentivize large loads to bilaterally contract for and \nfinance new clean generation, thereby alleviating PJM's severe supply deficit and protecting \ncaptive retail ratepayers. \nII.​\nCore Governance and Stakeholder Process Principles  \n3 Ratepayer Protection Pledge, The White House (Mar. 4, 2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/ (“Ratepayer Protection Pledge”); \nPresident Trump Secures Historic Commitment to Keep Electricity Costs Down Amid Data Center Boom, The White \nHouse (Mar. 5, 2026), \nhttps://www.whitehouse.gov/releases/2026/03/president-trump-secures-historic-commitment-to-keep-electricity-cost\ns-down-amid-data-center-boom/. \n2 See Chairman Laura Swett’s Comments at PJM’s Annual Meeting in Baltimore, MD (May 12, 2026), \nhttps://www.ferc.gov/news-events/news/chairman-laura-swetts-comments-pjms-annual-meeting-baltimore-md-0; \nCommission-Led Technical Conference on PJM Governance and Stakeholder Reforms (Jul. 23, 2026), \nhttps://www.ferc.gov/news-events/events/PJM-Governance-Stakeholder-Reforms (“Technical Conference”). \n2"},{"page":3,"startToken":515,"endToken":770,"text":"Based on Google's extensive participation, the pre-filed comments of other stakeholders, \nand technical conference discussions, three core structural principles should guide the \nCommission's evaluation of PJM governance reforms: \n1.​ Valuing Stakeholder Consensus Alongside the Need for Decisive Action \nPJM’s stakeholder process is an essential, highly valuable open forum for debate and \ncollaboration. However, with more than 1,100 members representing naturally conflicting \ncommercial interests, full consensus on foundational market and operational issues is simply not \nalways attainable. \nThe recent CIFP-LLA process illustrates this reality: While none of the twelve \nstakeholder packages achieved the required two-thirds sector-weighted vote, they were not \ntwelve completely divergent paths. In fact, most proposals were conceptually aligned around key \nthemes—specifically load forecasting, demand response, and BYONG incentives. Where broad \nagreement falls short of formal voting thresholds, PJM Executive Staff and the Board of \nManagers must step in to synthesize these shared themes, establish clear directives, and advance \nnecessary regulatory filings that reflect stakeholder priorities while moving the market forward. \n2.​ Building on Stakeholder Input Through Deliberate Process Discipline   \nEncouraging PJM leadership to step forward when consensus is difficult to reach is not a \ncall to bypass the stakeholder community through unilateral Section 205 filing rights. The \ncollaborative nature of PJM’s membership is one of its greatest strengths; setting it aside risks \ncreating new regulatory friction and unnecessary uncertainty before FERC. \nThe most effective path forward is to support and refine the stakeholder framework rather \nthan replace it. PJM can achieve this by establishing clearer issue scoping upfront and keeping \n3"},{"page":4,"startToken":770,"endToken":1060,"text":"discussions anchored to reasonable timelines. When a stakeholder process concludes, the Board \nof Managers is best positioned to synthesize the valuable insights and common ground members \nhave developed, translating shared ideas into timely, well-supported regulatory solutions. \n3.​ Structured State Collaboration is Vital, But Must Avoid Gridlock \nCompared with other RTOs and ISOs, PJM is an outlier in its limited institutional role for \nstate regulators and policymakers. Google supports a more robust role for states, particularly the \n13 governors and utility commissions within the footprint who are ultimately accountable for the \nretail rates customers pay and the siting of the infrastructure needed to maintain reliability.  \nHowever, as noted by Commissioner Judy Chang and other conference participants, \nsecuring a single \"states' view\" is incredibly challenging and potentially unrealistic given the \nregional diversity across PJM's 13 states and the District of Columbia. Google supports a \nstructure that would fund and empower states to coordinate their technical positions, bringing \nunified regional public-policy priorities directly into PJM's strategic planning and board selection \nprocesses without bogging down the day-to-day wholesale market operations.  \nIII.​\nResponses to Specific Comments and Questions \n \nA.​ PJM Board Independence \n \n \nQuestions/Comments \nY \nN \nNeutral \n1) \nShould Board members’ terms be extended to five or more years? \nx \n \n \n \nComments: Google does not take a rigid position on term lengths, but notes that the observed conference \nconsensus that longer terms (such as the 5-year term discussed by panelists) could help insulate Board \nmembers from short-term stakeholder pressures or concerns over annual renomination. Google encourages a \nreview of other RTO/ISO Board member lengths and renomination terms to identify potential best practices \nthat could be applicable to PJM.  \n2) \nShould there be a maximum number of years that a Board member may serve \n \n \nx \n4"},{"page":5,"startToken":1060,"endToken":1453,"text":"Questions/Comments \nY \nN \nNeutral \n(e.g., 10 years)? \n \nComments: Google supports clear term limits if they enhance Board independence and prevent stagnation, \nprovided they do not restrict PJM's ability to attract and retain qualified candidates with deep energy market \nexpertise. Any restrictions should be carefully considered and backed up with evidence in their favor, \nincluding defining under which circumstances such restrictions should be triggered.  \n3) \nShould the Board member qualification rules be revised to provide a preference \nfor some Board members that reside in the PJM region? \n \nx \n \n \nComments: While local familiarity with PJM's unique market and regulatory footprint is beneficial, \nestablishing strict residency requirements should not artificially limit the pool of national energy experts \neligible for Board service.  \n4) \nShould the conflict-of-interest rules be revised to reduce the cooling off period for \nBoard members from two years to one year? \nx \n \n \n \nComments: Reducing the cooling-off period to one year is a pragmatic reform. It expands the candidate pool \nto include recent industry professionals who deeply understand the complex, fast-evolving operational realities \nof modern grids and large loads without compromising core ethical independence. \n5) \nShould restrictions on Board communications be relaxed to enable more \ncommunication between the Board and stakeholders? \nx \n \n \n \nComments: The current ex parte communication limits isolate the Board from stakeholders, preventing direct \nand productive dialogue. During the CIFP-LLA process, PJM’s positions and acceptable pathways forward \nwere not consistently known to stakeholders, creating a disjointed process. Google agrees with conference \nfeedback that Board members should have regular, structured, and transparent contact with states and \nstakeholders early in the policy development process to build alignment.  \n6) \nIn order to increase transparency, should Board votes be made public or the \nBoard be required to explain its reasoning?  \nx \n \n \n \nComments: Google strongly supports requiring the Board to publicly defend its decision-making rationale, \nespecially when it deviates from stakeholder or state consensus on high-stakes processes, such as the recently \nconcluded CIFP-LLA process. Market participants and long-term energy investors make multi-billion dollar \ninvestment plans based on these proceedings and sudden, unexplained late-stage shifts in proposal directions \n(like those seen in connect-and-manage, now IRAS, and RBP in 2026) inject severe commercial uncertainty \nand disrupt contracting for new generation. \n7) \nIn order to increase transparency, should some Board meetings be open or \navailable to the public? \nx \n \n \n \nComments: Increased transparency in any form is a benefit.  \n5"},{"page":6,"startToken":1453,"endToken":1787,"text":"Questions/Comments \nY \nN \nNeutral \n8) \nShould PJM’s governing documents be revised to explicitly state that the \nresponsibility of PJM and its Board is to serve the public interest? \nx \n \n \n \nComments: Google strongly supports codifying an explicit public interest mandate. PJM must legally balance \nreliability and market efficiency with public interest objectives. This is critical to ensure grid rules \naccommodate the integration of large loads and support state energy policies while protecting residential \nratepayers from stranded asset risks or cost-shifting. This public interest responsibility underpins Google's \ncommitment to the Ratepayer Protection Pledge. \n9) \nShould state representatives have at least one voting member on the Nominating \nCommittee? \nx \n \n \n \nComments: Google supports structured state participation in the Board selection process.  \n10) \nShould PJM adopt public performance metrics and tie management \ncompensation to their achievement? \nx \n \n \n \nComments: Board and management accountability must be strengthened, and tying compensation to objective \nreliability and load-forecasting metrics is a proven practice in other peer RTOs. \n \nB. Section 205 Filing Rights \n \n \nQuestions/Comments \nYes \nNo Neutral \n11) \nShould the stakeholder process be advisory, i.e., stakeholder votes only inform \nthe Board? \n \nx \n \n \nComments: Google agrees the Board must not be permanently gridlocked, but making the process purely \nadvisory removes essential checks and balances. If the Board files a proposal without consensus, it should be \ntreated as an extraordinary measure that requires a heightened, public written justification. \n12) \nShould PJM have section 205 filing rights over the energy market and ancillary \nservices unencumbered by the requirement to obtain approval of two-thirds of \nthe Members Committee? \n \nx \n \n \nComments: Google does not endorse unconditioning PJM's Section 205 filing rights. If any modifications to \nfiling rights are made, they must be strictly conditional on a mandatory early state/stakeholder consultation \nwindow and a written Board demonstration of how the proposal protects retail customers and ensures \ncommercial predictability. \n13) \nShould PJM have section 205 filing rights over Regional Transmission \nExpansion Planning (RTEP) unencumbered by the requirement to obtain \napproval of two-thirds of the Members Committee? \n \nx \n \n6"},{"page":7,"startToken":1787,"endToken":2159,"text":"Questions/Comments \nYes \nNo Neutral \n \nComments:  Same as 12 \n14) \nShould the Organization of PJM States Inc (OPSI) have “jump ball” rights over \nresource adequacy and transmission cost allocation filings when a supermajority \nof OPSI agrees on an alternative proposal? \n \n \nx \n \nComments: While Google supports expanding states' strategic input, we are cautious about expanding formal \nSection 205 filing, particularly to states as diverse as those that make up the PJM region. Providing unilateral \nfiling rights risks creating parallel, conflicting regulatory paths. However, if \"jump ball\" rights are granted, \nthey must be tightly bound to resource adequacy and cost allocation, with a requirement that the states reach a \nsupermajority to ensure regional cohesion. \n15) \nShould the Members Committee have “jump ball” filing rights over the portions \nof the tariff where PJM has 205 filing rights when a supermajority of \nstakeholders approves an alternative proposal? \n \n \nx \n \nComments: Google does not advocate for \"jump ball\" rights for the Members Committee. To resolve the \ncurrent gridlock, PJM and its independent Board must maintain clear executive accountability for filing \nmarket and transmission rules. \n \nC. Stakeholder Process \n \n \nQuestions/Comments \nYes \nNo Neutral \n \n16) \nShould the approval threshold in the Members Committee be lowered from \ntwo-thirds sector-weighted voting? \n \n \nx \n \nComments: Lowering the voting threshold from 2/3 sector-weighted voting (as discussed by several states \nand panelists during the technical conference) could reduce gridlock. However, the mathematical threshold \nitself is not the primary bottleneck. The core issue is the lack of early executive direction, scoping, and \ndecision discipline from PJM leadership. If the stakeholder process is made advisory and the Board is \ngranted conditional independent Section 205 filing rights, the 2/3 voting threshold becomes a useful metric \nof stakeholder consensus rather than a barrier to regulatory filing. \n17) \nShould the voting rules barring affiliate votes, which apply to senior standing \ncommittees, also apply to lower-level committees? \nx \n \n \n \nComments: Google supports eliminating affiliate voting at lower-level committees and task forces. Under the \ncurrent \"status quo\" rules, large market participants can leverage multiple registered affiliates to dominate \nlower-committee processes and \"sector- block\" proposals. Extending sector-weighted voting or Member-only \nvoting to lower committees would prevent these coalitions from stifling innovative ideas and non-traditional \nproposals before they can even reach senior committees. \n \n7"},{"page":8,"startToken":2159,"endToken":2400,"text":"D. State Participation \n \n \nQuestions/Comments \nYes \nNo Neutral \n18) \nIn addition to OPSI, should there be a second state representative group \nconsisting of governors’ representatives and/or state legislators’ representatives? \nx \n \n \n \nComments: Google strongly supports the formal, tariff-recognized establishment of the PJM Governors' \nCollaborative. As Brian D. George noted in a pre-filed statement, Google successfully partnered with a \nbipartisan coalition of four state governors during the first CIFP-LLA process.  \n19) \nShould state representatives have a formal voting role in the stakeholder process \n(limited to certain topics, such as resource adequacy and regional transmission \ncost allocation) in addition to the consumer advocate votes?   \n \n \nx \n \nComments: Google takes no position on whether state representatives should have a formal voting role in the \nstakeholder process.  \n20) \nShould PJM be required to consult with OPSI prior to making a section 205 \nfiling related to resource adequacy and transmission cost allocation? \nx \n \n \n \nComments: Yes, although we recognize that PJM already engages extensively with OPSI today.  \n \nIV.​\nConclusion  \nEnsuring a reliable, affordable, and clean grid in PJM will require moving beyond the \npursuit of absolute stakeholder consensus toward more decisive, transparent, and collaborative \nleadership. By instilling greater process discipline, engaging states and stakeholders earlier, and \nempowering the Board to provide clear and proactive direction, PJM can deliver the regulatory \ncertainty needed to support the next generation of energy investment. Governance reform should \nfocus on strengthening these mechanisms rather than shifting or fragmenting filing rights \nRespectfully submitted,  \n \n \n \n \n \n8"},{"page":9,"startToken":2400,"endToken":2437,"text":"/s/ Brian George  \nBrian George \nSr. Lead, US Energy Markets  \nElizabeth Savage \nStrategic Negotiator \nGoogle LLC \n655 New York Ave., NW \nWashington, DC 20001 \n(202) 999-0990 \nbriangeorge@google.com \neomsavage@google.com  \n \n \n \n \n \n \n \n \n \nDated: August 24, 2026 \n9"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":211,"startToken":0,"endToken":24},{"p":1,"at":211,"title":"Introduction","method":"printed heading","endPage":6,"endAt":1172,"startToken":24,"endToken":1611},{"p":6,"at":1172,"title":"B. Section 205 Filing Rights","method":"printed heading","endPage":7,"endAt":1224,"startToken":1611,"endToken":1965},{"p":7,"at":1224,"title":"C. Stakeholder Process","method":"printed heading","endPage":8,"endAt":0,"startToken":1965,"endToken":2159},{"p":8,"at":0,"title":"D. State Participation","method":"printed heading","endPage":8,"endAt":1160,"startToken":2159,"endToken":2320},{"p":8,"at":1160,"title":"Conclusion","method":"printed heading","endPage":9,"endAt":266,"startToken":2320,"endToken":2437}]}