{"document":{"slug":"rec-20260826-4000","title":"Transcript of the 07/23/2025 Meeting held in Washington DC re the PJM Governance and Stakeholder Reforms","issued":"2026-08-26","accession":"20260826-4000","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"FEDERAL ENERGY REGULATORY COMMISSION","kind":"testimony","file":"sources/filings/text/20260826-4000_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260826-4000","tier":"record","sha256":"126271c00af7731222be9e7f273fd767a1a5aa13f115ac68634603e616d55d79","pages":null,"tokens":65959,"emptyPages":[],"textThemes":["adequacy","cost","flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":65959,"text":"1\n\n\n\n          1   UNITED STATES OF AMERICA\n\n          2   \n\n          3   FEDERAL ENERGY REGULATORY COMMISSION\n\n          4   \n\n          5   PJM Governance and Stakeholder Reforms\n\n          6   \n\n          7   Docket No. AD26-7-000\n\n          8   \n\n          9   THURSDAY, July 23, 2026\n\n         10   \n\n         11   9:00 a.m.-4:00 p.m.\n\n         12   \n\n         13   \n\n         14   \n\n         15   FEDERAL ENERGY REGULATORY COMMISSION\n\n         16   \n\n         17   888 FIRST STREET, NE\n\n         18   \n\n         19   WASHINGTON, D.C. 20426\n\n         20   \n\n         21   \n\n         22   \n\n         23   \n\n         24   \n\n         25   \n\n\n\n\n\n                                                                        2\n\n\n\n          1   APPEARANCES:\n\n          2   \n\n          3   FERC COMMISSIONERS:\n\n          4   CHAIRMAN LAURA V. SWETT\n\n          5   COMMISSIONER DAVID ROSNER\n\n          6   COMMISSIONER LINDSAY S. SEE\n\n          7   COMMISSIONER JUDY CHANG\n\n          8   COMMISSIONER DAVID A. LACERTE\n\n          9   \n\n         10   MODERATORS:\n\n         11   ALANDRO VALDEZ\n\n         12   STEPHANIE EYOCKO\n\n         13   \n\n         14   REMARKS OF INVITED SPEAKERS:\n\n         15   THE HONORABLE JAMES. P. DANLY, Deputy Secretary, U.S.\n\n         16   Department of Energy\n\n         17   PETER LAKE, The White House, Senior Director of Power,\n\n         18   National Energy Dominance Council\n\n         19   \n\n         20   \n\n         21   \n\n         22   \n\n         23   \n\n         24   \n\n         25   \n\n\n\n\n\n                                                                        3\n\n\n\n          1   PANEL 1: PJM GOVERNANCE MECHANICS-BOARD AUTHORITY, STATES'\n\n          2   ROLE, FILING RIGHTS, AND DOCUMENT ARCHITECTURE:\n\n          3   \n\n          4   PANELIST:\n\n          5   \n\n          6   DAVID MILLS, PJM Interconnection, L.L.C., President and CEO\n\n          7   THE HONORABLE PAT WOOD III, Hunt Energy Network, Executive\n\n          8   Chairman\n\n          9   THE HONORABLE KELSEY BAGOT, Virginia State Corporation\n\n         10   Commission, Chair\n\n         11   JACOB FINKEL, Pennsylvania Governor Josh Shapiro's Office,\n\n         12   Deputy Secretary of Policy\n\n         13   STACEY BURBURE, American Electric Power, Senior Vice\n\n         14   President, Transmission, Regulatory Engagement & Compliance\n\n         15   MAJORIE ROSENBLUTH PHILIPS, LS Power, Senior Vice President,\n\n         16   Wholesale Market Policy\n\n         17   MARIA GULLINI, ISO-NE, Vice President, General Counsel, and\n\n         18   Chief Compliance Officer\n\n         19   \n\n         20   \n\n         21   \n\n         22   \n\n         23   \n\n         24   \n\n         25   \n\n\n\n\n\n                                                                        4\n\n\n\n          1   PANEL 2: PJM STAKEHOLDER PROCESS-DESIGN, TRANSPARENCY, AND \n\n          2   DECISION-MAKING\n\n          3   \n\n          4   PANELIST GROUP 1:\n\n          5   ASIM HAQUE, PJM Interconnection L.L.C., Executive Vice\n\n          6   President Governmental and Member Services\n\n          7   SUZANNE JAWOROWSKI, Indiana Governor Mike Braun's Office,\n\n          8   Secretary Of Energy and Natural Resources\n\n          9   J. ARNOLD QUINN, Vistra Corp., Senior Vice President,\n\n         10   Regulatory Policy\n\n         11   STEVEN LIEBERMAN, American Municipal Power, Inc., Vice\n\n         12   President of Transmission & Regulatory Affairs\n\n         13   ABE SILVERMAN, Johns Hopkings University Ralph O'Connor\n\n         14   Sustainable Energy Institute, Assistant Research Scholar\n\n         15   KENT CHANDLER, R Street Institute, Non-Resident Senior\n\n         16   Fellow, Energy and Environmental Policy\n\n         17   PAMELA QUINLAN, GQS New Energy Strategies, Principal\n\n         18   \n\n         19   PANELIST GROUP 2:\n\n         20   DAVID ANDERS, PJM Interconnection L.L.C., Senior Director of\n\n         21   Stakeholder Affairs\n\n         22   GLEN THOMAS, PJM Power Providers Group, President\n\n         23   JODI MOSKOWITZ, Public Service Enterprise Group Inc., Vice\n\n         24   President Regulatory Law, Deputy General Counsel and RTO\n\n         25   Strategy Officer\n\n\n\n\n\n                                                                        5\n\n\n\n          1   JAMESON TWEEDIE, Delaware Division of the Public Advocate,\n\n          2   Public Advocate\n\n          3   MASON EMNETT, Constellation, Senior Vice President of\n\n          4   Public Policy\n\n          5   BRIAN GEORGE, Google, Senior Lead, U.S. Energy Markets\n\n          6   SUSAN BRUCE, PJM Industrial Customer Coalition, Counsel\n\n          7   DR. JOSEPH BOWRING, Monitoring Analytics, President and PJM\n\n          8   Independent Market Monitor\n\n          9   \n\n         10   \n\n         11   \n\n         12   \n\n         13   \n\n         14   \n\n         15   \n\n         16   \n\n         17   \n\n         18   \n\n         19   \n\n         20   \n\n         21   \n\n         22   \n\n         23   \n\n         24   \n\n         25   \n\n\n\n\n\n                                                                        6\n\n\n\n          1                      P R O C E E D I N G S\n\n          2              MR. VALDEZ:  Good morning, everybody.  My name is\n\n          3   Alandro Valdez.  I am from the Commission's Office of\n\n          4   Technical Reporting and Economics.\n\n          5              We are pleased to welcome you to this\n\n          6   Commissioner-led technical conference to discuss PJM's\n\n          7   governance and stakeholder processes.\n\n          8              The purpose of this technical conference is to\n\n          9   explore specific governance features and stakeholder\n\n         10   processes in PJM that affect timely actions on\n\n         11   operational and market needs.  The conference will also\n\n         12   explore potential reforms to PJM's governance and\n\n         13   stakeholder processes.\n\n         14              Before we begin with opening remarks from the\n\n         15   Chairman and the Commissioners, I will outline some\n\n         16   logistics for the conference.  \n\n         17              This technical conference will run from 9:00\n\n         18   a.m. to 4:00 p.m. today.  We will have opening remarks from\n\n         19   invited speakers in the first session, followed by two\n\n         20   panels, with three slates of panelists.\n\n         21              We will start with our opening speakers, followed\n\n         22   by the first panel, on the PJM governance structure.  This\n\n         23   will be followed by a second panel, on PJM's stakeholder\n\n         24   processes, which will have two slates.\n\n         25              We will have a break between each panel, one hour\n\n\n\n\n\n                                                                        7\n\n\n\n          1   for lunch after the first panel and a 15-minute break\n\n          2   between the two second panels.\n\n          3              Only the commissioners, panelists, and a small\n\n          4   group of Commission staff will have speaking roles during\n\n          5   the conference.  We will not be taking any questions from\n\n          6   the audience.\n\n          7              The conference is being webcast and transcribed\n\n          8   and a recording will be available for future viewing.\n\n          9              Commenters are also invited to file\n\n         10   post-conference comments in the docket, AD26-7, following\n\n         11   the conference.\n\n         12              For those standing in the back of the room, we\n\n         13   invite you to go to hearing room one, for overflow seating,\n\n         14   where the conference is being livestreamed from here.\n\n         15              As a reminder for all panelists, we will not\n\n         16   discuss at this technical conference any specific proceeding\n\n         17   before the Commission, including proceedings that involve\n\n         18   similar issues, whether listed on the supplemental notice\n\n         19   issued July 16th, or not.\n\n         20              We ask that panelists, similarly, refrain from\n\n         21   such discussion.  If anyone engages in these kinds of\n\n         22   discussions, my colleagues from the Office of the General\n\n         23   Counsel will interrupt the discussion to ask the speaker to\n\n         24   avoid that topic.\n\n         25              With those initial matters out of the way, I'll\n\n\n\n\n\n                                                                        8\n\n\n\n          1   now turn it over to Chairman Swett for her opening remarks.\n\n          2              CHAIRMAN SWETT:  Thank you very much.  Good\n\n          3   morning, everyone.  I don't think we've ever been so\n\n          4   popular.  It's probably because of our guest speakers to my\n\n          5   left, but it's probably more likely due to the gravity of\n\n          6   the situation.  Thank you all for being here.\n\n          7              I want to begin by grounding us in why we're\n\n          8   convened today and why this conversation is so urgent and\n\n          9   necessary.  As many of you know, at PJM's annual meeting in\n\n         10   Baltimore this past May I remarked on the history of the\n\n         11   market nearly a century ago when it formed and the brave\n\n         12   leadership and oversight that -- of the foresight of the\n\n         13   utilities that banded together in 1927 to form a power pool\n\n         14   that produced benefits greater than any one of them could\n\n         15   achieve individually.\n\n         16              For many decades, that spirit drove PJM to be a\n\n         17   leader in pursuing innovative market designs and operating\n\n         18   one of the largest, most complex, transmission systems in\n\n         19   the world.  We appreciate, at this commission, how difficult\n\n         20   that task is and how it has grown increasingly difficult\n\n         21   today, as PJM sits at the crossroads of 13 states and the\n\n         22   District of Columbia, and there are divergent regulatory\n\n         23   structures, resource portfolios, and politics, across the\n\n         24   footprint.  It's a very difficult needle to thread.\n\n         25              But we're here today because PJM is facing a\n\n\n\n\n\n                                                                        9\n\n\n\n          1   grave legitimacy crisis, frustrations are mounting, the\n\n          2   collaborative spirit that underpinned the market's formation\n\n          3   is fracturing, and some transmission owners are openly\n\n          4   discussing leaving the RTO altogether.  Put plainly, market\n\n          5   participants have lost confidence in PJM's decision-making\n\n          6   abilities.\n\n          7              But we are not here to cast blame today or point\n\n          8   fingers or simply just air grievances.  I convened this\n\n          9   conference today for one purpose.  That is to right the\n\n         10   ship.  We are at a global inflection point, where nations\n\n         11   are competing with the United States to harness the power of\n\n         12   AI in ways that will reshape economies and geopolitics, for\n\n         13   our lifetimes and generations after that.\n\n         14              Our adversaries are hard at work and it's time\n\n         15   that the companies and institutions represented in this room\n\n         16   come together to chart the path towards a well-functioning\n\n         17   RTO that can deliver for the American people.\n\n         18              As I have said before, PJM is the tip of the\n\n         19   spear, it's the laboratory of national and economic security on\n\n         20   which our country may rise or fall.  And I'm not being\n\n         21   dramatic; I truly believe that, and it is critical that we\n\n         22   come out of today's conference with solutions.\n\n         23              We need PJM to act decisively and reinstill the\n\n         24   confidence in investors that is necessary for the region to\n\n         25   attract the billions in capital that we need to build\n\n\n\n\n\n                                                                       10\n\n\n\n          1   generation and harden our infrastructure.  To do that, we\n\n          2   have to fix the cracks in the foundational governance\n\n          3   structure.\n\n          4              I want PJM to be set up for success as this\n\n          5   country navigates once-in-a-generation opportunities to\n\n          6   cement American leadership in the global economy.\n\n          7              As we consider potential reforms today, we can't\n\n          8   lose sight of the 67 million Americans who directly feel the\n\n          9   consequences of our actions on their pocketbooks. \n\n         10   Hard-working American families have enough on their plates\n\n         11   and the price of electricity cannot be another source of\n\n         12   strain.  Families in the PJM footprint should not be asked\n\n         13   to shoulder the financial burden of processes that are\n\n         14   slow, fragmented, or opaque.\n\n         15              I define success as a well-functioning RTO that\n\n         16   delivers stable, transparent, and cost-effective outcomes. \n\n         17   Today we begin the process of identifying and evaluating\n\n         18   actionable reforms that will allow PJM to operate with\n\n         19   speed, transparency, and accountability.\n\n         20              Here is what I ask of everyone participating\n\n         21   today.  First, be candid.  If a rule or process is failing,\n\n         22   say so.  If things need to be eliminated, streamlined, or\n\n         23   strengthened, we want to hear why.  We want specifics and we\n\n         24   want the truth.\n\n         25              Second, on the point of specificity, I personally\n\n\n\n\n\n                                                                       11\n\n\n\n          1   despise equivocations and hollow pledges.  We are looking\n\n          2   for the reforms that are clearly articulated, evaluated, and\n\n          3   we want them to be filed under Section 205, or Section 206,\n\n          4   as appropriate.  If there are roadblocks to turning those\n\n          5   reforms into realities, I want to hear what those are and\n\n          6   how to cut through them.\n\n          7              Third, I ask that each company and institution\n\n          8   approach today's conversation with an eye towards reaching\n\n          9   common ground.  This is not the time to fall back on\n\n         10   familiar positions that have been worn over time and decades\n\n         11   of businesses.  Reaffirming immovable stances is not\n\n         12   productive.  We need change.  The market is facing change,\n\n         13   and we're not going to succeed without it.  That means that\n\n         14   you need to listen as much as you speak and acknowledge\n\n         15   valid concerns, even when they come from a different side of\n\n         16   the table.\n\n         17              It also means looking at practical compromises\n\n         18   and being willing to adjust longstanding positions, for the\n\n         19   benefit of the 67 million Americans who are depending on us\n\n         20   to get this right.\n\n         21              And, if we can't all agree, then FERC will be in\n\n         22   a position where we may have to do it for you.  And I would\n\n         23   rather not be in that position.\n\n         24              So... we will not discuss at this technical\n\n         25   conference any specific proceedings before the Commission, including\n\n\n\n\n\n                                                                       12\n\n\n\n          1   proceedings that involve similar issues, whether listed on\n\n          2   the supplemental notice or not, and we ask that the\n\n          3   panelists similarly refrain from such discussions.  If\n\n          4   anyone engages in these types of discussions, my colleagues\n\n          5   from the Office of General Counsel will interrupt the\n\n          6   discussion to ask the speaker to avoid that topic.\n\n          7              With those initial matters out of the way, I will\n\n          8   turn to my colleagues for their opening remarks. \n\n          9   Commissioner Rosner.\n\n         10              COMMISSIONER ROSNER:  Thank you, Chairman, for\n\n         11   convening this important conference and thank you to the\n\n         12   panelists that will be appearing today for being here and\n\n         13   contributing your perspective.  \n\n         14              Thanks to everyone who filed comments, and thank\n\n         15   you to Secretary Danly and to Peter Lake for joining us.\n\n         16              And I'd be remiss if I didn't also thank the FERC\n\n         17   staff for organizing the conference.\n\n         18              Yes, PJM has problems.  Yes, they should be\n\n         19   fixed, and it's urgent to do so.  But I want to take a\n\n         20   moment to just acknowledge that, since it was created, PJM\n\n         21   has saved consumers billions of dollars, year after year. \n\n         22   PJM has also ensured that the grid has remained reliable. \n\n         23   And this has been particularly evident over the last few\n\n         24   years, when PJM has managed challenging conditions, to keep\n\n         25   the lights on.\n\n\n\n\n\n                                                                       13\n\n\n\n          1              So, while we're convened here today to discuss\n\n          2   changes to PJM to ensure that the nation's largest energy\n\n          3   market remains sustainable and viable in the coming years,\n\n          4   it's also important not to lose sight of PJM's importance\n\n          5   and value.\n\n          6              So, turning to the topic at hand, effective\n\n          7   governance processes, are critical, for PJM to continue\n\n          8   delivering for the region.  My hope is that today we build\n\n          9   consensus on durable, lasting, reforms, and I'm encouraged\n\n         10   by the hard work of reaching agreement that has already\n\n         11   begun in earnest, and I'm optimistic that we can continue\n\n         12   moving that ball forward today, because the opportunity\n\n         13   before us today is one we can't afford not to capitalize on.\n\n         14              I'm approaching today's conversation with an open\n\n         15   mind.  That said, I'd like to offer a few opening thoughts\n\n         16   on five categories of potential reforms that stakeholders\n\n         17   have discussed with me, both in meetings in person and in\n\n         18   comments.\n\n         19              First, I agree that states need an enhanced role\n\n         20   in the governance process, and this must be a real role,\n\n         21   with teeth.  For example, some form of increased state\n\n         22   participation in selecting the board sounds very reasonable,\n\n         23   appreciating that there are many different pathways to\n\n         24   achieve this.\n\n         25              Second, I see support for enhanced board\n\n\n\n\n\n                                                                       14\n\n\n\n          1   independence.  To succeed, the PJM board needs to be able to\n\n          2   make decisions confidently and openly, and decisively act\n\n          3   once it's reached the best possible decision.  Achieving\n\n          4   this outcome also can come in many different forms.\n\n          5              Third, I'm interested in discussing pathways,\n\n          6   either in the stakeholder process or in another venue, to\n\n          7   amplify state input on issues related to resource adequacy. \n\n          8   Under the Federal Power Act, jurisdiction between the\n\n          9   federal government and states is shared.  States are\n\n         10   critical partners in ensuring resource adequacy, because\n\n         11   states are ultimately responsible for siting and permitting\n\n         12   the generation and transmission that is needed to ensure\n\n         13   reliable and affordable power.  And I'll have more on this\n\n         14   later.\n\n         15              In this area, I hear a variety of potential\n\n         16   solutions, ranging from concepts like we have in other RTOs,\n\n         17   where state entities have opportunities to present issues\n\n         18   directly to the board, as well as processes like the one\n\n         19   that we set up in Order Number 1920, where we required public\n\n         20   utilities to tell FERC what states agreed to on\n\n         21   tranmission cost allocation.\n\n         22              And that takes me to the fourth area of focus,\n\n         23   state input on transmission cost allocation.  In my view,\n\n         24   the expectation, the norm, should always be that states and\n\n         25   their utilities agree on how to allocate the cost of\n\n\n\n\n\n                                                                       15\n\n\n\n          1   transmission such that a process like the one we established\n\n          2   in Order Number 1920 is never needed.\n\n          3              And, on that Order Number 1920 cost allocation in\n\n          4   PJM, I'm optimistic that we will get that agreement.  But\n\n          5   the point here is that states should always be able to\n\n          6   formally communicate to PJM, and to FERC, in turn, what they\n\n          7   agreed to.\n\n          8              Fifth, I also believe it's important to have an\n\n          9   entity for the governors' designees, and with this they can\n\n         10   ensure -- we should ensure that they have the resources\n\n         11   needed to organize themselves and their positions.\n\n         12              Next, as we consider PJM governance in the\n\n         13   stakeholder process and particularly a meaningful,\n\n         14   potentially expanded, role for the states, very\n\n         15   respectfully, states must also ensure that they make\n\n         16   progress on the issues within their own jurisdictions,\n\n         17   because I mentioned before, it's shared.\n\n         18              For example, we need states' help with retail\n\n         19   rate design, to ensure that they can assign wholesale costs\n\n         20   to the right customers.  We also need states' help on\n\n         21   curtailment priorities, otherwise known as emergency load\n\n         22   reduction rules, for large loads.  And we need states to put\n\n         23   in place cost allocation rules for a backstop auction, if and\n\n         24   when we have one.\n\n         25              And all of this, PJM state governors committed to\n\n\n\n\n\n                                                                       16\n\n\n\n          1   doing this backstop cost allocation when they signed the\n\n          2   \"statement of principles\" regarding PJM agreement, in\n\n          3   January, with the White House, and it's time for these\n\n          4   provisions to be in place across the region.\n\n          5              I also note that the Virginia SCC and the Data\n\n          6   Center Coalition, a state and industry working together,\n\n          7   proposed both backstop cost allocation and curtailment\n\n          8   rules, in June, and I hope that the rest of the PJM states\n\n          9   will join, and provide some place where we can have\n\n         10   transparent information on the status of their member\n\n         11   states' progress on these critical deliverables.\n\n         12              And I wouldn't be doing my job here if I didn't\n\n         13   also mention that we need states' help on permitting.  No\n\n         14   matter what signal the PJM market sends or what governance\n\n         15   reforms are implemented, PJM will not succeed without our state\n\n         16   colleagues also ensuring that we timely get generation and\n\n         17   transmission built.  We need help from states to make sure\n\n         18   that they can identify resources they want to see built in\n\n         19   their state, and then ensure that those resources get built\n\n         20   and connected fast.\n\n         21              For example, if your states has clean energy\n\n         22   goals, ask yourself, \"How long does it take to get a permit,\n\n         23   the CPCN, all the authorizations to build a battery?\"  If\n\n         24   it's longer than 60 days, that sounds like a problem.  If\n\n         25   you don't know the answer, to me that sounds like a problem\n\n\n\n\n\n                                                                       17\n\n\n\n          1   too.\n\n          2              If your state wants to embrace demand response\n\n          3   and demand side flexibility, how much retail demand response\n\n          4   currently participates in your state?  Does your state allow\n\n          5   aggregators access to retail meter data?  Do your utilities\n\n          6   allow negative peak load contribution values, to enable\n\n          7   innovative business models that can provide real RA during\n\n          8   stress periods?\n\n          9              And finally, on transmission, we all know that\n\n         10   transmission is needed, to interconnect new resources.  We\n\n         11   can have the fastest queue in the world, but if there's not a\n\n         12   grid to plug it in there is nothing we can do fast.  So, how\n\n         13   quickly and durably can transmission be developed in your\n\n         14   state?\n\n         15              So, thank you for humoring my request for\n\n         16   assistance from our state colleagues.  While the Commission\n\n         17   works to make progress on issues within our jurisdiction, we\n\n         18   really need PJM, the market participants, states and other\n\n         19   stakeholders, to make progress on these issues that are\n\n         20   beyond our reach.\n\n         21              But together I'm very confident that we can\n\n         22   address the challenges we face, and I remain optimistic\n\n         23   about PJM's future.\n\n         24              With that, I'm very much looking forward to the\n\n         25   conversation today and I turn it back to you, Chairman.\n\n\n\n\n\n                                                                       18\n\n\n\n          1              CHAIRMAN SWETT:  That was a nice balance to my\n\n          2   brimstone.  Commissioner See?\n\n          3              COMMISSIONER SEE:  There are tech conference and\n\n          4   there are tech conferences, and I think it's obvious from\n\n          5   the people who are here today and the attention that's been\n\n          6   placed on this issue that we're in the latter category.\n\n          7              First of all, a well-deserved round of thanks. \n\n          8   The prep work and the background for conversations like I\n\n          9   hope we'll have today don't just happen.  So, thank you,\n\n         10   Chair Swett, and to your office for bringing us together and\n\n         11   focusing on these issues.  Thank you to our FERC staff for\n\n         12   all of their work here, to PJM for being here and for\n\n         13   helpful conversations along the way.\n\n         14              To our distinguished guests and our panelists, I appreciate\n\n         15   your willingness to put your name to ideas and engage with\n\n         16   us on that as well.  And to the many other commenters who\n\n         17   have already given us a strong record to start from.\n\n         18              We have a lot to do today, so here's how I see\n\n         19   the problem statement.  PJM, like other organized markets,\n\n         20   has delivered huge value to customers over the years.  When\n\n         21   functioning right, competitive markets and the economies of\n\n         22   scale that can come with them can mean lower-cost power and\n\n         23   better operational reliability for millions of Americans.\n\n         24              But PJM hasn't been living up to that legacy\n\n         25   recently.  Even with market intervention, we still have\n\n\n\n\n\n                                                                       19\n\n\n\n          1   sky-high prices, and last week was the second time that the\n\n          2   auction failed to secure enough capacity to meet the reserve\n\n          3   threshold in PJM.  To put it lightly, those are serious\n\n          4   concerns.\n\n          5              Now, to be clear, some of the big factors for\n\n          6   this are outside of PJM's control.  Markets are designed to\n\n          7   withstand some fluctuation, but the pace and scale of large\n\n          8   load growth is well beyond an ordinary demand spike.\n\n          9              So, I don't see the need for reforms as the\n\n         10   problem itself.  For these conditions, we need real changes\n\n         11   in the short term, to get us through this time and to allow\n\n         12   PJM to keep delivering benefits into the future.\n\n         13              As I do see it, the problem is twofold.  First,\n\n         14   PJM's unique stakeholder process and system of voting may\n\n         15   work in many contexts, but it hasn't led to results in some\n\n         16   of the most consequential questions PJM is grappling with\n\n         17   now.  We need action, not stalemates.\n\n         18              And second, as a result of these and other\n\n         19   struggles, states, utilities, developers, and other\n\n         20   stakeholders have lost confidence in PJM.  Either of these\n\n         21   are serious issues on their own, but together they put PJM\n\n         22   at a crisis point.\n\n         23              And that's why governance reform and the\n\n         24   conversation today matter.  It's because I take so seriously\n\n         25   the substantive challenges PJM has had that we have to\n\n\n\n\n\n                                                                       20\n\n\n\n          1   address how to get governance right.  PJM needs a process\n\n          2   and a structure that can get these reforms done and can give\n\n          3   stakeholders confidence enough in them to bet their money\n\n          4   and their customers on the results.\n\n          5              So I think today we need more than just\n\n          6   conversation.  I'm really hoping to see us flesh out viable\n\n          7   options and see where there is, or can, or should be\n\n          8   consensus, moving forward.\n\n          9              We've had a lot of strong ideas teed up already\n\n         10   and I'm really grateful for that.  Some feel like they could\n\n         11   be low hanging fruit or areas where we should be able to get\n\n         12   easier momentum.\n\n         13              For me, that category includes ways to make the\n\n         14   board more transparent and accountable, so ideas like\n\n         15   lengthening board terms, reevaluating selection criteria and\n\n         16   conflict of interest rules, to get more members in the PJM\n\n         17   region and others with direct experience and investment,\n\n         18   consistent with good governance principles.\n\n         19              I also think we can talk, in this category, about\n\n         20   ways to increase board members' interaction with states and\n\n         21   stakeholders and to have more transparency around board\n\n         22   decisions.  So let's talk about these and other areas, where\n\n         23   we may be able to get some relatively fast wins.\n\n         24              But, there are other areas, of course, where I\n\n         25   acknowledge, as we all do, it'll be harder to get reforms in\n\n\n\n\n\n                                                                       21\n\n\n\n          1   place.  But that's all the more reason we have to talk about\n\n          2   them here, with the breadth of interests and expertise\n\n          3   represented, and the urgency of the stakes.\n\n          4              So I'm very interested in discussions about how\n\n          5   to give states a more meaningful voice in PJM and in selecting its\n\n          6   leadership.  State representation on the nominating\n\n          7   committee seems an obvious step forward, for me, in this\n\n          8   area, and I'm also interested in talking about ways to\n\n          9   strengthen OPSI or expand the states' formal mechanisms to\n\n         10   help set PJM's direction.\n\n         11              And I'm very focused on how we can make the\n\n         12   stakeholder process more effective and let PJM act more\n\n         13   decisively.  So, let's not shy away, today, from whether an\n\n         14   advisory stakeholder process, which is almost unique from\n\n         15   other markets, is the right path forward for PJM.  That\n\n         16   would undoubtedly be a big change, and I do have an open\n\n         17   mind on this issue.\n\n         18              But, paired with jump ball filing rights and\n\n         19   similar 4C mechanisms for collaboration, it could be a\n\n         20   method that lets PJM act in a faster and more decisive way\n\n         21   than it can now.\n\n         22              So, I'm interested in hearing from the panelists\n\n         23   why that is, or isn't, the path forward, and what it would\n\n         24   take to get there.\n\n         25              Now to be clear, in closing -- and I have respect\n\n\n\n\n\n                                                                       22\n\n\n\n          1   for PJM, especially when I talk with the technical staff,\n\n          2   it's clear that they are approaching the generational issues\n\n          3   in front of us, with nuance and thoughtfulness.  But we need\n\n          4   more.\n\n          5              As a PJM ratepayer and an American, I want PJM to\n\n          6   succeed.  As a FERC commissioner, I also take seriously our\n\n          7   regulatory responsibilities to make sure the market operates\n\n          8   in a just and reasonable way.  \n\n          9              So, success requires action, and let's work\n\n         10   together today to make sure that that can spur it on.  Back to you.\n\n         11              CHAIRMAN SWETT:  Thank you.  Commissioner Chang?\n\n         12              COMMISSIONER CHANG:  Thank you, Chair.\n\n         13              Welcome, everyone.  Thank you for being here on\n\n         14   this very special day, and thank you again for staff, that\n\n         15   has prepared us for this very important technical\n\n         16   conference.  And thank you for our guests and, of course,\n\n         17   all of the speakers that will make today's conversation very\n\n         18   focused on the task at hand.\n\n         19              I too want PJM to succeed.  I think we're all\n\n         20   here because we want to make contributions to PJM's success.\n\n         21              The way I see this is the problem in PJM's market\n\n         22   is actually a collective problem, and it needs to be solved\n\n         23   collectively, so this is definitely not a finger pointing\n\n         24   exercise.\n\n         25              I also want to acknowledge that PJM has\n\n\n\n\n\n                                                                       23\n\n\n\n          1   successfully -- and we talked about benefits, my colleagues\n\n          2   here have talked about the benefits, that PJM has yielded. \n\n          3   PJM also has successfully attracted merchant investments,\n\n          4   just on combined natural gas combined cycles, since the\n\n          5   inception of its capacity market, as the way, more or less,\n\n          6   that was designed today, over 30 -- about 39 gigawatts of\n\n          7   just combined cycle.  I'm not even talking about the other\n\n          8   resources.\n\n          9              And PJM also, through the last decade or two,\n\n         10   successfully facilitated the retirement of some\n\n         11   generation by enhancing its grid.  So, there have been\n\n         12   successes in the past, and I just want to make sure that\n\n         13   people don't forget about that.\n\n         14              But recently, I think, the resource adequacy has\n\n         15   been a tremendous concern for everyone, and while today's\n\n         16   governance discussion will not address all of the problems\n\n         17   and all the resource adequacy concerns, I think this is a\n\n         18   very important component of this.\n\n         19              I also want to acknowledge that PJM has been\n\n         20   relatively responsive to states, in the past, particularly\n\n         21   when certain states have specific needs, and studies.  And I\n\n         22   was working in New England when I jealously looked at PJM\n\n         23   and its staff, working with certain states in the PJM\n\n         24   footprint, to help them facilitate their needs.\n\n         25              So, I just want to make sure -- it's easy to\n\n\n\n\n\n                                                                       24\n\n\n\n          1   forget the challenges that PJM has overcome over the past\n\n          2   decade, so I appreciate the interest today and over the last\n\n          3   few months, the interest of so many stakeholders in\n\n          4   exploring potential ways to improve PJM's governance.\n\n          5              Now, in discussing governance, we need to think\n\n          6   carefully about which of PJM's challenges stem from PJM's\n\n          7   governance and decision-making, and which are rooted elsewhere. \n\n          8   Many factors outside of PJM's control have contributed to,\n\n          9   somewhat, this perfect storm, a combination of geographic,\n\n         10   political, regulatory, diversity of PJM's states, the unique\n\n         11   history of the markets reacting to FERC policy changes\n\n         12   including the minimum offer price rules, and the\n\n         13   happenstance that PJM happens to be ground zero for global\n\n         14   data center developments, at least the first in the US, have\n\n         15   all contributed to the recent resource adequacy challenges.\n\n         16              Now, as for solutions, I said earlier PJM cannot\n\n         17   do this alone.  Everyone, including FERC, and certainly the\n\n         18   states, and power producers, and the utilities, should take\n\n         19   collective responsibility and, correspondingly, work\n\n         20   constructively to develop long term solutions.\n\n         21              I say this because I want to make clear not every\n\n         22   problem at PJM will be fixed through changes of the\n\n         23   governance structure.  And, you know, certainly we will talk\n\n         24   about today the stakeholder process, the decision-making\n\n         25   process, and who gets input, and how much input, including\n\n\n\n\n\n                                                                       25\n\n\n\n          1   voting structures.\n\n          2              But these process-related challenges, even if we\n\n          3   can fix it quickly, we won't fix some of the technical and\n\n          4   market issues.  I just want to sort of set the stage to\n\n          5   make sure that our expectation of change, we set the proper\n\n          6   expectations for change.\n\n          7              But what is important is that these\n\n          8   process-related challenges, the answer to these challenges,\n\n          9   is swift decision-making.  You know, in some ways I think\n\n         10   about these questions in a very simple way.  How can we help\n\n         11   PJM make decisions made more swiftly?\n\n         12              The markets have always evolved.  Not just in PJM\n\n         13   but in all of the market design, all the market structures,\n\n         14   and their designs.  So, we need to make certain decisions,\n\n         15   understanding that these markets will evolve and we continue\n\n         16   to enhance them and improve them.\n\n         17              I want to just highlight two areas.  One is state\n\n         18   representation, when we discuss governance issues.  I\n\n         19   support, just like I supported, in Order 1920, strong state\n\n         20   representation.  I support having more representation from\n\n         21   consumer advocates, as well.\n\n         22              In PJM's decision-making process, in market\n\n         23   design, in system planning -- in system planning.\n\n         24              You know, coming from New England, I'm very\n\n         25   interested in how other regions might have included state\n\n\n\n\n\n                                                                       26\n\n\n\n          1   participation in their decision-making and how that can be\n\n          2   borrowed or that can enhance PJM's processes.\n\n          3              I'm very interested in hearing about formalized\n\n          4   options for states, and I know that in the last few weeks we\n\n          5   have heard from many stakeholders, including the state\n\n          6   representatives, of their proposal.  So today I hope to hear\n\n          7   more about that.\n\n          8              In the New England experience, I can speak\n\n          9   firsthand that states often are frustrated with ISOs' or\n\n         10   RTOs' decision-making process not formally inviting states\n\n         11   to be either at the center or even at the side in the voting\n\n         12   structure, so I think this is an important aspect of the\n\n         13   governance that we need to consider.\n\n         14              The second is stakeholder process.  Ultimately,\n\n         15   it's about speed to making decisions.  I don't claim to, you\n\n         16   know, know, and I hope to hear more about exactly how the\n\n         17   voting structures lead to either gridlock or swifter\n\n         18   decision making.  But I think, at this juncture, we really\n\n         19   need PJM and its leadership, along with stakeholders and\n\n         20   along with us, to make swift decisions.  In some ways you\n\n         21   might not make the perfect decisions, but we need to make\n\n         22   those decisions and then enhance them as we go along, and\n\n         23   I'm very interested in how either PJM or its stakeholders\n\n         24   bring ideas about how we can, sort of, get through this\n\n         25   gridlock and trying to get on with some of the reform that's\n\n\n\n\n\n                                                                       27\n\n\n\n          1   necessary for the markets.\n\n          2              Again, I just want to say where I started.  I\n\n          3   want to make sure PJM succeeds, and I'm confident that PJM\n\n          4   will overcome the challenges of today.  So, with that, I\n\n          5   hand it back to you, Chair.\n\n          6              CHAIRMAN SWETT:  Thank you.  LaCerte?\n\n          7              COMMISSIONER LACERTE:  Good morning.  James,\n\n          8   welcome back.  Thank you for your continued service over at\n\n          9   DOE.  Peter Lake, welcome back to the building.  I know\n\n         10   today is a big day for the White House, with their\n\n         11   \"Ratepayer Protection Pledge 2.0.\"  It's a big day for our\n\n         12   nation.  There's a lot of governors in town.  There's a lot\n\n         13   of utility leaders in town.  So, I want to thank the White\n\n         14   House and all the work you've done to continue to drive that\n\n         15   conversation forward.\n\n         16              Thank you for everyone here today, helping us\n\n         17   move forward with solutions to the impediments that we've\n\n         18   observed regarding PJM governance mechanics and the\n\n         19   stakeholder process.\n\n         20              I've said publicly that the status quo is\n\n         21   untenable, and that seems to be the public perception, the\n\n         22   perception of the Americans that rely on PJM, and the\n\n         23   investors that are necessary to dig PJM out of the hole that\n\n         24   they find themselves in.\n\n         25              We have a diverse group of participants and\n\n\n\n\n\n                                                                       28\n\n\n\n          1   different perspectives, but we share a common interest in\n\n          2   ensuring that PJM is fully equipped to tackle the region's\n\n          3   operational and market challenges with the urgency that is\n\n          4   required of the moment.\n\n          5              PJM is confronting rapid, larger load growth,\n\n          6   from the proliferation of data centers, reindustrialization,\n\n          7   and at the same time the capacity market is under increasing\n\n          8   pressure to send the right investment signals, while\n\n          9   maintaining reliability and affordability in a tighter\n\n         10   resource environment.\n\n         11              Transmission planning is also becoming more\n\n         12   complex, as PJM must better anticipate where new generation\n\n         13   and load will emerge, accelerate needed upgrades, and\n\n         14   coordinate long term regional planning with greater speed\n\n         15   and certainty.  Addressing these challenges requires an\n\n         16   effective and inclusive stakeholder process, and a board\n\n         17   that is responsive, decisive, and accountable.\n\n         18              Success today will be measured not by the number\n\n         19   of viewpoints expressed or the ability of one stakeholder to\n\n         20   advocate their position over others, but by your ability to\n\n         21   build consensus.  PJM has a binding stakeholder process that\n\n         22   is untransparent and designed to protect the interests of\n\n         23   those who profit.  The days of this being acceptable\n\n         24   management structure for our nation's largest grid operator\n\n         25   are in the past.\n\n\n\n\n\n                                                                       29\n\n\n\n          1              Operating a regional grid is much like a team\n\n          2   sport.  You know, we have the stakeholders that are the\n\n          3   players on the field, we have the board, who operate as the\n\n          4   referee.  But PJM operates this in a little bit different\n\n          5   manner.  The players get to call the shots that the referees\n\n          6   inherently have to make, and it creates a conflict in which\n\n          7   it drives the players to unilaterally advocate for their own\n\n          8   positions and their own bottom lines.\n\n          9              To make matters worse, if the players on the\n\n         10   field do not like the calls that the referees make, guess\n\n         11   what.  They can replace those referees that are more\n\n         12   beneficial, to ones that are going to make the calls that\n\n         13   are more beneficial to their area.  So, this is an\n\n         14   unsustainable operation that we have, at PJM.\n\n         15              Today's discussion should be more than just an\n\n         16   exchange of ideas or an airing of grievances.  The dialogue\n\n         17   today should take the tenor of a negotiation or mediation,\n\n         18   candid, respectful, and focused on finding workable common\n\n         19   ground.\n\n         20              I told you previously that I expect all parties\n\n         21   here to have settlement authority and to make your positions\n\n         22   known.  That sometimes means ceding ground when you have a\n\n         23   stalemate, and trusting that with a strong record of success\n\n         24   in other RTOs these changes will be good for continued\n\n         25   business and investment in PJM, and thus good for the\n\n\n\n\n\n                                                                       30\n\n\n\n          1   public.\n\n          2              We'll talk today about accountability and\n\n          3   transparency.  These objectives not only apply to the\n\n          4   PJM board but to the stakeholders as well.\n\n          5              By the end of the summer I'd like to see an\n\n          6   agreement in principle for an instrument with common sense\n\n          7   reforms, that are negotiated through this technical\n\n          8   conference.  And, if that doesn't happen, I want to know\n\n          9   why, I want to know where the roadblocks are, and my fellow\n\n         10   commissioners and I will take independent action to protect\n\n         11   the public.\n\n         12              Let's get started.\n\n         13              CHAIRMAN SWETT:  Thank you.  Alandro, we're ready\n\n         14   to proceed.\n\n         15              MR. VALDEZ:  Thank you, Chairman.\n\n         16              We will now hear from our invited speakers.  We\n\n         17   have James P. Danly, Deputy Secretary of the Department of\n\n         18   Energy, and Peter Lake, Senior Director of Power at the\n\n         19   White House's National Energy Dominance Council.  Chairman.\n\n         20              CHAIRMAN SWETT:  Thank you, Secretary Danley, for\n\n         21   being here today.  We are very much looking forward to your\n\n         22   remarks and really appreciate the time that you have taken\n\n         23   to be with us, because of the gravity of this issue.\n\n         24              SECRETARY DANLY:  Thank you.\n\n         25              So, it is a pleasure to be back here.  You can\n\n\n\n\n\n                                                                       31\n\n\n\n          1   imagine how much fun it is for me to return to the hearing\n\n          2   room.  Other than poking my head in a little while ago to\n\n          3   see that my portrait was properly aligned -- (laughter) -- I\n\n          4   haven't been here since I left, in 2025.\n\n          5              So anyway, the purpose of this technical\n\n          6   conference couldn't be more important.  PJM has had quite a\n\n          7   few problems.  We'll get into that in a second. \n\n          8              First, I just want to say how much fun it is to\n\n          9   see former colleagues, Joe McClelland and my long-suffering\n\n         10   deputy, David Morenoff when I was general counsel, and John\n\n         11   Katz, my partner in labor, and so many other people here. \n\n         12   It's great to see you.\n\n         13              And I have to say, also, that I am gratified and\n\n         14   a little bit surprised by the crowd we have here.  I don't\n\n         15   think I've ever seen the hearing room this full before. \n\n         16   That was even when we had truly-contentious questions up for\n\n         17   debate.  This is -- I mean, did I hear that is actually an\n\n         18   overflow room for this?  That's remarkable.\n\n         19              So I think we should all take a moment to wallow\n\n         20   in the fact that we're the kind of people who were excited\n\n         21   and invigorated to be here at 9:00 a.m. on a weekday, to\n\n         22   talk about RTO governance.  This is a special crew that we\n\n         23   have assembled.\n\n         24              (Laughter.)\n\n         25              SECRETARY DANLY:  So, I've written a lot about\n\n\n\n\n\n                                                                       32\n\n\n\n          1   PJM over the years, and I think everybody is aware of the\n\n          2   fact that I have pretty strong opinions on the subject. \n\n          3   And, before the technical conference begins, I'd like to say\n\n          4   that, at least from my standpoint, any of the critiques,\n\n          5   criticisms, and properly-laid charges at various parties'\n\n          6   feet does not include that of the staff of PJM.\n\n          7              There are truly excellent, capable, staff at PJM. \n\n          8   I think we all probably agree about that.  I think that Stu\n\n          9   is very talented.  I think Chris O'Hara is an excellent\n\n         10   lawyer.  Oh, and he's actually in the audience; I didn't\n\n         11   realize that.\n\n         12              (Laughter.)\n\n         13              SECRETARY DANLY:  So, avert your -- I didn't see\n\n         14   you before -- avert your eyes.  Pretend you didn't hear\n\n         15   that.\n\n         16              It is not the technical capacity of PJM's staff,\n\n         17   who are truly talented; it is something much more\n\n         18   fundamental than that.  So, I just want to highlight that\n\n         19   one point first, so that everybody understands that we're\n\n         20   talking about the mechanics of the institution and not about\n\n         21   the individual people who work at PJM, who are very good,\n\n         22   who have a very challenging problem set in front of them.\n\n         23              That being said, PJM is a mess.  Right?  This is\n\n         24   a market that has committed what I would consider to be some\n\n         25   of the gravest crimes against the FPA that we have witnessed\n\n\n\n\n\n                                                                       33\n\n\n\n          1   in the history of the Commission.  Right?\n\n          2              Shortening auction cycles, to make it more\n\n          3   difficult to deploy capital.  Right?  Re-running auctions in\n\n          4   obvious violation -- and I said it at the time -- obvious\n\n          5   violation of the filed rate doctrine.  Pure madness.  Right?\n\n          6              We've had an institution that has not wanted to\n\n          7   show confidence in its own reliability pricing model. \n\n          8   Right?  That mechanism was one of the great frontiers that\n\n          9   was created in the concept of organized markets.  The entire\n\n         10   mechanism established was supposed to take into account the\n\n         11   signs of scarcity and super abundance and then correct\n\n         12   organically to those over time, and when we got to a point\n\n         13   of scarcity signal, that caused people to panic, and a\n\n         14   complaint was mooted out with a self-imposed restriction on\n\n         15   the prices that are necessary to get formation.\n\n         16              What do we have now?  Two auctions in a row that\n\n         17   failed to meet the capacity requirement.  That is not a\n\n         18   functioning market.  \n\n         19              One wonders what all that money is spent for, in\n\n         20   the capacity market.  It sounds to me like those rates may\n\n         21   be not J and R.  If you were paying money for a capacity\n\n         22   market, to secure supply, and it doesn't happen, why are we\n\n         23   paying it?\n\n         24              I really do despair for the actual mechanics of\n\n         25   the market, and that is something that can be laid at the\n\n\n\n\n\n                                                                       34\n\n\n\n          1   feet of PJM very, very solidly.\n\n          2              So, what is the problem that we're facing, with\n\n          3   the governance of PJM?  It is, I think, fundamentally a\n\n          4   question of transparency and accountability.  Who is\n\n          5   responsible for what?\n\n          6              I was sitting right over there, where\n\n          7   Commissioner Rosner is, when we had another technical\n\n          8   conference.  I asked the question of everybody from PJM and,\n\n          9   in fact, Joe Bowring was there, and I said \"Who is responsible\n\n         10   for resource adequacy?\" and he said \"We all are.\"\n\n         11              That means nobody is.  Right?  You need to have\n\n         12   an absolutely clear line of responsibility and clear\n\n         13   authority.  So let's go back to the paradigm that I always\n\n         14   use when I want to chasten a market.  I talk about what the\n\n         15   paradigmatic utilities, the vertically-integrated IOU, in an\n\n         16   old-fashioned state, how they operate.\n\n         17              You have a CEO, who is responsible to a board of\n\n         18   directors, who is, himself -- or who are, themselves --\n\n         19   responsible to shareholders.  All of them are subject to the\n\n         20   oversight of a public utility commission, and they are all\n\n         21   subject to the state laws that require them to serve their\n\n         22   customers.\n\n         23              In the case of an RTO, it's just a different\n\n         24   model.  And in the case of PJM it's unclear exactly who it\n\n         25   is that's responsible for what.\n\n\n\n\n\n                                                                       35\n\n\n\n          1              I will note that in PJM's governing documents,\n\n          2   while there's plenty of talk about the capacity market\n\n          3   itself, there is very little when it comes to public\n\n          4   interest.  Right?  These are not the same institutions as\n\n          5   the IOUs created in a regulatory compact that guarantees a\n\n          6   franchise monopoly in return for serving every single\n\n          7   person in their franchise territory with the service that is\n\n          8   necessary, or at least deemed necessary by the public fiat. \n\n          9   Right?  It's not the same model.\n\n         10              It is not the way PJM works, where you have that\n\n         11   clear line of demarcation who's responsible for what. \n\n         12   Instead, we don't really know who does what, in PJM or, you\n\n         13   know -- this is particularly problematic, because not only\n\n         14   do we have a tension in the basic structure of an\n\n         15   independent board, and I take Commissioner LaCerte's point\n\n         16   here, that the board is only independent insofar as it is\n\n         17   chosen by the people that are going to be overseen by it, so\n\n         18   there is a complexity there, and it is a real tension.\n\n         19              I think that when you have self-interested\n\n         20   stakeholders -- and, by the way, nothing wrong with being\n\n         21   self-interested.  Right?  Every adjudicator relies upon the\n\n         22   pleadings of self-interested parties.  That's fine.  But we\n\n         23   do have a question of what board independence means, when\n\n         24   you have the self-interested parties actually having a say\n\n         25   in who the board members are.\n\n\n\n\n\n                                                                       36\n\n\n\n          1              But it's even worse than just that tension. \n\n          2   Further, we have the issue that the filing rights are split\n\n          3   between any number of different parties.  Right?  You have\n\n          4   the board has some filing rights.  They can direct PJM to\n\n          5   make filings on some subjects.  You have a stakeholder\n\n          6   process.  The TO's have retained some of theirs in the\n\n          7   operating agreement.\n\n          8              That means that we are deviating from the basic\n\n          9   premise of the Federal Power Act and, indeed, basically\n\n         10   every state commission law, which is you have a utility that\n\n         11   files its tariff revisions.  Right?  When you have it broken\n\n         12   down into different committees, and subcommittees, and\n\n         13   boards, you know, it's sort like \"Committees and board,\n\n         14   utilities, oh my!\"  The are so many different parties that\n\n         15   are playing the game that it's impossible to know exactly\n\n         16   who's doing it and to have a coherent picture.  That is\n\n         17   problematic.\n\n         18              I think that splitting those rights in the way\n\n         19   that they have been has been hard.  And then, on top of\n\n         20   that, we have the actual misery that is the PJM stakeholder\n\n         21   process.\n\n         22              So, a quick poll in the room.  How many people\n\n         23   have, at any times in their lives, endured any part of the\n\n         24   torture that is a stakeholder meeting?  Raise hands.\n\n         25              (There was a show of hands.)\n\n\n\n\n\n                                                                       37\n\n\n\n          1              SECRETARY DANLY:  Okay.  Now, put the hands down. \n\n          2   How many of you enjoyed it?\n\n          3              (Laughter.)\n\n          4              (There was a show of hands.)\n\n          5              SECRETARY DANLY:  Oh, come on!  (Laughs.)  There\n\n          6   is always one or two.  All right.\n\n          7              So, I actually believe you guys.\n\n          8              (Laughter.)\n\n          9              SECRETARY DANLY:  So, I do not enjoy them, and I\n\n         10   think that the fact that everybody else kept their hands\n\n         11   down -- and this isn't a shy audience; they all raised their\n\n         12   hands before -- I think that we have learned that, other\n\n         13   than the two masochists here --\n\n         14              (Laughter.)\n\n         15              SECRETARY DANLY:  -- this is not a process that\n\n         16   people like and it certainly is not one that delivers good\n\n         17   results.  Right?\n\n         18              We have had cases in which issue charges that are\n\n         19   critical cannot make it over the threshold even to be fully\n\n         20   considered.  And these are things that everybody would even\n\n         21   acknowledge that they want to see handled and talked about,\n\n         22   but the formal process does not allow for it.\n\n         23              I don't know.  I am glad that the Chairman\n\n         24   convened this.  I think it's long overdue.  \n\n         25              The worry that I have, to the extent that I have\n\n\n\n\n\n                                                                       38\n\n\n\n          1   one, is that in the inevitable arguments that are going to\n\n          2   ensue that were going to lose sight of the actual\n\n          3   substantive issues that have to be dealt with.  Right? \n\n          4   Because PJM has real problems in the way that it operates\n\n          5   its market.  \n\n          6              So we have this question about the long term\n\n          7   viability of the construct, but we also have another\n\n          8   question, which is \"What are we going to do right now about\n\n          9   the capacity market?  What are we going to do about the fact\n\n         10   that we're gigawatts short and we need to get that capacity\n\n         11   as quickly as possible?\"\n\n         12              What are we going to do about the\n\n         13   interconnection, both for load and gen?  These are the\n\n         14   substantive issues that need immediate resolution, because\n\n         15   PJM is -- I forget who said it, I'm sorry -- the first wave\n\n         16   of data centers being developed, have been developed there. \n\n         17   There is huge demand.  We are facing demand signals like\n\n         18   we've never seen before, certainly not in my entire time in\n\n         19   utility, and PJM has frictions that need to be fixed\n\n         20   immediately.\n\n         21              So my charge to everyone, both the Commission and\n\n         22   everybody in attendance, is while trying to work through this\n\n         23   subject of governance reform -- right? -- don't lose sight\n\n         24   of the fact that we actually have to fix the problems that\n\n         25   are inhibiting the biggest problem we have, which is getting\n\n\n\n\n\n                                                                       39\n\n\n\n          1   as much supply on line as quickly as possible, and doing so\n\n          2   while protecting rate payers.  Right?  That is the number\n\n          3   one priority and it cannot be forgotten.\n\n          4              In everything we're doing, in all of our federal\n\n          5   policy, what we're trying to do is get as much supply\n\n          6   developed and put in service as quickly as we can, while\n\n          7   protecting the rate payer.  That is the objective that\n\n          8   everybody shares, here at PJM, and PJM's board, as an\n\n          9   institution, needs to recommit itself to the market\n\n         10   functions that it was originally designed to oversee and\n\n         11   execute, and they need to do it protecting the rate payer\n\n         12   and getting as many of those obstacles out of the way as\n\n         13   they can.\n\n         14              So, we're shortly going to be entitled to hear a\n\n         15   bunch of people talk, and I am looking forward to it.  I am\n\n         16   actually going to be leaving.  I will look at it later,\n\n         17   though.\n\n         18              (Laughter.)\n\n         19              SECRETARY DANLY:  I will listen to it later.  And\n\n         20   I'm looking forward to it.  I am curious, though, to see who\n\n         21   advocates for what.\n\n         22              And, going back to this point about\n\n         23   self-interested parties, like, you know, we're going to,\n\n         24   doubtless, hear various people say that \"I, I alone, am the\n\n         25   one that should have the filing rights of this type or\n\n\n\n\n\n                                                                       40\n\n\n\n          1   another.\"  Arrogations of authority to make one type of\n\n          2   filing or another kind.\n\n          3              And we have to think about who they are and what\n\n          4   they're asking for.  Right?  So, doubtless the states are\n\n          5   going to say that the states should have more of a say. \n\n          6   Perhaps they should.  I'm agnostic as to the exact structure\n\n          7   that PJM will ultimately take.\n\n          8              But remember that the states, at least from my\n\n          9   witnessing it over the years, seem to only agree on thing,\n\n         10   which is that PJM needs reform.  I haven't seen a whole lot\n\n         11   of common consensus on other subjects besides that.\n\n         12              So, to the extent to which you think the states\n\n         13   are going to be the salvation of PJM, just think to\n\n         14   yourself, of any potential 205 or -- you know, filing that\n\n         15   might come out -- how many of the states are going to agree?\n\n         16              We're going to have TOs that are going to\n\n         17   advocate for one policy or another.  They who plan on, you\n\n         18   know, load forecasts that don't necessarily eventuate --\n\n         19   right? -- we're going to have a board who is going to ask\n\n         20   for more specific authorities, who have been reluctant to\n\n         21   exercise those authorities that they have now, even in the\n\n         22   face of capacity shortfalls.\n\n         23              So, I think a certain amount of clear-eyed -- a\n\n         24   clear-eyed view of how the different stakeholders, all of\n\n         25   whom, as I say, are self-interested -- and that is just fine\n\n\n\n\n\n                                                                       41\n\n\n\n          1   -- how it is they're going to see their roles, and a bit of\n\n          2   deliberation and discretion is going to be called for from\n\n          3   the Commission when listening to everything that's said\n\n          4   here.\n\n          5              What is the ultimate objective?  I think we\n\n          6   should all understand that when we try to figure out the\n\n          7   ultimate governance structure what are we looking for.  We\n\n          8   want a transparent process for all of the filings that PJM\n\n          9   makes and the way PJM operates, including its board.  We\n\n         10   want the board to not be shrouded in mystery or secrecy; we\n\n         11   want to know what's going on.\n\n         12              We want the responsibilities to be clearly\n\n         13   outlined, who is responsible for what.  Right?  I'm not\n\n         14   saying we have to go full-on vertically-integrated IOU,\n\n         15   although I am a fan, but we need to know who is responsible\n\n         16   for what part of the market.\n\n         17              And the idea of saying that we're all\n\n         18   responsible, we're all responsible for resource adequacy,\n\n         19   simply cannot be true.\n\n         20              I have in mind an Alexander Pope quote, which\n\n         21   I'll spare you, but the basic gist is if you honor everybody\n\n         22   you honor no one.  The same thing with responsibility.  And\n\n         23   what we need to do is keep in mind that the PJM was created\n\n         24   to administer a market, to harness market forces, in a\n\n         25   utility paradigm that's not perfectly apposite to it, and\n\n\n\n\n\n                                                                       42\n\n\n\n          1   though the markets can deliver miraculous results for the\n\n          2   rate payer, they don't do it when you have constant chopping\n\n          3   and changing, and you make things -- you make it impossible\n\n          4   for capital to be deployed.\n\n          5              It simply will not work if that happens.  So, we\n\n          6   want stability, as well.\n\n          7              So, that's my two cents.  Chairman Swett, I\n\n          8   really appreciate the opportunity to come back to FERC, just\n\n          9   to bask in the room again.  And I appreciate everyone's\n\n         10   attention.  Thank you.\n\n         11              (Applause.)\n\n         12              CHAIRMAN SWETT:  I would pay way more than two\n\n         13   cents for those remarks.  Thank you.\n\n         14              (Laughter.)\n\n         15              CHAIRMAN SWETT:  That was quite the homecoming. \n\n         16   We really appreciate your time, Secretary, and that was very\n\n         17   insightful framing for today.\n\n         18              Next we have the honor of introducing Peter Lake,\n\n         19   Senior Director of Power at the White House's National\n\n         20   Energy Dominance Council.\n\n         21              MR. LAKE:  Thank you, Chairman.  Thank you,\n\n         22   commissioners, for having me today.  And more importantly,\n\n         23   thank you for convening this very important technical\n\n         24   conference.  Like Commissioner See said, there are technical\n\n         25   conferences and there are technical conferences.  I\n\n\n\n\n\n                                                                       43\n\n\n\n          1   appreciate your leadership in calling this today.\n\n          2              And, before I start, I want to echo Secretary\n\n          3   Danly's comments about and appreciation for the staff of PJM\n\n          4   and, especially from the White House perspective, appreciate\n\n          5   the on-going dialogue we've had with the executive team and\n\n          6   the board, for many, many months, dating back to 2025.  So,\n\n          7   I appreciate that open communication.\n\n          8              But we're here for a reason.  And this White\n\n          9   House very much wants PJM to succeed, but will not tolerate\n\n         10   continued failure.  \n\n         11              The President will be gathering later today with\n\n         12   multiple utilities, data center developers, co-ops,\n\n         13   governors, state legislators, to acknowledge the expansion\n\n         14   of the \"rate payer protection pledge\" that established a\n\n         15   framework for investment in our power grid by the most\n\n         16   highly-valued companies in the history of markets.  There is\n\n         17   an avalanche of capital waiting to be invested in this power\n\n         18   grid.\n\n         19              Our President has established a framework by\n\n         20   which that investment can be made, to not only ensure\n\n         21   continued American lead, leadership, in AI, to continue\n\n         22   powering our reindustrialization, but to do it in a manner\n\n         23   that protects the average household citizens, protects our\n\n         24   small businesses, so yes, we can build the big\n\n         25   infrastructure this country needs.  Yes, we can maintain\n\n\n\n\n\n                                                                       44\n\n\n\n          1   America's lead in AI, and also protect residents and small\n\n          2   businesses.  But we cannot do it in a broken system like\n\n          3   PJM.\n\n          4              You'll hear a lot of details today about the\n\n          5   technicalities and mechanics of how these reforms should\n\n          6   take place.  I'll spare you my thoughts on the details of\n\n          7   those.  I won't add to the nuts and bolts.\n\n          8              But I will offer some observations from someone\n\n          9   who has dealt with a failed power grid.\n\n         10              We've been there before.  The bad news is that\n\n         11   PJM is broken.  The good news is we know how to fix power\n\n         12   grids, in this country.\n\n         13              When I took over responsibility of the Texas\n\n         14   power grid, in April of 2021, I inherited a power grid that\n\n         15   had been four minutes and 37 seconds away from total black\n\n         16   start failure, that would have caused millions of people to\n\n         17   be without power for not days but weeks.  Many people in\n\n         18   this room are familiar with that.\n\n         19              That was a very tough few years, righting that\n\n         20   ship, and turning ERCOT around.  But thanks to decisive\n\n         21   leadership from Texas Governor Greg Abbott, the Texas\n\n         22   legislature, some outstanding folks on the ERCOT team, and\n\n         23   some incredible folks at the Public Utility Commission of\n\n         24   Texas, we did it.\n\n         25              And, today, ERCOT, five years later, stands as a\n\n\n\n\n\n                                                                       45\n\n\n\n          1   great example of how to build big infrastructure in this\n\n          2   country while also delivering power at affordable prices, to\n\n          3   all of your citizens.\n\n          4              The important part of why I bring up the ERCOT\n\n          5   experience is that while the mechanical parts of that\n\n          6   failure during winter storm Uri were about wellheads\n\n          7   freezing over and pipes freezing up, and fuel access being\n\n          8   constricted, the root cause of that failure was a failed\n\n          9   governance structure and a failed stakeholder process, the\n\n         10   same ills that haunt PJM today.\n\n         11              PJM is clearly broken, multiple failed capacity\n\n         12   markets, capacity auctions, sky high price increases.  And\n\n         13   to be clear, when we throw around the term \"failed capacity\n\n         14   auction,\" to be clear, for the general public out there,\n\n         15   that means that in the winter of 2028-2029, in the event if\n\n         16   another -- not even \"in the event\" -- when another winter\n\n         17   storm comes, when another Winter Storm Fern hits, the PJM\n\n         18   market will be short six to eight hundred megawatts. \n\n         19   That's what that means.\n\n         20              This market will not have enough power, a supply\n\n         21   of power, to meet demand, in the winter of '28-'29 -- that's\n\n         22   two winters from now -- when we have another cold... and if\n\n         23   we don't have a cold winter storm in '28-'29, we'll have one\n\n         24   in '29-'30.  That's what a failed capacity auction means. \n\n         25   It has real impacts, on real people on the ground.\n\n\n\n\n\n                                                                       46\n\n\n\n          1              And to Secretary Danly's point earlier, markets\n\n          2   only work if you let them work.  If we're not going to let\n\n          3   this market work, let's stop pretending that PJM has a\n\n          4   market.  The cure for higher prices are high prices.  The\n\n          5   cure for low prices is low prices.  If we're going to have a\n\n          6   market, we've got to let it work.\n\n          7              And, perhaps there is no greater testament to the\n\n          8   failure of the existing stakeholder process than the fact\n\n          9   that when, as the Secretary said, the rare occasion that all\n\n         10   13 governors in PJM actually agreed on something, in the\n\n         11   statement of principles, along with Secretary of Energy\n\n         12   Chris Wright, Secretary of Interior and Chairman of the\n\n         13   National Energy Dominance Council Doug Burgum, and the\n\n         14   President of the United States, all agreed on a path forward\n\n         15   to redress the most acute problem facing PJM, the lack of\n\n         16   reliable, dispatchable, power, as it has evidenced in the\n\n         17   failed capacity auctions, with the alignment of all of those\n\n         18   stars, this system, this stakeholder process at PJM, could\n\n         19   still -- still -- not deliver, even without all of that\n\n         20   alignment.  No better indication that this is broken.\n\n         21              And this is the only industry in the world that\n\n         22   can stare in the face of trillions of dollars of expected\n\n         23   investment and argue amongst each other so effectively as to\n\n         24   scare off that investment.  The technology world is begging\n\n         25   to invest in this market, in this infrastructure, in these\n\n\n\n\n\n                                                                       47\n\n\n\n          1   utilities, and the failure of this system to move forward\n\n          2   productively in the stakeholder process, to move forward\n\n          3   productively, is scaring away that investment.\n\n          4              At the end of the day, the core function of PJM,\n\n          5   and any grid provider in the United States, is to delivering\n\n          6   reliable, affordable, power, to homes and businesses.  And,\n\n          7   like the Secretary said, when everyone is accountable, no\n\n          8   one is accountable.  We experienced that in ERCOT before\n\n          9   Winter Storm Uri.  Everyone was accountable.  The market\n\n         10   was accountable.  The stakeholders were accountable.  The\n\n         11   legislature was sort of accountable.  But nobody was truly\n\n         12   accountable.\n\n         13              And we have, again, other examples around the\n\n         14   country of how to do this right.  That's the good news.  We\n\n         15   know how to fix this.\n\n         16              ERCOT is in the midst of the early stages of one\n\n         17   of the largest transmission buildouts in American history,\n\n         18   with the 765KV lines out to west Texas.  That's a lot of\n\n         19   happy capital being deployed.  That's a lot of happy\n\n         20   investors that are able to grow their businesses, grow their\n\n         21   invested capital base.  That doesn't happen in PJM.\n\n         22              At risk of only talking about ERCOT, as the Texas\n\n         23   representative, MISO just next door has a very\n\n         24   well-functioning market, that is building things.  Happy\n\n         25   investors.  Happy stakeholders.  Reliable grid operations.\n\n\n\n\n\n                                                                       48\n\n\n\n          1              When I took over in Texas, and for the next 2-1/2\n\n          2   years, ERCOT did not experience any EEA event.  None.  PJM\n\n          3   has experienced two this month.  That's not a stable grid\n\n          4   and that's certainly not a grid poised for growth and ready\n\n          5   to accept the capital investment that the world is waiting\n\n          6   to put into this ecosystem.\n\n          7              In winter storm Fern, again, PJM, near miss. \n\n          8   Kudos to the control room at PJM, kudos to the team on the\n\n          9   ground at PJM for keeping the lights on.  But another EEA\n\n         10   event -- energy emergency event.  Barely got by.  Excellent work.\n\n         11   Those are not easy to get through.\n\n         12              But again, in a testament to know how to do this. \n\n         13   We know how to fix this, in this country.  ERCOT walked\n\n         14   through winter storm Fern and shrugged it off.  Five years\n\n         15   earlier, a similar storm broke the back of that grid.\n\n         16              MISO, similar outcome.\n\n         17              And it's important.  I mention ERCOT and MISO\n\n         18   because both of those grids have almost diametrically\n\n         19   opposite regulatory regimes.  And yes, every grid is\n\n         20   different, every grid is unique, and those are two very\n\n         21   different grids that somehow manage to function quite well.\n\n         22              What do they have in common?  ERCOT is fully\n\n         23   deregulated and MISO is all vertically integrated utilities. \n\n         24   What do they have in common?  They have a stakeholder\n\n         25   process that provides member companies a voice but not a\n\n\n\n\n\n                                                                       49\n\n\n\n          1   veto, and they have an independent empowered board that can\n\n          2   make decisions in the public interest without being so\n\n          3   fearful of the members \"jumping on their shadow\" that\n\n          4   they're forced into inaction.\n\n          5              Change is coming to PJM, one way or the other. \n\n          6   As we can see with the failed capacity auctions, in a few\n\n          7   years PJM won't be able to handle winter storm Fern.  They\n\n          8   won't be able to handle, as they didn't handle, winter storm\n\n          9   Elliott.  And those are only going to get worse and worse.\n\n         10              So, whether it's a coming affordability crisis or\n\n         11   a major load shed event, change is coming.  My hope -- and I\n\n         12   believe it's the hope of this commission, is that the change\n\n         13   can come sooner than that.  It can be proactive,\n\n         14   collaborative, change, led by this commission, led by the\n\n         15   stakeholders, led by the board.\n\n         16              State leadership is demanding change.  FERC is\n\n         17   demanding change.  The White House is demanding change. \n\n         18   Investors are demanding change.\n\n         19              We need to let this market function.  We need to\n\n         20   put in the reforms that we know lead to positive outcomes,\n\n         21   that lead to broader investment, better outcomes, more\n\n         22   reliability, and lower prices for our citizens, our\n\n         23   businesses, and the data centers and technology companies\n\n         24   that we're counting on to maintain America's lead in AI.\n\n         25              We need to align authority with accountability. \n\n\n\n\n\n                                                                       50\n\n\n\n          1   The states must have a more substantial role.  They also\n\n          2   need to bring more to the table.  As was mentioned earlier,\n\n          3   the states have a key role in siting, permitting, and cost\n\n          4   allocation.  They need to step up to the plate as well.\n\n          5              PJM must identify \"the north star.\"  What is our\n\n          6   guiding light?  What is the compass that guides every action\n\n          7   in this grid?  It cannot exist purely for the profit of the\n\n          8   companies that operate in it.  Reliability and\n\n          9   affordability.\n\n         10              PJM needs an independent, transparent, board,\n\n         11   that can take action and make tough decisions, without fear\n\n         12   of being fired after every board meeting.\n\n         13              They need a functional stakeholder process.  And\n\n         14   I'll be the first to say, after a lot of tussles in Texas\n\n         15   with the stakeholders and the advisory group down there, it\n\n         16   is incredibly important.  Again, aligning accountability\n\n         17   with affordability.  The governors have accountability but\n\n         18   so do the stakeholders.\n\n         19              They're the ones that have to live with the\n\n         20   technical realities on the ground, of running the power\n\n         21   plants, operating the transmission system.  They need a\n\n         22   voice in the stakeholder process but it cannot be a veto.\n\n         23              We must accelerate gen and load interconnect in\n\n         24   PJM, and we must immediately implement the statement of\n\n         25   principles that were agreed upon by all 13 governors and the\n\n\n\n\n\n                                                                       51\n\n\n\n          1   President of the United States to deliver the reliable,\n\n          2   dispatchable, power that we need.  Quickly.\n\n          3              Texas didn't have the chance to right the ship\n\n          4   before the tragedy of winter storm Uri.  I hope the\n\n          5   companies in PJM, the PJM executive team and board, will\n\n          6   take the chance to right the ship in PJM.  Change is coming,\n\n          7   one way or the other.  I hope it's proactive, collaborative,\n\n          8   and yields great results for the people of PJM, the\n\n          9   companies that operate in PJM, and PJM the entity that\n\n         10   keeps the lights on.\n\n         11              Never before has there been so much investment\n\n         12   poised to deploy in our US power grid, and especially in\n\n         13   PJM.  I'm speaking to a group of investors later today that\n\n         14   represent over a trillion dollars in capital, and they're\n\n         15   wondering why they would strand their capital in a broken\n\n         16   PJM system.  We should be able to tell them that that is an\n\n         17   opportunity.\n\n         18              We've never before had a framework agreed upon\n\n         19   across the entire political spectrum that allows, provides,\n\n         20   a blueprint to build infrastructure at a pace never before\n\n         21   seen in this country, at a scale never before seen in this\n\n         22   country, and protect rate payers, protect the average\n\n         23   household citizen.\n\n         24              The President will be holding that event later\n\n         25   this afternoon.  Over 200 utilities, co-ops, data center\n\n\n\n\n\n                                                                       52\n\n\n\n          1   developers, governors, legislators, representing 80 percent\n\n          2   of all the power delivered in this country, are signed onto\n\n          3   the President's rate payer protection pledge.  That is a\n\n          4   blueprint on how to do this.  I hope PJM can take advantage\n\n          5   of that.\n\n          6              And so, in closing, please, be proactive.  Seize\n\n          7   the opportunity to deliver this change.  Work together.  And\n\n          8   please find a way to get to yes.\n\n          9              Thanks, Chairman.\n\n         10              (Applause.)\n\n         11              CHAIRMAN SWETT:  Thank you, Peter. \n\n         12   Congratulations on your historic deal that you helped\n\n         13   broker.  And sorry the most powerful Americans can't be\n\n         14   there this evening to celebrate.  (Laughs.)\n\n         15              (Laughter.)\n\n         16              CHAIRMAN SWETT:  And back to you, Alandro.\n\n         17              MR. VALDEZ:  Thank you, Chairman.\n\n         18              We will now start with our first panel, on the\n\n         19   aspects of PJM's governance mechanics that may impede PJM's\n\n         20   ability to address operational and market needs.  The\n\n         21   panelists include a PJM representative, representatives from\n\n         22   PJM states, members of the five PJM member sectors, and\n\n         23   others.\n\n         24              Each panelist submitted in advance a statement\n\n         25   that includes their position on the questions on the\n\n\n\n\n\n                                                                       53\n\n\n\n          1   counsel's agenda.  To maximize the amount of time for\n\n          2   discussion, we will be foregoing opening remarks from\n\n          3   panelists, to go directly to the questions from the Chairman\n\n          4   and the commissioner.\n\n          5              Please, if you're on panel one, please come up.\n\n          6              (Pause.)\n\n          7              MR. VALDEZ:  Panelists, to answer a question from\n\n          8   the Chairman or the commissioners, please tip your name tent\n\n          9   like so.  When you are called on, you will know when your\n\n         10   mic is on when the LED is glowing green.  There is a gray\n\n         11   button at the base of the microphone that you have to press,\n\n         12   to turn it on.\n\n         13              To maximize the time of the discussion, please\n\n         14   keep your answer concise.\n\n         15              I'd like to introduce our panel one panelists\n\n         16   before I turn it back to the Chairman.  First, we have David\n\n         17   Mills, President and CEO of PJM Interconnection, L.L.C.\n\n         18              Next to him we have Pat Wood, Executive Chairman\n\n         19   of the Hunt Energy Network.\n\n         20              Then we have Kelsey Bagot, the Chair of the\n\n         21   Virginia State Corporation Commission.\n\n         22              Next to her we have Jacob Finkel, Deputy\n\n         23   Secretary of Policy for Pennsylvania Governor Josh Shapiro's\n\n         24   Office.\n\n         25              Then we have Stacey Burbure, Senior Vice\n\n\n\n\n\n                                                                       54\n\n\n\n          1   President of Transmission Regulatory Engagement and\n\n          2   Compliance at American Electric Power.\n\n          3              Then we have Marjie Rosenbluth Philips, Senior\n\n          4   Vice President of Wholesale Market policy, at LS Power.\n\n          5              Then finally we have Maria Gulluni, Vice\n\n          6   President, General Counsel and Chief Compliance Officer for\n\n          7   ISO New England.\n\n          8              Welcome, panel.  I'll now turn it over to\n\n          9   Chairman Swett to ask the questions.\n\n         10              CHAIRMAN SWETT:  Good morning, everyone.  Thank\n\n         11   you for being here.  You all were very deliberately selected\n\n         12   for your expertise, your backgrounds, the organizations you\n\n         13   represent, and you are all specifically sitting here because\n\n         14   this commission is very interested in what you have to say. \n\n         15   So, we really appreciate your time and the preparation that\n\n         16   went into your testimony, and your being here.\n\n         17              And, like I said in the beginning, we would\n\n         18   really appreciate your candor.  We want to dig in today and\n\n         19   really drive toward some solutions.  So, we very much\n\n         20   appreciate that.\n\n         21              I'm going to start with Stacey from AEP.  So,\n\n         22   many people, obviously, have heard that AEP is considering\n\n         23   leaving the market.  And, for a lot of us, that was a huge\n\n         24   alarm bell for us, looking at the markets across the\n\n         25   country, that a utility like AEP would be considering\n\n\n\n\n\n                                                                       55\n\n\n\n          1   publicly such a move.  So, can you please help us\n\n          2   understand what led AEP to consider that option and what\n\n          3   solutions you would like to see in order to recalibrate how\n\n          4   you're thinking about PJM?\n\n          5              MS. BURBURE:  Thank you for the question,\n\n          6   Chairman.\n\n          7              And before I begin, I'd like to thank the\n\n          8   Commission for its leadership in convening this technical\n\n          9   conference and for recognizing the importance of PJM\n\n         10   governance to the future of the electric grid.\n\n         11              As Peter Lake outlined, I also want to\n\n         12   acknowledge the unique bipartisan leadership of the PJM\n\n         13   governors, the Department of Energy, the White House, and\n\n         14   FERC.  The fact that leaders across political parties and\n\n         15   across federal and state governments have come together\n\n         16   around the need to strengthen PJM governance underscores\n\n         17   that this is not a partisan issue; it is a reliability,\n\n         18   affordability, and national competitiveness issue.\n\n         19              And that is the light through which AEP views its\n\n         20   membership in PJM.  Fundamentally, it's about our customers. \n\n         21   It's about whether we can meet the needs to bring on new\n\n         22   generation quickly and interconnect load.\n\n         23              We are at a crossroads, from a national security\n\n         24   standpoint, with respect to the need to meet this\n\n         25   imperative.\n\n\n\n\n\n                                                                       56\n\n\n\n          1              We also see the stakeholder process in PJM not\n\n          2   driving forth solutions.  There is continued deadlock, and\n\n          3   this is symptomatic.  It's seen in the market results, but\n\n          4   this has been an underlying issue in PJM for some time.\n\n          5              So, we need to see innovation.  We need concepts\n\n          6   like the accelerated load infrastructure, generation, and\n\n          7   network planning model that AEP has put forward, holistic\n\n          8   solutions, focused on speed, to meet the needs of customers.\n\n          9              And we also support a role for states, in terms\n\n         10   of what happens at PJM.  But that role must function with\n\n         11   accountability.\n\n         12              To Deputy Secretary Danley's point around\n\n         13   responsibility for resource adequacy, that question is\n\n         14   currently lacking at PJM.\n\n         15              So, this is the view through which we see the\n\n         16   question of PJM membership.  It's a question of can PJM be\n\n         17   fixed, and can it meet the needs of our customers.\n\n         18              CHAIRMAN SWETT:  Thank you for that explanation.\n\n         19              So, you specifically recommend an advisory\n\n         20   stakeholder structure with non-binding votes, in your\n\n         21   testimony.  What changes would you like to see the board\n\n         22   structure, composition, or selection criteria, that may be\n\n         23   necessary to complement the board's expanded authority under\n\n         24   an advisory stakeholder structure?\n\n         25              MS. BURBURE:  I want to say that AEP is\n\n\n\n\n\n                                                                       57\n\n\n\n          1   approaching this conversation in exactly the way that you've\n\n          2   requested, Chairman.  We are open to particular options with\n\n          3   respect to the composition of the board and what any reform\n\n          4   looks like.\n\n          5              Our focus is on \"Have we fixed the problem?  Have\n\n          6   we resulted in a governance structure that drives\n\n          7   solutions?\"\n\n          8              So, with respect to the board composition itself,\n\n          9   yes, we agree with Peter Lake's comment that stakeholders\n\n         10   should have a voice but not a veto, and we see the advisory\n\n         11   process in MISO working well.  We think that's something\n\n         12   that could be copied in cases, in terms of RTO governance\n\n         13   best practices.\n\n         14              With respect to the board, we agree with Deputy\n\n         15   Secretary Danly's remarks and some of the commissioner\n\n         16   remarks around transparency.  We agree with the need for\n\n         17   additional expertise with respect to the qualifications of\n\n         18   board members.\n\n         19              But there is no one particular issue on which we\n\n         20   are saying that this is a gating or threshold item, a must\n\n         21   have.  We are approaching this conversation holistically and\n\n         22   with an eye towards whether or not we've solved the problem.\n\n         23              So, we're at this table in a constructive fashion\n\n         24   and one that we hope is helpful to drive consensus.\n\n         25              CHAIRMAN SWETT:  Thank  you.\n\n\n\n\n\n                                                                       58\n\n\n\n          1              COMMISSIONER ROSNER:  Wonderful.  Thank you,\n\n          2   Chairman.\n\n          3              So, I just wanted to, first, turn to Maria\n\n          4   Gulluni for a question.  I was recently up in New England,\n\n          5   at the NECPUC, which is the state regulator convening up\n\n          6   there, and I was overwhelmed by how happy everyone was.\n\n          7              (Laughter.)\n\n          8              COMMISSIONER ROSNER:  All the state regulators\n\n          9   were happy with ISO, and, you know, some of my generator\n\n         10   friends had some things that they were concerned about but\n\n         11   overall felt well engaged.  And so I just wanted to ask you,\n\n         12   you know, my understanding is that a decade ago, and\n\n         13   Commissioner Chang probably mentioned this a little bit in\n\n         14   her opening -- a decade ago that was not the case.  I mean,\n\n         15   I'm old enough to remember, you know, hearing from the state\n\n         16   regulators in New England and they were not happy with ISO,\n\n         17   at that point.  And I won't say that they're perfectly\n\n         18   happy, but they're much happier today than they were then,\n\n         19   is my observation.  And my guess is that this did not happen\n\n         20   by accident.\n\n         21              And so, I was wondering if you could speak at a\n\n         22   high level, just for a minute or two, about how -- what did\n\n         23   ISO New England do, to foster this really collaborative\n\n         24   culture of engaging with the states, and how did you turn\n\n         25   that tide around?  What are some of the things you could do? \n\n\n\n\n\n                                                                       59\n\n\n\n          1   And if you have observations that maybe might resonate with\n\n          2   your view of how things are going in PJM, that would be\n\n          3   great.\n\n          4              MS. GULLUNI:  Thank you for the question.\n\n          5              It is true that we've had rockier times than\n\n          6   we're having now, and I will give all the credit to the\n\n          7   states.  So, the states have two organizations in New\n\n          8   England.  So, NECPUC, you were at the symposium, is the\n\n          9   organization of public utilities commissioners, which\n\n         10   represents the states on issues including water, et cetera.\n\n         11                             They also have a regional state\n\n         12   committee, NESCO, the New England State Committee on\n\n         13   Electricity, that is funded through a tariff and is very\n\n         14   well resourced.  They are, the NESCO managers are appointed\n\n         15   by the governors, so they include a mix of energy policy\n\n         16   folks as well as PUC commissioners.\n\n         17              And, about a decade ago, they came to us with a\n\n         18   vision statement.  All of them reached consensus on things\n\n         19   they wanted ISO New England to do.\n\n         20              When the states reached consensus, across six\n\n         21   states, we sit up and we listen.  It's very important to us. \n\n         22   We have the same reaction when the six sectors of our market\n\n         23   participants have consensus on an issue.  It's an important\n\n         24   issue; it warrants our attention.\n\n         25              In the case of the New England states' vision\n\n\n\n\n\n                                                                       60\n\n\n\n          1   statement, their primary concern was transmission related. \n\n          2   They wanted longer term studies from us.  So, we staffed up\n\n          3   to do it and we now have a set of rules around longer term\n\n          4   transmission planning that the states asked for, that we\n\n          5   worked for with them.\n\n          6              But really I will say the vehicle is the regional\n\n          7   state committee, appointed by governors, fully resourced,\n\n          8   contractually obligated to work through the stakeholder\n\n          9   process.  So, it has created an atmosphere that is conducive\n\n         10   to reaching consensus.\n\n         11              COMMISSIONER ROSNER:  Thank you for that.\n\n         12              I'd also like to ask a few folks, just their sort\n\n         13   of top line take on some of the reforms that we've been\n\n         14   discussing and that I've seen in the statements.\n\n         15              Marjie, I want to start with you.  Do you support\n\n         16   an increased state role in the board selection process, at\n\n         17   PJM?\n\n         18              MS. PHILIPS:  So, one, thank you for the honor,\n\n         19   privilege, and burden of testifying here today.  (Laughs.)\n\n         20              COMMISSIONER ROSNER:  You're welcome.  Thanks for\n\n         21   being here.\n\n         22              (Laughter.)\n\n         23              MS. PHILIPS:  We do.  And let me explain.  I'm\n\n         24   probably the only person here that sat on the nominating\n\n         25   committee at PJM a number of times, and others.  And, Jacob\n\n\n\n\n\n                                                                       61\n\n\n\n          1   and I had a great discussion the other day, because\n\n          2   everybody thinks the stakeholders get in there and we come\n\n          3   in, \"Ah!  I want somebody who's gonna vote for market\n\n          4   reform!\"\n\n          5              And the transmission owners, \"I want somebody\n\n          6   who's gonna give me the money!\"\n\n          7              It's astonishing how quickly the nominating\n\n          8   committee consolidates over who they want.  And you know\n\n          9   why?  We're not looking for you to support our position;\n\n         10   we're looking for you to show leadership.  Are you going to\n\n         11   challenge the PJM staff?  Frankly, that's our biggest\n\n         12   concern, is who we're nominating to the board going to have\n\n         13   the expertise, the courage?  Do they work well with other\n\n         14   board members?  Do they seem to have a personality...\n\n         15              So, it's kind of weird that people think it's\n\n         16   this secret society of stakeholder interests that are\n\n         17   nominating board members.  It's the opposite.\n\n         18              But I understand and appreciate there's a\n\n         19   concern, from the states, that they don't see that, they\n\n         20   haven't participated on it.\n\n         21              So, we suggested -- and, frankly, I'm very proud\n\n         22   -- I was on the nominating committee that brought Matt\n\n         23   Nelson, and Matt shared with us a lot of the NEPOOL\n\n         24   practices, and I think has been a terrific advocate, and he\n\n         25   was on the nominating committee.  So, he kind of made me\n\n\n\n\n\n                                                                       62\n\n\n\n          1   think yeah, we need to do that.\n\n          2              So, to proceed, the concern is, and with all of\n\n          3   this I just have to get in my side crack here, which is the\n\n          4   TOs and the states are all saying \"We want more independence\n\n          5   but we want more 205 rights.\"  Right?  None of the other\n\n          6   sectors are saying that.  Everybody's independent, but the\n\n          7   two folks that are saying they -- two groups saying they\n\n          8   want independence, also want greater 205 rights.  \n\n          9              So, I just throw that out for consideration.\n\n         10              COMMISSIONER ROSNER:  Okay.\n\n         11              MS. PHILIPS:  But getting back to your issue...\n\n         12              COMMISSIONER ROSNER:  All right.  So, thank you. \n\n         13   We have very limited time, so I want to pause you right\n\n         14   there...\n\n         15              MS. PHILIPS:  Yeah.  Okay.  Can I just... okay...\n\n         16              COMMISSIONER ROSNER:  ...and Stacey, I want to\n\n         17   ask you the same question.  Do you support increased state\n\n         18   participation in the board selection process?\n\n         19              MS. BURBURE:  Yes.  And a rebuttal, no.\n\n         20              COMMISSIONER ROSNER:  We'll come to the 205\n\n         21   question later.\n\n         22              MS. PHILIPS:  Sorry.  Sorry.\n\n         23              MS. BURBURE:  Okay.\n\n         24              COMMISSIONER ROSNER:  I also -- I wanted to ask,\n\n         25   do you support funding for a government, governors',\n\n\n\n\n\n                                                                       63\n\n\n\n          1   designee group?\n\n          2              MS. BURBURE:  We support a great role for state. \n\n          3   What that looks like, whether it's an expansion of OPSI,\n\n          4   whether it's a new group, whether it's on the nominating\n\n          5   committee, whether it's a direct board seat.\n\n          6              COMMISSIONER ROSNER:  Yeah.\n\n          7              MS. BURBURE:  We are open with respect to the\n\n          8   form in which that participation in a meaningful role in PJM\n\n          9   takes place.\n\n         10              COMMISSIONER ROSNER:  Great.\n\n         11              MS. BURBURE:  We're focused on the outcome, not\n\n         12   the exact structure.\n\n         13              COMMISSIONER ROSNER:  Uh-huh.  Okay.\n\n         14              MS. BURBURE:  And we would defer to state\n\n         15   commissions and the governors with respect to what this role\n\n         16   should look like and whether it fulfills their needs, in\n\n         17   terms of their participation at PJM.\n\n         18              COMMISSIONER ROSNER:  I agree with you.  I'm not\n\n         19   sure what it should look like, but I hear the need.\n\n         20              And, Marjie, do you agree as well?\n\n         21              MS. PHILIPS:  Uh-huh.\n\n         22              COMMISSIONER ROSNER:  Okay, great.\n\n         23              I wanted to ask -- and I'm focusing on your two\n\n         24   because I think you're both voting members in PJM, and I\n\n         25   don't think anybody else is, on this panel.\n\n\n\n\n\n                                                                       64\n\n\n\n          1              I want to ask, there was also a desire for state\n\n          2   input on resource adequacy issues, and this is where --\n\n          3   we've had a lot of ideas.  There is one concept of some\n\n          4   version of shared filings right that could be conditioned\n\n          5   on, you know, if agreement isn't reached.  Or other things,\n\n          6   like in New England they have an MOU with NESCO and NEPOOL\n\n          7   and the ISO.\n\n          8              But I want to ask this general question.  You\n\n          9   know, holding aside all the different iterations, some of\n\n         10   which are more widely agreed to or not, do you support\n\n         11   additional state input on resource adequacy issues, at PJM? \n\n         12   I'll start with Stacey.\n\n         13              MS. BURBURE:  Yes.  But we agree with Deputy\n\n         14   Secretary Danly that that responsibility should also be in\n\n         15   alignment with accountability, and that roles with respect\n\n         16   to resource adequacy should be better defined throughout\n\n         17   that process.\n\n         18              COMMISSIONER ROSNER:  I don't disagree with you.\n\n         19              MS. PHILIPS:  Agree.  Our concern is what are the\n\n         20   states' interests.  We're not New England, which has a very\n\n         21   consolidated view of \"No more gas, we want renewables.\"\n\n         22              PJM's 13 states, D.C., some want coal, some want\n\n         23   renewable, some want gas.\n\n         24              So what are the states' interests?  What's what\n\n         25   we're challenged with.  We absolutely agree they need a\n\n\n\n\n\n                                                                       65\n\n\n\n          1   greater role, but they don't come together on many issues,\n\n          2   so our challenge is how do we give them a greater voice,\n\n          3   while still acknowledging and accepting that they have very\n\n          4   different policies goals.  That scares us a little bit.\n\n          5              COMMISSIONER ROSNER:  Uh-huh, uh-huh.  You know,\n\n          6   in my mind, I think it's one thing to provide the greater\n\n          7   role, and it's a second to have that accountability on the\n\n          8   issue of resource adequacy.\n\n          9              And that leads, really directly, to my next\n\n         10   question, which is another area that I saw in the comments\n\n         11   was this increased role for board independence, so that the\n\n         12   board can make hard decisions on things that right now, as\n\n         13   was discussed earlier, entities have the opportunity to\n\n         14   veto, or preclude, the board from acting, if we can't reach\n\n         15   agreement among the stakeholders.\n\n         16              And so, my question is, you know, one idea was we\n\n         17   could move pieces that are currently in the operating\n\n         18   agreement into the tariff under certain conditions or under\n\n         19   no conditions.  And so my question is do you support moving\n\n         20   markets, and more the transmission planning authorities,\n\n         21   into the boards' more direct responsibilities?  Stacey, then\n\n         22   Marjie.\n\n         23              MS. BURBURE:  I want to make sure I understand\n\n         24   the question, because I think there are some nuances there. \n\n         25   So, I'll address it and then you can tell me if you'd like\n\n\n\n\n\n                                                                       66\n\n\n\n          1   me to elaborate on anything.\n\n          2              COMMISSIONER ROSNER:  Yeah.\n\n          3              MS. BURBURE:  I just want to be direct and\n\n          4   candid.\n\n          5              So, with respect to the planning protocols,\n\n          6   certainly we believe that should be in the tariff, and PJM\n\n          7   is unique in not having direct filing authority over that\n\n          8   aspect.\n\n          9              With respect to the market, that is an\n\n         10   interesting one in terms of how is that authority exercised. \n\n         11   But again, we support an advisory stakeholder model.\n\n         12              COMMISSIONER ROSNER:  Uh-huh.\n\n         13              MS. BURBURE:  So, overall, if that reform were\n\n         14   implemented, by definition it empowers the board to make\n\n         15   more decisions on an overall basis.\n\n         16              COMMISSIONER ROSNER:  Got it.\n\n         17              MS. BURBURE:  So, functionally, it's consistent\n\n         18   with the types of reforms that we support.\n\n         19              MS. PHILIPS:  Do you want candor or not?\n\n         20              COMMISSIONER ROSNER:  I think we're here for\n\n         21   candor.\n\n         22              MS. PHILIPS:  Okay.  Here it comes.\n\n         23              COMMISSIONER ROSNER:  I think the Chairman\n\n         24   charged us all with candor.\n\n         25              MS. PHILIPS:  Here it comes.  So, we've already\n\n\n\n\n\n                                                                       67\n\n\n\n          1   filed our comments.  There was a case that was before you\n\n          2   and then went to the courts, and so you know where we stand\n\n          3   on moving 205.\n\n          4              The challenge to PJM is when the board feels\n\n          5   pressure from the states, FERC has not always been the\n\n          6   economic regulator.  We're here because of MOPR, RMRs,\n\n          7   collars.  Those are all straight state-driven initiatives,\n\n          8   and FERC was not always acting as an economic regulator.\n\n          9              So, our message is the board needs to be\n\n         10   independent.  So does FERC.\n\n         11              You know, a couple years ago, we all thought\n\n         12   we're going to drive energy markets to incorporate\n\n         13   renewables.  Now we're worried about are combined cycle is\n\n         14   going to get enough energy revenues, because those are the\n\n         15   units that you want to come online now.\n\n         16              So, yes, the PJM has complete 205 over\n\n         17   reliability.\n\n         18              COMMISSIONER ROSNER:  Uh-huh.\n\n         19              MS. PHILIPS:  We did say we think the states\n\n         20   should have more rights on cost allocation.  But we think\n\n         21   the allocation of 205 rights, as they exist now, are\n\n         22   correctly done.  And everybody always has a 206 right, and\n\n         23   the Commission has acted very quickly on them sometimes, and\n\n         24   sometimes they sit on your shelves for years.\n\n         25              So, there are alternative approaches, when the\n\n\n\n\n\n                                                                       68\n\n\n\n          1   205 rights are not moving fast enough.\n\n          2              COMMISSIONER ROSNER:  Thank you.  And thank you\n\n          3   for humoring this line of questions.\n\n          4              CHAIRMAN SWETT:  Wait.  Before we move on -- I\n\n          5   will give you some of your time back.\n\n          6              COMMISSIONER ROSNER:  Oh!  Please!  Yes, yes.\n\n          7              CHAIRMAN SWETT:  I think we should hear from Mr.\n\n          8   Mills what he thinks about board independence.\n\n          9              MR. MILLS:  Thank you, Madam Chair, and thank\n\n         10   you, commissioners, for putting this together.  I am very\n\n         11   much enjoying the conversation, so far.\n\n         12              So, that is one of the things I intended to talk\n\n         13   about, was that we believe -- and I speak on behalf of the\n\n         14   board -- we believe that the board would be more independent\n\n         15   and able to act more quickly if we had those 205 rights over\n\n         16   the operating agreement, which is the energy and ancillary\n\n         17   services market.\n\n         18              As Marjie pointed out, we do have those rights\n\n         19   currently, under the resource adequacy agreement, which is\n\n         20   the capacity market, and to correct the record, we have used\n\n         21   those rights.  In fact, we've used the 205 and capacity\n\n         22   market 13 times since 2023.  So, it is a tool that we are\n\n         23   able to use.\n\n         24              The reason I think that's important is -- and\n\n         25   I'll point to what we call \"the reserve certainty senior\n\n\n\n\n\n                                                                       69\n\n\n\n          1   task force\" -- this is a task force we put together to make\n\n          2   sure that we are putting a number out there, a market number\n\n          3   for reserves, that comports with the status of the system.\n\n          4              It's a very technical and very detailed,\n\n          5   complicated, discussion to have.  A lot of time has been\n\n          6   spent educating members and, to some extent, ourselves.  But\n\n          7   that process has now languished for three years.  And yet,\n\n          8   to date, our reserve problems continue.\n\n          9              So, there is an instance where, with a\n\n         10   time-delimited basis, after a fulsome stakeholder process,\n\n         11   the board, if we're allowed to file a 205, we would\n\n         12   potentially, depending on the board's adjudication, we'd be\n\n         13   done with that and moving on to the next issue.\n\n         14              So, I do support, and the board supports, that,\n\n         15   and that's one of the things we think the Commission look\n\n         16   forward to, or look towards.\n\n         17              CHAIRMAN SWETT:  And we all have heard, at this\n\n         18   table, the board's concerns that they cannot act freely\n\n         19   because they are concerned about termination.  Can you weigh\n\n         20   in on that?\n\n         21              MR. MILLS:  Well, it's public record that two\n\n         22   annual meetings ago, in Virginia, we had taken, the board\n\n         23   had taken, a couple of what I'll say was independent\n\n         24   actions.  They had had consultation with stakeholders in\n\n         25   advance, but they were clearly outside of the pale of the\n\n\n\n\n\n                                                                       70\n\n\n\n          1   standard protocol for the board.  And, as a result, two\n\n          2   board members were not reconfirmed.  So, I think that's a\n\n          3   real concern.\n\n          4              And, the challenge with the construct of the\n\n          5   nominating committee and the appointment of the board, to\n\n          6   date, it's a three-year term, and so I came to PJM after 40\n\n          7   years of experience elsewhere in this country, in this\n\n          8   industry, and it was like starting over.\n\n          9              So, the reason I say that three years is a\n\n         10   problem is that, three years, you're just now figuring out\n\n         11   the decoding of the acronyms, and now you're standing for\n\n         12   renomination, or could be voted out.\n\n         13              One of the proposals that I've seen, and we\n\n         14   haven't taken a position on it, but it has some appeal, is a\n\n         15   single appointment, for a longer duration of board members. \n\n         16   That would alleviate that.\n\n         17              The board has demonstrated, over the last year,\n\n         18   that we are capable of taking care of any performance issues\n\n         19   of our fellow board members.  And that record, I think,\n\n         20   stands.\n\n         21              So, if this is a matter of we believe the members\n\n         22   need to weed out the poor-performing board members, believe\n\n         23   me, this board will take care of that themselves.\n\n         24              CHAIRMAN SWETT:  So, longer board terms.  I\n\n         25   think, did you say, five years?\n\n\n\n\n\n                                                                       71\n\n\n\n          1              MR. MILLS:  I didn't specify.  Longer than three.\n\n          2              CHAIRMAN SWETT:  So, what's the number?\n\n          3              MR. LACERTE:  Why don't you specify it for us? \n\n          4   Yeah.\n\n          5              MR. MILLS:  I would say, Commissioner, given the\n\n          6   complexity of the issues and that we want a board that looks\n\n          7   forward to a long term focus, I would say six to nine years.\n\n          8              CHAIRMAN SWETT:  And, would you change the\n\n          9   ability to terminate or not renew board members, for\n\n         10   performance?\n\n         11              MR. MILLS:  They would not come up for -- through\n\n         12   the nominating committee -- if it were a nine-year term,\n\n         13   every year the nominating committee would meet, to find a\n\n         14   new board member, for one that was going off.  So there'd be\n\n         15   no reconfirmation.  At the end of nine years you're termed\n\n         16   out and you're done.\n\n         17              Does that answer your question?\n\n         18              CHAIRMAN SWETT:  Yes.  And I have another follow\n\n         19   on.  So, if we were to implement, or PJM were to file to\n\n         20   implement such a thing, would  you propose that the existing\n\n         21   board members be grandfathered in to that timeline?\n\n         22              MR. MILLS:  That's a great question, and my\n\n         23   initial reaction is yes.  But I can also see reasons why\n\n         24   that they were brought in under one set of agreements and so\n\n         25   you would snap a chalk line on every board member from them. \n\n\n\n\n\n                                                                       72\n\n\n\n          1   So, I guess I don't have a clear answer to that.\n\n          2              MR. LACERTE:  I'd like the stakeholders to\n\n          3   respond to Mr. Mills there, and what is your position?\n\n          4              MS. PHILIPS:  I don't disagree.  I think nine\n\n          5   years is too long, to be honest.  I think that, given the\n\n          6   concerns about on-going independence, I think nine years is\n\n          7   a long time to go without any sort of stakeholder input.\n\n          8              But I think we would certainly be open to\n\n          9   extending the period.  Maybe five years sounds very\n\n         10   reasonable.\n\n         11              The one thing I think we might disagree with is\n\n         12   that if somebody serves for five years, that they would be\n\n         13   allowed to be renominated.  I think, if somebody's doing a\n\n         14   great job and they've understood the system and all of that,\n\n         15   they should be allowed to be renominated.\n\n         16              MS. BURBURE:  I would agree with Marjie on that\n\n         17   point, with respect to the terms.  I also will note the\n\n         18   thing that struck me the most about Mr. Mills' remarks was\n\n         19   how much experience in the PJM region matters, regardless of\n\n         20   the length of your experience in this industry, and so also\n\n         21   examining board qualifications I think is an important\n\n         22   consideration.\n\n         23              COMMISSIONER SEE:  I think this is really\n\n         24   interesting, the discussion about the length and\n\n         25   renominations.  I'm curious, David, your response.  So, if\n\n\n\n\n\n                                                                       73\n\n\n\n          1   it was five years, would your view on the ability for a\n\n          2   board member to be renominated to a next term change?\n\n          3              MR. MILLS:  I think that should be allowed, but I\n\n          4   think it should be -- it should be indicated early on, to\n\n          5   that expiring board member, that that's the preference of\n\n          6   the members.\n\n          7              To date, the renomination process includes an\n\n          8   interview in front -- this is for an existing board member -\n\n          9   - an interview in front of that nominating committee, and\n\n         10   judgment thereof at some later date.  I think an\n\n         11   acknowledgement of positive indications that \"Hey, the\n\n         12   members and the board would like to consider you.  Are you\n\n         13   willing?\"  I think under that, then yes.\n\n         14              COMMISSIONER CHANG:  Can I just have a quick\n\n         15   followup on the independence?  I heard \"independence.\" \n\n         16   Could you just elaborate or maybe -- maybe Stacey, Marjie,\n\n         17   but also David -- this independence.  So, is there a lack of\n\n         18   independence today?  Is that the view?  Or is there an\n\n         19   enhanced independence you're looking for?  Or is it less\n\n         20   independence?  Could you elaborate, please?\n\n         21              MS. PHILIPS:  I mean, the decisions that have\n\n         22   come out, that led us to where we are, were, in our view, a\n\n         23   very -- they were politically driven.  And I'm not\n\n         24   criticizing, we believe, at all, but they were decisions\n\n         25   tilted towards very direct outcomes.  Less gas, so prices go\n\n\n\n\n\n                                                                       74\n\n\n\n          1   down, and they were all state driven.\n\n          2              We think it's critical.  We don't think the\n\n          3   states and governors have enough direct discussion with PJM,\n\n          4   and we would like to see that enhanced.  But we don't want\n\n          5   that to lead to the misconception that PJM has to do what\n\n          6   they want them to do.\n\n          7              So, if PJM would benefit from understanding where\n\n          8   the states are coming from, understanding where the\n\n          9   governors are -- and we can talk about the collaborative and\n\n         10   where OPSI and the collaborative go.\n\n         11              But so, yes, they need better representation and\n\n         12   input.  Collective management, at PJM, is a great example. \n\n         13   They didn't tell the states they were thinking about.  That\n\n         14   would have had such a better, robust, introduction into the\n\n         15   stakeholder process had the state been told \"Hey, this is\n\n         16   what we're thinking.  This is your role.\"  Whatever.  And\n\n         17   they really weren't given a lot of advance warning.  So, we\n\n         18   think that process can be really enhanced.\n\n         19              But we think it's very much short of a vote, and\n\n         20   we think that PJM, at the end, the board has to remain\n\n         21   independent.  Just because a particular state, or five\n\n         22   states, want something, that may mean a lot of other states\n\n         23   don't support it.  \n\n         24              But they need a voice, absolutely.  And they need\n\n         25   a better voice.\n\n\n\n\n\n                                                                       75\n\n\n\n          1              CHAIRMAN SWETT:  Staying on this vein of the\n\n          2   board -- and I think we'll probably sit on this for a while\n\n          3   -- but The Honorable Pat Wood has very deep experience at\n\n          4   FERC and with these types of issues.\n\n          5              And, in your testimony you call for greater\n\n          6   transparency and public accountability, for the board,\n\n          7   including publish performance metrics and ethics documents. \n\n          8   Can you talk a little bit about your proposal?\n\n          9              CHAIRMAN WOOD:  It's really just thank you, and\n\n         10   thank you all for -- this is my first time back since I\n\n         11   left, so this is kind of an emotional day, to walk up the\n\n         12   street again.\n\n         13              COMMISSIONER ROSNER:  Welcome back.\n\n         14              CHAIRMAN WOOD:  It's nice to be back.\n\n         15              Just looking at things -- again, the bottom line,\n\n         16   and I heard it from our two guest speakers today, who did a\n\n         17   great job -- is do you have the buy-in.  Do the people feel\n\n         18   like you're working for them?  Do they know that you're\n\n         19   accountable, that you're not influenced by the \"backdoor\n\n         20   stuff\" that goes on, you know, not just in this city but\n\n         21   across the country?\n\n         22              And so, the transparency aspect of that is really\n\n         23   what permeates that part of my recommendations, Madam\n\n         24   Chairman.\n\n         25              And I'm looking at, kind of, other -- I'm looking\n\n\n\n\n\n                                                                       76\n\n\n\n          1   at ERCOT, I'm looking at MISO, looking at other of the RTOs,\n\n          2   because we've done this for a generation.  So, let's\n\n          3   consolidate the best practices and just get on with it.\n\n          4              So, I think that's where those ones that you\n\n          5   mentioned specifically, Chairman, came from, or specifically\n\n          6   MISO and ERCOT, that had more display, more transparency,\n\n          7   with regard to those public disclosures.\n\n          8              And again, the goal is to create a lot of\n\n          9   confidence that the people making decisions that affect 67\n\n         10   million of us, of y'all, becuase I live in ERCOT --\n\n         11              (Laughter.)\n\n         12              CHAIRMAN WOOD:  But, the decision makers are on\n\n         13   the up and up.  And, you know, it's not much deeper than\n\n         14   that.\n\n         15              CHAIRMAN SWETT:  Thank you.  Deputy Secretary\n\n         16   Finkel, I saw you had your tent raised.\n\n         17              DEPUTY SECRETARY FINKEL:  Yes.  Thank you.  Thank\n\n         18   you very much.\n\n         19              I just wanted -- my head is sort of still\n\n         20   ringing, from the amazing set of introductory remarks from\n\n         21   the Commission and from the guest speakers, and this great\n\n         22   discussion that we're having here, that laid out the stakes\n\n         23   and the reason why we're here.\n\n         24              So, I just wanted to zoom back for one second. \n\n         25   We're here because the market is in crisis, the market needs\n\n\n\n\n\n                                                                       77\n\n\n\n          1   to be fixed, and the market can't be fixed by the failed\n\n          2   governance that currently exists.  Those are the stakes. \n\n          3   That's why you have 12 governors' offices in the seats\n\n          4   behind me.  These folks have a lot of other things they\n\n          5   could be doing.  They're here because it matters to every\n\n          6   governor, because it matters to 67 million people.\n\n          7              And I just -- so that we have to get to\n\n          8   solutions.  And I appreciate -- I feel we've almost, sort\n\n          9   of, fallen from the skies of those consequences down to \"Is\n\n         10   it five years or is it nine years?\"  And there's a realm of\n\n         11   reasonableness in there, and reasonable minds can disagree. \n\n         12   But, I think we all agree on longer board terms.\n\n         13              But I just want to respond to this, to me very\n\n         14   strange, idea that the independence of the board is somehow\n\n         15   polluted or sullied by the public interest being represented\n\n         16   on the board nominating committee.  What you have today on a\n\n         17   nominating committee -- and I appreciate, we had a great\n\n         18   conversation, and I appreciate it very much, Marjie -- but\n\n         19   what you have today are the private interests represented. \n\n         20   They have five seats on the \"nomcom.\"  The existing board\n\n         21   has two seats on the \"nomcom.\"  So, every instance, the\n\n         22   incumbent interests who have a financial stake in the\n\n         23   outcome control who's on the board.\n\n         24              And then those nominees go to the member\n\n         25   committee, again, dominated by those interests.  And there's\n\n\n\n\n\n                                                                       78\n\n\n\n          1   nothing wrong with that.  Those interests have a financial\n\n          2   and fiduciary duty to their stakeholders to maximize the\n\n          3   outcomes.  And they are zealous to do that and it's to their\n\n          4   credit.\n\n          5              But the idea that having public representation in\n\n          6   that process is somehow going to impair some paradigm kind\n\n          7   of independence -- it's not independent; they are -- the\n\n          8   outcomes and the, candidly, what we see is the blind spots\n\n          9   in the board's outlook, are a direct and logical result of\n\n         10   the process.\n\n         11              So, we think it's necessary for the states to\n\n         12   have more of a role.  Not as a -- and I take Deputy\n\n         13   Secretary Danly's point -- the governors and the states are\n\n         14   not here saying, as some have said, \"The solution is just\n\n         15   give us more power.  That will solve it.\"  We hear that a\n\n         16   lot.\n\n         17              That is not the solution.  Just handing the\n\n         18   states more power is not the solution.  We agree with that. \n\n         19   That's why the governors are here, with some practical,\n\n         20   actionable, steps, that will improve that.  That includes\n\n         21   more power for the states, because the states need to be at\n\n         22   the table, but it also includes steps to improve PJM.\n\n         23              So, I just -- you know, very respectfully -- want\n\n         24   to push back on that idea that there's something wrong, or\n\n         25   incorrect, about the states being on the nominating\n\n\n\n\n\n                                                                       79\n\n\n\n          1   committee.\n\n          2              MS. PHILIPS:  Thanks, Jacob.  You can see we like\n\n          3   to talk about this.\n\n          4              First of all, there is a consumer advocacy seat on the\n\n          5   nominating committee, so consumers are, through the\n\n          6   stakeholder process, do have a vote on the nominating\n\n          7   committee.  I know.  I've served on it.  They were there.\n\n          8              The concern is, you know, our proposal is to have\n\n          9   the chair of OPSI on it as a non-voting.  There are\n\n         10   confidentiality issues.  The are FOIA concerns, that if the\n\n         11   states are on it, they can't receive anything in writing. \n\n         12   The whole thing is to protect the anonymity of candidates.\n\n         13              We are not, as a stakeholder, on the nominating\n\n         14   committee, I'm not allowed to go back to my colleagues and\n\n         15   ask them questions, \"Do you like this?  What do you want?\"\n\n         16              Right when it starts, we talk about what we're\n\n         17   looking for, and it's very prescriptive, what the board --\n\n         18   the seat that we're trying to fill.  And then I can ask them\n\n         19   about the renomination of existing board members.\n\n         20              But, once we go into discussion, I can't come\n\n         21   back and say \"Oh, hey, there's some concern that's been\n\n         22   expressed.\"  That's it; it's a \"cone of silence,\" so we're\n\n         23   concerned about FOIA.  \n\n         24              We're concerned, again going to the policy, you\n\n         25   pick three states.  So, you pick a state that's in RGGI one\n\n\n\n\n\n                                                                       80\n\n\n\n          1   year, out of RGGI another year, a commissioner -- what, are\n\n          2   you going to pick somebody who likes coal, somebody who\n\n          3   likes renewable, somebody who... it doesn't -- it assumes a\n\n          4   lack of integrity in the process that exists.\n\n          5              And that's why we think someone from OPSI should\n\n          6   be on the board, to get confidence in the integrity of the\n\n          7   process.  But we don't want the process to be politicized in\n\n          8   and of itself.\n\n          9              DEPUTY SECRETARY FINKEL:  I just have to respond. \n\n         10   And I don't want to -- you know, we all know we could debate\n\n         11   this all day, as you say, and we would enjoy doing that. \n\n         12   But the end use sector does include consumer advocates.  It\n\n         13   also includes large industrial customers, who may not have a\n\n         14   vote in that in the same vein.  So, I don't think that's\n\n         15   fair to say that's a seat just for consumer advocates.\n\n         16              And, you know, I guess I'm just -- I'm sort of\n\n         17   baffled by the idea that people in public office, who have\n\n         18   responsibility, can't have confidential information.  I\n\n         19   mean, thank goodness we don't allow national security\n\n         20   information to go to public officials.  Right?  Only private\n\n         21   corporations control national security information?\n\n         22              I mean, it just -- it's kind of ludicrous, to me. \n\n         23   To the extent that's a good faith concern, we're happy to\n\n         24   have a discussion and work around any FOIA issues.  But, you\n\n         25   know, commissioners and members in the governors' office\n\n\n\n\n\n                                                                       81\n\n\n\n          1   deal with confidential and sensitive matters literally all\n\n          2   day long, every day.  So that's not a reason not to have\n\n          3   them.\n\n          4              And I'd just go back to what Commissioner Rosner\n\n          5   said.  The state role has to have teeth.  Either the states\n\n          6   are respected partners in the process, which they have to\n\n          7   be, or they're not.  And being a non-voting observer is just\n\n          8   not going to do that.\n\n          9              COMMISSIONER ROSNER:  And I see Maria has her\n\n         10   card up, and maybe there's something from New England that\n\n         11   you wanted to offer.\n\n         12              MS. GULLUNI:  Yes, I just wanted to say we do\n\n         13   have a seat for the state, on our nominating committee.  But\n\n         14   our nominating committee is composed half of sitting board\n\n         15   members.\n\n         16              And we also have given a very narrow role to the\n\n         17   committee, to look for -- to fill vacancies.  The board\n\n         18   still controls the election, and the board decides whether\n\n         19   directors who are eligible for reelection can stand for\n\n         20   reelection.\n\n         21              It's a very narrow role, that we think ensures\n\n         22   the independence of our board.\n\n         23              COMMISSIONER LACERTE:  And Kelsy had her card up\n\n         24   and then she put it down.  She put it back up again.  So, I\n\n         25   want to hear her opinion.\n\n\n\n\n\n                                                                       82\n\n\n\n          1              CHAIR BAGOT:  I'll be brief, because I think\n\n          2   Jacob hit on some of the points.\n\n          3              But I guess what I'm struggling with, Marjie, is\n\n          4   on the one hand you say our current board nominating process\n\n          5   is not necessarily broken.  Right?  But you recognize that\n\n          6   the folks that sit on that are voting members that are\n\n          7   self-interested organizations to some extent.\n\n          8              So, I don't really understand the distinction\n\n          9   between those entities being able to successfully evaluate\n\n         10   and select independent board members, and that that should -\n\n         11   - we should have confidence in those board members, but the\n\n         12   states, in holding that role, are unable to also exercise\n\n         13   that same reasonableness and degree in selecting.  Right?\n\n         14              And, stepping back from arguing about, you know,\n\n         15   the makeup of the board nominating committee, just from a\n\n         16   practical perspective, you raised concerns with the process\n\n         17   being overly -- political results driving PJM\n\n         18   decision-making.  And I a hundred percent agree.  So that is\n\n         19   something that has happened and that is something that\n\n         20   cannot happen, and that is why I think we are supportive of\n\n         21   more board independence, to avoid perceptions, whether\n\n         22   correct or not, that politics are sort of driving\n\n         23   decision-making that's happening.\n\n         24              But, the practical reality is that if states, if\n\n         25   legislators, governors, OPSI, do not feel like their voices\n\n\n\n\n\n                                                                       83\n\n\n\n          1   are being adequately considered, by an independent board --\n\n          2   right? -- and they can't trust that process, they're going\n\n          3   to use whatever blunt instruments they have, to try to make\n\n          4   their voice heard.  And I think that's something that nobody\n\n          5   wants to happen.\n\n          6              And so, we can argue about, you know, whether\n\n          7   it's functioning or not, and the number of seats, but we\n\n          8   have to find a way for those states to feel like they have\n\n          9   trust in the process and in the independence of the board's\n\n         10   decisions.  And without that, no matter what solution, or\n\n         11   disagreements about whether it's independent now or not,\n\n         12   you're going to see intervention that is not helpful to the\n\n         13   long term stability of decision-making at PJM.\n\n         14              So, just practically, I think we have to keep\n\n         15   that in mind.  Even though it's fun to debate these little,\n\n         16   you know, differences, like from a practical\n\n         17   solutions-oriented -- like, we can't lose sight of what's\n\n         18   going to happen without state confidence in these\n\n         19   processes.\n\n         20              MS. PHILIPS:  So, I'm not authorized to speak on\n\n         21   behalf of LS, so this is me.  So, I think we should -- I\n\n         22   think it's compelling that we have a voting member.  I think\n\n         23   three is too much.\n\n         24              So, in the spirit of compromise, I throw out one. \n\n         25   (Laughs.)\n\n\n\n\n\n                                                                       84\n\n\n\n          1              COMMISSIONER LACERTE:  I wanted to piggyback on a\n\n          2   couple of these things.  I think, Marjorie, obviously you're\n\n          3   very well versed in all these topics but I think you've lost\n\n          4   a little bit of perspective here.\n\n          5              I think FOIA concerns are not real, with the\n\n          6   states participating.  There's plenty of deliberate process\n\n          7   protections on FOIA, and you're speaking to a body who has\n\n          8   to deal with FOIA issues every single day.  So, that is not\n\n          9   a persuasive argument.\n\n         10              I think, when we're dealing with these\n\n         11   initiatives that you might find unpalatable, whether it be\n\n         12   the price collar or another problem, that's not emblematic\n\n         13   of political influence in the process.  You have a number of\n\n         14   Democrat governors that are being driven to the White House\n\n         15   to agree with President Donald Trump.\n\n         16              So, if you're trying to drive, you know,\n\n         17   unparalleled things that have never happened before, the\n\n         18   system is the problem, and not the politics is the problem.\n\n         19              If we had a functional board, we had a functional\n\n         20   governing system in PJM, the Democrats would not be rushing\n\n         21   to the White House to agree with the President.\n\n         22              MS. PHILIPS:  But, Commissioner LaCerte, the\n\n         23   Democratic governors are not doing what they said they'd do. \n\n         24   They need -- you know, I don't disagree with you.\n\n         25              COMMISSIONER LACERTE:  I fully agree.\n\n\n\n\n\n                                                                       85\n\n\n\n          1              MS. PHILIPS:  So, it's easy to agree to\n\n          2   principle, but when it gets to implementation, that's where\n\n          3   the accountability has to come in.\n\n          4              COMMISSIONER LACERTE:  Look, the initiatives\n\n          5   which are problematic are the product of a system that has\n\n          6   failed to produce alternatives.  And this is the root cause. \n\n          7              And I think that there needs to be more state\n\n          8   voices at the table, and their solutions to finding the\n\n          9   avenues in which your concerns are addressed.\n\n         10              COMMISSIONER SEE:  Let's stay on this topic of,\n\n         11   kind of, state involvement, and I will say I've really\n\n         12   appreciated this conversation so far.  And Jacob, I liked\n\n         13   the way you put it, of just kind of noting the contrast\n\n         14   between the abstract discussions about broad ideas, and then\n\n         15   getting down to the minutiae of five versus nine.\n\n         16              And frankly, I was hoping that we would have both\n\n         17   today, because I think we need both of those, in order to\n\n         18   find some actionable solutions.\n\n         19              So, in the spirit of that, I want to talk a\n\n         20   little bit more about the proposals on the table for state\n\n         21   reform and kind of take it from a view of, sort of,\n\n         22   categorizing and prioritizing.\n\n         23              So, Chairman Bagot, I'm going to start with you\n\n         24   on this one, although I know others have views here too. \n\n         25   The way I see it, I think we've got basically three buckets\n\n\n\n\n\n                                                                       86\n\n\n\n          1   that have been proposed.  Right?  The first is states'\n\n          2   involvement in board selection.  The second is, you know,\n\n          3   the states having more of a directional voice.  You know,\n\n          4   kind of an OPSI or a second organization, on more of an\n\n          5   involvement in PJM strategic direction.  And then the third\n\n          6   is filing rights.\n\n          7              So, I guess the first question is \"Is that a fair\n\n          8   lay of the land of what we have?  Is there a fourth bucket\n\n          9   we need to be considering here?\"\n\n         10              And then, we've talked a lot about, kind of, the\n\n         11   merits of those, and I'm happy to keep doing that.\n\n         12              But I think what I'm most interested in is your\n\n         13   views on priority between those.  You know, what should we\n\n         14   be focusing on?  How do they interact?  You know, if we have\n\n         15   one, do we need three?  Right?\n\n         16              If we pair other reforms, you know, how important\n\n         17   are the others?  At what point do they become\n\n         18   counterproductive?  \n\n         19              So, I think I'm really interested in your\n\n         20   reactions on that, of do we have the right proposals out on\n\n         21   the table, and how should we be viewing them together?\n\n         22              So, I'm going to start with you and then, I know,\n\n         23   David, you talked a little bit about this.  I know Pat and\n\n         24   Jacob, in particular, your comments did.  I know we've got\n\n         25   reactions at this end of the table too.  But I'd like to\n\n\n\n\n\n                                                                       87\n\n\n\n          1   start at this end of the table on this question.\n\n          2              CHAIR BAGOT:  Sure.  So, I'll say up front that I\n\n          3   think OPSI and I are very closely aligned, though we're not\n\n          4   entirely aligned, so I'm not necessarily speaking on behalf\n\n          5   of OPSI; I'm speaking on behalf of myself.\n\n          6              And I appreciated your kind of terse but\n\n          7   introductory remarks of putting out honesty but also\n\n          8   practicality.\n\n          9              COMMISSIONER SEE:  Uh-huh.\n\n         10              CHAIR BAGOT:  And so, that's really what I'm\n\n         11   trying to come here today, what are practical,\n\n         12   implementable, solutions that are not going to have us in\n\n         13   litigation over these issues for the next three years.\n\n         14              And so, as I mentioned before, I think when\n\n         15   you're -- the most important thing, in my mind, is board\n\n         16   independence.  Right?  And confidence that the board not\n\n         17   only can weigh the feedback that is given to it by its\n\n         18   stakeholders, but then make an independent decision on what\n\n         19   is the optimal solution, going forward, but that also is\n\n         20   empowered to make that decision, to move that initiative\n\n         21   forward, and that can't be stagnating or, you know, in\n\n         22   gridlock, in the stakeholder process.\n\n         23              And so, I think that would be a huge fix, in\n\n         24   terms of moving the ball in the right direction.  Right? \n\n         25   And then some other things trickle out.\n\n\n\n\n\n                                                                       88\n\n\n\n          1              So, states asking for 205 rights, it makes sense\n\n          2   in the past, for --  up 'til now, that that's been a really\n\n          3   important initiative for the states, because they don't feel\n\n          4   like they have a voice in the process.\n\n          5              So, we do meet with the board three times a year,\n\n          6   and I've sat in on those meetings, and they don't feel\n\n          7   productive.  We talk at each other.  There's no actional\n\n          8   items or solutions that come out of it.  Oftentimes it's an\n\n          9   argument -- right? -- with the board supporting an\n\n         10   initiative that maybe the transmission owners or another\n\n         11   group have put forward, or saying that they don't have the\n\n         12   power to go make that filing effort.  Right?  So, it doesn't\n\n         13   feel productive.\n\n         14              So, 205 rights are a way to, one, make sure that\n\n         15   your voice is heard, because it's a point of leverage. \n\n         16   Right?  If you don't -- if you don't listen to us, don't\n\n         17   consider us in your filing, we're going to come and change\n\n         18   it.\n\n         19              Two, it gives the Commission options.  Rather\n\n         20   than having to reject, it's an alternative.  Right?  To move\n\n         21   the ball forward.\n\n         22              But I think that my -- to the extent that we feel\n\n         23   like the board has the ability to make its independent\n\n         24   decisions, I don't know that those 205 rights become as\n\n         25   necessary in that sort of, like, blunt force way.  Right?\n\n\n\n\n\n                                                                       89\n\n\n\n          1              And so, I think, if we have board independence,\n\n          2   paired with an opportunity for states to be part of the\n\n          3   discussion, develop the strategic priorities for PJM, and to\n\n          4   feel like their voice is heard equally by the PJM board,\n\n          5   then I think you maybe don't need those same blunt tools.\n\n          6              And I lay out a couple different ways I believe\n\n          7   these states could have some more meaningful communication,\n\n          8   going forward.\n\n          9              I do have to agree, when I put my tent card up\n\n         10   before, is that accountability is really important.  And I\n\n         11   personally believe that the states do need to think, you\n\n         12   know, look in the mirror and say \"How have we engaged in the\n\n         13   past?\"  Right?  \"Have we engaged in a productive way?  Have\n\n         14   we come with solutions?  Have we held up our end of the\n\n         15   bargain?\"  Right?  \"Have we delayed the process or have we\n\n         16   been efficient in providing our feedback?\"\n\n         17              We need to also be accountable on that, and too\n\n         18   for this process to work, and so I'm certainly working with\n\n         19   my state colleagues to make sure that we're doing our own\n\n         20   homework there.  And that's an important piece of the\n\n         21   puzzle.\n\n         22              And one way that we could actually be held\n\n         23   accountable, I think, is very clear defining boundaries on\n\n         24   what are the states' responsibilities with resource adequacy\n\n         25   and what are PJM's.  Right?\n\n\n\n\n\n                                                                       90\n\n\n\n          1              And then, if we have those boundaries, the states\n\n          2   can be held accountable for what their role in that is.  And\n\n          3   I think some of that is being explored in the on-going\n\n          4   discussion about, like, future market reforms in a capacity\n\n          5   market, and the white paper that PJM put out.\n\n          6              And they have been engaging with the states, to\n\n          7   figure out what is the appropriate state role there.  So, I\n\n          8   think there are opportunities to draw that boundary very\n\n          9   clearly.\n\n         10              COMMISSIONER SEE:  That's really helpful and I\n\n         11   appreciate it.  I don't want to put words in anybody's\n\n         12   mouth, but what I think I heard you saying is we've got the\n\n         13   right buckets that we're considering.  If we make meaningful\n\n         14   change in bucket one and some version of bucket two, bucket\n\n         15   three is not quite as important.\n\n         16              But bucket two, you know, involves the states'\n\n         17   involvement and voice.  It has to come with accountability.\n\n         18              CHAIR BAGOT:  Yes.\n\n         19              COMMISSIONER SEE:  Is that fair?\n\n         20              CHAIR BAGOT:  Yes.\n\n         21              COMMISSIONER SEE:  Okay, thank you.\n\n         22              David, you can take this one next.\n\n         23              MR. MILLS:  Yeah.  Thank you, Commissioner.  And\n\n         24   since I may not get a lot of opportunities, I do need to say\n\n         25   that both the board and the company, as well as myself, we\n\n\n\n\n\n                                                                       91\n\n\n\n          1   are fully committed to rise to the challenge here.  I just\n\n          2   want to be really clear, that you are not going to hear me,\n\n          3   or anybody from PJM, including our board, make excuses.  In\n\n          4   fact, I'm working to take accountability for the things PJM\n\n          5   may have done in the past that led to some of the issues we\n\n          6   are under right now.\n\n          7              But, we are going to do more than our part to\n\n          8   fulfill the challenge that's before us, and that includes\n\n          9   the capacity market reform that the speakers talked about\n\n         10   earlier.\n\n         11              Now, with respect to this issue, per se, I think\n\n         12   I'm on record as saying yeah, as Kelsey said, we meet with\n\n         13   OPSI, the board meets with OPSI three times a year.  And I\n\n         14   would agree, that it doesn't feel like it's very productive. \n\n         15   It's a good information exchange but, you know, the ball\n\n         16   doesn't really seem to move down the field in any meaningful\n\n         17   manner.\n\n         18              So now we have this proposal by the governors'\n\n         19   collaborative to add a second organization, legitimize it\n\n         20   with funding, which I have no problem with.\n\n         21              And then, somewhere in this, there's the concept\n\n         22   of the consolidated counsel, of the two of them.\n\n         23              Before I respond to which of those I prefer, I\n\n         24   also want to point out that, you know, there's another group\n\n         25   representing the states that is emerging as a loud voice,\n\n\n\n\n\n                                                                       92\n\n\n\n          1   and that is the legislators.  So, somehow that will be -- if\n\n          2   we don't do it now, it will be the next thing we have to\n\n          3   adjust for, to make sure that, in addition, those\n\n          4   legislators are heard.\n\n          5              Now obviously, from an efficiency perspective,\n\n          6   straight down the middle, one organization would be ideal,\n\n          7   for PJM to deal with.  Right?  Because otherwise, I worry\n\n          8   that all we will do is legitimize and create a structure for\n\n          9   the dissonance that exists between those functions, within\n\n         10   their respective states.\n\n         11              So, in Dave Mills' ideal world, we have a state\n\n         12   regional committee that speaks for the totality of their\n\n         13   state.  So it's that PJM can have a single point of\n\n         14   reference and a single answer.\n\n         15              Because, any given day -- and I'm not pointing\n\n         16   fingers, but on any given day, I can get a different\n\n         17   perspective from a governor than I can from a senator, that\n\n         18   I can from a state regulator, in a given state.  And that is\n\n         19   a problem.\n\n         20              So, as we go down this journey, obviously my\n\n         21   preference is for one organization, or no more than two. \n\n         22   (Laughs.)  At the end of the day.\n\n         23              COMMISSIONER LECERTE:  Dream big, Dave.  Dream\n\n         24   big.\n\n         25              (Laughter.)\n\n\n\n\n\n                                                                       93\n\n\n\n          1              MR. MILLS:  Yeah.  One!\n\n          2              COMMISSIONER SEE:  Yeah.  And I appreciate that. \n\n          3   I appreciate your comments.  We'll definitely hold you to\n\n          4   that spirit of moving forward.\n\n          5              Also, I apologize.  I was not laughing at you. \n\n          6   You all couldn't see, we had some legislators in the back,\n\n          7   who were waving when you made that comment.  So, I'm happy\n\n          8   to see all of the representation and interest we have.  I\n\n          9   appreciate that.\n\n         10              Pat, why don't we go to you and then Jacob, your\n\n         11   thoughts on this.\n\n         12              CHAIRMAN WOOD:  If states are in the kitchen\n\n         13   cooking the meal they're not going to be writing a nasty\n\n         14   Yelp review afterward.  I mean, that's what you want --\n\n         15              (Laughter.)\n\n         16              CHAIRMAN WOOD:  -- that's fundamentally -- that's\n\n         17   fundamentally what we haven't had here.  And I want to just\n\n         18   say the reason I'm here is I'm falling on the sword for\n\n         19   something I didn't get done 24 years ago, which was finish\n\n         20   the finding what the state obligation should be.\n\n         21              We did, I think, a pretty good job of that in\n\n         22   MISO and SBP, which were the later Order, 2000 filings, after\n\n         23   PJM's.\n\n         24              But I called Glen Thomas and said -- he was\n\n         25   chairman of the Pennsylvania commission at the time, to say\n\n\n\n\n\n                                                                       94\n\n\n\n          1   \"Can you move forward on this idea we've put out with\n\n          2   regional state committees?\"  And they went forward and OPSI\n\n          3   was formed about the time I left FERC, and it's kind of gone\n\n          4   on and done its own things.\n\n          5              It wasn't a squeaky wheel at the time.  I wish we\n\n          6   had spent more time thinking about that.\n\n          7              But my recommendations to, really, adopt a\n\n          8   version of the New England structure rests upon the fact\n\n          9   that OPSI is already up and operational.  It has a role\n\n         10   here.  I think it's a role that should be augmented and\n\n         11   should be aligned with those parts of the Federal Power Act\n\n         12   that align toward the states, which deal with generation,\n\n         13   deal with transmission, the planning and integration of both\n\n         14   of those with retail rates, with resource adequacy.  Those\n\n         15   are some big buckets.\n\n         16              And this RTO is an odd institution that we\n\n         17   crafted -- well actually was crafted a little before I got\n\n         18   here -- but to bridge those gaps that the Federal Power Act\n\n         19   thought it was so neat and wonderful to put this with states\n\n         20   and this with the fed, and all is an integrated blanket.\n\n         21              And so, when you start to unweave it, it really\n\n         22   falls apart.  So, we want to keep it weaved, and I think the\n\n         23   best way to do that is to keep the states in a very strong\n\n         24   role here, acknowledging that, quite frankly, with 13 of\n\n         25   'em, how in the hell often are you going to get large\n\n\n\n\n\n                                                                       95\n\n\n\n          1   agreement among that?  I wouldn't do it Articles of\n\n          2   Confederation style and require 13 votes.\n\n          3              But, you know, that's going to be y'all's issue,\n\n          4   to figure out how to speak as one voice.\n\n          5              But he does need to hear that voice.  If he\n\n          6   doesn't hear the voice and he's independent, he can take the\n\n          7   input and then make the decision.\n\n          8              So, I agree with Kelsey that it really does\n\n          9   depend on the nature of the overall advisory board versus\n\n         10   stakeholder structure that exists today, how that gets\n\n         11   resolved.  Once that gets resolved, I think these other\n\n         12   three buckets look kind of different.\n\n         13              COMMISSIONER SEE:  Uh-huh.\n\n         14              CHAIRMAN WOOD:  I don't think states -- I didn't\n\n         15   recommend that states have the jump ball or the filing\n\n         16   rights.  \n\n         17              I had a long discussion -- in fact, he was\n\n         18   sitting right in your chair, Commissioner See -- Joe\n\n         19   Kelliher and I had this tussle over regional state committee\n\n         20   role in Southwest Power Pool, as my last order here.\n\n         21              And I was engaged in a more robust state role. \n\n         22   He didn't think that complied with the Power Act.  So, we\n\n         23   kind of hit a middle ground there and both concurred in the\n\n         24   outcome.\n\n         25              But, you know, there is a tension there, that we\n\n\n\n\n\n                                                                       96\n\n\n\n          1   have to acknowledge.  It's not just all one way for the\n\n          2   states.  There is a huge role that they have to play, that\n\n          3   it wasn't clear.\n\n          4              I voted on the first capacity market.  It went\n\n          5   from an ICAP structure to a predecessor of today's capacity\n\n          6   market, and I was wondering \"What is this?\"  Coming from\n\n          7   Texas, we didn't have one of those, so I'm not sure what it\n\n          8   was.\n\n          9              But it was really an aggregation of the state\n\n         10   saying \"We don't want the retail open states to be free\n\n         11   riders on the vertically-integrated states that are\n\n         12   maintaining that extra reserve capacity.  We want them to\n\n         13   carry their fair share as well.\"\n\n         14              So, that was fine.  I'm like that made sense to\n\n         15   me, so we voted for it.  But the states did that\n\n         16   collaboratively, in the original PJM, which was growing\n\n         17   pretty fast back then, and agree to say, \"FERC, you take\n\n         18   care of that.\"\n\n         19              So, it was a clear delegation that the states\n\n         20   were in charge but they wanted, in the interest of\n\n         21   efficiency, and really just practicality, for that to be run\n\n         22   on a region-wide basis.\n\n         23              And so, PJM took over that role and, as a\n\n         24   chairman of Dynegy for six years, which was a big player in\n\n         25   this, in this Powerpool, it was a great place to do\n\n\n\n\n\n                                                                       97\n\n\n\n          1   business.  It was clear, it was very predictable, so the\n\n          2   capacity market work had kept its own obligation.  We had to\n\n          3   make damn sure we were ready on those cold nights and cold\n\n          4   days to work, because we were going to have to pay big\n\n          5   penalties if we didn't.\n\n          6              That structure was in place.  It's worked fine. \n\n          7   I think people knew whose role it was to do what.\n\n          8              But when you kind of come up to a point, and\n\n          9   we're now dropping the price now -- of course you're not\n\n         10   going to clear!  If the price is below what you could get in\n\n         11   a competitive market, who wants that?\n\n         12              So, I mean, a lot of these issues, I don't feel\n\n         13   like the resource adequacy thing was not clearly given from\n\n         14   the states to PJM.  The issue is \"Why haven't we...\" you\n\n         15   know, we haven't dealt with some of the fundamental issues I\n\n         16   mentioned in the last paragraph of my one-pager about -- on\n\n         17   the state side -- about the resource adequacy implications\n\n         18   to the state.\n\n         19              But, so filing rights, I think it's important to\n\n         20   have the state consultation there.  I went up to the line\n\n         21   and said \"File the OPSI agreement, if there is one, and it's\n\n         22   not the same as what PJM board wants to do.  File that at\n\n         23   FERC.\"\n\n         24              I didn't say if that was a jump ball filing or\n\n         25   not.  But I think FERC needs to know where the states land,\n\n\n\n\n\n                                                                       98\n\n\n\n          1   and the states need to know it's incumbent on them to come\n\n          2   together and get an answer for that.  Because that's really\n\n          3   going to be the challenge, I think, for my friends at the\n\n          4   state level, is to get consensus across the broad thing, but\n\n          5   not to allow that lack of consensus, if it's not achieved,\n\n          6   to stop what the board and the PJM need to get done.\n\n          7              COMMISSIONER SEE:  Thank you for that.  I really\n\n          8   appreciate the detail you added to that conversation.\n\n          9              There were a lot of really good points in there. \n\n         10   You know, one of them that's not lost is, I think, how\n\n         11   important it is for us to think through these reforms on\n\n         12   their own, how they stand or fall, but the idea that so much\n\n         13   of this is tied to what other decisions are, as well.\n\n         14              So, thank you for highlighting that.\n\n         15              I think let's go to Jacob, and I know Kelsey had\n\n         16   yours up too, so let me complicated the question a little\n\n         17   bit, especially because I know this is an area that you have\n\n         18   thought about a lot and have a lot of thoughts about.\n\n         19              But, when we're talking about the state voice --\n\n         20   right? -- and so much has come up about \"What does the state\n\n         21   voice mean?\"  And that's always a difficult question.  I\n\n         22   spent seven years in state government in a PJM state.  You\n\n         23   know, I understand that not all PJM states think alike. \n\n         24   That can be an understatement, right?\n\n         25              But state government doesn't think alike as well. \n\n\n\n\n\n                                                                       99\n\n\n\n          1   You know, working in the AG's office, you know, the\n\n          2   legislators and the governors, you know, and other agencies,\n\n          3   are sometimes not always on board.\n\n          4              So, there's a lot to be said about how do we make\n\n          5   sure that there is right input coming in and effective\n\n          6   inputs, and some of this comes down to I know you have a lot\n\n          7   of thoughts about one versus two bodies.  So, let's just\n\n          8   complicated the question and put a little bit of that on the\n\n          9   table too.\n\n         10              DEPUTY SECRETARY FINKEL:  No, I really appreciate\n\n         11   it.  And I'll just say I really agree with Judge Bagot and\n\n         12   with what Chairman Wood said.  I think there's a whole bunch\n\n         13   of things I'd love to engage on there, but I think in terms\n\n         14   of the one versus two, we have spent a lot of time thinking\n\n         15   about this.\n\n         16              I don't think there is one perfect answer.  I\n\n         17   think that reasonable minds can differ and there's no\n\n         18   perfect solution, as you see across the country, we have\n\n         19   different, multi, RTOs, a lot of ways this can work, and it\n\n         20   does work.\n\n         21              I think, as much as I would love to live in Dave\n\n         22   Mills' ideal world, I understand the reasons why, one, it's\n\n         23   efficient.  I do think it's a little bit of a red herring,\n\n         24   or a double standard, though.  I mean, the TOs, or the\n\n         25   generators, or any other group, do not speak with one voice. \n\n\n\n\n\n                                                                      100\n\n\n\n          1   There's a diversity of voices, and you don't say \"Oh well,\n\n          2   the TOs don't get a vote because they can't agree.\"\n\n          3              The states are a diverse bunch.  We're diverse\n\n          4   politically, we're importers, we're exporters, we're\n\n          5   diversely integrated, we're restructured.  Right.  We are\n\n          6   diverse.  And there are 67 million people.  So there's going\n\n          7   to be a diversity of viewpoints.\n\n          8              I think it's sort of too simple to say \"Well, you\n\n          9   have to be on the same page or you don't get to count.\" \n\n         10   That diversity is a challenge and it's also a strength.  And\n\n         11   that's PJM's unique role in this, and I think we need to\n\n         12   lean into that.\n\n         13              And what we've proposed, what we've put forward,\n\n         14   is a two-part proposal, because I think there's a different\n\n         15   role for the policymakers than there is for the regulators,\n\n         16   and we think that -- so, I guess I would just sort of\n\n         17   clarify the three buckets you laid out, Commissioner.  I see\n\n         18   that as two buckets.  I see it as kind of strategic, long\n\n         19   term, direction.  I put the board in that.  And then I see\n\n         20   it as kind of the filing advice and the day to day, and I\n\n         21   see the policymakers really absent from this conversation. \n\n         22   Or, as Judge Bagot said, like, they're not going to be\n\n         23   absent, because they're going to be, you know, involving\n\n         24   themselves late in the process and in the public arena and\n\n         25   using the bully pulpit that they possess.\n\n\n\n\n\n                                                                      101\n\n\n\n          1              We would much rather institutionalize that, give\n\n          2   them a proper place and a proper role, and be involved early\n\n          3   on in setting the direction and in choosing who sits on the\n\n          4   board, and then not being there, you know, last minute,\n\n          5   because of a crisis.\n\n          6              And, at the same time, we think the regulators\n\n          7   who are dealing with this every day, and who have a really\n\n          8   important responsibility on the retail side, when this comes\n\n          9   from the wholesale side to the retail side, you know,\n\n         10   there's a throughput there, and the regulators have to be at\n\n         11   the table.\n\n         12              So, I think, you know, we think it's really\n\n         13   important, these three seats on the nominating committee to\n\n         14   have a real role in that process and some real teeth.\n\n         15              And I'll just say that three is not a random\n\n         16   number.  Three is an important number because, as you think\n\n         17   about the three, those three state voices, imagine that they\n\n         18   were a unified bloc, which may not always be the case, but\n\n         19   imagine they were, and then the two incumbent board members\n\n         20   who vote on that committee, that's half that committee.\n\n         21              And then you have the private interests, the\n\n         22   other half of that committee, and that rough parity, we\n\n         23   think, is really important, if you're going to have\n\n         24   confidence in the public interest being expressed\n\n         25   meaningfully in that process.\n\n\n\n\n\n                                                                      102\n\n\n\n          1              And then, just on the filing rights, we do think\n\n          2   it's important -- and I really agree with the way Judge\n\n          3   Bagot framed it, and I would go back to what Chairman Swett\n\n          4   said about \"What does success look like?\"  I think we should\n\n          5   be focused on we're not here to say \"Oh, we have to have\n\n          6   blank,\" or we don't have a red line.  What we want to do is\n\n          7   focus on what is a successful outcome, and it's what Judge\n\n          8   Bagot said.  It's the states being listened to and being\n\n          9   respected and being part of these problems that we have an\n\n         10   important shared role in implementing.\n\n         11              It doesn't do anyone any good for PJM to have a\n\n         12   solution, no matter how great they may think it is, and go\n\n         13   all the way down the road and submit it to this commission\n\n         14   and have it be implemented, and then the states hate it and\n\n         15   don't work out of their -- or it doesn't go well.  That's\n\n         16   not in anyone's interest.  You've got to have the states\n\n         17   there early, and we think what we've seen in the other\n\n         18   regions, this is not something that is novel.  All the other\n\n         19   regions, the states have some form of filing right over some\n\n         20   aspect of this process.\n\n         21                             We think having those filing\n\n         22   rights is sort of the language in which this entire entity\n\n         23   speaks, and you need to have that in order to be a\n\n         24   meaningful participant.  If there are other variants, huge\n\n         25   respect for Chairman Wood, he has a different idea on that,\n\n\n\n\n\n                                                                      103\n\n\n\n          1   this consultation idea, I think we're open to that, as long\n\n          2   as it gets to that same result.\n\n          3              Because what we don't want is to say, you know,\n\n          4   sort of, we'll listen -- you know, you can have a\n\n          5   conversation, you can be heard, but not actually\n\n          6   meaningfully be listened to.  That doesn't move the ball. \n\n          7   That doesn't solve what we need to solve.\n\n          8              So, I think we're open to variants of doing that,\n\n          9   but we have to focus on what is the outcome and what does it\n\n         10   get to.\n\n         11              COMMISSIONER SEE:  Thank you.  Before I move on\n\n         12   to this conversation, I definitely want to make sure to pass\n\n         13   it on to my colleagues for other directions.  I do see a\n\n         14   couple cards up.  But Marjorie, if you can keep it brief,\n\n         15   and David if you can as well if you want to and then, yeah,\n\n         16   and Chair Bagot if  you wanted to have the final word on\n\n         17   this one.\n\n         18              MS. PHILIPS:  I'll try.  Using Pat's analogy, too\n\n         19   many cooks in the kitchen, we know what happens.  So, we\n\n         20   need a chef, and the sous chefs can tell the chef what they\n\n         21   see, what they're looking at, but the chef is chef.\n\n         22              I think I would like to go back to our proposal,\n\n         23   which was to expand OPSI, to have a governors appointing...\n\n         24   the reason is we are trying to minimize the amount of\n\n         25   change.  Chairman Swett, you put it so great.  We're looking\n\n\n\n\n\n                                                                      104\n\n\n\n          1   to fix the cracks.  We're not looking to pull out the\n\n          2   bricks.\n\n          3              And we're trying to look -- we want to focus on\n\n          4   getting market rules in place.  We don't want the governance\n\n          5   discussion to be a sideshow that we're all focused on.  And\n\n          6   so, we think that's the beauty of using OPSI.  You can do it\n\n          7   quick, you amend OPSI, the governors appoint.\n\n          8              Most critical, that we haven't talked about, is\n\n          9   the states need the resources to participate meaningfully,\n\n         10   and that's something that NESCO does really well, which is\n\n         11   we support greater funding for OPSI so that they get the\n\n         12   expertise, they understand the issues, and it's a very\n\n         13   selfish ask, because we find, in New England, we can go and\n\n         14   negotiate and talk to NESCO.  We may not agree, but they're\n\n         15   sophisticated, they understand our concerns, and that's some\n\n         16   of the happiness you see, which is we can compromise\n\n         17   because they see \"Oh, the generators aren't being greedy;\n\n         18   this is a real issue.\"\n\n         19              So I would emphasize no matter what you take away\n\n         20   from this, OPSI needs experts and they need more funding,\n\n         21   and we really support that, so that we can have a better\n\n         22   participation.\n\n         23              CHAIRMAN SWETT:  And, if OPSI is better funded,\n\n         24   then what is your ideal role for them, in the stakeholder\n\n         25   process?\n\n\n\n\n\n                                                                      105\n\n\n\n          1              MS. PHILIPS:  So, they can present issues now. \n\n          2   They can do user groups, they can write letters to the\n\n          3   board, and they can intervene at FERC.  There's not a lot of\n\n          4   that they can't do.\n\n          5              The problem is they often don't speak in one\n\n          6   voice and they often speak in generalities.  So, if OPSI\n\n          7   wants to make a presentation, that's why it needs the\n\n          8   experts.  Come with a proposal, not just \"We don't like\n\n          9   this.  It's going to raise costs, it's going to lower\n\n         10   costs.\"\n\n         11              So, the idea is that they meet with the board\n\n         12   and, as we have heard between David and Kelsey, that needs\n\n         13   to be more meaningfully enhanced.  We think a board member\n\n         14   should be assigned to the states, to deal with the\n\n         15   governors, so that even though we don't want the board to be\n\n         16   responding singly to a government, they need to understand\n\n         17   \"This is Pennsylvania's concerns.  This is Virginia's\n\n         18   concerns.\"\n\n         19              And so, they need to understand individual state\n\n         20   concerns.  A board member has responsibility for\n\n         21   relationship with the state, at the governors level.\n\n         22              And then OPSI becomes a more meaningful voice in\n\n         23   the stakeholder process.  And, if they were, we could talk\n\n         24   to them and get them more involved in the proposals.\n\n         25              I know my company has, in the past -- we often\n\n\n\n\n\n                                                                      106\n\n\n\n          1   volunteer to, like, let us talk to OPSI, let us explain\n\n          2   what's going on.  And frankly, the participation is pretty\n\n          3   low.\n\n          4              And so, we would like to see OPSI more involved,\n\n          5   but more meaningfully understanding the issues.  So, it\n\n          6   would be -- they would have rights to the board.\n\n          7              There's a reason they don't have voting rights. \n\n          8   When PJM was formed, the states didn't want voting rights. \n\n          9   The commissions wanted not to be treated to the ex parte\n\n         10   rules of the stakeholders.  They wanted to be able to\n\n         11   consult with the board separately.\n\n         12              And we think that's a great structure to keep.  I\n\n         13   hope that's responsive.\n\n         14              CHAIRMAN SWETT:  Uh-huh.  So, you raised the\n\n         15   point in your testimony and so did PJM, at the formation\n\n         16   that states did not want a voice.  So, to our state\n\n         17   representatives, it seems like those circumstances have\n\n         18   changed, and perhaps your ex parte concerns are no longer\n\n         19   the same?\n\n         20              CHAIR BAGOT:  Well, I don't know that it's\n\n         21   inconsistent.  I don't hear either of us advocating for us\n\n         22   to have a vote on the members committee.  And that's\n\n         23   something that we opted not to be.  We're not members.  So\n\n         24   we don't have a vote right now, and that's how things sort\n\n         25   of move through the stakeholder process.\n\n\n\n\n\n                                                                      107\n\n\n\n          1              I think the tradeoff there was that OPSI would\n\n          2   then have direct access to the board, and we have these\n\n          3   board meetings.\n\n          4              But, if that is not meaningful, if we don't have\n\n          5   a vote, and we also don't feel like we have meaningful\n\n          6   engagement with the board, or we have no ability to sort of\n\n          7   help develop what the strategic direction of PJM needs to be\n\n          8   going forward and what broader initiatives they need to\n\n          9   focus on -- right? -- and that's what, I think, is\n\n         10   appropriate for us to say, is to help shape the direction of\n\n         11   \"These are the reforms that we really need to see,\" I don't\n\n         12   know that we necessarily need to be telling the board\n\n         13   exactly what those little nitpicky things are.  I think we\n\n         14   can participate in the existing stakeholder process and\n\n         15   provide that feedback that way.\n\n         16              So, I don't think we're asking for a vote.  I\n\n         17   think what we're asking for is to make sure that the\n\n         18   existing process is working the way that it should be\n\n         19   working.\n\n         20              And I think some of the discussion -- I mean,\n\n         21   Marjie has had a lot of experience with the PJM process, and\n\n         22   I hear her frustration with working with the OPSI states and\n\n         23   whether we're coming with the type of feedback that she\n\n         24   wants us to come to.\n\n         25              And that goes to my point with accountability. \n\n\n\n\n\n                                                                      108\n\n\n\n          1   The states do need to figure out how to engage in a more\n\n          2   meaningful way.\n\n          3              But this sort of discussion I think is\n\n          4   illustrative of why the states feel like they don't have a\n\n          5   voice.  Right?  It's because that's often the response that\n\n          6   we get from stakeholders, is \"Well, you guys don't know what\n\n          7   you're talking about,\" or, you know, instead of the\n\n          8   assistance that maybe we need or helping direct us to, sort\n\n          9   of, the right sort of decision points we should be thinking\n\n         10   about.\n\n         11              And so, I think this sort of illustrates the\n\n         12   challenge that we have in participating in this process.\n\n         13              I do just want to say one thing that Pat Wood\n\n         14   brought up, which is that, you know, we need to think about\n\n         15   these roles in very distinct ways, and I think when we're\n\n         16   talking about the roles of the states, whether it's 205, or\n\n         17   consultation, or -- it would be helpful, and it would be\n\n         18   helpful, and it would help the states have accountability,\n\n         19   if we had well-defined roles, in terms of what areas the\n\n         20   states need to be part of the discussion.  Right?\n\n         21              Like, what elements of resource adequacy should\n\n         22   we be working with the PJM board to say, you know, in the\n\n         23   next one year, two years, three years, these are the things\n\n         24   that we should be focused on, and that should be working\n\n         25   through the stakeholder process.  Right?\n\n\n\n\n\n                                                                      109\n\n\n\n          1              Because I don't know that it makes sense for the\n\n          2   states just to have equal input of blanket across the board\n\n          3   on all of the issues, and it makes it hard, I think, for us\n\n          4   to be accountable and provide that meaningful feedback, when\n\n          5   we don't have that sort of very specific and precise\n\n          6   directive of where we sit.\n\n          7              So, I think, with states, greater state\n\n          8   involvement, comes also greater clarity on what role they\n\n          9   play and where they should really be speaking up, and where\n\n         10   maybe it's not appropriate.\n\n         11              CHAIRMAN SWETT:  Have the states coalesced around\n\n         12   the finer point on which issues you should be involved in?\n\n         13              CHAIR BAGOT:  Well, this -- I'm going to let\n\n         14   Jacob go -- this maybe is not the exact answer that you're\n\n         15   looking for.  But on the one group versus two groups, I\n\n         16   think I agree with Jacob that we don't necessarily need one\n\n         17   group; we need different bodies, that have different\n\n         18   purposes, and that they're very clearly defined.\n\n         19              And so, it makes sense for the governors to play\n\n         20   a role on the nominating committee.  It probably makes\n\n         21   sense, to the extent that they're sort of a steering\n\n         22   committee or strategic committee, that sits down with PJM\n\n         23   board and helps develop what the initiatives are going to be\n\n         24   over the next one, two, three years.\n\n         25              It makes sense that there probably is both a role\n\n\n\n\n\n                                                                      110\n\n\n\n          1   for OPSI and as, like, sort of the technocratic experts, but\n\n          2   also for the policymakers at the states.  Right?  It\n\n          3   probably makes sense that both of those voices are there.\n\n          4              But then, when we get into, like, the\n\n          5   consultation requirements for 205 rights, and you get into\n\n          6   providing feedback in the stakeholder process, well maybe\n\n          7   greater engagement or resources provided by PJM to OPSI, to\n\n          8   be able to provide that more meaningful technical feedback,\n\n          9   along the lines of what Marjie suggested, that I think is an\n\n         10   OPSI role, because we live the day to day of, like, what\n\n         11   these market rules mean, and how they affect our utilities\n\n         12   and how that impacts retail rate makers.\n\n         13              And so I think, if you have those very defined\n\n         14   roles, then you're not going to run into the issues that\n\n         15   David addressed, where you're hearing multiple states,\n\n         16   conflicting state voices, weigh in on the same issues.\n\n         17              COMMISSIONER LACERTE:  I wanted to get back to an\n\n         18   analogy that Marjorie made a minute ago, when you said \"The\n\n         19   chef is the chef.\"  And I presume the chef, in this\n\n         20   situation, is the PJM board, as let by the CEO.  Okay.\n\n         21              So, would you agree that the sous chefs should\n\n         22   not have two-thirds voting rights to tell the chef what to\n\n         23   do?\n\n         24              (Laughter.)\n\n         25              MS. PHILIPS:  I don't think that the sous chefs\n\n\n\n\n\n                                                                      111\n\n\n\n          1   get the right to tell PJM what to do.  There are 205 rights,\n\n          2   but the time you've gotten to that, pretty much the chef has\n\n          3   bought into the sous chef.  I can't think of -- the chef...\n\n          4              COMMISSIONER LACERTE:  It's not that complicated\n\n          5   of a question.\n\n          6              (Laughter.)\n\n          7              MS. PHILIPS:  My ex-husband was a chef, so --\n\n          8   this is touchy.  (Laughs.)\n\n          9              (Laughter.)\n\n         10              CHAIRMAN SWETT:  You're triggering her.\n\n         11              COMMISSIONER ROSNER:  Ask it without \"chefs.\"\n\n         12              (Laughter.)\n\n         13              CHAIRMAN SWETT:  She brought \"chef\" up.  Maybe\n\n         14   she wants to talk about it.\n\n         15              MS. PHILIPS:  I did.  I'm guilty.\n\n         16              COMMISSIONER LACERTE:  So when we say a chef has\n\n         17   to be a chef, we have to have somebody in charge.\n\n         18              MS. PHILIPS:  I actually, I go back to my view,\n\n         19   that it seems like the states -- I know it's hard for you to\n\n         20   get -- and I believe the states need to be invested because\n\n         21   they don't feel they are, but I can tell you from a\n\n         22   stakeholder perspective it looks like the states have had\n\n         23   far more influence on the board than the stakeholders.\n\n         24              And so that's why it's hard for me to answer the\n\n         25   question \"Are the stakeholders the sous chef.\"\n\n\n\n\n\n                                                                      112\n\n\n\n          1              COMMISSIONER LACERTE:  I don't know if anyone\n\n          2   agrees with that statement.  I think, by and large, the\n\n          3   prevailing opinion of everyone in this room is contrary to\n\n          4   that statement.\n\n          5              And I think that the boards themselves have told\n\n          6   me point blank that their position is that they are not\n\n          7   afraid of the governors or the states.  They are afraid of\n\n          8   the stakeholders.\n\n          9              So, I think that it's important that we listen. \n\n         10   When we say this is not a secret society, that's exactly\n\n         11   what a secret society would say.\n\n         12              (Laughter.)\n\n         13              COMMISSIONER LACERTE:  So, we have to listen to\n\n         14   these concerns; we can't wish them away.\n\n         15              MS. PHILIPS:  So, to be clear, I am not -- I want\n\n         16   to be clear that we absolutely support a larger role, and if\n\n         17   they want to create a two-step organization with the\n\n         18   governors and the states, have at it, because I agree, I\n\n         19   don't want PJM being attacked from the outside.  I want\n\n         20   everybody inside the tent and working collaboratively.\n\n         21              What I'm concerned with, if I could just give one\n\n         22   example, Jacob brought a proposal to the PJM stakeholder\n\n         23   process.  It was to go to seasonal markets.  Everybody\n\n         24   agrees PJM has to go there.  But we didn't agree on the\n\n         25   timing, because we were stuck with the ELCC, which was a\n\n\n\n\n\n                                                                      113\n\n\n\n          1   mess, in implementing, and nobody understood it.\n\n          2              So, what I'm concerned about is the governors\n\n          3   come to PJM and, by the way, PJM wanted to input seasonal\n\n          4   markets, and they finally realized it was too complicated.\n\n          5              What I'm worried about is that the governors come\n\n          6   to PJM and say \"This you must do,\" and as stakeholders we're\n\n          7   the ones working in the rules.  I'm the one investing.  I'm\n\n          8   having trouble telling my lenders what the ELCC is.  I don't\n\n          9   want to go back and tell them not only do I not know what\n\n         10   the ELCC is, but we're going to go to seasonal markets, and\n\n         11   nobody knows what that means.\n\n         12              So, I am speaking from my paranoia as a\n\n         13   stakeholder, looking to find that balance.  So, it is really\n\n         14   important that governors be there, to tell PJM what they\n\n         15   think.  It's really important that the states do that.\n\n         16              But I'm looking for the balance that the board,\n\n         17   at the end of the day, remains independent.\n\n         18              And the stakeholders, we're advisory.  Right?  I\n\n         19   mean, we have 205 votes, but it's on the energy market.\n\n         20              COMMISSIONER LACERTE:  But you're not advisory. \n\n         21   You are not advisory!\n\n         22              MS. PHILIPS:  But we're here because of the\n\n         23   capacity market.  That's why we're here.  Because we're not\n\n         24   getting enough built.  And that is an RAA issue, and that is\n\n         25   205 to PJM.\n\n\n\n\n\n                                                                      114\n\n\n\n          1              COMMISSIONER LACERTE:  Do you support the\n\n          2   stakeholders being advisory or not?  Or as an investor.\n\n          3              MS. PHILIPS:  If I thought PJM could truly be\n\n          4   independent, and that the FERC would back them up, as what\n\n          5   is economically sound, what are just and reasonable rates...\n\n          6              COMMISSIONER LACERTE:  We've got to take a leap\n\n          7   of faith here.\n\n          8              MS. PHILIPS:  Speaking for Marjie Philips, right \n\n          9   Not my company.  We could maybe get there.  It's a concern\n\n         10   that the board is not independent.  \n\n         11              Again, we're as paranoid as the states.  Right? \n\n         12   (Laughs.)\n\n         13              COMMISSIONER LACERTE:  Stacey, the same question. \n\n         14   Absent the chef sidetrack.\n\n         15              MS. BURBURE:  AEP supports advisory voting.\n\n         16              COMMISSIONER LACERTE:  Thank you.  I'm glad we\n\n         17   could put a bow on that one.\n\n         18              COMMISSIONER CHANG:  Is Jacob going to speak\n\n         19   next?\n\n         20              DEPUTY SECRETARY FINKEL:  Can I just make a\n\n         21   comment?  Because you mentioned the seasonal issue charge. \n\n         22   And that was such an educational experience for me, because\n\n         23   -- this was a year or so ago -- and the Pennsylvania\n\n         24   governor's office went to PJM, checked every box, went\n\n         25   through the whole process, we did an issue charge or problem\n\n\n\n\n\n                                                                      115\n\n\n\n          1   statement.  We went through this entire thing.\n\n          2              And it was just so clear to me that the -- again,\n\n          3   I think the members have such an important role and they\n\n          4   should retain an important role.  They know their businesses\n\n          5   better than anyone.  They know the market they work in\n\n          6   better than anyone.\n\n          7              But they don't have the strategic vision for the\n\n          8   larger, bigger, picture.  PJM is unable to take big, bold,\n\n          9   action, which is what is needed in this moment.  And I think\n\n         10   that's why the board does need to be empowered, and the\n\n         11   states need to be part of that conversation.\n\n         12              And I am just struck -- after the last CIFP, the\n\n         13   first CIFP, last fall, 12 different packages to solve,\n\n         14   large load integration, really every possible choose your,\n\n         15   you know, favorite menu option, the solution, everything was on\n\n         16   there.  All 12 were voted down by the members.  They hated\n\n         17   all the options.  Right?\n\n         18              And, the day after that, I went back to Valley\n\n         19   Forge for -- they had, like, a post mortem on what had\n\n         20   happened, and I could not believe my ears, that the members\n\n         21   went around patting themselves on the back for what a\n\n         22   thoughtful, deliberative, you know, creative, process they\n\n         23   had just gone through.\n\n         24              And I was, honestly, the only person in the room\n\n         25   saying \"This is a failure.  You have not advanced the ball. \n\n\n\n\n\n                                                                      116\n\n\n\n          1   You have not actually given the board clear direction or\n\n          2   told them which way you want them to go.  This is just a\n\n          3   muddle and a failure.\"\n\n          4              So, I just -- I take the criticism of the states,\n\n          5   and I think the states have not been perfect, and we can be\n\n          6   better, and I appreciate increased funding and increased\n\n          7   support, and we're open to that.  But, I just think, again,\n\n          8   taking it back one level, this is broken.  This is not\n\n          9   working.  And there needs to be a change.\n\n         10              COMMISSIONER CHANG:  Maybe that's a great segue\n\n         11   for some of my questions.  I want to summarize.  Sorry,\n\n         12   David, we'll give you a chance in a second here.\n\n         13              I want to summarize a little bit about the\n\n         14   states' involvement, because I hear a few things, and first\n\n         15   I think states want to be on the nominating committee, or\n\n         16   some representation on the nominating committee.  And states\n\n         17   might also want some version of I'll call it \"jump ball,\"\n\n         18   which basically says if PJM and its stakeholders presenting\n\n         19   a proposal of some kind -- let's stick with capacity market\n\n         20   just because we need -- there's different 205 rights with\n\n         21   different parts of the market.  Let's say capacity market,\n\n         22   or resolution of some changes in the capacity market.\n\n         23              If PJM and its stakeholders present some kind of\n\n         24   proposal that the states really don't like, or can't -- that\n\n         25   states might want some ability to present another counter\n\n\n\n\n\n                                                                      117\n\n\n\n          1   proposal or alternative proposal -- that's what I'm hearing. \n\n          2   Whether you exercise that right or not is a different\n\n          3   question.  But just having that right gives you more\n\n          4   leverage in saying \"Look, you know, maybe I don't have a\n\n          5   voting right in the members committee, but I have this other\n\n          6   potential jump ball.\"  Right?\n\n          7              Which is not, by the way, how New England works,\n\n          8   but we can save that for some other clarification.\n\n          9              Is that -- okay -- so, another topic on the\n\n         10   states' participation, I personally feel like -- I hear what\n\n         11   David had mentioned, which is I think it would make more\n\n         12   sense, to me, sort of, like, thinking how Dave might think,\n\n         13   is having one organization or some collective organization,\n\n         14   collected voices from the states, would be much easier for\n\n         15   PJM to deal with and understand, which then pushes the\n\n         16   obligation and the burden of getting to some kind of\n\n         17   agreement to the states. \n\n         18              I think this was, you know, when we talked, a few\n\n         19   days ago, this is where, you know, be careful what you wish\n\n         20   for because coming to an agreement with 13 states and D.C.\n\n         21   is not easy, but perhaps you're ready to take that on.  And\n\n         22   I take, you know, Chair Bagot, your point earlier, which is\n\n         23   if you don't get it in the front end, you're going to have\n\n         24   to get it at the back end.  You're going to try to oppose it\n\n         25   some other way, you're going to inject -- or the states,\n\n\n\n\n\n                                                                      118\n\n\n\n          1   some states might interject the other way, or \"We don't like\n\n          2   the prices because we never believed in the market design,\n\n          3   so now we're going to do something else.\"\n\n          4              So I do believe that states must have some way of\n\n          5   interacting and actually decision-making rights, whether\n\n          6   that's a 205 jump ball type of rights, or some other way,\n\n          7   and I think that has to be consolidated some way so that PJM\n\n          8   is -- because that's what PJM does today.  Like, you know,\n\n          9   \"What does Virginia want?  What does Pennsylvania want? \n\n         10   Well, what does Ohio want?\"\n\n         11              Like, I don't think it helps PJM when the states\n\n         12   don't have maybe not one voice, but at least some\n\n         13   consolidated voice.  So those are what I've already heard,\n\n         14   and I feel like that's coming -- to solidify in my head.\n\n         15              I do want to bring up another topic.  You can\n\n         16   answer them all together if you'd like.  Which is some\n\n         17   parties have discussed giving PJM more filing rights, and\n\n         18   this is no longer the states' jump ball rights; this is\n\n         19   PJM's filing rights.  And can someone just explain more\n\n         20   about the tradeoffs of that?  So, are we taking some rights\n\n         21   from the stakeholders, the TOs, and giving it to PJM?  And\n\n         22   what would look like, David, if that were the case?  Would\n\n         23   that come from -- how would you make those decisions?  Is\n\n         24   that the board making those decision?  And then what are the\n\n         25   tradeoffs?\n\n\n\n\n\n                                                                      119\n\n\n\n          1              And I don't mind who wants to go first, but\n\n          2   probably, David, if you can go first.\n\n          3              MR. MILLS:  Yeah.  Our perspective is not --\n\n          4   we're not talking about giving the board 205 rights on the\n\n          5   transmission cost allocation, CPOA.  What we are talking\n\n          6   about is the operating agreement, which would be the energy\n\n          7   and ancillary services model.\n\n          8              And I think that, you know, we would run a\n\n          9   fulsome stakeholder process.  And here I'm probably filling\n\n         10   in details that would be yet to be filled in, but I think\n\n         11   for illustrative purposes I need to do that.\n\n         12              And let's say we put a time limit on a\n\n         13   stakeholder process.  I don't know, six months, a year,\n\n         14   we'll all figure out a number.  But if the members are not\n\n         15   able to get to a conclusion at that point in time, the board\n\n         16   would be empowered to make a 205 filing.  That's how we had\n\n         17   thought about it.\n\n         18              COMMISSIONER CHANG:  But this is limited to all\n\n         19   the energy and ancillary services (off microphone).\n\n         20              MR. MILLS:  Well, in an ideal world, that would\n\n         21   be the first stop, but in an ideal world it would also\n\n         22   include the transmission planning aspect, in the RTEP.  That\n\n         23   would be the third dimension.\n\n         24              But the one thing I want to be careful of is\n\n         25   sometimes we're -- and the panelists in their pre-filed\n\n\n\n\n\n                                                                      120\n\n\n\n          1   testimony we were sort of doing this, and I want to make\n\n          2   sure we don't do it here live, is that we're talking about\n\n          3   jump ball rights for the states when, in fact, who are they\n\n          4   sharing those with?  Because it seems -- it would be\n\n          5   inconsistent from this independent discussion that we're\n\n          6   having for the states to have a jump ball right on rights\n\n          7   that the PJM board doesn't even have.\n\n          8              COMMISSIONER CHANG:  Are there other tradeoffs\n\n          9   you want to elaborate on?  Maybe not.  Okay.\n\n         10              (Laughter.)\n\n         11              DEPUTY SECRETARY FINKEL:  I'll just, to\n\n         12   anticipate advisory voting and moving the 205 rights that\n\n         13   are in the OA to the tariff, and giving the board control\n\n         14   over those, I think we're open to that idea, because we\n\n         15   understand things have to happen more quickly.  I would\n\n         16   encourage six months, not a year.  The shorter the better.\n\n         17              But I think we're open to that, as long as it is\n\n         18   balanced with a counterweight that serves the public\n\n         19   interest, because I think our fear is yes, we need to\n\n         20   empower the board, yes, we need to get to yes faster and\n\n         21   more predictably, but a board that is untethered from checks\n\n         22   and balances can go in any direction, and you need to have\n\n         23   some check in that process, which is why we think, if you\n\n         24   give the states a meaningful role in the nominating\n\n         25   committee and you give them these jump ball filing rights,\n\n\n\n\n\n                                                                      121\n\n\n\n          1   those are important checks on an otherwise unrestrained\n\n          2   board.  That allows us to feel comfortable with that\n\n          3   process.\n\n          4              And I just wanted to clarify, in terms of the\n\n          5   filing rights, our vision of it is actually quite narrow\n\n          6   jump ball filing rights on resource adequacy.  So not\n\n          7   dealing with other issues.\n\n          8              And, to David's point, not dealing with things\n\n          9   the board doesn't have today.  And we would envision that to\n\n         10   be an informal arrangement between the states and PJM.  We\n\n         11   would not envision that being something that would come to\n\n         12   this commission for approval, or to even have the necessary\n\n         13   force of law, but more of a convention or a practice that\n\n         14   would be solemnized in some sort of MOU or something, that\n\n         15   when a super majority of regulators disagree really\n\n         16   strongly with something, PJM is going to file in resource\n\n         17   adequacy and that pure nexus, where the states have an\n\n         18   important interest, PJM agrees voluntarily it would file a\n\n         19   state alternative alongside it, and this commission would\n\n         20   decide.\n\n         21              So, we think that's a really -- again, we are\n\n         22   trying to be extremely reasonable and practical and get\n\n         23   solutions that can come quickly.\n\n         24              And to your point, Commissioner Chang, I mean, I\n\n         25   totally hear the reasons why one is better than two, and one\n\n\n\n\n\n                                                                      122\n\n\n\n          1   would be more manageable than two.  I think, just in the\n\n          2   spirit of solving, improving, governance, not perfecting\n\n          3   governance but improving governance and getting on to\n\n          4   solving the market problems we face, we think it's just a\n\n          5   lot more advisable to have, you know, a distinct governors'\n\n          6   group, to Judge Bagot's point, that has a distinct role and\n\n          7   set of responsibilities from what the regulators do.  And we\n\n          8   think those two things, as they are in New England, can\n\n          9   coexist in a productive way.\n\n         10              COMMISSIONER LACERTE:  I have a followup question\n\n         11   for Stacey, as it relates to that.  In AEP's comments, they\n\n         12   stated that they support providing states with defined\n\n         13   authority under Section 205 to cause filings to be made\n\n         14   before the Commission, on matters within their collective\n\n         15   jurisdiction.\n\n         16              Can you elaborate on that?  Is that a jump ball\n\n         17   right?  Is that something that looks more like RSC has in\n\n         18   SPP?  Can you go a little further?\n\n         19              MS. BURBURE:  Thank you, Commissioner, for the\n\n         20   question, and the wording there was deliberate, because our\n\n         21   focus is on action rather than being hung up on how exactly\n\n         22   those rights are defined, the precise implications or\n\n         23   boundaries of that.\n\n         24              The real question that we are asking is \"Is this\n\n         25   a process that is going to drive us to big, bold, ideas, to\n\n\n\n\n\n                                                                      123\n\n\n\n          1   better solutions for PJM?\"  That's what we need, at the end\n\n          2   of the day.\n\n          3              COMMISSIONER LACERTE:  I thought your comments\n\n          4   were very all written, so compliments to whoever, behind the\n\n          5   scenes, helped compile those things.\n\n          6              MS. BURBURE:  Thank you.\n\n          7              COMMISSION CHANGE:  Marjie, do you want to talk\n\n          8   about 205?\n\n          9              MS. PHILIPS:  Can I be the defender of\n\n         10   stakeholder rights?\n\n         11              COMMISSIONER LACERTE:  You could try.\n\n         12              MS. PHILIPS:  It's kind of interesting that the\n\n         13   four sectors, in their filings, all said that PJM is\n\n         14   working.\n\n         15              What's not working is that we don't have\n\n         16   deadlines and discipline, and that is a different issue than\n\n         17   205 rights.\n\n         18              And I give you an example.  When PJM really\n\n         19   thinks there's something wrong, they file a 206.  \n\n         20              In EL-2226, there as a transmission congestion\n\n         21   penalty constraint issue.  That was a market issue.  PJM\n\n         22   filed.  Within 18 days, the Commission responded.\n\n         23              So, let's not pretend -- let's not ignore that\n\n         24   the rights that PJM has to act expediently.\n\n         25              The stakeholder process needs discipline, I\n\n\n\n\n\n                                                                      124\n\n\n\n          1   agree.  It was not a success that we had 14 proposals.\n\n          2              But I can tell you, as a stakeholder that's\n\n          3   worked through the process, like the Reserves Project, LS\n\n          4   brought a proposal, three years ago, and the PJM staff\n\n          5   didn't buy into it.  And so, if we don't get PJM's staff to\n\n          6   buy into it and then we go to the stakeholder proposal\n\n          7   process, it's kind of dead on arrival.\n\n          8              So, there is some logic to it.  Just like we all\n\n          9   felt that PJM personnel were going to get bonused if they\n\n         10   went to seasonal markets, and nobody in the stakeholder\n\n         11   process felt we were ready.  And that's the reason we like\n\n         12   that 205 check, and there's nothing wrong with it, if we\n\n         13   disciplined the process, if we had deadlines, that you can\n\n         14   only, you know, talk about something.\n\n         15              If you had -- you know, one of the stalling\n\n         16   things in PJM is \"I need more education.\"  That can push\n\n         17   discussions out for years.\n\n         18              And so, we need more discipline around how\n\n         19   stakeholders exercise the 205 rights.  And it's only the\n\n         20   energy markets.  Right?\n\n         21              But I think that that balance does create\n\n         22   discipline, that PJM staff can't just do what they think is\n\n         23   right, without talk about the people who are investing, and\n\n         24   interpreting, and dealing with these rules.  And yet, also,\n\n         25   if PJM staff doesn't support the stakeholders, it's not\n\n\n\n\n\n                                                                      125\n\n\n\n          1   going to go anywhere in the stakeholder process.\n\n          2              So it works.  It's just the actual mechanics of\n\n          3   the stakeholder process are lost.  There used to be decision\n\n          4   makers that came to these meetings, and you could vote. \n\n          5   That doesn't happen anymore.  You get wonks like me, that\n\n          6   are coming and trying to defend my company's decision --\n\n          7              COMMISSIONER ROSNER:  So, Marjie, the deadlines\n\n          8   and discipline look like, you know, we have some deadlines\n\n          9   on the stakeholder process, and then, if it's still -- those\n\n         10   are unable to resolve the issue, is there openness to the\n\n         11   board having access to the tools that they currently do not?\n\n         12              MS. PHILIPS:  Speaking for Marjie Philips, not\n\n         13   LS, I think that is not an unfair outcome.\n\n         14              COMMISSIONER ROSNER:  Okay.\n\n         15              MS. PHILIPS:  For energy now.\n\n         16              COMMISSIONER ROSNER:  For the areas of the\n\n         17   operating agreement that they don't clearly have a tariff.\n\n         18              MS. PHILIPS:  Right.  It's energy and ancillary\n\n         19   services.  I mean, they even control collateral.  Right? \n\n         20   They have the 205 rights over collateral.\n\n         21              COMMISSIONER ROSNER:  Yep.\n\n         22              MS. PHILIPS:  So, yes.  I don't think that's\n\n         23   unfair.\n\n         24              COMMISSIONER ROSNER:  Okay.\n\n         25              MS. PHILIPS:  I think David has one.\n\n\n\n\n\n                                                                      126\n\n\n\n          1              COMMISSIONER ROSNER:  I wanted to ask -- oh, Mr.\n\n          2   Mills, please.\n\n          3              MR. MILLS:  It's come up twice, and so I just\n\n          4   need to address it.  I'm sort of a -- you know, this is week\n\n          5   11 and I'm sort of a quick wins sort of person.  And one of\n\n          6   the things that was clearly identified as a result of the\n\n          7   prefiling is I believe that the board needs to take\n\n          8   ownership for prioritizing the work streams that come into\n\n          9   the stakeholder process.\n\n         10              So, the development of that, whether it's an\n\n         11   annual work plan or whether it's a longer term view, I think\n\n         12   we have to put some guardrails around the amount of material\n\n         13   and issue charges that are coming through the process,\n\n         14   because it is absolutely unwieldly.\n\n         15              I know I want to respect the members' ability to\n\n         16   bring discussion and bring topics in, but I think an\n\n         17   appropriately empowered board should be able, from a\n\n         18   strategic perspective, to at least prioritize the issues\n\n         19   that come in to the stakeholders.\n\n         20              MS. PHILIPS:  Can I follow up on that?\n\n         21              COMMISSIONER ROSNER:  Yes.\n\n         22              MS. PHILIPS:  To me, that's PJM leadership,\n\n         23   whether it's the board or your team.\n\n         24              MR. MILLS:  Yep.\n\n         25              MS. PHILIPS:  What's standing in your way of\n\n\n\n\n\n                                                                      127\n\n\n\n          1   prioritizing your work streams?\n\n          2              MR. MILLS:  It is the crisis of the moment type\n\n          3   issues.  And I think we just have -- we don't, today, have a\n\n          4   very good filter about \"How does that crisis of the\n\n          5   moment...\"\n\n          6              COMMISSIONER ROSNER:  Do you need authority from\n\n          7   us, to be able to do that?\n\n          8              MR. MILLS:  No.  This is something I am just\n\n          9   letting you know, because it's come up twice, about the\n\n         10   unwieldy process and the number of issues.\n\n         11              COMMISSIONER ROSNER:  Okay.  Great.\n\n         12              MR. MILLS:  And there's something that I am all\n\n         13   over right now.\n\n         14              COMMISSIONER CHANG:  But this is not because\n\n         15   someone's stopping you from prioritizing it.\n\n         16              MR. MILLS:  No.  Not at all.\n\n         17              COMMISSIONER CHANG:  Okay.  Okay.\n\n         18              MR. MILLS:  It's just a missing element right\n\n         19   now.\n\n         20              COMMISSIONER ROSNER:  I just want to take a\n\n         21   moment to acknowledge Senator Hester.  Thank you for coming,\n\n         22   and hello.  I have met with you and I appreciate you being\n\n         23   here.\n\n         24              I wanted to ask one more question.  You know,\n\n         25   someone made the point that politics were muting market\n\n\n\n\n\n                                                                      128\n\n\n\n          1   forces, and you know, that's something of great concern.  I\n\n          2   think Chairman Wood, you mentioned it.  Marjie, you\n\n          3   mentioned this too.\n\n          4              One of the steps back that I have taken on that\n\n          5   is that two years ago we had a dramatic increase in the\n\n          6   capacity market clearing price.  We had a lot of new demand. \n\n          7   And what we didn't have in place at that time was mechanisms\n\n          8   to get the cost of new infrastructure on some of the new\n\n          9   users of that infrastructure that have emerged.\n\n         10              And I think a lot has changed since then, but the\n\n         11   big thing that was missing was, really, retail rate tariff\n\n         12   design, that's since happened.  And, a general comment,\n\n         13   we're not going to talk about.  But the FERC has also been\n\n         14   taking some steps there, that I think work well with that.\n\n         15              But I think one thing that is urgent, that needs\n\n         16   to keep happening in order to have the political\n\n         17   sustainability of, you know, markets need to signal scarcity\n\n         18   in order to get responses, we need to make sure that all the\n\n         19   PJM states have gone through that process, which I think on\n\n         20   the Federal Power Act it's reserved for you all, to make\n\n         21   those judgments on, what classes of customers pay for what,\n\n         22   and we're there, to work with you, in our 206.\n\n         23              But I just want to underscore that that is urgent\n\n         24   for this market to work, and I don't want to take on Judge\n\n         25   Bagot, because I know you have been very active there and I\n\n\n\n\n\n                                                                      129\n\n\n\n          1   know a number of PJM states have as well.  Pennsylvania as\n\n          2   well.  But that work, it's urgent that it gets completed, if\n\n          3   it's not already.\n\n          4              And I would say the same for -- as we discussed\n\n          5   earlier -- the backstop auction, should there be one, Mr.\n\n          6   Mills.  We need the cost allocation in place for that now,\n\n          7   and the fact that it's not here is creating dramatic\n\n          8   uncertainty.\n\n          9              And we need you all, states, to do, with your\n\n         10   values judgment, the curtailment priority of which users,\n\n         11   should there not be enough energy, in 2029, who should have\n\n         12   access to that energy.  We need you to do that.  Urgently.  \n\n         13              And we also need really fast permitting, of\n\n         14   generation, transmission.  And I'd love to see a race to the\n\n         15   bottom on timelines, among the PJM states, on who can go the\n\n         16   fastest, on things that you want to build.\n\n         17              And so, I would just ask, Judge Bagot, Jacob,\n\n         18   with the tools that you have at OPSI, and hopefully soon the\n\n         19   tools that you have to convene governors and state\n\n         20   legislatures, and however we can accommodate those with\n\n         21   interests here, would OPSI be able to have a transparent,\n\n         22   you know, tracking mechanism so that we can all see what\n\n         23   states have done the large load tariff design, which states\n\n         24   have implemented the backstop auction, which states have\n\n         25   revisited curtailment priority, how long it takes to build a\n\n\n\n\n\n                                                                      130\n\n\n\n          1   battery in Pennsylvania, or Maryland, or a gas plant for\n\n          2   whoever wants it -- whatever it is -- or a transmission line\n\n          3   or a substation.  Just like how long it takes to get a CPCN\n\n          4   and whether it can be faster.\n\n          5              I think all of that needs to be a lot more\n\n          6   public, and in the meantime we're here to hear concerns\n\n          7   about the prices that our markets deliver.  But we need your\n\n          8   help to get those prices, in ways that actually get\n\n          9   infrastructure built.\n\n         10              Thank you.\n\n         11              CHAIR BAGOT:  If I can just react quickly, on\n\n         12   your last call to transparency on what's happening in the\n\n         13   states, and if we can provide that, I think the answer is\n\n         14   yes.\n\n         15              I think really what you're asking for, along with\n\n         16   transparency, is accountability, and that's a way to force\n\n         17   accountability and make sure states are sort of staying on\n\n         18   top of the issues that are within their jurisdictional\n\n         19   realm, if people can transparently see what they are or are\n\n         20   not doing and where they are in the process.\n\n         21              I just want to point to the last bullet in my\n\n         22   comments, which maybe does not seem the most significant,\n\n         23   but I think really is, which is that there are things that\n\n         24   we can do today with OPSI, the states, and PJM, that don't\n\n         25   require 205 action, that don't require changes to the\n\n\n\n\n\n                                                                      131\n\n\n\n          1   governance process.  Right?\n\n          2              Connect and manage I think is a place where, if\n\n          3   we had a more systematic process for communicating changes -\n\n          4   - right? -- in the stakeholder process, we could sort of\n\n          5   bring the states, and PJM, in at the same time, and say\n\n          6   \"Here's the things... if we go down this route, there's the\n\n          7   PJM role and the decisions that go there, and here's the\n\n          8   decisions that are complementary, that are going to have to\n\n          9   happen at the state level and they're going to have to\n\n         10   happen at the same time, and so let's create a forum where\n\n         11   we can start working on those issues at the same time.\"\n\n         12              There are ways that we can do that, that we are\n\n         13   not now, and we took the first step, or I'm trying to take\n\n         14   that first step, with respect to curtailment tariffs, and\n\n         15   other things, and that was discussed and announced at the\n\n         16   last PJM stakeholder meeting.\n\n         17   `          But I think there are very easy pathways forward,\n\n         18   to start to have that collaborative discussion where we can\n\n         19   work along parallel tracks, and we don't need 205 for that.\n\n         20              And I hear PJM saying that it's willing to work\n\n         21   with the states on that, and I think it's going to take both\n\n         22   of us sitting down and creating that framework and then\n\n         23   really executing on it.  But I think there's a path there.\n\n         24              COMMISSIONER ROSNER:  And that's wonderful to\n\n         25   hear.  And I would just say that that's urgent.  And I'll\n\n\n\n\n\n                                                                      132\n\n\n\n          1   give you, like, a practical effect of that coordination not\n\n          2   being present so far, is that we probably spent a year\n\n          3   talking with PJM about proposals like \"connect and manage,\"\n\n          4   which I won't go into any more details about.\n\n          5              But, because of the critical input that they need\n\n          6   from all the PJM states to be on the same page on, \"Here's\n\n          7   how we plan to do this,\" they actually can't move forward\n\n          8   with that, or they have been unable to.  So, you know, that\n\n          9   alignment just makes a lot of sense, and I really appreciate\n\n         10   your openness to working on that.\n\n         11              CHAIR BAGOT:  One last -- I guess my ask of PJM,\n\n         12   I think, to help the states be able to be more helpful\n\n         13   partners in that process, is tell us what you need, like\n\n         14   tell us what you need to know from us in order to haves a\n\n         15   coherent process.  Right?\n\n         16              And you have the ability to even be, sort of, an\n\n         17   informal convening body to get the states together, to say\n\n         18   \"Okay, if we do X, states, here's your role.  What's a way\n\n         19   that we can get you all in a room together, talking about\n\n         20   what that means, and let's put some aspirational timeframes\n\n         21   around it.\"  Right?\n\n         22              So, I think we can work together to create a\n\n         23   more, like, systematic process, going forward, where, when\n\n         24   these sorts of things come up, we are already have the\n\n         25   framework in place to engage in that way.\n\n\n\n\n\n                                                                      133\n\n\n\n          1              COMMISSIONER CHANG:  I just want to say that I\n\n          2   heard from Marjie and I hear from you as well, that, you\n\n          3   know, there's no substitute for communication.  I feel like\n\n          4   communication has broken down.  Communication with the\n\n          5   states and many multiple entities of the states, and maybe\n\n          6   communications with stakeholders even, or making decisions\n\n          7   in a timely manner, that has failed.\n\n          8              So, even if we change completely the governance,\n\n          9   you can't substitute communication.  So, I do think -- and I\n\n         10   sort of understand this also from my time in New England, is\n\n         11   that there's got to be so much communication, and you have\n\n         12   more states.  So, more people to talk to, and more alerts\n\n         13   and more, you know, heads ups, and nobody likes surprises,\n\n         14   particularly states and particularly governors.  Nobody\n\n         15   likes surprises.\n\n         16              So I think there's no substitute for\n\n         17   communication, no matter what the governance structure is. \n\n         18   But I also wonder if this is a moment where, like, yes, we\n\n         19   need to increase so much communications and so much more\n\n         20   leadership.  But there is something else in the governance\n\n         21   that has to change, and it sounds like maybe some version of\n\n         22   states' way of getting their version of proposals -- again,\n\n         23   they don't have to exercise it, but just the ability to have\n\n         24   jump ball with you, it sounds like is it's with you, not\n\n         25   with FERC, that's one area, and perhaps -- I also hear that\n\n\n\n\n\n                                                                      134\n\n\n\n          1   205 filing rights for PJM, if the stakeholders -- there's\n\n          2   got to be a, you know, timeline on the decisions on the\n\n          3   stakeholders.  It can't just be forever  stakeholdering.\n\n          4              And then PJM and its board have to make certain\n\n          5   decisions and make the filings.  I feel like that's the\n\n          6   urgency piece that's also missing.\n\n          7              CHAIRMAN SWETT:  So, I'm going to exercise my\n\n          8   chairman's rights now. We've got 15 minutes left, and I'm\n\n          9   going to channel the Senate.  I would like each of you, and\n\n         10   we're going to go down the line, in one or two sentences, if\n\n         11   there is one thing that you think is the most important\n\n         12   thing to fix PJM, I'd like to hear what that is.  With no\n\n         13   rebuttals and no extra window shades. \n\n         14              So, I'll start with you, Mr. Mills.\n\n         15              MR. MILLS:  Thank you, Madam Chair.  It's always\n\n         16   great to be first.\n\n         17              (Laughter.)\n\n         18              CHAIRMAN SWETT:  That's why they pay you the big\n\n         19   bucks, right?\n\n         20              (Laughter.)\n\n         21              MR. MILLS:  And this is one thing that we've only\n\n         22   tangentially talked about here today, but I think the most\n\n         23   binding constraint and largest risk is not getting new\n\n         24   generation online and into the auctions.  And they could be\n\n         25   hung up anywhere in the food chain, from permitting to\n\n\n\n\n\n                                                                      135\n\n\n\n          1   siting to financing to the actual interconnection.\n\n          2              And my datapoint is the last two auctions which,\n\n          3   yes, cleared short and, yes, cleared high at the cap.  They\n\n          4   showed an incredible lackluster amount of new generation.\n\n          5              So, you have to ask why.  What's driving that?\n\n          6              Now, to answer Commissioner Rosner's question, we\n\n          7   will very soon announce a backstop auction, with the details\n\n          8   that come around it.  We didn't want to distract from this\n\n          9   hearing.  So, in the next 72 hours, that will drop.\n\n         10              But, I think that while this governance and\n\n         11   stakeholder issue is completely -- and this has been a\n\n         12   wonderful discussion -- I don't think that those are to\n\n         13   blame for what's happening with the market right now.\n\n         14              CHAIRMAN SWETT:  You're going way over two\n\n         15   sentences and you're not answering my question about the\n\n         16   states' rights or board independence, that are the subject\n\n         17   of this panel.\n\n         18              MR. MILLS:  Okay.  Sorry.\n\n         19              CHAIRMAN SWETT:  So, if you have a magic wand,\n\n         20   what is the one thing that would fix those issues?\n\n         21              MR. MILLS:  I would create an augmented OPSI\n\n         22   organization that speaks for the, in totality of, the\n\n         23   states, and I would afford the PJM board 205 rights on the\n\n         24   operating agreement and transmission planning.\n\n         25              CHAIRMAN SWETT:  Perfect.  Thank you.  And I'm\n\n\n\n\n\n                                                                      136\n\n\n\n          1   not trying to be trite about the...\n\n          2              MR. MILLS:  No, I completely understand.  No\n\n          3   problem.\n\n          4              CHAIRMAN SWETT:  ...about the very great concern\n\n          5   that you raised, and...\n\n          6              MR. MILLS:  I'll read it to you later.\n\n          7              (Laughter.)\n\n          8              CHAIRMAN SWETT:  Great.  Chairman Wood?\n\n          9              CHAIRMAN WOOD:  I think we should make it really\n\n         10   clear, not just here but in all the RTOs, that the board\n\n         11   members have a responsibility to the public interest\n\n         12   consistent with the FPA, which draws in the just and\n\n         13   reasonable rate.\n\n         14              I think everything else follows from that,\n\n         15   because the public interest includes your co-sovereigns. \n\n         16   That's the states.  It includes an active and empowered\n\n         17   stakeholder group, which I think we've got a good basis for\n\n         18   that from 90 years in the PJM.\n\n         19              And I think public interest flows through with\n\n         20   the issues with transparency, and communication, and, you\n\n         21   know, clear leadership, that I think we've all pointed out\n\n         22   here today can be stepped up.  So, we're putting a lot on\n\n         23   your back, Mr. David, but I think you all can do it.\n\n         24              CHAIRMAN SWETT:  We're oh for two on two\n\n         25   sentences.\n\n\n\n\n\n                                                                      137\n\n\n\n          1              (Laughter.)\n\n          2              CHAIRMAN SWETT:  Chairman Bagot, I have faith in\n\n          3   you.\n\n          4              CHAIRMAN WOOD:  That was a lot of commas.\n\n          5              (Laughter.)\n\n          6              CHAIR BAGOT:  I'm going to --\n\n          7              CHAIRMAN SWETT:  That's fair; you are from Texas. \n\n          8   I stand corrected.\n\n          9              CHAIR BAGOT:  I'm going to echo Pat's comment,\n\n         10   but I'm going to add to that, that in addition to providing\n\n         11   them or clarifying that mandate, we actually have to make\n\n         12   sure that they have the authority to carry that mandate out. \n\n         13   And that means independence, and that means the ability to\n\n         14   make filings and brings positions before the Commission, to\n\n         15   the extent that they view that as the optimal or the\n\n         16   appropriate path forward.\n\n         17              CHAIRMAN SWETT:  Okay.  So that's two votes for\n\n         18   an independent board.  Deputy Secretary Finkel?\n\n         19              DEPUTY SECRETARY FINKEL:  Three votes for an\n\n         20   independent board, a real seat on the table for the states\n\n         21   with teeth and remembering that the reason that we need that\n\n         22   is because we need a function and a credible market, to\n\n         23   solve the governance, to solve these market problems before\n\n         24   it's too late.\n\n         25              CHAIRMAN SWETT:  Great.  Thank you.  I'm giving\n\n\n\n\n\n                                                                      138\n\n\n\n          1   up on two sentences, but pleased proceed.  (Laughs.)\n\n          2              MS. BURBURE:  What he said.\n\n          3              CHAIRMAN SWETT:  Oh!  You win!  Okay, thank you.\n\n          4              (Laughter.)\n\n          5              CHAIRMAN SWETT:  Marjie, this is going to be\n\n          6   tough for you.\n\n          7              MS. PHILIPS:  I'm trying.\n\n          8              (Laughter.)\n\n          9              MS. PHILIPS:  Board independence, better\n\n         10   structure around how PJM communicates with the governors and\n\n         11   states so they have a meaningful role, and I have to sneak\n\n         12   in for David, governance isn't about permitting; it's that\n\n         13   we can't get the generators.  It's that we can't -- we don't\n\n         14   have the load, signing onto the contracts.  All the\n\n         15   governance in the world isn't going to get us -- and we\n\n         16   want to focus on that -- we want to spend as little time on\n\n         17   governance as possible.  We want to spend our attention on\n\n         18   getting new generation and enhancing existing generation on\n\n         19   the system.\n\n         20              CHAIRMAN SWETT:  That was four, right?\n\n         21              MS. PHILIPS:  I don't think so.\n\n         22              (Laughter.)\n\n         23              CHAIRMAN SWETT:  But, well said.  Maria.\n\n         24              MS. GULLUNI:  205 rates to the board.  Actually,\n\n         25   let me say that, 205 rights to PJM, and the board should be\n\n\n\n\n\n                                                                      139\n\n\n\n          1   an oversight body.  Management should be running the company\n\n          2   on a day to day basis.  Management should be controlling\n\n          3   stakeholder process.  With the 205 rights, management should\n\n          4   be making the market and planning changes and prioritizing\n\n          5   their work.\n\n          6              CHAIRMAN SWETT:  Excellent.  Thank you.  So, do\n\n          7   any of my colleagues have any closing remarks, or can we\n\n          8   stop torturing these people 10 minutes early?\n\n          9              All right, thank you all very much.  That was\n\n         10   very engaging, illuminating.  I appreciate you coming before\n\n         11   us today.\n\n         12              And we will adjourn until 1:00 p.m. on the dot.\n\n         13              (Whereupon, the session adjourned for the lunch\n\n         14   break, at 11:50 a.m.)\n\n         15   \n\n         16   \n\n         17   \n\n         18   \n\n         19   \n\n         20   \n\n         21   \n\n         22   \n\n         23   \n\n         24   \n\n         25   \n\n\n\n\n\n                                                                      140\n\n\n\n          1                        AFTERNOON SESSION\n\n          2                             1:02 p.m.\n\n          3              MS. EYOCKO:  Good afternoon, everyone, and\n\n          4   welcome back.  My name is Stefanie Eyocko, and I'm from the\n\n          5   Office of Energy Market Regulation, here at the Commission.\n\n          6              We'll now begin with the first half of the second\n\n          7   panel, which will be a roundtable with energy\n\n          8   representatives, that will examine how PJM's stakeholder\n\n          9   process, including established sectors, committees, and\n\n         10   voting structures affects the RTO's ability to take\n\n         11   necessary and timely actions, including Section 205 filings,\n\n         12   to address the region's operational and market challenges.\n\n         13              Each panelist did submit an advanced statement\n\n         14   that includes their position on the questions and the\n\n         15   conference agenda.  To maximize the amount of time today, we\n\n         16   will be foregoing opening remarks and go directly to\n\n         17   questions from the Chairman and commissioners.\n\n         18              Panelists, to answer a question from the chairman\n\n         19   or the commissioner, please tip your name tent like so.\n\n         20              When you're called upon, please turn your\n\n         21   microphone on, with the gray button at the base of the\n\n         22   microphone in front of you.  You will know your mic is on\n\n         23   when the LED light is glowing green.\n\n         24              To maximize the time for discussion, please keep\n\n         25   your answers concise.\n\n\n\n\n\n                                                                      141\n\n\n\n          1              We do not intend to discuss, at this technical\n\n          2   conference, any specific proceedings before the Commission,\n\n          3   including proceedings that involve similar issues, whether\n\n          4   listed on the supplemental notice or not, and we ask that\n\n          5   panelists similarly refrain from such discussion.  If anyone\n\n          6   engages in these kinds of discussions, my colleagues from\n\n          7   the Office of General Counsel will interrupt the discussion\n\n          8   to ask the speaker to avoid that topic.\n\n          9              And now, to introduce group one of the second\n\n         10   panel, we first half Asim Haque, who is the Executive Vice\n\n         11   President of Governmental and Member Services at PJM.  \n\n         12              We have Suzanne Jaworowski, the Secretary of\n\n         13   Energy and Natural Resources at Indiana Governor Mike\n\n         14   Braun's Office.\n\n         15              We have Arnie Quinn, who is Senior Vice President\n\n         16   of Regulatory Policy at Vistra Corp.\n\n         17              We have Steve Lieberman, Vice President of\n\n         18   Transmission & Regulatory Affairs at American Municipal\n\n         19   Power.\n\n         20              And we have Kent Chandler, who is the\n\n         21   Non-Resident Fellow of Energy and Environmental Policy at R\n\n         22   Street Institute.\n\n         23              We have Pamela Quinlan, who is the Principal at\n\n         24   GQS New Energy Strategies.\n\n         25              And finally, we have Abe Silverman, who is an\n\n\n\n\n\n                                                                      142\n\n\n\n          1   Assistant Research Scholar at the Johns Hopkins University\n\n          2   Ralph O'Connor Sustainable Energy Institute.\n\n          3              Welcome panelists.\n\n          4              I will now turn it over to Chairman Swett for\n\n          5   questions.\n\n          6              CHAIRMAN SWETT:  Thank you.  Very well said. \n\n          7   Welcome, everyone.\n\n          8              Again, I will reiterate that you all have been\n\n          9   handpicked, based on your experience.  There are some big\n\n         10   thinkers on this panel.  And please be candid.  I expect\n\n         11   Pamela to throw some bombs, at the very least.\n\n         12              (Laughter.)\n\n         13              CHAIRMAN SWETT:  No, you're very shy, I know.\n\n         14              (Laughter.)\n\n         15              CHAIRMAN SWETT:  So, we'd like to focus this\n\n         16   panel, in particular, starting out on drilling down into the\n\n         17   stakeholder process, which everyone is pointing a lot of\n\n         18   fingers on, and I really want to reemphasize that we want\n\n         19   some very pointed suggestions, and problem identification. \n\n         20   So, Mr. Haque, I will start with you.\n\n         21              In the pre-conference comments that we got, many\n\n         22   stakeholders, including AMP, and we're going to turn to AMP\n\n         23   next, have expressed concern with the way that lower-level\n\n         24   voting is misaligned with voting at senior committees.\n\n         25              For example, they explain that the current\n\n\n\n\n\n                                                                      143\n\n\n\n          1   process impedes stakeholder decision-making because, at the\n\n          2   lower level committees the members have one vote, including\n\n          3   affiliates, but at the senior committees each corporate\n\n          4   entity only received one vote.  So, members with more\n\n          5   affiliates control the flow of proposals from the lower to\n\n          6   upper level committees. \n\n          7              So, with that as a table setting for the\n\n          8   question, can you please discuss why PJM's processes are\n\n          9   structured this way, and if there is broad support that\n\n         10   you're aware of, including in PJM itself, for changing that\n\n         11   structure, as there seems to be, at least from the outside,\n\n         12   and how can PJM implement those reforms?\n\n         13              MR. HAQUE:  Yeah.  Madam Chair, commissioners,\n\n         14   good afternoon.  Thank you for the invitation to be here,\n\n         15   and I realize we're going to spend some time talking about\n\n         16   the particulars of the stakeholder process, and specifically\n\n         17   the stakeholder process, we believe, has, you know,\n\n         18   functioned well for a particular period of time.  In this\n\n         19   particular period of time where we are focused on speed and\n\n         20   efficiency, I think the process has struggled.\n\n         21              Specifically with respect to the committee\n\n         22   structure, there are a number of stakeholder committees at\n\n         23   PJM.  There are two senior standing committees.  That is the\n\n         24   Markets and Reiability Committee and the Members\n\n         25   Committee.\n\n\n\n\n\n                                                                      144\n\n\n\n          1              Beneath that structure, there are four standing\n\n          2   committees.  Planning, Markets, Operations, and Risk.\n\n          3              And then, beneath that standing committee\n\n          4   structure are a series of subcommittees.\n\n          5              Now, you are correct, Chair; in the lower\n\n          6   committee structure, the voting differs than in the senior\n\n          7   standing committee structure.\n\n          8              Now, that conceivably could prevent proposals\n\n          9   from advancing from the lower committees all the way up to\n\n         10   the highest committees. \n\n         11              There is a check and balance there.  So, once a\n\n         12   lower committee vote, assuming that the lower committee\n\n         13   votes a proposal in the affirmative, gets up to the senior\n\n         14   standing committee and the voting structure changes, well\n\n         15   that voting structure change moves to this concept called\n\n         16   \"sector-weighted voting.\"  Okay?  \n\n         17              And that sector-weighted voting could act as a\n\n         18   check against the         lower committee proposal that\n\n         19   could have advanced.  Simultaneously, that proposal, which\n\n         20   would have, hopefully, advanced to the lower committee, may\n\n         21   not eventually get there, because of the voting structure in\n\n         22   the lower committees.\n\n         23              PJM's position, \"at the end of the day,\" is, you\n\n         24   know, these voting structure frameworks are codified in\n\n         25   Manual 34.  Manual 34 requires two-thirds sector-weighted\n\n\n\n\n\n                                                                      145\n\n\n\n          1   vote to amend.\n\n          2              Would we be willing to take a look at lower\n\n          3   committee voting structures?  Sure.  And make sure that they\n\n          4   align with the upper level committees?  Sure.  And\n\n          5   vice-versa.\n\n          6              I think what we're really trying to do is find\n\n          7   speed, and I think an interesting conversation to be had is,\n\n          8   frankly, whether we need all of these lower committees or\n\n          9   that we need so many committees that are leading up to PJM's\n\n         10   most senior committees.\n\n         11              CHAIRMAN SWETT:  Okay.  So you're teasing a\n\n         12   potential solution, which is cute.  But what do you think we\n\n         13   actually need to do?\n\n         14              (Laughter.)\n\n         15              CHAIRMAN SWETT:  Are you saying that we should\n\n         16   get rid of all of the lower committees or the voting\n\n         17   structure?\n\n         18              MR. HAQUE:  I think the standing committees and\n\n         19   the senior standing committees are essential to do business\n\n         20   operations.  I do question whether the lower committees are\n\n         21   necessary, underneath those standing committees, in order to\n\n         22   do business on behalf of the organization.\n\n         23              CHAIRMAN SWETT:  Okay.  And maybe this is not a\n\n         24   fair question, and if you don't know the answer then I\n\n         25   totally understand.  But why was the structure originally\n\n\n\n\n\n                                                                      146\n\n\n\n          1   conceived to have this type of imbalance?\n\n          2              MR. HAQUE:  Yeah.  I'm going to show my longevity\n\n          3   here at PJM, which is tipping over just about seven years. \n\n          4   You've got a panelist coming up, on panel three, who we like\n\n          5   to call the \"Elvis Presley\" of the stakeholder process,\n\n          6   named David Anders, who has been here from the very, very\n\n          7   beginning.\n\n          8              An answer that I'm going to give you, that I\n\n          9   don't know that you will love with respect to our\n\n         10   stakeholder process, is that that is just how it was done,\n\n         11   very early on in the process, and you're going to hear that\n\n         12   answer for quite a few of the particulars hat occur in the\n\n         13   stakeholder process.\n\n         14              CHAIRMAN SWETT:  So, will the stakeholder process\n\n         15   be more successful in producing efficient results if PJM\n\n         16   does get rid of the lower committees?\n\n         17              MR. HAQUE:  They will certainly be more timely. \n\n         18   And the reason why I say that is because when an issue is\n\n         19   advanced, in these lower committees, just think about it, if\n\n         20   you start here, at a lower committee, that lower committee\n\n         21   proposal then has to go to the next committee level, and the\n\n         22   next committee level, and the next committee level.\n\n         23              Again, the stakeholder process is great at\n\n         24   receiving feedback.  It's great at hearing from\n\n         25   stakeholders.\n\n\n\n\n\n                                                                      147\n\n\n\n          1              What it was not designed for was speed.  And so,\n\n          2   if we are going to enter this new era, if we're really going\n\n          3   to take big swings, I do think we need to think about that\n\n          4   over-arching committee framework and whether or not that\n\n          5   over-arching committee framework still makes sense.\n\n          6              CHAIRMAN SWETT:  Okay, thank you.  Yes, sir.\n\n          7              MR. LIEBERMAN:  Good afternoon.  Steve Lieberman,\n\n          8   American Municipal Power.  Thank you for having this\n\n          9   conference.\n\n         10              I do want to, perhaps, disagree slightly with the\n\n         11   comments that Mr. Haque just made.\n\n         12              So, the reason we have these lower level\n\n         13   committees is so that we could focus our attention on a\n\n         14   specific issue.  So, Asim talked about we have these\n\n         15   standing committees, like the Planning Committee, and Market\n\n         16   Committee, and what not.\n\n         17              In the first panel we heard from David Mills.  He\n\n         18   talked about the Reserve Certainty Senior Task Force.  So,\n\n         19   that is a -- and he said it's a very technical discussion,\n\n         20   and on and on.\n\n         21              So, that is an example where, intentionally, we\n\n         22   have decided to have a technical discussion on a very minute\n\n         23   subject, and that's all we talk about.  We don't talk about\n\n         24   anything else, at that senior task force, in that instance.\n\n         25              So, in my opinion, I would not support a magic\n\n\n\n\n\n                                                                      148\n\n\n\n          1   wand waving away of all these lower level committees.  I\n\n          2   think they have a purpose, in order to kind of focus subject\n\n          3   matter experts on a specific issue, and not detract from a\n\n          4   senior committee that's going to talk about more broad\n\n          5   topics or multiple topics.\n\n          6              CHAIRMAN SWETT:  So, how can they move more\n\n          7   quickly, if we keep them?\n\n          8              MR. LIEBERMAN:  Yeah, and I'd like to also talk\n\n          9   about that same task force that David Mills mentioned.\n\n         10              He said well, you know, this committee, the\n\n         11   senior task force, it started its initial meeting like three\n\n         12   years ago, and we hope to get something to FERC by October\n\n         13   this year, and it met 42 times.\n\n         14              So, taking advantage of AI, I found out that\n\n         15   there's 36 months between, basically, October, 2023, and\n\n         16   October, 2026, and if we met 42 times that's about 1.27\n\n         17   times per month.\n\n         18              So, if we want to advance the ball quicker, we've\n\n         19   got to meet more frequently than 1.27 times per month.\n\n         20              PJM is in complete control of the cadence in\n\n         21   which it schedules stakeholder meetings.  So, if we're\n\n         22   talking about -- and you mentioned this at the annual\n\n         23   meeting -- about moving quicker, well, PJM's got a schedule\n\n         24   that was meeting stakeholders, states, OPSI.  We have no\n\n         25   say, no input, over when PJM schedules meetings on any\n\n\n\n\n\n                                                                      149\n\n\n\n          1   topic.\n\n          2              In fact, Manual 34, that Asim just mentioned,\n\n          3   specifically says that PJM assigns the role of the secretary\n\n          4   of the Members Committee, which is Dave Ander, and that\n\n          5   person is fully in charge of setting the meetings.\n\n          6              So, when we want to get stuff done quicker, we've\n\n          7   got to meet more frequently than 1.27 times per month.\n\n          8              CHAIRMAN SWETT:  So, you're telling me that the\n\n          9   stakeholder process is slow because you don't have more\n\n         10   meetings?\n\n         11              (Laughter.)\n\n         12              MR. LIEBERMAN:  I'm saying if there is an issue\n\n         13   that's of paramount importance to PJM, then meeting more\n\n         14   frequently than once a month is probably the way to get\n\n         15   things done.\n\n         16              CHAIRMAN SWETT:  Okay.\n\n         17              COMMISSIONER LACERTE:  Steve, let me challenge\n\n         18   you on that.  Wouldn't these subsidiary meetings just happen\n\n         19   in an informal basis without there being a formal process\n\n         20   within a PJM manual?  Wouldn't these people just get\n\n         21   together in the nature of, like, the endless nature of --\n\n         22   couldn't this meeting have been a conference call?  Could\n\n         23   this conference call have been an email?\n\n         24              MR. LIEBERMAN:  Uh-huh.\n\n         25              COMMISSIONER LACERTE:  Like, couldn't we move\n\n\n\n\n\n                                                                      150\n\n\n\n          1   faster in that direction without it being a fixture of the\n\n          2   manual?\n\n          3              MR. LIEBERMAN:  It's possible.  You know, and I\n\n          4   would say that, you know, certainly there are a lot of\n\n          5   meetings that we have that could be done more efficiently\n\n          6   and done remotely.\n\n          7              And, in fact, after -- when PJM reopened after\n\n          8   the lockdown, we have conducted a lot of our meetings in a\n\n          9   remote manner.  So, we don't necessarily have to travel to\n\n         10   Valley Forge and meet.  We do a lot of them through -- yeah.\n\n         11              COMMISSIONER LACERTE:  So, could these frontline\n\n         12   discussions happen in an informal basis, outside the\n\n         13   requirement in the manual?\n\n         14   \n\n         15              MR. LIEBERMAN:  Yeah.  And I think to a degree\n\n         16   they do.  I think that's part of what stakeholders do, is\n\n         17   they contact each other outside of, let's say, \"PJM hours,\"\n\n         18   and talk about issues and figure out where their positions\n\n         19   are.\n\n         20              Yes, sir.\n\n         21              CHAIRMAN SWETT:  Pamela.\n\n         22              MS. QUINLAN:  Thank you so much for convening\n\n         23   this conference.  I think working even on the pre-filed\n\n         24   statement gave time in our schedules to really think through\n\n         25   these really hard questions that we need to understand\n\n\n\n\n\n                                                                      151\n\n\n\n          1   what's the purpose of these stakeholder processes, what is the\n\n          2   benefit to get there?  And, if we can't do things quickly\n\n          3   when they need to happen quickly, then we're obviously not\n\n          4   serving the region.\n\n          5              But there is a distinction between things that\n\n          6   need to be responded to so fast, and things that are really\n\n          7   worth taking time to really get into some of the details. \n\n          8   And I think the more I thought about it, the more I think\n\n          9   there's a distinction as to what you use the stakeholder\n\n         10   process for, and what you actually really don't need to\n\n         11   necessarily use it for.\n\n         12              And I think coming up with direction and\n\n         13   leadership of where we want to go is really helpful to get\n\n         14   from PJM leadership and the board.  And the details of how\n\n         15   you get that done and what that means, there's really no\n\n         16   replacement for the breadth of the PJM stakeholders and\n\n         17   their expertise across the board.\n\n         18              And I think, if you erase those lower committee\n\n         19   meetings -- I mean, whether it's in a committee or at\n\n         20   special sessions of the MIC, I mean, I've been around the\n\n         21   PJM stakeholder process long enough to see, like, many\n\n         22   iterations of subcommittees, task force, workshops, like...\n\n         23              But the point is you want to make sure that there\n\n         24   is a transparent way that parties who are going to be impacted,\n\n         25   have the ability to understand where this is going, and\n\n\n\n\n\n                                                                      152\n\n\n\n          1   explain how it uniquely impacts them.\n\n          2              That doesn't mean you need to meet a certain\n\n          3   amount of times, or however many times you said for that\n\n          4   meetings.\n\n          5              And I think, back to the earlier panel, where\n\n          6   they talked about priorities.  I think getting feedback on -\n\n          7   - you see this in other regions and other RTOs where, like,\n\n          8   this is a schedule -- and we start off with that in PJM\n\n          9   often.  Like, here is the plan of how many meetings we're\n\n         10   going to have, and we're going to have an objective for\n\n         11   that.  \n\n         12              We're not usually held to it.  Oftentimes it\n\n         13   continues to move on, beyond that.  But also a narrowing of\n\n         14   \"Here's the specific areas that we're looking for\n\n         15   stakeholder feedback,\" and it's not necessarily open-ended\n\n         16   to anything anyone wants to talk about.\n\n         17              And I don't know that there's a limitation and a\n\n         18   manual that says you can't do that, but that's generally not\n\n         19   been the culture.\n\n         20              So I think, when we have these discussions, I\n\n         21   think there is a distinction between -- we shouldn't throw\n\n         22   the baby out with the bathwater.  Like, the idea of having\n\n         23   technical expert people from across the industry provide\n\n         24   details on how this will work in practice cannot be\n\n         25   replicated.\n\n\n\n\n\n                                                                      153\n\n\n\n          1              Because if you remove it, we're going to have\n\n          2   unintended consequences and those can be very severe.\n\n          3              COMMISSIONER SEE:  I hear you, on trying to get\n\n          4   this line right, between deliberation and speed can be\n\n          5   different for different issues.  Can you or others maybe go\n\n          6   into more detail of what that might look like?  Because I'm\n\n          7   also concerned about creating dual tracks and more process\n\n          8   and adding more complexity to -- that's what we're talking\n\n          9   about here, is a process that's so complex we can't get\n\n         10   things done at the speed that we need.\n\n         11              So, can you give some more detail of what it\n\n         12   might look like to be able to have different processes\n\n         13   without adding to the complexity?\n\n         14              MS. QUINLAN:  I think part of that gets down to\n\n         15   prioritization and understanding what the urgency is for\n\n         16   something.  And every different stakeholder is going to have\n\n         17   a different view.  Like, if this is the way your company\n\n         18   makes money, then that's the biggest issue to you.\n\n         19              But I think going back to, like, the PJM board\n\n         20   and leadership, trying to figure out public interest and\n\n         21   trying to figure out public interest and understanding,\n\n         22   like, that's what's important to PJM as a whole and what's\n\n         23   going to be the critical path for its success.\n\n         24              Right now we have the resource adequacy issue. \n\n         25   That can't be bogged down in details of everyone negotiating\n\n\n\n\n\n                                                                      154\n\n\n\n          1   every single component to it.\n\n          2              And I think that gets down to priorities upfront\n\n          3   and you can decide and, you know -- and I know we're not\n\n          4   talking about state involvement on this panel, so I don't\n\n          5   want to get too much into it, but I think in areas where it\n\n          6   involves the states, the states should work with PJM and\n\n          7   identify which ones are the priorities that cannot go\n\n          8   through such an exhaustive stakeholder process.\n\n          9              But you can just put time bounds on it.  And\n\n         10   then, if you think you need to have infinite meetings -- I\n\n         11   think part of the challenges folks have had to date, in all\n\n         12   of the years that I've heard, now is that, for people\n\n         13   complaining about the stakeholder process, it was that\n\n         14   there's too many meetings and you can't follow all of this,\n\n         15   and I don't have enough resources to staff out every single\n\n         16   task force.\n\n         17              So, creating more of those is difficult.  There's\n\n         18   no simple answer to this.  If there was, we wouldn't have to\n\n         19   talk about it.\n\n         20              But I think coming up with \"These are the\n\n         21   critical things that we are going to move forward, no matter\n\n         22   what, and this is the date certain that we're going to move\n\n         23   forward,\" we want to take input from the stakeholders, and\n\n         24   the areas where the board or PJM leadership specifically\n\n         25   needs feedback can hone in and narrow those conversations,\n\n\n\n\n\n                                                                      155\n\n\n\n          1   then you actually can have less of those meetings.\n\n          2              And if people don't think those are the right\n\n          3   things to bring, then they can come at FERC and fight that.\n\n          4              And then, for areas where it's really, like, we\n\n          5   have a timeline, we're going to have some software changes,\n\n          6   it's going to take time to get there, whatever reason, you\n\n          7   have more details for that, then I think you can have a more\n\n          8   full, kind of, stakeholder process and try to get the tier\n\n          9   one consensus, because there's not this, like, firm deadline\n\n         10   on it.\n\n         11              But, having an infinite number of issues, with\n\n         12   never-ending creations of new task forces, puts folks that\n\n         13   are less well capitalized being able to not be able to\n\n         14   participate in that, they don't have the resources for it,\n\n         15   and you're not getting, like, the full suite of stakeholder\n\n         16   inputs, which was the intention in the first place.\n\n         17              So, prioritization becomes key, I think, and then\n\n         18   I think you can put things on actual timelines.\n\n         19              CHAIRMAN SWETT:  Arnie?\n\n         20              MR. QUINN:  Yeah, I want to thank you for the\n\n         21   opportunity to be here.  I completely agree with I think\n\n         22   where Steve and Pamela were going, that the deliberative\n\n         23   part of this is not the part that we want to lose.  That's\n\n         24   particularly important.\n\n         25              The issue is, though, PJM works on more issues, I\n\n\n\n\n\n                                                                      156\n\n\n\n          1   think, than any other ISO, certainly that we're in.  So, we\n\n          2   participate in, essentially, every ISO in the country,\n\n          3   including ERCOT, except for SPP.  I think we work on more\n\n          4   issues, in PJM, than any other ISO does in the country, and\n\n          5   so I think the challenge is, you know, how do you make all\n\n          6   of this go faster, how are we able to do these processes\n\n          7   with more speed.\n\n          8              You know, to Steve's point, how do you meet more\n\n          9   often if that's what it takes to get something done more\n\n         10   quickly?  Part of it is we've got to decide, on the front\n\n         11   end if there are some of the things that we deal with today\n\n         12   that we don't need to be dealing with right now, that there\n\n         13   are lower priority items, and there are almost certainly\n\n         14   examples that, you know, we could come up with, where you\n\n         15   identify somethings that we talked about for three years\n\n         16   that was a small, incremental, improvement, but if we had\n\n         17   sat down at the beginning of the year and said \"Where does\n\n         18   this stack up with all of our priorities?\" it would have\n\n         19   gone on the low priority part of the list, and we wouldn't\n\n         20   have dealt with it, and we would have had more time for\n\n         21   other things.\n\n         22              So I think that is crucially important, if we're\n\n         23   going to solve this.\n\n         24              Going back to the voting, I will note that there\n\n         25   is something that is difficult about the voting structure. \n\n\n\n\n\n                                                                      157\n\n\n\n          1   We happen to have an advantage.  We're a large company with\n\n          2   a lot of affiliates.  So we, on paper, have an advantage on\n\n          3   those lower committees, where we have more ability to shape\n\n          4   what goes to the higher companies.\n\n          5              For our company, we would conform the voting\n\n          6   structures.  We would take away what appears to be an\n\n          7   advantage, because in truth we're not just a good company\n\n          8   and a good corporate citizen; I actually think we don't get\n\n          9   that much of an advantage.\n\n         10              Because we can shape something that goes to the\n\n         11   higher committees, and then at the higher committees they\n\n         12   fail.  So, whatever we gained earlier on, we've probably\n\n         13   lost by the time we get to that higher committee, and now\n\n         14   we've spent more time.\n\n         15              So, in my mind, conforming the voting,\n\n         16   thinking this is one company speaking, there would be some\n\n         17   value to that, and that would potentially have an ability to\n\n         18   compress some of the process.  Not losing that important\n\n         19   deliberative element, but have people vote at the same\n\n         20   nature so that you have some confidence that, as it's being\n\n         21   developed, it can actually move forward.\n\n         22              CHAIRMAN SWETT:  \"Conforming the voting,\" what\n\n         23   does that mean?\n\n         24              MR. QUINN:  There would be sector-weighted voting\n\n         25   all along the way.  So, as it's going from lower committees,\n\n\n\n\n\n                                                                      158\n\n\n\n          1   if we continue to have lower committees to higher\n\n          2   committees, we are not asking to say \"Let's keep the\n\n          3   affiliate voting.\"  We would say do sector-weighted voting\n\n          4   that we do at the upper levels, do that earlier in the\n\n          5   process, if that's something that we continue to do.\n\n          6              CHAIRMAN SWETT:  That's very charitable of Vistra\n\n          7   to offer.\n\n          8              MR. QUINN:  I will say yes, it is.\n\n          9              (Laughter.)\n\n         10              MR. QUINN:  And, I also -- and I don't think we\n\n         11   get that much of an advantage, because in reality we get a\n\n         12   temporary win to have a later on loss.\n\n         13              CHAIRMAN SWETT:  Abe?\n\n         14              MR. SILVERMAN:  Great.  Thank you all very much\n\n         15   for the invite to be here.\n\n         16              So, I want to come back to this prioritization\n\n         17   piece, and I want to make sure we're focusing on the right\n\n         18   thing.  I actually don't think it's the lower level\n\n         19   committees that are bogging us down.  It's when we ask\n\n         20   committees to decide policy.\n\n         21              And again, I think the data center issue and the\n\n         22   large load integration is a perfect example of this.  We\n\n         23   would have saved so many hours of meetings for, I think,\n\n         24   most of the people up here, had we had input at the very\n\n         25   beginning from the states, and from the board, directing PJM\n\n\n\n\n\n                                                                      159\n\n\n\n          1   staff what to do, and then we could have had stakeholder\n\n          2   meetings on how to implement it.\n\n          3              And I think that's the key thing.  Right?  It's\n\n          4   not about the lower level committees.  Christine Cidione,\n\n          5   you know, five years ago, wrote her wonderful paper, and she\n\n          6   made the point that the stakeholder process in PJM works\n\n          7   fine for non-controversial issues.  And \"the wheels come\n\n          8   off\" as soon as it gets hard.\n\n          9              And so, if we had that prioritization element,\n\n         10   where the states were coming in, PJM was sitting with them\n\n         11   at the table, to come up with the priority how to deal with\n\n         12   some of these issues of first impression, the whole thing\n\n         13   would have just gone so much faster and smoother and,\n\n         14   frankly, resulted in something that was politically durable,\n\n         15   that investors could actually respond to.\n\n         16              CHAIRMAN SWETT:  So, who should set the agenda?\n\n         17              MR. SILVERMAN:  I think on different items,\n\n         18   especially things dealing with resource adequacy and issues\n\n         19   of first impressions, or where we need a cooperative\n\n         20   federalist approach.\n\n         21              I mean, I think everybody in this room would\n\n         22   agree that the only way to deal with large loads is to have\n\n         23   state and federal regulators and PJM sitting at the same\n\n         24   table, dividing up the universe and saying \"This is your\n\n         25   responsibility.  This is our responsibility, but let's do it\n\n\n\n\n\n                                                                      160\n\n\n\n          1   together and hold hands while we do it.\"\n\n          2              Had PJM sat down and really had that type of\n\n          3   partnership with the states, we would have had fewer\n\n          4   meetings and better outcomes.  \n\n          5              And so I think, on these issues, it really is PJM\n\n          6   potentially sitting down with states, perhaps without a lot\n\n          7   of other stakeholders at the table, and deciding how we want\n\n          8   to address these things for where there is this inherent\n\n          9   federal-state nexus.\n\n         10              I mean, I mentioned in my comments you could have\n\n         11   a FPA Section 209 joint board which, frankly, is probably\n\n         12   what we need here, where you have state and federal\n\n         13   regulations that need to be synced up.\n\n         14              You know, you probably don't actually have to go\n\n         15   to the -- actually having that formal process, but that, if\n\n         16   PJM were to internalize that approach, where states are\n\n         17   partners and they were going to sit down and solve problems\n\n         18   together at the very beginning, we would set an agenda that\n\n         19   was durable.\n\n         20              You know, we talked about restaurants before, but\n\n         21   to me this is about when the parents are fighting we can't\n\n         22   have a happy investment climate.  And here the parents are\n\n         23   fighting.  They're not on the same page.  So, if we bring\n\n         24   states and PJM together at the very beginning of the\n\n         25   process, instead of the very end of the process, you know,\n\n\n\n\n\n                                                                      161\n\n\n\n          1   the children would be much better off.\n\n          2              CHAIRMAN SWETT:  So, PJM and the states should\n\n          3   set the agenda for the entire stakeholder process.\n\n          4              MR. SILVERMAN:  I think on select issues.  To me\n\n          5   there's a clear state nexus with resource adequacy, and\n\n          6   there's a clear state nexus when you have issues of first\n\n          7   impression such as, you know, unprecedented data center load\n\n          8   growth.\n\n          9              CHAIRMAN SWETT:  Uh-huh.\n\n         10              MR. SILVERMAN:  There's not a right or wrong\n\n         11   answer.  Right?  It really is an inherent policy choice, and\n\n         12   I think this gets to where having the governors in there, as\n\n         13   well as the legislators, and OPSI, because they all have\n\n         14   three very different approaches to these kinds of issues. \n\n         15   So, I think bringing everyone to that table early on will\n\n         16   just make the whole process more efficient and more\n\n         17   durable.\n\n         18              CHAIRMAN SWETT:  What's your reaction to that,\n\n         19   Asim?\n\n         20              MR. HAQUE:  Chair, there's a lot of different\n\n         21   threads in the very initial question that you asked.  On the\n\n         22   concept of prioritization, PJM has tried to prioritize\n\n         23   efforts in the stakeholder process, in the past.  It has not\n\n         24   been terribly successful.\n\n         25              And my panelist colleagues here, fellow\n\n\n\n\n\n                                                                      162\n\n\n\n          1   colleagues, they're right in that we haven't tried to\n\n          2   enforce the priorities that we set out at the beginning of\n\n          3   the year, received feedback on, et cetera.\n\n          4              I think because it's getting such a spotlight\n\n          5   here, today, my hope is that if we try to enter into another\n\n          6   prioritization effort with the stakeholders, that it will be\n\n          7   better adhered to.  \n\n          8              But, it does lend itself to, kind of, a few\n\n          9   thoughts that I think we've got to sort of get clear with\n\n         10   the stakeholders, which is if these are the priorities and\n\n         11   you want, and inject -- you want to inject something into\n\n         12   the stakeholder process to get worked via this problem\n\n         13   statement issue charge framework, you know, please note that\n\n         14   it will not get worked, you know, this year.  Even though\n\n         15   it's your priority, it's not going to get worked within\n\n         16   this particular frame of time where we have set our\n\n         17   priorities for the organization.\n\n         18              We should undoubtedly get feedback from the\n\n         19   members and the states, when we are setting that priority\n\n         20   list.  But that, once we have set those priorities, assuming\n\n         21   that there is not a, you know, burning issue that has\n\n         22   occurred within the region that we have to tackle, you know,\n\n         23   that prioritization needs to be adhered to, and there\n\n         24   shouldn't be an expectation that PJM and the stakeholder\n\n         25   process team are just going to bend over backwards to take a\n\n\n\n\n\n                                                                      163\n\n\n\n          1   problem statement issue charge that was not already on the\n\n          2   prioritization list and work it and have it worked within\n\n          3   the stakeholder process.  That expectation should not be\n\n          4   there if we are going to truly, collectively -- and I mean\n\n          5   it -- I mean \"collectively,\" everybody prioritize the work.\n\n          6              The only other thing I wanted to say on this\n\n          7   issue is it does tie into the 205 rights issue.  Okay? \n\n          8   Because we can prioritize the work, and for whatever reason\n\n          9   we could be at a standstill in how to proceed, and\n\n         10   eventually someone's going to have to make that call, of\n\n         11   what to file.\n\n         12              And so, if PJM did have 205 rights over energy\n\n         13   ancillary services, planning protocol, et cetera, it would\n\n         14   make that situation sort of at least -- I'm not going to way\n\n         15   easier, but at least a little more clear on delineating the\n\n         16   sort of linking authority and accountability.\n\n         17              CHAIRMAN SWETT:  Well, you said PJM has not\n\n         18   enforced its priorities.  Why?\n\n         19              MR. HAQUE:  Generally speaking, our perspective,\n\n         20   as a stakeholder team, has been that it's the members\n\n         21   process.  They oversee Manual 34.  That is basically the\n\n         22   bylaws for the stakeholder process.\n\n         23              Now, everything that we do in the stakeholder\n\n         24   process is so incredibly meaningful to the day to day and to\n\n         25   the long term viability of the organization, and so you\n\n\n\n\n\n                                                                      164\n\n\n\n          1   might feel like there is a disconnect there.  Maybe there is\n\n          2   a disconnect there.\n\n          3              Am I confident that if, after this prioritization\n\n          4   topic has received such spotlight here at the Commission, am\n\n          5   I confident that PJM, it's management stakeholder affairs\n\n          6   team could sit down with the members in the states and come\n\n          7   up with, in 2027, \"Here are our...\"\n\n          8              Because our -- listen.  Our priority, in Pam\n\n          9   Quinlan's comments, you know, excellent, very solidly done -\n\n         10   - our priority is, right now, resource adequacy.  Right?  I\n\n         11   mean, if we don't have an eye towards -- if we don' have an\n\n         12   eye towards getting more infrastructure built, and getting\n\n         13   more supply on the system -- our priority, clearly, is\n\n         14   resource adequacy.\n\n         15              We've got our paper out there.  We need to drive\n\n         16   home a solution for what the next iteration of this\n\n         17   marketplace is going to be.  But sans that, let's say we get\n\n         18   together and we say, a few months' process, 2027, here --\n\n         19   you know, here are our priorities, look, we could figure out\n\n         20   a way to try and give, you know, us more, greater,\n\n         21   legislated or codified authority in that space, I think we\n\n         22   can work it out with our members and our states, if we do\n\n         23   set those priorities.\n\n         24              Maybe it's something that we file with you all,\n\n         25   preview with you all, so that you have a sort of -- you have\n\n\n\n\n\n                                                                      165\n\n\n\n          1   a glimpse, or there is light on what our gameplan is next\n\n          2   year, so if we don't adhere to it, you know, on the\n\n          3   collective side, you could sort of say \"Hey, all of you, PJM\n\n          4   member states, why didn't this happen?\"\n\n          5              COMMISSIONER LACERTE:  What's stopping you from\n\n          6   doing that now?\n\n          7              MR. HAQUE:  I don't think anything is stopping us\n\n          8   from doing it now, and I think we should do it now.  So,\n\n          9   commissioner, it's a very fair question.\n\n         10              I will say, we have, like I said, we have tried\n\n         11   these prioritization efforts in the past and they have\n\n         12   generally failed.  But I do think that, again, you all\n\n         13   putting a light on it will hopefully bring everybody through\n\n         14   to getting this done.\n\n         15              COMMISSIONER LACERTE:  But if you're a well\n\n         16   capitalized stakeholder with a bunch of affiliates, not\n\n         17   naming any names --\n\n         18              (Laughter.)\n\n         19              COMMISSIONER LACERTE: -- and if PJM says your\n\n         20   priorities are not on this year's schedule, what's stopping\n\n         21   them from saying \"We vote no on everything until you come to\n\n         22   the table?\"\n\n         23              MR. HAQUE:  Nothing.  But we know Arnie would not\n\n         24   behave like that.\n\n         25              (Laughter.)\n\n\n\n\n\n                                                                      166\n\n\n\n          1              COMMISSIONER LACERTE:  He's come to the table and\n\n          2   I'll give him a large degree of deference on that.\n\n          3              But -- so what you're saying, again here, is that\n\n          4   the issue is one of the two-thirds vote.\n\n          5              MR. HAQUE:  The issue -- I don't think that this\n\n          6   particular issue is one of the two-thirds vote.  The issue\n\n          7   is that, you know, the actual prioritization -- actually\n\n          8   just a quick aside -- there is actually, in Manual 34, our\n\n          9   stakeholder process bylaws, there actually is a requirement\n\n         10   that we come up with an annual workplan.  It's actually\n\n         11   member driven.\n\n         12              Now, we haven't seen that process play out\n\n         13   recently.  It's not something that we have done recently.\n\n         14              COMMISSIONER LACERTE:  I was just going to say\n\n         15   those work plans are not very good, if they're not...\n\n         16              MR. HAQUE:  Yeah, that's right.  So, I think this\n\n         17   prioritization effort is a worthwhile effort to try and\n\n         18   undertake -- I am trying to -- I am trying to be sort of\n\n         19   gracious with our members who, like we said -- that feedback\n\n         20   is really important to everything that we do day to day, and\n\n         21   I'm trying to be gracious with the states to say...\n\n         22              COMMISSIONER CHANG:  Can I interrupt you?\n\n         23              MR. HAQUE:  Please.\n\n         24              COMMISSIONER CHANG:  Sorry.  Can I just try to\n\n         25   understand this?  Are you saying that today PJM cannot work\n\n\n\n\n\n                                                                      167\n\n\n\n          1   with its members or stakeholders to come up with a short\n\n          2   term, and a long term, priority list and a work plan?  Is\n\n          3   that what you're saying?\n\n          4              MR. HAQUE:  No, I'm not saying that.\n\n          5              COMMISSIONER CHANG:  Okay.\n\n          6              MR. HAQUE:  I think we can.  I think we just need\n\n          7   to adhere to it as a collective.\n\n          8              COMMISSIONER CHANG:  \"Collective\" meaning you\n\n          9   take a leadership role, you work with your market\n\n         10   participants, your stakeholders --\n\n         11              MR. HAQUE:  Correct.\n\n         12              COMMISSIONER CHANG:  -- and states inputs --\n\n         13              MR. HAQUE:  Correct.\n\n         14              COMMISSIONER CHANG:  And you prioritize and say\n\n         15   \"Okay, everybody, this is good.  2027 priority list.\"  And\n\n         16   three year priority, one year priority, like we're going to\n\n         17   work on these things.\n\n         18              MR. HAQUE:  Yeah.\n\n         19              COMMISSIONER CHANG:  Like, you can do that today,\n\n         20   with no changes to whatever bylaw agreement, et cetera.\n\n         21              MR. HAQUE:  We can do that today.\n\n         22              COMMISSIONER CHANG:  Okay.\n\n         23              MR. HAQUE:  And what I would say is we have tried\n\n         24   to do that in the past, but we have not collectively adhered\n\n         25   to it.\n\n\n\n\n\n                                                                      168\n\n\n\n          1              And one of the things that I did reference is\n\n          2   when a member says \"We want to work this issue in the\n\n          3   stakeholder process,\" we say \"Yes, we are going to work this\n\n          4   issue in the stakeholder process.\"  That moves something\n\n          5   else off of the priority list.\n\n          6              And so on and so forth.  So, I do think that\n\n          7   there -- like I said, these are sort of soft authorities. \n\n          8   There is no sort of true codification of this anywhere.  But\n\n          9   I do think that the collective -- again, now that you all\n\n         10   have shown a big bright light on it, can work together to\n\n         11   try and create what a right prioritization framework should\n\n         12   be, going forward.\n\n         13              COMMISSIONER SEE:  Is that too optimistic, this\n\n         14   idea that, you know, now that we've shown a spotlight, we\n\n         15   can do this?\n\n         16              MR. HAQUE:  Optimism by heart...\n\n         17              COMMISSIONER SEE:  I guess the question is do we\n\n         18   need a formalized process for this sort of direction\n\n         19   setting?\n\n         20              MR. HAQUE:  My honest answer is I don't know.  I\n\n         21   think that, on one hand, the organization has really strong,\n\n         22   solid, members that participate in the stakeholder process.\n\n         23              We have all admitted, on multiple occasions\n\n         24   today, that sometimes those interests get entrenched.  And\n\n         25   there's nothing wrong with that, as was also said.  Everyone\n\n\n\n\n\n                                                                      169\n\n\n\n          1   is going to be pushing within their self-interest.\n\n          2              But I do -- so, I do think that, that sort of\n\n          3   lingers over this particular issue.  And so, I think I am\n\n          4   interested, after the -- like I said, after the kind of\n\n          5   light that you all have shown on this issue, if we can get\n\n          6   it done, if the Commission was to say \"We want to have PJM\n\n          7   and the stakeholders prioritize work, have it be submitted\n\n          8   to us as part of a suite of reforms that come through to\n\n          9   PJM,\" then sure.  I think the codification of that would be\n\n         10   good too.\n\n         11              COMMISSIONER CHANG:  You know, I would say I sort\n\n         12   of push back when the Chairman says PJM's too big to\n\n         13   function, whatever the words are.  But I feel like, in this\n\n         14   conversation...\n\n         15              CHAIRMAN SWETT:  I didn't say that.\n\n         16              COMMISSIONER CHANG:  Okay.  But this conversation\n\n         17   makes me agree with the Chairman.\n\n         18              (Laughter.)\n\n         19              COMMISSIONER CHANG:  Like, are you too big to\n\n         20   make decisions and prioritize work plans?\n\n         21              MR. HAQUE:  No.\n\n         22              COMMISSIONER CHANG:  Okay.\n\n         23              MR. HAQUE:  Yeah, my response is firmly no.  We\n\n         24   all just need to adhere to it.  And we'll see my colleagues\n\n         25   have multiple times up too. \n\n\n\n\n\n                                                                      170\n\n\n\n          1              (Laughter.)\n\n          2              MR. HAQUE:  I'm not trying to push back.  I am\n\n          3   curious about their opinions on this as well.  I am curious\n\n          4   about their opinions on this.\n\n          5              COMMISSIONER ROSNER:  Let's hear from --\n\n          6              COMMISSIONER LACERTE:  Let's go down the line. \n\n          7   Okay.\n\n          8              COMMISSIONER ROSNER:  Let's go down the line,\n\n          9   okay.  Secretary?\n\n         10              MS. JAWOROWSKI:  Thank you very much.  Good\n\n         11   afternoon.  Thank you, Chairman Swett and the Commission for\n\n         12   having me here today.\n\n         13              Before I became Secretary of Energy and Natural\n\n         14   Resources of the State of Indiana, I was Executive Director\n\n         15   for Stakeholder Services at MISO, and so I see this from\n\n         16   another perspective, and I do recognize and respect how\n\n         17   complex the stakeholder process is, how extremely important\n\n         18   those voices are.\n\n         19              But I think a major issue that should be\n\n         20   addressed is the fact that Asim said it is the stakeholders'\n\n         21   process.  It is their process.  They are running this show.\n\n         22              And my other colleague said, you know, when it\n\n         23   comes to policy, this is where we need the states' input. \n\n         24   And so, there are a few recommendations that I might make\n\n         25   from that observation, respectfully, and that is that I\n\n\n\n\n\n                                                                      171\n\n\n\n          1   really believe that the stakeholders' voices should be\n\n          2   advisory in this.\n\n          3              To ask a group of individuals that have different\n\n          4   motivations to come together to create policy and 90-day\n\n          5   plans, hundred-day plans, that are going to be\n\n          6   comprehensive, is a really challenging task to do.\n\n          7              The observation I made at my time at MISO was\n\n          8   often the technical staff would create a recommendation and\n\n          9   the stakeholders can weigh in from different committee\n\n         10   perspectives.\n\n         11              And so, I think that the recommendations that I'm\n\n         12   heading towards are advisory roles for the stakeholders, for\n\n         13   PJM itself, as an entity, to have more leadership and\n\n         14   authority over the process, so that they can make\n\n         15   recommendations and be more swift.\n\n         16              Because right now we are in an unprecedented\n\n         17   time.  I think Secretary Danly said it very well. \n\n         18   Everything is changed.  And what I see, from a front row\n\n         19   seat, in a state like Indiana, is speed to electrons.  Speed\n\n         20   to electrons.  And that is sometimes replacing former\n\n         21   plants.  That is building new capacity.  That is our deep\n\n         22   pocketed partners who need large load supply.\n\n         23              And so, anything we can do to be speeding up this\n\n         24   process will benefit the PJM footprint.\n\n         25              And then finally, asking respectfully for a stake\n\n\n\n\n\n                                                                      172\n\n\n\n          1   for the governor's offices -- our offices have a broader\n\n          2   view on policy, economic development issues, and I agree\n\n          3   with the comments from my colleagues about having that\n\n          4   worked in as part of the process.  Not asking to be involved\n\n          5   in every decision, by any means.  We don't have the\n\n          6   bandwidth or interest, I don't believe, for that.\n\n          7              But I do think in January we came together with\n\n          8   the 13 states on the statement of principles, and all\n\n          9   solidly agreed on those resource adequacy perspective\n\n         10   issues.  So I think, in summary, advisory roles for the\n\n         11   stakeholders, a more leadership role for the board, and PJM\n\n         12   as an organization, and a voice and a vote, as was said\n\n         13   earlier, for the state leadership.\n\n         14              Thank you.\n\n         15              COMMISSIONER ROSNER:  Thank you.  Arnie, would\n\n         16   you like to respond to Asim?  And, as you do that, I'd love\n\n         17   to get -- as a PJM member, I'd love to get  your opinion on\n\n         18   a couple of the things we just talked about.  Should PJM\n\n         19   management be empowered to prioritize the issues that the\n\n         20   stakeholder process considers over the course of the year?\n\n         21              I'm also curious on your reaction on this concept\n\n         22   of should the PJM board be more empowered to make decisions\n\n         23   independently, either on some of these issues that are in\n\n         24   the operating agreement, completely in an unconstrained way\n\n         25   or the other idea we heard was if stakeholders fail to\n\n\n\n\n\n                                                                      173\n\n\n\n          1   agree.\n\n          2              And the other question I just want to throw in is\n\n          3   should there be a time limit on some of the stakeholder\n\n          4   process deliberations, and should that be, you know, binding\n\n          5   in some way?\n\n          6              I just would recognize, you know, we just were\n\n          7   visiting with Congress yesterday, and Congress talks to us a\n\n          8   lot about permitting timelines and shot clocks, and you\n\n          9   know, one of the things that Congress is often surprised\n\n         10   about is, on the Federal Power Act, we have a 60-day clock,\n\n         11   and I think our staff and our commission does a really great\n\n         12   job with most of those.  Except for the very few that come\n\n         13   back through the courts.\n\n         14              But what you do is you staff to meet the need. \n\n         15   And so sometimes a deadline is helpful, so I've love your\n\n         16   opinion on all those things.\n\n         17              MR. QUINN:  All right.  Thank you.\n\n         18              So, on the prioritization, I'll start with just\n\n         19   saying we do it in almost every other ISO that we're in, and\n\n         20   so I have a lot of confidence that it can work, as it works\n\n         21   everywhere else we are.  And I think that is not directly\n\n         22   related to who has filing rights or not, but I will get to\n\n         23   that element of it.\n\n         24              Asim is right, though, that stakeholders are\n\n         25   going to have to be disciplined.  And in our other ISOs we\n\n\n\n\n\n                                                                      174\n\n\n\n          1   have to be disciplined, to recognize that once the work plan\n\n          2   is set, yes, we are going to come to the ISO occasionally to\n\n          3   say this is a really emergent issue and I think that you\n\n          4   should prioritize it.\n\n          5              And they should be open to that conversation, but\n\n          6   we should all be disciplined in recognizing that the answer\n\n          7   is mostly going to be no, because that's the point of\n\n          8   prioritization, that if is a Vistra only issue, then that's\n\n          9   something for me to bring up in the next annual plan.  If\n\n         10   it's a Vistra and all of the other stakeholders issue, then\n\n         11   maybe we should talk about that.\n\n         12              But, and in PJM, we do have this issue charge\n\n         13   problem statement that anyone can issue.  We're going to\n\n         14   have to either become disciplined about that or reform that,\n\n         15   because the prioritization has to be the place we do it.\n\n         16              Commissioner See, you asked about whether it has\n\n         17   to be a formal process.  I think the benefit of it being a\n\n         18   formal process is that that creates another avenue for the\n\n         19   states to have input, and so having a formal process that is\n\n         20   run so that the states have a very known place to go, along\n\n         21   with other stakeholders, to say \"Hey, we have to -- please,\n\n         22   these are our priorities for the next year.  Could you put\n\n         23   those on the list, and could you please prioritize them?\"\n\n         24              At the end of the day, it does need to be the ISO\n\n         25   that finalizes that plan and says \"This is what we're\n\n\n\n\n\n                                                                      175\n\n\n\n          1   adhering to.\"\n\n          2              COMMISSIONER ROSNER:  So, would that require a\n\n          3   change in this Manual 34?  It sounds like it would.  But\n\n          4   we'll go back and read it.\n\n          5              MR. QUINN:  Perhaps.  Perhaps.\n\n          6              COMMISSIONER ROSNER:  I had it open a minute ago\n\n          7   here.  It's kind of long.\n\n          8              MR. QUINN:  Yes.  Yes, that's what you'll find.\n\n          9              (Laughter.)\n\n         10              MR. QUINN:  On voting, or on 205 rights, what\n\n         11   I'll say is I've heard a lot of positive things about\n\n         12   stakeholder advisory -- and I will say, as a participant in\n\n         13   all the other markets, in MISO and in California, where it\n\n         14   is purely advisory, I will note that you want your ISO to be\n\n         15   both independent and responsive.\n\n         16              And, as we're working on the hard stuff, it's\n\n         17   always about a set of tradeoffs.  It's never a clear action;\n\n         18   it's always about a set of tradeoffs.\n\n         19              Vistra has a set of tradeoffs, the things that\n\n         20   are the most important.  My other stakeholders here would\n\n         21   say there's another set of tradeoffs, and the ISO has to,\n\n         22   kind of, develop the final set of tradeoffs that they're\n\n         23   managing.\n\n         24              In the markets where it is purely advisory, our\n\n         25   experience is the ISO is not as responsive to our set of\n\n\n\n\n\n                                                                      176\n\n\n\n          1   tradeoffs, and the reality in this is mildly controversial. \n\n          2   Our experience in those markets where it's purely advisory,\n\n          3   the transmission owners do get a little bit additional\n\n          4   benefit, a little bit additional say, because they are kind\n\n          5   of the core of that ISO.  If they leave, the ISO doesn't\n\n          6   exist.\n\n          7              So, I would -- I think we would be supportive of,\n\n          8   for instance in the energy market, a time clock to get\n\n          9   something done, and if we don't get done, then PJM has 205\n\n         10   rights.\n\n         11              The other idea that we talked about in our\n\n         12   comments was the New England stakeholder -- or New England\n\n         13   jump ball.  Again, I don't think most of our problems are\n\n         14   about filing rights, and I think filing rights are going to\n\n         15   be controversial and are going to take a lot of time.\n\n         16              COMMISSIONER ROSNER:  Yeah.\n\n         17              MR. QUINN:  We do like the jump ball process\n\n         18   because it disciplines the process.  It makes the ISO more\n\n         19   responsive because they know the stakeholders.  If it's not\n\n         20   just a Vistra issue, if it's a 60 percent of us issue, we\n\n         21   are going to come up with an alternative so that gives the\n\n         22   ISO more incentive to listen.\n\n         23              And I will note that in ISO New England the\n\n         24   states have a very central role in that process.  If you\n\n         25   want to get a 60 percent vote, the best place to do that is\n\n\n\n\n\n                                                                      177\n\n\n\n          1   to go talk to NESCO and see if they agree with you and you\n\n          2   can collectively find a coalition, and that's just a very\n\n          3   positive dynamic.\n\n          4              COMMISSIONER ROSNER:  Thank you.\n\n          5              COMMISSIONER LACERTE:  A following up question. \n\n          6   So, your concern is over responsiveness within the RTO, and\n\n          7   those concerns, you're saying, would be alleviated by a jump\n\n          8   ball process?\n\n          9              MR. QUINN:  I think they are.  I think they're --\n\n         10    again, I think all of the -- to start with, all of the\n\n         11   ISOs, the staff are all excellent, they're all public\n\n         12   service minded, they're all completely well intentioned.  It\n\n         13   is simply a power structure.\n\n         14              COMMISSIONER LACERTE:  Yeah.\n\n         15              MR. QUINN:  It is the question.  And, for us,\n\n         16   having the jump ball there balances the power.  So that the\n\n         17   responsiveness is improved.\n\n         18              COMMISSIONER LACERTE:  And I understand your\n\n         19   point on the responsiveness and the level of participation\n\n         20   and them, you know, heeding your call.  But respectfully,\n\n         21   the other ISOs aren't running a massive capacity deficit,\n\n         22   and we're more and more worried about that, these days.\n\n         23              MR. QUINN:  I am not sure that's true.\n\n         24              COMMISSIONER LACERTE:  Well, not to this level. \n\n         25   Perhaps a smaller level.\n\n\n\n\n\n                                                                      178\n\n\n\n          1              MR. QUINN:  I don't know.  I think California --\n\n          2   I mean, they're all my best friends.\n\n          3              (Laughter.)\n\n          4              COMMISSIONER LACERTE:  We're not going to solve\n\n          5   California's problems today, but noted.  I want to make sure\n\n          6   we have time.\n\n          7              MR. QUINN:  All right.\n\n          8              COMMISSIONER ROSNER:  And, Arnie, you know, I\n\n          9   appreciate the view there.  You know, again, I don't have a\n\n         10   preferred outcome on time clock, jump ball.  I mean, I think\n\n         11   the thing that I'm hearing is that, with the two-thirds\n\n         12   majority required, 34 percent of the folks in the\n\n         13   stakeholder group can stop a process from happening.\n\n         14              And the thing that I think I would like to see\n\n         15   unfold here is more compromise happen in the stakeholder\n\n         16   process before it has to go to the board.  And so that's, I\n\n         17   think, a really important goal, and I think the question\n\n         18   that I'm searching for especially member input on is \"What\n\n         19   are ways that we can turn the dial, to get more of a real,\n\n         20   you know, need to agree, and an opportunity for excellence\n\n         21   in the stakeholder process so we don't have to go to the\n\n         22   board.\"\n\n         23              But I also do think that having the independent\n\n         24   board and having those tools is important, but I -- and\n\n         25   you've just laid out some of them, but I just wanted to say\n\n\n\n\n\n                                                                      179\n\n\n\n          1   that in response to your comment.\n\n          2              MR. QUINN:  No, I appreciate that.  And I should have\n\n          3   also noted that at the end of the day we're not here because\n\n          4   the energy market in PJM isn't working well.  We're here\n\n          5   because the capacity market is challenged.  And that is a\n\n          6   part of the tariff for which PJM has 205 rights today.\n\n          7              So, in that sense, stakeholders are already\n\n          8   advisory, in that sense.  And, for me, that is...\n\n          9              COMMISSIONER ROSNER:  But Arnie, you know, I just\n\n         10   see those two things as inextricably related, and so we are\n\n         11   asking PJM to make changes to one without being able to have\n\n         12   the autonomy to do the other.  And so I just -- I hear you\n\n         13   but also there's a constraint here.\n\n         14              MR. QUINN:  I think that's fair.  I do think that\n\n         15   if I try to identify why the PJM capacity market is\n\n         16   challenged, it does come back to a lot of the nuts and bolts\n\n         17   stuff that we're talking about, where we haven't prioritized\n\n         18   it because we've been working on so many other things --\n\n         19              COMMISSIONER ROSNER:  Yes.\n\n         20              MR. QUINN:  -- that we've been distracted from\n\n         21   the thing that's right in front of us.\n\n         22              COMMISSIONER ROSNER:  All right.  Well, we could\n\n         23   keep going down the line, or other commissioners, please.\n\n         24              CHAIRMAN SWETT:  Let's continue down the line.\n\n         25              COMMISSIONER ROSNER:  Yeah.  The folks that are\n\n\n\n\n\n                                                                      180\n\n\n\n          1   waiting, yeah.\n\n          2              MR. LIEBERMAN:  Thank you.  So, a few things. \n\n          3   Well, yeah, a few things.\n\n          4              So, one of them is, you know, the board can\n\n          5   prioritize issues today.  In fact, they do that.  PJM talked\n\n          6   a little bit about that in the first panel, with the connect\n\n          7   and manage and the backstop process.  That was a board\n\n          8   initiated thing.  They said \"Hey, we're going to do this and\n\n          9   we're going to do it now.  And it's going to wrap up by this\n\n         10   date.\"  And that date was June 30th.\n\n         11              So, the board was in a position to prioritize an\n\n         12   issue, outline the schedule, schedule the meetings, which\n\n         13   ultimately led to a vote, and now we're waiting, as PJM\n\n         14   announced I guess, 72 hours they'll file something.  So,\n\n         15   that's an example.\n\n         16              But another thing to note, and I'm sorry I don't\n\n         17   remember where it is, if it's in the manual or which\n\n         18   governing document, but these senior task forces and the\n\n         19   like, they actually do have a lifespan, and it's a two year\n\n         20   thing.  So, after two years you have to go back and say\n\n         21   \"Hey, you know, 'Mother, may I have another?'\"\n\n         22              But what is supposed to happen is after two years\n\n         23   it ceases to continue working.  And that may not be enforced\n\n         24   today but that doesn't negate the fact that that rule\n\n         25   exists.\n\n\n\n\n\n                                                                      181\n\n\n\n          1              And I just wanted to also remind -- I mean, we\n\n          2   talked, you know, about getting the governors more involved. \n\n          3   The governors did announce, and I'm looking for my notes, a\n\n          4   PJM governor collaborative.  They announced this in\n\n          5   September of last year.  It was signed by, I think 11 of the\n\n          6   13 PJM state governors.\n\n          7              So, the governors have gotten together, and they\n\n          8   explained how they're going to get more involved and, you\n\n          9   know, I think that's a great thing.  I'm not sure that we\n\n         10   have to do more.  I mean, they've already said that they are\n\n         11   going to do something.\n\n         12              But an example, also, of where it can be\n\n         13   difficult, you know, where we come out with a work plan and\n\n         14   we say \"Okay, that's the work plan for the year,\" is, you\n\n         15   know, if the White House does -- you know, like today,\n\n         16   they're going to announce the rate payer protection pledge. \n\n         17   I don't know if it's 2.0 or just people, more people, are\n\n         18   signing onto it.  I was a little confused.\n\n         19              But depending on what comes of that, you know, we\n\n         20   may have a fresh crop of work that we need to reprioritize\n\n         21   our existing work.  So, we've got it.  We should have a work\n\n         22   plan.  But it shouldn't necessarily be set in stone.  We\n\n         23   have to recognize that Arnie might have an issue, and it is\n\n         24   really pressing, and maybe we do need to talk about it\n\n         25   sooner than later.  Thank you.\n\n\n\n\n\n                                                                      182\n\n\n\n          1              CHAIRMAN SWETT:  Kent?\n\n          2              MR. CHANDLER:  Yeah, I'll speak quickly on this\n\n          3   in hopes of maybe getting asked another question later.\n\n          4              (Laughter.)\n\n          5              MR. CHANDLER:  So, I do think -- Arnie alluded to\n\n          6   it -- but I do want to put a finer point.  I don't think\n\n          7   they're -- sort of channeling Thomas Sowell, like there are\n\n          8   no solutions; there are only tradeoffs.  This idea that\n\n          9   we're going to get an answer to this or an answer to that;\n\n         10   it's just going to be a matter of tradeoffs.\n\n         11              So we're going to give up things as we move or\n\n         12   transition or do things differently.  But this idea that a\n\n         13   lot of this prioritization can't just be done by the board\n\n         14   is not something that I adhere to or believe.  There is\n\n         15   nothing keeping the board from meeting with OPSI right now,\n\n         16   for instance, and sitting down and talking about the next\n\n         17   one in three years of joint goals or prioritization.\n\n         18              And then, there's nothing in Manual 34 that keeps\n\n         19   PJM from identifying how they want to use their internal\n\n         20   resources towards prioritization.\n\n         21              One thing I've learned from CPCNs and shot clocks\n\n         22   and being a recovering state regulator is that just because\n\n         23   you have a statutory deadline that's not when the work\n\n         24   starts.  It's when it starts for the regulators.  But\n\n         25   usually the applicant has done a lot of work ahead of\n\n\n\n\n\n                                                                      183\n\n\n\n          1   starting the process or filing an application.  Right?\n\n          2              So, there's nothing to say that if there's a shot\n\n          3   clock or a timeline on a stakeholder process that that's\n\n          4   when PJM has to start working on it, for the -- a straw\n\n          5   proposal or to start running numbers on certain items. \n\n          6   Like, they could be doing a lot of this work behind the\n\n          7   scenes, prior to initiating a proposal or bringing it to\n\n          8   stakeholders, and then the time-limited part could be the\n\n          9   engagement with, sort of, the outside world.\n\n         10              CHAIRMAN SWETT:  So, what do you think the\n\n         11   biggest problem is, and what's the solution?\n\n         12              MR. CHANDLER:  The biggest?  (Laughs.)  How much\n\n         13   time do we have?\n\n         14              CHAIRMAN SWETT:  Two minutes.\n\n         15              (Laughter.)\n\n         16              MR. CHANDLER:  Yes.  So, what is the biggest\n\n         17   problem, and the solution on the stakeholder process front? \n\n         18   I think it's -- I do think it goes back to who has the power\n\n         19   to act. \n\n         20              I mean, you know, I put this in my comments, but\n\n         21   I think to a certain extent some of the solution lies here. \n\n         22   Some of the solution lies within stakeholders, of just\n\n         23   mutually agreeing to do things differently.  Frankly, a lot\n\n         24   of it, I think, is things the board can do unilaterally.\n\n         25              I think, for one, folks need to be prepared to be\n\n\n\n\n\n                                                                      184\n\n\n\n          1   occasionally told no.  I see a lot of the issues that stem\n\n          2   from this is actually a lot of, just like, folks upset\n\n          3   because they don't necessarily win on a particular issue and\n\n          4   the easiest way to effectuate change from that is to throw\n\n          5   up your hands and say \"Oh, I lost.  That must mean\n\n          6   everything is wrong.\"\n\n          7              I think that setting things up like a\n\n          8   prioritization, I think that a big solution is telling\n\n          9   people what the consequences of not following through on the\n\n         10   prioritization is, so that everybody knows the rules to\n\n         11   start the game.  PJM has not done a great of that.\n\n         12              I remember, a long time ago, like seven years\n\n         13   ago, PJM, the board told everybody \"If you don't fix the\n\n         14   energy market we're going to, this is what our filing is\n\n         15   going to look like.\"\n\n         16              The members couldn't come to agreement.  PJM\n\n         17   showed up at FERC with a proposal that did not look -- that\n\n         18   did not adhere to what they told stakeholders it would look\n\n         19   like if they didn't come to agreement.\n\n         20              So I think a lot of it is just having\n\n         21   transparency and conveying expectations early, and then\n\n         22   holding each other accountable to the outcomes.\n\n         23              CHAIRMAN SWETT:  So, PJM should threaten the\n\n         24   stakeholders more with concrete filings?\n\n         25              (Laughter.)\n\n\n\n\n\n                                                                      185\n\n\n\n          1              MR. CHANDLER:  I think that there should be clear\n\n          2   expectations going into -- I mean, \"threat\" is probably a\n\n          3   strong term but, you know, \"eye of the beholder.\"  I think\n\n          4   there should be expectations and folks, I don't know, the\n\n          5   chips fall as they may.  You say \"This is what we're going\n\n          6   to do.\"\n\n          7              And I think the same thing for FERC, right?  It's\n\n          8   like we're not going to hear sore -- the commissioners\n\n          9   saying \"We're not going to hear from sore losers.  Just\n\n         10   because it didn't work out your way, we're not necessarily\n\n         11   going to be a sympathetic ear.\"\n\n         12              I also think this idea that you can't\n\n         13   reprioritize prioritization, based off of, like, ad hoc\n\n         14   needs or emergency is, I don't know, I just don't believe in\n\n         15   that. \n\n         16              I think that if the vast majority of stakeholders\n\n         17   agree, they should be able to, like, redo the\n\n         18   prioritization.  Or, if folks agree that it's a pressing\n\n         19   issue and it's not going to be prioritized, show up here\n\n         20   with a 206.  I mean, that makes you all's job a little bit\n\n         21   harder but, you know, heavy is the head...\n\n         22              CHAIRMAN SWETT:  We can do it.  Pamela?\n\n         23              MS. QUINLAN:  So, I agree with a lot of what\n\n         24   everyone's saying, and I think there's a lot of agreement on\n\n         25   this panel about some of the challenges here, on\n\n\n\n\n\n                                                                      186\n\n\n\n          1   prioritization.\n\n          2              And to exactly what you're saying, yes, I think\n\n          3   it's not just prioritizing; it's prioritizing with action\n\n          4   coming.  Right now, if you are benefiting with the existing\n\n          5   rules, you have a really strong incentive to delay the\n\n          6   entire process, because the existing rules work for you.\n\n          7              And no one wants to compromise off of what\n\n          8   they're going to litigate, if they think that they can win\n\n          9   at the end.  So, if you know that there is going to be a\n\n         10   filing coming, and you say -- and this isn't getting into\n\n         11   whether or not there needs to be expanded 205 rights, because I tend to\n\n         12   think we're not using the legal authority that they have\n\n         13   today.  Today they can say \"I'm going to make a 205 filing\n\n         14   under -- for resource adequacy issues,\" or \"We'd like to see\n\n         15   a 205 filing made with stakeholder support, but this is a\n\n         16   big enough issue, and we will bring it to FERC with a 206. \n\n         17   Here is the timeline in which we are setting to evaluate\n\n         18   this, and if you can't compromise, we're going to do what\n\n         19   PJM thinks is best and file that with the Commission.\"\n\n         20              And during that time period they have told FERC\n\n         21   \"This is what we're doing.  Here is the update for it,\" so\n\n         22   nothing's a surprise to anybody.  And that doesn't require a\n\n         23   single change.  That's just leadership and how we're\n\n         24   executing.  And that will drive compromise, because people\n\n         25   will compromise if they think that they're going to lose\n\n\n\n\n\n                                                                      187\n\n\n\n          1   something if they don't.\n\n          2              But there's going to be some things that people\n\n          3   will never agree upon, and that can't be the -- it's like\n\n          4   consensus can't be the prerequisite for leadership.  You\n\n          5   have to lead, even when people do not come to agreement,\n\n          6   because that is undoubtedly true, and it's particularly true\n\n          7   when it comes to issues of resource adequacy.\n\n          8              Going back to Secretary Danly, you asked the\n\n          9   question of who has the responsibility.  I spent some time\n\n         10   in my comments talking about this because I think until we\n\n         11   fix that specific issue, related to resource adequacy, the\n\n         12   stakeholder process will not be freed up to actually work on\n\n         13   the largest value proposition that PJM brings to these 13\n\n         14   states, which for my view is the IT SCED, that's the\n\n         15   security constraint security dispatch and long term\n\n         16   planning, and if we keep fighting over resource adequacy\n\n         17   decisions that the stakeholders did not make and cannot\n\n         18   change, if states can sign up new loads without a plan to\n\n         19   serve it or force early retirement with a plan to replace\n\n         20   it, and we are trying to figure out how to change a market\n\n         21   to undo that, we can't do that, as a stakeholder body.\n\n         22              So, that needs to be fixed.  There's probably\n\n         23   multiple ways to do that.  And I think, to Commissioner\n\n         24   LaCerte, your point about PJM being -- comparing to other\n\n         25   markets -- that, to me, is where PJM is really different. \n\n\n\n\n\n                                                                      188\n\n\n\n          1   It's the only region that relies upon a centralized capacity\n\n          2   market to solve resource adequate, where there's load growth.\n\n          3              And that's never really been tested before, and\n\n          4   we can talk -- like, when we put the RPM together in the\n\n          5   first place, when we started this, and I started my career\n\n          6   and we were talking about the RPM and it was coming to be\n\n          7   new in PJM, and have seen it through many different phases,\n\n          8   the realities that underpin the assumptions of why that\n\n          9   would work are just not true anymore.  And that has to do\n\n         10   with, like, a lot of things that are outside of\n\n         11   stakeholders' control, for sure, outside of FERC's control\n\n         12   as well, and we have to think about how we actually can fix\n\n         13   the largest challenge we have right now, which is \"Why don't\n\n         14   we have enough infrastructure?\"  And there is no governance\n\n         15   rule change that I think we can do to change that.\n\n         16              But I do think we need to act more quickly, and I\n\n         17   think the best way to get people to compromise on things\n\n         18   that are achievable is to actually threaten them with action\n\n         19   if they don't.\n\n         20              So, thanks.\n\n         21              COMMISSIONER LACERTE:  I think in our comments to\n\n         22   the technical conference here, I expect to hear all of the\n\n         23   multiple ways in which we can fix it.  Submitted within 30\n\n         24   days by you.  So, I appreciate that.\n\n         25              CHAIRMAN SWETT:  Abe?\n\n\n\n\n\n                                                                      189\n\n\n\n          1              MR. SILVERMAN:  Yeah, I'm actually going to\n\n          2   largely dovetail with that.  You know, the one thing you\n\n          3   will not find in Manual 34 is a sense of urgency.  And I\n\n          4   don't know where that urgency comes from, other than\n\n          5   leadership.\n\n          6              Interconnection.  It took us how many years to\n\n          7   get that done?  Large load growth.  Billions of dollars were\n\n          8   getting transferred for every day of delay and yet we're a\n\n          9   year into a process with no, really, end in sight.\n\n         10              These are fundamental problems.  And I think that\n\n         11   leadership needs to come from PJM and it needs to come from\n\n         12   this commission.  And I think we need to act to empower\n\n         13   PJM's staff, because it's a wonderful staff, but I often\n\n         14   feel bad criticizing PJM because they're wonderful,\n\n         15   dedicated people.\n\n         16              I think the things that we can do, largely talked\n\n         17   about in the earlier panel, independence for the board, so\n\n         18   that they're not afraid to make tough decisions, more\n\n         19   transparency, and then, again, coming back and getting the\n\n         20   governors, OPSI, and the legislators bought in.  Because, if\n\n         21   we get all the principals, all the sovereign stakeholders,\n\n         22   aligned, on a direction, then PJM can just move a lot\n\n         23   faster.\n\n         24              But, you know, that's just -- that sense of\n\n         25   urgency, it's just -- you're not going to find it in Manual\n\n\n\n\n\n                                                                      190\n\n\n\n          1   34, and we can't be in the situation where issues like\n\n          2   interconnection fester for years.  The fact that we're not\n\n          3   holding auctions on time.  So, thinking about \"How do we\n\n          4   align the board structure so they can act?\"  And I do think\n\n          5   that is 205 filing rights for states at the end of the day,\n\n          6   so there is some enforcement mechanism.  But it's also\n\n          7   giving PJM more authority, and insulating that board from,\n\n          8   you know, stakeholder concerns, when they don't like the way\n\n          9   the answer is going.\n\n         10              But sometimes it is more important to make a\n\n         11   decision than that the decision be the platonically correct\n\n         12   or best outcome.\n\n         13              COMMISSIONER SEE:  And I think that's important,\n\n         14   because this has been a really helpful conversation about\n\n         15   what we can do now and what we can do through a formal\n\n         16   process to set priorities.  I think that's been really\n\n         17   great.\n\n         18              But that's one part of it.  Right?  Because where\n\n         19   we started this panel is \"How do we work those priorities,\n\n         20   and dealing with complexity and time?\"\n\n         21              It seems like one of the things that's been on\n\n         22   the table from a number of you is let's have deadlines that\n\n         23   have teeth.  So I guess I've got two questions.  The first\n\n         24   is \"Is that something that PJM can do now, or does that\n\n         25   require changes?  Can there be enforceable deadlines on this\n\n\n\n\n\n                                                                      191\n\n\n\n          1   action?\"  And then, what else would be on that list?\n\n          2              Now, we started with, you know, reevaluating the\n\n          3   committee structure.  Do we need to do that as well?  Is\n\n          4   this just really a time and a deadline issue?\n\n          5              So, I'm not sure who to address that one to, so\n\n          6   whoever wants to jump in.\n\n          7              MR. SILVERMAN:  I'll just start.  I mean, part of\n\n          8   the problem when we talked on Manual 34 was this idea that\n\n          9   it's a member organization.\n\n         10              COMMISSIONER SEE:  Uh-huh.\n\n         11              MR. SILVERMAN:  And again, you know, PJM needs to\n\n         12   step up and set that agenda.  It would be much faster.  And\n\n         13   then do it with real input from the states.\n\n         14              CHAIRMAN SWETT:  Uh-huh.\n\n         15              COMMISSIONER LACERTE:  I really like Kent,\n\n         16   Pamela, and Abe's answers to the tail end of going down the\n\n         17   line there, and I think you make a good point.  I think Kent\n\n         18   said that PJM doesn't utilize the authorities it has as\n\n         19   much.  And Kent and Pamela both said that they need to\n\n         20   engage more with the states, and they don't.\n\n         21              And I think the reason why that doesn't happen\n\n         22   now is a culture issue in PJM, and the cultural issue, I\n\n         23   don't see us getting around this without breaking the chains\n\n         24   of making the stakeholder process advisory.  \n\n         25              I think that I've never had, in my entire life,\n\n\n\n\n\n                                                                      192\n\n\n\n          1   sometime tell me they were afraid of fired, before, until\n\n          2   the PJM board.  And I've worked in the White House!\n\n          3              (Laughter.)\n\n          4              COMMISSIONER LACERTE:  So, it's just I don't know\n\n          5   how to get around it without making breaking the system up,\n\n          6   to where the board is empowered to get a backbone.  And I\n\n          7   think -- you know, I appreciate the Chairman's comments, and\n\n          8   Judy's comments about PJM being too big to function,\n\n          9   perhaps.  But to me it's just question of nerve, and\n\n         10   backbone, and strength, and this is a cultural quagmire that\n\n         11   they've developed by eroding the board in the past and\n\n         12   creating this fear of being terminated, to where they're not\n\n         13   using their authorities, they're not engaging with the\n\n         14   states, because they don't want to get out of line with what\n\n         15   the stakeholders want.\n\n         16              And that is a fundamental problem of culture in\n\n         17   PJM, and I don't see a way around it by keeping the status\n\n         18   quo.\n\n         19              MR. HAQUE:  Commissioner, I just wanted to\n\n         20   comment on -- look, I think we are certainly in a different\n\n         21   moment today than we have been in our history.  For sure. \n\n         22   What we are seeing, the external forces that we're seeing,\n\n         23   are incredibly dynamic, and I don't think we can do business\n\n         24   as usual.\n\n         25              So, I am with you on that.  We've talked about\n\n\n\n\n\n                                                                      193\n\n\n\n          1   board independence.  We've talked about the lengthening of\n\n          2   board terms.  We've talked about 205 rights.\n\n          3              On the engagement with the states, I think it's a\n\n          4   good topic to explore.  We do a lot of engagement with our\n\n          5   states.  A lot.\n\n          6              Of course, that world has evolved quite a bit. \n\n          7   It used to just be we would interact with OPSI.  Now it's\n\n          8   governors' offices, energy offices, legislators, and all of\n\n          9   which  bring, sort of their own unique spin to, you know,\n\n         10   what their particular perspective is.\n\n         11              Look, I think that we're -- and getting back to\n\n         12   the stakeholder process, we, for a long time, have tried to\n\n         13   -- if the stakeholder process is the venue where stuff gets\n\n         14   done, we have tried to encourage OPSI in particular's\n\n         15   engagement in the stakeholder process.  Okay?\n\n         16              I think, after a few years on this job, I will\n\n         17   tell you, it really does feel like trying to fit a square\n\n         18   peg into a round hole.  For a variety of reasons.  Namely,\n\n         19   like we've talked about, the sheer volume of meetings, it's\n\n         20   hard, I think!\n\n         21              I'm a former state regulator myself.  It's hard,\n\n         22   when you have a day job, to go sit in a jillion stakeholder\n\n         23   meetings and monitor them, and participate in them.  It's\n\n         24   not an easy task.\n\n         25              And so, what we have started to do with our\n\n\n\n\n\n                                                                      194\n\n\n\n          1   states, and the real proof will be in the pudding on this\n\n          2   market reform issue, is we've basically started to do\n\n          3   parallel tracks with them.  Not just keeping them informed\n\n          4   about what's going on in the stakeholder process.\n\n          5              But, to Judge Bagot's point this morning, for\n\n          6   instance Order 1920, we said \"We're going to work this issue\n\n          7   with you,\" because this is so central to -- this long term\n\n          8   planning framework is so central to the states, and you all\n\n          9   put them in sort of a driver's seat there as well.\n\n         10              So, we worked a separate track with them, were\n\n         11   able to get them to get them to a point where they felt\n\n         12   really good about the framework that we are advancing\n\n         13   together.  We're going to do the same on the market reform. \n\n         14   That is the biggest, sort of, thing.\n\n         15              Look, on the PJM front, I appreciate all the\n\n         16   praise that's been given to PJM's staff.  They're certainly,\n\n         17   sort of, the kind of -- everything in the PJM sphere that\n\n         18   has gone from, you know, whether it's criticism or whatever\n\n         19   it is, that has gone from boutique to mainstream.  Okay?\n\n         20              I don't see it in Valley Forge.  I really don't. \n\n         21   I see a lot of dedicated staff who are running day ahead and\n\n         22   real time markets, planning the system, processing queue\n\n         23   requests, operating the power grid in the control room when\n\n         24   we were at an all-time peak a few weeks back.  Okay?\n\n         25              And I think we made a lot of progress.  Queue\n\n\n\n\n\n                                                                      195\n\n\n\n          1   backlog cleared, we're advancing long term planning, refined\n\n          2   load forecasting, connect and manage and the backstop are\n\n          3   going to be submitted to you.  David said 72 hours.  I want\n\n          4   to clarify that's 72 business hours.\n\n          5              (Laughter.)\n\n          6              MR. HAQUE:  And then -- and then -- the thing we\n\n          7   need to focus on, the big thing, the big ticket thing -- and\n\n          8   again, I'm going to praise Pam Quinlan and her comments; I\n\n          9   thought they were excellent -- is how are we going to get\n\n         10   infrastructure built, ultimately?\n\n         11              COMMISSIONER CHANG:  Can I interrupt?\n\n         12              MR. HAQUE:  Please.\n\n         13              COMMISSIONER CHANG:  And you brought up a segue\n\n         14   here, because we have seven minutes.\n\n         15              MR. HAQUE:  I'm so sorry.\n\n         16              COMMISSIONER CHANG: And I want to -- sorry, I\n\n         17   know there are many cards -- but it's getting really crystal clear,\n\n         18   to me, like, what needs to happen.  I'm not going\n\n         19   to articulate it right now, but I do want to ask you a\n\n         20   question.\n\n         21              MR. HAQUE:  Please.\n\n         22              COMMISSIONER CHANG:  Which is, back to the --\n\n         23   you know, there's the culture issue, there is sort of\n\n         24   setting priorities, et cetera.\n\n         25              But I want to get back to the filing rights\n\n\n\n\n\n                                                                      196\n\n\n\n          1   because that's something specific.\n\n          2              MR. HAQUE:  Yes.\n\n          3              COMMISSIONER CHANG:  What -- Pamela mentioned --\n\n          4   look, we have an urgent thing.  It's resource adequacy, and\n\n          5   PJM has filing rights on capacity market, or resource\n\n          6   adequacy.  So, that shouldn't be a hurdle.  Like, you\n\n          7   already have filing rights.\n\n          8              My question to you is:  Is that true?  Because,\n\n          9   to me, the resource adequacy problem is not only whether the\n\n         10   capacity market parameters are correct, whether ELCC is\n\n         11   correct.  To me it's the interconnection process, it's the\n\n         12   transmission planning process, which I think the states need\n\n         13   a role and a voice in.\n\n         14              And so, my question to you is:  Is there a 205\n\n         15   filing right issue associated with solving the resource\n\n         16   adequacy problem?  But really, it ties into the\n\n         17   interconnection process and planning process, which PJM does\n\n         18   not have 205 filing rights.\n\n         19              MR. HAQUE:  I think that -- and, Commissioner,\n\n         20   are you asking specifically about a 205 filing opportunity\n\n         21   for the states?  Is that what you're asking about.\n\n         22              COMMISSIONER CHANG:  Well, I just want to know if\n\n         23   anything needs to change, to solve the resource adequacy\n\n         24   problem, because I don't think it's just like \"Oh, PJM has\n\n         25   resource adequacy filing rights, so they should just be able\n\n\n\n\n\n                                                                      197\n\n\n\n          1   to solve it right now.\"  That's my question.  What needs to\n\n          2   change, to solve the resource adequacy?  Specifically on\n\n          3   205.\n\n          4              MR. HAQUE:  Well, first of all, I do -- yeah,\n\n          5   look, if we are going to be accountable for all things, I\n\n          6   think giving PJM the authority, as the grid operator for 67\n\n          7   million consumers, and the largest grid operator, 205 rights\n\n          8   over all of its core business functions makes sense.\n\n          9              COMMISSIONER CHANG:  Including transmission\n\n         10   planning and --\n\n         11              MR. HAQUE:  Including transmission planning.\n\n         12              COMMISSIONER CHANG:  -- and all the parameters\n\n         13   associated with transmission planning.\n\n         14              MR. HAQUE:  Yes.  I believe it's schedules one...\n\n         15              COMMISSIONER CHANG:  And interconnection\n\n         16   agreements, interconnection processes.\n\n         17              MR. HAQUE:  Yes, Commissioner.  I think in the\n\n         18   operating agreement it's schedules one, two, six, 6A, and\n\n         19   6B.\n\n         20              COMMISSIONER CHANG:  Okay.\n\n         21              MR. HAQUE:  That are in the operating agreement\n\n         22   right now.\n\n         23              COMMISSIONER CHANG:  That's how I think about\n\n         24   this, but I wanted to hear from PJM.\n\n         25              CHAIRMAN SWETT:  Kent's been waving his card.\n\n\n\n\n\n                                                                      198\n\n\n\n          1              MR. CHANDLER:  Yes, for being quiet for 50\n\n          2   minutes, I'm so aggressive now.\n\n          3              (Laughter.)\n\n          4              MR. CHANDLER:  I think that's the first half of\n\n          5   it.  So, in my comments, I think I would reiterate, two\n\n          6   years ago the vast majority of OPSI commissioners advocated,\n\n          7   or agreed that the PJM board should have 205 rights over the\n\n          8   regional transmission expansion plan; they just objected to\n\n          9   the way it was proposed to be moved to the board from the\n\n         10   members.\n\n         11              But there was agreement amongst the states that\n\n         12   the board should have those 205 rights.\n\n         13              I think that is only part of the answer to your\n\n         14   question.  I still think that just the board having those\n\n         15   205 rights doesn't fundamentally change the way regional\n\n         16   transmission planning is done in PJM, and I don't think you\n\n         17   will get the optimal level of regional transmission planning\n\n         18   in PJM, which is a significant hurdle to getting new\n\n         19   capacity online, until and unless you fix the independence\n\n         20   issue with -- in some way with -- voluntary RTO membership.\n\n         21              And I think the fact that transmission owners in\n\n         22   PJM and in any RTO can effectively threaten or say they're\n\n         23   going to leave the RTO if they don't get their way, and\n\n         24   effectively take the backbone of the RTO with them, given\n\n         25   their inherit capital bias to invest in transmission, and\n\n\n\n\n\n                                                                      199\n\n\n\n          1   the benefits of regional transmission planning, and leading\n\n          2   to more cost effective transmission investment rather than\n\n          3   utility by utility investment, leads to sub-optimal outcomes\n\n          4   in regional transmission planning, whether the board has the\n\n          5   205 rights or not.\n\n          6              COMMISSIONER CHANG:  So it's essential but not\n\n          7   sufficient.  Okay.\n\n          8              CHAIRMAN SWETT:  Do you think that PJM can\n\n          9   transfer the RTEP protocol to the tariff on its own, or is it\n\n         10   perpetually beholden to the TO's control?\n\n         11              MR. CHANDLER:  I believe that...\n\n         12              CHAIRMAN SWETT:  And I'd like to hear from Asim\n\n         13   after this.\n\n         14              MR. CHANDLER:  I believe that the transmission\n\n         15   expansion, the RTEP protocols, can be transferred from the\n\n         16   operating agreement to the tariff or to the board, through a\n\n         17   Section 206 filing, whether it's Sua sponte by the\n\n         18   Commission or through a complaint under Section 206.  There\n\n         19   are likely conforming changes that would need to be made to\n\n         20   other governing documents, but they are in them -- those\n\n         21   other governing may or may not have all the Sierra\n\n         22   provisions, et cetera.  (Laughs.)\n\n         23              I think there would need to be conforming changes\n\n         24   to other governing documents, but those, themselves, don't\n\n         25   have to have the 206 complaint file against them.\n\n\n\n\n\n                                                                      200\n\n\n\n          1              CHAIRMAN SWETT:  Okay.  And Asim, we'll give you\n\n          2   the last word here.\n\n          3              MR. HAQUE:  Agree.  I agree with Kent on that.\n\n          4              CHAIRMAN SWETT:  Okay.  That was easy.  All\n\n          5   right.  Well, I don't -- who had their flag up first? \n\n          6   Because we've got 2-1/2 minutes.  Secretary.\n\n          7              MS. JAWOROWSKI:  Thank you very much.  I wanted\n\n          8   to first make one note, that in the first panel Jacob Finkel\n\n          9   was here on behalf of the governors' collaborative, and I\n\n         10   was also asked to be here on behalf of the governors'\n\n         11   collaborative.  So, that organization has been very active\n\n         12   in a lot of recommended solutions.\n\n         13              Also, I want to say I completely agree with you,\n\n         14   Commissioner LaCerte.  It's a culture issue that needs to be\n\n         15   changed and shift, and the power is with the stakeholders\n\n         16   right now, and having an advisory, non-binding, stakeholder\n\n         17   engagement would -- and then giving the power to PJM and the\n\n         18   board is essential for change.\n\n         19              We also believe that the governors should have\n\n         20   some input that is voting, and an opportunity for a veto on\n\n         21   operational agreements and resource adequacy matters.\n\n         22              But, another note I'd like to make is -- I made\n\n         23   it in my testimony that was written, and that is the at MISO\n\n         24   the short term incentives are something that is built into\n\n         25   the culture there.  People know that there are seven\n\n\n\n\n\n                                                                      201\n\n\n\n          1   categories of goals that the organization is working towards\n\n          2   all the time.  All the staff know that.  All the board know\n\n          3   that.\n\n          4              The board then ranks the organization on how well\n\n          5   they're going after those priorities and achieving those,\n\n          6   and then there are bonsuses given out to the staff based on\n\n          7   that.\n\n          8              It is a very effective tactical tool to ensure\n\n          9   the priorities are right in line, and the board and the\n\n         10   staff have the authority to do that.\n\n         11              The stakeholders are well respected.  The staff\n\n         12   does not like to go against stakeholder recommendations, but\n\n         13   they will when it comes to affordability and reliability,\n\n         14   and they have the authority to do that.  So, I think that's\n\n         15   an essential part of why MISO is operationally sound.\n\n         16              CHAIRMAN SWETT:  Thank you for bringing us back\n\n         17   to first principles, and thank you all for your time, and\n\n         18   the very thorough preparation.  This has been very riveting,\n\n         19   and going against the stereotype of a tech conference.\n\n         20              COMMISSIONER LACERTE:  I've got a final question\n\n         21   for Steve I didn't get to ask yet.\n\n         22              CHAIRMAN SWETT:  Oh, please.\n\n         23              COMMISSIONER LACERTE:  So, do you believe that\n\n         24   the sou chefs should have two-thirds voting rights authority\n\n         25   over the chef?\n\n\n\n\n\n                                                                      202\n\n\n\n          1              (Laughter.)\n\n          2              MR. LIEBERMAN:  No.\n\n          3              COMMISSIONER LACERTE:  Good answer.\n\n          4              (Laughter.)\n\n          5              CHAIRMAN SWETT:  Thank you all.  We have -- and\n\n          6   go ahead.\n\n          7              MS. EYOCKO:  All right.  Thank you, Chairman, and\n\n          8   commissioners, and thank you to panelists.  We have reached\n\n          9   the end of this panel.  We will now take a 15-minute break. \n\n         10   I believe it's 2:15.  So, please come back here at 2:30. \n\n         11   Thank you very much.\n\n         12              (Brief recess.)\n\n         13   PANEL III\n\n         14   2:31 p.m.\n\n         15              MS. EYOCKO:  Welcome back, everyone.\n\n         16              As a reminder, the first two rows are reserved\n\n         17   for all the panelists.  And next door, in the hearing room,\n\n         18   there is additional seating.  All right, let's get started.\n\n         19              Again, my name is Stefania Eyocko, and I am from\n\n         20   the Office of the Energy Market Regulation here at the\n\n         21   Commission, and we are going to begin the final portion of\n\n         22   the second panel, which will be similar to earlier, a\n\n         23   conversation with energy representatives, that will examine\n\n         24   how the PJM stakeholder process, including established\n\n         25   sectors, committees, voting structures, affects the RTOs'\n\n\n\n\n\n                                                                      203\n\n\n\n          1   ability to take necessary and timely actions, including\n\n          2   Section 205 filings, to address the region's operational and\n\n          3   market challenges.\n\n          4              As a reminder, panelists did submit an advanced\n\n          5   statement that includes their position, and so, to maximize\n\n          6   the amount of time for discussion, we will be foregoing\n\n          7   opening remarks from the panelists and go directly to\n\n          8   questions from the commissioners and the chairman.\n\n          9              Panelists, to answer a question from the chairman\n\n         10   or the commissioners, please tip your name tent like so, and\n\n         11   when you're called upon please turn your microphone on with\n\n         12   the gray button at the base of the microphone in front of\n\n         13   you.  You will know your mic is on when the LED light is\n\n         14   glowing green.\n\n         15              As a reminder from earlier, we do not intend to\n\n         16   discuss at this technical conference any specific proceeding\n\n         17   before the Commission, and we ask that panelists similarly\n\n         18   refrain from such discussion.  If anyone engages in these\n\n         19   kinds of discussions, my colleagues from the Office of\n\n         20   General Counsel will interrupt the discussion to ask the\n\n         21   speaker to avoid that topic.\n\n         22              And now, for the panelists.\n\n         23              We first have Dave Anders, the Senior Director of\n\n         24   Stakeholder Affairs in PJM.\n\n         25              We have Glen Thomas, President of PJM Power\n\n\n\n\n\n                                                                      204\n\n\n\n          1   Providers Group.\n\n          2              We have Jodi Moskowitz, Vice President of\n\n          3   Regulatory Law and Deputy General Counsel and RTO Strategy\n\n          4   Officer with the Public Service Enterprise Group,\n\n          5   Incorporated.\n\n          6              We have Jameson TWEEDIE, Public Advocate for the\n\n          7   Delaware Division of the Public Advocate; Mason Emnett,\n\n          8   Senior Vice President for Public Policy at Constellation;\n\n          9   Brian George, Senior Lead for U.S. Energy Markets, at\n\n         10   Google; Susan Bruce, Counsel for the PJM Industrial Customer\n\n         11   Coalition, and finally we have Dr. Joe Bowring, who is the\n\n         12   President of Monitoring Analytics and independent market\n\n         13   monitor for PJM.\n\n         14              Chairman, please take it away.\n\n         15              CHAIRMAN SWETT:  Thank you for being here,\n\n         16   everyone.  I am expecting a spicy discussion to take us home\n\n         17   for the day.  We're going to continue our Supreme Court\n\n         18   style here, but the chief justice will be Commissioner See\n\n         19   for this panel.\n\n         20              (Laughter.)\n\n         21              COMMISSIONER SEE:  Great.  Thanks for the\n\n         22   promotion.\n\n         23              (Laughter.)\n\n         24              COMMISSIONER SEE:  All right.  We're going to\n\n         25   bring it home strong, for the last panel of the day.\n\n\n\n\n\n                                                                      205\n\n\n\n          1              Brian, I'm going to start with you.  It is a very\n\n          2   easy question.  So, you're not a PJM member, but you have\n\n          3   significant financial stakes in PJM.  You've also been\n\n          4   sitting here all day.  You've heard a lot of proposals that\n\n          5   are on the table.\n\n          6              So, I want to start focusing things a little bit. \n\n          7   You know, we've heard some of them that PJM could enact\n\n          8   tomorrow.  We've heard some of them that are obviously going\n\n          9   to take some more time, to go through a process.\n\n         10              So, from your perspective, what are the proposals\n\n         11   that will give us the highest value add, and kind of, how do\n\n         12   you discount that, based on the time that some of those\n\n         13   solutions are going to take?\n\n         14              MR. GEORGE:  Yeah, well thank you, \"chief\n\n         15   justice\" See, for the question.\n\n         16              (Laughter.)\n\n         17              MR. GEORGE:  And thank you, Chair and\n\n         18   commissioners for the invitation.\n\n         19              So, you know, I think, as you articulated, we've\n\n         20   made a tremendous bet on this market, as we have many other\n\n         21   markets in the U.S.  We have billions of dollars of capital\n\n         22   that have already been invested in the region.  Right?  And\n\n         23   we have operating data centers across the footprint, and we\n\n         24   continue to add to that fleet, as we grow.\n\n         25              And so, the ability to serve those sites, to\n\n\n\n\n\n                                                                      206\n\n\n\n          1   serve our customers, to serve our demand reliably, is\n\n          2   critical to our ability to grow and continue to provide the\n\n          3   services that we all use.\n\n          4              And so, I think, when it comes to the PJM\n\n          5   process, what I've heard today, the discussion I've heard, I\n\n          6   think someone mentioned it really well, on the preceding\n\n          7   panel, which is consensus is not a prerequisite for\n\n          8   leadership.  Right?\n\n          9              At the end of the day, we know that PJM has 205\n\n         10   filing rights over the capacity market, and we know the\n\n         11   central issue in front of us is resource adequacy.  Right? \n\n         12   And we know that PJM can act on the things that it wants to\n\n         13   do to fix that problem.\n\n         14              I think over the past year -- right? -- we've\n\n         15   seen various, well two specifically, CIFP processes -- that\n\n         16   we, as Google, have been very engaged in from the beginning. \n\n         17   Despite being a non-member of PJM, we've worked with other\n\n         18   members, and other non-members of PJM, to build consensus on\n\n         19   proposals, on positions, to move forward.  Yet, we still\n\n         20   don't see a pathway out of this.\n\n         21              And so I think what is really frustrating, from\n\n         22   that point of view, is that, for us to go out and make the\n\n         23   investments in the things that we are expected to -- right?\n\n         24   -- not just data centers, but to the rate payer protection\n\n         25   pledge, bringing our own new generation, building, buying that,\n\n\n\n\n\n                                                                      207\n\n\n\n          1   going out and deploying the capital to do that, we can't do\n\n          2   that without the certainty that the market rules are going\n\n          3   to exist in such a way that we know that investment is going\n\n          4   to be worthwhile.\n\n          5              And so, where I see us today, we just need some\n\n          6   leadership on what we're going to do next.  Right?  We've\n\n          7   heard discussions about proposals, we've seen changes. \n\n          8   Sometimes those changes happen with very little\n\n          9   transparency.  Right?  And so, in addition to leadership, I\n\n         10   think we need transparency as to why we're making the\n\n         11   decisions we are.\n\n         12              But, at the end of the day, we've had enough\n\n         13   discussion about the issues in front of us, that we do need\n\n         14   to move forward.  And, without that ability to move forward,\n\n         15   we're not going to be able to deploy the capital that we\n\n         16   want to, in a manner that we have agreed to do it, to go out\n\n         17   and serve our businesses, to grow.\n\n         18              COMMISSIONER SEE:  So, clear direction, assertive\n\n         19   leadership, and transparency around those decisions.\n\n         20              MR. GEORGE:  Yeah.\n\n         21              COMMISSIONER SEE:  Great.  I suspect others may\n\n         22   have thoughts on that question, so if there are others who\n\n         23   want to jump in on where are our highest value-add\n\n         24   solutions, especially when we're considering the time it\n\n         25   takes to put those into place.\n\n\n\n\n\n                                                                      208\n\n\n\n          1              We'll start doing a couple of tent cards.  I\n\n          2   suspect my colleagues will jump in at some point before\n\n          3   everybody answers this one, so we'll keep going until that\n\n          4   happens.\n\n          5              Dr. Bowring.\n\n          6              DR. BOWRING:  Thank you.  Thanks for the\n\n          7   opportunity to be here.  I'll defend my honor against James\n\n          8   Danly's comments later.\n\n          9              (Laughter.)\n\n         10              DR. BOWRING:  I'm not the spokesperson for lack\n\n         11   of accountability.  Sorry, James.\n\n         12              So, I mean, I agree about leadership.  I mean, I\n\n         13   think there are two key things.  One is the independence of\n\n         14   the board, which has been talked about a lot.  But there are\n\n         15   two ways to -- two, at least two, essential ways to get\n\n         16   there.  One is the nominating committee, but the other is to\n\n         17   ensure that the board cannot be voted out by members without\n\n         18   at least some participation by states.  We made a specific\n\n         19   recommendation about that.\n\n         20              So, at the moment -- and again, nothing I say\n\n         21   should be taken as a comment about any individual person. \n\n         22   The folks at PJM and the board are all doing, you know,\n\n         23   great jobs, but they are constrained by the structural\n\n         24   nature or the structural facts of the positions they're in.\n\n         25              And the board, at the moment, as Commissioner\n\n\n\n\n\n                                                                      209\n\n\n\n          1   LaCerte pointed out, is, at the moment, worried about being\n\n          2   fired, as they should be, because they can be.  That means\n\n          3   they cannot be independent.  That's just a fact, not a\n\n          4   criticism.\n\n          5              The nominating committee is really part of that\n\n          6   as well.\n\n          7              But one of the issues that has not been talked\n\n          8   about as much is also about the staff.  PJM's staff.  Again,\n\n          9   not a criticism of PJM's staff role.  Obviously they are\n\n         10   very smart, they keep the lights on.\n\n         11              But what, exactly, are the staff's goals?  The\n\n         12   staff's goals should be specified as acting in the public\n\n         13   interest, not acting in the interests of their members.  And\n\n         14   those are two very different things.\n\n         15              And Asim pointed out that some members -- members\n\n         16   driven -- but that's what the stakeholders are about; it's a\n\n         17   members process.  But it shouldn't be a members process. \n\n         18   Obviously the members are part of it.  PJM has to listen to\n\n         19   the members.  But ultimately PJM's staff and the board's\n\n         20   role, in our view, should be stated clearly, as acting in\n\n         21   the public interest, consistent with the Order 2000.\n\n         22              And one last piece of independence, which was\n\n         23   raised by Kent, is the TO.  Now, if there's a veto power\n\n         24   anywhere, it's the TO's veto power, the ability to leave,\n\n         25   and that has to be addressed.\n\n\n\n\n\n                                                                      210\n\n\n\n          1              While I don't expect the Commission to rule that\n\n          2   membership is mandatory in an RTO, I do think there need to\n\n          3   be clear, specific, rules about when a TO could leave, and\n\n          4   when that threat could be credible.  Otherwise, that threat\n\n          5   hangs over every decision that PJM staff and the PJM board\n\n          6   makes.\n\n          7              COMMISSIONER SEE:  Dr. Bowring, I was hoping that\n\n          8   we could start streamlining the solutions but, of course,\n\n          9   leave it to you to put more on the table.  But no, I really\n\n         10   appreciate your thoughts there.\n\n         11              DR. BOWRING:  No.  Three things.  Three things. \n\n         12   Board independence, staff independence.\n\n         13              COMMISSIONER SEE:  Yeah.\n\n         14              DR. BOWRING:  Adress the TO question.\n\n         15              COMMISSIONER SEE:  Great.  Thank you.\n\n         16              DR. BOWRING:  Thanks.\n\n         17              CHAIRMAN SWETT:  Wait, I'm sorry.  Just on that\n\n         18   point, do you think the staff is not independent?  And, if\n\n         19   they are not, then what needs to change?\n\n         20              DR. BOWRING:  I think the question is \"What are\n\n         21   their objectives?\"  Are their objectives to make the members\n\n         22   happy, to do what the members ask them to do?  When members\n\n         23   come and say \"I want a particular kind of rule,\" is it their\n\n         24   job to make that work, or is it their job to say \"We don't\n\n         25   think that's in the public interest, we don't think that's\n\n\n\n\n\n                                                                      211\n\n\n\n          1   consistent with the overall interest of the market?\"\n\n          2              So, I would hope it's the latter.  I don't think\n\n          3   it is, from my experience.  I think it is member driven.\n\n          4              Again, nothing, nothing -- there is something\n\n          5   wrong with it but it's nothing -- they're not -- staff is\n\n          6   not doing anything wrong.  I think that's the culture, as\n\n          7   we've talked about.\n\n          8              CHAIRMAN SWETT:  So what's the fix for that?\n\n          9              DR. BOWRING:  The fix about that is to make sure\n\n         10   that the board directs the staff that their sole objective\n\n         11   is to act in the public interest, consistent with Order\n\n         12   2000, competitive markets, the lowest possible cost, not\n\n         13   catering to the specific issues of individual members, which\n\n         14   may not be consistent with that overarching goal.\n\n         15              CHAIRMAN SWETT:  Okay.  Please continue.\n\n         16              COMMISSIONER ROSNER:  And does this have to do\n\n         17   with this, the board's charter, or operating document,\n\n         18   saying that it should act in the public interest?  Is that -\n\n         19   -\n\n         20              DR. BOWRING:  Well, I think that is true, and\n\n         21   that's what Order 2000 said, and that is what the board is\n\n         22   supposed to be doing, and that's what the staff is supposed\n\n         23   to be doing, and that's what the board should be directing\n\n         24   the staff to be doing.  But something's gotten lost along\n\n         25   the way.  I don't think that's happening effectively enough,\n\n\n\n\n\n                                                                      212\n\n\n\n          1   and I don't think 205 rights are the solution.\n\n          2              MS. BRUCE:  First of all, I'll add my thanks for\n\n          3   the invitation to speak on this very important panel.\n\n          4              You know, hopefully -- one of the things, in\n\n          5   terms of thinking about the stakeholder process and reform\n\n          6   looking forward at this moment, this inflection point, is thinking\n\n          7   a bout what needs to be done to get things built.  In the\n\n          8   the stakeholder world, what are the processes that are\n\n          9   forestalling investment?\n\n         10              And I think that that is a lens, as we think\n\n         11   about prioritization.  Maybe there's issues that we've not\n\n         12   even thought about, within the stakeholder process, that\n\n         13   should be on that list?  What are those issues that are\n\n         14   within PJM's control?  What are those issues that are within\n\n         15   the states' control, and where is there a joint issue, a\n\n         16   really clear plan on what do we need to do to get things\n\n         17   built, whether or not it's, you know, in front of the meter\n\n         18   generation, if it's battery storage, you know, anything? \n\n         19   Anything and everything, all of the above.  What can we do\n\n         20   to get things built?\n\n         21              And I think, as we think about that, there's\n\n         22   probably an element of speed that's necessary, speed to\n\n         23   market, speed to deal with the supply chain, how do we deal\n\n         24   with some of those issues, are there interventions that are\n\n         25   necessary, to accelerate that?  So, speed is an undeniable\n\n\n\n\n\n                                                                      213\n\n\n\n          1   feature of all of this.\n\n          2              But I will also add in -- and I don't -- the role\n\n          3   of stability, as well, because in this investment climate,\n\n          4   when people are being expected, or want to invest billions\n\n          5   of dollars, knowing what the rules of the road are, and\n\n          6   keeping them stable is, I think, also a consideration, as we\n\n          7   think about speed.  Where is speed necessary?  Where is\n\n          8   stability necessary?  And being really thoughtful about\n\n          9   that, as we think about any plan, any work plan that the\n\n         10   stakeholders might undertake and those that regulate us.\n\n         11              And, the other tension that's inherent here is\n\n         12   the tension between where is there a place for consensus and\n\n         13   where is the role of independence?  Consensus can build\n\n         14   really durable solutions, but they might not -- they're\n\n         15   harder ones.  And it requires us thinking about things in a\n\n         16   more comprehensive way. \n\n         17              And I think one of the stakeholder processes\n\n         18   we've not talked about a lot is that we talk about a lot of\n\n         19   things in silos, and to get real, durable, consensus\n\n         20   probably means looking at a couple of issues together so\n\n         21   that you can have real tradeoffs across issues. And where\n\n         22   are we asking the board to be independent, and then how is\n\n         23   that independence -- what is guiding that independence, what\n\n         24   is the metric?\n\n         25              And I do think that it's being really the -- in\n\n\n\n\n\n                                                                      214\n\n\n\n          1   my comments I raised the question of whether or not the PJM\n\n          2   board should be more mindful of -- or the operating\n\n          3   agreement being amended to consider the retail market\n\n          4   considerations, because there is that element here too.\n\n          5              But I think that, hearing the conversation today,\n\n          6   really thinking about the public interest and understanding\n\n          7   what that means, and having the board be -- having that be\n\n          8   part of their mantra when they're making their decisions. \n\n          9   It's a useful thing.\n\n         10              COMMISIONER SEE: I think you have the tensions\n\n         11   right there, and I speak in tensions a lot too.  Right? \n\n         12   Between speed and deliberateness, and independence and\n\n         13   consensus.  But, we're trying to find solutions here too.\n\n         14   \n\n         15              MS. BRUCE: I know, I know. \n\n         16              COMMISSIONER SEE:  So tell me, like, when you\n\n         17   think about that, where do you think we're able to draw that\n\n         18   line better?\n\n         19              MS. BRUCE:  In terms of speed...\n\n         20              COMMISSIONER SEE:  You can take either one.\n\n         21              MS. BRUCE:  Either one, either one?\n\n         22              COMMISSIONER SEE:  Yeah.\n\n         23              MS. BRUCE:  You know, I think that it goes to the\n\n         24   work plan.\n\n         25              COMMISSIONER SEE:  Uh-huh.\n\n\n\n\n\n                                                                      215\n\n\n\n          1              MS. BRUCE:  And being very deliberate about it. \n\n          2   What are the ones, again, going back to that, you know, what\n\n          3   do we need to do?  We need to get things built.  And it's\n\n          4   generation, transmission.  We need to think about demand\n\n          5   response in, perhaps, new ways.  Focus on those.  Those are\n\n          6   the places where we need speed.\n\n          7              You know, sort of, some of the bigger questions,\n\n          8   about where we need stability, I think knowing -- are we\n\n          9   going to have a capacity market in two or three years? \n\n         10   That's a scary thing, if you're asking people to make -- and\n\n         11   when is that decision going to be made?  Because people are\n\n         12   making decisions today, about -- they made them yesterday --\n\n         13    about whether or not they're going to be building.\n\n         14              So I think that that is a lens, and I know it's -\n\n         15   - but I'm hopeful that that kind of prioritization and lens\n\n         16   of looking at things might be helpful in terms of framing\n\n         17   things.  So, thank you.\n\n         18              COMMISSIONER SEE:  I appreciate that.\n\n         19              CHAIRMAN SWETT:  I saw -- I know Glen has had his\n\n         20   up for a while.  I lost track of the order for everyone\n\n         21   else.\n\n         22              MR. THOMAS:  Yeah.  No, thank you.  And again,\n\n         23   thank you for the invitation and for all the commissioners\n\n         24   to be here.\n\n         25              You know, we're going to give you a unique\n\n\n\n\n\n                                                                      216\n\n\n\n          1   moment.  Commissioner Rajiv always talked about people\n\n          2   building consensus.  I agree with everything Susan just\n\n          3   said.\n\n          4              So, literally, you have somebody representing the\n\n          5   largest consumers in the PJM footprint, and somebody\n\n          6   representing the largest suppliers in the PJM footprint\n\n          7   agreeing wholeheartedly.\n\n          8              Maybe I'll stand on a few things and she may or\n\n          9   may not agree with these things, but at least I'll expand on\n\n         10   a couple of them, to your question, Commissioner See. \n\n         11   (Laughs.)\n\n         12              First of all, in terms of low hanging fruit, I\n\n         13   think state involvement and state input is the easiest and\n\n         14   the lowest hanging fruit here.\n\n         15              Before I had this job as chairman of a public\n\n         16   utility commission, before that I was an advisor to a\n\n         17   governor.  I actually had Jacob's job well before Jacob had\n\n         18   that job.  (Laughs.)  So, I've seen this market from a bunch\n\n         19   of different areas and I've seen the evolution of state\n\n         20   participation in the capacity markets in a very unique way.\n\n         21              And Dave will remember some of these stories, but\n\n         22   I've told this a couple times.  I'll spare you all the\n\n         23   details.\n\n         24              But when I was chairman of the commission, I was\n\n         25   told I was not allowed to meet with the PJM board.  Very\n\n\n\n\n\n                                                                      217\n\n\n\n          1   specifically.  That has evolved a lot.  A lot.  To the point\n\n          2   where commissioners are regularly meeting with the PJM\n\n          3   board, having unique input throughout the process.\n\n          4              Can more be done?  Certainly.  You know, are\n\n          5   states important players in this game?  A hundred percent.\n\n          6              The introduction of the governors into the\n\n          7   conversation I think, at the end of the day, could be very\n\n          8   helpful, because let's face it, five-six years ago most\n\n          9   governors probably didn't hear, had never heard, of PJM. \n\n         10   Now they certainly most all have.  And getting the governors\n\n         11   more involved, I think, could ultimately be helpful to the\n\n         12   overall credibility of, you know, the enterprise we're\n\n         13   trying to work on here.\n\n         14              What I would suggest there is exactly what we did\n\n         15   with OPSI when I stood it up in -- what was the year of\n\n         16   that?  2005.  Yeah.  \n\n         17              So, funny story.  I actually wrote all the bylaws\n\n         18   and left the Commission before I had a chance to actually\n\n         19   serve on OPSI.  I actually served on OMS, as a member of the\n\n         20   organization's MISO states.  I was one of the charter members\n\n         21   of that, one of the original signers of those documents.\n\n         22               But, you know, we developed a piece of paper in\n\n         23   OPSI.  We brought it to the stakeholder process and we\n\n         24   talked about it with the PJM stakeholders.  There was a give\n\n         25   and take about what OPSI would look like, how it would be\n\n\n\n\n\n                                                                      218\n\n\n\n          1   funded.\n\n          2              You know, but ultimately, you know, we worked it\n\n          3   through the process.  And I would suggest doing exactly that\n\n          4   here.  There's nothing preventing, you know, the governors,\n\n          5   OPSI, collectively, individually, what have you, putting a\n\n          6   proposal in front of the stakeholders and let's have at it.\n\n          7              I mean, I think you've heard -- I don't think\n\n          8   you've heard any objections here today to governors and\n\n          9   commissions being involved in the PJM process in a very\n\n         10   constructive way.  I think we can make that happen.\n\n         11              Let me talk a minute about board independence,\n\n         12   because it's come up multiple times today.  And to me, you\n\n         13   know, there's a couple critical cogs in this situation here. \n\n         14   And board independence is one of them.\n\n         15              Having a board independence, that's not too\n\n         16   dissimilar to a regulatory commission that can take input,\n\n         17   hear from the various sides, make reasoned decisions that\n\n         18   are in the best interests of the market.  That's a good\n\n         19   thing, and that's ultimately the role that the board plays.\n\n         20              What also should be appreciated in that is the\n\n         21   role that you all play, as the regulator, because it's\n\n         22   almost like a shared responsibility because PJM could come\n\n         23   up, you know, with all the best ideas in the world, but they\n\n         24   ultimately have to get through this body.\n\n         25              So, having an engaged commission on these issues\n\n\n\n\n\n                                                                      219\n\n\n\n          1   is critically important.  And having a focused commission as\n\n          2   well.  Because, let's face it, I mean, this commission has\n\n          3   the ability to set an agenda as well.  That's why we're here\n\n          4   today.  Right?  Because you all have identified some issues\n\n          5   that are our priorities, and you have the ability do that as\n\n          6   well.\n\n          7              So I would, maybe, challenge you all a little\n\n          8   bit, you know, to evaluate how FERC can be, you know,\n\n          9   helpful in that prioritization at the RTO level.\n\n         10              And maybe I'll stop there.  I'll save a few\n\n         11   comments maybe for later, in the interest of time.  But\n\n         12   those are just a few initial thoughts on constructive things\n\n         13   that could be done right away.\n\n         14              CHAIRMAN SWETT:  Are you saying that we should\n\n         15   focus more on PJM at this juncture?\n\n         16              MR. THOMAS:  I did not say that.  (Laughs.)\n\n         17              (Laughter.)\n\n         18              MR. THOMAS:  I did not say that.\n\n         19              CHAIRMAN SWETT:  All right.  Just checking.  Just\n\n         20   checking.\n\n         21              MR. THOMAS:  Well, let me maybe -- I mean, offer\n\n         22   a few...\n\n         23              (Laughter.)\n\n         24              MR. THOMAS:  Yeah.  Well, and that maybe goes to\n\n         25   the point of board members getting fired.  Right?  I mean,\n\n\n\n\n\n                                                                      220\n\n\n\n          1   you know, the comments come up that, a couple times, that\n\n          2   board members shouldn't be afraid of being fired.  And, you\n\n          3   know, I would respectfully say, if I'm a board member and\n\n          4   afraid of being fired, I'm in the wrong job.  You know?  I\n\n          5   should be feeling, as a board member, empowered to make what\n\n          6   I think are the best interests of the organization,\n\n          7   reportable to the operating agreement, and if I can't handle\n\n          8   the pressure, and if I'm afraid of being fired -- you all\n\n          9   live with that pressure every day.  So, I --\n\n         10              COMMISSIONER LACERTE:  The nominating the\n\n         11   committee.\n\n         12              MR. THOMAS:  Huh?\n\n         13              COMMISSIONER LACERTE:  Somebody's controlling the\n\n         14   nominating committee, then who is making the decisions to\n\n         15   nominate the people who are afraid of being fired?  Like,\n\n         16   how deep down the hole do we need to go?\n\n         17              MR. THOMAS:  The nominating -- well, the way it\n\n         18   works, from a process perspective, the nominating committee\n\n         19   goes forward, they put up their nominees.  The members vote\n\n         20   and go forward accordingly.  So, if the nominating committee\n\n         21   can agree on the candidates, whether they're for renewal or\n\n         22   somebody new, that's part of the process as well.\n\n         23              But, like I said -- I mean, you could talk to the\n\n         24   people that serve on the accountability, or have served on\n\n         25   the nominating committee.  I'd be surprised if any one of\n\n\n\n\n\n                                                                      221\n\n\n\n          1   them said to you \"We're not reappointing this member because\n\n          2   of a vote that the PJM board made.\"\n\n          3              First of all, we don't know who voted what.  We\n\n          4   don't know what's going on in those discussions.  I know\n\n          5   that's probably one of your issues as well.\n\n          6              COMMISSIONER LACERTE:  Right.\n\n          7              MR. THOMAS:  So...\n\n          8              COMMISSIONER LACERTE:  Neither do we.\n\n          9              MR. THOMAS:  Right.  You know, and that could be\n\n         10   -- that's a separate conversation.\n\n         11              COMMISSIONER LACERTE:  Who does?\n\n         12              MR. THOMAS:  Huh?\n\n         13              COMMISSIONER LACERTE:  If you can narrow it down\n\n         14   by who does know who voted?\n\n         15              MR. THOMAS:  Yeah, there are a few people.\n\n         16              COMMISSIONER LACERTE:  The non-secret society.\n\n         17              MR. THOMAS:  Right.\n\n         18              COMMISSIONER SEE:  To hijack a little bit, to\n\n         19   drill on this, you mentioned that we haven't heard\n\n         20   disagreement about state involvement in a more formalized,\n\n         21   involved, process.\n\n         22              MR. THOMAS:  Right.\n\n         23              COMMISSIONER SEE:  Great.  An areas where we did\n\n         24   hear some disagreement, that was state involvement on the\n\n         25   nominating committee.  So, I'm interested in getting\n\n\n\n\n\n                                                                      222\n\n\n\n          1   specific perspectives on that.\n\n          2              MR. THOMAS:  Yeah, I mean, here would be my\n\n          3   thought.  I mean, I think -- I think there's a general\n\n          4   unappreciation of how the nominating committee works.  And\n\n          5   Marjie served on the nominating committee.  I think it would\n\n          6   be really helpful to talk to the folks who have served on\n\n          7   that nominating committee, including the PJM board members\n\n          8   that have served on that nominating committee, so you all\n\n          9   have a better sense of how that works.\n\n         10              Yeah, I -- it seemed like there was a little bit\n\n         11   of an impression that people aren't voting their interests\n\n         12   and people are -- you know, there's a lot of votes being\n\n         13   taken, and things like that.\n\n         14              I don't think it works that way.  I have never\n\n         15   served on the nominating committee, so I can't offer you\n\n         16   that perspective.  And even those who serve on that\n\n         17   committee -- I mean, there are some very strict rules about\n\n         18   what they can and cannot say about their participation in\n\n         19   that.\n\n         20              But I think it would be helpful to get a better\n\n         21   appreciation for how that works.\n\n         22              I think having state involvement in that process\n\n         23   can be constructive.  I don't know that three, and how\n\n         24   they're appointed, and everything else like that -- you\n\n         25   know, maybe you want to reserve judgment on that.\n\n\n\n\n\n                                                                      223\n\n\n\n          1              But one thing I will offer, that when I was on\n\n          2   the commission -- this goes to, maybe, a point Commissioner\n\n          3   LaCerte made earlier -- at that point states did not have\n\n          4   access to confidential data at PJM.  And we had to go\n\n          5   through a series of rule changes in order for states to have\n\n          6   that access.\n\n          7              We sat down with the stakeholders.  We actually\n\n          8   had a situation where we thought the markets were being\n\n          9   manipulated, we couldn't see the details, we wanted to see\n\n         10   the details.  And I had obligation under state law at the\n\n         11   time to investigate.\n\n         12              So, we actually had to sit down and rewrite\n\n         13   tariff provisions that were eventually approved by this\n\n         14   commission, to allow states to have access to it, where we\n\n         15   addressed things like confidentiality and other things.\n\n         16              But, in my mind, we've got to go through a\n\n         17   similar process with this.  So, at the end of the day, you\n\n         18   want some sort of confidence in the process.  And I don't\n\n         19   know that we want to rush into that conversation 'til we\n\n         20   have a full visibility into, you know, really what all the\n\n         21   consequences could be if we don't do it right.\n\n         22              COMMISSIONER ROSNER:  But what I hear is you're\n\n         23   not sure you're there on three seats, but you're not opposed\n\n         24   to some number.\n\n         25              MR. THOMAS:  Some level of participation,\n\n\n\n\n\n                                                                      224\n\n\n\n          1   assuming some other boxes can be checked, yes.\n\n          2              COMMISSIONER LACERTE:  So, is that a yes?\n\n          3              MR. THOMAS:  It is.  Yeah, no, it's a yes but,\n\n          4   like, until you see -- as you know, Commissioner, until you\n\n          5   see all the details, it's hard to give an unequivocal yes.\n\n          6              COMMISSIONER LACERTE:  Yes, sure.\n\n          7              COMMISSIONER ROSNER:  And on this topic, you\n\n          8   know, I'll just note, you know, there's a variety of things\n\n          9   that we've talked about.  Everything from terms, length of\n\n         10   the terms, to the number of people on the board, to the\n\n         11   concept that Chairman Wood had, of the public interest\n\n         12   charter, you know, the board operating in the public\n\n         13   interesting, making that explicit, to things I've heard\n\n         14   about, you know, maybe we need more people from the region,\n\n         15   or maybe we need to make sure that some amount of the board\n\n         16   lives in the region, to get that better understanding and\n\n         17   more engagement with the states here.\n\n         18              You know, from my perspective, you know, I think\n\n         19   we have a lot of dials to turn here.  But also, you know,\n\n         20   the big gap, and what you described as low hanging fruit --\n\n         21   somebody here did -- is that engaging the states more in\n\n         22   this process, especially based on what we've heard about the\n\n         23   nominating committee, so far, is that, based on its rules,\n\n         24   you know, it sounds like if Marjie can do it, someone from a\n\n         25   -- you know, the state governor might want to -- should be\n\n\n\n\n\n                                                                      225\n\n\n\n          1   able to do it as well.\n\n          2              And so, you know -- but it is very helpful to\n\n          3   have that feedback and I hear your reservations, and we want\n\n          4   to get those dials turned.\n\n          5              MR. THOMAS:  Yeah, and if I could just make one\n\n          6   last comment, then I'll allow others to speak, one of the\n\n          7   challenges I have heard from the nominating committee\n\n          8   process is -- and PJM actually addressed this very publicly\n\n          9   a few year ago -- it is challenging finding qualified\n\n         10   candidates that pass all the screens in terms of conflicts\n\n         11   and everything else like that, whether they're financial or\n\n         12   otherwise.\n\n         13              So, it has been a frustration of mine that we\n\n         14   haven't seen representation from the PJM footprint, but\n\n         15   that's more, my understanding, a reflection of the conflicts\n\n         16   than some sort of institutional bias against people who live\n\n         17   in the area.\n\n         18              COMMISSIONER LACERTE:  James Danly just moved to\n\n         19   the area, if you're interested.\n\n         20              (Laughter.)\n\n         21              MR. THOMAS:  He might be conflicted.  (Laughs.)\n\n         22              (Laughter.)\n\n         23              COMMISSIONER SEE:  Maybe.  You have to respond to\n\n         24   that.  I do think it's interesting, on the state involvement\n\n         25   in the nominating committee.  One of the responses we've\n\n\n\n\n\n                                                                      226\n\n\n\n          1   heard is that the members of the committee are not\n\n          2   necessarily voting their own interests, because there's lots\n\n          3   of processes in place.\n\n          4              But one thing that occurs to me in that case is,\n\n          5   then, why are we so concerned about the states being the\n\n          6   ones who are doing that, as well?  So, we'll throw that out\n\n          7   there, and you can respond to it if you want to.\n\n          8               But it's been about 30 minutes and we haven't\n\n          9   heard from PJM yet.  So maybe we have David, and then we've\n\n         10   got a couple people in the middle who haven't talked either,\n\n         11   so you can keep adding to the list of things you want to\n\n         12   tell us about.\n\n         13              MR. ANDERS:  Thank you very much for inviting us\n\n         14   to be here today, and I'm really pleased to be with you. \n\n         15   So, thank you.\n\n         16              Chair Swett, you asked for candor.  I hope to\n\n         17   fulfill that.  And thank you for all the questions.\n\n         18              There's a couple things I wanted to share with\n\n         19   you, right at the top, and these aren't necessarily to your\n\n         20   point, Commissioner See, about what's the low hanging fruit. \n\n         21   But things that I see as needing to be taken care of.\n\n         22              COMMISSIONER SEE:  The most impactful.\n\n         23              MR. ANDERS:  And important.  And one of those,\n\n         24   actually, Commissioner LaCerte, you touched on, on the last\n\n         25   panel, which is culture.  And we heard Joe talk about\n\n\n\n\n\n                                                                      227\n\n\n\n          1   culture, in a way, talking about PJM staff and so forth. \n\n          2   And I think it's a really important discussion to have.\n\n          3              I'm going to bring it back a little bit, in a\n\n          4   \"way back machine,\" if you will.  (Laughs.)  If it's\n\n          5   helpful.  I don't want to waste all of your time with too\n\n          6   much detail about history here, but I think there's a couple\n\n          7   things that are important.\n\n          8              Number one is why are schedules one and six in\n\n          9   the operating agreement to begin with?  \n\n         10              I met with our founding CEO -- well first of all,\n\n         11   I became secretary of the members committee in 2002, so that\n\n         12   dates me.  Tuesday's meeting will be my 250th as secretary\n\n         13   of the members committee.  \n\n         14              And that may actually ask you -- or point your\n\n         15   questioning to well maybe all the problems are mine. \n\n         16   (Laughs.)\n\n         17              (Laughter.)\n\n         18              MR. ANDERS:  And, as a result of this technical\n\n         19   conference, I may be entering therapy, and David, I may be\n\n         20   expensing my therapy.\n\n         21              But I do want to share a few things.  I met with\n\n         22   then-CEO Phil Harris, founding CEO, about many things.  And\n\n         23   one time I asked him, you know, \"Why do we have schedule one\n\n         24   and schedule six in the operating agreement to begin with?\"\n\n         25              And, at that time, schedule six was -- it deals\n\n\n\n\n\n                                                                      228\n\n\n\n          1   with the RTEP protocol.  It's the planning process\n\n          2   protocol.\n\n          3              Schedule one, the energy markets looked different\n\n          4   then, but, you know, it's the energy markets.  And, at that\n\n          5   time, we had the rudiments of an early-early capacity market\n\n          6   in the operating agreement as well.  They were taken out\n\n          7   when the RPM went into effect, in roughly 2005.\n\n          8              But the energy markets, and the RTEP protocol\n\n          9   were put in there because, at the early stages of the RTO --\n\n         10    or PJM, as it was being formed, it was being formed by\n\n         11   folks who were turning over their assets to this new\n\n         12   fledgling organization that hadn't really -- I mean, we'd\n\n         13   operated as PJM since 1927, in different forms, but it was a\n\n         14   new, independent, organization, not run by the TOs.\n\n         15              And it was a new board, that hadn't even been\n\n         16   seated yet, and what -- maybe you'd call this hearsay, but\n\n         17   what Phil shared with me was that there was a certain level\n\n         18   of confidence that they didn't have at the time, in this new\n\n         19   board, in this new organization.\n\n         20              And so, one way to ensure that their assets were\n\n         21   being operated in a way that was appropriate, in their view,\n\n         22   was to maintain some level of control over certain functions\n\n         23   at PJM, and to do that through a document they clearly\n\n         24   controlled, which was the operating agreement.  Anything in\n\n         25   the tariff, you know, the public utility, PJM, has the 205\n\n\n\n\n\n                                                                      229\n\n\n\n          1   filing authority and so on.\n\n          2              So, if you go back to that, there's this level of\n\n          3   confidence in PJM, and there's also a strong cultural norm\n\n          4   within PJM, the community of PJM, not just PJM staff; the\n\n          5   full community, that it's a very member-centric\n\n          6   organization.  It's a very stakeholder-centric organization.\n\n          7              And, frankly, I think that's a strong -- a very\n\n          8   fundamental strength of PJM, is our desire, our true desire\n\n          9   and commitment, to serving the community.  The whole\n\n         10   community, including all of our 67 million customers.\n\n         11              I think where I want to help people understand\n\n         12   the impact of that on not only staff but how the stakeholder\n\n         13   process works is that there's this concentration on what the\n\n         14   stakeholders are seeing as their priorities, or what their\n\n         15   inputs are and so forth.\n\n         16              And so, when that translates into the stakeholder\n\n         17   process, if there's no firm deadline that can be put in\n\n         18   place, you know, this issue of who holds the 205 rights, on\n\n         19   those two critical pieces, discussions continue, and\n\n         20   continue, and continue, even though we might try to put a\n\n         21   deadline on it.  We might say \"Hey, there's a line in the\n\n         22   sand.  We need to get something done by a certain date,\" we\n\n         23   meet those 42 times...\n\n         24              Now, albeit it was over 36 months.  Perhaps we\n\n         25   can work on that.  We get to the end of that time and we\n\n\n\n\n\n                                                                      230\n\n\n\n          1   have people telling us, still, that they don't understand,\n\n          2   or they need more time.\n\n          3              So, what do we do with that?  You know, we're\n\n          4   left saying \"Okay, we've got to, you know, call the\n\n          5   question, but we're still going to have to file it under\n\n          6   Section 206.\"  And so it's not really helpful.  Right?\n\n          7              And so, I agree with you that there is a cultural\n\n          8   aspect to this, but I think it can be tied, in a way, and\n\n          9   it's a nuance that others haven't explored yet -- it can be\n\n         10   tied to the 205 authorities here.  And I think it's very\n\n         11   important.  So...\n\n         12              It's funny.  I was wondering whether we were\n\n         13   channeling, because I have culture at the top of my page,\n\n         14   and I was happy to hear you say that earlier.\n\n         15              COMMISSIONER LACERTE:  I saw your notes.\n\n         16              MR. ANDERS:  Yeah.  (Laughs.)\n\n         17              (Laughter.)\n\n         18              MR. ANDERS:  There are a couple.\n\n         19              COMMISSIONER CHANG:  Can you be a little bit more\n\n         20   specific?  You're saying we should tie it to the 205, and\n\n         21   it's cultural.  So, what do we need to do?\n\n         22              MR. ANDERS:  So, I think we need to remove\n\n         23   schedule one, and its derivative, schedule two, and schedule\n\n         24   six and its derivatives, schedule 6A and 6B, from the\n\n         25   operating agreement.\n\n\n\n\n\n                                                                      231\n\n\n\n          1              Now, schedule one is already in the tariff.  It's\n\n          2   the addendum to attachment K.  So, nothing more needs to be\n\n          3   done, aside from removing it from the operating agreement.\n\n          4              Schedule six and its derivatives would, then,\n\n          5   need to be put in the operating agreement -- or excuse me,\n\n          6   in the tariff.\n\n          7              COMMISSIONER CHANG:  Is that something that PJM\n\n          8   is willing to spearhead?\n\n          9              MR. ANDERS:  I would need to discuss that with\n\n         10   David and others, but speak with the folks on the board. \n\n         11   But...\n\n         12              CHAIRMAN SWETT:  David, do you want to come back? \n\n         13   For that?\n\n         14              (Laughter.)\n\n         15              COMMISSIONER CHANG:  Sorry, can you be more\n\n         16   specific about that?  I don't know the schedules like you\n\n         17   do.\n\n         18              MR. ANDERS:  Schedule one is the energy and\n\n         19   ancillary services markets.\n\n         20              COMMISSIONER CHANG:  Yeah, but what does it mean\n\n         21   when you say take it out?  What are you precisely saying?\n\n         22              MR. ANDERS:  So, the operating agreement, when we\n\n         23   look at the filing authorities on the different governing\n\n         24   documents we have -- so, three primary governing documents\n\n         25   we -- well, that PJM has some level of input on.  We've got,\n\n\n\n\n\n                                                                      232\n\n\n\n          1   probably, four, and some others.  But we have the CTOA,\n\n          2   which...\n\n          3              COMMISSIONER CHANG:  No, but what are you trying\n\n          4   to say?  What does it mean to \"take it out\" of the operating\n\n          5   agreement?  What's the implication?\n\n          6              MR. ANDERS:  PJM doesn't have the authority to\n\n          7   take it out of the operating agreement.  To change the\n\n          8   operating agreement, under Section 205, requires a\n\n          9   two-thirds sector majority, you know, weighted vote.\n\n         10              COMMISSIONER CHANG:  Yeah.\n\n         11              MR. ANDERS:  Of the members committee.  So...\n\n         12              COMMISSIONER LACERTE:  And you anticipate not\n\n         13   getting a two-thirds vote from the members committee to\n\n         14   accomplish this task.\n\n         15              MR. ANDERS:  I have suggested removing these\n\n         16   schedules from the operating agreement all the way back to\n\n         17   when we were working in the GAST, the Governance\n\n         18   Assessment Special Team, back in 2008.\n\n         19              COMMISSIONER CHANG:  But what's the implication\n\n         20   of that?\n\n         21              MR. ANDERS:  The implication is that we're going\n\n         22   to continue doing what we've been doing.  We're going to\n\n         23   continue with the same inability to call that question, and\n\n         24   people are still wanting to talk, and talk, and talk.\n\n         25              And then, the other implication, which, you know,\n\n\n\n\n\n                                                                      233\n\n\n\n          1   we haven't talked about yet -- people talked, on other\n\n          2   panels, about it -- is with respect to the prioritization.\n\n          3              So, yeah, people have asserted that we have the\n\n          4   205 rights on the tariff.  We've got the ability to do\n\n          5   prioritization.  And, for some reason, we're not actually\n\n          6   grasping that and going forward with it.\n\n          7              Certainly there's some accountability there, for\n\n          8   PJM.  I'm not trying to shirk that, whatsoever.\n\n          9              But, when we take independent action, when we say\n\n         10   we're not going to work on this thing in the stakeholder\n\n         11   process, it becomes -- it's just a -- it's almost, like, a\n\n         12   PR nightmare.  You have members accusing us of not being\n\n         13   attentive to their needs, not listening to them, telling us\n\n         14   that we're not operating in that customer centric.\n\n         15              COMMISSIONER CHANG:  Okay.\n\n         16              COMMISSIONER ROSNER:  So, Dave, let me drill down\n\n         17   a little more, and you have to excuse me, I went to a\n\n         18   football school, so you've got to be slow with me sometimes.\n\n         19              So, what you're telling me is you don't believe\n\n         20   you're going to get the mandate from the stakeholders to\n\n         21   accomplish this task\n\n         22              MR. ANDERS:  I don't.\n\n         23              COMMISSIONER ROSNER:  And you think FERC needs to\n\n         24   file a 206 to accomplish it.\n\n         25              MR. ANDERS:  That would be one way of doing it,\n\n\n\n\n\n                                                                      234\n\n\n\n          1   yeah.\n\n          2              COMMISSIONER ROSNER:  What would be another?\n\n          3              COMMISSIONER LACERTE:  Well, the members could\n\n          4   agree.\n\n          5              COMMISSIONER ROSNER:  Well, without the members\n\n          6   agreeing.\n\n          7              MR. ANDERS:  I think that some people, over the\n\n          8   years, have floated that there's some legal argument that\n\n          9   PJM's being a public utility and not having the ability to\n\n         10   file under Section 205 to amend its rates, terms and\n\n         11   conditions, service, doesn't comport to the FPA.  But I'm\n\n         12   not a lawyer.  That's, again -- I'm speaking -- I'm way out\n\n         13   over my skis on that.\n\n         14              COMMISSIONER ROSNER:  But also to reflect -- you\n\n         15   can jump back in here, but just to offer a point, what I've\n\n         16   heard from the other panels is some openness from the\n\n         17   members to discuss changes to the encumbrance on the 205\n\n         18   rights of these aspects of the operating agreement.\n\n         19              I haven't heard everyone say, you know, \"We're\n\n         20   willing to just move it carte blanche.\"  I've heard\n\n         21   discussions of \"If we fail to agree, after some period of\n\n         22   time, it might make sense to revisit -- or revisit the\n\n         23   two-thirds threshold.\"  But I haven't asked the people on\n\n         24   this panel that question, but I want to.\n\n         25              COMMISSIONER LACERTE:  Well, let's put the\n\n\n\n\n\n                                                                      235\n\n\n\n          1   stakeholders who are on the panel on the spot.  \n\n          2              COMMISSIONER ROSNER:  Yeah.\n\n          3              COMMISSIONER LACERTE:  Like, what do you have to\n\n          4   say about the proposal?\n\n          5              MS. MOSKOWITZ:  I'll jump in, and first just echo\n\n          6   the thanks for inviting me to participate on this panel. \n\n          7              I'm going to just start by harkening back to\n\n          8   where Chairman Swett started this morning, and reminding\n\n          9   everyone that PJM, or the predecessor to PJM, was formed in\n\n         10   1927.\n\n         11              It turns out that I am with PSE&G, and we are one\n\n         12   of the three founding members of PJM.  So, we have been, not\n\n         13   surprisingly, thinking about the issues of PJM governance\n\n         14   and how to make PJM work effectively, for quite a long time.\n\n         15              And, in our opinion, these issues have been\n\n         16   percolating for a long time.  That, in our opinion, the\n\n         17   governance has been broken for a long time.\n\n         18              But externalities now, and the extreme supply and\n\n         19   demand imbalance -- and that's kind of a multi-faceted, very\n\n         20   complicated, problem -- but that has brought all the\n\n         21   governance problems to light.\n\n         22              But this did not happen two years ago or, you\n\n         23   know, even five years ago.  It's been there for a while.\n\n         24              Before I jump into specific solutions, I just\n\n         25   want to respond quickly to this notion -- I've been hearing\n\n\n\n\n\n                                                                      236\n\n\n\n          1   this on a few of the panels -- that somehow the TOs have\n\n          2   veto power, and I feel like I have to speak, since I'm the\n\n          3   TO rep on this panel.  That we have veto power and that we\n\n          4   can, you know, \"vote with our feet,\" and we can leave PJM.\n\n          5              I mean, the reality is you don't see many TOs\n\n          6   leave RTOs, because it's really, really expensive to do\n\n          7   that.\n\n          8              So, I want to just level set that.  And this\n\n          9   notion that the TOs have veto power -- I was speaking to\n\n         10   someone a little while ago and we were talking about, kind\n\n         11   of, what happened when, a few years ago, there was\n\n         12   discussion about moving schedule six, the RTEP planning\n\n         13   protocols, from the operating agreement to the tariff.  So,\n\n         14   the very issue that we're talking about now, and that there\n\n         15   seems to be some, you know, at least some, support for that\n\n         16   notion, the fact is that went to a members committee vote\n\n         17   and it was voted down 80 percent, by 80 percent.\n\n         18              So, the only sector that voted in favor was the\n\n         19   transmission owner sector.  Because we strongly believe that\n\n         20   that was going to be necessary, to empower PJM to get to the\n\n         21   right decisions and to have that authority over its RTEP\n\n         22   planning protocols, like every other RTO does.\n\n         23              So, I just -- I want to be clear about that.  So,\n\n         24   to start with solutions, as you can tell, we've had concerns\n\n         25   with the sector-weighted voting for a while.  We don't think\n\n\n\n\n\n                                                                      237\n\n\n\n          1   that it works, because it doesn't sufficiently align voting\n\n          2   interest with accountability.\n\n          3                             There's been some discussion,\n\n          4   earlier, about affiliate votes.  I mean, the fact is PSEG\n\n          5   has a 1-1/2 percent vote in the process, even though we own\n\n          6   a significant amount of transmission assets and generation\n\n          7   assets.  We have a less than half percent vote in the\n\n          8   affiliate voting.  So, for us, it's all the same problem.\n\n          9              Now, one way to deal with that -- and there's\n\n         10   been a lot of discussion today -- is about -- is potential\n\n         11   move to advisory, stakeholder advisory voting.  I mean, that\n\n         12   is -- and we talked about it in our comments -- that maybe\n\n         13   that's not our preferred approach right now, but I can see\n\n         14   some merit in it, if we are comfortable that it's going to\n\n         15   get us to better outcomes, and that it's going to then\n\n         16   empower PJM to make the decisions that it needs to make.\n\n         17              But, it's clear to us the current voting doesn't\n\n         18   work, there need to be changes to voting.\n\n         19              In terms of, maybe, lower hanging fruit -- and I\n\n         20   think this is -- it's difficult and complicated, but\n\n         21   certainly wouldn't require operating agreement changes, is\n\n         22   what Dave is talking about.  And maybe it's tied to filing\n\n         23   rights, I'm not sure, but culture, leadership.\n\n         24              I will say, and we've communicated this to PJM,\n\n         25   that we were disappointed in the white paper that PJM issued\n\n\n\n\n\n                                                                      238\n\n\n\n          1   a few months ago on market reform, because it didn't really\n\n          2   set forth, kind of, a long term strategy and an actionable\n\n          3   plan.  You know, it put out to stakeholders three potential\n\n          4   paths, one of which was lower reliability, which seems like,\n\n          5   you know, when you -- when I read that, as a transmission\n\n          6   owner that has, you know -- we have 2-1/2 million electric\n\n          7   customers -- the idea of lower reliability doesn't seem like\n\n          8   the right answer.\n\n          9              So, we want PJM to have the tools and be\n\n         10   empowered to act, to get to better outcomes.  And, you know,\n\n         11   I know, Commissioner See, you asked about the nominating\n\n         12   committee.\n\n         13              I mean, I don't know how much that moves the\n\n         14   needle.  I mean, we certainly support more state engagement. \n\n         15   I think we have seen some of it working effectively\n\n         16   recently, whether it's with the PARSEC on transmission cost\n\n         17   allocation, or load forecasting.  I think that's an area\n\n         18   where PJM has done a good job of working with asset owners,\n\n         19   working with states, to get the states to give them a\n\n         20   formalized role in the process.\n\n         21              So, definitely understand and support the need\n\n         22   for more state engagement.  What exactly it looks like, I\n\n         23   think we can talk about.\n\n         24              COMMISSIONER SEE:  Great.  One of the benefits of\n\n         25   having such incredible expertise and experience here is we\n\n\n\n\n\n                                                                      239\n\n\n\n          1   have eight people on a panel for 75 minutes.  So, Jameson\n\n          2   and Mason you've been incredible patient.  So, if the two of\n\n          3   you want to give us your thoughts on any of the above,\n\n          4   please go for it, and then I strongly suspect there'll be\n\n          5   more questions from this side of the table, afterwards.\n\n          6              MR. TWEEDIE:  Thank you.  So, I'll just step back\n\n          7   one little bit, which is I'm here as the public advocate for\n\n          8   the State of Delaware.  I'm the representative for consumers\n\n          9   interests, and particularly residential and small commercial\n\n         10   customers.\n\n         11              I'm the only voice on these panels that has that\n\n         12   specific role, and I think it's noteworthy to think about\n\n         13   the role that we have in PJM.  We have an incredibly small\n\n         14   voice, even though what we do is represent the interests of\n\n         15   all 67 million consumers in the region.\n\n         16              We have 1.5 percent for PSEG vote -- jumped out\n\n         17   at me.  The consumer advocates have 14 votes.  That's 1.3\n\n         18   percent.\n\n         19              So, the representative of all the interests of\n\n         20   consumers has less votes than many of the other members, in\n\n         21   this process.\n\n         22              And even in sector weighting, we have a very\n\n         23   diminished vote.  We have roughly one-third of one-fifth of\n\n         24   -- one-third of a sector, which is one of the five sectors.\n\n         25              And I was really caught by something you said,\n\n\n\n\n\n                                                                      240\n\n\n\n          1   Chair LaCerte, and possibly somewhat in jest, but joking\n\n          2   about PJM as a secret society.  Because when I am talking to\n\n          3   members of the public and trying to explain what PJM is,\n\n          4   that's very similar to the reaction I get.  A body whose\n\n          5   members have financial interests in the decisions they're\n\n          6   making, that are making decisions that are putting those --\n\n          7   those decisions have direct consequences for all the rate\n\n          8   payers in the region.  And you try and explain that to people\n\n          9   and it is very challenging.\n\n         10              So, one of the things that I've heard today -- I\n\n         11   think that was the original question -- was \"What is the\n\n         12   reform  you've heard today that seemed the most meaningful?\"\n\n         13              And, to me, it is firmly and clearly establishing\n\n         14   public interest in PJM's mission and in is operating\n\n         15   documents, and having that operationalized through what PJM\n\n         16   does, both in its board and through the stakeholder process.\n\n         17              So, we've heard a lot about expanded board\n\n         18   authority today, and expanded board authority may be very\n\n         19   necessary.  It may be a near consensus opinion.  But that\n\n         20   needs to come with transparency and a clear obligation to\n\n         21   the public interest in what it does.\n\n         22              We've heard that the board hasn't necessarily\n\n         23   already taken all of the steps they could under their\n\n         24   existing authority.  So, expanding this authority may be a\n\n         25   solution, but it's certainly not sufficient in its own.\n\n\n\n\n\n                                                                      241\n\n\n\n          1              And we have, in our submitted comments, we had a\n\n          2   bunch of specific proposals, and I'm happy to go through\n\n          3   that.  But I do think that, in addition, there needs to be a\n\n          4   more significant role for the states, and that the consumer\n\n          5   advocates are currently the only members that are, in fact,\n\n          6   representatives of the states and all of the customers that\n\n          7   live in those states.\n\n          8              And that means that we -- there needs to be a\n\n          9   meaningful role for the states.  I think a role in the\n\n         10   nominating process makes a ton of sense, and I think having\n\n         11   rights to help shape what PJM does is essential.  So, thank\n\n         12   you.\n\n         13              COMMISSIONER ROSNER:  Thank you.\n\n         14              COMMISSIONER SEE:  Great.\n\n         15              MR. EMNETT:  Good afternoon.  Thank you for the\n\n         16   opportunity to be here.  It is really great to dig in on\n\n         17   these issues with the entire Commission.  I appreciate your\n\n         18   attention to it.\n\n         19              I do not have a good poker face, so you've been\n\n         20   seeing my reaction to the whole conversation.  (Laughs.)\n\n         21              (Laughter.)\n\n         22              MR. EMNETT:  I'll try and kind of step back and\n\n         23   distill what I'm hearing and then also, kind of, weave in\n\n         24   where we come at this, as the largest generation company in\n\n         25   the U.S., and within PJM.\n\n\n\n\n\n                                                                      242\n\n\n\n          1              So, what is the problem we're trying to solve?  I\n\n          2   hear three things.  Independence, the role of the states,\n\n          3   and leadership.  Just to kind of tick 'em off, independence,\n\n          4   I hear there's a concern with the board, that board members\n\n          5   have not been retained because members were unhappy with\n\n          6   them.  That was not a nomination committee issue.  They\n\n          7   weren't nominated by the nominating committee.  It was the\n\n          8   members who chose not to move forward with that.\n\n          9              What are solutions to that?  It could be term\n\n         10   limits.  It could be other, you know, proposals put on the\n\n         11   table, requirements associated or criteria associated with\n\n         12   the retention, or with the incoming members.  But what\n\n         13   problem are we trying to solve and are we tailoring the\n\n         14   problem to that, tailoring a solution to that problem?\n\n         15              State participation and authorities.  From my\n\n         16   perspective, it's about clarity of expectations, staffing\n\n         17   resources, so that states can do the job that's being\n\n         18   expected of them, that they want to do.  And partnership\n\n         19   within PJM, which is clearly not happening today.\n\n         20              But that goes both ways.  Both PJM being clear\n\n         21   here is what PJM needs input on from the states.  Where,\n\n         22   when, how, with transparency, the decision that is made,\n\n         23   feed back to whether the state's view was incorporated or\n\n         24   not, as well as PJM identifying for the states, \"Here is\n\n         25   what I need from you.  Here is the infrastructure that we\n\n\n\n\n\n                                                                      243\n\n\n\n          1   are planning for,\" and the exercise of jurisdiction at the\n\n          2   state level in order to accomplish the infrastructure build\n\n          3   that we need, as was mentioned earlier.  Because we do need\n\n          4   to be building things, and it's great to have a\n\n          5   conversation on governance, but if it's not for the purpose\n\n          6   of actually getting the things built and the customer\n\n          7   served, then we're losing sight.\n\n          8              Which takes me to the third issue, of leadership. \n\n          9   I'll just say it is a little bit telling, from my\n\n         10   perspective, that we have heard the PJM response, today,\n\n         11   that the members own the stakeholder process.  Well, if the\n\n         12   stakeholders aren't reaching consensus within the\n\n         13   stakeholder process, well, that's just -- you know, we\n\n         14   tried.\n\n         15              The PJM stakeholder process is managed by PJM. \n\n         16   PJM needs to have leadership.  They control the agendas, \n\n         17   They can set the priorities.  They can set the expectations,\n\n         18   the timeline, the accountability, as was mentioned earlier.\n\n         19              205 versus 206, I see that as a red herring.  PJM\n\n         20   has authority to move forward, regardless of its filing\n\n         21   mechanism.  And it can say \"Here is the timeline at which we\n\n         22   will make a decision, and we will move forward, using our\n\n         23   authority.\"\n\n         24              Most of the conversation has been around resource\n\n         25   adequacy, over which PJM has 205 rights.  So, to say\n\n\n\n\n\n                                                                      244\n\n\n\n          1   expanding 205 filing rights to the issue where we don't\n\n          2   spend most of our time fighting about is, again, not\n\n          3   tailored to the solution.  We need to bring it back to\n\n          4   accountability, expectations, level setting, and getting\n\n          5   the job done using the existing authorities today.\n\n          6              Frankly, I think that will get things done more\n\n          7   quickly.\n\n          8              CHAIRMAN SWETT:  David, do you have a response to\n\n          9   that?\n\n         10              MR. ANDERS:  A few thoughts I'd like to share.\n\n         11              I mentioned before that the 205 issue, in my\n\n         12   mind, is integrally linked to the cultural issue.  The\n\n         13   cultural issue, I think, is also linked to whether or not\n\n         14   the 205 rights are used differently with respect to resource\n\n         15   adequacy issues, where we already have the 205.\n\n         16              We address the stakeholder process with the same\n\n         17   posture, regardless of what the issue is.  So, maybe what\n\n         18   I'm hearing folks say is we ought not to do that; maybe we\n\n         19   ought to treat resource adequacy issues differently because\n\n         20   we already have the 205 rights.  That's something we could\n\n         21   consider, I suppose.\n\n         22              I want to be clear about a couple things, though. \n\n         23   First, Commissioner Rosner, you referred to, perhaps,\n\n         24   flavors of the 205.  Of course, all those things could be\n\n         25   discussed.\n\n\n\n\n\n                                                                      245\n\n\n\n          1              I want to be clear, though, should PJM -- should\n\n          2   the schedule one and schedule sixes, and so forth, be\n\n          3   removed, as I mentioned before, and 205 rights be vested in\n\n          4   PJM, that does not mean that PJM would abandon the\n\n          5   stakeholder processes.  We see tremendous value in the\n\n          6   stakeholder processes.  I've invested too much of my life in\n\n          7   these processes.  (Laughs.)    (Laughter.)\n\n          8              COMMISSIONER ROSNER:  Just to be clear, me too.\n\n          9              MR. ANDERS:  Yeah.\n\n         10              COMMISSIONER ROSNER:  The point I was making was\n\n         11   are there dials we can turn, to drive more consensus, within\n\n         12   the stakeholder process.\n\n         13              MR. ANDERS:  Right.\n\n         14              COMMISSIONER ROSNER:  What people have described. \n\n         15   You know, they already have tools.  They could do a 206,\n\n         16   they could do a -- you know, I get that.  But also, what if\n\n         17   the sector, what if it required a 50 percent threshold to\n\n         18   agree instead of the current...\n\n         19              MR. ANDERS:  That's something we could absolutely\n\n         20   explore.\n\n         21              COMMISSIONER ROSNER:  Yeah-yeah.\n\n         22              MR. ANDERS:  Yeah.\n\n         23              COMMISSIONER ROSNER:  Or what if you don't reach\n\n         24   agreement in six months, then you get access to make a 205,\n\n         25   or if a stakeholder vote fails and it's something that is,\n\n\n\n\n\n                                                                      246\n\n\n\n          1   you know, in a category of things that is of most\n\n          2   importance.  You know, but I just want to be clear.\n\n          3              I think the stakeholder process is incredibly\n\n          4   important.  And I was looking through the flow chart of all\n\n          5   the task forces and, you know, some of them are on things\n\n          6   that are, like, effective load carrying capability, things\n\n          7   that we need expertise on.\n\n          8              MR. ANDERS:  Uh-huh.\n\n          9              COMMISSIONER ROSNER:  And so, I'm not saying\n\n         10   anything about denigrating the stakeholder process, at all. \n\n         11   I think it's essential.\n\n         12              MR. ANDERS:  Yeah.\n\n         13              COMMISSIONER ROSNER:  What we need are decisions.\n\n         14              CHAIRMAN SWETT:  I thought you said you wanted to\n\n         15   bring it down.\n\n         16              (Laughter.)\n\n         17              CHAIRMAN SWETT:  Just kidding.  Just making sure\n\n         18   he's awake.\n\n         19              COMMISSIONER ROSNER:  Yeah.\n\n         20              COMMISSIONER LECERTE:  And I think all five\n\n         21   commissioners agree that having a robust stakeholder process\n\n         22   is essential to positive outcome.\n\n         23              MR. ANDERS:  Yeah.\n\n         24              COMMISSIONER LECERTE:  But we have to have the\n\n         25   positive outcomes, and that's what we're not getting.\n\n\n\n\n\n                                                                      247\n\n\n\n          1              (Laughter.)\n\n          2              MR. ANDERS:  And not having the ability to, you\n\n          3   know, call that question, after a certain point in time I\n\n          4   think inhibits us from being able to do that.\n\n          5              Now, I hear folks saying \"Well, you can always\n\n          6   file under Section 206.\"  Of course we can.  But there are\n\n          7   implications to that as well.  You don't have the 60-day\n\n          8   clock.  The thresholds for approval or acceptance by the\n\n          9   Commission are different, and so forth.  So, that just\n\n         10   changes the whole posture of the proceeding.\n\n         11              CHAIRMAN SWETT:  You can always ask for a clock,\n\n         12   in your filing.\n\n         13              MR. ANDERS:  True.\n\n         14              CHAIRMAN SWETT:  Susan?\n\n         15              MS. BRUCE:  You are living in a stakeholder\n\n         16   process.  Because I initially put my tent up when we were --\n\n         17    that the challenge was about talking about the nominating\n\n         18   committee.  And the conversation has moved on to very\n\n         19   interesting places, but that was where my tent went up for.\n\n         20              Because I am currently on the nominating\n\n         21   committee, and I am reluctant to say that out loud.\n\n         22              (Laughter.)\n\n         23              MS. BRUCE:  But I do feel an obligation to PJM's\n\n         24   stakeholder process, to be transparent about it.\n\n         25              And the question, I think, Commissioner LaCerte,\n\n\n\n\n\n                                                                      248\n\n\n\n          1   that you asked around was whether or not support for the\n\n          2   states' involvement, and speaking as Susan Bruce and as\n\n          3   counsel, not as a PJM ICC position, I certainly -- I think\n\n          4   that there is value in having, if states want to be part of\n\n          5   the nominating committee, I think that there is value in\n\n          6   terms of having the buy-in, to understand who is on the\n\n          7   board and who is making the decisions on the board.\n\n          8              I will say that, having served on the nominating\n\n          9   committee several times, it is an exercise where everyone\n\n         10   does come at it with the vantage point of being what's in\n\n         11   the best interest of PJM.  It's something that you do not\n\n         12   talk about with your colleagues.  My clients don't know\n\n         13   what's going on.  No one knows.  It's really put the \"What\n\n         14   is in the best interest of PJM?  What does PJM need right\n\n         15   now?\"  \n\n         16              And they're really, sometimes, very hard\n\n         17   conversations, but it's always productive and respectful\n\n         18   conversations, and certainly I think the states have a role\n\n         19   there, especially if PJM is becoming more of an integrated\n\n         20   grid, if you think about the 21st century grid being very\n\n         21   different than it was 30 years ago.  So, I think that there\n\n         22   is value in thinking about that.\n\n         23              I think there's probably also values in thinking\n\n         24   about what -- you know, we have struggled in terms of\n\n         25   thinking about honoring the independence, making sure\n\n\n\n\n\n                                                                      249\n\n\n\n          1   there's no conflicts of interest.  There's a two year stay\n\n          2   out provision for candidates.\n\n          3              PJM is the largest marketplace.  And so, people\n\n          4   that have expertise in the energy space, they touch in some\n\n          5   respects PJM.  So, that limits the pool.  But it's really\n\n          6   important to think about making sure that the board members\n\n          7   don't have even the appearance that they're making financial\n\n          8   choices personally, as opposed to what's in the best\n\n          9   interest of PJM.\n\n         10              Thinking about pension plans, things like that. \n\n         11   Those are all things that become issues of consideration.\n\n         12              I think there's probably things to think through\n\n         13   there.\n\n         14              CHAIRMAN SWETT:  Let me stop you there.\n\n         15              MS. BRUCE:  Uh-huh?\n\n         16              CHAIRMAN SWETT:  How should we change that\n\n         17   conflict rule?  Because several people have brought it up.\n\n         18              MS. BRUCE:  I don't know what the right answer\n\n         19   is, because I think that having a board that is above\n\n         20   reproach is -- it's 67 million people and all of the\n\n         21   businesses in it, you know, having it be something that has\n\n         22   -- everyone can have confidence in, is really important.\n\n         23              So, whether or not it's, you know, two years is\n\n         24   too long, you know, one year, it becomes a balancing of the\n\n         25   interests, as well.  Because, you know, one of the reasons\n\n\n\n\n\n                                                                      250\n\n\n\n          1   why there's not too many people in the footprint, and the\n\n          2   one that we have had on the longest, she was not within the\n\n          3   industry.\n\n          4              So, I think that that, you know, was two years\n\n          5   too long?  Is one year enough, to make sure people feel\n\n          6   comfortable that they're not still thinking that they --\n\n          7   everyone sort of has a mindset.  I represent industrial\n\n          8   customers.  I've represented industrials for 30 years.  I\n\n          9   know how other segments of the market think, but I know that\n\n         10   I come at things with my own view of the world.\n\n         11              So, I think that that element comes into the\n\n         12   nominating committee process.\n\n         13              COMMISSIONER SEE:  I'm curious about that.  We\n\n         14   use one year, in government, and the interests aren't\n\n         15   exactly the same.  But, you know, that largely works in a\n\n         16   similar contexts.\n\n         17              MS. BRUCE:  Uh-huh.  Uh-huh.\n\n         18              COMMISSIONER SEE:  So that's one option.\n\n         19              But, from your perspective -- and others may have\n\n         20   thoughts about that too -- does changing, from two to one,\n\n         21   meaningfully increase the pool?  Like, how much value would\n\n         22   that give us?\n\n         23              MS. BRUCE:  I think it would increase the pool.\n\n         24              COMMISSIONER SEE:  Yeah, uh-huh.\n\n         25              MS. BRUCE:  I can't say anything about anything,\n\n\n\n\n\n                                                                      251\n\n\n\n          1   but I do think --\n\n          2              (Laughter.)\n\n          3              MS. BRUCE:  -- that it would be helpful.  It may\n\n          4   make the pool slightly larger.\n\n          5              COMMISSIONER SEE:  I thought you might say that. \n\n          6   I agree with that.\n\n          7              MS. BRUCE:  The other thing I would just throw in\n\n          8   there is, if we're talking about boards and we're talking\n\n          9   about the stakeholder compromises, if you're doing it well,\n\n         10   you're pulling things from a whole bunch of different areas,\n\n         11   and I know Section 205 rights have been discussed.  But, as\n\n         12   that's been discussed, I think thinking about who is on the\n\n         13   board, is it useful to have people that have experienced\n\n         14   buying power, whether or not it's as a very large data\n\n         15   center, or as an industrial customer, someone that has that\n\n         16   knowing of what it's like to be on the other side of a\n\n         17   change in law, for example, for a retail contract.  Those\n\n         18   types of skill sets might be something to think about, in\n\n         19   terms of expanding the qualifications for the board.\n\n         20              Thinking about the OA changes, in terms of\n\n         21   thinking about public interest.  But I think whether or not\n\n         22   requiring cost/benefit analysis, sensitivity analysis, of\n\n         23   cost impacts for customers, and having that be de rigueur\n\n         24   and not something that you have to ask for repeatedly.  So,\n\n         25   there's things like that, I think, that are useful to put\n\n\n\n\n\n                                                                      252\n\n\n\n          1   into that soup that's being made right now.\n\n          2              So, thanks.\n\n          3              CHAIRMAN SWETT:  Dr. Bowring?\n\n          4              DR. BOWRING:  Thanks.  So, there's been lots of\n\n          5   conversation about speed.  I trust it's obvious to everyone\n\n          6   that speed to a bad decision is not the right idea.  So, no,\n\n          7   but it hasn't been said, and speed has been emphasized over\n\n          8   and over again.  So, speed doesn't get you anywhere, if you\n\n          9   get to the wrong place, and I think that's what the 205\n\n         10   filing rights are about.  It's speed, but speed to a bad\n\n         11   decision.\n\n         12              There's no reason -- I agree with you -- sorry\n\n         13   for agreeing with you -- the representative of\n\n         14   Constellation.  The 205 thing is a red herring.  That's not\n\n         15   what the issue is.  And really, as David said, it changes\n\n         16   the standards.  It lowers the standards.  There's no reason\n\n         17   for PJM to have 205 rights over the tariff.  \n\n         18              Having it -- no one has a veto.  PJM can file a\n\n         19   206 any time they want, with the right standard.  It has to\n\n         20   be just and reasonable, and they have to show the existing\n\n         21   tariff is not just and reasonable.  That's a perfectly fine\n\n         22   standard.  That's the Commission's standard.  There's\n\n         23   absolutely no reason to change the 205.\n\n         24              But it all comes back to none of that makes any\n\n         25   difference.  Speed, decisiveness.  None of it makes any\n\n\n\n\n\n                                                                      253\n\n\n\n          1   difference unless you address these two fundamental issues\n\n          2   that I raised at the beginning.\n\n          3              And other people have said it.  One is about the\n\n          4   board independence, and what does that mean.  It's both\n\n          5   nominating and being able to be voted out.  And I don't care\n\n          6   if you think that people shouldn't react to that fact.  They\n\n          7   do react to it.  It is a fact.  It's a reality, and you\n\n          8   can't avoid it and it needs to be addressed.\n\n          9              The same thing is true for the charge of the\n\n         10   staff.  The staff should be charged with acting in the\n\n         11   public interest.  Unless you address both those things, all\n\n         12   the speed and decisiveness is not going to get you anywhere.\n\n         13              And last but not least, the members are not to\n\n         14   blame to bogging down the stakeholder process.  \n\n         15              And, I'm sorry, actually one other statement. \n\n         16   (Laughs.)\n\n         17              (Laughter.)\n\n         18              DR. BOWRING:  Members are not customers.  As the\n\n         19   public advocate said.  Members are not customers.  PJM\n\n         20   should be responsive to its customers.  And it frequently\n\n         21   confuses those two things and calls its members its\n\n         22   customers.  Its members are not its customers.\n\n         23              Thank you.\n\n         24              CHAIRMAN SWETT:  Who is to be blamed for bogging\n\n         25   down the stakeholder process, then?\n\n\n\n\n\n                                                                      254\n\n\n\n          1              DR. BOWRING:  I think, significantly, PJM.  And\n\n          2   it's because -- it's the lack of leadership, that other\n\n          3   people have pointed to.  And it all comes back, again, to\n\n          4   the same thing I said.  If the board were guaranteed its\n\n          5   independence, if the staff were charged with the public\n\n          6   interest, that would make the process work more smoothly.\n\n          7              And look, I mean, I can point to lots of examples\n\n          8   of what bogs it down.  We don't need to get into all the\n\n          9   details.  But, I mean, it's a shared responsibility, to be\n\n         10   fair.\n\n         11              But leadership, structuring the process better,\n\n         12   would help.\n\n         13              And I'm a firm believer in all the subcommittees,\n\n         14   by the way.  So...\n\n         15              (Laughter.)\n\n         16              DR. BOWRING:  Thanks.\n\n         17              CHAIRMAN SWETT:  I think Jodi's was next.\n\n         18              MS. MOSKOWITZ:  Just two points.  On the board\n\n         19   composition, I do think, you know, it's so critical that the\n\n         20   members have confidence in the board and in its\n\n         21   capabilities.  I know, in New Jersey, we have rules that\n\n         22   require our board of directors to have a certain percentage\n\n         23   of board members who either reside in the state or have\n\n         24   significant ties to the state.\n\n         25              So, one thing, and I think Commissioner Rosner,\n\n\n\n\n\n                                                                      255\n\n\n\n          1   you mentioned this, that, you know, thinking about there\n\n          2   probably should be requirements, to tie more board members -\n\n          3   - to make sure that they have connections to the PJM region. \n\n          4   So that's one -- one point I would make.\n\n          5              Another, broader, point to kind of -- to some of\n\n          6   the points that Dave has been making, about culture -- and I\n\n          7   can hear some of this on the panel here.  I think it's very\n\n          8   important.  I don't think we're going to get to the best\n\n          9   outcomes where there's a lack of clarity of\n\n         10   responsibilities.  I think we have suffered from that for a\n\n         11   while.\n\n         12              You know, when I think about what PJM is and what\n\n         13   they're not, PJM is a public utility, just like PSE and G\n\n         14   is.  Fully regulated by FERC, has to make filings at FERC,\n\n         15   show that the filings are just and reasonable.  PJM is not -\n\n         16   - they're not a regulatory agency.  They're not a rate\n\n         17   regulator.  They are not a siting or permitting agency.\n\n         18              And I think that sometimes -- and look, maybe\n\n         19   this gets to PJM taking better control of these processes --\n\n         20    I would also add they are not an integrated resource\n\n         21   planner, which is where, I think, we've had a lot of lack of\n\n         22   clarity on resource adequacy, because the states do have\n\n         23   responsibility for that.\n\n         24              So, I think that lack of clarity on respective\n\n         25   responsibilities and accountabilities has really hurt PJM,\n\n\n\n\n\n                                                                      256\n\n\n\n          1   and continues to hurt PJM.  And I think until we have more\n\n          2   of that, we're not going to get to the outcomes that we need\n\n          3   in an expeditious and effective way.\n\n          4              CHAIRMAN SWETT:  Okay, we're going to -- I'm\n\n          5   going to execute my chairman's privilege one more time.  But\n\n          6   first we'll let Jameson make his comment, and then we're\n\n          7   going to take another vote.\n\n          8              (Laughter.)\n\n          9              MR. TWEEDIE:  Thank you.  So, just on the\n\n         10   stakeholder process, why I think it is so important that the\n\n         11   public interest, affordability, cost, be part of that\n\n         12   process, is because we came here and we heard the opening\n\n         13   statements this morning.  The massive growth in large loads\n\n         14   is creating an immense problem in this region especially,\n\n         15   but across the country, and that is going to have\n\n         16   consequences for consumers.\n\n         17              And we heard -- we have had the White House and\n\n         18   all the governors reach a statement of principles, and we've\n\n         19   had the hyper scalers reach a pledge, a rate payer\n\n         20   protection pledge, with the White House.  And yet, we are in\n\n         21   a stakeholder process that is failing those goals, and for\n\n         22   which the states cannot succeed in allocating costs not to\n\n         23   their existing customers, if PJM doesn't succeed in its\n\n         24   part.\n\n         25              So, we already have an estimated 30 billion in\n\n\n\n\n\n                                                                      257\n\n\n\n          1   capacity costs, that are getting shared out to consumers\n\n          2   across the region.  And those are the direct result -- thank\n\n          3   you, Dr. Bowring, for this analysis -- of large loads. \n\n          4   Right?\n\n          5              And we have proposals right now that are, in the\n\n          6   view of consumer advocates, not sufficient and, in fact,\n\n          7   will prevent the states from being able to properly allocate\n\n          8   costs, because costs from data centers and this load growth\n\n          9   will be included in things that the states can't allocate\n\n         10   away.\n\n         11              And so, what the states need and consumers need\n\n         12   is a partner at PJM that will help them effectuate what the\n\n         13   rate payer protection pledge and what the statement of\n\n         14   principles promise, that we are all striving to do.\n\n         15              And if consideration of costs and the public\n\n         16   interest, in consumers, are not part of PJM's decision\n\n         17   making and are, in fact, often rejected as part of the\n\n         18   stakeholder process, then we are never going to get to\n\n         19   outcomes that achieve the purposes that we all heard this\n\n         20   morning -- and I think we all agree with -- are the basic\n\n         21   premises that we should be trying to strive for.\n\n         22              Thank you.\n\n         23              CHAIRMAN SWETT:  Thank you.  Well said.\n\n         24              So, we're going to go down the line and take a\n\n         25   yes/no vote.  Do you, or do you not, support PJM moving\n\n\n\n\n\n                                                                      258\n\n\n\n          1   schedules one, two, and six -- that's the energy market and\n\n          2   RTEP protocol -- from the operating agreement to the\n\n          3   tariff, per David's suggestion?\n\n          4              So, if you support David's suggestion, vote yes. \n\n          5   And I'll start with David because, I mean, I've got to give\n\n          6   you something.\n\n          7              MR. ANDERS:  I don't normally get a vote in the\n\n          8   process, but thank you.\n\n          9              (Laughter.)\n\n         10              MR. ANDERS:  So, I vote yes.\n\n         11              MR. THOMAS:  Because I don't want to be tied up\n\n         12   in court for years when there are so many other things we\n\n         13   need to address, no.\n\n         14              CHAIRMAN SWETT:  Okay.\n\n         15              MS. MOSKOWITZ:  Yes, with enhanced accountability\n\n         16   for PJM.  But yes.\n\n         17              MR. TWEEDIE:  I think any changes like that have\n\n         18   to come with changes that ensure accountability,\n\n         19   transparency, and public interest in PJM.\n\n         20              CHAIRMAN SWETT:  So, is that a yes or a no?\n\n         21              MR. TWEEDIE:  Neither.\n\n         22              CHAIRMAN SWETT:  Neither!  Okay, you're\n\n         23   abstaining.  Interesting.\n\n         24              MR. EMNETT:  No, we need leadership using the\n\n         25   tools that are already available.\n\n\n\n\n\n                                                                      259\n\n\n\n          1              CHAIRMAN SWETT:  No, okay.  Brian?\n\n          2              MR. GEORGE:  Yes, with the recognition, to\n\n          3   Mason's point -- right? -- that it doesn't really address\n\n          4   the problem that's in front of us right now.\n\n          5              MS. BRUCE:  I have to be no for now, because it\n\n          6   doesn't get anything built.\n\n          7              DR. BOWRING:  No, because it doesn't even begin\n\n          8   to address the question.\n\n          9              CHAIRMAN SWETT:  Okay.  Thank you all very much\n\n         10   for that.\n\n         11              COMMISSIONER LACERTE:  I wanted to open it up to\n\n         12   Mason real quick, since we have a few minutes left, and Jodi\n\n         13   answered my question, but we didn't get to Mason before.\n\n         14              So, Mason, you've been in my office many times,\n\n         15   with Constellation, which I greatly appreciate.  We've had\n\n         16   these discussions and I've sent you back to the drawing\n\n         17   board and told you to come back and look at things\n\n         18   differently, which I greatly appreciate you going through\n\n         19   the exercise.\n\n         20              But now that you've heard me ask it many times\n\n         21   over, I want to give you the opportunity to tell me you see\n\n         22   things my way.\n\n         23              (Laughter.)\n\n         24              COMMISSIONER LACERTE:  So, essentially, like, are\n\n         25   you a member of the sous chefs union or not?\n\n\n\n\n\n                                                                      260\n\n\n\n          1              (Laughter.)\n\n          2              MR. EMNETT:  PJM is the chef.  It has different\n\n          3   tools in is tool box.  Right?  And we don't believe that\n\n          4   those tools need to be changed; we believe they should be\n\n          5   used.\n\n          6              COMMISSIONER LACERTE:  I appreciate that answer. \n\n          7   I also say we are in a time and place in history, at FERC,\n\n          8   and with PJM, that we cannot simply lean back and trust that\n\n          9   these things will occur, with PJM not receiving reforms.\n\n         10              I think just hoping that things will be different\n\n         11   is woefully insufficient in this environment, and we need to\n\n         12   undertake initiatives which drive that change, from our\n\n         13   chairs.\n\n         14              MR. EMNETT:  If I could, what I suggest\n\n         15   consideration of, PJM, the things that we are spending most\n\n         16   of our time on, and the states and federal policymakers are\n\n         17   the most concerned about are the resource adequacy planning\n\n         18   and infrastructure issues, over which PJM has 205 rights.\n\n         19              And so, changing 205 rights over the thing we are\n\n         20   not fighting about does not solve the issue, and in fact\n\n         21   might reinforce that the approach to using 205 rights, to\n\n         22   date, is sufficient, which we don't believe that it is.  We\n\n         23   should not use a critical infrastructure fast path process,\n\n         24   that has \"critical\" in the title, to spend a good chunk of\n\n         25   last year on developing solutions to meeting large load, to\n\n\n\n\n\n                                                                      261\n\n\n\n          1   end up, at the end of that process, starting another\n\n          2   critical issues fast path, with the word \"critical\" in it,\n\n          3   to get to solutions that now we hear are coming, which are\n\n          4   great -- right?  But we needed those previously.\n\n          5              That is about leadership and execution of\n\n          6   responsibilities, and I appreciate that these challenges are\n\n          7   difficult, but that's what we are all called upon to do. \n\n          8   Call the balls and strikes, move things forward.  If there\n\n          9   isn't membership agreement on energy market issues, well\n\n         10   then can move under 205, but those are not the\n\n         11   disagreements that we have today.\n\n         12              The one issue that is pointed to as an example,\n\n         13   the reserve certainty task force.  So that is already ORDC\n\n         14   2.0. \n\n         15              We already lived through that process of multiple\n\n         16   years working through ORDC reforms, which made their way to\n\n         17   the Commission, and were approved.  They ended up facing\n\n         18   legal troubles or remand -- you know, a whole saga there. \n\n         19   Right?  \n\n         20              But PJM had the ability to move that issue, and\n\n         21   PJM could have moved on those issues in their rebirth.  Much\n\n         22   easier.  It did not need to languish for three years, in the\n\n         23   stakeholder process.  It could have been moved forward.\n\n         24              Yes, there was a lot of education that was\n\n         25   needed.  But people can get the resources to come to the\n\n\n\n\n\n                                                                      262\n\n\n\n          1   table and negotiate those issues, and you move forward.\n\n          2              That's the only thing that has been pointed to,\n\n          3   on 205 versus 206.  Everything that we're spending our time\n\n          4   on, there are already 205 rights over.  So we just don't see\n\n          5   the solution that's being offered as actually fixing\n\n          6   anything.\n\n          7              COMMISSIONER LACERTE:  So, it's your opinion that\n\n          8   PJM simply lacks the will to make these decisions?\n\n          9              DR. EMNETT:  We haven't seen the evidence of\n\n         10   that.\n\n         11              COMMISSIONER LACERTE:  Dave?\n\n         12              MR. ANDERS:  I'll just add a couple of other data\n\n         13   points to the RCSTF, the reserve certainty.  Years before\n\n         14   that, it was the Energy Market Uplift Senior Task Force. \n\n         15   Then it was the Energy Market Price Formation Senior Task\n\n         16   Force.  All of which languished, all of which were energy\n\n         17   market issues in schedule one.\n\n         18              COMMISSIONER LECERTE:  Look, I think that we've\n\n         19   all been a little frustrated by many things, in this room\n\n         20   today.  And, as we've stated over the course of several\n\n         21   years.\n\n         22              First and foremost is we don't get to see the\n\n         23   stakeholder votes, in this process.  And very limited people\n\n         24   get to see those stakeholder votes.  I still don't know who\n\n         25   gets to see the stakeholder votes, in this process.\n\n\n\n\n\n                                                                      263\n\n\n\n          1              So, I think it's important that we all get to see\n\n          2   these opinions and who holds them, and where those opinions\n\n          3   fall in line.  I think we have a list of good governance\n\n          4   reforms that are on the table.\n\n          5              So, I think what we should do, Madam Chairman, is\n\n          6   I think we should attach a ballot, to be sent out to all the\n\n          7   PJM stakeholders, to put them on the record, say \"Where do\n\n          8   we stand on these issues?  Do we stand in favor of good\n\n          9   governance reforms where we see them?  Are we opposed?\"\n\n         10              Because I do think the public believes a lot of\n\n         11   these stakeholders vote in line with their interests.  I\n\n         12   think that's a commonality.  And I think that's one thing\n\n         13   that we expect the process to flesh out in that direction. \n\n         14   And it's just not acceptable anymore.\n\n         15              I think that some of these proposals will drive\n\n         16   change, in a positive manner.  Like Dr. Bowring said, we\n\n         17   don't want to go in the wrong direction, but I think a lot\n\n         18   of these things are very simplistic in nature.  Cooperating\n\n         19   with the states.  A better use of our time and priorities. \n\n         20   Prioritizing our effort.\n\n         21              So, I think it would be helpful for us to attach\n\n         22   a ballot to each individual PJM stakeholder, to put them on\n\n         23   the record as to where they stand with these issues.\n\n         24              CHAIRMAN SWETT:  Well, thank you all very much\n\n         25   for your time and participation today.  This has been very\n\n\n\n\n\n                                                                      264\n\n\n\n          1   engaging.\n\n          2              It's very clear that there are a few frontrunner\n\n          3   issues.  I agree with you there.\n\n          4              So, we're going to deliver some closing remarks\n\n          5   now.  I'll give my colleagues an opportunity.  Well, you've\n\n          6   got five minutes, right Judy?\n\n          7              COMMISSIONER CHANG:  No.  Less than five minutes.\n\n          8              CHAIRMAN SWETT:  Okay, go ahead.\n\n          9              COMMISSIONER CHANG:  I just want to say thank\n\n         10   you, and thank you, thank you, thank you, for everyone's\n\n         11   participation.  But I also wanted to summarize a few things\n\n         12   that are -- I think, everybody agreed.  And I just want to,\n\n         13   maybe, have you all take some notes and see -- maybe you can\n\n         14   respond in writing afterwards.\n\n         15              One is that -- I have in my notes sort of\n\n         16   categories.  States, and then PJM management, and PJM board.\n\n         17              For states, representation on board nomination\n\n         18   committee, I feel like there was some, more or less,\n\n         19   agreement.  Active engagement, PJM and PJM board, on\n\n         20   strategy, or goals, or some sort of thing like that. \n\n         21              Either one or two organization of states that\n\n         22   will -- that might have a jump ball ability with the PJM, so\n\n         23   that they have some leverage in, like, big ticket decisions.\n\n         24              For PJM management, I think I just want to\n\n         25   reiterate, prioritize goals, work streams, set deadlines for\n\n\n\n\n\n                                                                      265\n\n\n\n          1   stakeholders.  And I put a big question mark, because\n\n          2   listening to this panel, like, whether or not the 205 rights\n\n          3   need to be shifted a little bit or not, or whether the\n\n          4   existing 205 rights on resource adequacy is adequate for the\n\n          5   current challenge, I put a question mark on that.  But I\n\n          6   think that was raised a lot.\n\n          7              And for PJM board, I heard a lot about\n\n          8   independence.  The word \"independence\" is overused, so we\n\n          9   probably need to define what -- independence from what.\n\n         10              I also heard \"skill sets\" and residency.  But\n\n         11   probably more like skill sets, or just qualifications in\n\n         12   general.  I think that's something worth examining.\n\n         13              And, board decisions transparency.  I think we\n\n         14   heard that quite a bit, and whether it's board transparency\n\n         15   or is voting member transparency, but there seems to be some\n\n         16   accountability about who is agreeing to this and who is\n\n         17   making these decisions, and how do we arrive at the final\n\n         18   outcome.\n\n         19              And then, need to get more empowerment for the\n\n         20   management.  So that's, I think, between the board and the\n\n         21   management.\n\n         22              And then, public interest in both board and\n\n         23   management, probably.  I think that's what we heard from\n\n         24   states and definitely Dr. Bowring.  I think that's worth\n\n         25   talking about.\n\n\n\n\n\n                                                                      266\n\n\n\n          1              And then, I put a question mark on ex parte\n\n          2   rules, just accessibility of the board members from\n\n          3   stakeholders.  I put a question mark.  It was raised and\n\n          4   written up, but I put a question mark, because I don't know\n\n          5   if we have a consensus on that.\n\n          6              But I just want to put that out there as a straw\n\n          7   man, so that you all can think about it in terms of \"Is\n\n          8   that a package that, or parts of a package that everyone can\n\n          9   agree to as a solution?\"\n\n         10              So, with that, thank you very, very much.  This\n\n         11   was such an engaging day, and thank you, Chair, for your\n\n         12   leadership to make this happen.\n\n         13              CHAIRMAN SWETT:  Thank you for that summary. \n\n         14   That was helpful.  And safe travels.\n\n         15              So, let's -- I just want to be unmistakably clear\n\n         16   about the path forward today.  Governance is not glamorous. \n\n         17   But you all did a great job of engaging us, for a very long\n\n         18   amount of time.\n\n         19              So, this conference was not an academic exercise. \n\n         20   We're on the beginning of a path, and the end of it is going\n\n         21   to be reform.  How we get there is really up to you and the\n\n         22   stakeholders in the market.\n\n         23              So, here is what we're going to do.  We're going\n\n         24   to issue a post-conference notice seeking comments on the\n\n         25   issues that were discussed today, and per Commissioner\n\n\n\n\n\n                                                                      267\n\n\n\n          1   LaCerte's suggestion, that notice is going to include a list\n\n          2   of questions for stakeholders, that are designed to gather\n\n          3   robust and unambiguous answers to the core issues affecting\n\n          4   PJM's governance model and stakeholder process.\n\n          5              This is your opportunity to be heard, and I\n\n          6   expect full engagement.  We want clear positions and a\n\n          7   willingness to move toward solutions.  And if you do not\n\n          8   respond, and you are a stakeholder, then we are going to\n\n          9   assume that you do not care.  That is a rebuttal presumption\n\n         10   that you have the opportunity to overturn.\n\n         11              After we've received these post-conference\n\n         12   comments, we are going to direct the Commission's dispute\n\n         13   resolution service to convene a forum, in September.  It\n\n         14   will be rigorously structured and time bound, so that we can\n\n         15   finalize a package of solutions.\n\n         16              So, 99 years ago, in 1927, September, PJM was\n\n         17   formed, and perhaps this September is when PJM can be saved. \n\n         18   But I want you all to hear this plainly.  If the\n\n         19   stakeholders cannot reach a set of credible, meaningful,\n\n         20   reforms, or an agreement in principle, by the end of\n\n         21   September, then this Commission is not going to hesitate to\n\n         22   use the full extent of our legal authority to implement\n\n         23   reforms necessary to restore confidence in PJM's governance.\n\n         24              But I am confident that the people in this room,\n\n         25   and the ones who are not here, can work together to reach\n\n\n\n\n\n                                                                      268\n\n\n\n          1   reforms, so that PJM can be on a path toward success, and\n\n          2   hopefully without Commission intervention.\n\n          3              Finally, I really, sincerely, want to thank\n\n          4   Commission staff, who made this conference possible.  You\n\n          5   did a fantastic job moderating, and so did your predecessor,\n\n          6   and a lot of hard work went into this.  Especially Kevin, in\n\n          7   my office, who was integral to putting this together for us. \n\n          8   And I hope he doesn't regret working for me, but I'm glad\n\n          9   you're still here.\n\n         10              And thank you all to the panelists who\n\n         11   participated today, and thank you for enduring our grilling,\n\n         12   and your contributions were very invaluable, and we have a\n\n         13   lot to walk away with today and a lot to think about.  So,\n\n         14   thank you all.\n\n         15              So, Commissioner Rosner?\n\n         16              COMMISSIONER ROSNER:  Thank you, Chairman.  Thank\n\n         17   you to all the panelists and to the Commission staff, for\n\n         18   putting this together.  I know it's non-trivial to come\n\n         19   spend a day in Washington with FERC, and I really appreciate\n\n         20   it.  Not just in person but your statements.\n\n         21              I want to come back, briefly, to just why we're\n\n         22   here.  For me, the highest priority issue is that we're\n\n         23   6,800 megawatts short, two years from now.  And that puts us\n\n         24   below the requirement that we have to have a reliable grid.\n\n         25              And, for me, that's quite scary.  When you think\n\n\n\n\n\n                                                                      269\n\n\n\n          1   -- you heard from Peter Lake earlier, in Texas, during\n\n          2   winter storm Uri, their reliability problem cost 246 people\n\n          3   their lives.  And when you think about a region like PJM,\n\n          4   where we have equally hot weather -- in fact, the hottest\n\n          5   place in the country, two weeks ago, I believe, was here, in\n\n          6   Washington, D.C.\n\n          7              And so, if we move forward and we don't have\n\n          8   enough resources to be reliable, people could die, and that\n\n          9   is very serious business, and it's a really solemn burden\n\n         10   that we need to solve.\n\n         11              And so, I hear you all on the frustrations with\n\n         12   the leadership, with the stakeholder process.  There's a\n\n         13   variety of different opinions on where we need to go.\n\n         14              The way I see it is that the board has not acted\n\n         15   on this statement of principles regarding PJM, that the\n\n         16   governors agreed to, along with the White House.  And that's\n\n         17   because you all don't agree on how to close the 6,800\n\n         18   megawatt resource adequacy gap, what the best way to do that\n\n         19   is.\n\n         20              And it's not that any particular stakeholder is\n\n         21   wrong about the way to do it.  I think the reality is that\n\n         22   there's a variety of different ideas for how to do that, and\n\n         23   we've talked about many of them, both in writing and in\n\n         24   person.\n\n         25              But, the reality is that the board now does need\n\n\n\n\n\n                                                                      270\n\n\n\n          1   to decide, and they're going to do that.  And what I see the\n\n          2   value of this conference is, is that we had a really hard\n\n          3   time reaching agreement on that issue.  It's a very\n\n          4   complicated issue.  And this is a very important moment for\n\n          5   us all to think, again, about if our stakeholder process\n\n          6   worked better, are there things that we learned from this\n\n          7   last go-around that might make it work better in the\n\n          8   future?\n\n          9              Because, there will be more critical issues for\n\n         10   us to work on then.  And so that's the takeaway.\n\n         11              I think there's a lot that's been changing, in\n\n         12   the energy system recently.  There's a lot of new demand. \n\n         13   It's demand that we just haven't seen for a generation.\n\n         14              And part of the frustration that I heard from\n\n         15   some stakeholders is oh, you know, a governor and states\n\n         16   filed a complaint that limited the ability of the RPM to\n\n         17   deliver the capacity that it was designed to deliver,\n\n         18   because of the price cap, and there's been a big debate\n\n         19   about that.\n\n         20              And the reality is just that things are changing\n\n         21   very fast.  The states, they do the retail rate allocation. \n\n         22   I know that's a very critical -- affordability is a critical\n\n         23   issue.  It's a critical political issue.\n\n         24              You know, we spent a day with the US Senate.  We\n\n         25   spent another day with the US House.  And this is just is a\n\n\n\n\n\n                                                                      271\n\n\n\n          1   political issue.  And so that's why we've heard so much\n\n          2   about governance.  That's why the state role is so\n\n          3   important.  That's why we need our state regulators working\n\n          4   with us, to do the cost allocation, to do the curtailment\n\n          5   priority, to make sure that we have the CPECNs ready for\n\n          6   things that come out of this market.\n\n          7              But I'd encourage you, as we contemplate a next\n\n          8   step here, which I really hope is not a long delay to a next\n\n          9   step, is that we really think about \"Are there things that\n\n         10   we can do that might require you to give up a little bit of\n\n         11   control, that ultimately get us better outcomes, faster\n\n         12   outcomes, that drive you to make the harder decisions with\n\n         13   each other, faster.  That's what I want to get out of this\n\n         14   conference.\n\n         15              And I think -- I feel optimistic, based on the\n\n         16   corners of the debate we've had, that there are\n\n         17   opportunities.  And I look forward to working on that with\n\n         18   you.\n\n         19              Thank you.\n\n         20              CHAIRMAN SWETT:  Commissioner See?\n\n         21              COMMISSIONER SEE:  Thank you to our panelists\n\n         22   from this panel and all the others, to FERC staff and\n\n         23   others, who worked so hard on this.  I know better than to\n\n         24   keep everybody late.  It's coming up on four o'clock, after\n\n         25   seven hours of the tech conference.  But I genuinely\n\n\n\n\n\n                                                                      272\n\n\n\n          1   appreciate everyone's engagement here.\n\n          2              And I think the energy goes down at the end of\n\n          3   the day, but that definitely didn't change the quality of\n\n          4   the ideas and the discussion.  I really appreciate that.\n\n          5              I was glad to see a number of things come out of\n\n          6   today.  I said at the beginning of the day I hope that there\n\n          7   was some low hanging fruit, and I think that we found that. \n\n          8   So, I really encourage you stakeholders in PJM, especially\n\n          9   going into this September process, to use that as a starting\n\n         10   point but not an end point.\n\n         11              There's a number of things that came out of\n\n         12   today, obviously, and \"board independence\" I think is\n\n         13   probably the phrase we heard more than any other.  So, I'm\n\n         14   also encouraged to see a lot of good discussion around those\n\n         15   areas, paired of course with accountability and also, I\n\n         16   think, figuring out who chooses the board matters.  And\n\n         17   we've heard a number of compelling conversations on that\n\n         18   point.\n\n         19              You know, from my point, I find it pretty\n\n         20   persuasive to have a meaningful role for the states, in that\n\n         21   area.  So, I really look forward to continued conversation\n\n         22   and movement in those areas.\n\n         23              You know, I also think we talk a lot about how\n\n         24   consensus is the gold standard for decision making and I\n\n         25   think that's definitely true.  But we've got to figure out\n\n\n\n\n\n                                                                      273\n\n\n\n          1   what happens when we can't get to consensus.  We just have\n\n          2   to figure out how to break through the stalemate.\n\n          3              And, to my mind, we heard a lot of traction about\n\n          4   an advisory stakeholder process.  I am not saying that that\n\n          5   is the end of the road, but I think that, as we go through\n\n          6   the rest of the process, we need to have some serious\n\n          7   conversation \"If not that, what else?\"  Because we can't\n\n          8   have a process where we are hoping for a consensus and don't\n\n          9   always get there at the time that we need, especially with\n\n         10   the urgency of the issues in front of us.\n\n         11              Another theme that came out is there's a number\n\n         12   of things that PJM can be doing now, and I think that's\n\n         13   great, and I would love to see that happen.  I think there's\n\n         14   a really helpful conversation about leadership and\n\n         15   ownership.\n\n         16              We talked a lot about setting priorities, of\n\n         17   setting work streams.  We talked a lot about getting the\n\n         18   states involved earlier, and forcing deadlines and some\n\n         19   discipline in the stakeholder process.  There's a number of\n\n         20   things that don't require formal changes, so why aren't we\n\n         21   doing them now?  Let's make sure we've moving forward in\n\n         22   that direction.\n\n         23              We have a formal process we're going to continue,\n\n         24   because we don't want to lose sight here, but that doesn't\n\n         25   mean we have to wait 'til the end of the process, to move\n\n\n\n\n\n                                                                      274\n\n\n\n          1   forward.\n\n          2              And I think, on that point, I'd also say, you\n\n          3   know, especially in reflecting on this panel here, I hear\n\n          4   from many of the stakeholders who, you know, say maybe we\n\n          5   should be focusing on other things, or this may not be the\n\n          6   right way to solve all these problems.  And I heard a couple\n\n          7   of times that the tools are in PJM's hands, we don't have to\n\n          8   make broader reforms.\n\n          9              But we're here for a reason, because we have a\n\n         10   process that hasn't been delivering the results we need. \n\n         11   So, I would really encourage you, help PJM on some of these\n\n         12   changes that you think already exist and are possible.  Make\n\n         13   them happen.  You know, help us figure out ways that we can\n\n         14   be smart about the sort of additional reforms that are\n\n         15   necessary.\n\n         16              And if you really believe we don't need to be\n\n         17   doing more, or that we're not focusing the right way, then\n\n         18   we've got to have a way to show confidence that we're going\n\n         19   to get the results we need, under the status quo.\n\n         20              I think it's probably obvious I'm revealing my\n\n         21   cards.  I'm skeptical that that's true, but we have to make\n\n         22   sure that we have concrete ideas and solutions other than\n\n         23   just \"It could be better,\" based with the tools that exist\n\n         24   today.\n\n         25              So, I really encourage everyone to continue\n\n\n\n\n\n                                                                      275\n\n\n\n          1   working collaboratively through this process.  As we all\n\n          2   said, we would love to not have to take additional actions\n\n          3   as a Commission, and I have real confidence in the people\n\n          4   and the interests that are represented in this room and\n\n          5   across PJM, to be able to make the sort of meaningful and\n\n          6   thoughtful changes we need, at the pace we need to.\n\n          7              So, please do that.  We want to be a resource to\n\n          8   help, as well.  You know, we do take seriously that we've\n\n          9   got some timing considerations in order to make sure that we\n\n         10   keep moving forward here.  But I am leaving today with a lot\n\n         11   of optimism that there are some clear paths forward, and I\n\n         12   hope that in a few months and in a year we'll be able to\n\n         13   look back and see that PJM is weathering this really\n\n         14   critical moment.  So, thank you for all of your work so far.\n\n         15              We've all got a lot ahead, but I'm optimistic\n\n         16   that we have a good outcome.  Thank you all.\n\n         17              CHAIRMAN SWETT:  Very well said.  LaCerte?\n\n         18              COMMISSIONER LACERTE:  I want to repeat my thanks\n\n         19   to all the panelists today.  It takes a lot of courage, a\n\n         20   lot of preparation, a lot of risk, to come up here and speak\n\n         21   your mind, when you're called to -- asked your opinion on\n\n         22   things that might not have been fully vetted with your own\n\n         23   folks.  I know sometimes that's uncomfortable.\n\n         24              But I want to say thank you for taking the time\n\n         25   out to talk to us, to let us know your opinions and\n\n\n\n\n\n                                                                      276\n\n\n\n          1   thoughts.\n\n          2              A couple things Dr. Bowring said that kind of\n\n          3   stuck out to me.  I know he talked about the staff at PJM. \n\n          4   And I visited PJM a couple weeks ago, and I think what he\n\n          5   means is the leadership and the board, because I've seen it\n\n          6   firsthand.  The staff at PJM is truly talented.  And these\n\n          7   are individuals that pour themselves out into their jobs for\n\n          8   the common good, and are truly aligned with the public\n\n          9   mission of keeping the lights on, in PJM.\n\n         10              So, I want to say thank you to the staff.  They\n\n         11   are kind of embroiled in this because they're caught up in\n\n         12   leadership a little bit, in these key issues with\n\n         13   leadership.  But theses are all issues that have solutions. \n\n         14   But we cannot let them figure it out on their own and hope\n\n         15   that it goes away and everything's going to be okay.\n\n         16              There's another thing Dr. Bowring said, is that\n\n         17   we don't want to run in the wrong direction, and we don't\n\n         18   want to run in the wrong direction.  Every single choice we\n\n         19   have at the table entails a certain amount of risk.  But,\n\n         20   you know, where we stand right now, where we sit, if we\n\n         21   don't change, there's a hundred percent chance of failure. \n\n         22   It is going to get worse if we don't adapt and change and\n\n         23   get better.  So, we need to be bold.\n\n         24              Another thing is, like if I am on the board and I\n\n         25   am David in the CEO's chair, I think there's a lot of\n\n\n\n\n\n                                                                      277\n\n\n\n          1   optimism out of this conference, because I take this as a\n\n          2   mandate.  Any time you have individuals at this table saying\n\n          3   you're not taking action, and you can, guess what I'm going\n\n          4   to do.  I'm going to run out and I'm going to take action,\n\n          5   and I'm going to let it rip, because that is what you're\n\n          6   being told here today.\n\n          7              So, you're getting top cover, from this table. \n\n          8   You have support from this commission.  You have all the\n\n          9   mandate in the world to take all the action you need, to\n\n         10   make sure the lights stay on in PJM, we procure the capacity\n\n         11   we need, we build out the transmission we have, and we do\n\n         12   everything we can to go to the end of the line.\n\n         13              Now, all that being said, am I going to trust\n\n         14   that that happens?  I think you guys know the answer to\n\n         15   that.\n\n         16              I think I want to see some bold action and ideas\n\n         17   out of PJM, and if we don't get that action out of PJM, we\n\n         18   will use every single legal authority within us, and maybe\n\n         19   some more, to figure that out.\n\n         20              So, that's the name of the game here.  It's a\n\n         21   mandate and it's a charge.  \n\n         22              You know, I am a little more optimistic here.  I\n\n         23   mean by nature I'm a pessimist.  So that's a good thing.\n\n         24              Again, thank you all for coming today.\n\n         25              CHAIRMAN SWETT:  All right.  Let it rip,\n\n\n\n\n\n                                                                      278\n\n\n\n          1   everybody.\n\n          2              (Laughter.)\n\n          3              (Whereupon, at 4:02 p.m., the technical\n\n          4   conference adjourned.)\n\n          5   \n\n          6   \n\n          7   \n\n          8   \n\n          9   \n\n         10   \n\n         11   \n\n         12   \n\n         13   \n\n         14   \n\n         15   \n\n         16   \n\n         17   \n\n         18   \n\n         19   \n\n         20   \n\n         21   \n\n         22   \n\n         23   \n\n         24   \n\n         25   \n\n\n\n\n\n                                                                      279\n\n\n\n          1   \n\n          2                CERTIFICATE OF OFFICIAL REPORTER\n\n          3   \n\n          4              This is to certify that the attached proceeding\n\n          5   before the FEDERAL ENERGY REGULATORY COMMISSION in the\n\n          6   Matter of:\n\n          7              Name of Proceeding:\n\n          8              PJM Governance and Stakeholder Reforms\n\n          9   \n\n         10   \n\n         11   \n\n         12   \n\n         13   \n\n         14   \n\n         15              Docket No.:  AD26-7-000\n\n         16              Place:       Washington, D.C.\n\n         17              Date:        Thursday, July 23, 2026\n\n         18   were held as herein appears, and that this is the original\n\n         19   transcript thereof for the file of the Federal Energy\n\n         20   Regulatory Commission, and is a full correct transcription\n\n         21   of the proceedings.\n\n         22   \n\n         23   \n\n         24                                  Larry Flowers\n\n         25                                  Official Reporter"}],"sections":[{"p":1,"at":0,"title":"Document text","method":"document text","endPage":1,"endAt":482625,"startToken":0,"endToken":65959}]}