{"document":{"slug":"rec-20260828-5273","title":"Motion for Leave to Answer and Answer of Northern Virginia Electric Cooperative, Inc. to the 08/18/2026 Answer et al. of Vistra Corp","issued":"2026-08-28","accession":"20260828-5273","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Northern Virginia Electric Cooperative, Inc.","kind":"answer","file":"sources/filings/text/20260828-5273_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260828-5273","tier":"record","sha256":"898ce3a94fa81b650456106625a6328bb30cd4acf46ad0d7cb0be0a9e9c2601c","pages":5,"tokens":1068,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":182,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \nDocket Nos. EL25-49-002 \n                      EL25-49-000"},{"page":2,"startToken":182,"endToken":427,"text":"2 \n \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, \nDivision of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc.\nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \n \nLarge Loads Co-Located at Generating Facilities  \n \n \nConstellation Energy Generation, LLC \n \nv.  \n \nPJM Interconnection, L.L.C. \n \n) \n) \n)\n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n \n \n \n \n \n \n \n \n \n \n \n \nAD24-11-000\n \nEL25-20-000\n                    (Consolidated) \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF  \nNORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC.  \nTO THE AUGUST 18, 2026, MOTION FOR LEAVE TO ANSWER AND ANSWER OF \nVISTRA CORP. \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or the “Commission”),1 Northern Virginia Electric \nCooperative, Inc. (“NOVEC”) respectfully submits this Motion for Leave to Answer and Answer \nto the August 18, 2026, Motion for Leave to Answer and Answer of Vistra Corp. (“Vistra”)2 filed \nin response to NOVEC’s Motion for Clarification3 of the Commission’s June 18, 2026, Order in \nthese consolidated dockets.4 \n \n1 18 C.F.R. § 385.212-213. \n2 Vistra Corp., Motion for Leave to Answer and Answer, Docket Nos. EL25-49-000, et al. (Aug. 18, 2026) \n(Accession No. 20260818-5146) (“August 18 Answer”). \n3 NOVEC, Motion for Clarification, Docket Nos. EL25-49-000, et al. (Jul. 29, 2026) (Accession No. 20260729-\n5083) (“July 29 Motion for Clarification”).  \n4 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“Order”)."},{"page":3,"startToken":427,"endToken":796,"text":"3 \n \nI. \nMOTION FOR LEAVE TO ANSWER \nNOVEC respectfully requests leave to submit this Answer. The Commission regularly \nallows answers for good cause shown, such as when the answers help ensure a more accurate and \ncomplete record, clarify the issues, or provide useful and relevant information that will assist the \nCommission in its deliberative process.5 This Answer will correct Vistra’s mischaracterizations of \nNOVEC’s pleading and provide other useful and relevant information that will assist the \nCommission in its deliberative process. As such, the Commission has good cause to accept \nNOVEC’s Answer. \nII. \nANSWER \n \n \nVistra wrongly asserts that NOVEC’s July 29 Motion for Clarification is an untimely \nrequest for rehearing because “the substance of the filing directly contests the merits” of the Order.6 \nVistra may disagree with NOVEC as to the clarity of the Order and may disagree with NOVEC’s \nopinion on aspects of the Order, but it should not inaccurately characterize the nature of NOVEC’s \npleading. NOVEC’s Motion for Clarification did not ask the Commission to set aside, in whole or \nin part, its Order. NOVEC asked the Commission to provide additional detail on cost support \ninformation and to clarify whether the Order permits an earlier section 205 proposal on a Grid \nReliance Charge than when Co-Located Load begins operating, which the Commission may or \nmay not answer.  \nNOVEC is quite aware of the difference between a request for rehearing and a motion for \nclarification. It is precisely because NOVEC is seeking clarification and not rehearing that \n \n5 See, e.g., City Utils. of Springfield, Mo. v. Sw. Power Pool, Inc., 168 FERC ¶ 61,085, P 51 (2019) (“We accept [the] \nanswers…because they have provided information that assisted us in our decision-making process.”), order on reh’g \n& clarification, 170 FERC ¶ 61,024 (2020); Morgan Stanley Capital Grp., Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 \nFERC ¶ 61,017, at 61,036 (2000) (accepting an answer as “helpful in the development of the record”). See also, \nHawtree Creek Farm Solar, LLC, 179 FERC ¶ 61,048, P 21 (2022); California Ridge Wind Energy, LLC, 175 FERC \n¶ 61,110, P 25 (2021); Pleinmont Solar 1, LLC, 173 FERC ¶ 61,126, P 18 (2020). \n6 August 18 Answer at 2."},{"page":4,"startToken":796,"endToken":990,"text":"4 \n \nNOVEC did not conform its pleading to any of the requirements set forth by Rule 713. NOVEC \nalso understands that, unlike a request for rehearing, its motion for clarification does not satisfy \nthe statutory precondition for seeking judicial review of the Order. NOVEC’s Motion for \nClarification simply is not a request for rehearing. Because the foundational premise of Vistra’s \nAnswer is simply wrong and belied by NOVEC’s pleading, the Commission should reject Vistra’s \nAnswer. Whether or not the Commission elects to provide any clarification of the Order, there is \nnothing procedurally improper about NOVEC’s request.  \nIII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the \nCommission reject Vistra’s August 18 Answer and issue an order clarifying the June 18, 2026, \nOrder as requested in NOVEC’s July 29 Motion for Clarification. \nRespectfully submitted, \n \n  //s// Alan I. Robbins \n \n \nAlan I. Robbins \nDebra D. Roby \nThomas B. Steiger III \nPeter E. Colvin \nWashington Energy Law LLP \n900 17th Street, N.W., Suite 500-A  \nWashington, D.C. 20006 \nTel: (202) 326-9313 \nEmail: arobbins@washingtonenergylaw.com \ndroby@washingtonenergylaw.com \ntsteiger@washingtonenergylaw.com \npcolvin@washingtonenergylaw.com \n \nCounsel to Northern Virginia Electric Cooperative, Inc. \n \n \nDated: August 28, 2026."},{"page":5,"startToken":990,"endToken":1068,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Federal Energy \nRegulatory Commission in this proceeding. \nDated at Washington, D.C. this 28th day of August, 2026.  \n \n  //s// Emma Kirby \n \n \nEmma Kirby \nLegal Administrative Assistant \nWashington Energy Law LLP \n900 17th Street, N.W., Suite 500-A \nWashington, D.C. 20006 \nTel: (202) 326-9313  \nEmail: ekirby@washingtonenergylaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":428},{"p":3,"at":5,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":3,"endAt":613,"startToken":428,"endToken":519},{"p":3,"at":613,"title":"II. ANSWER","method":"printed heading","endPage":4,"endAt":634,"startToken":519,"endToken":892},{"p":4,"at":634,"title":"III. CONCLUSION","method":"printed heading","endPage":5,"endAt":0,"startToken":892,"endToken":990},{"p":5,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":5,"endAt":517,"startToken":990,"endToken":1068}]}