{"document":{"slug":"rec-20260903-5020","title":"Comments of Hans Royal re the Interim Resource Adequacy Service proposed by PJM Interconnection, L.L.C","issued":"2026-09-03","accession":"20260903-5020","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Individual No Affiliation","kind":"comments","file":"sources/filings/text/20260903-5020_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5020","tier":"record","sha256":"72e333f9a52e3a01a4f906dceaf4fdab7aef9a16bff2d52d289ace8fb72b2e3f","pages":5,"tokens":2082,"emptyPages":[],"textThemes":["registry","flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":402,"text":"Comments of Hans Royal, Docket No. ER26-3515-000, page 1 \nUNITED STATES OF AMERICA \nBEFORE THE FEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C.\nDocket No. ER26-3515-000\nCOMMENTS OF HANS ROYAL \nSeptember 3, 2026 \n1. Introduction and Interest of the Commenter \nI am an energy professional and researcher, and spent nearly two decades advising large electricity \nbuyers on electricity procurement before turning to this research full time. I developed the \nCompute Heat Rate (CHR) framework to answer a practical question: how high can the price of \nelectricity rise before AI data center workloads are no longer profitable? CHR expresses that \nthreshold in dollars per megawatt-hour and reports it by workload type. I published the framework \non SSRN in February 2026 (Royal, 2026, doi 10.2139/ssrn.6322318), and I update the underlying \nindex quarterly at computeheatrate.com. PJM discussed CHR at pages 49 through 50 of its May 6, \n2026 white paper, Powering Reliability Through Market Design, in connection with demand-side \nprice tolerance. \nI am filing these comments on my own behalf as an independent researcher. I publish the index \nand provide advisory work drawing on this research; I have no client with an interest in this \nproceeding, and I represent no load, supplier, or other market participant, nor am I asking the \nCommission to adopt CHR, or any other single metric, as a tariff standard. Instead, my point is \nnarrower: PJM is proposing a framework under which large loads are identified and, through \nTransmission Owners and Electric Distributors, reduced and compensated during capacity \nshortages. Two facilities can look the same on an interconnection diagram and have radically \ndifferent economic responses to interruption, so my recommendation is that the design leave room \nfor that fact. \n2. Summary of Position \nPJM needs an interim answer to a real resource adequacy problem, and this filing is a reasonable \none. I support approval of the Interim Resource Adequacy Service (IRAS), the Large Load \nRegistry, and the Bring Your Own New Capacity (BYONC) provisions. The July 27 Board \nframework followed a substantial stakeholder process and places the reliability obligation where \nit belongs: on new load that enters without bringing new supply, not on customers already served \nby the system. \nThere is one issue the Commission should keep in view as it evaluates the filing and the work that \nwill follow it, which is that large loads are not economically interchangeable. This shows up in \nthree ways:"},{"page":2,"startToken":402,"endToken":931,"text":"Comments of Hans Royal, Docket No. ER26-3515-000, page 2 \nFirst, the cost of interrupting one large load can differ from the cost of interrupting another by well \nover an order of magnitude. The Q3 2026 CHR index puts the operating electricity threshold for \ninternal, self-hosted AI inference at about $1,200 per MWh and the threshold for frontier inference \nat about $18,400 per MWh. The consumption-weighted figure is about $9,100 per MWh. A pro \nrata zonal allocation and one compensation rate wouldn’t adequately reflect the real economics.  \nSecond, the filing itself provides evidence of this economic spread. A load that arranges new \ncapacity under the BYONC rules or installs enough backup generation to take its load off the \nsystem is paying for firmness. Another load may accept IRAS exposure and the accompanying \ncredit. Those are different choices about the value of uninterrupted service. BYONC and the \nbackup-generation provisions will begin sorting loads on that basis even though the tariff does not \ndescribe the process in those terms. \nThird, the Registry can capture what PJM learns from those choices. I am not proposing a new \nmandate for the interim phase. I am asking the Commission to encourage PJM to keep the Registry \nand IRAS flexible enough to support voluntary reduction preferences and, where states and \nElectric Distributors choose to use them, economically informed reduction priorities later. \n3. Background: What the Compute Heat Rate Measures \nCHR starts with the revenue earned by an AI workload and the energy needed to deliver the \nservice. From published inputs and disclosed assumptions, it estimates the electricity price the \nworkload can absorb before continued operation ceases to make economic sense. \nThe index reports two related values. Long-run CHR asks whether it still makes sense to build and \noperate new capacity for the workload. Dispatch CHR, or CHR-D, asks a different question: after \nthe facility has been built and its capital cost is sunk, at what hourly electricity price would a \nrational operator stop running? CHR-D is the more relevant value here because curtailment is an \noperating decision. \nThe Q3 2026 index was published September 1. It reports a blended long-run CHR of \napproximately $5,630 per MWh and a blended CHR-D of approximately $9,070 per MWh. Those \nfigures are about 113 and 181 times a conventional gas-fired reference price of $50 per MWh. The \nlong-run CHR declined by nearly 30 percent from Q2, reflecting both market developments, \nincluding falling token prices and the commoditization of inference, and methodology updates \ndisclosed with the release. That movement is important: the index tracks the market rather than \nfixing a number. It did not, however, change the basic result. For the commercial workloads that \naccount for most deployed compute, the rational curtailment threshold remains far above any price \nPJM's energy market is permitted to produce. \nThose numbers require two qualifications. First, neither CHR nor CHR-D says whether a facility \ncan physically reduce load in ten minutes, or by how much. That depends on the operator, the \nfacility, and PJM's operating rules. Second, CHR is not a price forecast. It is an economic ceiling: \na measure of economic tolerance, not a prediction of what power will cost."},{"page":3,"startToken":931,"endToken":1438,"text":"Comments of Hans Royal, Docket No. ER26-3515-000, page 3 \n4. Observations on the Proposal \nReferences below to the 'Board framework' are to PJM's CIFP Framework for Service During \nPeriods of Insufficient Resource Adequacy (July 27, 2026), which the August 13, 2026 filing \nimplements. Where the filed tariff language differs from that framework, the filed language \ncontrols. \n4.1 Curtailment economics are heterogeneous, and the spread is large \nThe label \"AI data center\" hides a very wide range of economics. In the Q3 2026 index, CHR-D \nruns from approximately $1,227 per MWh for internal and self-hosted inference to approximately \n$18,378 per MWh for frontier inference, a spread of roughly fifteen times. At the low end, a \ncompensated interruption may be a sensible bargain. At the high end, the lost workload value \nduring the same hour can exceed the credit many times over. \nElectric Distributors would compensate compliant IRAS reductions at a single flat hourly rate set \nby PJM and tied to the rate already used for pre-emergency demand response (Board framework, \nCredits, item 6). Measured against CHR-D, that credit is likely to cover much of what some \nworkloads lose and a small fraction of what others lose. \n4.2 What uniform treatment leaves on the table \nIf PJM needs a given number of megawatts during an emergency, it can obtain those megawatts \nfrom loads with very different interruption costs. The framework allocates reductions across \naffected zones pro rata and leaves customer-specific implementation to Transmission Owners and \nElectric Distributors in coordination with states and affected customers, with no economic \ncriterion. That order could cut a workload that would pay almost anything to continue operating \nwhile leaving another workload online that would have reduced voluntarily at a much lower price. \nReliability sees the same megawatts either way; customers do not bear the same cost. Over time, \nPJM could reduce that cost by allowing loads to volunteer for earlier reduction or by permitting \nstates and Electric Distributors to use economic exposure when setting reduction order. \nThe single credit rate creates the same mismatch. The credit is below the operating value of most \ndeployed compute as measured by CHR-D. I do not view that as a flaw in the proposed rate. Fully \ncompensating frontier inference would impose an unreasonable cost on other customers, and the \nBoard reasonably concluded that an IRAS reduction happens earlier and under less severe \nconditions than a full emergency. But the credit should not be mistaken for the value of the \ncurtailed activity. A high-CHR-D load has little economic reason to rely on it and every reason to \nseek firmness through BYONC or on-site generation. A lower-CHR-D load may find the credit \nmeaningful and may be willing to reduce first. \n4.3 The proposal already sorts loads by willingness to pay for firmness \nBYONC and the Registry's backup-generation field (Registration Content, item 10) will give PJM \na rough but useful signal about the value that individual loads place on firmness. A customer that \narranges BYONC backed by a resource subject to the proposal's maintenance and price-taker"},{"page":4,"startToken":1438,"endToken":1827,"text":"Comments of Hans Royal, Docket No. ER26-3515-000, page 4 \nrequirements, or installs backup generation sufficient to remove its load from the system, has made \nan expensive choice not to be interrupted. \nThis is why the economic spread is not merely theoretical. Once implementation begins, the \nRegistry is expected to show some large loads arriving with BYONC or backup generation and \nothers arriving without either. The proposal will produce economic differentiation through those \ncustomer choices. It simply does not yet use the resulting information when reductions are \nassigned. \n4.4 The Registry as a foundation \nThe Board describes the Registry as providing \"the critical data transparency needed to establish \nload reduction priorities for retail customers.\" It also commits PJM to publish aggregate \ninformation where confidentiality permits. I agree with both decisions. The Registry can also hold, \non a voluntary basis, the information that states and Electric Distributors would need to set \nreduction order more intelligently when they \"coordinate with the individual customers that will \nbe subject to Interim Resource Adequacy Service\" (Participation Details, item 9). \nPJM does not need to collect detailed economic data in this proceeding. It should, however, avoid \ndesigning a schema that forecloses the option. A voluntary field stating a customer's reduction \npreference, or noting planned participation in Price Responsive Demand or a state economic-\npriority program, would be enough to preserve a path forward. Adding that capacity now is easier \nthan rebuilding the Registry after it is populated. \n5. Recommendations \nI ask the Commission to take four steps: \n(a) Approve IRAS, the Large Load Registry, and BYONC as interim measures on PJM's \nrequested schedule. \n(b) Recognize in its order that pro rata allocation and a uniform credit are interim \nsimplifications. The Commission should encourage PJM and its stakeholders to examine \neconomically differentiated participation and reduction order in the follow-on process. \nThat work could use Price Responsive Demand, state and Electric Distributor programs \ninformed by Registry data, voluntary self-designation, or a combination of those \napproaches. \n(c) Encourage PJM to include voluntary Registry fields that can support that work and to \npublish enough aggregate detail for independent analysis of how large loads are actually \nentering the system. \n(d) Encourage the use of transparent, published, independently verifiable economic \nreferences when states, Electric Distributors, or PJM develop economically differentiated \nreduction priorities in the follow-on process. Published frameworks can be inspected,"},{"page":5,"startToken":1827,"endToken":2082,"text":"Comments of Hans Royal, Docket No. ER26-3515-000, page 5 \nchallenged, and updated, which is what makes them suitable as a common reference for \noperators, regulators, and lenders. \n6. Conclusion \nPJM has proposed a workable interim response to an urgent problem, and I support approval. The \nCommission should also be clear about what the interim design leaves unresolved. Large loads \nthat appear similar electrically can differ by an order of magnitude in the value they lose when \ncurtailed. BYONC and backup-generation choices should make part of that difference visible \nalmost immediately. PJM should preserve the ability to use what it learns, instead of hardening a \ntemporary pro rata approach into the long-term answer. \nRespectfully submitted, \nHans Royal \nAuthor, The Compute Heat Rate (Royal, 2026) \ncomputeheatrate.com \nSeptember 3, 2026 \nReferences \nRoyal, Hans. The Compute Heat Rate: Quantifying AI-Driven Electricity Price Tolerance and Its \nImplications \nfor \nWholesale \nMarket \nRepricing \n(February \n28, \n2026). \nSSRN, \nhttp://dx.doi.org/10.2139/ssrn.6322318. \nRoyal, \nHans. \nCHR \nReference \nValues, \nQ3 \n2026 \n(September \n1, \n2026). \nhttps://computeheatrate.com/chr-index. \nRoyal, Hans. The Price of Flexibility (August 2026). https://computeheatrate.substack.com/p/the-\nprice-of-flexibility. \nPJM Interconnection, L.L.C. Powering Reliability Through Market Design (May 6, 2026), at 49-\n50. \nPJM Board of Managers. CIFP Framework for Service During Periods of Insufficient Resource \nAdequacy, PJM Proposal, Executive Summary and Detailed Proposal (July 27, 2026). \nPJM Interconnection, L.L.C. Proposal to Establish Interim Resource Adequacy Service and a \nLarge Load Registry, Docket No. ER26-3515-000 (filed August 13, 2026), Accession No. \n20260813-5118."}],"sections":[{"p":1,"at":0,"title":"Pages 1 to 4","method":"page range","endPage":5,"endAt":0,"startToken":0,"endToken":1827},{"p":5,"at":0,"title":"Page 5","method":"page range","endPage":5,"endAt":1777,"startToken":1827,"endToken":2082}]}