{"document":{"slug":"rec-20260903-5023","title":"Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer Service Ratepayers to PJM Interconnection, L.L.C.'s 08/13/2026…","issued":"2026-09-03","accession":"20260903-5023","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Individual No Affiliation","kind":"protest","file":"sources/filings/text/20260903-5023_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5023","tier":"record","sha256":"4246bbe71c9155c272934ed903da4845c207ddb49ba9a7758b84d7a9b30ba4bf","pages":17,"tokens":4561,"emptyPages":[],"textThemes":["retail","registry","adequacy","procedure"]},"pages":[{"page":1,"startToken":0,"endToken":253,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nDocket No. ER26-3515-000 \n \nMOTION TO INTERVENE AND PROTEST OF NICHOLAS MAX NEAL AND \nDAVID NEAL, DELAWARE STANDARD OFFER SERVICE RATEPAYERS \nPursuant to Rules 211, 212, and 214 of the Commission's Rules of Practice and Procedure, 18 \nC.F.R. §§ 385.211, 385.212, 385.214, and the Commission's Combined Notice of Filings #2 \nissued August 18, 2026 (FR Doc. 2026-16808), Nicholas Max Neal (\"the Customer\") and David \nNeal (\"Mr. Neal\") (together, \"Movants\") move to intervene in the above-captioned proceeding \nand protest the August 13, 2026 filing of PJM Interconnection, L.L.C. (\"PJM\") in Docket No. \nER26-3515-000 (Accession No. 20260813-5118) (the \"IRAS Filing\"). \nI. INTRODUCTION AND SUMMARY \n1. PJM asks the Commission to accept a wholesale rate that has no value and a cost \nallocation that has no allocator. \n2. The rate for Interim Resource Adequacy Service (\"IRAS\") is not a number. Under \nproposed Tariff, Attachment DD-4, § X(a), it is any point on a continuum between 50% of the \nNon-Performance Charge Rate and zero dollars, and which point governs is decided not by this \nCommission, not by the tariff, and not at the time of filing, but by a retail election made later, in \na state forum, under state law. No customer reading PJM's tariff can determine what the rate is. \nNeither can a State. The Pennsylvania Public Utility Commission has already told the \nCommission it cannot read the provision, finding \"ambiguity due to discrepancies between PJM's"},{"page":2,"startToken":253,"endToken":553,"text":"transmittal letter and the red-lined tariff amendments proposed on this issue of 0-50% \ncompensation.\" \n3. PJM's own cited authority forecloses this. In footnote 315 of its transmittal, PJM \ninvokes Electric District No. 1 v. FERC, 774 F.2d 490, 493 (D.C. Cir. 1985), for the proposition \nthat \"[p]urchasers of electricity cannot plan their activities unless they know the cost of what \nthey are receiving,\" and that \"providing the necessary predictability is the whole purpose of the \nwell-established filed rate doctrine,\" quoting Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 571, \n577 (1981). PJM deploys that principle to demand that the Commission prescribe with precision \nany language the Commission itself revises. The principle does not run in one direction only. A \nrate that cannot be ascertained from the tariff, and whose value awaits a state proceeding that no \none is obliged to open, supplies precisely the predictability the filed rate doctrine exists to \nguarantee — and PJM has not supplied it. \n4. The cost allocation fails for the same reason and more starkly. PJM states that \"the \nentities to be paid the rate and the loads to be charged to support such compensation must be \ndetermined at the state level,\" and then concedes that its \"proposal imposes no obligation on any \nstate to do anything.\" IRAS Filing, transmittal at 104, 106. PJM's framework therefore identifies \nno charged party in any State that has not acted. In the companion Reliability Backstop \nProcurement filing, PJM at least proposed a \"backup default cost allocation\" for that \ncontingency. Here it proposes nothing. \n5. Delaware is the proof. The Delaware proceeding that would supply PJM's missing \nterms — Public Service Commission Docket No. 25-0826 — has been suspended since April \n14, 2026, and Delaware has adopted no large-load rate structure of any kind. Delaware is also"},{"page":3,"startToken":553,"endToken":845,"text":"restructured, which by PJM's own footnote 281 is the harder case, in which the Electric \nDistributor is not the Load Serving Entity — the case PJM identifies and then declines to \nanalyze. Against that, PJM's 132-page transmittal never once mentions Delmarva Power & Light \nCompany, the Electric Distributor on which the entire scheme would operate in Movants' zone. \n\"Delaware\" appears a single time, in a footnote listing the thirteen Governors who signed a \nvoluntary pledge. \n6. Meanwhile the tariff is precise about one thing. Proposed Attachment DD-4, § X(b)(iii) \nprovides that \"any default shall be assessed to the Electric Distributor.\" PJM has drafted with \ncare to ensure that no uncollected IRAS obligation reaches PJM or its membership. It has drafted \nnothing to keep that obligation from reaching Delmarva's captive retail customers, who are not \nNew Large Loads, caused none of the shortfall IRAS addresses, receive no IRAS compensation, \nand are already absorbing a 21.8% increase in Delaware Docket No. 25-1555. \n7. Under section 205 of the Federal Power Act, the burden of proving that this rate is just \nand reasonable rests on PJM and on no one else. 16 U.S.C. § 824d(e). PJM has not carried it. The \nCommission should not accept proposed Tariff, Attachment DD-4, § X as filed. \nII. MOTION TO INTERVENE \nA. Timeliness \n8. This motion is timely. The Commission's Combined Notice of Filings #2 established a \ncomment date of 5:00 p.m. ET on September 3, 2026. On September 2, 2026, the Commission \ndenied the Organization of PJM States, Inc.'s (\"OPSI\") motion for an extension of time and \nconfirmed that \"[t]he deadline to submit interventions, protests, and comments in the above-\nreferenced proceeding remains 5pm ET September 3, 2026.\" Notice Denying Extension of Time,"},{"page":4,"startToken":845,"endToken":1088,"text":"Docket No. ER26-3515-000 (Sept. 2, 2026) (Accession No. 20260902-3019). This filing is \nsubmitted within that deadline. \nB. Identity of Movants \n9. The Customer is a retail electric customer of Delmarva Power & Light Company \n(\"DPL\") taking service in the State of Delaware, within the DPL transmission zone of the PJM \nRegion, under DPL Service Classification MGS-S (Medium General Service — Secondary). The \nCustomer has not selected a competitive electricity supplier and therefore receives Standard \nOffer Service (\"SOS\") from DPL. Under DPL's Delaware retail tariff, MGS-S constitutes its own \nFixed Price SOS Customer Group. See DPL, P.S.C. Del. No. 8 — Electric, Rider \"SOS\" § A. \n10. Mr. Neal was the DPL customer of record for the same premises, under the same \nService Classification MGS-S and likewise taking Standard Offer Service, until approximately \nAugust 2025. Mr. Neal is obligated, under a written contract with the Customer, to reimburse the \nCustomer for the electric charges billed at that premises, and therefore bears the economic \nburden of the charges described below. \n11. Movants appear on their own behalf and are not represented by counsel. \n12. Movants are parties to the companion proceeding in Docket No. ER26-3380-000, \nwhere they filed a timely motion to intervene and protest on August 20, 2026 (Accession No. \n20260820-5015), to which no answer in opposition was filed. Movants are also complainants \nbefore the Delaware Public Service Commission in Complaint Docket No. 26-0847, in which \nDelmarva's answer is due September 14, 2026. \nC. Movants' Interest"},{"page":5,"startToken":1088,"endToken":1378,"text":"13. Rule 214(b)(2) requires a movant to show an \"interest which may be directly affected \nby the outcome of the proceeding,\" or that participation \"is in the public interest.\" 18 C.F.R. § \n385.214(b)(2)(ii), (iii). Movants satisfy both. \n14. The tariff names the entity that will bill them. Proposed Attachment DD-4, § \nX(b)(iii) assigns any IRAS billing default to \"the Electric Distributor.\" The Electric Distributor \nin Movants' zone is Delmarva. An obligation assessed to Delmarva at wholesale is an obligation \nDelmarva will seek to recover in Delaware retail rates, where Movants are captive. The chain is \nnot inferential; it runs from a tariff provision to a named utility to Movants' bill. \n15. The proposed VRR Curve exclusion moves the price Movants pay. PJM would \nexclude specified New Large Load MW from the Variable Resource Requirement Curve \nbeginning with the 2029/2030 Delivery Year, \"regardless of whether PJM is experiencing a \nshortfall that triggers IRAS in the relevant Delivery Year.\" IRAS Filing, transmittal at 110. \nAltering the demand curve alters the capacity clearing price for every load in the zone. The \nCustomer's supply is procured and repriced annually, and DPL's Rider \"SOS\" § B provides that \nthe SOS Rate \"will include the costs for energy, capacity and ancillary services as reflected in the \nawarded electric supply prices for specific services in each year.\" The Delaware Public Service \nCommission's own consultant has confirmed the mechanism: \"[b]idders use $/MW-day capacity \nauction prices to create a capacity component (in $/MWh) of their SOS bid prices,\" and \"[l]ower \nload factor customer classes . . . feel a greater impact from capacity prices than high load factor . \n. . customers since they have fewer MWh over which to spread their demand-based capacity \ncharges.\""},{"page":6,"startToken":1378,"endToken":1645,"text":"16. No one else in this docket represents this interest. Movants are end-use Standard \nOffer Service customers in the zone of the Electric Distributor PJM's tariff makes the residual \nobligor. \"Delmarva\" appears zero times in PJM's transmittal. No participant in this proceeding \nhas placed a single Delaware fact before the Commission. Granting intervention will not delay \nthis proceeding or burden any party. \n17. The Commission should grant this motion and accord each Movant party status. \nIII. THE FILING \n18. On August 13, 2026, PJM submitted a filing under section 205 of the Federal Power \nAct proposing to establish IRAS and a Large Load Registry, requesting an effective date of \nOctober 12, 2026. IRAS Filing, transmittal at 8. \n19. IRAS is a load-reduction service. When PJM lacks sufficient available economic real-\ntime supply to maintain reserves or remain within Interconnection Reliability Operating Limits, \nit may direct load reductions by New Large Loads that have neither entered into \"bring your own \nnew capacity\" (\"BYONC\") arrangements nor received Allocated RBP UCAP MW. PJM may \ncall on IRAS reductions \"prior to calling on Pre-Emergency Load Management Reductions \nActions\" — that is, ahead of resources that bid into a market and hold a capacity obligation. Id. \nat 28. \"New Large Load\" means \"an end-use customer load that is either (a) a Large Load that \ngoes into service after June 1, 2027, or (b) incremental load in-service after June 1, 2027, that \nincreases the existing end-use customer load at a single electrical site that, prior to such \nincremental load, did not previously meet the definition of Large Load.\" Proposed Tariff, \nDefinitions — New Large Load."},{"page":7,"startToken":1645,"endToken":1954,"text":"20. PJM has severed this filing from its Reliability Backstop Procurement (\"RBP\") filing \nin Docket No. ER26-3380-000, stating that \"the two filings are independent of each other\" and \nthat \"IRAS can and should be accepted and made effective as requested.\" IRAS Filing, \ntransmittal at 2 n.3. PJM must therefore defend this filing on its own terms, without borrowing \nsupport from a proceeding it has disclaimed. \nIV. PROTEST \nA. PJM has not filed a rate. It has filed a range and deferred its value to a proceeding that \nmay never occur. \n21. PJM proposes a rate \"equal to 50% of the Non-Performance Charge Rate.\" IRAS \nFiling, transmittal at 102. The tariff does not stop there. The rate drops below 50% \"if the \nEligible New Large Load accepts in its retail rate a sum less than 50% of the Non-Performance \nCharge Rate,\" and \"a rate of zero dollars for IRAS would apply where Eligible New Large Loads \nwaive in their retail rates receipt of compensation.\" Id. The proposed tariff makes the wholesale \nrate follow the retail election: it \"shall reflect the accepted sum less than 50% of the Non-\nPerformance Charge Rate or if compensation is waived entirely, the rate shall be zero dollars.\" \nProposed Tariff, Attachment DD-4, § X(a). \n22. The filed wholesale rate is therefore every value between zero and 50% of the Non-\nPerformance Charge Rate. Which value governs depends on a retail election, made in a state \nforum, under state law, at a time no one can specify — and, in a State with no proceeding in \nwhich to make it, never made at all. \n23. This is not a drafting quibble raised by lay customers. The Pennsylvania Public \nUtility Commission, a State commission with a standing energy bar, told this Commission on \nSeptember 1, 2026 that it finds \"some ambiguity due to discrepancies between PJM's transmittal"},{"page":8,"startToken":1954,"endToken":2266,"text":"letter and the red-lined tariff amendments proposed on this issue of 0-50% compensation,\" and \nthat while PJM's redlines \"identify EDC compensation obligations and collection thereof from \njurisdictional customers,\" the \"tariff does not expressly recognize state authority to prohibit, \napprove, or modify such compensation and jurisdictional recovery.\" Answer of the Pennsylvania \nPublic Utility Commission to Motion for Extension of Time, Docket No. ER26-3515-000, at 2–3 \n(Sept. 1, 2026) (Accession No. 20260901-5028). When the regulator of PJM's largest state \ncannot determine what the tariff does, the tariff has not given notice. \n24. PJM has told the Commission the governing standard, in its own transmittal. Footnote \n315 quotes Electric District No. 1: \"[P]urchasers of electricity cannot plan their activities unless \nthey know the cost of what they are receiving, 'providing the necessary predictability is the \nwhole purpose of the well-established filed rate doctrine.'\" 774 F.2d at 493 (quoting Ark. La. Gas \nCo. v. Hall, 453 U.S. 571, 577 (1981)). PJM adds that \"mere 'direction' without 'sufficient detail \non each element [of the replacement rate] that [customers/market participants] could determine \nwhen their transactions would be subject to [the new rule]'\" would \"violate the filed rate \ndoctrine.\" PJM invokes this to constrain the Commission. It applies with at least equal force to \nPJM's own submission: a tariff that states a range and locates the operative number in an \nunscheduled state proceeding gives market participants no way to \"determine when their \ntransactions would be subject to\" what rate. \n25. In Delaware today, the wholesale IRAS rate is unknowable. It is not zero — zero is \nwhat results from an affirmative waiver election that Delaware provides no forum to make. It is \nundetermined, and PJM asks the Commission to accept it in that condition. \nB. PJM concedes that its framework cannot function without state action, and supplies no \ndefault when that action does not come."},{"page":9,"startToken":2266,"endToken":2546,"text":"26. PJM's transmittal states the concession plainly: \n\"That said, PJM's proposal imposes no obligation on any state to do anything. \nStates are free to design retail rate regimes that facilitate the recovery and \nallocation of wholesale IRAS rates through generally applicable retail rate tariffs. \nAlternatively, if states decline to act generically, they could negotiate specific \nretail filed rates with affected entities. Further still, if states decline to act, Eligible \nNew Large Loads could initiate regulatory proceedings to develop retail pathways \nto recover wholesale IRAS rates. Or, if states decline to act and Eligible New \nLarge Loads decline to initiate regulatory proceedings to recover through retail \nrates the wholesale IRAS rate, they would effectively waive a right to \ncompensation.\" \nIRAS Filing, transmittal at 106–07. \n27. PJM presents this as flexibility. It is an admission that the filing is incomplete. The \npassage answers one question — who gets paid when no State acts — and leaves three that \nbelong to this Commission because they concern the operation of a federal tariff: \n(a) The service is still compelled. Nothing conditions PJM's authority to direct IRAS load \nreductions on the existence of a state-approved compensation mechanism. PJM takes the \nreliability benefit in a non-acting State on identical terms. \n(b) The Electric Distributor's obligations still attach. Under the proposed tariff the Electric \nDistributor administers the program, identifies the beneficiaries, and absorbs the billing default \n— in a State that has adopted no plan enabling it to do the first two. \n(c) The tariff supplies no charged party. PJM's answer that compensation may be \"effectively \nwaive[d]\" addresses only payment. It says nothing about who is charged, and it leaves § \nX(b)(iii)'s default assignment fully operative."},{"page":10,"startToken":2546,"endToken":2821,"text":"28. PJM knows how to solve this, because it did so in the companion docket. There PJM \nproposed a \"backup default cost allocation\" governing precisely the case in which a Relevant \nElectric Retail Regulatory Authority (\"RERRA\") declines to act. Here PJM proposes none, while \nrelying on the same assumption of state action. \n29. The regulators on whom that assumption rests have told the Commission they do not \nyet understand it. OPSI sought additional time so that \"the retail regulators in the PJM region\" \ncould \"consider the interaction between the rights and responsibilities of PJM, Electric \nDistributors, and retail regulators related to the implementation of Interim Resource Adequacy \nService and the associated compensation mechanism.\" Notice Denying Extension of Time at 1. \nGoogle LLC, the Pennsylvania Public Utility Commission, and East Kentucky Power \nCooperative supported that request; no party opposed it. PJM's response to the fact that the \nregion's retail regulators have not worked out the handoff is to ask that the framework be \naccepted anyway, effective October 12, 2026. \nC. Delaware refutes PJM's premise. \n30. PJM tells the Commission that some States \"have begun proceedings to evaluate how \nto best facilitate coordination with PJM on implementing IRAS,\" and that \"PJM welcomes all \nsuch efforts.\" Delaware began one. It stopped. \n31. On October 14, 2025, the Delaware Public Service Commission opened Docket No. \n25-0826 to establish a large load tariff, to ensure that \"large load facilities, like data centers, do \nnot shift costs to other ratepayers.\" That is the proceeding in which Delaware would adopt the \n\"state-approved load reduction plans and other state-approved programs, rates, and rules\" on \nwhich PJM's framework depends. IRAS Filing, transmittal at 104."},{"page":11,"startToken":2821,"endToken":3118,"text":"32. On April 14, 2026, by Order No. 10998, the Hearing Examiner suspended the \nprocedural schedule in Docket No. 25-0826. No Hearing Examiner's Report issued on the \nscheduled date. No Commission deliberation occurred on the scheduled date. Nearly five months \nlater the docket remains suspended, and Delaware has adopted no large-load rate structure. \nThere is no state-approved load reduction plan in Delaware, and no state-approved program, rate, \nor rule under which Delmarva could identify either the beneficiaries of an IRAS reduction or the \nloads to be charged for it. PJM's framework, applied to Delaware on October 12, 2026, would \noperate with both terms blank. \n33. The loads are already at the door. Order No. 10998 records that Delmarva is \"working \nwith seven developers on large load projects seeking a total of 2,455 MW,\" that five of the seven \nare data centers \"seeking 82% of the total load request,\" and that one proposed project is 1.2 GW \nagainst a Delaware summer peak load of 2.7 GW. These are the very loads that would qualify as \nNew Large Loads, in the very zone where no retail mechanism exists. \n34. Delaware is also the case PJM identified and then abandoned. Footnote 281 states: \n\"PJM understands that in traditional, non-restructured states, the Electric Distributor also doubles \nas the LSE for the New Large Load, while in restructured states, the LSE may be an independent \nentity, not affiliated with the Electric Distributor.\" IRAS Filing, transmittal at 105 n.281. \nDelaware is restructured. Delmarva is the Electric Distributor and is not the LSE for a \ncompetitively supplied large load. PJM assigns administration, identification, and default risk to \nan entity whose compensation obligations run through LSEs it does not control, notes the \nproblem in a footnote, and never returns to it."},{"page":12,"startToken":3118,"endToken":3415,"text":"35. The absence is not confined to analysis. \"Delmarva\" appears zero times in PJM's \n132-page transmittal letter. \"DPL\" appears zero times. \"Delaware\" appears once — in a \nfootnote listing the thirteen Governors who signed the Statement of Principles Regarding PJM of \nJanuary 16, 2026. \"RERRA\" appears twenty-three times. PJM has built a framework that \noperates through Electric Distributors and RERRAs without examining what happens at the one \nit never names, in the State it mentions only as a signature on a voluntary pledge that binds no \none and that no order of this Commission can enforce. \nD. Section X(b)(iii) shifts uncollected wholesale obligations onto Delmarva's captive \ncustomers. \n36. PJM drafted protection for itself with precision. The indemnification language exists \n\"to make clear that neither PJM nor the PJM membership, generally, is financially responsible \nfor any potential defaults that may arise in association with the billing of this compensation.\" \nIRAS Filing, transmittal at 108. If \"a LSE does not pay as required . . ., the default will not pass \nto the PJM membership.\" Id. Where PJM bills at the Electric Distributor's request, \"such billing \nwill be viewed as a bilateral transaction between the Electric Distributor and the other party and \nany default shall be assessed to the Electric Distributor.\" Id. at 109; proposed Tariff, \nAttachment DD-4, § X(b)(iii). \n37. The provision fixes where a default lands and is silent on who ultimately pays it. In a \nrestructured State with no state-approved allocation mechanism, that silence has an obvious \nanswer: the Electric Distributor's captive retail customers. \n38. Delmarva is at this moment seeking a distribution base rate increase before the \nDelaware Public Service Commission in Docket No. 25-1555 that includes a 21.8% increase for \nthe MGS-S class — the Customer's class — with interim rates already in effect and collecting"},{"page":13,"startToken":3415,"endToken":3723,"text":"subject to refund. A wholesale default assessed to Delmarva under § X(b)(iii) is an amount \nDelmarva will seek from that same customer base: customers who are not New Large Loads, did \nnot cause the shortfall IRAS addresses, and receive no IRAS compensation. \n39. A provision is not just and reasonable merely because it protects the PJM \nmembership. PJM has shown where the cost stops being its problem. It has not shown that the \nplace it comes to rest is lawful. \nE. The Large Load Registry cannot perform the function PJM assigns it. \n40. Every allocation in this framework depends on knowing which loads are New Large \nLoads and when they entered service. PJM would maintain that information in the Large Load \nRegistry and rely on States and Electric Distributors to act on it. A State cannot allocate costs to \nloads it cannot identify, and an Electric Distributor cannot bill them. \n41. A State commission that supports PJM has told the Commission the predicate fails. \nThe Illinois Commerce Commission stated that \"expecting the states to make such \ndeterminations for PJM and the Commission may be unreasonable,\" and that \"PJM would seem \nto be in a better position and have access to the appropriate data to make an assessment of the \ncost causers and even beneficiaries.\" Comments of the Illinois Commerce Commission, Docket \nNo. ER26-3380-000, at 6 (Aug. 19, 2026) (Accession No. 20260819-5134). On the Registry \nitself, the ICC warned that \"[s]tates have different rules that can limit their access to confidential \ndata,\" that the ICC \"would not be in a position to sign the pro forma non-disclosure agreements \nto access confidential data from PJM as it reads at this time,\" and that it \"is crucial that any large \nload registry be accessible to ICC staff in order to fulfill any state's cost allocation obligations.\" \nId. at 7."},{"page":14,"startToken":3723,"endToken":3973,"text":"42. That is the assessment of an engaged, supportive State commission with resources \nand an active docket. PJM's framework fares worse, not better, in a State whose large-load \nproceeding is suspended. \nF. The VRR Curve exclusion raises capacity prices for every customer in the zone, and \nrests on a pledge no one can enforce. \n43. Beginning with the 2029/2030 Delivery Year, PJM would exclude from the VRR \nCurve the MW of New Large Loads that have not entered BYONC arrangements and hold no \nAllocated RBP UCAP MW, above the level in the 2028/2029 load forecast — and would do so \n\"regardless of whether PJM is experiencing a shortfall that triggers IRAS in the relevant \nDelivery Year.\" IRAS Filing, transmittal at 110. Removing load from the demand curve raises \nthe capacity clearing price for every load in the zone, including residential and MGS-S Standard \nOffer Service customers who are nowhere near the New Large Load threshold and receive no \nIRAS compensation. \n44. PJM's justification is the Ratepayer Protection Pledge — a voluntary commitment \nthat appears in no tariff, binds no signatory, and cannot be enforced by this Commission or by \nany party. A demand curve is a price-formation instrument. PJM has offered no tariff \nconsequence if the pledge on which the modification rests goes unhonored. \nV. RELIEF REQUESTED \n45. The Commission should reject proposed Tariff, Attachment DD-4, § X as filed. PJM \nbears the burden under FPA section 205 and has not carried it as to either the rate or its \nallocation."},{"page":15,"startToken":3973,"endToken":4259,"text":"46. In the alternative, the Commission should accept the IRAS compensation framework \nonly as conditioned on the following, each of which PJM has consented in advance to have the \nCommission prescribe. PJM asks that the Commission \"expressly prescribe the revised rate or \nrule in its order,\" and confirms that \"the proposal put forth here is not a stakeholder compromise \npackage,\" so no bargain is disturbed. IRAS Filing, transmittal at 122–23. \n47. First, PJM must state on the face of Attachment DD-4, § X the wholesale IRAS rate \nand the responsible collecting entity that apply in an Electric Distributor zone where the RERRA \nhas not established a mechanism identifying the entities to be paid and the loads to be charged. \nPJM proposed exactly such a backstop in the companion RBP filing. A federal filed rate must be \nascertainable from the tariff in every zone to which it applies. \n48. Second, the Commission should condition acceptance of § X(b)(iii) so that a default \nassessed to an Electric Distributor may not be recovered, directly or indirectly, from retail \ncustomer classes containing no Eligible New Large Loads and receiving no IRAS compensation. \n49. Third, PJM must make the Large Load Registry information necessary to identify \nNew Large Loads within a zone — at minimum identity, location, in-service date, and \ncumulative peak load quantity — available to the RERRA and the Electric Distributor for that \nzone on terms each is legally able to accept, so that the allocation function PJM assigns to the \nStates can actually be performed. \n50. Fourth, the Commission should not permit the VRR Curve exclusion to take effect \nwithout a tariff provision specifying the consequence if the Ratepayer Protection Pledge \ncommitments on which it rests are not performed."},{"page":16,"startToken":4259,"endToken":4496,"text":"51. Any modification the Commission adopts should be expressly prescribed in its order, \nas PJM has requested. IRAS Filing, transmittal at 122. \nVI. CONCLUSION \n52. PJM asks the Commission to approve a rate no one can compute and an allocation no \none is required to make, and to make both effective on October 12, 2026. Its answer to the State \nthat has not acted is that compensation is waived — an answer that resolves nothing about who is \ncharged, and leaves a tariff provision routing every uncollected dollar to the Electric Distributor \nand from there to captive retail customers. Delaware has been in that position since April 14, \n2026, and appears in PJM's 132-page filing exactly once, as one of thirteen signatures on a \npledge that binds no one. The Commission should require the tariff to answer, in its own text, \nwhat PJM has left to a forum that may never convene: in a zone where the State has not acted, \nwhat is the rate, who is charged, and who bears the default. \n53. For the foregoing reasons, Movants respectfully request that the Commission grant \nthis motion to intervene and the relief requested herein. \nRespectfully submitted, \n/s/ Nicholas Max Neal               /s/ David Neal \n_______________________________     _______________________________ \nNicholas Max Neal                   David Neal \n111 Centrenest Lane                 111 Centrenest Lane \nWilmington, Delaware 19807          Wilmington, Delaware 19807 \n(845) 263-0012                      (646) 509-3146 \nmax@nicholasneal.com                shaun@shaunneal.com \n \nPro se                              Pro se \n \nDated: September 2, 2026"},{"page":17,"startToken":4496,"endToken":4561,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person designated \non the official service list compiled by the Secretary in this proceeding, in accordance with Rule \n2010 of the Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.2010. \nDated at Wilmington, Delaware, this 2nd day of September, 2026. \n/s/ David Neal \n_______________________________ \nDavid Neal"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":772,"startToken":0,"endToken":118},{"p":1,"at":772,"title":"I. INTRODUCTION AND SUMMARY","method":"printed heading","endPage":3,"endAt":1300,"startToken":118,"endToken":764},{"p":3,"at":1300,"title":"II. MOTION TO INTERVENE","method":"printed heading","endPage":3,"endAt":1325,"startToken":764,"endToken":768},{"p":3,"at":1325,"title":"A. Timeliness","method":"printed heading","endPage":4,"endAt":121,"startToken":768,"endToken":861},{"p":4,"at":121,"title":"B. Identity of Movants","method":"printed heading","endPage":4,"endAt":1573,"startToken":861,"endToken":1085},{"p":4,"at":1573,"title":"C. Movants' Interest","method":"printed heading","endPage":6,"endAt":495,"startToken":1085,"endToken":1453},{"p":6,"at":495,"title":"III. THE FILING","method":"printed heading","endPage":7,"endAt":414,"startToken":1453,"endToken":1711},{"p":7,"at":414,"title":"IV. PROTEST","method":"printed heading","endPage":7,"endAt":427,"startToken":1711,"endToken":1713},{"p":7,"at":427,"title":"A. PJM has not filed a rate. It has filed a range and deferred its value to a proceeding that","method":"printed heading","endPage":8,"endAt":1896,"startToken":1713,"endToken":2245},{"p":8,"at":1896,"title":"B. PJM concedes that its framework cannot function without state action, and supplies no","method":"printed heading","endPage":10,"endAt":1101,"startToken":2245,"endToken":2714},{"p":10,"at":1101,"title":"C. Delaware refutes PJM's premise.","method":"printed heading","endPage":12,"endAt":601,"startToken":2714,"endToken":3213},{"p":12,"at":601,"title":"D. Section X(b)(iii) shifts uncollected wholesale obligations onto Delmarva's captive","method":"printed heading","endPage":13,"endAt":467,"startToken":3213,"endToken":3496},{"p":13,"at":467,"title":"E. The Large Load Registry cannot perform the function PJM assigns it.","method":"printed heading","endPage":14,"endAt":204,"startToken":3496,"endToken":3754},{"p":14,"at":204,"title":"F. The VRR Curve exclusion raises capacity prices for every customer in the zone, and","method":"printed heading","endPage":14,"endAt":1319,"startToken":3754,"endToken":3937},{"p":14,"at":1319,"title":"V. RELIEF REQUESTED","method":"printed heading","endPage":16,"endAt":145,"startToken":3937,"endToken":4281},{"p":16,"at":145,"title":"VI. CONCLUSION","method":"printed heading","endPage":17,"endAt":0,"startToken":4281,"endToken":4496},{"p":17,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":17,"endAt":426,"startToken":4496,"endToken":4561}]}