{"document":{"slug":"rec-20260903-5060","title":"Comments of the Solar Energy Industries Association in response to PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service","issued":"2026-09-03","accession":"20260903-5060","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Solar Energy Industries Association","kind":"comments","file":"sources/filings/text/20260903-5060_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5060","tier":"record","sha256":"56461b7cb7864e63c32ef016998162818ace9dbcfda815981c5b16261225fcb9","pages":9,"tokens":2605,"emptyPages":[],"textThemes":["adequacy","colo"]},"pages":[{"page":1,"startToken":0,"endToken":278,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.                   \n      ) \nDocket Nos. \nER26-3515-000 \n \n \n \nCOMMENTS OF THE SOLAR ENERGY INDUSTRIES ASSOCIATION \n \nPursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (Commission),1 the Solar Energy Industries Association (SEIA) submits \nthese comments in response to PJM Interconnection, L.L.C.’s (PJM) filing to establish Interim \nResource Adequacy Service (IRAS).2  IRAS is a new transmission service that will be \nimplemented solely during periods when there are insufficient resources to reliably meet demand \nin real time operations.3 When triggered, IRAS will enable PJM to prioritize load reduction in \nzones where New Large Loads that have not brought their own new capacity or have their \ncapacity needs met through the Reliability Backstop Procurement (RBP).4 New Large Loads may \navoid IRAS by bringing new capacity to the system through the Bring Your Own New Capacity \n(BYONC) construct.5 BYONC would allow New Large Loads that bring new capacity to the \nPJM Region to remove themselves—in whole or in part—from IRAS.6 \nSEIA does not take a position on the new transmission service created by PJM’s IRAS \nproposal. These comments address the program that would allow New Large Loads to avoid \nIRAS—the BYONC construct. As the trade association representing both utility-scale and \n \n1 18 C.F.R. § 385.213 (2026). \n2 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service & a Large Load Registry, \nDocket No. ER26-3515 (Aug. 13, 2026) (IRAS Filing). \n3 IRAS Filing at 1. \n4 IRAS Filing at 1-2. \n5 IRAS Filing at 2. \n6 IRAS Filing at 50."},{"page":2,"startToken":278,"endToken":650,"text":"2 \ndistribution-scale solar and storage developers in PJM, SEIA submits these comments to provide \nrecommendations to the Commission and PJM that would allow Surplus and Distributed Energy \nResources (DERs) to provide more capacity to the PJM system through a BYONC. \n \nI. \nComments: To make BYONC more effective, PJM must remove market barriers for \nSurplus and Distributed Energy Resources. \nUnder BYONC, the “new” capacity brought to the system “may be supported by \ngeneration, storage, or demand-side resources that meet certain gating criteria.”7 That gating \ncriteria would allow surplus resources and DERs to be part of a BYONC.8 SEIA supports PJM’s \nproposal to allow surplus resources and DERs to qualify for BYONC. In a recent presentation to \nthe PJM Load Analysis Subcommittee, Charles River Associates stated that behind the meter and \nco-located resources, like Surplus Resources and DERs, will play a critical near- and medium-\nterm role in meeting new demand from data centers, especially as structural supply gaps in PJM \nwiden.9  \nStructural supply gaps cannot be remedied by pricing signals. A strong willingness to pay \nby a developer cannot resolve the significant backlogs facing turbine manufacturers.10 More \nmoney cannot build transmission faster in the face of significant transformer backlogs.11 PJM \nitself publicly acknowledged in a January 2026 stakeholder meeting that significant new capacity \n \n7 IRAS Filing at 53.  \n8 IRAS Filing at 53-54 (“Thus, for generation and storage resources, PJM proposes that the BYONC must be \nsupported by:… (3) the incremental capacity created by the utilization of Surplus Interconnection Service. … \nBecause capacity may also be supplied by demand-side resources, PJM proposes that BYONC may be supported by \nPlanned Demand Resource or Planned Distributed Energy Resources (“DER”) Capacity Aggregation Resources”). \n9 Charles River Associates, Review of Data Center Forecast Methodology, at 20 (Aug. 26, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2026/20260826/20260826-item-04--\ncharles-river-associates-review-of-data-center-forecast-methodology.pdf (CRA Load Analysis). \n10 Umed Paliwal, Amol Phadke, Existing power plants sharing grid access with new resources can lower costs and \ndouble PJM’s generation capacity, at 11 (2025), https://surplusinterconnection.s3.us-east-1.amazonaws.com/PJM.pdf \n(Repower PJM). \n11 American Society of Civil Engineers, Infrastructure Report Card, Energy, at 76 (2025), \nhttps://infrastructurereportcard.org/wp-content/uploads/2025/03/Energy.pdf."},{"page":3,"startToken":650,"endToken":1058,"text":"3 \nadditions are unlikely to come online before 2032 due to, among other factors, transmission \nconstraints.12 If PJM is going to overcome these supply gaps, then it must use what is available. \nSurplus and distributed resources are the available resources in the near term. Adding \nbattery storage to existing wind and solar sites through surplus interconnection could add 13.57 \nGW of capacity to PJM.13 This amount of capacity would increase even more if storage were to \nbe added to thermal plants as well.14 Capacity from surplus resources can be deployed within 12-\n18 months, as opposed to the 5-7 year timeline associated with traditional generation.15 Across \nthe PJM region, over 2 GW of distributed energy capacity could be available within just a few \nmonths.16 Several states across the PJM region have already, or are in the process of, \nimplementing programs that would encourage the development of even more distribution-\nconnected resources.17 But this potential for new capacity can only be unlocked with the right \nmarket rules in place. PJM must take further action to put those rules in place. \n \n12 See Devin Leith-Yessian, Government-Proposed “Backstop” Auction to Test PJM Stakeholder Process, RTO \nINSIDER (Jan. 26, 2026), https://www.rtoinsider.com/124178-government-proposed-backstop-auction-test-pjm-\nstakeholder-process/. (“Even with a backstop auction, [David] Mills [PJM board chair and interim CEO] said there \nare significant barriers to getting new resources built, including transmission upgrades, financing, tariffs, siting, \npermitting and supply chain constraints. Significant new capacity is unlikely to be available until 2032.”). \n13 Repower PJM at 32. \n14 Repower PJM  at 12. \n15 Repower PJM  at 34. \n16 Sunrun, Renew Homes, Tesla, Capacity as a Solution Framework, https://www.vppcapacity.com/, calculated using \nthe Capacity Explorer Tool. \n17 About the Legislation: Clean and Reliable Grid Affordability Act (CRGA), Ill. Power Agency, \nhttps://ipa.illinois.gov/crga.html; N.J. Exec. Order No. 2, § 3 (Jan. 20, 2026), \nhttps://www.nj.gov/infobank/eo/057sherrill/pdf/EO-2.pdf. Maryland Energy Storage Program, Order Initiating \nWorkgroup to Develop a Maryland Energy Storage Program, Order No. 90823, Case No. 9715 (Md. P.S.C. Oct. 2, \n2023), http://psc.maryland.gov/wp-content/uploads/Order-initiating-Maryland-Energy-Storage-Program-\nWorkgroup.pdf. Maryland Energy Storage Program, Order on Investor-Owned Utility Energy Storage Plan \nProposals in Compliance with the Next Generation Energy Act, Order No. 92281, Case No. 9715 (Md. P.S.C. Apr. 8, \n2026), https://psc.maryland.gov/wp-content/uploads/2026/04/ORDER_1.pdf"},{"page":4,"startToken":1058,"endToken":1420,"text":"4 \nA. \nSurplus Resources: Barriers to BYONC Participation and Solutions \nAs explained by SEIA, Advanced Energy United, and Google in the Reliability Backstop \nProcurement (RBP) filing, in Docket No. ER26-3380, existing PJM rules limit the ability for \nSurplus Resources to add capacity to the PJM system.18 Currently, PJM only grants capacity \ninterconnection rights (CIRs) and capacity accreditation to surplus resources that merge with the \nexisting facility as a single hybrid resource,19 a developer seeking capacity value through surplus \ninterconnection must elect hybrid treatment—which potentially requires unwinding existing \nfinancial arrangements. The alternative—interconnecting independently as a co-located \nresource—preserves independent financing but limits the surplus resource to energy-only market \nparticipation, forfeiting capacity value entirely. Because hybrid treatment requires combined \nmarket participation as a single resource,20 it does not allow for component-level settlement, and \ncapacity performance penalty risk cannot be isolated from the host resource. Lenders to the \nexisting facility will rarely consent to the addition of a surplus resource under these conditions, \nbecause it exposes the existing project to performance liability arising from a resource it does not \nown or control. This effectively renders the surplus interconnection pathway commercially \nunavailable for many projects. \nIn the RBP proceeding, SEIA and Advanced Energy United each make recommendations \non how to resolve these concerns and make the surplus interconnection pathway commercially \n \n18 See Solar Energy Industries Association, Comments, Docket No. ER26-3380-000, at 9-12 (filed Aug. 21, 2026); \nGoogle LLC, Comments, Docket No. ER26-3380-000, at 10-11 (filed Aug. 21, 2026); Advanced Energy United, \nComments, Docket No. ER26-3380-000, at 11-15 (filed Aug. 21, 2026). \n19 See PJM Tariff, Part VIII, Subpart E, § 414 (Surplus Interconnection Service); see also Hybrid Resources Market \nModel Selection—Problem Statement, PJM Interconnection, L.L.C. (Aug. 2026) (“Hybrid PS/IC”), available at: \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-1---\nhybrid-resources-market-model-selection---problem-statement.pdf (recognizing that under current rules, the only \npathway for surplus resources to obtain capacity value is to become a hybrid resource with the existing project). \n20 See Hybrid PS/IC (discussing issues relating to hybrid resource combined market participation as a single market \nunit in PJM’s energy, capacity, and ancillary services markets)."},{"page":5,"startToken":1420,"endToken":1762,"text":"5 \nviable.21 To address these barriers and unlock the significant capacity potential of surplus \nresources, SEIA recommends three reforms. First, PJM should enable surplus resources to obtain \nindependently recognized and bankable capacity positions—distinct from the host resource—\nwithout requiring the wholesale restructuring of existing commercial arrangements. This could \nbe achieved through several mechanisms, including: (i) split UCAP settlement between \ncomponent accounts; or (ii) CIR transfer mechanisms between co-located resources.22 Whichever \nmechanism is adopted, the objective should be to provide each component of a surplus \narrangement with independent settlement, revenue allocation, and penalty isolation necessary to \nsupport separate financing.  \nSecond, PJM should establish clear protections ensuring that a default or performance \nissue arising from the surplus resource cannot create cross-default risk or otherwise interfere \nwith the existing resource’s interconnection agreement or operations. This protection is essential \nto obtaining lender consent: Absent an explicit structural separation of liability, lenders to the \nexisting facility will not approve the addition of a surplus resource that could jeopardize the \nproject’s existing financing and operational arrangements.  \nThird, SEIA encourages PJM to evaluate whether additional resources or process \nmodifications can be devoted to surplus interconnection studies to reduce the time from \napplication to completion, particularly for projects that could deliver capacity within the RBP’s \ntimeframe. The Commission’s acceptance of PJM’s Docket No. ER25-778-000 reforms removed \n \n21 Solar Energy Industries Association, Comments, Docket No. ER26-3380-000, at 9-12 (filed Aug. 21, 2026); \nAdvanced Energy United, Comments, Docket No. ER26-3380-000, at 11-15 (filed Aug. 21, 2026). \n22 Under PJM’s current framework, a surplus interconnection arrangement results in a revised or amended Generation \nInterconnection Agreement for the existing facility, rather than a separate, standalone GIA for the surplus resource. \nSee PJM Tariff, Part VIII, Subpart E, § 414(B)(2) (providing that a “revised Interconnection Service Agreement or \nGeneration Interconnection Agreement will be prepared and issued to the owner of the existing or planned Generating \nFacility”). This structure means the surplus resource’s market participation, obligations, and potential liabilities are \nhoused within the existing project’s agreement, creating the cross-default risk discussed above."},{"page":6,"startToken":1762,"endToken":2115,"text":"6 \nthe prior automatic disqualifications that blocked surplus requests. Developers now need PJM to \ncomplete the studies on time so they can bring resources online in time for the RBP.23 Together, \nthese reforms—addressing commercial structure, lender protections, and study timelines for \nsurplus interconnection—would enable surplus interconnection to serve as a meaningful near-\nterm pathway for delivering additional accredited capacity to the PJM system, potentially \nunlocking gigawatts of storage and other resources that are positioned to connect quickly at \nexisting points of interconnection. \nSEIA again urges PJM to adopt those recommendations so that New Large Loads can \nactually use surplus resources as new capacity under the BYONC construct. \nB. \nDistributed Energy Resources: Barriers to BYONC Participation and \nSolutions \nIn Order No. 2222, the Commission set out to remove the barriers to distributed energy \nresource aggregations participation in wholesale markets.24 Despite the Commission issuing the \nrulemaking in September 2020, implementation of Order No. 2222 is still ongoing. For PJM,  \nDER Capacity Aggregation Resources cannot participate in the capacity auction until the \n2028/2029 Base Residual Auction.25 \nPJM will allow DER Aggregations to support a BYONC.26 The BYONC construct is a \nprogram designed to help address the capacity shortfalls that begin in the 2027/2028 Delivery \n \n23 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,083 at PP 30, 33–34 (accepting revisions that expand availability \nof surplus interconnection service and noting that PJM’s proposal “should expand the use of surplus interconnection \nservice and allow additional capacity resources to connect to the PJM system”); see also Clean Energy Associations \nSurplus Comments at 3 & n.10. \n24 Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission \nOrganizations and Independent System Operators, Order No. 2222, 172 FERC ¶ 61,247 (2020), order on \nreh'g, Order No. 2222-A, 174 FERC ¶ 61,197 (2021). \n25 PJM Interconnection, L.L.C., 187 FERC ¶ 61,180, P 1 (2024) (“PJM states that the proposed revisions would \nallow Planned DER Capacity Aggregation Resources to participate in the PJM capacity market beginning with the \n2028/2029 Base Residual Auction (BRA).”). \n26 IRAS Filing at 54."},{"page":7,"startToken":2115,"endToken":2441,"text":"7 \nYear.27 But to participate in a BYONC, the resource must be a Capacity Resource that is \ncommitted in the capacity auction.28 With capacity market access delayed until the 2028/2029 \ndelivery year,29 DERs will not be available to participate in a BYONC until a year after the \nBYONC construct begins. And even then, a DER participating in a BYONC must then face the \nadditional burden of demonstrating the Accredited UCAP requirement each year in the 10-year \nBYONC period,30 a requirement that is not imposed on other resources participating in a \nBYONC. \nEven after DERs can participate in the capacity market, and in a BYONC, other structural \nlimitations impede the ability of New Large Loads to leverage DERs in a BYONC. Several of \nthese limitations are actively being litigated in a paper hearing before the Commission.31  \nThese comments are not intended to relitigate PJM’s Order No. 2222 compliance filing. \nHowever, given the significant changes in the markets since the Commission initially accepted \nPJM’s initial Order No. 2222 compliance filing, the increasing supply chain and transmission \nconstraints facing the PJM region, and the growing interest in DER programs in the region, it \nwould be wise for PJM to reevaluate how it can unlock new, and readily available, capacity \nquickly. These comments should serve as guidance to PJM on ways to improve DER access to \nthe wholesale markets so that more resources can quickly be made available to New Large \nLoads. \n \n27 IRAS Filing at 6. \n28 IRAS Filing at 55; proposed Tariff, Attachment DD-4, section VIII(a). \n29 See PJM Interconnection, L.L.C., 187 FERC ¶ 61,180, P 1 (2024); see also Charles River Associates, Grid Under \nPressure, at 19 (Feb. 2026), https://media.crai.com/wp-content/uploads/2026/02/17103809/Grid-under-pressure-\nCRA-Energy-Report.pdf. \n30 Proposed Tariff, Attachment DD-4, section VI(b)(ii). \n31 See Voltus, Inc., and Mission:data v. PJM Interconnection, L.L.C., 196 FERC ¶ 61,074 (2026)."},{"page":8,"startToken":2441,"endToken":2557,"text":"8 \nII. \nCONCLUSION \nThe IRAS proposal is another necessary response to PJM’s growing resource adequacy \nissues. But there is much to do to ensure the program is successful. These comments do not \npropose an alternative to what PJM filed. These are recommendations that will allow New Large \nLoads to leverage what is already on the grid, or what can be added quickly, so that PJM can \nunlock the full potential of its proposal. Accordingly, SEIA requests that the Commission and \nPJM consider the market refinements identified in these comments.  \nMelissa Alfano  \nSenior Director of Energy Markets and Counsel  \nSolar Energy Industries Association  \n1425 K St NW Ste. 1000  \nWashington, DC 20005  \n(202) 566-2873  \nmalfano@seia.org"},{"page":9,"startToken":2557,"endToken":2605,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day caused the foregoing to be served upon each person \ndesignated on the official service list compiled by the Secretary in the captioned proceeding.   \nDated at Washington, D.C. this 3rd day of September, 2026. \n/s/ Melissa Alfano"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":270,"startToken":0,"endToken":318},{"p":2,"at":270,"title":"I. Comments: To make BYONC more effective, PJM must remove market barriers for","method":"printed heading","endPage":4,"endAt":3,"startToken":318,"endToken":1059},{"p":4,"at":3,"title":"A. Surplus Resources: Barriers to BYONC Participation and Solutions","method":"printed heading","endPage":6,"endAt":760,"startToken":1059,"endToken":1872},{"p":6,"at":760,"title":"B. Distributed Energy Resources: Barriers to BYONC Participation and","method":"printed heading","endPage":8,"endAt":3,"startToken":1872,"endToken":2442},{"p":8,"at":3,"title":"II. CONCLUSION","method":"printed heading","endPage":9,"endAt":0,"startToken":2442,"endToken":2557},{"p":9,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":290,"startToken":2557,"endToken":2605}]}