{"document":{"slug":"rec-20260903-5125","title":"Limited Comments of Buckeye Power, Inc. on PJM Interconnection, L.L.C.’s proposal filed on 08/13/2026","issued":"2026-09-03","accession":"20260903-5125","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Buckeye Power, Inc.","kind":"comments","file":"sources/filings/text/20260903-5125_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5125","tier":"record","sha256":"cac0aa5a8e482956c1b30e9ac85236a11940d374c767841fa34cd598ba633ec9","pages":10,"tokens":2711,"emptyPages":[],"textThemes":["flex","adequacy","registry"]},"pages":[{"page":1,"startToken":0,"endToken":272,"text":"UNITED STATES OF AMERICA  \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \nDocket No. ER26-3515-000 \n \nLIMITED COMMENTS OF BUCKEYE POWER, INC. \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedure,1 Buckeye Power, Inc. (“Buckeye”)2 \nrespectfully submits these limited comments on PJM Interconnection, L.L.C.’s (“PJM”) \nproposed revisions to its Open Access Transmission Tariff (“Tariff”) and the Reliability \nAssurance Agreement Among Load Serving Entities (“RAA”) to establish the Interim \nResource Adequacy Service (“IRAS”).3 In order to eliminate a potential unjust and \nunreasonable result, Buckeye seeks clarification as to how PJM intends to measure the \nMW quantity it directs Electric Distributors to reduce in an IRAS Action.  \nSpecifically, Buckeye seeks to avoid the possibility of PJM directing an Electric \nDistributor to drop a specified amount of MW based on registered peak loads of New \nLarge Loads that exceeds the amount of actual New Large Load demand in real time, \nwhich would require the Electric Distributor to drop existing customer load. Such an \noutcome would be contrary to PJM’s intent to address the reliability challenges caused by \nNew Large Loads unsupported by new capacity, and it would not be just and reasonable. \nPJM should therefore identify what in its proposed Tariff language or forthcoming PJM \n \n1 18 C.F.R. § 385.211. \n2 Buckeye timely intervened in this proceeding. See (doc-less) Motion to Intervene of Buckeye Power, Inc. \n(Aug. 20, 2026), eLibrary No. 20260820-5106.  \n3 PJM, Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry to Address \nSystem Reliability (Aug. 13, 2026), eLibrary No. 20260813-5118 (“PJM Filing”)."},{"page":2,"startToken":272,"endToken":527,"text":"- 2 - \n \nManuals details will prevent this problem, and the Commission should require PJM to \nclarify this issue if it does not do so on its own. To the extent further revisions to PJM’s \nproposed Tariff language are needed to address this issue, PJM should either make such \nrevisions or the Commission should direct it to do so. \nCOMMENTS \nI. \nIntroduction \nPJM is proposing IRAS as an operational tool to address the reality that New \nLarge Loads are developing more quickly than generation and transmission can be built, \nmaking it difficult for PJM to maintain a reliable electric grid while allowing these New \nLarge Loads to interconnect at their desired pace.4 The IRAS framework is intended to \nallow PJM to identify the amount in MW of New Large Loads that exceeds capacity and \norder load reduction based on that amount during potential grid emergencies. This \napproach is intended to protect existing customers, including residential customers, from \nbearing the reliability impacts caused by New Large Loads, particularly to the extent \nNew Large Loads are not supported by Bring Your Own New Capacity (“BYONC”) or a \nshare of Reliability Backstop Procurement (“RBP”).  \nAs detailed in the proposed Tariff language, PJM may initiate an IRAS Action, \n“prior to calling on Pre-Emergency Load Management Reductions Actions after \ndetermining that available economic real-time supply may not be sufficient to maintain \nreserves to meet applicable Reserve Requirements and/or Interconnection Reliability \n \n4 Id., Attach. C, Affidavit of Christopher Pilong on Behalf of PJM Interconnection, L.L.C., P 19 (“Pilong \nAff.”)."},{"page":3,"startToken":527,"endToken":918,"text":"- 3 - \n \nOperating Limits within prescribed limits and prevent cascading outages.”5 PJM has \nadded the IRAS Action early in the emergency action process, prior to calling on \nDemand Response and Deploying All Resources.6 The very last action PJM proposes to \ntake is a Manual Load Dump Action, which would require dropping existing loads and \nresidential loads that have not opted for demand response. PJM’s goal of “prevent[ing] \nManual Load Dump”7 properly recognizes that keeping existing customers, particularly \nresidential loads, online is the primary goal in the event of a grid emergency. \nAs PJM notes, “the IRAS framework is not motivated by any desire to single out \nNew Large Loads for reduction because of their size or vintage, but rather for the valid \nand legitimate reason that New Large Loads have led to periods of insufficient resource \nadequacy and should, justifiably, play a significant role in the remedy.”8 In order to \navoid perceived jurisdictional limitations, PJM states that when conducting an IRAS \nAction, it will issue MW load reduction to “Electric Distributors to implement reductions \nin load up to, and capped at, the pre-Delivery Year IRAS obligations they were \nassigned.”9 PJM states that it will be up to the Electric Distributors, not PJM, to direct \nwhich individual loads will drop in response to the directive:10 \n \n5 Id., Attach. A, Revisions to the PJM Open Access Transmission Tariff and Resource Adequacy \nAgreement (Marked/Redline Format) (“Redlined Tariff”), Attach. DD-4 § I(b). \n6 Id., Transmittal Letter at 79 (“Transmittal Letter”) (“Thus, it is appropriate for PJM to direct Electric \nDistributors to reduce those New Large Loads that have failed to cover their capacity obligations before \nrelying on Demand Resources, through Pre-Emergency Load Management Reductions Actions, to maintain \nreliability.”). \n7 Transmittal Letter at 81. \n8 Id. at 100 (emphasis added).  \n9 Pilong Aff. P 42.  \n10 Id. (footnote omitted). See also Transmittal Letter at 87 (“Thus, under the IRAS framework, the specific \nretail customers that must reduce load consumption or switch to backup resources will be determined by \nthe Electric Distributor and relevant LSEs in the zone/area, in coordination with the appropriate state and/or \nRERRA. Indeed, while PJM has proposed definitions of Large Load, New Large Load, and Eligible New \nLarge Load that may be subject to IRAS, PJM simultaneously recognizes that states may each define ‘large"},{"page":4,"startToken":918,"endToken":1401,"text":"- 4 - \n \nImportantly, PJM will not direct specific New Large Loads to \nreduce load, even though Electric Distributors—in coordination, \nwhere applicable, with relevant states, Load Serving Entities, and \nNew Large Loads—may issue more specific directives to specific \nretail customers. PJM will only direct load reduction of an aggregate \nMW IRAS within the zone or area. \n \nPJM’s filing is largely silent as to exactly how it will determine the MW amount \nwhen issuing an IRAS Action. PJM states that the “IRAS reduction MW quantity . . . will \nbe based on the IRAS quantity PJM determined for the Delivery Year.”11 PJM’s filing \ndescribes how it determines the yearly IRAS quantity based on Eligible New Large Load \nAmounts,12 which will be less than or equal to the Electric Distributor’s Eligible New \nLarge Load Amount for that year.13 But PJM’s Filing does not explain how PJM will \ndetermine the IRAS quantity it directs an Electric Distributor to cause to be reduced in a \ngiven emergency event in real-time.  \nII. \nPJM Should Clarify How IRAS MW Quantity is Determined in Real-\nTime to Protect Existing Customers from Unnecessary Shut-Off. \nBuckeye generally supports PJM’s proposal to ensure continued reliability for \nexisting customers by issuing IRAS Actions during times of grid stress, which should \n \nloads’ differently for purposes of their retail tariffs, particularly those governing load reduction protocols. \nThus, while PJM will determine the quantity of MW that load in a zone/area will need to be reduced by to \nmaintain system reliability in the PJM Region, states may determine—under their own laws, policies, and \ndefinition of what constitutes ‘large load’—which resources will be called on to reduce load.”). \n11 Transmittal Letter at 83.  \n12 Redlined Tariff, Attach. DD-4 § V(b) (“A New Large Load’s Eligible New Large Load Amount shall be \ndetermined as follows: (New Large Load’s registered peak load (in MW), as provided in the Large Load \nRegistry) minus (the sum of all BYONC arrangements with the New Large Load in accordance with Tariff, \nAttachment DD-4, section VII divided by the Forecast Pool Requirement for the first Delivery Year in \nwhich the BYONC cleared an RPM Auction, plus Allocated RBP UCAP MW assigned to the New Large \nLoad, in accordance with Tariff, Attachment DD-4, section IX divided by the Forecast Pool Requirement \nfor the first Delivery Year in which the Allocated RBP UCAP MW cleared an RPM Auction).”). \n13 Transmittal Letter at 70-72. As PJM describes, the maximum IRAS quantity will occur when the capacity \nshortfall exceeds the cumulative sum of all Eligible New Large Load Amounts, in which case all Eligible \nNew Large Load Amounts need to be available to provide IRAS. If the capacity shortfall is less than that \ncumulative sum, then only Eligible New Large Loads Amounts equal to that shortfall must be available for \nIRAS. If there is no capacity shortfall, then no amount needs to be available for IRAS."},{"page":5,"startToken":1401,"endToken":1708,"text":"- 5 - \n \nfacilitate New Large Loads not supported by new capacity (i.e., those contributing to \nreliability concerns) reducing load before existing customers are subject to curtailment. \nAdditional clarification is needed, however, as to how IRAS Actions will be implemented \nin real-time to ensure that the mechanism does not unintentionally require that existing \ncustomers, including residential loads, be unnecessarily curtailed.  \nAs detailed below, PJM should clarify how the MW quantity that PJM directs \nElectric Distributors to drop in an IRAS Action will be determined in a manner that \nensures that Electric Distributors are not required to reduce more load in real-time than is \nbeing operated by New Large Loads at that time. Buckeye is concerned that directing the \nElectric Distributor to reduce a specific amount of MW quantity based on registered peak \nload of New Large Loads determined for the Delivery Year will not match the actual \namount of load being used by the New Large Loads in real-time. If PJM were allowed to \ndirect IRAS quantities in real-time that exceed the real-time demand of New Large \nLoads, this mismatch between the peak load reported by the New Large Load in the \nregistry and the amount of load the Large Load is using in real-time could require the \nElectric Distributor to reduce existing customers, including residential loads, to make up \nthe difference. \nFor example, assume the Large Load Registry for an Electric Distributor \nzone/area shows 3,000 MW of peak load attributable to three New Large Loads for the \napplicable delivery year with 1,000 MW of BYONC. That would result in 2,000 MW of \nEligible New Large Load Amounts subject to IRAS. PJM issues a real-time IRAS Action \nthat requires the Electric Distributor to reduce 2,000 MW of load based on the Electric \nDistributor’s maximum Eligible New Large Load Amount for that Delivery Year."},{"page":6,"startToken":1708,"endToken":2022,"text":"- 6 - \n \nHowever, in real-time, the demand of the three New Large Loads is only 1,500 MW \n(perhaps because one reduced usage in response to earlier alerts, or because one or more \nof the New Large Loads are not yet fully operational). \nImportantly, because the real-time load of the New Large Loads is just \n1,500 MW, the Electric Distributor would have no ability to meet a 2,000 MW reduction \nobligation from just the New Large Loads—even though those New Large Loads are the \nsole reason the IRAS obligation exists. As a result, in this scenario, the Electric \nDistributor would be forced to reduce 500 MW of load for existing customers, which \nmay impact residential loads and other non-New Large Load end-users. Moreover, that \nadditional 500 MW of curtailment from non-large load customers would be unnecessary, \nas an IRAS quantity equal to the New Large Load’s real-time load should be sufficient to \naddress the reliability impacts of New Large Loads unsupported by new capacity. \nThis outcome is clearly contrary to PJM’s intent, which is to base the IRAS load \nreduction obligation specifically on the extent to which New Large Loads have failed to \ncover their capacity obligations with new generation. Nothing in PJM’s desire to provide \nflexibility to states and Relevant Electric Retail Regulatory Authorities (“RERRAs”) \nsuggests an intent that Electric Distributors would be forced to reduce existing customers’ \nload as a result of New Large Loads. Indeed, PJM’s emphasis that load curtailment is the \nlast resort, with IRAS Actions coming well before that, confirms that existing customers \nare not intended to be forced to bear the burden of IRAS reductions. \nBuckeye asks that PJM clarify how the MW amounts Electric Distributors will be \nasked to curtail will be determined in a real-time IRAS Action, and whether this \ndetermination will consider the actual demand of the New Large Loads in real-time to"},{"page":7,"startToken":2022,"endToken":2360,"text":"- 7 - \n \navoid requiring impacts to existing customer load described above. Specifically, PJM \nshould ensure that the amount of MWs the Electric Distributor is required to drop in \nresponse to an IRAS Action will not exceed the amount of MWs being used by the New \nLarge Loads in real-time.14 This clarification will still allow the Electric Distributors, \nworking with its applicable state or RERRA, to determine how the MW drop will be \nassigned to individual loads, while at the same time ensuring that Electric Distributors are \nnot put in the position of being forced to drop existing load (the action of last resort to \nmaintain grid integrity) to comply with an IRAS Action. \nTo the extent that the proposed Tariff language must be revised to make this \nclarification, PJM should do so. To the extent PJM does not voluntarily do so, the \nCommission should direct it to make these changes in order to protect existing customers \nfrom reliability impacts caused by New Large Loads and to ensure just, reasonable, and \nnot unduly discriminatory rates. At minimum, if PJM does not clarify this issue \nconsistent with Buckeye’s limited comments herein, the Commission should issue a \ndeficiency letter directing PJM to explain how the existing proposal is just, reasonable, \nand not unduly discriminatory.  \nPJM has already consented to make modifications “consistent with PJM’s \noverarching objectives in this filing,”15 which the clarification described above would be. \nAnd although clarification of this issue is important to protecting everyday ratepayers, it \nis permissible because it would not result in an entirely different rate design than what \n \n14 For example, PJM should consider clarifying that the Electric Distributor would fulfill the IRAS Action \nby dropping the New Large Load to zero if the total IRAS Action MW directive exceeds the actual amount \nof New Large Load online in real-time. Where the New Large Load is an incremental increase of an \nexisting load, the Electric Distributor would fulfill the IRAS Action by reducing the load to its prior output. \n15 Transmittal Letter at 122."},{"page":8,"startToken":2360,"endToken":2600,"text":"- 8 - \n \nPJM has proposed.16 Rather, it is a change to one element in order to ensure PJM’s IRAS \nproposal functions as intended and without forcing non-large load ratepayers to bear the \nreliability burdens caused by New Large Loads.17 \nCONCLUSION \n \nFor the reasons stated above, the Commission should (to the extent PJM does \nnot do so on its own) require PJM to clarify how it will calculate the IRAS Action \nreduction quantity in real-time, including whether that amount could exceed New Large \nLoad in real-time such that an Electric Distributor is forced to curtail other, existing \ncustomers. To the extent Tariff revisions are required to prevent this problem, the \nCommission should direct PJM to make those further revisions to the extent it does not \ndo so voluntarily.  \n \n \n \n \n \n \n \n \n \n16 Old Dominion Elec. Coop., 162 FERC ¶ 61,262, P 35 (2018) (“[T]he Commission may propose revisions \nto a section 205 filing that do not amount to an entirely different rate design or rate scheme, provided that \nthe filing utility consents to the changes.” (citing NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 116-117 \n(D.C. Cir. 2017))). \n17 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,210, P 62 (2026) (directing a \ncompliance filing “to incorporate into the Tariff language clarifying MISO’s stated intent” regarding one \nelement of a filing to reform its tariff provisions on demand-side resources and certain supply-side \nresources participating during emergencies)."},{"page":9,"startToken":2600,"endToken":2662,"text":"- 9 - \n \n \nRespectfully submitted, \n/s/ Jeffery M. Bayne  \nJeffrey M. Bayne \nSpiegel & McDiarmid LLP \n1818 N Street, NW \n8th Floor \nWashington, DC 20036 \nPhone: (202) 879-4000 \nKurt P. Helfrich \nGeneral Counsel \nLija Kaleps-Clark \nDeputy General Counsel \nBuckeye Power, Inc. \n6677 Busch Boulevard \nColumbus, Ohio 43229 \nTelephone: (614) 681-5151 \nkhelfrich@ohioec.org  \nlkaleps@ohioec.org \nCounsel for Buckeye Power, Inc. \nDated:  September 3, 2026"},{"page":10,"startToken":2662,"endToken":2711,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day caused the foregoing document to be served \nupon each person designated on the official service list compiled by the Secretary in this \nproceeding. \nDated on this 3rd day of September, 2026. \n \n \n \n/s/ Jeffrey M. Bayne  \n \nJeffrey M. Bayne"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":342,"startToken":0,"endToken":330},{"p":2,"at":342,"title":"I. Introduction","method":"printed heading","endPage":4,"endAt":1019,"startToken":330,"endToken":1084},{"p":4,"at":1019,"title":"II. PJM Should Clarify How IRAS MW Quantity is Determined in Real-","method":"printed heading","endPage":8,"endAt":238,"startToken":1084,"endToken":2400},{"p":8,"at":238,"title":"CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2400,"endToken":2662},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":303,"startToken":2662,"endToken":2711}]}