{"document":{"slug":"rec-20260903-5133","title":"Comments of the Public Service Commission of West Virginia re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service","issued":"2026-09-03","accession":"20260903-5133","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Public Service Commission of West Virginia","kind":"comments","file":"sources/filings/text/20260903-5133_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5133","tier":"record","sha256":"7f531628cae8ef1ea8ffd69e33dffc997869d9932e99b993fe66458ae8cfc2d8","pages":7,"tokens":1527,"emptyPages":[],"textThemes":["retail","flex"]},"pages":[{"page":1,"startToken":0,"endToken":300,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \n \nCOMMENTS OF THE PUBLIC SERVICE COMMISSION OF WEST VIRGINIA  \n \n \nThe Public Service Commission of West Virginia (“PSCWV”) respectfully files these \ncomments to address concerns regarding PJM’s August 13, 2026, filing to establish Interim \nResource Adequacy Service (“IRAS”) — a service to be implemented by PJM solely during \nperiods when there are insufficient resources to reliably meet demand in real time operations. PJM \nexplains that “IRAS will enable PJM to prioritize load reduction in zones/areas where New Large \nLoads have not brought their own new capacity or had their capacity needs covered through the \nReliability Backstop Procurement (“RBP”). New Large Loads can avoid this condition on taking \ntransmission service by bringing new capacity to the system.” \nThus, the only New Large Load (NLL) that will be at risk of prioritized or first-in-line \ncurtailment under the new PJM proposal are those that have failed to cover their own capacity \nrequirement (“Uncovered NLL”).1  Although the IRAS is targeted to Uncovered NLL, PJM \nattempts to navigate the maze between clear Federal jurisdiction over interstate transmission, \nimplicit Federal jurisdiction over retail transactions that might affect wholesale electricity markets, \nand clear state jurisdiction over retail service and  rates.  PJM states that the IRAS “has been \ncarefully designed to respect the cooperative federalism approach established under the FPA and \nanimating several other recent landmark Commission determinations.”  PJM supports its filing to \ninvolve the Federal Energy Regulatory Commission (“Commission”) in retail service describing \n                                                 \n1 PJM refers to New Large Load that has not covered its own needs by supplying its own capacity as “Eligible New \nLarge Load.”  That description is accurate and clear in reference to the IRAS, but we refer to that load more generally \nas being “Uncovered.”"},{"page":2,"startToken":300,"endToken":676,"text":"2 \n \nit as “an example of the federal regime helping to effectuate state decisions associated with the \nrates, terms, and conditions of retail service.” \nThe PSCWV does not fully support PJM’s structure to address unusual and historic \ncapacity needs created by growth in NLL, mostly associated with the growth of data centers, \nhowever, it does agree with the goals enumerated in the Administration’s Ratepayer Protection \nPledge and similar ratepayer protections plans put forth by the Governors of the thirteen PJM \nStates.  PJM refers to the Pledge and ratepayer protection in its filing and appears to understand \nthe need to protect non-NLL customers (“Other Customers”) from costs associated with all NLL \ngenerally and  Uncovered NLL particularly.  Yet, its filing contains a provision to provide a \nwholesale rate credit to effectively pay Uncovered NLL for mandatory curtailments that are \napplicable to NLL only because they elected to add Uncovered Load.  It is that credit that the \nPSCWV opposes and requests that the Commission reject. \nThe concept of compensation through any rate to be paid based on uncovered NLL that is \ninterrupted is, if given to the Uncovered NLL,  the antithesis of everything that is intended to be \nachieved by the Ratepayer Protection Pledge.  PJM admits in its filing that: “A rate of zero dollars \nfor IRAS would apply where Eligible New Large Loads “waive”2 in their retail rates receipt of \ncompensation for the provision of wholesale Interim Resource Adequacy Service—an outcome \nthat would be consistent with the Ratepayer Protection Pledge signatories’ commitment ‘to protect \nAmerican consumers from price hikes due to data center energy and infrastructure requirements, \nand lower electricity costs for consumers in the long term.’”  Yet, by offering a rate, or \n                                                 \n2 The PJM filing references the option of a lower or zero rate as residing with the Uncovered NLL to “waive” the \nCommission-approved rate credit, “agree” to a lower rate, or “voluntarily negotiate” to not receive the wholesale rate \ncredit.  This is troubling since PJM later implies that who gets the credit is solely the choice of the retail rate regulator.  \nThus, PJM in its filling admits to the potential future tension between the pass-through of a rate credit federally targeted \nto a particular demand response customer to that customer or Other Customers."},{"page":3,"startToken":676,"endToken":982,"text":"3 \n \ncompensation, to Uncovered NLL for IRAS the PJM tariff establishes an unnecessary potential \nconflict at the retail level.  \nIf the Uncovered NLL receives the compensation, a cost is created that would fall on Other \nCustomers.  Because that “cost” is solely due to payments to the Uncovered NLL, the PJM tariff, \nif approved, creates a cost that would not exist, but for the Uncovered NLL.  The only choice that \nStates would have to prevent  rate increase on Other Customers is to prohibit the compensation \nfrom going to the Uncovered NLL and use it to offset the cost when setting rates for Other \nCustomers.   \nPJM defends its complicated and unnecessary payment to Uncovered NLL by assuming \naltruism of the Uncovered NLL.  PJM explains: “PJM’s proposal also allows Eligible New Large \nLoads to agree upon a retail rate between 50% of the Non-Performance Charge Rate and zero \ndollars, to further facilitate implementation of the Ratepayer Protection Pledge and retail level \narrangements.”  What happens if the Eligible New Large Load does not agree to a lower rate or \nzero?  If the Commission approves the PJM proposal it will set up a potential conflict if an Eligible \nNew Large Load does not “agree” to waive its Commission-approved wholesale compensation for \ninterpretability and a State retail regulatory authority denies it that compensation, which it would \nhave to do to protect other Customers. This regulatory free-for-all could be further complicated in \nmulti-state PJM Zones where the states have conflicting interests and policies for passing through \nthe PJM IRAS compensation to Uncovered NLL or Other Ratepayers under their individual \njurisdiction. \nThe complexity, pitfalls, and potential for adding costs on Other Customers created by the \nPJM proposal can be simply resolved by rejecting the IRAS compensation.  It is unjust and \nunreasonable to pay Uncovered NLL for a capacity deficiency-driven curtailed when it could have"},{"page":4,"startToken":982,"endToken":1280,"text":"4 \n \nbeen insulated from being first-in-line for curtailment by arranging for new capacity  but decided \nto go forward as Uncovered NLL, thereby creating the capacity deficiency.  \nCONCLUSION \nThe State of West Virginia, the other states in PJM and the White House have similar \npublic policies that NLL, mostly data centers, must not come at the expense of residential or \ncommercial utility customers. The PSCWV fully supports the West Virginia State policy that, \nconsistent with the national Ratepayer Protection Pledge, developers will build, bring, or procure \nsufficient power resources and assume responsibility for infrastructure investments necessary to \nserve their projects. This approach reinforces the State’s commitment to ensuring that utility costs \nassociated with large-scale data center development are not shifted to West Virginia ratepayers \nwhile promoting a stronger, more resilient electric grid.  While we believe there could be \nimprovements to the PJM proposal to manage Uncovered NLL, it generally  furthers the goal of \nprotecting Other Customers, except for the IRAS compensation to Uncovered NLL.  While West \nVirginia as a fully retail regulated state with vertically integrated electric utilities has regulatory \ntools to set retail rates for Uncovered NLL that protect Other Ratepayers, those tools could be \nchallenged if the Commission approves the PJM wholesale compensation for interruption of \nUncovered NLL and those loads do not “voluntarily” turn down receiving that compensation.  The \nPSCWV would have to order that the payments that were specifically calculated based on the \nUncovered NLL not be assigned and paid to that load in order to protect Other Customers.  The \nfederal/state tension that such action would set up is problematic, both administratively and legally.  \nThat tension is easily avoided if the Commission rejects that portion of the PJM tariff, which it \nshould because the payments are not only unnecessary, they are unjust and unreasonable."},{"page":5,"startToken":1280,"endToken":1332,"text":"5 \n \nRespectfully submitted this 3rd day of September, 2026. \n \nPublic Service Commission of West Virginia, \nby counsel \n \n \n \n     /s/ Susan M. Stewart \nSusan M. Stewart, Associate General Counsel \nWV State Bar I.D. No. 7342 \nsstewart@psc.state.wv.us \n201 Brooks Street, Post Office Box 812 \nCharleston, West Virginia 25323 \n(304) 340-0450"},{"page":6,"startToken":1332,"endToken":1408,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that the foregoing has been served in accordance with 18 C.F.R. §385.2010 \nupon each person designated on the official service list compiled by the Secretary in this \nproceeding.  \n \nDated at this 3rd day of September, 2026. \nSusan M. Stewart, Associate General Counsel \nsstewart@psc.state.wv.us \n201 Brooks Street, Post Office Box 812 \nCharleston, West Virginia 25323 \n(304) 340-0450 \n \n \n \n \n \n \n \n \n \n \n     /s/ Susan M. Stewart____________ \nSusan M. Stewart"},{"page":7,"startToken":1408,"endToken":1527,"text":"Public Service Commission  \n \n \n \n \n \nSusan M. Stewart, Associate General Counsel \n201 Brook Street, P.O. Box 812 \n \n \n \n \n       Phone: (304) 340-0450 \nCharleston, WV  25323 \n \n \n \n \n \n \nFax: (304) 340-3758 \n \n \n \n \n \n \n \n   E-mail: sstewart@psc.state.wv.us \n \n \nSeptember 3, 2026 \n \nThe Honorable Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \n888 First Street, N.E. \nWashington, D.C. 20426 \n \nRe: \nDocket No. ER26-3515-000 \n \nDear Secretary Reese: \n \nEnclosed for filing in the above referenced proceeding is the Comments of the Public \nService Commission of West Virginia. \n \nCopies of this document have been sent to the persons named on the Service List in \nthis proceeding. \n \n \n \n \n \n \n \n \nRespectfully submitted, \n \n \n \n \n \n \n \n \nSusan M. Stewart \n \n \n \n \n \n \n \n(filed electronically) \n \n \n \n \n \n \n \n \n \n \n \nSusan M. Stewart  \nAssociate General Counsel  \n \n \n \n \n \n \n \nWV State Bar I.D. No. 7342 \n \n \nSMS/rm"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":181,"startToken":0,"endToken":1008},{"p":4,"at":181,"title":"CONCLUSION","method":"printed heading","endPage":6,"endAt":0,"startToken":1008,"endToken":1332},{"p":6,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":940,"startToken":1332,"endToken":1527}]}