{"document":{"slug":"rec-20260903-5134","title":"Comments of Dominion Energy Services, Inc. o/b/o its affiliate, Virginia Electric and Power Company d/b/a Dominion Energy Virginia re PJM Interconnection,…","issued":"2026-09-03","accession":"20260903-5134","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Dominion Energy Services, Inc.","kind":"comments","file":"sources/filings/text/20260903-5134_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5134","tier":"record","sha256":"fdbd4cac5c88907a3b4138b3a7135295f978c96df435dabb0c4da42b9efbf00a","pages":11,"tokens":3113,"emptyPages":[],"textThemes":["adequacy","retail","registry"]},"pages":[{"page":1,"startToken":0,"endToken":260,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C. \n) \n) \n) \nER26-3515-000\n \n \nCOMMENTS OF DOMINION ENERGY SERVICES, INC. \n \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or “Commission”),1 Dominion Energy Services, Inc. on behalf \nof its affiliate, Virginia Electric and Power Company d/b/a Dominion Energy Virginia (“Dominion \nEnergy Virginia”), hereby submits the following comments in the above captioned proceeding \nregarding PJM Interconnection, L.L.C.’s (“PJM”) proposal to establish a new supplemental \ncapacity product, the Interim Resource Adequacy Service (“IRAS”), and related new obligations \ndeemed necessary to support it.2   \nDominion Energy Virginia, a subsidiary of Dominion Energy, Inc., is a public service \ncorporation organized under the laws of the Commonwealth of Virginia and a public utility subject \nto regulation by the Commission and does business in the Commonwealth of Virginia and in the \nState of North Carolina. It is a regulated, vertically integrated public utility engaged in the \ngeneration, transmission, distribution, and sale of electric energy. Dominion Energy Virginia \nfurnishes electric service to approximately 2.8 million retail customers in its approximately 30,000 \nsquare miles of certificated service territory covering parts of Virginia and North Carolina. To \nprovide that service, Dominion Energy Virginia owns and operates a diverse fleet of nuclear, oil, \n \n1 18 C.F.R. §§ 385.211 (2026). \n2 PJM Interconnection, L.L.C., Docket No. ER26-3515-000 (August 13, 2026) (“PJM Filing”). Dominion Energy \nServices, Inc. filed a “doc-less” intervention in this proceeding on August 25, 2026."},{"page":2,"startToken":260,"endToken":644,"text":"2 \n \nbiomass, pumped storage, hydro, coal, solar, wind and natural gas-fired electric generating \ncapacity of approximately 21,000 megawatts. Dominion Energy Virginia owns 6,800 miles of \nelectric transmission lines in Virginia, North Carolina and West Virginia, which is operated by \nPJM. Dominion Energy Virginia joined PJM effective May 1, 2005, after obtaining prior approval \nfrom the Commission, the Virginia State Corporation Commission, and the North Carolina Utilities \nCommission.3 \nI. \nIntroduction \nThe PJM Filing proposes reforms to the PJM Open Access Transmission Tariff (“Tariff”) \nand the Reliability Assurance Agreement Among Load-Serving Entities in the PJM Region \n(“RAA”) to establish IRAS, a load reduction service associated with PJM’s capacity market, that \nwill be in effect when the capacity market clears short of the PJM Reliability Requirement.4  New \nLarge Loads added to the system without matching new capacity will be required to provide IRAS, \ni.e., be interruptible at PJM’s direction, during the Delivery Year.  To establish IRAS, PJM proposes \nseveral other related changes as part of the framework. \nFirst, PJM proposes to clarify that Load Serving Entities (“LSE”) interconnecting New \nLarge Loads in a Delivery Year must bring new capacity in an amount that equals or exceeds the \nNew Large Loads’ peak load as of the commencement of that Delivery Year.  To the extent that \nthey do not fully cover the peak load, the difference will be considered IRAS eligible and subject \n \n3 PJM Interconnection, L.L.C., 109 FERC ¶ 61,012 (2004), on reh’g in part, 110 FERC ¶ 61,234 (2005); Ex Parte: \nIn the matter concerning the application of Virginia Electric and Power Company d/b/a Dominion Virginia Power \nfor approval of a plan to transfer functional and operational control of certain transmission facilities to a regional \ntransmission entity, V.S.C.C. Case No. PUE-2000-00551, Order Granting Approval (Nov. 10, 2004); In the Matter \nof Application of Virginia Electric and Power Company, d/b/a Dominion North Carolina Power, for Authority to \nTransfer Functional Control of Transmission Assets to PJM Interconnection, LLC, N.C.U.C. Docket No. E-22, Sub \n418, Order Approving Transfer Subject to Conditions (Apr. 19, 2005). \n4 Capitalized terms not otherwise defined herein have the meaning as defined in the Tariff, Amended and Restated \nOperating Agreement of PJM Interconnection, L.L.C., and the RAA."},{"page":3,"startToken":644,"endToken":942,"text":"3 \n \nto reduction requests during Emergencies prior to Pre-Emergency Load Management Response.5  \nSecond, PJM plans to establish a Large Load Registry to track Large Loads currently on the system \nand New Large Loads that will interconnect in the future.  The registry will inform load forecasts \nand provide information needed to implement IRAS from an eligibility and operational \nstandpoint.6  Third, PJM defines Bring Your Own New Capacity (“BYONC”) to establish the \ncategory of new capacity that is required to cover New Large Loads’ peak load and avoid \ndesignation as IRAS for a Delivery Year.7  Fourth, PJM proposes to exclude IRAS eligible load \nfrom the VRR Curve used in the Base Residual Auctions (“BRA”) and Incremental Auctions \n(“IA”).  By doing so, capacity auction clearing prices will not be influenced by LSE’s that fail to \nbring sufficient new capacity online to cover New Large Loads.8  Finally, PJM proposes a \ncompensation mechanism for IRAS Large Loads that PJM curtails during a Delivery Year due to \nsystem conditions.  PJM requires Electric Distributors to implement the compensation scheme but \nwill defer to the states and their Relevant Electric Retail Regulatory Authorities (“RERRAs”) to \nthe extent they establish specific retail rates addressing the proposed compensation.9  \nDominion Energy Virginia generally supports the proposed framework for IRAS.  \nHowever, PJM’s approach for implementation as presented in the transmittal letter and the Tariff \namendments raises concerns that it will not accommodate all business models and state regulatory \nframeworks within the PJM Region.  The following comments highlight where PJM’s proposal \nshould be further clarified, either through the Commission’s order or a requirement for PJM to \nsubmit a compliance filing.  \n \n5 PJM Filing at p. 21. \n6 Id. at p. 22. \n7 Id. at p. 23. \n8 Id. at pp. 23-24. \n9 Id. at pp. 27-28."},{"page":4,"startToken":942,"endToken":1355,"text":"4 \n \n  \nII. \nComments \nPJM correctly recognizes that LSEs should have an affirmative obligation to procure new \ncapacity to cover any new Large Loads they seek to interconnect and serve during a Delivery Year. \nLSEs are the wholesale entities serving retail customers, and the costs and obligations for Large \nLoads, which are retail customers, should flow through the LSEs.  Some of the current resource \nadequacy shortfall in PJM can be attributed to the lack of incentives for LSEs to procure new \ncapacity outside the BRA and LSEs relying solely on the BRA to procure needed new capacity.10  \nPJM’s proposed amendment to the RAA to clarify LSE obligations is a needed first step toward \nreestablishing resource adequacy obligations. \nMuch of PJM’s proposed framework, however, moves needlessly from federal wholesale \njurisdiction into retail jurisdiction and is likely to cause confusion and potential legal challenges.  \nInstead of establishing IRAS obligations with the LSE, the wholesale jurisdictional entity, PJM \nfocuses its proposal from the perspective of Large Loads, the retail customer. For example, PJM \nchooses to call new capacity eligible to cover New Large Loads, “Bring Your Own New Capacity,” \na term that suggests that the only way for New Large Loads to avoid IRAS is to enter their own \narrangements for new capacity.  In describing the BYONC concept, PJM states “to the extent a \nNew Large Load does not want to provide IRAS, it needs to contract with new capacity that meets \n \n10 See PJM, Considerations to Better Align Default Service Programs with PJM Capacity Market, February 2026, at \npp. 1 and 11, available at https://www.pjm.com/-/media/DotCom/library/reports-notices/special-\nreports/2026/20260218-considerations-for-default-service-programs-to-better-align-with-pjm-wholesale-\nmarkets.pdf, (“Currently, none of PJM’s seven restructured state procure capacity outside of the capacity market.” \nAnd “Currently, these [restructured] states rely heavily, if not exclusively, on PJM’s capacity market to fulfill their \nresource adequacy needs. The capacity market, also known as the Base Residual Auction, was initially intended to \nbe a truly residual market for states to procure for additional unfilled capacity needs, not to serve as the primary \nmarket to satisfy such needs.”) See also, PJM, Prefiled Statement of Manu Asthana o/b/o PJM Interconnection, \nL.L.C. under AD25-7, Docket No. AD25-7-000, at p. 6 (“Load serving entities in some regions appear to be \nprimarily relying on the spot capacity market rather than using bilateral contracting first, and using the capacity \nmarket as a secondary, residual market. This is exacerbating the affordability challenges referenced above.”)"},{"page":5,"startToken":1355,"endToken":1663,"text":"5 \n \nthe BYONC gating criteria.”11 Proposed Tariff Attachment DD-4 Section VII, titled “Bring Your \nOwn New Capacity Arrangements with New Large Loads”, is written to only consider \n“arrangements” that represent a contractual agreement between a New Large Load and a “resource \nowner.”  The section places only a reporting obligation on the LSE suggesting that they are not \nassociated with any BYONC designated to cover the New Large Loads they will serve during the \nDelivery Year.12 \nThis myopic view fails to consider that the regulatory framework for retail electric service \ncan differ between states and also between LSEs operating within those states.  In Virginia, for \nexample, Vertically Integrated Utilities (“VIU”) like Dominion Energy Virginia have an obligation \nto interconnect and serve new customers, including Large Loads, and utilize integrated resource \nplanning to identify the appropriate build out of new capacity to address resource adequacy needs. \nThe costs for Dominion Energy Virginia to serve Large Loads are allocated through retail rates \ndesigned to ensure that Large Load customers pay their fair share.  There is not an obligation for \nLarge Loads seeking to interconnect in Dominion Energy Virginia’s franchised territory to either \nbuild or contract for new capacity.  In the IRAS framework, Dominion Energy Virginia as LSE \nwill be the entity arranging for new capacity to cover New Large Load expected to interconnect \nduring the Delivery Year.  New Large Loads “bringing their own new capacity” should not be the \nonly means to avoid IRAS, as conveyed by the Tariff.  \nIt is likely that PJM chose its IRAS approach to align the design with the Ratepayer \nProtection Pledge13 and to accommodate the regulatory framework in restructured states where \n \n11 PJM Filing at p. 23 (emphasis added). \n12 Proposed Tariff Attachment DD-4, Section VII (a). \n13 Ratepayer Protection Pledge, The White House (March 4, 2026)(available at https://perma.cc/N8PH-K82T)."},{"page":6,"startToken":1663,"endToken":2026,"text":"6 \n \nutilities do not own or build new capacity.14  However, by framing the pathway for avoiding IRAS \nbased solely on the New Large Load bringing their own new capacity, PJM’s proposal will \nassuredly cause confusion in states with VIUs or other utilities that self-supply their capacity \nrequirements.  It also creates a disconnect between the resource adequacy obligation PJM seeks to \nplace on LSEs in the RAA and the language in the proposed Tariff amendments that place the \nobligation solely on New Large Loads.   \nIf the Commission approves the PJM Filing, it should make clear in its order that IRAS \nand BYONC provisions also accommodate Vertically Integrated Utilities and other self-supply \nentities that plan generation build out to meet customer load growth in their territories.  As PJM \nstates, there is a need for “regulatory certainty,” but as presented the PJM proposal does not provide \nthat certainty absent additional clarifications and potentially revised Tariff language.15  Tariff \namendments would not require any significant change to the proposal itself but would involve \nreframing the obligations from the standpoint of the LSE serving the New Large Load.   \nAttachment A to this filing provides example edits to PJM’s proposed Tariff Attachment DD-4, \nSection VII to accomplish this adjusted approach.  Additional conforming edits would be required \nthroughout the Tariff and the RAA. \n \n \n \n14 It should be noted that the PJM Board of Managers took a broader, more appropriate view of the BYONC concept \nwhen it issued its letter initiating the Critical Issue Fast Path process that resulted in this filing. See Board \nDecisional Letter on Critical Issue Fast Path - Large Load Additions, PJM Board of Managers at p. 3 (“Create \nincentives for Load Serving Entities (LSEs), large loads and/or states to bring new capacity resources to offset their \nload additions consistent with cost causation principles”)(January 16, 2026)(available at https://www.pjm.com/-\n/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-\nprocess-large-load-additions.pdf). The Board also recognized the federal/state jurisdictional issue raised in these \ncomments.  See Id. (“The Board is mindful of the jurisdictional limits of PJM’s authority, which apply to PJM’s \nrelationship with LSEs rather than individual retail customers.”) \n15 PJM Filing at p.8."},{"page":7,"startToken":2026,"endToken":2142,"text":"7 \n \nIII. \nConclusion \nDominion Energy Virginia respectively requests that the Commission issue an order \ngranting PJM’s proposed Tariff revisions subject to clarification of the issues discussed above or \nsubject to a compliance requirement for PJM to submit amended Tariff language reframing the \nobligations from the standpoint of the LSE serving New Large Load.  \n \nRespectfully submitted, \n/s/ Wesley Walker \n \nWesley Walker \nManaging Counsel \nDominion Energy Services, Inc. \n120 Tredegar Street \nRichmond, VA 23219 \n(804)-819-2345 \nwesley.walker@dominionenergy.com \n/s/ James G. Davis \n \nJames G. Davis \nRegulatory and Market Policy Senior Strategic \nAdvisor \nDominion Energy Services, Inc. \n120 Tredegar Street \nRichmond, VA 23219 \n(804)-819-2718 \njames.g.davis@dominionenergy.com \nOn behalf of Dominion Energy Services, Inc"},{"page":8,"startToken":2142,"endToken":2154,"text":"8 \n \n \n \nATTACHMENT A \nSample Redlines to Proposed Tariff Attachment DD-4, Section VII"},{"page":9,"startToken":2154,"endToken":2640,"text":"9 \n \nVII. \nREQUIREMENTS FOR ASSOCIATING BRING YOUR OWN NEW \nCAPACITY ARRANGEMENTS WITH NEW LARGE LOADS \n \n(a) \nFor any BYONC to be in an arrangement associated with a New Large Load, the Load \nServing Entity serving the New Large Load or the applicable Electric Distributor shall \nreport the BYONC associated with the New Large Load in accordance with the PJM \nManuals. \n \n(i)   If the BYONC is owned or affiliated with the Load Serving Entity serving the \nNew Large Load, the Load Serving Entity must certify to the Office of \nInterconnection, in accordance with the PJM Manuals, attesting that the BYONC \nwill follow the requirements of Tariff, Attachment DD-4, section VIII. the Load \nServing Entity serving the New Large Load or the applicable Electric Distributor \nshall report the BYONC in an arrangement with the New Large Load, in accordance \nwith the PJM Manuals. The Office of the Interconnection may also accept \ninformation to the extent interconnection customers, Large Loads, Transmission \nOwners, or other entities voluntarily report any BYONC that may be in an \narrangement with a New Large Load; and \n \n(ii)  If the BYONC is not owned by or affiliated with the Load Serving Entity \nserving the New Large Load, the resource owner or entity with contractual authority \nover the BYONC to enter into a BYONC arrangement must certify to the Office of \nInterconnection, in accordance with the PJM Manuals, attesting to the arrangement \nthat the BYONC will be associated with the New Large Load and that the BYONC \nwill follow the requirements of Tariff, Attachment DD-4, section VIII. \n \n(b)   For BYONC associated with an arrangement between a New Large Load and \nBYONC to be effective for the 2027/2028 and 2028/2029 Delivery Years, for any \nassociated BYONC arrangement to be considered, the requirements of Tariff, Attachment \nDD-4, section VII(a) must be met by April 1 for the first Delivery Year such arrangement \nassociation is to result in a reduction in the New Large Load’s Eligible New Large Load \nAmount. By April 15, the Office of the Interconnection shall update the Large Load \nRegistry to reflect any verified arrangements associations between New Large Loads and \nBYONC. \n \n(c)   For BYONC associated with an arrangement between a New Large Load and BYONC \nto be effective for the 2029/2030 Delivery Year, for any associated BYONC arrangement \nto be considered, the requirements of Tariff, Attachment DD-4, section VII(a) must be \nreported to the Office of the Interconnection no later than by 50 days prior to the \ncommencement of the 2029/2030 Base Residual Auction or by 30 days prior to the posting \nof the planning parameters for the Incremental Auctions arrangement for the 2029/2030 \nDelivery Year. The Office of the Interconnection shall update the Large Load Registry to \nreflect any verified arrangements associations between New Large Loads and BYONC \nafter the relevant RPM Auction. \n \n(d)   For BYONC associated with an arrangement between a New Large Load and"},{"page":10,"startToken":2640,"endToken":3058,"text":"10 \n \nBYONC to be effective for the 2030/2031 Delivery Year and subsequent Delivery Years, \nthe requirements of Tariff, Attachment DD-4, section VII(a) must be reported to the Office \nof the Interconnection no later than by 30 days prior to the posting of the planning \nparameters for the relevant RPM Auction for the initial Delivery Year the BYONC enters \ninto an arrangement with the New Large Load. The Office of the Interconnection shall \nupdate the Large Load Registry to reflect any verified arrangements associations between \nNew Large Loads and BYONC after the relevant RPM Auction. \n \n(e)   BYONC that is in an arrangement associated with a New Large Load must remain in \nsuch arrangement associated with that New Large Load unless and until the New Large \nLoad is permanently out-of-service. \n \n(f)     A physical resource may support multiple BYONC, each of which may be in an \narrangement associated with different New Large Loads, as long as no BYONC is in an \narrangement associated with more than one New Large Load. \n \n(g) \nA Load Serving Entity may associate New Large Load may enter into an \narrangement with discrete BYONC supported by different physical resources. \n \n(h)   A Load Serving Entity may associate New Large Load may enter into an arrangement \nwith BYONC in excess of its current Eligible Large Load Amount, e.g., to allow for \nexpected growth in the New Large Load, and the full megawatt quantity of such BYONC \nshall be offered in the first RPM Auction for which the New Large Load is included in the \nVariable Resource Requirement Curve,. \n \n(i)  For any generation or storage resource, the Accredited UCAP of any BYONC \nshall be the Accredited UCAP for the RPM Auction in which the BYONC cleared \nfor the initial Delivery Year the BYONC is in an arrangement with the New Large \nLoad. \n \n(ii)  For Demand Resources or DER Capacity Aggregation Resources, the \nAccredited UCAP shall be the Accredited UCAP for the RPM Auction in which \nthe BYONC cleared for the initial Delivery Year the BYONC is in an arrangement \nwith the New Large Load and must be demonstrated each year for a 10-year period \nusing the Demand Response or DER Capacity Aggregation Resources installed \ncapacity for the first Delivery Year after the BYONC is in an arrangement with the \nNew Large Load. For Demand Resources or DER Capacity Aggregation Resources \nthat are also the actual New Large Load, there is no demonstration required for the \ninitial Delivery Year only to not be an Eligible New Large Load."},{"page":11,"startToken":3058,"endToken":3113,"text":"11 \n \nCERTIFICATE OF SERVICE \nI hereby certify that in accordance with Rule 2010 of the Commission’s \nRules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026), I have served a copy of the \nforegoing to all parties on the official service list in these proceedings.   \n \n/s/ Wesley Walker\nWesley Walker\n \n \nSeptember 3, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":493,"startToken":0,"endToken":330},{"p":2,"at":493,"title":"I. Introduction","method":"printed heading","endPage":4,"endAt":8,"startToken":330,"endToken":943},{"p":4,"at":8,"title":"II. Comments","method":"printed heading","endPage":7,"endAt":5,"startToken":943,"endToken":2027},{"p":7,"at":5,"title":"III. Conclusion","method":"printed heading","endPage":8,"endAt":9,"startToken":2027,"endToken":2143},{"p":8,"at":9,"title":"ATTACHMENT A","method":"printed heading","endPage":9,"endAt":5,"startToken":2143,"endToken":2155},{"p":9,"at":5,"title":"VII. REQUIREMENTS FOR ASSOCIATING BRING YOUR OWN NEW","method":"printed heading","endPage":11,"endAt":6,"startToken":2155,"endToken":3059},{"p":11,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":327,"startToken":3059,"endToken":3113}]}