{"document":{"slug":"rec-20260903-5156","title":"Comments and Limited Protest of NRG Business Marketing LLC, et. al. re the Interim Resource Adequacy Service proposed by PJM Interconnection, L.L.C","issued":"2026-09-03","accession":"20260903-5156","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"NRG Business Marketing LLCNRG Energy, Inc.Aspen Gen Funding, LLC ,Direct Energy Business, LLC ,Doswell, LLC ,Energy Plus Holdings LLC ,Enerwise Global Technologies, LLC ,Green Mountain Energy Company ,Helix Ironwood LLC ,Independence Energy Group LLC ,LSP University Park, LLC ,Midwest Generation LLC ,NRG Curtailment Solutions, Inc. ,Reliant Energy Northeast LLC ,Riverside Generating Company, LLC ,Stream Energy Pennsylvania, LLC ,University Park Energy, LLC ,XOOM Energy, LLC ,","kind":"protest","file":"sources/filings/text/20260903-5156_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5156","tier":"record","sha256":"62da697077062d57740512fe8e2b5e29532afca01e79823acd656ea418a7f632","pages":22,"tokens":6093,"emptyPages":[],"textThemes":["flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":279,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n)\nDocket No. ER26-3515-000\n \nCOMMENTS AND LIMITED PROTEST OF THE NRG COMPANIES \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission”) \nRules of Practice and Procedures,1 the NRG Companies2 (“NRG”) respectfully submit these \ncomments and limited protest in response to PJM Interconnection, L.L.C.’s (“PJM”) August 13, \n2026, filing proposing to establish interim resource adequacy service (“IRAS”) and a large load \nregistry to address system reliability (“PJM IRAS Filing” or “IRAS Filing”). \nIn general, NRG supports PJM’s efforts to provide certainty and clarity to market \nparticipants and New Large Loads3 that do not bring new supply into the PJM market. NRG also \nsupports PJM’s efforts to articulate rules pertaining to the curtailment of New Large Loads that \n \n1 18 C.F.R. § 385.211 (2026).  \n2 The NRG Companies include the following subsidiaries of NRG Energy, Inc. (“NRG”): \nNRG Business Marketing LLC, Aspen Gen Funding, LLC, Direct Energy Business, LLC, \nDoswell, LLC, Energy Plus Holdings LLC, Enerwise Global Technologies, LLC d/b/a CPower, \nGreen Mountain Energy Company, Helix Ironwood, LLC, Independence Energy Group LLC, \nLSP University Park, LLC, Midwest Generation LLC, NRG Curtailment Solutions, Inc., Reliant \nEnergy Northeast LLC, Riverside Generating Company, LLC, Stream Energy Pennsylvania, \nLLC, University Park Energy, LLC and XOOM Energy, LLC. The NRG Companies have \nseparately moved to intervene in this proceeding. See (doc-less) Motion to Intervene of NRG \nBusiness Marketing LLC, et al., Docket No. ER26-3515-000 (filed Aug. 31, 2026). \n3 Terms utilized herein that are not otherwise defined have the meaning ascribed by the \nPJM IRAS Filing’s proposed definitions or the PJM Tariff."},{"page":2,"startToken":279,"endToken":524,"text":"2 \ndo not bring new supply where such customers are curtailed before existing pre-emergency and \nemergency customers. \nHowever, PJM’s proposal contains elements that are unjust, unreasonable, unduly \ndiscriminatory, and must be revised. These consist of (i) PJM’s permanent exclusion of every \nDemand Resource4 that has ever supported a capacity commitment in any prior Delivery Year \nand (ii) the requirement for new capacity serving New Large Loads to bid into the capacity \nmarket as a price-taker for 10 years without certain necessary protections for asset owners. \nFinally, there are a number of clarifications NRG seeks related to the IRAS requirements around \nDemand Resources.  \n \nI. \nABOUT NRG \nThrough various subsidiaries, NRG owns or controls over 9 GW of generation in PJM as \nwell as generation in adjacent markets that can be imported into the PJM market. Additionally, \nNRG subsidiaries provide retail power throughout PJM and two NRG subsidiaries provide \nDemand Resources in PJM. Thus, NRG actively participates in the organized markets \nadministered by PJM, including the PJM capacity market.  \n \nII. \nBACKGROUND \nThe PJM IRAS Filing creates a new supplemental capacity product through which New \nLarge Loads may provide a load reduction service during periods of insufficient capacity instead \n \n4 This limited protest refers to Demand Resources and Distributed Energy Resources \n(“DER”) Capacity Aggregation Resources, as the terms are defined by the PJM OATT, as \n“Demand Resources” to improve readability, but is not intended to refer only to Demand \nResources with the term unless the context requires otherwise."},{"page":3,"startToken":524,"endToken":801,"text":"3 \nof participating in the Base Residual Auction (“BRA”). IRAS resources will be issued \ncurtailment instructions prior to PJM calling on Pre-Emergency Load Management. For \nproviding the reduction, PJM proposes an IRAS rate equal to 50% of the Non-Performance \nCharge Rate, with flexibility for Electric Distributors and states to reduce the rate or for eligible \nNew Large Loads to waive compensation entirely.  \nInstead of participating as an IRAS resource, New Large Loads may instead meet their \ncapacity obligations through a Bring Your Own New Capacity (“BYONC”) option. BYONC is \ndefined as megawatts of new Unforced Capacity (“UCAP”) that meet the eligibility criteria set \nforth in Tariff, Attachment DD-4, section VI.5 A single physical resource may support multiple \nBYONC arrangements with different New Large Loads, and a New Large Load may enter into \nBYONC arrangements with discrete resources.6 BYONC must be supported by: (1) a new-build \ngeneration resource (including resources obtaining Capacity Interconnection Rights transferred \nfrom deactivated resources); (2) incremental capacity from an uprate; (3) incremental capacity \nfrom Surplus Interconnection Service; (4) repowering of a deactivated resource that deactivated \nprior to April 10, 2026; or (5) incremental capacity from a fuel-type change.7 BYONC may also \nbe supported by Planned Demand Resources or Planned DER Capacity Aggregation \nResources. However, PJM has proposed to only permit BYONC to be supported by Demand \nResources if those resources “did not previously support a capacity commitment or reduce the \namount of capacity needed to meet the PJM Reliability Requirement … for or prior to the \n \n5 Proposed Tariff, Definitions (“Bring Your Own New Capacity”).  \n6 Proposed Tariff, Attach. DD-4, section VII(f). \n7 Proposed Tariff, Attach. DD-4, section VI(b)(i)."},{"page":4,"startToken":801,"endToken":1072,"text":"4 \n2026/27 Delivery Year” 8 – thus permanently excluding every Demand Resource that has ever \nsupported a capacity commitment in any prior Delivery Year.  \nEach BYONC must participate as a price taker ($0/MW offer) in BRAs for 10 \nconsecutive Delivery Years, starting with the first Delivery Year of the arrangement. BYONC is \nalso subject to the capacity must-offer requirement and is prohibited from seeking an exception \nto provide an external sale during the 10-year period. BYONC supported by a Demand Resource \nor DER Capacity Aggregation Resource also has a 10-year commitment, but the seller may \nreplace its BYONC obligation with a different qualifying resource, subject to conditions. This \nprovides a “bridge to power” allowing near-term demand-supported capacity to be eventually \nreplaced with new generation. Additionally, beginning with the 2029/30 Delivery Year, PJM \nproposes to exclude from the VRR Curve the MW of New Large Loads that have not entered \ninto BYONC arrangements and do not have allocated capacity (IRAS resources), above and \nbeyond the MW included in the 2028/29 Delivery Year load forecast.  \nBYONC BRA participation requirements (including the price-taker obligation) are \nextinguished if IRAS is not needed for three consecutive Delivery Years. At that point, BYONC \nresources become regular Capacity Resources, though still subject to the general capacity must-\noffer requirement. If the PJM Region meets its reliability requirements for three consecutive \nDelivery Years and then re-enters shortage, the “new” benchmark resets. Demand-side capacity \nwould then be measured against registration “in the Delivery Year prior to the first Delivery \nYear” in which PJM is again short of capacity. \n \n8 Proposed Tariff, Attach. DD-4, section VI(b)(ii)."},{"page":5,"startToken":1072,"endToken":1343,"text":"5 \nIII. \nCOMMENTS IN SUPPORT OF THE PJM IRAS FILING \nIn general, NRG supports PJM’s IRAS Filing. PJM proposes to require Load Serving \nEntities (“LSEs”) to “bring new capacity in an amount that equals or exceeds its New Large \nLoads’ peak load or be subject to load reduction requests during Emergencies prior to Pre-\nEmergency Load Management Response.”9 PJM notes that it is “currently short of capacity and \nlooking to reestablish healthy capacity reserve margin.”10 PJM’s approach is commonsense: New \nLarge Loads must be supported by Capacity Resources. Furthermore, NRG supports the \nrequirement that the BYONC capacity be “new” generation.  \nNRG also supports PJM’s proposal to curtail New Large Loads before existing \ncustomers, including Pre-Emergency and Emergency Demand Response customers. Specifically, \nthe PJM IRAS Filing provides that “PJM can call on IRAS load reductions prior to calling on \nPre-Emergency Load Management Reductions Actions when needed to avoid a capacity \nshortage.”11 As PJM notes, this provision does not identify the specific load that an Electric \nDistributor must reduce.12 Rather, the Electric Distributor, in coordination with the appropriate \nstates and/or Relevant Electric Retail Regulatory Authorities, LSEs, and LSE customers, will \ndetermine which loads should ultimately be curtailed.13 The proposed curtailment obligation \n \n9 PJM IRAS Filing at 3-4, 49.  \n10 Id. at 52.  \n11 PJM IRAS Filing at 25 (citing Proposed Tariff, Attach. DD-4, Section 1(b)).  \n12 PJM IRAS Filing at 26.  \n13 Id. Nonetheless, PJM should consider clarifying that if Electric Distributors, in \ncoordination with these entities, do not take action, PJM will use the registry to curtail New \nLarge Loads ahead of all other loads."},{"page":6,"startToken":1343,"endToken":1590,"text":"6 \ngives states and LSEs latitude to curtail efficiently and, in particular, to prioritize customers that \ncurtail voluntarily. The construct also provides a “bridge to power” that protects existing \ncustomers.  \n \nIV. \nLIMITED PROTEST \nPursuant to the Commission’s Rule 211,14 NRG provides the following limited protest. \nAs written, the tariff proposed by PJM fails to be just and reasonable and is unduly \ndiscriminatory because it (i) excludes otherwise capable Demand Resources based on an \nunwarranted permanent bar to such resources that have participated in any prior BRA; and \n(ii) imposes an overly broad and unjust and unreasonable ten-year price-taker obligation on all \nBYONC resources. \nPJM has consented to the Commission’s exercise of authority to modify or sever any \nelement of the filing to the extent necessary, so long as the modification is consistent with PJM’s \noverarching objectives.15 Thus, the Commission has authority to modify PJM’s proposed tariff in \nthe manner proposed by NRG by directing a compliance filing.16 NRG’s modest proposals do not \n \n14 18 C.F.R. § 385.211. \n15 PJM IRAS Filing at 9 (citing NRG Power Marketing LLC v. FERC, 862 F.3d 108 (D.C. \nCir. 2017)). \n16 N.Y. Indep. Sys. Operator, Inc., 188 FERC ¶ 61,051, at P 22 n.36 (2024) (citing NRG \nPower Mktg., LLC v. FERC, 862 F.3d 108, 114-15 (D.C. Cir. 2017)) (“the Commission has \n‘authority to propose modifications to a utility’s [FPA section 205] proposal if the utility consents \nto the modifications.’ ”)."},{"page":7,"startToken":1590,"endToken":1869,"text":"7 \nconflict with PJM’s Board Directive, or with the objectives reflected in the Critical Issue Fast \nPath’s (“CIFP”) accelerated stakeholder process related to the PJM IRAS Filing.17 \nA. New Demand Resources Should Be Permitted to Bid into the Market to Support \nNew Large Loads Regardless of Prior Market Participation \nPJM states that new capacity, BYONC, is at a basic level, “megawatts of Unforced \nCapacity” and thus is “consistent with how Capacity Resources under PJM’s capacity market \ndesign are also MW and not the underlying physical resource.”18 PJM explains that BYONC is \n“designed to offset the capacity need presented by the New Large Load.”19 PJM further explains \nthat “new capacity may be supported by generation, storage, or demand-side resources that meet \ncertain gating criteria.”20 \nHowever, PJM’s “gating criteria” for BYONC applicable to Demand Resources include a \nrequirement that Planned Demand Resources “did not previously support a capacity commitment \nor reduce the amount of capacity needed to meet the PJM Region Reliability Requirement … for \nor prior to the 2026/2027 Delivery Year.”21 This means that PJM has permanently excluded \nevery Demand Resource that has ever supported a capacity commitment in any prior Delivery \n \n17 See PJM IRAS Filing at 17-18 (citing Letter from Paula Conboy, Chair, PJM Board of \nManagers, Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop \nProcurement and Connect and Manage, 1 (July 27, 2026), https://www.pjm.com/-\n/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-board- \ndecisional-letter-on-cifp-reliability-backstop-procurement-and-connect-and-manage.pdf (“PJM \nBoard Directive”).  \n18 PJM IRAS Filing at 51.  \n19 Id.  \n20 Id. at 53.  \n21 PJM IRAS Filing at 54 (emphasis supplied) (citing Proposed Tariff, Attach. DD-4, \nSections VI(b)(i)(1)-(5))."},{"page":8,"startToken":1869,"endToken":2165,"text":"8 \nYear even though Demand Resources have proven their value in PJM. They have been critical in \nmitigating emergencies and have helped to “avoid the cost of dispatching [or building] additional \ngeneration or involuntarily curtailing load.”22 In 2025 alone, PJM successfully relied on Demand \nResources that provided more than 4,000 MW of capacity during emergencies.23  \nUnder PJM’s proposal, a customer location that participated as a Demand Resource as far \nback as 200624 and later ceased participation would be ineligible to participate as a BYONC \ncapacity resource. The ban on eligibility applies even if the ownership or occupancy at the \ncustomer location has changed or if there are new flexibility capabilities. For example, a \ncustomer location that ceased participation as a Demand Resource in 2010 and was no longer in \nany way considered an existing capacity resource would be banned from participation in \nBYONC. This exclusion is patently unjust, unreasonable, and unduly discriminatory.25 \nFirst, this restriction applies only to Demand Resources, not to retired generators or \nstorage resources that exited the market but could reactivate their Capacity Interconnection \nRights.26 Deactivated generators also may be “repower[ed]” if they were deactivated before April \n \n22 Fed. Energy Reg. Comm’n, 2025 Assessment of Demand Response and Advanced \nMetering, 16 (Dec. 2025) https://www.ferc.gov/news-events/news/ferc-staff-issues-2025-\nassessment-demand-response-and-advanced-metering.  \n23 Id. at 17.  \n24 PJM Interconnection, L.L.C., 115 FERC ¶ 61,079, at P 84 (2006). \n25 Xcel Energy Servs. Inc. v. FERC, 41 F.4th 548, 559 (D.C. Cir. 2022) (explaining \ndiscriminatory standards and referencing the Commission policy that “the Commission can \npromote market entry by ensuring that all generators compete on a level playing field”).  \n26 IRAS Filing at 53-54 (citing Proposed Tariff, Attach. DD-4, Sections VI(b)(i)(1)-(5))."},{"page":9,"startToken":2165,"endToken":2538,"text":"9 \n10, 2026 and be considered “new” capacity that can qualify as BYONC.27 PJM has provided no \nexplanation or support for allowing deactivated generation that had once participated in a prior \nBRA to participate as BYONC, while excluding Demand Resources that also had participated in \na prior BRA from qualifying as BYONC.28 The fact that “new” Demand Resources can qualify \nfor BYONC just like new generation necessarily means that the nature of the Capacity Resource \nis not a relevant factor to discriminate or differentiate for inclusion as BYONC.29 Therefore, this \ninconsistent treatment of retired generation and Demand Resources that had participated in prior \nBRAs is de facto unjust, unreasonable, and unduly discriminatory. \nSecond, there is no justification for such discriminatory treatment.30 The discriminatory \ntreatment of previously enrolled Demand Resource locations excludes gigawatts of potential \nDemand Resources from qualifying as BYONC. As noted, generation that has deactivated can \n \n27 Id.  \n28 West Deptford Energy, LLC v. FERC, 766 F.3d 10, 20-22 (D.C. Cir. 2014) (“the \nCommission would have to provide a reasoned analysis, resting on articulated objective, \nnondiscriminatory, and evenhanded criteria, that would justify treating [one generator] \ndifferently than the generators in all those other cases.”); FERC v. Elec. Power Supply Ass’n, 577 \nU.S. 260, 292 (2016), as revised (Jan. 28, 2016) (noting FERC’s position that demand response \nand other generators should be treated equally because “both provide the same value to a \nwholesale market”).  \n29 Tenaska Clear Creek Wind, LLC v. FERC, 108 F.4th 858, 868 (D.C. Cir. 2024) (citation \nomitted) (“[U]ndue discrimination occurs when similarly situated entities are charged different \nrates for no good reason.”); Black Oak Energy, LLC v. FERC, 725 F.3d 230, 239 (D.C. Cir. 2013) \n(allowing FERC to rely upon “differences between parties that are relevant to the achievement of \npermissible policy goals”). \n30 PJM Interconnection, L.L.C., 115 FERC ¶ 61,079, at P 72-73 (2006) (“We encourage \nPJM to examine and incorporate reasonable accommodations to maximize demand response \nparticipation in the capacity market.”); 16 U.S.C. § 824d; Wisconsin Pub. Power, Inc. v. FERC, \n493 F.3d 239, 246 (D.C. Cir. 2007) (“Section 205 … prohibits undue discrimination in rates, \ncharges, or terms of service.”)."},{"page":10,"startToken":2538,"endToken":2829,"text":"10 \nrepower or obtain new interconnection rights and participate as BYONC. By contrast, a Demand \nResource that once participated in a BRA as a Capacity Resource does not need to be repowered \nor obtain new interconnection rights to participate. Allowing such Demand Resources to qualify \nas BYONC can add meaningful capacity immediately by improving the utilization of existing \nresources,31 while aiding PJM in reestablishing the “healthy capacity reserve margins” it seeks \nthrough the IRAS Filing.32 Moreover, unlike generators or storage resources, Demand Resources \ncan grow or shrink in response to price signals. That flexibility is a feature, not a flaw; when \npower prices are high due to demand, Demand Resources can offer greater participation.33 And \nunlike physical generation facilities, Demand Resources can respond with little delay to changes \nin demand signals.34  \nThird, allowing Demand Resources that have ceased participation in BRAs in prior \nDelivery Years to qualify as BYONC is consistent with limiting BYONC eligibility for \ngeneration to new resources. Existing generation resources in PJM are required to offer their \navailable unforced capacity into the capacity market. Therefore, existing generation in PJM \nalready participates in the BRA and should not be allowed to withdraw from the capacity market \nin order to qualify as BYONC as discussed herein. Demand Resources voluntarily participate in \nthe capacity market. Thus, Demand Resources that have participated in past Delivery Years, but \n \n31 New York Indep. Sys. Operator, Inc., 147 FERC ¶ 61,152, at P 20 (2014) (noting \nresources “such as demand response and repowering options” provide “shorter term capacity \nresponses” to meet capacity needs). \n32 PJM IRAS Filing at 52. \n33 Dept. of Energy, Benefits of Demand Response in Electricity Markets and \nRecommendations for Achieving Them, at 13-15 (Feb. 2006).  \n34 Id."},{"page":11,"startToken":2829,"endToken":3172,"text":"11 \nceased participation as Capacity Resources prior to 2026/27, should be allowed to qualify as \nBYONC, as allowing such participation has no negative implications on future BRAs. \nTaken together, these factors contradict how PJM proposes treating these resources. \nIndeed, the flexible and voluntary nature of Demand Resource participation in the PJM capacity \nmarket supports inclusion of Demand Resources as BYONC, as Demand Resources can provide \nsignificant immediate capacity to help serve New Large Load rather than relying on IRAS.  \nNRG further notes that PJM’s IRAS Filing is inconsistent with the proposal approved by \nthe PJM Board. PJM’s July 31, 2026, version of the IRAS proposal – the final public version \nbefore the PJM IRAS Filing that was approved by the PJM Board – would only restrict Demand \nResources that had participated in the 2026/27 or 2027/28 Delivery Year.35 This three-year \nlimited lookback is just, reasonable, and not unduly discriminatory because it treats all Capacity \nResources equally.36 As proposed, the PJM Board has not reviewed the issue herein to deem it \nnon-discriminatory.37 However, in the IRAS Filing, PJM bars participation by Demand \n \n35 PJM, PJM Interim Resource Adequacy Service Detailed Proposal, at 7 (July 31, 2026) \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260731/20260731-\nitem-02b---cifp-framework-for-service-during-periods-of-insufficient-resource-adequacy---\nexecutive-summary---redline.pdf.  \n36 Alabama Elec. Co-op., Inc. v. FERC, 684 F.2d 20, 29 (D.C. Cir. 1982) (“In the typical \ncase, where the section 205(b) challenge is raised against a rate design calling for different rates \nto customer classes which are similarly situated.”); New York Pub. Serv. Comm’n v. New York \nIndep. Sys. Op., Inc., 153 FERC ¶ 61,022, at P 79 (2015) (finding a narrowly tailored exemption \nwas appropriate).  \n37 PJM Operating Agreement § 7.7(vii) (requiring the PJM Board to “review for \nconsistency with the creation and operation of a robust, competitive and non-discriminatory \nelectric power market in the PJM Region any change to rate design or to non-rate terms and \nconditions proposed by Transmission Owners for filing under section 205 of the Federal \nPower Act”)."},{"page":12,"startToken":3172,"endToken":3464,"text":"12 \nResources that had ever been Capacity Resources in any prior BRA, without explaining the \ndeparture from the proposal submitted to the Board.  \nThe IRAS Filing contemplates that, if the PJM Region meets its reliability requirements \nfor three consecutive Delivery Years and then re-enters shortage, the “new” benchmark resets. At \nthat point, the demand-side gating criterion measures against registration “in the Delivery Year \nprior to the first Delivery Year” in which the PJM Region is short of capacity.38 Here, PJM itself \nrecognizes a lookback-window approach is workable and reasonable. There is no principled \njustification for the asymmetry of applying a lookback in one context but not in the related \nDemand Resources context. To address this unjust, unreasonable, and unduly discriminatory \ntreatment, NRG requests that the Commission adopt a three-year lookback window rather than a \npermanent exclusion.39 Namely, PJM should permit Demand Resources that have not \nparticipated in the three most recent BRAs to qualify for BYONC.  \nThe overly broad ineligibility is inconsistent with the policy announced by the Secretary \nof Energy to leverage available backup generation to address the United States’ reliability \nchallenges and other grid challenges.40 There are gigawatts of backup generation that were once \neligible and did participate in demand response but subsequently discontinued participation. \nDemand response participation by backup generators may become economically viable through \n \n38 PJM IRAS Filing at 55 (citing Proposed Tariff, Attach. DD-4, Section VI(b)(ii)(1)). \n39 Id.  \n40 Letter from Sec. of Energy Christopher Wright to Reliability Coordinators, Leveraging \nBackup Generation Facilities During Energy Emergencies (Jan. 22, 2026) \nhttps://www.energy.gov/documents/leveraging-backup-generation-facilities-during-energy-\nemergencies (suggesting reliability coordinators “deliberately prioritize the dispatch order of \nbackup generation to achieve the greatest benefit to the bulk power system while balancing \nmission-essential functions”)."},{"page":13,"startToken":3464,"endToken":3729,"text":"13 \nBYONC arrangements and should be considered as new resources. The BYONC mechanism \nwould present a powerful means to leverage this latent backup generation capacity to meet \ntoday’s reliability challenges and foster economic growth. PJM’s ban on prior customer location \neligibility to participate in BYONC undermines the Secretary of Energy’s directive to develop \nand encourage backup generation resources. \nIn short, a Demand Resource that chooses to re-enter the market still provides new \ncapacity to the system, just as a generator that undertakes an uprate project adds new capacity. To \narbitrarily exclude a Demand Resource from participating solely because it had participated in \npast BRAs, while simultaneously permitting reactivated or repowered generators to qualify, is \nunjust, unreasonable, and unduly discriminatory.41 \nB. Capacity Serving New Large Loads Should Not Be Required to Bid into the BRA as \na Price Taker for 10 Years Without a Replacement Mechanism \nPJM proposes that “BYONC must participate, as a price taker (i.e. $0/MW offer) in RPM \nAuctions for 10 consecutive Delivery Years.”42 PJM states that the BYONC arrangement “serves \nas the commitment to provide [] capacity.”43 PJM further states that because the “resource is \nalready obligated to provide the capacity, its incremental, going-forward avoidable costs to \nsecure the RPM commitment are zero.”44 The ten-year price-taker obligation is not just and \nreasonable as applied to all Capacity Resources, including generation, storage, and demand-side \nresources. NRG’s protest on this point is not limited to Demand Resources. NRG requests that \n \n41 See n.29, supra.  \n42 PJM IRAS Filing at 55-56. \n43 Id. at 57.  \n44 Id. at 58-59."},{"page":14,"startToken":3729,"endToken":4116,"text":"14 \nthe Commission direct PJM to provide opportunities to reflect costs in offers for unknown and/or \nunknowable costs imposed upon the Capacity Resource owner and not otherwise recoverable \nunder the terms of the asset owner’s bilateral contracts with large loads. \nA ten-year capacity obligation for a resource is significant.45 Participation as an existing \nCapacity Resource in PJM is subject to a must-offer requirement for capacity auctions only three \nyears into the future.46 A ten-year must-offer commitment with a mandatory zero-dollar offer \ncompounds the significance of the commitment.47 Circumstances may change materially during a \nten-year bilateral agreement between third parties, potentially altering a facility’s operating costs \nin unpredictable ways. For instance, new environmental obligations may arise that require capital \nexpenditures, a facility may suffer a catastrophic loss, or fuel may become prohibitively \nexpensive in a constrained region. Given the corresponding requirement to offer into the BRA at \nzero-cost for 10 years, a BYONC resource cannot be economically replaced as operating and \nmarket conditions evolve. As a result, this market construct is effectively designed to keep \n \n45 Though hypothetically, a BYONC price-taker obligation may cease if PJM has met the \nReliability Requirement for three years, the practical reality is that the obligation will remain \nthrough several additional BRAs, which occur three years in advance of performance. For \ninstance, if PJM has thrice met its Reliability Requirement in 2032 – the last date that Reliability \nBackstop Procurement resources are eligible for market entry under a parallel tariff proposal by \nPJM – BYONC resources will not know whether they retain an obligation until 2034. By that \ntime, BRAs will have occurred through 2037/38. In this plausible scenario, a BYONC resource \nwould be required to offer as a price taker well past when PJM demonstrates sufficient capacity \nto meet all load.   \n46 PJM Capacity Manual 18 § 5.7 (rev. 62, Dec. 17, 2025).  \n47 The Commission has previously found that even a five-year must-offer obligation may \nbe unjust and unreasonable because it ultimately undercompensated sellers. See, e.g., California \nIndep. Sys. Operator Corp., 118 FERC ¶ 61,097, at P 5 (2007) (discussing the Commission’s \nfinding that a must-offer obligation lasting five years to be unjust and unreasonable and \nundercompensated sellers), vacating on other grounds, City of Anaheim, Cal. v. FERC, 558 F.3d \n521, 526 (D.C. Cir. 2009)."},{"page":15,"startToken":4116,"endToken":4438,"text":"15 \neconomically inefficient generators operating, potentially at a loss, rather than allowing more \nefficient resources to displace them. \nThe Commission should direct PJM to include the opportunity for such costs to be \nreflected in subsequent capacity auctions should conditions such as those described above arise. \nThe PJM Tariff already has mechanisms for other resources to reflect their costs through unit \nspecific Avoidable Cost Rate (“ACR”) offers.48 NRG proposes a similar approach here. This \nwould ensure in the limited cases where otherwise unforeseen circumstances are unaddressed or \nare at issue in bilateral transactions, the resource owner has an opportunity (but not the \nguarantee) to recover such unforeseen costs.49 The ACR approach also offers benefits to PJM \ncustomers: (1) the market receives the benefit of the zero-offer price for ten years in most cases, \nabsent detailed showings; (2) in extraordinary circumstances, the Capacity Resource serving a \nNew Large Load is able to continue doing so while recovering exceptional and unforeseen costs; \n(3) more economic resources are able to enter the market and replace highly inefficient Capacity \nResources; and (4) reliability is improved over the course of the IRAS-imposed commitments.50   \nAdditionally, to the extent PJM imposes a price-taker requirement on BYONC resources, \nthe requirement should not apply to excess capacity beyond the BYONC commitment. If a \n1,200-MW generation facility has committed 700 MW as BYONC, the remaining 500 MW \n \n48 PJM Tariff, Attach. DD §§ 6.4(b) & 6.7. Specifically, the proposed ACR, and all “data \nand documentation” shall be submitted to the IMM for consideration. \n49 If these costs are inframarginal, there is no impact on auction outcomes, but provides \nsignificant assurances for the resource owner. If the resource is extramarginal as a result of these \ncosts, the large load will bear the responsibility to replace it or be subject to IRAS service. \n50 The alternative may be generator bankruptcy that will benefit neither PJM, its \ncustomers nor the generator."},{"page":16,"startToken":4438,"endToken":4672,"text":"16 \nshould be permitted to bid economically into the BRA. PJM’s own filing acknowledges that a \nphysical resource may support multiple BYONC arrangements, each of which may be in an \narrangement with different New Large Loads.51 PJM provides no justification for requiring non-\nBYONC MW to offer at zero when those MW are not committed to any New Large Load and \nwould otherwise compete in the market on economic terms. To the extent PJM disagrees with \nthis clarification, NRG requests that the Commission direct non-BYONC MW from the same \nCapacity Resource be permitted to offer economically into the RPM Auction. \n   \nV. \nNRG SEEKS CLARIFICATION, OR IN THE ALTERNATIVE, TARIFF \nMODIFICATIONS, PERMITTING EXPANDED DEMAND RESPONSE \nCAPACITY TO BE TREATED AS NEW CAPACITY \nNRG has identified four areas in the IRAS Filing that lack clarity, and to the extent these \nareas are inconsistent with NRG’s requested clarification, are unjust and unreasonable because \nthey are discriminatory. First, existing Demand Resources should be permitted to offer BYONC \nin excess of prior capacity offers as “new” capacity. Second, any resource that would qualify as \n“new” capacity can also be eligible to serve as replacement capacity for Demand Resources. \nThird, curtailment-based Demand Resources should be eligible for BYONC without requiring \ngeneration or storage assets at the location. Fourth, the methodology used to determine eligibility \nof Demand Resources must be defined. \n \n51 See Proposed Tariff, Attach. DD-4, section VII(f)."},{"page":17,"startToken":4672,"endToken":4954,"text":"17 \nFirst, NRG seeks clarification, or an amendment of the proposed tariff, that an existing \nDemand Resource could offer BYONC in excess of prior capacity offers,52 consistent with other \nCapacity Resources that may include uprates and Surplus Interconnection Service capacity.53 \nWith this clarification, additional investments may be encouraged at an existing “registered \nlocation” such as construction of behind-the-meter generation, on-site battery storage, or other \ncustomer-site enhancements, even if that resource previously supported a capacity \ncommitment.54 Similarly, treating increased Demand Resource capacity as “new” capacity \nprovides a comparable benefit to PJM customers.55 Thus, this clarification would ensure that \nDemand Resources are treated the same as other Capacity Resources and ensure that Demand \nResources are available to offset New Large Loads.  \nSecond, the IRAS Filing does not clearly define what may serve as replacement capacity \nfor BYONC Demand Resources, except that it would “need to be supported by the certification \nrequired by Tariff, Attachment DD-4, section VII(a)(ii)”, that circularly requires compliance with \nAttachment DD-4, Section VIII.56 NRG seeks clarification, or an amendment to the tariff, that \nany resource that would qualify as “new” capacity can also be eligible to serve as replacement \n \n52 NRG seeks this clarification for the PJM proposed permanent bar or the NRG proposed \nmodification that would limit the restriction to 2026/27 BRA participation, whichever is adopted \nby the Commission.  \n53 See Proposed Tariff, Attach. DD-4, section VI(b)(i)(2) & (3).  \n54 See PJM IRAS Filing at 54. \n55 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 292 (2016), as revised (Jan. 28, \n2016). \n56 See IRAS Filing at 56-67; see also Proposed Tariff, Attach. DD-4, section VIII(e)."},{"page":18,"startToken":4954,"endToken":5272,"text":"18 \ncapacity for Demand Resources committed to an existing BYONC arrangement under \nAttachment DD-4, section VIII(e). \nThird, NRG seeks clarification that Demand Resources achieving load reductions through \ncurtailment alone, without the installation of new generation or storage assets, are eligible for \nBYONC. As proposed, the IRAS tariff requires that demand-side BYONC be composed of \nlocations “at which an incremental amount at that location is the result of the registration of new \ngeneration or storage assets at the location.”57 This language appears to compound the historical-\nparticipation exclusion with a separate requirement for new physical assets at the location. If so, \nthis would exclude the vast majority of curtailment-based Demand Resources, which achieve \nreductions through operational adjustments rather than new “generation or storage assets.” \nCurtailment-based Demand Resources provide the same reliability value as a generator obtaining \nnew Capacity Interconnection Rights. Their exclusion would be unjust and discriminatory. \nFourth, the methodology used to determine eligibility of Demand Resources must be \ndefined. NRG recognizes that the demand-side BYONC replacement mechanism was developed \nthrough the CIFP stakeholder process and supports the concept of permitting replacement \ncapacity for demand-side BYONC. However, the Commission must require PJM to provide \nclarity on how a Curtailment Service Provider (“CSP”) will be required to demonstrate each year \nof a 10-year period for a Demand Resource.58 Matters that significantly affect the rates, terms \nand conditions of service must be specified in the tariff.59 PJM’s proposed tariff states: \n \n57 See Proposed Tariff, Attach. DD-4, section VI(b)(ii)(1). \n58 See PJM IRAS Filing at 66; Proposed Tariff, Attachment DD-4, section VII(i)(ii) \n59 See, e.g., PJM Interconnection, L.L.C., 171 FERC ¶ 61,145 at P 20 (2020) (finding \nPJM’s inclusion of threshold criteria in a manual insufficient, and directing inclusion in the \ntariff); see also City of Cleveland, Ohio v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (holding"},{"page":19,"startToken":5272,"endToken":5599,"text":"19 \nDemand Resources or DER Capacity Aggregation Resources, the \nAccredited UCAP shall be the Accredited UCAP for the RPM Auction in \nwhich the BYONC cleared for the initial Delivery Year the BYONC is in \nan arrangement with the New Large Load and must be demonstrated \neach year for a 10-year period using the Demand Response or DER \nCapacity Aggregation Resources installed capacity for the first Delivery \nYear after the BYONC is in an arrangement with the New Large Load. For \nDemand Resources or DER Capacity Aggregation Resources that are also \nthe actual New Large Load, there is no demonstration required for the \ninitial Delivery Year only to not be an Eligible New Large Load.60  \nNRG seeks clarification that the 10-year demonstration is made by showing the “installed \ncapacity for the first Delivery Year after the BYONC is in an arrangement with the New Large \nLoad.”61 More specifically, that PJM’s proposed language does not mean that incremental \ncustomers that make up an aggregation must have a 10-year commitment to make this \ndemonstration. If PJM disagrees with this interpretation, that would be unjust and unreasonable \nand unduly discriminatory, and NRG requests the Commission direct amendments.  \nIt must be recognized that a Demand Resource is typically an aggregated portfolio that \nmay be composed of many Demand Resource registrations, each representing an individual \ncustomer location. Such aggregations are composed of heterogeneous and highly variable \ncustomers, each having different negotiated contract length and expirations and each of them \nexperiencing changes in the way they consume electricity over time. Aggregation activities by \nCSPs are what allows a diverse, evolving group of customers to provide a firm capacity resource. \n \nthat under Section 205, a party must file “those practices that affect rates and service \nsignificantly, that are realistically susceptible of specification, and that are not so generally \nunderstood in any contractual arrangement as to render recitation superfluous.”). \n60 Proposed Tariff, Attachment DD-4, section VII(i)(ii) (emphasis added). \n61 Id. (emphasis added)."},{"page":20,"startToken":5599,"endToken":5924,"text":"20 \nIn PJM, the quantum of Demand Resources that a customer can provide is capped at its \nPeak Load Contribution (“PLC”).62 Individual contributions to an aggregator’s portfolio change \nannually and may be difficult to predict more than one year into the future. Individual customer \nvolumes of participating demand response expands and contracts based upon PLC as well as \ncustomer usage patterns. Businesses and homes change owners/tenants and new occupants may \ndecide to start or stop participation in demand response. Technology evolves. Equipment gets old \nand may be replaced. Batteries, distributed generation, electric vehicles, etc., all can change \ncustomer PLC and load reduction capabilities. This diversity and the ebb and flow of customer \ndemand response capabilities is managed by aggregators – who can add new customers to \nreplace customers who depart or whose flexible capability declines. However, in the aggregate, \nthe volume of the Demand Resource is reliable. \nPJM’s proposal, if interpreted inconsistently with NRG’s approach, would mandate \nindividual customer locations to make the required eligibility showing for the full 10-year period. \nThis is anathema to long-standing Commission-approved approaches for demand response \nportfolio management.63 The Commission should specify that Demand Resources may \n \n62 PJM Capacity Market, Manual 18 § 4.3.7 (rev. 62, Dec. 17, 2025). \n63 Participation of Distributed Energy Res. Aggregations in Markets Operated by Reg’l \nTransmission Organizations & Indep. Sys. Operators, Order No. 2222, 172 FERC ¶ 61,247, at P \n337 (2020) (“We find that the incremental impacts on RTO/ISO markets and operations that \nwould result from the addition or removal of individual distributed energy resources from a \ndistributed energy resource aggregation, after the initial registration, are likely to be minimal and \nthus individual distributed energy resources should generally be able to enter and exit distributed \nenergy resource aggregations participating in RTO/ISO markets without impairing safety and \nreliability”) reh’g granted, Order No. 2222-A, 174 FERC ¶ 61,197 at P 71, reh’g granted, Order \nNo. 2222-B,  175 FERC ¶ 61,227 (2021)."},{"page":21,"startToken":5924,"endToken":6046,"text":"21 \nparticipate at the aggregator level and need not show individual contracts with each sub-resource \nwithin a CSP contain a 10-year commitment. \n \nVI. \nCONCLUSION \nNRG respectfully requests that the Commission order PJM to make a compliance filing, \nbased on this protest and any responsive pleadings filed by PJM, to revise PJM’s tariff consistent \nwith the changes proposed herein, thus ensuring that PJM’s tariff is just and reasonable and not \nunduly discriminatory.  \nRespectfully submitted, \n/s/ Michael A. Yuffee \nMichael A. Yuffee \nJoe Bower \nBAKER BOTTS LLP \n700 K Street NW \nWashington, DC 20001 \n \nCortney Madea Slager  \nVice President & Assistant General Counsel \nBrianna Anderson  \nRegulatory Counsel  \nNRG Energy, Inc.  \n804 Carnegie Center  \nPrinceton, NJ 08540 \n \nCounsel for the NRG Companies \n \nDated September 3, 2026"},{"page":22,"startToken":6046,"endToken":6093,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document on each person \ndesignated on the official service list compiled by the Secretary in the above-captioned \nproceeding. \nDated at Washington, D.C., this 3rd day of September 2026. \n \n \nJoe Bower \n \n \n \nJoe Bower"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":690,"startToken":0,"endToken":381},{"p":2,"at":690,"title":"I. ABOUT NRG","method":"printed heading","endPage":2,"endAt":1117,"startToken":381,"endToken":446},{"p":2,"at":1117,"title":"II. BACKGROUND","method":"printed heading","endPage":5,"endAt":3,"startToken":446,"endToken":1073},{"p":5,"at":3,"title":"III. COMMENTS IN SUPPORT OF THE PJM IRAS FILING","method":"printed heading","endPage":6,"endAt":215,"startToken":1073,"endToken":1373},{"p":6,"at":215,"title":"IV. LIMITED PROTEST","method":"printed heading","endPage":7,"endAt":184,"startToken":1373,"endToken":1618},{"p":7,"at":184,"title":"A. New Demand Resources Should Be Permitted to Bid into the Market to Support","method":"printed heading","endPage":13,"endAt":842,"startToken":1618,"endToken":3584},{"p":13,"at":842,"title":"B. Capacity Serving New Large Loads Should Not Be Required to Bid into the BRA as","method":"printed heading","endPage":16,"endAt":622,"startToken":3584,"endToken":4539},{"p":16,"at":622,"title":"V. NRG SEEKS CLARIFICATION, OR IN THE ALTERNATIVE, TARIFF","method":"printed heading","endPage":21,"endAt":149,"startToken":4539,"endToken":5946},{"p":21,"at":149,"title":"VI. CONCLUSION","method":"printed heading","endPage":22,"endAt":0,"startToken":5946,"endToken":6046},{"p":22,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":22,"endAt":301,"startToken":6046,"endToken":6093}]}