{"document":{"slug":"rec-20260903-5157","title":"Protest of PJM Power Providers Group re the Interim Resource Adequacy Service","issued":"2026-09-03","accession":"20260903-5157","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"PJM Power Providers Group","kind":"protest","file":"sources/filings/text/20260903-5157_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5157","tier":"record","sha256":"65a05304422b49ca221ccf75ffa191489d7b2c25aa3199e144e168b32a4c9952","pages":106,"tokens":39494,"emptyPages":[],"textThemes":["adequacy","flex","registry","study"]},"pages":[{"page":1,"startToken":0,"endToken":231,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interim Resource Adequacy \nService and Large Load Registry \n)  \n)            Docket No. ER26-3515-000 \n) \nPROTEST OF PJM POWER PROVIDERS GROUP \nPJM is at a critical moment in its history. Facing the challenges presented \nby the emergence of potentially significant new large demand and finding the \nmarket-based means of building the capacity to support the new growth will \ndemand economically rational and structurally sound market design.  Now is \nprecisely the time that PJM and the Commission need to dedicate themselves to \nthe proposition that a properly designed and well-functioning market will ultimately \nserve the consumers of the PJM region by providing reliability at the least cost. \nUnfortunately, the interim resource adequacy service (“IRAS”)1 and large \nload registry proposal (the “IRAS Proposal”) PJM has submitted represents an ill-\nconceived and unnecessary step away from PJM’s core principles and, perhaps \nmore troubling, has long term implications for PJM’s capacity construct that may \npermanently scar it.  PJM’s IRAS Proposal reflects an untested and unsupported, \nunjust, unreasonable and unduly discriminatory experiment with the nation’s \nlargest power grid that has historically provided the consumers of the region with \nreliable service at competitive capacity prices.  Astoundingly, PJM asks the \n \n1 PJM’s nomenclature of “interim” in the context of IRAS is misleading.  PJM does not \npropose that the program sunset, but rather it is filed as a permanent program."},{"page":2,"startToken":231,"endToken":526,"text":"2 \nCommission to sanction this experiment with not as much as a single economist’s \nor market design witness’ testimony, analysis, study or supporting data.    \nThe PJM Power Providers Group (“P3”)2 recognizes the pressure on the \nCommission and PJM to implement reforms to address the unprecedented load \ngrowth associated with New Large Loads and the potential price impact thereof on \nconsumers. 3  Unfortunately, however, the IRAS Proposal represents an \nabandonment of core tenets of the PJM capacity construct that will provide \ntroubling messages to both new and existing capacity resources, jeopardizing \nreliability and resource adequacy, while raising the specter of litigation that is \nbound to interject further uncertainty at the very moment that certainty is \nparamount.     \nThe IRAS Proposal cannot and should not be approved in accordance with \nSection 205 of the Federal Power Act (“FPA”) as it is unjust, unreasonable and \nunduly discriminatory and preferential and will increase costs and undermine \nregional resource adequacy.4  For one, it explicitly is premised on the imposition \nof discriminatory treatment of certain classes of generators and certain types of \ncustomers, and the discrimination it proposes is undue. And second, PJM is \n \n2 P3 is a non-profit organization dedicated to advancing federal, state and regional policies \nthat promote properly designed and well-functioning electricity markets in the PJM \nInterconnection, L.L.C. (“PJM”) region. Combined, P3 members own over 108,000 MWs of \ngeneration assets and produce enough power to supply over 63 million homes in the PJM \nregion covering 13 states and the District of Columbia. For more information on P3, visit \nwww.p3powergroup.com. \n3 The comments contained herein represent the position of P3 as an organization, but not \nnecessarily the views of any particular member with respect to any issue. \n4 16 U.S.C. § 824d."},{"page":3,"startToken":526,"endToken":870,"text":"3 \nleagues away from having met its burden of proof to support the proposal.  Third, \nthe IRAS Proposal is facially inconsistent with both FPA Sections 2015 and 215,6 \nand also cannot be approved on that basis.   \nOn the merits of a review of the soundness of IRAS as a market-design \nproposal, the IRAS Proposal must be rejected for a plethora of reasons, including: \n Put simply, IRAS sends the wrong incentives.  It reflects bad market \ndesign policy, and impermissibly deviates from well-established \nprecedent, because PJM seeks to remedy recently-experienced \nshortfalls in its Reliability Pricing Model (“RPM”) capacity \nprocurement, counterintuitively, by artificially suppressing the price \nsignals that are needed to incentivize the capacity PJM needs to \nremain in and enter into the market in order to cure the resource \nadequacy shortfall; \n It proposes to reduce reliability by intentionally under-procuring \ncapacity. It is unsupported by evidence to warrant its fundamental \nrestructuring of the RPM demand curve it proposes, given that the \nonly filed affidavit – by Christopher Pilong – focused only on \noperations, not market analysis, price impacts, or loss-of-load \nexpectation analysis. Specifically, there is no analysis of either the \nshort or long-term implications of acting as if load that actually exists \ndoes not exist in the RPM process;   \n IRAS dangerously degrades the regional reliability standard by \ntreating IRAS as akin to accredited capacity when it is not, effectively \nchanging the regional reliability criteria in the process, again without \nproviding any support, let alone acknowledgment, of that effect and \nwithout addressing the consequences of such change.  IRAS is an \ninvoluntary reduction of service and represents a degradation of \nreliability;   \n IRAS is impermissibly vague as a rate filing because it depends on \nthe outcome of state retail proceedings that may or may not ever \noccur and PJM cannot compel; and \n IRAS is an untested and unsupported experiment that seeks to \ninappropriately commandeer North American Electric Reliability \nCorporation (“NERC”) Reliability Standards that apply to the Bulk \nElectric System for use on the retail distribution system for which they \n \n5 16 U.S.C. § 824. \n6 16 U.S.C. § 824o."},{"page":4,"startToken":870,"endToken":1289,"text":"4 \nwere not designed, representing another way the proposal puts \nreliability at risk.  \n If approved, the IRAS filing will have long-lasting implications for \nPJM’s capacity construct, resource adequacy and costs that will not \neasily be rectified.  Load on PJM’s system will be eliminated from the \nVariable Resource Requirement (“VRR”) Curve with no firm \nenforcement mechanism governing the satisfaction of that load’s \ndemand. This departs from the checks and balances associated with \nevery other type of load reduction, which each are paired with \nenforceable obligations (e.g., Fixed Resource Requirement (“FRR”), \nDemand Resources, Price Responsive Demand, Peak Shaving \nAdjustments and behind-the-meter generation).  This reduction of \nload unpaired with an enforceable obligation to procure sufficient \ncapacity to meet the demand represents an incredibly dangerous \nand perhaps irreversible policy divergence from one of the PJM \ncapacity market’s core tenets.    \nI. \nPROTEST \nA. \nThe Federal Power Act Dictates Rejection of the IRAS Proposal \n1. \nPJM Has Not Met Its Burden of Proof  \nUnder FPA Section 205, the filing public utility proposing tariff revisions \nbears the burden of proof to demonstrate that its proposal is just, reasonable, and \nnot unduly discriminatory or preferential.7  It is not the Commission’s role to resolve \nthe evidentiary gaps in order to develop the substantial evidence that would be \nrequired to accept a proposal that was inadequately supported when filed. 8  \n \n7 16 U.S.C. § 824d. \n8 See Sw. Power Pool, Inc. GridLiance High Plains LLC, 180 FERC ¶ 61,192 at P 52 (2022) \n(“The party with the burden of proof bears the burden of production, or the need to provide \nsufficient evidence to establish a prima facie case”); see also, e.g., Nantahala Power & \nLight Co. v. FERC, 727 F.2d 1342, 1351 (4th Cir. 1984) (“Nantahala”) (“A utility bears the \nburden of justifying each component of” a proposed rate change and “[b]ecause a regulated \nutility is the party with access to the necessary information, it bears the risk of an \nundeveloped or inconclusive record”); Nw. Corp. v. FERC, 884 F.3d 1176, 1182-83 (D.C. \nCir. 2018) (explaining that “because it was [the utility’s] burden under Section 205 to show \nthat its proposed rate was just and reasonable, [] failure [to do so] was fatal” and rejecting \narguments that it was FERC’s burden to identify alternative bases for finding the proposed \nrate just and reasonable); Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. \nCir. 2017) (explaining, in the context of the Section 205 burden of proof, that “[w]hen acting"},{"page":5,"startToken":1289,"endToken":1756,"text":"5 \nRather, the Commission routinely rejects Section 205 filings when the filing utility  \nfails to meet its burden of proof,9  and it is most critical that it do so here, because \nof the substantial and fundamental negative consequences and market design \nflaws endemic to the IRAS Proposal.  As described herein, PJM has not come \nclose to satisfying this burden and, as such, the Commission should reject the \nIRAS proposal for that reason alone. \nNotably, PJM relies on a single affidavit as the evidentiary support for its \nentire ground-breaking IRAS Proposal: the affidavit of Christopher Pilong, its \nSenior Director of Operations Planning.10  That affidavit addresses only operational \nissues, including emergency procedures and dispatch sequencing.11  At the IRAS \nProposal’s peril,12 and confoundingly given the import of the proposal, PJM opted \n \non a public utility’s rate filing under section 205, the Commission undertakes ‘an essentially \npassive and reactive role’ and restricts itself to evaluating the confined proposal”). \n9 Midcontinent Independent System Operator, Inc., 191 FERC ¶ 61,131 at P 197 (2025) \n(rejecting tariff revisions where filer failed to meet Section 205 burden show approach for \naddressing resource adequacy and reliability needs was just and reasonable and not \nunduly discriminatory or preferential); PJM Interconnection, L.L.C., 180 FERC ¶ 61,089 at \nPP 47, 51 (2022) (rejecting PJM tariff revisions because PJM failed to meet Section 205 \nburden to show proposal was just and reasonable), order on reh’g, 181 FERC ¶ 61,191 at \nP 15 n.49 (2022) (stating “PJM bears the burden of proof to show that the . . . proposal is \njust and reasonable”) (citing 16 U.S.C. § 824d(e); Nw. Corp. v. FERC, 884 F.3d 1176, 1182 \n(D.C. Cir. 2018); Panda Stonewall LLC, Opinion No. 574, 174 FERC ¶ 61,266 at P 30 \n(2021)); PJM Interconnection, L.L.C., 168 FERC ¶ 61,133 at P 25 (2019) (rejecting filing \nwhere Section 205 burden was not met). \n10 PJM IRAS Proposal, Attachment C, Affidavit of Christopher Pilong on Behalf of PJM \nInterconnection, L.L.C. (“Pilong Aff.”).   \n11 PJM IRAS Proposal, Transmittal Letter (“PJM Transmittal Letter”) at 76; Att. C.   \n12 See Nw. Corp., 884 F.3d at 1182 (“because it was [the utility’s] burden under Section \n205 to show that its proposed rate was just and reasonable, [] failure [to do so] was fatal”); \nsee also Nantahala, 727 F.2d at 1351 (“[b]ecause a regulated utility is the party with access \nto the necessary information, it bears the risk of an undeveloped or inconclusive record”). \nFERC cannot accept the proposal in the absence of evidence demonstrating that it is just \nand reasonable. See, e.g., N. States Power Co. (Minnesota) v. FERC, 30 F.3d 177, 180 \n(D.C. Cir. 1994) (“the Commission must be able to demonstrate that it has ‘made a"},{"page":6,"startToken":1756,"endToken":2045,"text":"6 \nnot to provide the evidentiary support of any economist or market-design witness.  \nAs a consequence, among other things, PJM failed to quantify the clearing-price \neffect on costs and resource adequacy of excluding New Large Loads that do not \nBring Your Own New Capacity (“BYONC”) from the VRR curve, provided no \nanalysis of the resource adequacy or cost effect of the decade of mandated \n$0/MW-Day offers its proposal would impose, omitted a loss-of-load-expectation \nstudy or any explanation as to the effect its proposal would have on its long-held \nand widely accepted loss-of-load expectations and whether any change thereof is \njust or reasonable, and neglected to estimate the MW volumes that would be \nexcluded from the VRR curve. \nWhile PJM’s burden to carry would not differ if its IRAS Proposal had \nsubstantial stakeholder support, PJM’s omissions of evidentiary support as to \nmarket design, economic merit and reliability are even more glaring given that the \nIRAS Proposal in fact did not have widespread stakeholder support, as PJM \nconcedes that all of the “proposals regarding the concepts addressed by IRAS \nfailed to achieve two-thirds stakeholder support.”13 \nAs relevant to the burden of proof that PJM bears and that the Commission \nmust hold PJM to meeting, Attachment DD, Section 5.10(a)(iii) of PJM's Tariff \nrequires that any review of the VRR Curve be grounded in simulations of market \nconditions establishing, on a probabilistic basis, that the curve will procure \n \nreasoned decision based upon substantial evidence in the record’”); see also Emera Maine \nv. FERC, 854 F.3d 9, 28 (D.C. Cir. 2017) (rejecting FERC’s ROE where FERC “failed to \nexplain how any evidence demonstrated that” the proposed rate was just and reasonable).  \n13 PJM Transmittal Letter at 16."},{"page":7,"startToken":2045,"endToken":2501,"text":"7 \nsufficient capacity to meet reliability requirements while supporting investment in \nnew resources.14  PJM has honored that requirement in conducting its quadrennial \nreviews, retaining independent consultants and submitting Monte Carlo simulation \nand loss-of-load-expectation modeling in support of changes to the curve's \nshape.15  And the Commission has expressly relied on that rigorous analysis to \nsupport its orders accepting these VRR Curve adjustments.16  Here,  in contrast to \nits actions in the periodic review, PJM proposes to alter the quantity on which every \n \n14 PJM, Intra-PJM Tariffs, OATT, Attach. DD, § 5.10(a)(iii), states, in part: \niii) Procedure for ongoing review of Variable Resource Requirement \nCurve shape.  \nBeginning with the Delivery Year that commences June 1, 2018, and \ncontinuing no later than for every fourth Delivery Year thereafter, the Office \nof the Interconnection shall perform a review of the shape of the Variable \nResource Requirement Curve, as established by the requirements of the \nforegoing subsection.  Such analysis shall be based on simulation of market \nconditions to quantify the ability of the market to invest in new Capacity \nResources and to meet the applicable reliability requirements on a \nprobabilistic basis.  Based on the results of such review, PJM shall prepare \na recommendation to either modify or retain the existing Variable Resource \nRequirement Curve shape. . . .  \n15 PJM’s filing in Docket No. ER26-455, in which a mere 1.5% change to the foot of the \nVRR Curve was proposed, was supported by both The Brattle Group and Sargent & Lundy. \nSee PJM Interconnection, L.L.C., 194 FERC ¶ 61,049 (2026). Despite the expert support \nand small size of the change, the Commission in that case correctly put PJM through the \npaces, adjudicating the propriety of the model’s project timeline, variable operations and \nmaintenance estimates, depreciation schedule, and more, relying heavily on a Brattle study \nand other evidence filed by PJM.  Here, in contrast, where the consequences of the change \nare in a whole other league to the tiny 1.5% curve shift proposed in the sixth quadrennial \nreview, PJM gives the Commission nothing to support the VRR Curve change presented \nin its proposal.    \n16 PJM Interconnection, L.L.C., 194 FERC ¶ 61,049 at PP 11, 45 (2026) (finding that “the \nanalysis on which PJM relies to support its proposed VRR Curve is consistent with the \nTariff requirements\" because “the analysis on which PJM relies to support its proposed \nVRR Curve is consistent with the requirements of the Tariff and results in adjustments to \nthe VRR Curve that are just and reasonable. As part of the 2025 Periodic Review, PJM's \nconsultant, Brattle, tested the performance and reliability of potential VRR Curves by using \nhistorical-based Monte Carlo modeling, a probabilistic analysis methodology\"), reh’g \ndenied, 194 FERC ¶ 62,139 (2026)."},{"page":8,"startToken":2501,"endToken":2754,"text":"8 \npoint of the VRR Curve is anchored, a change that bears on procurement \nadequacy at least as directly as a change in the curve's slope, while submitting no \nsimulation, no probabilistic analysis, no loss-of-load-expectation study (or even \nconsideration of loss-of-load impacts), no sensitivity analysis, no related \nindependent expert testimony, and no estimate of the MW quantity that will be \nexcluded for the Base Residual Auction (“BRA”) by the IRAS Proposal.  PJM does \nnot explain why a modification of this consequence warrants less analytical support \nthan its Tariff demands for a modification of the curve's shape in a quadrennial \nreview, and the Commission would be shirking its regulatory responsibilities were \nit to  accept such consequential changes without the important data such modeling \nand analysis would provide, especially in the face of meaningful evidence that the \nIRAS Proposal, if implemented, would exacerbate resource adequacy issues in \nPJM and result in increased costs overall.  The Commission cannot accept this \nfiling without departing from the standards, and rigorous evidence requirements, it \njust recently required to justify a change to the VRR Curve and departing from \ntroves of well-established precedent. \n2. \nThe Commission Cannot Cure the Defects in the IRAS \nProposal by Accepting It Subject to Condition; Rejection \nis its Only Option. \nIn an acknowledgement of the controversy surrounding its IRAS Proposal, \nPJM preemptively provided notice in the filing that it would consent to the \nCommission’s use of authority to modify or sever portions of the proposed Open \nAccess Transmission Tariff (“Tariff”) and Reliability Assurance Agreement (“RAA”)"},{"page":9,"startToken":2754,"endToken":3132,"text":"9 \nchanges in the proposal, if deemed necessary and appropriate under FPA Section \n205 and if consistent with PJM’s overarching objectives.17 \nThe Commission cannot condition acceptance on modifications to the IRAS \nProposal, however, as FPA Section 205 limits the Commission to a “passive and \nreactive role” 18  and the relevant precedents disallow modifications to a filed \nproposal where the modification would transform the proposal into an entirely \ndifferent rate design.19 The defects requiring correction in the IRAS Proposal are \nsubstantial and pervasive and would run afoul of the permitted “minor” \nmodifications precedents permit. Moreover, the consent to Commission alterations \nthat PJM granted in the filing itself is extremely circumscribed and insufficient to \nallow the proposal’s major defects to be cured.20 \nIn NRG, the Court of Appeals for the D.C. Circuit acted on a PJM Section \n205 capacity market filing in a situation similar to the one the Commission confronts \nhere. PJM had filed a package of revisions to the Minimum Offer Price Rule, parts \n \n17 PJM Transmittal Letter at 9.   \n18 NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114 (D.C. Cir. 2017) (“NRG”) (quoting \nAdvanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017)). \n19 City of Winnfield v. FERC, 744 F.2d 871, 875-876 (D.C. Cir. 1984) (indicating that the \nCommission cannot insert original notions of the rate because doing so would stray from \nits essentially passive and reactive role); W. Res., Inc. v. FERC, 9 F.3d 1568, 1578 (D.C. \nCir. 1993) (precluding the Commission from adopting remedies “methodologically distinct” \nfrom what was initially proposed). While Western Resources arose under NGA section 4, \nthe NGA has been determined to be “substantially identical” to FPA section 205 as to the \napplicability of this precedent. See, e.g., FPC v. Sierra Pacific Power Co., 350 U.S. 348, \n350 (1956). \n20 NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 116 (D.C. Cir. 2017) (finding that PJM's \nconsent to FERC's modifications of its Section 205 filing was inadequate to cure the harm, \nbecause consent only cures \"minor\" Commission-suggested changes and does not excuse \nmodifications that create \"an entirely new rate scheme,\" which deprive customers of \nadequate notice and opportunity to comment)."},{"page":10,"startToken":3132,"endToken":3327,"text":"10 \nof which the Commission determined not just and reasonable.  As a result, the \nCommission proposed modifications it believed would cure the deficiency, and \naccepted the filing as so modified, obtaining PJM’s consent.21 The D.C. Circuit \nnonetheless vacated, holding that “Section 205 does not allow FERC to make \nmodifications to a proposal that transform the proposal into an entirely new rate of \nFERC’s own making,” and that the Commission’s modifications had produced an \n“entirely different rate design” than both PJM’s proposal and PJM’s prior rate \nscheme.22 The Commission had “in essence approved ‘only half of a proposed \nrate.’”23 \nHere, as discussed further infra, rehabilitating the PJM rate proposal would \nrequire, inter alia, removing PJM’s proposed exclusion of load from the VRR Curve, \nexcluding the ten-year price taker mandate, and allowing existing capacity to \ncompete on equal footing to new capacity in PJM’s BYONC scheme.  Fundamental \nchanges of such magnitude would neither be consistent with the Commission’s \nreactionary role under NRG, nor fall within the circumscribed consent to changes \nPJM provided.   \n \n21 Id. at 114.  \n22 Id. at 110, 115-16. \n23 Id. at 116 (quoting W. Res., 9 F.3d at 1579)."},{"page":11,"startToken":3327,"endToken":3608,"text":"11 \nB. \nPJM’s Proposal Would Inappropriately Stifle Supply from \nResponding to the Resource Adequacy Challenge \n1. \nFor the VRR Curve Development Only, PJM Improperly \nWill Treat Load on the System as if it Doesn’t Exist \nStarting as of the 2029/2030 Delivery Year, PJM proposes to remove from \nboth the Regional Transmission Organization (“RTO”)-wide and Locational \nDeliverability Area (“LDA”) VRR Curves the unforced capacity (“UCAP”) of New \nLarge Loads that do not BYONC or procure capacity in its newly-proposed and \nnot-yet-approved Reliability Backstop Procurement (“RBP”) auction, measured \nagainst the 2028/2029 BRA load forecast.24  In other words, PJM seeks to erase \nload from the demand curve notwithstanding that the load actually exists on the \nsystem.  PJM understands the load is actually on the system, and has not \nproposed that the required transmission or other required infrastructure need not \nbe built to reliably serve this load, just that the load will not be included in the \ndemand curve. Removing forecasted load from the quantity procured moves the \nDemand Curve to the left. Once the auction clears on a price-responsive segment, \nthat reduction lowers the clearing price, which signals to existing supply that it \nshould exit and to new supply that it should not invest.   \nAs P3 Witness Carl Coscia concludes in the attached affidavit, PJM’s IRAS \nProposal is inconsistent with the design of RPM, which was developed to deliver \nthe Net Cost of New Entry as revenue to a capacity resource on average over the \nasset’s life in capacity revenue to supplement the revenues provided by the energy \n \n24 PJM Transmittal Letter at 109-114; proposed Tariff, Definitions – Excluded RTO New \nLarge Load Amounts and Excluded LDA New Large Load Amounts."},{"page":12,"startToken":3608,"endToken":3882,"text":"12 \nand ancillary services markets.25  RPM was to provide the missing money to attract \nand retain needed resources, yet PJM has not shown that the IRAS Proposal will \nnot exacerbate the missing money problem.  Mr. Coscia provides analysis \nindicating that clearing prices below the Net Cost of New Entry across successive \nDelivery Years are outcomes of this model change.26  He indicates that RPM was \nadopted in the first place due to “a spike in announced retirements of units that \nnonetheless are needed for reliability,” and considering PJM’s warning that \n“generator revenues in PJM may not be adequate to sustain the investments \nneeded to maintain reliability in all parts of the PJM region.”27 \nNotwithstanding PJM’s historical experience and the Commission’s \nresponse acknowledging the importance of permitting an opportunity to recover \nthe Net Cost of New Entry over time, Mr. Coscia concludes as follows: \nIf the filing is accepted, PJM will construct the 2029/2030 Demand \nCurve using the reduced procurement base. The reduction will recur \nas qualifying load enters the forecast and will apply whether or not \nPJM ultimately calls an Interim Resource Adequacy Service event. \nUnder the scenarios examined, the immediate effect is a smaller \nprocurement target and increased sensitivity to the location of supply \nrelative to Point 1; after the collar expires, several modeled paths \nproduce materially lower clearing prices than the most recent Net \nCost of New Entry calculation published by PJM.28 \n \n25 Affidavit of Carl Coscia at ¶ 10 (“Coscia Aff.”).   \n26 Coscia Aff. at ¶ 15.   \n27 Id. (citing PJM Interconnection, L.L.C., Docket No. ER05-1410-000, Transmittal at 6 \n(Aug. 31, 2005)). \n28 Coscia Aff. at ¶ 18."},{"page":13,"startToken":3882,"endToken":4119,"text":"13 \n2. \nPJM’s VRR Curve Reset Will Cause Fewer Resources to \nClear Despite its Need For Additional Resources to Meet \nIncreasing Demand, Increasing Shortages and Leading to \nIncreased Prices. \nMr. Coscia models the effect of the load exclusion subsumed in the IRAS \nProposal on RPM clearing prices, showing that the capacity market clearing prices \nwith the demand exclusion begin a downward trajectory, quickly leading to a >50% \nreduction in the clearing price by 2030/2031 in the modeled scenario regardless of \nPJM’s projected continuing needs for additional capacity (e.g., the modeled clearing \nprice falls from the Point 1 price of $554.72/MW-day to $206.02/MW-day in \n2030/2031 and to $156.79/MW-day by 2032/2033):29   \n \n \nThus, while PJM has represented that it is entering the 2027/2028 Delivery \nYear short of capacity because load is growing faster than supply,30 its solution \ncounter-intuitively is to exacerbate the shortage it states it is seeking to remedy.  \nAt the same time, PJM has not provided, and cannot provide, evidence that the \nCost of New Entry or the return on investment that investors require has \n \n29 Id. at ¶ 38.  \n30 PJM Transmittal Letter at 21 (“PJM will enter the 2027/2028 Delivery Year short of \nsufficient capacity[,]” which PJM claims is due to, inter alia, an “unprecedented surge in \ndata center load” resulting in “resource adequacy in the PJM service area [being] under \nsignificant stress”)."},{"page":14,"startToken":4119,"endToken":4459,"text":"14 \ndecreased. Thus, despite PJM having more load than it can serve reliably, the \nRPM auction post-IRAS would send the improper signal that existing resources \nwhose offers exceed those depressed clearing prices and that therefore do not \nclear should exit the market.  Similarly, the message will be sent that new \nresources that cannot be financially sustained at the depressed clearing prices \nshould stay out, and resource adequacy will continue to suffer in the region.  As a \nresult of this effect on the RPM market, reliable service in PJM — even service to \nthe “existing” load — will be degraded.  This will force PJM to again engage in one \nor more out-of-market stop-gap measures to shore up resource adequacy for even \nadequate service to existing load, but as with its other out-of-market measures, the \nsolutions will not be as efficient as those driven by the market and ultimately will \nbe more costly for consumers in PJM.31  \nTo be clear, the IRAS Proposal is not expected to lower consumer costs \njust because it may yield lower RPM BRA clearing prices.  The feedback loop is \nexplained by Mr. Coscia as follows:  First, “[t]he Excluded Amount rises from 5,223 \nUCAP MW in 2029/2030 to 28,060 UCAP MW in 2032/2033, or from 3.5 percent \nto 16.4 percent of the Reliability Requirement before the subtraction.”32 Then, “load \ngrowth increases the system PJM must plan to serve; the Excluded Amount \n \n31 For example, the Reliability Must Run (“RMR”) Agreements involving Brandon Shores \nand H.A. Wagner demonstrate the phenomenon PJM was trying to avoid when it proposed \nthe RPM construct in 2005. Both facilities receive fixed payments under those RMR \nAgreements above the prevailing 2025/2026 capacity price of $269.92/MW-day with fuel \nand Variable O&M reimbursed separately.  And instead of a broad allocation, over 80% of \nthose costs are borne directly by Maryland rate payers.  H.A. Wagner LLC et al., 191 FERC \n¶ 61,098 on reh’g, 192 FERC ¶ 61,189 (2025).  \n32 Coscia Aff. at ¶ 67."},{"page":15,"startToken":4459,"endToken":4813,"text":"15 \nprevents a corresponding increase in what the Reliability Pricing Model procures; \na reduced procurement quantity lowers the price signal for entry and retention; and \na weaker investment signal can leave fewer resources available when the forecast \nload materializes.”33  And this all occurs without any PJM analysis of the long-term \nresource adequacy impacts.   \nMr. Coscia cites to PJM’s own words, and that of its expert witnesses who \nsupported the introduction of RPM in the first place, showing that the IRAS \nProposal is inconsistent with their statements of sound market design at the time.  \nHe explains:  \nConsumers may pay lower Reliability Pricing Model charges in the \nnear term, but that reduction results from buying less capacity, not \nfrom a reduction in the resources needed to serve the load or in the \ncost of providing them. PJM made the connection between reserve \nlevels and consumer costs when it originally proposed the model \nmore than twenty years ago. It told the Commission that recognizing \nvalue in capacity above the reserve margin dampens volatility and \nallows “investors to make reasonable predictions of revenue \nstreams,” which “reduces reserve and capacity price volatility and \nconsequently the return required by investors resulting in savings in \nconsumer costs.” PJM Interconnection, L.L.C., Docket Nos. ER05-\n1410-000 and EL05-148-000, Transmittal at 24 (Aug. 31, 2005). PJM \nadded that “additional reserves due to the VRR curve result in lower \ncapacity and energy costs to consumers,” and that “[e]xcess reserves \nalso further reduce the probability of loss of load and discourage \nwithholding by suppliers to increase profits.” Id. at 24-25. It supported \nthat with a table showing capacity cost falling as the reserve level \ncleared higher, and explained that the capacity savings “will be \naugmented by energy cost savings” because, as both Mr. Ott and \nProfessor Hobbs explained, “the commitment of capacity at a higher \nreserve level will tend to decrease energy market prices.” Id. at 74 \n(citing Ott Affidavit at 23-26). Reducing the reserves procured, as this \nfiling proposes, should be expected to have the opposite result across \neach of those measures: a lower capacity charge, and higher energy \n \n33 Id."},{"page":16,"startToken":4813,"endToken":5214,"text":"16 \ncosts, higher scarcity costs, and a higher probability of loss of load. \nThe filing does not analyze that trade.34 \nThe IRAS Proposal would impose a market construct that is contrary to \ndecades of well-established precedents providing that a just and reasonable \nmarket design must send appropriate price signals to encourage resource \ninvestment.35  Under applicable law, the Commission cannot depart from such \nwell-established precedent without providing reasoned analysis justifying such \ndeparture,36 but PJM has utterly failed to provide the analysis the Commission \nwould need to rely on.  \nMr. Coscia tests PJM’s assertion that its BYONC proposal represents a \n“symmetrical, one-for-one addition” and yields “an effectively price-neutral \noutcome.”37  He invalidates the assertion in several scenarios, showing that the \n \n34 Id. at ¶ 68.  \n35 See, e.g., PJM Interconnection, L.L.C., 171 FERC ¶ 61,153, at P 221 (2020) (finding \nPJM’s reserve market unjust and unreasonable in part because it did “not yield market \nprices that reasonably reflect the marginal cost of procuring necessary reserves, and thus \ndoes not send appropriate price signals for efficient resource investment”); PJM \nInterconnection, L.L.C., 119 FERC ¶ 61,318, at P 51 (2007) (“[a]n important function in \ndesigning rates is to ensure that such rates provide sufficient incentive for the construction \nof infrastructure necessary to meet the needs of the system”); Calpine Corp., 163 FERC ¶ \n61,236, at P 65 (2018) (finding PJM's “Capacity Repricing” mechanism unjust and \nunreasonable because, by disconnecting price and quantity determination, it would “fail to \nprovide a useful signal to market participants regarding whether a resource will clear the \nmarket or whether new entry or retirement is needed, jeopardizing the PJM capacity \nmarket's ability to ensure resource adequacy going forward”); N.Y. Indep. Sys. Operator, \n103 FERC ¶ 61,201, at P 1 (2003) (accepting a tariff revision as just and reasonable \nbecause it “will provide better price signals to investors for the construction of new \ngeneration”). The Commission has stated that “accurate price signals are the link between \ncurrent usage and future expansion.” Regional Transmission Organizations, Order No. \n2000, 65 Fed. Reg. 810, 910 (Jan. 6, 2000).    \n36 W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 17 (D.C. Cir. 2014) (“The Commission \ncannot depart from [its precedent] without ‘provid[ing] a reasoned analysis indicating that \nprior policies and standards are being deliberately changed, not casually ignored’”).   \n37 PJM Transmittal Letter at 58."},{"page":17,"startToken":5214,"endToken":5556,"text":"17 \nVRR Curve moves to the left as more load is excluded from it.  Troublingly, he \nconcludes that the asserted price-neutral outcome does not hold in numerous \nTariff scenarios.38  Mr. Coscia concludes: \nThe filed record does not establish whether the proposed changes \nwill meet the objective of the design they modify: to provide, on \naverage over an asset’s useful life, the Net Cost of New Entry. PJM’s \nfiling does not identify the threshold at which the exclusion begins to \naffect price, provide a sensitivity around the Excluded Amount, \nevaluate the exclusion together with the zero-priced backstop supply \navailable in the same auctions, or test the resulting price against Net \nCost of New Entry — the figure PJM itself calculates to represent the \ncost of a new reference resource, and the anchor from which the \nDemand Curve’s price coordinates are derived. \nFrom an investor’s standpoint, the range of outcomes introduces significant \ndoubt as to whether there is an opportunity to recover the Net Cost of New Entry \nover time.  Mr. Coscia explains that the range of outcomes:  \ndepends on future supply, backstop participation, Bring Your Own \nNew Capacity coverage, and the allocation of RBP UCAP MW. None \nof those inputs will be known when an investor commits capital. An \ninvestor financing a long-lived generating asset would reflect the \nresulting range of potential capacity revenues in its required return, in \nfinancing terms, or in both. That is the uncertainty PJM said the \nReliability Pricing Model would remove: in 2005 PJM told the \nCommission that recognizing capacity value above the reserve \nmargin would dampen volatility, “making estimates of future prices \nmore reliable and allowing investors to make reasonable predictions \nof revenue streams,” and would thereby “reduce[] . . . the return \nrequired by investors resulting in savings in consumer costs.”39 \nOver the longer term, Mr. Coscia explains that the PJM proposal results in \na bifurcated capacity market wherein there is: \n \n38 Coscia Aff. at ¶¶ 53-58.   \n39 Coscia Aff. at ¶ 62 (citing PJM Interconnection, L.L.C., Docket No. ER05-1410-000, \nTransmittal Letter at 24 (filed Aug. 31, 2005))."},{"page":18,"startToken":5556,"endToken":5909,"text":"18 \nload inside the Demand Curve, against which PJM procures capacity, \nand load outside it, which PJM plans and operates the system to \nserve but does not buy against. A market in which a substantial and \ngrowing share of load sits outside the mechanism designed to price \nreliability weakens the connection between the system PJM plans to \noperate and the capacity the model procures, with corresponding \nconsequences for entry, retention and resource adequacy.40    \nHe explains:   \nThe resource-adequacy effect reaches both entry and retention. A \nsustained price below the most recently posted Net Cost of New Entry \nbenchmark weakens the signal for new investment. Lower expected \ncapacity revenues may also affect retention, where an existing \nresource’s expected market revenues no longer cover its going-\nforward costs. Measured against the Reliability Requirement before \nthe exclusion, the modeled market is short in every Delivery Year \nexamined, and Appendix A.5 shows the shortfall widening across the \nperiod. New generation becomes existing generation, so the same \nmarket design reaches a resource first as a new entrant and later as \nan existing unit: capacity supporting a Bring Your Own New Capacity \narrangement offers as a price taker for ten Delivery Years and then \ncompetes as merchant capacity, and backstop capacity does so for \nfifteen. The modeled price reduction is therefore not merely a \nredistribution of capacity-market revenues between sellers and \nbuyers. It is the means by which the reduced procurement target \nreaches decisions to build, finance, retain or retire the resources PJM \ncontinues to rely on to serve the full load forecast.41 \nThe counter-intuitive nature of what PJM has proposed in relation to what it \nstates its proposal seeks to accomplish may explain why PJM was unable to find \na market-design witness to sponsor the IRAS Proposal.  As a result, the filing \nleaves the answers to critical questions unanswered.  Mr. Coscia provides \nexamples: \nPJM derives the Forecast Pool Requirement from the full load \nforecast and applies it to a load basis from which the Excluded \nAmount has been removed. PJM does not show that the planning \n \n40 Coscia Aff. at ¶ 19.   \n41 Coscia Aff. at ¶ 63."},{"page":19,"startToken":5909,"endToken":6202,"text":"19 \nparameters are inert to that removal. The question is whether the \nreliability model would solve to the same Installed Reserve Margin, \nthe same ELCC Class Ratings and the same pool-wide factor if the \nexcluded load were taken out of the load scenarios.42 \nBecause of unanswered questions like these, the Commission has no option but \nto reject the IRAS Proposal.  It would be facially arbitrary and capricious to accept \na proposal requesting action inconsistent with the proposal’s own proffered \njustification.43   \n3. \nPJM’s VRR Curve Reset is Fundamentally Flawed. \nThe exclusion of this load from the VRR Curve is not conditioned on the \nexistence of a capacity shortfall, or on whether any load reduction is ever called. \nBeginning with the 2029/2030 Delivery Year, the curve is proposed to be reduced \nin every Delivery Year, in an amount recalculated annually against a fixed \n2028/2029 baseline.  IRAS, by contrast, is available only in Delivery Years with a \nshortfall measured after the Third Incremental Auction, and only up to that shortfall. \nThus, in any Delivery Year without a shortfall, the demand curve is reduced while \nno curtailments will be triggered.  \n \n42 Coscia Aff. at ¶ 82.   \n43 Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983) \n(agency must articulate a rational connection between facts found and choice made); World \nShipping Council v. Fed. Mar. Comm'n, 152 F.4th 215, 223-224 (D.C. Cir. 2025) (vacating \nportion of a Federal Maritime Commission rule that was inconsistent with the rule’s central \nlogic); see also Ameren Servs. Co. v. FERC, 880 F.3d 571, 582 (D.C. Cir. 2018) \n(remanding portion of FERC order for failure to demonstrate how it would address the \nalleged discrimination it sought to remedy)."},{"page":20,"startToken":6202,"endToken":6507,"text":"20 \nPer the IRAS Proposal, in a Delivery Year with no capacity shortfall, IRAS \nwon’t be invoked,44 but the VRR Curve will still be reduced.  And adding further \ninjury still, even in years when IRAS is invoked, the MW quantity taken out of the \nVRR Curve is likely to  exceed the MW quantity interruptible under IRAS because, \nas PJM admits, IRAS is available only in Delivery Years in which a PJM Region \nReliability Requirement shortfall exists following the Third Incremental Auction, and \nonly up to that shortfall.45  The MWs removed from the curve therefore are primed \nto exceed the MWs PJM can actually interrupt.46  PJM offers zero analysis as to \nthe quantity of the MWs it will exclude from the VRR Curve versus the MWs that it \nactually expects will be interrupted in any particular Delivery Year.    \nPJM asserts that its treatment of New Large Loads causes no harm, \nbecause such loads “are not expected to be indefinitely excluded” and since \nincluding them in the demand curve “is counterbalanced by the inclusion of a \ncommensurate amount of additional Capacity Resources that are added to the \nsupply curve,” producing “an effectively price-neutral outcome for the rest of the \nmarket.”47 However, PJM’s statements are only true as to those New Large Loads \nthat arrive with BYONC. They are untrue as to the New Large Load that is excluded \nfrom the demand curve that does not have BYONC. For excluded load there is no \n \n44 PJM Transmittal Letter at 97 (“IRAS is only applicable in Delivery Years when New Large \nLoads without arrangements with new capacity give rise to a PJM Region Reliability \nRequirement shortfall”). \n45 See PJM Transmittal Letter at 70-72; proposed Tariff, Attachment DD-4, section IV(b)(i)–\n(ii). \n46 Coscia Aff. at ¶¶ 106–07. \n47 PJM Transmittal Letter at 58, 115."},{"page":21,"startToken":6507,"endToken":6713,"text":"21 \ncounterbalancing supply addition, no commensurate Capacity Resource, and no \nsymmetry. The demand curve moves left against an unchanged supply curve, \nyielding a clearing price that should be expected to prompt the exit of existing \nresources and have a chilling effect on any new entry, given the lack of  a path to \nrecovering its capital investment.  Capital will predictably flow away from electric \ngeneration into industries where positive returns rather than losses are \ncontemplated.   \nThus, at the same time PJM acknowledges the importance of hewing to \nmarket design fundamentals, it proposes to violate them.  It requires that a BYONC \nresource not clear before its associated load is added to the demand curve, \nbecause otherwise “the RPM Auction would not reflect actual supply and demand \nfundamentals.” 48  But even though Excluded New Large Load remains \ninterconnected, takes Network Integration Transmission Service, and consumes in \nevery hour, PJM is unbothered by the departure from supply and demand \nfundamentals excluding its load represents. It provides no analysis of IRAS’ effect \non long-term resource adequacy.49  PJM is speaking out of both sides of its mouth.  \nThe Commission should not endorse the departure from market fundamentals the \nIRAS Proposal would memorialize. \n \n48 Id. at 115.  \n49 Coscia Aff. at ¶ 67."},{"page":22,"startToken":6713,"endToken":6951,"text":"22 \n4. \nPJM Inappropriately Would Mandate BYONC Resources \nto Submit $0/MW-Day Offers for 10 Years, Further \nExacerbating Regional Resource Adequacy Concerns. \nPJM proposes that each BYONC resource must offer as a price taker by \nexpressly obligating them to make $0/MW-Day offers in RPM Auctions for ten \nconsecutive Delivery Years, during which they will be subject to a must-offer \nobligation and are precluded from obtaining an external-sale exception.50  PJM \nreasons that “[b]ecause the resource is already obligated to provide the capacity, \nits incremental, going-forward avoidable costs to secure the RPM commitment are \nzero.”51  But there is no evidence to support the accuracy of PJM’s assumption, \nand absolutely nothing in the Tariff that assures the seller is made whole bilaterally.  \nIf a BYONC seller’s incremental costs exceed $0/MW-Day, PJM will still require a \n$0/MW-Day offer.  While a cost-based BYONC seller’s offer might not clear, \nleaving the load's demand in the curve and the price higher, PJM’s proposed \nmandatory $0/MW-Day offer will by necessity clear and will suppress the clearing \nprice, leading to increased resource adequacy issues. Generators whose offers \nexceed that clearing price will not clear, even if they would have cleared without \nthe interference, and regardless of whether their capacity is needed to meet the \ntrue loads of the system.   \n \n50 PJM Transmittal Letter at 55–58; proposed Tariff, Attachment DD-4, §§ VIII(b), VIII(e). \n51 PJM Transmittal Letter at 57-58."},{"page":23,"startToken":6951,"endToken":7254,"text":"23 \nPJM’s citations in support of the reasonableness of its assertions as to the \npropriety of a $0/MW-Day offer in an auction are inapposite.52  They all relate to \nRMR-type situations, in which the seller has a contract that guarantees its cost \nrecovery, and within the small subset of RMR sellers, specifically to those that are \nsubject to a $0/MW-Day offer requirement.53  The discussion thus fails to apply to \nBYONC sellers, which do not have RMR protections. Regardless, PJM also misses \nthat while any individual $0/MW-Day offer requirement could be problematic for \nresource adequacy, the cumulative effect of $0/MW-Day offers from RMR \nresources, RBP resources (as PJM proposes in pending Docket No. ER26-3380) \nand now BYONC will be devastating on resource adequacy in PJM. \nThese $0/MW-Day offers are imposed by fiat rather than reflecting marginal \ncost like other offers subject to the Minimum Offer Price Rule, the Market Seller \nOffer Cap, unit-specific exemption procedures and the Independent Market \nMonitor’s Tariff Attachment M review.  In sum, whenever marginal costs exceed \n$0/MW-Day, PJM will be mandating behavior by BYONC sellers that would be \nconsidered market manipulation or an exercise of buyer market power if attempted \nby other sellers. \n \n52 PJM Transmittal Letter at 58 and n.153 (citing, inter alia, PJM Interconnection, L.L.C., \n190 FERC ¶ 61,088 at P 50; Indep. Power Producers of N.Y. v. NYISO, 150 FERC ¶ 61,214 \n(2015); and ISO New England Inc., 165 FERC ¶ 61,202 at PP 82–88 (2018)). \n53 PJM interim provisions for certain RMR units through the 2027/2028 Delivery Year are \nset forth in section 4.2.8 of PJM Manual 18: PJM Capacity Market, Revision: 62, Effective \nDecember \n17, \n2025 \nat \n68, \navailable \nat \n \nhttps://www.pjm.com/-\n/media/DotCom/documents/manuals/m18.ashx."},{"page":24,"startToken":7254,"endToken":7520,"text":"24 \nC. \nPJM Improperly Proposes to Degrade the Regional Reliability \nRequirement \nPJM proposes to establish the IRAS quantity to reflect the regional capacity \nshortfall that it measures after the Third Incremental Auction pertaining to a \nDelivery Year has occurred. 54  In other words, PJM will reduce the regional \nreliability requirement by the amount of the shortfall by relying on an expectation \nof load curtailment instead of continuing to seek to fulfil that reliability requirement \nwith capacity.  As Mr. Coscia explains: \nFrom 2028/2029 through 2032/2033, peak load net of load in an FRR \nService Area grows 31,026 MW while the Reliability Requirement net \nof the Excluded Amount changes by 584 UCAP MW. These are not \nequivalent reliability measures, but their divergence shows that the \nprocurement target no longer moves proportionately with the load \nPJM must plan to serve. Excluding load of that magnitude from the \nDemand Curve, year after year, bears directly on the premise of the \nconstruct.55 \nTherefore, while more demand is being placed on PJM’s system during that time, \nPJM’s Reliability Requirement is barely capturing any of it.  Reduced reliability is \nbaked into the IRAS Proposal, despite that PJM never acknowledges it is degrading \nreliability, let alone proves why that reliability reduction is just and reasonable.56  \nUnlike PJM, P3 Witness Mr. Coscia analyzes the proposal’s impact on winter risk, \nfinding it increased between the Delivery Years analyzed:57 \n \n54 PJM Transmittal Letter at 70-72; proposed Tariff, Attachment DD-4, §§ IV(b)(i)–(iii), \nIV(c)(i)-(ii). \n55 Coscia Aff. at ¶ 11.   \n56 Id. at ¶¶ 13, 27-35.  \n57 Id. at ¶ 75."},{"page":25,"startToken":7520,"endToken":7785,"text":"25 \n \nThe IRAS Proposal suffers from other fundamental flaws as well.  First, \nunlike Demand Response Resources, IRAS is not offered into the auction and \ndoes not clear, it is not a tested resource category, and it is not subject to the \nstringent qualification, performance, penalty and other requirements of the \nCapacity Performance construct.  Indeed, these stringent Capacity Performance \nrequirements would apply to voluntary Demand Response before it could ever \nqualify to serve as a capacity resource.  Nonetheless, PJM attempts to treat IRAS \nas accredited capacity when it is not subject to these strict checks and balances \nthat apply to actual capacity, including Demand Response.  Second, PJM \nconcedes that while IRAS depends upon load reductions being implemented when \nOperating Instructions directing them issue, it is not directing any specific Load \nServing Entity (“LSE”), any specific customer of an LSE, or any specific Large Load \nto reduce load.  PJM is relying on Electric Distributors, states and other entities \nwith which they coordinate to execute its wishes.58   \n \n58 PJM cites to model state tariffs under development in Virginia and by the Data Center \nCoalition.  PJM Transmittal Letter at 87-89.  Even the already-pending Virginia proposal, \nwhich is in the development stage, is not expected to be in place until February 1, 2027, \nwhereas IRAS would go live on June 1, 2027.  Id.  Any state without an existing model in \nplace that does not have a proceeding ongoing is unlikely to have a state tariff that is \neffective before the IRAS’ proposed implementation date.  And states are not obliged to \nproceed with any such state rules, in any event."},{"page":26,"startToken":7785,"endToken":8093,"text":"26 \nIn addition, PJM is beholden to state retail programs it concedes have yet \nto be developed and it cannot compel to be developed.  The stool that PJM seeks \nto build has no legs without the buy-in of thirteen states and the District of Columbia \non critical underpinnings to the proposal.  Through the Organization of PJM States, \nInc. (“OPSI”) those fourteen jurisdictions previously told the PJM Board of \nManagers of their concerns with what has now been filed as the IRAS Proposal.  \nOPSI stated, inter alia: \n “PJM’s updated proposal declines to address the region’s current \nresource adequacy challenges at the regional level”; \n “[T]he proposal functionally eliminates the incentive for [New Large \nLoads] to bring new capacity”;  \n The “approach is likely to lead to a patchwork of regulatory \nresponses that could lead to more reliability events in the future and \nmakes it more likely that existing residential and commercial loads \nwill be subject to curtailment. . .”; and \n The “proposal leaves important cost containment and cost \nassignment concerns unaddressed”.59 \nThe Commission cannot find a rate construct so reliant on state buy-in, and to \nwhich PJM’s member states have expressed reservations and not unanimously \nagreed, to be just and reasonable.60 \nThird, as is discussed elsewhere infra, PJM opted not to support its filing \nwith a loss of load study.  Yet its proposed change to the curtailable load on the \n \n59 Statement of OPSI to the PJM Board of Managers at the June 30, 2026 Critical Issue \nFast Path Meeting, available at https://opsi.us/wp-content/uploads/2026/06/OPSI-RBP-\nCM-Verbal-Remarks.pdf. \n60 See Delaware Div. of Pub. Advoc. v. FERC, 3 F.4th 461, 469 (D.C. Cir. 2021) (holding \nFERC could not rely on an assumption, without record evidence, that an optional market \nrule would actually be utilized as envisioned, particularly where there was evidence to the \ncontrary)."},{"page":27,"startToken":8093,"endToken":8407,"text":"27 \nsystem changes the loss of load expectation (“LOLE”).  Despite that change, PJM \ndid not, in turn, explicitly seek to change the reliability criteria set forth in the RAA.61  \nWhile PJM has not explicitly stated that the IRAS Proposal changes the regional \nreliability criteria, the proposal produces that result through a tariff change.  An \nalteration as significant as a reduction to the reliability criteria cannot proceed \nwithout supporting record evidence that is absent from the IRAS Proposal.62   \nA contrast to PJM’s FRR construct highlights a dangerous dichotomy.  In \nthe IRAS Proposal, PJM does not extend IRAS to New Large Loads in FRR \nService Areas.63  It explains that its reason is that “FRR Entities must procure \nsufficient capacity for all their New Large Loads and include such in their FRR \nCapacity Plans” and reiterates that “the FRR Entity must add new capacity for any \nNew Large Load in its territory.\"64  In its proposed RAA changes, PJM requires that \nthe procurement for such loads must be from new capacity, stating an FRR Entity: \n\"may not include in its FRR Capacity Plan any MW quantity of Existing Generation \nCapacity Resource in excess of what such FRR Entity owned or contracted . . . \n \n61 PJM enumerates the RAA changes, see PJM Transmittal Letter at 3-6, and this is not \namong them. \n62 See supra pp. 7–9 (discussing the type of evidence typically required for such changes); \nsee also PJM Interconnection, L.L.C., 194 FERC at PP 11, 45 (finding that “the analysis on \nwhich PJM relies to support its proposed VRR Curve is consistent with the Tariff \nrequirements\" because “[a]s part of the 2025 Periodic Review, PJM's consultant, Brattle, \ntested the performance and reliability of potential VRR Curves by using historical-based \nMonte Carlo modeling, a probabilistic analysis methodology\"), reh’g denied, 194 FERC ¶ \n62,139 (2026).   \n63 PJM Transmittal Letter at 73.  \n64 Id."},{"page":28,"startToken":8407,"endToken":8699,"text":"28 \nprior to June 1, 2027, to serve New Large Load.\"65  Thus, in an FRR area, the \nobligation to procure new capacity is enforceable, but outside such areas, it is not.   \nPJM has not justified this unduly discriminatory difference in treatment in \nFRR versus non-FRR areas.  In fact, for other mechanisms that reduce load \n(Demand Resources, Price Responsive Demand, Peak Shaving Adjustments, and \nbehind-the-meter generation) loads removed from PJM procurement are paired \nwith enforceable obligations associated with the load reduction.  PJM’s departure \nfrom that guiding principle in the IRAS Proposal is unsupported, unjust and \nunreasonable, and unduly discriminatory. \nD. \nPJM Seeks to Add Unduly Discriminatory Requirements to its \nTariff Through IRAS \nP3 understands that others are addressing the discriminatory nature of \nIRAS in more detail, but these points bear repeating because Section 205 of the \nFPA provides that discrimination may not be undue.  Despite this restriction, the \nIRAS Proposal would memorialize unduly discriminatory treatment in a variety of \nways, and accordingly cannot be accepted.  At a high level, the proposal unduly \ndiscriminates because: \n PJM will favor new generation over existing generation, setting up a system \nof preferences based on the vintage of the generation resource. Yet both \nnew and existing generation are capable of serving Large Loads. \n PJM would apply IRAS only to large load that connects after its proposed \nJune 2027 cutoff date.  Yet loads added to the system before and after that \ndate place the same demands on the system in terms of the capacity, \nenergy and ancillary services and transmission service they require. \n Section 202(g) of the FPA explicitly provides that in the case of an energy \nor capacity shortage, all public utility customers “will be treated, without \n \n65 Proposed RAA, Schedule 8.1 § D.1.1."},{"page":29,"startToken":8699,"endToken":9001,"text":"29 \nundue prejudice or disadvantage.”66  Yet by establishing two classes of \nlarge loads, those served by BYONC, and those not served by BYONC, and \ncodifying different treatment based on what class a large load falls within, \nPJM proposes the exact discriminatory treatment that FPA Section 202(g) \nexplicitly forbids. \n IRAS reduces the load PJM will acquire capacity to serve in the auction but \nmaterially deviates, without adequate justification, from the other Tariff-\nsanctioned mechanisms that govern situations in which PJM may reduce \nacquired load.  As Mr. Coscia details, IRAS reductions occur without the \nrigor or obligations imposed by the Fixed Resource Requirement \nAlternative, the Peak Shaving Adjustment, or Price Responsive Demand.67 \nE. \nIRAS is too Indeterminate to be Found to be a Just and \nReasonable Rate \nAttachment DD-4 § X sets the IRAS rate at 50% of the Non-Performance \nCharge Rate except in the event that an Eligible New Large Load elects to accept \nless in its retail rates or waives compensation entirely.  PJM admits that whether \nany given load is compensated “will be determined by state authorities under state \nlaw or [Relevant Electric Retail Regulatory Authority],” that implementation “relies \non application of state retail law,” and that “the IRAS rate is intended to be \nconjoined with retail rates.”68  PJM admits that the rate of compensation to Eligible \nNew Large Loads under IRAS may be zero:  \nif states decline to act and Eligible New Large Loads decline to initiate \nregulatory proceedings to recover through retail rates the wholesale \nIRAS rate, they would effectively waive a right to compensation.69 \n \n66 16 U.S.C. § 824a(g)(3)(B). \n67 Coscia Aff. at ¶¶ 96–102.  \n68 PJM Transmittal Letter at 104, 106; see also proposed Tariff, Attachment DD-4, §§ X(a), \nX(b)(i), X(c). \n69 PJM Transmittal Letter at 107."},{"page":30,"startToken":9001,"endToken":9387,"text":"30 \nThus, unlike a Demand Resource that would be compensated at a market clearing \nprice, IRAS providers would receive different compensation (or in fact no \ncompensation at all) based on the happenstance of where they are located.  Mr. \nCoscia observes:  \nThe filing does not separately analyze compensation for the recipient. \nIt provides no estimate of a New Large Load’s curtailment cost, no \nanalysis of the value of the service provided, and no comparison \nbetween the rate and the capacity charges paid by the same load.70 \nA federal program adopting such a scheme would institutionalize unduly \ndiscriminatory ratemaking treatment, 71 or at least an indeterminate ratemaking \ntreatment that Section 205 of the FPA does not abide and is also inconsistent with \nsection 202(g).72  PJM is essentially creating a pool of resources that compete with \ngeneration suppliers in PJM that may be compensated at zero for the federally-\ncompelled obligations to reduce capacity it seeks to implement.  In fact, PJM’s \nprioritization of interruptions of IRAS before Demand Response when IRAS is not \n \n70 Coscia Aff. at ¶ 120.  \n71 See 16 U.S.C. § 824d; see also Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265, 282 \n(D.C. Cir. 2022) (“undue discrimination occurs when similarly situated entities are charged \ndifferent rates for no good reason””); Dynegy Midwest Generation, Inc. v. FERC, 633 F.3d \n1122, 1127–28 (D.C. Cir. 2011) (holding unduly discriminatory an RTO tariff that permitted \ntransmission owners to choose whether or not to compensate power generators for \nproviding the same reactive power service depending on their location); FPC v. Conway \nCorp., 426 U.S. 271, 277–82 (1976) (explaining that the Commission may consider relevant \nretail-rate circumstances when determining whether a jurisdictional wholesale rate is \nunduly discriminatory). \n72 See 16 U.S.C. §§ 824d(c), 824a(g); see also, e.g., Elec. Dist. No. 1 v. FERC, 774 F.2d \n490, 493 (D.C. Cir. 1985) (“[P]urchasers of electricity cannot plan their activities unless they \nknow the cost of what they are receiving, ‘providing the necessary predictability is the whole \npurpose of the well-established filed rate doctrine’”); Transwestern Pipeline Co. v. FERC, \n897 F.2d 570, 577 (D.C. Cir. 1990) (the tariff must let purchasers “know in advance the \nconsequences of the purchasing decisions they make”)."},{"page":31,"startToken":9387,"endToken":9638,"text":"31 \nsubject to a similar accreditation process and may be uncompensated, unduly \ndiscriminates against the latter. \nF. \nPJM Seeks to Use the Reliability Standards in a Way That FPA \nSection 215 Expressly Prohibits and is Reserved to the States \nby FPA Section 201(B) \n1. \nPJM Already Has Authority to Direct Load Reductions, \nand Impermissibly Seeks to Extend that Authority to the \nRetail Level Through the IRAS Proposal \nP3 does not contend that PJM lacks authority to direct load reduction. As \nReliability Coordinator, PJM “shall act to address the reliability of its Reliability \nCoordinator Area via direct actions or by issuing Operating Instructions,” and each \nTransmission Operator, Balancing Authority, Generator Operator, and Distribution \nProvider “shall comply” with those Operating Instructions. 73  PJM, however, is \nseeking more than to confirm its authority to issue Operating Instructions that \naddress load shed through the addition of its “Interim Resource Adequacy Service \nAction.” \nExamining what proposed Attachment DD-4 adds to PJM’s existing \nauthorities lays bare the retail nature of all the new actions and demonstrates why \nits IRAS Proposal treads on states’ jurisdiction in an impermissible manner. \nIRAS Component\nRetail Character of the Addition\nAdvance designation, by registry and \nclass, of which retail customers are \ncurtailed74\nA retail service classification — a \ndetermination of what service the \ncustomer is buying\n \n73\n NERC, \nReliability \nStandard \nIRO-001-4, \nRequirements \nR1, \nR2, \nhttps://www.nerc.com/globalassets/standards/projects/technical-rationale/iro-001-\n4_clean_030723.pdf. \n74 PJM Transmittal Letter at 84 (quoting proposed Tariff, Definitions – Interim Resource \nAdequacy Service Action)."},{"page":32,"startToken":9638,"endToken":9904,"text":"32 \nIRAS Component\nRetail Character of the Addition\nA \nstanding \npriority \nplacing \nthose \ncustomers ahead of Pre-Emergency \nLoad Management75\nPriority of service among classes of \nretail customers \nA trigger measured against a capacity \nshortfall after the Third Incremental \nAuction76\nA \nplanning-horizon \nresource \nadequacy \ninstrument, \nnot \nan \noperating directive\nA compensation rate defined by what the \ncustomer accepts “in its retail rates”\nA retail rate term \nIndefinite duration, with no proposed end \ndate77\nA standing condition of retail service \n \nThe difference between what PJM already has the authority to do and what PJM \nproposes in the IRAS Proposal is retail regulation in its entirety. \n2. \nPJM Concedes That It Cannot Compel the Load Reduction \non Which the Proposal Depends. \nPJM states that its Board directed a service “applicable to ‘[N]ew Large \nLoads that, as of June 1, 2027, do not bring sufficient capacity to serve their \nresource adequacy needs and cannot otherwise be served at the 1-in-10 reliability \nstandard,’” with load reductions “occurring before deployment of Pre-Emergency \nLoad Management.”78  New Large Loads are retail customers. Whether and in \nwhat order a retail customer’s service is interrupted is determined by the states. \nIn particular, PJM acknowledges that “today Electric Distributors select, \nconsistent with their state programs, which loads to reduce in response to a PJM \n \n75 Id. at 101 (IRAS called ahead of Demand Resources and DER Capacity Aggregation \nResources). \n76 Id. at 70–72 (shortfall trigger and quantity). \n77 Id. at 72 (“PJM is not proposing an end date to the IRAS program.”) \n78 Id. at 17 (quoting the PJM Board’s July 2026 Decisional Letter)."},{"page":33,"startToken":9904,"endToken":10127,"text":"33 \nload reduction directive,” that “PJM is not looking to change any existing approach,” \nand that “the manner in which an Electric Distributor reduces load is a function of \ntheir state-approved contracts and state-approved curtailment and load reduction \nplans.” 79  PJM states that “PJM will not direct specific LSEs and/or specific \ncustomers of LSEs—including specific Large Loads—to reduce their load and/or \nswitch to on-site backup resources.”80  PJM describes the reductions as occurring \n“under state curtailment priorities implementing IRAS at the retail level.”81 \nThe remaining mechanisms of IRAS state they are elective on their face. \nThe Large Load Registry supplies information that Electric Distributors and state \nentities “may elect to rely upon when fashioning such load reduction protocols.”82 \nIRAS would “facilitate a decision by an Electric Distributor in conjunction with \nrelevant state entities.”83  And it is “Electric Distributors, in coordination with the \nappropriate states and/or RERRAs, LSEs, and LSE customers” who “will \ndetermine which loads should ultimately reduce subject to IRAS.”84  Finally, PJM \nanticipates that the operative determinations “would be worked out through revised \nstate retail tariffs” and offers that “PJM stands ready to assist states in developing \n \n79 Id. at 85. \n80 Id. at 86–87. \n81 Id. at 23. \n82 Id. at 7 (emphasis added). \n83 Id. \n84 Id. at 26, 92."},{"page":34,"startToken":10127,"endToken":10389,"text":"34 \nthose tariffs if they so desire.” 85  PJM cannot require that any such tariff be \ndeveloped, and does not claim that it can. \nPJM presents the foregoing as “cooperative federalism,” and P3 does not \ndispute that Electric Distributors and States should make retail curtailment \ndecisions.  The objection is narrower. Having conceded that the load reduction \ndepends on decisions PJM does not control, PJM proceeds to treat that reduction \nas though it were assured: it calibrates the Eligible New Large Load Amount to a \nshortfall against the PJM Regional Reliability Requirement, and it deducts that \namount from each of the three points on the VRR Curve beginning with the \n2029/2030 Delivery Year.86  The reduction in procurement is certain, recurring, and \neffective on PJM’s own motion.  The resource offered in exchange is contingent \non retail proceedings in thirteen States and the District of Columbia that have not \noccurred, under tariffs that do not yet exist, administered by regulators PJM \nconcedes it cannot direct. \nPJM’s premise is that the states will conform. But this premise is untested \nand there are good reasons states won’t conform.  A state may reasonably decline \nto implement a retail curtailment priority that penalizes reliance on the existing \ngeneration fleet, as it may conclude that doing so would accelerate the retirement \nor exit of existing resources by threatening their economic viability and \nundermining investors’ expectations that any generation can serve any load, \n \n85 Id. at 87. \n86  Id. at 70–72, 109–114, 117–18; proposed Tariff, Attachment DD-4, §§ IV, V; Id., \nAttachment DD, § 5.10(a)(i)."},{"page":35,"startToken":10389,"endToken":10627,"text":"35 \nthereby exacerbating resource adequacy problems in the region. States \nunderstand that today’s new generation is tomorrow’s existing generation, and \nmay object to the discriminatory two-class system that PJM proposes, \nunderstanding the negative signal it sends about long-lived generation assets’ \nopportunity to recover their costs over their depreciable lives.   A state may decline \nto disadvantage retail customers that have contracted with existing generation.  \nUnder the proposed framework, a New Large Load that secures capacity \nfrom an existing resource remains an Eligible New Large Load and is exposed to \ncurtailment, while an otherwise identical load that contracts for new capacity is \nnot.87  Yet it is beyond cavil that neither the FPA nor PJM can impose on states a \nrequirement to prefer new capacity over existing capacity as a principle of retail \nservice. \nFurther undermining the propriety of its proposal, PJM acknowledges that \nstates need not accept even the threshold definition on which its proposed \nframework rests, recognizing that “states may each define ‘large loads’ differently \nfor purposes of their retail tariffs, particularly those governing load reduction \nprotocols.”88  One can see how tenuous PJM’s proposal is upon considering that \nstates don’t even need to oblige on the most basic foundation of what a large load \nis, no less any of the more intrusive aspects of PJM’s proposal.  \n \n87 Proposed Tariff, Attachment DD-4, §§ VI(b)(i)–(ii); PJM Transmittal Letter at 52–55. \n88 PJM Transmittal Letter at 87."},{"page":36,"startToken":10627,"endToken":10868,"text":"36 \n3. \nThe \nBYONC \nAlternative \nDoes \nNot \nAvoid \nLoad \nInterruptions \nPJM represents that a New Large Load may “avoid facing potential load \nreduction under state curtailment priorities implementing IRAS at the retail level” \nby contracting for capacity satisfying the BYONC gating criteria.89  It does not and \ncannot say that BYONC will avoid, or even receive a priority in avoiding, \ninterruptions.  Instead, an IRAS Action  “will not be specific as to which New Large \nLoads would need to be reduced; rather, it will be based on the aggregate MW” of \nthe Electric Distributor’s assignment.90  PJM “will only direct load reduction of an \naggregate MW IRAS within the zone or area.”91  The Electric Distributor decides \nwho to curtail “consistent with their state programs” and “state-approved \ncurtailment and load reduction plans.” 92 That interruption priority need not be \nconsistent with PJM’s preferences.  Therefore, a New Large Load that contracts \nfor ten years of new capacity that must offer at $0/MW-Day obtains no assurance \nagainst curtailment and no guaranteed curtailment preference. Whether and what \nbenefit the BYONC will provide is left to the state.  Attachment DD-4 exempts no \ncustomers from emergency procedures, and PJM acknowledges that there will be \ntimes a BYONC load can contribute toward alleviating the emergency condition \n \n89 Id. at 23. \n90 Id. at 83–84. \n91 Pilong Aff. at ¶ 42; see also id. at ¶¶ 48–55; PJM Transmittal Letter at 82. \n92 PJM Transmittal Letter at 85."},{"page":37,"startToken":10868,"endToken":11267,"text":"37 \nwhereas the non-BYONC load cannot, such that the BYONC load should be \ninterrupted.93   \nPJM’s entire scheme relies on the states obliging PJM’s preferences.  Its \nproposal is founded upon avoiding the burden of interruptions by using BYONC, \nbut BYONC does not avoid the burden.  The Commission cannot reach a decision \ngrounded in solid market design principles on a hope and a prayer that the fourteen \nretail jurisdictions within PJM will oblige PJM’s preferred outcomes.94   \n4. \nPJM Seeks Authority not Granted in FPA Section 215  \nSection 215 defines the “Bulk-Power System” as facilities and control \nsystems necessary for operating an interconnected transmission network, together \nwith generation needed to maintain transmission system reliability, and provides \nthat “[t]he term does not include facilities used in the local distribution of electric \n \n93  PJM considered a hypothetical situation in which an emergency occurred in the \nDominion Zone and reasoned “[i]f load in a particular Electric Distributor zone/area is not \nnegatively impacting transmission flows into the Dominion Zone, load reduction in that \nzone/area may not have any effect on the Dominion Zone.” PJM Transmittal Letter at 82–\n83 (quoting Pilong Aff. at ¶ 53 (Example 3, AP South IROL scenario)). \n94 Delaware Div. of Pub. Advoc. v. FERC, 3 F.4th 461, 469 (D.C. Cir. 2021) (finding FERC’s \nassumption, absent evidence, that an optional market mechanism would actually be used \nwas arbitrary and capricious, particularly where evidence indicated its use would be \ncontrary to economic interests). FERC has consistently held that market rules should be \ndesigned to incentivize investments in new generation and infrastructure needed for \nsystem reliability. See, e.g., PJM Interconnection, L.L.C., 171 FERC ¶ 61,153, at P 221 \n(2020) (finding PJM’s reserve market unjust and unreasonable in part because it did “not \nyield market prices that reasonably reflect the marginal cost of procuring necessary \nreserves, and thus does not send appropriate price signals for efficient resource \ninvestment”); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318, at P 51 (2007) (“[a]n \nimportant function in designing rates is to ensure that such rates provide sufficient incentive \nfor the construction of infrastructure necessary to meet the needs of the system”); N.Y. \nIndep. Sys. Operator, 103 FERC ¶ 61,201, at P1 (2003) (accepting a tariff revision as just \nand reasonable because it “will provide better price signals to investors for the construction \nof new generation”)."},{"page":38,"startToken":11267,"endToken":11567,"text":"38 \nenergy.”95  The Electric Reliability Organization’s authority to develop and enforce \nreliability standards extends to “only the bulk-power system.”96  The Reliability \nCoordinator (“RC”) may direct a quantity of load reduction at the transmission \ninterface, but the RC’s existing authority does not extend to identifying the retail \ncustomers, served through distribution facilities, whose loads will be reduced. \nSection 215 is explicit on this point: \nThis section does not authorize the ERO or the Commission to order \nthe construction of additional generation or transmission capacity or \nto set and enforce compliance with standards for adequacy or safety \nof electric facilities or services.97 \nCongress, in fact, included a savings clause in FPA Section 215 stressing that the \nprovision not be interpreted as reducing state authority: \nNothing in this section shall be construed to preempt any authority of \nany State to take action to ensure the safety, adequacy, and reliability \nof electric service within that State, as long as such action is not \ninconsistent with any reliability standard . . . .98 \nYet through the IRAS Proposal, PJM is seeking authority to do exactly what FPA \nSection 215 says is not authorized, that is to set a standard for the adequacy of \nelectric service.99  In particular, PJM is seeking an outcome whereby a defined \nclass of retail customers, Eligible New Large Loads, will receive service of a lesser \ngrade than every other customer, and it proposes to enforce that declaration \n \n9516 U.S.C. § 824o(a)(1). \n96 Id. § 824o(i)(1). \n97 16 U.S.C. § 824o(i)(2). \n98 16 U.S.C. § 824o(i)(3). \n99 PJM admits this as it describes IRAS as addressing “resource adequacy,” and calibrates \nthe IRAS quantity to a shortfall against the PJM Region Reliability Requirement. See PJM \nTransmittal Letter at 21–22, 70–72."},{"page":39,"startToken":11567,"endToken":11829,"text":"39 \nthrough the Reliability Standards. But FPA Section 215 does not allow that result.  \nInstead, it provides that which classes of customers receive firm service, the order \nin which those classes are curtailed when service must be reduced, and how much \ncurtailable load a class must supply, are state matters.  Consistent with the FPA, \nthese cannot be set by federal tariff as PJM seeks.  \nPJM further wants to displace states’ authorities to prioritize the order of \ncurtailment contrary to Section 215.  It plans to call IRAS before Pre-Emergency \nLoad Management, a category that includes Demand Resources that voluntarily \nelected to curtail to be compensated at a federally determined rate.100  A state may \nprefer that Demand Resources be exhausted first, because those customers \nvoluntarily elected to provide, and be compensated for, their curtailments.  PJM \nwould preclude that such that, while today, priority of service among customer \nclasses is the core of what state commissions determine, in the future, that will be \ndetermined by PJM Tariff Attachment DD-4. \nPJM, in fact, concedes that state retail tariffs must be revised to fit within its \nnew framework, ironically, just within a few breaths of saying that “PJM is not \nlooking to change any existing approach.”101  A federal tariff that is premised on \nstates taking action to rewrite their retail tariffs to conform, but that cannot require \nthat to happen, yet operates whether or not they do so, cannot be found to be just \nand reasonable.   \n \n100 PJM Transmittal Letter at 101; proposed Tariff, Attachment DD-4, § III. \n101 PJM Transmittal Letter at 85, 87–89."},{"page":40,"startToken":11829,"endToken":12166,"text":"40 \nG. \nPJM’s Proposal is Inconsistent with NERC Reliability Standards \nit Relies Upon \nPJM seeks to define an Interim Resource Adequacy Service Action as “an \nOperating Instruction, as defined by NERC.”102  From there, it is able to mandate \ncompliance because Reliability Standards IRO-001-4 R2 and TOP-001-6 R3 on \nwhich PJM relies affirmatively apply to Registered Entities subject to the \nstandards.103  IRAS does not satisfy NERC’s definition of an Operating Instruction, \nhowever.  NERC’s Glossary defines an Operating Instruction as:  \nA command by operating personnel responsible for the Real-time \noperation of the interconnected Bulk Electric System to change or \npreserve the state, status, output, or input of an Element of the Bulk \nElectric System or Facility of the Bulk Electric System. (A discussion \nof general information and of potential options or alternatives to \nresolve Bulk Electric System operating concerns is not a command \nand is not considered an Operating Instruction.)104 \nIRAS does not meet that definition for a variety of reasons, a key one of which is \nthat, by statute, the Bulk Electric System excludes retail load served through \ndistribution facilities, 105  and there is no mistake that IRAS is targeted to a \ncurtailment response by retail load.  This is a critical point because if the response \nto PJM’s instruction is not mandatory under a NERC Reliability Requirement, IRAS \n \n102 Id. at 84; proposed Tariff, Definitions – Interim Resource Adequacy Service Action. \n103 While these Standards are mandatory on the Registered Entities to which they apply, \nPJM has failed to address the fact that they contain exceptions. For example, IRO-001-4 \nR2 requires compliance “unless compliance with the Operating Instructions cannot be \nphysically implemented or unless such actions would violate safety, equipment, regulatory, \nor statutory requirements.”  NERC, Reliability Standard IRO-001-4, Requirement R2, \nhttps://www.nerc.com/globalassets/standards/projects/technical-rationale/iro-001-\n4_clean_030723.pdf.  State requirements can trigger the exception.  \n104 NERC, Glossary of Terms Used in NERC Reliability Standards, “Operating Instruction,” \nhttps://www.nerc.com/glossary-of-terms?alpha=O.  \n105 16 U.S.C. § 824o(a)(1)."},{"page":41,"startToken":12166,"endToken":12414,"text":"41 \nadds nothing to the authorities PJM has today, and Attachment DD-4 is \nimplementing processes not authorized by the NERC Reliability Standards.  As a \nfurther disconnect, PJM has fabricated Attachment DD-4 § III(a) as providing \ndirections to “Electric Distributors,”  and neither Reliability Standards IRO-001-4 nor \nTOP-001-6 apply to Electric Distributors.   \nSuffice it to say that a discussion of the problems with, and internal \ninconsistencies and potential unintended consequences of, the PJM IRAS Proposal \nare extensive and significant.  PJM is seeking to tinker with decades of carefully \ncrafted market rules and Reliability Standards that protect the grid from failure.  Its \nproposal is an untested and unsupported experiment, the failure of which could \nhave catastrophic consequences.  PJM’s failure to sponsor witnesses on these \npoints is an omission the Commission should not overlook, as reputable economic \nand market design experts providing evidentiary support are a necessity to support \na major market rule change as is proposed in IRAS but are notably absent. PJM \nhas not justified its proposal and the Commission should reject it.   \nH. \nThe IRAS Proposal is Inconsistent with FPA Section 201 and \nCommission Decisions Imposing the Bright-Line Test it \nImposes. \nFPA Section 201(b)(1) provides the Commission with jurisdiction over the \nsale of electric energy at wholesale in interstate commerce, and provides that such \njurisdiction “shall not apply to any other sale of electric energy,” and further excludes \nfrom the Commission's jurisdiction “facilities used in local distribution.”106  Section \n \n106 16 U.S.C. § 824(b)(1)."},{"page":42,"startToken":12414,"endToken":12719,"text":"42 \n201(a) confines federal regulation to matters “not subject to regulation by the \nStates.”107  Here, PJM is seeking to influence whether a retail customer receives \nfirm or interruptible service.  This falls on the state side of the FPA’s bright line.   \nPJM wrongly relies on the decision in EPSA108 as supporting a finding of \nfederal jurisdiction over IRAS because IRAS has a direct effect on wholesale \ncapacity rates.  However, the EPSA decision stated the following, which is not true \nof the IRAS Proposal, the order: (1) “addresse[d] — and addresse[d] only — \ntransactions occurring on the wholesale market”; (2) it “did not set actual rates,” \nbecause “States continue to make or approve all retail rates;” and (3) it preserved \na veto for retail regulators.109  IRAS satisfies none of the three. First, Attachment \nDD-4 § III(b) requires Electric Distributors to furnish PJM the “applicable state or \nRERRA retail tariff or contractual obligations.” Second, its § X(c) provides that \nunless the retail customer elects to accept a lesser sum “in its retail rates” it must \nwaive compensation.  Third, PJM concedes that “the IRAS rate is intended to be \nconjoined with retail rates” and that implementation “relies on application of state \nretail law.”110 \nThe contrast between the IRAS Proposal and a proposal that does respect \nthe jurisdictional line, that in Order No. 719, is stark.  Order No. 719 supplies an \nexpress requirement that aggregator bids cannot be accepted when “the laws or \n \n107 16 U.S.C. §§ 824(a), (b)(1); see also New York v. FERC, 535 U.S. 1, 22–24 (2002). \n108 PJM Transmittal Letter at 91 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260 \n(2016) (“EPSA”)). \n109 EPSA, 577 U.S. at 281–83. \n110  PJM Transmittal Letter 104, 106; proposed Tariff, Attachment DD-4, §§ III(b), X(c)."},{"page":43,"startToken":12719,"endToken":13159,"text":"43 \nregulations of the relevant electric retail regulatory authority do not permit a retail \ncustomer to participate.”111  PJM obtains evidence of Retail Authority authorization \nbefore it acts.112  To the contrary, PJM proposes to impose IRAS whether or not \nstates have agreed to all of its provisions.  PJM essentially states in its filing that it \nis seeking to accomplish indirectly what it cannot do directly through IRAS. 113  \nHowever, an agency may not accomplish indirectly what it lacks power to \naccomplish directly.114  The Commission should tread with caution with regard to \noverstepping Section 201 of the FPA’s bright line in favor of avoiding the serious \nquestion of whether a federal program can be imposed on unwilling states given \nCongress’ respective authorities granted to the states and withheld from the \nCommission.115  This was true even before Loper Bright removed deference to the \n \n111 Order No. 719, 125 FERC ¶ 61,071 at P 154 (2008), and Order No. 719-B, 129 FERC \n¶ 61,252 at P 5 (2009). \n112 PJM Transmittal Letter at 47.   \n113 PJM Transmittal Letter at 85 (“PJM might not be able to directly reduce the loads of \nEligible New Large Loads to the extent they are available to provide IRAS, PJM can direct \nothers to do so with a high degree of confidence that such directives will be followed.”) A \nPJM-mandated wholesale quantity executed through directed retail-level curtailment \nachieves indirectly—by the Electric Distributor's compelled compliance—the functional \nequivalent of the retail curtailment mandate PJM disclaims authority to impose directly. \n114 See Altamont Gas Transmission Co. v. FERC, 92 F.3d 1239, 1248 (D.C. Cir. 1996) \n(rejecting FERC's attempt “to do indirectly what it could not do directly,” where the \nCommission used its jurisdictional authority over an interstate pipeline's certificate to \npressure a state regulator into changing a non-jurisdictional, state-regulated rate structure \nthat FERC itself lacked power to order directly); Nw. Cent. Pipeline Corp. v. State Corp. \nComm’n of Kan., 489 U.S. 493, 512 (1989) (quoting FPC v. Panhandle E. Pipe Line Co., \n337 U.S. 498, 513 (1949)) (“The NGA was designed to supplement state power and to \nproduce a harmonious and comprehensive regulation of the industry. Neither state nor \nfederal regulatory body was to encroach upon the jurisdiction of the other.”) (internal \nquotation marks omitted). \n115 See Edward J. DeBartolo Corp. v. Fla. Gulf Coast Bldg. & Constr. Trades Council, 485 \nU.S. 568, 575 (1988) (stating that “where an otherwise acceptable construction of a statute \nwould raise serious constitutional problems, the Court will construe the statute to avoid \nsuch problems unless such construction is plainly contrary to the intent of Congress”); see"},{"page":44,"startToken":13159,"endToken":13540,"text":"44 \nCommission’s decisions as to the scope of its own authority, but is especially \nimportant today.116  \nThe IRAS Proposal deviates from Commission precedent respecting the \nstates’ zones of authority.  As PJM acknowledges, the Commission has held that \nstates retain exclusive jurisdiction over “how the costs of the wholesale sale and \ntransmission of electricity assigned to a wholesale customer are allocated among \nthat wholesale customer’s retail customers,”117 and that states continue to regulate \n“the specific terms of retail sales to large load.”118  Contrary to these restrictions, \nIRAS would introduce a curtailment priority and a compensation-waiver election \nthat each apply to retail sales to large loads.  The load reductions in the quantities \nIRAS proposes would be federally enforced based on PJM’s method of calculating \nthe MWs to be curtailed and its method of allocating curtailments to a state, region \n \nalso Solid Waste Agency of N. Cook Cnty. v. U.S. Army Corps of Eng'rs, 531 U.S. 159, \n172–174 (2001) (holding that where an agency's interpretation “invokes the outer limits of \nCongress' power,” courts “expect a clear indication that Congress intended that result,” and \ndeclining to read the Clean Water Act to reach isolated waters because doing so “would \nresult in a significant impingement of the States' traditional and primary power over land \nand water use”); Gregory v. Ashcroft, 501 U.S. 452, 460–61 (1991) (explaining that “if \nCongress intends to alter the usual constitutional balance between the States and the \nFederal Government, it must make its intention to do so unmistakably clear in the language \nof the statute”) (internal quotation marks omitted); cf. Murphy v. NCAA, 584 U.S. 453, 473–\n78 (2018) (distinguishing impermissible federal commands to states from permissible \n“cooperative federalism” arrangements in which a state retains a genuine choice whether \nto participate in a federal regulatory scheme). \n116 Loper Bright Enters. v. Raimondo, 603 U.S. 369 (2024); see also West Virginia v. EPA, \n597 U.S. 697 (2022). \n117 PJM Transmittal Letter at 90 (quoting PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 \nat P 68 (2025), order directing compliance, December 2025 Show Cause Order, 193 FERC \n¶ 61,217 (2025)). \n118 PJM Transmittal Letter at n.239 (quoting June 2026 Order to Show Cause, 195 FERC \n¶ 61,211 at P 48 (2026))."},{"page":45,"startToken":13540,"endToken":13754,"text":"45 \nor zone.  This displaces state authority in an area reserved to the states.  The \nCommission should reject the IRAS proposal as being inconsistent with FPA \nSection 201.   \nII. \nCOMMUNICATIONS \nPlease add the following representatives of P3 to the service list maintained \nby the Secretary in this proceeding: \nSandra E. Rizzo \nAdam Masurovsky \nArnold & Porter Kaye Scholer LLP  \n601 Massachusetts Avenue, NW  \nWashington, DC 20001  \n(202) 942-5826  \nSandra.Rizzo@arnoldporter.com \nAdam.Masurovsky@arnoldporter.com \nTo the extent necessary, P3 respectfully requests a waiver of Commission \nRule 203(b)(3), 18 C.F.R. § 385.203(b)(3), to allow service to be made and \ncommunications to be addressed to each of these individuals. \nIII. \nCONCLUSION \nP3 members stand ready to address the challenge of adding new capacity \nto the grid to support the demands of New Large Loads.  The overwhelming \nresponse to the recent Cycle One queue – over 220 GWs of new capacity – stands \nas a testament to the available supply poised to enter the market if durable market \nrules are upheld.119  However, to maintain reliability while new large loads are \nadded to the grid, both new and existing resources require market-based signals \n \n119 See RTO Insider, “PJM Receives 811 Interconnection Requests in Queue Cycle 1,” \nhttps://www.rtoinsider.com/131291-pjm-receives-811-interconnection-requests-queue-\ncycle-1/."},{"page":46,"startToken":13754,"endToken":14028,"text":"46 \nthat accurately reflect the value of capacity.  That accurate price signal can only \nbe achieved by including all loads in the capacity auctions so that all supply can \ncompete to serve that load.  The vision of the PJM capacity construct is to \nencourage new capacity to be added to the system, and existing capacity to remain \non the system, based on the auction price signal.  The IRAS Proposal represents \na fundamental and dangerous divergence from this tenet of a sound market \ndesign. \nP3 takes little comfort in this moment in arguing that this filing must be \nrejected, but this filing is so fundamentally flawed that rejection is the only just and \nreasonable action the Commission can take.  In rejecting the filing, the \nCommission should encourage PJM to refile the Large Load Registry proposal as \na separate Section 205 submission while offering to provide all necessary and \nappropriate support to state commissions seeking to integrate large loads at the \ndistribution level on terms and conditions set by state regulatory authority.  These \nstate efforts can include the development of state regulatory frameworks designed \nto enable states to better integrate large loads while maintaining reliability and \nprotecting existing customers.  \nIn particular, the Commission and PJM should support the collaborative \neffort put forward by the Virginia State Corporation Commission and the Data \nCenter Coalition to develop a model large load interruptible tariff and a model \nemergency load reduction tariff that states throughout the region may decide to \nuse as a springboard for their efforts.  While no states are required to adopt any \nmodel, and every state interested in doing so can customize the tariff to meet its"},{"page":47,"startToken":14028,"endToken":14114,"text":"47 \nown state laws and needs, this approach avoids the jurisdictional overreach \nsubsumed in the IRAS Proposal.  Thoughtful state-level tariffs throughout PJM that \nprovide clear rules of the road for developers and protections for consumers will \nprovide the forward visibility necessary to shepherd the entire region through this \nunique and unprecedented challenge. \n \n/s/ Sandra E. Rizzo \n \nSandra E. Rizzo \nAdam Masurovsky \nArnold & Porter Kaye Scholer LLP \n601 Massachusetts Avenue, NW \nWashington, DC 20001 \n(202) 942-5826 \nSandra.Rizzo@arnoldporter.com \nAdam.Masurovsky@arnoldporter.com \n \n \nSeptember 3, 2026"},{"page":48,"startToken":14114,"endToken":14490,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n) \n \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \n \n) \n \n \nAFFIDAVIT OF CARL COSCIA \nON BEHALF OF PJM POWER PROVIDERS GROUP \nI. INTRODUCTION AND QUALIFICATIONS \n1. My name is Carl F. Coscia. I am the Principal of Toller Energy, an independent energy \nconsulting firm. My business address is Wynnewood, Pennsylvania 19096. I have been \nretained by the PJM Power Providers Group to evaluate the capacity market consequences \nof the Interim Resource Adequacy Service (“IRAS”) and Large Load Registry proposed by \nPJM Interconnection, L.L.C. The opinions expressed in this affidavit are my own. No part of \nmy compensation is contingent on the outcome of this proceeding. \n2. I hold a Ph.D. in Economics from the University of Minnesota, and a B.S. in Economics \nand a B.A. in Mathematics from the University of Kansas. I have more than twenty-five \nyears of experience in wholesale power and commodity markets, concentrated in market \ndesign, risk and regulatory proceedings, and have provided testimony, affidavits or \neconomic analysis in more than forty proceedings before the Federal Energy Regulatory \nCommission, the Commodity Futures Trading Commission, and other regulatory and self-\nregulatory bodies. \n3. From September 2022 to March 2026 I served as Chief Risk Officer of PJM \nInterconnection, L.L.C., where I led the corporate risk function across the energy, capacity \nand financial transmission rights markets. In that role I was responsible for the risk \nassessment of market design changes, including changes to the Reliability Pricing Model \n(“RPM”), and for the Key Risk Metrics reported to the Risk Management Committee. \n4. Earlier in my career I served as a Branch Chief in the Office of Enforcement at the Federal \nEnergy Regulatory Commission, during the period in which the Commission was approving \nthe formation of Regional Transmission Organizations and considering the capacity market \nconstructs that became the Reliability Pricing Model. I subsequently held senior risk and \ncommercial roles at EnBW AG, Hartree Partners, LP, Constellation Energy and TXU, and \nconsulting positions at The Brattle Group. My experience has required me to evaluate the \nReliability Pricing Model as Commission staff, as PJM’s Chief Risk Officer, and in commercial \nroles in which market participants commit capital in reliance on market prices."},{"page":49,"startToken":14490,"endToken":14982,"text":"2 \n \n5. In preparing this affidavit I have reviewed the August 13, 2026 filing in this docket and \nthe affidavit submitted with it, the provisions of the Open Access Transmission Tariff, the \nOperating Agreement and the Reliability Assurance Agreement to which those provisions \nrefer, PJM’s planning parameters and Base Residual Auction reports, the materials \npresented to PJM stakeholders during development of the proposal, the record in Docket \nNo. ER26-3380-000, and PJM’s 2005 filing proposing the Reliability Pricing Model. \nMaterials on which I rely are cited where used. \n6. Terms used in this affidavit have the meanings given in the PJM Tariff unless otherwise \nstated. “Posted” and “Published” identify figures reproduced from cited PJM materials. \n“Derived” identifies calculations from those sources. “Scenario” identifies results under \nstated fixed assumptions; none is a forecast. \nII. EXECUTIVE SUMMARY \n7. What the model was built to do. PJM named its capacity market construct the Reliability \nPricing Model. The first word is reliability; the second is pricing. PJM proposed it in 2005 to \nreplace a construct that, in its words, “fail[ed] to assure that reliability will be maintained \nat the lowest reasonable cost, and as such, [was] unjust and unreasonable.” PJM \nInterconnection, L.L.C., Docket Nos. Nos. ER05-1410-000 and EL05-148-000, Transmittal at \n3 (Aug. 31, 2005). Its central feature was a downward-sloping demand curve, selected as \nthe curve offering “the best combination of high reliability and low long-term cost,” on the \nreasoning that dampening volatility would allow “investors to make reasonable predictions \nof revenue streams” and thereby “reduce[] . . . the return required by investors resulting in \nsavings in consumer costs.” Id. at 12, 24. The demand curve is where the quantity of \ncapacity the Region needs becomes the price paid to whatever resource meets it. \n8. How this filing departs from that design. The proposal removes New Large Load from the \ndemand curve while PJM continues to plan around serving that same load in the load \nforecast, the reliability studies, the capacity obligations allocated under the Reliability \nAssurance Agreement, transmission planning and real-time operations. In 2005 PJM \nidentified as a defect of the prior construct that it gave demand resources “no meaningful \nopportunity . . . to compete to satisfy reliability requirements,” and sought a design letting \nthem “compete on an equal basis with existing generation resources.” Id. at 3, 9. Interim \nResource Adequacy Service load is not treated as Demand Response is treated. These \nreductions are: not willingly supplied; not studied for accreditation value; not clearly \nmeasured against a committed quantity; without a clear compliance obligation; and paid a \nrate asserted to be just and reasonable only by analogy to a charge applied to resources \nthat hold capacity commitments. Under the proposed filing these reductions do not \ncompete with other capacity resources as the original design contemplated. The load is \nremoved from the Curve instead, and its removal de facto eliminates the need for the \nGeneration Capacity Resources and Demand Resources that would otherwise have \ncompeted to serve it."},{"page":50,"startToken":14982,"endToken":15519,"text":"3 \n \n9. How the Excluded Amount operates. The Excluded Amount is New Large Load, as \nrecorded in the Large Load Registry this filing would establish, appearing in the load \nforecast above the 2028/2029 level, less load supported by Bring Your Own New Capacity \n(“BYONC”) or assigned Allocated RBP UCAP MW. It is subtracted before the Curve is \nconstructed, so the three points defining the downward-sloping portion are located at a \nsmaller quantity: the Curve moves left and its sloped segments steepen. Reliability \nBackstop Procurement capacity offering at $0/MW-day separately moves supply right. \nEither change can reduce the clearing price where the auction clears on a price-responsive \nsegment of the Demand Curve. \n10. My principal conclusion. The proposal separates the load PJM plans to serve from the \ncapacity the Reliability Pricing Model procures to serve it. PJM designed that model to \ndeliver, on average over an asset’s life, the net cost of new entry — the revenue a resource \nrequires beyond what the energy and ancillary services markets provide. In 2005 PJM told \nthe Commission the problem it sought to solve was that “net revenue to generators from all \nsources . . . has been insufficient to cover the cost of investment in the most efficient \nmarginal capacity unit.” Id. at 7. The filing makes no showing that the price its design \nproduces will deliver that revenue. \n11. Planning and procurement diverge. From 2028/2029 through 2032/2033, peak load net \nof load in an FRR Service Area grows 31,026 MW while the Reliability Requirement net of \nthe Excluded Amount changes by 584 UCAP MW. These are not equivalent reliability \nmeasures, but their divergence shows that the procurement target no longer moves \nproportionately with the load PJM must plan to serve. Excluding load of that magnitude \nfrom the Demand Curve, year after year, bears directly on the premise of the construct. ¶ \n64. \n12. Investor perspective. I evaluate the proposal from the perspective of an investor \ndeciding whether to build, finance or retain capacity in PJM. Entry and retention are \nconnected over the life of an asset: every new resource becomes an existing resource, and \nboth are required to maintain reliability. The results are scenarios, not forecasts, and \nAppendix A states the model and assumptions. \n13. The exclusion is large enough to matter. The 2028/2029 auction cleared 5,380 MW to \nthe left of Point 1, the first of the three points from which the Demand Curve is constructed \nand the quantity at which the Curve reaches its maximum price. For 2029/2030 the \nmodeled Excluded Amount closes all but approximately 290 MW of that distance. The \nauction therefore remains on the flat segment in the base case, and the collar \nindependently controls that year’s result. The exclusion nevertheless makes the outcome \nsensitive to a small change in supply, and positions later auctions to clear on the reduced \nCurve once the collar expires. PJM offers no forecast of what this does to reliability, in \nterms either of retaining the current rate of new investment or of stemming recent \nretirements. ¶¶ 27–35. \n14. Modeled effect on clearing prices. The Excluded Amount does not change the supply \navailable; it changes the Demand Curve against which that supply is offered. Holding the"},{"page":51,"startToken":15519,"endToken":16062,"text":"4 \n \nmodeled supply path constant and changing only the Demand Curve, the modeled clearing \nprice first falls below the most recently posted Net Cost of New Entry in 2030/2031, the \nfirst Delivery Year after the collar expires. ¶¶ 38–40. \n15. Consequences for entry and retention. Numerous price paths in the scenarios examined \nproduce clearing prices below the most recently posted Net Cost of New Entry, and on \nseveral of them the shortfall persists across successive Delivery Years. PJM identified the \nconsequence of revenues below that level in its 2005 filing: a spike in announced \nretirements of units that “nonetheless are needed for reliability,” and a warning that \n“generator revenues in PJM may not be adequate to sustain the investments needed to \nmaintain reliability in all parts of the PJM region.” Id. at 6. A sustained price below that \nbenchmark may weaken the signal for new entry and, depending on resource-specific \ngoing-forward costs, may also affect retention. ¶¶ 41–45, 63. \n16. Matched Bring Your Own New Capacity. PJM’s one-for-one rationale substantially holds \nwhere the supporting capacity is additional to projected additions, arrives with the load, \nand is deliverable to the relevant location. The Tariff permits configurations in which those \nconditions may not hold: the capacity may already be among the projected additions, may \nprecede the load under section VII(h), or may sit outside a constrained Locational \nDeliverability Area in which the load remains excluded. The filing does not quantify those \nalternatives. ¶¶ 53–57. \n17. The reduction is not conditioned. The Fixed Resource Requirement Alternative, the Peak \nShaving Adjustment and Price Responsive Demand each condition a reduction in the \nprocurement target on a defined commitment, and Price Responsive Demand on a price \nstated in advance. The Excluded Amount is triggered by the appearance of load in a \nforecast. Unlike those mechanisms, the Excluded Amount is not conditioned on a specified \ncommitment or performance requirement. ¶¶ 96-102, 134-135. \n18. The cumulative effect. If the filing is accepted, PJM will construct the 2029/2030 \nDemand Curve using the reduced procurement base. The reduction will recur as qualifying \nload enters the forecast and will apply whether or not PJM ultimately calls an Interim \nResource Adequacy Service event. Under the scenarios examined, the immediate effect is a \nsmaller procurement target and increased sensitivity to the location of supply relative to \nPoint 1; after the collar expires, several modeled paths produce materially lower clearing \nprices than the most recent Net Cost of New Entry calculation published by PJM. ¶¶ 64-68. \n19. The long-term effect. Load that is on the system and requires generation to serve it \nwould be excluded from the Demand Curve. That is a departure from the premise of the \nconstruct, and if approved the filing would make the departure part of the ordinary \noperation of the Reliability Pricing Model rather than a one-time accommodation. PJM \nproposes no end date for the program. Where the Region is not short for three consecutive \nDelivery Years the program becomes dormant, but the Large Load Registry is retained and \nthe exclusion re-emerges on a reset load vintage if shortfall conditions return. As additional \nqualifying load enters the forecast the Excluded Amount recurs and grows, and the filed \nTariff does not state when previously excluded load returns to the procurement base. The"},{"page":52,"startToken":16062,"endToken":16541,"text":"5 \n \nresult is a bifurcated capacity market: load inside the Demand Curve, against which PJM \nprocures capacity, and load outside it, which PJM plans and operates the system to serve \nbut does not buy against. A market in which a substantial and growing share of load sits \noutside the mechanism designed to price reliability weakens the connection between the \nsystem PJM plans to operate and the capacity the model procures, with corresponding \nconsequences for entry, retention and resource adequacy. ¶¶ 64-68. \n20. Five matters warrant Commission attention: whether procurement against a reduced \nload base satisfies the same reliability criterion used to derive the planning parameters; \nwhether the proposed mechanisms provide an equivalent accredited or binding substitute \nin every permitted configuration; whether the modeled price path remains adequate to \nsupport entry and retention; whether the differing treatment of other demand-side \nprocurement reductions is justified; and whether the proposed compensation benchmark \nmeasures the service New Large Load provides. ¶¶ 146-151. \nIII. EFFECT ON RPM CLEARING PRICES AND THE RESOURCE-\nADEQUACY INVESTMENT SIGNAL \nHow I approached the question \n21. I evaluate how the proposal affects decisions to commit, retain or withdraw capital in \nPJM capacity. A resource that cannot expect to cover its going-forward costs may deactivate \nor leave the Region, and that decision responds to the same signal as a decision to build. \nPrice is the mechanism through which a reduced procurement quantity reaches those \ndecisions. New entry and retention are not separate market-design questions. Every new \nresource becomes an existing resource, and PJM must provide a sufficient and durable \ninvestment signal throughout the asset’s operating life. The Reliability Pricing Model was \ndesigned to deliver, on average over that life, the net cost of new entry: the revenue a \nresource requires beyond what the energy and ancillary services markets provide. That \nshortfall is what the capacity market exists to supply. A capacity market that lowers the \nrevenue a resource can expect affects both the decision to build and the decision to keep \noperating, and resource adequacy depends on both. \n22. The mechanism works through the auction’s demand curve. PJM decides in advance \nhow much capacity it will buy at each price, and that schedule is the Variable Resource \nRequirement Curve. The filing would subtract the Excluded Amount from the quantity on \nwhich that Curve is built, so PJM would buy less capacity at every price, while continuing to \ncount the same load when it calculates how much capacity the Region needs to serve its \nload reliably. Separately, capacity procured through the Reliability Backstop Procurement \nis required to participate in the auction as a price taker at $0/MW-day, which adds supply \nthat clears regardless of price. Buying less and adding supply that always clears both push \nthe clearing price down. Neither does so while the auction clears on the flat portion of the \nCurve; once it clears on a sloped portion, both do."},{"page":53,"startToken":16541,"endToken":16837,"text":"6 \n \n23. Attachment DD, section 5.10(a) establishes the Curve by reference to three points. The \nunforced capacity at each point is a percentage of a bracketed quantity, and the price at \neach point is fixed by a separate formula. The percentages are 99, 101.5 and 106.0 percent, \nand the prices run from the Point 1 price down to zero at Point 3. The Excluded Amount is \nsubtracted inside the bracket, before the percentages are applied. \n24. Subtracting the Excluded Amount inside the bracket moves every point on the Curve \nleft and reduces the horizontal distance between the points in the same proportion. \nBecause the price at each point remains unchanged, the Curve steepens by a factor of 1 / (1 \n− E / RR). \n25. Figure 1 shows both effects and their consequence for price. The same supply that met \nthe flat segment of the original Curve, and cleared at the Point 1 price, meets a sloped \nsegment of the reduced Curve and clears below it. Whether that occurs depends on where \nsupply sits relative to Point 1. The next subsection quantifies that distance. \n \nFigure 1. The two effects of the Excluded Amount on the Curve, and the \nconsequence for the clearing price. \n26. The results below are scenarios and not forecasts of auction outcomes. They hold \nspecified assumptions constant in order to isolate the direction, magnitude and sensitivity \nof the effects an investor would evaluate. They compare capacity revenues between two \nmodeled cases; they are not an asset valuation, and I have not performed a discounted cash \nflow analysis. Appendix A sets out the auction model, the data sources, the calculations and \nthe full sensitivities. \nStarting conditions \n27. The 2028/2029 Base Residual Auction establishes the conditions against which the \nexclusion would first operate."},{"page":54,"startToken":16837,"endToken":17284,"text":"7 \n \nQuantity \nUCAP MW \nFRR-adjusted Reliability Requirement \n145,149.1 \nCapacity committed \n138,317.8 \nShortfall \n6,831.3 \nShortfall as a share of the requirement \n4.71% \nThe auction cleared at $325.00/MW-day, on the horizontal segment of the Curve and 5,380 \nMW to the left of Point 1. 2028/2029 Base Residual Auction Report 11, Table 5 (July 14, \n2026), available at https://perma.cc/X6UH-4ER4. \n28. Figure 2 places that outcome on the Curve. Supply is the near-vertical line at 138,318 \nUCAP MW; Point 1 stands at 143,698 MW; and the 5,380 MW between them is the distance \nthe market must close before price begins to respond. A price collar also applied. The collar \nheld the price at $325.00 where the tariff Curve, shown as the grey dashed line, would have \nproduced a higher figure. \n29. The collar is a Commission-accepted cap and floor on the clearing price, extended to all \nReliability Pricing Model auctions for the 2028/2029 and 2029/2030 Delivery Years. PJM \nInterconnection, L.L.C., 195 FERC ¶ 61,076 (2026). The Tariff states the cap as \n$256.75/MW-day in installed capacity terms divided by the ELCC Class Rating for the \nReference Resource, which is the Gas Combustion Turbine Dual Fuel class. Tariff, \nAttachment DD, section 5.10(a). That formula reproduces each posted value: at a 78 \npercent rating the cap was $329.17 for 2026/2027; at 77 percent, $333.44 for 2027/2028; \nand at 79 percent, $325.00 for 2028/2029, the price at which that auction cleared. \n[Derived.] The endorsed 2029/2030 rating is 76 percent, which sets the cap at \n$337.83/MW-day and the corresponding floor at $181.91. [Derived.] The collar does not \napply to any later Delivery Year in the period examined. \n30. PJM described the purpose of the collar in terms that bear directly on this proceeding. It \nsaid the cap and floor together would “protect[] consumers from price volatility outside the \nbounds of the price collar while also enabling capacity prices to reflect the system’s need \nfor capacity and support near-term capacity investment in PJM,” and that narrowing \nauction outcomes “is necessary to maintain investor confidence because the capacity \nmarket relies on investors to respond to auction clearing price signals.” Id. PJM added that \nthe viability of its capacity market “hinges on its ability to induce efficient entry, retention, \nand/or retirement of Capacity Resources through capacity prices.” Id. The Commission \naccepted the collar as reasonably addressing “concerns about excessive price volatility” \nwhile PJM considers reforms “to address resource adequacy challenges and better reflect \nthe needs of investors and customers.” Id. PP 129-130."},{"page":55,"startToken":17284,"endToken":17659,"text":"8 \n \n \nFigure 2. The 2028/2029 Curve, the collar, and the cleared quantity. \n31. PJM proposes in Docket No. ER26-3380-000 to procure capacity through a Reliability \nBackstop Procurement. Committed capacity is subject to a $0/MW-day offer obligation, and \nonce subject to that obligation it enters the supply stack at that price and would ordinarily \nclear, whether or not the load it was procured against has arrived. \n32. The Final Target is not fixed, and I use the illustrative quantity of 6,075.7 UCAP MW. \nEligibility for the procurement requires a commercial operation date no later than June 1, \n2032, so the outer limit on when the capacity enters service is established. What the record \ndoes not establish is which auction the capacity first offers into, and paragraph 37 states \nthe assumption I make for 2029/2030. One effect is fixed: capacity offered at $0/MW-day \nmoves the supply curve to the right. \n33. Dr. Shanker addresses the supply-side timing effect created when backstop capacity \nenters the auction before the associated load. Shanker Aff. paragraphs 13 to 17, Docket \nNo. ER26-3380-000 (Aug. 21, 2026). My analysis examines the corresponding demand-side \neffect created when forecast load is removed from the Curve. The two operate on opposite \nsides of the same auction. \n34. The exclusion first affects price when the reduced Curve intersects supply on a \ndownward-sloping segment rather than the flat segment at the Point 1 price. I refer to that \nquantity of exclusion as the threshold, because the market clears at the Point 1 price until \nthe threshold is reached and then moves down the slope, with every further megawatt of \nexclusion and every megawatt of zero-priced supply lowering the price. The distance \nbetween supply and Point 1 therefore determines both whether the exclusion affects price \nand how quickly. Figure 2 shows the geometry: supply is to the left of Point 1, so the \nmarket clears on the flat segment, and the distance between them is what has to be closed. \n35. The 2029/2030 Curve can be located from posted data, because its quantities follow \nfrom the endorsed planning parameters and the Excluded Amount is the only unposted \nterm. Figure 3 repeats the construction of Figure 2 one Delivery Year forward, with the"},{"page":56,"startToken":17659,"endToken":17936,"text":"9 \n \nExcluded Amount applied. On the Table B-9b proxy for that term, the modeled supply sits \n5,461 MW from Point 1. The Excluded Amount alone closes 5,171 MW of that distance, \nleaving approximately 290 MW. [Derived; Appendix A.2.] A market 4.71 percent below its \nReliability Requirement moves within 290 MW of Point 1 without any backstop capacity, \nbecause Point 1 is 99 percent of a requirement from which the Excluded Amount has \nalready been subtracted. The exclusion therefore brings the market close enough to Point 1 \nthat a relatively small additional supply increment can affect price in the first Delivery Year \nin which the exclusion operates. \n \nFigure 3. The 2029/2030 Curve with and without the Excluded Amount, and the \ndistance from supply to Point 1. Derived, scenario. The same construction as \nFigure 2, one Delivery Year forward and with the Excluded Amount applied. The \nExcluded Amount closes all but approximately 290 MW of the distance between \nsupply and Point 1. \nThe two cases and their common assumptions \n36. I compare two cases. In the counterfactual case the Curve is constructed on the \nReliability Requirement without the Excluded Amount. In the filing case it is constructed as \nsection 5.10(a) provides. Supply follows a single path across the Delivery Years, growing at \nthe rate stated below, and that same path is used in both cases. Within any one Delivery \nYear, therefore, the two cases face identical supply and differ only in the Curve, so the \ndifference in clearing price for that year is attributable to the Excluded Amount alone. \n37. The following inputs are held on the same basis in both cases."},{"page":57,"startToken":17936,"endToken":18312,"text":"10 \n \nInput \nTreatment \nSupply \nadditions \n4,164 MW of installed capacity per year, the rate observed across the \nfour most recent Delivery Years, converted to unforced capacity at the \nmarginal accreditation rate stated at Appendix A.4 \nBackstop, \n2029/2030 \nNone in the Base Residual Auction. Awards are expected after the \ndeadline for a Notice of Intent to Offer into that auction, and \nAttachment DD section 18.6(a) contemplates that resources without \nsuch a notice enter through an Incremental Auction. Full participation \nis stated as a sensitivity \nBackstop, later \nyears \nThe illustrative Final Target of 6,075.7 UCAP MW offered at $0/MW-\nday \nBYONC, \n2029/2030 \nNone. The reporting deadline under Attachment DD-4 section VII(c) is \nOctober 20, 2026, fifty days before the auction PJM states will \ncommence December 9, 2026. Even if the Commission acted by that \ndate, no meaningful interval remains in which to establish the Large \nLoad Registry, form and verify a ten-year arrangement, and report it. \nBYONC, later \nyears \nAlternative coverage tested below \nAllocated RBP \nUCAP MW \nRestores load to the Curve without adding supply, the backstop \nquantity already being in the zero-price block. The quantity reaching \npost-baseline New Large Load is not determinable on this record \nExcluded \nAmount \nThe Table B-9b increment above the 2028/2029 baseline, converted to \nunforced capacity terms. This is a proxy and an upper bound \nForecast Pool \nRequirement \n0.9232 in every Delivery Year. That value is endorsed for 2029/2030 \nonly \nAppendix A.5 sets out the scenario results in full, and A.2 to A.4 the derivation of each \nassumption. \nModeled effect on RPM clearing prices \n38. The table below compares the clearing price with and without the Excluded Amount, \nholding the modeled supply path constant. Under the current growth path for installed \ncapacity, the exclusion produces a price path that falls below the most recently posted Net \nCost of New Entry as early as 2030/2031 and remains below it in each later Delivery Year \nexamined. \nDelivery \nYear \nWithout exclusion \n($/MW-day) \nWith exclusion \n($/MW-day) \nPrice effect \n($/MW-day) \nAnnual effect per \nUCAP MW \n2029/30 \n$337.83 \n$337.83 \n— \n— \n2030/31 \n$554.72 \n$206.02 \n−$348.70 \n−$127,276 \n2031/32 \n$554.72 \n$178.07 \n−$376.65 \n−$137,477"},{"page":58,"startToken":18312,"endToken":18845,"text":"11 \n \nDelivery \nYear \nWithout exclusion \n($/MW-day) \nWith exclusion \n($/MW-day) \nPrice effect \n($/MW-day) \nAnnual effect per \nUCAP MW \n2032/33 \n$554.72 \n$156.79 \n−$397.93 \n−$145,244 \n[Derived, scenario. Appendix A.5.] In 2029/2030 the collar sets the price in both cases and \nthe exclusion produces no modeled price effect. Where the illustrative backstop quantity is \ninstead assumed to offer into that auction, the price with the exclusion falls to $244.64 and \nthe effect is −$93.19/MW-day, or −$34,014 per UCAP MW-year. [Derived; Appendix A.5.] \n39. For a portfolio with 1,000 UCAP MW of cleared capacity, the modeled 2030/2031 \ndifference is approximately $127 million in annual capacity revenue. The corresponding \neffect of $127,276 per UCAP MW exceeds the most recently posted annualized Net Cost of \nNew Entry benchmark of $118,877 per MW-year. [Derived.] This is a comparison of \ncapacity revenues between two modeled cases and not a valuation of any asset. \n40. The Excluded Amount does not change the supply available to the market. It changes \nthe Demand Curve against which that supply is offered. The same physical resources are \noffered in both cases; what differs is the quantity PJM commits to buy and the price at \nwhich the auction clears. \nConsequences for entry, retention and resource adequacy \n41. Under the modeled offer curve and the assumptions stated above, no rate of new \ncapacity additions holds the clearing price at the most recently posted Net Cost of New \nEntry once the illustrative Reliability Backstop Procurement quantity offers into the \nauction at $0/MW-day. With the Excluded Amount applied and no organic additions at all, \nthe modeled 2030/2031 price is $297.00. [Derived; Appendix A.5.] If the Reliability \nBackstop Procurement instead produced no megawatts, additions would have to remain \nbelow approximately 5,330 MW of installed capacity per year in 2030/2031, 3,656 MW in \n2031/2032 and 3,018 MW in 2032/2033 to hold the price at that benchmark, against an \nobserved rate of 4,164 MW. [Derived; installed capacity converted at the marginal \naccreditation rate of approximately 50 percent stated at Appendix A.33.] The modeled price \ntherefore falls below the most recently posted entry benchmark while PJM continues to \nproject a need for additional capacity. \n42. The full-proxy paths assume the whole Table B-9b increment is excluded, the \nillustrative Final RBP Target of 6,075.7 UCAP MW offers at $0/MW-day from 2030/2031, \nadditions arrive at the observed rate of 4,164 MW of installed capacity per year, and no \nNew Large Load holds Bring Your Own New Capacity or Allocated RBP UCAP MW. On those \npaths the Reliability Pricing Model produces a sustained price below the most recently \nposted Net Cost of New Entry from 2030/2031 forward, weakening the price signal for new \nentry during a period in which PJM projects a need for both entry and retention. A single \nDelivery Year below that benchmark would not establish that new entry cannot be \nfinanced, and the same-year benchmark for 2029/2030 has not been posted. What the \nanalysis shows is a sustained path below the most recent posted value across the Delivery \nYears examined."},{"page":59,"startToken":18845,"endToken":19367,"text":"12 \n \n43. The prospect that lower prices may eventually slow entry does not protect capital \ncommitted before the price effect becomes apparent. When PJM proposed the Reliability \nPricing Model it recognized that a centralized forward procurement obviates the need for \neach Load Serving Entity to arrange its own coverage and for each developer to find its own \nbuyer. PJM rejected the alternative proposals that would have relied on voluntary bilateral \nmarkets, telling the Commission that a voluntary forward market “would not require LSEs \nto arrange to cover their entire load obligation until the short-term residual auction,” that \nthis “is essentially what exists in PJM today, with the option but not the obligation to \ncontract forward for capacity,” and that “as has been experienced to date, this approach \ncreates fundamental inconsistencies between forward market results and reliability \nrequirements.” PJM Interconnection, L.L.C., Docket Nos. Nos. ER05-1410-000 and EL05-\n148-000, Transmittal at 22 (Aug. 31, 2005). The demand curve permits a merchant \ndeveloper to sell capacity without first identifying a specific buyer. Removing forecast load \nfrom the procurement quantity reduces the demand available through the centralized \nauction and returns a developer to the bilateral arrangement PJM declined to rely on. \n44. A resource relying on Bring Your Own New Capacity assumes bilateral counterparty \nexposure for ten consecutive Delivery Years against a counterparty it must identify, assess \nand monitor. Under the Reliability Pricing Model a Load Serving Entity satisfies its \nobligation by paying the Locational Reliability Charge, and Attachment DD section 5.12 \naddresses resource nonperformance and replacement with PJMSettlement as the \ncontracting party. On the compensation side of Interim Resource Adequacy Service, \nAttachment DD-4 section X(b)(iii) provides that where PJM facilitates billing the \narrangement remains bilateral, PJMSettlement is not a contracting party, and PJM, \nPJMSettlement and the Members assume no responsibility for a party’s failure to pay. The \nfiling does not address the counterparty exposure arising from the bilateral procurement \ntoward which it directs New Large Load. \n45. PJM has separately identified credit and collateral issues associated with long-term \nbilateral capacity arrangements. In its March 4, 2026 Credit and Securitization Overview, \nprepared for the Reliability Backstop Procurement, PJM reported that 41 percent of \ngeneration owners and 77 percent of Load Serving Entities are sub-investment grade, and \nthat it had identified limitations in the credit information available for data-center \ncounterparties, recording that their profile “remains opaque due to lack [of] clarity \nregarding the specific contracting entity.” PJM, Credit and Securitization Overview 7, 8 \n(Mar. 4, 2026), available at https://perma.cc/4BVQ-WDTR. That analysis addresses the \nproposed fifteen-year backstop contract rather than a Bring Your Own New Capacity \narrangement. It identifies credit issues that may also arise in a ten-year bilateral capacity \ncommitment. \nSensitivity to uncertain implementation and market outcomes \n46. The results depend on the share of New Large Load that arranges Bring Your Own New \nCapacity, whether the capacity supporting it is additional to the entry already projected, \nand how much of the Final RBP Target is allocated to post-baseline load. None is resolved \nwhen the Demand Curve is set. The following cases hold every other input at the values"},{"page":60,"startToken":19367,"endToken":19883,"text":"13 \n \nstated at paragraph 37 and vary only those three. Each figure is the clearing price with the \nExcluded Amount applied. \nCase \n2030/31 \n2031/32 \n2032/33 \nNo BYONC coverage \n$206.02 \n$178.07 \n$156.79 \nBYONC half; capacity incremental to observed growth \n$209.71 \n$182.60 \n$163.22 \nBYONC half; capacity within observed growth \n$521.34 \n$554.72 \n$554.72 \nHalf the RBP Target allocated to post-baseline load \n$267.53 \n$228.35 \n$199.46 \n[Derived, scenario. 2029/2030 is omitted: the collar sets the price in that year and, for the \nreasons at paragraph 32, no Bring Your Own New Capacity arrangement is assumed. \nAppendix A.6 sets out each case and the intermediate coverage levels.] \n47. Where the Demand Curve moves right without additional supply, the price moves \nmaterially. Where the capacity supporting Bring Your Own New Capacity is already among \nthe projected additions, restoring the covered load to the Demand Curve adds nothing to \nsupply that was not already there. Allocated RBP UCAP MW work the same way. The \nbackstop quantity is in the zero-price block whether or not it is allocated to anyone, so \nallocating it restores load to the Demand Curve without adding a megawatt of supply. \n48. The two mechanisms are not equivalent, and the difference matters. Under a Bring \nYour Own New Capacity arrangement the load returns to the Demand Curve and capacity \narrives with it; both sides of the pairing are new. Under an allocation of RBP UCAP MW only \nthe demand side is new. The capacity was procured earlier, against a different forecast, and \nentered the auction without load of its own. \n49. That difference follows from how the two quantities are determined. The Reliability \nBackstop Procurement is sized on load growth from the 2026/2027 to the 2028/2029 \nDelivery Year. Affidavit of Danielle Croop on behalf of PJM Interconnection, L.L.C. ¶¶ 43, 46, \nDocket No. ER26-3380-000 (July 31, 2026) (“Croop Aff.”). Attachment DD-4, section IX then \nallocates the entire Final RBP Target pro rata across Electric Distributor zones, and within \neach zone to New Large Loads — load in service after June 1, 2027 and above the \n2028/2029 baseline. No provision allocates any part of the Target to the load whose \ngrowth justified procuring it. \n50. An allocation of any size implies that the backstop capacity was not consumed by the \nload it was procured against, which is the configuration Dr. Shanker identifies in the \nbackstop proceeding: capacity in the auction without the load that justified it. Shanker Aff. \nparagraphs 13 to 17, Docket No. ER26-3380-000 (Aug. 21, 2026). The same Reliability \nBackstop Procurement capacity first enters the auction supply stack and may then support \nan allocation that restores different load to the Demand Curve, without adding further \nsupply. PJM would procure capacity for load that did not materialize and apply that \ncapacity to reduce what it buys against load that did. \n51. The Excluded Amount produces the widest range of modeled outcomes. At half the \nTable B-9b proxy the modeled 2030/2031 price is $521.34; at three-quarters it is $286.65."},{"page":61,"startToken":19883,"endToken":20209,"text":"14 \n \n[Derived; Appendix A.5.] One quarter of the proxy separates a clearing near the Point 1 price \nfrom one near half that price. \n \nFigure 4. The Demand Curve and the clearing price at three levels of the Excluded \nAmount, 2030/2031. Derived, scenario. Supply is the offer curve at Appendix A.4 \nshifted by two years of additions and by the illustrative backstop quantity offered \nat $0/MW-day. The three Curves carry identical price coordinates and differ only \nin the quantity excluded: none, half the Table B-9b proxy, and the full proxy. \n52. Backstop participation in the 2029/2030 Base Residual Auction is a further variable. \nAwards under the procurement are expected after the deadline for a Notice of Intent to \nOffer into that auction, and Attachment DD section 18.6(a) contemplates that resources \nwithout such a notice enter through an Incremental Auction instead. I therefore take no \nbackstop capacity into the 2029/2030 Base Residual Auction as the base case, and state full \nparticipation as a sensitivity at Appendix A.5. \n53. PJM states that a matched Bring Your Own New Capacity arrangement produces a \n“symmetrical, one-for-one addition” and “an effectively price-neutral outcome.” \nTransmittal at 58. That characterization holds in one configuration among several the \nTariff permits, and PJM offers it without identifying the conditions on which it depends or \nexamining the configurations in which it does not hold. A demonstration that the design is \nneutral in a single case is not a demonstration that it is neutral. The scenarios above show \nthat the outcome depends on three matters the filing does not address. \n54. The first is quantity. Restoring a megawatt of load moves the Curve right by the \napplicable percentage multiplier, which is 101.5 percent on the segment where these \nauctions clear, while the supporting capacity moves supply right by the megawatt itself. On \nthat measure the claim substantially holds, and I do not contend that matched capacity \nsuppresses price."},{"page":62,"startToken":20209,"endToken":20769,"text":"15 \n \n55. The 2030/2031 column of the table at paragraph 46 shows how the price moves as \ncoverage changes. With no Bring Your Own New Capacity and new entry arriving at the \nrate observed over the past four Delivery Years, the modeled price is $206.02. Where half \nthe excluded load arranges Bring Your Own New Capacity and that generation is \nincremental to the entry already expected, the price rises only to $209.71: load returns to \nthe Demand Curve and supply increases with it, so the two changes largely offset. Where \nhalf the excluded load arranges Bring Your Own New Capacity from resources that were \nexpected to enter in any event, the price rises to $521.34, because the load returns to the \nDemand Curve and nothing is added to supply. Where half the Final RBP Target is allocated \nto post-baseline load, the price is $267.53, for the same reason applied to a smaller \nquantity. [Derived; Appendix A.6.] The price responds to whether the megawatts that return \nload to the Demand Curve are new, not to whether the load is covered. \n56. On its face, a New Large Load in a constrained Locational Deliverability Area that \ncontracts with capacity outside that area may remain excluded from the Demand Curve for \nits own area even though it is restored to the Region-wide Demand Curve. The Excluded \nLDA New Large Load Amounts definition subtracts only load “in an arrangement with \nBYONC in the Locational Deliverability Area.” Tariff, Attachment A. In that configuration the \narrangement would be matched at the Region level and unmatched where the constraint \nbinds. \n57. Attachment DD-4, section VII(h) adds a fourth possibility that I do not model. It permits \na New Large Load to contract in excess of its current eligible amount in anticipation of \nexpected growth, with the full quantity offered in the first auction in which the load is on \nthe Demand Curve. The capacity may therefore precede the load, in which case the prices \nshown in the table above would be lower than my simulation indicates. \n58. The filed record does not establish whether the proposed changes will meet the \nobjective of the design they modify: to provide, on average over an asset’s useful life, the \nNet Cost of New Entry. PJM’s filing does not identify the threshold at which the exclusion \nbegins to affect price, provide a sensitivity around the Excluded Amount, evaluate the \nexclusion together with the zero-priced backstop supply available in the same auctions, or \ntest the resulting price against Net Cost of New Entry — the figure PJM itself calculates to \nrepresent the cost of a new reference resource, and the anchor from which the Demand \nCurve’s price coordinates are derived. \nInvestment implications \n59. A price below Net Cost of New Entry leaves a prospective entrant without the revenue \nto bring an investment forward, and may also affect an existing resource where its \nexpected market revenues no longer cover its going-forward costs. PJM would continue to \ninclude the associated load in determining the Region’s reliability needs while procuring \nless capacity through the auction to meet them. \n60. For a resource already in service, the modeled reduction reaches approximately \n$127,276 per UCAP MW-year by 2030/2031 and increases in later years — a shortfall \nmeasured against the revenue the Reliability Pricing Model was designed to deliver. It does"},{"page":63,"startToken":20769,"endToken":21303,"text":"16 \n \nnot reflect a change in the resource’s performance or a decline in the Region’s need for \ncapacity. The same fleet remains available, and the market remains short of its Reliability \nRequirement under both modeled cases. The difference is the quantity PJM procures and \nthe price at which the market clears. The proposal provides no direct compensation to \nexisting resources for that reduction. \n61. A prospective investor commits capital only where expected revenues support the \ncommitment. Under the full-proxy cases described in paragraph 42, the modeled price falls \nbelow the most recently posted Net Cost of New Entry beginning in 2030/2031 and \ncontinues to decline. Some other cases remain above that benchmark. The results therefore \ndo not establish a single price outcome, but they do show several plausible paths on which \nauction revenues fall below the benchmark used to assess new entry. \n62. The magnitude of the effect depends on future supply, backstop participation, Bring \nYour Own New Capacity coverage, and the allocation of RBP UCAP MW. None of those \ninputs will be known when an investor commits capital. An investor financing a long-lived \ngenerating asset would reflect the resulting range of potential capacity revenues in its \nrequired return, in financing terms, or in both. That is the uncertainty PJM said the \nReliability Pricing Model would remove: in 2005 PJM told the Commission that recognizing \ncapacity value above the reserve margin would dampen volatility, “making estimates of \nfuture prices more reliable and allowing investors to make reasonable predictions of \nrevenue streams,” and would thereby “reduce[] . . . the return required by investors \nresulting in savings in consumer costs.” Id. at 24. \n63. The resource-adequacy effect reaches both entry and retention. A sustained price \nbelow the most recently posted Net Cost of New Entry benchmark weakens the signal for \nnew investment. Lower expected capacity revenues may also affect retention, where an \nexisting resource’s expected market revenues no longer cover its going-forward costs. \nMeasured against the Reliability Requirement before the exclusion, the modeled market is \nshort in every Delivery Year examined, and Appendix A.5 shows the shortfall widening \nacross the period. New generation becomes existing generation, so the same market design \nreaches a resource first as a new entrant and later as an existing unit: capacity supporting a \nBring Your Own New Capacity arrangement offers as a price taker for ten Delivery Years \nand then competes as merchant capacity, and backstop capacity does so for fifteen. The \nmodeled price reduction is therefore not merely a redistribution of capacity-market \nrevenues between sellers and buyers. It is the means by which the reduced procurement \ntarget reaches decisions to build, finance, retain or retire the resources PJM continues to \nrely on to serve the full load forecast. \nConsequences for reliability and for the design of the market \n64. Under the stated scenario the procurement quantity has substantially stopped \nresponding to load growth. Across 2028/2029 through 2032/2033, peak load net of load in \nan FRR Service Area grows 31,026 MW while the Reliability Requirement net of the \nExcluded Amount moves 584 UCAP MW. Measured from 2029/2030, the first Delivery Year \nin which the exclusion operates, the same load base grows 25,478 MW while the net"},{"page":64,"startToken":21303,"endToken":21800,"text":"17 \n \nrequirement grows 685 UCAP MW. [Derived; Appendix A.30. Both quantities are stated net of \nload in an FRR Service Area, consistent with the Reliability Pricing Model procurement base.] \nPJM would plan the system for the larger figure and buy against the smaller one. \n65. If the Commission accepts the filing as proposed, PJM constructs the 2029/2030 \nDemand Curve in December 2026 using the Excluded Amount. The exclusion is applied \nbefore the later availability determination under Attachment DD-4, section IV(b), and \napplies whether or not Interim Resource Adequacy Service is ever called. No provision \nautomatically restores the procurement quantity if it is not, and the mechanism carries \nforward in each subsequent auction in which qualifying load remains above the 2028/2029 \nbaseline. \n66. The structure is continuing rather than temporary. PJM states that it “is not proposing \nan end date to the IRAS program,” and that it “will continue to maintain the Large Load \nRegistry” regardless of whether the Region has maintained capacity sufficient to meet the \nPJM Region Reliability Requirement for three or more years. Transmittal at 72. Where the \nRegion is not short for three consecutive Delivery Years, PJM describes the program as one \nthat “effectively goes to sleep,” with existing Bring Your Own New Capacity “relieved of \ntheir RPM participation obligations” and all New Large Loads becoming Large Loads. Id. \nThe definition then resets the vintage to load entering service “after June 1 of the first \nDelivery Year” in which the Region is again short. Id.; Proposed Tariff, Definitions — New \nLarge Load. The market rule survives the dormancy: qualifying load can again be removed \nfrom the quantity PJM procures while remaining part of the system PJM plans and operates. \nThe filed Tariff does not state when previously excluded load returns to the procurement \nbase. \n67. A lower clearing price produced by reducing the quantity procured does not establish \nthat the cost of serving the same load reliably has declined. Under the stated full-proxy \nscenario the quantity involved grows across the period examined. The Excluded Amount \nrises from 5,223 UCAP MW in 2029/2030 to 28,060 UCAP MW in 2032/2033, or from 3.5 \npercent to 16.4 percent of the Reliability Requirement before the subtraction. [Derived; \nAppendix A.3.] That final figure is the capacity-terms equivalent of 30,394 MW of large-load \ngrowth net of load in an FRR Service Area, which is 98 percent of the total net load growth \nreported at paragraph 64. [Derived.] The long-term consequence is a feedback problem: \nload growth increases the system PJM must plan to serve; the Excluded Amount prevents a \ncorresponding increase in what the Reliability Pricing Model procures; a reduced \nprocurement quantity lowers the price signal for entry and retention; and a weaker \ninvestment signal can leave fewer resources available when the forecast load materializes. \nThe filing makes the feedback possible, establishes the mechanism on a continuing basis, \nand provides no analysis of its effect on long-term resource adequacy."},{"page":65,"startToken":21800,"endToken":22306,"text":"18 \n \nIV. PLANNING ON GROSS LOAD AND PROCUREMENT NET OF \nEXCLUDED LOAD \nThe load stays in the reliability model \n68. Consumers may pay lower Reliability Pricing Model charges in the near term, but that \nreduction results from buying less capacity, not from a reduction in the resources needed \nto serve the load or in the cost of providing them. PJM made the connection between \nreserve levels and consumer costs when it originally proposed the model more than twenty \nyears ago. It told the Commission that recognizing value in capacity above the reserve \nmargin dampens volatility and allows “investors to make reasonable predictions of \nrevenue streams,” which “reduces reserve and capacity price volatility and consequently \nthe return required by investors resulting in savings in consumer costs.” PJM \nInterconnection, L.L.C., Docket Nos. ER05-1410-000 and EL05-148-000, Transmittal at 24 \n(Aug. 31, 2005). PJM added that “additional reserves due to the VRR curve result in lower \ncapacity and energy costs to consumers,” and that “[e]xcess reserves also further reduce \nthe probability of loss of load and discourage withholding by suppliers to increase profits.” \nId. at 24-25. It supported that with a table showing capacity cost falling as the reserve level \ncleared higher, and explained that the capacity savings “will be augmented by energy cost \nsavings” because, as both Mr. Ott and Professor Hobbs explained, “the commitment of \ncapacity at a higher reserve level will tend to decrease energy market prices.” Id. at 74 \n(citing Ott Affidavit at 23-26). Reducing the reserves procured, as this filing proposes, \nshould be expected to have the opposite result across each of those measures: a lower \ncapacity charge, and higher energy costs, higher scarcity costs, and a higher probability of \nloss of load. The filing does not analyze that trade. \n69. PJM’s reliability model includes New Large Load, PJM serves that load in real time, and \nthe proposal removes it only from the quantity PJM procures. The proposal does not amend \nthe Reserve Requirement Study, the ELCC study, or the Reliability Assurance Agreement \nschedules governing capacity obligations. Its only planning-parameter change adds the \nExcluded Amounts to the quantities PJM posts under Attachment DD section 5.11(a)(iii). \n70. Load that will be served must be planned for. That treatment creates the central \ndisconnect: the same load sets the planning parameters, carries the resulting capacity \nobligation, and is then removed from the quantity procured. \nThe shape change and its drivers \n71. PJM used hourly load profiles derived from the 2026 PJM Load Forecast for the \n2029/2030 Reserve Requirement and ELCC studies, the same forecast vintage used for \n2028/2029. PJM, 2026 Long-Term Load Forecast Report (Jan. 14, 2026), available at \nhttps://perma.cc/AHU2-KQ29; PJM, IRM, FPR and ELCC for the 2029/2030 BRA, Markets \nand Reliability Committee 3 (Aug. 19, 2026), available at https://perma.cc/2GK5-GHQC. \nThe load shape changed: summer extreme loads declined relative to the annual peak, while \nwinter extreme loads increased. PJM concluded that the 2029/30 load shapes placed \nupward pressure on winter risk. Id."},{"page":66,"startToken":22306,"endToken":22686,"text":"19 \n \n72. Comparing the top twentieth percentile of the seasonal peak distributions across the \ntwo studies, PJM identifies the following winter driver: “Data Center Loads: rapid data \ncenter growth is resulting in more load in January than the preceding summer.” Id. at 16. \n73. PJM’s sensitivity analysis isolates the load-shape effect from the other modeled inputs. \nThe load shapes increased the Installed Reserve Margin by about 0.4 percentage points in \nthe sensitivity, while “[o]ther inputs to the 2029/30 BRA case, particularly the updated \nResource Portfolio, have negligible impact on the IRM.” Id. at 17. The load shapes also \nincreased winter loss-of-load-hour risk by about 8 percentage points. PJM further reports \nthat other inputs, “particularly the updated Resource Portfolio, put downward pressure on \nsummer risk (which results in more winter risk).” Id. at 18. Both movements raise the \nwinter share. \n74. PJM’s sensitivity attributes the parameter movement to the load shapes collectively \nrather than to the resource portfolio. PJM separately identifies data-center growth as one \ncontributor to those shapes. The sensitivity does not isolate the data-center component \nfrom the other load-shape changes, and this opinion does not attribute the full parameter \nmovement to data centers. \nWhat the shape change did to the parameters \n75. Winter risk rose across every measure between the two studies: \nSeasonal winter share of \n2028/2029 BRA \n2029/2030 BRA \nLoss of load expectation \n60.5% \n77.9% \nLoss of load hours \n76.6% \n89.4% \nExpected unserved energy \n90.2% \n96.3% \nId. at 7. \n76. Most ELCC Class Ratings fell as the winter risk share increased. PJM states that a \n“[m]ajority of ELCC Classes see a decrease in rating due to higher winter risk share,” and \nthat the classes with the larger decreases “are those with worse performance in winter risk \nhours relative to summer risk hours.” Id. at 6. Gas CT shows the largest movement, from 67 \nto 59 percent. \nELCC Class \nAssumed ICAP \nRating change \nAccredited capacity \nGas CC \n59,922 \n−3 pts \n−1,798 \nGas CT \n11,378 \n−8 pts \n−910 \nSolar Tracking Panel \n14,900 \n−3 pts \n−447 \nGas CT Dual Fuel \n14,205 \n−3 pts \n−426 \nCoal \n31,304 \n−1 pt \n−313 \nStorage classes \n7,144 \n−2 pts \n−143 \nOnshore Wind \n3,599 \n+3 pts \n+108"},{"page":67,"startToken":22686,"endToken":23080,"text":"20 \n \n[Derived: installed capacity by class at 4; rating changes at 6.] UCAP MW. The table shows \nthe composition of the movement. It does not reconcile to the pool-wide factor, which the \nmodel solves rather than calculating as a weighted average of published class ratings. \n77. The same changes reduced the Pool-Wide Average Accredited UCAP Factor from \n0.7834 to 0.7668, which PJM attributes to “[h]igher winter risk share,” and the Forecast \nPool Requirement fell from 0.9401 to 0.9232, which PJM attributes to “[l]ower \naccreditation of resources.” Id. at 9. The Installed Reserve Margin rose from 20.0 to 20.4 \npercent on “[h]igher extreme winter loads.” Id. \nPJM quantifies the effect on an unchanged fleet \n78. Applying the 2029/2030 parameters to the 2028/2029 assumed resource portfolio and \npeak load forecast, PJM reports: \nParameter \n2028/2029 BRA \nvalues \n2029/2030 parameters, \n2028/2029 portfolio and load \nChange \nAssumed resource \nportfolio, ICAP \n196,871 \n196,871 \n— \nPeak Load Forecast \n165,567 \n165,567 \n— \nInstalled Reserve \nMargin \n20.0% \n20.4% \n+0.4 pts \nPool-Wide Average \nUCAP Factor \n0.7834 \n0.7668 \n−0.0166 \nForecast Pool \nRequirement \n0.9401 \n0.9232 \n−0.0169 \nAccredited UCAP \n154,234 \n150,961 \n−3,273 \n“Reliability \nRequirement” \n155,650 \n152,851 \n−2,799 \nUCAP Surplus \n−1,416 \n−1,890 \n−474 \nId. at 19. PJM holds the assumed portfolio and the peak load forecast at their 2028/2029 \nvalues “instead of the applicable 29/30 BRA values,” so the movement in the remaining \nrows is attributable to the parameters alone. The installed-capacity figure is the assumed \nresource portfolio described at Appendix A.4, paragraph A31, a modeling input rather than \ncapacity available in the market. The 2029/2030 assumed portfolio is 203,004 MW; this \nrun substitutes the 2028/2029 value of 196,871 MW so that the parameter effect is \nisolated. PJM states the Reliability Requirement here as the Forecast Pool Requirement \nmultiplied by the peak load forecast, assuming all load participates in the Reliability Pricing \nModel; the scenarios in Part I use the FRR-adjusted quantity. \n79. Applying the 2029/2030 parameters to the 2028/2029 portfolio and load reduces \naccredited capacity by 3,273 UCAP MW. Gas CT accounts for 910 MW of the reduction on \n11,378 MW of installed capacity. [Derived.] On the actual 2029/2030 portfolio, which is"},{"page":68,"startToken":23080,"endToken":23515,"text":"21 \n \n6,133 MW larger, Accredited UCAP instead rises 1,429 MW year over year; PJM attributes \nthat increase to the higher installed capacity and notes that “overall accreditation of \nportfolio (i.e., UCAP Factor) is lower.” Id. at 9. The counterfactual therefore measures what \nthe parameter change did to the accredited value of a given fleet, not a decline in accredited \ncapacity between the two Delivery Years. The sensitivity does not isolate the data-center \ncomponent of the load-shape change. See paragraph 74. \n80. The Forecast Pool Requirement moves in the opposite direction. Its reduction lowers \nthe Reliability Requirement by 2,799 MW over the same interval, leaving a net tightening of \n474 MW rather than 3,273 MW. PJM likewise observes that the parameters “have a small \nimpact on the UCAP Surplus change.” Id. The 3,273 MW figure measures the decline in the \naccredited value of existing supply; the 474 MW figure measures the net effect on the \nbalance. The figures answer different questions. \nPlanning on the full load and procuring against the reduced load \n81. The mechanics produce an asymmetry between the load basis used to derive the \nplanning parameters and the load basis to which those parameters are applied. \nDeriving the planning parameters \nNew Large Load \nHourly load profiles driving the Reserve Requirement Study \nincluded \nInstalled Reserve Margin \nincluded \nELCC Class Ratings and the Pool-Wide Accredited UCAP Factor \nincluded \nForecast Pool Requirement \nincluded \n \nApplying them in the procurement equation \nNew Large Load \nLoad basis to which the Forecast Pool Requirement is applied \nremoved \nQuantity against which PJM procures \nremoved \n82. PJM derives the Forecast Pool Requirement from the full load forecast and applies it to \na load basis from which the Excluded Amount has been removed. PJM does not show that \nthe planning parameters are inert to that removal. The question is whether the reliability \nmodel would solve to the same Installed Reserve Margin, the same ELCC Class Ratings and \nthe same pool-wide factor if the excluded load were taken out of the load scenarios. The \nfiling does not address it. \n83. The parameters are not fixed between auctions. Between the Base Residual Auction \nand the Third Incremental Auction for the 2026/2027 Delivery Year, a 1.61 percent \nreduction in the peak load forecast accompanied an Installed Reserve Margin falling from \n19.1 to 18.6 percent and a Pool-Wide Average Accredited UCAP Factor rising from 77.0 to \n78.3, raising the Forecast Pool Requirement 1.32 percent. [Derived: 2026/2027 planning \nparameters for both auctions.] Several inputs changed together, so the comparison does not \nisolate the load basis."},{"page":69,"startToken":23515,"endToken":24046,"text":"22 \n \n84. PJM has already sought and obtained relief from accreditation volatility for capacity \nsellers. In Docket No. ER25-2002, PJM proposed to limit the Capacity Resource Deficiency \nCharge where a shortfall results from a reduction in a resource’s Accredited UCAP Factor \nbetween the Base Residual Auction and the start of the Delivery Year, reducing the charge \nfrom the greater of 120 percent of the clearing price or $20/MW-day to 100 percent of that \nprice. PJM’s stated ground was that Accredited UCAP values “may change as a result of \nfactors that are not within the control of the resource owner, including changes in the \nexpected patterns of resource adequacy risk on the system,” and that the must-offer \nrequirement leaves a seller unable to hedge by offering less than its full Accredited UCAP. \nThe Commission accepted the revisions, finding that shifts in accreditation under the \neffective load carrying capability methodology “are driven by more complex, system-wide \nfactors” that “may not entirely be within the control of the Capacity Market Seller.” PJM \nInterconnection, L.L.C., 191 FERC ¶ 61,203 at PP 6, 39-40 (2025). The relief applies from the \n2026/2027 Delivery Year forward. \n85. The changed pattern of resource adequacy risk that gave rise to that relief is the same \none at issue here. PJM attributes the 2029/2030 accreditation decline to a higher winter \nrisk share, see paragraphs 74 and 75, and identifies data center growth as a driver of the \nload shapes that produced it, see paragraph 72. \n86. The two filings before the Commission take the further step of fixing accreditation \noutright. In Docket No. ER26-3380, Attachment DD section 18.2(d) values Qualifying RBP \nOffset UCAP MW on “the applicable ELCC Class Ratings for the 2028/2029 Delivery Year \nBRA,” and section 18.5(e) caps a Reliability Backstop Procurement Sell Offer at 120 percent \nof the resource type’s most recent maximum Preliminary ELCC Class Ratings for \n2028/2029 through the last posted Delivery Year. In this docket, Attachment DD-4 section \nVII(i) fixes the Accredited UCAP of Bring Your Own New Capacity at its value “for the RPM \nAuction in which the BYONC cleared for the initial Delivery Year the BYONC is in an \narrangement with the New Large Load.” PJM fixes accreditation where a commitment \ndepends on it, and leaves it to move where the price does. \n87. For the 2029/2030 Delivery Year the quantity removed from the procurement target is \n5,223.1 UCAP MW on the Table B-9b proxy. The accredited value lost by the existing fleet \non PJM’s counterfactual is 3,273 UCAP MW. [Derived.] The two arise from different causes \nand I draw no reconciliation between them: the first is a scenario proxy for the tariff \nexclusion, the second the product of the whole load-shape and parameter change. \nV. CONTINUING CAPACITY OBLIGATIONS AND COST \nALLOCATION \nThe obligation base includes the load the procurement target excludes \n88. The separation between the load PJM plans for and the load it procures against is not \nconfined to the Demand Curve. Capacity obligations are allocated on a peak load base that \ncounts large load in full. Reliability Assurance Agreement, Schedule 8, section A provides"},{"page":70,"startToken":24046,"endToken":24571,"text":"23 \n \nthat for each billing month the Daily Unforced Capacity Obligation of a Party that has not \nelected the FRR Alternative is determined for each Zone as Obligation Peak Load multiplied \nby the Final Zonal RPM Scaling Factor multiplied by the Forecast Pool Requirement. \nObligation Peak Load is the weather-adjusted coincident summer peak of the end-users for \nwhich the Party is responsible, \nas adjusted further to include the Obligation Peak Load associated with any Large \nLoad Adjustment that may be allocated to the Party. \nRAA, Schedule 8, section A. \n89. The two tariff terms do not cover the same load, and the analysis does not require them \nto. A Large Load Adjustment is “any MW quantity of adjustments to summer peak load at \nthe ‘zone/area’ level and summed by Zone.” RAA, article 1. New Large Load is narrower: an \nend-use load with cumulative peak load of at least 50 MW at a single electrical site, entering \nservice after June 1, 2027, and the Excluded Amounts definition further conditions it by \nexcluding load in an FRR Service Area and subtracting load in an arrangement with Bring \nYour Own New Capacity or assigned Allocated RBP UCAP MW. All the analysis requires is \nthat New Large Load sit inside the Large Load Adjustment population, so that the load \nremoved from the procurement target still carries an obligation. The population mapping \nshould be obtained to confirm that it does. \n90. Schedule 8 allocates the quantity procured. Section B sets the Base Zonal Unforced \nCapacity Obligation as the zone’s share of the Preliminary Zonal Peak Load Forecast \nmultiplied by “the RTO Unforced Capacity Obligation satisfied in the Base Residual \nAuction.” Section C1 sets the Final RTO Unforced Capacity Obligation as the sum of the \nobligations satisfied through the Base Residual and Incremental Auctions, allocated to \nzones on the Final Zonal Peak Load Forecast. \n91. PJM amended these provisions in 2024 for the express purpose of making forecasted \nlarge load carry a capacity obligation. The revisions to Schedule 8, Schedule 8.1 and the \nLarge Load Adjustment definition were presented to the Members Committee on June 27, \n2024 under the heading “Capacity Obligations for Forecasted Large Load Adjustments.” If \nthe Large Load Adjustment quantities assigned under Schedule 8 include the same New \nLarge Load removed through the Excluded Amount definitions, the design would assign an \nobligation using the full forecast while constructing the Curve on a reduced procurement \nbase. That population mapping should be confirmed against the currently effective \nReliability Assurance Agreement, and I state the conclusion conditionally on that basis. \n92. If the Large Load Adjustment population includes the New Large Load removed \nthrough the Excluded Amount definitions, that load continues to enter the obligation \nallocation. Its Obligation Peak Load would be counted, and its Load Serving Entity would \npay a Locational Reliability Charge on that basis. Reliability Assurance Agreement, \nSchedule 8 builds Obligation Peak Load from the Weather Normalized Summer Peak, a \nhistorical and weather-adjusted quantity, plus “the Obligation Peak Load MW associated \nwith any Large Load Adjustment specified for such Delivery Year.” A Large Load \nAdjustment is a forecast adjustment. On that construction the forecast quantity continues"},{"page":71,"startToken":24571,"endToken":24987,"text":"24 \n \nto enter the obligation base while being removed from the procurement base. Because the \nobligation base rises with the load forecast while the procurement target does not, the ratio \nbetween them falls as follows. \nDelivery \nYear \nPeak load less FRR \nload \nReliability Requirement net of the \nexclusion \nRatio \n2028/29 \n154,038 \n142,208 \n0.9232 \n2029/30 \n159,586 \n142,107 \n0.8905, down \n3.5% \n2030/31 \n170,264 \n142,135 \n0.8348, down \n9.6% \n2031/32 \n177,716 \n142,287 \n0.8006, down \n13.3% \n2032/33 \n185,064 \n142,792 \n0.7716, down \n16.4% \n[Derived, scenario. Both columns are stated net of load in an FRR Service Area, consistent with \nthe Reliability Pricing Model obligation base. Excluded Amounts on the Table B-9b proxy at \nparagraph 37; Forecast Pool Requirement held at 0.9232; FRR share held at its 2028/2029 \nvalue of 6.9634 percent.] \n93. The reduction is not confined to the zones where the growth is concentrated. Section B \nallocates the reduced Reliability Pricing Model obligation to zones on peak load forecast \nshares, so a zone with little or no New Large Load receives a proportionately reduced \nobligation on the same basis as a zone where the growth is concentrated. I state that at the \nlevel of the obligation allocation and not at the level of charges, which are locational: Final \nZonal RPM Scaling Factors and Final Zonal Capacity Prices differ by zone, and load in an \nFRR Service Area is outside the mechanism described at paragraphs 88 to 93 entirely. \nLimits of the opinion \n94. New Large Load should remain in PJM’s reliability studies because load that will be \nserved must be reflected in the model and in the resulting planning parameters. The \nconcern addressed here is not its inclusion in those studies. Nor is data center load the sole \ncause of the change in load shape: PJM also identifies electrification of heating as a winter \ndriver and rooftop solar growth as a summer driver. Id. at 16, and paragraph 74 states \nwhat the sensitivity does and does not establish. Finally, no load is charged for capacity \nthat PJM does not procure; total obligations equal the quantity satisfied in the auctions. The \nissue is the quantity PJM purchases. \nRelief \n95. PJM should clarify three points. \nFirst, PJM should state whether Attachment DD section 5.10(a) applies a Forecast Pool \nRequirement derived from the full load forecast or from the load basis net of the Excluded"},{"page":72,"startToken":24987,"endToken":25373,"text":"25 \n \nAmounts. If it uses the former, PJM should explain why it applies a conversion factor solved \non one load basis to another. \nSecond, PJM should explain how it reconciles the reduced Reliability Pricing Model \nobligation with an obligation base that continues to include the excluded load under \nReliability Assurance Agreement, Schedule 8, section A, and whether it intends a \ncorresponding revision to that Schedule. \nThird, PJM should state the reserve margin it expects the PJM Region to carry, measured \nagainst served load rather than the reduced procurement target, in each Delivery Year in \nwhich the exclusion operates. \n \nVI. THE ABSENCE OF A BINDING SUBSTITUTE, AND THE \nCOMPENSATION DESIGN \nComparison of the procurement reductions \n96. PJM has established several ways to reduce the quantity of capacity it procures, and \neach of them requires something in return. The Fixed Resource Requirement Alternative, \nthe Peak Shaving Adjustment and Price Responsive Demand each condition the reduction \non a defined commitment or performance condition. The Excluded Amounts do not. \nWhether the exclusion is an appropriate continuing adjustment to the procurement base, \nrather than one more demand-side mechanism, turns on that difference. \n97. The Excluded Amounts operate by formula. As Appendix B explains, New Large Load \nabove the 2028/2029 baseline holding neither Bring Your Own New Capacity nor Allocated \nRBP UCAP MW is subtracted from the Curve without any election, application, approval, or \nfinding by PJM. See Appendix B. The load appears in the forecast and the subtraction \nfollows. \nWhat the Tariff requires of the comparable mechanisms \n98. The Fixed Resource Requirement Alternative. An FRR Entity removes its load from the \nReliability Pricing Model entirely, and must designate Capacity Resources in a quantity no \nless than the Forecast Pool Requirement multiplied by its allocated share of the \nPreliminary Zonal Peak Load Forecast. RAA, Schedule 8.1, section D.2. The plan must be \napproved, must run for a multi-year term, and must comprise only Capacity Performance \nResources and Seasonal Capacity Performance Resources. Id. sections C.1, D.1.1. Deficiency \nis charged at the Point 1 price of the Variable Resource Requirement Curve. Id. section F.2. \nFor the 2028/2029 Delivery Year the FRR reduction was 10,863.8 UCAP MW, subtracted on \nthe same worksheet line as the Excluded Amounts would be. See Appendix A.2, paragraph \nA15."},{"page":73,"startToken":25373,"endToken":25807,"text":"26 \n \n99. The Peak Shaving Adjustment. A Peak Shaving Adjustment is “a load forecast \nmechanism that allows load reductions by end-use customers to result in a downward \nadjustment of the summer load forecast for the associated Zone.” Tariff, Attachment A. It \nrequires a program sponsored by the Relevant Electric Retail Regulatory Authority, \ncompliance with Attachment DD-2, and exclusivity: “[a]ny End-Use Customer identified in \nan approved peak shaving plan shall not also participate in PJM Markets as Price \nResponsive Demand, Demand Resource, Base Capacity Demand Resource, Capacity \nPerformance Demand Resource, or Economic Load Response Participant.” Id. \n100. Price Responsive Demand. Price Responsive Demand is end-use customer load \nregistered by a PRD Provider under Reliability Assurance Agreement, Schedule 6.1, with \nmetering capability specified in the PJM Manuals. Tariff, Attachment A. It requires an \napproved PRD Plan, a registered Provider, a Firm Service Level, a Maximum Emergency \nService Level, and a stated PRD Reservation Price, defined as “an RPM Auction clearing \nprice identified in a PRD Plan for Price Responsive Demand load below which the PRD \nProvider desires not to commit the identified load as Price Responsive Demand.” Id. \n101. Price Responsive Demand provides the closest tariff comparison. Its reduction of the \nReliability Requirement is price-conditioned and self-executing: the reduction applies only \nwhere the Reservation Price is at or below the clearing price. Attachment DD, section \n5.4(c)(3)(i). A PRD Provider therefore cannot reduce the quantity PJM buys on the strength \nof an expectation. It must name a price at which it will stand behind the reduction, and if \nthe market clears below that price the reduction does not occur. \n102. The four mechanisms compare as follows. \nMechanism \nWhat the Tariff requires before the procurement target is reduced \nFixed Resource \nRequirement \nApproved multi-year plan; designated Capacity Resources covering \nthe entire obligation; deficiency charged at the Point 1 price \nPeak Shaving \nAdjustment \nRERRA-sponsored program; Attachment DD-2 compliance; \nexclusivity against other participation \nPrice Responsive \nDemand \nApproved PRD Plan; registered Provider; Firm Service Level; \nMaximum Emergency Service Level; stated Reservation Price; \nreduction applies only when the clearing price equals or exceeds \nthe stated Reservation Price \nExcluded New \nLarge Load \nAmounts \nAppearance in the load forecast \n103. Attachment DD, section 5.4(c) addresses Price Responsive Demand and the Excluded \nAmounts in the same clause, directing PJM to compare the requirement “including any \nreductions to such reliability requirements as a result of any Price Responsive Demand \nwith a PRD Reservation Price equal to or lower than the clearing price in the Base Residual \nAuction for such Delivery Year and any adjustments associated with Excluded RTO New"},{"page":74,"startToken":25807,"endToken":26339,"text":"27 \n \nLarge Load Amounts or Excluded LDA New Large Load Amounts.” The price condition \nattaches to one and not the other, in a single sentence. \n104. The Tariff contains interaction rules for the Peak Shaving Adjustment, Price \nResponsive Demand, Demand Resources and demand-side Bring Your Own New Capacity, \nbut not for the Excluded Amount. The Peak Shaving Adjustment definition bars an end-use \ncustomer in an approved plan from also participating as Price Responsive Demand or as a \nDemand Resource. Attachment DD-4, section VI(a)(2) conditions demand-side Bring Your \nOwn New Capacity on locations “not previously supported [by] a Capacity Resource, a Peak \nShaving Adjustment, or Price Responsive Demand.” Neither Excluded Amounts definition \ncontains any such rule. A New Large Load whose site already carries a Peak Shaving \nAdjustment is not excluded from the Excluded Amount on that account, and nothing nets \nthe two. \n105. PJM has also stated the standard by which conditions of this kind are judged. In \nsustaining the RERRA-sponsorship limitation on the Peak Shaving Adjustment, the \nCommission accepted that the requirement gives PJM greater confidence in the durability \nof the reduction. PJM Interconnection, L.L.C., 167 FERC ¶ 61,114 at P 28 (2019). The \nExcluded Amounts are permanent as to the Tariff and conditional as to any individual load \n— the load may obtain Bring Your Own New Capacity at any time and cease to be excluded \n— which is the opposite of the durability the Commission approved. \n106. Nothing reverses an Excluded Amount for non-performance. Where Interim Resource \nAdequacy Service is called and the load does not reduce, no provision restores the \nmegawatts to the Demand Curve for the auction already completed. The vintage-date \nprovision may affect later Delivery Years, but its treatment of previously excluded load is \nunclear, as Appendix B explains. Where the service is never needed, the same is true. \n107. Bring Your Own New Capacity is not practically available for the 2029/2030 Delivery \nYear. PJM states that the Base Residual Auction for that year “is scheduled to commence on \nDecember 9, 2026, i.e., within 60 days from the requested effective date of this filing.” \nTransmittal at 62. The reporting deadline under Attachment DD-4, section VII(c) is fifty \ndays before commencement, or October 20, 2026. Even if the Commission were to act by \nthat date, the filing provides no meaningful interval in which to establish the Large Load \nRegistry, form and verify a ten-year arrangement, and report that arrangement before the \nauction. I therefore assume that no New Large Load holds Bring Your Own New Capacity \nfor the 2029/2030 Delivery Year. The exclusion nonetheless applies to that auction in full. \nThe exclusion does not depend on the IRAS availability test \n108. The shortfall test does not condition the exclusion. The Excluded RTO New Large Load \nAmounts formula subtracts the 2028/2029 baseline and post-2028/2029 New Large Load \nsupported by BYONC or assigned Allocated RBP UCAP MW. New Large Load above the \nbaseline with neither form of coverage is removed by formula without a section IV(b) \nfinding. The treatment of partially covered load remains ambiguous; that ambiguity does \nnot change the point that the exclusion occurs before the shortfall test."},{"page":75,"startToken":26339,"endToken":26833,"text":"28 \n \n109. The quantity removed and the quantity the service can deliver are computed by \ndifferent methods and need not be equal. The Excluded Amount is “converted in UCAP \nterms by using the Forecast Pool Requirement.” Tariff, Attachment A. That factor states the \ncapacity required per megawatt of load; it does not measure the contribution a curtailable \nload makes during the hours in which resource adequacy is at risk. Section IV(b) separately \ndetermines how much Interim Resource Adequacy Service must be available, by comparing \ncommitted capacity to the PJM Region Reliability Requirement determined before the Third \nIncremental Auction, divided by the Pool-wide Accredited UCAP Factor. That determination \nmay call for the whole of the Eligible New Large Load Amounts under section IV(b)(i), part \nunder IV(b)(ii), or none under IV(b)(iii). \n110. The ratio between those two quantities is the share of the removed load that converts \ninto a reliability contribution. For a Demand Resource the analogous ratio is set by an ELCC \nClass Rating derived from a probabilistic study of the resource’s contribution during risk \nhours, 90 percent for 2029/2030, and is confirmed by capacity testing. For Interim \nResource Adequacy Service no such rating is struck. The Excluded Amount leaves the \nDemand Curve in full, four years before the section IV(b) determination is made, on a \nformula that contains no reference to the shortfall against which the service is measured. \nThe filing supplies no analysis of the relationship between the two quantities. \n111. The three determinations occur years apart. PJM applies the exclusion when it \nconstructs the Curve for the December 2026 Base Residual Auction for the 2029/2030 \nDelivery Year. Section IV(b) determines annual availability after the Third Incremental \nAuction for that Delivery Year, in February 2029. During the Delivery Year, PJM separately \ndetermines whether to issue an Interim Resource Adequacy Service Action and how much \nload reduction to request. \n112. No provision restores excluded megawatts when the shortfall fails to materialize. By \nthe time section IV(b)(iii) determines that PJM “does not need any Eligible New Large \nLoads to be available,” PJM has already reduced the Curve and completed the auction. \nMr. Pilong confirms that the framework “does not require PJM to reduce affected load \nwhenever an IRAS requirement exists,” Pilong Aff. ¶ 22, and that PJM will establish the \noperational mechanics through later Manual 13 revisions, id. ¶ 24. \nThe proposed IRAS compensation \n113. Attachment DD-4, section X(a) sets the Interim Resource Adequacy Service rate at 50 \npercent of the Non-Performance Charge Rate specified in Attachment DD, section 10A(e). \nAn Eligible New Large Load may elect a lower rate or waive compensation entirely. \nThe formula \n114. Section 10A(e) states the Non-Performance Charge Rate as follows: \nFor Capacity Performance Resources and Seasonal Capacity Performance Resources, \nthe Non-Performance Charge Rate = (Net Cost of New Entry (stated in terms of \ninstalled capacity) for the LDA and Delivery Year for which such calculation is"},{"page":76,"startToken":26833,"endToken":27265,"text":"29 \n \nperformed * (the number of days in the Delivery Year / 30) / (the number of Real-\nTime Settlement Intervals in an hour). \n115. The formula calibrates the charge to one year of Net Cost of New Entry. It states Net \nCost of New Entry as a daily rate in installed-capacity terms, multiplies that rate by the \nnumber of days in the Delivery Year divided by thirty, and divides the result by the number \nof settlement intervals in an hour. On an hourly basis, the rate equals annual Net Cost of \nNew Entry divided by thirty. A Capacity Performance Resource that fails to perform in each \nof the thirty assumed Performance Assessment Hours therefore pays approximately one \nyear of Net Cost of New Entry. Net Cost of New Entry is a reference value used to construct \nthe rate, not the resource’s capacity revenue, which depends on the clearing price, \ncommitted quantity, and accreditation. \n116. Section 10A(e) introduces the formula with the words “For Capacity Performance \nResources and Seasonal Capacity Performance Resources.” An Eligible New Large Load is \nneither. Section X(a) cross-references the formula without addressing that limitation. I \ntherefore raise, but do not resolve, whether the express cross-reference carries the \nnumerical formula beyond its stated scope. \n117. Applying the 50 percent factor to the posted 2027/2028 Net Cost of New Entry \nproduces the following. \nLocational Deliverability \nArea \nNet CONE, ICAP \nNon-Performance \nCharge Rate \nSection X(a) \nrate \nRTO \n$68,347/MW-yr \n$2,278/MWh \n$1,139/MWh \nPS / PS North \n$114,258/MW-\nyr \n$3,809/MWh \n$1,904/MWh \nCOMED \n$106,831/MW-\nyr \n$3,561/MWh \n$1,781/MWh \nDOM \n$50,203/MW-yr \n$1,673/MWh \n$837/MWh \nBGE \n$40,934/MW-yr \n$1,364/MWh \n$682/MWh \n[Derived.] The locational spread reflects the Energy and Ancillary Services offset rather than \nthe value of curtailment. Net Cost of New Entry equals Gross Cost of New Entry less that offset; \nBaltimore Gas and Electric therefore has the lowest rate because it has the highest offset. \nZones in which large load is concentrating include those with the lowest rates. \nPJM’s support for the rate \n118. PJM supports the rate by analogy. It proposes “to extend the rate applicable for Pre-\nEmergency Load Response non-performance (and conversely for bonus payments) — 50% \nof the Non-Performance Charge Rate — as the maximum rate for IRAS performance,” notes \nthat the Commission accepted that rate in PJM Interconnection, L.L.C., 195 FERC ¶ 61,253 \n(2026), and concludes that it “is a just and reasonable analog for the wholesale rate PJM \nproposes here for IRAS.” Transmittal at 102-103."},{"page":77,"startToken":27265,"endToken":27663,"text":"30 \n \n119. PJM’s rationale addresses system conditions. PJM explains that the 50 percent figure \nreflects that “the PJM system is at an earlier stage of emergency conditions, so the system \nconditions are not as severe, so the value of the load reduction, while still substantial, is \nalso not as high as during a Performance Assessment Interval.” PJM further states that \nInterim Resource Adequacy Service “would be called at the emergency conditions similar \nto when Pre-Emergency Load Response is called today.” Id. at 103. \n120. The filing does not separately analyze compensation for the recipient. It provides no \nestimate of a New Large Load’s curtailment cost, no analysis of the value of the service \nprovided, and no comparison between the rate and the capacity charges paid by the same \nload. The cited precedent addresses the same numerical rate applied to different parties for \na different purpose. \nLimits of the analogy \n121. The participants differ in four respects relevant to whether the rate accepted for one \nis just and reasonable when applied to the other. \nElement \nPre-Emergency Load \nResponse participant \nEligible New Large Load \nHow it enters \noffers into the program \nregistered in the Large Load Registry; \navailability then determined under \nAttachment DD-4, section IV(b) \nPosition in the \ncapacity market \nreceives a capacity payment \npays a Locational Reliability Charge \nTerms known on \nentry \ncommitment, measurement \nand clawback are the terms \nof the offer \nthe rules did not exist when the load \nwas sited \nOrder of \ncurtailment \ncalled after \ncalled before \n122. Registration in the Large Load Registry identifies the population to which Interim \nResource Adequacy Service may apply. Attachment DD-4, section IV(b) then determines \nannually, after the Third Incremental Auction, whether any Eligible New Large Load \nAmount must be available and in what quantity. See Appendix B and paragraph 111. \nNeither step is elective for the load: the load does not choose registration or the result of \nthe section IV(b) test. It may procure Bring Your Own New Capacity, which removes it from \nthe Excluded Amount and from eligibility. \n123. A Pre-Emergency Load Response participant enters voluntarily. It offers into the \nprogram, receives payment for a capacity commitment, and accepts in advance the \nmeasurement of its performance and the recovery of part of that payment if it does not \ndeliver. The 50 percent rate forms part of an arrangement entered with knowledge of its \nterms and compensation."},{"page":78,"startToken":27663,"endToken":28194,"text":"31 \n \n124. An Eligible New Large Load enters from the buyer side. Its Obligation Peak Load \nenters the allocation under Reliability Assurance Agreement, Schedule 8, section A, and its \nLoad Serving Entity pays a Locational Reliability Charge on that basis for every day of the \nDelivery Year. See paragraphs 88 to 92. The load holds no capacity commitment and \nreceives no capacity payment. \n125. The Locational Reliability Charge the load pays and the Interim Resource Adequacy \nService rate it may receive are not linked by the Tariff, and I do not treat them as offsetting. \nAppendix A.7 sets out an arithmetic comparison of the two for a single Delivery Year. \n126. PJM’s stated rationale focuses on customers. PJM explains that “the non-performance \nrate appropriately reflects that load paid for capacity but did not get the benefit of the Pre-\nEmergency Load Response Program that PJM called upon at a time when the PJM system \nwas in stressed system conditions.” PJM further explains that the collected amounts are \nallocated to demand resources that overperformed, “with residual monies collected in \ncertain situations reverting to LSEs that did not get the benefit of the load response service \nfor which they paid.” Transmittal at 103. Section X(a) directs the same rate away from load, \nto a party that also pays for capacity, for a service that the load did not purchase. \n127. The operating sequence creates an additional distinction. Mr. Pilong explains, and PJM \nrepeats, that “IRAS load reductions would now be introduced just before the Pre-\nEmergency Load Reduction Actions.” Id.; Pilong Aff. paragraph 46. The Eligible New Large \nLoad is curtailed first; the Pre-Emergency Load Response participant, which received \npayment for a capacity commitment, is curtailed second. The rate applied to the first-\ncurtailed party derives from the charge applicable to the second-curtailed party. \n128. This sequence also creates tension with PJM’s rationale for the 50 percent figure. PJM \ngrounds the discount in the proposition that Pre-Emergency Load Response is called at “an \nearlier stage of emergency conditions,” when “the value of the load reduction, while still \nsubstantial, is also not as high as during a Performance Assessment Interval.” Transmittal \nat 103. Interim Resource Adequacy Service is called earlier still. Under that reasoning, the \nappropriate discount would be larger rather than equal. I do not quantify that discount. \nThe election to zero \n129. Section X(a) permits an Eligible New Large Load to accept less than 50 percent of the \nNon-Performance Charge Rate or to waive compensation entirely, in which case “the rate \nshall be zero dollars.” PJM states that where credits are waived, “the wholesale IRAS rate \nwill be reduced to zero dollars… This is a just and reasonable rate.” PJM further states that \nthe election follows “appropriate engagement with Electric Distributors,” which “would \noccur at the state level.” Transmittal at 105. \n130. Section X(a) therefore allows each seller to set the wholesale rate for the service \nbetween zero and the stated ceiling. Two Eligible New Large Loads providing identical \nservice in the same zone and hour may receive different rates. On PJM’s description, the \ndifference turns on state-level engagement rather than a difference in cost, service, or \nperformance."},{"page":79,"startToken":28194,"endToken":28565,"text":"32 \n \nSettlement \n131. PJM assumes no settlement responsibility for the compensation. The Electric \nDistributor compensates Eligible New Large Loads and charges “customers in its zone/area \nto fund any such compensation.” Attachment DD-4, section X(b)(i). If PJM facilitates billing, \n“such billing shall be considered a bilateral transaction between the Electric Distributor \nand the identified Members and PJMSettlement shall not be a contracting party to the \nsettlement.” PJM, PJMSettlement, and the Members “will not assume financial responsibility \nfor the failure of a party to pay any amounts owed to another party under this section.” Id. \nsection X(b)(iii). \nComparison with section 10B \n132. Attachment DD, section 10B applies the same 50 percent factor to a Non-PAI Event \nand originated in the proceeding PJM cites. Effective with the 2028/2029 Delivery Year, \nsection 10B(a) applies to “Demand Resources and Price Responsive Demand with capacity \ncommitments.” Section 10B(b) defines the Non-Curtailment Charge as “Performance \nShortfall * 50% * Non-Performance Charge rate specified in Tariff, Attachment DD, section \n10A(e).” \nElement \nSection 10B \nSection X(a) \nRate \n50% of the 10A(e) rate \n50% of the 10A(e) \nrate \nApplies to \nDemand Resources and Price Responsive Demand \nwith capacity commitments \nEligible New Large \nLoads, no capacity \ncommitment \nDirection \ncharge \ncredit \nTriggered by failure to curtail \ncurtailment \nMeasured \nagainst \ncommitted capacity or Nominal PRD Value \nregistered peak load \nless an offset \nAnnual limit \nsection 10A(f-1), denominated in committed \nUnforced Capacity \nnone identified \nWhere the \nmoney goes \nfirst to providers with a negative shortfall; any \nremainder “distributed on a pro-rata basis to LSEs \nthat were charged a Locational Reliability Charge \non the Non-PAI Event day” \nto the curtailing load \n133. The two provisions allocate amounts in opposite directions. Under section 10B, \namounts collected from providers that failed to curtail are paid first to providers that over-\ncurtailed; any remainder returns to Load Serving Entities that paid a Locational Reliability \nCharge. Under section X(a), Load Serving Entities and other customers in the zone fund a \npayment to the curtailing load, with no residual return. The quantity measurements also \ndiffer. Section 10B measures Expected Curtailment against committed capacity or Nominal \nPRD Value and limits the charge in committed Unforced Capacity terms. Section X measures"},{"page":80,"startToken":28565,"endToken":28935,"text":"33 \n \nactual curtailment against registered peak load less an offset, without accreditation or \ncapacity testing. \nComparison with capacity Demand Response \n134. Both Demand Response and Interim Resource Adequacy Service may reduce load \nduring emergency conditions, but the proposed design recognizes them differently at each \nstep below. \nElement \nDemand Resource \nInterim Resource Adequacy \nService \nUnderlying load \nremains in the forecast \nremoved from the Curve \nReduces load \nonly when called \nonly when called \nAccreditation \nELCC Class Rating, 90 percent for \n2029/2030 \nnone \nIn the assumed \nresource portfolio \n8,711 MW of installed capacity for \n2029/2030 \nnot modeled \nEnters the market \noffered into RPM as supply \neffected by subtraction from \nthe procurement quantity \nReliability studies \ncontribution solved in the ELCC and \nReserve Requirement Studies \nnothing in the proposal \namends those studies \nCapacity testing \nrequired \nnone \nPayment \ncapacity payment at the clearing \nprice, subject to charges under \nsections 10A and 10B \n50 percent of the Non-\nPerformance Charge Rate for \nhours called \n[Class rating and portfolio quantity from PJM, IRM, FPR and ELCC for the 2029/2030 BRA, at \n4 and 5. The 8,711 MW figure is installed capacity in the assumed portfolio and is not the \nnominated value of committed Demand Resources.] \n135. The principal difference is accreditation. A Demand Resource receives a capacity \nrating based on a probabilistic model of its contribution during hours of resource-adequacy \nrisk, appears in the assumed resource portfolio, and is subject to capacity testing. An \nEligible New Large Load providing the same conditional curtailment receives no \ncorresponding ex ante capacity rating: no rating is assigned to it; it does not appear in the \nstudies as a resource; and it undergoes no test establishing the capacity value it will \nprovide. Actual curtailment is measured after the fact for settlement, but the mechanism \nmakes no prior determination of the service’s capacity value. Whether that difference is \nunduly discriminatory is a question for the Commission; what the mechanics establish is \nthat the two are not treated alike. \n136. Section IV addresses the consequence for the planning parameters. Because the \nproposal implements the service by removing load rather than by adding supply, the \nservice does not enter the Reserve Requirement Study or the ELCC study, and no class"},{"page":81,"startToken":28935,"endToken":29359,"text":"34 \n \nrating is assigned to it. The procurement target is reduced by an amount calculated using a \nconversion factor derived from a model in which the service has no capacity rating. \nLimits of the opinion \n137. This opinion addresses the conditions governing the procurement reduction and the \nsupport for the proposed rate; it does not address whether Interim Resource Adequacy \nService may provide a useful operational tool. The comparison in paragraphs 96 to 107 \nrests on the cited Tariff provisions and Commission precedent and does not attribute an \nintent to PJM. I also do not resolve whether section 10A(e) and section 10B apply to an \nEligible New Large Load. Each cross-referencing provision appears in a clause whose stated \nscope is Capacity Performance Resources and Seasonal Capacity Performance Resources, \nand an Eligible New Large Load is neither. \nRelief \n138. The procurement reduction for New Large Load should require a binding, self-\nexecuting commitment comparable to the PRD Reservation Price construct or, \nalternatively, the durability conditions applicable to the Peak Shaving Adjustment. \n139. Net the Peak Shaving Adjustment. Any Peak Shaving Adjustment applicable to a \nregistered site should be netted against the Excluded Amount, consistent with the \ninteraction rules PJM applies in the Peak Shaving Adjustment definition and in Attachment \nDD-4, section VI(a)(2). \n140. Support the rate or replace it. PJM should either demonstrate that a rate calibrated as \na clawback from a paid, voluntary participant is just and reasonable compensation for an \nobligated participant that holds no capacity commitment and is curtailed ahead of it, or \npropose a rate derived from the cost or value of the service the Eligible New Large Load \nprovides. The election to zero should be removed or explained, and the class limitation in \nsection 10A(e) should be addressed. \nVII. CONCLUSION \n141. Interim Resource Adequacy Service addresses a real operational problem. PJM needs \na means of protecting reliability if forecast New Large Load does not materialize as \nexpected or cannot be served during stressed conditions. That objective does not resolve \nthe market-design question examined in this affidavit: whether PJM may remove that load \nfrom the quantity it procures while continuing to include it in the studies that set the \nplanning parameters and without identifying a corresponding adjustment to the capacity \nobligations allocated to Load Serving Entities. \n142. The price effect follows from the auction mechanics. The Excluded Amount shifts the \nCurve left and steepens its sloped segments; backstop capacity offered at $0/MW-day shifts \nsupply right. Neither moves the price while the intersection stays on the horizontal"},{"page":82,"startToken":29359,"endToken":29893,"text":"35 \n \nsegment. Once it reaches a sloped segment, both do. The 2029/2030 Excluded Amount \nalone brings supply within 290 MW of that point. \n143. Under the full-proxy scenario described in paragraph 42, the exclusion reduces the \ncapacity revenue supporting both new investment and continued operation by \napproximately $127,276 per UCAP MW-year in 2030/2031, and the price falls below the \nmost recently posted Net Cost of New Entry from that Delivery Year forward. Over the \nsame period the procurement quantity ceases to track the load PJM must plan and operate \nthe system to serve: peak load net of load in an FRR Service Area grows 31,026 MW while \nthe Reliability Requirement net of the Excluded Amount moves 584 UCAP MW. \n144. The numerical results are scenarios rather than forecasts. They show the direction \nand range of the price effect under the stated assumptions concerning the New Large Load \nproxy, backstop participation, supply additions, Bring Your Own New Capacity, Allocated \nRBP UCAP MW, and the offer curve. PJM’s filing does not identify the threshold at which the \nexclusion begins to affect price, provide a sensitivity around the Excluded Amount, or \nevaluate the exclusion together with zero-priced backstop supply available in the same \nauctions. \n145. My analysis complements and extends the timing concern Dr. Shanker raises in the \nConstellation limited protest. He explains how backstop supply can enter the auction at \nzero before the associated load materializes. This affidavit addresses the demand side of \nthat interaction. To the extent related RBP capacity is not allocated to the same load under \nAttachment DD-4, section IX, the Excluded Amount removes forecast load from the Curve \nwhile that capacity remains in the supply stack. The two mechanisms then operate on \nopposite sides of the same auction and press the clearing price in the same direction. \n146. Five unresolved features of the proposed design warrant Commission attention. \n147. PJM states in its 2028/2029 auction report that a price cap below the established \nCurve “can reduce the amount of investment, and therefore supply” in the Region. It ties \nmarket effectiveness to durability and identifies “backstop procurement mandates and \nprice cap proposals” among the interventions that lead investors to discount the revenue \nstream. In the backstop proceeding, PJM proposes a maximum willingness to pay of \n$555/MW-day for capacity it will then require to offer into RPM at $0/MW-day. The filing \ndoes not reconcile the resulting reduction in the procurement quantity and potential \nclearing-price effect with the durable price signal PJM identifies as necessary. \n148. The filing does not test the resulting price against Net Cost of New Entry. That figure is \nPJM’s own estimate of the cost of bringing a new reference resource to the system, and the \nprice coordinates of the Variable Resource Requirement Curve are derived from it. PJM \nproposes to modify the Curve without showing whether the prices it would produce \nremain adequate measured against the benchmark on which the Curve itself is built. \n149. PJM uses New Large Load in the load shapes from which it determines the Installed \nReserve Margin, ELCC Class Ratings and Forecast Pool Requirement, but removes the \nExcluded Amount from the procurement quantity. The filing identifies no corresponding"},{"page":83,"startToken":29893,"endToken":30249,"text":"36 \n \nremoval from the Obligation Peak Load used to allocate capacity obligations. See \nparagraphs 69 to 93. It therefore does not explain whether a conversion factor derived \nfrom the full load forecast remains appropriate when applied to a procurement quantity \nnet of that load, or why load that continues to carry a capacity obligation should be \nremoved from the quantity procured against it. \n150. The Fixed Resource Requirement Alternative, Peak Shaving Adjustment and Price \nResponsive Demand condition reductions in the procurement target on defined \ncommitments or performance terms. Price Responsive Demand also conditions the \nreduction on a price stated by the provider in advance. See paragraphs 95 to 106. Interim \nResource Adequacy Service, by contrast, reduces the procurement target when load enters \nthe forecast without requiring a comparable binding commitment. The filing does not \nexplain this difference. \n151. Section X(a) sets the Interim Resource Adequacy Service rate at 50 percent of a charge \nbenchmarked to one year of Net Cost of New Entry and applied to capacity resources with \ncapacity commitments. An Interim Resource Adequacy Service provider has no capacity \ncommitment, receives no capacity-market payment for the service obligation, pays a \nLocational Reliability Charge through its Load Serving Entity, and is curtailed before the \ncapacity-market participants whose performance charge supplies the benchmark. See \nparagraphs 113 to 136. An Eligible New Large Load may also elect a rate of zero. PJM relies \nprincipally on the Commission’s acceptance of related penalty and compensation \nconstructs but does not explain why those constructs support compensation for an Interim \nResource Adequacy Service provider with materially different obligations and economics. \n152. Interim Resource Adequacy Service may prove a useful operational backstop. The \npresent record, however, does not establish an equivalence between the reduction in the \nquantity PJM procures and any accredited or binding commitment substituting for the \ncapacity no longer bought. Until that equivalence is shown, the procurement reduction \nrests on the appearance of load in a forecast rather than on a resource-adequacy \ncommitment the Tariff can enforce. I recommend that the Commission require PJM to \nresolve these matters before the exclusion first operates in the 2029/2030 Base Residual \nAuction."},{"page":84,"startToken":30249,"endToken":30737,"text":"37 \n \nAPPENDIX A — AUCTION MODEL, DATA AND SENSITIVITIES \nA.1 Tariff and Curve mechanics \nA1. Attachment DD, section 5.10(a) of the proposed Tariff sheets establishes the Variable \nResource Requirement Curve for the 2029/2030 Delivery Year by reference to three \npoints. The quantity at each point is a percentage of a bracketed quantity, and the price at \neach point is established by a separate formula. The provision states: \nFor point (1), price equals: {the greater of [1.15 times Cost of New Entry minus \n0.75 times the Net Energy and Ancillary Service Revenue Offset] or [0.2 times Cost \nof New Entry)]} divided by (the applicable ELCC Class Rating of the Reference \nResource) and Unforced Capacity equals: [the PJM Region Reliability Requirement \nminus Excluded RTO New Large Load Amounts] multiplied by 99%; For point (2), \nprice equals: [0.5 times the price calculated for point 1] divided by (the applicable \nELCC Class Rating of the Reference Resource) and Unforced Capacity equals: [the \nPJM Region Reliability Requirement minus Excluded RTO New Large Load \nAmounts] multiplied by 101.5%; and For point (3), price equals zero and \nUnforced Capacity equals: [the PJM Region Reliability Requirement minus \nExcluded RTO New Large Load Amounts] multiplied by 106.0%. \nProposed Tariff, Attachment DD § 5.10(a), Attachment A to PJM transmittal, \nDocket No. ER26-3515-000 (Aug. 13, 2026). \nA2. The subtraction moves the Curve to the left by the Excluded Amount. Because the \nsubtraction occurs inside the bracket and the percentages are applied afterward, it also \ncontracts the horizontal distance between the points in the same proportion without \nchanging the price at any point. The Curve therefore becomes steeper by a factor of 1 / (1 − \nE / RR). \nA3. Point 1 of the Curve stands at 99 percent of the Reliability Requirement, and the Curve \nis horizontal from the y-axis to that point. The auction therefore clears at the Point 1 price \nwhenever committed capacity is more than one percent below the requirement, and begins \nto clear on a sloped segment as soon as it comes within one percent of it. [Derived from the \nquoted provision.] \nA4. The 2028/2029 auction cleared at the cap because committed capacity of 138,317.8 \nUCAP MW fell 6,831.3 MW below the FRR-adjusted Reliability Requirement of 145,149.1 \nMW - a shortfall of 4.71 percent and 5,380 MW to the left of Point 1. [Derived.] Supply met \nthe Curve well inside its horizontal segment, where the temporary cap set the price. \nA5. If the reliability shortfall persists, the Excluded Amount does not affect price until the \nreduction moves Point 1 back to the supply quantity. That exclusion level is the threshold. \nThe threshold depends on the size of the shortfall: a market four percent short has a large \nthreshold, while a market within one percent of its requirement has none because supply \nalready meets a sloped segment before the exclusion applies."},{"page":85,"startToken":30737,"endToken":31187,"text":"38 \n \nA6. The 2028/2029 shortfall will not necessarily persist. Before the exclusion first \noperates, the Reliability Backstop Procurement and the Incremental Auction restatement \nboth change the relationship between supply and the requirement. \nA7. PJM sets the Initial Reliability Backstop Procurement Target at the observed UCAP \nshortfall in the 2028/2029 Base Residual Auction — 6,831.3 MW, the same quantity — and \nreduces it by Qualifying RBP Offset UCAP MW and Opt-Out UCAP MW to give the Final RBP \nTarget. Proposed Tariff, Attachment DD § 18.1. Ms. Croop illustrates the calculation at a \nFinal Target of 6,075.7 UCAP MW. Affidavit of Danielle Croop ¶ 48, Docket No. ER26-3380-\n000 (July 31, 2026). The figure is illustrative and the Final Target has not been set; the \nprocurement window opens September 30, 2026. Id. ¶ 4. \nA8. Committed backstop capacity must offer its available capacity, up to its committed RBP \nUCAP MW, as a price taker at $0/MW-day. Proposed Tariff, Attachment DD § 18.6(a). The \nobligation attaches to the commitment and not to the arrival of any load. The commitment \nperiod runs for up to fifteen years; Ms. Croop states that the term varies with each \nresource’s commercial operation date, so that resources entering service after 2028/2029 \ncarry shorter commitments. Croop Aff. ¶ 5. \nA9. The 2028/2029 Reliability Requirement is not final. PJM restates it at each Incremental \nAuction. For the 2026/2027 Delivery Year, between the Base Residual Auction and the \nThird Incremental Auction: \n2026/2027 parameter \nBase Residual \nAuction \nThird Incremental \nAuction \nChange \nPreliminary Forecast Peak Load \n159,329.1 \n156,760.6 \n−2,568.5 \nTotal Peak Load of FRR Entities \n12,633.9 \n11,668.7 \n−965.2 \nInstalled Reserve Margin \n19.1% \n18.6% \n−0.5 pt \nPool-Wide Accredited UCAP \nFactor \n77.0% \n78.3% \n+1.3 pt \nForecast Pool Requirement \n0.9170 \n0.9291 \n+1.32% \nReliability Requirement \n146,104.8 \n145,646.3 \n−458.5 \nPreliminary FRR Obligation \n11,585.3 \n10,841.4 \n−743.9 \nReliability Requirement adjusted \nfor FRR \n134,519.5 \n134,804.9 \n+285.4 \nPJM, 2026/2027 RPM Base Residual Auction Planning Parameters (Apr. 28, 2025) \nand 2026/2027 RPM Third Incremental Auction Planning Parameters (Mar. 11, \n2026). The latter states the change in Reliability Requirement for the RTO as \n285.4 MW. \nA10. The FRR-adjusted Reliability Requirement is the product of two quantities: peak load \nnet of the peak load of FRR entities, and the Forecast Pool Requirement. For 2026/2027 the \nfirst fell 1.09 percent between the two auctions — less than the 1.61 percent reduction in \ntotal peak load, because the peak load of FRR entities fell 7.64 percent and left the"},{"page":86,"startToken":31187,"endToken":31571,"text":"39 \n \nnumerator as well. The second rose 1.32 percent, the pool-wide Accredited UCAP Factor \nhaving risen 1.69 percent against a reserve margin 0.42 percent lower. Their product rose \n0.21 percent. [Derived.] \nThe Reliability Requirement fell 458.5 MW while the quantity procured through \nRPM rose 285.4 MW because the FRR obligation fell by more than the \nrequirement. Peak-load changes alone therefore do not determine the direction of \nthe restatement. \nA11. The analysis therefore does not forecast the restatement. The PJM Region holds \ncapacity in excess of its requirement only if the restatement reduces that requirement by \nmore than the shortfall remaining after the backstop delivers. \nBackstop delivered at \nCommitted capacity \nShort of the requirement \nNone \n138,317.8 \n6,831.3 \nHalf the illustrative Final Target \n141,355.7 \n3,793.4 \nThe illustrative Final Target in full \n144,393.5 \n755.6 \n \nDerived. UCAP MW, measured against the 2028/2029 FRR-adjusted Reliability \nRequirement of 145,149.1. \nA12. The price effect depends on how much of the shortfall the procurement closes. \n(a) The procurement closes most of the shortfall, leaving a small residual short. This \ncase most nearly isolates the effect of the Excluded Amount, because supply sits \nclose to the requirement and further movement of the clearing point is attributable \nto the reduction in the Curve. \n(b) The procurement leaves the Region long. The excess is zero-priced capacity in the \nstack with no corresponding demand. New Large Load must then absorb that length \nbefore the Curve can return to a sloped segment at a positive price, and the \nExcluded Amount removes that load from the Curve as it arrives. \n(c) The procurement leaves the Region materially short. The horizontal segment \ncontinues to govern and the exclusion is inert until the threshold at paragraph A5 is \nreached. \nA13. Dr. Shanker addresses this configuration in the backstop proceeding. He describes a \nrequirement that available backstop capacity offer at $0/MW-day in the applicable RPM \nauctions, and observes that capacity arriving before, or in excess of, the associated load \ncreates an unmatched zero-offer block that shifts the supply curve rightward and \nsuppresses price. Limited Protest of Constellation Energy Generation, LLC, Docket \nNo. ER26-3380-000, Affidavit of Roy J. Shanker ¶¶ 18–23 (Aug. 21, 2026). He presents it as \na potential outcome."},{"page":87,"startToken":31571,"endToken":31976,"text":"40 \n \nLoad forecasts are routinely revised between the Base Residual Auction and the \nThird Incremental Auction. A procurement sized to an earlier shortfall is \nultimately measured against the Third Incremental Auction requirement. \nWhether a load revision changes the RPM procurement quantity also depends on \nthe Forecast Pool Requirement and the FRR obligation; in 2026/2027, it did not. \nParagraph A12 identifies the three configurations that may arise as Interim \nResource Adequacy Service is implemented; each is examined below. \nA14. The sequence does not permit that question to be resolved before the auction in \nwhich the exclusion first operates. The 2029/2030 Base Residual Auction is conducted in \nDecember 2026. The Second and Third Incremental Auctions for the 2028/2029 Delivery \nYear follow in July 2027 and February 2028. Proposed Tariff, Attachment DD sections \n5.14(a)-(b). The Curve for 2029/2030 is therefore constructed, and the Excluded Amount \napplied to it, before the 2028/2029 position is settled. The scenarios below accordingly \ntreat the backstop quantity and the residual shortfall as ranges rather than as known \nquantities. Appendix B addresses the operation of Attachment DD-4, section IV(b), and \nparagraph A46 addresses the separate question of when the exclusion lapses. \nA.2 Starting conditions and the backstop threshold \nA15. The 2028/2029 auction establishes the conditions against which the reduction will \noperate: \nParameter \nValue \nPJM Region Reliability Requirement \n156,012.9 \nTotal Peak Load of FRR Entities \n11,556.0 \nPreliminary FRR Obligation \n10,863.8 \nReliability Requirement adjusted for FRR \n145,149.1 \nCleared, RPM \n138,317.8 UCAP at $325.00 \nShortfall, RPM and FRR combined \n6,831.3 \nPJM, 2028/2029 RPM Base Residual Auction Planning Period Parameters (posted \nJuly 27, 2026); PJM, 2028/2029 Base Residual Auction Report 3–5 (July 14, 2026), \navailable at https://perma.cc/X6UH-4ER4. \nA16. The Curve is constructed on the FRR-adjusted figure. The posted Curve points confirm \nthis: Point (b) at 147,326.3 MW is 1.01500 times 145,149.1, and Point (d) at 153,858.0 MW \nis 1.06000 times 145,149.1. [Derived: the ratios.] \nA17. Supply is inelastic in the region where the auction clears. PJM ran the same auction \ntwice, once with the price collar in effect and once as a simulation without it: \nCase \nClearing price \nCleared UCAP \nActual, collar applied \n$325.00 \n138,317.8 \nSimulation, no cap or floor \n$554.72 \n138,394.6"},{"page":88,"startToken":31976,"endToken":32409,"text":"41 \n \nCase \nClearing price \nCleared UCAP \nDifference \n$229.72 \n76.8 MW \n2028/2029 Base Residual Auction Report, Table 2 and Appendix Table 1. \nA18. Removing the collar raised the clearing price by $229.72, an increase of seventy-one \npercent, and would have cleared 76.8 MW more from the same submitted offer curve. \nThe uncapped simulation holds submitted offers fixed. PJM states that it “does not \nknow how offers may have changed” without the temporary cap and floor. Id. at \n17 n.4. The simulation also does not establish that every capable resource \nparticipated: 6,202.9 MW of installed capacity was excused or unoffered, and \n278.7 MW subject to a must-offer requirement did not offer. Id. at 8, 10 (Table 4). \nOf 139,594.6 MW offered, 1,276.8 MW did not clear at the $325.00 cap. Id. at 11 \n(Table 5). The uncapped simulation cleared 138,394.6 MW, so 1,200.0 MW \nremained uncleared at $554.72. [Derived by subtraction from the two posted \nquantities; id. at 17.] \nA19. The RTO failed the Three Pivotal Supplier test, and market power mitigation was \napplied to all Existing Generation Capacity Resources, substituting the lesser of the seller’s \napproved Market Seller Offer Cap or its submitted offer price. Id. at 3. Mitigation therefore \nestablishes a cost-based ceiling on offers. \nA20. The 2029/2030 Delivery Year requires separate treatment. The price collar applies \nonly in that year, and backstop resources are least likely to be in service because the \nprocurement window does not open until September 30, 2026. Croop Aff. paragraphs 4-5. \nBackstop generation not subject to a Notice of Intent to Offer in the Base Residual Auction \nmust instead offer into the Incremental Auctions. Proposed Tariff, Attachment DD section \n18.6(a). Incremental Auction entry does not set the earlier Base Residual Auction clearing \nprice. \nThe procurement opens September 30, 2026, and the Base Residual Auction \noccurs in December 2026. Awards will therefore follow the deadline for a Notice \nof Intent to Offer into that auction. The base case includes no backstop capacity in \nthe 2029/2030 Base Residual Auction and reports participation as a sensitivity: \nBackstop capacity in the 2029/2030 Base Residual \nAuction \nZero-price \nblock \nClearing \nprice \nNone — base case \n95,000 \n$337.83 \nHalf the illustrative Final Target \n98,038 \n$337.83 \nThe illustrative Final Target in full \n101,076 \n$244.64 \n \nDerived, scenario. UCAP MW. The collar holds the price in the first two cases. Absent the \ncollar the same three cases give $554.72, $554.72 and $244.64. From 2030/2031, the"},{"page":89,"startToken":32409,"endToken":32835,"text":"42 \n \nscenario assumes that the resources are in service, subject to a Notice of Intent to Offer, \nand fully participating. \nA21. The 2028/2029 auction fell 6,831.3 MW short of its Reliability Requirement. The \ncollar nevertheless ceases to bind at 3,124 MW of backstop capacity. The two quantities are \nmeasured against different things. \nStep \nUCAP MW \n2029/2030 Reliability Requirement, gross of the Excluded Amount \n147,329.8 \nSupply — 2028/2029 cleared plus one year of additions \n140,395.8 \nShort of the Reliability Requirement \n6,934.0 — 4.71% \nPoint 1 stands at 99 percent of the requirement \n−1,473.3 \nSupply short of Point 1, before the Excluded Amount \n5,460.7 \nThe Excluded Amount moves Point 1 left by 0.99 × 5,223.1 \n−5,170.9 \nSupply short of Point 1, after the Excluded Amount \n289.8 \n \nDerived. Zero Bring Your Own New Capacity assumed throughout, per paragraph A25. \nA22. The Excluded Amount closes 5,171 MW of the 5,461 MW between supply and Point 1. \n[Derived.] A market 4.71 percent below its Reliability Requirement moves within 290 MW \nof Point 1 without any backstop capacity because Point 1 is 99 percent of a requirement \nfrom which the Excluded Amount has already been subtracted. \nA.3 The Excluded Amount proxy \nA23. 2029/2030. The endorsed parameters are a peak load forecast of 171,530 MW and a \nForecast Pool Requirement of 0.9232, giving a Reliability Requirement, before adjustment \nfor FRR, of 158,356 MW. The scenarios below are built on the FRR-adjusted quantity of \n147,329.8 MW. PJM, IRM, FPR and ELCC for the 2029/2030 BRA, Markets and Reliability \nCommittee (Aug. 19, 2026), slides 8–10, available at https://perma.cc/2GK5-GHQC. \nA24. No published figure states the Excluded RTO New Large Load Amount for 2029/2030. \nThe analysis uses the increment in Table B-9b of the 2026 PJM Load Forecast as a proxy. \nTable B-9b reports RTO summer-peak adjustments of 21,280 MW in 2028 and 27,361 MW \nin 2029, an increment of 6,081 MW. \nThe proxy is an upper bound, not the tariff quantity. Table B-9b combines large \nand unanticipated load changes, market adjustments, and peak-shaving \nadjustments. The filed definition is narrower: tariff-defined New Large Load \nabove the 2028/2029 baseline, outside FRR Service Areas, and net of load \nsupported by BYONC or assigned Allocated RBP UCAP MW. Table B-9b is also \nsubject to revision; the 2028 figure moved 2,128 MW between the 2025 and 2026 \nLoad Forecast Reports."},{"page":90,"startToken":32835,"endToken":33351,"text":"43 \n \nPJM Manual 19, Attachment B at 28 states that a submission included in the \nforecast period for an RPM Auction “must be considered Firm.” PJM Manual 19, \nLoad Forecasting and Analysis, Rev. 39, available at https://perma.cc/NEB7-L5ET. \nThe definition includes a long-term supply commitment coupled with a financial \ncommitment, an Electric Service Obligation, or a Construction Commitment. It is \nbroader than the definition used in the Load Analysis Subcommittee materials. \nPJM 2026 Long-Term Load Forecast, LAS (Jan. 23, 2026), available at \nhttps://perma.cc/DR7H-W8E6. The analysis treats the 2029 increment as firm on \nthat basis. \nA25. I assume three inputs. \nFirst, that no New Large Load in the 2029/2030 Delivery Year has Bring Your \nOwn New Capacity. The facts supporting that assumption are these. This filing \nwas submitted on August 13, 2026 and has not been accepted. The Large Load \nRegistry it would establish does not exist. The Base Residual Auction for the \n2029/2030 Delivery Year is scheduled for December 2026, and PJM targets \nopening the Reliability Backstop Procurement window on September 30, 2026. \nThe second subtraction in the Excluded Amounts definition reaches only New \nLarge Load added on or after the 2029/2030 Delivery Year that is in an \narrangement with Bring Your Own New Capacity or has been assigned Allocated \nRBP UCAP MW. Attachment DD-4 section VII(c) sets the deadline. For the \n2029/2030 Delivery Year the requirements of section VII(a) must be reported to \nPJM no later than fifty days before the Base Residual Auction commences — late \nOctober 2026 for a December 2026 auction. The capacity then offers into that \nauction, and PJM updates the Large Load Registry to reflect verified arrangements \n“after the relevant RPM Auction.” Section VII(i) fixes the Accredited UCAP of the \ncapacity at its value for the auction in which it cleared for the initial Delivery Year \nof the arrangement. The reporting deadline therefore falls before the rule \nestablishing it can be accepted. Paragraphs A59 to A62 address later Delivery \nYears. \nSecond, that no New Large Load has Allocated RBP UCAP MW reducing its \nExcluded Amount. Attachment DD-4 section IX(a) allocates the Final RBP Target \nacross Electric Distributor zones on each zone’s share of Reliability Backstop \nProcurement Charges, which are assessed on load growth from the 2026/2027 to \nthe 2028/2029 Delivery Year. Section IX(b) then allocates within the zone as the \nElectric Distributor directs, or, absent direction by April 1, pro rata among all New \nLarge Loads in the zone. Because New Large Load includes loads entering service \nafter June 1, 2027 — both those within the 2028/2029 baseline and those after it \n— the default rule does not confine the allocation to the loads whose growth \ngenerated the charge. The quantity reaching post-baseline load is not \ndeterminable on this record, and paragraph A63 states the sensitivity. \nThird, that the Forecast Pool Requirement is 0.9232 in every Delivery Year. That \nvalue was endorsed on August 19, 2026 for 2029/2030. No later Delivery Year \nhas an endorsed value. The Forecast Pool Requirement is re-struck for each"},{"page":91,"startToken":33351,"endToken":33803,"text":"44 \n \nDelivery Year and again at each Incremental Auction, and for 2026/2027 it moved \nfrom 0.9170 at the Base Residual Auction to 0.9291 at the Third Incremental \nAuction. Holding it fixed isolates the effect of the Excluded Amount from \nmovements in the conversion between load and capacity. \nA26. The proposal removes load from the Curve without recalculating the Forecast Pool \nRequirement, although that requirement depends on the load being removed. The Forecast \nPool Requirement equals one plus the Installed Reserve Margin, multiplied by the pool-\nwide Accredited UCAP Factor; both inputs come from a reliability model driven by the \npeak-load forecast. The 2026/2027 restatement illustrates the sensitivity: a 1.61 percent \nreduction in peak load accompanied a decline in the Installed Reserve Margin from 19.1 to \n18.6 percent and an increase in the pool-wide Accredited UCAP Factor from 77.0 to 78.3 \npercent, raising the Forecast Pool Requirement by 1.32 percent. The Excluded Amount \nnevertheless uses a Forecast Pool Requirement computed on all load, including the load the \nsame provision removes. The filing does not demonstrate whether the reliability model \nwould produce the same conversion factor on a load basis net of the Excluded Amounts, \nand it does not address that question. \nA27. 2029/2030 remains collared. The price cap and floor apply for that Delivery Year and \nbear on the effect of any Interim Resource Adequacy Service exclusion, as paragraph A20 \naddresses. The collar expires thereafter; from 2030/2031 the Curve runs from Point 1 to \nzero price at Point 3, with no cap and no floor. \nA28. Substantially all forecast load growth in the PJM Region is large load growth. Under \nthe zero-offset proxy scenario stated at paragraph A25, substantially all of it is therefore \nremoved from the Curve as it arrives. \nYear \nB-1 peak \nPeak growth \nB-9b large load \nLarge load growth \nShare \n2029 \n171,530 \n+5,963 \n27,361 \n+6,081 \n102% \n2030 \n183,008 \n+11,478 \n38,805 \n+11,444 \n100% \n2031 \n191,017 \n+8,009 \n46,638 \n+7,833 \n98% \nPJM, 2026 Load Report Tables Workbook, Tables B-1 and B-9b (Jan. 14, 2026), \navailable at https://perma.cc/U65B-Y5NX. Table B-9b RTO summer-peak \nadjustments are 21,280 MW for 2028, 27,361 for 2029, 38,805 for 2030, 46,638 \nfor 2031 and 53,949 for 2032. \nA29. The Curve exclusion leaves the quantity against which PJM procures substantially \nunchanged. \nDelivery \nYear \nPeak \nload \nLess FRR \nload \nLess Excluded Amount, \nzero offsets \n× FPR = RR net of the \nexclusion \n2028/29 \n165,567 \n154,038 \n154,038 \n142,208 \n2029/30 \n171,530 \n159,586 \n153,928 \n142,107 \n2030/31 \n183,008 \n170,264 \n153,960 \n142,135"},{"page":92,"startToken":33803,"endToken":34211,"text":"45 \n \nDelivery \nYear \nPeak \nload \nLess FRR \nload \nLess Excluded Amount, \nzero offsets \n× FPR = RR net of the \nexclusion \n2031/32 \n191,017 \n177,716 \n154,124 \n142,287 \n2032/33 \n198,915 \n185,064 \n154,671 \n142,792 \n \nDerived. Assumptions: Forecast Pool Requirement held at the endorsed 0.9232 in every \nDelivery Year, per paragraph A25; that value is endorsed for 2029/2030 only. FRR \nshare of peak held at its 2028/2029 value of 6.9634 percent. Excluded Amount taken as \nlarge load above the 2028/2029 baseline of 21,280 MW, net of the FRR share, with no \nreduction for Bring Your Own New Capacity or Allocated RBP UCAP MW. Paragraphs \nA59 to A64 address the cases in which such reductions apply. \nA30. Across 2028/2029 through 2032/2033 the Reliability Requirement net of the \nExcluded Amount moves 584 UCAP MW while peak load net of load in an FRR Service Area \nrises 31,026 MW. Gross of the FRR adjustment the load figure is 33,348 MW; the net figure \nis the comparable basis, because the Reliability Requirement is itself FRR-adjusted. \n[Derived.] Under the stated scenario, load has substantially stopped driving the \nprocurement quantity while supply continues to arrive. \nA.4 Supply and offer-curve construction \nA31. PJM’s assumed resource portfolio has grown as follows. PJM describes that portfolio \nas a modeling input incorporating Notices of Intent to Offer, assumed deactivations and \ntransitional capability, and cautions that modeled Accredited UCAP is not necessarily \ncapacity available in the actual RPM market. \nDelivery Year \nICAP \nChange \nClearing price \n2025/26 \n191,693 \n— \n$269.92 \n2026/27 \n193,738 \n+2,045 \n$329.17 \n2027/28 \n198,379 \n+4,641 \n$333.44 \n2028/29 \n196,871 \n−1,508 \n$325.00 \n2029/30 \n203,004 \n+6,133 \n— \nPJM IRM and FPR presentations to the Markets and Reliability Committee: \n2026/2027 (Mar. 19, 2025), available at https://perma.cc/VA7T-ZLKL; \n2027/2028 (Jul. 23, 2025), available at https://perma.cc/F667-PR66; 2028/2029 \n(Feb. 19, 2026), available at https://perma.cc/8SK6-45FW; 2029/2030 (Aug. 19, \n2026), available at https://perma.cc/2GK5-GHQC. Clearing prices from: PJM, \n2025/2026 BRA Report (Jul. 30, 2024), available at https://perma.cc/KF9C-L8ES, \n2026/2027 BRA Report (Jul. 22, 2025, available at https://perma.cc/UE43-ML7P, \n2027/2028 BRA Report (Dec. 17, 2025), available at https://perma.cc/N2UZ-\nXSVD, and 2028/2029 BRA Report (July 14, 2026), available at \nhttps://perma.cc/X6UH-4ER4."},{"page":93,"startToken":34211,"endToken":34621,"text":"46 \n \nA32. Announced deactivations, excluding units operating under a Reliability Must Run \narrangement, are 835 / 1,270 / 3,238 / 0 / 217 MW across the 2026/2027 through \n2030/2031 Delivery Years. PJM, Generator Deactivations (downloaded Aug. 23, 2026). The \nfour intervals over which the portfolio is measured carry 835, 1,270, 3,238 and 0 MW; the \n217 MW figure is 2030/2031 and falls outside that period. Adding the four quantities back \nto the net change of 11,311 MW gives gross additions of 16,654 MW over four years, or \napproximately 4,164 MW per year. [Derived.] Retirements absorbed roughly one-third of \ngross additions over four years. No announced deactivation quantity falls within the final \nmeasured interval. \nA33. Between the 2027/2028 and 2029/2030 studies, the assumed portfolio rose 4,625 \nMW in installed-capacity terms and 2,568 MW in Accredited Unforced Capacity, an implied \nmarginal factor of 0.5552. Applying the class-specific ELCC ratings to the additions \nproduces a weighted average ELCC of roughly 50 percent. The scenarios use that \nconservative estimate for future installed-capacity additions. \nA34. A clearing price is the intersection of supply and demand, not a function of available \ncapacity alone. A vertical supply line at the quantity assumed available would treat every \nmegawatt as offered at every price down to zero. The 2028/2029 auction shows otherwise: \n1,276.8 MW of 139,594.6 MW offered did not clear at $325.00, and offers span the prices \nbelow that level. 2028/2029 Base Residual Auction Report 11 (Table 5). When the Curve \nmoves left, the clearing point moves down the offer curve; offers above the new price do \nnot clear, so quantity and price fall together. A vertical-supply assumption misses that \nrelationship and overstates both the quantity cleared and the price decline. The model \ntherefore constructs an offer curve and solves the intersection. \nA35. The offer curve is calibrated to PJM’s published 2028/2029 RTO supply curve. PJM \nposts a smoothed curve of sell offers submitted into the RTO and constrained LDAs. PJM, \n2028/2029 BRA Supply Curves (July 17, 2026). Intermediate quantities are read from that \ngraph and anchored to the two quantities PJM reports exactly. \nPrice, $/MW-day UCAP \nQuantity offered, UCAP MW \n$0 \n95,000 \n$8 \n110,000 \n$30 \n120,000 \n$55 \n125,000 \n$100 \n130,000 \n$150 \n133,000 \n$200 \n135,500 \n$250 \n137,000 \n$300 \n138,000 \n$325.00 \n138,317.8 \n$554.72 \n138,394.6"},{"page":94,"startToken":34621,"endToken":35043,"text":"47 \n \nPrice, $/MW-day UCAP \nQuantity offered, UCAP MW \nAbove $554.72 \n139,594.6 \n \nRead and Derived. The shaded rows are posted quantities — the cleared quantity at the \ncap and the uncapped simulation — and fix the top of the curve. The intermediate \nquantities are my readings from the published graph and are approximations. Roughly \n95,000 MW, some sixty-nine percent of the quantity cleared, was offered at or near zero. \nThe curve is flat to that point, rises gently through the 120,000 MW range, and is near \nvertical above 137,000 MW: 76.8 MW separates $325.00 from $554.72, and a further \n1,200 MW lies above $554.72. Paragraph A44 tests the sensitivity of the results to the \nreadings. \nA36. For each later Delivery Year, the model shifts the offer curve right by the installed-\ncapacity additions at paragraph A32, converted at the weighted ELCC rating from \nparagraph A33. It also extends the zero-price segment by the Reliability Backstop \nProcurement quantity, which must offer at $0/MW-day. Adding 6,075.7 UCAP MW of \nbackstop capacity moves the zero-price block from approximately 95,000 MW to \napproximately 101,000 MW. The clearing price is the intersection of the shifted offer curve \nand the Curve reduced by the Excluded Amount. The scenario uses the full Excluded \nAmount and assumes that no New Large Load holds Bring Your Own New Capacity, as \nparagraph A25 states. \nA.5 Scenario results and sensitivities \nThe assumptions held constant across the two cases are stated at paragraph 37. Their \nderivation appears at A.3 for the Excluded Amount proxy, A.4 for supply and the offer \ncurve, and A.2 for the backstop quantity and the collar. \nA37. For 2029/2030 the following table applies the full-participation sensitivity described \nat A20. For later Delivery Years it applies the assumed full participation of the illustrative \nFinal Target of 6,075.7 UCAP MW. \nDelivery Year \nCleared quantity \nClearing price \n2029/30 \n144,993 \n$244.64 \n2030/31 \n145,912 \n$206.02 \n2031/32 \n146,713 \n$178.07 \n2032/33 \n147,727 \n$156.79 \n \nDerived, scenario. This is a bounding case and its four assumptions run in the same \ndirection: the Excluded Amount is at the full Table B-9b proxy; no New Large Load \nholds Bring Your Own New Capacity or Allocated RBP UCAP MW; the backstop delivers \nthe illustrative Final Target in full and, from 2030/2031, offers wholly into the Base \nResidual Auction; and none of that capacity is already among the projected additions."},{"page":95,"startToken":35043,"endToken":35451,"text":"48 \n \nParagraphs A20, A42, A44 through A45, A58 through A62 and A63 test these \nassumptions. Offer curve at paragraph A35 shifted by 2,078 UCAP MW per year of \nadditions and by the backstop quantity at $0/MW-day. Curve as reduced by the \nExcluded Amounts at paragraph A29. Point 1 price held at $554.72 and Point 2 at half \nthat figure per the posted 2028/2029 convention; the 2029/2030 collar applied. \nForecast Pool Requirement held at 0.9232 and zero Bring Your Own New Capacity \nassumed, per paragraph A25. \nA38. Under the full-participation sensitivity for 2029/2030 and the stated later-year \nassumptions, the effect of the Excluded Amount is the difference between two clearings of \nthe same supply against Curves that differ only in the Excluded Amounts. Both clearings \nassume that no New Large Load holds Bring Your Own New Capacity or Allocated RBP \nUCAP MW, per paragraph A25. \nDelivery Year \nWithout the Excluded Amount \nWith it \nEffect \n2029/30 \n$337.83 — at the collar \n$244.64 \n−$93.19 \n2030/31 \n$554.72 — at Point 1 \n$206.02 \n−$348.70 \n2031/32 \n$554.72 — at Point 1 \n$178.07 \n−$376.65 \n2032/33 \n$554.72 — at Point 1 \n$156.79 \n−$397.93 \n \nDerived, scenario. \nA39. In 2030/2031, the same physical supply clears at the Point 1 price without the \nexclusion and at $206.02 with it. The two Curves have identical price coordinates and differ \nonly by the Excluded Amount, and neither case assumes Bring Your Own New Capacity or \nAllocated RBP UCAP MW. Measured against the Reliability Requirement before the \nexclusion, the modeled market is 5.4 percent short without it and 7.2 percent short with it. \n[Derived.] The physical supply available is the same in both cases; what differs is the \nquantity procured and the price at which it clears. \nA40. Under the modeled offer curve and the other assumptions stated above, maintaining a \nclearing price near $325 would require net supply growth near the following quantities: \nDelivery \nYear \nGrowth over the prior \nyear \nInstalled capacity at \n0.4991 \nObserved \nadditions \n2030/31 \n29 UCAP MW \n58 MW \n4,164 MW \n2031/32 \n154 UCAP MW \n308 MW \n4,164 MW \n2032/33 \n510 UCAP MW \n1,023 MW \n4,164 MW \n \nDerived. The 2029/2030 figure is omitted: the 2028/2029 price of $325.00 was set by \nthe collar rather than by the Curve, and the two are not comparable."},{"page":96,"startToken":35451,"endToken":35928,"text":"49 \n \nA41. Paragraph A30’s quantity result, in price terms. The Reliability Requirement net of the \nExcluded Amount moves 584 MW across four Delivery Years. Supply can move by that \nquantity without moving down the Curve; additions beyond it erode the price. Solving for \nthe addition rate that holds the clearing price at the most recently posted Net Cost of New \nEntry of $325.69/MW-day gives no solution once the illustrative backstop quantity offers \nat $0/MW-day: with the Excluded Amount applied and no organic additions, the modeled \n2030/2031 price is $297.00. Excluding the backstop from the auction, the maxima are \napproximately 2,665 UCAP MW per year in 2030/2031, 1,828 in 2031/2032 and 1,509 in \n2032/2033, equivalent at the 50 percent marginal accreditation rate to 5,330, 3,656 and \n3,018 MW of installed capacity. [Derived, scenario.] The observed rate of 4,164 MW \ninstalled per year therefore exceeds the maximum from 2031/2032 forward. \nA42. Excluded Amount. The Table B-9b increment is a proxy and an upper bound, reaching \nquantities the filed definition does not. Varying the Excluded Amount as a share of that \nproxy: \nDelivery Year \n0% \n25% \n50% \n75% \n100% \n2029/30 \n$337.83 \n$337.83 \n$317.08 \n$274.19 \n$244.64 \n2030/31 \n$554.72 \n$554.72 \n$521.34 \n$286.65 \n$206.02 \n2031/32 \n$554.72 \n$554.72 \n$554.72 \n$280.10 \n$178.07 \n2032/33 \n$554.72 \n$554.72 \n$554.72 \n$280.92 \n$156.79 \n \nDerived, scenario. The lower columns sit at the Point 1 price because the exclusion is \nbelow the threshold at paragraph A22 and supply does not reach the sloped portion of \nthe Curve. This sensitivity addresses the composition of the proxy and not its vintage. \nThe operative quantity will be computed from the load forecast governing the \n2029/2030 auction rather than the 2026 vintage used here, and successive vintages \nhave risen: the 2028 figure alone moved 2,128 MW between the 2025 and 2026 Load \nForecast Reports. \nA43. The response is strongly nonlinear across the threshold. At half the proxy, the \n2030/2031 price is $521.34; at three-quarters, it is $286.65. One-quarter of the proxy \nseparates a clearing near the Point 1 price from one near half that price. This threshold \nbehavior makes the Excluded Amount more consequential than the other modeled inputs. \nA44. Offer curve. The intermediate readings at paragraph A35 are approximations from a \nsmoothed graph. Scaling the curve between the zero-price anchor and the posted quantity \nat $325, with the backstop quantity added to the zero-price block in every case: \nDelivery \nYear \n85,000 MW at \n$0 \n95,000 MW at \n$0 \n105,000 MW at \n$0 \n115,000 MW at \n$0 \n2029/30 \n$250.41 \n$244.64 \n$237.24 \n$227.22 \n2030/31 \n$216.17 \n$206.02 \n$194.62 \n$180.36"},{"page":97,"startToken":35928,"endToken":36363,"text":"50 \n \nDelivery \nYear \n85,000 MW at \n$0 \n95,000 MW at \n$0 \n105,000 MW at \n$0 \n115,000 MW at \n$0 \n2031/32 \n$188.75 \n$178.07 \n$163.39 \n$142.72 \n2032/33 \n$170.36 \n$156.79 \n$139.46 \n$114.69 \n \nDerived, scenario. A 30,000 MW range in the zero-price block moves the result by $23 \nto $56. The conclusion is not sensitive to reading error in the published curve, and a \nlarger zero-price block produces a lower price, so the reading used is the conservative \none within the range tested. \nA45. Rate of supply additions. \nDelivery Year \n2,000 MW per year \n4,164 MW per year \n6,000 MW per year \n2029/30 \n$268.47 \n$244.64 \n$227.36 \n2030/31 \n$246.72 \n$206.02 \n$179.28 \n2031/32 \n$230.84 \n$178.07 \n$141.60 \n2032/33 \n$221.78 \n$156.79 \n$111.89 \n \nDerived, scenario. 4,164 MW is the average observed across the four Delivery Years at \nparagraph A32. \n \nOn the full-proxy paths at paragraphs A44 and A45 the clearing price falls below the \n2028/2029 Net Cost of New Entry of $325.69 in every Delivery Year from 2030/2031. \nHalving the rate of new entry changes how far the price falls, not whether. Where the \nExcluded Amount is materially below the proxy, or where Allocated RBP UCAP MW \nreach post-baseline load in quantity, the price is higher and may remain at Point 1; \nparagraphs A42 and A63 state those cases. The scenario treats backstop entry as the \nresult of the procurement obligation and the $0/MW-day offer requirement rather than \nas a response to auction prices. I state these as scenarios and not as forecasts: the \nauctions have not been held, the Final RBP Target has not been set, and the 2029/2030 \nplanning parameters, endorsed at the August 19, 2026 Markets and Reliability \nCommittee meeting, have not been posted for the Base Residual Auction. \nA46. The Excluded Amounts do not run indefinitely by their terms. The New Large Load \ndefinition provides that where “three consecutive Delivery Years meet the requirements of \nTariff, Attachment DD-4, section IV(b)(iii),” the vintage date advances: New Large Load \nthereafter means load in service after June 1 of the first Delivery Year in which those \nrequirements are not met. That provision may therefore limit how long future load \nadditions enter the Excluded Amount. The tariff text does not state whether an advance \nreleases load already registered and excluded, or applies only prospectively to load sited \nafter the new date. I do not assume either interpretation in the price scenarios above."},{"page":98,"startToken":36363,"endToken":36867,"text":"51 \n \nA47. Section IV(b)(iii) is applied after the Third Incremental Auction, against a Reliability \nRequirement restated at that auction and against capacity commitments made in the Base \nResidual and Incremental Auctions together. It does not establish a Base Residual Auction \nclearing price at which the vintage date advances. Appendix B addresses the formula and \nillustrates why PJM should state its operation expressly. \nA48. Across the four studies since 2025/2026, PJM’s assumed resource portfolio rose \n11,311 MW in installed-capacity terms. Accredited Unforced Capacity rose 6,514 MW over \nthe three reported intervals, notwithstanding the retirement of Rockport 1 and 2, Cardinal \n3, and Kincaid 1 and 2. PJM’s assumptions show additions outpacing retirements on both \nmeasures. \nA49. I do not assume that any particular resource reaches commercial operation. Berkeley \nLab reports that 13 percent of capacity submitting interconnection requests between 2000 \nand 2020 had reached commercial operation by the end of 2025, while 75 percent had \nwithdrawn. Rand et al., Queued Up: 2026 Edition (Lawrence Berkeley Nat’l Lab. 2026), \navailable at https://web.archive.org/web/20260603095350/https:/emp.lbl.gov/queues. \nThe model assumes only that investment continues at approximately the rate reflected in \nPJM’s planning studies. \nA50. Resources committed to date reflect forward conditions that the proposal alters. A \ndeveloper reaching financial close forecasts the Delivery Years in which a plant will first \noffer, including the load PJM publishes and expects to procure against. The proposal \nremoves substantially all of that load growth from the procurement quantity after those \ncommitments. Reliability Resource Initiative projects were bid in March 2025 and selected \nin May 2025, when the two most recent auctions had cleared at $269.92 and $329.17; once \nin service, those projects must offer into the Base Residual Auction for at least ten years. \nA51. PJM has stated the relationship between price suppression and supply. Its 2028/2029 \nauction report states that a cap below the established Variable Resource Requirement \nCurve “can reduce the amount of investment, and therefore supply” in the PJM Region. \n2028/2029 Base Residual Auction Report 3 (July 14, 2026), available at \nhttps://perma.cc/X6UH-4ER4. PJM elsewhere ties market effectiveness to \ndurability - investors’ confidence that high prices will persist long enough to \nattract and retain the capital they are intended to signal \nPJM identifies “actual regulatory interventions, backstop procurement mandates \nand price cap proposals that have emerged in the PJM region” among the risks \ninvestors consider. It adds that uncertainty from contemplated but unfinished \nintervention may itself dampen investment. PJM, Powering Reliability Through \nMarket Design 25-26 (May 6, 2026). \nA52. On the bounding case at paragraph A37 the scenario clearing price falls below the cost \nof new entry from 2030/2031 forward. Net Cost of New Entry for the RTO was \n$325.69/MW-day in unforced capacity terms for the 2028/2029 auction. A single Delivery \nYear clearing below a prior year’s Net CONE does not establish that new entry cannot be \nfinanced, Net CONE being a reference-resource benchmark whose later-year values have"},{"page":99,"startToken":36867,"endToken":37384,"text":"52 \n \nnot been posted for the Base Residual Auction. What the scenario shows is a sustained path \nbelow the most recent posted benchmark, in the Delivery Years the Reliability Resource \nInitiative and the Reliability Backstop Procurement were designed to reach. \nA53. The filing does not quantify this price effect. The transmittal at 58 states that matched \nBring Your Own New Capacity produces a “symmetrical, one-for-one addition” and “an \neffectively price-neutral outcome,” but provides no supporting scenario or sensitivity and \ndoes not address the interaction with Reliability Backstop Procurement discussed above. \nA.6 Coverage, allocation and accreditation \nA54. A declining accreditation factor might appear to offset the reduction by shrinking \nsupply in unforced-capacity terms. Under a uniform construction, it would not. Supply \nwould equal installed capacity multiplied by the pool-wide Accredited UCAP Factor; the \nReliability Requirement would equal peak load multiplied by one plus the Installed Reserve \nMargin and by the same factor. The factor cancels. \nA55. The scenario uses a different construction. It begins with the 2028/2029 offer curve, \nwhose posted unforced-capacity quantities do not rescale, and converts additions at the \nmarginal rate from paragraph A33 rather than the pool-wide factor. Supply so constructed \nis substantially independent of the pool-wide factor, while the Curve quantity remains \nproportional to it. The cancellation does not hold, and the analysis does not rely on it. \nA56. Restoring the Point 1 price on the 2031/2032 inputs would require a Forecast Pool \nRequirement of approximately 0.9462 against the endorsed 0.9232 — either an Accredited \nUCAP Factor of 0.7859 at the endorsed reserve margin, or an Installed Reserve Margin of \n23.4 percent at the endorsed accreditation factor. [Derived.] The pool-wide factor has run \n0.7699, 0.7717, 0.7834 and 0.7668 across four consecutive studies. The Installed Reserve \nMargin has risen from 19.1 percent to 20.4 percent across the same four. \nA57. Neither parameter offsets the reduction at values observed to date. The clearing price \ndepends on more than the Excluded Amount and the supply that arrives: it depends also on \nthe Curve’s price inputs, being Gross and Net Cost of New Entry, on the offers submitted, \nand on locational constraints. \nA58. Paragraphs A37 to A57 assume that no New Large Load holds Bring Your Own New \nCapacity or Allocated RBP UCAP MW. The Excluded Amounts definition subtracts, along \nwith the 2028/2029 baseline, the megawatt quantity of New Large Load added on or after \nthe 2029/2030 Delivery Year that is in an arrangement with such capacity, converting the \nwhole to unforced capacity terms by the Forecast Pool Requirement. Whether that \nsubtraction reaches the whole load of a New Large Load holding an arrangement or only \nthe covered portion is not stated; the cases below assume the covered portion. \nA59. The two constructs enter the analysis differently and must be modeled separately. \nBring Your Own New Capacity is capacity procured by the load and must participate as a \nprice taker for ten consecutive Delivery Years beginning with the first Delivery Year of the \narrangement. Proposed Tariff, Attachment DD-4 § VIII. Allocated RBP UCAP MW are"},{"page":100,"startToken":37384,"endToken":37828,"text":"53 \n \nalready in the supply stack. The backstop quantity enters the zero-price block at paragraph \nA36 whether or not it is allocated to any load; allocating it to a New Large Load restores \nthat load to the Curve but does not create a second block of supply. \nA60. The table varies the share of New Large Load holding Bring Your Own New Capacity \nand solves each case on the offer curve at paragraph A35. Covered load returns to the \nCurve. Whether the supporting capacity is additional to the projected additions at \nparagraph A32 or already included in them is a modeling assumption, not a filed mechanic; \nthe table therefore states both cases. \nCase 1 — the supporting capacity is additional to the projected additions. \nDelivery Year \nNo coverage \n25 percent covered \n50 percent covered \n2030/31 \n$206.02 \n$207.89 \n$209.71 \n2031/32 \n$178.07 \n$180.36 \n$182.60 \n2032/33 \n$156.79 \n$160.05 \n$163.22 \nCase 2 — the supporting capacity is already included in the projected additions. \nDelivery Year \nNo coverage \n25 percent covered \n50 percent covered \n2030/31 \n$206.02 \n$286.65 \n$521.34 \n2031/32 \n$178.07 \n$280.10 \n$554.72 \n2032/33 \n$156.79 \n$280.92 \n$554.72 \n \nDerived, scenario. 2029/2030 is omitted; paragraph A25 sets out the dates bearing on \nwhether an arrangement can be formed for that Delivery Year. In the additive cases the \nsupporting capacity is added to the zero-price block. In the embedded cases the same \nmegawatts are repriced to zero within the projected additions and are not added again. \nThe Allocated RBP UCAP MW quantity remains in the zero-price block in every case and \nis not varied here. \nA61. When the supporting capacity is additional, Bring Your Own New Capacity coverage \nmodestly reduces the modeled price effect. Covered load moves the governing Curve point \nright by the applicable quantity multiplier, 101.5 percent on the segment where these \nauctions clear, while supply moves right by the capacity quantity. The Curve therefore \nmoves roughly 1.5 percent farther than supply. PJM’s price-neutrality rationale \nsubstantially holds under that construction, and I do not contend that covered capacity \nsuppresses price. When capacity is already included in projected additions, restoring load \nto the Curve without an offsetting supply addition produces a much larger effect. \nA62. Available capacity limits coverage. Fifty percent coverage requires 7,526 UCAP MW of \nnew capacity by 2030/2031 and 14,029 UCAP MW by 2032/2033, equivalent to 3.6 and 6.8 \nyears of additions at the paragraph A32 rate of 4,164 MW of installed capacity per year, \nconverted to unforced capacity at the marginal accreditation rate of approximately 50"},{"page":101,"startToken":37828,"endToken":38318,"text":"54 \n \npercent stated at paragraph A33. [Derived.] The scarcity that produced the 2028/2029 \nshortfall limits the quantity of new capacity available, and therefore the share of New Large \nLoad that can obtain coverage. \nA63. Allocated RBP UCAP MW reduce the Excluded Amount without adding supply, the \nbackstop quantity already being in the zero-price block. Varying the quantity allocated to \npost-baseline New Large Load: \nDelivery \nYear \nNone allocated to post-baseline \nload \nHalf the Final \nTarget \nThe Final Target in \nfull \n2030/31 \n$206.02 \n$267.53 \n$416.15 \n2031/32 \n$178.07 \n$228.35 \n$299.27 \n2032/33 \n$156.79 \n$199.46 \n$258.47 \n \nDerived, scenario. The allocated quantity restores the corresponding load to the Curve; \nno capacity is added, the backstop quantity already having entered the zero-price block \nat paragraph A36. \nA64. Apart from the quantity of load excluded, allocation of RBP UCAP MW produces the \nwidest sensitivity in the analysis, and it runs in one direction. The zonal quantity is based \non Table B-9b load growth from 2026/2027 through 2028/2029, totaling 9,033.2 MW. \nCroop Aff. paragraphs 43, 46. That load falls within the 2028/2029 baseline and is never \nexcluded. Section IX(b) nevertheless allocates within a zone as the Electric Distributor \ndirects or, absent direction, pro rata among all New Large Loads. Cost responsibility is fixed \non one vintage, but the allocation rule does not confine the benefit to that vintage. PJM \nstates that the benefit should follow cost responsibility. The present record does not \ndetermine the quantity reaching post-baseline load. \nA65. A load that brings its own capacity contracts against a revenue stream the proposal \nreduces. Such capacity offers at $0/MW-day for ten consecutive Delivery Years, clears, and \nreceives the resource clearing price. Relative to Net Cost of New Entry of $325.69, the \nparagraph A37 scenario leaves a gap of approximately $43,700 per MW-year in \n2030/2031. [Derived.] For 2029/2030 the base case clears at $337.83 under the collar, so \nno gap arises in that case. In the full-participation sensitivity at paragraph A37 the modeled \nclearing price is $244.64, which lies within the collar and is therefore the clearing price. \nThe bilateral arrangement must account for that annual revenue gap, and for uncertainty in \nthe price path, over its ten-year term. In exchange, the load receives relief from an \nobligation compensated under Attachment DD-4 section X at fifty percent of the Non-\nPerformance Charge Rate, electable to zero, without a settlement backstop. The exclusion \nalso alters the choice the load faces. A New Large Load weighs the cost of procuring \ncapacity against the cost of remaining eligible for Interim Resource Adequacy Service: the \nLocational Reliability Charge it pays in any event, plus the expected cost of curtailment, \ncompensated at not more than fifty percent of the Non-Performance Charge Rate and \nelectable to zero. The exclusion lowers the clearing price, and so lowers the cost of the"},{"page":102,"startToken":38318,"endToken":38502,"text":"55 \n \ncapacity the load pays for through its Load Serving Entity, while the compensation for \ncurtailment is set administratively. To that extent the mechanism reduces the incentive to \nprocure Bring Your Own New Capacity, which is the outcome the filing seeks to encourage. \nThese economics may affect the availability and pricing of Bring Your Own New Capacity \narrangements, and the paragraph A25 assumption may extend beyond 2029/2030. \nA.7 Locational Reliability Charge and the section X(a) rate \nA66. The two quantities can be compared using the posted parameters for a single Delivery \nYear, though the Tariff does not link them. For 2027/2028 the Forecast Pool Requirement \nis 0.9260 and the clearing price is $333.44/MW-day. \nOne megawatt of New Large Load, 2027/2028 \n \nLocational Reliability Charge \n$112,699 per MW-year \nSection X(a) rate, RTO \n$1,139 per MWh \nHours of curtailment at which compensation equals the charge \n99 \n[Derived.] The comparison is arithmetic only. The charge is an obligation allocated under \nSchedule 8 and the rate is compensation for curtailment; neither is calculated by reference \nto the other."},{"page":103,"startToken":38502,"endToken":38994,"text":"56 \n \nAPPENDIX B — ADDITIONAL IMPLEMENTATION ISSUE: \nATTACHMENT DD-4, SECTION IV(b) \nB1. Attachment DD-4, section IV(b) governs the amount of Eligible New Large Load that \nmust be available to provide Interim Resource Adequacy Service, determined after the \nThird Incremental Auction for each Delivery Year. It does not determine the amount \nremoved from the auction procurement quantity. That reduction is made by the Excluded \nAmounts definitions and applied in Attachment DD, section 5.10(a). \nB2. The provision does not express its calculation unambiguously. Two features leave the \nformula unclear. \nB3. The placement of the divisor. In subsections (i) and (ii) the bracket encloses a \ncomparison — capacity “is less than” the requirement — the division by the Pool-wide \nAccredited UCAP Factor follows the bracket, and a clause then measures the result against \nthe Eligible New Large Load Amounts. In subsection (iii) the bracket encloses “equals or \nexceeds,” the division again follows a completed comparison, and nothing follows it. A \ncomparison yields no quantity that can be divided. At least three readings are available: the \ndivisor applies to the difference between the two quantities, to the requirement alone, or to \nnothing at all in subsection (iii). \nB4. The units on each side, and the factor used. Section V(b) converts Bring Your Own New \nCapacity and Allocated RBP UCAP MW to load by dividing by the Forecast Pool \nRequirement, and both Excluded Amounts definitions convert load to capacity “by using \nthe Forecast Pool Requirement.” Section IV(b) instead applies the Pool-wide Accredited \nUCAP Factor, and measures the result against the Eligible New Large Load Amounts, which \nsection V(b) defines as registered peak load less an offset — a quantity denominated in \nload. The Commission has described the Forecast Pool Requirement as reflecting “PJM’s \ninstalled capacity requirement in Unforced Capacity (UCAP) terms,” and as applied to a \nDemand Resource’s Nominated Value to yield unforced capacity. PJM Interconnection, L.L.C., \n186 FERC ¶ 61,080 at PP 2, 9 (2024). The Forecast Pool Requirement converts load to \ncapacity; the Pool-wide Accredited UCAP Factor converts installed capacity to unforced \ncapacity. \nB5. The Reliability Requirement is also unqualified. Section IV(b) refers to “the PJM Region \nReliability Requirement determined prior to the Third Incremental Auction” without \nstating whether that quantity is gross or net of the Excluded Amounts, and without stating \nwhether the comparison is made on a regional basis or net of the obligations of FRR \nEntities. Attachment DD, section 5.4(c)(2)(i) states a comparison of the same shape — the \nupdated Reliability Requirement against total capacity committed — and there qualifies \nthe requirement as “inclusive of any adjustments associated with Excluded RTO New Large \nLoad Amounts or Excluded LDA New Large Load Amounts.” \nB6. PJM should state the calculation and its units expressly on the tariff sheets: what \nquantity the Pool-wide Accredited UCAP Factor operates on; the units on each side of the \ncomparison; why that factor rather than the Forecast Pool Requirement; whether the"},{"page":104,"startToken":38994,"endToken":39380,"text":"57 \n \nReliability Requirement is gross or net of the Excluded Amounts; and whether the \ncomparison is regional or adjusted for FRR. \nB7. A further item requires clarification and is addressed at paragraphs A46 and A47. The \nNew Large Load definition advances its vintage date where three consecutive Delivery \nYears meet the requirements of section IV(b)(iii). The definition redefines New Large Load \nprospectively. Whether load already registered and excluded ceases to be excluded on the \nnew date, or whether the advance applies only to load sited afterward, is not stated. On the \nfirst reading the accumulated Excluded Amount unwinds; on the second it stops growing. \nIllustration — why the ambiguity is worth resolving \nB8. On the 2029/2030 endorsed parameters, the FRR-adjusted Reliability Requirement \ngross of the exclusion is 147,329.8 UCAP MW, the Excluded Amount on the Table B-9b \nproxy is 5,223.1 UCAP MW, the requirement net of the exclusion is 142,106.7 UCAP MW, \nand Point 1 of the reduced Curve is 140,685.6 UCAP MW. [Derived.] \nB9. The calculation below assumes committed capacity equal to Point 1 of the reduced \nCurve, and applies the divisor to the difference between the requirement and committed \ncapacity. The two rows differ only in whether the Reliability Requirement is read gross or \nnet of the Excluded Amounts. \nReading \nCalculation \nResult \nConsequence \nRequirement \ngross of the \nexclusion \n(147,329.8 − \n140,685.6) ÷ \n0.7668 \n8,664.8 \nMW \nexceeds the 5,657.6 MW of Eligible \nNew Large Load Amounts available, so \nsection IV(b)(i) applies and all must be \navailable \nRequirement net \nof the exclusion \n(142,106.7 − \n140,685.6) ÷ \n0.7668 \n1,853.3 \nMW \nsection IV(b)(ii) applies and roughly \none-third must be available \n[Derived.] The difference between the two results, 6,811.6 MW, is the Excluded Amount \ndivided by the same factor. The same auction outcome therefore yields materially different \navailability determinations depending on which reading governs. \nB10. The two readings therefore produce materially different annual availability \ndeterminations from the same auction outcome. Neither determination causes curtailment; \na real-time Interim Resource Adequacy Service Action remains subject to the separate \noperational trigger, and Mr. Pilong confirms that the framework “does not require PJM to \nreduce affected load whenever an IRAS requirement exists.” Pilong Aff. ¶ 22."},{"page":105,"startToken":39380,"endToken":39447,"text":"58 \n \nAFFIDAVIT OF CARL COSCIA \nON BEHALF OF PJM POWER PROVIDERS GROUP \nI, Carl F. Coscia, hereby declare under penalty of perjury pursuant to 28 U.S.C. § 1746 that \nthe statements contained in the foregoing affidavit on behalf of PJM Power Providers Group \nare true and correct to the best of my knowledge, information, and belief. \nExecuted this 3rd day of September, 2026. \n  \n______________________________ \nCarl F. Coscia"},{"page":106,"startToken":39447,"endToken":39494,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document on each \nperson designated on the official service list compiled by the Secretary in the \nabove-captioned proceeding. \nDated at Washington, D.C., this 3rd day of September, 2026. \n \n \n_Hazel Lavarn-Walker_______ \n \n \n \nHazel Lavarn-Walker"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":978,"startToken":0,"endToken":1006},{"p":4,"at":978,"title":"I. PROTEST","method":"printed heading","endPage":4,"endAt":991,"startToken":1006,"endToken":1008},{"p":4,"at":991,"title":"A. The Federal Power Act Dictates Rejection of the IRAS Proposal","method":"printed heading","endPage":11,"endAt":4,"startToken":1008,"endToken":3328},{"p":11,"at":4,"title":"B. PJM’s Proposal Would Inappropriately Stifle Supply from","method":"printed heading","endPage":24,"endAt":4,"startToken":3328,"endToken":7255},{"p":24,"at":4,"title":"C. PJM Improperly Proposes to Degrade the Regional Reliability","method":"printed heading","endPage":28,"endAt":677,"startToken":7255,"endToken":8506},{"p":28,"at":677,"title":"D. PJM Seeks to Add Unduly Discriminatory Requirements to its","method":"printed heading","endPage":29,"endAt":757,"startToken":8506,"endToken":8812},{"p":29,"at":757,"title":"E. IRAS is too Indeterminate to be Found to be a Just and","method":"printed heading","endPage":31,"endAt":116,"startToken":8812,"endToken":9403},{"p":31,"at":116,"title":"F. PJM Seeks to Use the Reliability Standards in a Way That FPA","method":"printed heading","endPage":40,"endAt":4,"startToken":9403,"endToken":11830},{"p":40,"at":4,"title":"G. PJM’s Proposal is Inconsistent with NERC Reliability Standards","method":"printed heading","endPage":41,"endAt":1166,"startToken":11830,"endToken":12337},{"p":41,"at":1166,"title":"H. The IRAS Proposal is Inconsistent with FPA Section 201 and","method":"printed heading","endPage":45,"endAt":177,"startToken":12337,"endToken":13568},{"p":45,"at":177,"title":"II. COMMUNICATIONS","method":"printed heading","endPage":45,"endAt":732,"startToken":13568,"endToken":13654},{"p":45,"at":732,"title":"III. CONCLUSION","method":"printed heading","endPage":48,"endAt":221,"startToken":13654,"endToken":14144},{"p":48,"at":221,"title":"I. INTRODUCTION AND QUALIFICATIONS","method":"printed heading","endPage":49,"endAt":900,"startToken":14144,"endToken":14621},{"p":49,"at":900,"title":"II. EXECUTIVE SUMMARY","method":"printed heading","endPage":52,"endAt":1095,"startToken":14621,"endToken":16218},{"p":52,"at":1095,"title":"III. EFFECT ON RPM CLEARING PRICES AND THE RESOURCE-","method":"printed heading","endPage":65,"endAt":6,"startToken":16218,"endToken":21801},{"p":65,"at":6,"title":"IV. PLANNING ON GROSS LOAD AND PROCUREMENT NET OF","method":"printed heading","endPage":69,"endAt":2816,"startToken":21801,"endToken":23984},{"p":69,"at":2816,"title":"V. CONTINUING CAPACITY OBLIGATIONS AND COST","method":"printed heading","endPage":72,"endAt":637,"startToken":23984,"endToken":25085},{"p":72,"at":637,"title":"VI. THE ABSENCE OF A BINDING SUBSTITUTE, AND THE","method":"printed heading","endPage":81,"endAt":1894,"startToken":25085,"endToken":29231},{"p":81,"at":1894,"title":"VII. CONCLUSION","method":"printed heading","endPage":106,"endAt":0,"startToken":29231,"endToken":39447},{"p":106,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":106,"endAt":330,"startToken":39447,"endToken":39494}]}