{"document":{"slug":"rec-20260903-5159","title":"Limited Protest of Public Interest Organizations requesting narrow modifications of the proposed Interim Resource Adequacy Service by PJM Interconnection, L.L.C","issued":"2026-09-03","accession":"20260903-5159","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Sierra ClubNatural Resources Defense CouncilAppalachian Voices ,Environmental Law and Policy Center ,Center for Progressive Reform ,","kind":"protest","file":"sources/filings/text/20260903-5159_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5159","tier":"record","sha256":"59e27b263e9e2f37d01b9d96b7af962e9b4d3ebfd8f28f6e1ac8be164b607f27","pages":63,"tokens":17922,"emptyPages":[],"textThemes":["flex","adequacy","registry","cost"]},"pages":[{"page":1,"startToken":0,"endToken":246,"text":"UNITED STATES OF AMERICA  \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.  \n)  \n)  \n) \nDocket No. ER 26-3515\n \n \nLIMITED PROTEST OF PUBLIC INTEREST ORGANIZATIONS \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or the “Commission”),1 Sierra Club, Natural Resources \nDefense Council (“NRDC”), Environmental Law and Policy Center, Appalachian Voices, and the \nCenter for Progressive Reform (collectively, “Public Interest Organizations” or “PIOs”) submit \nthis limited protest of four aspects of PJM Interconnection, L.L.C.’s (“PJM”) proposed Interim \nResource Adequacy Service and Large Load Registry (“IRAS Filing”).2  \nWith the limited modifications described below, the IRAS Filing is an essential \nmechanism to protect customers in PJM from skyrocketing costs and degrading reliability caused \nby the forecasted rapid influx of large loads. PIOs believe the IRAS Filing could, if modified as \ndescribed below, permanently resolve emerging resource adequacy shortfalls while respecting \njurisdictional boundaries. PIOS therefore urge the Commission to approve PJM’s IRAS Filing \nwith modifications to (1) ensure IRAS and Bring Your Own New Capacity (“BYONC”) \nrequirements are permanent for all new large loads, or else to clarify that the trigger for the IRAS \nprogram going to sleep is the capacity market clearing for three consecutive years with sufficient \n \n1 18 C.F.R. § 385.211. \n2 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service & a \nLarge Load Registry, Docket No. ER26-3515-000 (Aug. 13, 2026), Accession No. 20260813-\n5118 (“IRAS Filing”)."},{"page":2,"startToken":246,"endToken":325,"text":"ii \nsupply to satisfy all demand including new large loads; (2) require penalties for LSEs that fail to \ncomply with IRAS Actions; (3) either eliminate compensation for IRAS resource curtailment, or \nrequire PJM to cap the compensation awarded to IRAS loads at no more than the amount the \nnew large load paid in capacity charges for the relevant delivery year; and (4) require BYONC \nsupply to be fully deliverable to new large loads by considering transmission limits between \nzones."},{"page":3,"startToken":325,"endToken":671,"text":"iii \nTABLE OF CONTENTS \nINTRODUCTION .......................................................................................................................... 1 \nBACKGROUND ............................................................................................................................ 5 \nI. PJM is facing resource adequacy and affordability concerns as it struggles to meet data \ncenter load growth............................................................................................................... 5 \nA. PJM’s capacity market faces increased reliability risks as data center load grows \nfaster than PJM can bring new supply online. .............................................................. 6 \nB. PJM’s supply and demand imbalance is causing high capacity prices, leading to \nhistorically high bills for all ratepayers. ....................................................................... 9 \nII. The Commission should accept PJM’s Interim Resource Adequacy Service and Large \nLoad Registry with modifications to better achieve the IRAS’s objectives. .................... 11 \nDISCUSSION ............................................................................................................................... 12 \nI. The IRAS Framework is just and reasonable and not unduly discriminatory. ................. 12 \nA. Large load customers are differently situated from other customers. ......................... 13 \nB. IRAS is jurisdictionally sound and respects the roles of states and PJM. .................. 18 \nC. Removing New Large Loads from RPM is just, reasonable, and not unduly \ndiscriminatory. ............................................................................................................ 20 \nII. The Commission Should Only Modify PJM’s IRAS Filing to Better Accomplish PJM’s \nObjectives. ........................................................................................................................ 23 \nA. Objective One: Promote Reliability by Requiring New Large Loads to be Curtailable \nUntil They Bring New Capacity to Meet Their Needs. .............................................. 24 \nB. Objective Two: Promote Affordability by Requiring New Large Loads to Pay for \nTheir Own New Capacity and Avoid Shifting Costs to Residential and Other Existing \nRatepayers. .................................................................................................................. 26 \nC. Objective Three: Provide States and LSEs With Sufficient Information to Ensure the \nRight Loads are Curtailed and Charged. ..................................................................... 28 \nIII. Modification 1: The Commission must ensure that the IRAS filing effectively removes \nnew large loads from the capacity market until associated new capacity is online and \ndeliverable. ........................................................................................................................ 30 \nA. Suspending the IRAS Framework during periods of resource adequacy risks pinning \nprices at the cap. .......................................................................................................... 31 \ni. Suspending the IRAS Framework will reduce the incentive for New Large Loads \nto fully BYONC, raising costs for other customers. ............................................. 33 \nii. Suspending the IRAS Framework based on the lower Reliability Requirement \nwhich excludes New Large Loads that have not demonstrated BYONC is not an \nappropriate trigger. ................................................................................................ 34 \nB. PJM’s proposal to toggle IRAS on and off creates regulatory uncertainty and \nwhiplash for market participants. ................................................................................ 34"},{"page":4,"startToken":671,"endToken":882,"text":"iv \nC. The Commission should modify PJM’s IRAS Filing to make the IRAS Framework \nPermanent or correct the Reliability Requirement Trigger. ........................................ 36 \nIV.  Modification 2: The Commission Should Modify the IRAS Filing to Include Penalties \nWhen Eligible New Large Loads Fails to Curtail ............................................................. 38 \nA. Commission Precedent Supports Operational and Financial Consequences When a \nLage Load Fails to Curtail. ......................................................................................... 39 \nB. The Commission Should Require Operational Penalties for Failure to Curtail. ......... 40 \nC. If the Commission declines to impose operational penalties, then the Commission \nshould modify PJM’s proposal to include financial penalties. ................................... 44 \nV. Modification 3: The Commission Should Reject IRAS Compensation or, in the \nAlternative, Limit Any Payment to a Make-Whole Payment for Capacity Charges. ....... 46 \nA. Curtailability Is a Condition of Speed to Power, Not a Separately Compensable \nService......................................................................................................................... 47 \nB. Cost Causation Principles Support a Zero-Dollar Rate or a Capacity-Charge Credit. 49 \nC. PJM’s Reliance on the Commission’s Decision on Compensation for Pre-Emergency \nLoad Response Does Not Justify the Proposed Rate. ................................................. 50 \nD. The Commission Should Remove IRAS Performance Compensation or, in the \nAlternative, Limit Any Compensation to a Make-Whole Payment. ........................... 51 \nVI. Modification 4: The Commission should require BYONC supply to be fully deliverable \nto new large loads by considering transmission limits between zones. ............................ 52 \nCONCLUSION ............................................................................................................................. 56"},{"page":5,"startToken":882,"endToken":1204,"text":"1 \nINTRODUCTION \n \nThe unprecedented number of new and forecasted large load additions, mostly data \ncenters, in the PJM footprint has outstripped new supply, and PJM’s capacity auctions have \ncleared short of the region’s reliability requirement for two consecutive auctions despite hitting \nauction price caps in both auctions.3 These shortfalls increase the risk of loss-of-load events and \nsustained high-capacity prices for existing ratepayers who are not responsible for these new \nshortfalls. Moreover, PJM expects that capacity shortfalls may continue due to the rapid growth \nof data centers and other large loads that PJM cannot currently serve reliably.  \nThe IRAS Filing is an attempt by PJM to ensure that future shortfalls do not create \nreliability risks and to avoid shifting costs to residential or other existing ratepayers. PJM \nproposes four changes to its governing documents. First, PJM will require that a Load Serving \nEntity (“LSE”) must bring new capacity to offset or exceed the amount of peak load from new \nlarge loads.4 If an LSE fails to bring such new capacity, it will be subject to load reduction \nrequirements prior to Pre-Emergency Load Management Response.5 Second, PJM will establish \na Large Load Registry, which will allow PJM to identify how much new capacity an LSE is \nrequired to bring to offset new large loads.6 Third, PJM will define Large Loads, New Large \nLoads, and Eligible New Large Loads.7 Fourth, PJM will exclude New Large Loads that do not \nBring Your Own New Capacity (“BYONC”) from the Variable Resource Requirement (“VRR”) \n \n3 The auction fell short by 6,623 MW and 6,831 MW of unforced capacity in the 2027/2028 and \n2028/2029 auctions, respectively. IRAS Filing, supra note 2, at 14. \n4 Id. at 3–4. \n5 Id. \n6 Id. at 5. \n7 Id. at 5–6. Unless otherwise noted, capitalized terms in this limited protest have the same \ndefinition as the referenced PJM filing and proposed Tariff."},{"page":6,"startToken":1204,"endToken":1489,"text":"2 \nCurve to ensure that existing customers do not purchase new capacity for New Large Loads.8 \nNew BYONC supply must participate in the PJM Reliability Procurement Mechanism (“RPM”) \nas price takers (i.e., $0/MW offer) for 10 consecutive delivery years.9 PIOs strongly support \nPJM’s proposal to limit reliability service for LSEs serving New Large Loads that fail to \nBYONC. \nPIOs support many aspects of the IRAS Filing and find the overarching framework just, \nreasonable, and not unduly discriminatory. It is admirable that PJM is proposing to limit the \nreliability guarantee for zones in which New Large Loads fail to bring new capacity to the \nsystem. By excluding those resources from the capacity market, PJM will ensure that residential \nand other existing ratepayers do not purchase capacity for New Large Loads. PJM is proposing \nchanges that generally support the Statement of Principles Regarding PJM issued on January 16, \n2026, by the National Energy Dominance Council and the 13 governors of the PJM States,10 the \nRatepayer Protection Pledge signed by more than 200 utilities, developers, cooperatives, and \ngovernors,11 and the repeated recommendations that PIOs, consumer advocates, and other \nstakeholders made during the PJM stakeholder process.12 \n \n8 Id. at 5–8. \n9 Id. at 55. \n10 Statement of Principles from the White House Nat’l Energy Dominance Council & PJM \nGovernors Regarding PJM (Jan. 15, 2026), https://www.energy.gov/documents/statement-\nprinciples-regarding-pjm. \n11 Ratepayer Protection Pledge, The White House (Mar. 4, 2026), \nhttps://www.whitehouse.gov/ratepayer-protection-pledge/#signatories (“Ratepayer Protection \nPledge”). \n12 See, e.g., NRDC & the PJM Legislators Collaborative, Protecting Ratepayers Proposal: \nExecutive Summary (Nov. 17, 2025), https://www.pjm.com/-/media/DotCom/committees-\ngroups/cifp-lla/2025/20251119/20251119-item-02e---pjm-legislators-and-nrdc-package---\nexecutive-summary.pdf"},{"page":7,"startToken":1489,"endToken":1749,"text":"3 \nPJM’s consent to modification is a further signal that it is committed to the most effective \nIRAS Filing possible. Rather than present a take-it-or-leave-it package, PJM “consents to the \nCommission’s exercise of authority to modify and/or sever any element of the proposed Tariff \nand RAA language” so long as any modification “is consistent with PJM’s overarching \nobjectives in this filing.”13 PJM invites stakeholders to “comment as they feel necessary and \nappropriate.”14 PIOs accept this invitation by proposing several narrow but important \nmodifications that the Commission can prescribe in an order approving the IRAS Filing. \nPJM’s consent is bounded by its “overarching objectives in this filing,” yet the IRAS \nFiling never explicitly defines the objectives.15 Fairly read, however, the IRAS Filing pursues \nthree objectives: \n1. Promote reliability by requiring new large loads to be curtailable until they bring new \ncapacity to meet their needs. \n2. Promote affordability by requiring new large loads to pay for their own new capacity \nand avoid shifting costs to residential and other existing ratepayers. \n3. Provide states and LSEs with sufficient information to ensure that new large loads, \nand not existing customers, are curtailed when new large loads fail to BYONC and \nthat new large loads pay for their own new capacity. \nThe IRAS Filing fails to fully satisfy the first two objectives. This limited protest \nidentifies four narrow but important modifications that will help PJM advance these objectives \nwith the IRAS Filing. \n \n13 IRAS Filing, supra note 2, at 9, 122. \n14 Id. at 124. \n15 Id. at 9, 122."},{"page":8,"startToken":1749,"endToken":2050,"text":"4 \nFirst, the IRAS Filing allows resources that do not BYONC to exit IRAS without first \nbringing new generation. The IRAS program “effectively goes to sleep” after three consecutive \ndelivery years of meeting PJM’s Reliability Requirement, even though the Reliability \nRequirement excludes load subject to IRAS.16 PIOs propose that the Commission either require \nPJM to never put the IRAS program to sleep, or else to clarify that the trigger for the IRAS \nprogram being put to sleep is the capacity market clearing for three consecutive years with \nsufficient supply to meet all demand including new large loads subject to IRAS . \nSecond, the IRAS Filing does not have any penalty provisions for non-compliance with \nIRAS curtailment requirements. The Commission should require PJM to create a penalty applied \nto LSEs that fail to reduce load when PJM makes an IRAS Action and require PJM to provide \nLSEs and states with sufficient information to enable retail regulators to ensure that any such \npenalties are borne by loads that fail to curtail as instructed, rather than by other consumers.  \nThird, the IRAS Filing provides compensation to unmatched large loads that curtail under \nthe IRAS program. And the IRAS filing lacks a cap on the total amount of compensation IRAS \nresources may receive in the aggregate.17 The Commission should remove this compensation \nbecause the ability to pursue speedy interconnection prior to bringing their own capacity \nresources already provides IRAS resources with sufficient consideration for their commitment to \ncurtail when required. Moreover, because the purpose of the proposed compensation for IRAS \nActions is to make up for any capacity bills that large loads may still be required to pay, the \nCommission should require PJM to cap the compensation at no more than the amount the \n \n16 Id. at 72. \n17 Id. at 10 n.22."},{"page":9,"startToken":2050,"endToken":2294,"text":"5 \nEligible New Large Load paid in capacity charges for the relevant delivery year if it allows any \ncompensation for IRAS curtailments. To the extent compensation is provided for IRAS \ncurtailment, PIOs strongly support PJM’s position that states and retail regulators retain authority \nto waive such compensation entirely.18  \nFourth, the IRAS Filing does not include a locational requirement for the new BYONC \nsupply. Without a locational requirement, PJM risks relying on new capacity that will not \nactually be able to serve the zone in which the sponsoring new large load resides, thus failing to \nachieve the reliability objective described above. Similarly, allowing distant load and supply \narrangements could result in significant regional transmission needs, which shift costs to other \nratepayers, failing objective 2. The Commission should direct PJM to require BYONC to be \nlocated only in zones that are not constrained with regard to the zone in which the new large load \nresides. \nThese modifications will disturb neither the IRAS Filing’s architecture nor its schedule, \nand they fall squarely within PJM’s consent. These modifications will help the IRAS Filing \nensure that PJM maintains reliability without imposing undue costs on residential and other \nexisting ratepayers. \nBACKGROUND \n \nI. \nPJM is facing resource adequacy and affordability concerns as it struggles to meet \ndata center load growth. \n \nPJM’s capacity market, the RPM, worked relatively well at assuring resource adequacy at \nreasonable rates for nearly twenty years, under conditions of predictable, gradual load growth \n \n18 Id. at 102."},{"page":10,"startToken":2294,"endToken":2634,"text":"6 \nspread relatively evenly across the PJM footprint. New generation resources could be built and \ninterconnected closer to the market’s three-year forward timeline.19 However, as load growth, \ngeneration retirement, interconnection timelines, and supply chain delays have all increased in \nrecent years, PJM has recognized that the current state of its markets is untenable.20 Due in part \nto PJM’s slow progress on interconnection reform and lack of multi-value transmission planning, \nPJM’s markets are facing two major pain points: (1) data center load is growing faster than new \nsupply can come online, leading to reliability concerns; and (2) PJM’s supply and demand \nimbalance is causing sustained high capacity prices, leading to historically high bills for all \nratepayers. \nA. \nPJM’s capacity market faces increased reliability risks as data center load \ngrows faster than PJM can bring new supply online. \nPJM’s market is facing unprecedented load growth from rising data center demand that is \noutstripping supply and threatening reliability. These threats will accelerate if data center \ndemand materializes as projected. Markets across the U.S. have not experienced this level of \ndemand growth in recent memory. Electricity demand in the U.S. was relatively flat from the \nearly 2000s until the early 2020s.21 That trend has quickly changed. Over the next five years, the \nU.S. expects electricity usage to grow 5.7% per year.22 Data centers are expected to make up \n \n19 PJM, Powering Reliability Through Market Design, 4 (May 6, 2026), https://www.pjm.com/-\n/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-\nthrough-market-design.pdf (“Powering Reliability Through Market Design”). \n20 Id. at 3, 27. \n21 Mark Schipper & Tyler Hodge, After More Than a Decade of Little Change, U.S. Electricity \nConsumption is Rising Again, U.S. Energy Info. Admin (May 13, 2025), \nhttps://www.eia.gov/todayinenergy/detail.php?id=65264. \n22 John Wilson et. al., Grid Strategies, Power Demand Forecasts Revised Up for Third Year \nRunning, Led by Data Centers, 6 (Nov. 2025), https://gridstrategiesllc.com/wp-\ncontent/uploads/Grid-Strategies-National-Load-Growth-Report-2025.pdf (“Grid Strategies 2025 \nLoad Growth Report”)."},{"page":11,"startToken":2634,"endToken":2994,"text":"7 \n25% to 55% of the total demand growth in the U.S. through 2030.23 PJM predicts that 30 GW of \nlarge load demand will come online by 2030 and 70 GW of large load demand will come online \nby 2038.24 \nMost data center load growth through 2030 will be concentrated in the Electric \nReliability Council of Texas (“ERCOT”) and PJM.25 Three states—Virginia, Texas, and \nCalifornia—host the highest concentration of data centers, and Virginia, located in the PJM \nfootprint, hosts the largest number of data centers in the country.26 PJM’s Dominion Zone, which \ncovers Virginia, is expected to have the largest absolute increase in summer peak demand \nthrough 2030.27 RTO-wide, PJM expects its peak load growth to increase 65,773 MW by 2026 \nfrom its summer peak and 66,980 MW for its winter peak.28 \n \n23 Grid Strategies 2025 Load Growth Report at 3; Jonathan Koomey et. al., Bipartisan Pol’y Ctr. \n& Koomey Analytics, Electricity Demand Growth and Data Centers: A Guide for the Perplexed, \n10 (Feb. 2025), https://bipartisanpolicy.org/wp-content/uploads/2025/02/BPC-Report-Electricity-\nDemand-Growth-and-Data-Centers-A-Guide-for-the-Perplexed.pdf. \n24 Letter from Paula Conboy, Chair, PJM Board of Managers, to PJM Stakeholders on Critical \nIssue Fast Path – Reliability Backstop Procurement and Connect and Manage, 1 (Jul. 27, 2026), \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement-\nand-connect-and-manage.pdf (“PJM Board July 2026 Decisional Letter”); PJM Proposes \nFramework to Connect Data Centers Without Compromising Reliability, Affordability, PJM \nInside Lines (Aug. 13, 2026), https://insidelines.pjm.com/pjm-proposes-framework-to-connect-\ndata-centers-without-compromising-reliability-affordability/. \n25 Grid Strategies 2025 Load Growth Report, supra note 23, at 5. \n26 Rebecca Leppert, What We Know About Energy Use at U.S. Data Centers Amid the AI Boom, \nPew Research center, Pew Research (Oct. 24, 2025), https://www.pewresearch.org/short-\nreads/2025/10/24/what-we-know-about-energy-use-at-us-data-centers-amid-the-ai-boom/. \n27 Mark Schipper & Jonathan Church, Commercial Electricity Sales Have Soard in Virginia, \nDriven by Data Centers, U.S. Energy Info. Admin. (May 5, 2026), \nhttps://www.eia.gov/todayinenergy/detail.php?id=67664. \n28 PJM, 2026 PJM Load Forecast Report, 6 (Jan. 14, 2026), https://www.pjm.com/-\n/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf."},{"page":12,"startToken":2994,"endToken":3317,"text":"8 \nPJM’s expected data center load growth is incompatible with current generation \ndevelopment timelines that have increased due to a slow interconnection process, supply chain \nissues, a lack of proactive, multi-value regional transmission planning, and the slow pace of \nnetwork upgrade construction. While developers can typically build hyperscale data centers \nwithin 18 to 24 months, new generation resources can spend 4 to 5 years in interconnection \nqueues and endure lengthy siting, permitting, and construction processes before coming online.29 \nTransmission upgrades can take even longer, with average timelines ranging from 7 to 10 years \nto plan, approve, and build.30 In short, it takes far longer to build new power plants than data \ncenters. \nAs a result of its supply and demand imbalance, PJM has fallen short of its Reliability \nRequirement for the past two RPM Base Residual Auctions (“BRAs”) for delivery years \n2027/2028 and 2028/2029. PJM’s 2028/2029 BRA cleared 6,831.3 MW short of PJM’s \nreliability requirement, while the 2027/2028 BRA cleared 6,6623 MW short.31 While PJM has \nsuggested that these gaps may narrow as the delivery year approaches,32 the trend is concerning. \nPJM expects that without its Reliability Backstop Procurement, the 2029/2030 BRA in \nDecember of this year will also clear short.33 Falling below the reserve margin means that PJM \n \n29 Rachel Mural et. al, Data Centers and Large-Scale Electric Growth: The Virginia and Texas \nExperiences, Belfer Ctr. For Science and Int’l Aff. (Apr. 20, 2026), \nhttps://www.belfercenter.org/research-analysis/data-centers-texas-virginia-comparison. \n30 Id.  \n31 IRAS Filing, supra note 2, at 14. \n32 PJM Auction Procures 134,479 MW of Generation Resources, PJM Inside Lines (Dec. 1, \n2025) https://insidelines.pjm.com/pjm-auction-procures-134479-mw-of-generation-resources/  \n33 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource \nAdequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (Jul. 31, 2026), \nAccession No. 20260731-5214 (“RBP Filing”). PJM’s filing is pending at FERC. PIOs filed a"},{"page":13,"startToken":3317,"endToken":3695,"text":"9 \nhas to operate with slimmer reserves and endure more reliability risks.34 The North American \nElectric Reliability Corporation (“NERC”) has classified PJM as an elevated risk area from 2026 \nto 2028 and a high risk area from 2029 onward.35 NERC predicts that as data center load growth \ncontinues to increase in the coming years, the risk of reliability shortfalls will increase as well.36 \nB. \nPJM’s supply and demand imbalance is causing high capacity prices, leading \nto historically high bills for all ratepayers. \nPJM’s market is also facing unsustainably high prices. The past three BRAs cleared at the \nprice cap, clearing at $325/MW-day in the 2028/2029 BRA,37 $333.44/MW-day in the \n2027/2028 BRA,38 and $329.17/MW-day in the 2026/2027 BRA.39 For reference, PJM’s \n2024/2025 BRA cleared at only $28.92/MW-day and at $269.92/MW-day in the 2025/2026 \nBRA.40 PJM’s independent market monitor (“IMM”) estimated that data centers caused 63% of \nthe increase in prices in the 2025/2026 BRA, resulting in an increase of $9.3 billion in higher \ncosts for PJM customers.41 As of January 2026, the IMM estimated that the costs to the other \n \nLimited Protest in response to PJM’s RBP proposal, largely supporting PJM’s proposal. See \nSierra Club & NRDC, Limited Protest of Public Interest Organizations, Docket No. ER26-3380-\n000 (Aug. 21, 2026), Accession No. 20260821-5180. \n34 PJM Capacity Auction Procures 138,318 MW of Generation Resources as Work Continues to \nAddress Growing Electricity Demand, PJM Inside Lines (Jul. 14, 2026), \nhttps://insidelines.pjm.com/pjm-capacity-auction-procures-138318-mw-of-generation-resources-\nas-work-continues-to-address-growing-electricity-demand. \n35 N. Am. Elec. Reliability Corp. (“NERC”), 2025 Long Term Reliability Assessment (Jan. \n2026), https://www.nerc.com/globalassets/our-work/assessments/nerc_ltra_2025.pdf. \n36 NERC, 2025 Long Term Reliability Assessment, supra note 35. \n37 IRAS Filing, supra note 2, at 14. \n38 Id. at 14. \n39 PJM, 2026/2027 Base Residual Auction Report, 3, 5 (Jul. 22, 2025), https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/2026-2027/2026-2027-bra-report.ashx. \n40 Id. at 5. \n41 Cathy Kunkel, Projected Data Center Growth Spurs PJM Capacity Prices by Factor of 10, \nInst. for Energy Econ. And Fin. Analysis (Jul. 30, 2025), https://ieefa.org/resources/projected-\ndata-center-growth-spurs-pjm-capacity-prices-factor-10 (“Kunkel, Projected Data Center \nGrowth”)."},{"page":14,"startToken":3695,"endToken":3997,"text":"10 \ncustomers increased by $23 billion as a result of data center demand in the 2025/2026, \n2026/2027, and 2027/2028 BRAs.42 \nPJM’s increased capacity costs are raising ratepayers’ bills. In June 2025, Pepco \ncustomers in Washington, D.C. saw their bills increase by $21 per month, and D.C.’s Office of \nConsumers’ Counsel attributed about half of that increase to the spike in capacity market \nprices.43 Similar trends are expected across PJM. In June 2026, PJM customers collectively \nbegan paying an additional $1.4 billion in capacity market costs driven by data center demand.44 \nThe increase in PJM’s capacity market prices has sparked concern from the White House, \nthe 13 PJM states, the PJM board, residential ratepayers,45 and from data center companies \nthemselves. On January 15, 2026, the White House’s National Energy Dominance Council and \nthe governors of the PJM states signed a joint Statement of Principles Regarding PJM, urging \nPJM to hold a Reliability Backstop Auction to procure new capacity resources for data centers \nand allocate the costs of that new capacity to LSEs with new data centers that have not procured \ntheir own new capacity.46 Similarly, on January 16, 2026, the PJM board released a board \ndecisional letter that directed PJM staff to develop several proposals to address reliability and \n \n42 Monitoring Analytics, Analysis of the 2027/2028 RPM Base Residual Auction Part A, 3 (Jan. \n5, 2026), \nhttps://www.monitoringanalytics.com/reports/Reports/2026/IMM_Analysis_of_the_20272028_R\nPM_Base_Residual_Auction_Part_A_20260105.pdf. \n43 Kunkel, Projected Data Center Growth, supra note 41. \n44 Id. \n45 Including members of the PIOs. \n46 Statement from the White House Nat’l Energy Dominance Council & PJM Governors of \nPrinciples Regarding PJM (Jan. 15, 2026), https://www.energy.gov/documents/statement-\nprinciples-regarding-pjm."},{"page":15,"startToken":3997,"endToken":4302,"text":"11 \naffordability challenges caused by large load additions in PJM.47 Like the White House and PJM \nGovernors’ Statement of Principles, PJM’s board urged PJM staff to initiate a process to enable \ncurtailment of large loads that do not bring their own new capacity or participate in a reliability \nbackstop auction.48 \nThe largest AI data center companies and developers in the country signed the White \nHouse’s Ratepayer Protection Pledge—introduced on March 4, 2026, and expanded in July—a \nvoluntary commitment from data center owners to build, bring, or buy the new generation \nresources needed to satisfy their new energy demands and pay the full cost of those resources.49 \nFrom April through June 2026, PJM held meetings through the Critical Issue Fast Path – \nReliability Backstop Procurement / Connect & Manage process. The work products associated \nwith that process include both the IRAS Filing and the RBP Filing.50 These filings constitute \nmajor components of PJM’s effort to comply with the Board’s directive in the January 16 letter. \nII. \nThe Commission should accept PJM’s Interim Resource Adequacy Service and \nLarge Load Registry with modifications to better achieve the IRAS’s objectives. \nFor the reasons detailed below, PIOs generally support PJM’s Interim Resource \nAdequacy Service and Large Load Registry proposal. But PIOs urge the Commission to exercise \nits authority to modify the proposal to better accomplish PJM’s objectives to: (1) promote \nreliability by requiring new large loads to be curtailable until they bring new capacity to meet \n \n47 Letter from David E. Mills, Chair, PJM Board of Managers, to PJM Stakeholders on Critical \nIssue Fast Path – Large Load additions (Jan. 16, 2026), https://www.pjm.com/-\n/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-\nresults-of-the-cifp-process-large-load-additions.pdf. \n48 Id. \n49 White House Ratepayer Protection Pledge, supra note 11. \n50 See IRAS Filing, supra note 2; RBP Filing, supra note 33."},{"page":16,"startToken":4302,"endToken":4609,"text":"12 \ntheir needs; (2) promote affordability by requiring new large loads to pay for their own new \ncapacity and avoid shifting costs to residential and other existing ratepayers; and (3) provide \nstates and LSEs with sufficient information to ensure that it is new large loads and not existing \ncustomers are who curtailed when new large loads fail to BYONC and/or charged for capacity \nused to serve new large loads.  \nSpecifically, the Commission should accept PJM’s proposal, but only on the conditions \nthat PJM make the following modifications: (1) ensure IRAS and BYONC requirements are \npermanent for all new large loads regardless of PJM’s resource adequacy status or else require \nthat PJM always include New Large Loads in the Reliability Requirement when determining \nwhether the IRAS program may go to sleep; (2) require PJM to create a penalty applied to LSEs \nthat fail to curtail when PJM makes an IRAS curtailment request; (3) either eliminate the \ncompensation for IRAS resource curtailment or require PJM to cap the compensation awarded to \nIRAS loads at no more than the amount the new large load paid in capacity charges for the \nrelevant delivery year; and (4) require PJM to only allow new large loads to BYONC with \nsupply resources located in a zone that is not constrained with regard to the zone in which the \nnew large load resides. \nDISCUSSION \n \nI. \nThe IRAS Framework is just and reasonable and not unduly discriminatory. \nOverall, the IRAS proposal presents a just and reasonable approach to protect reliability \nand fairly allocate costs among PJM customers and zones. Without the IRAS proposal, PJM \ncustomers will be doomed to bear ever-rising costs and degrading reliability as large loads \nconsistently outpace new supply. This reality warrants new rules. The IRAS framework is an \nessential course-correction that will help rectify years of public subsidization of large load"},{"page":17,"startToken":4609,"endToken":4893,"text":"13 \ncapacity costs, protect customers from emerging reliability risks, and respect jurisdictional \nboundaries. While we propose narrow but important modifications to make IRAS more effective, \nPIOs strongly support the overarching IRAS framework.  \nAs described above, the IRAS Filing has distinct components which all must operate \ntogether to form a comprehensive solution. PJM proposed to establish a Large Load Registry, \nrequire LSEs to ensure that New Large Loads BYONC, implement IRAS load reduction requests \nprior to Pre-Emergency Load Management Response, and remove New Large Loads that do not \nBYONC from the VRR Curve in the capacity auction. These comments will refer to New Large \nLoads that do not BYONC as “unmatched large load.” The interplay between these components \nis essential to the function of the IRAS proposal. Together, these components can be referred to \nas the “IRAS Framework.” \nThe IRAS Framework is not unduly discriminatory because it recognizes that large load \ncustomers are differently situated from other customers due to their outsized impacts on other \ncustomers’ costs, resource adequacy, and reliability risks. Similarly, the IRAS Framework is \njurisdictionally sound because it respects the roles of PJM, states, end-use customers, and \nElectric Distributors (“EDs”) outlined in the Federal Power Act. Finally, the IRAS Framework \nensures just and reasonable rates by removing unmatched large loads from the capacity auction, \nensuring that new large loads are responsible for their own capacity costs. \nA. \nLarge load customers are differently situated from other customers. \nLarge load customers are differently situated than traditional residential and commercial \ncustomers and warrant new rules and obligations. The IRAS Filing correctly recognizes this \ndistinction and applies new responsibilities to large loads, through their EDs, that will protect \nother customers from unjust costs and reliability risks."},{"page":18,"startToken":4893,"endToken":5227,"text":"14 \nLarge loads are unlike other customers. Traditional residential and commercial loads \ngrow slowly and predictably over decades, but large loads grow rapidly and unpredictably, with \nmassive, hyper-concentrated impacts on the electricity system. Large loads are also distinct from \norganic load growth because the pace of large load development is significantly faster than the \nconstruction timeline of new supply. Slower and more diffuse organic load growth is easier to \nsatisfy under current generation development timelines, whereas large loads that can come online \nmuch more quickly than new power plants cause distinct challenges for reliability and \naffordability throughout the PJM region. Indeed, this distinct load growth pattern has already led \nto significant documented impacts on costs and reliability. First, large loads have driven capacity \nand energy market price spikes and shifted costs to other customers. As the PJM Independent \nMarket Monitor (“IMM”) recently remarked, “[l]arge data center load additions have already had \na significant and irreversible impact on PJM customers that will be paid through May 31, 2029, \nand will have additional significant impacts on other customers as a result of higher transmission \ncosts, higher energy market prices and higher capacity market prices.”51 Two years ago, PJM’s \n2025/2026 Base Residual Auction cleared at a (then) record high of $269.92/MW-day, raising the \ntotal regional capacity bill from $2.2 billion to $14.7 billion. Since then, three additional auctions \nhave cleared at the administrative cap, resulting in roughly $63.6 billion total in bills paid by all \ncustomers in PJM through 2029.52 Similarly, energy prices have jumped 40.2% since 2025, from \n \n51 Monitoring Analytics, L.L.C., Quarterly State of the Market Report for PJM: January through \nJune (Q2), 2 (Aug. 13, 2026), \nhttps://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2026/2026q2-som-\npjm.pdf (“Monitoring Analytics Q2 Report”). \n52 Ethan Howland, Data Centers Drove $6.3B in PJM Capacity Auction Costs: Market Monitor, \nUtility Dive (July 20, 2026). https://www.utilitydive.com/news/pjm-data-centers-capacity-\nauction-imm-bowring/825626/"},{"page":19,"startToken":5227,"endToken":5501,"text":"15 \n$51.8/MWh to $72.5/MWh. Total wholesale power costs have increased 54% since 2024.53 \nThese higher costs are caused almost exclusively by forecast large loads outpacing new supply.54 \nWhen a single segment of commercial demand leads to multi-billion-dollar regional wholesale \nprice increases, it ceases to be standard incremental load growth and warrants urgent structural \nchanges to PJM’s markets and reliability obligations.  \nSecond, large loads have demonstrated outsized impacts on future resource adequacy and \non real-time reliability which warrant different approaches to electric service as proposed in the \nIRAS Filing. As described in the Background section, PJM has cleared without sufficient \ncapacity to meet the Reliability Requirement in both the 2027/2028 BRA and the 2028/2029 \nBRA due to the pace of large load growth. PJM cleared 6,623 MW and 6,831 MW short, \nrespectively.55 Large loads have degraded reliability from the 1-in-10 year reliability standard to \ncloser to 1-in-3 years. PJM customers face an increased risk of blackouts starting in 2027 due to \nunmitigated large load growth.  \nBeyond these long-term capacity shortfalls, large computational loads introduce real-time \noperational risks to the bulk power system. The North American Electric Reliability Corporation \n(“NERC”) documented that data center facilities pose an unprecedented reliability threat: they \ncan instantly trip over 1,000 MW of power offline simultaneously, without time for RTOs or \n \n53 Monitoring Analytics Q2 Report, supra note 51, at 17, tbl. 1-9.  \n54 Ethan Howland, Data Centers Drove $6.3B in PJM Capacity Auction Costs: Market Monitor, \nUtility Dive (July 20, 2026). https://www.utilitydive.com/news/pjm-data-centers-capacity-\nauction-imm-bowring/825626/ \n55 IRAS Filing, supra note 2, at 14."},{"page":20,"startToken":5501,"endToken":5818,"text":"16 \nutilities to respond, leading to the risk of cascading failures and blackouts.56 This occurred in \nPJM on July 22, when nearly 4,000 MW of data center load tripped offline unexpectedly in \nVirginia and led to cascading actions to restore reliability.57 The IRAS Framework recognizes the \nunique risks that data centers pose to resource adequacy and reliability, and appropriately \nproposes common-sense solutions to maintain reliability and affordability. \nLongstanding precedent supports the distinct treatment of large loads. Under Sections \n205 and 206 of the Federal Power Act, FERC is mandated to ensure that all rules, regulations, \nand practices “affecting” wholesale rates or interstate transmission service are just, reasonable, \nand not unduly discriminatory.58 Large loads are clearly “affecting” wholesale rates, as described \nabove. Moreover, FERC has also already ruled that a tariff’s failure to differentiate large loads \nfrom traditional native loads is a structural deficiency.59 In the IRAS Filing, PJM resolves this \ndeficiency by defining Large Loads, New Large Loads, and Eligible New Large Loads and \nplacing unique requirements on these customers through their EDs and LSEs. Likewise, FERC \naccepted the emergency “price collar” designed to insulate regular ratepayers from the price \ndistortions caused by large loads.60 The IRAS Filing follows on these precedents by removing \n \n56 NERC, Level 3 Essential Action Alert: Computational Load Modeling, Studies, \nInstrumentation, Commissioning, Operations, Protection, and Control (May 4, 2026). \nhttps://www.nerc.com/globalassets/programs/bpsa/alerts/level-3-computational-load-alert.pdf \n57 PJM, Dominion Review Large Load Transfer Event, PJM Inside Lines (Aug. 11, 2026). \nhttps://insidelines.pjm.com/pjm-dominion-review-large-load-transfer-event/ \n58 16 U.S.C. §§ 824d–e. \n59 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at P 58 (June 2026) (finding that “PJM's \nTariff appears to be unjust and unreasonable because it lacks a definition of large load, as a new \ncategory of load”). \n60 PJM Interconnection, L.L.C., 195 FERC ¶ 61,076 (Apr. 2026)."},{"page":21,"startToken":5818,"endToken":6081,"text":"17 \nunmatched large load from future RPM auctions and ensuring that large loads are responsible for \nbringing their own supply. \nMore recent Commission precedent reinforces that the IRAS Filing is not unduly \ndiscriminatory but instead appropriately recognizes how large loads are differently situated from \nnative load. The Commission recently acknowledged the unique effects that large loads are \nhaving on the transmission system and instituted a show cause proceeding directing PJM to \ndevelop specific provisions in its tariff relating to large load interconnection.61 The \nCommission’s Order recognizes that large loads can be more energy intensive and exhibit \ndifferent load profiles, which may make providing transmission service to Eligible Customers on \nbehalf of large loads more complex and raise more reliability concerns for the transmission \nsystem.62 The Commission directed PJM to address several issues regarding the distinct impacts \nof large loads on the transmission system including: (1) the application process, study procedures \nand ongoing operational requirements that apply to large loads; (2) additional transparency \nconcerning transmission costs caused by large loads; (3) new transmission services reflecting the \nability of flexible large loads to limit their use of the transmission system; (4) and rates, terms, \nand conditions of service for electrically proximate of co-located loads.63 The IRAS proposal \naddresses some of the Commission’s concerns around large load interconnection, cost-\ntransparency, and large loads’ unique reliability impacts on the system by proposing a large load \n \n61 Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ \n61,211 (Jun. 18, 2026) \n62 Id. at P 53.  \n63 Id. at P 35."},{"page":22,"startToken":6081,"endToken":6381,"text":"18 \ndefinition, establishing a large load registry, and creating a new capacity product that seeks to \nallow large loads to connect, while maintaining system reliability. \nB. \nIRAS is jurisdictionally sound and respects the roles of states and PJM. \nPJM took care to compose a solution that respects the roles and responsibilities outlined \nin the Federal Power Act.64 Far from encroaching on retail domains, the IRAS Framework is a \nmodel of cooperative federalism that relies on a clear division of labor between PJM, Electric \nDistributors, LSEs, state authorities, and end-use customers. PJM proposes new rules that \ndirectly affect wholesale market prices and grid reliability. Even if those federal rules affect retail \ncustomer behavior, they are legally sound.65 \nThroughout every element of the proposed IRAS Framework, PJM has a specific and \nlimited role with no direct control over retail end-use customers. This is because (a) PJM relies \non aggregate megawatt quantities of load and supply to implement the IRAS Framework, and (b) \nPJM implements IRAS Actions through Electric Distributors, who are in turn regulated by state \nauthorities.  \nFirst, while PJM will track individual end-use customer data and supply arrangements in \nthe Large Load Registry, it will only act based on aggregate megawatt quantities. Electric \ndistributors will be required to track and report data about individual large load customers, but \nPJM will only implement IRAS Actions and add load into RPM using aggregate megawatt \nquantities by zone/area. This balance of tracking at the customer level but acting at the macro \n \n64 See 16 U.S.C. § 824(b)(1) (outlining federal jurisdiction over interstate wholesale transmission \nand sales while explicitly reserving regulation of local distribution facilities, retail sales, and end-\nuse consumption to state commissions). \n65 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 281 (2016) (“EPSA”)."},{"page":23,"startToken":6381,"endToken":6650,"text":"19 \nlevel using aggregate quantities by zone is a key feature that makes PJM’s proposal just and \nreasonable and aligned with FERC precedent.66 By tracking individual large loads and BYONC \narrangements, the Registry helps ensure that EDs allocate interruptions to the correct customers \nduring IRAS Actions. Similarly, the Registry informs PJM as to the proper quantity of load to \nremove from RPM until New Large Loads bring their own new supply. This careful design \nrespects jurisdictional boundaries while also protecting other customers and overall system \nreliability. \nSecond, PJM will respect jurisdictional boundaries by directing IRAS Actions at the \nwholesale level. PJM will never curtail individual retail customers—instead, it uses the Registry \nand results from the most recent BRA to designate megawatt quantities of IRAS curtailment by \nzone.67 It will be up to the Electric Distributor, overseen by state regulators, to allocate IRAS \ncurtailments among end-use customers. This clear delineation between PJM and state-regulated \nentities complies with the findings of the Supreme Court, which affirmed that wholesale grid \nmanagement rules are fully lawful when they target aggregate wholesale metrics and leave \nindividual retail consumer implementation and retail cost allocation to the states.68 Here, the \nLarge Load Registry again protects against unintended consequences: by using actual data from \nlarge loads and BYONC to inform IRAS quantities, but then directing aggregate curtailment \nquantities by zone, PJM provides EDs with all the information necessary to ensure that \ncurtailments go to the correct customers without encroaching on state authorities. \n \n66 IRAS Filing, supra note 2, at 45–48. \n67 Id. at 40. \n68 EPSA, 577 U.S. at 279–81."},{"page":24,"startToken":6650,"endToken":6944,"text":"20 \nThese design elements ensure that the IRAS Framework respects jurisdictional roles and \nis a just and reasonable approach to maintaining resource adequacy and protecting other \ncustomers. \nC. \nRemoving New Large Loads from RPM is just, reasonable, and not unduly \ndiscriminatory. \n \nRemoving New Large Loads that do not BYONC from the VRR Curve in RPM is the \nlynchpin of the IRAS filing and is essential to comply with cost-causation principles.69 This \nprovision is an urgent course-correction after three consecutive auctions that resulted in \ndegrading reliability margins and massive public subsidies for power needed to serve large loads. \nThe IRAS Framework does not undermine market fundamentals; rather, it correctly recognizes \nthat one single customer class is driving unjust and unreasonable outcomes, and suggests fair \nchanges to preserve competitive results for all ratepayers in PJM. Similarly, the provision does \nnot block market access for large load customers—it simply clarifies commercial conditions. It is \nclear beyond reasonable doubt that, without this solution, the trend of high clearing prices, cross-\nsubsidization, and degrading reliability would continue for the foreseeable future.  \nRemoving new large loads that do not BYONC from the VRR Curve observes principles \nof cost causation because it prevents the RPM from forcing other ratepayers to subsidize  \ncapacity on behalf of new large loads. As described in the previous section, large loads have \nincreased the clearing price for the last three consecutive capacity auctions as they outpace new \nsupply. These clearing prices are spread across all customers and resulted in significantly higher \nutility bills for residential and commercial customers.70 Leaving unmatched large loads in the \n \n69 See e.g., Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004). \n70 See Kunkel, Projected Data Center Growth, supra note 41."},{"page":25,"startToken":6944,"endToken":7227,"text":"21 \nVRR Curve allows them to act as “free riders”—gambling on the broader system’s existing \ncapacity safety cushion while forcing traditional public ratepayers to fund ever-higher clearing \nprices. This treatment flies in the face of legal precedent for cost-causation. The D.C. Circuit has \nacknowledged FERC’s statutory mandate to ensure that costs are reasonably allocated to \ncustomers in light of the benefits they receive from the PJM system.71 Similarly, the Seventh \nCircuit established that regional grid operators cannot approve market designs that force one \nsegment of ratepayers to subsidize infrastructure expansions for another without a clear, \nempirical showing of proportionate benefit, which, in this case, other customers are not \nreceiving.72 \nSimilarly, PJM’s proposed VRR Curve adjustment does not undermine market \nfundamentals. Instead, it counteracts a deep market distortion. Including massive blocks of \ndemand that connect faster than supply can be built creates a price spike that hands windfall \nrevenues to existing generators without actually stimulating new supply. Prices will not be \nartificially suppressed, nor will development be stymied, by this adjustment. On the contrary: \nthere has never been a more lucrative investment environment for new capacity developers than \nthe rapid influx of power-hungry large loads. PJM’s accompanying BYONC framework and \nRBP will open new doors for rapid commercial arrangements all while ensuring power costs are \npaid by large loads, not other customers. The removal of unmatched new large loads from RPM \ndoes not limit their opportunities to secure supply—it simply ensures that the rest of PJM is no \nlonger paying for that supply.  \n \n71 Midwest ISO Transmission Owners v. FERC, 373 F.3d at 1371. \n72 Ill. Comm. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009)."},{"page":26,"startToken":7227,"endToken":7500,"text":"22 \nLikewise, the VRR Curve modification does not permanently bar large loads from joining \nPJM or from participating in the capacity market. It simply allows New Large Loads to join \nRPM once they BYONC. If a New Large Load fulfills its public commitments under the \nRatepayer Protection Pledge through BYONC or securing supply from the RBP, its megawatt \ndemand is added back to the VRR Curve. Requiring proof that a New Large Load has BYONC \nbefore adding the load back into the capacity market is not undue discrimination. The D.C. \nCircuit found that when customers are not similarly situated, it is not unduly discriminatory to \nestablish different conditions based on a customer’s unique impact on the system.73 Here, large \nloads and other customers are not similarly situated for all the reasons described above, including \nlarge loads’ distinct load growth pattern and extreme impacts on prices and reliability. The clear \ndistinctions between large loads and other customers provide an ample basis for the Commission \nto find that they are not similarly situated and that the IRAS Framework is not unduly \ndiscriminatory. PJM maintains that it will still provide electric service for all customers, with the \nunderstanding that New Large Loads that do not BYONC may be subject to interruptions during \ngrid emergencies if PJM does not have sufficient capacity. In other words, while unmatched large \nloads are excluded from PJM’s capacity procurement, they are otherwise allowed to join PJM \nand become operational without requiring any new capacity, so long as they accept occasional \ninterruptions.  \n \n \n \n \n73 Transmission Agency of N. Cal. v. FERC, 628 F.3d 538, 549–50 (D.C. Cir. 2010)."},{"page":27,"startToken":7500,"endToken":7796,"text":"23 \nII. \nThe Commission Should Only Modify PJM’s IRAS Filing to Better Accomplish \nPJM’s Objectives. \n \nPJM has consented to Commission modification of “any element” of its proposal, so long \nas the modification “is consistent with PJM’s overarching objectives” in the IRAS Filing.74 That \nconsent is bounded by the decision in NRG Power Marketing L.L.C. v. FERC to not permit \nmodifications that would produce “an entirely different rate design.”75 PJM’s objectives set the \nlimits of what modifications the Commission can require. PJM summarizes the filing as a “multi-\nprong approach to incent New large Loads to bring their own capacity to meet their resource \nadequacy needs and avoid imposing costs on ratepayers.”76 However, the IRAS Filing does not \ninclude any explicit statement of PJM’s objectives. To assist the Commission’s consideration of \nmodifications to PJM’s filing, PIO’s explain that the text and context of PJM’s filing reveal the \nfollowing three objectives. \nFirst, require new large loads to be curtailable until they bring new capacity to meet their \nneeds. PJM describes the “foundation” of IRAS as the rule that large loads (through their LSEs) \nmust bring new capacity in an amount equal to or greater than their contribution to peak demand, \nor else the load may be reduced during emergency conditions.77 \n \nSecond, promote affordability by requiring large loads to pay for their own new capacity, \navoiding cost shifts to residential and other existing ratepayers. PJM quotes the Ratepayer \nProtection Pledge’s commitment that large loads will “build, bring, or buy” the resources their \n \n74 IRAS Filing, supra note 2, at 9, 122. \n75 NRG Power Mtkg. L.L.C. v. FERC, 862 F.3d 108, 115–16 (D.C. Cir. 2017). \n76 IRAS Filing, supra note 2, at 124. \n77 Id. at 3–4."},{"page":28,"startToken":7796,"endToken":8084,"text":"24 \ndemand requires, and repeatedly explains that the rest of PJM’s load should not bear the resulting \ncapacity-price effects.78 \n \nThird, provide states and LSEs sufficient information to ensure that large loads are \ncurtailed when those loads have not brought sufficient new capacity and are charged for capacity \nused to serve them. The proposal assigns specific retail curtailment and retail cost allocation to \nstate-regulated actors, and it uses the Large Load Registry as the repository of information \nsufficient for those making those decisions.79 \nPIOs respectfully recommend that the Commission adopt this articulation of the IRAS’s \nobjectives and use those objectives when requiring modification to the IRAS. \n \nA. \nObjective One: Promote Reliability by Requiring New Large Loads to be \nCurtailable Until They Bring New Capacity to Meet Their Needs. \n \nThe first objective responds to a specific reliability problem caused by data centers. \nPJM’s recent capacity auctions have cleared thousands of megawatts short of the regional \nreliability requirement because new large loads—principally data centers—are arriving faster \nthan new generation and transmission can be built. PJM’s operations witness explains that this \nmismatch threatens PJM’s ability to both serve existing customers and to maintain required \nreserves during periods of peak demand or significant outages.80 \n \nIRAS addresses that mismatch by offering a deal to new large loads: receive electric \nservice now but accept that the service is not firm. A new large load may interconnect before \nsufficient new capacity is in place, but the unmatched load must remain available for reduction \n \n78 Id. at 4–5. \n79 Id. at 5–7. \n80 Id. at 13–15, 21; see also id. at Attach. C, Affidavit of Christopher Pilong on Behalf of PJM \nInterconnection, L.L.C. at ¶ 19 (“Pilong Aff.”)."},{"page":29,"startToken":8084,"endToken":8365,"text":"25 \nduring defined reliability conditions. PJM expressly analogizes the proposal to service that \nremains “subject to curtailment and interruption” until sufficient capacity resources are in place. \nPJM characterizes IRAS as permitting interconnection without new capacity on the condition \nthat the load “must reduce” or switch to on-site backup resources during some emergencies.81 \nCurtailability is therefore not simply an implementation decision of the IRAS proposal. It is the \nconsideration the new large load provides for receiving the benefit of receiving electric service \nbefore it has supplied the capacity needed to receive firm service without disrupting existing \ncustomers. \n \nThat deal for service in exchange for curtailability protects residential and other existing \ncustomers. PJM calls IRAS a tool for managing resource-adequacy shortfalls “that would \notherwise drive shedding of native loads,” and places an IRAS Action before Pre-Emergency \nLoad Management Reductions.82 A design that did not include curtailability would wholly fail to \nsolve the reliability problem that is the foundation of the IRAS Filing. \n \nThe IRAS Filing ties the amount of a new large load’s curtailment exposure to the \namount of new capacity it brings to the system. The amount that PJM can call for the curtailment \nof a new large load is reduced by the new capacity it brings to the system, and a load ceases to be \neligible for curtailment only once enough capacity exists to meet its peak demand needs.83 PJM \ninsists that qualifying BYONC be genuinely new, obtain capacity commitments, and remain \n“real and last,” rather than merely relying on repackaging capacity already on the system.84 Each \n \n81 Id. at 4, 39, 49–50. \n82 Id. at 22.  \n83 Id. at 69. \n84 Id. at 52–58."},{"page":30,"startToken":8365,"endToken":8660,"text":"26 \nincrement of unmatched demand remains curtailable unless and until a corresponding increment \nof qualifying new capacity is available to meet it. \n \nIn evaluating the IRAS and any modifications proposed in this protest and by other \nparties, the Commission should ensure that the IRAS require that new large loads that do not \nbring their own new capacity be curtailed until they have brought enough capacity to cover their \nneeds. A modification that improves the correspondence between curtailability and BYONC, like \nthe modifications described below, advances this objective and falls squarely within PJM’s \nconsent. \nB. \nObjective Two: Promote Affordability by Requiring New Large Loads to Pay \nfor Their Own New Capacity and Avoid Shifting Costs to Residential and \nOther Existing Ratepayers. \n \nThe second objective comes out of the same issues that create the need for the first \nobjective. New large loads create incremental capacity needs that would otherwise not exist. \nCost-causation principles require a rate to compare the costs imposed on a customer with the \nburdens that customer creates or the benefits it receives.85 Here, the new capacity is needed \nprecisely because of the new large load’s demand, so the new large load should bear the cost of \nadding that capacity to the PJM system. \nThe IRAS Filing quotes the commitment that new large loads will pay the “full cost” of \nthe new resources their demand requires because doing so “protects Americans from higher \nprices.”86 PJM explains that unmatched New Large Loads would be excluded from the capacity-\nmarket demand curve because “[t]he rest of PJM’s load should not be exposed to the price \n \n85 See e.g., Midwest ISO Transmission Owners v. FERC, 373 F.3d at 1368. \n86 IRAS Filing, supra note 2, at 5 (quoting White House Ratepayer Protection Pledge)."},{"page":31,"startToken":8660,"endToken":8928,"text":"27 \nimpacts” of procuring new capacity for them.87 PJM also states that the IRAS Filing’s \ninterlocking components are designed to induce new large loads to meet their capacity needs \nwhile “avoid[ing] imposing costs on [other] ratepayers.”88 \n \nThe BYONC and demand-curve provisions are specifically designed to ensure new large \nloads bear their costs. When a New Large Load brings qualifying new capacity, PJM adds the \nload to the demand curve in the same auction in which the associated BYONC enters the supply \nstack as a $0/MW-day price taker.89 PJM describes this as a “symmetrical, one-for-one addition” \nthat is “effectively price-neutral” for the rest of the market.90 PJM explains that if BYONC could \nwithdraw while the associated load remained in the demand curve, responsibility for that load’s \ncapacity would be transferred to PJM and “shared with other PJM loads, contrary to the purpose \nof the IRAS scheme.”91 Conversely, when a new large load has not BYONC, excluding it from \nthe demand curve prevents the RPM from buying capacity for that load and spreading the price \neffects across existing customers. \nIn evaluating the IRAS and any modifications proposed in this protest and by other \nparties, the Commission should ensure that the IRAS does not impose the costs created by new \nlarge loads on residential and other existing customers. A modification that prevents costs created \nby new large loads from being imposed on existing ratepayers advances this objective and falls \nsquarely within PJM’s consent. \n \n \n \n87 Id. at 23. \n88 Id. at 124. \n89 Id. at 55–56. \n90 Id. at 58. \n91 Id. at 56."},{"page":32,"startToken":8928,"endToken":9228,"text":"28 \nC. \nObjective Three: Provide States and LSEs With Sufficient Information to \nEnsure the Right Loads are Curtailed and Charged. \n \nThe third objective is necessary because PJM recognizes its lack of authority to regulate \nat the retail level.92 PJM determines the aggregate MW quantity of IRAS needed in an electric \ndistributer’s (“ED”) zone or area.93 PJM then leaves “retail load reduction plans and retail cost \nallocation to state-level entities,” and assigns EDs, acting in coordination with states, LSEs, and \ncustomers, the task of choosing which retail loads will be curtailed.94 PJM’s operations witness \nexplains that PJM “will not direct specific New Large Loads to reduce load even though Electric \nDistributors . . . may issue more specific directives to specific retail customers.”95 \nThat division of authority makes it imperative that PJM provide a mechanism that \nensures the right customers are curtailed and charged. A state, ED, or LSE cannot implement the \nfirst objectives of the IRAS Filing without unless it can identify each new large load, determine \nthe portion of its demand that remains uncovered by new capacity, and match a reduction \ndirective by PJM to that load rather than to residential, small-business, or other existing \ncustomers. Nor can a state implement the second objective of the IRAS Filing unless it can \ndetermine which new large load received or was credited with capacity and assign the \ncorresponding retail cost to that customer. \nPJM itself recognizes the need to provide such information. It says the Large Load \nRegistry will facilitate “transparent implementation of IRAS” and help states monitor whether \ndata centers and other large loads are honoring their commitment to provide for their own \n \n92 Id. at 3. \n93 Id. at 6. \n94 Id. at 3. \n95 Id. at Pilong Aff. ¶ 52; see also id. at 82 nn. 220–21."},{"page":33,"startToken":9228,"endToken":9496,"text":"29 \nneeds.96 PJM also relies on stakeholder comments explaining that a registry is needed “to ensure \ncosts and curtailments are assigned appropriately,” because without one it is unclear how \nexisting consumers could be protected from either capacity costs or curtailment.97 \nThe required information must therefore be sufficiently detailed. PJM proposes that the \nregistry identify, among other things, each load’s customer and location, in-service date, peak \nload quantity, BYONC quantity, Allocated RBP UCAP MW, backup generation quantity, and \nrelevant utility contracts.98 PJM also emphasizes that the registry must be “accurate, complete, \nand reliable,” because it will determine the MW quantity of new large loads subject to IRAS.99 \n \nIn evaluating the IRAS and any modifications proposed in this protest and by other \nparties, the Commission should ensure that PJM provide states, EDs, LSEs, and any other \nrelevant state actor with sufficient information to identify which large loads must curtail and how \nretail costs should be allocated. A modification that is necessary for the collection and \ndissemination of sufficient information needed to complete the other objectives of the IRAS \nFiling advances this objective and falls squarely within PJM’s consent. \nTaken together, these three objectives state what PJM designed IRAS to do: preserve \nreliability by allowing the curtailment of new large loads without BYONC, ensure that new data \ncenters and other large loads pay their own way, and provide enough information to ensure that \nthe right loads are curtailed and pay their share. The Commission should evaluate each proposed \n \n96 Id. at 28. \n97 Id. at 30 n.85. \n98 Id. at 37. \n99 Id. at 43–44."},{"page":34,"startToken":9496,"endToken":9872,"text":"30 \nmodification to the IRAS Filing against these objectives and should adopt PIOs’ modifications \ndescribed below, which will help ensure that the IRAS Filing achieves these objectives.  \nIII. \nModification 1: The Commission must ensure that the IRAS filing effectively \nremoves new large loads from the capacity market until associated new capacity is \nonline and deliverable. \n \nPJM proposes to suspend the entire IRAS Framework if the PJM capacity auction meets \nthe Reliability Requirement—not including large loads subject to IRAS—for three consecutive \ndelivery years, but this proposal risks creating a volatile market that traps prices at the cap and \ninvites gaming by large load customers. If this risk occurs, PJM will treat all customers the same: \nthere will be no differentiation between large loads and other customers; no customers will have \nan obligation to demonstrate BYONC; there will be no IRAS load; and all load will be included \nin the demand curve for the capacity auction.100 In fact, even the definition of New Large Load \nand BYONC—the foundation of the IRAS Framework—will be ineffective as long as the IRAS \nFramework is suspended.101 PJM also proposed to turn the IRAS Framework back “on” in the \nevent that a delivery year once again fails to meet the Reliability Requirement. \nWhile this may seem like an innocent provision which accounts for the fact that IRAS \ncurtailments are not needed during periods of resource adequacy, suspending the entire IRAS \n \n100 Id. at 52.  \n101 Id. at 39–40. The proposed definition of New Large Load includes the following \nspecification:  \n[T]o the extent three consecutive Delivery Years meet the requirements of Tariff, \nAttachment DD-4, section IV(b)(iii), then New Large Load shall mean end-use customer \nload that is either (a) a Large Load that goes into service after June 1 of the first Delivery \nYear for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not \nmet or (b) incremental load in-service after June 1 of the first Delivery Year for which the \nrequirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met that increases the \nexisting end-use customer load at a single electrical site that, prior to such incremental \nload, did not previously meet the definition of Large Load."},{"page":35,"startToken":9872,"endToken":10214,"text":"31 \nFramework is logically flawed and raises the risk that the capacity market will be permanently \npinned at the price cap. To resolve this, the Commission should direct PJM to either (1) ensure \nthe IRAS Framework, including BYONC requirements, is permanent for all New Large Loads, \nor else (2) ensure that the trigger for the IRAS program becoming inactive is the capacity market \nclearing for three consecutive years with sufficient supply to meet all demand including all large \nloads subject to IRAS.  \nA. \nSuspending the IRAS Framework during periods of resource adequacy risks \npinning prices at the cap. \n \nPJM will take the following steps when putting the IRAS Framework to “sleep” which, \ntogether, create economic hazards and incentivize gaming: \n1. PJM’s definition for New Large Load and associated obligations will not apply to any \ncustomer;102 \n2. PJM’s definition for BYONC and associated obligations will not apply to any \ncapacity;103  \n \n102 Id. at Attach. B, Revisions to the PJM Open Access Transmission Tariff and Resource \nAdequacy Agreement (Clean Format), at pdf 323 (“Proposed Tariff”) (see Definition of New \nLarge Load). Specifically: \nHowever, to the extent three consecutive Delivery Years meet the requirements of Tariff, \nAttachment DD-4, section IV(b)(iii), then New Large Load shall mean end-use customer \nload that is either (a) a Large Load that goes into service after June 1 of the first Delivery \nYear for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not \nmet or (b) incremental load in-service after June 1 of the first Delivery Year for which the \nrequirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met that increases the \nexisting end-use customer load at a single electrical site that, prior to such incremental \nload, did not previously meet the definition of Large Load. \n103 Id. at Proposed Tariff, pdf 287 (see Definition of “Bring Your Own New Capacity”). \nSpecifically:  \nHowever, to the extent three consecutive Delivery Years meet the requirements of Tariff, \nAttachment DD-4, section IV(b)(iii), then BYONC that has been included previously in"},{"page":36,"startToken":10214,"endToken":10586,"text":"32 \n3. All load is added back into the VRR Curve and Reliability Requirement;104 and \n4. No IRAS Actions will be called.105 \nThere are two problems that emerge from these steps. First, they create a perverse \nincentive for large loads not to fully BYONC. Second, the IRAS Framework could be suspended \nwhen PJM is not truly resource adequate, given the fact that New Large Loads that have not fully \nBYONC-ed will be excluded from the Reliability Requirement used to determine if PJM clears \nwith adequate supply for three consecutive delivery years. Put another way, PJM will suspend \nthe IRAS Framework without ensuring that all large loads BYONC—or even that there is \nadequate capacity on the system to satisfy the needs of all IRAS resources. When this unmatched \nlarge load is added back into the VRR Curve, PJM may clear at or below the Reliability \nRequirement. Together, these two risks effectively guarantee that prices will clear at or near the \ncap for the foreseeable future. PJM’s market will become volatile and binary, with obligations on \nNew Large Loads, LSEs, and new capacity resources changing every year as PJM flips the IRAS \nFramework “on” and “off.” That outcome—a volatile market that creates unpredictable \n \nan FRR Capacity Plan prior to the first Delivery Year for which the requirements of \nTariff, Attachment DD-4, section IV(b)(iii) are not met and (2) meet the eligibility criteria \nset forth in Tariff, Attachment DD-4, section VI do not qualify as BYONC. \n104 Id. at Proposed Tariff, pdf 293 (see Definitions E–F, Definition of “Excluded LDA New Large \nLoad Amounts” and “Excluded RTO New Large Load Amounts”). The quantity of load that PJM \nwill remove from the VRR Curve and the Reliability Requirement—rely on the definition of \nNew Large Load, which will not apply to any customer in the event that PJM clears with \nsufficient capacity for three consecutive delivery years. In other words, PJM will not exclude any \nload from the Reliability Requirement or VRR Curve during periods of resource adequacy, \nregardless of if a New Large Load has actually offset load with qualified BYONC. \n105 Id. at Proposed Tariff, pdf 306 (see Definitions I-K, Definition of “Interim Resource \nAdequacy Service Action”)."},{"page":37,"startToken":10586,"endToken":10886,"text":"33 \nperformance obligations for large loads and risks shifting costs from large loads back to \nconsumers—would be unjust and unreasonable.106 \nPJM is currently operating under a negotiated price cap of $325/MW-day, but this cap \nwill expire after the 2029/2030 delivery year, and the subsequent cap will be around $550/MW-\nday. This means residential utility bills could increase significantly under PJM’s proposal. \ni. \nSuspending the IRAS Framework will reduce the incentive for New Large \nLoads to fully BYONC, raising costs for other customers. \n \nIf PJM suspends the IRAS Framework, New Large Loads that fail to BYONC are \n“forgiven” and re-integrated into the VRR Curve. This allows them to bypass both the BYONC \nrequirement and IRAS curtailments simply by waiting. Rather than fully offsetting their footprint \nwith new supply, these large loads can gamble on using broader system capacity without paying \nfor it. This creates a perverse incentive for large loads to not BYONC. \nIf the auction clears short again, PJM will reactivate the IRAS framework. However, the \ndefinition of a New Large Load will reset. Consequently, no penalties or retroactive requirements \nwill apply to the large loads that successfully entered the prior auction empty-handed. This \nloophole creates a permanent, perverse incentive to avoid BYONC, keeping the market on the \nrazor’s edge of resource adequacy. As the IRAS framework repeatedly triggers “on” and “off” \nyear after year, capacity prices will persistently clear at the cap, harming regular ratepayers. \nAdditionally, by incorporating large loads that failed to BYONC back into the capacity market, \n \n106 See, e.g., PJM Interconnection, L.L.C., 117 FERC 61,331, at P 48 (2006) (approving the \nsettlement establishing the basic structure of the current capacity market based on ”a substantial \nrecord showing that the [previously] existing capacity market leads to volatile prices”)."},{"page":38,"startToken":10886,"endToken":11191,"text":"34 \nPJM risks forcing other ratepayers to fund the price signals to procure capacity for those new \nlarge loads—counter to the IRAS Filing’s stated goals.  \nii. \nSuspending the IRAS Framework based on the lower Reliability \nRequirement which excludes New Large Loads that have not \ndemonstrated BYONC is not an appropriate trigger. \n \nPJM’s proposal to remove New Large Loads from the VRR Curve and the Reliability \nRequirement is an appropriate way to shield other consumers from bearing the costs of capacity \nto serve New Large Loads. PIOs support this essential step. However, because PJM proposes to \nremove New Large Loads from the VRR Curve and the Reliability Requirement, the capacity \nmarket merely satisfying that lowered Reliability Requirement is not an appropriate trigger for \nsuspending the IRAS Framework. This approach risks suspending IRAS and BYONC \nrequirements when they are still needed, shifting costs to other customers, and pegging prices at \nthe cap.  \nThe moment the IRAS framework is put to sleep, those very same New Large Loads that \ndid not BYONC, which were excluded to lower the target, will be dumped back into the market. \nAdding this unmatched demand back into the auction without corresponding supply pushes \ncapacity prices ever upward toward the cap, forcing existing customers to fund the necessary \nnew generation through inflated clearing prices—effectively subsidizing private growth at public \nexpense. This flood of unmatched New Large Loads risks re-triggering the IRAS Framework \nback “on” if PJM clears short, and the cycle starts again. \nB. \nPJM’s proposal to toggle IRAS on and off creates regulatory uncertainty and \nwhiplash for market participants.  \n \nLarge loads have a demonstrated, outsized impact on reliability and costs. These impacts \nhold true regardless of PJM’s resource adequacy situation. The entire premise of the IRAS \nFramework is hinged upon the fact that large loads are differently situated from other customers,"},{"page":39,"startToken":11191,"endToken":11489,"text":"35 \nand PJM needs new rules and procedures—while respecting jurisdictional boundaries—to \nmaintain reliability and uphold just and reasonable rates. Halting the entire IRAS Framework, \nincluding BYONC obligations for New Large Loads, and adding all New Large Loads back into \nthe VRR Curve during periods of resource adequacy is logically inconsistent with the intent of \nthis Filing and goes against FERC’s finding in its Show Cause Order that the impacts of large \nloads require permanent changes to PJM’s rules.  \nChanging the obligations for EDs during periods of scarcity and surplus is also illogical \nand confusing. When the IRAS Framework is active, EDs have many obligations and \nresponsibilities: tracking and reporting New Large Loads and associated BYONC for the Large \nLoad Registry and for the RPM Planning Parameters, verifying IRAS quantities, and of course \nactually implementing IRAS curtailments, to name a few. EDs may have additional obligations \nplaced on them by state regulators to, for example, allocate IRAS curtailments to specific end-\nuse customers. When the IRAS Framework is suspended, all of these responsibilities go away. \nBut, as soon as the Framework is re-instated, EDs are once again required to fully implement \nIRAS. EDs are the fascia of the IRAS Framework: without their cooperation, the proposal falls \napart. This proposal promises persistent whiplash for EDs, eroding trust and leading to confusion \nthat could materially harm other customers or even large load customers themselves.  \nAdditionally, changing the obligations for new capacity resources creates cost risks. PJM \nrequires BYONC to meet certain criteria107 and to offer into RPM at a bid of $0 for at least 10 \ndelivery years. But, when PJM suspends the IRAS Framework, all of these obligations are \n \n107 IRAS Filing, supra note 2, at Proposed Tariff, pdf 376, Section VI: Bring Your Own New \nCapacity Criteria."},{"page":40,"startToken":11489,"endToken":11787,"text":"36 \nremoved for existing and new BYONC. That means that existing BYONC paid for by large loads \ncan begin bidding higher costs into the capacity auction, potentially driving prices up for all \ncustomers.  \nC. \nThe Commission should modify PJM’s IRAS Filing to make the IRAS \nFramework Permanent or correct the Reliability Requirement Trigger. \n \nTo resolve the issues identified above, the Commission should direct PJM to either (1) \nensure the IRAS Framework, including BYONC requirements, is permanent for all New Large \nLoads regardless of PJM’s resource adequacy status, or else (2) ensure that the trigger for IRAS \nbeing turned off is the capacity market clearing for three consecutive years with sufficient supply \nto meet all demand including large loads subject to IRAS.  \nThe simplest fix would be to ensure the IRAS Framework is permanent. This would \nentail removing the provision to suspend the IRAS Framework after three consecutive delivery \nyears of sufficient supply. It would also entail changing the definitions of New Large Load and \nBYONC to ensure there is no “carve out” for periods when PJM is resource adequate.108 New \nLarge Loads will maintain the same definition regardless of PJM’s capacity status, and will be \nrequired to BYONC or be interruptible under IRAS. PJM is correct that during period of \nresource adequacy, no IRAS Actions need to be called. But PJM’s existing IRAS Framework \nalready allows this; there is no need to toggle IRAS off merely because resources will not be \ncurtailed during times of ample resource adequacy. IRAS Actions will only be called when PJM \n \n108 Supra note 103. Specifically, PJM should remove the section of the definition for New Large \nLoad and BYONC that changes the definitions “to the extent three consecutive Delivery Years \nmeet the requirements of Tariff, Attachment DD-4, section IV(b)(iii).”"},{"page":41,"startToken":11787,"endToken":12140,"text":"37 \nexperiences a capacity shortfall, and the quantity of IRAS will match the shortfall. During \nperiods of resource adequacy or surplus, no IRAS Actions will be taken.  \nAlternatively, the Commission could require PJM to clarify the trigger for the IRAS \nprogram becoming inactive. Under PJM’s proposal, the trigger for the IRAS program becoming \ninactive is when the capacity market clears for three consecutive years in excess of the \nReliability Requirement, which does not include large loads subject to IRAS. As described \nabove, this proposed trigger is unjust and unreasonable because it could lead PJM to suspend the \nIRAS program before the region actually has sufficient supply to meet all demand including new \nlarge loads. In other words, the proposed trigger risks PJM suspending the IRAS program while \nit is still needed. To prevent that outcome, the Commission could require PJM to clarify that the \ntrigger for suspending the IRAS program is when the capacity market clears for three \nconsecutive years with sufficient supply to meet all demand including large loads subject to \nIRAS.109That clarification would ensure that PJM does not suspend the IRAS program while it is \nstill needed. However, that modification would not necessarily ensure that large loads are \nresponsible for paying for and bringing their own new capacity online. For that reason, PIOs’ \nfirst recommendation is that the IRAS program simply be permanent. However, modifying the \n \n109 This clarification should be simple to implement by modifying PJM’s proposed language in \nTariff Attachment DD-4, section IV(b)(3). While PIOs defer to PJM and the Commission \nregarding the specific Tariff language for this clarification, PIOs believe it could be effectuated \nthrough the following modification:  \nIn the event ([the amount of Capacity Resources committed for a given Delivery \nYear (as determined after the Third Incremental Auction) equals or exceeds the PJM \nRegion Reliability Requirement including all large loads subject to IRAS \ndetermined prior to the Third Incremental Auction] divided by the Pool-wide \nAccredited UCAP Factor), then the Office of the Interconnection does not need any \nEligible New Large Loads to be available to provide Interim Resource Adequacy \nService for that Delivery Year."},{"page":42,"startToken":12140,"endToken":12409,"text":"38 \ntrigger for IRAS suspension as described here would be an acceptable alternative because it \nwould avoid the IRAS program being suspended while the region lacks supply to meet the \ndemand of large loads subject to IRAS.    \nEither way, PJM must close this loophole that could pin prices at the cap, harm other \ncustomers, and produce a volatile market with constantly changing expectations. \nIV. \nModification 2: The Commission Should Modify the IRAS Filing to Include \nPenalties When Eligible New Large Loads Fails to Curtail \n \nWith the IRAS Framework, PJM permits new large loads to obtain “speed to power” \nbefore bringing sufficient capacity online.110 In exchange, the unmatched portion of that load \nremains available for curtailment during defined reliability conditions.111 That bargain works \nonly if the reduction obligation is real. A load that continues drawing electricity when directed to \nreduce receives the benefit of accelerated service without providing the promised reliability \nprotection. \nPJM’s proposal does not have any penalty if a new large load subject to IRAS fails to \ncurtail. Attachment DD-4 authorizes PJM to issue an Interim Resource Adequacy Service Action, \ndirects an ED to implement a specified aggregate reduction among new large loads in its zone or \narea, and requires all eligible loads to be available to curtail,112 but it does not establish a \nconsequence if a large load fails to reduce. The IRAS Filing would pay a load that performs, but \nnothing holds the load accountable if it does not. \n \n110 IRAS Filing, supra note 2, at 94. \n111 Id. \n112 Id. at Proposed Tariff, Attach. DD-4 (Interim Resource Adequacy Service), pdf 540–42."},{"page":43,"startToken":12409,"endToken":12683,"text":"39 \nPJM’s operations witness explains that IRAS will be deployed before Pre-Emergency \nLoad Management Reduction Actions.113 This creates a new step “prior to impacting existing \ncustomers.”114 If reduction from IRAS are not curtailed, PJM may discover the shortfall only \nduring the emergency, when the system has the least time and flexibility to respond. The \nCommission should not approve a purported reliability service that relies only on carrots and has \nno sticks. \nA. \nCommission Precedent Supports Operational and Financial Consequences \nWhen a Lage Load Fails to Curtail. \n \nThe Commission addressed the same lack of performance penalties when establishing \nPJM’s new transmission services for flexible and co-located loads. Those services were designed \nfor customers “willing and able to limit their withdrawals from the transmission system under \ncertain conditions.”115 The Commission found that both operational and financial penalties for \nnonperformance were just and reasonable.116 \nIRAS embodies a similar bargain as the flexible and co-located loads proceedings. PJM \npermits a new large load that does BYONC to interconnect before it supplies necessary capacity \nto support firm service. In exchange, the load must remain available for curtailment. Indeed, PJM \ninvokes the new transmission services as a precedent for the straightforward bargain reflected in \nthe IRAS Filing.117 Curtailability is no less foundational here, and an unexcused failure has the \nsame basic risk that the system would continue to experience withdrawals that PJM’s emergency \n \n113 Id. at Pilong Aff. ¶ 20. \n114 Id. at Pilong Aff. ¶ 26. \n115 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 15 (2025) (“Co-location Order”). \n116 Id. at P 515. \n117 IRAS Filing, supra note 2, at 20–21."},{"page":44,"startToken":12683,"endToken":12946,"text":"40 \nprocedures assumed would stop. The Commission should, therefore, require operational penalties \nfor non-performance under the IRAS. If the Commission declines to require operational penalties \nfor IRAS loads that fail to curtail, then the Commission should, at the very least, require \nfinancial penalties.  \nB. \nThe Commission Should Require Operational Penalties for Failure to \nCurtail. \n \nThe Commission should condition acceptance of the IRAS Filing on the implementation \nof nonperformance penalties, consistent with its previous finding that loads that fail to curtail as \nrequired under non-firm transmission service agreements “should be subject to unreserved use \npenalties.”118 At a minimum, the IRAS proposal should require each ED after an IRAS action to \nreport the MW quantity directed, the aggregate MW reduction achieved, and any shortfall. \nWhere the ED can, it should include the called or curtailed load’s Large Load Registry identifier, \ndirected MW reduction, actual reduction, and the reason for any shortfall. Failure by an ED to \nreduce the load during an IRAS action should result in an operational penalty of either a \ntermination of service or a pause in service, consistent with the Commission’s June 18th Order in \nPJM’s Co-location docket.  \n \nThe Commission’s December Show Cause Order directed PJM to establish an \nappropriate penalty charge and “any other remedial action” that PJM should take to address a \ncustomer’s unreserved use of the transmission system or excess energy withdrawals. PJM \nestablished three different penalties—pause in service, disqualification, and financial penalties—\nwhere data centers fail to follow Load Shedding and Curtailment directives, face misoperation of \n \n118 Co-location Order, 193 FERC ¶ 61,217, at P 212."},{"page":45,"startToken":12946,"endToken":13316,"text":"41 \nnecessary control technology, or make unreserved use of the transmission system. PJM explicitly \nacknowledged that these operational penalties were necessary because financial penalties would \nnot be sufficient to incentivize data centers to follow curtailment procedures.119 \n \nThe Commission found that it was just and reasonable for PJM to impose operational \npenalties because PJM’s new transmission services were designed based on the assumption that \nEligible Customers would be willing and able to limit their withdrawals from the transmission \nsystem, and because of the significant reliability risks that would occur if Eligible Customers \nfailed to limit their withdrawals from the system.120 PJM and the Commission agreed that the \nconsequences of Remedial Action Scheme (“RAS”) failure or failures to follow curtailment \ndirectives are severe. A data center’s RAS misoperation or failure to comply with curtailment \ndirectives could have serious consequences, including the loss of all interim or non-firm load in \none area—or even cascading outages across the Eastern Interconnection.121 PJM found that strict \npenalties were needed to mitigate these significant reliability risks posed by customers who \ndisregard or fail to follow Load Shed and Curtailment procedures.122 PJM reasoned that its \npenalties were just and reasonable and consistent with the assumptions underlying its new \n \n119 Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49-000, at 50 (Feb. 23, 2026), \nAccession No. 20260223-5189 (“PJM Initial Brief”). \n120 Order on Rehearing, Clarification, Compliance Filing, and Paper Hearing, 195 FERC ¶ \n61,209, at P 515 (2026) (“Order on Rehearing”). The Commission declined to adopt PJM’s \nproposed replacement rate because the Commission found that PJM’s proposal to completely \ndisqualify an Eligible Customer from taking any of the new transmission services after the first \ninstance of failing to curtail was excessive. Instead, the Commission found that it would be just \nand reasonable for PJM to establish an operational penalty where PJM would terminate the \ntransmission service agreement with the Eligible Customer after the second instance of failing to \nfollow a curtailment or load shedding directive.  \n121 PJM Initial Brief, supra note 119, at Attach C., Affidavit of Matthew Wharton on behalf of \nPJM Interconnection, L.L.C., ¶ 21, 22 (“Wharton Affidavit”). \n122 PJM Initial Brief, supra note 119 at 6, 41–42."},{"page":46,"startToken":13316,"endToken":13615,"text":"42 \ntransmission services, which were that (1) Eligible Customers taking PJM’s new services were \n“willing and able to control their withdrawals from the transmission system;” and (2) the new \ntransmission services were designed to allow PJM to maintain system reliability.123 PJM stated \nthat allowing customers to connect to the transmission system on the condition that they would \ncontrol their energy withdrawals as necessary, but then not penalizing the customers for failing to \nperform would run counter to the Show Cause Order and would “implicitly bless such dangerous \nbehavior.”124  \n \nThe Commission should apply similar penalties to the IRAS framework because, like \nPJM’s new transmission services, IRAS was designed on the assumptions that (1) IRAS \nresources will reduce their load or switch to on-site backup resources when called; and (2) IRAS \nwill maintain system reliability. First, PJM describes IRAS as “a service that specifically allows \nfor Large Loads to interconnect without bringing their own capacity, on the condition that ‘they \nmust reduce their load or switch to on-site backup resources under specific, limited’ emergency \nconditions.”125 Like in the case of PJM’s new transmission services, the “straightforward \nbargain” here is that IRAS resources agree to reduce their MW load in exchange for getting to \ninterconnect quickly to PJM’s transmission system.126 Like PJM previously stated, allowing \ncustomers to connect to the system on the condition that they will curtail when called, but not \npenalizing them when they fail to curtail, would fail to ensure that customers will actually uphold \n \n123 Id. at 42. \n124 Id. \n125 IRAS Filing, supra note 2, at 39 (citing PJM, CIFP Framework for Service During Periods of \nInsufficient Resource Adequacy—PJM Proposal, at 1 (Jul. 27, 2026), https://www.pjm.com/-\n/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-cifp-framework-for-\nservice-during-periods-of-insufficient-resource-adequacy-executive-summary.pdf).  \n126 Id. at 95."},{"page":47,"startToken":13615,"endToken":13879,"text":"43 \ntheir end of the bargain. Here, a broken promise wouldn’t just be a sweet deal for data centers, it \nwould mean potential loss of load events or cascading outages across the Eastern \nInterconnection.  \n Second, like PJM’s new transmission services, IRAS was specifically designed to \n“maintain system reliability” as PJM integrates New Large Loads to the PJM Region.127 \nHowever, the reliability risks if IRAS loads fail to curtail will be even greater than in the case of \nthe Eligible Customers taking PJM’s new transmission services. IRAS will become available \nunder an EEA1, prior to deploying Pre-Emergency Load Management Reductions, but after \nPJM’s new non-firm transmission services (which are subject to PJM’s operational penalties).128 \nThis means that IRAS curtailments will be deployed closer to an emergency than PJM’s non-firm \nservices, and IRAS loads are therefore more essential to curtail to protect system reliability. \nIRAS is essentially the last stop before pre-emergency procedures. To mitigate the risks of \nsystem emergencies, the Commission should modify PJM’s IRAS framework to include strong \noperational penalties to ensure that IRAS loads curtail when called, or have their service \nterminated if they fail to curtail. Because IRAS will be called even closer to an emergency than \nnon-firm transmission services, and their curtailment is therefore even more important, PJM’s \npenalties for IRAS nonperformance should be at least as strong as the penalties the Commission \naccepted for PJM’s new non-firm transmission services, which were to terminate an Eligible \nCustomer’s transmission service after the second instance of failing to follow a curtailment or \n \n127 Id. at 75.  \n128 Id. at 77–78."},{"page":48,"startToken":13879,"endToken":14168,"text":"44 \nload shedding directive and establish a suspension in service for a period of up to 120 days after \nthe first misoperation of necessary control technologies.129 \nSimilar to how PJM will issue MW load reduction directives to EDs to implement IRAS \nreductions,130 PJM can issue directives to EDs to terminate service for the amount of MWs that \ndid not show up during an IRAS action. As with the IRAS reductions, PJM does not need to \ndirect EDs to terminate service for specific New Large Loads, but may direct EDs to terminate \nservice for an aggregate MW load amount. The EDs, subject to state regulation, will ultimately \nbe responsible for determining which individual retail customers face suspension or termination \nof service.   \nC. \nIf the Commission declines to impose operational penalties, then the \nCommission should modify PJM’s proposal to include financial penalties. \n \nFinancial penalties are insufficient to ensure that IRAS loads will curtail as directed, but \nif the Commission declines to require operational penalties for the IRAS framework, then the \nCommission should implement financial penalties for IRAS loads that fail to curtail so that there \nis some disincentive for failures to curtail. As it stands, absolutely no penalty for an IRAS load’s \nfailure to curtail is inadequate and inconsistent with PJM’s and the Commission’s prior approach \nto curtailment enforcement.  \nIn its initial brief in the Co-Location docket, PJM found that financial penalties alone are \ninsufficient to incentivize data centers to comply with load shed and curtailment directives.131 \nLarge load customers have virtually unlimited capital and high contractual uptime requirements, \n \n129 Order on Rehearing, 195 FERC ¶ 61,209 at PP 515, 516.  \n130 IRAS Filing, supra note 2, at 26.   \n131 PJM Initial Brief, supra note 119, at 50."},{"page":49,"startToken":14168,"endToken":14473,"text":"45 \ngiving them little to no incentive to curtail. An effective financial penalty must be more than \nmerely the cost of doing business for wealthy large loads. But research suggests that there is no \nprice level currently observed in wholesale markets where certain data center loads will \ncurtail.132 \n \nIf the Commission declines to impose operational penalties as part of the IRAS \nFramework, then it should consider the financial realities of the large loads likely to take service \nunder the IRAS Framework—mostly data centers—when devising any financial penalties. In \nlight of the fact that recent evidence suggests that financial penalties are unlikely to alter data \ncenters’ behavior—and PJM’s own representation that financial penalties would not be effective \nin the non-firm transmission services context—financial penalties for IRAS resources that fail to \ncurtail may need to be severe in order to be effective. If the Commission imposes a system of \nsevere financial penalties for IRAS resources that fail to curtail, then those penalties should fund \nrefunds to other consumers. A refund to load funded by IRAS penalties would be appropriate in \nlight of the reliability risks that other consumers would experience when IRAS resources fail to \ncurtail.   \n \n \n \n132 In February 2026, Hans Royal, Senior Director of Renewable Energy and Carbon Advisory at \nSchneider Electric, introduced the Compute Heat Rate, which is the first measurement to \nquantify the maximum electricity price at which AI computation remains economically viable, \ni.e. the demand-side price tolerance for data centers relative to curtailment thresholds. Royal’s \npreliminary analysis found that for four data center workload tiers, AI demand will not curtail at \nany price level currently observed in U.S. wholesale markets. Hans Royal, The Compute Heat \nRate: Quantifying AI-Driven Electricity Price Tolerance and its Implications for Wholesale \nMarket Repricing, 8 (June 2026), https://ssrn.com/abstract=6322318."},{"page":50,"startToken":14473,"endToken":14762,"text":"46 \nV. \nModification 3: The Commission Should Reject IRAS Compensation or, in the \nAlternative, Limit Any Payment to a Make-Whole Payment for Capacity Charges. \n \nPJM accurately describes the IRAS framework as a “straightforward bargain.”133 \nUnmatched large loads are allowed to receive service on the condition that they curtail when \nneeded. This allows data centers to achieve “speed to power” without jeopardizing the reliability \nof residential and other customers.134 This is a fair trade that PIOs endorse. PJM, however, goes \nfurther by adding a second benefit for large loads that do not BYONC: a payment equal to 50 \npercent of the Capacity Performance Non-Performance Charge Rate, funded by other customers. \nThe Commission should reject that added payment. Required IRAS curtailment is the condition \non which unmatched large loads receive accelerated service, not an independently procured \nproduct for which other customers should pay.  \nPJM describes the IRAS compensation as a “discount on capacity costs” whose “net \nresult is a reduced capacity charge” for a new large load that does not BYONC.135 That \ndescription does not justify an incentive payment. The new large load already receives the \nbenefit of “speed to power” in exchange for being curtailable. The Commission should instead \nestablish a zero-dollar wholesale rate for curtailment. Alternatively, if the Commission concludes \nthat a curtailed large load should receive an adjustment for capacity charges, the aggregate \ncompensation paid to that load for a delivery year should not exceed the lesser of (1) the \naggregate compensation calculated under PJM’s filed rate or (2) the capacity charges actually \nassessed to and paid by that load for the delivery year, prorated to reflect the verified amount and \n \n133 IRAS Filing, supra note 2, at 94. \n134 Id. \n135 Id. at 104."},{"page":51,"startToken":14762,"endToken":15022,"text":"47 \nduration of curtailment. That alternative would be a make-whole adjustment, rather than an \nincentive or a windfall. \nA. \nCurtailability Is a Condition of Speed to Power, Not a Separately \nCompensable Service. \n \nAn Eligible New Large Load does not provide IRAS curtailment as an independently \nprocured capacity or demand-response resource. It becomes subject to IRAS because it seeks to \ninterconnect and consume electricity before arranging sufficient new capacity to meet its needs. \nPJM calls this a “straightforward bargain”: the new large load receives speed to power but \naccepts curtailment during emergencies if it does not BYONC.136 \nCurtailability is the consideration the unmatched large load gives in return for speed to \npower. PJM has not shown that a second, consumer-funded payment is needed to induce \ncompliance with the condition that makes speed to power possible. Paying for ordinary \ncompliance would upend that bargain by forcing consumers to pay for a service for which large \nloads are already compensated through speedy interconnection. This flies in the face of the \nRatepayer Protection Pledge and White House Statement of Principles. \nThe Commission’s recent treatment of PJM’s conditional transmission services confirms \nthe distinction. There, the Commission explained that the “fundamental principle” supporting the \nnew services was participating loads’ willingness and ability to limit their withdrawals under \nspecified conditions.137 The Commission required an operational and financial consequences for \nfailure to limit withdrawals, but it did not establish a payment to a conditional load merely for \ncomplying with a curtailment order. \n \n136 Id. at 94. \n137Order on Rehearing, 195 FERC ¶ 61,209, at P 519."},{"page":52,"startToken":15022,"endToken":15327,"text":"48 \nPJM justifies its IRAS payment by noting that it uses the same 50 percent of the Non-\nPerformance Charge Rate used in the Pre-Emergency Load Response proceeding.138 In that case, \nhowever, the payment is funded by resources that underperformed during a curtailment event and \nonly paid to resources that overperformed.139 Here, the curtailing large loads are not being paid \nfor overperforming through penalties imposed on underperforming large loads, but rather is \nbeing paid for anticipated performance—for which they have already been compensated through \nspeed to power. Moreover, the payment to curtailing large loads does not come from \nunderperforming resources that earned a penalty, but is instead borne by other customers who \nshould not be forced to subsidize large loads performing as directed. \nIn justifying the IRAS process, PJM invokes Tenaska Clear Creek Wind, where the \nCommission found that a generator whose early operation caused the need for network upgrades \ncould be curtailed until those upgrades were complete so that the cost-causing customer bore \n“the system-reliability burdens that flow from its decision to operate prior completion of the \nrequired network upgrades.”140 The same principle supports a zero-dollar rate for curtailment. \nThe party electing accelerated service should bear the reliability condition that accompanies that \nelection, not transfer the burden of its early operation to existing customers. If the Commission \nnevertheless accepts PJM’s separate capacity-charge premise, that premise supports only the \nalternative, limited refund described below. \n \n \n138 IRAS Filing, supra note 2, at 102 n.271 (citing PJM Interconnection, L.L.C., 195 FERC ¶ \n61,253 (2026)). \n139 PJM Interconnection, L.L.C., 195 FERC ¶ 61,253, at P 4 (2026). \n140 See IRAS Filing, supra note 2, at 99 n.264 (citing Tenaska Clear Creek Wind, L.L.C. v Sw. \nPower Pool, Inc., 183 FERC ¶ 61,043, at P 24 (2023))."},{"page":53,"startToken":15327,"endToken":15612,"text":"49 \nB. \nCost Causation Principles Support a Zero-Dollar Rate or a Capacity-Charge \nCredit. \n \nThe Federal Power Act’s just-and-reasonable standard incorporates cost causation. Rates \nmust be roughly commensurate with the costs imposed or the benefits received by any given \nratepayer.141 PJM’s proposed default rate does not satisfy that standard. \nThe customers—including residential customers—who would be charged to pay large \nloads under the IRAS process did not cause the capacity need associated with an unmatched \nlarge load’s decision to interconnect before bringing online the capacity it requires. Nor does the \ncurtailment transform the load into a new capacity resource that those customers procured. \nExisting customers already pay for reliable service through the RPM. IRAS curtailment does not \nprovide existing customers with a service, it simply restores the reliability that would exist \nabsent the demand from unmatched large loads. \nNor can it be said that customers who must pay the Eligible New Large Loads for \ncurtailing receive a benefit for not being curtailed themselves. Forcing them to pay for this \nputative benefit is more akin to the extortion of a mob protection racket than receiving security \nfrom an outside threat. Even if the Commission characterizes emergency avoidance through a \npre-emergency calling of Eligible New Large Loads as a regional benefit, PJM must show that \nthe resulting charges are roughly commensurate with that benefit, which it has not. PJM has \nneither substantiated the need for the charge nor explained how it should be calculated and \nassessed that it is roughly commensurate with the alleged benefits received. PJM’s failure to \nmake that showing supports a zero-dollar IRAS rate. PJM has not established that a capacity \n \n141 Midwest ISO Transmission Owners v. FERC, 373 F.3d at 1368."},{"page":54,"startToken":15612,"endToken":15871,"text":"50 \ncharge guarantees uninterrupted service or that curtailment creates an independent right to a \nrefund. When, for example, existing customers are curtailed during a load-shed event, they are \nnot refunded their prior capacity payments. \nThe only justification PJM provides is that the rate is a “discount on capacity.”142 If the \nCommission accepts that justification, it should allow compensation only up to a load-specific \ncap at the portion of a capacity charge assessed to the same load and attributable to the verified \ncurtailed amount and duration. Otherwise, the Commission should allow no compensation for \nIRAS curtailment. \nC. \nPJM’s Reliance on the Commission’s Decision on Compensation for Pre-\nEmergency Load Response Does Not Justify the Proposed Rate. \n \nTo justify its proposed rate in this proceeding, PJM relies on the Commission’s \nacceptance of a nonperformance rate and corresponding bonus-payment rate equal to 50 percent \nof the Non-Performance Charge Rate in a prior proceeding.143 That decision, however, does not \nestablish that the same rate is just and reasonable in this proceeding. The distinct funding \nstructure and purpose of the Pre-Emergency Load Response program make in inapposite as a \nprecedent for the current filing.  \nThe Pre-Emergency Load Response nonperformance rate reflects that a customer “paid \nfor capacity but did not get the benefit” of the called resource.144 Under that regime, charges \ncollected from resources that underperformed fund bonus payments to resources that \n \n142 IRAS Filing, supra note 2, at 104. \n143 Id. at 102 n.271 (citing PJM Interconnection, L.L.C., 195 FERC ¶ 61,253 (2026)). \n144 Id. at 103."},{"page":55,"startToken":15871,"endToken":16146,"text":"51 \noverperformed.145 The nonperformer funds the overperformer. Other customers are not charged \nsimply because a resource honored its obligation to curtail. \nThe Commission applied the same principle when approving penalties for failing to meet \nthe requirements of PJM’s new conditional transmission service.146 It required revenues from \nthose penalties to be distributed to “all non-offending transmission customers consistent with \nOrder No. 890.”147 A penalty-and-bonus design thus links the payment of one party to another \nparty’s misconduct. \n \nHere, the IRAS contains no comparable funding pool. The IRAS Filing does not include \na nonperformance charge for failure to curtail whose proceeds would fund IRAS payments. \nInstead, it requires the ED to charge its customers or permits it to ask PJM to charge “certain \nLoad Serving Entities,” to fund the payment.148 The Non-Performance Charge Rate was used to \ndetermine a penalty in an unrelated PJM program, not to measure the capacity charge borne by \nan Eligible New Large Load. The same number may supply a reasonable penalty metric for \nfailure to curtail without establishing a reasonable compensation rate for performance.  \nD. \nThe Commission Should Remove IRAS Performance Compensation or, in \nthe Alternative, Limit Any Compensation to a Make-Whole Payment. \n \nAs explained above, the compensation scheme for IRAS actions is unjust and \nunreasonable. It provides unnecessary payments to Eligible New Large Loads that are already \ncompensated by their speed to power and funds those payments through charges to existing \nratepayers who derive no benefit. \n \n145 Co-Location Order, 193 FERC ¶ 61,217, at P 5. \n146 Id. \n147 Id. at PP 5, 529. \n148 IRAS Filing, supra note 2, at Proposed Tariff, Attach. DD-4 § X(b)(i)."},{"page":56,"startToken":16146,"endToken":16436,"text":"52 \nThe Commission should replace the proposed IRAS compensation mechanism with a \nzero-dollar rate and prohibit any charge under the PJM Tariff to fund IRAS compensation. \nNothing in that remedy would prevent a state or RERRA from establishing a separate \ncompensation program under state law. In the alternative, the Commission can prescribe a make-\nwhole payment up to the amount of capacity charges assessed to the ED for curtailed loads.  \nVI. \nModification 4: The Commission should require BYONC supply to be fully \ndeliverable to new large loads by considering transmission limits between zones.  \n \nPJM’s proposed BYONC requirements do not consider the location of the New Large \nLoad nor the associated supply. This jeopardizes reliability and risks socializing costs to other \ncustomers in violation of the objectives of the IRAS Framework. Without a locational \nrequirement, PJM risks relying on new capacity that will not actually be able to serve the zone in \nwhich the sponsoring new large load resides, thus failing to achieve reliability objectives.149 \nSimilarly, allowing distant load and supply arrangements could result in significant regional \ntransmission needs, which shift costs to other ratepayers, failing objective 2. Because PJM’s \ncapacity and energy markets recognize locational constraints, new supply that is transmission \nconstrained will not deliver cost relief. The Commission should direct PJM to require BYONC to \nbe located only in zones that are not constrained with respect to the zone in which the new large \nload resides. \n \n149 See, e.g., PJM Interconnection, L.L.C., 117 FERC 61,331, at P 48 (2006) (approving the \nsettlement establishing the basic structure of the capacity market in part because the prior market \n“d[id] not provide incentives for generators to locate in the geographical areas where they are \nmost needed”)."},{"page":57,"startToken":16436,"endToken":16722,"text":"53 \nPJM proposes to define BYONC as any Network Resource(s) that satisfy the BYONC \nrequirements outlined in the proposed tariff.150 While PJM requires BYONC resources to be \nnew, it does not impose any locational limitations. This means that BYONC could be located \nphysically far away from new large loads. PJM does not justify the lack of locational limitations \nfor BYONC, despite there being documented transmission limitations between PJM zones. Some \nzones, like BGE, PSEG, and PEPCO—and notably the COMED (Illinois) and DOM (Virginia) \nzones, which contain much of the region’s planned data center expansion—frequently “separate” \nfrom the rest of the RTO in capacity auctions, clearing with higher prices than the rest of the \nRTO due to transmission constraints.151  \nNetwork upgrades alone are not designed to fix transmission constraints between zones. \nAlthough PJM requires BYONC resources to be “network resources,” which are theoretically \nfully deliverable to the entire PJM system once their network upgrades are constructed, the \nexistence of regular price separation undermines this characterization. Standard network \nupgrades focus on mitigating the immediate interconnection impacts at a specific point of \ninjection, and are not systemic upgrades to resolve region-wide reliability violations. Those \nupgrades proceed through PJM’s Regional Transmission Expansion Planning process (“RTEP”).  \nExcluding any locational requirement for BYONC could result in higher RTEP costs, \nwhich are paid for by other customers. These costs could be significantly more than the capital \ncosts of new power plants, eclipsing any benefits that ratepayers would receive through the \n \n150 IRAS Filing, supra note 2, at 49–54. \n151 See, e.g., PJM Interconnection, L.L.C., 2023/2024 RPM Base Residual Auction Results, \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2023-2024/2023-\n2024-base-residual-auction-report.pdf."},{"page":58,"startToken":16722,"endToken":17080,"text":"54 \nBYONC scheme. Distant supply could trigger new long-distance transmission projects through \nthe RTEP. Under PJM rules, all utilities across PJM pay for RTEP projects based on cost \nallocation methodology that includes load-ratio share.152 In other words, even if a new large load \ncustomer pays for its own BYONC including any associated network upgrades, there is still a \nsignificant risk that costs will still be shifted to other customers through RTEP. The most recent \nRTEP will cost $11.8 billion, driven largely by increases in large loads.153 The IRAS proposal \nincludes no changes to how transmission or new generation or load is studied. There is every \nreason to expect that if transmission constraints do not inform BYONC decisions, future RTEP \ncycles may cost even more. Given that one major objective of BYONC is to reduce the cost \nburden of data center load growth on other consumers, it would be illogical to allow remote \nBYONC to result in higher costs. In short, because total system costs matter, it is unreasonable to \nencourage new generation without considering the transmission investments needed to support it.  \nSimilarly, allowing large loads to rely on distant capacity risks increasing locational \nmarginal prices (“LMPs”) in constrained zones, which are passed on to ratepayers in the form of \nhigher electricity bills. While new remote capacity might help the overall system’s capacity \nbalance, it does not fix the physical delivery problem. Adding massive new loads could force \nconstrained zones to dispatch more expensive generators when the transmission paths between \ndistant load and supply are congested. This appears to already be occurring: real time LMPs in \n \n152 PJM Manual 14B, Att. A, Section A. 3.1 RTEP Baseline Reliability Upgrade Cost Allocation, \navailable at https://www.pjm.com/-/media/DotCom/documents/manuals/m14b.pdf.  \n153 See, e.g., PJM, RTEP 2025: Regional Transmission Expansion Plan, at 16 (Apr. 16, 2026), \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/2025-rtep/2025-rtep-report.pdf \n(showing that addressing load growth and deliverability comprised 95% of the drivers of that \nyear’s RTEP projects); see also id. at 1 (“Load growth continues to increase, driven primarily by \nthe proliferation of data centers”)."},{"page":59,"startToken":17080,"endToken":17367,"text":"55 \nthe DOM zone, home to the largest concentration of data centers, have increased 67.9% from \n2024 to 2025, compared with 50.4% for PJM overall.154 Congestion costs PJM-wide increased \n80.9%, or $1.75 billion, between 2024 and 2025.155 These energy costs are paid by all customers, \nviolating the objectives of the IRAS Filing. \nOn top of raising costs for other customers, the lack of a locational requirement could \nlead to delays that worsen or extend resource adequacy shortfalls. Remote resources could take \nsignificantly longer to become fully deliverable to large load customers in constrained zones \nbecause of network upgrade delays and reliance on long lead-time RTEP upgrades. NRDC \nanalysis found that Network Upgrades already contribute to significant project withdrawals from \nthe interconnection queue and multi-year delays before new supply can deliver power.156 The \nlack of a locational requirement risks extending these timelines and exacerbating resource \nadequacy shortfalls as new supply built to serve large loads is forced to wait behind network \nupgrade bottlenecks, undermining the BYONC scheme. \nTo resolve these risks, the Commission should direct PJM to consider available transfer \ncapacity from the most recent PJM base residual capacity auction delivery year to determine if a \nnew BYONC resource is “deliverable” to new large loads. This approach would exclude \nBYONC supply from any zones in PJM that show limited transfer capacity, recognizing the fact \n \n154 Monitoring Analytics, 2025 State of the Market Report for PJM: Volume 2 Detailed Analysis, \nat 200, tbls. 3-53, 3-54, (March 12, 2026), \nhttps://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2025/2025-som-pjm-\nvol2.pdf.  \n155 Id at. 665.  \n156 Yamit Lavi, Unlocking the Grid, NRDC (Apr. 7, 2026). \nhttps://www.nrdc.org/resources/unlocking-grid"},{"page":60,"startToken":17367,"endToken":17651,"text":"56 \nthat this capacity will likely trigger significant network upgrades or new regional transmission \nbefore becoming deliverable to the new large load customers. It should be straightforward for \nPJM to evaluate these constrained zones using the RPM planning parameters or even the auction \nclearing results. For example, if the large load is located in a load deliverability area (“LDA”) \nthat cleared with an RPM “adder” to its clearing price, indicating a transmission constraint, it \nmust seek BYONC located within that LDA. This way, costs are truly allocated to the large load \ncausers.   \nCONCLUSION \n \nPJM’s IRAS Filing generally presents a just and reasonable mechanism to ensure large \nloads are responsible for their own new capacity and protect other customers from unintended \nreliability consequences while respecting state jurisdiction over retail rates. However, to ensure \nthat the IRAS Filing achieves its objectives, the Commission must make the modifications \ndescribed above to: (1) ensure IRAS and BYONC requirements are permanent for all new large \nloads or else clarify that the trigger for turning IRAS off requires the capacity market to clear for \nthree consecutive years with sufficient supply to meet all demand including all large loads \nsubject to IRAS; (2) require penalties for LSEs that fail to comply with IRAS Actions; (3) either \neliminate compensation for IRAS resource curtailment or require PJM to cap the compensation \nawarded to IRAS loads at no more than the amount the new large load paid in capacity charges \nfor the relevant delivery year; and (4) require BYONC supply to be fully deliverable to new large \nloads by considering transmission limits between zones. Accordingly, PIOs \nrespectfully request that the Commission approve the IRAS Filing with the \nmodifications described above. \nDated: September 3, 2026"},{"page":61,"startToken":17651,"endToken":17755,"text":"57 \n \nRespectfully submitted,  \n \nSIERRA CLUB \n \n/s/ Nick Lawton  \nNick Lawton  \nEarthjustice  \n1400 L St NW   \nLobby 2, Unit 34117   \nWashington DC 20005  \n(202) 780-4835  \nnlawton@earthjustice.org  \n \n/s/ Aaliyah Adkins  \nAaliyah Adkins  \nEarthjustice  \n1400 L St NW   \nLobby 2, Unit 34117   \nWashington DC 20005  \n(202) 797-5253  \naadkins@earthjustice.org  \n \n/s/ Justin Vickers  \nJustin Vickers  \nSenior Attorney  \nSierra Club  \n2101 Webster St., 13th Floor   \nOakland, CA 94612  \n(224) 420-0614  \njustin.vickers@sierraclub.org  \n \nCounsel for Sierra Club \n \nNATURAL RESOURCES DEFENSE COUNCIL \n \n/s/ Claire Lang-Ree \nClaire Lang-Ree \nAdvocate, Sustainable FERC Project,  \nNatural Resources Defense Council \n40 W 20th St \nNew York, NY, 10011 \nclangree@nrdc.org"},{"page":62,"startToken":17755,"endToken":17860,"text":"58 \nENVIRONMENTAL LAW AND POLICY CENTER \n \n/s/Nicholas Wallace \nNicholas Wallace \nSenior Associate Attorney \nEnvironmental Law & Policy Center  \n35 East Wacker Drive, Suite 1600 \nChicago, IL 60601 \n(312) 673-6500 \nnwallace@elpc.org \n \nAPPALACHIAN VOICES \n \n/s/ Nicholas J. Guidi \nNicholas J. Guidi \nSenior Attorney \nnguidi@selc.org \n  \n/s/ Katherine L. Rogers  \nKatherine L. Rogers  \nAssociate Attorney \nkrogers@selc.org \nSouthern Environmental Law Center \n500 New Jersey Ave. NW, Suite 600 \nWashington, DC 20001 \n  \nCounsel for Appalachian Voices  \n \n \nCENTER FOR PROGRESSIVE REFORM \n \nBryan Dunning \nSenior Policy Analyst \nCenter for Progressive Reform \n1250 Connecticut Ave. NW \nWashington, D.C. 20036 \nbdunning@progressivereform.org \n(202) 747 0698 ext. 7"},{"page":63,"startToken":17860,"endToken":17922,"text":"59 \nCERTIFICATE OF SERVICE \n \nI hereby certify that the foregoing has been served in accordance with 18 C.F.R. § \n385.2010 upon each party designated in the official service list compiled by the Secretary in this \nproceeding, by email.   \n/s/ Nick Lawton  \nNick Lawton  \nEarthjustice  \n1400 L St NW   \nLobby 2, Unit 34117   \nWashington DC 20005  \n(202) 780-4835  \nnlawton@earthjustice.org"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":326},{"p":3,"at":5,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":3,"endAt":302,"startToken":326,"endToken":333},{"p":3,"at":302,"title":"I. PJM is facing resource adequacy and affordability concerns as it struggles to meet data","method":"printed heading","endPage":3,"endAt":527,"startToken":333,"endToken":352},{"p":3,"at":527,"title":"A. PJM’s capacity market faces increased reliability risks as data center load grows","method":"printed heading","endPage":3,"endAt":724,"startToken":352,"endToken":374},{"p":3,"at":724,"title":"B. PJM’s supply and demand imbalance is causing high capacity prices, leading to","method":"printed heading","endPage":3,"endAt":925,"startToken":374,"endToken":394},{"p":3,"at":925,"title":"II. The Commission should accept PJM’s Interim Resource Adequacy Service and Large","method":"printed heading","endPage":3,"endAt":1549,"startToken":394,"endToken":457},{"p":3,"at":1549,"title":"C. Removing New Large Loads from RPM is just, reasonable, and not unduly","method":"printed heading","endPage":3,"endAt":1752,"startToken":457,"endToken":472},{"p":3,"at":1752,"title":"II. The Commission Should Only Modify PJM’s IRAS Filing to Better Accomplish PJM’s","method":"printed heading","endPage":3,"endAt":1973,"startToken":472,"endToken":487},{"p":3,"at":1973,"title":"A. Objective One: Promote Reliability by Requiring New Large Loads to be Curtailable","method":"printed heading","endPage":3,"endAt":2161,"startToken":487,"endToken":510},{"p":3,"at":2161,"title":"B. Objective Two: Promote Affordability by Requiring New Large Loads to Pay for","method":"printed heading","endPage":3,"endAt":2456,"startToken":510,"endToken":538},{"p":3,"at":2456,"title":"C. Objective Three: Provide States and LSEs With Sufficient Information to Ensure the","method":"printed heading","endPage":3,"endAt":2656,"startToken":538,"endToken":558},{"p":3,"at":2656,"title":"III. Modification 1: The Commission must ensure that the IRAS filing effectively removes","method":"printed heading","endPage":3,"endAt":2970,"startToken":558,"endToken":587},{"p":3,"at":2970,"title":"A. Suspending the IRAS Framework during periods of resource adequacy risks pinning","method":"printed heading","endPage":3,"endAt":3640,"startToken":587,"endToken":653},{"p":3,"at":3640,"title":"B. PJM’s proposal to toggle IRAS on and off creates regulatory uncertainty and","method":"printed heading","endPage":4,"endAt":4,"startToken":653,"endToken":672},{"p":4,"at":4,"title":"C. The Commission should modify PJM’s IRAS Filing to make the IRAS Framework","method":"printed heading","endPage":4,"endAt":185,"startToken":672,"endToken":693},{"p":4,"at":185,"title":"IV. Modification 2: The Commission Should Modify the IRAS Filing to Include Penalties","method":"printed heading","endPage":4,"endAt":386,"startToken":693,"endToken":715},{"p":4,"at":386,"title":"A. Commission Precedent Supports Operational and Financial Consequences When a","method":"printed heading","endPage":4,"endAt":681,"startToken":715,"endToken":743},{"p":4,"at":681,"title":"C. If the Commission declines to impose operational penalties, then the Commission","method":"printed heading","endPage":4,"endAt":866,"startToken":743,"endToken":764},{"p":4,"at":866,"title":"V. Modification 3: The Commission Should Reject IRAS Compensation or, in the","method":"printed heading","endPage":4,"endAt":1033,"startToken":764,"endToken":788},{"p":4,"at":1033,"title":"A. Curtailability Is a Condition of Speed to Power, Not a Separately Compensable","method":"printed heading","endPage":4,"endAt":1337,"startToken":788,"endToken":816},{"p":4,"at":1337,"title":"C. PJM’s Reliance on the Commission’s Decision on Compensation for Pre-Emergency","method":"printed heading","endPage":4,"endAt":1523,"startToken":816,"endToken":836},{"p":4,"at":1523,"title":"D. The Commission Should Remove IRAS Performance Compensation or, in the","method":"printed heading","endPage":4,"endAt":1690,"startToken":836,"endToken":856},{"p":4,"at":1690,"title":"VI. Modification 4: The Commission should require BYONC supply to be fully deliverable","method":"printed heading","endPage":5,"endAt":3,"startToken":856,"endToken":883},{"p":5,"at":3,"title":"INTRODUCTION","method":"printed heading","endPage":9,"endAt":1297,"startToken":883,"endToken":2245},{"p":9,"at":1297,"title":"BACKGROUND","method":"printed heading","endPage":9,"endAt":1311,"startToken":2245,"endToken":2246},{"p":9,"at":1311,"title":"I. PJM is facing resource adequacy and affordability concerns as it struggles to meet","method":"printed heading","endPage":10,"endAt":785,"startToken":2246,"endToken":2411},{"p":10,"at":785,"title":"A. PJM’s capacity market faces increased reliability risks as data center load","method":"printed heading","endPage":13,"endAt":394,"startToken":2411,"endToken":3383},{"p":13,"at":394,"title":"B. PJM’s supply and demand imbalance is causing high capacity prices, leading","method":"printed heading","endPage":15,"endAt":1051,"startToken":3383,"endToken":4164},{"p":15,"at":1051,"title":"II. The Commission should accept PJM’s Interim Resource Adequacy Service and","method":"printed heading","endPage":16,"endAt":1360,"startToken":4164,"endToken":4528},{"p":16,"at":1360,"title":"DISCUSSION","method":"printed heading","endPage":16,"endAt":1374,"startToken":4528,"endToken":4529},{"p":16,"at":1374,"title":"I. The IRAS Framework is just and reasonable and not unduly discriminatory.","method":"printed heading","endPage":17,"endAt":1548,"startToken":4529,"endToken":4837},{"p":17,"at":1548,"title":"A. Large load customers are differently situated from other customers.","method":"printed heading","endPage":22,"endAt":172,"startToken":4837,"endToken":6106},{"p":22,"at":172,"title":"B. IRAS is jurisdictionally sound and respects the roles of states and PJM.","method":"printed heading","endPage":24,"endAt":193,"startToken":6106,"endToken":6677},{"p":24,"at":193,"title":"C. Removing New Large Loads from RPM is just, reasonable, and not unduly","method":"printed heading","endPage":27,"endAt":4,"startToken":6677,"endToken":7501},{"p":27,"at":4,"title":"II. The Commission Should Only Modify PJM’s IRAS Filing to Better Accomplish","method":"printed heading","endPage":28,"endAt":726,"startToken":7501,"endToken":7903},{"p":28,"at":726,"title":"A. Objective One: Promote Reliability by Requiring New Large Loads to be","method":"printed heading","endPage":30,"endAt":626,"startToken":7903,"endToken":8458},{"p":30,"at":626,"title":"B. Objective Two: Promote Affordability by Requiring New Large Loads to Pay","method":"printed heading","endPage":32,"endAt":4,"startToken":8458,"endToken":8929},{"p":32,"at":4,"title":"C. Objective Three: Provide States and LSEs With Sufficient Information to","method":"printed heading","endPage":34,"endAt":189,"startToken":8929,"endToken":9523},{"p":34,"at":189,"title":"III. Modification 1: The Commission must ensure that the IRAS filing effectively","method":"printed heading","endPage":35,"endAt":510,"startToken":9523,"endToken":9954},{"p":35,"at":510,"title":"A. Suspending the IRAS Framework during periods of resource adequacy risks","method":"printed heading","endPage":38,"endAt":1588,"startToken":9954,"endToken":11132},{"p":38,"at":1588,"title":"B. PJM’s proposal to toggle IRAS on and off creates regulatory uncertainty and","method":"printed heading","endPage":40,"endAt":206,"startToken":11132,"endToken":11522},{"p":40,"at":206,"title":"C. The Commission should modify PJM’s IRAS Filing to make the IRAS","method":"printed heading","endPage":42,"endAt":396,"startToken":11522,"endToken":12203},{"p":42,"at":396,"title":"IV. Modification 2: The Commission Should Modify the IRAS Filing to Include","method":"printed heading","endPage":43,"endAt":474,"startToken":12203,"endToken":12482},{"p":43,"at":474,"title":"A. Commission Precedent Supports Operational and Financial Consequences","method":"printed heading","endPage":44,"endAt":313,"startToken":12482,"endToken":12726},{"p":44,"at":313,"title":"B. The Commission Should Require Operational Penalties for Failure to","method":"printed heading","endPage":48,"endAt":740,"startToken":12726,"endToken":14001},{"p":48,"at":740,"title":"C. If the Commission declines to impose operational penalties, then the","method":"printed heading","endPage":50,"endAt":4,"startToken":14001,"endToken":14474},{"p":50,"at":4,"title":"V. Modification 3: The Commission Should Reject IRAS Compensation or, in the","method":"printed heading","endPage":51,"endAt":122,"startToken":14474,"endToken":14780},{"p":51,"at":122,"title":"A. Curtailability Is a Condition of Speed to Power, Not a Separately","method":"printed heading","endPage":53,"endAt":4,"startToken":14780,"endToken":15328},{"p":53,"at":4,"title":"B. Cost Causation Principles Support a Zero-Dollar Rate or a Capacity-Charge","method":"printed heading","endPage":54,"endAt":639,"startToken":15328,"endToken":15708},{"p":54,"at":639,"title":"C. PJM’s Reliance on the Commission’s Decision on Compensation for Pre-","method":"printed heading","endPage":55,"endAt":1191,"startToken":15708,"endToken":16051},{"p":55,"at":1191,"title":"D. The Commission Should Remove IRAS Performance Compensation or, in","method":"printed heading","endPage":56,"endAt":445,"startToken":16051,"endToken":16216},{"p":56,"at":445,"title":"VI. Modification 4: The Commission should require BYONC supply to be fully","method":"printed heading","endPage":60,"endAt":597,"startToken":16216,"endToken":17459},{"p":60,"at":597,"title":"CONCLUSION","method":"printed heading","endPage":63,"endAt":4,"startToken":17459,"endToken":17861},{"p":63,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":63,"endAt":388,"startToken":17861,"endToken":17922}]}