{"document":{"slug":"rec-20260903-5167","title":"Comments of Tesla, Inc. re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service","issued":"2026-09-03","accession":"20260903-5167","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Tesla, Inc.","kind":"comments","file":"sources/filings/text/20260903-5167_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5167","tier":"record","sha256":"42b6a57cce88b3528dbe5416b1e9ca0b9654c2f7e23fc29cde3a49c8ef38f640","pages":10,"tokens":3280,"emptyPages":[],"textThemes":["adequacy","flex","registry"]},"pages":[{"page":1,"startToken":0,"endToken":278,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nDocket No. ER26-3515 \nCOMMENTS OF TESLA, INC. \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory \nCommission (\"Commission\"), Tesla, Inc. (\"Tesla\") respectfully submits these comments \nregarding PJM Interconnection, L.L.C.'s (\"PJM\") proposed Interim Resource Adequacy Service \n(\"IRAS\") framework and associated provisions affecting Peak Shaving Adjustments (\"PSAs\"), \nReliability Backstop Procurement (\"RBP\"), and related resource adequacy mechanisms. \nI. INTRODUCTION AND SUMMARY \nTesla does not take a position in these comments on whether the Commission should \napprove or reject PJM's proposed IRAS construct as a whole. Tesla does, however, \nrespectfully request that the Commission modify PJM's proposal in several important \nrespects to ensure that the final rules do not unnecessarily disadvantage forecast-reducing \ndemand-side reliability solutions relative to supply-side reliability solutions. \nThese modifications are important regardless of the Commission's ultimate disposition of \nthe broader IRAS framework. They improve forecast accuracy, preserve technology \nneutrality, support resource adequacy, facilitate emerging state-level reliability initiatives, \nand ensure that customers funding reliability solutions receive comparable treatment \nregardless of whether those solutions are modeled as incremental supply or forecast \nreductions. \nSpecifically, Tesla requests that the Commission: \n1. Require that qualifying Peak Shaving Adjustments funded by Large Loads receive the \nsame exemption from IRAS curtailment obligations that PJM proposes to provide \nthrough Bring Your Own New Capacity (\"BYONC\") arrangements, with such \nexemption equal to the PJM-approved MW value associated with the applicable PSA; \n2. Ensure that reliability mechanisms producing equivalent reductions in PJM reliability \nrequirements receive equivalent regulatory treatment, regardless of whether those \nreductions are achieved through supply-side capacity additions or forecast-reducing \ndemand-side actions;"},{"page":2,"startToken":278,"endToken":647,"text":"2 \n \n3. Direct PJM to expeditiously modernize Manual 19 Attachment D so that residential \nand commercial customers with eligible technologies, particularly export-capable \ndistributed energy resources, may receive appropriate recognition for verifiable peak-\nreducing performance; \n4. Clarify that, pending Attachment D modernization, PJM may utilize existing Manual 19 \nAttachment B authorities to recognize committed and verifiable demand-side \nreductions that lower load forecasts and Reliability Requirements in the same \nmanner that known load additions increase them; and \n5. Ensure that baseline methodologies utilized under both Attachment B and \nAttachment D properly recognize export-related performance and do not terminate \nmeasurement of performance merely because a resource becomes a net exporter. \nThese issues affect more than individual market participants. Multiple PJM states are \nactively pursuing programs designed to reduce peak demand and capacity obligations \nthrough resources such as battery aggregations, smart thermostats, electric vehicles, and \nVirtual Power Plants (\"VPPs\"). PJM itself has identified Peak Shaving Adjustment \nmechanisms as an important component of Reliability Backstop Procurement flexibility and \npotential state-driven solutions. The success of these initiatives depends upon accurate \nforecasting, appropriate baseline treatment, and equal treatment of equivalent reliability \ncontributions. \nII. LARGE LOADS FUNDING PEAK SHAVING ADJUSTMENTS SHOULD RECEIVE THE \nSAME IRAS CURTAILMENT TREATMENT AS LARGE LOADS UTILIZING BYONC \nTesla respectfully submits that Large Loads funding qualifying Peak Shaving Adjustment \nprograms should receive the same IRAS curtailment treatment as Large Loads utilizing \nBYONC arrangements. \nUnder PJM's proposal, a Large Load that directly procures or funds incremental reliability \nresources through BYONC receives the benefit of that procurement in the form of relief from \nIRAS curtailment obligations. The same principle should apply where a Large Load funds \nreliability through a qualifying Peak Shaving Adjustment that produces a measurable \nreduction in PJM's Reliability Requirement. From a reliability perspective, the outcome is the \nsame. In each case, the Large Load is paying for capacity or reliability benefits that reduce \nthe amount of residual reliability procurement PJM must otherwise secure. \nA Large Load funding a qualifying PSA has already paid to reduce the reliability need that \nIRAS is intended to address. Subjecting that same load to IRAS curtailment obligations while \nexempting a similarly situated BYONC-supported load would effectively require the \ncustomer to pay twice for the same reliability objective."},{"page":3,"startToken":647,"endToken":1029,"text":"3 \n \nThe distinction between the two approaches is one of accounting treatment rather than \nreliability outcome. BYONC-supported megawatts reduce the amount of reliability \nprocurement PJM must otherwise obtain through additional supply. PSA-supported \nmegawatts reduce the amount of reliability procurement PJM must otherwise obtain by \nlowering forecasted reliability requirements. Both mechanisms reduce the quantity of \nremaining reliability procurement required from PJM. Both improve resource adequacy. Both \nreduce obligations that otherwise would have been imposed upon the broader market. \nAccordingly, the exemption from IRAS curtailment obligations associated with a qualifying \nLarge Load-funded PSA should be equal to the MW value approved by PJM for that PSA. \nWhere PJM has determined through its established Peak Shaving Adjustment processes that \na PSA produces a specified reduction in Reliability Requirements, the Large Load \nresponsible for funding that reduction should receive an equivalent MW quantity of relief \nfrom IRAS curtailment obligations. This approach aligns the scope of the exemption directly \nwith the reliability value recognized by PJM, ensures that customers receive credit only for \nverified and approved reliability contributions, and places PSA-funded reliability solutions \non equal footing with BYONC-supported reliability solutions that produce equivalent \nreliability outcomes. \nTesla is aware of no reliability, operational, market design, or regulatory rationale that would \njustify disparate treatment between these equivalent reliability outcomes. To the contrary, \nunequal treatment would materially devalue PSA-supported reliability solutions, undermine \ninvestment in customer-funded peak-shaving programs, and create an artificial preference \nfor one reliability mechanism over another despite equivalent reliability outcomes. \nThe importance of this parity extends beyond individual customer economics. PJM's \nproposed Reliability Backstop Procurement opt-out framework and several emerging state-\nlevel initiatives contemplate circumstances in which Large Loads may fund peak-shaving \nand Virtual Power Plant programs that offset incremental load growth through PSA-based \nmechanisms. The viability of these frameworks depends upon Large Loads receiving \nreliability treatment commensurate with the reliability value they fund. If Large Loads can \nsecure curtailment relief through BYONC but not through a PJM-approved PSA that delivers \nan equivalent reliability benefit, the economic rationale for utilizing PSA-supported solutions \nis substantially diminished. \nAccordingly, the Commission should modify PJM's proposal to ensure that Large Loads \nsupported by qualifying PSA megawatts receive IRAS curtailment relief equal to the PJM-\napproved MW value of the applicable PSA, consistent with the treatment provided to Large \nLoads utilizing BYONC arrangements."},{"page":4,"startToken":1029,"endToken":1457,"text":"4 \n \nIII. PSA PARITY IS ESSENTIAL TO THE SUCCESS OF RBP OPT-OUTS AND STATE-LEVEL \nRELIABILITY INITIATIVES \nThe consequences of unequal treatment extend far beyond individual customer economics. \nMultiple PJM states are actively working toward implementation of technology-neutral \nprograms intended to reduce zonal capacity obligations through dispatchable distributed \nenergy resources and Virtual Power Plants. Many of these initiatives rely, either explicitly or \nimplicitly, upon the Peak Shaving Adjustment framework contained in Manual 19 \nAttachment D. \nLikewise, PJM has identified Peak Shaving Adjustments as a mechanism that may support \nstate-directed approaches to Reliability Backstop Procurement and enable customers or \nstates to address reliability needs through targeted peak reduction efforts. The success of \nthese initiatives depends on a straightforward principle: a Large Load that pays for reliability \nshould receive the reliability value created by that payment. \nThis principle is particularly important for emerging initiatives in Virginia and New Jersey, \nwhere policymakers have explored frameworks under which Large Loads could support \nVirtual Power Plant deployments and peak reduction programs that offset incremental load \nadditions through PSA-based mechanisms.12 Those programs depend upon the ability of \nLarge Loads to fund reliability solutions that reduce PJM Reliability Requirements and \nreceive treatment comparable to that provided under BYONC. \nIf a Large Load funds a PSA-supported reduction in reliability requirements but remains fully \nsubject to IRAS curtailment obligations from which a BYONC-supported Large Load would \nbe exempt, the practical value of the PSA pathway is substantially diminished. Such a result \nwould undermine the economic foundation of the Reliability Backstop Procurement opt-out \nconcept, weaken state-directed reliability initiatives, discourage investment in customer-\n \n1 See, e.g., In the Matter of Establishing New Jersey's Virtual Power Plant Program, N.J. Board of Public \nUtilities, Straw Proposal, Docket No. QO26030099 (filed March 31, 2026), available at \nhttps://nj.gov/bpu/pdf/publicnotice/VPP%20Straw%20Proposal%20Final.pdf (proposing a structured \nstatewide framework to aggregate distributed resources for peak load shaving and grid support); An Act \nConcerning the Provision of Electricity to Certain Data Centers, N.J. Stat. Ann. § 48 (enacted as New Jersey \nBill A796/S731, July 7, 2026), text available at https://njleg.state.nj.us/bill-search/2026/A796 (requiring \nspecial tariffs for data centers with large energy demands to protect grid costs and encourage demand \nreduction measures). \n2 Virginia Senate Bill 371 (Acts of Assembly Chapter 0378), Va. Code Ann. § 56-596.7 (enacted April 8, 2026), \ntext available at https://lis.virginia.gov/bill-details/20261/SB371 (mandating large electric utilities to petition \nfor voluntary demand flexibility programs targeting high energy demand customers to lower total grid system \nload)."},{"page":5,"startToken":1457,"endToken":1791,"text":"5 \n \nfunded reliability solutions, and create an artificial preference among reliability mechanisms \ndespite equivalent reliability outcomes. \nLikewise, limiting PSA eligibility to participants in the RBP would limit the benefits of large-\nload funded PSA-eligible load reduction programs to only a subset of large load coming \nonline in the near future, rather than establishing a more permanent pathway for large load \ncustomers to fund demand-side programs that can reduce zonal capacity obligations and \nprovide immediate ratepayer benefits. \nThe Commission should therefore ensure that Large Load-funded PSA programs receive \ntreatment equivalent to Large Load-supported BYONC arrangements wherever they produce \nequivalent reductions in PJM reliability requirements. \nIV. FEDERAL POWER ACT PRINCIPLES REQUIRE COMPARABLE TREATMENT OF \nEQUIVALENT RELIABILITY OUTCOMES \nSections 205 and 206 of the Federal Power Act prohibit rates, terms, conditions, and \npractices that are unjust, unreasonable, unduly discriminatory, or preferential.3 The \nCommission has long recognized that similarly situated customers and resources should \nnot receive materially different treatment absent a legitimate basis for differentiation.4 \nThe Commission's comparability principles have consistently focused on substance rather \nthan form. Where two mechanisms provide equivalent service, equivalent value, or \nequivalent system benefit, disparate treatment requires a demonstrable justification tied to \noperational or reliability differences. \nThose principles are directly applicable here. \nA Large Load that funds reliability through a qualifying Peak Shaving Adjustment and a Large \nLoad that funds reliability through BYONC have each taken action to reduce PJM's remaining \nreliability procurement requirement. Likewise, a resource that reduces net demand through \nreduced consumption and a resource that reduces net demand through increased exports \ncan produce equivalent reductions in PJM's expected reliability requirements. The reliability \noutcome is what matters. \n \n3 Federal Power Act §§ 205-206, 16 U.S.C. §§ 824d-824e. \n4 See, e.g., Order No. 888, Promoting Wholesale Competition Through Open Access Non-Discriminatory \nTransmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting \nUtilities, FERC Stats. & Regs. ¶ 31,036 (1996); Order No. 890, Preventing Undue Discrimination and \nPreference in Transmission Service, FERC Stats. & Regs. ¶ 31,241 (2007)."},{"page":6,"startToken":1791,"endToken":2066,"text":"6 \n \nAbsent a demonstrated reliability distinction, differential treatment elevates accounting \nform over reliability substance and risks creating an undue preference for one reliability \nmechanism over another. \nAccordingly, the Commission should modify PJM's proposal to ensure that: \n1. Reliability mechanisms producing equivalent reliability outcomes receive equivalent \ntreatment; \n2. Supply-side and forecast-reducing reliability solutions are evaluated on a \ntechnology-neutral basis; \n3. Export-capable distributed resources are not disadvantaged relative to traditional \nload-reducing resources; \n4. Baseline methodologies appropriately recognize both load reductions and export-\nrelated performance; and \n5. PSA-supported reliability contributions funded by Large Loads receive treatment \nequivalent to BYONC-supported reliability contributions where both reduce PJM \nreliability requirements to the same extent. \nSuch treatment is consistent with longstanding Commission policy favoring comparability, \nnon-discrimination, and competition among resources capable of producing equivalent \nreliability benefits. \nV. IMMEDIATE RECOGNITION OF PSA-LIKE DEMAND-SIDE FORECAST REDUCTIONS \nUNDER ATTACHMENT B AND EXPEDITED ATTACHMENT D MODERNIZATION ARE \nNECESSARY REGARDLESS OF THE ULTIMATE IRAS OUTCOME \nRegardless of the Commission's disposition of the broader IRAS proposal, PJM should adopt \nreforms that remove remaining barriers to both supply-side and demand-side participation \nby distributed energy resources and aggregations in order to create simpler pathways for \nmuch-needed capacity to provide untapped value. \nImmediate recognition under existing Attachment B processes of PSA-like demand-side \nforecast reductions, together with expedited modernization of Attachment D, represents \none of the most important near-term opportunities to improve forecast accuracy and \nresource adequacy. \nThese reforms are necessary so that verified peak-reducing resources and programs, \nparticularly those serving residential and small commercial customers with eligible \ntechnologies, and especially resources with injection capability, can be accurately reflected \nas downward adjustments to the load forecast and Reliability Requirement. Doing so will"},{"page":7,"startToken":2066,"endToken":2443,"text":"7 \n \nimprove forecast accuracy, reduce capacity cost exposure for all ratepayers, improve the \naccuracy of zonal reliability signals, allow aggregators to stack wholesale and retail value \nstreams in a non-duplicative manner, and ensure that the growing fleet of residential \nbatteries and other distributed energy resources can contribute to resource adequacy. \nMultiple PJM states are actively working toward implementation of technology-neutral \nprograms specifically designed to reduce zonal capacity purchase obligations for the benefit \nof ratepayers. In order for these programs to work, they explicitly require or will rely upon the \nPeak Shaving Adjustment mechanism under Manual 19 Attachment D. In parallel, PJM has \nidentified Peak Shaving Adjustments as a means through which states, utilities, or Load \nServing Entities may address reliability needs through targeted peak reduction efforts rather \nthan relying exclusively upon traditional procurement pathways. \nThese parallel state and PJM initiatives underscore the urgency of clarifying the application \nof Attachment B to PSA-like demand-side forecast reductions and expediting modernization \nof Attachment D. Without prompt, non-discriminatory operationalization of these Manual 19 \ntools, including modern measurement and verification approaches suitable for residential \nand injection-capable resources, state programs and PJM's own reliability frameworks \ncannot deliver their intended wholesale forecast and Reliability Requirement reductions. \nUnder any IRAS outcome, improved load forecast accuracy and the ability of customers with \neligible distributed energy resources, especially those with injection capability, to provide \nverifiable system benefits are foundational. Manual 19 Attachments B and D already contain \nthe mechanisms necessary to accomplish those objectives. They require only prompt \noperationalization and targeted modernization to ensure that committed and measurable \npeak reductions lower the unrestricted forecast and resulting Reliability Requirement in the \nsame manner that verified load additions increase them. \nVI. ATTACHMENT B SHOULD RECOGNIZE PSA-LIKE DEMAND-SIDE PROGRAMS \nPENDING ATTACHMENT D MODERNIZATION \nAttachment B already establishes a process through which Electric Distribution Companies \nand Load Serving Entities may propose significant forecast adjustments so that PJM's load \nforecast accurately reflects known deviations not captured by the underlying forecast \nmodel. \nTesla is not requesting a new category of load forecast adjustment. Nor is Tesla suggesting \nthat Attachment B lacks authority to recognize forecast reductions. Attachment B already \nprovides a mechanism through which significant forecast adjustments, including \nreductions, may be reflected in PJM's planning assumptions where supported by appropriate \ndocumentation and analysis."},{"page":8,"startToken":2443,"endToken":2788,"text":"8 \n \nRather, Tesla requests that PJM explicitly recognize that committed and verifiable demand-\nside programs designed to reduce peak demand and Reliability Requirements may be \nsubmitted and evaluated under Attachment B using a framework that mirrors the \nestablished Peak Shaving Adjustment process contained in Attachment D. \nSpecifically, demand-side programs seeking Attachment B treatment should be subject to \nsubstantially the same requirements that currently apply to Peak Shaving Adjustments, \nincluding plan documentation, performance commitments, officer certification, data \nsubmission requirements, review processes, and future performance accountability. Doing \nso ensures that forecast-recognized demand reductions are supported by the same level of \nrigor and oversight currently applied to forecast-recognized Peak Shaving Adjustments. \nThe principal area in which Attachment B treatment should differ from the existing \nAttachment D framework is measurement and verification. \nAttachment B should utilize measurement and verification methodologies already \nestablished elsewhere in PJM manuals, including Customer Baseline Load methodologies, \nMetered Generator Output methodologies, and other approaches suitable for export-\ncapable distributed energy resources. Such methodologies should be applied in a manner \nthat appropriately recognizes export-related performance and avoids understating the \nreliability value provided by injection-capable resources, as discussed in Section VII below. \nAt the same time, Attachment D should be modernized on an expedited basis so that the \nsame types of resources can be recognized directly through the Peak Shaving Adjustment \nframework itself and utilize equivalent export-aware measurement and verification \napproaches. \nUnder this approach, Attachment B serves as an immediately available pathway for \nrecognizing committed forecast reductions using the proven administrative framework of \nAttachment D, while Attachment D modernization proceeds through the stakeholder \nprocess. \nThis clarification would improve forecast accuracy, facilitate state-directed peak reduction \ninitiatives, and ensure that committed and measurable demand-side actions lower the \nunrestricted forecast and resulting Reliability Requirement in the same manner that \nsignificant known load additions increase them. \nVII. BASELINE METHODOLOGIES UNDER BOTH ATTACHMENT B AND ATTACHMENT D \nMUST PROPERLY RECOGNIZE EXPORT-RELATED PERFORMANCE \nFor both the interim Attachment B pathway and expedited Attachment D reforms, PJM \nshould ensure that baseline methodologies accurately capture the reliability benefits \nprovided by modern export-capable forecast modifying resources."},{"page":9,"startToken":2788,"endToken":3104,"text":"9 \n \nExisting Manual 11 baselines were developed for demand-side wholesale supply resources. \nLimitations on export, which currently apply to supply resources, should not be imposed on \ndemand-side forecast modifying resources. \nBaseline methodologies should therefore measure actual system impacts rather than rely \nupon assumptions developed for a purely consumptive load environment. \nFor example, a customer may already be exporting power during a system peak event when \na dispatch signal from a smart thermostat, battery aggregation, electric vehicle program, or \nother demand-side mechanism may further reduce load wholesale supply resources. \nThe resulting reliability benefit does not cease once the customer's net consumption \nreaches zero. \nTo the contrary, the system receives additional reliability value because net load reduction \ncontinues to increase beyond that point. \nAccordingly, any Customer Baseline Load methodology utilized under either Attachment B \nor Attachment D should continue measuring performance beyond the point at which exports \nbegin rather than terminating performance recognition at the net-export threshold. \nSimilarly, where Metered Generator Output (\"MGO\") methodologies are utilized under either \nAttachment B or Attachment D to establish performance for battery energy storage systems \nparticipating through Peak Shaving Adjustment programs or comparable forecast-reducing \nmechanisms, the baseline should appropriately exclude prior event days and other \ndistortive operating periods. \nIn particular, where net-metered battery systems have previously discharged during peak \nevents, those event days should not be allowed to suppress future baseline values in a \nmanner that understates actual reliability contributions. Baseline methodologies should \nestimate expected performance absent the reliability action being measured rather than \nembedding prior dispatch events into future baseline calculations. \nThe relevant question should not be whether a resource reduced consumption or increased \nexports. The relevant question should be whether the resource produced a measurable \nreduction in PJM's expected reliability requirement. \nBaseline methodologies under both Attachment B and Attachment D should be designed \naccordingly. \nVIII. CONCLUSION \nFor the foregoing reasons, Tesla respectfully requests that the Commission modify PJM's \nproposal to:"},{"page":10,"startToken":3104,"endToken":3280,"text":"10 \n \n1. Require equivalent treatment of Large Load-funded PSA-supported and BYONC-\nsupported reliability contributions for purposes of IRAS curtailment obligations, \nincluding IRAS curtailment relief equal to the PJM-approved MW value associated \nwith a qualifying PSA; \n2. Apply longstanding Federal Power Act comparability and non-discrimination \nprinciples to ensure that reliability mechanisms producing equivalent reliability \noutcomes receive equivalent treatment; \n3. Ensure that the final IRAS framework preserves the viability of Reliability Backstop \nProcurement opt-outs and state-directed reliability initiatives that rely upon PSA-\nbased mechanisms; \n4. Encourage expedited modernization of Manual 19 Attachment D; \n5. Recognize Manual 19 Attachment B as an appropriate interim mechanism for PSA-\nlike demand-side forecast reductions utilizing the administrative framework of \nAttachment D and modernized measurement and verification methodologies; and \n6. Ensure that baseline methodologies under both Attachment B and Attachment D \nappropriately recognize export-related performance and that MGO and related \nmethodologies appropriately measure net-metered battery performance. \nRespectfully submitted, \nTesla, Inc. \nBy: /s/ Jaden D. Crawford \nJaden D. Crawford \nHead of VPP Policy, North America \nTesla, Inc. \njadcrawford@tesla.com \nDated: September 3, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":605,"startToken":0,"endToken":80},{"p":1,"at":605,"title":"I. INTRODUCTION AND SUMMARY","method":"printed heading","endPage":2,"endAt":1446,"startToken":80,"endToken":463},{"p":2,"at":1446,"title":"II. LARGE LOADS FUNDING PEAK SHAVING ADJUSTMENTS SHOULD RECEIVE THE","method":"printed heading","endPage":4,"endAt":5,"startToken":463,"endToken":1030},{"p":4,"at":5,"title":"III. PSA PARITY IS ESSENTIAL TO THE SUCCESS OF RBP OPT-OUTS AND STATE-LEVEL","method":"printed heading","endPage":5,"endAt":774,"startToken":1030,"endToken":1560},{"p":5,"at":774,"title":"IV. FEDERAL POWER ACT PRINCIPLES REQUIRE COMPARABLE TREATMENT OF","method":"printed heading","endPage":6,"endAt":1122,"startToken":1560,"endToken":1920},{"p":6,"at":1122,"title":"V. IMMEDIATE RECOGNITION OF PSA-LIKE DEMAND-SIDE FORECAST REDUCTIONS","method":"printed heading","endPage":7,"endAt":2118,"startToken":1920,"endToken":2344},{"p":7,"at":2118,"title":"VI. ATTACHMENT B SHOULD RECOGNIZE PSA-LIKE DEMAND-SIDE PROGRAMS","method":"printed heading","endPage":8,"endAt":2359,"startToken":2344,"endToken":2743},{"p":8,"at":2359,"title":"VII. BASELINE METHODOLOGIES UNDER BOTH ATTACHMENT B AND ATTACHMENT D","method":"printed heading","endPage":9,"endAt":2279,"startToken":2743,"endToken":3088},{"p":9,"at":2279,"title":"VIII. CONCLUSION","method":"printed heading","endPage":10,"endAt":1374,"startToken":3088,"endToken":3280}]}