{"document":{"slug":"rec-20260903-5170","title":"Supportive Comments and Limited Protest of the New Jersey Board of Public Utilities re PJM Interconnection, L.L.C.’s filing to establish Interim Resource…","issued":"2026-09-03","accession":"20260903-5170","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"New Jersey Board of Public Utilities","kind":"protest","file":"sources/filings/text/20260903-5170_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5170","tier":"record","sha256":"1c850a066b8233a5f7b43f93382d51323403cc10e5867588030b6cf0900d0441","pages":18,"tokens":5457,"emptyPages":[],"textThemes":["adequacy","registry","flex"]},"pages":[{"page":1,"startToken":0,"endToken":229,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, LLC  \n  \n) \n) \n)  \n   \n                   \nDocket No. ER26-3515-000\n                                         \n \nSUPPORTIVE COMMENTS AND LIMITED PROTEST OF THE NEW JERSEY \nBOARD OF PUBLIC UTILITIES \n \nOn August 13, 2026, PJM Interconnection, L.L.C. (“PJM”) proposed revisions to the \nReliability Assurance Agreement Among Load Serving Entities (“RAA”) and the PJM Open \nAccess Transmission Tariff (“Tariff”) to establish Interim Resource Adequacy Service (“IRAS”).1  \nThis proposed service would be implemented by PJM during periods of insufficient resources to \nreliably meet demand in real-time operations, enabling PJM to prioritize load reduction in \nzones/areas where New Large Loads have not brought their own new capacity or had their capacity \nneeds covered through the Reliability Backstop Procurement (“RBP”).  The New Jersey Board of \nPublic Utilities (“Board”) supports the Proposal with a limited protest, as it presents a largely \nworkable solution to the region’s resource adequacy shortfall and appropriately incentivizes New \nLarge Loads in the region to bring new capacity to the system.   \nI. \nBackground \nPJM is facing a period of unprecedented structural scarcity.  For the first time in history, \nPJM’s Base Residual Auction (“BRA”) for the 2027/2028 Delivery Year (“DY”) cleared short of \n \n1 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large \nLoad Registry to Address System Reliability, Docket No. ER26-3515 (Aug. 13, 2026) (“PJM IRAS \nProposal” or “Proposal”)."},{"page":2,"startToken":229,"endToken":649,"text":"2 \n \nits Reliability Requirement by 6.6 gigawatts (“GW”), 2 and the BRA for the following 2028/2029 \nDY followed suit, clearing 6.8 GW short of PJM’s Reliability Requirement.3  This shortfall is \nlargely attributable to rapid load growth from data centers, as approximately 30 of the 32 GW of \nprojected peak load growth between 2024 and 2030 is attributable to these customers.4  PJM stated \nthat “[t]his onrush of demand has…raised future resource adequacy concerns.”5  This growth is \nforecasted to persist, with PJM predicting summer peak load increases of 65.7 GW over the next \nten years and 96.7 GW over the next 20 years.6   \nTo confront this, PJM held a Critical Issue Fast Path (“CIFP”) Large Load Additions \n(“LLA”) workstream beginning in September 2025,7 and a main discussion point centered on \ndifferential reliability for certain new large load customers.  A PJM Board Decisional Letter \nconcluded this workstream and directed PJM staff to develop the mechanics of this differential \n \n2 PJM Auction Procures 134,479 MW of Generation Resources, PJM Interconnection, L.L.C., 1 (Dec. 17, \n2025), https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2025-releases/20251217-pjm-\nauction procures-134479-mw-of-generation-resources.pdf [https://perma.cc/A89W-W99B]. \n3 2028/2029 Base Residual Auction Report, PJM Interconnection, L.L.C., 3 (July 14, 2026) (“PJM \n2028/2029 BRA Report”), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-\ninfo/2028-2029/2028-2029-bra results-report.pdf [https://perma.cc/A53K-TXXY]. \n4 Letter from David E. Mills, Chair, PJM Board of Managers, to PJM Stakeholders (Aug. 8, 2025), \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2025/20250808-pjm-\nboard-letter-re-implementation-of-critical-issue-fast-path-process-for-large-load-additions.pdf. Since the \nissuance of the August 2025 Board Letter, PJM has published its 2026 Long-Term Load Forecast Report.  \nForecasting improvements have resulted in the peak load forecast for 2030 to be revised downwards by \n875 MW.  However, it still confirms significant growth in the next 20 years.  PJM Interconnection, \nL.L.C., PJM’s Updated 20-Year Forecast Continues to See Significant Long-Term Load Growth, PJM \nInside Lines (Jan. 14, 2026), https://insidelines.pjm.com/pjms-updated-20-year-forecast-continues-to-see-\nsignificant-long-term load-growth/ [https://perma.cc/W3UY-F9HE].  \n5 Ibid.  \n6 PJM Interconnection, L.L.C., 2026 Load Forecast Report Tables tbl.  B1 (2026) (“PJM 2026 Load \nForecast Tables”), https://www.pjm.com/-/media/DotCom/planning/res-adeq/load-forecast/2026-load-\nreport tables.xlsx. \n7 PJM Interconnection, L.L.C., Critical Issue Fast Path – Large Load Additions: Issue Charge (Sept. 15, \n2025), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/2025/20250915/20250915-\nitem-06---critical-issue-fast-path---large-load-additions---issue-charge.pdf."},{"page":3,"startToken":649,"endToken":982,"text":"3 \n \nreliability service.  Specifically, it stated that new LLAs should be subject to curtailment prior to \nthe deployment of pre-emergency Demand Response (“DR”) if they do not offset their growth \nwith incremental generation.8  This initiated a separate stakeholder process to specifically focus \non this differential reliability service, the Connect and Manage (“C&M”) Senior Task Force, which \nwas eventually combined with PJM’s CIFP-RBP.  The stakeholder process for this CIFP concluded \nwith a July 2026 PJM Board Decisional Letter requiring electric distribution companies (“EDC”) \nto implement a similar differential reliability service, though changed to “IRAS,” for new Large \nLoads that do not bring sufficient capacity.9   \nTherefore, PJM’s Proposal at the Federal Energy Regulatory Commission (“FERC”) \nreflects almost a year of deliberation and stakeholder engagement surrounding the feasibility and \npotential implications of implementing such a program.  The Board thinks PJM’s Proposal presents \nthoughtful consideration of the various stakeholder proposals and perspectives and thinks its final \nIRAS plan strikes an appropriate balance between state and federal jurisdictional divisions in the \nFederal Power Act (“FPA”).  While there are certain elements of the Proposal that the Board does \nnot support, these elements are not consequential to the foundational principles or procedures of \nIRAS and could be modified, or severed and rejected, without undermining the overall package \nreforms.10  In some instances, the Board is simply asking for additional clarification from PJM.  \nUltimately, the Board is appreciative of PJM’s leadership role to initiate and lead this mandatory \n \n8 Letter from David Mills, Interim President & CEO, PJM Bd. of Managers, to PJM Stakeholders \n(January 16, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-load-additions.pdf.  \n9 PJM Bd. of Managers, Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop \nProcurement and Connect and Manage (July 27, 2026), https://www.pjm.com/-/media/DotCom/about-\npjm/who-we-are/public-disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-\nprocurement-and-connect-and-manage.pdf. \n10 PJM IRAS Proposal at 9-10 (consenting to FERC’s modification and severance of individual elements \nof the proposed Tariff and RAA language)."},{"page":4,"startToken":982,"endToken":1302,"text":"4 \n \nPJM-led curtailment service and Large Load Registry and thinks it falls squarely within PJM’s \nauthority in maintaining resource adequacy at the wholesale level.  The Board also appreciates that \nPJM is proposing to exclude New Large Loads from future capacity market demand curves if they \ndo not bring their own new capacity onto the system.  This treatment will help protect ratepayers \nfrom capacity market cost increases that would have been caused by future large loads. \nIRAS is an important step to protect the PJM system, but it is only one step of many.  \nCrucially, PJM has workstreams to address the supply-and-demand imbalance alongside IRAS.  \nThese include the RBP, the Expedited Interconnection Track, and the Reliability Resource \nInitiative, which primarily focus on getting new megawatts (“MW”) of supply online.  However, \nit will likely take many years for this new supply to start contributing energy to the grid, with \nproject development timelines extended due to supply chain constraints and siting and permitting \ndelays.  Therefore, IRAS serves as an important operational resource adequacy tool for PJM.  The \nwork is not over, however.  More reforms at the PJM and state levels will be needed to bring \nstability to prices and reliability.  \nII. \nInterim Resource Adequacy Service \nThe Board appreciates PJM’s decision to propose a PJM-led resource adequacy service for \nNew Large Loads that fail to offset their registered peak load with sufficient capacity arrangements \nthrough Bring Your Own New Capacity (“BYONC”) or by being allocated a share of the RBP \nUnforced Capacity (“UCAP”) MW.  PJM’s Proposal is a departure from PJM staff’s Stage 4 CIFP \nRBP/C&M proposal, which envisioned a voluntary state-led program,11 and the Board appreciates \nPJM’s tenacity in advancing a PJM-led program instead.  The PJM-led approach addresses the \n \n11 PJM Interconnection, L.L.C., “PJM Connect & Manage CIFP Proposal Stage 4” (June 23, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02a--\n-pjm-stage-4-proposal---connect-and-manage---executive-summary.pdf."},{"page":5,"startToken":1302,"endToken":1616,"text":"5 \n \ncollective action problem and ensures that ratepayers across the region can be protected, even if \ntheir states and other states pursue different policies for large load developments. \nAt a high level, this new service will enable the grid operator to direct load shed directives \nto each zone/area during grid stress events in an amount commensurate with its uncovered New \nLarge Load capacity.  In other words, PJM is directing a differential reliability service to those \nwho have contributed the most to the grid’s current resource adequacy shortfall, New Large Load \ncustomers.  This tool will help PJM maintain reliability for the system when the grid is short of \ncapacity, specifically helping maintain reliability for existing customers.  Importantly, this \nproposed step will be initiated prior to calling on Pre-Emergency Load Management Reductions \nActions,12 which will help maintain the participation of certain load management reduction \nresources, like DR, by minimizing “fatigue” that can occur from being over-called on during stress \nevents.   \nThe Board thinks the placement for IRAS in PJM’s Emergency Procedures framework \ncreates a strong incentive for New Large Loads to engage in bilateral agreements, which is the best \nway to protect ratepayers from the costs and risks associated with load growth from these \ncustomers while also resulting in new MW of supply to the system.  In sum, the Board thinks this \nProposal: (1) takes a strong initiative to confront the resource adequacy shortfall facing the system \nat large; (2) provides teeth to incentivize New Large Loads to contribute new capacity to the grid; \n(3) respects the state and federal jurisdictional division outlined in the FPA; and (4) avoids the \ncollective action problem of PJM’s previous state opt-in proposal.  The Board will work with \nrelevant state entities, utilities, large loads, and PJM to ensure that the IRAS quantity aligns with \n \n12 PJM IRAS Proposal, Attachments A and B, at Attachment DD-4, section I(b)."},{"page":6,"startToken":1616,"endToken":1941,"text":"6 \n \nEligible New Large Loads in New Jersey’s zones, and to ensure that appropriate policies and \nprotocols are in place to direct IRAS to these Eligible New Large Loads by June 1, 2027.  \n \nLimited Protest - Already-Cleared Resources Should Not Qualify for BYONC \nWhile the Board generally supports the BYONC criteria that PJM lists in Attachment DD-\n4 section VI,13 the Board is not supportive of PJM’s decision to include capacity that cleared in the \nBRAs for the 2027/2028 and 2028/2029 DYs to qualify as BYONC-eligible resources.  The Board \nthinks new capacity to meet BYONC eligibility should be defined as capacity that has not yet \ncleared a Reliability Pricing Model (“RPM”) auction.  Additionally, the Board appreciates that the \nprocess for setting new capacity for the 2029/2030 BRA is underway.  To the extent new resources \nwant to participate in the 2029/2030 BRA and serve as a BYONC resource, they should present \nPJM with a BYONC contract before the auction, as contemplated in Attachment DD-4 section \nVII(c), and commit to acting as a price taker – otherwise new resources clearing in the 2029/2030 \nBRA should likewise not be eligible to serve as a BYONC resource.  \nPrincipally, the Board does not think capacity resources that cleared for the first time in the \nBRAs for the 2027/2028, 2028/2029, and 2029/2030 (if they did not present a BYONC contract \nbefore the BRA, as noted above) DYs should qualify as BYONC because these resources have \nalready been committed to contribute to our system’s reliability.  Frankly, these are not new \nresources that require additional price certainty to enter PJM’s uncertain investment environment, \ntake on risks from federal regulatory uncertainty, and undergo longer project development \ntimelines due to supply constraints and siting and permitting delays.  They are not resources that \nlarge loads brought to the system.  Rather, these are resources that have already committed to come \n \n13 See PJM IRAS Proposal, Attachments A and B."},{"page":7,"startToken":1941,"endToken":2261,"text":"7 \n \nonline in the next few DYs.  Our region is facing an enormous reliability shortfall, considering \nrobust reforms to its wholesale markets, and has implemented and extended a lower maximum \nprice cap through the BRA for the 2029/2030 DY, acknowledging that even the soaring capacity \nmarket clearing price cannot provide the certainty that developers need.  Thus, the BYONC and \nRBP serve an important role in attracting new supply investment that this provision undermines.   \nAllowing already-cleared resources and resources that will newly clear in the 2029/2030 \nBRA to serve as BYONC would allow New Large Load customers with the highest willingness to \npay for firm capacity the ability to direct attractive terms and conditions toward resources that are \nalready committed to coming online.  This will effectively result in New Large Loads being \ngrandfathered into the RPM in the amount of the new MW UCAP between the 2027/2028 and \n2028/2029 DYs, which is 774.314 and 524.7 MW UCAP,15 respectively, of new generation and \ngeneration uprates.  These buyer-side bids should instead be directed to new supply resources that \nmay be able to accelerate their time to commercial operation if they have more attractive bilateral \nand demand-side offers.  Moreover, this provision will allow new large-load data centers to \nsidestep their commitment in the Ratepayer Protection Pledge to “build, bring, or buy the new \ngeneration resources and electricity needed to satisfy their new energy demands,”16 as these \nBYONC commitments would be with supply resources that have already cleared the RPM to serve \nPJM’s broader customer base.   \n \n14 PJM Interconnection, L.L.C., 2027/2028 Base Residual Auction Report 7 (2025) (“PJM 2027/2028 \nBRA Report”), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-\n2028/2027-2028-bra-report.pdf.  \n15 PJM 2028/2029 BRA Report at 3. \n16 The White House, Ratepayer Protection Pledge (March 4, 2026) (“Ratepayer Protection Pledge”), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/."},{"page":8,"startToken":2261,"endToken":2705,"text":"8 \n \nThe Board recognizes that, if new capacity were defined as new supply resources that have \nnot yet cleared any RPM auction, it would result in gap between the beginning of IRAS service \nand the date by which new capacity procured through the next BRA would be expected to come \nonline.  Specifically, IRAS eligibility begins June 1, 2027, while new capacity procured for the \nnext BRA—for the 2029/2030 DY—would not be expected to come online until June 1, 2029.  \nTherefore, New Large Loads that enter into arrangements with otherwise qualifying BYONC \nresources could remain subject to IRAS before those arrangements become effective,17 which may \nexplain why PJM chose to include capacity resources that cleared an RPM auction for the first \ntime in the BRAs for the 2027/2028, 2028/2029, and 2029/2030 DYs.  However, the Board thinks \nthe inclusion of already-cleared resources departs from the core tenets that underpin this Proposal, \nincluding the Ratepayer Protection Pledge and the benefits of BYONC to the system at large.   \nThe Board thinks there are workable complementary protocols to recognize the benefits of \nNew Large Loads in BYONC arrangements even when that capacity is not yet contributing power \nto the grid.  In fact, in its description of its planned IRAS filing, PJM staff recommended to EDCs \nand states that New Large Loads that do not have a BYONC arrangement may be subject to load \nreduction prior to load reduction of New Large Loads that have arranged for BYONC that has not \nyet achieved commercial operation.18  Such a tiered curtailment pathway could complement a \n \n17 There are several exceptions that could shorten this gap.  For example, new supply resources that clear \nin the RBP may have commercial operation dates earlier than 2029 and may not have previously cleared \nan RPM auction.  In that case, Eligible New Large Loads may have a portion of their capacity needs \ncovered by Allocated RBP UCAP MWs as early as June 1, 2028.  Demand-side resources, including \nDemand Resources and DER Capacity Aggregation Resources, may also have shorter development \ntimelines than new-build generation such as a gas combustion turbine or combined-cycle plant.  In \naddition, an Eligible New Large Load could satisfy some or all of its capacity needs through BYONC if \nan otherwise eligible resources clears the Third Incremental Auction (“IA”) for the 2027/2028 DY, \nscheduled for February 2027, or the Second or Third IAs for the 2028/2029 DY, scheduled for July 2027 \nand February 2028, respectively.  \n18 PJM Interconnection, L.L.C., CIFP Framework for Service During Periods of Insufficient Resource \nAdequacy – PJM Proposal 3 (July 27, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-"},{"page":9,"startToken":2705,"endToken":3010,"text":"9 \n \nprovision that requires new capacity to be capacity that has not yet cleared in any RPM auction, \nas New Large Loads with BYONC arrangements could still have a higher level of reliability than \nthose without.   \n \nUltimately, there is no perfect solution.  New large loads are seeking to interconnect at a \npace that supply resources are simply unable to keep up with, leaving PJM with a significant \nresource adequacy shortfall.  However, allowing capacity resources that have already been \ncommitted in the RPM to count toward BYONC will not contribute to resource adequacy and thus, \nthe Board thinks this aspect of the proposed Tariff revisions should be severed. \n \nLimited Protest - IRAS and BYONC Obligations Should Not Expire After Three DYs Without a \nShortfall \nThe Board has concerns with PJM’s provision proposing that, upon three consecutive years \nwith no capacity shortfall,19 IRAS \"goes to sleep,\" relieving existing BYONC of their RPM \nparticipation obligations and rendering New Large Loads' BYONC obligations obsolete.20  PJM’s \nProposal frequently refers to the Ratepayer Protection Pledge as a basis for having data centers \n“build, bring, or buy the new generation resources and electricity needed to satisfy their new \nenergy demands” through a framework that includes IRAS, BYONC, and the exclusion of certain \nNew Large Load amounts from the Variable Resource Requirement (“VRR”) Curve.21  However, \n \nare/public-disclosures/2026/20260727-cifp-framework-for-service-during-periods-of-insufficient-\nresource-adequacy-executive-summary.pdf. To better align with the eligibility requirements in PJM’s \nIRAS proposal, “not yet achieved commercial operation” could be changed to “not cleared an RPM \nauction for that Delivery Year.”  \n19 For purposes of these comments, the Board refers to a DY in which committed capacity, as determined \nafter the Third IA, is less than the PJM Region Reliability Requirement as a DY in which PJM faces a \n“capacity shortfall.” \n20 PJM IRAS Proposal at 72. \n21 See Id. at 109."},{"page":10,"startToken":3010,"endToken":3323,"text":"10 \n \nthis exemption would relieve existing New Large Loads of the obligation to maintain their ten-\nyear new capacity commitments merely because PJM has not faced a capacity shortfall for three \nconsecutive DYs.  \nFurthermore, the Board is concerned about the provision in Attachment DD-4 section VIII(f) \nthat existing BYONC capacity resources will be relieved of their RPM participation obligations \nshould committed capacity equal or exceed the PJM Region Reliability Requirement for three \nconsecutive DYs.22  In line with its other feedback, the Board does not think these obligations \nshould be relieved merely because PJM does not face a capacity shortfall for three consecutive \nDYs.  The Board thinks New Large Loads should only continue to be reflected in the VRR Curve \nwithout corresponding BYONC obligations once their BYONC has completed the applicable \nrequirements outlined in section VIII, including its ten-year RPM participation commitment, and \nhas thereby demonstrated a meaningful and durable contribution to system reliability.  Because \nrelieving BYONC of these obligations also eliminates certain resource-specific RPM participation \nrequirements, this concern is heightened for DR and distributed energy resource (“DER”) Capacity \nAggregation Resources, which would no longer be subject to the BYONC-specific requirement to \nparticipate as an Annual Demand Resource or DER Capacity Aggregation Resource for the ten-\nyear period.  This framework could therefore result in a situation in which committed capacity \nequals or exceeds the PJM Region Reliability Requirement for three consecutive DYs, existing \nBYONC is relieved of its participation obligations, and the subsequent withdrawal of that capacity \ncontributes to a renewed capacity shortfall.23   \n \n22 Id. at Attachments A and B. \n23 The Board also notes that PJM IRAS Proposal Attachment DD-4, section VIII(f) does not expressly \nrelieve the separate ten-year annual demonstration requirement for Demand Resources and DER Capacity \nAggregation Resources in section VII(i)(ii), creating additional ambiguity regarding the obligations that \nremain after the three-year condition is met."},{"page":11,"startToken":3323,"endToken":3601,"text":"11 \n \nLastly, the Board thinks IRAS can continue to be a useful resource adequacy tool even in \nDYs in which PJM does not face a capacity shortfall and thus does not think the service should \n“go to sleep” or that Eligible New Large Loads should permanently lose that status once the system \nhas sufficient capacity.  New Large Loads that have not secured sufficient capacity through \nBYONC arrangements or Allocated RBP UCAP MW should continue to be subject to differential \nreliability and, when system conditions require load reductions, should continue to be called on \nbefore Pre-Emergency Load Management Resources.  At a minimum, previously Eligible New \nLarge Loads should again be subject to IRAS if PJM subsequently re-enters a capacity shortfall.  \nThe Board also requests clarification regarding the interaction between the three-year \nshortfall condition and PJM’s proposed exclusion of New Large Load amounts from the VRR \nCurve.  PJM states that, after three consecutive DYs without a capacity shortfall, all New Large \nLoads effectively become just “Large Loads,” and the in-service date cutoff for “New” Large Load \nresets prospectively once a capacity shortfall reemerges.24  At the same time, PJM indicates that \nNew Large Load amounts without sufficient BYONC or Allocated RBP UCAP MW will remain \nexcluded from the VRR Curve whether or not they are subject to IRAS, stating that securing \nsufficient capacity is the basis for subsequently reflecting such load in the VRR Curve.  Thus, the \nBoard requests clarification that New Large Load amounts previously excluded from the VRR \nCurve will remain excluded notwithstanding the three-year condition unless and until the \nassociated load secures sufficient capacity.   \n \nLimited Protest - BYONC Arrangements Should Be Transferable \n \n24 PJM IRAS Proposal at 72."},{"page":12,"startToken":3601,"endToken":3904,"text":"12 \n \n \nThe Board thinks that BYONC should be transferable for New Large Loads and new supply \nresources.  PJM asserts that “[a]llowing BYONC to leave or be traded after entering into an \narrangement with a New Large Load would dramatically increase the complexity of the program \nwithout commensurate benefit.”25  The Board disagrees.  Transferable BYONC obligations serve \nan important role.  Transferring BYONC can reduce long-term counterparty and performance risk \nand can allow a New Large Load to replace a resource that becomes uneconomic, unavailable, or \notherwise unable to support the arrangement.  It can also allow a large load to transfer its BYONC \nto another large load if the two loads value reliable service differently from each other over time.  \nThe Board thinks there should be more flexibility for New Large Loads and new supply resources \nover the course of the ten-year BYONC term, and the Board suggests PJM and FERC sever this \nrestrictive provision.   \n \nThe Board, however, thinks PJM provides a reasonable accommodation for Demand \nResources and DER Capacity Aggregation Resources.  These resources must show an initial ten-\nyear commitment, but they also have the ability to replace locations and contracts, if needed.  \nHowever, the Board suggests that PJM’s proposed Tariff language provides further clarity on the \neligibility of Demand Resources and DER Capacity Aggregation Resources that may qualify as \nBYONC, because as drafted, the criteria limits the eligibility of these resources to only those \nlocations that have not participated in a prior RPM auction, which may be inappropriate if the \ncharacteristics of the load at such location have changed over time.  The Board requests that PJM \nallow more flexibility and permit a location to participate as a new Demand Resource or DER if \nthe characteristics of the load have changed since it last participated in an RPM auction.  \n \n \n25 Id. at 65."},{"page":13,"startToken":3904,"endToken":4206,"text":"13 \n \nLimited Protest - PJMs Proposed IRAS Compensation Mechanisms Should Be Removed \nThe Board thinks PJM’s compensation structure is ambiguous, unclear, and unnecessary, \nand requests that Attachment DD-4 section X, which puts forth the conditions of compensation for \nIRAS, is severed.  PJM states that whether a particular Eligible New Large Load is entitled to \ncompensation will be determined by state authorities under state law.26  Attachment DD-4 section \nX establishes a wholesale rate of 50% of the Non-Performance Charge Rate unless the Eligible \nNew Large Load elects to accept less compensation or waive it altogether.  The interaction between \nthe rate, state action, and the large load is unclear.  For instance, if a state directs the large load to \nwaive the rate through its retail tariff, is the large load obligated to waive it?  The Board is \nconcerned that this mechanism may be setting up future litigation and disputes about who has the \nright to certain rate treatments.   \nThe Board thinks that the easier path is to sever the provision.  The compensation scheme \nappears intended, in part, to redress loads that may be subject to capacity price obligations even if \nthey do not get the same reliability as other loads on the system.  However, if states wish to \ncompensate Eligible New Large Loads for accepting reduced reliability of service in lieu of \nbringing their own capacity, they can do so through their existing retail ratemaking authority, and \nthe large loads are fully able to challenge those retail ratemaking decisions through the proper \nvenues.  Accordingly, the Board recommends that Attachment DD-4 section X of PJM’s proposed \nTariff revisions be severed.  \nIII. \nLarge Load Registry \nThe Board supports the proposed Large Load Registry and appreciates PJM’s role in \nleading the development and maintenance of such registry.  The Large Load Registry will help \n \n26 Id. at 106."},{"page":14,"startToken":4206,"endToken":4610,"text":"14 \n \nstates and the relevant utilities develop standards and protocols for IRAS.  The Board appreciates \nPJM’s receptiveness in including this in its Proposal after encouragement from stakeholders during \nthe CIFP process.  The Board will work with relevant state agencies, utilities, PJM, and large load \ncustomers, as needed, to ensure the Eligible New Large Loads in this registry are accurate and \nproper protocols are in place ahead of PJM curtailment directives.  \nIV. \nRemoval of Demand from VRR Curve \nThe Board strongly supports PJM’s decision to remove uncovered incremental New Large \nLoad amounts from the VRR Curve.  The Board has advocated for this in many stakeholder \nforums, including direct letters to the PJM Board of Managers from the Board’s President,27 and a \nseparate letter from the Board’s Executive Director on this matter.28   \nThe Board has advocated this position for multiple reasons.  First, if Eligible New Large \nLoads29 subject to IRAS were included in the VRR Curve, the market would signal to these \ncustomers that the system will continue to procure capacity for them.  This would undermine one \nof the core tenets for designating this service to Eligible New Large Loads in the first place, which \nis to provide an incentive for these customers to procure their own capacity.  Additionally, keeping \n \n27 Letter from Christine Guhl-Sadovy, President, New Jersey Board of Public Utilities, to the PJM Board \nof Managers (Mar. 27, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2026/20260401-njbpu-letter-re-connect-and-manage-issue-charge.pdf.  \n28 Letter from Bob Brabston, Executive Director, New Jersey Board of Public Utilities, to the PJM Board \n(Nov. 18, 2025), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2025/20251118-njbpu-staff-re-cifp-lla.pdf.  \n29 “Eligible New Large Loads” is used here consistent with PJM’s definition of Eligible New Large Loads \nin its IRAS Proposal, i.e., “All New Large Loads shall be eligible to provide IRAS and considered \nEligible New Large Loads to the extent the combination of their BYONC arrangements and Allocated \nRBP UCAP MW does not meet their capacity needs.” See proposed Tariff, Attachment DD-4, section \nV(a); see also proposed Tariff, Definitions – Eligible New Large Load (‘“Eligible New Large Loads’ shall \nmean a New Large Load eligible to provide Interim Resource Adequacy Service in accordance with \nTariff, Attachment DD-4, section V.”); proposed Tariff, Attachment DD-4, section IV(a) (“All Eligible \nNew Large Loads shall be available to be requested to provide Interim Resource Adequacy Service by \n[PJM].”)."},{"page":15,"startToken":4610,"endToken":4942,"text":"15 \n \nloads subject to IRAS in the demand stack would cause existing ratepayers to pay to procure supply \nfor these entities, as costs from the RPM are currently socialized across the region.  This would \nconflict with the Ratepayer Protection Pledge.30  Therefore, while the Board has some concerns \nwith aspects of this section, it is an important step toward protecting ratepayers from high costs \nattributable to these customers.  Furthermore, removing these customers from the VRR Curve also \nprotects ratepayers from the risks associated with uncertain New Large Load forecasts, \nappropriately placing this risk on the customers driving that growth rather than requiring existing \nratepayers to procure capacity in advance for load that may not ultimately materialize.  This is \nparticularly relevant as PJM predicts a summer peak load increase of nearly 100 GW over the next \n20 years.31  The Board commends PJM for making the removal of these loads a key component of \nits Proposal.     \nHowever, to reiterate a previous request, the Board seeks clarification that Eligible New \nLarge Loads will not be allowed into the VRR Curve so long as they have not fulfilled their \ncapacity requirement through BYONC arrangements or Allocated RBP UCAP MW if the three-\nyear regional transmission organization (“RTO”) Reliability Requirement criterion is met.  \n \nLimited Protest - The IRAS Trigger Must Account for Eligible New Large Load Amounts \nImportantly, PJM has not made it clear how the capacity shortfall will be determined after \nEligible New Large Loads are removed from the VRR Curve.  Specifically, PJM has not clarified \nwhether the PJM Region Reliability Requirement determined prior to the Third IA and used in \nsection IV(b) is calculated before or after the deduction of the Excluded RTO New Large Load \n \n30 Ratepayer Protection Pledge (“Companies will build, bring, or buy the new generation resources and \nelectricity needed to satisfy their new energy demands, paying the full cost of those resources whether by \nbuilding, or buying from, new or otherwise additive power plants.”). \n31 PJM 2026 Load Forecast Tables."},{"page":16,"startToken":4942,"endToken":5244,"text":"16 \n \nAmounts.  The Board thinks the capacity shortfall determination should account for the Excluded \nRTO New Large Load Amounts used to reduce the VRR Curve.  This clarification is needed to \nbetter understand and evaluate other elements of PJM’s Proposal.  \n \nEnergy Market Costs Should Be Monitored  \nTo the extent that a significant amount of New Large Load elects to interconnect without \nBYONC or Allocated RBP UCAP MW, and thus remain subject to IRAS, energy prices may \nincrease substantially for ratepayers.  We have yet to see how many New Large Loads will choose \nto be subject to IRAS service over seeking bilateral contract arrangements.  However, if a \nsubstantial amount of New Large Load fails to offset its registered peak load with sufficient \ncapacity arrangements through BYONC or Allocated RBP UCAP MW and are subject to IRAS, \nPJM may need to consider additional measures to protect ratepayers from consistently higher costs \nin the energy market.  While there can be financial benefits to having a higher grid utilization rate \nat large, the Board suggests PJM and FERC monitor whether IRAS loads are resulting in \nsubstantially higher energy market costs.  In the future, it may be worth considering further \nincentivizing or requiring New Large Loads to bring commensurate new supply resources with \nthem.  \nV. \nConclusion \nThe Board commends PJM for proposing an RTO-led curtailment program that applies to \nNew Large Loads that have not met their capacity obligations.  The Board also appreciates PJM’s \nproposed removal of Eligible New Large Loads from the VRR Curve, as it will protect ratepayers \nfrom many of the costs and risks associated with New Large Loads in the capacity market and \nbetter incentivize New Large Loads to bring their own new capacity.  However, the Board’s support \ndoes not come without concerns, and the Board requests that certain elements of the Proposal are"},{"page":17,"startToken":5244,"endToken":5381,"text":"17 \n \nsevered where doing so would better uphold the Ratepayer Protection Pledge without significantly \naffecting the Proposal’s core components.  \n \nRespectfully,  \n \nNEW JERSEY BOARD OF PUBLIC \nUTILITIES \n \nBy: /s/ Paul Youchak \n \nIan Oxenham \nAlex Cary \nAmanda Lescano \nTimothy Randazzo \nMahala Lahvis \nAiri Kogishi \nNew Jersey Board of Public Utilities  \n44 South Clinton Ave. \nTrenton NJ 08609 \nPaul.youchak@bpu.nj.gov \nIan.oxenham@bpu.nj.gov \nAlex.Cary@bpu.nj.gov \nAmanda.lescano@bpu.nj.gov \nMahala.lahvis@bpu.nj.gov \nAiri.kogishi@bpu.nj.gov \nMICHAEL ZUCKERMAN \nACTING ATTORNEY GENERAL  \nOF NEW JERSEY \n \nBy: /s/ Steven Chaplar \n \nDeputy Attorney General \nDepartment of Law and Public Safety \nDivision of Law \nP.O. Box 112 \nTrenton, NJ 08625 \nSteven.chaplar@law.njoag.gov \n \nAttorneys for the New Jersey Board of \nPublic Utilities \n \n \n \nDated: September 3, 2026 \n \n \n \nTrenton, New Jersey"},{"page":18,"startToken":5381,"endToken":5457,"text":"18 \n \nCERTIFICATE OF SERVICE \nI hereby certify that, on this 3rd day of September 2026, I have caused the foregoing \ndocument to be served upon each party designated on the official service list compiled by the \nSecretary in this proceeding, by email. \nBy: /s/ Steven Chaplar \nSteven Chaplar \n \n \n \n \n \n \nDeputy Attorney General \n \n   \n \n \n \n \nNew Jersey Office of the Attorney General \nDepartment of Law & Public Safety  \nP.O. Box 112  \nTrenton, New Jersey 08625  \nSteven.chaplar@law.njoag.gov"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1212,"startToken":0,"endToken":164},{"p":1,"at":1212,"title":"I. Background","method":"printed heading","endPage":4,"endAt":1276,"startToken":164,"endToken":1179},{"p":4,"at":1276,"title":"II. Interim Resource Adequacy Service","method":"printed heading","endPage":13,"endAt":1706,"startToken":1179,"endToken":4171},{"p":13,"at":1706,"title":"III. Large Load Registry","method":"printed heading","endPage":14,"endAt":472,"startToken":4171,"endToken":4276},{"p":14,"at":472,"title":"IV. Removal of Demand from VRR Curve","method":"printed heading","endPage":16,"endAt":1334,"startToken":4276,"endToken":5150},{"p":16,"at":1334,"title":"V. Conclusion","method":"printed heading","endPage":18,"endAt":6,"startToken":5150,"endToken":5382},{"p":18,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":18,"endAt":494,"startToken":5382,"endToken":5457}]}