{"document":{"slug":"rec-20260903-5176","title":"Limited Protest of American Municipal Power, Inc. to PJM Interconnection, L.L.C.’s proposal filed on 08/13/2026","issued":"2026-09-03","accession":"20260903-5176","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"American Municipal Power, Inc.","kind":"protest","file":"sources/filings/text/20260903-5176_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5176","tier":"record","sha256":"0394c9aaaefc0f0f965d0513b36329bf8e8510679a703be3e29d1f9c12db45c4","pages":11,"tokens":3228,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":255,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \nLIMITED PROTEST OF \nAMERICAN MUNICIPAL POWER, INC. \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission” or “FERC”),1 American Municipal Power, Inc. \n(“AMP”) submits this limited protest of the August 13, 2026 filing by PJM Interconnection, \nL.L.C. (“PJM”) in the above-captioned docket,2 in which PJM proposes revisions to its \nOpen Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among \nLoad Serving Entities (“RAA”) to establish Interim Resource Adequacy Service (“IRAS”). \nAMP submits this limited protest to express concerns with PJM’s proposal for accrediting \nBring Your Own New Capacity (“BYONC”), which fails to properly account for changes in \naccredited capacity values over time. \nI. \nINTRODUCTION \nPJM is facing an enormous influx of new data center load, which threatens to \nexacerbate the region’s capacity shortfall and impose billions of dollars in additional costs \non existing native load customers. It is imperative that PJM have the tools to \naccommodate these new loads while ensuring reliability and affordability for current \ncustomers. Consistent with the Ratepayer Protection Pledge,3 and longstanding cost \n1  18 C.F.R. § 385.211. \n2\nPJM, Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a \nLarge Load Registry to Address System Reliability, Docket No. ER26-3515-000 (August 13, 2026) (“PJM \nFiling”). \n3  Ratepayer \nProtection \nPledge, \nThe \nWhite \nHouse \n(Mar. \n4, \n2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/."},{"page":2,"startToken":255,"endToken":736,"text":"2 \ncausation principles, existing native load customers should not be required to shoulder \nthe costs or reliability risks attributable to serving these new large loads. The IRAS \nproposal – aside from the concerns discussed below – appears to be a reasonable \nresponse to the challenges presented by new large loads. \nIRAS is “a new supplemental capacity product through which New Large Loads \nprovide a load reduction service that is a tool available to PJM to manage resource \nadequacy shortfalls that would otherwise drive shedding of native loads.”4 New Large \nLoads that are not supported either by capacity from PJM’s proposed Reliability Backstop \nProcurement (“RBP”),5 or by capacity that qualifies as BYONC would be eligible to provide \nIRAS (“Eligible New Large Loads”).6 Under the IRAS proposal, in Delivery Years where \nauctions under PJM’s Reliability Pricing Model (“RPM”) construct fail to procure sufficient \ncapacity to meet reliability requirements, “each Electric Distributor zone/area may be \n4  PJM Filing, Transmittal Letter at 22. The PJM Filing proposes to establish “Large Load” and “New Large \nLoad” as new defined terms. See id. at 5. Large Load is defined as “end-use customer(s) load that has \na cumulative peak load of 50 megawatts or greater at a single electrical site behind one or more points \nof interconnection, where for configurations involving multiple affiliated load facilities or multiple points \nof interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-mile \nradius will be considered a single electrical site as further described in the PJM Manuals.” PJM Filing, \nAttachment A, proposed RAA, Art. 1 - Definitions. New Large Load is defined as: \n[E]nd-use customer load that is either (a) a Large Load that goes into service after June 1, \n2027, or (b) incremental load in-service after June 1, 2027, that increases the existing end-\nuse customer load at a single electrical site that, prior to such incremental load, did not \npreviously meet the definition of Large Load. However, to the extent three consecutive \nDelivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then \nNew Large Load shall mean end-use customer load that is either (a) a Large Load that \ngoes into service after June 1 of the first Delivery Year for which the requirements of Tariff, \nAttachment DD-4, section IV(b)(iii) are not met or (b) incremental load in-service after June \n1 of the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section \nIV(b)(iii) are not met that increases the existing end-use customer load at a single electrical \nsite that, prior to such incremental load, did not previously meet the definition of Large \nLoad. \nPJM Filing, Attachment A, proposed Tariff – Definitions – L-M-N.  \n5\nSee PJM, Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from \nLarge Loads, Docket No. ER26-3380-000 (July 31, 2026). \n6\nSee, e.g., PJM Filing, Transmittal Letter at 69."},{"page":3,"startToken":736,"endToken":1026,"text":"3 \ndirected by PJM dispatchers to reduce load up to the [megawatt] quantity of capacity \nattributable to Eligible New Large Loads in that zone/area.”7\nPJM proposes numerous other Tariff and RAA revisions in support of the IRAS \nframework, including implementation of a Large Load Registry database, and \nestablishment of BYONC as a new category of capacity that would “allow New Large \nLoads to remove themselves—in whole or in part—from the [megawatts] eligible for IRAS \nwhere such loads bring new capacity to the PJM Region.”8 Further, beginning with the \n2029/2030 Delivery Year, “PJM will exclude from the demand curve (i.e., the [Variable \nResource Requirement] Curve used in RPM Auctions) the [megawatts] of New Large \nLoads that have not entered into BYONC arrangements” or do not have any associated \nRBP capacity.9\nAMP actively participated in the Critical Issue Fast Path (“CIFP”) process that \ninformed the development of the IRAS framework.10 During that process, AMP endorsed \n– and continues to endorse – many of the core features of PJM’s IRAS proposal, including \nthe Large Load Registry, offsetting IRAS obligations with BYONC, preserving retail \nregulatory authority over the determination of the end use loads ultimately subject to \nIRAS, and the exclusion of unhedged New Large Loads from the Variable Resource \nRequirement Curve. In general, the PJM Filing proposes a reasonable framework to \n“connect and manage” new large loads in the PJM region. \n7\nId. at 6. PJM would implement IRAS “prior to calling on Pre-Emergency Load Management, placing \nIRAS appropriately at the beginning of PJM’s actions in the event of NERC Energy Emergency Alert \nLevel 1.” Id. at 22; see also id. at 78-80. \n8\nId. at 50. \n9\nId. at 109. \n10 See id. at 15-17."},{"page":4,"startToken":1026,"endToken":1310,"text":"4 \nThere is at least one aspect of the PJM Filing, however, that the Commission \nshould direct PJM to revise, in accordance with PJM’s advance consent to modifications \nthat are consistent with its overarching objectives.11 The Commission should not accept \nPJM’s proposal to fix the level of BYONC for a generation or storage resource at the \nresource’s accredited capacity in the first year it is in an arrangement with a New Large \nLoad.12 PJM’s proposal to fix BYONC at the first-year accreditation level risks over-\ncrediting New Large Loads for BYONC given PJM’s projections that the effective load \ncarrying capability (“ELCC”) of certain resource classes (particularly storage resources) \nwill decline significantly over the next decade. In addition, the PJM Filing does not \nadequately explain how its proposed treatment of BYONC in RPM capacity auctions will \nresult in just and reasonable outcomes in light of projected ELCC changes over time. To \naddress these concerns, PJM should be required to revise its proposal to better account \nfor projected ELCC declines in resources supporting BYONC. \nII. \nLIMITED PROTEST \nA. \nPJM’s proposal to fix the Accredited UCAP of BYONC without \naccounting for declining ELCC could understate the need for IRAS. \nUnder the IRAS framework, capacity that qualifies as BYONC would offset the \namount of New Large Load eligible (i.e., required) to provide IRAS.13 In setting the level \nof this BYONC offset, PJM explains that “[f]or BYONC supported by any resource type \n(generation, storage, and demand-side), the Accredited UCAP of the BYONC ‘shall be \nthe Accredited UCAP for the RPM Auction in which the BYONC cleared for the initial \n11 Id. at 121-25. \n12 See id. at 65-66. \n13 See generally, id. at 50-66."},{"page":5,"startToken":1310,"endToken":1602,"text":"5 \nDelivery Year the BYONC is in an arrangement with the New Large Load.’”14 In other \nwords, the Accredited UCAP of a resource supporting BYONC would be fixed based on \nthe resource’s ELCC in the first Delivery Year that it is supporting New Large Load. \nThe core problem with setting BYONC’s Accredited UCAP based on a single year \nsnapshot is that ELCC is not expected to remain static for every resource category. The \nELCCs of storage resources, in particular, are projected to decline significantly over the \nnext decade, as shown by PJM’s recently posted preliminary ELCC Class Ratings for \nDelivery Years 2028/29 – 2042/43.15\nUnder PJM’s proposal, if a 200 MW New Large Load (after accounting for the \nForecast Pool Requirement), comes online in 2029 and brings 200 MW UCAP of BYONC \nsupported by four-hour Capacity Storage Resources for that year, then the load will have \nno IRAS responsibility in all future years. But PJM’s own projections indicate that by \n2031/2032, that storage resource would be accredited with only 119 MW of UCAP.16\n14 Id. at 66 (quoting Proposed Tariff, Attachment DD-4, sections VII(i)(i)-(ii)). More specifically, the level of \nthe BYONC offset would be set using the Installed Capacity (“ICAP”) equivalent of this Accredited UCAP \nvalue. Id. at 65-66. \n15  Available at: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/postings/preliminary-\nelcc-class-ratings-for-period-dy28-dy42.pdf. \n16  A four-hour battery resource with capacity of 350 megawatts (MW) UCAP could be expected to provide \n200 MW of Accredited UCAP in the 2029/2030 Delivery Year based on the projected ELCC of 57 \npercent. The same 350 MW resource would be expected to provide 119 MW of Accredited UCAP at the \nprojected 2031/2032 ELCC of 34 percent."},{"page":6,"startToken":1602,"endToken":1913,"text":"6 \nGiving New Large Load “credit” for Accredited UCAP of BYONC that exceeds the \nactual ELCC-measured Delivery Year capacity value of the resources supporting the \nBYONC raises reliability concerns under PJM’s IRAS proposal. The portion of a New \nLarge Load that exceeds the ELCC-measured UCAP of a supporting BYONC resource \nis effectively the same as unhedged, Eligible New Large Load, but without the \ncorresponding IRAS load curtailment obligation. PJM could be forced to implement \nemergency procedures driven by such unhedged New Large Loads, with the adverse \nreliability consequences falling broadly on native load customers and those New Large \nLoads that brought sufficient BYONC, in contravention of PJM’s objectives. \nWhile PJM projects most resource classes to have relatively stable ELCCs over \nthe next decade (see the table above), the significant ELCC declines predicted for certain \nresource classes (particularly storage) highlight the need to address potential UCAP \ndeclines for all resources in the IRAS framework. Otherwise, PJM could understate the \namount of New Large Load that should be considered Eligible New Large Load obligated \nto provide IRAS.17\nB. \nPJM has not established that the proposed treatment of BYONC in the \nBase Residual Auction (“BRA”) will result in just and reasonable, and \nnot unduly discriminatory rates. \nBYONC would be required to participate as a price taker in RPM auctions for ten \nconsecutive Delivery Years “to ensure that BYONC clear the auction and obtain a \n17  Notably, PJM proposes to require Demand and DER Capacity Aggregation Resources to demonstrate \ntheir Accredited UCAP values “each year for a 10-year period using the Demand Response or DER \nCapacity Aggregation Resources installed capacity for the first Delivery Year after the BYONC is in an \narrangement with the New Large Load.” PJM Filing, Transmittal Letter at 66 (quoting proposed Tariff, \nAttachment DD-4, section VII(i)(ii) (quotation marks omitted)). No similar requirement applies to \ngeneration or storage resources."},{"page":7,"startToken":1913,"endToken":2296,"text":"7 \ncapacity commitment.”18 Similarly, New Large Loads with BYONC arrangements would \nbe reflected in the Variable Resource Requirement Curve.19 While it is reasonable to \nrequire BYONC to be offered in RPM auctions (and to be offered as a price-taker), PJM’s \nproposal lacks necessary clarity regarding how resources supporting BYONC will be \naccredited for BRA purposes, and how the PJM Filing will result in just and reasonable, \nand not unduly discriminatory outcomes in those auctions. \nAs noted above, PJM specifically proposes that for any generation, storage, or \ndemand-side resource, “the Accredited UCAP of any BYONC shall be the Accredited \nUCAP for the RPM Auction in which the BYONC cleared for the initial Delivery Year the \nBYONC is in an arrangement with the New Large Load.”20 Accredited UCAP is a defined \nterm in the RAA, and denotes the “upper limit on the amount of Unforced Capacity that \nan ELCC Resource can physically provide or offer to provide in the applicable Delivery \nYear.”21 A Tariff provision stating that the “Accredited UCAP” of BYONC will be fixed at \nits initial Delivery Year level indicates that PJM will not account for year-to-year ELCC \ndeclines in resources supporting BYONC. If the fixed “Accredited UCAP” of BYONC \noffered in an RPM auction exceeds the UCAP that would result from applying updated \nELCCs to the underlying resources, PJM would be counting (and customers would be \npaying for) megawatts of Accredited UCAP that may not exist. Such a scenario would \n18 Id. at 55-56. Specifically, proposed Tariff, Attachment DD-4, section VIII(e) provides that “[a]ll BYONC \nin an arrangement with a New Large Load and not qualifying for an exception pursuant to Tariff, \nAttachment DD, section 6.6(g), must be offered into the applicable RPM Auctions as price takers, i.e., \n$0/MW-day UCAP for a 10-year period starting with the first Delivery Year which the BYONC is in an \narrangement with the New Large Load.”  \n19 See PJM Filing, Transmittal Letter at 56. \n20  PJM Filing, Attachment A, proposed Tariff, Attachment DD-4, section VII(i)(i)-(ii) (emphasis added). \n21  PJM Manual 21B, PJM Rules and Procedures for Determination of Generating Capability, Rev. 5 at p. \n21 (effective Jan. 22, 2026). ELCC Resources include Generation Capacity Resources and Demand \nResources. See RAA, Art. 1 - Definitions."},{"page":8,"startToken":2296,"endToken":2613,"text":"8 \nraise significant reliability and rate reasonableness concerns. Further, it would likely have \ndifferential impact on the generators that offer capacity into RPM, with some enjoying \nfixed capacity accreditation over time and others facing the risk of variations in ELCC \nvalues. PJM has not provided a justification for this treatment. \nOn the other hand, if resources supporting BYONC will be subject to the usual \nresource accreditation process for each respective BRA over the ten-year must-offer \nperiod, changes in ELCC over that period could create a divergence between BYONC \nand the New Large Load it is ostensibly supporting. PJM recognizes that New Large \nLoads included in the Variable Resource Requirement Curve should match “the \ncorresponding BYONC MW in the supply stack” in order to prevent “artificial price shifts.”22\nIf the megawatts of BYONC in the RPM auction supply stack are diminished by ELCC \ndeclines, however, the BYONC will not match the corresponding New Large Loads, \nshifting costs to other customers. \nThe PJM Filing does not adequately explain how the proposed treatment of \nBYONC in RPM auctions will produce just and reasonable, and not unduly discriminatory \noutcomes given PJM’s projected ELCC declines for storage and other resources. As with \nthe related issues discussed in section II.A above, revisions to PJM’s proposal are \nrequired to account for the impact of expected ELCC declines in resources supporting \nBYONC.23\n22  PJM Filing, Transmittal Letter at 58. \n23  The risks associated with ELCC declines may be mitigated somewhat by PJM’s proposal that BYONC \nresources revert to ordinary Capacity Resources if PJM has sufficient capacity to satisfy the region’s \nReliability Requirement for three consecutive Delivery Years. See id. at 52 (citing proposed Tariff, \nAttachment DD-4, section IV(b)(iii)). A proviso that New Large Loads and BYONC are essentially “re-\nset” after three Delivery Years without a shortfall, however, does not eliminate the concerns in Delivery \nYears where IRAS is operative."},{"page":9,"startToken":2613,"endToken":2909,"text":"9 \nC. \nThe Commission should direct PJM to modify its proposal for \ndetermining Accredited UCAP for BYONC. \nSeveral solutions were offered during the CIFP process to address concerns about \ndeclining ELCCs for resources supporting BYONC. One approach would be to re-accredit \nBYONC each year, with penalties if the New Large Load exceeds its supporting BYONC, \nand sell-back rights if the BYONC exceeds the New Large Load. While this would be the \nmost accurate approach, PJM argued in the CIFP process that it would add significant \nmonitoring and matching requirements to the IRAS framework. \nAnother approach would be to set a resource’s Accredited UCAP of BYONC for all \nfuture Delivery Years using PJM’s preliminary ELCC Class Ratings projection. Under this \nmethod, PJM would only be required to perform the Accredited UCAP analysis for a \nparticular BYONC resource once, but the analysis would reflect projected declines (or \nincreases) in ELCC over time. Accordingly, a New Large Load would know up-front \nwhether and to what extent it would need to provide for additional BYONC to account for \nELCC declines in its supporting BYONC resources over time.  \nThe use of projected ELCC figures to set BYONC Accredited UCAP would, to be \nsure, still result in some level of mismatch between projected and actual ELCC for \nresources supporting BYONC. Given the potential adverse reliability impacts and cost \nshifts associated with resources that have declining accreditations over time, however, it \nis better to err on the side of capturing these projected declines, albeit imprecisely, rather \nthan use PJM’s “set and forget” approach to accrediting BYONC. \nPJM’s consent to modifications to the PJM Filing should encompass AMP’s \nproposal to better account for ELCC declines in BYONC resources supporting New Large \nLoads. Such a revision is certainly “consistent with PJM’s overarching objectives in this"},{"page":10,"startToken":2909,"endToken":3164,"text":"10 \nfiling,”24 inasmuch as it would more precisely encourage New Large Loads “to address \nthe capacity shortfall caused by their rapid growth, in both speed to interconnection and \nvolume of capacity needed,”25 and better promote “the development of new capacity so \nthat the PJM Region has sufficient capacity to maintain reliability without entering into a \ncapacity shortage and/or having to shed existing native load customers.”26 These \nrevisions would also better reflect PJM’s objective of matching BYONC with \ncorresponding New Large Loads to avoid cost shifts in RPM auctions.27 Finally, directing \nPJM to revise its filing to address the discrete concerns identified by AMP would not \nconstitute the imposition of an “entirely different rate design” in contravention of NRG.28\nIII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, American Municipal Power, Inc. submits \nits limited protest in this proceeding and asks that the Commission consider it in acting \non the PJM Filing.  \nRespectfully submitted, \n/s/ John McCaffrey                \nJohn McCaffrey \nStinson LLP  \n1775 Pennsylvania Avenue NW  \nSuite 800  \nWashington, DC 20006  \n(202) 728-3026  \njohn.mccaffrey@stinson.com \nDated: September 3, 2026\n/s/ Gerit F. Hull                        \nLisa G. McAlister                               \nSenior Vice President & General Counsel  \nGerit F. Hull                                   \nDeputy General Counsel for Regulatory Affairs\nAmerican Municipal Power, Inc.                 \n1111 Schrock Road, Suite 100  \nColumbus, OH 43229                   \n(614) 540-1111 \nlmcalister@amppartners.org \nghull@amppartners.org \n24 Id. at 122. \n25 Id. at 50. \n26 Id. at 59.  \n27 Id. at 58. \n28 NRG Power Marketing v. FERC, 862 F.3d 108, 115 (D.C. Cir. 2017)."},{"page":11,"startToken":3164,"endToken":3228,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, D.C., this 3rd day of September, 2026. \n/s/ John McCaffrey                      \nJohn McCaffrey \nStinson LLP  \n1775 Pennsylvania Avenue NW  \nSuite 800  \nWashington, DC 20006  \n(202) 728-3026  \njohn.mccaffrey@stinson.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":919,"startToken":0,"endToken":133},{"p":1,"at":919,"title":"I. INTRODUCTION","method":"printed heading","endPage":4,"endAt":1108,"startToken":133,"endToken":1200},{"p":4,"at":1108,"title":"II. LIMITED PROTEST","method":"printed heading","endPage":4,"endAt":1130,"startToken":1200,"endToken":1203},{"p":4,"at":1130,"title":"A. PJM’s proposal to fix the Accredited UCAP of BYONC without","method":"printed heading","endPage":6,"endAt":1179,"startToken":1203,"endToken":1778},{"p":6,"at":1179,"title":"B. PJM has not established that the proposed treatment of BYONC in the","method":"printed heading","endPage":9,"endAt":3,"startToken":1778,"endToken":2614},{"p":9,"at":3,"title":"C. The Commission should direct PJM to modify its proposal for","method":"printed heading","endPage":10,"endAt":787,"startToken":2614,"endToken":3033},{"p":10,"at":787,"title":"III. CONCLUSION","method":"printed heading","endPage":11,"endAt":0,"startToken":3033,"endToken":3164},{"p":11,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":437,"startToken":3164,"endToken":3228}]}