{"document":{"slug":"rec-20260903-5183","title":"Motion to Intervene, Protest, and Request for Clarification of PPL Electric Utilities Corporation regarding PJM Interconnection L.L.C.’s Interim Resource…","issued":"2026-09-03","accession":"20260903-5183","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"PPL Electric Utilities Corporation","kind":"protest","file":"sources/filings/text/20260903-5183_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5183","tier":"record","sha256":"2dba3b8f84e416ed15bb6c04282d2eccee5c87650ff49dac81bb369f5eface69","pages":25,"tokens":7823,"emptyPages":[],"textThemes":["adequacy","retail","registry","flex"]},"pages":[{"page":1,"startToken":0,"endToken":381,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \n) \n) \n \nDocket No. ER26-3515-000 \n \nMOTION TO INTERVENE, PROTEST,  \nAND REQUEST FOR CLARIFICATION OF  \nPPL ELECTRIC UTILITIES CORPORATION \nPursuant to Rules 211,1 212,2 and 2143 of the Federal Energy Regulatory \nCommission’s (“FERC” or the “Commission”) Rules of Practice and Procedure, PPL Electric \nUtilities Corporation (“PPL Electric”) respectfully moves to intervene in the above-captioned \nproceeding, provides the following protest (“Protest”), and requests clarification regarding \nPJM Interconnection L.L.C.’s (“PJM”) Interim Resource Adequacy Service (“IRAS”) Filing.4 \nPPL Electric greatly appreciates the work of the PJM Board and staff in acting to \naddress the unique operational, planning, and markets challenges presented by large loads in \nthe PJM Region,5 and PPL Electric remains committed to working towards an enduring \nconnect and manage framework to “meet the moment.”6  It is in this collaborative spirit that \n \n1 18 C.F.R. § 385.211(a)(1) (“Any person may file a protest to object to any application, complaint, petition, order \nto show cause, notice of tariff or rate examination, or tariff or rate filing.”). \n2 18 C.F.R. § 385.212(a)(1) (“A motion may be filed: [a]t any time, unless otherwise provided.”). \n3 18 C.F.R. § 385.214(a)(3) (“Any person seeking to intervene to become a party, other than the entities specified \nin paragraphs (a)(1) and (a)(2) of this section, must file a motion to intervene.”).   \n4 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service & a Large Load \nRegistry, Docket No. ER26-3515-000 (Aug. 13, 2026) (hereafter, the “IRAS Filing”). \n5 Terms not otherwise defined herein shall have the same meaning as set forth in the PJM Open Access \nTransmission Tariff (“Tariff”), the Amended and Restated Operating Agreement of PJM Interconnection, L.L.C. \n(“Operating Agreement”), and the Reliability Assurance Agreement Among Load-Serving Entities in the PJM \nRegion (“RAA”).  Each of these Governing Agreements is currently located under PJM’s “Intra-PJM Tariffs” \neTariff title, available here: https://etariff.ferc.gov/TariffBrowser.aspx?tid=1731. \n6 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026), LaCerte Concurrence at P 6 (“This is not a time \nto be cavalier and dodge the urgent need to meet the moment.”)."},{"page":2,"startToken":381,"endToken":656,"text":"2 \nPPL Electric submits this protest to highlight for the Commission a core reality of the IRAS \nFiling—it is not legally durable on appeal.   \nAs explained below, because of how PJM has drafted its Tariff language, if accepted \nwithout modification, the IRAS Filing would mark the first time in history that the Commission \nwould be requiring the mandatory and involuntary designation of end-use retail customers \n(Eligible New Large Loads) to provide a FERC-jurisdictional wholesale rate service (IRAS), \nand the compulsory provision of that FERC-jurisdictional wholesale rate service (IRAS) to a \nRegional Transmission Organization (“RTO”) pursuant to FERC-approved rates, terms, and \nconditions in a FERC-approved tariff.  While PJM correctly, and consistent with current \nprocess, defers to the applicable Electric Distributor and state/local regulatory authorities in \ndetermining which specific individual Eligible New Large Loads within a given zone should \nactually provide IRAS when called upon, the fact remains that all Eligible New Large Loads \n(end-use, retail customers) within a zone are assigned responsibility by PJM to provide this \nwholesale rate service, pursuant to FERC-jurisdictional rates, terms, and conditions, and must \nprovide this wholesale rate service to PJM when called upon.  This exceeds the Commission’s \nlegal authority under the Federal Power Act (“FPA”), under the plain language of the statute \nand applicable precedents.   \nPPL Electric agrees with Chairman Swett on the need to create “legally durable”7 \nsolutions in this space.  Because PJM has provided the Commission with broad NRG \n \n7 Id. at Swett Concurrence, P 3 (“I wholeheartedly, fully concur with these orders, which we carefully crafted to \nexecute upon the problems the Secretary identified in a manner that is quick, efficient, and legally durable.”)."},{"page":3,"startToken":656,"endToken":1043,"text":"3 \nflexibility8 in this FPA section 2059 proceeding, PPL Electric offers two alternative routes that \nthe Commission could take to ameliorate the jurisdictional challenges for the IRAS initiative.   \nOption 1 -  \nHave PJM’s Tariff language stop at the issuance of the \nOperating Instruction to Electric Distributors to curtail load, and \nleave the rates, terms, and conditions of that load curtailment \nservice to state and local regulatory authorities—many of whom \nhave already signed the Ratepayer Protection Pledge.  This \nwould avoid a scenario where federally imposed obligations are \ncolliding with state and local-jurisdictional law and tariffs, \nincluding the statutory “obligation to serve,” and would provide \na much more jurisdictionally sound legal pathway to effectuate \nconnect and manage under FPA section 201.   \nOption 2 - \nAlternatively, make IRAS a voluntary FERC-jurisdictional \nservice, whereby Electric Distributors and/or large load \ncustomers themselves can voluntarily choose to participate like \nany other wholesale market service provider in PJM (including \ndemand response providers).  Given the enthusiasm with which \nmany large load developers and Electric Distributors have \nsigned the Ratepayer Protection Pledge,10 there should clearly \nbe a high level of interest in voluntarily participating in such a \nprogram.  Such a program would also be consistent with EPSA,11 \nwhere the Supreme Court affirmed the Commission’s ability to \ncreate programs that “lure,” rather than force, end-use retail \n \n8 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) (“NRG”).  See IRAS Filing at 9 (“Nevertheless, \nin the event the Commission deems it necessary, and to help facilitate the Commission’s acceptance of this filing \nwithout delay, PJM provides notice that it consents to the Commission’s exercise of authority to modify and/or \nsever any element of the proposed Tariff and RAA language to the extent necessary and permitted under FPA \nsection 205 and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent \nwith PJM’s overarching objectives in this filing. While the [sic] each of the reforms proposed in this filing is just \nand reasonable and act together to advance important resource adequacy objectives, they may also be considered \ndiscretely.”). \n9 16 U.S.C. § 824d. \n10 \nSee \nRatepayer \nProtection \nPledge, \nThe \nWhite \nHouse \n(Mar. \n4, \n2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.  \n11 FERC v. Electric Power Supply Ass’n, 577 U.S. 260, 286 (2016) (“EPSA”)."},{"page":4,"startToken":1043,"endToken":1295,"text":"4 \ncustomers into participating in FERC-jurisdictional wholesale \nmarkets. \nBeyond this, PPL Electric also highlights below several structural deficiencies in the \nIRAS Filing and respectfully requests that the Commission reject or modify these components, \nconsistent with PJM’s NRG invitation. \nFinally, PPL Electric respectfully requests that PJM and/or the Commission clarify in \nthis proceeding several important policy and implementation details of the IRAS Filing.  \nI. \nMOTION TO INTERVENE \nPPL Electric respectfully moves to intervene in the above-captioned proceeding.  PPL \nElectric is a Pennsylvania corporation and a wholly owned subsidiary of PPL Corporation.  \nPPL Electric is an owner of transmission facilities in PJM Interconnection, L.L.C. (“PJM”), \ndistributes electricity to all retail customers within its service territory in central and eastern \nPennsylvania, and is a provider of last resort under Pennsylvania’s Electricity Generation \nCustomer Choice and Competition Act, 66 Pa.C.S.A. § 2801, et seq.  PPL Electric is a \ndesignated Load Serving Entity in PJM, and a signatory to the PJM Consolidated Transmission \nOwners Agreement (“CTOA”) and the RAA. \nOn August 13, 2026, PJM initiated the above-captioned FPA section 205 proceeding \nby submitting proposed Tariff and RAA revisions to establish IRAS—a service to be \nimplemented by PJM during periods when there are insufficient resources to reliably meet \ndemand in real time operations. \nGiven the direct nexus between the IRAS Filing and PPL Electric’s roles and \nresponsibilities within the PJM Region, PPL Electric has a direct, substantial, and independent \ninterest in this proceeding, which no other party can adequately represent, and respectfully"},{"page":5,"startToken":1295,"endToken":1590,"text":"5 \nrequests that the Commission grant this motion to intervene and that PPL Electric be afforded \nall the rights of a party to this proceeding. \nII. \nPROTEST \nA. PJM’s Proposal Unlawfully Requires the Mandatory and Involuntary Designation \nof End-Use Retail Customers (Eligible New Large Loads) to Provide a FERC-\nJurisdictional Wholesale Rate Service (IRAS), and the Compulsory Provision of \nthat FERC-Jurisdictional Wholesale Rate Service to an RTO, Pursuant to FERC-\nApproved Rates, Terms, and Conditions in a FERC-Approved Tariff. \nThe acute appellate risk presented by the IRAS Filing can be summarized by the \nfollowing five sequential points: \n1. IRAS is a new wholesale rate service, subject to the exclusive jurisdiction of the \nCommission, with rates, terms, and conditions established by the Commission \nunder the Commission-approved PJM Tariff; \n2. PJM’s Tariff language makes clear that Eligible New Large Loads are the entities \nthat provide IRAS as a wholesale rate service—not the Electric Distributor or Load \nServing Entity; \n3. PJM’s Tariff language requires the mandatory and involuntary designation of \nEligible New Large Loads to provide IRAS to PJM, and the compulsory provision \nof IRAS to PJM when called upon by PJM (through an implementing directive \nissued to the applicable Electric Distributor); \n4. Eligible New Large Loads have no contractual privity with PJM, are not subject to \na FERC-jurisdictional load interconnection process, and are not public utilities \nunder FPA section 201;12 and  \n5. The FPA does not grant the Commission the legal authority to force end-use retail \ncustomers to be designated to provide a FERC-jurisdictional wholesale rate service, \nor to compel the provision of that wholesale rate service, pursuant to a FERC-\napproved Tariff. \nPPL Electric describes each of these five points in seriatim below, in subsections II.A.i-v. \n \n12 16 U.S.C. § 824."},{"page":6,"startToken":1590,"endToken":1905,"text":"6 \ni. \nAs proposed, IRAS is a new wholesale rate service, subject to the exclusive \njurisdiction of the Commission, with rates, terms, and conditions established \nby the Commission under the Commission-approved PJM Tariff. \nAs presented by PJM, IRAS is a new wholesale rate service, with rates, terms, and \nconditions established under the jurisdictional authority of the Commission.  This is axiomatic \nfrom the extensive Tariff and RAA revisions that PJM has submitted in this FPA section 205 \nproceeding, covering everything from the definition of the service,13 eligibility requirements \nas to who can provide the service (Eligible New Large Loads),14 and the applicable rates for \nthe service.15  Indeed, proposed Tariff, Attachment DD-4 explicitly states that it “sets forth the \nterms and conditions governing the provision of Interim Resource Adequacy Service.”    \nMoreover, the intended objective of IRAS is clear and unequivocal—“to maintain \nsystem reliability for the purpose of supporting the integration of New Large Loads to the PJM \nRegion that are not in arrangements with new capacity additions to the PJM Region.”16  In \nother words, IRAS serves a fundamentally PJM-specific regional and FERC-centric purpose, \nand is not intended to fulfill any smaller state or local jurisdictional legal function under FPA \nsection 201.   \nAccordingly, as presented by PJM, IRAS is a new wholesale rate service, subject to the \nexclusive jurisdiction of the Commission, with its rates, terms, and conditions codified in the \nCommission-jurisdictional PJM Tariff. \n \n13 See Proposed Tariff, Definitions I-J-K (“Interim Resource Adequacy Service shall mean a load reduction \nservice through which New Large Loads reduce load as directed by the applicable Electric Distributor in response \nto an Interim Resource Adequacy Service Action requested by the Office of the Interconnection. Such reductions \nin load may be eligible for compensation pursuant to Attachment DD-4, section X.”). \n14 See Proposed Tariff, Attachment DD-4, Section V. \n15 Id. at Section X.  \n16 Id. at Section I."},{"page":7,"startToken":1905,"endToken":2182,"text":"7 \nii. \nPJM’s Tariff language makes clear that Eligible New Large Loads are the \nentities that provide IRAS—not the Electric Distributor or Load Serving \nEntity. \nThe Tariff language accompanying the IRAS Filing is unambiguous—Eligible New \nLarge Loads (i.e., end-use retail customers) are the entities that “provide” IRAS as a FERC-\njurisdictional wholesale rate service. \nEligible New Large Loads” shall mean a New Large Load \neligible to provide Interim Resource Adequacy Service in \naccordance with Tariff, Attachment DD-4, section V.17 \nInterim Resource Adequacy Service is a load reduction service, \neffective starting with the 2027/2028 Delivery Year, through \nwhich Eligible New Large Loads may be compensated for \nproviding load reductions requested by the Office of the \nInterconnection to maintain system reliability for the purpose \nof supporting the integration of New Large Loads to the PJM \nRegion that are not in arrangements with new capacity additions \nto the PJM Region;18 \nThe Large Load Registry maintained by the Office of the \nInterconnection, pursuant to the Reliability Assurance \nAgreement, shall inform which New Large Loads are eligible \nto be called on to provide Interim Resource Adequacy \nService;19  \nThe Office of the Interconnection Shall . . . determine the \nmegawatt quantity of New Large Loads eligible to provide \nInterim Resource Adequacy Service in each Electric Distributor \nzone/area for a given Delivery Year.20 \nAll Eligible New Large Loads shall be available to be requested \nto provide Interim Resource Adequacy Service by the Office of \nthe Interconnection.21 \n \n17 Proposed Tariff, Definitions E-F. \n18 Proposed Tariff, Attachment DD-4, Section I(a). \n19 Id. at Section I(c). \n20 Id. at Section II(c). \n21 Id. at Section IV(a)."},{"page":8,"startToken":2182,"endToken":2504,"text":"8 \nFor purposes of removing its eligibility to provide Interim \nResource Adequacy Service, a New Large Load may enter into \narrangements with BYONC supported by one or more resources. \nWhile under PJM’s proposal, Electric Distributors and Load Serving Entities play an \nimportant role in “implementing” IRAS,22 they are not the entities actually “providing” IRAS \nas a wholesale, Commission-jurisdictional rate service to PJM.  This dynamic can be seen \nunder PJM’s proposed compensation scheme as well, where the Eligible New Large Load is \nthe entity entitled to compensation for providing IRAS service, notwithstanding that the \nElectric Distributor and state/local regulatory authorities can determine the implementation \n(and the ultimate applicability) of this compensation.23  \niii. \nPJM’s Tariff language requires the mandatory and involuntary designation \nof Eligible New Large Loads to provide IRAS to PJM, and the compulsory \nprovision of IRAS to PJM when called upon by PJM (through an \nimplementing directive issued to the applicable Electric Distributor). \nUnder PJM’s proposed Tariff language, Eligible New Large Loads (i.e., end-use retail \ncustomers) are automatically designated as IRAS service providers by PJM.  In other words, \ndesignation as an entity that must provide FERC-jurisdictional wholesale IRAS service to PJM \nwhen called upon is mandatory, and this designation is made exclusively by PJM under its \nproposed Tariff language.   \n(c) The Large Load Registry maintained by the Office of the \nInterconnection, pursuant to the Reliability Assurance \nAgreement, shall inform which New Large Loads are eligible \nto be called on to provide Interim Resource Adequacy \nService.24 \n \n22 See, e.g., id. at Section III(a) (“Electric Distributors shall . . . execute the Office of the Interconnection’s \ndirectives to implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in the \nElectric Distributor’s zone/area . .  .”).  See also id. at Section III(c) (“Electric Distributors shall . . . implement \ncompensation program consistent with Tariff, Attachment DD-4, section X.”). \n23 See id. at Section X. \n24 Proposed Tariff, Attachment DD-4, Section I(c)."},{"page":9,"startToken":2504,"endToken":2806,"text":"9 \nAll New Large Loads shall be Eligible New Large Loads to the \nextent that the sum of a New Large Load’s Eligible New Large \nLoad Amount is less than the New Large Load’s registered \npeak load (in MW), as provided in the Large Load Registry. \nNew Large Loads with a cumulative installed capacity \nequivalent of their BYONC arrangements and assigned \nAllocated RBP UCAP MW that equals or exceeds the New \nLarge Load’s registered peak load, as provided in the Large \nLoad Registry, shall not be Eligible New Large Loads. New \nLarge Loads that are located within an FRR Service Area cannot \nbe Eligible New Large Loads.25 \nThe Office of the Interconnection shall . . . identify Eligible \nNew Large Loads.26 \nWhile a New Large Load can theoretically reduce or eliminate its classification as an Eligible \nNew Large Load and as an IRAS service provider via BYONC, this process too is exclusively \ndetermined pursuant to the terms and conditions of the FERC-jurisdictional PJM Tariff. \nFor purposes of removing its eligibility to provide Interim \nResource Adequacy Service, a New Large Load may enter into \narrangements with BYONC supported by one or more \nresources.27 \nOnce designated as an Eligible New Large Load by PJM, PJM’s proposed Tariff \nlanguage states that an Eligible New Large Load “shall” be available to provide IRAS when \nPJM sends out an implementing Operating Instruction to an applicable Electric Distributor.     \nAll Eligible New Large Loads shall be available to be requested \nto provide Interim Resource Adequacy Service by the Office of \nthe Interconnection. \nPJM explains that “in recognition of the jurisdictional divide between PJM and the states \nand/or RERRAs, PJM will not direct reductions to specific New Large Loads pursuant to \n \n25 Id. at Section V(a). \n26 Id. at Section II(b). \n27 Id. at Section V(c)."},{"page":10,"startToken":2806,"endToken":3101,"text":"10 \nIRAS,” but rather, “PJM is leaving it to Electric Distributors, in coordination with the \nappropriate states and/or RERRAs, LSEs, and LSE customers to determine which loads should \nultimately reduce subject to IRAS.”28  This framing of the proposal’s jurisdictional challenges \nmisses the point.  The issue is not about which entity gets to identify the specific individual \nEligible New Large Loads that must provide IRAS when PJM calls for it.  The issue is that, \nwhen called upon to provide IRAS under that process, the Eligible New Large Load cannot \nsay no.  It must, pursuant to a FERC-approved Tariff, provide IRAS as a FERC-jurisdictional \nwholesale rate service to PJM.  Put another way, the jurisdictional concern is not with the \nlogistics of the “top-down,” directive to provide IRAS, but rather with the “bottom-up” \nrequirement that IRAS be provided by the Eligible New Large Load when called upon by the \nElectric Distributor.  Or, as PJM describes it, “IRAS is a supplemental capacity product \nthrough which Eligible New Large Loads may be directed by the Electric Distributor to reduce \ntheir load in response to an Interim Resource Adequacy Service Action called by PJM.”29 \nIndeed, under PJM’s proposed Tariff language, the Electric Distributor is functionally \nlittle more than a conduit to implement PJM’s Operating Instruction.  This fact is built into the \nvery definition of Interim Resource Adequacy Service, and Interim Resource Adequacy \nService Action. \n“Interim Resource Adequacy Service” shall mean a load \nreduction service through which New Large Loads reduce load \nas directed by the applicable Electric Distributor in response to \nan Interim Resource Adequacy Service Action requested by the \nOffice of the Interconnection. Such reductions in load may be \neligible for compensation pursuant to Attachment DD-4, section \nX.  \n \n28 IRAS Filing at 92. \n29 Id. at 74."},{"page":11,"startToken":3101,"endToken":3389,"text":"11 \n“Interim Resource Adequacy Service Action” shall mean an \nOperating Instruction, as defined by NERC, issued from the \nOffice of the Interconnection to reduce load prior to calling on \nPre-Emergency \nLoad \nManagement \nReductions \nafter \ndetermining that available economic real-time supply may not \nbe sufficient to maintain reserves to meet applicable Reserve \nRequirements and/or Interconnection Reliability Operating \nLimits within prescribed limits and prevent cascading outages. \nWhile the Electric Distributor is the entity that is picking the specific individual Eligible \nNew Large Loads to provide IRAS, it is simply a vehicle through which PJM “instruct[s] \nthe implementation of an Interim Resource Adequacy Service Action.” \nStarting with the 2027/2028 Delivery Year, the Office of the \nInterconnection may, in accordance with the Manuals, instruct \nthe implementation of an Interim Resource Adequacy Service \nAction prior to calling on Pre-Emergency Load Management \nReductions Actions after determining that available economic \nreal-time supply may not be sufficient to maintain reserves to \nmeet applicable Reserve Requirements and/or Interconnection \nReliability Operating Limits within prescribed limits and \nprevent cascading outages;30 \nElectric Distributors shall:  \nexecute the Office of the Interconnection’s directives to \nimplement Interim Resource Adequacy Service Actions among \nthe Eligible New Large Loads in the Electric Distributor’s \nzone/area, which is an area within a Zone for which the relevant \nElectric Distributor specifies a separate Obligation Peak Load \nMW value and is a service area of an Electric Distributor that is \na separately identifiable, geographic area bounded by wholesale \nmetering;31 \nThis language does not solve the core jurisdictional problem, since the retail load is \nstill being required to take action pursuant to an FPA jurisdictional tariff.  The obligation under \n \n30 Proposed Tariff, Attachment DD-4, Section I(b). \n31 Id. at Section III(a)."},{"page":12,"startToken":3389,"endToken":3944,"text":"12 \nthe tariff is not on the Electric Distributor, but forwarded onto its retail end-use customers (the \nEligible New Large Loads) to provide the wholesale service under the tariff.   \niv. \nEligible New Large Loads have no contractual privity with PJM, are not \nsubject to a FERC-jurisdictional load interconnection process, and are not \npublic utilities under FPA section 201. \nIn many instances, Electric Distributors32 and Load Serving Entities33 are not public \nutilities by default, as defined in the FPA, and are therefore excluded from the Commission’s \ngeneral rate and transmission jurisdiction under FPA section 201.34  These entities may \nnonetheless voluntarily agree to become subject to a multitude of obligations and requirements \nfrom PJM by virtue of signing the PJM Operating Agreement (for Electric Distributors) and \nRAA (for Load Serving Entities), which in addition to being FERC-filed tariffs,35 are also \ncontracts.  This framework can also apply to end-use retail customers who choose to participate \nin PJM’s demand response market.  These entities are not jurisdictional public utilities solely \n \n32 Under the Operating Agreement, Electric Distributor means “a Member that: 1) owns or leases with rights \nequivalent to ownership electric distribution facilities that are used to provide electric distribution service to \nelectric load within the PJM Region; or 2) is a generation and transmission cooperative or a joint municipal agency \nthat has a member that owns electric distribution facilities used to provide electric distribution service to electric \nload within the PJM Region.”). \n33 Under the Operating Agreement, a Load Serving Entity is defined as “any entity (or the duly designated agent \nof such an entity), including a load aggregator or power marketer, (i) serving end-users within the PJM Region, \nand (ii) that has been granted the authority or has an obligation pursuant to state or local law, regulation or \nfranchise to sell electric energy to end-users located within the PJM Region. Load Serving Entity shall include \nany end-use customer that qualifies under state rules or a utility retail tariff to manage directly its own supply of \nelectric power and energy and use of transmission and ancillary services.”). \n34 16 U.S.C. § 824(b)(1) (“The Commission . . . shall not have jurisdiction . . . over facilities used in local \ndistribution . . .”).  See also 16 U.S.C. § 824(f) (“No provision in this subchapter shall apply to, or be deemed to \ninclude, the United States, a State or any political subdivision of a State, an electric cooperative that receives \nfinancing under the Rural Electrification Act of 1936 or that sells less than 4,000,000 megawatt hours of \nelectricity per year, or any agency, authority, or instrumentality of any one or more of the foregoing, or any \ncorporation which is wholly owned, directly or indirectly, by any one or more of the foregoing, or any officer, \nagent, or employee of any of the foregoing acting as such in the course of his official duty, unless such provision \nmakes specific reference thereto.”). \n35 18 C.F.R. § 35.2(c)(1) (“The term tariff as used herein shall mean a statement of (1) electric service as defined \nin paragraph (a) of this section offered on a generally applicable basis, (2) rates and charges for or in connection \nwith that service, and (3) all classifications, practices, rules, or regulations which in any manner affect or relate \nto the aforementioned service, rates, and charges.”)."},{"page":13,"startToken":3944,"endToken":4414,"text":"13 \nby virtue of selling demand response into PJM’s markets.36  Nonetheless, they may voluntarily \nagree to take on obligations to PJM by becoming PJM Members and executing the Operating \nAgreement.  PJM is correct in its assessment that the Operating Agreement and RAA can and \ndo create these obligations and requirements on entities that are otherwise excluded from the \nCommission’s general rate and transmission jurisdiction under FPA section 201.37  \nYet none of these traditional jurisdictional or contractual “hooks” are present under \nPJM’s IRAS proposal.  Eligible New Large Loads (i.e. end-use retail customers) are required \nto provide IRAS when commanded by PJM (through the Electric Distributor), yet these entities \nare not jurisdictional public utilities under FPA section 201 and have no contractual privity \nwith PJM through which they have voluntarily agreed to assume the obligations associated \nwith providing this service.  These entities have not agreed to undertake such obligations with \nPJM as a condition of their load interconnection, because the terms and conditions of service \nto end-use customers, including their connection to the system, lies solely within the purview \nof individual states and RERRAs, not PJM or FERC.  \n \n36 See, e.g., EnergyConnect, Inc., 130 FERC ¶ 61,031 (2010) (“[W]here an entity is only engaged in the provision \nof demand response services, and makes no sales of electric energy for resale, that entity would not own or operate \nfacilities that are subject to the Commission's jurisdiction and would not be a public utility that is required to have \na rate on file with the Commission. While jurisdictional facilities may include contracts, memoranda and other \nrecords utilized in connection with jurisdictional sales, we do not regard agreements to provide services from only \ndemand response resources to be jurisdictional facilities because they involve agreements to reduce demand, i.e., \nagreements not to purchase electric energy under certain circumstances, rather than agreements to sell electric \nenergy at wholesale. Such agreements are not jurisdictional facilities that cause a seller to be a public utility.”). \n37 IRAS Filing at 46 (“Authority exists today in the Operating Agreement to require Electric Distributors to \nprovide to PJM all System, accounting, customer tracking, load forecasting (including all load to be served from \nits System) and other data necessary or appropriate to implement or administer [the Operating Agreement], and \nthe Reliability Assurance Agreement[.]”).  See also IRAS Filing at 81 (“Indeed, the Operating Agreement \nexplicitly authorizes PJM to coordinate the curtailment or shedding of load, or other measures appropriate to \nalleviate an Emergency, in order to preserve reliability in accordance with NERC, or Applicable Regional Entity \nprinciples, guidelines and standards, and to ensure the operation of the PJM Region in accordance with Good \nUtility Practice and this Agreement where an “Emergency” is defined as a condition that requires implementation \nof emergency procedures as defined in the PJM Manuals.”)."},{"page":14,"startToken":4414,"endToken":4744,"text":"14 \nThe absence of these jurisdictional and contractual “hooks” leads to only one possible \noutcome—PJM’s proposal would use the Commission’s general rate and transmission \njurisdiction under FPA section 201 to directly impose requirements on entities that are \nexcluded from that jurisdiction by the same statutory section, and have not voluntarily agreed \nto become subject to those requirements.  For the reasons described below in the next section, \nthis is beyond the Commission’s legal authority under the FPA, and is not legally durable on \nappeal. \nv. \nThe FPA does not grant the Commission the legal authority to force end-\nuse retail customers to be designated to provide a FERC-jurisdictional \nwholesale rate service, or to compel the provision of that wholesale rate \nservice, pursuant to a FERC-approved Tariff. \nSimply put, in the IRAS Filing PJM is asking the Commission to do something that it \nis not statutorily permitted to do under the FPA.  As the D.C. Circuit has noted on more than \none occasion, “as a federal agency, FERC is a creature of statute, having no constitutional or \ncommon law existence or authority, but only those authorities conferred upon it by \nCongress.”38  There is nothing in the FPA that grants the Commission the legal authority to \nforce end-use retail customers (in this case, Eligible New Large Loads) to be designated to \nprovide a FERC-jurisdictional wholesale rate service (IRAS), or to compel the provision of \nthat wholesale rate service, pursuant to a FERC-approved tariff.  PJM cites to two primary \nlegal authorities in support of the IRAS Filing, but as explained below, neither of these supports \nthe action that PJM is suggesting the Commission take here. \nFirst, PJM cites to the Supreme Court’s ruling in EPSA, correctly noting that there “the \nSupreme Court held that the Commission’s regulation of demand response ‘addresses—and \n \n38 Atlantic City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir.2002) (quoting Michigan v. EPA, 268 F.3d 1075, 1081 \n(D.C. Cir. 2001))."},{"page":15,"startToken":4744,"endToken":5046,"text":"15 \naddresses only—transactions occurring on the wholesale market’ and takes aim at ‘enhanc[ing] \nthe wholesale, not retail, electricity market.”39  PJM also correctly describes the Court’s \nholding that “the Commission’s rules for demand response withstood the Electric Power \nSupply Association’s jurisdictional challenge by respecting the division of federal/state \nauthority set forth in the FPA.”40  Yet EPSA affirmed the Commission’s legal authority under \nthe FPA to set the rates, terms, and conditions of voluntary wholesale demand response \nprograms administered by RTOs.  EPSA is therefore inapposite to the proposition before the \nCommission under the IRAS Filing—the mandatory and involuntary designation of end-use \nretail customers (Eligible New Large Loads) to provide a FERC-jurisdictional wholesale rate \nservice (IRAS) under the PJM Tariff, and the compulsory provision of that service pursuant to \nthe rates, terms, and conditions of the PJM Tariff. \nSecond, PJM similarly cites to the Commission’s 2025 ruling on the Midcontinent \nIndependent System Operator, Inc.’s (“MISO”) Revised Expedited Resource Addition Study \n(“ERAS”) proposal41 for the proposition that placing the responsibility to determine which \nspecific individual Eligible New Large Load will provide IRAS on PJM’s command with state \nand local regulatory authorities is “permissible and not an improper delegation of federal \nauthority to the states.”42  PJM’s reliance on the MISO order is similarly misplaced.  As noted \nabove, the jurisdictional concern is not with the logistics of the “top-down,” directive to \nprovide IRAS, but rather with the “bottom-up” requirement that IRAS be provided by the \nEligible New Large Load when called upon by PJM, through the Electric Distributor.  MISO’s \n \n39 IRAS Filing at 91 (citing EPSA, 577 U.S. at 282, 287).  \n40 Id. (citing EPSA, 577 U.S. at 288-91). \n41 Midcontinent Indep. Sys. Operator, Inc., 192 FERC ¶ 61,064 at P 99 (2025). \n42 IRAS Filing at 92."},{"page":16,"startToken":5046,"endToken":5390,"text":"16 \nERAS proposal created a framework for the expedited study of generator interconnection \nrequests to address urgent, near-term resource adequacy and reliability needs.  It did not compel \ninvoluntary participation in that process.  Importantly, it was also focused on generator \ninterconnection—an area that the Commission has clear jurisdiction over going back at least \nto Order No. 200343 and Tennessee Power.44  The Commission has never claimed such organic \njurisdiction over retail load interconnection, which is the core problem that IRAS seeks to \naddress. \nB. The IRAS Filing Contains Several Structural Deficiencies that Should Be Rejected \nor Modified under PJM’s NRG Invitation.  \ni. \nAllowing Electric Distributors and state and local regulatory authorities to \ndetermine the wholesale rate paid for IRAS service is an impermissible \ndelegation of the Commission’s wholesale rate-making authority under the \nFPA, and violates the Commission’s requirement under Part 35 that rates be \nstated “clearly and specifically” within a filed tariff. \nAs referenced above, IRAS is a wholesale, FERC-jurisdictional service.  Yet PJM’s \nproposed Tariff language would turn over the ability to set and modify the rate paid for this \nwholesale service entirely to entities that do not have the legal authority to set and modify \nwholesale rates—Electric Distributors, and state and local regulatory authorities.  Specifically, \nPJM proposes a rate for IRAS that is equal to 50% of the Non-Performance Charge Rate, but \nnotes that “the wholesale IRAS rate is flexible and can be further reduced to less than 50% of \nthe Non-Performance Charge Rate if the Eligible New Large Load accepts in its retail rate a \n \n43 Standardization of Generator Interconnection Agreements and Procedures, 104 FERC ¶ 61,103 at P 12 (2003) \n(“Order No. 2003”) (“Interconnection is a critical component of open access transmission service, and standard \ninterconnection procedures and a standard agreement applicable to Large Generators will serve several important \nfunctions.”). \n44 Tennessee Power Co., 90 FERC ¶ 61,238, 61,761-62 (2002) (“Tennessee Power”) (finding that interconnection \nis a critical component of open access transmission service and thus is subject to the requirement that utilities \noffer comparable service under the OATT.)."},{"page":17,"startToken":5390,"endToken":5706,"text":"17 \nsum less than 50% of the Non-Performance Charge Rate.”45  To this point, PJM explains that \nit “is not mandating how IRAS-directed load reductions are to be compensated,” but is instead \n“proposing a just and reasonable maximum rate for such service.”46  As PJM further explains, \n“given that the Electric Distributors, in accordance with state programs, will have identified \nthe loads to be reduced, it is the responsibility of the Electric Distributor and its applicable \nstate regulator to determine the appropriate compensation scheme.”47  According to PJM, \nunder its proposal “[w]hether a specific New Large Load may be entitled to compensation for \nprovision of IRAS will be determined by state authorities under state law or RERRA as may \nbe applicable.”48 \nThis is impermissible under the FPA, where only the Commission may set and modify \nrates for wholesale services.  As the Court stated in EPSA, the FPA “leaves no room either for \ndirect state regulation of the prices of interstate wholesales or for regulation that would \nindirectly achieve the same result.”49  The Court highlighted this fact again that very same year \nin Hughes, noting that “[a] State must [] give effect to Congress’ desire to give FERC plenary \nauthority over interstate wholesale rates, and to ensure that the States do not interfere with this \nauthority.”50  PJM’s proposal would not just allow states to “interfere” with FERC’s authority \nover interstate wholesale rates, it would delegate to states, local regulatory authorities, and \nElectric Distributors the ability to set and modify the interstate wholesale rate for IRAS, \n \n45 IRAS Filing at 102.  \n46 Id. at 27. \n47 Id. at 28. \n48 Id. at 106. \n49 EPSA, 577 U.S. at 288 (citing N. Natural Gas Co. v State Corp. Comm’n of Kan., 372 U.S. 84, 91 (1963) \n(internal quotation marks omitted)). \n50 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164 (2016) (“Hughes”)."},{"page":18,"startToken":5706,"endToken":6089,"text":"18 \nincluding the ability to set the rate to $0.  To this point, PJM explains that the “IRAS rate is \ncompensation for a wholesale load reduction service, but the entities to be paid the rate and the \nloads to be charged to support such compensation must be determined at the state level \nconsistent with the Electric Distributor’s state-approved load reduction plans and other state-\napproved programs, rates, and rules.”51  \nBeyond this impermissible delegation, this compensation scheme also fails to meet the \nCommission’s regulations implementing FPA section 205(c), which are unambiguous—clarity \nand specificity are required when rates and charges are filed with the Commission. \nEvery public utility shall file with the Commission and post, in \nconformity with the requirements of this part, full and complete \nrate schedules and tariffs and those service agreements not \nmeeting the requirements of § 35.1(g), clearly and specifically \nsetting forth all rates and charges for any transmission or sale \nof electric energy subject to the jurisdiction of this \nCommission, the classifications, practices, rules and regulations \naffecting such rates, charges, classifications, services, rules, \nregulations or practices, as required by section 205(c) of the \nFederal Power Act (49 Stat. 851; 16 U.S.C. 824d(c)).52 \nThe Commission has explained that an RTO has “[an] obligation to set forth its Commission-\njurisdictional rates clearly and specifically in its tariff.”53  The need to set forth rates and \ncharges “clearly and specifically” is essential for the Commission’s own FPA section 205(c) \nanalysis, as “[a] minimum level of specificity within the tariff is necessary for the Commission \nto determine whether the charges that result are just and reasonable.”54  It is also important in \n \n51 IRAS Filing at 104. This presents jurisdictional issues somewhat similar those at issue in Mass. Dep’t of Pub. \nUtils. v. FERC, 729 F.2d 886, 888 (1st Cir. 1984).  Here, instead of a state directing a public utility to file a \nparticular FERC jurisdictional tariff, the state is setting the rate that is enforced under a federal tariff.  In either \ncase, the state, not the public utility or FERC, is setting the FERC jurisdictional rate. \n52 18 C.F.R. § 35.1(a) (emphasis added). \n53 Cal. Indep. Sys. Operator Corp., 112 FERC ¶ 61,009 at P 114 (2005).  \n54 Id."},{"page":19,"startToken":6089,"endToken":6410,"text":"19 \nfulfilling the fundamental purpose of FPA section 205(c) to provide notice to customers, as the \nrequirement “allows [] customers the opportunity to assess for themselves whether they were \nproperly charged.”55  Yet here, the wholesale rate paid or the charges imposed on funding \ncustomers from PJM’s proposed Tariff language in proposed Attachment DD-4, Section X, are \nunascertainable because the specific wholesale rate actually charged would be determined by \nentities wholly outside of the PJM Tariff.  Furthermore, the delegation of the wholesale rate \nsetting function to Electric Distributors and state/local regulatory authorities would deny \ncustomers the protections afforded by FPA section 206.  If a customer viewed a charge for \nIRAS as too high, or not properly implemented, a complaint under FPA section 206 would be \nof little use, since the rate is being set outside of the PJM Tariff by entities other than the \nCommission, where FPA section 206 is legally incognizable. \nii. \nPJM has not explained why it is appropriate to exclude New Large Loads \nfrom the VRR Curve to avoid charging customers, simultaneously charge \nthose same customers in order to pay New Large Loads to provide IRAS, and \ndeploy IRAS before demand resources for which customers have already been \ncharged via the capacity market. \nUnder the IRAS Filing PJM proposes to, beginning with the 2029/2030 Delivery Year, \nexclude from the demand curve (i.e., the VRR Curve used in RPM Auctions) the MW of New \nLarge Loads that have not entered into BYONC arrangements or do not have Allocated RBP \nUCAP MW, over and above the MW of New Large Loads that were included in the load \nforecast for the 2028/2029 Delivery Year.56  This, by definition, means that end-use retail \ncustomers (including the New Large Loads themselves) will receive the benefit of not being \ncharged for the capacity necessary to support these New Large Loads.  However, these benefits \n \n55 Id. \n56 IRAS Filing at 109."},{"page":20,"startToken":6410,"endToken":6713,"text":"20 \nare not sustained under PJM’s proposal since customers would be separately charged to \ncompensate Eligible New Large Loads for providing IRAS.57  This concept stands out even \nmore when considering that, according to PJM, IRAS will be deployed before demand \nresources that customers have already paid for via the capacity market.58  In other words, under \nPJM’s proposal: (i) customers (including New Large Loads themselves) will receive the \nbenefit of not being charged for capacity by virtue of New Large Loads being excluded from \nthe VRR Curve; (ii) customers will then be charged anyway in order to pay Eligible New Large \nLoads to provide IRAS; and (iii) PJM will deploy IRAS before calling demand resources, \nwhich customers have already paid for via the capacity market.  PJM has simply not justified \nwhy this approach is logically consistent from a policy perspective, much less just and \nreasonable under FPA section 205. \niii. \nPJM’s Proposed Tariff Language Fails to Require Any Geographic Nexus \nBetween BYONC Generation and the Load It is Intended to Offset, Which \nWill Shift Generation Constraints Into Transmission Constraints and Impose \nAdditional Costs on Other Customers.   \nPJM’s proposed BYONC provisions impose no requirement that generation supporting \na BYONC arrangement be located in the same Locational Deliverability Area, Zone, or other \ndefined geographic proximity to the New Large Load it is intended to offset.59  This issue was \nraised repeatedly during the Critical Issue Fast Path (“CIFP”) process, where the Joint EDCs \nand other stakeholders proposed various locational requirements for BYONC, but the PJM \nBoard declined to adopt any such requirement.  As a Transmission Owner in PJM, PPL Electric \nis concerned that allowing BYONC generation to be sited anywhere on the system, without \n \n57 See Proposed Tariff, Attachment DD-4, Section X. \n58 IRAS Filing at 74-75, 79. \n59 See id. at 23, 50-55."},{"page":21,"startToken":6713,"endToken":7008,"text":"21 \nregard to its proximity to the load it offsets, will not eliminate resource adequacy risk so much \nas convert generation-related constraints into transmission-related constraints.  These \ntransmission constraints must then be addressed via new transmission facilities that take years \nto plan, permit, and build, and the costs of which will ultimately be borne by other zonal \ncustomers.  PJM has failed to justify why these eminently foreseeable cost shifts under the \nIRAS Filing are just and reasonable under FPA Section 205. \nIII. \nREQUEST FOR CLARIFICATION \nPPL Electric respectfully requests that PJM or the Commission provide clarification in \nthis proceeding on several important components of the IRAS Filing.  \nFirst, PPL Electric requests that PJM confirm on the record in this proceeding that it \ncan in fact implement the mechanisms contemplated by the IRAS Filing between the requested \neffective date of October 26, 2026, and June 1, 2027, when IRAS would become available for \nuse by PJM as a wholesale rate service.  Because so much of the IRAS Filing relies on \ncooperation among PJM’s fourteen distinct state jurisdictions and the diverse array of local \nregulatory authorities, Electric Distributors, and Load Serving Entities therein, this \nconfirmation by PJM may very well help put these jurisdictions “on notice” as to the \nexpectation and spur action to prepare.  PPL Electric remains concerned that this timeframe is \nsimply too short for all of these external, non-PJM actors to stand up implementation regimes, \nbut an “on-the-record” guidepost from PJM, the Commission, or both may help motivate at \nleast some of these entities to seize the initiative and “meet the moment.”60 \nSecond, PPL Electric requests that PJM provide further detail in this proceeding \nregarding how RBP UCAP MWs will be allocated to a given zone for purposes of offsetting \n \n60 Supra note 6."},{"page":22,"startToken":7008,"endToken":7287,"text":"22 \nIRAS responsibilities.  Under PJM’s proposed Tariff, Attachment DD-4, section IX, each \nElectric Distributor allocated RBP UCAP MWs must inform PJM of how RBP UCAP MWs \nshould be further allocated among the New Large Loads located in the Electric Distributor’s \nzone/area.  However, in the event that the Electric Distributor has not informed PJM of how \nits RBP UCAP MWs should be further allocated by April 1 before a given Delivery Year, PJM \nmust then allocate the RBP UCAP MWs to the Electric Distributor’s zone/area pro-rata among \nall New Large Loads located in the zone/area.  PPL Electric is concerned about the practical \nlogistics of this proposal and the potential for inconsistency in allocation methods, given the \nextreme diversity among Electric Distributors and state/local regulatory authorities across the \nPJM Region.  Additional detail from PJM in this proceeding regarding its expectations and \nhow it plans to deal with this contingency would be helpful as PPL Electric and other entities \nlook to implementation.  \nThird, PPL Electric requests clarification on the application of UCAP and ICAP in the \ncontext of BYONC.  While PJM proposes to define BYONC as “megawatts of Unforced \nCapacity that meet the eligibility criteria set forth in Tariff, Attachment DD-4, section VI,”61 \nPJM also notes that “the ICAP equivalent of this Accredited UCAP value is used to reduce a \nNew Large Load’s potential IRAS availability.”62  PPL Electric is unclear from the IRAS \nFiling as to the reasoning for using these two different values in these two different contexts, \nand requests further explanation from PJM as to the implications of using these two very \ndifferent values.   \n \n61 Proposed Tariff, Definitions A-B. \n62 IRAS Filing at 65-66."},{"page":23,"startToken":7287,"endToken":7595,"text":"23 \nFourth, PPL Electric seeks clarity from PJM regarding the requirement in proposed \nTariff, Attachment DD-4, Section VII(e), which states that “BYONC that is in an arrangement \nwith a New Large Load must remain in such arrangement with that New Large Load unless \nand until the New Large Load is permanently out-of-service.”  PPL Electric is unclear if the \npurpose of this provision is that a BYONC must stay in an arrangement with a New Large \nLoad for the term of the contract underpinning the BYONC arrangement, or if the purpose of \nthis provision is to force BYONC MWs to permanently be associated with that New Large \nLoad.  It is also unclear if this obligation expires once BYONC has participated as a price taker \nfor the first 10 years.  PPL Electric requests that PJM provide clarification on this point as well. \nFifth, PPL Electric requests clarification regarding an apparent inconsistency between \nPJM’s proposed Tariff language and its transmittal letter description of the IRAS compensation \nscheme.  While the transmittal letter states that “it is the responsibility of the Electric \nDistributor and its applicable state regulator to determine the appropriate compensation \nscheme,”63 proposed Tariff, Attachment DD-4, Section X contains no reference to any Electric \nDistributor or state/RERRA role in setting or approving the compensation rate.  Rather, it \naddresses only a New Large Load’s own “election” to reduce or waive the applicable rate.64 \nPPL Electric requests that PJM clarify how the state/RERRA role described in the transmittal \nletter is intended to be implemented under the actual proposed Tariff language, and, if that role \nis not reflected in the Tariff, that PJM revise proposed Section X accordingly. \nFinally, PPL Electric requests that PJM clarify whether and how PJM intends to address \nthe transmission cost-shifting risk created by geographically unconstrained BYONC \n \n63 Id. at 28.  \n64 Id. at 107."},{"page":24,"startToken":7595,"endToken":7765,"text":"24 \narrangements, as noted above.  To this end, PPL Electric requests that PJM clarify whether it \nwould consider adopting a preference, even short of a strict requirement, for geographic \nconcentration between BYONC generation and the New Large Load it supports, given the \ntransmission planning and cost allocations described above.  \nIV. \nCONCLUSION \nWherefore, for the foregoing reasons, PPL Electric respectfully requests that the \nCommission grant PPL Electric’s timely intervention in this proceeding and accept this Protest \ninto the record.  PPL Electric also requests that either PJM or the Commission provide \nadditional clarity regarding the items described above in Part III, and provide any additional \nguidance deemed appropriate. \n \nRespectfully submitted, \n \nSteven Nadel \nSenior Counsel \nPPL Services Corporation  \n645 Hamilton Street, Suite 601  \nAllentown, PA 18101  \nTel: (610) 774-4102 \nSMNadel@pplweb.com \n/s/ Thomas DeVita      \nThomas S. DeVita \nKimberly B. Frank \nK&L Gates LLP  \n1601 K Street, N.W.  \nWashington, DC 20006 \nTel: 202.778.9064 \nkimberly.frank@klgates.com \nthomas.devita@klgates.com \n \nCounsel for PPL Electric \nDated: September 3, 2026"},{"page":25,"startToken":7765,"endToken":7823,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nRespectfully submitted, \n/s/Stuart Robbins \nAssociate  \nK&L Gates LLP \n1601 K Street, NW \nWashington, DC 20006 \nTel: 202-778-9148 \nstuart.robbins@klgates.com \n \n \nDated: September 3, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":474,"startToken":0,"endToken":1106},{"p":4,"at":474,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":5,"endAt":145,"startToken":1106,"endToken":1320},{"p":5,"at":145,"title":"II. PROTEST","method":"printed heading","endPage":5,"endAt":159,"startToken":1320,"endToken":1322},{"p":5,"at":159,"title":"A. PJM’s Proposal Unlawfully Requires the Mandatory and Involuntary Designation","method":"printed heading","endPage":16,"endAt":569,"startToken":1322,"endToken":5129},{"p":16,"at":569,"title":"B. The IRAS Filing Contains Several Structural Deficiencies that Should Be Rejected","method":"printed heading","endPage":21,"endAt":534,"startToken":5129,"endToken":6793},{"p":21,"at":534,"title":"III. REQUEST FOR CLARIFICATION","method":"printed heading","endPage":24,"endAt":337,"startToken":6793,"endToken":7644},{"p":24,"at":337,"title":"IV. CONCLUSION","method":"printed heading","endPage":25,"endAt":0,"startToken":7644,"endToken":7765},{"p":25,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":25,"endAt":384,"startToken":7765,"endToken":7823}]}