{"document":{"slug":"rec-20260903-5185","title":"Motion to Intervene and Comments of The Retail Energy Supply Association re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service","issued":"2026-09-03","accession":"20260903-5185","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"The Retail Energy Supply Association","kind":"comments","file":"sources/filings/text/20260903-5185_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5185","tier":"record","sha256":"86ac81e0920d9259dd11d1e515faa953ad3d54bfe4f5c7ca40785c06a7e41c39","pages":9,"tokens":2374,"emptyPages":[],"textThemes":["flex"]},"pages":[{"page":1,"startToken":0,"endToken":281,"text":"4928-6149-2173.1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C.  \n) \n Docket No. ER26-3515-000 \nMOTION TO INTERVENE AND COMMENTS OF \nTHE RETAIL ENERGY SUPPLY ASSOCIATION \nPursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission’s \n(“Commission’s”) Rules of Practice and Procedure, 18 C.F.R. §§ 385.211 and 385.214, the \nRetail Energy Supply Association (“RESA”)1 hereby files this Motion to Intervene and \nComments in the above-referenced proceeding, in which PJM Interconnection, LLC (“PJM”) \nseeks to revise the Reliability Assurance Agreement (“RAA”) of its Open Access Transmission \nTariff (“Tariff”) to establish Interim Resource Adequacy Service (“IRAS”).  IRAS would be a \nservice utilized solely during periods when there are insufficient resources to reliably meet \ndemand in real time operations.       \nRESA files these Comments to express the need for market certainty, stability and clarity \nand the importance of the granular allocation of costs using principles of cost causation.   As \ndescribed below, significant changes to the PJM market design can cause harm if implemented to \nupset settled expectations of Market Participants and if a change in market design creates rate \n1\nThe comments expressed in this filing represent the position of the Retail Energy Supply Association \n(RESA) as an organization but may not represent the views of any particular member of the Association.  Founded \nin 1990, RESA is a broad and diverse group of more than twenty retail energy suppliers dedicated to promoting \nefficient, sustainable and customer-oriented competitive retail energy markets.  RESA members operate throughout \nthe United States delivering value-added electricity and natural gas service at retail to residential, commercial and \nindustrial energy customers.  More information on RESA can be found at www.resausa.org."},{"page":2,"startToken":281,"endToken":505,"text":"2 \n4928-6149-2173.1 \nshock. In particular, RESA does not believe that compensation is appropriate for large loads that \nare curtailed when they are allowed to interconnect and receive service prior to all necessary \ninfrastructure being in place.  In support of this Motion to Intervene and Comments, RESA \nsubmits as follows: \nI. \nMOTION TO INTERVENE \nA. \nCorrespondence and Communications \nCorrespondence and communications regarding this matter should be addressed to the  \nfollowing person(s), and the same should also be designated for service on the Commission’s  \nofficial list for this proceeding: \nElizabeth W. Whittle  \nCharles Iannello \nNixon Peabody LLP \nInterstate Gas Supply, LLC \n799 Ninth Street, N.W. \n6100 Emerald Parkway \nSuite 500 \nDublin, OH 43016 \n \nWashington, DC 20001 \n217-899-2537 \n202-585-8338  \ncharlie.iannello@igs.com\newhittle@nixonpeabody.com\nB. \nRESA \nRESA is a non-profit trade association of independent corporations that are involved in the \ncompetitive supply of electricity and natural gas to end-use consumers.  RESA and its members \nare actively involved in retail electricity and natural gas markets throughout the United States in \nstates that have implemented markets that allow entities other than the incumbent electric or natural \ngas utility to provide commodity electric and gas service. RESA members are Load Serving \nEntities (“LSEs”) active in the following RTO/ISOs: PJM, ISO New England, Inc. (“ISO-NE”), \nMidcontinent Independent System Operator, Inc. (“MISO”), New York Independent System"},{"page":3,"startToken":505,"endToken":912,"text":"3 \n4928-6149-2173.1 \nOperator, Inc. (“NYISO”), and California Independent System Operator, Inc. (“CAISO”).  RESA \nmembers possess market-based rate authority from the Commission.   \nC. \nMotion to Intervene  \nOn August 13, 2026, PJM made a filing to modify the RAA provisions of its Tariff to \nimpose IRAS that would enable PJM to prioritize load reduction in zones/areas where New Large \nLoads have not brought their own new capacity or had their capacity needs covered through the \nReliability Backstop Procurement (“RBP”).  New Large Loads would be able to avoid the \ncondition on taking transmission service by bringing new capacity to the system.  According to \nPJM, the IRAS proposal is within the Commission’s jurisdiction, but acknowledges that the states \nwill have a role in load reduction.   \nRESA, with members who are active in PJM markets, have an interest in this proceeding \nthat cannot be represented by any other party, moves to intervene. \nII. \nCOMMENTS \nPJM’s IRAS proposal includes three substantive tariff changes in addition to creating the \nprogram.  First, PJM proposes to modify the RAA to “clarify” that it is the LSE’s obligation to \nbring new capacity in an amount equal to or greater than its New Large Loads’2 peak load or be \n2\nPJM proposes to add definitions for Large Load and New Large Load.  “Large Load” is defined as “end-\nuse customer(s) load that has a cumulative peak load of 50 MW or greater at a single electrical site behind one or \nmore points of interconnection, where for configurations involving multiple affiliated load facilities or multiple \npoints of interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-mile \nradius will be considered a single electrical site as further described in the PJM Manuals.”  “New Large Load” is \ndefined as “ end-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) \nincremental load in-service after June 1, 2027, that increases the existing end-use customer load at a single electrical \nsite that, prior to such incremental load, did not previously meet the definition of Large Load. . . .”  The proposed \ndefinition notes that if there are three consecutive Delivery Years where there is no capacity shortfall, then New \nLarge Load means: “end-use customer load that is either (a) a Large Load that goes into service after June 1 of the \nDelivery Year for which the requirements of Tariff, Attachment DD-4, section IV9b)(III) are not met or (b)"},{"page":4,"startToken":912,"endToken":1235,"text":"4 \n4928-6149-2173.1 \nsubject to load reduction during Emergencies prior to Pre-Emergency Load Management \nResponse.3   Second, PJM proposes to modify the RAA to establish a Large Load Registry that \nwill be maintained by PJM with information submitted by third parties.  This Large Load Registry \nwill “aid PJM in administering recent resource adequacy initiatives, including IRAS.”4\nFinally, beginning with the 2029/2030 Delivery Year, PJM proposes to exclude certain \nNew Large Loads from the Variable Resource Requirement (“VRR”) Curve.  PJM asserts that the \neffect of this change is to “protect residential customers from capacity price increases. . . .”5\nUnder IRAS, PJM may direct any Electric Distributor zone/area to reduce load up to the \nMW quantity of capacity attributable to Eligible New Large Loads in the zone/area.  The Electric \nDistributor affected by this direction will determine which load to reduce, consistent with state \nregulatory rules.  In short, IRAS is “a mechanism to support reliability while allowing New Large \nLoads to connect even when new capacity supply lags behind load growth.”6\nA. The Commission Should Reject PJM’s Proposal to Compensate New Large Loads \nfor Curtailment \nOne additional feature of IRAS is that New Large Loads would be compensated to the \nextent that they reduce load when directed by PJM.7  The proposed rate would equal 50% of the \nNon-Performance Charge Rate.  PJM notes that the rate could be lower if the New Large Load \nincremental load in-service after June 1 of the first Delivery Year for which the requirements of Tariff, Attachment \nD-4, section IV9b)(iii) are not met that increases the existing end-use customer load at a single electrical site that, \nprior to such incremental load, did not previously meet the definition of Large Load.” \n3\nIRAS filing letter at 4. \n4\nIRAS filing letter at 5. \n5\nIRAS Filing letter at 5-6. \n6\nIRAS Filing letter at 14. \n7\nSee, PJM Proposed Tariff, Attachment DD-4, sections IV(b)(i)-(ii)."},{"page":5,"startToken":1235,"endToken":1570,"text":"5 \n4928-6149-2173.1 \naccepts in its retail rate something less.  PJM attempts to distinguish compensation under IRAS \nfrom other load reduction by alleging that current rapid load growth in Large Loads is different \nthan historical load growth, “in both their inherent concentration of demand and the rapidity at \nwhich their cumulative demands have grown throughout PJM.”8 In short, under the IRAS, a New \nLarge Load can interconnect, but must either bring its own capacity or provide IRAS.   \nWhile these Large Loads may be a primary reason for the rapid load growth in PJM, \ninterconnecting and receiving service before there is capacity to support the New Large Load is \nthe benefit that Large Loads receive by participating in PJM before such capacity is available to \nsupport them.  There should be no reason to also compensate the Large Load for being curtailed \nwhen that is the result of the benefit of their bargain.  Moreover, PJM’s proposed compensation \nmethodology, along with the uncertainty as to the actual rate that will be paid once each state \nmakes that determination, creates significant market uncertainty.  Section X(b)(ii) of the IRAS \nTariff clearly states that LES’s will incur charges to compensate large loads for reductions.9  This \nrisk cannot be appropriately hedged or managed by an LSE and, therefore, adds uncertainty to the \nmarket.  Any compensation to a large load customer is a penalty to the customers in that Electric \nDistributor’s Zone. \nRESA asks that the Commission take note of the need for market certainty and stability \nand the importance of granular cost allocations consistent with cost causation principles.10  In light \n8\nIRAS Filing letter at 99. \n9        \nPJM Proposed Tariff, Attachment DD-4, section X (b)(ii). \n10\nCost causation requires “all approved rates reflect to some degree the costs actually caused by the customer \nwho must pay them.”  K N Energy v FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); Midwest ISO Transmission \nOwners v FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004)."},{"page":6,"startToken":1570,"endToken":1865,"text":"6 \n4928-6149-2173.1 \nof today’s ever increasing capacity prices, rate shock caused by mis-allocated costs will cause \nsignificant harm to those entities who are not causing the costs to increase.  While there are \nsignificant risks posed by the RBP that RESA identified in its Protest, IRAS adds to those risks.   \nAny New Large Load that is curtailed would not have been on the PJM system had it not \nmade the agreement to interconnect without providing necessary capacity.  The New Large Load \nagrees to be curtailable in exchange for IRAS.  The interconnection of the New Large Load without \ncapacity is the benefit and compensation is duplicative and would reward a New Large Load taking \nIRAS.  Here, compensation for IRAS is not consistent with cost causation principles and is unjust \nand unreasonable.  In fact, as noted by PJM, a zero-dollar “rate” is consistent with the Ratepayer \nProtection Pledge.11\nB. Market Certainty, Transparency and Stability are Critical to Market \nParticipants, such as RESA Members \nRESA members purchase services in the RTO/ISO markets such as energy, capacity and \nancillary services, but they offer more than just electricity service to their customers.  Competitive \nretail suppliers may provide retail energy to end-use customers at contracted fixed or variable \nprices which are tied to wholesale electricity prices.  Retail suppliers may offer demand response \nservices – assisting customers in reducing peak demand and receiving benefits for reducing \nconsumption at peak times.  Retail suppliers may offer energy efficiency services to assist \ncustomers in reducing their electricity consumption.  Retail suppliers may offer electricity with a \ncertain component of renewable energy – or all renewable energy.  There is no one model – \n11\nRatepayer Protection Pledge, The White House (Mar. 4, 2026), \nhttps://www.whitehouse.gov/releases/2026/03/ ratepayer-protection-pledge/ [https://perma.cc/N8PH-K82T] \n(“Ratepayer Protection Pledge”)."},{"page":7,"startToken":1865,"endToken":2173,"text":"7 \n4928-6149-2173.1 \ncompetitive wholesale markets and the introduction of retail choice in states such as Ohio, Illinois, \nPennsylvania, New Jersey, Delaware and Maryland, have allowed significant innovation, which \nhas reduced consumption of energy, lowered prices, and provided valuable services to consumers.   \nCompetitive retail suppliers operate in an environment of risk.  Retail suppliers are unlike \ntraditional utilities in several important ways.  For example, retail suppliers are not cost-based \nregulated by state public utility commissions (although they comply with a myriad of state \nrequirements to be authorized to provide energy-related products and services to retail customers).  \nRetail suppliers do not have a mechanism to defer costs, like traditional utilities, and thus bear the \nrisk of wholesale market volatility and uncertainty.  Retail suppliers do not have a specified service \narea.  They contract with customers bilaterally.  Generally, these contracts are long-term – of a \nduration of one to five years. As a result, when a contract expires, it may or may not be renewed. \nThus, a customer today may not be a customer tomorrow.  As a result, charges allocated to a utility \nservice area or load zone must be properly allocated to the appropriate retail end use customer, \neven if the customer has changed suppliers or returned to default service (i.e. the customer is served \nby different LSEs).   \nTo offer valuable and innovative services at competitive prices, retail suppliers \nparticipating in competitive wholesale markets require market certainty, transparency and stability.  \nMarket certainty, transparency and stability allow retail suppliers to offer products and services \nthat they know they can deliver during the term of the applicable contract.  The importance of \nhaving confidence in the competitive wholesale market cannot be overstated.  As with products \nand services offered by retail suppliers, the contracts vary by company, by service, by customer \ntype, by term and other conditions.  If competitive retail suppliers are participating in default"},{"page":8,"startToken":2173,"endToken":2323,"text":"8 \n4928-6149-2173.1 \nservice programs, those programs often require winning suppliers to agree to a standard form \ncontract, which may or may not address unanticipated market changes, including changes to \ncapacity cost allocations caused by RBP and the new IRAS.   \nThis IRAS program, especially when coupled with the RBP, filed by PJM in Docket No. \nER26-3380, may fundamentally alter the risks and credit exposure of all customers in a utility \nservice area depending on how IRAS is implemented.12\nWHEREFORE, RESA respectfully requests that RESA’s Motion to Intervene is granted \nand its Comments considered by the Commission in this proceeding.  \nRespectfully submitted, \nElizabeth W. Whittle \nElizabeth W. Whittle \nCounsel for \nThe Retail Energy Supply Association \nOf Counsel: \nNixon Peabody LLP \n799 9th Street, N.W. \nSuite 500 \nWashington, DC 20001 \n202-585-8338 \newhittle@nixonpeabody.com\nDated: September 3, 2026 \n12\nOn August 21, 2026, RESA filed a Protest of the RBP."},{"page":9,"startToken":2323,"endToken":2374,"text":"4928-6149-2173.1 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document, via email, on each \nperson listed on the Official Service List compiled by the Secretary in this proceeding. \nDated in Washington, DC this 3rd day of September 2026. \nElizabeth W. Whittle\nElizabeth W. Whittle"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":328,"startToken":0,"endToken":331},{"p":2,"at":328,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":2,"endAt":353,"startToken":331,"endToken":335},{"p":2,"at":353,"title":"A. Correspondence and Communications","method":"printed heading","endPage":2,"endAt":874,"startToken":335,"endToken":407},{"p":2,"at":874,"title":"B. RESA","method":"printed heading","endPage":3,"endAt":182,"startToken":407,"endToken":527},{"p":3,"at":182,"title":"C. Motion to Intervene","method":"printed heading","endPage":3,"endAt":958,"startToken":527,"endToken":654},{"p":3,"at":958,"title":"II. COMMENTS","method":"printed heading","endPage":4,"endAt":1119,"startToken":654,"endToken":1084},{"p":4,"at":1119,"title":"A. The Commission Should Reject PJM’s Proposal to Compensate New Large Loads","method":"printed heading","endPage":6,"endAt":913,"startToken":1084,"endToken":1717},{"p":6,"at":913,"title":"B. Market Certainty, Transparency and Stability are Critical to Market","method":"printed heading","endPage":9,"endAt":18,"startToken":1717,"endToken":2325},{"p":9,"at":18,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":319,"startToken":2325,"endToken":2374}]}