{"document":{"slug":"rec-20260903-5189","title":"Protest of Office of the Ohio Consumers' Counsel to PJM Interconnection, L.L.C.'s 08/13/2026 Interim Resource Adequacy Service Filing","issued":"2026-09-03","accession":"20260903-5189","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Office of the Ohio Consumers' Counsel","kind":"protest","file":"sources/filings/text/20260903-5189_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5189","tier":"record","sha256":"d54bb7f9aa9f048ee31e82aed5f55be08b8c9dfef3abac53cf5612e2927f0093","pages":39,"tokens":10975,"emptyPages":[],"textThemes":["flex","registry","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":104,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C.  \n) \nDocket No. ER26-3515-000 \nPROTEST BY \nOFFICE OF THE OHIO CONSUMERS’ COUNSEL \nMaureen Willis  \nOhio Consumers’ Counsel \nAngela O’Brien \nDeputy Consumers’ Counsel  \nOffice of the Ohio Consumers’ Counsel \n65 East State Street, Suite 700 \nColumbus, Ohio 43215 \nTelephone: (614) 466-9531 \nangela.obrien@occ.ohio.gov\nDenise C. Goulet \nMcCarter & English, LLP \n1301 K Street, N.W. \nSuite 1000 West \nWashington, D.C. 20005 \n(202) 753-3400 \ndgoulet@mccarter.com\nSpecial Counsel to the Ohio Office of the Attorney \nGeneral for the Office of the Ohio Consumers’ \nCounsel \nSeptember 3, 2026"},{"page":2,"startToken":104,"endToken":323,"text":"i \nTable of Contents \nI.\nBACKGROUND ............................................................................................................... 3\nII.\nPROTEST .......................................................................................................................... 7\nA.\nPJM’s IRAS proposal to compensate IRAS load for curtailments is \npatently unjust, unreasonable, and unduly discriminatory or \npreferential and fails to protect existing consumers. ................................................... 10\nB.\nFERC should direct PJM to modify the IRAS proposal to include \nstate consumer advocates in the list of those allowed to access \nconfidential information in the proposed new Large Load Registry. ........................ 20\nC.\nThe IRAS Proposal is Unjust and Unreasonable because it fails to \naddress resource adequacy constraints caused by Existing Large Load \ncustomers (pre June 2027 large loads). ......................................................................... 23\nD.\nPJM’s proposal to rely on state programs for curtailment and \nallocation of IRAS program costs to retail consumers is unjust and \nunreasonable. ................................................................................................................... 26\nE.\nPJM’s failure to include a penalty for New Large Load customer non-\ncompliance or under-performance of curtailment directives is unjust \nand unreasonable. ........................................................................................................... 28\nF.\nThe IRAS proposal is unjust and unreasonable because it does not \ncontain sufficient protections against double recovery by New Large \nLoads of incentive compensation for curtailments. ..................................................... 32\nG.\nFERC should consider directing PJM to directly assign curtailment \nobligations and related costs to the New Large Loads driving the \nreliability concerns on the grid due to their failure to bring generating \nassets to the system to satisfy their capacity obligations. ............................................ 33\nIII.\nCONCLUSION ............................................................................................................... 34"},{"page":3,"startToken":323,"endToken":549,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \nPROTEST BY \nOFFICE OF THE OHIO CONSUMERS’ COUNSEL \nOn August 13, 2026, PJM Interconnection, L.L.C.’s (“PJM’s”) filed an application in this \ncase to implement a new Interim Resource Adequacy Service (“IRAS”). PJM requests an \nOctober 12, 2026 effective data with the IRAS beginning in the 2027/2028 capacity auction \nDelivery Year.   \nOCC supports PJM’s proposal to interrupt New Large Loads that connect to the grid \nwithout sufficient supporting capacity before curtailing residential and other existing consumers.   \nHowever, that proposal does not guarantee that it is the New Large Loads that will be curtailed, \nleaving other consumers at risk of bearing the burden of those curtailments.  Additionally, OCC \ndoes not support PJM’s proposal to compensate those New Large Loads for interruptions that are \nan inherent condition of their receipt of service without providing adequate capacity for their \nobligations. While the IRAS proposal would establish curtailment conditions for new data \ncenters and large loads (at least 50 MW) that lack sufficient capacity, it fails to ensure that \nresidential consumers will be protected from the costs or operational risks of IRAS.   \nPJM’s proposal will impose excessive rates and curtailments of service on existing \nconsumers in Ohio—consumers who are not causing the incurrence of these costs and operating"},{"page":4,"startToken":549,"endToken":870,"text":"2 \nconditions.1 It will unreasonably shift the risks and costs associated with acquiring new capacity \nfor large data center loads away from those very customers onto existing consumers in Ohio and \nelsewhere in PJM.  It also will put existing Ohio consumers at risk of reduced reliability by \nsubjecting them to potential curtailments of electric service when large data center load \ncustomers fail to bring sufficient new generating capacity to satisfy their electricity needs.  \nPJM’s proposal essentially places existing Ohio consumers at risk of subsidizing both the cost \nand consequences of resource inadequacy for large data center loads.   \nAs discussed below, the Federal Energy Regulatory Commission (“FERC”) should reject \nthose portions of the filing that fail to protect Ohio consumers and other consumers in PJM from \nthe risks and costs associated with large data center load. PJM’s proposal will result in excessive, \nunjust, unreasonable and unduly discriminatory and preferential rates for existing Ohio \nconsumers.   \nThe Office of the Ohio Consumers’ Counsel is the statutory representative of millions of \nOhio residential utility consumers, per R.C. Chapter 4911.  OCC actively participates in \nnumerous state and federal regulatory proceedings, including proceedings before FERC. OCC \ntimely intervened in this case on September 3, 2026.2  Ohio residential consumers may be \nadversely affected if FERC accepts PJM’s proposed IRAS filing without modification. The \nproposal would require other consumers to pay for resource inadequacy risks and related costs \nthat they did not cause, i.e., risks and costs associated with obtaining adequate generating \ncapacity to satisfy the loads of new Artificial Intelligence (“AI”) and large data center customers.   \n1 This Protest is submitted pursuant to Rule 211 of the Federal Energy Regulatory Commission Rules of Practice \nand Procedure, 18 C.F.R. § 385.211. \n2 Doc-less Motion to Intervene in PJM Interconnection, L.L.C., Docket No. ER26-3515-000, filed by Office of the \nOhio Consumers’ Counsel, available on FERC’s e-library website as Accession Document No. 20260903-5029."},{"page":5,"startToken":870,"endToken":1205,"text":"3 \nI.\nBACKGROUND \nPJM proposes to implement the IRAS proposal starting with the June 1, 2027 Reliability \nPricing Model (“RPM”) Delivery Year.3 The filing proposes to require New Large Loads to be \nautomatically enrolled for IRAS if they fail to bring sufficient capacity to satisfy their capacity \nobligations.4 PJM offers no proposal to address existing large loads that affected the capacity \nauctions run prior to the June 1, 2027 cutoff.   \nPJM represents in the filing that it “hosts the largest concentration of data center load in the \nworld.”5  It states that its load forecast “predicts peak load growth of 32 gigawatts [(“GW”)] from \n2024 to 2030, 30 GW of which is projected to be from data centers.”6 PJM explains that the \n2027/2028 RPM base residual auction (“BRA”) cleared over 6,600 MW short of the region’s \nreliability requirement, and that the 2028/2029 RPM capacity auction cleared over 6,800 MW short \nof that requirement.7 In other words, PJM represents that the addition of new supply has not kept \npace with rapid large load demand growth, thus giving rise to the significant tightening of the \ncapacity market in recent years and subsequent resource adequacy shortfalls.8  To mitigate the \npotential reliability risks associated with resource adequacy shortfalls, PJM proposes the IRAS “as a \n3 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Proposal of PJM Interconnection, L.L.C. to Establish \nInterim Resource Adequacy Service and A Large Load Registry to Address  System Reliability at 7 (Aug. 13, 2026) \n(“IRAS will be available starting with the 2027/2028 Delivery Year, i.e., June 1, 2027”) (hereinafter “IRAS \nApplication”). \n4 IRAS Application at 22 (“PJM is proposing Interim Resource Adequacy Service, a new supplemental capacity \nproduct through which New Large Loads provide a load reduction service that is a tool available to PJM to manage \nresource adequacy shortfalls that would otherwise drive shedding of native loads.”) \n5 Id. at 13. \n6 Id.\n7 Id. at 14. \n8 Id. at 13."},{"page":6,"startToken":1205,"endToken":1572,"text":"4 \nmechanism to support reliability while allowing New Large Loads to connect even when new \ncapacity supply lags behind load growth.”9\nPJM proposes to define “New Large Load” as an “end-use customer load that is either (a) \na Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June \n1, 2027, that increases the existing end-use customer load at a single electrical site that, prior to \nsuch incremental load, did not previously meet the definition of Large Load.”10  After June 1, 2027 \nand going forward, PJM proposes that to the extent three consecutive Delivery Years fall short of \nprocuring capacity needed to serve all loads on the system, New Large Load shall mean end-use \ncustomer load that is either (a)  Large Load that goes into service after June 1 of the first Delivery \nYear for which the capacity procurement requirements of the Tariff are not met or (b) incremental \nload in-service after June 1 of the first Delivery Year for which the capacity procurement \nrequirements of the Tariff are not met.11 PJM, however, does not explain the justification for the \ncut-off or how pre-existing Large Loads in PJM’s forecasts will be treated.\nNew Large Load customers would be excluded from the RPM capacity auctions to be run \nstarting with the 2029/2030 Delivery Year unless and until these customers can acquire the \ngenerating capacity needed to serve their loads.12  PJM represents that excluding both the loads \nand capacity of these New Large Load entities from the RPM BRAs would protect residential \nconsumers from the costs associated with serving such loads.13  Although the New Large Load \n9 Id. at 13-14.   \n10 Id. at 1, n.2. \n11 Id. \n12 Id. at 23. \n13 Id. at 23-24.  The central risk is that this protection works only if the large load is genuinely interruptible.  If a \nstate lacks an enforceable curtailment mechanism (see infra) or the large load fails to reduce, PJM will have \nexcluded its demand from capacity procurement while still allowing it to consume electricity. Exiting consumers \nwould then bear the reliability consequences. There should be a tested, legally enforceable interruption arrangement \nand penalties to secure performance."},{"page":7,"startToken":1572,"endToken":1841,"text":"5 \ncustomers’ loads would be excluded from the auctions, PJM would still allow these entities to \nconnect to and receive electricity from the system.14\nIf there are resource shortages in any given year, PJM dispatchers would call an IRAS \nemergency before calling on certain other load shedding events.15 PJM dispatchers would direct \nthe Electric Distributor(s) in whose zone(s) the New Large Loads that have not procured \nsufficient generating capacity are located to shed load in an amount necessary to address the \nresource shortages.16 PJM anticipates implementing IRAS when “(1) it is no longer able to \nmaintain reserves in the RTO or a zone; or (2) there are insufficient resources to keep IROLs \n[Interconnection Reliability Operating Limits] within defined operating limits in order to prevent \ninstability, uncontrolled separation, or cascading outages that adversely impact the reliability of the \ninterconnection.” 17\n PJM proposes to leave the question of who within each zone would have to shed the load \nneeded to restore system reliability to the states.18  In other words, the states would have to set up \nthe rules for retail curtailments.19 It is possible under this proposal that an Electric Distributor \ncould shut off power to all customers in the zone, even existing consumers, during the emergency \nif a state does not have a program to protect residential and other consumers from these PJM-\ndirected curtailments.20  Ohio currently does not have such a program.\n14 Id. at 13-14. \n15 Id. at 75, 79. \n16 Id. at 79. \n17 Id. at 75. \n18 Id. at 82-85. \n19 Id. at 86-87. \n20 Id. at 90-91."},{"page":8,"startToken":1841,"endToken":2130,"text":"6 \nPJM also proposes to “compensate” the New Large Loads for the interruption through a \nnew federal charge imposed on the Electric Distributor.21 PJM likened its proposal here to the \nPre-Emergency Load Response Program in which it compensates entities willing to discontinue \nservice at an early stage of the emergency causing the need for curtailment.22 PJM states that the \nIRAS compensation charge is for “a wholesale load reduction service, but the entities to be paid the \nrate and the loads to be charged to support such compensation must be determined at the state \nlevel.”23 States could work out an arrangement with the New Large Load that would have the \nNew Large Load forego compensation, thus saving other consumers in the zone from having to \npay those costs.24\nAlthough the IRAS proposal applies only to New Large Loads, PJM proposes to maintain \na Large Load Registry that would incorporate information on all Large Loads in the region, \nincluding information that identifies the entities, their peak loads, their locations and Electric \nDistributor zones, their in-service dates, peak load shaving capability, if any, ramp rates, back-up \ngeneration if any, and other related information.25  PJM proposes to define Large Load as “end-\nuse customer(s) load that has a cumulative peak load of 50 megawatts or greater at a single \nelectrical site behind one or more points of interconnection . . . .”26 PJM further proposes that for \nconfigurations involving multiple affiliated load facilities or multiple points of interconnection with \naffiliated load facilities behind them, “all affiliated load facilities within a one-mile radius will be \n21 Id. at 99. \n22 Id. at 99-100.   \n23 Id. at 104. \n24 Id. at 105. \n25 Id. at 28-29, and 37.   \n26 Id. at 31."},{"page":9,"startToken":2130,"endToken":2427,"text":"7 \nconsidered a single electrical site as further described in the PJM Manuals.”27 PJM represents that it \nwill provide access to that information on a confidential basis to authorized state commissions, \nTransmission Owners, the Independent Market Monitor for PJM (“IMM”), Electric Distributors, \nFERC and Load Serving Entities.28  PJM argues the purpose of the Registry is to provide \ntransparency and “key information” for state and retail entities.29 But under PJM’s proposal, \nindependent state consumer advocates are not permitted access to the confidential registry.    \nThe filing provides additional details regarding how the proposed new IRAS would be \nimplemented.  While OCC is not providing a complete summary of all those details in this \nProtest, it has summarized above the foundational elements that raise significant concerns for \nOhio consumers.\nII.\nPROTEST \nThe PJM grid must be maintained to ensure reliable and adequate generation and \ntransmission services.  FERC has an obligation to ensure that this objective is satisfied in a \nmanner that ensures just, reasonable, and not unduly discriminatory or preferential rates for \nservices.  In fact, FERC’s primary obligation is to provide consumers a “complete, permanent \nand effective bond of protection from excessive rates and charges.”30\nPJM seeks in this filing to ensure that New Large Loads that do not bring sufficient \ngenerating capacity to the system to satisfy their capacity obligations are placed at risk of \ncurtailment when capacity is insufficient to satisfy their needs. This objective is laudable. It  is \nintended to protect existing consumers from the resource scarcity that could result from the \n27 Id.\n28 Id. at 28. \n29 Id. at 29, 37-38. \n30 Atl. Seaboard Corp. v. FPC, 397 F.2d 753, 756 (4th Cir. 1968), quoting Atl. Refining Co. v. Pub. Serv. Comm’n of \nN.Y., 360 U.S. 378, 388 (1959)."},{"page":10,"startToken":2427,"endToken":2719,"text":"8 \naddition of significant new large loads to the system without also adding significant new \ngenerating resources.  Indeed, OCC agrees that a reasonable and affordable system to implement \nthis objective is urgently needed given the capacity shortages forecast to start with the 2027/2028 \nDelivery Year and continue into the 2028/2029 Delivery Year.   \nOCC supports PJM’s proposal to interrupt New Large Loads that connect without \nsufficient supporting capacity before curtailing residential and other existing consumers. \nHowever, OCC is concerned that the PJM’s design of that program will not achieve PJM’s \nintent, leaving consumers other than Large Load and New Large Load customers at risk of \ncurtailment.  OCC also does not support compensating those New Large Loads for interruptions \nthat are an inherent condition of receiving service without adequate capacity.  Nor does OCC \nsupport the portions of PJM’s proposal that would leave the details of curtailment \nimplementation to the states. \nPJM’s proposed IRAS program, as detailed in its filing, does not deliver the protection \nneeded for consumers who are not data centers.  PJM’s proposed program will result in \nsubsidized rates for existing Large Loads and New Large Loads in the PJM region. And PJM’s \nproposal will result in excessive and unduly discriminatory rates for existing consumers in Ohio \nand elsewhere in PJM.    \n OCC protests PJM’s filing for three primary reasons.  First, PJM provides no reasoned \nexplanation for its compensation proposal. Why should existing consumers whose capacity \nobligations are procured in the RPM auctions have to compensate New Large Loads for \ncurtailments when those New Large Loads have not procured sufficient capacity to meet their \ncapacity obligations? PJM’s zone-wide compensation proposal should be rejected.  At a \nminimum, if compensation is to occur, (it should not occur) it should be directly assigned to the"},{"page":11,"startToken":2719,"endToken":2995,"text":"9 \nparticipating New Large Load customer causing the shortages or waived by that customer as a \ncondition of IRAS service, with no curtailments for or recovery from residential consumers.  A \nstrong penalty on New Lard Loads for non-compliance with curtailment directives would ensure \nreliability for the grid in a more just and reasonable manner. \nSecond, PJM’s proposed new Large Load Registry unreasonably excludes state consumer \nadvocate offices from the list of entities entitled to access the information to be retained in that \nregistry. The Registry is designed to contain precisely the information needed by state \ncommissions, state consumer advocates, Electric Distributors and LSEs to evaluate retail \ncurtailment and cost allocation. OCC is an independent, statutorily-created representative of \nresidential consumers.  OCC is not part of the Public Utilities Commission of Ohio (“PUCO”).  \nAccess to the Registry by the PUCO does not give OCC access to that information. PJM’s \nproposal would permit other participants in the industry, utilities and LSEs which may have \ncommercial interests in serving the load, to obtain this confidential information. At the same \ntime, it would bar access to that information by the statutory representative of the consumers \npotentially charged for IRAS compensation and potentially bearing the interruptions in service \nfrom curtailments.   \n Third, PJM’s proposal attempts to protect existing consumers from the resource \nshortages resulting from New Large Loads coming on the system as of June 1, 2027.  But PJM \nhas not supported the cutoff date, nor explained how pre-cutoff Large Load additions will be \ntreated.  Yet  PJM’s filing admits that those Large Loads were primarily responsible for the \nshortfall of capacity procurement under two prior BRA Delivery Years ( 2027/2028 and \n2028/2029)."},{"page":12,"startToken":2995,"endToken":3285,"text":"10 \nFERC should reject PJM’s proposal to impose a federal compensation charge for \ncurtailments associated with the failure of New Large Loads to bring sufficient capacity to \nsatisfy their capacity obligations.  Instead it should (a) direct PJM to adopt strong penalties for \nnon-compliance with curtailment directives; (b) expand the list of entities entitled to access the \nLarge Load Registry to include state consumer advocate offices; (c) direct PJM to develop and \nfile a curtailment plan that addresses emergency priorities for pre-cutoff (June 1, 2027) existing \nLarge Load additions, including those associated with already run auctions for the 2027/2028 \nand 2028/2029 Delivery Years, i.e., the recent Delivery Years where resource adequacy \nobligations were not met; and (d) grant the additional relief proposed in this Protest.      \nA.\nPJM’s IRAS proposal to compensate IRAS load for curtailments is patently \nunjust, unreasonable, and unduly discriminatory or preferential and fails to \nprotect existing consumers.  \nThere is no justification for compensating New Large Loads for curtailment during \nperiods of resource shortages when those loads have failed to bring sufficient capacity to the \nsystem. PJM’s resource adequacy rules encompassed in the PJM Reliability Assurance \nAgreement Among Load Serving Entities are designed to obligate LSEs to bring sufficient \ncapacity to the grid to meet the capacity needs of the consumers they serve.  PJM’s IRAS \nproposal would allow New Large Load customers to connect to the system without an obligation \nto bring sufficient capacity to satisfy their needs.  Treating the removal of the risk New Lare \nLoad customers have caused as a separately compensable service and assigning the costs to \nexisting consumers improperly shifts to other consumers costs attributable to the conditional \nservice furnished to the New Large Load.  In that sense, PJM’s proposal is fundamentally"},{"page":13,"startToken":3285,"endToken":3619,"text":"11 \ninconsistent with the White House Ratepayer Protection Pledge, posted on the White House \nwebsite on March 4, 2026.31\nThat Pledge, now signed by over 300 organizations including many of the large data \ncenters and electric utilities in the nation,32 commits in relevant part that Large Loads will  \n1. build, bring, or buy the new generation resources and electricity needed to satisfy their \nnew energy demands, paying the full cost of those resources whether by building, or \nbuying from, new or otherwise additive power plants; \n2. pay for all new power delivery infrastructure upgrades required to service their data \ncenters, including adequate network upgrade costs to ensure that these expenses are \nnot passed on to the ordinary household; and\n3. pay these rates for the power and related infrastructure that are brought online to \nservice their data centers, whether they use the electricity or not.33\nThis commitment calls for the imposition of the costs and burdens associated with these very \nlarge load electricity customers on the large load electricity customers themselves.  \n  \nIn contrast, PJM is proposing that consumers throughout its region, including Ohio \nconsumers, will be at risk of: \n1. curtailments if these Large Loads fail to bring the generating capacity needed to serve \ntheir capacity obligations, especially where state laws may be inadequate to protect them \nfrom such curtailments;\n2. paying generating and transmission capacity costs associated with these new loads; and  \n3. compensating these New Large Loads for any curtailments if generating capacity \nshortages occur and PJM must curtail load to retain reliability in the region.   \n31 White House Ratepayer Protection Pledge, available at https://www.whitehouse.gov/releases/2026/03/ratepayer-\nprotection-pledge/ \n32 Data Centers Pay their Way; Ratepayers pay theirs, “A public commitment that hyperscalers, AI companies and \nthe utilities and data-center developers behind them will build, bring or buy every kilowatt their facilities need – and \ncover every dollar of the infrastructure that delivers it;” available at https://www.whitehouse.gov/ratepayer-\nprotection-pledge/ \n33 Supra, n.31."},{"page":14,"startToken":3619,"endToken":3909,"text":"12 \nAlthough the intent of PJM’s IRAS proposal is to target the New Large Loads with the \ncurtailment orders, that intent will not necessarily be achieved.  By design, PJM is proposing \nmerely to direct the Electric Distribution in whose zone the New Large Load is located to curtail \nenergy usage, and leaves the question of which end use customers will have to curtail to the \nstates. But as discussed later in section II.D of the Protest, not all states in PJM have laws \nregarding large load-related curtailments.  Nor do they have laws regarding who pays for the \ncompensation that will be required under PJM’s FERC-jurisdictional tariff.  Ohio is one such \nstate.  Consequently, OCC protests PJM’s proposal to provide compensation to New Large \nLoads in the event they are curtailed under the new program. At a minimum, if compensation is \nto occur (and it should not), compensation and administrative costs of the IRAS should be \ndirectly assigned to the participating New Large Load or waived, with no recovery from \nresidential consumers. \nThe only possible explanation PJM offers for its IRAS proposal is its inapposite reference \nto its non-comparable program for compensating Pre-Emergency Load Response participants.34\nThis program allows PJM to call upon Pre-Emergency Load Response participants to curtail \ntheir loads in response to PJM’s issuance of a pre-emergency call for load reductions due to \ngrowing near-term generating capacity scarcity. Under this program PJM charges the participants \nthat underperform or pays those who overperform 50% of the capacity Non-Performance Charge \nrate.35 PJM argues that “[f]rom a customer perspective, the non-performance rate appropriately \nreflects that load paid for capacity but did not get the benefit of the Pre-Emergency Load \n34 IRAS Application at 101, 103. \n35 Id. at 103."},{"page":15,"startToken":3909,"endToken":4188,"text":"13 \nResponse Program that PJM called upon at a time when the PJM system was in stressed system \nconditions.”36 PJM proposes to use this rate as the compensation charge for IRAS curtailments. \nBut there is a big difference between the two programs that makes compensating New \nLarge Loads under the IRAS program unreasonable. The Pre-Emergency Load Response \nparticipants that are compensated for curtailment during pre-emergency conditions are existing \ncustomers whose loads are within the load growth forecasts of the RPM auction parameters.  In \nother words, PJM is procuring generating capacity on their behalf.  The system is designed to \nserve them.   \nIn contrast, the New Large Loads subject to IRAS curtailments will receive accelerated \naccess to the grid despite insufficient capacity and are curtailed only because the condition \nsupporting that access has occurred.37 Unlike Pre-Emergency Load Response participants, IRAS \nloads will not be included in the RPM auction parameters.38 That means that unlike the Pre-\nEmergency Load Response participants, PJM has not procured capacity to serve New Large \nLoad capacity obligations. The system is not designed to reliably serve their electricity needs.  \nInstead, the IRAS program will rely on curtailment options when generating capacity shortages \nexist.   \nIt makes sense to compensate existing Pre-Emergency Load Response participants for \ncurtailment because their loads are covered by RPM auctions.  They are compensated for the \ninconvenience of having to shed load during emergencies. And their participation in the program \nis voluntary.  But where the capacity needed to serve the New Large Loads is not part of the \nRPM capacity procurement auction to begin with, their participation in IRAS is not voluntary,  \n36 Id.\n37 Id. at 1. \n38 Id. at 23."},{"page":16,"startToken":4188,"endToken":4569,"text":"14 \nand PJM clearly is not procuring sufficient generating capacity to cover their loads, it makes no \nsense to compensate these New Large Loads for curtailment. Under that scenario, New Large \nLoad customers should be curtailed first and without compensation, especially without \ncompensation from other customers whose capacity obligations are covered by the auctions.   \nThese New Large Loads are imposing a huge new burden on the system that is \nunprecedented and unlike the minimal load growth forecasts for existing Pre-Emergency Load \nResponse customers. The forecast peak load for the 2028/2029 Delivery Year BRA was 165,954 \nMW.39 This is 0.8%, above the forecast peak load of 164,579 MW for the prior 2027/2028 \nBRA.40 In contrast, as noted above, PJM anticipates an increase in load due to the influx of New \nLarge Load customers of 30 Gigawats (“GW”), or 30,000 MW, from 2024 to 2030.41 An \nincrease of 30,000 MW over the current forecast peak load of 164,579 MW for the 2028/2029 \nDelivery Year represents a total increase of 18% during that period, or an average of 3% \nannually.42 This impact on resource adequacy is significantly larger than the 0.8% increase in \nload forecasted from the 2027/2028 to the 2028/2029 Delivery Year which includes Pre-\nEmergency Load Response customers.   \nIn other words, it simply is not reasonable to develop IRAS rules based on the Pre-\nEmergency Load Response program rules. The impact of the New Large Loads on the system \nhas been so significant as to provoke PJM to propose this new curtailment program to protect \n39 2028/2029 RPM Base Residual Auction Planning Period Parameters at 1 (May 12, 2026), available at \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-report.pdf \n40 Id.\n41 IRAS Application at 13.  The IRAS Application calculates this forecast as 30 Gigawats of new large loads.  Given \nthat 1,000 MW is equal to 1 GW, the 30 GW forecast is the equivalent of 30,000 MW of new load in PJM over a six \nyear period. Two of those years are now behind us.   \n42 30,000 MW represents an 18.2% increase over the 164,579 MW of demand forecasted for the 2027/2028 Delivery \nYear."},{"page":17,"startToken":4569,"endToken":4889,"text":"15 \nreliable electric service in the region during generation scarcity emergencies. While it may have \nbeen reasonable to compensate voluntary Pre-Emergency Load Response participants to curtail \nloads under the design parameters of that program, it simply makes no sense to pay New Large \nLoads for involuntary curtailments when (1) PJM has not had sufficient notice of their \ninterconnection in time to procure new generating capacity on their behalf, (2) they have not \nbrought their own sufficient generating capacity to the system to serve their needs, and (3) their \nloads are not included in the RPM parameters.   \nTo illustrate the unreasonableness of PJM’s proposal, consider the following example. \nThe Governor of Ohio is holding a meeting to discuss the importance of affordable electricity in \nthe state..  The Governor has invited entities that represent transmission owners and consumers \nto this meeting and tells everyone participating to bring their own lunch. A new entity finds out \nabout the meeting, and the day before the meeting informs the Governor that it too is a consumer \nand plans to attend the meeting.  Only this new entity brings 25,000 to 50,000 people with it to \nthe meeting.  None of these people bring their own lunch. The Ohio Governor has not included \nthese entities in its plans for this meeting given the short one-day notice and does not have \nenough food to serve lunch to all these unanticipated meeting participants.  As a result, the \nGovernor must tell the late-notice guests that they cannot share the food of those who were \ninvited and who brought their own lunches. Under the PJM IRAS model, the Ohio Governor \nwould have to compensate the uninvited guests for going without food during lunch, potentially \nat the expense of the other participants.   \nThis example is not outrageously exaggerated, nor is it unreasonable. PJM’s filing states \nthat the peak loads of 50-MW New Large Load customers are roughly equivalent to the electricity"},{"page":18,"startToken":4889,"endToken":5193,"text":"16 \ndemands of 25,000 and 50,000 residential homes.43  In effect, the load associated with just one \nNew Large Load customer will equal the load of a mid-sized city in the PJM region. The New \nLarge Loads anticipated to interconnect to the PJM system that are not bringing their own \ngenerating capacity (food) will impose a huge drain on the system with relatively short notice, \nespecially considering PJM’s three-year forward procurement model for capacity \nauctions.  Existing consumers in Ohio and elsewhere in PJM should not be paying these New \nLarge Loads for their “curtailment inconvenience” when these new loads caused the shortage \nconditions by not procuring sufficient generating capacity, and by being unable or unwilling to \nsecure that needed new capacity. \nPJM also attempts to justify its proposed compensation scheme by arguing that “[u]nder \nconditions of tightening supply and demand, it is a measured and well-considered response to \npermit the new demand causing the shortfall on the system to interconnect, subject to load reduction \nunder limited emergency conditions, but receive compensation for that load reduction.” 44  In \nsupport, PJM cites to an order on rehearing in a generator interconnection complaint case:   \nTenaska Clear Creek Wind, LLC v. Sw. Power Pool, Inc., 183 FERC ¶ 61,043 at P 24 (2023) \n(“Tenaska II”).  \n That case does not support PJM’s premise that interconnections allowed under limited \nemergency conditions may receive compensation for that curtailment.  In Tenaska II, FERC \ndismissed a complaint in which the generator argued that its facility had been unjustly \ncurtailed.45 As PJM correctly notes in footnote 264 of the IRAS Application, FERC found that \ncurtailment may be appropriate where a generator begins commercial operation before the \n43 IRAS Application at 35.   \n44 Id. at 99 (emphasis added). \n45 Tenaska Clear Creek Wind, LLC, 183 FERC ¶ 61,043 at P 24."},{"page":19,"startToken":5193,"endToken":5490,"text":"17 \nnetwork upgrades needed to accommodate its reliable interconnection to the grid are \ncompleted.46 But unlike PJM’s characterization of this order, the ruling says nothing about a \ncompensation payment for those curtailments. \nAlthough FERC did not address the question of compensation for the generator \ninterconnection curtailments in Tenaska II, it did reject Tenaska’s request for refunds of more \nthan $9 million in alleged lost revenues during the curtailment events.47 In fact, FERC’s rulings \nin Tenaska I and Tenaska II support a program of curtailment without compensation where the \ncommercial operation of the interconnection customer begins before service can be reliably \nprovided because of the need for new infrastructure investment in the region.  \nFERC found in Tenaska II that “[s]ubjecting the interconnection customer that causes the \nneed for upgrades in this manner ensures that the interconnection customer, bears the system-\nreliability burdens that flow from its decision to operate prior to completion of the required \nnetwork upgrades.”48 FERC further found that curtailment in Tenaska II was appropriate because \nthe curtailment occurred “on the basis that it [the generator], as an interconnecting facility, was \nsubject to limited operation.”49 Like the generator in Tensaka I and Tenaska II, curtailment \nwithout compensation of a load interconnection customer is appropriate where the customer is \nbeing interconnected and begins taking service before sufficient generating facilities have been \nconstructed to provide reliable service.   \nThe sole purpose of the IRAS program is to allow interconnection of New Large Loads \nbefore there is sufficient generating capacity to reliably serve their needs.  But, like the tariff in \n46 Id.\n47 Tenaska Clear Creek Wind, LLC v. Sw. Power Pool, Inc., 181 FERC ¶ 61,225, at PP 19, 61 (2022) (“Tenaska I”). \n48 Tenaska II at P 24. \n49 Id. at P 25."},{"page":20,"startToken":5490,"endToken":5762,"text":"18 \neffect in Tenaska I and Tenaska II, that interconnection occurs subject to the right of the grid \noperator to curtail service until generating capacity is sufficient to allow connection to the grid. \n FERC should reject PJM’s attempt to bootstrap compensation for curtailment where \ncustomers interconnect before they can be reliably served into the ruling in Tenaska II.  FERC \ndid not require compensation of curtailed generators in Tenaska II – indeed, FERC did not even \nconsider the question of compensation.  FERC similarly should not require compensation here.     \nThe provisions of the Southwest Power Pool (“SPP”) tariff at issue in Tenaska II provide \nthe best example for how to move forward with New Large Loads interconnections before \nsufficient generating capacity is available to reliably serve their loads. Those provisions limit \ngenerator interconnection customer operations and provide for curtailments in times of scarcity \nuntil needed new infrastructure is in place. As FERC found in Tenaska II, this process allows the \ninterconnection customer “to decide whether to operate its generating facility under limited \noperation pending availability of full interconnection capacity.”50  FERC properly concluded that \n“[t]he alternative is that the generating facility does not operate until full interconnection \ncapacity is available.”51\nCurtailment without compensation is also the model in SPP’s recently approved \nConditional High Impact Large Load Service (“CHILLS”) interruptible transmission \ninterconnection program.52 That program allows interconnection of large load customers for \ntransmission service before needed new transmission network upgrades are constructed to \nreliably provide that service, subject to curtailment when needed to maintain transmission system \n50 Id. at P 29. \n51 Id.\n52 Southwest Power Pool, Inc., 195 FERC ¶ 61,196 (2026)."},{"page":21,"startToken":5762,"endToken":6057,"text":"19 \nreliability.53 Similar to the generation interconnection rules involved in Tenaska I and Tenaska \nII, CHILLS loads are not compensated for those curtailments.54  Instead of compensation \npayments for curtailments, CHILLS customers are penalized for failure to follow curtailment \norders.55 Both SPP’s generator interconnection rules and its CHILLS rules serve as more apt \nmodels for PJM’s IRAS curtailment rule than the Pre-Emergency Load Response program PJM \nused to design the curtailment rules for IRAS customers.   \nPJM is proposing to pay very large entities that have recently appeared on the system for \nthe “risk” that these New Large Loads will be curtailed. And yet these customers did not timely \nnotify PJM of their inability to acquire sufficient generating capacity to satisfy their needs and \ndid not bring their own capacity to the system. Why reward these entities for a situation they \ncreated by compensating them?  The reduction in energy usage (via the curtailment) merely \neliminated the incremental demand they created or materially aggravated. The New Large Load \nis the principal cost-causer because its uncovered demand creates the IRAS obligation. Existing \nresidential consumers do not cause the IRAS curtailments.  \nAny reliability benefit other consumers receive is principally the removal of a risk \nintroduced by the new load itself.  Charging households for that mitigation shifts the \nconsequences of the New Large Load’s conditional interconnection to customers who did not \ncause it. In other words, there is no reasoned justification for the compensation proposal, or to \nput existing consumers at risk of paying for that compensation charge.   \nThe compensation proposal also is completely inconsistent with the White House \nRatepayer Protection Pledge that new large loads absorb the costs and risks associated with their \n53 Id. at P 7.   \n54 Id. at PP 31, 85, 97-99.   \n55 Id."},{"page":22,"startToken":6057,"endToken":6348,"text":"20 \ninterconnection requests.  PJM has not provided an adequate or reasoned explanation for a \nfederal charge to compensate entities for curtailment when those entities failed to bring capacity \nto the system sufficient to serve their needs.  Accordingly, FERC should reject the curtailment \ncompensation element of PJM’s proposed IRAS program.  \nB.\nFERC should direct PJM to modify the IRAS proposal to include state \nconsumer advocates in the list of those allowed to access confidential \ninformation in the proposed new Large Load Registry. \nOCC supports PJM’s proposal to create a Large Load Registry that will track up-to-date \ninformation related to the location, generating capacity needs, load needs and other information \nrelated to interconnection of Large Loads to the PJM grid. However, PJM’s proposal to exclude \nstate consumer advocates from the category of entities eligible to access that confidential Large \nLoad Registry information is not just and reasonable. OCC, a statutorily-mandated state \nconsumer advocate office, represents end-use customers service by PJM’s markets and has the \nsame need for transparency and access to this information as do the entities PJM proposes to \nallow access to this information.   \nPJM relies in part on its justification for the Large Load Registry on the support provided \nby stakeholders. PJM reports that 82% of stakeholders supported a Large Load Registry, and this \nsupport extends across a broad swath of often divergent stakeholder views in the region.56 PJM \nrepresents that this support includes 18 Electric Distributors, 16 End-Use Customers, six \nGeneration Owners, seven Other Suppliers, and seven Transmission Owners.57 The reasons \nprovided by these stakeholders for their support, as recounted by PJM in its IRAS Application, \nare similar to the reasons OCC and other state consumer advocate offices need this information. \n56 Id. at 31, n. \n57 Id."},{"page":23,"startToken":6348,"endToken":6624,"text":"21 \nFor example, PJM represents that one comment received in its Reliability Backstop \nProcurement and IRAS poll states that “[a]bsent a registry, it is unclear how other end-use \nconsumers could be insulated from these costs. . . . Additionally, it is unclear how, absent a \nregistry, a Connect & Manage [IRAS] framework could be implemented in a way that protects \nother end-use consumers from being curtailed in response to a PJM Connect & Manage \n[IRAS] event.”58  Another stakeholder responded that “[a] registry provides the transparency \nneeded to identify new large loads, their locations, and whether they have secured qualifying \nBYONC [Bring Your Own New Capacity] or other reliability arrangements.”59  Still another \nstated that “[a] registry is one means of satisfy[ing] the principle of ensuring that costs of new \ncapacity required to serve new large load (i.e., data centers) should be allocated to data \ncenters.”60\nNotwithstanding this broad stakeholder support for the critical and greatly needed \ntransparency the Large Load Registry would provide, PJM proposes to restrict access to that \ninformation.  Access would only be permitted to authorized state commissions, Transmission \nOwners, Electric Distributors, Load Serving Entities (“LSEs”), the IMM and this Commission.61\nWith respect to inclusion of authorized state commissions in the group  allowed to access the \nRegistry, PJM argued that “[s]tates may leverage the Large Load Registry to inform the \nimplementation of retail constructs including load reduction priorities and cost allocation at the \nretail level to appropriate end-use customers.”62 PJM further explained that “[t]he Large Load \n58 IRAS Application at 30, n.85. \n59 Id. at 30-31.   \n60 Id. at 31. \n61 IRAS Application at 28. \n62 Id. at 29."},{"page":24,"startToken":6624,"endToken":6899,"text":"22 \nRegistry will assist states in administering their respective programs at the retail level while \nallowing each state to retain the flexibility to administer those programs, including the flexibility \nto determine when and whether Large Loads and Existing Large Loads have demonstrated that \ntheir loads are matched with new capacity that they have procured to serve their needs.”63\nState consumer advocate offices, like OCC, are statutorily mandated to represent the \ninterests of residential consumers in their respective states. Authorized state commissions need to \naccess confidential Registry information to assess the impact of Large Loads in their states and \nto ensure just and reasonable cost and curtailment allocations for their retail customers.  State \nconsumer advocates need access to that information as well. State consumer advocates like OCC \nare statutorily obligated to advocate for residential consumers in their state and ensure that any \nretail programs to share costs or curtailment impacts are just and reasonable for those \nconsumers. State consumer advocates in PJM will not be able to provide robust advocacy for \ntheir consumers without access to the confidential information in the Large Load Registry. \nConsumer advocates need this information for the same reasons the state commissions need this \ninformation.   \nMore importantly, state consumer advocates seeking to protect retail consumers in state \nproceedings involving Large Load have no other means to obtain this critical information.  They \nwill find their efforts to obtain that information in state proceedings stymied by the proposed \nconfidentiality provisions in the Large Load Registry tariff.  Without a federal rule providing for \nregistry access, state consumer advocates will most likely be denied access to this essential \ninformation in the state proceedings.   \n63 Id."},{"page":25,"startToken":6899,"endToken":7248,"text":"23 \nThat lack of transparency for consumers is egregious, unjust and unreasonable. By \nexcluding authorized state consumer advocates from the Registry, PJM’s proposal unduly \ndiscriminates against consumer representatives in violation of sections 205 and 206 of the \nFederal Power Act, 16 U.S.C. §§ 824d and 824e, and in violation of long-held judicial precedent \nprohibiting such undue discrimination.64 PJM provides no reason for excluding OCC and other \nPJM state consumer advocates from access to the Registry. Furthermore, FERC itself has \nrecognized the importance of sufficient transparency regarding Large Loads and expressed \nconcern that “without sufficient transparency . . . stakeholders may lack information and \nvisibility regarding the costs driven by large load additions.”65\nThe Large Load Registry is too important to eliminate from PJM’s proposal given the \ncritical need for the transparency the Registry will provide. Thus, rejection of the proposal would \nnot be just or reasonable.  Yet excluding state consumer advocate offices from having access to \nthat information is not just and reasonable either. FERC should direct PJM to amend the \nproposed tariff language to allow access to the Large Load Registry by state consumer advocate \noffices, their attorneys and retained experts, subject to the same certification, nondisclosure and \ndata-security requirements applicable to the Authorized State Commissions.  \nC.\nThe IRAS Proposal is Unjust and Unreasonable because it fails to address \nresource adequacy constraints caused by Existing Large Load customers \n(pre June 2027 large loads).   \n The IRAS proposal addresses what happens only with respect to New Large Loads, and \nany incremental increases to existing Large Loads, that seek interconnection to the system on or \n64  See, e.g., New England Power Gen. Ass’n. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (citing BP Energy Co. v. \nFERC, 828 F.3d 959, 968 (D.C. Cir. 2016) (“vacating finding of no undue discrimination where Commission \nidentified differences between two natural-gas companies but failed to adequately explain why they provide a \nrational basis for the difference in treatment”)).\n65 IRAS Application at 48, citing PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211 at P 74 (2026)."},{"page":26,"startToken":7248,"endToken":7551,"text":"24 \nafter June 1, 2027.66 Yet, the last three BRAs in RPM, i.e., auctions for the 2026/2027, the \n2027/2028 and the 2028/2029 Delivery Years, all cleared short of the PJM reliability \nrequirement for RPM auctions.67 The last two cleared short by more than 6,600 MWs each – and \nPJM represents that the reason for this shortfall is anticipated Large Loads on the system \nforecasted for those periods.68  PJM states that “in recent years, the majority of the new load that \nhas come onto the PJM system has been Large Load,” and therefore, PJM proposes to limit the MW \nquantity of Large Load that may be subject to reduction under  IRAS to the MW value of New \nLarge Load that has not brought their own capacity.”69\nThe failure of the IRAS curtailment proposal to address both existing (pre June 2027) and \nNew Large Loads makes the proposal unjust and unreasonable.  OCC supports PJM’s intent in \nthe IRAS proposal to interrupt New Large Loads that connect without sufficient supporting \ncapacity before curtailing residential and other existing consumers.  OCC does not, however, \nsupport leaving the allocation of those curtailments to non-existent state laws.  Nor does it \nsupport compensating those New Large Loads for interruptions that are an inherent condition of \nreceiving service without adequate capacity.  Such customers should bear the consequences of \ntheir decision to take conditional service. The associated costs should not be shifted to other \nconsumers, including residential consumers.  \nBut relief regarding cost and curtailment allocations is also urgently needed with respect \nto forecasted existing Large Load already included in the RPM auction parameters for near-term \nDelivery Years, especially given the resource shortages in those BRA clearing results. PJM’s \n66 IRAS Application at 1. \n67 Id. at 39, n.108. \n68 Id. at 39. \n69 Id."},{"page":27,"startToken":7551,"endToken":7849,"text":"25 \nproposal does not address a plan for shortages in the prior auctions attributable to forecast load \nadditions occurring before the cutoff.  Yet all of the reasons PJM lays out in the IRAS \nApplication that support the need for the IRAS program for New Large Loads apply equally to \nexisting Large Loads incorporated in RPM auctions run for the past three Delivery Years. To \nensure adequate protection for consumers in Ohio and elsewhere in PJM, PJM and FERC must \naddress curtailment priorities for Large Loads that have already cleared in the 2026/2027, the \n2027/2028 and the 2028/2029 Delivery Years.   \nThe White House Ratepayer Protection Pledge commits to holding residential consumers \nharmless from the effects of Large Loads on transmission rates, on procurement costs for needed \ngenerating capacity, and from curtailments related to transmission and resource scarcities.70 The \nfailure of the filing to address this concern is inconsistent with the White House agenda, and \nresults in unjust, unreasonable, and unduly discriminatory and preferential rates for consumers.  \nBoth existing and future ratepayers need the protections of the IRAS proposal.  \nMoreover, the White House Ratepayer Protection Pledge does not distinguish between \nconsumers taking service today and those taking service next year, or in three years.  FERC \nshould condition its acceptance of PJM’s IRAS program on a directive that PJM submit a \nproposal for how curtailments for scarcity emergencies associated with existing Large Loads on \nthe system prior to June 1, 2027 will be addressed in the near term. This program is urgently \nneeded so that state commissions and state consumer advocates will have the information they \nneed to develop retail curtailment plans for shortages associated with these existing Large Loads \nand any related cost. \n70 White House Ratepayer Protection Pledge, available at https://www.whitehouse.gov/ratepayer-protection-pledge/"},{"page":28,"startToken":7849,"endToken":8230,"text":"26 \nD.\nPJM’s proposal to rely on state programs for curtailment and allocation of \nIRAS program costs to retail consumers is unjust and unreasonable. \nAs noted on several occasions in this protest, PJM proposes that state legislatures and \ncommissions will address how the curtailments and related costs associated with New Large \nLoad curtailments will be allocated among retail consumers in their states.71  Ohio does not have \na state law addressing allocations of costs or curtailment obligations among retail consumers in \nrelation to the IRAS or other federal large load regulatory programs.  Nor does it have state-\njurisdictional tariffs that address these issues.  \nOhio does have one state jurisdictional utility, American Electric Power (“AEP”), that \nhas a tariff for assigning the costs associated with generation procurement and transmission and \ndistribution investment associated with Large Load interconnections. The PUCO approved a \nmulti-party settlement, supported by OCC and others, that implements a special tariff.72\nAEP’s tariff, however, does not adequately protect consumers from the federal \ncurtailments PJM is proposing for large load customers. Under this state tariff, AEP generally \ncan curtail nonresidential customer service in an emergency, if the nonresidential customer is \nviolating the tariff or engaging in activity that is otherwise unlawful.  Under the large load \ninterconnection tariff changes agreed upon in the settlement, AEP can curtail data center load if \nthat load has Behind the Meter generation.73  The minimum demand calculation allows netting to \ninclude consideration of the customer’s firm commitments to reduce load with Behind the Meter \n71 IRAS Application at 2-3, 7, 26, 101, 104-106. \n72 In the Matter of the Application of Ohio Power Company for New Tariffs Related to Data Centers and Mobile \nData Centers, Opinion and Order (Jul. 9, 2925), in PUCO Case No. 24-508-EL-ATA (“AEP July 2025 Order”); see \nalso In the Matter of the Application of Ohio Power Company for New Tariffs Related to The Standard Service Offer \nService for Data Center Load, Finding and Order (Aug. 5, 2026) in PUCO Case No. 26-113-EL-ATA (“AEP \nAugust 2026 Order”).  While there are additional matters pending or contemplated to implement specific data center \nload tariffs for American Transmission Systems, Inc., Dayton Power and Light Company and Duke Energy Ohio, to \ndate the PUCO has not adopted orders establishing programs for these utilities.  \n73 Id."},{"page":29,"startToken":8230,"endToken":8519,"text":"27 \ngeneration.74 To ensure that the customer’s election to net does not result in it exceeding its contract \ncapacity, equipment must be in place and maintained to instantaneously curtail load equal to or \ngreater than the Behind the Meter generation output, subject to the then-current technical \nrequirements of the transmission provider.75 The objective of this requirement is to ensure that the \ndata center load does not exceed its contracted capacity.  The only other reference to curtailment \nin that Order is the finding that “[w]hile we recognize 10/10 Stipulation signatories state that data \ncenters can curtail their loads during peak times, regardless, the Company still needs to invest in \nits transmission system to serve the incoming data center capacity.”76\nFor purposes of the IRAS program, the Ohio AEP tariff does not address curtailment \npriorities and related cost allocations.  More importantly, no protections exist currently for \nconsumers of the three other utilities in the state.  There is no guarantee under Oho law that all \nOho consumers, even customers of AEP, will be protected against the cross-subsidies inherent in \nPJM’s IRAS proposal. It is fundamentally unreasonable for PJM to rely on a system of shared \nstate-federal jurisdiction to resolve a problem raised directly by its proposed wholesale IRAS \nprogram where inadequate protections exist at the state level.    \nPJM should not rely on hypothetical state action to establish that IRAS is a deliverable \nresource-adequacy service. Unless an Electric Distributor has enforceable retail authority, \ncustomer specific arrangements, telemetry and tested ten-minute curtailment capability, its \nassigned IRAS curtailment quantity is merely a paper resource.  PJM nevertheless proposes to \nrely on that quantity for emergency operations and ultimately exclude the associated load from \n74 Id.\n75 Id.\n76 Id. at 77."},{"page":30,"startToken":8519,"endToken":8821,"text":"28 \ncapacity procurement. This transfers the risk of nonperformance to existing consumers. That is \nunjust and unreasonable and contrary to the Ratepayer Protection Pledge. \nFERC should reject PJM’s approach. Instead, FERC should condition acceptance on \nPJM’s filing of a modification to the IRAS proposed tariff language. The modification should  \nrequire PJM to verify that an effective state-approved tariff or binding contract makes the \nassociated reduction legally and operationally enforceable. If PJM cannot make that verification, \nthen the tariff should require that the New Large Load customer be directly assigned the \ncurtailment risk and associated costs as a condition of IRAS, interconnection to the grid and \nprovision of electric service without the required capacity resource support.   \nE.\nPJM’s failure to include a penalty for New Large Load customer non-\ncompliance or under-performance of curtailment directives is unjust and \nunreasonable. \nPJM proposes paying New Large Loads for successful reductions in energy consumption, \nbut does not establish a comparably clear customer-level penalty when they fail to reduce \nconsumption in a timely manner, e.g., within ten minutes.  Without enforceable contracts, \ntelemetry, testing and penalties, Ohio households could remain exposed to emergency outages.   \nRegulatory obligations need enforcement penalties to ensure compliance with tariff rules.  \nPJM is no stranger to a penalty structure to ensure market participant compliance with its tariff \nrules.  Such penalties already exist in the RPM capacity auction tariffs for generating resource, \ndemand response and transmission upgrade non-performance events.77\n77 See, e.g., PJM Open Access Transmission Tariff, ATT DD, section 7.1 (Generator Resource Reliability Test \nFailure Charge); R section 8.1 (Capacity Resource Deficiency Charge); section 10A Charges for Non-Performance \nand Credits for Performance); section 10B (Charges and Credits for Curtailments During Non-PAI Event); section \n11A (Demand Response Resource Test Failure Charge); and section 12 (Qualifying Transmission Upgrade \nCompliance Penalty Charge). ."},{"page":31,"startToken":8821,"endToken":9167,"text":"29 \nThe PJM IMM reports related to specific demand response non-performance support the \nneed for a penalty for curtailment non-compliance. Those reports indicate that during the January \n25, 2026 demand response event, actual compliance with the requirements for curtailments \namounted to only 50 to 58%.78  For the June, July, and August demand response events in 2025, \ndemand response providers’ performance ranged from 49 to 70%.79 This level of curtailment \nperformance is unacceptable.   \nMoreover, the PJM IMM has recently criticized the insufficiency of PJM’s existing \ndemand response non-performance penalties, and has proposed modifications. The IMM report, \npresented to the PJM Markets and Reliability Committee on April 22, 2026, states that PJM’s \nproposed demand response tariff changes (a) allow payment for demand response even when \ndispatch results in increased loads; (b) make it profitable for demand response even when these \nresources provide zero performance (e.g., with zero performance, demand response resources are \nstill able to retain 87.8% of their RPM revenues in non-Performance Assessment Intervals); (c) \nprovide proposed penalties for non-performance that are significantly weaker than the existing \npenalties for simply failing a demand response test; and (d) fail to provide for return of penalties \nto load that paid for the capacity.80  The IMM concluded that the proposed penalty structure will \nnot provide effective performance incentives, and that there should be no payment for zero \n78 Market Monitor Report to the PJM Members Committee at Slides 4, 9-10 (Jun. 24, 2026), presented by Marketing \nAnalytics, LLC, available on the PJM website at https://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/mc/2026/20260624/20260624-item-07---market-monitoring-report---presentation.pdf. \n79 DR Nonperformance Penalties Report to the PJM Markets Implementation Committee at Slides 12-14 (Jan. 20, \n2026), presented by Marketing Analytics, LLC, available on the PJM website at https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mic/2026/20260120/20260120-item-01-3---load-management--\nprice-responsive-demand-event-performance---imm.pdf. \n80 IMM Comments on Proposed DR Penalties as Slides 2, 18-20, Monitoring Analytics, LLC, presentation to the \nPJM Markets and Reliability Committee (Apr. 22, 2026), available on the PJM website at"},{"page":32,"startToken":9167,"endToken":9488,"text":"30 \nperformance.81 As the IMM demonstrates, the likelihood of non-compliance with curtailment \ndirectives during system emergencies by demand response providers is not speculative.   \nThe need for strong penalties for non-performance of load shedding or curtailment \nactivities is paramount, including curtailments associated with the IRAS program.  In his \ncomments on PJM’s Reliability Backstop Procurement (“RBP”) proposal in Docket No. ER26-\n3380-000, the IMM stated that “[a]llowing the new data center to designate its own load as \nAnnual DR further creates an opportunity to avoid the curtailment obligation that would \notherwise apply to the load under PJM’s Interim Resource Adequacy Service (“IRAS”). In \neffect, the data center can transform a reliability obligation imposed on an inadequately supplied \nlarge load into a self-designated RBP offset, while providing PJM with a demand side resource \nwhose availability is dependent on emergency curtailment rather than an economically \ndispatchable supply resource.”82 The IMM concludes that “[i]n substance, the proposal allows \nthe large load to satisfy the reliability obligation created by its own demand by making itself a \ndemand response resource, even though that resource provides a fundamentally different and less \ndurable reliability product than the capacity procurement it displaces.”83\nAs noted in section II.A earlier, even SPP’s new large load interruptible transmission \ntariff, the CHILLS program, includes a penalty for over-use of the transmission system on an \ninterruptible basis.84 While SPP’s proposed penalty for CHILLS customers is not a curtailment \npenalty per se, it achieves a similar objective.  As FERC explained in accepting SPP’s proposed \npenalty for excessive use of the transmission system on an interruptible basis, “SPP’s proposed \n81 Id. at Slide 21. \n82 Protest of Independent Market Monitor for PJM at 23, PJM Interconnection, L.L.C. Docket No. ER26-3380-000 \n(Aug. 21, 2026), available on FERC’s e-library website as Accession Document No. 20260821-5317.   \n83 Id. at 24.   \n84 Southwest Power Pool, Inc., 195 FERC ¶ 61,196 at P 98."},{"page":33,"startToken":9488,"endToken":9763,"text":"31 \npenalty structure for instances in which CHILLS Customers use transmission service in excess of \ntheir CHILLS Reserved Capacity is also just and reasonable and not unduly discriminatory or \npreferential because it ensures that CHILLS Customers pay for unreserved use of SPP’s \ntransmission system based on the amount and duration of such unreserved use.  As described \nabove, SPP’s proposed penalty amount increases as any unreserved use is repeated,” and “will \nhelp deter CHILLS Customers from repeatedly failing to adhere to their CHILLS Reserved \nCapacity amounts.”85\nIn essence, PJM’s IRAS program works in a manner similar to the SPP CHILLS \ninterruptible transmission program.  Large data center loads on the SPP system are required to \ntake CHILLS interruptible transmission service on an interim basis until the network upgrades \nneeded to reliability accommodate their interconnection to the system can be built.  PJM’s IRAS \nprogram pursues a similar objective, albeit in the capacity side of operations as opposed to the \ntransmission side of operations.   \nPJM’s IRAS proposal contains neither non-performance, nor excessive take penalties for \nfailure of a New Large Load customer to comply with curtailment directives under the program.  \nInstead of imposing a penalty for non-compliance with curtailment directives, PJM seeks to \ncompensate such entities through an incentive to encourage such compliance. As discussed in \nsection II.A above, that proposed incentive is unjust, unreasonable and unduly discriminatory \nand preferential in a situation where New Large Load is allowed to interconnect only on \ncondition that their loads can be curtailed in the event of a system resource shortage. Reliability \nand resource adequacy are too important to leave to the hope that incentives will encourage good \n85 Id."},{"page":34,"startToken":9763,"endToken":10070,"text":"32 \nbehavior. Strong penalties are more appropriate under such circumstances, such as the strong \npenalties for non-performance of capacity obligations under the RPM rules.   \nFERC should reject the curtailment compensation proposal and direct PJM instead to \nadopt a penalty for New Large Load non-compliance with curtailment directives.  PJM might \nargue that its proposal contemplates issuance of the curtailment directive to the Electric \nDistributor in whose zone the New Large Load is located, rather than to the New Large Loads, \nand thus there is no direct nexus between the New Large Load and PJM’s directives to justify a \npenalty. This argument and proposal are seriously flawed. \n  Imposing curtailment penalties on the Electric Distributor suffers from the same \nproblem that invades all of PJM’s IRAS proposal. The objective is to allow New Large Loads to \ninterconnect to the system and receive electricity services regardless of whether they bring \nsufficient generating capacity to satisfy their capacity obligations. But PJM proposes no direct \nmeasures to order New Large Loads to do anything, even when critically needed to ensure grid \nreliability.  FERC should direct PJM to correct this flaw and impose curtailment non-\nperformance penalties directly on New Large Loads as a condition of their interconnection to the \nsystem and receipt of energy from the system.  \nF.\nThe IRAS proposal is unjust and unreasonable because it does not contain \nsufficient protections against double recovery by New Large Loads of \nincentive compensation for curtailments. \nThe IRAS proposal does not appear to contain rules preventing double recovery by New \nLarge Loads under potentially overlapping programs.  For example, the IRAS program is a \ncapacity market program, designed to allow New Large Loads to interconnect even in the \nabsence of sufficient generation capacity to meet their needs so long as they participate in the \nIRAS curtailment program.  However, these loads may also be eligible for discounted"},{"page":35,"startToken":10070,"endToken":10369,"text":"33 \ntransmission rates if they take interruptible transmission services or may be eligible for demand \nresponse payments in the capacity and energy markets. In other words, New Large Load \ncustomers may be eligible for multiple incentive payments associated with the same curtailment \nevent.    \nAt a minimum, FERC should direct PJM to require New Large Loads to disclose all \npayments received under all PJM market programs for the same curtailment event.  FERC \nlikewise should direct PJM to implement tariff provisions that would net additional forms of \npayments for the same curtailment event so that New Large Loads are compensated only once \nfor the same curtailment event. Absent such a disclosure obligation and a pricing structure that \nprevents double payment for the same event, there would be no mechanism to ensure that \nconsumers in Ohio and elsewhere in PJM do not pay excessive rates for electricity services in \nPJM’s markets.   \nG.\nFERC should consider directing PJM to directly assign curtailment \nobligations and related costs to the New Large Loads driving the reliability \nconcerns on the grid due to their failure to bring generating assets to the \nsystem to satisfy their capacity obligations.   \nMuch of the electric utility industry, large data center loads and even the White House \nagree that existing consumers on the system should be held harmless from the costs and risks of \nNew Large Load interconnections to the grid. The White House has even titled its webpage \naddressing this matter “Data Centers Pay their Way; Ratepayers pay theirs.”86\n In keeping with this commitment, the IMM stated in his alternative proposal to PJM’s \nRBP program that “[t]he most important criterion for evaluating proposals to address how to \nreliably serve new data center load is the assignment of the costs and risks associated with LSEs \n86 Supra, n.32."},{"page":36,"startToken":10369,"endToken":10648,"text":"34 \nserving data center load.”87 The IMM explains that “the failure to exclude new data center load \nfrom the BRAs, as PJM proposes, would by definition impose significant costs on other \ncustomers and therefore violate the basic principle that data center costs should not be imposed \non other customers.”88\nThe IRAS proposal suffers from similar flaws.  It directs curtailment orders to Electric \nDistributors in whose zones New Large Loads are located, leaving it to the states to implement \ncurtailment and cost allocation rules. It provides incentive compensation for New Large Load \ncompliance and yet fails to implement penalties for non-compliance with curtailment directives. \nSimply put, the IRAS program does not satisfy the all encompassing objectives of the White \nHouse Ratepayer Protection Pledge – that existing consumers be truly held harmless from the \nrisks and costs associated with both existing Large Loads and New Large Loads.  \n Only direct and complete assignment of these costs and risks to the Large Load \ncustomers will fulfill this promise. Consequently, FERC should direct PJM to submit a \ncompliance filing that requires direct assignment to New Large Loads taking IRAS of \ncurtailment directives, related penalties and associated costs as a condition to interconnection \nwithout bringing adequate generating capacity as required under the Reliability Assurance \nAgreement capacity obligation rules.  \nIII.\nCONCLUSION \nOCC supports PJM’s proposal to interrupt New Large Loads that connect without \nsufficient supporting capacity before curtailing residential and other existing consumers.  OCC \n87 Monitoring Analytics, Critical Issue Fast Path Proposed Reliability Backstop Auction Proposal (Jun. 30, 2026), \navailable at \nhttps://www.monitoringanalytics.com/reports/Presentations/2026/IMM%20Backstop%20auction%20design%20pro\nposal%20-%20V6%202026.06.19.pdf (“IMM RBP Proposal”). \n88 Id."},{"page":37,"startToken":10648,"endToken":10721,"text":"35 \ndoes not, however, support the proposal to saddle the states with the obligation of ensuring New \nLarge Loads bear the consequences of their actions, nor does it support compensating those New \nLarge Loads for interruptions that are an inherent condition of receiving service without \nadequate capacity. Such customers should bear the consequences of their decision to take \nconditional service. The associated costs should not be shifted to other consumers, including \nresidential consumers."},{"page":38,"startToken":10721,"endToken":10901,"text":"36 \nWHEREFORE, OCC respectfully requests that FERC protect Ohio consumers by  \nrejecting the curtailment compensation element of PJM’s Interim Resource Adequacy Service \nproposal in this case; direct PJM to expand the list of entities entitled to access the Large Load \nRegistry to include state consumer advocate offices; direct PJM to submit a filing to address \ncurtailments that could be associated with Large Loads included in the RPM auctions for the \n2026/2027, the 2027/2028 and the 2028/2029 Delivery Years; and grant the additional forms of \nrelief requests in this Protest.       \nRespectfully submitted, \nMaureen Willis  \nOhio Consumers’ Counsel \n/s/ Angela O’Brien  \nAngela O’Brien \nDeputy Consumers’ Counsel  \nOffice of the Ohio Consumers’ Counsel \n65 East State Street, Suite 700 \nColumbus, Ohio 43215 \nTelephone: (614) 466-9531 \nangela.obrien@occ.ohio.gov\n/s/ Denise C. Goulet  \nDenise C. Goulet, Esq. \nMcCarter & English, LLP \n1301 K Street, N.W. \nSuite 1000 West \nWashington, D.C. 20005 \n(202) 753-3400 \ndgoulet@mccarter.com\nSpecial Counsel to the Ohio Office of the Attorney \nGeneral for the Office of the Ohio Consumers’ \nCounsel \nDATED:  September 3, 2026"},{"page":39,"startToken":10901,"endToken":10975,"text":"37 \nCERTIFICATE OF SERVICE \nI hereby certify that I have on this date served a copy of the foregoing document via \nelectronic mail upon all parties of record on the Commission’s official service list in this \nproceeding. Dated in Columbus, Ohio this 3rd day of September, 2026. \n/s/ Denise C. Goulet \nDenise C. Goulet \nMcCarter & English, LLP \n1301 K Street, N.W. \nSuite 1000 West \nWashington, D.C. 20005 \n(202) 753-3400 \ndgoulet@mccarter.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":105},{"p":2,"at":3,"title":"Table of Contents","method":"printed heading","endPage":2,"endAt":287,"startToken":105,"endToken":114},{"p":2,"at":287,"title":"A. PJM’s IRAS proposal to compensate IRAS load for curtailments is","method":"printed heading","endPage":2,"endAt":525,"startToken":114,"endToken":140},{"p":2,"at":525,"title":"B. FERC should direct PJM to modify the IRAS proposal to include","method":"printed heading","endPage":2,"endAt":750,"startToken":140,"endToken":173},{"p":2,"at":750,"title":"C. The IRAS Proposal is Unjust and Unreasonable because it fails to","method":"printed heading","endPage":2,"endAt":1004,"startToken":173,"endToken":201},{"p":2,"at":1004,"title":"D. PJM’s proposal to rely on state programs for curtailment and","method":"printed heading","endPage":2,"endAt":1270,"startToken":201,"endToken":225},{"p":2,"at":1270,"title":"E. PJM’s failure to include a penalty for New Large Load customer non-","method":"printed heading","endPage":2,"endAt":1539,"startToken":225,"endToken":249},{"p":2,"at":1539,"title":"F. The IRAS proposal is unjust and unreasonable because it does not","method":"printed heading","endPage":2,"endAt":1784,"startToken":249,"endToken":277},{"p":2,"at":1784,"title":"G. FERC should consider directing PJM to directly assign curtailment","method":"printed heading","endPage":5,"endAt":3,"startToken":277,"endToken":871},{"p":5,"at":3,"title":"I. BACKGROUND","method":"printed heading","endPage":9,"endAt":865,"startToken":871,"endToken":2258},{"p":9,"at":865,"title":"II. PROTEST","method":"printed heading","endPage":12,"endAt":847,"startToken":2258,"endToken":3122},{"p":12,"at":847,"title":"A. PJM’s IRAS proposal to compensate IRAS load for curtailments is patently","method":"printed heading","endPage":22,"endAt":347,"startToken":3122,"endToken":6106},{"p":22,"at":347,"title":"B. FERC should direct PJM to modify the IRAS proposal to include state","method":"printed heading","endPage":25,"endAt":1438,"startToken":6106,"endToken":7106},{"p":25,"at":1438,"title":"C. The IRAS Proposal is Unjust and Unreasonable because it fails to address","method":"printed heading","endPage":28,"endAt":4,"startToken":7106,"endToken":7850},{"p":28,"at":4,"title":"D. PJM’s proposal to rely on state programs for curtailment and allocation of","method":"printed heading","endPage":30,"endAt":808,"startToken":7850,"endToken":8634},{"p":30,"at":808,"title":"E. PJM’s failure to include a penalty for New Large Load customer non-","method":"printed heading","endPage":34,"endAt":1389,"startToken":8634,"endToken":9974},{"p":34,"at":1389,"title":"F. The IRAS proposal is unjust and unreasonable because it does not contain","method":"printed heading","endPage":35,"endAt":948,"startToken":9974,"endToken":10218},{"p":35,"at":948,"title":"G. FERC should consider directing PJM to directly assign curtailment","method":"printed heading","endPage":36,"endAt":1433,"startToken":10218,"endToken":10582},{"p":36,"at":1433,"title":"III. CONCLUSION","method":"printed heading","endPage":39,"endAt":4,"startToken":10582,"endToken":10902},{"p":39,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":39,"endAt":442,"startToken":10902,"endToken":10975}]}