{"document":{"slug":"rec-20260903-5190","title":"Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate on PJM Interconnection, L.L.C.’s filing to establish Interim…","issued":"2026-09-03","accession":"20260903-5190","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Ohio Federal Energy Advocate","kind":"comments","file":"sources/filings/text/20260903-5190_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5190","tier":"record","sha256":"1b2f5f8e7b20a8ea3391bf632d7bae488094e24ba9a0bde5dce301d3c9a4c309","pages":11,"tokens":2820,"emptyPages":[],"textThemes":["flex","adequacy","registry","retail"]},"pages":[{"page":1,"startToken":0,"endToken":273,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n  \nPJM Interconnection, L.L.C.                                    )                          Docket No. ER26-3515-000 \n                       \n \n \n \n \nCOMMENTS OF THE PUBLIC UTILITIES COMMISSION OF OHIO’S \nOFFICE OF THE FEDERAL ENERGY ADVOCATE \n \nOn August 13, 2026, PJM Interconnection, L.L.C. (PJM) filed, pursuant to section 205 of \nthe Federal Power Act, revisions to the PJM Open Access Transmission Tariff (OATT) and the \nReliability Assurance Agreement (RAA) to establish a new Interim Resource Adequacy Service \n(IRAS). PJM proposes IRAS as a condition of transmission service for New Large Load (NLL), \nas defined in the filing, to be used during periods when there are insufficient resources to reliably \nmeet demand in real time operations starting with the 2027/2028 Delivery Year (i.e., June 1, \n2027). When triggered by system conditions, IRAS will enable PJM to prioritize load reduction \nin zones/areas where NLLs have not brought their own new capacity or had their capacity needs \ncovered through the Reliability Backstop Procurement (RBP).1  \nTo support the IRAS framework, PJM proposes numerous revisions to the OATT and/or \nRAA to include, among others, 1) incorporating definitions of Large Load, New Large Load, and \nEligible New Large Load; 2) clarifying a Load Serving Entity’s (LSE) obligation to bring new \ncapacity in an amount equal to or exceeding the peak load of the NLL it serves or be subject to \nload curtailment prioritization during emergencies; 3) establishing a Large Load Registry and \nrequiring LSEs and electric distribution utilities (EDUs) to provide information to the Registry as \nnecessary for PJM to determine the megawatt (MW) quantity of IRAS responsibility by \n \n1 PJM Transmittal Letter at 1-2."},{"page":2,"startToken":273,"endToken":560,"text":"2 \nzone/area; 4) establishing curtailment prioritization for Eligible NLL during emergency grid \nconditions; and 5) establishing a compensation scheme for Eligible NLL that has provided IRAS \nload reduction service. \nThe Office of the Federal Energy Advocate (Ohio FEA) of the Public Utilities \nCommission of Ohio (PUCO), fulfilling its statutory duty to advocate on behalf of Ohio’s retail \nelectricity consumers,2 offers the following comments for consideration by the Federal Energy \nRegulatory Commission (Commission). \nI. \nBackground \nPJM’s capacity market, called the Reliability Pricing Model (RPM), is designed to ensure \nlong-term grid reliability by procuring the appropriate amount of supply needed to meet \npredicted peak load, plus an adequate reserve margin, three years in the future. A primary \nobjective of the capacity market is to match (or balance) power supply with future demand, \nthereby creating long-term price signals to attract needed investments to ensure resource \nadequacy. Under the RPM, capacity resources are procured by PJM through an annual, \ncompetitive Base Residual Auction (BRA). \nIn December 2025, the BRA conducted for the 2027/2028 Delivery Year represented the \nfirst time in recent history that large load additions significantly increased PJM’s load forecast \nwhich, in turn, significantly increased the PJM Region Reliability Requirement, in megawatts, \nPJM sought to procure in the auction. The auction resulted in a capacity procurement that was \n6,517 MW short of the PJM Region Reliability Requirement and 5.6 percent below the target \n20% Installed Reserve Margin (IRM).3 Similarly, in July 2026, the BRA conducted for the \n \n2 Ohio Revised Code 4928.24. \n3 PJM 2027/2028 Base Residual Auction Reserve Target Shortfall Report, February 9, 2026, available at \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-2028/2027-2028-bra-reserve-\ntarget-shortfall-report.pdf at 1."},{"page":3,"startToken":560,"endToken":854,"text":"3 \n2028/2029 Delivery Year cleared 6,831 MW below the PJM Region Reliability Requirement and \n5.6 percent below the 20% IRM.4 \nOver this time, PJM undertook various efforts to address the increasingly urgent resource \nadequacy needs of the region, including establishing a Reliability Resource Initiative and then an \nExpedited Interconnection Track to expedite the interconnection of new capacity resources, and \ninitiating multiple Critical Issue Fast Path (CIFP) stakeholder processes to address the challenge \nof maintaining reliability while efficiently integrating new large loads, namely data centers. In \nAugust 2025, PJM initiated a broad CIFP on Large Load Additions, which the PJM Board of \nManagers (PJM Board) addressed in a decisional letter in January 2026.5 The PJM Board \ndirected PJM, among other endeavors, to implement a “connect-and-manage” framework for \nnew large loads that do not bring their own new generation with curtailment expected to occur \nprior to the deployment of pre-emergency Demand Response, subject to stakeholder \ndevelopment of the appropriate operational framework.6  \nIn March 2026, PJM initiated a Connect and Manage Senior Task Force, which later \nmerged with the CIFP on the RBP. The CIFP held lengthy discussion over two months and \nconsidered nearly a dozen “connect-and-manage” solution packages; however, the members \nfailed to endorse a package to the PJM Board to conclude the effort. As a result, on July 27, \n2026, the PJM Board issued a decisional letter setting forth the framework contained in the \n \n4 PJM 2028/2029 Base Residual Auction Report, July 14, 2026, available at https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results-report.pdf at 3. \n5 PJM Board Decisional Letter, January 16, 2026, available at https://www.pjm.com/-/media/DotCom/about-\npjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-load-\nadditions.pdf. \n6 Id. at 4-5."},{"page":4,"startToken":854,"endToken":1152,"text":"4 \ninstant docket, renaming “connect-and-manage” as Interim Resource Adequacy Service.7 The \nOhio FEA supports the filing. \nII. \nComments \nA. \nData Centers Are the Large Loads Driving Historic Demand.  \nAs an initial matter, the Ohio FEA maintains that data centers are the large loads driving \nhistoric demand in the PJM footprint and, therefore, PJM should define Large Load to be \nspecific to data centers, not all loads of a designated size. It has become obvious to most that data \ncenters are unique large loads that warrant distinction from other commercial or industrial \ncustomers. Ohio was one of the first states to establish data center tariffs with a defined data \ncenter customer class, and the Ohio FEA recommends PJM do likewise.8  \nPJM goes on to define New Large Load for purposes of applying a Bring Your Own New \nCapacity (BYONC) construct, and Eligible New Large Load for purposes of determining an \nIRAS obligation based on whether NLL fulfills its BYONC requirement. Eligible NLL is \ncalculated as the difference between a NLL’s registered peak load in MW and its BYONC \narrangements and/or Allocated RBP Unforced Capacity in MW, as reported in the Large Load \nRegistry.9 Again, no distinction is made between the computational loads that are directly \nresponsible for the current state of resource adequacy – such as hyperscale data centers and \ncryptocurrency miners – and traditional manufacturing loads that drive American industry. As \nthis nation, under the current administration’s leadership, works to onshore and expand domestic \n \n7 PJM Board Decisional Letter, July 27, 2026, available at https://www.pjm.com/-/media/DotCom/about-pjm/who-\nwe-are/public-disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement-and-\nconnect-and-manage.pdf.  \n8 The PUCO has approved, or is currently in the process of reviewing, this tariff for each of its EDUs. \n9 Proposed PJM Tariff Attachment DD-4, Section V."},{"page":5,"startToken":1152,"endToken":1471,"text":"5 \nmanufacturing, it is counterproductive to place additional constraints on traditional \nmanufacturers and other non-data center large loads.  \nB. \nBYONC Is Necessary to Avoid Curtailment and Maintain Reliability.  \nThe Ohio FEA supports a BYONC framework and PJM’s proposal to incent LSEs to \nbring new capacity resources to bear commensurate with the addition of NLL, which PJM \ndefines to mean new or incremental large loads that go into service after June 1, 2027. We agree \nthat bringing new capacity to match new large load is the optimal solution to address resource \nadequacy concerns and is strongly preferred to IRAS. However, given the challenges of bringing \nnew capacity resources online to meet new demand in the near term, we find PJM’s BYONC \nproposal to be reasonable. PJM proposes that, starting on June 1, 2027, any NLL that has not yet \nbrought new capacity would be subject to priority curtailment during emergency grid conditions \n(i.e., IRAS Action). As the electric grid is and will continue to be stressed by an imbalance \nbetween demand and supply, IRAS Action is a critical operational tool for PJM to use when \nsystem conditions threaten reliability in real time. As further discussed below, this tool also \nprotects other non-large load customers from curtailment. To avoid potential IRAS Action, NLL \nmust contract with new capacity that meets the BYONC gating criteria, including that the new \ncapacity will be available for at least 10 years.  \nC. \nRegistry Is Key to Successful Implementation. \nThe Ohio FEA appreciates PJM’s proposal to establish a Large Load Registry, which is \nfundamental to the IRAS framework and necessary for successful state implementation. As \ndescribed in the filing,  \nPJM will use the registry to determine the quantity of [NLL] by zone/area \nand allocate IRAS responsibility to each zone/area accordingly, starting \nwith the 2027/2028 Delivery Year. States may leverage the Large Load \nRegistry to inform the implementation of retail constructs including load"},{"page":6,"startToken":1471,"endToken":1752,"text":"6 \nreduction priorities and cost allocation at the retail level to appropriate \nend-use customers.10  \n \nThe Ohio FEA agrees that the registry will be extremely helpful in assisting states with \nstandardizing data around large loads generally and is a necessary component for administering \nthe IRAS framework. Details around the proposed registry highlight the significant and ongoing \ncollaboration of many parties that will be necessary to execute a connect-and-manage program. \nConsistent with state public record laws and administrative procedures, state commissions \nroutinely receive and maintain confidential information from regulated utilities and suppliers, \nparties to legal proceedings, auditors, project developers, competitive auction bidders, etc. Thus, \nthere should be no concern about data protection standards for state commissions with access to \nthe registry. On the contrary, the only way that states, LSEs, EDUs, and PJM can reasonably be \nexpected to accurately co-manage a program like IRAS is through a centralized repository like \nthe Large Load Registry.   \nD. \nIRAS Actions Must Precede Other Emergency Actions to Protect Other \nCustomers. \n \nPJM’s filing describes the current practices set forth in PJM Manual 13 for when capacity \nshortages give rise to emergency procedures, including three levels of NERC Energy Emergency \nAlert Levels (EEA1 through EEA3), with EEA3 being the highest alert level. PJM also describes \nthe way it would incorporate IRAS Actions into those emergency procedures.11 While PJM \nexplains that grid operators have the flexibility to implement emergency procedures in whatever \norder is required to ensure system reliability, the Ohio FEA strongly supports PJM’s proposal to \ngenerally sequence IRAS Actions first at the beginning of an EEA1.12 The electric grid is \n \n10 PJM Transmittal Letter at 28-29. \n11 Pilong Affidavit at 7-12.  \n12 Id.at 6."},{"page":7,"startToken":1752,"endToken":2055,"text":"7 \nincreasingly constrained by the addition of large loads; therefore, it is reasonable for large loads \nthat do not play a role in remedying the supply and demand imbalance to be curtailed prior to \nother load. This is an essential element of PJM’s proposal. Deploying IRAS Actions prior to \ndeploying Pre-Emergency Load Management Reductions will protect other customers from a \nwide range of pre-emergency (EEA1) and emergency (EEA2) actions that otherwise would \nimpose significant financial impact and shift reliability risk to other customers. Further, \nprioritizing IRAS Actions is a necessary step to comply with the Statement of Principles \nRegarding PJM, as signed by the National Energy Dominance Council and the 13 PJM \ngovernors, and the Ratepayer Protection Pledge.  \nShould PJM fail to prioritize IRAS Actions, such as re-sequence them to occur just prior \nto the issuance of manual load shed under an EEA3, damage to retail ratepayers will already \nhave been done. During emergency system conditions, the dispatch of Emergency Demand \nResponse Resources (generally under EEA2) will cause energy prices to rise dramatically for all \nloads. Non-essential building loads will be curtailed. Emergency back-up generators will be \ndispatched. These costly and harmful scenarios could all be avoided (or at least minimized) by \ndeploying IRAS Actions first, at the beginning of an EEA1, as PJM proposes. \nAlso importantly, as PJM notes, if PJM were to call IRAS Actions after Demand \nResponse Resources have been exhausted, this would eliminate the incentive of NLL to contract \nfor new capacity because they would be insulated from curtailment by Demand Response.13 \nPutting IRAS in the privileged position of being deployed after Emergency Demand Response \nwould serve as a perverse incentive for NLL to actually prefer IRAS over bringing new capacity \nto the system as required to ensure resource adequacy and reliability. \n \n13 PJM Transmittal Letter at 80."},{"page":8,"startToken":2055,"endToken":2389,"text":"8 \nE. \nStates Must Have Flexibility to Determine IRAS Action Compensation. \nThe need for curtailment, and therefore compensation, would not exist but for Eligible \nNLL connecting to the system before adequate supply is available. The foundation of PJM’s \nIRAS proposal, if approved by the Commission, is that Eligible NLL will be able to connect to \nthe grid prior to meeting the BYONC requirement. Thus, the Eligible NLL will benefit from the \ncapacity market and appropriately pay capacity costs. Under IRAS, the capacity market will still \nserve as the primary vehicle to incent resource adequacy in the PJM region, and most capacity \nresources will still be obligated to make a cost-based bid into the energy market. And as \nrecognized by PJM’s Effective Load Carrying Capability accreditation methodology, capacity \nwill continue to have value across all hours and seasons, not only during critical peak hours. \nAccordingly, Eligible NLL will derive capacity market benefits most of the time (i.e., all \nintervals during which they are not called upon to curtail pursuant to an IRAS Action). \nHowever, the Ohio FEA recognizes that Eligible NLL subject to priority curtailment may \nnot receive the full benefit afforded to other capacity backed loads. While allowing Eligible NLL \nto connect to the system and benefit from the capacity market without bringing new supply could \nbe considered a form of compensation, some stakeholders in the CIFP process asserted that a \nlevel of compensation may be appropriate. To address the issue, PJM proposes a wholesale \ncompensation rate equal to 50% of its existing Non-Performance Charge Rate but asserts that the \nwholesale rate is flexible and can be reduced to less than 50% of the Non-Performance Charge \nRate based on retail rates.14 In establishing the wholesale compensation rate, PJM specifically \nstates: \nNothing in this Tariff, Attachment DD-4, section X shall interfere with any \nEligible New Large Load’s election to (i) accept in its retail rates a sum less \nthan 50% of the Non-Performance Charge Rate as compensation for the \n \n14 Id. at 102."},{"page":9,"startToken":2389,"endToken":2661,"text":"9 \nprovision of wholesale Interim Resource Adequacy Service, or (ii) waive \nreceipt in its retail rates any compensation for the provision of wholesale \nInterim Retail Adequacy Service.15 \n \nWhile offering no opinion on whether the proposed 50% of the Non-Performance Charge \nRate is just and reasonable, the Ohio FEA appreciates the deference shown to states to further \ndetermine IRAS compensation through retail ratemaking.16 States may find it necessary or \nappropriate to consider whether compensation is consistent with the Ratepayer Protection Pledge \nand/or other commitments to insulate other customers from cost shifting that could arise if \nEligible NLL is compensated for IRAS Action. Accordingly, as PJM describes, states may \ndetermine, through their retail tariffs or other regulatory mechanisms, whether IRAS \ncompensation should be 50% of the Non-Performance Charge Rate or lower, even zero. Should \nthe Commission find there to be a lack of clarity on PJM’s proposed compensation framework, \nwe request the Commission affirm in its Order that states have optionality to determine the level \nof IRAS compensation at the retail level. \nIII. \nConclusion \nPJM’s IRAS is a timely effort to confront reliability concerns caused by significant data \ncenter load growth in the region. The proposed BYONC construct, the Large Load Registry, and \nthe curtailment prioritization of certain loads when necessary to ensure reliability during \nemergency conditions will all require massive new coordination effort by PJM, states, EDUs, \nand LSEs. Together we must ensure that new resources are secured to meet new demand while \nmitigating any compounding effect on PJM grid operations, markets, or other ratepayers. \n \n \n \n15 Proposed PJM Tariff Attachment DD-4, Section X(c).  \n16 PJM Transmittal Letter at 106-107."},{"page":10,"startToken":2661,"endToken":2727,"text":"10 \nRespectfully submitted,  \nD. Andrew Wilson \nOhio Attorney General  \n \nJohn H. Jones  \nSection Chief \n \n \n  \n \n \n \n \n/s/ Thomas G. Lindgren \n \n \n \nThomas G. Lindgren  \nAssistant Attorney General  \nPublic Utilities Section  \n30 East Broad Street, 16th Floor  \nColumbus, Ohio 43215-3414  \n614.644.8768 (telephone)  \n866.818.6152 (facsimile)  \nThomas.Lindgren@OhioAGO.gov  \n \nOn Behalf of the Public Utilities  \nCommission of Ohio’s Office of the  \nFederal Energy Advocate  \n \nSeptember 3, 2026"},{"page":11,"startToken":2727,"endToken":2820,"text":"11 \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have on this date caused a copy of the foregoing document to be \nserved on each person included on the official service list maintained for this proceeding by the \nCommission’s Secretary, by electronic mail or such other means as a party may have requested, \nin accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.2010.  Dated this the 3rd day of September 2026, at Columbus, Ohio. \n \n/s/ Thomas G. Lindgren \n \nThomas G. Lindgren  \nAssistant Attorney General"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":524,"startToken":0,"endToken":347},{"p":2,"at":524,"title":"I. Background","method":"printed heading","endPage":4,"endAt":124,"startToken":347,"endToken":871},{"p":4,"at":124,"title":"II. Comments","method":"printed heading","endPage":4,"endAt":139,"startToken":871,"endToken":873},{"p":4,"at":139,"title":"A. Data Centers Are the Large Loads Driving Historic Demand.","method":"printed heading","endPage":5,"endAt":145,"startToken":873,"endToken":1170},{"p":5,"at":145,"title":"B. BYONC Is Necessary to Avoid Curtailment and Maintain Reliability.","method":"printed heading","endPage":5,"endAt":1478,"startToken":1170,"endToken":1388},{"p":5,"at":1478,"title":"C. Registry Is Key to Successful Implementation.","method":"printed heading","endPage":6,"endAt":1087,"startToken":1388,"endToken":1624},{"p":6,"at":1087,"title":"D. IRAS Actions Must Precede Other Emergency Actions to Protect Other","method":"printed heading","endPage":8,"endAt":3,"startToken":1624,"endToken":2056},{"p":8,"at":3,"title":"E. States Must Have Flexibility to Determine IRAS Action Compensation.","method":"printed heading","endPage":9,"endAt":1152,"startToken":2056,"endToken":2562},{"p":9,"at":1152,"title":"III. Conclusion","method":"printed heading","endPage":10,"endAt":30,"startToken":2562,"endToken":2664},{"p":10,"at":30,"title":"D. Andrew Wilson","method":"printed heading","endPage":11,"endAt":4,"startToken":2664,"endToken":2728},{"p":11,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":556,"startToken":2728,"endToken":2820}]}