{"document":{"slug":"rec-20260903-5197","title":"Comments of ACORE on PJM Interconnection, L.L.C.'s 08/13/2026 proposal to establish Interim Resource Adequacy Service and a large load registry","issued":"2026-09-03","accession":"20260903-5197","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"American Council on Renewable Energy","kind":"comments","file":"sources/filings/text/20260903-5197_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5197","tier":"record","sha256":"09c36cb556fc42083331fa8963196d57f4e66ae385eb6a551b6a3e6496a0e71b","pages":4,"tokens":846,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":253,"text":"1 \n \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \nDocket No. ER26-3515-000 \n \nACORE COMMENTS ON PJM INTERCONNECTION LLC  \nINTERIM RESOURCE ADEQUACY SERVICE PROPOSAL \n \n Pursuant to Rule 211 of the Federal Energy Regulatory Commission (Commission) \nRules of Practice and Procedure,1 ACORE submits these comments on the PJM Interconnection, \nL.L.C. (PJM) proposal to establish Interim Resource Adequacy Service (IRAS) and a large load \nregistry (IRAS Proposal) submitted on August 13, 2026 in the above captioned docket.  \nACORE provides these supportive comments directed at the specific IRAS requirements \nfor Bring Your Own New Capacity (BYONC). ACORE recognizes the immediate need for PJM \nto address the dramatic increase in demand resulting from the expansion of large loads within its \nfootprint. Any reforms developed to address this need must incent and be aligned with a longer-\nterm contracting paradigm rather than reliance on the short-term volatile pricing in PJM’s annual \nReliability Pricing Model (RPM) capacity market. \nACORE therefore supports the requirement for a new large load to contract for new \ncapacity under BYONC to avoid being subject to potential curtailments under IRAS.  Such a \nrequirement will strongly incent longer-term (at least 10 year) contracting with BYONC capacity \nby the large loads availing themselves of the IRAS BYONC provision.  ACORE is also \nsupportive of the requirement that the BYONC resources participate as a price taker in the Base \nResidual Auction (BRA) for 10 consecutive Delivery Years and be subject to the RPM’s must \n \n1 18 C.F.R. § 385.211 (2024)."},{"page":2,"startToken":253,"endToken":576,"text":"2 \n \noffer requirement during that time frame.2 The submission of capacity as a price taker allows the \ncapacity prices to reflect that these long-term arrangements will settle at a more stable price \noutside of the volatile clearing prices of the BRAs. \nIn PJM’s May whitepaper, Powering Reliability Through Market Design, PJM accurately \ndescribes the importance of revenue predictability and stability for the development of capital-\nintensive generation and storage capacity: \nIn conversations with generation developers, project finance lenders, equity investors and \npower project consultants in furtherance of this initiative, PJM heard a strikingly \nconsistent message: High capacity prices alone do not drive investment decisions. The \nbarriers cited – repeatedly and across investor types – were revenue durability over the \nproject financing horizon and regulatory stability sufficient to make long-term revenue \nprojections credible.3 \nIn addition to the ten-year price taker requirement, ACORE also appreciates the \nexpansive scope of BYONC to include not only needed new builds, but also capacity obtained \nthrough the utilization of Surplus Interconnection Service (SIS), as well as new demand response \nand distributed energy resources, and other types of capacity expansion. ACORE has long \nsupported a greater use of SIS, especially for storage, but more improvements are needed.4 In a \nrecent letter, PJM President and CEO David Mills stated that: “PJM understands that some \naspects of our existing market rules for facilities interconnecting via the SIS process make it \nchallenging for these facilities to provide capacity. Given the abundant interest in leveraging SIS \nto provide additional capacity, PJM staff and stakeholders recently initiated a workplan to \n \n2 PJM IRAS Proposal at 55-56. \n3 PJM Interconnection LLC, Powering Reliability Through Market Design (May 2026) at 32, \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-\nreliability-through-market-design.pdf  \n4 See ACORE comments in support of PJM’s proposal for revisions to its Open Access Transmission \nTariff governing Surplus Interconnection Service, Docket No. ER25-778 (Jan. 13, 2025), \nhttps://acore.org/resources/acore-comments-on-pjm-surplus-interconnection-service-proposal/"},{"page":3,"startToken":576,"endToken":800,"text":"3 \n \naddress market rules that are potentially limiting its current use.”5 ACORE supports both the use \nof SIS for BYONC and the importance of further PJM actions to improve its feasibility.  \nFinally, while not directly within the scope of IRAS but highly relevant to its success, \nACORE continues to emphasize that a holistic approach is needed to address both the challenges \nand opportunities of large load integration. Such an approach will entail additional reforms and \nimprovements that provide greater certainty and stability in the interconnection process,6 \nCommission action on PJM’s Order No. 1920 compliance filing, and greater development of \nhigh-voltage interregional transmission between PJM and other regions. ACORE and our \nmembership look forward to ongoing engagement with the Commission on these important \nissues. \n \n \n \n \n \n \n \nRespectfully submitted, \n/s/ Elise Caplan  \nElise Caplan  \nVice President, Regulatory Affairs \nACORE \n1150 Connecticut Ave NW, Suite 401  \nWashington, D.C. 20036  \n(301) 646-7130 \ncaplan@acore.org  \n \nSeptember 3, 2026 \n \n \n5 Letter from David Mills, President and CEO, PJM Interconnection LLC to Senator Koch, Delegate \nHernandez, and Senator VanValkenburg (August 19, 2026), https://www.pjm.com/-\n/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260827-pjm-president-ceo-response-\nto-indiana-virginia-legislators-letter-regarding-surplus-interconnection-service.pdf.  \n6 For more details on needed interconnection reforms, see the ACORE Issue Brief, Interconnection \nBarriers Continue and Fundamental Reforms are Needed (July 2026), https://acore.org/wp-\ncontent/uploads/2026/07/ACORE-Issue-Brief-Interconnection-Barriers-Continue-and-Fundamental-\nReforms-are-Needed.pdf."},{"page":4,"startToken":800,"endToken":846,"text":"4 \n \nCERTIFICATE OF SERVICE \nThe undersigned certifies that a copy of this pleading has been served this day upon each \nperson designated on the official service list compiled by the Secretary in this proceeding.  \nDated this 3rd day of September, 2026.  \n/s/ Elise Caplan  \nElise Caplan"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":5,"startToken":0,"endToken":801},{"p":4,"at":5,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":4,"endAt":287,"startToken":801,"endToken":846}]}