{"document":{"slug":"rec-20260903-5200","title":"Motion to Intervene and Protest of Talen Energy Corporation re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service","issued":"2026-09-03","accession":"20260903-5200","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Talen Energy Corporation","kind":"protest","file":"sources/filings/text/20260903-5200_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5200","tier":"record","sha256":"648dfb54d1885379ed030536eb8ee7a6e851db3dc375b72a50fdba811c809c9f","pages":52,"tokens":12452,"emptyPages":[],"textThemes":["adequacy","flex","registry"]},"pages":[{"page":1,"startToken":0,"endToken":320,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \n \nMOTION TO INTERVENE AND  \nPROTEST OF TALEN ENERGY CORPORATION \n \nPJM Interconnection, L.L.C.’s (“PJM”) Interim Resource Adequacy Service (“IRAS”) and \nLarge Load Registry to Address System Reliability1 proposal should be rejected because it is \nunjust, unreasonable, and unduly discriminatory.  While Talen appreciates PJM’s goals of \nprotecting ratepayers from rising costs while maintaining reliability, the vehicle chosen by PJM to \narrive at that destination is a lemon and, as explained in the attached testimony of Zachary Ming \nof Energy and Environmental Economics, Inc. (“E3”), will result in inaccurate price signals, early \nand unnecessary generation resource retirements, and increased prices in the long-term.  First and \nforemost, however, PJM’s vehicle should not even be on the road because it does not comply with \nwell-established law. \nThe IRAS Proposal fails to comply with PJM’s Operating Agreement and the Federal \nPower Act (“FPA”).2  PJM claims that New Large Load is not similarly situated to other load, \nincluding existing Large Load, and thus is not unduly discriminated against under the IRAS \nProposal.  PJM’s argument is erroneous and conclusory.  PJM cannot explain how New Large \nLoad is uniquely situated in the context of procuring new capacity and emergency curtailment.  In \n \n1  \nProposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load \nRegistry to Address System Reliability, Docket No. ER26-3515-000 (filed Aug.13, 2026) (“IRAS Proposal”). \n2  \n16 U.S.C. § 824d(b) (2024) (prohibiting the Federal Energy Regulatory Commission from approving \ndiscriminatory tariffs); PJM Operating Agreement, Schedule 1, section 1.7.11(a) (“The standards, policies and \nprocedures of the Office of the Interconnection for declaring the existence of an Emergency, including but not \nlimited to a Minimum Generation Emergency, and for managing, alleviating or ending an Emergency, shall apply \nto all Members on a non-discriminatory basis.”) (emphasis added)."},{"page":2,"startToken":320,"endToken":624,"text":"2 \n \nfact, PJM’s Operating Agreement requires the grid operator to apply emergency procedures “to all \nMembers on a non-discriminatory basis.”3  The IRAS Proposal, contrary to the Operating \nAgreement, singles out New Large Load for curtailment during NERC Emergency Energy Alert \nLevel 1 (“EEA1”) periods even before Demand Resources that have previously agreed to curtail.4   \nPJM’s claim that the States retain “exclusive jurisdiction” to determine which specific New \nLarge Load customers will be curtailed is also unavailing.5  PJM proposes to single out which \ncustomers to curtail but leave the final “flip the switch” decision to the States.  A State is not truly \nexercising its “exclusive jurisdiction” if the only decision it is left with is to take the action PJM \ndirects or not act at all.  In effect, PJM is creating an unduly discriminatory tariff regime that \nunlawfully encroaches on the States’ exclusive jurisdiction.  This is patently unjust and \nunreasonable. \nThe IRAS Proposal does not make economic sense either and will not result in the long-\nterm stability that PJM is seeking.  Zachary Ming of E3 explains in his attached testimony that the \nIRAS Proposal will have “knock-on effects” resulting in uneconomic outcomes and diminished \nreliability in the long-term.6  Specifically, excluding New Large Load7 from the Variable Resource \nRequirement (“VRR”) Curve artificially limits competition in the existing capacity market.8  The \nresult will initially be a capacity clearing price that fails to equal net Cost of New Entry (“CONE”), \n \n3  \nId. \n4  \nIRAS Proposal at 78-79 (citing PJM Manual 13, section 2.3.1). \n5  \nId. at 90. \n6  \nSee Exhibit A at 20, Testimony of Zachary Ming, Energy and Environmental Economics, Inc. (Sept. 3, 2026) \n(“Ming Testimony”). \n7  \nCapitalized terms not otherwise defined herein shall have the meaning provided thereto in the IRAS Proposal. \n8  \nSee Ming Testimony at 27."},{"page":3,"startToken":624,"endToken":926,"text":"3 \n \nwhich will lead to a reduced incentive to invest in the existing generation fleet and potentially early \nretirement of existing resources that are limited to the existing capacity market.9  Therefore, the \nparadoxical result of PJM’s IRAS Proposal will be increased societal costs and decreased system \nreliability. \nTalen Energy Corporation (“Talen”) agrees that PJM capacity market reform is necessary.  \nThe IRAS Proposal is just not the solution.  PJM conducted several Critical Issue Fast Path \nprocesses over the past year to address capacity shortfalls and large load demand.  The result of \nthat effort were dozens of rejected proposals, including eleven proposals related to PJM’s “connect \nand manage” construct—the predecessor to IRAS.10  PJM’s Board eventually overruled the \nstakeholders’ rejections and moved forward with the rebranded “IRAS” Proposal nonetheless.11 \nTalen supports holistic market reform that is non-discriminatory, legally durable, and \nmethodical, with short-term and long-term implications in mind.  Such holistic reform should focus \non increasing supply in the PJM region by incentivizing new generation resources to come online \ninside the existing reliability pricing model (“RPM”) structure.  The IRAS Proposal is premature \nand permanent and should not be adopted because it will circumvent much needed holistic \nreform.12  Talen respectfully submits this protest (“Protest”) to the IRAS Proposal accordingly13 \n \n9  \nId. at 28. \n10  Stakeholder Process on Backstop Procurement and Connect and Manage Moves Forward, PJM INSIDE LINES \n(July 1, 2026), available at https://insidelines.pjm.com/stakeholder-process-to-procure-generation-and-serve-\nlarge-loads-moves-forward/. \n11  See Brooks, Michael and Leith-Yessian, Devin, PJM to Create Large Load Registry, Proposes to Hold Backstop \nAuction in October, RTO INSIDER (July 28, 2026), available at https://www.rtoinsider.com/137723-pjm-to-create-\nlarge-load-registry-proposes-backstop-auction/. \n12  See Ming Testimony at 25. \n13  Talen is filing this protest pursuant to Rule 211 of FERC’s Rules of Practice and Procedure.  18 C.F.R. § 385.211 \n(2026)."},{"page":4,"startToken":926,"endToken":1217,"text":"4 \n \nand requests that the Federal Energy Regulatory Commission (“FERC” or “Commission”) reject \nPJM’s filing as unjust, unreasonable, and unduly discriminatory. \nI. \nMOTION TO INTERVENE \nPursuant to Rule 214 of the Commission’s Rules of Practice and Procedure,14 Talen \nrespectfully submits this motion to intervene in the above-captioned proceeding.  The formal legal \nname of Talen is Talen Energy Corporation.  Talen is a corporation organized and existing under \nthe laws of Delaware.  Talen maintains its principal place of business at 2929 Allen Parkway, 22nd \nFloor, Houston, Texas 77019. Talen is a leading independent power producer and energy \ninfrastructure company which owns and operates approximately 15.7 gigawatts of power \ninfrastructure in the United States.  Talen produces and sells electricity, capacity, and ancillary \nservices into wholesale U.S. power markets, including and primarily in PJM.  Accordingly, the \nactions taken by the Commission in this matter will directly affect the interests of Talen.  Talen \nhas a direct and material interest in the instant proceeding that no other party can adequately \nrepresent.  Talen therefore requests that the Commission grant this motion to intervene and permit \nTalen to participate in this proceeding with full rights as a party thereto. \nII. \nPROTEST \nThe existing RPM construct was designed to improve price stability, enhance reliability, \nand produce accurate price signals to incentivize new generation build.15  The U.S. Supreme Court \nobserved that  \n[t]he capacity auction serves to identify the need for new generation:  \nA high clearing price in the capacity auction encourages new \ngenerators to enter the market, increasing supply and thereby \nlowering the clearing price in the same-day and next-day auctions \n \n14  18 C.F.R. § 385.214.  \n15  PJM Interconnection, L.L.C., 117 FERC ¶ 61,331 at PP 68-69 (2006) (internal citation omitted)."},{"page":5,"startToken":1217,"endToken":1531,"text":"5 \n \nthree years’ hence; a low clearing price discourages new entry and \nencourages retirement of existing high-cost generators.16   \nPJM has adapted its approach to capacity auctions over past decades to produce more accurate and \ndefined price signals.  For example, PJM’s historical Capacity Credit Market (“CCM”) was \nreplaced by the reliability pricing model (“RPM”) twenty years ago because the CCM did “not \nenable market participants to see the reliability problems in particular locations” and did “not \nprovide price signals that would elicit solutions to reliability problems in enough time before the \nproblem occurs. . . .”17  If the goal is to produce accurate price signals that send clear messages to \nnew generation to build or to existing and costly generation to retire, then the market—a simulated \ncompetitive construct—cannot perform efficiently if PJM interferes with the capacity auctions by \nimplementing artificial caps on supply and demand.  Yet, that is the imprudent design and purpose \nof the IRAS Proposal.      \nA. \nPJM’s proposal to require New Large Loads to procure new capacity or be \nsubject to curtailment is unjust, unreasonable, and unduly discriminatory, and \nunlawfully encroaches on State jurisdiction.  \nSection 205(b) of the FPA prohibits the Commission from approving unjust, unreasonable, \nand unduly discriminatory tariffs.18  The regulated utility, as the movant under FPA Section 205, \ncarries the burden of proof that its proposal is just and reasonable and not unduly discriminatory \n“[b]ecause a regulated utility is the party with access to the necessary information [and] bears the \nrisk of an undeveloped or inconclusive record.”19 “Discrimination is undue when there is a \n \n16  Hughes v. Talen Energy Mktg., 136 S. Ct. 1288, 1293 (2016). \n17  PJM Interconnection, L.L.C., 117 FERC ¶ 61,331 at P 20. \n18  16 U.S.C. § 824d(b). \n19  Nantahala Power & Light Co. v. FERC, 727 F.2d 1342, 1351 (4th Cir. 1984); 16 U.S.C. § 824d."},{"page":6,"startToken":1531,"endToken":1817,"text":"6 \n \ndifference in rates or services among similarly situated customers that is not justified by some \nlegitimate factor.”20   \nThe Commission has explained that similarly situated does not mean that customers must \nbe without difference.21  Rather, “it means that there are no differences that are material to the \ninquiry at hand.”22  The Commission has also held that “entities are similarly situated if they are \nin the same position with respect to the ends that the law seeks to promote or the abuses that it \nseeks to prevent, even if they are different in many other respects.”23  For example, in Calpine \nOneta Power, L.P.,24 the Commission held that new and existing generators were similarly situated \nfor purposes of providing reactive power because they were equally capable of providing that \nservice.25  In Iberdrola Renewables, Inc. v. Bonneville Power Admin.,26 the Commission held that \n“non-[f]ederal resources are similarly situated to [f]ederal hydroelectric and thermal resources for \npurposes of transmission curtailments because they all take firm transmission service.”27 \nThe purpose of the IRAS Filing is to address a capacity shortfall, which means procuring \nnew capacity and curtailing load during emergency events.  Most load can procure new capacity \nprior to and after commencing service.  Moreover, requiring curtailment of New Large Load in the \n \n20  El Paso Natural Gas Co., 104 FERC ¶ 61,045, at P 115 (2003), reh’g denied, 106 FERC ¶ 61,233 (2004) (internal \ncitations omitted). \n21  New York Independent System Operator, 162 FERC ¶ 61,124 at P 10 (2018). \n22  Id. \n23  Id.  \n24  116 FERC ¶ 61,282 (2006) (“Calpine Oneta”). \n25  Id. at P 36. \n26  137 FERC ¶ 61,185 (2011) (“Iberdrola”). \n27  Id. at P 62."},{"page":7,"startToken":1817,"endToken":2156,"text":"7 \n \nbroad sense fails to take into consideration both that not all New Large Load is so flexible and that \ncertain load other than New Large Load is also capable of electing to curtail.  PJM’s proposed \ndisparate treatment of New Large Load is therefore unjust, unreasonable, and unduly \ndiscriminatory. \n1. \nPJM’s requirement that only New Large Load execute contracts with \nBYONC resources or be subject to curtailment is unjust, unreasonable, and \nunduly discriminatory. \nPJM is only requiring New Large Load to contract with BYONC resources to avoid \ncurtailment.  PJM does not dispute this disparate treatment.  Instead, PJM attempts to argue that \nNew Large Load is not similarly situated to any other load.  What PJM means is that the IRAS \nProposal admittedly discriminates against New Large Load, but PJM does not believe it is “undue” \ndiscrimination.  PJM is mistaken.  The evidence presented by PJM to justify its argument is limited \nto two statements:  (1) members of Congress have said that it would not be unduly discriminatory \nto treat data centers differently given their “incomparably large energy demands, how quickly data \ncenters can come online, and their unique potential to impact the reliability of the electric grid”;28 \nand (2) an out-of-context statement by the Commission  that “large loads constitute ‘a separate \ncategory of load’ because of their “size, operational behavior, and unique potential to impact the \ntransmission system.”29  However, these are mere differences in customer profiles and cannot \nsupport a finding of differences “that are material to the inquiry at hand.”30  The inquiry at hand is \n \n28  IRAS Proposal at 95-96 (citing Letter from the Members of Congress to David E. Mills, PJM Board Chair, PJM \nInterconnection, L.L.C., 4 (Nov. 5, 2025), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-\nare/publicdisclosures/2025/20251106-congressional-letter-re-cifp-lla.pdf [https://perma.cc/ZKA9-Q5LZ]). \n29  IRAS Proposal at 95-96 (citing PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 50 (2026) (“PJM June \n2026 Order”)). \n30  See New York Independent System Operator, 162 FERC ¶ 61,124 at P 10."},{"page":8,"startToken":2156,"endToken":2444,"text":"8 \n \nwhich loads are capable of bringing their own new capacity and which loads are capable of electing \nto curtail in emergency events.   \nNearly all new commercial load is capable of procuring new capacity.  PJM does not limit \nbilateral capacity markets to specific customers, nor does PJM limit capacity transactions to only \nlarge loads.  In fact, PJM’s Capacity Exchange system allows unit-specific bilateral transactions \nof as little as 0.1 MW.31  This means that New Large Load, existing Large Load, new commercial \nload, and others are “in the same position with respect to the ends that” the IRAS Proposal “seeks \nto promote.”32     \nResources beyond just New Large Load are also capable of electing to curtail service \nduring emergency events, e.g., large commercial industrial customers and existing Large Load.  \nExisting Large Load is completely indistinguishable from New Large Load in this context, just as \nnew and existing generation resources were equally capable of providing reactive power service \nin Calpine.33  This is also similar to federal and non-federal generation resources being equally \nable to curtail transmission service in Iberdrola.34  Although the customers at issue in Iberdrola \nwere all taking firm transmission service, the only reason New Large Load would be taking a \ndifferent service here, i.e., IRAS, is because PJM would force them to do so.   \nPJM attempts to build its argument for discriminating against New Large Load based on \nprior Commission language from the recent series of show cause orders issued to the six regional \n \n31  PJM Manual 18 at Section 4.6.2. \n32  See New York Independent System Operator, 162 FERC ¶ 61,124 at P 10. \n33  See Calpine Oneta, 116 FERC ¶ 61,282. \n34  See Iberdrola, 137 FERC ¶ 61,185."},{"page":9,"startToken":2444,"endToken":2750,"text":"9 \n \ngrid operators.35  Although the Commission proposed a definition for large load in the show cause \norders, the Commission was not implying that discriminating against such large load was just and \nreasonable.  Moreover, the broad definition of large load that the Commission used in the show \ncause orders is not applicable to the inquiry at hand in this proceeding.  Even the Commission \nrecognized in the show cause orders that only “flexible large loads that are willing and able to limit \ntheir use of the transmission system under certain conditions” should be offered a different \ntransmission service.36  The Commission clarified that “‘flexible’ large loads are a subset of large \nloads, as used in [that] order, that are not co-located with generation, but are willing and able to \nlimit their energy withdrawals from the transmission system under certain conditions.”37  \nTherefore, PJM’s reliance on the Commission’s recent show cause orders to discriminate against \nNew Large Loads is misplaced. \n2. \nCertain features of the IRAS Proposal are also unjust and unreasonable \ndue to PJM’s arbitrary and disparate treatment of load. \na. \nThe IRAS Proposal arbitrarily sets an unsupported floor for New \nLarge Load. \nThe size of a particular load is irrelevant to an inquiry regarding which entities can curtail.  \nNonetheless, the IRAS Proposal sets a 50 MW floor for New Large Load.  PJM has not provided \nany justification for this disparate treatment of load, nor can it.   \nTake an electric arc furnace facility (steel plant) in Pennsylvania for example.  Electric arc \nfurnaces are now the predominant method for steel production in the country and consume 40-200 \n \n35  IRAS Proposal at 96 (arguing that the Commission acknowledged that large loads are ‘a separate category of \nload’”) (citing PJM June 2026 Order, 195 FERC ¶ 61,211 at P 50). \n36  PJM June 2026 Order at P 3.  \n37  Id."},{"page":10,"startToken":2750,"endToken":3232,"text":"10 \n \nMW of electricity.38  Steel mills can temporarily shut down if needed during power shortages.39  \nUnder the IRAS Proposal, a 50 MW electric arc furnace would be curtailed first as a New Large \nLoad, even though a 40 MW electric arc furnace in the same region could similarly reduce its \nrespective load (and be compensated by PJM for doing so).  There is no difference between these \ncustomers with respect to the inquiry at hand.  In fact, they are equally capable of providing the \nends that PJM seeks.  Accordingly, PJM’s disparate treatment of New Large Load under the IRAS \nProposal is unjust, unreasonable, and unduly discriminatory. \nb. \nThe IRAS Proposal provides PJM with unjust, unreasonable, and \nunfettered discretion to issue curtailment directives. \nWell-established Commission precedent provides that matters directly affecting rates must \nbe included in an RTO’s filed tariff if the matter “significantly affects rates, terms, and conditions” \nof service, are readily susceptible of specification, and not generally understood in a contractual \nagreement.40  The IRAS Proposal provides that PJM will determine a quantity of MW that load in \na zone/area needs to curtail to maintain system reliability and will instruct the Electric Distributor \n \n38  Tita, Bob, AI Data Centers Have Been Great for The Steel Industry. Now, a Power Crisis Looms: Steelmakers \nWarn of Competition for Electricity From Their Newest Big Customer, WALL STREET JOURNAL (June 29, 2026), \navailable at https://www.wsj.com/business/energy-oil/ai-data-centers-power-competition-steel-48a17dbd. \n39  Id.  Other non-large load can also curtail.  For example, paper mills can act as a distributed energy resource by \n“burn[ing] black liquor (a paper-manufacturing byproduct) to generate electricity for their own operations or to \nfeed back into the system.”  The Many Types of Distributed Energy Resources, Common and Obscure, PJM \nINSIDE LINES (Aug. 14, 2019), available at https://insidelines.pjm.com/the-many-types-of-distributed-energy-\nresources-common-and-obscure/. \n40  Energy Storage Ass’n v. PJM, 162 FERC ¶ 61,296 at P 103 (2018) (“Energy Storage Ass’n”) (citing Midcontinent \nIndep. Sys. Operator, Inc., 158 FERC ¶ 61,003 at P 69 (2017); PacifiCorp, 127 FERC ¶ 61,144 at P 11 \n(2009); City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (finding that utilities must file “only \nthose practices that affect rates and service significantly, that are reasonably susceptible of specification, and that \nare not so generally understood in any contractual arrangement as to render recitation superfluous”); Public Serv. \nComm'n of N.Y. v. FERC, 813 F.2d 448, 454 (D.C. Cir. 1987) (holding that the Commission properly excused \nutilities from filing policies or practices that dealt with only matters of “practical insignificance” to serving \ncustomers);  Midwest Indep. Trans. Sys. Operator, Inc., 98 FERC ¶ 61,137, at 61,401 (2002), clarification \ngranted, 100 FERC ¶ 61,262 (2002) (“It appears that the proposed Operating Protocols could significantly affect \ncertain rates and services and as such are required to be filed pursuant to Section 205.”))."},{"page":11,"startToken":3232,"endToken":3558,"text":"11 \n \nto curtail such MW quantity, which will be equal to or less than the Eligible New Large Load \nAmount.41  The IRAS Proposal is silent, however, with respect to how PJM will determine the \nMW quantity to be curtailed or which Electric Distributors will be instructed to curtail.  The ability \nto curtail load and the potential to receive IRAS payments for such action certainly and \nsignificantly affects the rates, terms, and conditions of IRAS.  PJM must also have a process that \nis capable of being translated in written form to make such determinations and include those \ndeterminations in its Tariff.  Moreover, this proposal is a novel construct introduced for the first \ntime by PJM and is not generally understood under traditional Tariff contractual arrangements.  \nTherefore, under FERC’s “rule of reason” doctrine, PJM must include specific language regarding \nhow it will determine the MW quantity to be curtailed and which Electric Distributors it will \ninstruct to do so.  The potential for arbitrary and capricious decision-making in PJM’s process is \ntoo great to move forward without such specification.  Load being served under IRAS cannot make \ninformed commercial decisions if it must read tea leaves to determine when and how much it will \nbe curtailed in a region-wide reliability event. \nPJM carries the burden to prove that the IRAS Proposal is just and reasonable.42  The \neconomic reality of the IRAS Proposal is that it will result in inaccurate price signals, early and \nunnecessary generation retirements, increased prices in the long term, and its implementation will \nbe left to an opaque process known only to PJM.  The Commission cannot find such results to be \njust and reasonable and thus must reject the IRAS Proposal. \n \n41  IRAS Proposal at 86-87 (defining Eligible New Large Load Amount as “the MW value of load that an Eligible \nNew Large Load in a given zone/area may be required to be made available to IRAS.”).  \n42  See 16 U.S.C. § 824d."},{"page":12,"startToken":3558,"endToken":3878,"text":"12 \n \nc. \nThe IRAS proposal fails to account for New Large Load that \npreviously contracted for capacity from existing resources. \nChairman Laura Swett assured stakeholders that the Commission’s actions with respect to \nlarge load reforms and procedures “are not intended to disrupt existing commercial agreements.”43  \nTalen has previously explained that PJM’s reliability backstop procurement (“RBP”) proposal \nwould result in such load paying incremental capacity charges under the RBP.44  This is harmful \nto the entire market because “uncertainties regarding rate stability and contract sanctity can have \na chilling effect on investments and a seller’s willingness to enter into long-term contracts and this, \nin turn, can harm customers in the long run.”45  PJM is inserting additional uncertainty into the \nmarket through the forced interruption of service to certain New Large Loads that are not allocated \nRBP capacity and costs.  Accordingly, the IRAS Proposal fails to even treat New Large Load on \na consistent basis and unjustly introduces a chilling effect on investments in PJM.   \n3. \nPJM’s directive to curtail New Large Load unlawfully commandeers the \nStates’ exclusive jurisdiction. \nThe FPA properly establishes the Commission’s jurisdiction over wholesale activity, while \nStates retain their exclusive jurisdiction to regulate retail transactions.46  The FPA follows the \nTenth Amendment of the U.S. Constitution, which provides that “[t]he powers not delegated to \nthe United States by the Constitution, nor prohibited by it to the States, are reserved to the States \n \n43  Statement of FERC Chairman Laura Swett, FERC Open Meeting (June 18, 2026) at 10:42, https://ferc.gov/news-\nevents/events/june-18-2026-open-meeting-10082025. \n44  Motion to Intervene and Request for Clarification of Talen Energy Corporation, Docket No. EC26-3380-000 \n(filed Aug. 21, 2026). \n45  Market–Based Rates for Wholesale Sales of Electric Energy, Capacity and Ancillary Services by Public Utilities, \nOrder No. 697, 72 Fed. Reg. 39,904, 119 FERC ¶ 61,295, at P 6 (2007). \n46  16 U.S.C. § 824(b)."},{"page":13,"startToken":3878,"endToken":4157,"text":"13 \n \nrespectively, or to the people.”47  This does not mean the Commission cannot take action that \nwould indirectly impact retail rates or State regulatory practices.  Such is an inevitability in an \nindustry subject to multiple jurisdictions.  However, there are limits on the Commission’s ability \nto impact State practices. \nThe U.S. Supreme Court has clarified the “anti-commandeering doctrine” over years of \nprecedent.  Most pertinent here, in New York v. United States,48 the Court held that “Congress may \nnot commandeer the States’ legislative processes by directly compelling them to enact and enforce \na federal regulatory program . . . .”49  In that case, Congress passed a law requiring States to either \nestablish nuclear waste disposal sites or, if a State chose not to establish such waste sites, the State \nwould be required to take title to the waste and be liable for any damage to the generator or owner \nas a result of the State’s failure to take prompt possession.  The option to establish waste sites was \nencouraged through monetary incentives.  The Court held that this choice “would effectively \n‘commandeer’ States into the service of federal regulatory purposes” and in reality “the States’ \n‘choice’ is no choice at all.”50 \nThe IRAS Proposal similarly leaves States with no “choice.”  PJM claims that its proposal \ndoes not infringe on States’ exclusive jurisdiction because the decision “rests with the [S]tates to \nensure that the appropriate retail customers, i.e., New Large Loads, including data centers—and \nnot residential customers or small industrial customers—are reduced when system conditions call \n \n47  U.S. Const., 10th Amen. \n48  505 U.S. 144 (1992). \n49  Id. at 145. \n50  Id. at 146 (internal citations omitted)."},{"page":14,"startToken":4157,"endToken":4451,"text":"14 \n \nfor PJM to require load reductions according to IRAS.”51  However, PJM also explains that the \nentities directing load reductions “will be guided by the Large Load Registry.”52  In other words, \nPJM will provide the incentive and tools to curtail a specific class of customers, but argues that its \nhands are clean because it does not make the ultimate decision.  The ultimate decision is left to \nStates, LSEs, and Electric Distributors or, if these entities do not act accordingly, residential \ncustomers and other small industrial load will bear additional costs in a manner inconsistent with \ncost causation principles.  This is not a “choice” at all.  Rather, PJM has commandeered State \nregulatory constructs and entities to implement its IRAS Proposal.  Such a result cannot stand \nunder the Constitution and well-established precedent. \nPJM relies heavily on the Ratepayer Protection Pledge53 and the Statement of Principles \nRegarding PJM, which was signed by 13 governors of the PJM States, to justify the IRAS \nProposal.54  Notwithstanding PJM’s reliance on these sources, they do not supersede the \nConstitution.  Even if the governors of each State publicly supported the IRAS Proposal, the IRAS \nProposal would still run afoul of the anti-commandeering doctrine.  The Court in New York v. \nUnited States explained there that New York officials’ support of the legislation was irrelevant \nbecause “[t]he Constitution does not protect the sovereignty of States for the benefit of States or \nstate governments . . . [t]o the contrary, the Constitute divides authority between federal and state \n \n51  IRAS Proposal at 90-91. \n52  Id. at 92. \n53  See, e.g., id. at 4 (citing Ratepayer Protection Pledge, The White House (Mar. 4, 2026), \nhttps://www.whitehouse.gov/releases/2026/03/ \nratepayer-protection-pledge/ \n[https://perma.cc/N8PH-K82T] \n(“Ratepayer Protection Pledge”)). \n54  Id. at 6."},{"page":15,"startToken":4451,"endToken":4725,"text":"15 \n \ngovernments for the protection of individuals.”55  Thus, the Court held, “departure from the \nconstitutional plan cannot be ratified by the ‘consent’ of state officials.”56  So too here, the \nRatepayer Protection Pledge and Statement of Principles, while informative, cannot usurp the \nprinciples of federalism.  The IRAS Proposal rests on a quasi-federal governmental entity \ncommandeering the role of States by directing curtailment of a class of end-use customers.  PJM \nwill dispute this claim based on the “choice” presented to States, LSEs, and Electric Distributors, \nbut the choice is illusory at best.   \nPJM’s argument cannot find refuge under EPSA either.57  The Court in that case held that \nthe Commission’s regulation of demand response as permissible because it only addressed \n“transactions occurring on the wholesale market” and was intended to “enhance the wholesale, not \nretail, electricity market.”58  The IRAS Proposal is not so limited here.  The IRAS Proposal requires \nElectric Distributors to coordinate with PJM on developing and maintaining the Large Load \nRegistry, including by providing applicable state retail tariffs or contractual obligations.59  PJM \neven acknowledges that the implementation of the compensation scheme under IRAS “relies on \napplication of state retail law.”60 Any one of these issues is fatal to the legality of the IRAS \nProposal and, taken in the aggregate, the IRAS Proposal is certainly an overstep and encroachment \n \n55  New York v U.S., 505 U.S. at 181. \n56  Id. at 182.  \n57  See IRAS Proposal at 91 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 266 (2016) (“EPSA”). \n58  EPSA, 577 U.S. 282, 287. \n59  IRAS Proposal at 26. \n60  Id. at 106."},{"page":16,"startToken":4725,"endToken":5017,"text":"16 \n \non States’ exclusive jurisdiction.  As a result, the Commission must reject the IRAS Proposal as \nunjust and unreasonable. \nB. \nEven if the IRAS Proposal stood on solid legal ground—which it does not—\nthe proposal is unjust and unreasonable because it will ultimately result in \nincreased costs and could lead to further unduly discriminatory behavior. \nIt is a well-accepted economic principle that competitive markets result in fair prices for \ngoods, incentivize innovation, and encourage overall market efficiency, as further described in the \nattached Affidavit of Zachary Ming.61  Such markets, however, are difficult to develop organically \nin industries with high cost of entry.  Governmental or quasi-governmental organizations may \ndesign and oversee regulated markets under operational parameters that the regulators believe \nwould simulate the results that a competitive market would produce.  PJM’s capacity market is a \nprime example of such a simulated market.  The simulated market results will inevitably start to \ndiverge from true competitive market outcomes as more artificial interference is introduced to the \nmarket design.  The IRAS Proposal and its ultimate impact on PJM’s capacity market is no \nexception.  The IRAS Proposal will result in reduced competition, increased pricing, and new entry \nof uneconomic resources.62   \n1. \nThe IRAS Proposal will reduce competition in a simulated market that is \ndesigned to replicate competition. \nPJM proposes to exclude New Large Loads “from the VRR Curve starting with the \n2029/2030 Delivery Year, regardless of whether PJM is experiencing a shortfall that triggers IRAS \nin the relevant Delivery Year,” unless the New Large Load has entered into a bring your own new \ncapacity (“BYONC”) arrangement.63  What this means practically is that there will be separate \n \n61  See Ming Testimony at 7. \n62  See id. at 26. \n63  IRAS Proposal at 110."},{"page":17,"startToken":5017,"endToken":5324,"text":"17 \n \nmarkets for indistinguishable capacity.64  Existing resources will be subject to the artificially \nlimited RPM market and new capacity will naturally seek more valuable bilateral contracts with \nNew Large Load in the bilateral (out-of-) market.  This prevents two identical resources from \ncompeting head-to-head. \nThe IRAS Proposal involves removing New Large Load demand from the existing RPM \nmarket in an attempt to lower base residual auction (“BRA”) and incremental auction clearing \nprices in the near-term.  As the Supreme Court has recognized, lower clearing prices discourage \nnew investment and encourage retirement of existing generators.65  PJM is aware of this \nundesirable effect of its proposal.  In fact, with respect to the IRAS Proposal’s predecessor, \n“connect and manage,” PJM explained that it would not remove connect and manage load from \nthe RPM market because “including connection and manage [load] in the RPM Auction continues \nto provide price signals for new investment . . . .”66  Despite this logical conclusion reached by \nPJM only three months prior to filing the IRAS Proposal, PJM has reversed course and will now \nallow this exact scenario to play out. \nUnder this predictable scenario, existing resources will receive a clearing price in the BRA \nand incremental auctions that may fail to equal net CONE, resulting in the existing resources no \nlonger being economic.67  In the other artificial and inflated New Large Load market, the contract \nprices available to new resources will be greater than the RPM clearing prices.  New resources will \n \n64  See Ming Testimony at 16 (explaining the market available to New Large Load and the market available to “all \nother loads”).   \n65  Hughes, 136 S. Ct. at 1293. \n66  Ming Testimony at 25 (citing Connect and Manage PJM Package, PJM (May 27, 2026), available at \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-item-04---\nconnect-and-manage-pjm-package---pjm-presentation.pdf)). \n67  Id. at 18, 20-21."},{"page":18,"startToken":5324,"endToken":5660,"text":"18 \n \nlogically choose to enter more profitable, bilateral New Large Load market rather than compete in \nthe BRA.68  This will create real challenges for existing generation.   \nIt may very well be the case that it is less expensive for an existing generator to invest in \nretrofits or repowerings of active but aging resources than it is for a new generator to come online; \nhowever, the artificially suppressed BRA clearing price will make such investments in existing \ngeneration uneconomic, while new generation can recoup its investment through bilateral \ncontracting.69  It will not take long for residential ratepayers to feel the results. \n2. \nThe IRAS Proposal will ultimately result in increased prices. \nEarly retirement of existing resources, a market clearing price that begins to clear at less \nthan net CONE,70 and the incentivization for new capacity to bilaterally contract with New Large \nLoad will diminish the reliability of PJM’s system.  PJM will then have a limited set of levers to \npull.  It may run another backstop procurement auction (again resulting in the allocation of \nreliability backstop procurement costs across LSE zone/areas), enter into off-market reliability \nmust run contracts with generators to stave off retirement, or increase the demand curve to restore \na long-run average price of net CONE.71  Each of the levers will increase prices.  Therefore, any \ntheoretical consumer savings from the initial price suppression in the BRA resulting from the IRAS \nProposal are temporary vapors because the IRAS Proposal will end up costing consumers more in \nthe long run. \n \n68  Although the IRAS Proposal requires the New Large Load and new capacity to enter the RPM once there is a \nbinding contract between the two, this will not rectify the damage to the RPM market. The entry of load and \ncorresponding capacity will be a wash, i.e., the benefit of the new supply will be negated by the impact of the \nincreased demand from New Large Load. \n69  Ming Testimony at 28. \n70  Id. at at 27-28. \n71  Id. at 22."},{"page":19,"startToken":5660,"endToken":5856,"text":"19 \n \n3. \nThe IRAS Proposal could result in the uneconomic entry of new \ngeneration. \nAs explained above, the new bilateral market for New Large Load will result in increased \nprices for such capacity.  There are several plausible scenarios under which IRAS could incentivize \nNew Large Load to procure such BYONC, even though it is unnecessary and inefficient from a \nPJM system standpoint.  For example, PJM could implement IRAS because of a near-term capacity \nshortfall.  New Large Load would procure BYONC resources to avoid being curtailed.  The \ncapacity shortfall may be alleviated in a year or two, but the BYONC resource is contracted at a \nhigher rate for 20 years.  In this scenario it would have been more economically efficient to \nincrease the capacity shortfall for a limited year or two rather than increase the capacity surplus \nfor a larger number of years.72   \nSimply put, PJM has not satisfied its burden to demonstrate that the IRAS Proposal is not \nunjust, unreasonable, or unduly discriminatory. The Ming Testimony and its application of the \nIRAS Proposal to realistic and predictable hypotheticals actually demonstrate the opposite.  The \nCommission must reject the IRAS Proposal accordingly.   \n \n \n \n72  See id. at 26."},{"page":20,"startToken":5856,"endToken":6097,"text":"20 \n \nIII. \nCONCLUSION  \nPJM needs to go back to the drawing board to develop significant and more holistic \ncapacity market reforms that encourage accurate market pricing signals, can be implemented on a \nnon-discriminatory basis, and provide PJM customers with a safe and reliable future.  That may \ntake the form of longer forward-term BRAs, e.g., 5 years in advance of the Delivery Year rather \nthan 3 years, to allow new capacity to respond to accurate market pricing signals, and additional \nreview of the VRR Curve and must-offer rules.  Talen does not imply that this is an easy task; \nhowever, this is the burden that the operator of the largest capacity market in the country carries.  \nTalen looks forward to working with PJM and FERC on such reforms.   \nThe IRAS Proposal is not the reform PJM needs.  Simply put, the IRAS filing is unjust and \nunreasonable for the reasons discussed herein.  Talen respectfully submits this Protest accordingly \nand requests that the Commission reject the IRAS Proposal in its entirety.  \n \n \n \n \n \n \n       Respectfully Submitted, \n /s/ Jennifer Mansh \n \n \nJennifer Mansh \nSenior Vice President, Regulatory \nCounsel \nTalen Energy Corp. \n600 Hamilton Street, Suite 600 \nAllentown, PA 18101 \nJennifer.Mansh@talenenergy.com \n /s/ John Decker \n \nJohn Decker \nAndrew DeVore \nCassidy Hall \nKirkland & Ellis LLP \n1301 Pennsylvania Avenue, N.W. \nWashington, D.C. 20004 \n(202) 389-3470 \n(202) 389-3117 \nJohn.decker@kirkland.com  \nandrew.devore@kirkland.com \ncassidy.hall@kirkland.com \n \n \n \nCounsel for Talen Energy Corporation \n \n \nDated: September 3, 2026"},{"page":21,"startToken":6097,"endToken":6108,"text":"EXHIBIT A \nTESTIMONY OF ZACHARY MING \nENERGY AND ENVIRONMENTAL ECONOMICS, INC."},{"page":22,"startToken":6108,"endToken":6145,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \nTestimony of Zachary Ming \n Partner \nEnergy and Environmental Economics, Inc. \nOn behalf of \nTalen Energy Corporation \nSeptember 3, 2026"},{"page":23,"startToken":6145,"endToken":6169,"text":"2 \nTable of Contents \n1 \nIntroduction .............................................................................................. 3 \n2 \nBackground and Overview of IRAS ........................................................ 6 \n3 \nEconomic Impact of IRAS ..................................................................... 16 \n4 \nRecommendations & Summary .............................................................. 28"},{"page":24,"startToken":6169,"endToken":6364,"text":"3 \nTalen Energy Corporation \n1 \n \n2 \nPJM Interim Resource Adequacy Service \n3 \n \n4 \n \n5 \nTestimony of Zachary Ming, Partner, Energy and Environmental Economics, Inc. \n6 \n1 Introduction \n7 \nQ1. \nPLEASE STATE YOUR NAME, OCCUPATION, AND BUSINESS \n8 \nADDRESS. \n9 \nA1. \nMy name is Zachary Ming. My current position is Partner at Energy and \n10 \nEnvironmental Economics, Inc. (“E3”). My business address is 44 Montgomery \n11 \nStreet Suite 1250, San Francisco, California 94104. \n12 \nQ2. \nPLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY. \n13 \nA2. \nI am filing this testimony as an independent expert, and it represents my own \n14 \npositions and perspectives. This testimony was funded by Talen Energy \n15 \nCorporation (“Talen”). \n16 \nQ3. \nPLEASE DESCRIBE YOUR PROFESSIONAL BACKGROUND AND \n17 \nEXPERIENCE. \n18 \nA3. \nI received a B.S. in Civil and Environmental Engineering (Atmosphere and Energy \n19 \nprogram) with a Minor in Economics, and an M.S. in Management Science and \n20 \nEngineering (Energy track), both from Stanford University. For thirteen years I \n21 \nhave held various roles at E3, an energy consulting firm specializing in the \n22 \neconomics of the electricity system where I am currently a Partner. In addition to \n23"},{"page":25,"startToken":6364,"endToken":6655,"text":"4 \nfull-time consulting work at E3, I teach a graduate-level course at Stanford \n1 \nUniversity titled Electricity Economics. \n2 \nQ4. \nPLEASE DESCRIBE YOUR QUALIFICATIONS AS IT RELATES TO THE \n3 \nTOPICS OF RELIABILITY, CAPACITY MARKET DESIGN, AND \n4 \nGENERATION INVESTMENT ECONOMICS. \n5 \nA4. \nIn my role as Partner at E3, I oversee projects across a number of areas including \n6 \nreliability, capacity market design, and generation investment economics. I have \n7 \nauthored several reports related to reliability that evaluate the most cost-effective \n8 \npathway to meeting long-term system needs, including Resource Adequacy for the \n9 \nEnergy Transition: A Critical Periods Reliability Framework and its Applications \n10 \nin Planning and Markets,1 Assessment of Market Reform Options to Enhance \n11 \nReliability of the ERCOT System,2 and Long-Run Resource Adequacy under Deep \n12 \nDecarbonization Pathways for California.3  I have worked on resource adequacy \n13 \nand capacity market design topics in PJM, MISO, ERCOT, CAISO, NYISO, and \n14 \nISO-NE. I have worked with generators, developers, investors, and utilities in \n15 \nassessing the economics of new generation opportunities. Most broadly, I lead E3 \n16 \nteams that help develop system-wide solutions that are both economic and reliable. \n17 \n \n1 Energy & Environmental Economics, Inc., Critical Periods Reliability Framework, E3 (Aug. 2025), \nhttps://www.ethree.com/wp-content/uploads/2025/08/E3_Critical-Periods-Reliability-Framework_White-\nPaper.pdf.  \n2 Energy & Environmental Economics, Inc., Assessment of Market Reform Options to Enhance Reliability \nof the ERCOT System (Nov. 10, 2022), https://www.ethree.com/wp-content/uploads/2023/05/E3-\nPUCT_Assessment-of-Market-Reform-Options-to-Enhance-Reliability-of-the-ERCOT-System_11.10.22-\nSent.pdf. \n3 Energy & Environmental Economics, Inc., Long Run Resource Adequacy under Deep Decarbonization \nPathways for California (June 2019), https://www.ethree.com/wp-\ncontent/uploads/2019/06/E3_Long_Run_Resource_Adequacy_CA_Deep-Decarbonization_Final.pdf."},{"page":26,"startToken":6655,"endToken":6939,"text":"5 \nQ5. \nHAVE YOU PREVIOUSLY TESTIFIED BEFORE THE FEDERAL \n1 \nENERGY REGULATORY COMMISSION (“FERC”)? \n2 \nA5. \nYes, I have testified multiple times before FERC. My previous testimony has \n3 \ncovered various topics related to rate design and wholesale markets in PJM, \n4 \nincluding the capacity market price cap,4 the participation of reliability must run \n5 \n(“RMR”) units in the capacity market,5 PJM’s filing to use marginal effective load \n6 \ncarrying capability (“ELCC”) as the basis for resource accreditation in the capacity \n7 \nmarket,6 and co-location rate design.7 I have also testified before FERC on behalf \n8 \nof MISO in their proposal to implement the direct loss of load (“DLOL”) \n9 \nmethodology for resource accreditation8 and on the topic of ISO-NE’s “Pay-for-\n10 \nPerformance” capacity market construct. 9 Additionally, I have testified before \n11 \nstate, provincial, and territorial public utility commissions in Oregon, Texas, South \n12 \nCarolina, Colorado, New Brunswick, and Puerto Rico on topics relating to \n13 \nreliability, resource adequacy, market design, and rate design. \n14 \nQ6. \nWHAT IS THE PURPOSE OF THIS TESTIMONY? \n15 \nA6. \nThe purpose of my testimony is to illustrate how the Interim Resource Adequacy \n16 \nService (“IRAS”), despite being designed as a means to “protect residential \n17 \ncustomers from capacity price increases” actually does the opposite. 10  I \n18 \n \n4 Docket EL25-46-000. \n5 Docket EL24-148. \n6 Docket ER24-99-000. \n7 Dockets EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000. \n8 Docket ER24-1638. \n9 Docket EL25-106-000. \n10 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large \nLoad Registry, at 5, FERC Docket No. ER26-3515-000, August 13, 2026, accession no. 20260813-5118, \nhttps://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20260813-5118&optimized=false. \n[hereinafter PJM Filing]"},{"page":27,"startToken":6939,"endToken":7162,"text":"6 \ndemonstrate how IRAS creates an expectation of reduced future capacity market \n1 \nprices which reduces new investment and retention of existing resources. The \n2 \nparadoxical impact of this is higher prices and lower reliability. I conclude with the \n3 \nrecommendation that FERC should reject PJM’s IRAS proposal. \n4 \nQ7. \nPLEASE PROVIDE AN OUTLINE OF YOUR TESTIMONY. \n5 \nA7. \nMy testimony is organized as follows: \n6 \n• In Section 2, I provide background on the PJM capacity market, including how \n7 \nPJM uses price signals to incent the entry of new resources and retention of \n8 \nexisting resources. I also provide an overview of salient features of PJM’s \n9 \nproposed IRAS; \n10 \n• In Section 3, I illustrate the economic impacts of IRAS, including how it would \n11 \n1) reduce new investment and retention of existing resources and 2) hinder \n12 \ncompetition between resources serving new large loads and existing loads. I \n13 \ndemonstrate how both factors increase societal costs, increase consumer prices, \n14 \nand decrease reliability; and \n15 \n• In Section 4, I summarize my arguments and recommendations. \n16 \n2 Background and Overview of IRAS \n17 \nQ8. \nPLEASE PROVIDE AN OVERVIEW OF HOW PJM ENSURES \n18 \nRESOURCE ADEQUACY. \n19 \nA8. \nPJM’s principal means of ensuring resource adequacy is the Reliability Pricing \n20 \nModel, more colloquially known as the PJM capacity market. The capacity market \n21"},{"page":28,"startToken":7162,"endToken":7422,"text":"7 \nprovides price signals to secure sufficient capacity to satisfy PJM’s reliability \n1 \nstandard.11 \n2 \nQ9. \nHOW DO PRICE SIGNALS SECURE SUFFICIENT CAPACITY? \n3 \nA9. \nThe capacity market is designed to provide the additional revenues that generation \n4 \nresources require to recover their full costs beyond what they earn in the energy \n5 \nand ancillary service markets. Without this additional revenue, investors in \n6 \ngeneration would not recover their full costs and would reduce investment in both \n7 \nnew generation and in retention of existing generation. Specifically, the required \n8 \nadditional revenue is the net Cost of New Entry (“net CONE”). \n9 \nThe capacity market is designed to run once per year, and prices fluctuate \n10 \non a year-to-year basis based on supply and demand. A capacity market designed \n11 \nto produce an average price of net CONE in the long-run provides sufficient \n12 \nrevenues for investors to recover their full costs and sends the signal that they \n13 \nshould invest. \n14 \nQ10. PLEASE DESCRIBE THE MECHANISM USED TO DETERMINE \n15 \nCAPACITY MARKET PRICES IN ANY GIVEN YEAR. \n16 \nA10. PJM determines capacity market prices each year based on the intersection between \n17 \nan administratively-determined demand curve and a supply curve formed from \n18 \nsupplier bids. The demand curve is also known as the Variable Resource \n19 \nRequirement (“VRR”) curve. \n20 \n \n11 In PJM, the specified resource adequacy target is 0.1 days/year loss of load expectation (“LOLE”). This \ntarget aims to ensure that loss-of-load events should occur no more frequently than one day in every ten \nyears."},{"page":29,"startToken":7422,"endToken":7683,"text":"8 \nThe VRR curve is defined by three points that PJM calls A, B, and C, which \n1 \nare derived for each auction using multiple key inputs: \n2 \n• The estimated gross Cost of New Entry (“CONE”) for a selected \n3 \nreference technology; \n4 \n• A forecast of the reference technology’s net energy and ancillary service \n5 \nrevenues expected from the PJM market; and \n6 \n• PJM’s reliability requirement expressed in unforced capacity (“UCAP”) \n7 \nMW. \n8 \nGross CONE reflects the annualized capacity and fixed operating cost of \n9 \nthe reference technology and is the total amount of revenue that a new resource \n10 \nwould need to recover to justify entering the market. Estimated net energy and \n11 \nancillary service revenues are subtracted from gross CONE to calculate net CONE, \n12 \nwhich is the amount of revenue that a new resource would need to recover through \n13 \nthe capacity market after accounting for net revenues earned in PJM’s other \n14 \nmarkets. The reliability requirement is the amount of UCAP MW capacity needed \n15 \nto achieve the reliability standard. \n16 \nPoints A, B, and C are calculated for each auction using these core \n17 \nparameters. For the latest auction for the 2028/2029 Delivery Year (held in July \n18 \n2026), these points were calculated using the following formulas: \n19 \nA. For a UCAP MW quantity equal to 99% of the reliability requirement, the \n20 \nprice is equal to the greater of (i) 1.15 times gross CONE minus 0.75 times \n21 \nenergy and ancillary service revenues and (ii) 0.20 times gross CONE. \n22"},{"page":30,"startToken":7683,"endToken":7877,"text":"9 \nB. For a UCAP MW quantity equal to 101.5% of the reliability requirement, \n1 \nthe price is equal to half of the price value used for point A. \n2 \nC. For a UCAP MW quantity equal to 106% of the reliability requirement, the \n3 \nprice is equal to zero.12 \n4 \nIn the case of the 2028/2029 Delivery Year auction, there was an additional \n5 \nfinal step where both a price cap of $325/MW-day and price floor of $175/MW-\n6 \nday were applied to the curve.13 This demand curve is illustrated in the figure \n7 \nbelow. \n8 \nFigure 1: VRR curve used by PJM in the BRA (Not to Scale) \n9 \n \n10 \nQ11. PLEASE DESCRIBE THE INTENDED GOAL IN STRUCTURING THE \n11 \nDEMAND CURVE. \n12 \nA11. The demand curve is designed to accomplish two goals. First, it is structured to \n13 \ndeliver dynamic price signals such that prices rise when the system needs additional \n14 \n \n12 PJM OATT § 5.10.a.ii. \n13 PJM Interconnection L.L.C, 2028/2029 BRA Supply Curves(July 17, 2026), https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-supply-curves.pdf."},{"page":31,"startToken":7877,"endToken":8118,"text":"10 \ncapacity and vice versa. Second, it is designed to deliver an average long-run price \n1 \nof net CONE (i.e., the “reference price”) across many years. An investor must \n2 \nexpect that the capacity market will deliver this long-run average net CONE price \n3 \nto invest in new capacity. PJM designs the demand curve such that some years will \n4 \nyield prices higher than net CONE, some years would yield lower prices, but prices \n5 \nwould average to net CONE across all years. This is illustrated in the figure below. \n6 \nFigure 2: Distribution of Expected Capacity Market Prices from VRR Design Study14 \n7 \n \n8 \nThe implementation of both a price cap and a price floor has the theoretical \n9 \npotential to narrow the range of pricing outcomes while preserving the long-run \n10 \naverage price signal of net CONE. However, because the price cap was \n11 \nimplemented during the current conditions of capacity shortage while the price \n12 \nfloor was not implemented during the preceding conditions of capacity excess, it is \n13 \n \n14 Graph showing simulated results cleared price for 2026/2027 VRR curve. Dark grey bar represents \nmedian results. Reference price is equal to the Administrative Reference Price ($350/MW-day UCAP), \nwhich is a Net CONE Proxy. PJM Interconnection L.L.C, Sixth Review of PJM’s Variable Resource \nRequirement Curve 52 ( April 9, 2025), at , https://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/mic/2025/20250411-special/item-1-03-sixth-review-of-pjm-vrr-curve.pdf"},{"page":32,"startToken":8118,"endToken":8267,"text":"11 \nlikely that this market intervention is suppressing long-run average prices below \n1 \nnet CONE. \n2 \nQ12. WHAT RECENT TRENDS HAS PJM OBSERVED IN THE CAPACITY \n3 \nMARKET? \n4 \nA12. In recent years, PJM has observed a level of load growth that has not been present \n5 \nsince at least the conception of the Reliability Pricing Model capacity market in \n6 \n2007. This load growth is primarily driven by an increase in new large loads, \n7 \nnamely data centers. The impact of this load growth has been an increase in the \n8 \ncapacity price. Both of these trends are illustrated in the figure below. \n9 \n \nIn addition, recent capacity market auctions have cleared short of the \n10 \nrequired quantity of capacity to meet PJM’s reliability requirement. For example, \n11 \nthe auction for the 2027/2028 Delivery Year (held in July 2026) cleared short by \n12 \n6,831 MW. \n13"},{"page":33,"startToken":8267,"endToken":8372,"text":"12 \nFigure 3: Illustration of Recent Trends in PJM Capacity Market15 \n1 \n  \n2 \nQ13. WHAT HAS BEEN THE RESPONSE TO THESE TRENDS? \n3 \nA13. These trends have prompted concerns that the growth driven by new large loads is \n4 \nunfairly increasing electricity costs for residential consumers. This led to a \n5 \n \n15 PJM Interconnection, L.L.C.,  PJM Load Forecast Report 9 (July 14, 2026), at 9, https://www.pjm.com/-\n/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf. \nPJM Interconnection, L.L.C., 2028/2029 Base Residual Auction Results Report 6 (2025), \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-\nresults-report.pdf."},{"page":34,"startToken":8372,"endToken":8622,"text":"13 \nStatement of Principles Regarding PJM, a joint policy directive signed by all PJM \n1 \nstate governors along with Secretary of Interior and Secretary of Energy urging \n2 \nPJM to “protect residential customers from capacity price increases.”16 In response, \n3 \nthe PJM Board initiated a Critical Issue Fast Path process to engage stakeholders in \n4 \nsolutions to this challenge.17 \n5 \nQ14. WHAT PROPOSALS HAS PJM RECENTLY FILED REGARDING THESE \n6 \nCAPACITY MARKET ISSUES? \n7 \nA14. PJM has recently filed two proposed changes regarding the capacity market to \n8 \nFERC for approval. \n9 \n \nFirst, PJM has proposed to hold a one-time Reliability Backstop \n10 \nProcurement (“RBP”) for new capacity in response to capacity shortfall observed \n11 \nin the most recent auction. \n12 \n \nSecond, PJM has proposed to implement a new Interim Resource Adequacy \n13 \nService (“IRAS”).18  Under this service, new large loads must either (a) bring new \n14 \ngeneration supply sufficient to serve their peak demand, or (b) agree to receive \n15 \ninterruptible service. Loads can satisfy the requirement to bring new generation \n16 \neither by entering into a bilateral arrangement with a new resource, referred to as \n17 \nBring Your Own New Capacity (“BYONC”), or by being allocated a share of \n18 \nPJM’s RBP. \n19 \n \n16 U.S. Dep't of Energy, Statement of Principles Regarding PJM (Jan. 15, 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm. \n17 PJM, Critical Issue Fast Path – Reliability Backstop Procurement / Connect & Manage, \nhttps://www.pjm.com/committees-and-groups/cifp-rbp. \n18 PJM Filing, at 2."},{"page":35,"startToken":8622,"endToken":8894,"text":"14 \nQ15. PLEASE DESCRIBE THE KEY FEATURES OF PJM’S IRAS PROPOSAL \n1 \nIN MORE DETAIL. \n2 \nA15. Under the IRAS proposal, PJM would create a permanent requirement for new large \n3 \nloads to bring new capacity into the market to cover their peak demand if the PJM \n4 \nsystem does not have sufficient capacity to meet the reliability requirement.19 A \n5 \nnew large load is defined as a load that is 50 MW or greater that goes into service \n6 \nafter June 1, 2027.20  Failing to bring new capacity into the market would result in \n7 \nthe new large loads being interrupted before PJM takes other existing emergency \n8 \nactions, such as pre-emergency load management reductions. \n9 \nNew large loads can satisfy the requirement to bring new capacity into the \n10 \nmarket in two distinct ways. First, the load can be allocated a portion of the cost of \n11 \nPJM’s RBP procurement.21  However, because the RBP is proposed as a one-time \n12 \nprocurement, this is likely to only be available for new large loads in the near-term. \n13 \nSecond, new large loads can enter into a BYONC bilateral arrangement with a new \n14 \ngenerating resource. 22  Information about both RBP allocations and BYONC \n15 \narrangements for each large load would be captured as part of a new “Large Load \n16 \nRegistry” that will be maintained by PJM.23 \n17 \nQ16. HOW ARE THE PROPOSED IRAS REQUIREMENTS APPLICABLE TO \n18 \nNEW LARGE LOADS DIFFERENT FROM THE REQUIREMENTS THAT \n19 \n \n19  Id. at 27. \n20  Id. at 44–45. \n21 Id. at 320. \n22  Id. at 14. \n23 Id. at 43."},{"page":36,"startToken":8894,"endToken":9153,"text":"15 \nAPPLY TO ALL OTHER LOADS ON THE SYSTEM (I.E., EXISTING \n1 \nLOADS AND NON-LARGE NEW LOADS)? \n2 \nA16. The key difference is that under PJM’s proposal, new large loads can only procure \n3 \ncapacity through the BYONC or RBP construct, while all other loads (i.e., not new \n4 \nlarge loads) would retain the option to procure their capacity either through a \n5 \nbilateral BYONC construct or through the capacity market. As is generally true, \n6 \noptionality has value (or conversely, reduced optionality is costly). Depriving new \n7 \nlarge loads the option to procure capacity through the capacity market is \n8 \ndiscriminatory and costly, as these loads may perceive that procuring capacity \n9 \nthrough the capacity market will be lower cost than a BYONC construct that likely \n10 \nrequires upfront capital or entering into a long-term contract. \n11 \nQ17. HOW IS DEMAND FROM NEW LARGE LOADS INCORPORATED INTO \n12 \nTHE CAPACITY MARKET UNDER PJM’S IRAS PROPOSAL? \n13 \nA17. There are two ways in which demand from new large loads will (or will not be) \n14 \nincorporated into the capacity market under PJM’s IRAS proposal. If the new large \n15 \nload brings online a new BYONC resource or is allocated a portion of RBP, the \n16 \ndemand from the new large load and the supply from the new capacity will both be \n17 \nincorporated into the capacity market. If the new large load does not BYONC and \n18 \nis instead subject to IRAS, PJM will not include its demand in the capacity market.24 \n19 \n \n24 Id. 115."},{"page":37,"startToken":9153,"endToken":9406,"text":"16 \n3 Economic Impact of IRAS \n1 \nQ18. WHAT IS THE OVERALL IMPACT OF PJM’S IRAS PROPOSAL? \n2 \nA18. The overall impact of PJM’s IRAS proposal is that it would increase societal costs, \n3 \nincrease consumer prices, and reduce reliability. It does this through two primary \n4 \nmechanisms: \n5 \n• Reduction in new investment and retention of existing resources; and \n6 \n• Hindrance of competition between resources serving new large loads and \n7 \nexisting loads. \n8 \nI address each of these in turn, including a step-by-step overview of the chain of \n9 \nevents that cause costs to rise and reliability to degrade. \n10 \n3.1 Reduction in New Investment and Retention of Existing Resources \n11 \nQ19. WHAT WOULD BE THE IMMEDIATE IMPACT ON THE CAPACITY \n12 \nMARKET OUTLOOK DUE TO IMPLEMENTING IRAS? \n13 \nA19. The immediate impact of implementing IRAS would be an expectation of reduced \n14 \nfuture capacity market prices. This is the case for two reasons. \n15 \nFirst, IRAS creates an expectation of reduced future market prices because \n16 \nit asymmetrically prevents price increases from growth in new large loads without \n17 \nprotecting prices from downside risk. IRAS structurally prevents new large loads \n18 \nfrom increasing prices because it either requires new large loads to BYONC or be \n19 \ninterruptible. In either case, new large loads do not increase capacity market prices \n20 \nbecause they either 1) bring new supply that exactly offsets their new demand or 2) \n21 \ntheir demand is excluded from the capacity market. On the other hand, IRAS \n22"},{"page":38,"startToken":9406,"endToken":9630,"text":"17 \nintroduces future downside price risk. As an example, imagine a new large load \n1 \nthat, after investing in a new generation resource through a BYONC arrangement, \n2 \nreduces its demand or leaves the market entirely. The reduction in demand could \n3 \nbe caused by any number of factors, including global market dynamics for compute \n4 \nor changes in policy and regulation. If demand is reduced, the BYONC resource \n5 \nwould still exist and contribute to excess capacity in the market, which would \n6 \ndecrease prices. \n7 \nSecond, IRAS creates an expectation of reduced future market prices \n8 \nbecause it can incentivize uneconomic entry of new generation resources. Imagine \n9 \na situation where a new large load that requires firm service is forced to make a \n10 \nlong-term investment through BYONC arrangement because the market has a \n11 \nshort-term capacity deficiency for one year even though the market is projected to \n12 \nhave excess capacity in the long-term. New capacity in this case may be \n13 \nuneconomic if it is less costly to incur the costs of a larger short-term shortfall than \n14 \nthe costs of additional unneeded capacity for many years. This uneconomic excess \n15 \ncapacity will put downward pressure on prices. \n16 \nThis phenomenon of expected reduced future capacity market prices due to \n17 \nIRAS is illustrated in the figure below. \n18"},{"page":39,"startToken":9630,"endToken":9761,"text":"18 \nFigure 4: Impact of IRAS on Future Price Expectations in PJM Capacity Market \n1 \n \n \n2 \nQ20. ISN’T THE EXPECTATION OF REDUCED FUTURE MARKET PRICES \n3 \nA BENEFIT TO CONSUMERS? \n4 \nA20. If only it were that easy. However, consumers ultimately do not benefit from these \n5 \nreduced market prices because of the knock-on effects that come from the market \n6 \nreacting and responding to this decrease in future price expectations. \n7 \nQ21. HOW WILL THE MARKET REACT AND RESPOND TO THE \n8 \nEXPECTATION OF REDUCED FUTURE MARKET PRICES? \n9 \nA21. Very simply, the market will react and respond to expected reduced future market \n10 \nprices with reduced new entry and increased retirements. This is because \n11 \ninvestment decisions are based on expectations of pricing over the life of the \n12"},{"page":40,"startToken":9761,"endToken":9919,"text":"19 \ninvestment. This reduced investment and increased retirement will paradoxically \n1 \ncause market prices to increase and reliability to decline in the near-term in an effort \n2 \nto re-equilibrate to the new normal of increased future downside risk. \n3 \nThe next step in this chain reaction is that PJM will observe the reduction \n4 \nin system reliability and be compelled to take steps to rectify this outcome. The tool \n5 \nthat PJM has to rectify this outcome is the structure of the capacity market demand \n6 \ncurve. PJM would necessarily need to increase the demand curve in order to induce \n7 \nadditional capacity into the market to achieve the reliability standard. The end result \n8 \nis that (as is the case with most market intervention) the “consumer savings” from \n9 \nprice suppression are illusory. This dynamic is illustrated in the figure below. \n10 \nFigure 5: Illustration of Price and Reliability Dynamics Due to Introduction of IRAS \n11 \n \n12"},{"page":41,"startToken":9919,"endToken":10197,"text":"20 \nQ22. HOW IN PRACTICE WOULD PJM INCREASE THE DEMAND CURVE? \n1 \nA22. The capacity market demand curve is an administratively-determined curve that \n2 \nPJM periodically reevaluates through a study and stakeholder review process to \n3 \nensure that it is delivering the appropriate balance of price and reliability.25 It is \n4 \nthrough this process that PJM would surface any deficiencies in the current curve \n5 \nand make adjustments. There are several ways the VRR curve can be increased, \n6 \nincluding increasing the maximum price of the curve, increasing the UCAP MW \n7 \nquantity for point B on the curve, elongating the tail of the curve by increasing the \n8 \nUCAP MW quantity for point C, or a combination of all of these adjustments. \n9 \nQ23. ARE THERE OTHER EXAMPLES WHERE EXPECTATIONS OF \n10 \nFUTURE EVENTS IMPACT CURRENT MARKET PRICES? \n11 \nA23. Yes, there are examples both inside and outside the electricity sector where \n12 \nexpectations of future events impact current market prices. For example, analysis \n13 \nprepared for PJM demonstrates that lower expected long-term capacity market \n14 \npricing requires much higher near-term pricing in order to support investment.26 \n15 \nOutside of electricity, the potential for future geopolitical instability can increase \n16 \noil prices through a “risk premium.” \n17 \n \n25 PJM OATT § 5.10.a.iii. \n26 Sixth Review of PJM’s Variable Resource Requirement Curve at 68, BRATTLE, (Apr. 9, 2025), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2025/20250411-special/item-\n1-03-sixth-review-of-pjm-vrr-curve.pdf (the “same [battery] resource will require a much higher price … in \nthe first three years … if future prices will return to the lower long-run price … over years 4-10 of the asset \nlife”)."},{"page":42,"startToken":10197,"endToken":10586,"text":"21 \nQ24. IS THE DYNAMIC OF REDUCED FUTURE CAPACITY MARKET \n1 \nPRICES \nMATERIAL \nENOUGH \nTO \nIMPACT \nNEAR-TERM \n2 \nINVESTMENT AND RETIREMENTS? \n3 \nA24. Yes, the magnitude of new large load growth forecasted to enter the PJM system \n4 \nmakes the downside price risk I describe above very material. PJM forecasts a \n5 \nreliability requirement of approximately 200 GW in 203527, a 55 GW28 increase \n6 \nfrom today.29 This projected growth is primarily driven by new large loads. If even \n7 \njust 10% of this increased demand (i.e., 5.5 GW) were to disappear after bringing \n8 \nonline new capacity, this could be material enough to decrease the market clearing \n9 \nprice by almost 50%.30 The magnitude of this impact demonstrates that this is a \n10 \nvery material potential future risk. \n11 \n \n27 This is found from taking projected peak load for 2035 and multiplying it by the Forecast Pool \nRequirement (FPR) from the 2028/2029 BRA:  216,872 × 0.92 = 198,872 MW. The forecasted peak load \ncan be found here: PJM Inside Lines, PJM’s Updated 20-Year Forecast Continues To See Significant \nLong-Term Load Growth, (January 14, 2026)_, https://insidelines.pjm.com/pjms-updated-20-year-forecast-\ncontinues-to-see-significant-long-term-load-growth/. \n28 This is found by taking the 2028/2029 Reliability Requirement adjusted for FRR and subtracting the \nforecasted 2035 Reliability Requirement adjusted for FRR: 198,872-145,149 = 53,723 MW. See infra note \n36 for 2028/2029 Reliability Requirement adjusted for FRR.. \n29 This is the 2028/2029 Reliability Requirement adjusted for FRR found from: PJM Interconnection, \nL.L.C., Planning Period Parameters for Base Residual Auction, (July 27, 2026) https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-planning-period-parameters-for-\nbase-residual-auction.xlsx. \n30 Example assumes: Gross CONE of 600 $/MW-day UCAP, E&AS Value of 300 $/MW-day UCAP, VRR \ncurve determined using same methodology as 2028/2029 BRA, and 2028/2029 Forecast Pool Requirement \n(FPR). Supply curve shape chosen to imitate curve from 2026/2027 BRA result found from: \nPJM Interconnection, L.L.C., 2026/2027 BRA Supply Curves, (August 1, 2025), https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/2026-2027/2026-2027-bra-supply-curves.pdf.  \nInspiration for Gross CONE and E&AS values from:  \nPJM Interconnection, L.L.C., Planning Period Parameters for Base Residual Auction, (July 27, 2026) \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-\nplanning-period-parameters-for-base-residual-auction.xlsx."},{"page":43,"startToken":10586,"endToken":10740,"text":"22 \nFigure 6: Example of How a Decrease in Load in the Market Causes a Material Price \n1 \nDecrease \n2 \n  \n3 \nQ25. ARE THERE ANY OTHER MECHANISMS THROUGH WHICH IRAS \n4 \nIMPACTS INVESTMENT AND RETENTION SIGNALS IN THE \n5 \nCAPACITY MARKET? \n6 \nA25. Yes. Even if we were to assume that all new large load is permanent and that no \n7 \nuneconomic entry of new generation resources occurs, the introduction of IRAS \n8 \nwould still chill new investment and retention of resources in the capacity market. \n9 \nThe underlying reason for this is that IRAS, just like the currently imposed price \n10 \ncap, fundamentally and artificially limits the auction clearing price. This deprives \n11 \nthe market of the ability to send a long-term average price equal to net CONE. \n12 \nInvestors made previous investments on the expectation that future capacity prices \n13 \nwould reflect actual market conditions, including increased demand for new large \n14"},{"page":44,"startToken":10740,"endToken":10996,"text":"23 \nloads. Depriving those investors of the ability to realize market-driven pricing sends \n1 \nthe signal that future high prices cannot be trusted. This fundamentally chills \n2 \ninvestment which, once again, paradoxically increases near-term pricing. \n3 \nQ26. HAS PJM SUFFICIENTLY EVALUATED THE IMPACT OF MAKING \n4 \nIRAS A PERMANENT FEATURE OF THE CAPACITY MARKET? \n5 \nA26. No. Separate from PJM’s current RBP and IRAS proposals to address the near-term \n6 \nreliability and price issues that I describe above, “the PJM Board has directed staff \n7 \nto undertake a holistic review of the capacity market design.”31 This holistic review \n8 \nwill evaluate long-term structural changes to the PJM market that will be in place \n9 \nfor many decades. Nonetheless, PJM’s proposal to make IRAS a permanent feature \n10 \nof the capacity market circumvents this process by implementing a long-term \n11 \nmarket design change that results in permanent price suppression in the capacity \n12 \nmarket that PJM has not sufficiently evaluated. \n13 \nQ27. HAS PJM ITSELF OPINED ON THE LONG-TERM SIGNALS SENT BY \n14 \nEXCLUDING DEMAND FROM NEW LARGE LOADS THAT DO NOT \n15 \nBYONC? \n16 \nA27. Yes. Before PJM’s current proposal to FERC that excludes demand from new large \n17 \nloads in the capacity market that do not BYONC, PJM had previously proposed the \n18 \nopposite. Specifically, PJM stated that “connect and manage load will not be \n19 \n \n31 PJM Interconnection, L.L.C., Powering Reliability Through Market Design, 3, (May 6, 2026) \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-\nreliability-through-market-design.pdf."},{"page":45,"startToken":10996,"endToken":11269,"text":"24 \nremoved from the [Reliability Pricing Model] auction.”32 PJM’s stated rationale for \n1 \nthis was that “including connect and manage [load] in the [Reliability Pricing \n2 \nModel] auction continues to provide price signals for new investment.” 33 So \n3 \nclearly, PJM recognizes that excluding IRAS demand impacts long-term price \n4 \nsignals and reduces the incentive for new entry and retention of existing resources. \n5 \nQ28. ARE ANY OF YOUR CONCLUSIONS IMPACTED BY THE FACT THAT \n6 \nIRAS IS ONLY ACTIVE DURING PERIODS OF CAPACITY SHORTAGE? \n7 \nA28. No. As I describe above, BYONC can suppress prices during periods of both \n8 \ncapacity shortage (when IRAS is active) and during periods of capacity surplus \n9 \n(when IRAS becomes inactive). Suppressing prices at any time, including during \n10 \ntimes of shortage, hinders the ability of the demand curve to provide a long-run \n11 \naverage price equal to net CONE. \n12 \n3.2 Hindrance of Competition Between Resources Serving New Large \n13 \nLoads and Existing Loads \n14 \nQ29. ARE THERE OTHER ECONOMIC IMPACTS THAT WOULD RESULT \n15 \nFROM THE INTRODUCTION OF IRAS? \n16 \nA29. Yes. Another key impact of the introduction of IRAS is the creation of two different \n17 \nmarkets (the market to serve new large loads and the market to serve all other loads) \n18 \nwith two different prices for otherwise identical products (capacity). The \n19 \n \n32 “Connect and manage” was PJM’s previous term for what they now call IRAS. PJM Interconnection, \nL.L.C., Connect and Manage PJM Package, 29, (May 27, 2026) https://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-item-04---connect-and-manage-\npjm-package---pjm-presentation.pdf. \n33 Id. at 29."},{"page":46,"startToken":11269,"endToken":11426,"text":"25 \nbifurcation of the same product into two different markets hinders competition \n1 \nbetween resources in each market, which ultimately increases societal costs. \n2 \nQ30. HOW DOES MARKET BIFURCATION HINDER COMPETITION AND \n3 \nINCREASE SOCIETAL COSTS? \n4 \nA30. Bifurcating the market increases societal costs because it can require one market to \n5 \nprocure more expensive capacity when it might be available for less cost in the \n6 \nother market. In the case of IRAS, it is plausible that capacity market prices will \n7 \nnot be high enough to retain existing resources let alone induce new entry. In this \n8 \ncase, existing resources may retire. At the same time, IRAS requires new large \n9 \nloads to procure new capacity. Thus, new large loads would unnecessarily incur the \n10 \nhigher cost of building new generation when it could have been more economic to \n11 \ninvest in retaining existing generation. This dynamic is illustrated in the figure \n12 \nbelow. \n13"},{"page":47,"startToken":11426,"endToken":11557,"text":"26 \nFigure 7: Illustration of How Market Bifurcation Can Lead to a Lower Cost Resource Being \n1 \nCrowded Out by a Higher Cost Resource \n2 \n \n3 \nThe outcome illustrated above is particularly relevant for cases where \n4 \nexisting resources are contemplating expensive investments (such as repowering of \n5 \nan existing but aging resource) that are still more economic than developing a new \n6 \nresource. The result is that society pays more for the new resource when it could \n7 \nhave received the same reliability benefit by paying less for the existing resource. \n8 \nQ31. ARE THE INEFFICIENCIES OF A BIFURCATED MARKET WELL-\n9 \nESTABLISHED? \n10 \nA31. Yes. As one example, the market monitor for the New York Independent System \n11 \nOperator (“NYISO”) examined capacity market outcomes under both a “uniform” \n12"},{"page":48,"startToken":11557,"endToken":11793,"text":"27 \nand “bifurcated” market structure between new and existing resources. 34 The \n1 \nmarket monitor found that “approaches with price discrimination [i.e., bifurcation] \n2 \nincentivize less efficient behavior, ultimately resulting in greater need for \n3 \nexpensive new capacity over time.” \n4 \nMore generally, economists have found that a uniform price market (i.e., \n5 \nnot a bifurcated market) promotes efficiency and maximizes social welfare. For \n6 \nexample, preeminent energy economists Peter Cramton and Steven Stoft state that \n7 \n“the uniform-price auction yields a competitive equilibrium, and the competitive \n8 \nequilibrium is efficient: the outcome maximizes social welfare.”35 FERC has also \n9 \nfound that “paying all cleared … resources a uniform price [will] send an efficient \n10 \nprice signal, and be consistent with long-standing Commission policy approving \n11 \nuniform clearing prices.”36 In other words, a market that sends the same uniform \n12 \nprice to all supply is able to harness competition to meet demand for electricity at \n13 \nthe lowest total societal cost. \n14 \n \n \n15 \n \n34  Potomac Economics, MMU Analysis of Capacity Market Structure, 18, (May 22, 2025) \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-item-04---\nconnect-and-manage-pjm-package---pjm-presentation.pdf. \n35 Peter Cramton & Steven Stoft, Uniform-Price Auctions in Electricity Markets. Pg 8. (Mar. 20, 2006), \nhttps://www.cramton.umd.edu/papers2005-2009/cramton-stoft-clearing-price-markets.pdf. \n36 Frequency Regulation Compensation in the Organized Wholesale Power Markets, Order No. 755-A, 138 \nFERC ¶ 61,123, at 2 (2012)."},{"page":49,"startToken":11793,"endToken":11975,"text":"28 \n4 Recommendations & Summary \n1 \nQ32. PLEASE PROVIDE A SUMMARY OF THE CONCERNS RAISED IN \n2 \nYOUR TESTIMONY. \n3 \nA32. The key concerns I raise in my testimony are: \n4 \n• IRAS creates a discriminatory requirement for new large loads to bring their \n5 \nown new capacity to the market or face priority interruption. This same \n6 \nrequirement does not apply to all other loads that retain the option to procure \n7 \ncapacity from the capacity market. \n8 \n• The introduction of IRAS will paradoxically increase societal costs, \n9 \nincrease consumer prices, and degrade reliability. It does this through two \n10 \nprimary mechanisms: \n11 \n1. A reduction in new investment and reduction in retention of existing \n12 \nresources. This itself is caused by: \n13 \n▪ The expectation of reduced future capacity market prices due \n14 \nto the introduction of asymmetric downward price risk and \n15 \nincentivization of uneconomic new entry; and \n16 \n▪ A chilling of investment due to the prevention of new large \n17 \nloads from increasing current prices. \n18 \n2. Hindrance of competition between resources serving new large \n19 \nloads and existing loads. \n20"},{"page":50,"startToken":11975,"endToken":12238,"text":"29 \nQ33. WHAT IS YOUR OVERALL ASSESSMENT OF IRAS? \n1 \nA33. While IRAS appears to be a genuine attempt to “protect residential customers from \n2 \ncapacity price increases,” the problem is it does exactly the opposite.37 In this \n3 \nregard, IRAS is simply a new spin on the intuitive but ultimately self-defeating idea \n4 \nof providing consumer benefits through price suppression (i.e., price manipulation). \n5 \nIf it were possible to provide consumer benefits through price suppression, PJM \n6 \nhas many tools at its disposal and could have done so long ago. Chief among these \n7 \noptions would be simply reducing the capacity market demand curve to “reduce” \n8 \nprices. However, this doesn’t work, because the market adapts and responds and \n9 \nultimately forms the prices that are necessary to cover resource costs, even at the \n10 \nexpense of reliability due to reduced entry and increased exit. The fact that IRAS \n11 \nwill increase societal costs, increase consumer prices, and degrade reliability \n12 \ndemonstrates that this is not the solution that PJM needs. \n13 \nQ34. IN LIGHT OF THE ARGUMENT YOU MAKE, DO YOU HAVE ANY \n14 \nRECOMMENDATIONS? \n15 \nA34. The overarching goal of the capacity market should be to maximize efficiency, \n16 \nwhich simply means providing reliability at the lowest total societal cost. Such an \n17 \noutcome ultimately minimizes consumer costs – an idea reinforced by leading \n18 \nenergy economists: \n19 \n“As with any type of productive investment, the goal should be to \n20 \nminimize the total cost of production and delivery. If the market is \n21 \n \n37 PJM Filing, at 5."},{"page":51,"startToken":12238,"endToken":12385,"text":"30 \ncompetitive or the regulation effective, these costs savings will be \n1 \npassed through to consumers.”38 \n2 \nTo minimize societal costs, all resources should face the same non-\n3 \ndiscriminatory price signal (i.e., a uniform market clearing price). PJM should \n4 \nimplement long-term market reforms to provide a sufficient uniform price signal to \n5 \nboth new and existing resources to meet all demand (not just demand associated \n6 \nwith new large loads). \n7 \nI therefore recommend that PJM should not move forward with the IRAS \n8 \nproposal as it is distortionary, discriminatory, bifurcates the market, unnecessarily \n9 \nincreases societal costs and consumer prices, and front-runs PJM’s long-term \n10 \nmarket design reforms. \n11 \nQ35. DOES THIS CONCLUDE YOUR TESTIMONY? \n12 \nA35. Yes. \n13 \n \n38 Steven Stoft, Problems of Transmission Investment in a Deregulated Power Market, in Competitive \nElectricity Markets and Sustainability 6 (François Lévêque ed., 2006)."},{"page":52,"startToken":12385,"endToken":12452,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day caused to be served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this docket. \nDated at Washington, D.C. this 3rd day of September, 2026. \n \n \n \n \n \n \n  \n   /s/ Andrew DeVore  \n \n \n \n \n \n \n \nAndrew DeVore \nKirkland & Ellis LLP \n1301 Pennsylvania Avenue, N.W. \nWashington, D.C. 20004 \n \nCounsel for Talen Energy Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":163,"startToken":0,"endToken":947},{"p":4,"at":163,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":4,"endAt":1312,"startToken":947,"endToken":1120},{"p":4,"at":1312,"title":"II. PROTEST","method":"printed heading","endPage":5,"endAt":1044,"startToken":1120,"endToken":1374},{"p":5,"at":1044,"title":"A. PJM’s proposal to require New Large Loads to procure new capacity or be","method":"printed heading","endPage":16,"endAt":130,"startToken":1374,"endToken":4744},{"p":16,"at":130,"title":"B. Even if the IRAS Proposal stood on solid legal ground—which it does not—","method":"printed heading","endPage":20,"endAt":6,"startToken":4744,"endToken":5857},{"p":20,"at":6,"title":"III. CONCLUSION","method":"printed heading","endPage":23,"endAt":3,"startToken":5857,"endToken":6146},{"p":23,"at":3,"title":"Table of Contents","method":"printed heading","endPage":29,"endAt":1300,"startToken":6146,"endToken":7637},{"p":29,"at":1300,"title":"A. For a UCAP MW quantity equal to 99% of the reliability requirement, the","method":"printed heading","endPage":30,"endAt":3,"startToken":7637,"endToken":7684},{"p":30,"at":3,"title":"B. For a UCAP MW quantity equal to 101.5% of the reliability requirement,","method":"printed heading","endPage":30,"endAt":149,"startToken":7684,"endToken":7714},{"p":30,"at":149,"title":"C. For a UCAP MW quantity equal to 106% of the reliability requirement, the","method":"printed heading","endPage":52,"endAt":0,"startToken":7714,"endToken":12385},{"p":52,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":52,"endAt":453,"startToken":12385,"endToken":12452}]}