{"document":{"slug":"rec-20260903-5201","title":"Protest and Comments of Constellation Energy Generation, LLC addressing PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service…","issued":"2026-09-03","accession":"20260903-5201","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Constellation Energy Generation, LLC","kind":"protest","file":"sources/filings/text/20260903-5201_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5201","tier":"record","sha256":"46dab5860d3a164ebe01f6a96816184e76e49aeeb1eff3107c4f7cf60433ed70","pages":90,"tokens":30255,"emptyPages":[87],"textThemes":["flex","adequacy","retail","registry"]},"pages":[{"page":1,"startToken":0,"endToken":249,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.: \n205(d) Rate Filing: Proposal to Establish \nInterim Resource Adequacy Service & a \nLarge Load Registry to be effective \n10/12/2026 \n) \n) \n) \n) \n) \n) \n \nDocket No. ER26-3515-000 \n \nPROTEST AND COMMENTS OF CONSTELLATION ENERGY GENERATION, LLC  \nPursuant to the Commission’s August 13, 2026 notice in the above-captioned proceeding, \nConstellation Energy Generation, LLC (“Constellation”) submits this protest and these comments \naddressing issues raised by the August 12, 2026 Proposal of PJM Interconnection, L.L.C. to \nEstablish Interim Resource Adequacy Service and A Large Load Registry to Address System \nReliability (the “PJM Proposal,” “IRAS Proposal,” or “Proposal”). \nThe Commission should reject the PJM Proposal for multiple independent reasons.  First, \nadoption of the Proposal falls outside the scope of the Commission’s jurisdiction as defined by the \nFederal Power Act (“FPA”).  Although PJM’s filing seems to suggest that the Commission should \nbe willing to expand its jurisdiction to address novel problems or those involving technology \nthat—in PJM’s words—would have seemed like “science fiction” to the drafters of FPA Section \n201,1 those circumstances cannot justify any departure from the statute’s plain language or the \nprecedent interpreting it.  As those authorities provide, the Commission cannot intrude on the retail \nsphere by “specif[ying] terms of sale at retail” or otherwise—and “cannot take an action \ntransgressing” that “limit no matter how direct, or dramatic, [the action’s] impact on wholesale \n \n1 PJM Proposal 91, Docket No. ER26-3515-000 (Aug. 13, 2026)."},{"page":2,"startToken":249,"endToken":572,"text":"2 \n \nrates” might be.2  Yet that is exactly what PJM’s Proposal seeks to do:  it seeks to impose special \nburdens on a class of retail load, by requiring new, large retail customers to take interruptible retail \nservice in exchange for federally prescribed compensation.  The Commission cannot accept a \nProposal that asks it to regulate based on retail characteristics and force a change in retail rules.  \nMoreover, accepting PJM’s Proposal would send the Commission down a slippery jurisdictional \nslope, raising the possibility of all sorts of federal regimes governing the service conditions and \ngeneration-procurement choices of specific types of retail customers. \nSecond, PJM has failed to carry its burden to show that the Proposal is not unduly \ndiscriminatory or preferential.  PJM singles out New Large Loads for disfavored treatment \n(potential curtailment) based on their size and their in-service date.  But those distinctions make \nno material difference to IRAS’s purpose of supporting reliability and capacity.  The capacity of \nthe system is as taxed on a megawatt basis by one fifty-megawatt customer as by fifty one-\nmegawatt customers.  And the system is as burdened by a customer that came into service the day \nbefore the New Large Load cutoff as one that came into service the day after.  PJM’s proposal also \nwould discriminate among supply resources, by allowing New Large Loads to avoid potential \ncurtailment only if they make arrangements with qualifying “new” capacity.  But a megawatt of \nexisting capacity provides the same reliability to the system as a megawatt of new capacity, and \nshould be permitted to enter the same commercial arrangements.   \nFinally, PJM has failed to carry its burden to show that its Proposal is just and reasonable \nbecause the Proposal suffers from significant design flaws and a fundamental economic \nirrationality, such that this Commission’s approval would be subject to reversal on appeal as \n \n2 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 280 (2016), as revised (Jan. 28, 2016) (“EPSA”)."},{"page":3,"startToken":572,"endToken":900,"text":"3 \n \narbitrary and capricious.  PJM’s Proposal to deploy IRAS before Pre-Emergency Load \nManagement Reduction Actions arbitrarily and unreasonably fails to adhere to core economic \ndispatch principles, fails to reflect any IRAS load curtailment in energy price formation, and fails \nto maximize social surplus, while also serving no clear reliability purpose and potentially \nundermining reliability.  In addition, PJM’s Proposal to exclude New Large Loads without \nsufficient “BYONC” (i.e., “bring your own new capacity”) from the demand curve used in RPM \nAuctions is an arbitrary and unreasonable step that would significantly undermine the efficient \noperation of the RPM and exacerbate an existing crisis that PJM itself has identified as a significant \nproblem.  And the Proposal is irrational in other ways as well, including by failing to allow any \nqualifying BYONC to be replaced by other qualifying BYONC, by limiting the resources that \nqualify as BYONC to resources that cleared an auction for the first time in the Base Residual \nAuction for certain delivery years rather than in any auction for those years, and by failing to \ninclude incremental capacity created by an energy resource in the definition of BYONC. \nTaken separately, each of those three flaws is enough to doom the Proposal.  But it is also \nworth considering the Proposal’s many flaws together as a whole.  Since its beginning decades \nago, the PJM market has been premised on the principles that all load is equally entitled to firm \nservice, with a reliability target of one interruption every ten years, and that all generation capable \nof providing service should be subject to the same rules.  The Proposal abandons those basic \nprinciples, without ever acknowledging the fundamental changes it would make.  It singles out \none class of load to receive inferior service and treats new resources more favorably than existing \nresources—and it does so by running roughshod over the jurisdictional line that separates the \nfederal domain from that of the states.  The Commission should reject the Proposal.  And in the"},{"page":4,"startToken":900,"endToken":1187,"text":"4 \n \nevent that the Commission were to accept the Proposal, it should condition acceptance on \nmodification of the Proposal as described in this filing. \nBACKGROUND \nPJM Interconnection, L.L.C. (“PJM”) has proposed to define certain customers as New \nLarge Loads and subject those customers to Interim Resource Adequacy Service (“IRAS”), a \n“service to be implemented by PJM … [w]hen triggered by system conditions.”3  Specifically, \nNew Large Loads that do not bring their own qualifying new capacity (known as “BYONC”) in \nan amount that equals or exceeds their peak load will be subject to involuntary load reductions.4 \nPJM contends that the IRAS framework will “support system reliability in the PJM \nRegion.”5  PJM states that “the unprecedented addition of large loads, most notably data centers, \nhave given rise to resource adequacy shortfalls—and associated real-time operational issues that \nIRAS is intended to address.”6  Accordingly, PJM has submitted proposed revisions to its Open \nAccess Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load \nServing Entities (“RAA”) to effectuate the IRAS framework.   \nPJM proposes to define New Large Load based on size and in-service date.  Under the \nproposed RAA changes, “Large Loads” are customers with cumulative peak load of 50 megawatts \nor greater “at a single electrical site behind one or more points of interconnection” (and, for \nconfigurations involving multiple affiliated facilities or points of interconnection, “all affiliated \nload facilities within a one-mile radius will be considered a single electrical site”).7  Additionally, \nunder the proposed revised tariff, “New Large Loads” are Large Loads that, after June 1, 2027, go \n \n3 PJM Proposal 1.   \n4 Id. at 74. \n5 Id. at 6. \n6 Id. \n7 Id. at 5 n.13; Proposed RAA, Definitions – Large Load."},{"page":5,"startToken":1187,"endToken":1535,"text":"5 \n \ninto service, are the incremental increase in an existing Large Load, or are the incremental increase \nat an existing end-use customer load at a single electrical site to bring it within the definition of \nLarge Load.8  PJM also proposes to create and maintain a Large Load Registry with information \nabout all Large Loads in the PJM region that will be used to identify New Large Loads forced to \ncurtail and to implement IRAS starting in the 2027/2028 Delivery Year.  The information used to \ndevelop and maintain the Large Load Registry would be “submit[ted] or cause[d] to be submitted” \nto PJM by LSEs and validated as needed by Electric Distributors.9 \nUnder PJM’s Proposal, New Large Loads are forced to provide IRAS (and are considered \n“Eligible New Large Loads”) unless their capacity needs are satisfied by either BYONC or \nAllocated RBP UCAP MW (described further below).  First, a New Large Load may avoid being \nforced into IRAS by “contract[ing] with new capacity that meets the BYONC gating criteria.”10  \nThose requirements “are designed to ensure the capacity is actually new and not repackaged and \nwill provide capacity over at least 10 years.”11  As described in the proposed tariff, qualifying \nBYONC must be “supported by” one of (1) a new generation resource; (2) incremental capacity \ncreated by an “uprate” of existing generation capacity resources, subject to specified requirements \nregarding how the incremental capacity is created; 12 (3) incremental capacity created by the \nutilization of Surplus Interconnection Service; (4) repowering of a deactivated generation resource; \n(5) incremental capacity created by an existing generation resource changing to a more efficient \nfuel type; or (6) new Demand Response or DER Capacity Aggregation Resources.13  Second, as \n \n8 Id. at 1 n.2; Proposed Tariff, Definitions – New Large Load. \n9 Id. at 45. \n10 Id. at 23. \n11 Id. \n12 As discussed below (see Part IV.C), incremental capacity created by an uprate of energy resources, as \nwell as existing generation capacity resources, should equally count as BYONC.  \n13 Proposed Tariff, Attachment DD-4, § VI(b)(i)-(ii)."},{"page":6,"startToken":1535,"endToken":1891,"text":"6 \n \nan alternative to BYONC, a New Large Load “may have its IRAS availability reduced by being \nallocated a share of” Reliability Backstop Procurement Unforced Capacity megawatts (RBP UCAP \nMW).14  Allocated RBP UCAP MW is allocated at the Electric Distributor zone/area level, and \nthen further allocated by the Electric Distributor “among the New Large Loads located in the \nElectric Distributor’s zone/area.”15 \nPJM proposes to implement IRAS, starting with the 2027/2028 Delivery Year, as part of \nits tiered response to a potential or actual capacity shortage.16  Specifically, “after determining that \navailable economic real-time supply may not be sufficient” to maintain reserves or to keep \nInterconnection Reliability Operating Limits within prescribed limits, PJM may initiate an IRAS \nAction.17  IRAS would be deployed after non-firm transmission services are curtailed18 —but \n“before relying on Demand Resources[] through Pre-Emergency Load Management Reductions \nActions.” 19   Under PJM’s proposal, PJM will issue load reduction directives to Electric \nDistributors, who “must execute” them.20  According to PJM, “[d]irecting an Electric Distributor, \nrather than a specific end-use customer, to reduce a quantity of load is in keeping with PJM’s \n \n14 PJM Proposal 67. \n15 Id. at 68. \n16 Id. at 75.  When PJM faces a capacity shortage, it undertakes a cascading series of emergency actions \nthat are aligned with NERC Energy Emergency Alert Level classifications (EEA1 through EEA3).  PJM \nManual \n13, \npp. \n24, \n32, \n83-84, \navailable \nat \nhttps://www.pjm.com/-\n/media/DotCom/documents/manuals/m13.ashx; see also PJM Proposal 79 Fig. 1. \n17 PJM Proposal 75.  Such an IRAS Action would occur “at the beginning of PJM’s actions” under the first \nalert stage, called EEA1.  PJM Proposal 22; PJM Proposal 80 Fig. 2 (placing “IRAS Large Load reduction” \nprior to “Pre-Emergency DR” in the chronology of PJM emergency procedures). \n18 Id. at 78. \n19 Id. at 79 (emphasis in original); Pilong Affidavit 7, 10. \n20 PJM Proposal 26, 82; see Proposed Tariff §§ II(e), III(a) (“Electric Distributors shall … execute the Office \nof the Interconnection’s directives to implement Interim Resource Adequacy Service Actions among the \nEligible New Large Loads in the Electric Distributor’s zone/area”)."},{"page":7,"startToken":1891,"endToken":2172,"text":"7 \n \nlongstanding practice and reflects and respects the allocation of jurisdiction between the federal \nand state levels.”21  \nPJM’s proposal assumes that curtailment decisions as to specific Large Loads “would be \nworked out through revised state retail tariffs”22 —necessitating that “appropriate, documented \nstate-sanctioned load reduction plans” would either “already [be] in place or will be developed and \nrefined in conjunction” with the rollout of IRAS.23  PJM’s filing acknowledges that such tariffs \nhave not yet been developed, citing “the need to establish retail mechanisms authorizing utilities \nto curtail designated large commercial and industrial customers.”24  PJM concedes that “states may, \nof course, establish and enforce their own retail load reduction programs,”25 and “states may each \ndefine ‘large loads’ differently for purposes of their retail tariffs, particularly those governing load \nreduction protocols.”26  \nPJM also has proposed “a rate for IRAS that is equal to 50% of the Non-Performance \nCharge Rate.”27  The proposed tariff states that “the Electric Distributor shall be responsible for \ncompensating” the loads that were required to provide IRAS and “shall be responsible for charging \ncustomers in its zone/area to fund any such compensation,” unless the Electric Distributor requests \nthat PJM take steps to “assess charges” to “fund such compensation.”28  At the same time, PJM \npurports to “provide[] Electrical Distributors and states flexibility in the applicable IRAS rate for \n \n21 PJM Proposal 86. \n22 Id. at 87. \n23 Id. at 6.  \n24 Id. at 88-89; see id. at 87 (“PJM stands ready to assist states in developing those tariffs if they so desire.”). \n25 Id. at 99. \n26 Id. at 87.  \n27 Id. at 102. \n28 Proposed Tariff, Attachment DD-4, § X(b)(i)-(ii)."},{"page":8,"startToken":2172,"endToken":2485,"text":"8 \n \nits territory,”29 apparently in the sense that the amount can be adjusted downwards, and specifies \nthat “[w]hether a specific New Large Load may be entitled to compensation for provision of IRAS \nwill be determined by state authorities under state law or RERRA as may be applicable.”30 \nFinally, PJM proposes to exclude New Large Loads from PJM’s capacity-market demand \ncurve (the “Variable Resource Requirement” or “VRR Curve”) beginning with the 2029/2030 \nDelivery Year, unless those loads have “arrangements with sufficient BYONC.”31  Where New \nLarge Load does contract with sufficient new capacity to avoid IRAS, PJM would add that load to \nthe VRR Curve but require the new capacity to participate in RPM Auctions as a price taker (at an \noffer of $0/MW) for ten consecutive Delivery Years.32  That approach is a reversal from PJM’s \nprior development of this proposal, which warned that excluding Large Loads from the demand \ncurve could skew market signals and distort costs to existing customers.33  PJM now asserts that \nthis element of its proposal “is designed to protect residential customers from capacity price \nincreases resulting from the effects of New Large Loads.”34 \nPJM is requesting expedited approval of the revisions to the Tariff and RAA needed to \nimplement IRAS—effective 60 days after the filing, on October 12, 2026—in part to “support \nongoing state efforts to establish retail-level, operational procedures” for reducing New Large \nLoads without BYONC ahead of other customers.35  PJM does not propose an expiration date for \nIRAS or a path for Eligible New Large Loads subject to IRAS to transition to non-interruptible \nservice over time, short of fulfilling requirements associated with BYONC. \n \n29 PJM Proposal 102. \n30 Id. at 106. \n31 Id. at 23. \n32 Id. at 55, 57-58. \n33 Jan. 16, 2026 Decisional Ltr. at 5. \n34 PJM Proposal 23-24. \n35 Id. at 8-9."},{"page":9,"startToken":2485,"endToken":2883,"text":"9 \n \nPROTEST AND COMMENTS36 \nI. \nPJM’s Proposal Is Beyond The Commission’s Jurisdictional Reach \nA. \nThe Commission’s Jurisdiction Is Subject To Strict Statutory Limits \nSection 201(b) of the FPA limits the Commission’s jurisdiction to “the transmission of \nelectric energy in interstate commerce and to the sale of electric energy at wholesale in interstate \ncommerce.”37  The Commission cannot regulate “any other sale of electric energy.”38   \nIn keeping with those formal limits, Section 201(a) declares that “Federal regulation … \nextend[s] only to those matters which are not subject to regulation by the States.”39  It also declares \nthat federal regulation “is necessary in the public interest” only as to “that part of [the electric \nenergy] business which consists of the transmission of electric energy in interstate commerce and \nthe sale of such energy at wholesale in interstate commerce.”40  Those declarations “cannot nullify \na clear and specific grant of jurisdiction” elsewhere in the statute,41 but they are relevant as a \nguiding expression of congressional purpose where there is no clear and specific grant of \njurisdiction and the Commission is asked to take a novel action.42 \n \n36 Constellation does not object on jurisdictional (or other) grounds to the portion of PJM’s Proposal that \nwould establish a Large Load Registry.  Such a registry does not involve interference with the retail market; \nit is merely an information-gathering exercise that, in and of itself, does not affect retail prices or the service \nprovided to Large Loads or any other category of retail customer.  Moreover, as PJM points out, “the \nproposed registry will give Electric Distributors and state entities access to critical information they may \nelect to rely upon when fashioning … load reduction protocols (including through recently-announced VA \nSCC and DCC state-led workshops).”  PJM Proposal 7.  Accordingly, references below to flaws in PJM’s \nProposal do not encompass the portion of the Proposal relating to the registry. \n37 FPA Section 201(b)(1), 16 U.S.C. § 824(b)(1). \n38 Id. \n39 Id. § 824(a). \n40 Id. (emphasis added). \n41 New York v. FERC, 535 U.S. 1 (2002) (citations omitted). \n42 See generally W. Virginia v. EPA, 597 U.S. 697, 721, 724 (2022) (rejecting notion that an agency can \n“claim to discover in a long-extant statute an unheralded power representing a transformative expansion in \n[its] regulatory authority,” particularly when that power is of great “economic and political significance”)."},{"page":10,"startToken":2883,"endToken":3246,"text":"10 \n \nIn FERC v. EPSA, the Supreme Court interpreted Section 201(b) and established a test for \nassessing whether the Commission has acted within the scope of its statutory jurisdiction.43  The \nCommission’s jurisdiction extends only “to rules or practices that directly affect the [wholesale] \nrate.” 44  And even if a Commission action has that necessary direct effect, the Commission \nnevertheless cannot intrude on a sphere that is “reserv[ed]” for the states—namely, “retail \nelectricity sales.”45  Because the “wholesale and retail markets in electricity … are not hermetically \nsealed from each other,” the fact that a Commission action merely affects the retail sphere is not \nenough to create a jurisdictional problem.46  Conversely, mere effects on wholesale rates are not \nenough to make a Commission action jurisdictionally permissible:  “FERC cannot take an action \ntransgressing th[e] limit” on intruding on the retail sphere “no matter how direct[] or dramatic” \nthat action’s “impact on wholesale rates” may be.47  Thus, the Commission cannot “specif[y] terms \nof sale at retail,” which “is a job for the States alone,” even though such a specification could \nundoubtedly have a significant effect on wholesale rates.48   \nIn deciding whether a proposed Commission action crosses the line into an area reserved \nfor the States, several factors are highly relevant.  First, it is critical to ask whether a Commission \naction “addresses—and addresses only—transactions occurring on the wholesale market” and \n \n43 577 U.S. at 276-77. \n44 Id. at 278.  Unless otherwise indicated, references to “wholesale rates” in these comments refer to “both \nwholesale rates and the panoply of rules and practices affecting them.”  Id. at 277-78. \n45 Id. at 279.   \n46 Id. at 281; see id. (transactions occurring “on the wholesale market have natural consequences at the retail \nlevel”). \n47 Id. at 280. \n48 Id. (emphasis added); see id. at 266, 280 (rule “compelling every consumer to buy a certain amount of \nelectricity on the retail market” would “exceed FERC’s authority” even though it would “necessarily \ndetermine the load purchased on the wholesale market too, and thus would alter wholesale prices”); \nCalifornia v. FERC, 495 U.S. 490, 497 (1990) (discussing “zone of exclusive state jurisdiction”)."},{"page":11,"startToken":3246,"endToken":3584,"text":"11 \n \nwhether “every aspect of the regulatory plan happens exclusively on the wholesale market.”49  If \nso, then the Commission has stayed within the lines that Congress drew in Section 201(b).  Those \nlimitations were central to the Supreme Court’s decision in EPSA that regulation of demand \nresponse on the wholesale market was within the scope of the Commission’s power.50 \nSecond, it is important to analyze whether the Commission’s “justifications for \nregulating … are all about, and only about, improving the wholesale market” such that the \nwholesale market, rather than the retail market, is the “target at which” the action “aims.”51  Again, \nthe Supreme Court leaned heavily on that factor in EPSA in upholding the Commission’s action as \njurisdictionally proper.52  And in invoking the “target” concept, the Court pointed to general \nprinciples of preemption law.  In that context, the Supreme Court has looked past the question of \nwhether a government body is using tools that formally fall within its proper sphere of action and \nconsidered whether that body is using those tools to functionally intrude on an area outside of its \nproper sphere.53 \nNumerous cases illustrate the “targeting” inquiry.  For instance, in Schneidewind v. ANR \nPipeline Co., 485 U.S. 293 (1988), which is cited repeatedly in Oneok, Inc. v. Learjet, Inc., 575 \nU.S. 373 (2015) (on which EPSA relies), the Supreme Court held a state law invalid because “the \nthings [the state law’s] regulation is directed at, the control of rates and facilities of natural gas \ncompanies, are precisely the things over which FERC has comprehensive authority.”54  And in \n \n49 Id. at 282.   \n50 See id. at 279-289. \n51 Id. at 282-83; see id. at 287. \n52 See id. \n53 See id. at 281-282 (twice citing Oneok, Inc. v. Learjet, Inc., 575 U.S. 373 (2015), in which the Supreme \nCourt emphasized in deciding that the Natural Gas Act does not preempt general state antitrust laws “the \nimportance of considering the target at which the state law aims”). \n54 Id. at 308."},{"page":12,"startToken":3584,"endToken":3932,"text":"12 \n \nHughes v. Talen Energy Marketing, LLC, 578 U.S. 150 (2016), the Supreme Court rejected \nMaryland’s program to encourage new generation by requiring a new generator to bid and clear in \nthe capacity market in exchange for a guaranteed capacity price.55  The Court held that the program \nwas unlawful even though it worked entirely through the state-jurisdictional domain of payments \nto generators from retail customers.  The Court concluded that although Maryland “may regulate \nwithin the domain Congress assigned to [it] even when [its] law[] incidentally affect[s] areas within \nFERC’s domain,”56 “Maryland’s program” was targeted at the wholesale market and in substance \n“set[] an interstate wholesale rate.”57  Those cases involved a state intruding into the federal sphere, \nrather than vice-versa—but the “targeting” analysis that they undertake is fully applicable in \nassessing whether the federal government is intruding into a sphere that the FPA reserves for the \nStates. \nThird, it is pertinent whether a proposed Commission action would regulate matters that \nare “subject to regulation by the States.”58  If the States themselves have the jurisdictional authority \nto develop rules or approve tariffs that carry out essentially the same action that the Commission \nis considering, then the federal action in question would cross over into what Section 201 calls \n“any other sale of electric energy”—i.e., retail sales.59  After all, the States have authority to act \nonly within the retail sphere, and federal action cannot be necessary to carry out the FPA’s core \npurposes if state regulation is otherwise available. 60   Indeed, in ruling in EPSA that the \n \n55 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 158-59 (2016). \n56 Id. at 164. \n57 Id. at 163. \n58 16 U.S.C. § 824(a). \n59 Id. § 824(b)(1); see Entergy Texas, Inc. v. Nelson, 889 F.3d 205, 212 (5th Cir. 2018) (“There is no overlap \nof jurisdiction.”). \n60 See NextEra Energy Res., LLC v. FERC, 118 F.4th 361, 368 (D.C. Cir. 2024) (asking “whether the \ncontested assertion of authority is consistent with the statute’s core purposes”)."},{"page":13,"startToken":3932,"endToken":4223,"text":"13 \n \nCommission had stayed within its jurisdictional limits, the Supreme Court relied on the fact that \nStates had no power to regulate wholesale demand response—which meant that if the Commission \ncould not regulate in that area, then no one could.61 \nB. \nThe Proposal Exceeds The Statutory Limits On The Commission’s \nJurisdiction By Targeting Retail Activities And Thereby Impermissibly \nIntruding Into The States’ Regulatory Sphere \n1. \nPJM’s Proposal Impermissibly Intrudes On The States’ Regulatory \nSphere   \nThe Proposal impermissibly takes a federal reliability function—telling distribution \nutilities how much load must be shed during an emergency—and transforms it into a federal \nregulatory regime governing which categories of retail customers must procure generation, which \nretail customers must accept curtailment if they do not, and how those curtailed customers are to \nbe compensated. \nThe Proposal regulates and targets New Large Loads, which are a specific type of retail \ncustomer.  It does so based on retail characteristics:  the size and newness of individual retail loads.  \nThe Proposal seeks to force changes to certain retail terms of service for those disfavored loads, \nrequiring EDCs to develop interruptible service that involves curtailment of New Large Loads that \ndo not bring their own new capacity (the “Eligible” New Large Loads, in the Proposal’s parlance).  \nIn doing so, the Proposal imposes direct requirements on retail customers and requires ongoing \nretail-side administration—for instance, confirmation that loads that have brought new capacity \nhave done so within the limits set forth in the proposal.62  In addition, the Proposal’s primary input \n \n61 See EPSA, 577 U.S. at 289-91. \n62 See PJM Proposal 59 (setting forth “[r]eporting arrangements between BYONC and New Large Loads” \nand a “process for PJM to recognize arrangements between New Large Loads and BYONC”)."},{"page":14,"startToken":4223,"endToken":4685,"text":"14 \n \nfor determining the quantity of load each EDC must subject to interruptible supply is a forecasted \nshortage associated with those Eligible New Large Loads.63 \nAs to compensation, the Proposal is even more intrusive into the retail sphere.  Section X \nof the proposed tariff revisions fixes the rate that retail customers are paid for IRAS—at “50% of \nthe Non-Performance Charge Rate,” or lower under certain circumstances in which an “Eligible \nNew Large Load elects” to accept less—and requires the EDC to pay that amount and (absent a \nrequest from the EDC to PJM for a different arrangement) to fund that amount by assessing charges \nagainst retail “customers” in its zone or area so as to pay compensation to other retail customers.64  \nThat is effectively a regulation of a retail rate, even though at a load’s election the amount of \ncompensation can go below the 50% amount that the Proposal specifies.   \nThe Proposal contends that “[w]hether a specific New Large Load may be entitled to \ncompensation for provision of IRAS will be determined by state authorities,” that as to \ncompensation “PJM is not mandating any action at the retail or state level,” and that “PJM’s \nproposal” on compensation “imposes no obligation on any state to do anything.”65  That PJM \n \n63 See id. at 82 (“PJM will issue MW load reduction directives to ‘Electric Distributors to implement \nreductions in load up to, and capped at, the pre-Delivery Year IRAS obligations they were assigned.’”).  As \na practical matter, New Large Loads will be data centers or other commercial or industrial customers.  PJM \nconcedes that it “does not contemplate that residential customers or smaller industrial customers would \nhave peak loads anywhere near 50 MW, which represents, roughly, the electricity consumption of between \n25,000 and 50,000 homes.”  Id. at 35. \n64 Id. at 102 & n.270; Proposed Tariff, Attachment DD-4, § X (“The rate for the provision of Interim \nResource Adequacy Service shall be 50% of the Non-Performance Charge Rate specified in Tariff, \nAttachment DD, section 10A(e), unless any Eligible New Large Load elects to (i) accept in its retail rates \na sum less than 50% of the Non-Performance Charge Rate as compensation for the provision of wholesale \nInterim Resource Adequacy Service, or (ii) waive receipt in its retail rates any compensation for the \nprovision of wholesale Interim Resource Adequacy Service as contemplated by Tariff, Attachment DD-4, \nsection X(c)… . Following an Interim Resource Adequacy Event, unless the Electric Distributor informs \nthe Office of the Interconnection otherwise in accordance with Tariff, Attachment DD-4, section X(b)(ii), \nthe Electric Distributor shall be responsible for compensating all Eligible New Large Loads that provided \nInterim Resource Adequacy Service for up to the amount of such service provided.”). \n65 PJM Proposal 106-107."},{"page":15,"startToken":4685,"endToken":4996,"text":"15 \n \nleaves to States the details of how to implement IRAS compensation does not change the reality \nthat PJM’s tariff is targeting the retail domain.  PJM asks the Commission to reach directly into \nthe retail sphere by approving a tariff that regulates the retail rate and the funding of compensation \nto retail customers—and that is not jurisdictionally permissible. \nThus, the Proposal targets a subset of retail customers in an effort to establish the conditions \nunder which those customers receive electric service—i.e., as EPSA put it, the “terms of sale at \nretail”66—and dictate the resource arrangements necessary to obtain firm service.  Walking through \neach of the three factors discussed above that are significant in assessing whether Commission \njurisdiction exists—whether the proposed action addresses only transactions on wholesale markets, \nwhether that action is justified only by improving the wholesale market and does not target the \nretail market, and whether the States could regulate in essentially the same way that the \nCommission is considering 67 —confirms that adoption of PJM’s Proposal is outside of the \nCommission’s jurisdictional power. \nFirst, PJM’s Proposal does not address only transactions on wholesale markets, and every \naspect of the plan does not happen exclusively on the wholesale market.  As discussed, IRAS \ncannot work without extensive reliance on retail-customer features:  it requires assessing new loads \nto decide if they constitute New Large Loads, deciding whether such loads are bringing their own \nnew capacity in a manner that PJM considers adequate, eliminating certain New Large Loads from \nany possibility of curtailment under IRAS, calculating the total number of megawatts to be \ncurtailed in light of an analysis of Eligible New Large Loads, and dictating the not-to-exceed \namount of compensation retail customers will be paid and how such compensation is to be funded.  \n \n66 EPSA, 577 U.S. at 280. \n67 See Part I.A, supra."},{"page":16,"startToken":4996,"endToken":5381,"text":"16 \n \nPJM also proposes that under IRAS it will directly instruct that curtailment at the retail level be \ncarried out to (in the words of the proposed Tariff modification) “implement Interim Resource \nAdequacy Service Actions among the Eligible New Large Loads in [an] Electric Distributor’s \nzone/area.”68  And all of that consideration of retail features and intervention in the retail market \nis in the service of attempting to force the retail customers that fall into the “New Large Loads” \ncategory to operate in a certain manner—for instance, by bringing a certain amount of new capacity \nthat is “actually new and not repackaged and will provide capacity over at least 10 years.”69  In \nshort, PJM’s Proposal is suffused with retail-market involvement. \nThat is a very far cry from the wholesale-only Commission action that the Supreme Court \nconsidered in EPSA, in which wholesale-market operators “administer[ed] the entire program” and \n“those footing the bill” were only “wholesale purchasers.”  577 U.S. at 282.  But it is not dissimilar \nto an example given in the Supreme Court’s decision in EPSA of a jurisdictionally impermissible \nCommission action:  “Suppose, to take a far-fetched example, that the Commission issued a \nregulation compelling every consumer to buy a certain amount of electricity on the retail market. \nSuch a rule would necessarily determine the load purchased on the wholesale market too, and thus \nwould alter wholesale prices.  But even given that ineluctable consequence, the regulation would \nexceed FERC’s authority, as defined in § 824(b), because it specifies terms of sale at retail—which \nis a job for the States alone.”70  The thrust of the IRAS Proposal is similar to that example, as the \nProposal seeks to force changes in use of retail electricity and the terms of retail sales, whether by \n \n68 Proposed Tariff § III(a).  \n69 PJM Proposal 23. \n70 EPSA, 577 U.S. at 280; see also Br. for FERC, FERC v. EPSA, No. 14-840 (U.S. July 9, 2015), 2015 WL \n4237680, at *40 (a “demand-response program in which wholesale-market operators would somehow \nprovide credits on retail bills to any consumer who reduced its expected use of retail electricity (rather than \nonly those consumers who make bids into wholesale markets)” would “run headlong into Section 824(b)(1) \nby directly altering the terms of retail sales”)."},{"page":17,"startToken":5381,"endToken":5717,"text":"17 \n \nincentivizing New Large Loads to act differently or by punishing New Large Loads that do not do \nso. \nSecond, the justifications that PJM offers are not all about improving the wholesale market, \nand the Proposal targets the retail market.  PJM essentially says as much, making clear that its \nProposal is motivated by issues with a specific type of retail customer and intended to change how \nretail service is provided to such customers.71  And PJM is focused on those large loads even \nthough, from a wholesale-market perspective, it should not matter whether 50 megawatts of new \nload comes from one Large New Load or from fifty customers at 1 megawatt each; the distinction \nbetween those two load compositions arises only in the retail sphere.72 \nAccordingly, this is not a circumstance in which a Commission action would merely affect \nthe retail sphere as an incidental result of regulation of a wholesale market.  It is in fact exactly the \nopposite:  the action the Commission is asked to approve targets the retail market as a means of \naffecting the wholesale market.  Under Section 201, it is impermissible for PJM to use the \nconnection between the wholesale and retail markets to effect change in the federal sphere through \nadjustments that fall within the retail sphere—“no matter how direct[] or dramatic” the Proposal’s \n“impact on wholesale rates” would ultimately be.73 \nThe analysis in the Supreme Court’s “targeting” decisions discussing the jurisdictional \ndivision of labor between the Commission and the States is therefore directly on point.  Just as in \nSchneidewind the state law at issue was invalid because “the things [the state law’s] regulation is \ndirected at, the control of rates and facilities of natural gas companies, are precisely the things over \n \n71 E.g., PJM Proposal 6 (asserting insufficient future commitments of capacity in RPM auctions are \n“primarily driven by the unprecedented addition of large loads, most notably data centers”). \n72 See, e.g., Part II.B, infra (discrimination argument). \n73 EPSA, 577 U.S. at 280."},{"page":18,"startToken":5717,"endToken":6013,"text":"18 \n \nwhich FERC has comprehensive authority,”74 the focus of IRAS is precisely a thing over which \nthe States have authority:  large new retail loads, as defined by retail-specific characteristics. \nThe fact that PJM is seeking to change a wholesale tariff, and otherwise to use federally \nregulated tools, does not change that analysis.  In this regard, PJM’s Proposal is closely analogous \nto the state action that the Supreme Court rejected in Hughes v. Talen.  In Hughes, Maryland was \nformally using state-jurisdictional tools:  payments to generators from retail customers and retail \nregulation.  But Maryland was doing so in a way that “disregard[ed] interstate wholesale rates \nFERC ha[d] deemed just and reasonable” by guaranteeing that a generator that bid and cleared in \nthe capacity market would receive a state-determined payment for capacity regardless of the \nclearing price, thus in substance “set[ting] an interstate wholesale rate.”75 \nThis case is the mirror image of Hughes.  PJM claims to act by using federal tools—\nwholesale rates and reliability-related load-shedding requirements—but it is using those tools to \ntarget the conditions and rates of retail service to a particular class of retail customers:  new large \nloads.  Accepting PJM’s Proposal would effectively “disregard” state decisions about what retail \ncustomers can obtain service and under what conditions.  That makes PJM’s Proposal different \nthan circumstances in which PJM has traditionally been permitted to require load-shedding, \nbecause in those circumstances the impermissible input of specific retail characteristics and \nspecific categories of retail customers is not present.  Looking at the target of a proposed action, \nand what the regulation does in substance, makes clear that PJM’s Proposal is jurisdictionally \nimpermissible because it steps too far over the wholesale/retail line. \n \n74 485 U.S. at 308. \n75 EPSA, 577 U.S. at 280."},{"page":19,"startToken":6013,"endToken":6407,"text":"19 \n \nThird, the States could institute essentially the same regulatory changes that PJM proposes \nin IRAS.  Nothing would stop the States, via state-jurisdictional tariffs, from developing \ninterruptible services for large retail customers that do not bring their own capacity and for \ndeciding what compensation to provide to affected customers and how to fund it.  Indeed, Virginia \nhas stated that it is working on model state tariffs along those lines that would go into effect before \nthe date when PJM requests that IRAS go into effect.76  The States would, of course, be fully \nempowered to use specific retail characteristics in deciding which customers would be subject to \nthat regime and its particular incentives and penalties.  And, in doing so, the States would be \noperating well within their statutorily protected retail sphere, which typically involves (among \nother things) deciding how different types of retail customers should be treated and incentivizing \npreferred generation in a way that is not tied to “a generator’s wholesale market participation.”77  \nThat is a strong indicator that the PJM Proposal is outside of the Commission’s jurisdictional power, \neven though the Proposal would affect wholesale rates.78   \nIn addition, although the Proposal leaves certain matters to state regulation,79 it does not \ndisplay the kind of “solicitude toward the States” that was persuasive to the Supreme Court in \nEPSA.  There, the Commission action in question voluntarily gave States a full “veto power” over \nthat action, “allow[ing] any State regulator to prohibit its consumers from making demand \n \n76 See June 20, 2026 Ltr. from Virginia State Corporation Comm’n to PJM (explaining that “many of the \ntools necessary to achieve the[] objectives” of PJM’s Proposal “fall within state jurisdiction” and stating \nthat Virginia is working on “model retail tariff structures and regulatory frameworks for consideration by \ninterested state commissions”), available at https://perma.cc/S7C6-C86H; PJM Proposal 88. \n77 Hughes, 578 U.S. at 166; see, e.g., id. (“Nothing in this opinion should be read to foreclose Maryland \nand other States from encouraging production of new or clean generation through measures ‘untethered to \na generator’s wholesale market participation.’  So long as a State does not condition payment of funds on \ncapacity clearing the auction, the State’s program would not suffer from the fatal defect that renders \nMaryland’s program unacceptable.”  (citation omitted)). \n78 See p. 10, supra. \n79 See PJM Proposal 85-93."},{"page":20,"startToken":6407,"endToken":6745,"text":"20 \n \nresponse bids in the wholesale market.”80  That was what the Court referred to when it discussed \n“a program of cooperative federalism, in which the States retain the last word,” and it was the \n“finishing blow” that persuaded the Court that the Commission did not “aim[] to obliterate[]” the \nStates’ “regulatory authority.” 81   Although PJM labels the Proposal a form of “cooperative \nfederalism,”82 the label here is misplaced.  The Proposal does not give States veto power and, more \nto the point, it does aim to interfere with the retail sphere and override state authority—while \nleaving to the States only a few minor or essentially illusory tasks (as further described below).83   \n2. \nPJM’s Proposal Is Not Jurisdictionally Permissible Merely Because \nElectric Distributors, In Coordination With The States, Would \nUltimately Select The Specific Customers To Be Curtailed \nPJM argues that its Proposal is saved by leaving to the state regulatory sphere the choice \nof which particular identifiable retail customers will be subject to curtailment under IRAS.84  But \nthat aspect of the Proposal does not render it jurisdictionally permissible.  \nThat is because, regardless of which particular customers are ultimately curtailed, the \nimposition of the obligation to effectuate curtailment in the first place is necessarily a function of \nexamining the load and generation commitments of a particular type of retail customer.  The \nCommission does not have the jurisdictional authority to approve a proposal that tries to shape and \nregulate the retail sphere in those ways,85 regardless of which customers among the disfavored \ngroup are ultimately affected and regardless of which entity makes that ultimate choice. \n \n80 EPSA, 577 U.S. at 287-88.   \n81 Id.   \n82 PJM Proposal 2, 85, 87. \n83 See Part I.B.2, infra. \n84 See, e.g., PJM Proposal 86 (“Directing an Electric Distributor, rather than a specific end-use customer, to \nreduce a quantity of load is in keeping with PJM’s longstanding practice and reflects and respects the \nallocation of jurisdiction between the federal and state levels.”). \n85 See pp. 13-15, supra."},{"page":21,"startToken":6745,"endToken":7119,"text":"21 \n \nIn any event, under IRAS, the States are not truly free to curtail retail customers—the \nselected customers are for practical purposes, and are intended to be, predetermined by PJM’s \nfocus on Eligible New Large Loads—that is, large loads that did not bring their own new \ncapacity.86  PJM’s Proposal declares that “it does not mandate any state-specific action”; it “avoids \nthe potential for conflicts with state policy determinations”; and it “respect[s] state law choices \nabout whether and how to facilitate implementation of a wholesale paradigm.”87  But the proposed \nchanges to the Tariff and the Proposal itself are to the contrary.   \nThe proposed changes to the Tariff state that the PJM “Office of Interconnection shall … \nrequest Electric Distributors to direct that a quantity of Eligible New Large Load Amounts in their \nrespective zone(s)/area(s) be reduced in accordance with an Interim Resource Adequacy Service \nAction” and that “Electric Distributors shall … execute the Office of the Interconnection’s \ndirectives to implement Interim Resource Adequacy Service Actions among the Eligible New \nLarge Loads in the Electric Distributor’s zone/area.”88  In addition, the proposed tariff provision \non compensation specifically talks about “compensating all Eligible New Large Loads that \nprovided [IRAS]” and “charging customers in its zone/area to fund any such compensation.”89  \nThe submission could therefore hardly be clearer that under PJM’s Proposal there is no unbounded \nchoice about which retail customers to curtail; rather, IRAS curtailment is only for customers in a \nspecific retail-customer category. \n \n86 E.g., PJM Proposal 86 (“In a Delivery Year in which IRAS applies, PJM will identify, for each zone/area, \nthe Eligible New Large Load Amounts, i.e., MW quantities that are eligible to be called upon to reduce load \nunder IRAS”). \n87 Id. at 107-108. \n88 Proposed Tariff §§ II(e), III(a) (emphasis added).  Those proposed tariff changes also state that IRAS “is \na load reduction service, effective starting with the 2027/2028 Delivery Year, through which Eligible New \nLarge Loads may be compensated for providing load reductions,” and that the proposed registry will \n“inform which New Large Loads are eligible to be called on to provide” IRAS.  Id. at I(a), I(c).   \n89 Proposed Tariff § X(b)(i) (emphasis added)."},{"page":22,"startToken":7119,"endToken":7505,"text":"22 \n \nAs if that were not enough, PJM’s Proposal says exactly the same thing in numerous places: \n• “IRAS is a supplemental capacity product through which Eligible New Large Loads \nmay be directed by the Electric Distributor to reduce their load in response to an \nInterim Resource Adequacy Service Action called by PJM… . In other words, IRAS \nis needed to manage the capacity needs of New Large Loads that have not satisfied \ntheir capacity needs on their own.”90 \n• IRAS “will be applicable to ‘[N]ew Large Loads that, as of June 1, 2027, do not bring \nsufficient capacity to serve their resource adequacy needs and cannot otherwise be \nserved at the 1-in-10 reliability standard[,]’ with load reductions under the service \noccurring before deployment of Pre-Emergency Load Management.”91 \n• “IRAS, as proposed, is a service that specifically allows for Large Loads to \ninterconnect without bringing their own capacity, on the condition that ‘they must \nreduce their load or switch to on-site backup resources under specific, limited’ \nemergency conditions.”92 \n• “At bottom, ‘exclusive jurisdiction’ rests with the states to ensure that the appropriate \nretail customers, i.e., New Large Loads, including data centers—and not residential \ncustomers or small industrial customers—are reduced when system conditions call for \nPJM to require load reductions according to IRAS.”93 \nThose are just a few of many similar examples.  Accordingly, the notion that selection of retail \ncustomers for curtailment under IRAS will extend beyond Large Loads is belied by numerous \naspects of the Proposal. \nIn addition, even setting those statements aside, it beggars belief that under IRAS States \nwould in fact curtail residential customers or other customers that do not fall within the Eligible \nNew Large Load category.  States surely have an incentive to avoid doing so as a political and \npublic-relations matter.  And, as noted, the whole structure of IRAS is designed to disfavor New \nLarge Loads that do not bring their own new capacity by making them subject to a new curtailment \nregime that is intended to kick in before Pre-Emergency Load Management Reductions.94  If those \n \n90 PJM Proposal 75-76. \n91 Id. at 17 (quoting PJM Board July 2026 Decisional Ltr. at 2). \n92 Id. at 39 (citation omitted). \n93 Id. at 90-91 (quoting PJM Interconnection, 190 FERC ¶ 61,115 at P 68). \n94 See p. 6, supra."},{"page":23,"startToken":7505,"endToken":7876,"text":"23 \n \nNew Large Loads are not disfavored in that way, then their incentive to bring their own new \ncapacity would be seriously reduced, and IRAS would no longer carry out the function for which \nit is intended.  Moreover, the IRAS procedures for curtailment in advance of the existing Pre-\nEmergency Load Management Reductions would be undermined, as that existing reduction \nprocedure can apply to all kinds of retail customers and is a workable means of interrupting service \nto reduce load. \nFor all of those reasons, the supposed “choice” that States are given under the PJM Proposal \nis illusory.  The curtailment that the Proposal envisions will undoubtedly be carried out against a \nspecific class of retail customers, defined by specific characteristics—just as the amount of any \ncurtailment requirement is dictated by that specific class of customers with those specific \ncharacteristics.  That means that the practical effect of IRAS is the same as if PJM directly picked \nthe New Large Loads for interruptible service, which—as PJM recognizes—would be \njurisdictionally impermissible.95 \n3. \nOther Considerations Also Cut Against Exercise Of Jurisdiction \nAlthough the Commission need not go further to conclude that jurisdiction is lacking here, \nit is also worth noting that accepting PJM’s Proposal is not necessary to address large new load \nissues and would likely have cascading negative effects when the Commission attempts in the \nfuture to answer jurisdictional questions like the one posed here. \nPJM’s filing all but insists that there is such an immense real-world problem arising from \nlarge new loads that the Commission must accept PJM’s specific IRAS Proposal.96  Of course, the \n \n95 PJM Proposal 92 (“[I]n recognition of the jurisdictional divide between PJM and the states and/or \nRERRAs, PJM will not direct reductions to specific New Large Loads pursuant to IRAS.”).  In this way, \nthe PJM Proposal can be understood to recognize that it is intruding into the retail sphere on curtailment, \nbut then to try to pull back from the jurisdictional precipice at the last moment—to no avail. \n96 See, e.g., PJM Proposal 6 (asserting that insufficient capacity commitments have been “primarily driven \nby the unprecedented addition of large loads, most notably data centers”); id. at 21 (asserting that PJM’s"},{"page":24,"startToken":7876,"endToken":8224,"text":"24 \n \nseriousness of a practical problem is no justification for distorting the plain meaning of a binding \njurisdictional statute.97  In any event, PJM’s premise is wrong, because there are other ways to \naddress the problem that do not create jurisdictional issues.  As noted, the States could develop \ninterruptible services for large retail customers that do not bring their own capacity, if the States—\nwith which PJM has been consulting 98 —perceive that a serious problem exists that needs \nsolving.99  And the Commission itself could act in ways that do not raise the fatal jurisdictional \nissues presented by the IRAS Proposal.  For instance, the Commission could explore other ways \nto incentivize additional capacity resources, including adding voluntary demand response projects \nwith limited call options.  Last fall, a coalition of supply-side companies, including Constellation, \njoined with several of the largest data center owners to propose just such additional demand \nresponse products.100  Another option would be a return to “market fundamentals” through other \nmarket improvements, as discussed in the recent Statement of Principles Regarding PJM signed \nby National Energy Dominance Council officials and the governors of the States located in the \nPJM, to spur investment in generation resources.101   \nThere is therefore no reason to accept PJM’s suggestion that the Commission is presented \nhere with a choice between adopting PJM’s Proposal and some sort of large-new-load-inflicted \n \ncapacity shortfall is due particularly to “the ‘unprecedented surge in data center load’ at a faster pace than \nnew supply can come online” (citation omitted)).   \n97 See, e.g., Pereira v. Sessions, 585 U.S. 198, 200 (2018) (explaining that practical considerations “do not \njustify departing from [a] statute’s clear text”).   \n98 PJM Proposal 3 (IRAS framework “developed following consultations and discussions with states and \nstakeholders”). \n99 See p. 19, supra. \n100 See 20251107-item-03c---joint-stakeholders-proposal.pdf.  As PJM’s Proposal states, PJM also has \nmade other filings with the Commission recently, and plans to make yet others later, to address large new \nload issues.  PJM Proposal 18-20. \n101 See Statement of Principles Regarding PJM, available at https://www.energy.gov/documents/statement-\nprinciples-regarding-pjm."},{"page":25,"startToken":8224,"endToken":8583,"text":"25 \n \ndisaster.102  Ahead of the final stakeholder meeting, PJM itself dropped the concept of mandatory \ncurtailment entirely in favor of a proposal that featured only a large load registry.  In advocating \nfor its revised proposal, PJM noted the “issues associated with PJM’s jurisdictional authority to \nimplement its [original] proposal” and the risk of “extended litigation over its authority.”103  PJM \nalso stated that among the Board-level considerations in developing a revised registry-only \nproposal was the desire to “[r]espect[] jurisdictional boundaries between PJM and states.”104  After \nthe stakeholder process was completed, PJM reversed itself and included the mandatory \ncurtailment proposal in the filing at issue here.105 \nAt the same time, there is a serious risk that accepting PJM’s Proposal as within the scope \nof the Commission’s jurisdiction would effectively destroy the statutorily mandated distinction \nbetween the wholesale and retail spheres.  Retail power is of course inevitably connected to the \nwholesale market, as such power must be bought at wholesale and transmitted to the distribution \nsystem before a retail customer can use it.  If the Commission could permissibly authorize PJM to \nshape retail service through a wholesale tariff that relies on specific retail-customer characteristics, \nthen it is difficult to see how the statute would bar use of such a federal lever in a wide variety of \nother situations to target disfavored features of the retail market.  In other words, if PJM’s Proposal \n \n102 See PJM Proposal 16 (“All 11 proposals regarding the concepts addressed by IRAS failed to achieve \ntwo-thirds stakeholder support.”); PJM Overrules Its Own Two Thirds Vote (Aug. 14, 2026), \nhttps://servola.de/journal/pjm-board-overrules-two-thirds-vote-on-curtailment/. \n103  PJM Connect & Manage CIFP Proposal Stage at 1, available at https://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02a---pjm-stage-4-proposal-\n--connect-and-manage---executive-summary.pdf. \n104 Id. at 4. \n105 PJM to Create Large Load Registry, Proposes to Hold Backstop Auction in October, RTO Insider (July \n28, 2026) (“The [PJM’s] board’s decision revives mandatory curtailment after PJM staff dropped the \nconcept from their proposal days before the final CIFP meeting, citing questions stakeholders raised around \nthe \nRTO’s \njurisdictional \nauthority \nto \nrequire \ncurtailment.”), \navailable \nat \nhttps://www.rtoinsider.com/137723-pjm-to-create-large-load-registry-proposes-backstop-auction/."},{"page":26,"startToken":8583,"endToken":8869,"text":"26 \n \nwere jurisdictionally permissible, then so too would be a proposal under which PJM (or some other \nRTO or ISO) were permitted to ration electric service based on (for instance) use of behind-the-\nmeter solar, deployment of LED lightbulbs, residential demand-response participation, or \nresidential use of energy-star heat pumps.  The upshot would be that States’ independent authority \nover the retail sphere would be displaced in all kinds of circumstances, contrary to Congress’s \nstatutory design and to the Supreme Court’s analysis in EPSA.106  The Commission should not \nstart down that slippery slope. \nMoreover, the Commission should be especially reluctant to do so given the novelty of \nPJM’s Proposal.  When agencies “‘claim to discover in a long-extant statute an unheralded power’ \nrepresenting a ‘transformative expansion in [its] regulatory authority,’” there is strong reason for \nskepticism, particularly when that power is of great “economic and political significance.”107  Here, \nPJM’s Proposal undermines the obligation to serve all customers, which is a fundamental principle \nof state-regulated utility service, and does so by relying on the actions of and targeting disfavored \nretail customers.  That is in and of itself enough to counsel great caution in accepting PJM’s \nProposal and to take special care before acting in what is, at a minimum, a highly jurisdictionally \nquestionable area. \nC. \nThe Proposal Exceeds The Statutory Limits On The Commission’s \nJurisdiction Because The Proposal Does Not Directly Affect Wholesale Rates  \nFinally, insofar as PJM’s Proposal is tied to specific retail-customer characteristics, it fails \nthe first part of EPSA’s jurisdictional test:  it does not directly affect wholesale rates. \n \n106 See pp. 10-13, supra.   \n107 W. Virginia, 597 U.S. at 724; see, e.g., Presidential Memorandum, Directing the Repeal of Unlawful \nRegulations (Apr. 9, 2025)."},{"page":27,"startToken":8869,"endToken":9208,"text":"27 \n \nIt may be true that load additions, taken as a whole, directly affect wholesale rates.  But \nPJM’s Proposal is not directed at load additions as such—that is, at all load additions, whether they \nare large or small or somewhere in between.  Rather, the Proposal is directed only at load additions \nthat are individually 50 megawatts or greater and that enter after a certain date.  There is no \ndifference, from the standpoint of assessing the effect on wholesale rates, between (a) a single load \naddition of 50 megawatts and (b) fifty load additions of one megawatt each, or between (a) a load \nthat enters on June 1, 2027, and (b) a load that enters on May 31, 2027.108  In each instance, (b) \ncan affect wholesale prices the same as (a). \nBecause the PJM Proposal addresses only the former situations and not the latter ones, it \nis far from apparent that the effect that the Proposal would have on wholesale rates is sufficiently \ndirect.  The distinctions drawn by PJM’s Proposal do not directly affect wholesale rates—and a \nproposal in this context that did have such a direct effect would account for all additional load, \nregardless of its size or when it energizes.   \nThe PJM Proposal takes a much more roundabout approach precisely because its focus is \nnot wholesale rates at all—it is rather the behavior of specific types of retail customers.  Regulation \nof the retail sphere undoubtedly does affect wholesale rates down the line, but it does not affect \nthose rates sufficiently directly to pass the EPSA test.109  A contrary view would improperly give \nSection 201 “near-infinite breadth” and swallow up the States’ area of jurisdictional authority.110 \nD. \nThe Authorities On Which PJM Relies Do Not Support Jurisdiction Here \nPJM tries to analogize its IRAS Proposal to various prior decisions by courts and this \nCommission.  But none of those authorities justifies the Commission’s exercise of jurisdiction here. \n \n108 See p. 2, supra. \n109 See EPSA, 577 U.S. at 277-79. \n110 Id. at 278."},{"page":28,"startToken":9208,"endToken":9511,"text":"28 \n \nFor instance, PJM tries to rely on EPSA itself.111  But, as discussed above, although EPSA \nsets forth the governing jurisdictional test, the facts here are readily distinguishable from the facts \nin EPSA.  There, the challenged wholesale rule regulated participation in a wholesale market, as a \nretail customer voluntarily offered a demand reduction into a FERC-jurisdictional wholesale \nmarket and received wholesale-market compensation.112  That rule affected retail sales, but the \nnature of the retail service was not an input to the wholesale rule.113  Here, the nature of the retail \nservice is just such an input, and IRAS effectively regulates the conditions under which certain \nspecified customers consume retail power. \nPJM also relies on decisions such as New PJM Companies, 107 FERC ¶ 61,272 (2004), for \nthe proposition that the Commission has decided that PJM can determine the location, quantity \nand timing of curtailment, while a distribution utility determines the manner in which retail load \nis actually curtailed. 114   But New PJM Companies involved procedures for a transmission \nemergency—and no one questions that Commission-mandated curtailment can be proper in that \ncircumstance.  The problem here is distinctions and curtailment rules based on specific retail \ncharacteristics, with the resulting intrusion into the retail jurisdictional sphere; that problem did \nnot arise in New PJM Companies. \nIn addition, PJM cites the Commission’s 2025-2026 Large Load proceedings and says that \nthey establish that Large Loads implicate both federal and state interests.115  That is undoubtedly \ntrue, but it says nothing about whether the specific design of the PJM Proposal is jurisdictionally \npermissible.  As discussed, there are alternative ways that the Commission could regulate Large \n \n111 PJM Proposal 91. \n112 See EPSA, 577 U.S. at 278-79. \n113 See id. at 281. \n114 E.g., PJM Proposal 85 n.228. \n115 E.g., id. at 2, 89."},{"page":29,"startToken":9511,"endToken":9797,"text":"29 \n \nLoads that would not present the same jurisdictional problems that doom IRAS.116  And the \nCommission and States could take separate actions, each in their own jurisdictional sphere, that \nwould harmoniously address large-load-related issues.  \nII. \nThe Commission Would Unduly Discriminate Based On Load Size, Load Date, And \nResource Vintage If It Accepted PJM’s Proposal \nPJM’s Proposal unduly discriminates in at least two respects:  (1) against certain load, \nbased on load size and load in-service date, and (2) against certain generation, based on resource \nvintage.  Those are independent reasons why the Commission should reject the Proposal. \nA. \nThe Commission Must Reject The Proposal Unless PJM Shows That The \nProposal Is Not Unduly Discriminatory And Preferential \nThe FPA prohibits undue discrimination in utility rates and dealings.  Specifically, under \nFPA Section 205, a utility is barred from “grant[ing] any undue preference or advantage,” \n“subject[ing] any person to any undue prejudice or disadvantage,” or “maintain[ing] any \nunreasonable difference in rates, charges, service, facilities, or in any other respect.”117  If the \nCommission finds that a “rate, charge, or classification” is “unduly discriminatory or preferential,” \nit must “determine the just and reasonable rate, charge, classification, rule, regulation, practice, or \ncontract to be thereafter observed and in force, and … fix the same by order.”118 \nCongress also prohibited undue prejudice or disadvantage in the specific circumstance at \nissue here:  the accommodation of anticipated capacity shortages.  Section 202(g) of the FPA \n(added by the Public Utilities Regulatory Act of 1978) mandates certain Commission obligations \nwith respect to “any anticipated shortage of electric energy or capacity which would affect [any] \n \n116 See p. 24, supra. \n117 16 U.S.C. § 824d(b). \n118 16 U.S.C. § 824e(a)."},{"page":30,"startToken":9797,"endToken":10152,"text":"30 \n \nutility’s capability of serving its wholesale customers.”119  In that circumstance, the Commission \n“shall require” each utility to “accommodate” such capacity shortage “in a manner” that “provide[s] \nthat all persons served directly or indirectly by such public utility will be treated, without undue \nprejudice or disadvantage.”120 \nThe trigger for Section 202(g) has plainly been met, as PJM’s proposal is (by its own \naccount) motivated by “[i]nsufficient commitments of capacity” in the 2027/2028 and 2028/2029 \nRPM Auctions that PJM says “have given rise to resource adequacy shortfalls.”121  There is also \nno question that New Large Loads qualify as “persons served directly or indirectly” by the public \nutilities within PJM. 122  Thus, in addition to reviewing the Proposal under Section 205, the \nCommission must ensure that IRAS complies with the mandate of Section 202(g), where Congress \nexpressly reiterated that discrimination should be avoided even when the system faces a shortfall.  \nIn substance, that means that the Commission must ensure that IRAS “equitably accommodate[s] \nservice” to “direct retail customers,” including New Large Loads.123 \nUnder the FPA, it is PJM, as the filer of the tariff revision, that bears the burden to show \nthat its proposal is not unduly discriminatory.124  The Commission, in turn, must “provide an \nadequate explanation before it treats similarly situated parties differently.” 125   In evaluating \ndiscrimination, the “critical determination” is whether a difference in treatment is “unreasonable \n \n119 16 U.S.C. § 824a(g). \n120 16 U.S.C. § 824a(g). \n121 PJM Proposal 6. \n122 61 Fed. Reg. 41,780 (Aug. 12, 1996) (stating that Section 202(g) requires “contingency plans respecting \nshortages of electric energy or capacity which would equitably accommodate service to both direct retail \ncustomers and those served by utilities supplied at wholesale by the public utility” (emphasis added)). \n123 Id.  \n124 Sacramento Mun. Utility Dist. v. FERC, 616 F.3d 520, 537 (D.C. Cir. 2010); Electricity Consumers \nResource Council v. FERC, 747 F.2d 1511, 1515 (D.C. Cir. 1984). \n125 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 267 (D.C. Cir. 2014)."},{"page":31,"startToken":10152,"endToken":10485,"text":"31 \n \nor undue.”126  Undue discrimination means that a practice “provides different treatment to different \nclasses of entities” and those entities are “similarly situated.”127  The determination that entities \nare similarly situated “does not mean that there are no differences between them,” but only “that \nthere are no differences that are material to the inquiry at hand.”128 \nB. \nPJM’s Proposal Unduly Discriminates Based On Load Size And Load Date \nPJM’s Proposal unduly discriminates against Large Load customers because it singles them \nout for interruptible service and load reduction based on their size and date of entry—yet those \ncharacteristics are not material distinctions justifying that unfavorable treatment. \nThe Proposal by its terms differentiates New Large Load based on size and date of entry.  \nLarge Load is defined as “end-use customer(s) load that has a cumulative peak load of 50 \nmegawatts or greater at a single electrical site behind one or more points of interconnection.”129  \nAnd New Large Load is defined as “Large Load that is in-service after June 1, 2027,” with the \n“relevant in-service date” potentially shifting in future years.130  The Proposal then treats New \nLarge Load unfavorably:  Eligible New Large Load is subject to curtailment, in the event of a \nshortage, before Pre-Emergency Load Management Reductions or emergency measures are \ntaken.131 \nYet New Large Loads are similarly situated to relevant comparators, notwithstanding their \nsize and date of entry.  The stated purpose of IRAS is to address “resource adequacy shortfalls—\n \n126 Complex Consol. Edison Co. of New York, Inc. v. FERC, 165 F.3d 992, 1013 (D.C. Cir. 1999).   \n127 Calpine Corp., 171 FERC ¶ 61,035, P 318 (2020); Complex Consol. Edison Co. of New York, Inc. v. \nFERC, 165 F.3d 992, 1013 (D.C. Cir. 1999). \n128 Calpine Corp., 171 FERC ¶ 61,035, P 318. \n129 PJM Proposal 31.  Under certain circumstances, “all affiliated load facilities within a one-mile radius \nwill be considered a single electrical site.”  Id. \n130 Id. \n131 See id. at 21-22."},{"page":32,"startToken":10485,"endToken":10805,"text":"32 \n \nand associated real-time operational issues.”132  Although aggregate load size surely matters to \nresource adequacy, PJM has not demonstrated that individual customer load size is relevant to the \nresource-adequacy harm that the Proposal seeks to address—except to the extent that individual \ncustomers contribute to aggregate load.  The baseline equitable principle, which PJM has not \ncontested, is that every customer “is economically marginal,” meaning that “the costs of increased \ndemand may equitably be attributed to every user.”133  Specifically, PJM has not shown that there \nis a material difference with respect to resource adequacy between one new 50 MW facility and \n50 new one MW facilities in the same area.  Yet PJM proposes that only New Large Loads would \nbe prioritized for service interruptions. \nPJM also has failed to demonstrate that the date of interconnection is relevant to any \noperational and resource adequacy challenges created by the load.  Indeed, setting aside the fact \nthat PJM’s justification for distinguishing Large Loads based on size is unjustified, PJM’s own \nstated rationale for differentiating New Large Loads has nothing to do with date in service; it \nrelates only to “size, operational behavior, and unique potential to impact the transmission \nsystem.”134  Yet under the Proposal, a data center that achieved commercial operation on May 31, \n2027, is exempt from IRAS entirely—free from pressure to enter into new-capacity arrangements, \nand free from the threat of load reduction requests that precede pre-emergency load management \nresponse. 135   By contrast, a nearby, identically sized data center that achieves commercial \noperation on June 1, 2027, is subject indefinitely to the consequences of IRAS. \n \n132 PJM Proposal 6; see id. (“The IRAS and the related revisions proposed herein support system reliability \nin the PJM Region”). \n133 BNP Paribas, 743 F.3d at 268-69 (quoting Southeastern Michigan Gas Co. v. FERC, 133 F.3d 34, 41 \n(D.C. Cir. 1998)). \n134 PJM Proposal 96. \n135 Id. at 17."},{"page":33,"startToken":10805,"endToken":11158,"text":"33 \n \nThe D.C. Circuit has rejected a Commission decision that would have allowed a scheme, \nlike PJM’s Proposal, that disfavored new customers—there, by charging new customers, but not \nhistoric customers, for the cost of base gas replenishment needed to maintain service levels.136  \nThe court of appeals reasoned that the Commission’s “cost causation” principle “generally calls \nfor giving the same treatment to new and continuing customers.”137  That approach is economically \nrational:  “Where ‘all customers cause the incurrence of the costs,’” sharing burdens equally among \ncustomers “forces each set ‘to weigh the marginal benefits of the capacity to them against the \nmarginal costs they impose on society by continuing to make demands.’”138  Here, all load—large \nand small, new and old—equally cause the need for capacity.  Accordingly, arbitrarily singling out \na subset of load as PJM proposes is inconsistent with the FPA and governing precedent. \nThe Commission’s recent order in Basin Electric Power Cooperative also is instructive.139  \nBasin submitted a Section 205 proposal to establish special wholesale power sales rate schedules \nfor cryptocurrency (“crypto”) operations and other new large loads.140  Specifically, Basin wanted \nto charge loads related to crypto mining operations in a different (and more expensive) way than \nother loads.141  Basin also sought to impose the same rate structure as for crypto loads on non-\ncrypto loads larger than 75 MW, but would have allowed those large loads to transition to the \n(cheaper) generally applicable rate schedule with five years’ notice.142 \n \n136 BNP Paribas, 743 F.3d at 266.  Although the case involved the Natural Gas Act, that statute has a parallel \nrequirement that rates must not be unduly discriminatory, see 15 U.S.C. § 717c(b), and the Court expressly \nrecognized the “rough equivalence” between the Natural Gas Act and the FPA, BNP Paribas, 743 F.3d at \n269-70.  \n137 Id. at 268.   \n138 Id. at 268 (quoting 1 Alfred E. Kahn, The Economics of Regulation 140 (1988) (citation omitted)). \n139 Basin Electric Power Cooperative, 188 FERC ¶ 61,132 (2024).   \n140 Id. P 1. \n141 Id. P 10. \n142 Id. PP 17, 18."},{"page":34,"startToken":11158,"endToken":11449,"text":"34 \n \nBasin argued that the differential treatment of crypto loads and large loads was justified \nbecause of the volatility of those loads.  Serving crypto loads through market-price pass-throughs \nwas necessary, Basin asserted, to reduce the risk that Basin would “construct new generation to \nserve Crypto Loads that will ultimately relocate in the near future,” as that would “result in \nstranded assets.”143  For large loads, Basin stated, federal tax incentives had spurred investment in \n“large industrial, manufacturing, commercial, and innovative facilities,” but such funding could \nbe “easily withdrawn,” again creating the risk that investment costs related to new generation \nresources could be stranded.144 \nThe Commission rejected Basin’s proposal as unduly discriminatory.145  The Commission \nexplained that there was “a risk of stranded assets when any large project is built in Basin’s service \nterritory,” yet Basin subjected only crypto loads to disfavored treatment.146  Even though Basin \nclaimed that both crypto loads and large loads were volatile, only crypto loads were excluded from \nthe generally applicable rate schedule indefinitely—while large loads could transition to the \ngenerally applicable rate schedule after five years.147  And there was no showing that crypto loads \nwere “more likely to ‘quickly shut down and move’” than other large loads, such as data centers.148  \nAlthough the Commission was “sympathetic to Basin’s concerns regarding its ability to serve load \ngrowth reliably and economically,” it rejected the proposal as unlawful discrimination.149 \nThe Commission’s rejection of Basin’s proposal maps directly onto PJM’s Proposal here.  \nPJM has raised concerns about load growth, resource adequacy, and reliability, but PJM fails to \n \n143 Id. P 16. \n144 Id. P 63. \n145 Id. P 94. \n146 Id. P 95. \n147 Id. P 97. \n148 Id. P 97. \n149 Id. P 99."},{"page":35,"startToken":11449,"endToken":11799,"text":"35 \n \nsupport the premise of its Proposal that New Large Loads pose a greater threat to those values than \nother kinds of load.  There is a risk of resource adequacy implications for all loads (regardless of \nindividual size or date of interconnection).  \nPJM claims that “[t]he IRAS framework does not single out New Large Loads … because \nthey are new or large.”150  But the Proposal demonstrates just the opposite:  it defines New Large \nLoads exclusively based on their date and size.  PJM also argues that Large Loads can “pose[] \nspecific challenges to transmission system operation.”151  To be sure, new data centers may be \nlarge and fast-growing, as well as politically salient.  But the question for purposes of the \ndiscrimination inquiry is not whether Large Loads are different; they are indisputably larger, as a \ncategorical matter.  The question is whether they are different in a way that is “material to the \ninquiry at hand.”152  Because PJM has not shown that 50 megawatts of large load has a different \nimpact on reliability than 50 aggregate megawatts of small load, PJM’s proposed differential \ntreatment as to interruptible service and curtailment is not warranted. \nPJM also points to a recent Commission decision accepting a proposal by Southwest Power \nPool (“SPP”) to add a new large load service product dubbed Conditional High Impact Large Load \nService (“CHILLS”).153  The analogy between IRAS and CHILLS does not hold.  As a threshold \nmatter, “participation in CHILLS is entirely voluntary.”154  CHILLS provides “an accelerated path \ntowards transmission service” for large loads that could not yet obtain firm transmission service \n \n150 PJM Proposal 99. \n151 Id. at 96 (citation omitted); see also id. at 99 (contending that Large Loads “are the cause of the recent \nreliability shortfall” because of “their inherent concentration of demand and the rapidity at which their \ncumulative demands have grown”). \n152 Transmission Agency of N. Cal. v. FERC, 628 F.3d 538, 549 (D.C. Cir. 2010). \n153 Southwest Power Pool, Inc., 195 FERC ¶ 61,196, P 84 (2026); see PJM Proposal 97.   \n154 195 FERC ¶ 61,196, at P 103."},{"page":36,"startToken":11799,"endToken":12217,"text":"36 \n \nbecause network upgrades were not yet in place.155  And for such loads, it offers “a new non-firm \ntransmission service” that “is subject to curtailment and interruption on a non-discriminatory basis \nwhen the transmission system is constrained or under emergency or other unforeseen \nconditions.”156  In approving CHILLS, the Commission emphasized “key limitations … such as \nthe interim nature of the service” and its “maximum term of seven years.”157  By contrast, the \nIRAS program is not voluntary, it is not interim, and it carries no maximum term.  Nor is it \nconsistent with the nature of non-firm transmission service, which is classified and compensated \ndifferently.158  Instead, IRAS imposes an involuntary curtailment condition on certain large firm \nNetwork Integration Transmission Service (“NITS”) customers—without any expiration date and \nbefore even relying on Pre-Emergency Load Management Reductions or emergency measures.159 \nPJM also suggests that the Proposal does not unduly discriminate against New Large Load \ncustomers because they will still be served by LSEs taking NITS and “will—like other NITS \ncustomers—have their transmission service curtailed after non-firm customers.”160  But the fact \n \n155 Id. P 41.   \n156 Id. P 7, 10. \n157 Id. P 84.   \n158 See PJM Interconnection, 195 FERC ¶ 61,209, P 551 (2026) (approving PJM’s Interim NITS service \nproduct as just and reasonable because it was “consistent with … the nature of the transmission service as \na non-firm transmission service for which Eligible Customers do not pay generation capacity charges”). \n159 PJM also argues that Large Loads can be treated “as a separate category” consistent with a recent \nCommission order to show cause.  See PJM Proposal 96 & n.259 (citing June 2026 Order to Show Cause, \n195 FERC ¶ 61,211, P 50 (2026)).  The order to show cause responded to an advance notice of proposed \nrulemaking (ANOPR) addressing “urgent challenges associated with providing the transmission service \nneeded to serve the ongoing influx of large loads while maintaining reliability and affordability.”  Id. P 1.  \nThat context was different, because it recognized that large loads may present distinct transmission-service \nissues with respect to reliability.  Id. P 1.  The Commission did not make any merits determination on a \nspecific proposal, and it expressly did not address the appropriate treatment of large loads with respect to \nthe need for generation capacity.  To the contrary, the Commission acknowledged that resource adequacy \nwas “not expressly contemplated in the ANOPR” and simply ordered PJM to submit a future informational \nreport on resource adequacy.  Id. PP 102, 104. \n160 PJM Proposal 94, 100."},{"page":37,"startToken":12217,"endToken":12622,"text":"37 \n \nthat Eligible New Large Loads retain their status as “NITS customers” is beside the point.  The \nproblem is not how New Large Loads are labeled or even how they are treated vis-à-vis non-firm \ncustomers.  It is that they are subject to IRAS based on size and in-service date—in other words, \nsubject to curtailment before other NITS customers unless they incur the unique burden of bringing \ntheir own new capacity—even though those characteristics do not correlate to the loads’ relative \nimpacts on the stated objectives of IRAS. \nC. \nPJM’s Proposal Unduly Discriminates Based On Resource Vintage \nThe IRAS proposal also is unduly discriminatory because it treats existing and new \ncapacity resources differently.  Under the Proposal, if “a New Large Load does not want to provide \nIRAS, it needs to contract with new capacity that meets the BYONC gating criteria, which are \ndesigned to ensure the capacity is actually new and not repackaged and will provide capacity over \nat least 10 years.”161  “[C]apacity already on the system would not fall within the definition of \nBYONC.”162  Yet PJM says nothing to justify why “new” capacity is different from existing \ngeneration when existing and new resources provide the very same call option for capacity, energy, \nand ancillary services products.163  It should not matter whether a Large Load customer contracts \nwith a new gas plant or contracts with an existing plant; in both cases, the grid will benefit from \nmegawatts in the same way. \n \n161 Id. at 23; see id. at 50 (“PJM is proposing to allow New Large Loads to remove themselves—in whole \nor in part—from the MW eligible for IRAS where such loads bring new capacity to the PJM region”). \n162 Id. at 52; see id. (“the capacity must be new to the PJM system, not just new to the capacity market”).   \n163 BYONC resources must meet specific eligibility requirements described in PJM’s Proposed Tariff, \nAttachment DD-4, § VI(b).  They must (i) “be supported by one of” (1) a new-build generation resource; \n(2) incremental capacity created through an uprate of Existing Generation Capacity Resources; (3) \nincremental capacity created by utilization of Surplus Interconnection Service; (4) repowering of a \ndeactivated generation resource that deactivated prior to April 10, 2026; (5) incremental capacity created \nby an Existing Generation Capacity Resource’s change to a more efficient fuel type; or (ii) be Demand \nResources or DER Capacity Aggregation Resources that meet specified conditions."},{"page":38,"startToken":12622,"endToken":13000,"text":"38 \n \nIndeed, the general rule is that “new entrants and existing suppliers” should be \n“compensated comparably,” absent a demonstration why they are not comparable for relevant \npurposes.164  As the D.C. Circuit has explained, any proposal that differentiates between new and \nexisting generators must demonstrate “how” new and existing suppliers “are not similarly situated \nand in what respects the reasons are material” to the proposal.165   \nThus, the Commission has rejected a PJM proposal to provide price assurance to new entry \nprojects because it failed to adequately serve PJM’s twin objectives—to “attract new entry when \nneeded” but also “to retain existing efficient capacity.”166  The Supreme Court in Hughes v. Talen \nacknowledged the Commission’s reasoning:  “Both new entry and retention of existing efficient \ncapacity are necessary to ensure reliability and both should receive the same price so that the price \nsignals are not skewed in favor of new entry.”167  Applying similar principles, the Commission \nalso rejected PJM’s recent proposal to implement a framework for computing Effective Load \nCarrying Capability (“ELCC”) for certain supply resources.168  The proposal included a “transition \nmechanism” that resulted in favorable treatment for resources that entered the market earlier, \nwhich the Commission rejected as undue discrimination. 169   The Commission reasoned that \nexisting resources and newer resources “are similarly situated” because they “share a common set \n \n164 PJM Interconnection, LLC, 128 FERC ¶ 61,147, P 103 (2009); see id. n. 60 (citing 1 Alfred E. Kahn, \nThe Economics of Regulation 140 (1970), for the proposition that “prices for new and existing customers \nshould be the same”). \n165 New England Power Generators Ass’n, Inc. v. FERC, 881 F.3d 202, 213 (2018) (granting petitions for \nreview that challenged a provision allowing new suppliers to lock in a guaranteed auction price for seven \nyears, as well as a provision requiring a locked-in supplier to offer capacity as a price-taker). \n166 PJM Interconnection, LLC, 128 FERC ¶ 61,157, P 102. \n167 Hughes, 578 U.S. at 158 (quoting PJM, 128 FERC ¶ 61,157). \n168 PJM Interconnection, LLC, 175 FERC ¶ 61,084, P 5 (2021).  In the Commission’s order, ELCC \nresources were defined as resources that are unable to maintain output at a stated capability continuously \non a daily basis without interruption. \n169 Id. P 8."},{"page":39,"startToken":13000,"endToken":13364,"text":"39 \n \nof operational characteristics and are reasonably homogeneous with respect to their impact on \nsystem resource adequacy.”170  Nonetheless, the Commission explained, PJM’s Proposal would \n“unreasonably discount the capacity value of ELCC Resources that enter the market at a later date, \ndespite the fact that these resources are likely to provide similar capacity value to existing ELCC \nresources”—thus demonstrating undue discrimination.171 \nThe IRAS proposal similarly fails to demonstrate “how” new and existing resources “are \nnot similarly situated and in what respects the reasons are material” to the proposal.172  PJM’s \nstated objective through IRAS is to “restor[e] resource adequacy” by assuring sufficient capacity \nto serve load, especially New Large Loads.173  Yet PJM would treat two generating resources \ndifferently based on whether they are “new,” even if they can provide the exact same capacity.  \nThat is contrary to the straightforward principle that “[b]oth new entry and retention of existing \nefficient capacity are necessary to ensure reliability.”174 \nThe practical effect and design of PJM’s Proposal underscore that it intentionally disfavors \ncapacity that would aid the system simply because it is not BYONC-qualifying new capacity.  In \npractice, the Proposal will disadvantage existing resources in a manner that is self-reinforcing:  \nexisting resources are excluded from providing capacity that protects against IRAS, making it less \nlikely that those resources will contract with a New Large Load, depriving them of a significant \nsource of revenue, and making it more likely they will exit the market and increase the resource \n \n170 Id. P 108. \n171 Id. P 17 (emphasis added); see id. P 108 (“The transition mechanism would discriminate between \nresources in a class based on vintage despite the fact that all resources within a class bear equal \nresponsibility for the decrease in the capacity contribution of their ELCC Class.”). \n172 New England Power Generators, 881 F.3d at 213 (granting petitions for review that challenged a \nprovision allowing new suppliers to lock-in a guaranteed auction price for seven years, as well as a provision \nrequiring the locked-in suppliers to offer capacity as a price-taker). \n173 PJM Proposal 17. \n174 Hughes, 578 U.S. at 158 (citing PJM Interconnection, LLC, 128 FERC ¶ 61,275 (2009))."},{"page":40,"startToken":13364,"endToken":13646,"text":"40 \n \nadequacy shortfall.175  As a matter of design, PJM’s Proposal also would exclude from the demand \ncurve the megawatts of New Large Loads that have not entered into BYONC arrangements or do \nnot have RBP UCAP MW.176  PJM would seek to artificially “protect residential customers from \ncapacity price increases resulting from the effects of New Large Loads”177 by including New Large \nLoads in the VRR Curve only where they have capacity arrangements, so that “the impact of \nincluding such load in the demand curve is counterbalanced by the inclusion of a commensurate \namount of additional Capacity Resources that are added to the supply curve.”178   \nThe result is a design that intentionally blunts the market signals that would have \nencouraged new entry and the retention and cultivation of existing resources, replacing those \nsignals with a pathway to encourage only BYONC-qualifying capacity.  That design privileges \nnew resources while discouraging other resources, even though those others are likewise capable \nof providing the very same reliability value through megawatts.  That provides still more evidence \nthat PJM’s Proposal unduly discriminates and should be rejected.  Even “a difference in treatment \notherwise justified” (which the vintage distinction is not) “might be less so if it had an \nanticompetitive impact.”179   \n \n175 See pp. 51-52, infra (further discussing this problem). \n176 PJM Proposal 109; see id. at 110-111 (justifying this exclusion based on “commitment of New Large \nLoads to cover their own energy and capacity needs”). \n177 Id. at 23-24. \n178 Id. at 115. \n179 Town of Norwood v. FERC, 202 F.3d 392, 404 (1st Cir. 2000) (“the agency might be faulted if it declined \neven to inquire into a well-supported claim of this kind”)."},{"page":41,"startToken":13646,"endToken":13963,"text":"41 \n \nIII. \nThe Commission Must Reject PJM’s Proposal Because Market Design Flaws Make \nThe Proposal Unjust And Unreasonable \nUnder Section 205 of the FPA, PJM bears the burden to demonstrate both that its proposed \ntariff revisions are not unduly discriminatory and that they are “just and reasonable.” 180  To \nevaluate whether the tariff can be approved as just and reasonable, the Commission must engage \nin reasoned decision making,181 including by “examin[ing] the relevant data and articulat[ing] a \nrational connection between the facts found and the choice made.”182   \nThe Proposal fails that test on several grounds.  First, curtailing New Large Load before \ncalling on emergency resources is irrational and detrimental to proper energy price formation and \nreliability.  Second, excluding New Large Load from the VRR Curve used in RPM Auctions to the \nextent that the load lacks sufficient BYONC (or Allocated RBP UCAP MW) will substantially \nundermine RPM’s operation and harm the capacity market and customers, reflecting the overall \neconomic irrationality of the Proposal and its inconsistency with the design of the market.  Third, \nthe Proposal unreasonably fails to allow any qualifying BYONC to be replaced by other qualifying \nBYONC and unreasonably limits the resources that qualify as BYONC to resources that cleared \nan auction for the first time in the Base Residual Auction for certain delivery years rather than in \nany auction for those years.  In explaining those points below, Constellation cites and relies on the \naccompanying September 3, 2026 affidavit of Aaron T. Patterson (which is attached to this filing \nas Appendix A). \n \n180 16 U.S.C. §§ 824d(a)-(e), 824e(a); Advanced Energy Management Alliance v. FERC, 860 F.3d 656, 662 \n(D.C. Cir. 2017). \n181 TransCanada Power Marketing Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. 2015). \n182 West Deptford Energy, LLC v. FERC, 766 F.3d 10, 17 (D.C. Cir. 2014) (citation omitted)."},{"page":42,"startToken":13963,"endToken":14324,"text":"42 \n \nA. \nPJM’s Proposal To Curtail New Large Load Prior To Calling On Emergency \nResources Is Unjust And Unreasonable \nWhen faced with a potential or actual capacity shortage, PJM currently undertakes a \ncascading series of emergency actions that are aligned with NERC Energy Emergency Alert Level \nclassifications (EEA1 through EEA3).  PJM proposes to place IRAS “at the beginning of PJM’s \nactions” in the event of an EEA1 situation 183 —meaning that an IRAS Action would be \nimplemented to reduce load prior to calling on Pre-Emergency Load Management Reductions.184  \nIn other words, “while IRAS and Pre-Emergency Load Management Reductions would both be \ncategorized as EEA1 actions, … PJM will generally call on IRAS before Pre-Emergency Load \nManagement Reductions to address an Emergency.”185 \nPJM’s Proposal to call on IRAS prior to Demand Response is not just or reasonable.  The \nbedrock principle of least-cost economic dispatch ordinarily calls for using available resources in \nincreasing order of marginal cost, which maximizes the total social surplus for all market \nparticipants.186  Although emergency conditions may alter certain dispatch priorities, they do not \neliminate the benefits of taking less costly actions before more costly actions of materially equal \nreliability.187  By contrast, deploying higher-cost emergency actions before lower-cost actions of \n \n183 PJM Proposal 22; see id. at 80, Fig. 2 (placing “IRAS Large Load reduction” prior to “Pre-Emergency \nDR” in the chronology of PJM emergency procedures). \n184 Pilong Affidavit ¶ 20; see id. ¶ 26 (“In real-time, PJM Dispatch will deploy Interim Resource Adequacy \nService Actions before Pre-Emergency Load Management Reduction Actions.”).  Pre-Emergency Load \nManagement Reduction Actions are the final step in EEA1, taken just before Emergency Load Reduction \nAction, which triggers an escalation to EEA2.  PJM Manual 13, at pp. 82-83.   \n185 PJM Proposal 82.  PJM proposes to revise its Tariff to define an Interim Resource Adequacy Service \nAction as an Operating Instruction “to reduce load prior to calling on Pre-Emergency Load Management \nReductions after determining that economic real-time supply may not be sufficient to maintain reserves to \nmeet applicable Reserve Requirements and/or Interconnection Reliability Operating Limits within \nprescribed limits and prevent cascading outages.”  PJM Proposal 84 n.224. \n186 Patterson Affidavit ¶ 11. \n187 Id. ¶ 12."},{"page":43,"startToken":14324,"endToken":14597,"text":"43 \n \nequivalent effect “unnecessarily increases the total costs borne by market participants and reduces \ntotal surplus.”188   \nAs a result, “during emergency conditions PJM should seek to take lower cost actions \nbefore it takes higher cost actions if possible” and “should design its emergency action protocols \nand emergency action deployment order accordingly.” 189  Prior to its IRAS proposal, PJM’s \napproach aligned with those principles:  for instance, PJM represented in an August 2025 \npresentation that an effective Operating Reserve Demand Curve “should ensure that 1) all more \ncost-effective actions are taken prior to engaging more expensive emergency procedures,” and “2) \nthat those costs are made transparent to the market.”190   \nYet PJM now proposes to curtail IRAS load before calling on Demand Response, which \nblatantly violates the core least-cost dispatch principle because curtailment of IRAS load is likely \nto be significantly more costly than Demand Response.191  Loads offering Demand Response \nrepresent a self-selected population that has voluntarily agreed to curtail in response to PJM \ninstruction in emergency conditions, in exchange for compensation as capacity resources in the \nRPM Auction and a minimum dispatch payment per MW-hour of curtailment when deployed.192  \nThose loads have already weighed their own assessment of interruption costs—from business \ndisruption or similar harms—against an established compensation scheme and determined that the \ntrade-off is economically beneficial to them.193  By contrast, Eligible New Large Loads that would \n \n188 Id. \n189 Id. \n190 PJM, Operating Reserve Demand Curves at 14, https://www.pjm.com/-/media/DotCom/committees-\ngroups/task-forces/rcstf/2025/20250813/20250813-item-03---operating-reserve-demand-curves.pdf \n(last \nupdated Aug. 13, 2025). \n191 Patterson Affidavit ¶ 14. \n192 Id. ¶ 15. \n193 Id."},{"page":44,"startToken":14597,"endToken":14884,"text":"44 \n \nbe subject to IRAS have not made such a choice.  Loads subject to IRAS may include customers \nthat have not elected Demand Response precisely because their own interruption costs are too high \nor their operating characteristics prevent them from meeting the notice and response time required \nto provide Demand Response.194  By reducing IRAS load before calling on customers that have \nvoluntarily offered load reductions, PJM would intentionally and unnecessarily prioritize higher-\ncost over lower-cost actions—contrary to fundamental principles of economic and market \nrationality.195 \nPJM has not pointed to any reliability or resource adequacy benefit that would justify that \nunreasonable result.  In fact, IRAS curtailments would be implemented by EDCs rather than \ndirectly by PJM, and the manner in which curtailment is physically implemented would be left to \nthe States, making physical performance in response to PJM instruction less certain and less visible.  \nBy contrast, Demand Response resources are deployed directly in response to PJM instruction and \nhave undergone a rigorous accreditation process to verify that they can perform as required; they \nalso are subject to testing and performance measurement and can be penalized for \nnonperformance.196   \nFor that reason, too, PJM’s Proposal to prioritize curtailment of IRAS is fundamentally \nirrational.  PJM assumes that IRAS is effectively a reliable capacity resource without any PJM-\noverseen accreditation or performance assurance whatsoever.   \nPJM contends that its sequence is rational on the ground that engaging Pre-Emergency \nLoad Management before IRAS “would reduce the incentive for New Large Loads to bring new \n \n194 Id. ¶ 17. \n195 Id. ¶ 18. \n196 See generally RAA Schedule 9.2, available at https://agreements.pjm.com/raa/43707; PJM Manual 18, \navailable at https://www.pjm.com/-/media/DotCom/documents/manuals/m18.ashx."},{"page":45,"startToken":14884,"endToken":15184,"text":"45 \n \ncapacity to the system, as they would be insulated by the Demand Resource capacity products.”197  \nMarket incentives point the opposite way:  placing properly compensated voluntary load reduction \nahead of involuntary load reduction in the hierarchy of emergency actions will support the efficient \nfunctioning of the PJM energy market, which will in turn provide the market price signals \nnecessary to stimulate the addition of new resources when needed. 198  In any event, PJM’s \npurported rationale is not sufficient to justify sequencing a less economically rational and \npotentially less reliable option above voluntary, accredited Demand Response during a capacity \nshortage.   \nPJM also has suggested that deploying Demand Response prior to IRAS would reduce the \neconomic incentive for customers to offer Demand Response199—but that concern is misplaced.  \nDemand Response receives both a capacity payment and a per-MWh payment for deployment.  In \ncontrast, PJM proposes that IRAS would receive no capacity payment; for deployment, PJM \nproposes a rate for IRAS of no more than 50 percent of the capacity Non-Performance Charge \nRate and potentially far less than that amount.200  The result is an estimated payment around $5,000 \nper MWh of curtailment for Demand Response, compared to $1,500 per MWh of curtailment for \nIRAS.201  Given those “starkly different economics,”202 a significant amount of load would likely \nremain willing to elect to provide voluntary Demand Response. \n \n197 PJM Proposal 80.  \n198 See, e.g., Energy Price Formation, FERC, https://www.ferc.gov/industries-data/electric/electric-power-\nmarkets/energy-price-formation  (last updated June 17, 2020) (when “actions taken to avoid reserve \ndeficiencies are not priced appropriately … , the price signals sent when the system is tight will not incent \nappropriate short- and long-term actions by resources and load”). \n199 PJM Proposal 80. \n200 Id. at 102. \n201 Patterson Affidavit ¶ 17. \n202 Id."},{"page":46,"startToken":15184,"endToken":15502,"text":"46 \n \nB. \nPJM’s Proposal To Exclude New Large Load Without Sufficient BYONC \nFrom The Demand Curve Used In RPM Auctions Is Unjust And Unreasonable  \nPJM also proposes to exclude New Large Load from the VRR Curve used in RPM Auctions \nto the extent that the load lacks sufficient BYONC (or Allocated RBP UCAP MW).203  That \nexclusion is unjust and unreasonable because it will substantially undermine the RPM’s structural \nintegrity, removing actual demand without removing a matching amount of accredited capacity (as \nPJM does with the Fixed Resource Requirement option).  That will harm long-term resource \nadequacy, the capacity market, and customers’ pocketbooks by muting the price signals that are \nnecessary to encourage new entry and retain existing resources.  Indeed, this aspect of the Proposal \nhighlights the degree to which the Proposal is inconsistent with the market’s design and \nundermines the RPM’s ability to attract and retain market-based supply—thereby exacerbating an \nexisting negative spiral that PJM itself has identified as a serious threat.204 \nUnder normal circumstances, new load growth would be reflected in the RPM demand \ncurve, which in turn would send a market signal that additional supply is needed and that existing \nsupply should be retained.205  PJM proposes to instead exclude New Large Loads from the demand \ncurve to the extent that they lack arrangements with sufficient BYONC.  The result is that no \ndemand signal will be sent to the market in connection with any New Large Load that enters \nwithout sufficient BYONC.  If New Large Load does contract with sufficient new capacity to avoid \nIRAS, PJM proposes to add that load to the VRR Curve but require a commensurate quantity of \nBYONC to participate in RPM Auctions as a price taker (i.e., at an offer of $0/MW) for ten \n \n203 PJM Proposal 109.  The exclusion would begin with the 2029/2030 Delivery Year.  See id. \n204 Patterson Affidavit ¶ 44. \n205 Id. ¶ 31."},{"page":47,"startToken":15502,"endToken":15870,"text":"47 \n \nconsecutive Delivery Years, regardless of whether the load stays on the system.206  PJM labels that \n“an effectively price-neutral outcome” that offsets additional demand by supply priced at zero.207   \nThus, whether New Large Load contracts with BYONC or enters without it, the RPM will \ncreate no meaningful price signal that incremental supply is needed to meet new load, no matter \nhow substantial the need for new supply to serve that load may be.208  Those features of PJM’s \nProposal will render the RPM fundamentally incapable of accurately reflecting a need for capacity \nto support demand from New Large Load, 209 in violation of “the first principles of capacity \nmarkets.”210 \nPJM’s Proposal incorrectly assumes that IRAS itself will resolve the resource adequacy \nneed created by the entry of the excluded Large Load. 211   In other words, PJM’s Proposal \ncontemplates that excluding Eligible New Large Load from the demand curve is functionally \nequivalent to incorporating that load into the demand curve along with an equivalent amount of \ncapacity.212  That is an unjust, unreasonable, and indefensible market maneuver.  IRAS is not an \naccredited capacity resource that will reliably offset the incremental reliability requirement of \nEligible New Large Loads.213  It is, at best and by PJM’s own label, a “supplemental capacity \n \n206 PJM Proposal 55, 57-58.  Requiring BYONC to offer into the RPM at $0/MW disconnects the actual \nprice of capacity providing BYONC, as secured via bilateral arrangements entered into outside of the RPM, \nfrom the price of that capacity as reflected in the market—meaning that BYONC cannot send a reliable \nprice signal as to the need for or cost of new capacity.  Patterson Affidavit ¶ 30. \n207 PJM Proposal 58. \n208 Patterson Affidavit ¶¶ 30-31. \n209 Id. \n210 ISO New England Inc., 162 FERC ¶ 61,205 P 21 (2018) (“A capacity market should facilitate robust \ncompetition for capacity supply obligations, provide price signals that guide the orderly entry and exit of \ncapacity resources, result in the selection of the least-cost set of resources that possess the attributes sought \nby the markets, provide price transparency, shift risk as appropriate from customers to private capital, and \nmitigate market power.”). \n211 Patterson Affidavit ¶ 32. \n212 Id. \n213 Id. ¶ 34."},{"page":48,"startToken":15870,"endToken":16187,"text":"48 \n \nproduct.”214  Nor is IRAS a customer-desired solution; rather, it imposes a mandatory interruptible \nservice on customers without their election.   \nThe problems with PJM’s Proposal to exclude certain New Large Load from the demand \ncurve do not end there.  PJM’s Proposal further specifies that New Large Loads without BYONC \nshould be excluded from the RPM curve “regardless of whether PJM is experiencing a shortfall \nthat triggers IRAS in the relevant Delivery Year.”215  The practical result is that in delivery years \nwhen IRAS is not triggered, the New Large Load excluded from the demand curve would be \nbacked by no resources at all on the capacity side.216  In that circumstance, the RPM is distorted \neven further, because the excluded New Large Load will be physically present and will have the \nsame service priority as other loads, but PJM’s capacity market “will simply pretend it is not \nthere.”217 \nPJM contends that including Eligible New Large Load in the demand curve “would fail to \nrecognize that New Large Loads have committed to ‘build, bring, or buy the new generation \nresources and electricity needed to satisfy their new energy demands,’” which PJM asserts is \nconsistent with the Ratepayer Protection Pledge. 218  But alignment with the Pledge is not a \nsubstitute for necessary economic signals that are relied on to produce properly functioning \ncapacity markets.  If approved, PJM’s exclusion proposal would force the RPM to permanently \nreflect a fictional reliability outcome—one that is necessarily different from, and less demand-\n \n214 PJM Proposal 74.  That is distinct from a “Capacity Resource,” which is defined in the PJM tariffs as a \nresource that has met the qualification requirements to participate in the PJM capacity market.  See, e.g., \nPJM Glossary, https://www.pjm.com/Glossary.aspx#index_C, (last accessed September 2, 2026).  \n215 PJM Proposal 110. \n216 Patterson Affidavit ¶ 33. \n217 Id. \n218 PJM Proposal 110 (citation omitted)."},{"page":49,"startToken":16187,"endToken":16557,"text":"49 \n \nintensive than, the actual on-the-ground resource adequacy situation.219  Put another way, PJM’s \nProposal would create the illusion that no net New Large Load demand exists on the system, even \nif there is substantial need for new supply to serve New Large Load.220 \nThat outcome is directly contrary to PJM’s own stated objectives.  In a January 2026 \ndecisional letter, the PJM Board identified the objective of providing “the appropriate price signals \nto support the timely development of new capacity resources” and ensuring that the markets “retain \nstructural integrity during the pendency of this review and beyond.”221  Indeed, the PJM Board \npreviously specified that its proposal did not suggest “remov[ing]” new large load “from the \ncapacity market,” 222  as doing so would “result in large new loads avoiding capacity costs \naltogether, with those costs shifted to existing customers.”223  PJM reversed course, however, and \nhas now proposed to ignore actual market signals and rely instead on a purposefully skewed \nrepresentation of demand.  Doing so would erode the investor confidence necessary to ensure \nresource adequacy at just and reasonable rates224 by blunting the signal for existing resources to \nremain in and new resources to enter the capacity markets, thus intensifying the market stagnation \n \n219 Patterson Affidavit ¶¶ 36-37. \n220 Id. ¶ 38. \n221 Jan. 16 Ltr. at 3, 5; id. at 7 (recognizing that PJM’s markets must “deliver clear and transparent price \nsignals regarding the resources needed to maintain grid reliability”), available at https://www.pjm.com/-\n/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-\nthe-cifp-process-large-load-additions.pdf. \n222 Id. at 5.  \n223 Id.  Likewise, in a May 6 white paper addressing reliability and market design, PJM reinforced that “the \nefficacy of a competitive market relies on its ability to send accurate price signals that reflect the true state \nof the system,” and that only “[w]hen those signals align with physical reality” will “the market effectively \ncoordinate[] entry and exit.”  PJM, Powering Reliability Through Market Design: Addressing Rising \nDemand and Constrained Supply, and Stimulating Investment to Support Durable Reliability, at 11, \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-\nreliability-through-market-design.pdf (last updated May 6, 2026). \n224 ISO New England Inc., 162 FERC ¶ 61,250 at P 21."},{"page":50,"startToken":16557,"endToken":16883,"text":"50 \n \nthat PJM has identified as a significant detriment to stimulating sufficient investment to support \ndurable reliability.225 \nFor all of those reasons, exclusion of certain load from the demand curve reflects economic \nirrationality that is fundamentally inconsistent with the Commission’s objectives. 226   More \nspecifically, the Commission has recognized that capacity-market rules may be unreasonable when \nthey override and conflict with economic rationality in the market. 227   In one example, the \nCommission struck down provisions of PJM’s tariff as unjust, unreasonable, and unduly \ndiscriminatory because subsidies paid outside the RPM allowed certain resources to “reduce the \nprice of their offers into capacity auctions below the price at which they otherwise would offer.”228  \nThe Commission reasoned that the relevant tariff provisions “fail[ed] to protect the integrity of \ncompetition in the wholesale capacity market against unreasonable price distortions and cost shifts \ncaused by out-of-market support.”229  Although IRAS involves a different mechanism, the same \nprinciple applies.   \nFurther, the RPM-related aspects of IRAS are unjust and unreasonable because they are \nfundamentally incompatible with the basic market design of a capacity auction.  As the \nCommission has explained, the RPM was designed to “creat[e] accurate price signals to incent \n \n225 Patterson Affidavit ¶ 47; see Powering Reliability Through Market Design at 6 (describing a “Credibility \nTrap” that occurs when “high scarcity prices” that are economically necessary to signal the need for \ninvestment become … “the triggers [for governmental intervention] that undermines [the credibility of \nthose same prices],” leading investors to “discount revenue signal” and capital to “stay[] on the sidelines”), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20260520/20260520-\npowering-reliability-through-market-design (last updated May 20, 2026). \n226 See 18 CFR § 2.22(b)(3) (“Transmission pricing should promote economic efficiency”); ISO New \nEngland Inc., 162 FERC ¶ 61,205, at ¶ 21. \n227 See Calpine Corp. v. PJM Interconnection, LLC, 163 FERC ¶ 61,236 (2018), reh’g denied, 171 FERC \n¶ 61,034 (2020).   \n228 Id. P 2. \n229 Id. P 150."},{"page":51,"startToken":16883,"endToken":17239,"text":"51 \n \nnew generation.  It is designed to encourage market signals, not interfere with them.”230  Not only \ndoes excluding New Large Load without BYONC from the demand curve and forcing BYONC to \nbe a $0/MW price-taker interfere with RPM market signals, it actively and intentionally suppresses \nthe ability of RPM to incentivize capacity and retain existing capacity.  Through these two aspects \nof the IRAS proposal, PJM is essentially abandoning the fundamental theory underlying RPM (and \ncapacity markets generally) and asserting that an extra-market intervention is needed to incentivize \nnew capacity.  But on a basic level, PJM has not adequately established through its proposal that \nRPM’s market-based ability to incentivize new capacity is broken.  And even had PJM made that \nshowing, a just and reasonable proposed fix for that issue would be to work within the current \nmarket—i.e., attempt to strengthen the signals that the RPM sends to incentivize capacity—rather \nthan actively working to weaken those signals through a capacity product that exists outside of the \nmarket and serves to further undermine its proper functioning. \nAs Mr. Patterson explains, these twin market-suppressing features of IRAS are “the latest \nin a series of recently-implemented or pending actions by PJM that will collectively destroy the \nability of RPM to meet the resource adequacy needs of PJM going forward,” unless the \nCommission takes action to reverse the trend.231  By creating one after another “special, high-value \ndiscriminatory pathways” for new capacity entry, PJM continues to gradually erode the incentive \nfor capacity resources to enter the market traditionally, via the RPM.232  When higher-priced, \nlower-risk pathways for new entry exist—such as through the proposed BYONC contracts—no \n \n230 PJM Interconnection, LLC, 117 FERC ¶ 61,331, at P 69 (2006); see id. P 68 (detailing “the Commission’s \nconcerns that appropriate price signals are available to provide incentives to construct facilities necessary \nfor regional reliability”); see also PJM Interconnection, LLC, 167 FERC  ¶ 61,029, at ¶ 16 (2019) (VRR \nCurve designed to “produce accurate market signals that will encourage appropriate capacity investment \nand achieve an adequate level of reliability”). \n231 Patterson Affidavit, Part IV & ¶¶ 41, 43.  \n232 Id. ¶ 45."},{"page":52,"startToken":17239,"endToken":17504,"text":"52 \n \nrational capacity provider will enter via the RPM, which renders such resources “new” for only \none year, and afterwards locks them out of the ability to use any subsequently created, higher-\nvalue, new-only resource pathway.233  Instead, the rational approach becomes to hold out for the \nnext capacity-related intervention by PJM—or, for existing resources, to exit the market entirely.234  \nMeanwhile, each special extra-market entrance pathway that results in new capacity being bid into \nthe RPM as a price-taker artificially lowers the clearing price for capacity, depressing market prices \nfor existing resources and further suppressing the ability of the RPM to send the proper price \nsignals to incentivize new capacity and retain existing capacity, as originally intended.235  The \neconomic irrationality of this vicious cycle leads to “a market that is continually in a spiraling \ncrisis,” eroding long-run reliability.236 \nIn sum, the Commission should not endorse an economically irrational response to a \nresource adequacy problem, artificially and unreasonably shift system costs among participants, \nand mute market signals that would ordinarily feed demand.  Indeed, PJM has already told the \nCommission as much, by publishing a white paper describing the so-called “Credibility Trap” that \noccurs when providers of capacity lack confidence that the market will provide the compensation \nnecessary to support the entry or retention of that capacity.237  The Proposal is exactly the kind of \nintervention that would exacerbate that problem.  The Commission should reject that harmful \napproach as unjust and unreasonable. \n \n233 Id. ¶¶ 45-47.  \n234 Id. ¶¶ 47-48. \n235 Id. ¶¶ 42, 46, 51. \n236 Id. ¶ 50. \n237 Id. ¶ 44 (discussing PJM white paper)."},{"page":53,"startToken":17504,"endToken":17817,"text":"53 \n \nIV. \nIf the Commission Nonetheless Were To Accept PJM’s Unlawful Proposal, It Should \nCondition Acceptance On Certain Small Modifications \nThe Commission should reject the Proposal due to the defects described above.  If the \nCommission were to choose to accept the Proposal, however, the Commission should exercise its \nauthority to condition such acceptance on three small modifications identified below.   \nAs PJM acknowledges in its filing,238 the Commission may under certain circumstances \ncondition the acceptance of a Section 205 filing on modifications, as provided under the FPA and \nconsistent with NRG Power Marketing, LLC v. FERC.239  Modifications are acceptable if (1) the \npublic utility has consented to the modification, and (2) the modification does not transform the \nproposal into an entirely new rate scheme.240  Those preconditions are satisfied here because PJM \nhas expressly “consent[ed] to the Commission’s exercise of authority to modify” the Proposal \nconsistent with the principles above,241 and the specified modifications are technical issues that do \nnot transform the proposal or undermine “PJM’s overarching objectives.”242 \nA. \nIf Accepted, The Proposal Should Be Modified To Allow Any Qualifying New \nCapacity To Serve As A Bridge To Other New Capacity \nIf the Commission were to accept the Proposal, it should modify the Proposal to allow any \nqualifying BYONC to be replaced by other qualifying BYONC.  The proposed tariff revisions \nstate a rule that “BYONC that is in an arrangement with a New Large Load must remain in such \narrangement with that New Large Load unless and until the New Large Load is permanently out-\nof-service.”243  The Proposal specifies, however, that “the seller of the BYONC may replace its \n \n238 PJM Proposal 122. \n239 862 F.3d 108 (D.C. Cir. 2017); see PJM Proposal 122. \n240 NRG Power Marketing, 862 F.3d at 115. \n241 PJM Proposal 122. \n242 Id. \n243 Proposed Tariff, Attachment DD-4, § VII(e)."},{"page":54,"startToken":17817,"endToken":18097,"text":"54 \n \nBYONC obligation with a different BYONC” during the ten-year commitment period—but only \nfor “BYONC supported by a Demand Resource or DER Capacity Aggregation Resource.”244  \nDistinguishing between DR and other qualifying BYONC by failing to extend that replacement \nprovision to all qualifying BYONC, not just DR and DER Capacity Aggregation Resources, is not \njust and reasonable in this context. \nPJM’s own justification for allowing replacement of DR and DER Capacity Aggregation \nResources with other qualifying BYONC supports modifying the Proposal to allow replacement \nof any qualifying BYONC.  PJM explains that the replacement approach “provides New Large \nLoads a ‘bridge to power’ of near-term demand-supported capacity that is eventually replaced with \nnew generation as that supply comes online.” 245  It “increases commercial opportunities for \nBYONC without adversely affecting the region’s ability to address its capacity needs,” and it \nallows New Large Loads to “spur the development of additional capacity in a few years” while \nrelying on existing or different capacity in the meantime.246   \nThe same rationales would be equally served by allowing another type of BYONC to \nsupply the bridge.  For example, if a new generating facility was intended to support a New Large \nLoad but was delayed by two years, that load should be able to rely on an arrangement with other \nqualifying BYONC during those two years, with the intended facility later substituted for the \nremaining eight years.  That approach would provide a bridge to longer-term generation and \nincrease commercial flexibility, while still conforming to the IRAS premise that the New Large \nLoad’s capacity needs be supported by BYONC throughout the relevant timeframe.  It also would \n \n244 PJM Proposal 56-57. \n245 Id. at 57. \n246 Id."},{"page":55,"startToken":18097,"endToken":18470,"text":"55 \n \nconform with the general RPM principle that serves flexibility and reliability by allowing \nsubstitution of replacement capacity when intended resources are unavailable.247 \nB. \nIf Accepted, The Proposal Should Be Modified To Specify That BYONC \nIncludes Otherwise Qualifying Capacity Resources That Clear Any RPM \nAuction For 27/28, 28/29, And 29/30 \nIf the Commission were to accept the Proposal, it also should modify the Proposal to clarify \nthat qualifying BYONC is not limited to capacity resources that clear a Base Residual Auction for \n27/28, 28/29, or 29/30, but rather includes capacity resources that clear additional incremental \nauctions for those Delivery Years. \nSection VI(a)(i) of the proposed tariff states that “Capacity Resources that cleared an RPM \nAuction for the first time in the Base Residual Auction for the 2027/2028, 2028/2029, and \n2029/2030 Delivery Years may qualify as BYONC.”248  But the Base Residual Auction is not the \nonly auction that will occur for those Delivery Years; there also will be incremental auctions \nbetween a Base Residual Auction and the moment when the electrons begin to flow.249  There is \nno reason why Capacity Resources that cleared an incremental auction in the relevant time period \nshould not be treated the same way as Capacity Resources that cleared a Base Residual Auction in \nthe relevant time period for purposes of deciding whether those resources qualify as BYONC.  In \nfact, the Proposal itself seems to recognize the wisdom of that approach, as it describes the \n \n247 For example, PJM’s tariff allows sellers to submit buy bids for replacement capacity resource in the \nevent of “resource retirement, resource cancellation or construction delay,” or “any reason” causing the \n“need to purchase replacement Capacity Resources.”  Proposed Tariff, Attachment A, § 5.4(d); see also \nProposed Tariff, Attachment A, “Definitions – L-M-N” (defining “Locational UCAP” as unforced capacity \nsold to a Member “that previously committed capacity through an RPM Auction but now requires \nreplacement capacity to fulfill its RPM Auction commitment”). \n248 Proposed Tariff, Attachment DD-4, § VI(a)(i). \n249 PJM Proposal 113 n.300 (acknowledging existence of incremental auctions); see PJM Capacity Auction \nCalendar, \navailable \nat \nhttps://www.esaipower.com/capacity-market-auction-calendar/pjm-capacity-\nauction-calendar/ (calendar of base residual and incremental auctions)."},{"page":56,"startToken":18470,"endToken":18789,"text":"56 \n \nCapacity Resources that may qualify as BYONC in general terms, referring only to “RPM \nAuctions” and not specifically to the Base Residual Auction, and notes that multiple “Auctions” \ntake place:  “Given that New Large Loads are included in the RPM Auctions through the \n2028/2029 Delivery Year and eligible BYONC that previously cleared an RPM Auction through \nthe 2028/2029 Delivery Year was not on notice of this limitation, any eligible BYONC that is \noffered in RPM Auctions through the 2028/2029 Delivery Year can be procured by New Large \nLoads to avoid IRAS.”250  This point could easily be clarified by simply striking the words “the \nBase Residual Auction for” from Section VI(a)(i) of the proposed tariff, so that the provision \ninstead stated that “Capacity Resources that cleared an RPM Auction for the first time in the \n2027/2028, 2028/2029, and 2029/2030 Delivery Years may qualify as BYONC.” \nC. \nIf Accepted, The Proposal Should Be Modified To Include Incremental \nCapacity Created By An Energy Resource In The Definition Of BYONC \nPJM’s Proposal requires that generation and storage resources must meet certain \n“eligibility requirements” to qualify as BYONC, which are specified in the Proposed Tariff at \nSection VI(b).  Resources “must be supported by one of the following”:  (1) a new-build generation \nresource; (2) “incremental capacity created through an uprate of Existing Generation Capacity \nResources”; (3) incremental capacity created by utilization of Surplus Interconnection Service; (4) \nrepowering of a deactivated generation resource that deactivated prior to April 10, 2026; or (5) \nincremental capacity created by an Existing Generation Capacity Resource’s change to a more \nefficient fuel type.251  If the Commission were to accept the Proposal, it should modify requirement \n(2) above to include incremental capacity created by an Energy Resource that acquires Capacity \nInterconnection Rights through an Interconnection Request. \n \n250 PJM Proposal 115 n.302. \n251 Proposed Tariff, Attachment DD-4, § VI(b)(i)."},{"page":57,"startToken":18789,"endToken":19030,"text":"57 \n \nThe current language of the BYONC criteria covers “incremental capacity created by an \nuprate of Existing Generation Capacity Resources, but only to the extent such incremental capacity \nis created through an increase in such Generation Capacity Resource’s installed capacity and \nincrease in Capacity Interconnection Rights associated with that Generation Capacity \nResource.”252  As drafted, that language could be interpreted to exclude an energy-only resource \nseeking new capacity rights, because an energy-only resource would not yet be considered an \n“Existing Generation Capacity Resource.”   \nSuch exclusion would be unreasonable and inconsistent with PJM’s objectives.  An Energy \nResource that wishes to acquire Capacity Interconnection Rights, like a resource pursuing an \nuprate, must submit an Interconnection Request, proceed through PJM’s interconnection study \nprocess, and pay for any required network upgrades to accommodate its request.253  An Energy \nResource that requests capacity rights also provides incremental capacity in a manner materially \nindistinguishable from a Generation Capacity Resource that uprates its capacity.  Accordingly, the \nBYONC criteria should be expanded to encompass incremental capacity created by an Energy \nResource that acquires Capacity Interconnection Rights through an Interconnection Request.  \nV. \nConclusion \nThe Commission should reject all portions of PJM’s Proposal other than the proposal to \ncreate the Large Load Registry and, in the alternative, should condition acceptance on the \nmodifications described in this filing. \n \n \n \n \n \n \n \n \n252 Proposed Tariff, Attachment DD-4, § VI(b)(i)(2). \n253 See PJM Tariff, Part VIII, Subpart B, § 403(A)(1) (Generation Interconnection Request Requirements)."},{"page":58,"startToken":19030,"endToken":19178,"text":"58 \n \n \n \n \n \n \n       Respectfully submitted, \nBy:  /s/ Elaine J. Goldenberg \nCarrie Hill Allen \nSr. Vice President & Deputy General \n  Counsel \nJohn M. White \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \njohn.white@constellation.com \nChristopher A. Wilson \nVice President, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \nElaine J. Goldenberg \nMUNGER, TOLLES & OLSON LLP \n601 Massachusetts Avenue NW \n  Suite 500 E \nWashington, DC 20001 \n(202) 220-1100 \nElaine.Goldenberg@mto.com \n \nHenry Weissmann \nMUNGER, TOLLES & OLSON LLP \n350 South Grand Avenue, 50th Floor \nLos Angeles, CA 90071-3426 \n(213) 683-9100 \nHenry.Weissmann@mto.com \n \nTeresa Reed Dippo \nMUNGER, TOLLES & OLSON LLP \n560 Mission Street, 27th Floor \nSan Francisco, CA 94105 \n(415) 512-4000 \nTeresa.ReedDippo@mto.com \nCounsel for Constellation Energy Generation, LLC \n \nDated:  September 3, 2026"},{"page":59,"startToken":19178,"endToken":19258,"text":"59 \nCERTIFICATE OF SERVICE \nI hereby certify that I have on this 3rd day of September 2026 served a copy of the \nforegoing upon all parties on the service list in this proceeding in accordance with Rule 2010 of \nthe Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.  \nBy: /s/ Elaine J. Goldenberg  \nElaine J. Goldenberg \nMUNGER, TOLLES & OLSON LLP \n601 Massachusetts Avenue NW \n   Suite 500 E \nWashington, DC 20001 \n(202) 220-1100\nElaine.Goldenberg@mto.com"},{"page":60,"startToken":19258,"endToken":19260,"text":"Appendix A"},{"page":61,"startToken":19260,"endToken":19314,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n PJM Interconnection, L.L.C.:  \n205(d) Rate Filing: Proposal to Establish \nInterim Resource Adequacy Service & a \nLarge Load Registry to be effective \n10/12/2026 \n) \n) \n) \n) \n) \n) \n \n \n \nDocket No. ER26-3515-000 \n \n \n \nAFFIDAVIT OF \nAARON T. PATTERSON \nON BEHALF OF  \nCONSTELLATION ENERGY GENERATION, LLC \n \n \nSeptember 3, 2026"},{"page":62,"startToken":19314,"endToken":19699,"text":"1 \n \nI. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT \nA. QUALIFICATIONS \n1. \nMy name is Aaron T. Patterson.  I am a partner of The NorthBridge Group, Inc \n(“NorthBridge”).  NorthBridge is a consulting firm that provides economic and strategic advice to \nthe electric and natural gas industries.  My business address is 30 Monument Square, Concord MA \n01742. \n2. \nI joined NorthBridge in 2001.  Before that, I was an analyst at Lexecon, Inc. which I joined \nin 1996.  I have over 25 years of experience working with clients in the electric and natural gas \nindustries.  My electric industry business consulting work has focused on market design, \nenvironmental policy, finance, and mergers and acquisitions.  I received a Bachelor of Arts in \nEnvironmental Science and Public Policy from Harvard University, and a Master of Business \nAdministration from the Tuck School of Business at Dartmouth.  I have previously testified before \nthe Commission and have also submitted expert testimony and/or expert reports in proceedings \nbefore the U.S. Department of the Treasury, the Illinois Commerce Commission, the Public Utility \nCommission of Texas and the New York State Public Service Commission. \n3. \nA list of my past prepared testimony is provided as Attachment A.  \nB. BACKGROUND AND PURPOSE OF AFFIDAVIT \n4. \nOn August 13th, 2026, PJM Interconnection L.L.C (“PJM”) filed a set of proposed revisions \nto its tariff (“PJM’s Proposal”) at the Commission to establish a new Interim Resource Adequacy \nService (“IRAS”) that would be applicable to certain loads seeking to interconnect with the PJM \nsystem.1  PJM’s Proposal would require end-use loads with a peak load in excess of 50 Megawatts \n(“Large Loads”) that come online or add incremental demand on or after June 1, 2027 (“New \nLarge Loads”) to establish a “Bring Your Own New Capacity” (“BYONC”) arrangement with new \nentrant capacity or be allocated new entrant capacity from PJM’s proposed Reliability Backstop \nProcurement (“RBP”) in an amount equal to their load; or be required to provide IRAS during \ndelivery years where the PJM Reliability Pricing Model (“RPM”) clears short of its reliability \n \n1 PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C to Establish Interim Resource Adequacy \nService and a Large Load Registry to Address System Reliability to be effective 10/12/2026, Docket No. ER26-3515-\n000 (filed August 13, 2026) (the “PJM Proposal”)."},{"page":63,"startToken":19699,"endToken":20109,"text":"2 \n \nrequirement.  Loads required to provide IRAS would be subject to curtailment by their local \nElectric Distribution Company (“EDC”) when PJM issues a zonal instruction to curtail IRAS load \nunder North American Reliability Corporation (“NERC”) Energy Emergency Alert (“EEA”) 1 \nconditions, prior to any other emergency actions other than the curtailment of load taking non-firm \ntransmission service and the curtailment of non-firm interchange transactions.  PJM also proposes \nthat New Large Loads entering the market in the 2029/30 delivery year or later that do not enter \ninto BYONC arrangements or receive allocations of RBP supply sufficient to cover their load be \nexcluded from RPM demand unless and until they make sufficient BYONC arrangements, \nregardless of whether IRAS is triggered for a given delivery year or not. \n5. \nThe purpose of my affidavit is to assist the Commission in its decision-making process in \nevaluating and ultimately taking action on PJM’s Proposal by approving, not approving, or \nmodifying it.  My analysis focuses on four aspects of PJM’s Proposal: 1) the placement of IRAS \ncurtailments within the overall priority order of actions taken by PJM under emergency operating \nconditions, 2) the impact of IRAS curtailments on price formation in the PJM energy market, 3) \nthe exclusion of New Large Loads which do not bring new capacity from RPM demand, and 4) \nthe overall effect of the proposal on the viability of PJM Markets going forward coupled with its \nlong-term impacts on reliability and consumer costs. \nC. SUMMARY OF CONCLUSIONS \n6. \nI reach four primary conclusions in my assessment of PJM’s Proposal: \n7. \nFirst, PJM’s proposed placement of IRAS load curtailments near the front of the emergency \naction priority order and prior to calling upon Demand Response is economically inefficient and \nalso is likely to drive increased reliability risk during operations.  The Large Loads which are \nultimately forced to provide IRAS are likely to be those Large Loads for whom curtailment is \nrelatively costly and difficult.  Relying on such loads as the initial line of defense under emergency \nconditions will raise production costs, decrease total social surplus, and increase reliability risk.  If \nthe Commission accepts PJM’s IRAS proposal, it should require PJM to move IRAS curtailments \nback in the emergency action priority order to just in front of general manual load shed under \nEEA3 conditions. \n8. \nSecond, PJM’s Proposal does not include any provisions addressing energy price formation \nwhen IRAS load curtailments occur.  In order to maintain proper incentives to deploy all less costly"},{"page":64,"startToken":20109,"endToken":20535,"text":"3 \n \nresources and to invest in lower-cost resources that can provide energy (or demand response) under \nemergency conditions, energy prices during IRAS load curtailments should reflect the economic \ncost associated with the curtailment of IRAS loads.  The Commission should require PJM to \ndevelop and implement measures that effectuate this treatment. \n9. \nThird, PJM’s proposed exclusion from RPM demand of New Large Loads that do not offset \ntheir load with new capacity will compromise reliability and greatly limit the ability of the RPM \nto attract new supply going forward.  Excluding this load unless it has secured its own new capacity \ncreates a disconnect between the level of resource adequacy signaled by the RPM and the level of \nphysical resource adequacy that exists in reality.  As a result, new resources will not be provided \nwith a signal to enter via the RPM to serve the New Large Load, and existing resources will not \nbe provided with a similar signal to remain in the market.  This disconnect harms reliability \nbecause it effectively treats IRAS curtailment as a full substitute for capacity when in reality its \nperformance is likely to be different than and less visible or directly controllable than actual \naccredited capacity resources, and in any event will not even exist at all in delivery years where \nIRAS is not triggered.  The Commission should require PJM to include all New Large Load in \nRPM demand, regardless of whether it brings new capacity or not. \n10. Fourth, the BYONC mechanism of PJM’s IRAS Proposal along with the other issues \ndiscussed above and other recent and pending actions affecting the RPM will greatly reduce \ninvestor confidence in the RPM to the point where it will likely become non-viable as a pathway \nfor new entry and the retention of existing resources.  This outcome will force PJM to contend \nwith recurring resource adequacy shortfalls that cannot be resolved via the operation of the RPM \nbut rather must be resolved via further ad-hoc intervention.  The result, ultimately, will be reduced \nreliability and increased costs for consumers.  While this problem is deep-seated and multi-causal, \nas documented in PJM’s recent white paper “Powering Reliability Through Market Design” (the \n“PJM White Paper”),2 the Commission can help PJM avoid this more costly and less reliable path \nby requiring PJM to remove or at least mitigate the BYONC mechanism. \n \n2 Power Reliability Through Market Design:  Addressing Rising Demand and Constrained Supply, and Stimulating \nInvestment to Support Durable Reliability, PJM (May 6, 2026), https://www.pjm.com/-\n/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-\ndesign.pdf (“PJM White Paper”)."},{"page":65,"startToken":20535,"endToken":21001,"text":"4 \n \nII. IRAS LOAD SHOULD BE CURTAILED AFTER DEPLOYMENT OF DEMAND RESPONSE AND OTHER \nLOWER-COST ACTIONS, AND THE COST OF IRAS CURTAILMENT SHOULD BE REFLECTED IN \nENERGY MARKET PRICES \nA. DURING EMERGENCY OPERATIONS, RTOS SHOULD DEPLOY THE \nLOWEST-COST EMERGENCY ACTIONS FIRST WHEN POSSIBLE IN ORDER \nTO MAXIMIZE TOTAL SOCIAL SURPLUS \n11. A bedrock principle underlying organized power markets since their inception in PJM and \nelsewhere is that resources should be deployed and load served in a manner that maximizes the \ntotal social surplus for all participants on both the supply and demand side of the market, subject \nto all physical and operational constraints.  Under normal operating conditions in PJM’s energy \nmarket, this is achieved by dispatching resources in increasing order of their marginal cost and \nserving all load which has expressed a willingness to pay that is equal to or higher than the marginal \ncost of serving the final increment of load (or which has expressed a lack of demand elasticity, as \nis the case for most loads, which is treated as a willingness to pay in excess of administrative \nmarket price caps under normal operating conditions).  The market clearing energy price under \nthis design is effectively3 determined by the intersection of the supply and demand curves, where \nthe marginal cost of serving load is equal to the marginal benefit that the final increment of load \nderives from consumption.  This market organization maximizes social surplus because the sum \nof the benefits that load derives from the consumption of electricity minus the production cost of \nelectricity (effectively the area between the supply and demand curves) is maximized.  Simply put, \nthe maximum amount of load that can be economically served is served, and the production cost \nof serving that load is minimized.  The Commission has stated that a primary goal, or objective \nfunction, of organized power markets is to maximize total surplus,4 and has approved numerous \n \n3 In technical terms, the market clearing price is the incremental cost of serving the next increment of load at a given \nlocation, whether that is achieved through the incremental dispatch of supply resources or the curtailment of price-\nsensitive demand resources.  The supply and demand intersection provides a useful heuristic for visualizing the \nformation of market prices that is sufficient for this discussion but in actual operation the determination of prices is \nmore complex. \n4 Price Formation in Energy and Ancillary Services Markets Operated by Regional Transmission Organizations and \nIndependent System Operators, Notice Inviting Post-Technical Workshop Comments, Docket No. AD14-14-000 (Jan \n16, 2015) at 1: “The goals of proper price formation are to: maximize market surplus for consumers and suppliers…”  \nIn Order 2000 (1999) the Commission broadly articulated a goal of utilizing organized power markets to increase \nmarket efficiency to the greatest extent possible.  See 89 FERC ¶ 61,285, 32-71."},{"page":66,"startToken":21001,"endToken":21421,"text":"5 \n \nmarket designs, such as PJM’s energy and capacity markets, that explicitly seek to maximize total \nsurplus through their operation.5 \n12. The benefits of maximizing total surplus remain when the system is operating under \nemergency conditions, although such maximization can be more challenging to fully achieve.  \nWhen PJM is operating under emergency conditions the amount of available excess generation \nsupply will typically approach zero, and PJM thus must rely on other actions, such as the \ncurtailment of load, in order to maintain reliable operations.  All of the actions PJM may take under \nemergency operations have a cost, however, and these costs should be considered when deciding \nwhich emergency actions to take at any particular point in time.  For instance, curtailing load, \nwhether it occurs through the deployment of demand response resources, through the curtailment \nof IRAS loads under PJM’s IRAS proposal, or via manual load shed actions, has an economic cost \nbecause the load in question is deprived of the benefits it derives from the consumption of \nelectricity, whether that be through business disruption, damage to assets, or other problems.  The \ncost of curtailment is commonly referred to as the Value of Lost Load or “VOLL.”  Similarly, \nother emergency actions such as ordering generation to produce at emergency levels also result in \nincremental costs.  When operating under emergency conditions PJM does not take emergency \nactions based on a surplus-maximizing market optimization algorithm like it does under normal \nconditions.  Rather PJM utilizes a combination of an established deployment order coupled with \noperator judgement to decide which actions to take and when.6  Nonetheless, actions that PJM \ntakes under emergency conditions still have economic costs, which are often very high.  To the \nextent that PJM deploys high-cost emergency actions while lower-cost actions which can also help \nthe market maintain reliable operations remain available and unutilized, that choice unnecessarily \nincreases the total costs borne by market participants and reduces total surplus.  Thus, to remain \nin alignment with the overall goal of maximizing market surplus, during emergency conditions \nPJM should seek to take lower cost actions before it takes higher cost actions if possible and should \ndesign its emergency action protocols and emergency action deployment order accordingly. \n \n5 Any market that determines price by equalizing the marginal cost of supply with the marginal benefit of consumption, \nas both the PJM energy and capacity markets do, seeks to maximize total surplus by construction. \n6 PJM Proposal, Attachment C, Affidavit of Christopher Pilong on Behalf of PJM Interconnection, L.L.C. (“Pilong \nAffidavit”), PP 14-16."},{"page":67,"startToken":21421,"endToken":21811,"text":"6 \n \nB. CURTAILMENT OF IRAS LOAD IS LIKELY TO BE MORE EXPENSIVE THAN \nDEPLOYMENT OF DEMAND RESPONSE, AND SHOULD THUS BE \nCURTAILED AFTER DEMAND RESPONSE IN THE EMERGENCY ACTION \nORDER \n13. Under its IRAS proposal, during emergency operations PJM proposes to locate curtailment \nof IRAS loads at a very early point in its emergency action deployment priority order.  Specifically, \nPJM proposes to curtail IRAS loads after it curtails loads operating under non-firm transmission \nservice and curtails non-firm interchange transactions, but before all other emergency actions, \nincluding the deployment of Demand Response, maximum emergency generation actions, voltage \nreduction, and general manual load shed.7   \n14. While there is little data on the relative costs of the various emergency actions at PJM’s \ndisposal, curtailment of IRAS loads is almost certainly significantly more costly than many of the \nother actions that PJM proposes to deploy after IRAS in the emergency action priority order.  In \nparticular, as I discuss below, curtailment of IRAS load is highly likely to be significantly more \ncostly than Demand Response.  Thus, curtailment of IRAS in favor of deployment of Demand \nResponse almost certainly will lead to higher-than-necessary loss of consumer benefits from \nconsumption and a corresponding reduction in total surplus. \n15. The predominant types of Demand Response in PJM, Emergency and Pre-Emergency Load \nManagement service, are voluntary services where loads are voluntarily certified as capacity \nresources, offer into and clear the RPM on a purely voluntary basis without a capacity must-offer \nobligation, and, if cleared as a capacity resource, agree to curtail load in response to PJM \ninstruction under emergency conditions.  In exchange for this service, loads providing Demand \nResponse are compensated as capacity resources via the RPM and are also paid a minimum \ndispatch price per MW-hour of curtailment when deployed.8  Implicitly, loads which choose to \nprovide Demand Response will weigh the compensation they receive (the combination of capacity \n \n7 Pilong Affidavit PP 44-46. \n8 Loads which elect the capacity-only option for the Pre-Emergency and Emergency Demand Response are not paid \nthe minimum dispatch price.  As of 2025/26 loads electing the capacity-only option comprise 1.3 percent of total \nnominated Demand Response capacity.  See 2025 Quarterly State of the Market Report for PJM: January Through \nJune, Monitoring Analytics, LLC (August 14, 2025), 399.  \nhttps://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2025/2025q2-som-pjm.pdf"},{"page":68,"startToken":21811,"endToken":22297,"text":"7 \n \nrevenues and minimum dispatch payments) against their private estimate of their own VOLL in \nthe form of business disruption costs or similar.  If projected demand response compensation \nexceeds the load-specific VOLL for a given load, it will be economically advantageous to them to \nprovide Demand Response services to PJM. \n16. Given these economics, the population of loads that voluntarily provide Demand Response \nto PJM will generally represent a self-selected population of loads with relatively low VOLL \nbecause only those loads with a VOLL below the projected total Demand Response compensation \ncan economically provide the service.  As an example, I estimate that the total compensation to a \nrepresentative demand response resource in 2025/26 receiving the RPM Base Residual Auction \nclearing price of $270 per MW-Day and deploying for a total of 22.7 hours consistent with actual \ndeployments of demand response in eastern PJM over 2025/26 was on the order of $5,000 per \nMegawatt-hour of curtailment, comprised of the capacity payment of about $3,350 per MWh and \na per-MWh deployment payment (the Minimum Dispatch Price) of between $1,100 and  $1,849 \nper MWh depending on the notice time.9  Thus, in this example only loads with a VOLL of about \n$5,000 per MWh or less would be likely to be willing to offer and supply demand response at that \nlevel of compensation. \n17. Unlike Demand Response, however, IRAS is not a voluntary service, despite PJM putting \n“service” in the name.  New Large Loads that cannot render themselves exempt from IRAS by \nbringing new capacity via BYONC arrangements or RBP allocations are involuntarily placed on \nIRAS if they enter the market and the conditions to trigger IRAS  are in effect.  New Large Loads \nhave the option to provide Demand Response if they are willing and able, just like other loads.  \nFor New Large Loads that are able to economically curtail, providing Demand Response and \nutilizing Demand Response to qualify for the BYONC exemption is a categorically superior option \nto not providing Demand Response and instead being forced to provide IRAS.  As discussed above, \nDemand Response receives both a capacity payment and a per-MWh payment for actual \ndeployments.  IRAS, by contrast, receives no capacity payment at all and receives a maximum \n \n9 The curtailment hours are for Pre-Emergency Load Management with a 120-minute response time in the PECO \nZone. \n \nAccording \nto \nPJM’s \nActive \nLoad \nManagement \nhistory \ndata \n(https://www.pjm.com/-\n/media/DotCom/planning/res-adeq/load-forecast/alm-history.xlsx), demand response in this category was deployed \nfor 7 hours on 6/23/2025, 7 hours on 6/24/2025, 3.2 hours on 7/25/2025, and 5.5 hours on 7/29/2025 for a total of 22.7 \nhours.  Given the RTO clearing price of $270/MWD and demand response ELCC of 77% for the 2025/26 delivery \nyear, this translates to a capacity payment per deployment megawatt-hours of $3,342."},{"page":69,"startToken":22297,"endToken":22776,"text":"8 \n \nper-deployment payment equal to 50% of the capacity Non-Performance Charge Rate, which will \nbe about $1,500 per MWh for the first year in which IRAS is proposed to be in effect (rising to \nabout $2,000/MWh for the following year).10  Thus, for the representative resource discussed \nabove, Demand Response is compensated at about $5,000 per MWh of curtailment, while the same \nresource placed on IRAS would be compensated at most at about $1,500 per MWh of curtailment.  \nThe net effect of these starkly different economics is that New Large Loads that can economically \ncurtail and meet the physical and notice requirements needed to supply Demand Response will \nprovide Demand Response and avoid IRAS via the BYONC exemption (where the Demand \nResponse is the new capacity).  The loads that actually end up being placed on IRAS will be the \nleftovers: those New Large Loads that cannot easily curtail either because their VOLL is too high \nto make Demand Response economic or because their physical operating characteristics preclude \nthem from meeting the notice and response time required to provide Demand Response or even \nfrom curtailing at all.  These loads will thus typically have a VOLL which is much higher than the \nloads that are able to provide Demand Response.  EDC compliance with a NERC instruction to \ncurtail these loads will likely require curtailment via utility-controlled breakers rather than \nreductions implemented by the load itself, which is a particularly costly and disruptive form of \ncurtailment.  A recent study on the VOLL of different classes of load in the Electric Reliability \nCouncil of Texas indicates that the VOLL of typical large loads is generally between $6,500 and \n$23,000 per MWh.11  I expect that a typical load placed on IRAS would have a VOLL at least in \nthis approximate range. \n18. Thus, by prioritizing the curtailment of IRAS loads over those providing Demand Response \nwithin its proposed new emergency action priority order, PJM is affirmatively choosing to \nundertake high-cost actions while lower-cost actions that provide at least the same level, if not \nmore, of relief against emergency conditions remain unused.  As discussed above, this \n \n10 PJM Proposal 101-108.  The Non-Performance Charge Rate for the 2027/28 delivery year based on the published \nRTO Net CONE is $2,951/MWh, which translates to an IRAS Credit Rate of $1,475/MWh.  For 2028/29 these values \nwill rise to $3,963/MWh and $1,981/MWh, respectively. \n11 Value of Lost Load Study for the ERCOT Region, The Brattle Group (Charles Gibbons and Sanem Sergici), August \n19th, 2024, Table ES-1. https://www.brattle.com/wp-content/uploads/2024/09/Value-of-Lost-Load-Study-for-the-\nERCOT-Region.pdf Table ES-1 provides estimated VOLL for Medium/Large Commercial and Industrial customers \nas a function of interruption duration ranging between $22,721/MWh for a 1-hour interruption and $6,507/MWh for \na 8-hour interruption."},{"page":70,"startToken":22776,"endToken":23209,"text":"9 \n \nunnecessarily reduces total market surplus and runs counter to the basic design principles \nunderlying PJM markets. \n19. Further, it is likely that other emergency actions that PJM proposes to prioritize below the \ncurtailment of IRAS loads have incremental costs that are lower than the VOLL of IRAS loads.  \nSpecifically, PJM proposes that IRAS loads be curtailed before it takes a Maximum Generation \nEmergency Action (including curtailment of firm exports), before Emergency Voluntary Energy-\nOnly Demand Response Reductions, Curtailment of Non-Essential Building Load, and the Deploy \nAll Resources Action.12  While PJM has not provided data on the cost of these actions, they are all \ndeployed under EEA1 or EEA2 conditions and in advance of involuntary manual load shed and \nthus may have costs that are generally lower than the cost of involuntary load shed including load \nshed due to IRAS curtailment.  For example, the Maximum Emergency Generation and Deploy \nAll Resources actions will typically have costs consistent with the marginal cost of high-cost \nthermal generation with some additional accrued operations and maintenance costs due to \noperating outside of normal economic limits but nonetheless will typically be far below most \nVOLL levels under most types of emergency conditions.  Voluntary Emergency Energy-Only \nDemand Response Reductions and Curtailment of Non-Essential Building Load are a form of load \nshed but as discussed above, are likely to be less costly than curtailment of IRAS load. \n20. In addition to the economic cost implications, placing IRAS load curtailments at the front of \nthe curtailment order carries the risk of adverse reliability consequences in actual operations.  PJM \nproposes that it issue instructions to curtail IRAS loads to EDCs up to the amount of IRAS service \nthat PJM has allocated to an EDC’s zone.  This will be a NERC instruction that EDCs must comply \nwith if they are physically able, but PJM will not directly control the curtailment, nor will it have \nreal-time operating insight or real-time enforcement capability to ensure that the curtailment \nproduces the expected relief, and nor can it require a specific method of curtailment.   Given the \nuncertainties and frictions inherent in emergency operations, this creates real reliability risk.  As \nan example, assume an EDC is allocated 1,000 MW of IRAS service due to the presence of a large \nload with projected peak demand of 1,000 MW (without BYONC) on its system.  In real-time, \nPJM issues an instruction to the EDC to curtail 1,000 MW of IRAS load, but the particular large \nload in question is operating at a lower-than-expected level of 600 MW.  In this instance, even if \n \n12 Pilong Affidavit Figure 3."},{"page":71,"startToken":23209,"endToken":23661,"text":"10 \n \nthe EDC has installed a utility-controlled breaker at the large load, it will likely not be able to fully \ncomply with the IRAS instruction.  More generally, PJM will not have the ability to mandate a \nparticular method of compliance with IRAS instructions, so it is possible that EDCs may \nimplement compliance methods that perform differently than expected by PJM with respect to \nimplementation time, certainty of curtailment level, and so on.  While capacity resources face \nperformance uncertainty as well, PJM directly interfaces with capacity resources in real-time, \nsubjects them to rigorous qualification and testing, and measures, quantifies, updates their \nexpected performance based on actual physical performance over time and has stringent penalties \nit can enforce to incent performance.  These mechanisms will not be in place for IRAS.  In other \nwords, capacity is a standardized, tested product whereas IRAS, as proposed, is not.    Thus, PJM \ncould be faced with a situation where it calls on IRAS load to curtail in anticipation of system \nstress, but the IRAS load does not perform as expected, even if EDCs comply with the instruction \nto the extent they are physically able.  PJM then will have an unanticipated need to deploy Demand \nResponse or other actions, but may not be able to do so quickly enough to avoid a more serious \nphysical reliability problem.  Thus, by placing a high degree of reliance in real-time operations on \nwhat is likely to be a less visible, non-standardized, and less controllable group of resources in the \nform of IRAS curtailments, PJM creates material reliability risk.  Moving IRAS back in the \nemergency operation order will not make it more reliable, but it will reduce PJM’s reliance on it \nand reduce the risk of unanticipated performance shortfalls. \n21. Given these economic and reliability problems, I recommend that if the Commission accepts \nIRAS, it should require PJM to revise its proposed emergency order to move IRAS curtailment \nback in the order of emergency actions to behind all actions that take place under EEA1 or EEA2 \nconditions and just before actions which are only deployed under EEA3 conditions, such as manual \nload shed.  Further, I recommend that the Commission require PJM to designate IRAS curtailment \nas an EEA3 action (rather than EEA1 as PJM proposes) and place it first in the order of EEA3 \nactions.  \n22. To the extent that existing voluntary Demand Response would experience an increase in \ncurtailment risk with an appropriate deployment prioritization, resulting in fewer or higher-priced \noffers for such service, that is the nature of providing the capacity product: suppliers should offer \nonly those demand response services and at the prices they are comfortable providing.  In addition, \nto the extent demand response providers are not comfortable providing unlimited Demand"},{"page":72,"startToken":23661,"endToken":24071,"text":"11 \n \nResponse capacity but PJM still believes there is benefit available, PJM can develop other more \nlimited Demand Response products that Demand Response providers are comfortable providing.  \nLimited Demand Response could limit the total number of curtailment hours per year, daily \ncurtailment hours, or curtailment time window in a similar fashion to the limits that existed prior \nto the transition to the current unlimited Demand Response Product and consistent with proposals \nput forth by stakeholders in the process leading up to PJM’s Proposal. 13  Limited Demand \nResponse would receive a lower Effective Load Carrying Capacity to reflect its lower availability, \nbut would allow Demand Response providers to better tailor their product choice to their unique \ncurtailment economics, allowing for Demand Response participation to be maintained or even \ngrown despite potentially increased deployment frequency.  PJM may be better served pursuing \nsuch new, voluntary Demand Response products instead of forcing certain load to curtail \ninvoluntarily \nC. THE COST OF CURTAILING IRAS LOAD SHOULD BE REFLECTED IN \nENERGY PRICES WHEN IT OCCURS \n23. As discussed above, a core feature of PJM’s energy market design is that the market clearing \nprice for energy under normal operating conditions is set by the incremental cost of serving the \nnext increment of load (or of curtailing the final increment of load, if it is price-responsive).  \nSetting the market price in this manner ensures that all potential lower-cost resources have an \nincentive to offer and provide energy during operations, and that the market sends a price signal \nfor lower-cost resources to invest in their assets and enter the market.  This market design is \ncommonly referred to as “marginal cost pricing.” \n24. Adhering to a marginal cost pricing design is more challenging under emergency conditions \nbecause the marginal costs of many emergency actions are not well defined but nonetheless \nbecomes even more important under such conditions.  During emergency conditions, PJM needs \nevery potential resource to provide energy to serve load, and the costs of emergency actions that \nit would otherwise take if load cannot be served using conventional resources are very high.  \nTherefore, it is imperative that the energy market clearing price during emergency conditions be \n \n13 See Joint Stakeholder Package PJM CIFP – Large Load Additions, Presentation from Joint Stakeholders (Amazon, \nCalpine, Constellation, Google, Microsoft, Talen) at the Nov. 7th, 2025 Meeting of the Critical Issue Fast Path – Large \nLoad Additions stakeholder process, Slide 4. https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nlla/2025/20251107/20251107-item-03c---joint-stakeholders-proposal.pdf"},{"page":73,"startToken":24071,"endToken":24493,"text":"12 \n \nset high enough such that it provides a clear signal for all potential lower-cost resources to make \ntheir energy available to the market.  In a situation where PJM must curtail load in order to maintain \nreliable operations (through Demand Response deployment, IRAS curtailment, or manual load \nshed), the appropriate energy clearing price is the VOLL of the load that PJM must curtail.  Setting \nthe price at this level sends a clear signal for all resources with economic costs that are lower than \nthe cost of curtailment to provide their energy to the market and provides a longer-term signal \nencouraging market entry of resources that can provide energy under emergency conditions. \n25. PJM’s real-time economic dispatch software (specifically the Real-Time Security \nConstrained Economic Dispatch and Locational Price Calculator tools), which it utilizes to \ndetermine real-time energy market dispatch and prices, cannot without specific, special \nintervention reflect the cost of load curtailment, such as the curtailment of IRAS loads, in market \nprices.  PJM’s Proposal is completely silent as to how it proposes to handle energy price formation \nwhen IRAS loads are curtailed.  Absent specific changes to its economic dispatch software, which \nPJM does not indicate any plans to implement, a load curtailment is simply treated as a drop in \ndemand, and market prices will adjust accordingly, with the energy clearing price set based on the \nenergy offers of whatever dispatchable resources move in response to the load reduction.  Under \nhigh-stress conditions this price-setting resource will usually be some type of thermal generation \nresource with a marginal cost far below the VOLL of IRAS load, which as discussed above are \nlikely to be well in excess of $5,000 per MWh.  Thus, without intervention, the prevailing price \nsignal that PJM’s economic dispatch software will produce when IRAS is deployed will be far \nbelow the VOLL of IRAS load, and thus far below the level needed to send the appropriate \neconomic signals.  Put simply, absent changes to PJM’s economic dispatch software, curtailment \nof IRAS loads will suppress prices despite the existence of emergency conditions serious enough \nto warrant involuntary load curtailment, completely inconsistent with marginal cost pricing \nprinciples. \n26. PJM does make Demand Response eligible to set the energy price when it is deployed.14 \nPJM utilizes a workaround mechanism in its economic dispatch software called “closed-loop \ninterfaces” to implement this, despite its economic dispatch software ordinarily being unable to \nreflect load reductions in energy prices.  Specifically, PJM defines constraints around the potential \n \n14 PJM Open Access Transmission Tariff Attachment K Appendix Section 8.5."},{"page":74,"startToken":24493,"endToken":24889,"text":"13 \n \nzones in which Demand Response may be deployed, which allows Demand Response to set the \nprice at its minimum dispatch price (that is, up to $1,849 per MWh) when it is deployed.15  While \nthis provides a potential model for allowing IRAS resources to set price when curtailed, PJM’s \nProposal does not contain any proposed tariff revisions that would allow IRAS curtailments to set \nprice in a manner similar to Demand Response.   \n27. In order to ensure that proper market price incentives are maintained when PJM curtails \nIRAS loads, if the Commission accepts PJM’s IRAS proposal, it should require PJM to make \nchanges to its real-time economic dispatch software to allow IRAS to set the energy clearing price \nwhen it is curtailed.  This modification could take the form of a closed-loop interface workaround \nsimilar to that used for Demand Response or a more fundamental modification that treats IRAS \n(and potentially Demand Response as well) as a dispatchable resource.  The Commission should \ndirect PJM to set the dispatch cost of IRAS at a level that is consistent with its VOLL ($5,000 per \nMWh or more) or at the least, at the level of the proposed IRAS credit payment (about $1,500 per \nMWh) which is parallel with the approach taken with Demand Response even if it is well below \nthe likely VOLL of IRAS loads. \n28. Because capacity supply offers and the reference resource cost used to calibrate the capacity \ndemand curve are based on “missing money,” or the additional revenue that resources need to enter \nor stay in the market in excess of their expected energy and ancillary services revenue, properly \nreflecting IRAS deployment costs in energy prices during emergency operations will increase \nexpected energy revenues and decrease capacity offers and ultimately decrease capacity prices.  \nGiven that most of the damaging interventions that have led to the problems in attracting new entry \nidentified in the PJM White Paper have targeted the capacity market, moving overall market \ncompensation from the capacity market to the energy market via improved price formation can \ngenerally be expected to have a positive effect on overall market performance in attracting and \nretaining capacity. \n \n15 PJM Manual 11 at 12-13 and 2018 State of the Market Report for PJM, Monitoring Analytics, LLC (March 14, \n2019), 238-240.  https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2018/2018-som-pjm-\nsec4.pdf"},{"page":75,"startToken":24889,"endToken":25313,"text":"14 \n \nIII. PJM’S PROPOSAL TO EXCLUDE NEW LARGE LOADS FROM RPM DEMAND UNLESS THEY \nBRING THEIR OWN NEW CAPACITY WILL COMPROMISE RELIABILITY INCREASE COSTS,AND \nGREATLY LIMIT THE ABILITY OF THE RPM TO ATTRACT NEW SUPPLY GOING FORWARD  \n29. PJM proposes that new large loads that enter starting in the 2029/30 delivery year and do not \nbring an equivalent amount of new capacity in UCAP terms be excluded from the RPM demand \ncurve until and unless they bring such capacity.  PJM proposes that this exclusion apply regardless \nof whether IRAS service is triggered in a given delivery year.  New large loads “bring” new \ncapacity under PJM’s proposal either by being allocated capacity procured in the one-time \nReliability Backstop Procurement or by forming bilateral “BYONC arrangements” whereby new \ncapacity is attributed to new large loads that would otherwise be subject to IRAS and would \notherwise be excluded from RPM demand.16  This new capacity that is tied to new large loads \nmust subsequently be offered into the RPM at a price of $0 per MW-day (that is, as a price-taker) \nfor a period of 10 years.17 \n30. This proposed structure effectively creates a new source of value for new capacity only that \nis generally referred to as “BYONC” in PJM’s filing.  BYONC is tied to new entrant resources \nthat are able to provide capacity that is otherwise the same as standard RPM capacity provided by \nother capacity resources on a UCAP MW-for-MW basis.  However, under PJM’s IRAS proposal, \nresources that qualify to supply BYONC would be also uniquely able to provide new large loads \nthat seek to enter PJM with a means of avoiding IRAS and its associated curtailment risk if the \nlarge load is able to amass sufficient BYONC MWs to offset its load.18  Thus, BYONC as proposed \nrepresents a new source of value only available to new entrant capacity supply resources that is \nseparate from and additional to standard RPM capacity.  Resources qualifying to supply BYONC \nwill monetize this new, discriminatory source of value by effectively selling their “newness” to \nnew large loads via bilateral BYONC arrangements that will be made outside of the RPM.  The \nvalue of the “newness” feature of BYONC capacity is likely to be quite high in the coming years \n– supply of new entrant capacity supply resources is limited and demand is likely to be high – and \nbecause BYONC contracting occurs outside the RPM on a bilateral basis there are no limits on \n \n16 PJM Proposal 109-117. \n17 PJM Proposal 55-58. \n18 PJM Proposal 49-54, 69-72."},{"page":76,"startToken":25313,"endToken":25813,"text":"15 \n \nprice.  But because capacity providing BYONC must subsequently be offered into the RPM as a \nprice-taker, the bilateral price paid to BYONC resources will be completely disconnected from \nand external to the RPM.  While BYONC resources may be able to command very high bilateral \nprices via bilateral BYONC arrangements with new large loads, these high prices cannot be \nreflected in the RPM offers associated with these resources.  Rather, resources providing BYONC \non a bilateral basis will be offered into the RPM as price-takers and thus will provide no RPM \nprice signal with regards to the need for or cost of new entry. \n31. Large loads that are unable to make BYONC arrangements or receive RBP allocations \nsufficient to cover their load may still interconnect with the PJM system, but PJM proposes that, \nstarting with loads entering in the 2029/30 Delivery Year, these new large loads be excluded from \nRPM demand.  Under normal circumstances, when load grows or enters the system, it will be \nincluded in the RPM demand curve which in turn will send a signal to the market that additional \nsupply is needed and existing supply should remain in the market.  This signal occurs through the \ndemand parameters that PJM makes available to market participants prior to each auction, as well \nas through auction results themselves, including market clearing prices and quantities.  But under \nPJM’s Proposal, this will not occur because the load is excluded from the demand curve.  Despite \nthis, the load in question will still be physically present when it comes to real-world operations, \nwill be taking Network Integration Transmission Service on the same basis as other loads, and but-\nfor the IRAS curtailments will have the same right to be served as any other load. \n32. The implicit logic underlying PJM’s proposal is that because the excluded large loads can be \ncalled on to provide IRAS, the provision of IRAS offsets the resource adequacy need created by \nthe physical entry of the excluded large load.  Thus, within the RPM framework, PJM’s proposal \nto remove large loads without BYONC arrangements or RBP allocations is effectively equivalent \nto incorporating the excluded large loads into the demand curve while also entering an equivalent \namount of price-taker capacity supply that serves as a proxy for the IRAS curtailments that the \nexcluded large load may be forced to provide.19 \n \n19 The amount of megawatts PJM proposes to remove from the RPM demand curve will vary slightly at different \npoints along the curve because PJM will deduct the excluded load from the reliability requirement before multiplying \nby the relevant percentages at that define each point on the demand curve (99% for point A, 101.5% for point B, 106% \nfor point C) (see PJM Proposal 117-118).  For this reason, PJM’s proposal is not exactly equivalent to retaining the \nexcluded load in the supply curve and adding an equivalent amount of price-taker supply because the price-taker \nsupply is not multiplied by the relevant percentages, but the difference is very minor."},{"page":77,"startToken":25813,"endToken":26266,"text":"16 \n \n33. This implicit logic fails badly, for two reasons.  First, in any given delivery year IRAS will \nnot exist at all if it is not triggered.    In this scenario, the excluded new large load will be physically \npresent and will have the same service priority as other loads, but for RPM purposes PJM will \nsimply pretend it is not there.  Furthermore, it will be uncertain whether or not IRAS will be in \neffect for a given delivery year until less than three months before the start of the delivery year \nbecause PJM proposes that the triggering conditions for the provision of IRAS are not to be \nfinalized until the conclusion of the third Incremental Auction.  This lack of forward certainty as \nto whether IRAS will even be present at all further complicates PJM’s ability to plan for reliable \noperations both with respect to resource adequacy specifically as well as general transmission \nsecurity in operations. \n34. Second, even when it is in effect, IRAS is not capacity.  Unlike its nearest capacity analogue, \nDemand Response, IRAS is not subject to any sort of rigorous accreditation process to verify that \nit can perform as required; it does not receive an Effective Load Carrying Capacity or UCAP award \nquantifying its capability; it is not subject to testing or performance measurement; and it is not \nsubject to capacity performance incentives or penalties.  Instead, IRAS is implemented as a NERC \nInstruction to EDCs, which carries the weight of NERC oversight and potential enforcement, but \nis nonetheless far different from capacity.  Specifically, PJM will lack the same level of visibility \nand control it has with capacity resources because it cannot issue direct curtailment instructions to \nIRAS loads, because it cannot subject IRAS to the same precise, rigorous testing regime it places \non capacity, because it cannot quantify expected IRAS performance via ICAP and UCAP ratings, \nand because it cannot assess or credit Non-Performance incentive payments to IRAS resources.  \nBut PJM’s proposed treatment of loads that are eligible to provide IRAS in the RPM effectively \nassumes that IRAS is equivalent to capacity resources that offset the incremental reliability \nrequirement of the load in question on a one-for-one UCAP basis.  In mechanical terms, this is \nequivalent to assuming IRAS is a capacity resource with an ELCC equal to the forecast pool \nrequirement, or about 92% in the upcoming 2029/30 BRA, which is better than Demand Response \nand most Generation Capacity Resource types. \n35. In addition to the reliability aspects, deployment of IRAS is likely to be very costly, and thus \nas a resource adequacy product it is likely to be much more costly than Demand Response or other \ncapacity resources.  Excluding IRAS-eligible large load from RPM demand removes any pathway"},{"page":78,"startToken":26266,"endToken":26629,"text":"17 \n \nto express these economic differences and replace costly IRAS with less costly capacity resources \nover time, but rather effectively treats IRAS as if it is a zero-cost resource. \n36. The consequence of PJM’s exclusion of non-BYONC large loads from the RPM is that \nregardless of whether or not IRAS is triggered, the RPM will reflect a fictional reliability outcome \nthat will be materially different from the real physical resource adequacy situation.  This is at odds \nwith the purpose of the RPM, which is to conduct a competitive procurement for physical capacity \nsupply sufficient to achieve PJM’s resource adequacy standard at the level of the RTO and Local \nDelivery Areas based on forecasted demand.  The amount of capacity procured, and the price paid \nfor that capacity, will be inconsistent with the real underlying resource adequacy situation.   \n37. This mismatch will be particularly stark in delivery years where IRAS is not triggered.  For \nexample, consider the following illustrative example depicted below in Figure 1: \nFigure 1 \n \nIn this example, there is 5 GW of IRAS-eligible demand on the system which is excluded from the \nRPM demand curve, but the RPM just barely clears enough supply to avoid triggering IRAS.  As \na result, there is a sharp divergence between the apparent “on-paper” outcome of the BRA and the \nactual, physical reliability situation.  On paper the market clears at a low price with an apparent \nexcess - 103.8% in this example - when compared to the fictional, reduced amount of demand \nembedded in the demand curve.   If, instead, actual physical fundamentals were properly reflected \nin the RPM, it would show a quantity cleared just barely in excess of the reliability requirement – \n100.3% in this example – and a clearing price greater than the actual clearing price.  The clearing \nprice thus signals a large amount of excess while in reality the market is dangerously close to \nfalling short of the reliability requirement.  There is no signal to retain the resources needed to \nRPM Supply Curve\nUCAP MW\n5 GW of IRAS-Eligible Load \nExcluded from Demand\n“On-Paper” Cleared \noutcome: 103.8% of \nReliability Requirement; \nPrice \n($/MWD)\nOutcome Consistent with Physical Reality: \n100.3% of Reliability Requirement; \nRPM Demand Curve"},{"page":79,"startToken":26629,"endToken":27097,"text":"18 \n \nmaintain resource adequacy and address potential future shortfalls, nor is there a signal for new \nresources to begin the often-lengthy process of entering the market in anticipation of further \ntightening of the resource adequacy situation.  And if the market were actually short of the \nreliability requirement and IRAS were triggered, there would be no signal for the procurement of \nactual, accredited capacity resources to replace the reliance on IRAS as a resource adequacy \nproduct, which as discussed above is both costly and subject to uncertainty.  This raises the risk \nthat PJM’s proposal will trap it in a kind of reliability purgatory: the RPM will paint a better \nresource adequacy picture than exists in reality and thus fail to signal the need for new resource \nentry or resource retention consistent with the actual underlying physical resource adequacy \nsituation, leaving PJM stuck.  But actual physical operations will unforgivingly expose these \nshortcomings. When actual system stress occurs in real operations, and IRAS was never triggered \nin the first place or does not perform as expected, PJM will be faced with a real, physical \nemergency.  Fundamentally, excluding demand from the RPM that will nonetheless ultimately be \nphysically present undermines the ability of PJM to achieve its resource adequacy standard or even \nto know where it stands relative to its resource adequacy standard at any given point in time.  Going \nforward over time as more load is excluded under PJM’s proposal, the wedge between the fictional \nRPM and underlying physical reality will widen, and the risk that it will lead to real physical load \nshed will multiply, with no endpoint because PJM’s proposal to exclude load that does not bring \nnew capacity is permanent.   \n38. Thus, when PJM faces a need for new capacity (or retention of existing capacity) to support \nnew demand from large load, there is no avenue for the RPM to reflect this need.  New large loads \nwill either contract with new supply outside the RPM via BYONC arrangements whose economics \ncannot be reflected in the RPM, or they may enter without BYONC arrangements but will not be \nincluded in RPM demand.  In either case, no signal is sent to the RPM that incremental supply or \nretention of existing supply is needed to support the new demand, despite there being a very clear \nfundamental need in reality.  PJM’s proposal creates the illusion within the RPM that no net new \nlarge load demand exists on the system, even if there is substantial need for new supply to serve \nnew large load. \n39. The overall result of PJM’s proposed treatment of new large loads is that the only viable \npathway to attract new supply when faced with new demand from large load is through the \nBYONC mechanism, which as discussed above occurs outside the RPM and does not result in a"},{"page":80,"startToken":27097,"endToken":27502,"text":"19 \n \nnew entry price signal being sent to the RPM.  When large load enters without the BYONC \nmechanism in place, it will be excluded from the RPM and a price signal for new entry and/or \nretention of existing supply to support this new demand will not be sent.  Rather, the new demand \nwill be effectively assumed to be served via the deployment of IRAS, which is both much more \ncostly than actual capacity and subject to considerable uncertainty around its availability and \nperformance. \n40. If it accepts the PJM Proposal, the Commission should order PJM to modify its proposal to \ninclude new large load in RPM demand under all circumstances, regardless of whether or not the \nnew large load brings new capacity through a BYONC arrangement.  This treatment ensures that \nthe RPM parameters and market clearing outcomes will be consistent with the actual underlying \nresource adequacy situation and will provide an accurate market price signal for resources to enter \nand/or remain in the market to support this incremental demand. \nIV. IRAS IS THE LATEST IN A SERIES OF RECENTLY-IMPLEMENTED OR PENDING ACTIONS BY \nPJM THAT WILL COLLECTIVELY DESTROY THE ABILITY OF RPM TO MEET THE RESOURCE \nADEQUACY NEEDS OF PJM GOING FORWARD UNLESS CORRECTIVE ACTION IS TAKEN \n41. PJM’s IRAS proposal is the latest in a series of actions and proposed actions that collectively \ndepress market prices in the RPM for existing resources while providing higher, discriminatory \nprices for new resources under specific conditions.  Without corrective action by the Commission, \nthe collective weight of these proposals, coupled with the specific problems created by the IRAS \nproposal, will act together to effectively make it impossible for the RPM to attract new entry to \nserve any type of new demand, Large Load or otherwise, or to forestall resource exit. \n42. As discussed above, PJM’s proposal in this proceeding creates a special pathway for new \nresources to enter the market via bilateral BYONC arrangements with new large loads while \nrequiring the capacity entering under such arrangements to offer into the RPM as price-takers and \nwhile excluding large loads that do not make BYONC arrangements from RPM altogether.  Both \nof these elements depress market prices in the RPM even when supply is needed to meet new \ndemand. \n43. In addition to PJM’s proposal in this proceeding, in recent years, actions taken by PJM which \nerode the ability of the RPM to attract and retain market-based supply include:"},{"page":81,"startToken":27502,"endToken":27961,"text":"20 \n•\nCounting resources operating under Reliability-Must-Run contracts that do not provide \ncapacity as if they are nonetheless providing capacity and entering those resources into \nthe RPM supply curve as price-takers, despite the resources receiving full cost-based \ncompensation.20\n•\nEnacting a temporary ad-hoc price cap (and non-binding price floor) that reduced the \nnormal standard price cap determined through Quadrennial VRR Review process by \napproximately 35% when it became apparent that the 2026/27 and 2027/28 RPM auctions \nwould likely clear at the price cap.21\n•\nExtending the temporary ad-hoc price cap at the same nominal level to the 2028/29 and \n2029/30 auctions when it became apparent that those auctions too were likely to \notherwise clear at the normal price cap.  This extension of the ad-hoc price cap occurred \ndespite PJM filing and the Commission approving a new VRR Curve and normal price \ncap through the 2025 Quadrennial Review process.22\n•\nProposing to procure up to 6.8 Gigawatts of new build capacity outside of the RPM via \nthe Reliability Backstop Procurement process which would allow new resources to offer \nand realize prices that are approximately 70% higher than those currently available to \nexisting resources in the RPM for up to 15 years while requiring that those high-cost new\n20 PJM Interconnection, L.L.C., Revisions to Reliability Pricing Model, Docket No. ER25-682-000 (filed December \n9, 2024) (PJM petition seeking to incorporate RMR resources into RPM capacity supply curve, among other changes). \nPJM Interconnection, L.L.C., 190 FERC ¶ 61,088 (2025) (Order approving PJM’s proposed treatment of RMR \nresources). \n21 PJM Interconnection, L.L.C., Proposal for Revised Price Cap and Price Floor for the 2026/2027 and 2027/2028 \nDelivery Years, and Request for a Waiver of the 60-Days’ Notice Requirement to Allow for a March 31, 2025 \nEffective Date, Docket No. ER25-1357-000 (filed February 20, 2025) (PJM petition seeking a cap at $325/MWD and \na floor at $175/MWD, as compared to the but-for price cap of approximately $500/MWD for the 2026/27 and 2027/28 \nDelivery Years).  Commonwealth of Pennsylvania v. PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 (2025) (Order \napproving the revised cap and floor). \n22 PJM Interconnection, L.L.C., Proposal to Extend the Price Cap and Price Floor for the 2028/2029 and 2029/2030 \nDelivery Years, And Request for a Waiver of the 60-Days’ Notice Requirement to Allow for a March 31, 2026 \nEffective Date, Docket No. ER26-1556-000 (filed February 27, 2026) (PJM petition seeking to extend the cap at \n$325/MWD and floor at $175/MWD for the 2028/29 and 2029/30 Delivery Years).  PJM Interconnection, L.L.C., 195 \nFERC ¶ 61,076 (2026) (Order approving the extension of the revised cap and floor)."},{"page":82,"startToken":27961,"endToken":28179,"text":"21 \n \nresources offer into the RPM as price-takers for the full duration of their contracts \nregardless of whether the forecasted load that motivated the RBP ever shows up.23 \n44. PJM is well aware of the corrosive effect that these one-sided interventions have on the \nincentives for new resources to enter the market and for existing resources to remain in the market.  \nThe PJM White Paper eloquently describes this phenomenon as the “Credibility Trap.”  The \nCredibility Trap occurs when PJM seeks to utilize its markets to signal a need for capacity, but \nproviders of capacity have little or no confidence that the market will provide the compensation \nnecessary to support the entry or retention of that capacity due to the ongoing risk of politically-\ndriven interventions similar to those taken by PJM in the recent past.  The PJM White Paper \nillustrated the credibility trap with the following graphic: \n \n \n \n \n \n \n \n \n \nSource: PJM White Paper 26 \n45. When a resource enters via RPM, rather than via one of the special, discriminatory paths that \nPJM has proposed, such as via the RBP or a bilateral BYONC arrangement, it is “new” for only \n \n23  PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (currently pending before the \nCommission)."},{"page":83,"startToken":28179,"endToken":28623,"text":"22 \n \none year.  After that it becomes an existing resource that is forever locked out of the special, high-\nvalue discriminatory pathways and instead must rely on the ongoing compensation from RPM.  As \nsuch, it is subject to ongoing risk of further one-sided interventions such as further extension or \nre-imposition of “temporary” ad-hoc price caps or further infusions of price-taker new supply \nentering via new-only pathways.  To the extent that load growth does not materialize as forecast \nor materializes later than originally forecast, such resources are likely to endure an extended period \nof oversupply and extremely depressed prices driven by entry of new resources availing \nthemselves of the RBP or BYONC arrangements.  \n46. PJM is well aware of the impact that low prices have on resource adequacy over time, \nparticularly if the low prices are not consistent with physical fundamentals. In 2023, it published \nits Energy Transition in PJM: Resource Retirements, Replacements & Risks report (the “4R \nReport”) detailing how resource retirements and forecasted load growth were likely to result in a \nresource adequacy crunch.24 The 4R Report was published during a period of low capacity prices \nfrom 2021/22 through 2024/25 that sent a clear exit signal to many existing resources. Now that \nthe predicted resource adequacy crunch is here, PJM is trying to incent replacement of these retired \nresources via new build capacity (or potentially re-activation of some of the retired resources) \nthrough more expensive RBP or BYONC contracts that, when entered into the market as price \ntakers, will lead to the same price suppressing outcome for current existing resources that drove \nthese deactivated resource to retire less than half a decade earlier. \n47. Given this market landscape, the market stagnation identified in the PJM White Paper is \nlikely to take hold.  No rational entrant will enter via the RPM, particularly when higher-priced, \nlower-risk pathways for new entry such as bilateral BYONC contracts, the proposed RBP, or a \nrepeat of the proposed RBP at a later date are available or are likely to be available in the future, \nparticularly if PJM further blunts the signal for new entry by removing new large load without \nassociated new capacity from the RPM.  The rational approach for potential new entrant resources \nunder these circumstances is to avoid entry via the RPM and instead enter via these special \ndiscriminatory new-only resource pathways.  And if these pathways are not available at a given \npoint in time, investors in potential new entrant resources will prefer to wait until they do become \n \n24 Energy Transition in PJM: Resource Retirements, Replacements & Risks, PJM (February 24, 2023).  \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2023/energy-transition-in-pjm-\nresource-retirements-replacements-and-risks.ashx"},{"page":84,"startToken":28623,"endToken":29116,"text":"23 \n \navailable rather than enter via the RPM.  Given PJM’s emerging track record in this area, waiting \nis likely to be a rational, winning bet.  The results of the 2028/29 Base Residual Auction provide \nan initial confirmatory datapoint of this phenomenon: despite clearing at the temporary price cap \nof $325 per MW-day and 6,831 MW short of the reliability requirement, only 525 MW of new \nresources (uprates and new build capacity) entered the market, the lowest level of new entry in 20 \nyears.25  The likely reason is obvious: investors in new resources are holding out for the RBP \nand/or the prospect of bilateral BYONC arrangements.  If they enter via the RPM, they become an \nexisting resource going forward that can never access those higher-value pathways. \n48. Existing resources will also respond to these various one-sided interventions that \ncumulatively erode the ongoing revenues that they can expect to realize through the RPM.  Some \nresources may choose to retire if expected market revenues are insufficient to cover their ongoing \noperating costs and risks.  In addition to resources that simply retire, many existing resources have \nthe capability to exit the RPM and instead sell into other markets.  Many generators can physically \nmove their equipment to other regions of the country and effectively become a new generator in a \ndifferent market.  Approximately 900 MW of gas-fired combustion turbine capacity in the ComEd \nzone of Illinois recently elected to leave the PJM market by physically moving their turbines to \nTexas and re-installing them there, effectively becoming a new resources in the Electric Reliability \nCouncil of Texas.26  Other existing resources have in recent years acquired firm transmission into \nneighboring markets such as MISO to export their capacity27 and can be expected to continue to \ndo so in increasing numbers.  Finally, resources may relinquish their interconnection with PJM \naltogether and instead serve self-contained “islanded” networks. \n \n25 2028/29 Base Residual Auction Report, PJM Interconnection, L.L.C, Figure 2.  https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results-report.pdf 2019/20 Base \nResidual Auction Report, PJM Interconnection, L.L.C, Table 7. https://www.pjm.com/-/media/DotCom/markets-\nops/rpm/rpm-auction-info/2019-2020-base-residual-auction-report.pdf \n26 Editorial: Owner of Massive Elwood Energy Plant isn’t Waiting for Illinois Closure Deadlines.  They’re Literally \nMoving the Plant to Texas.  Chicago Tribune Editorial Board (April 17, 2026).  \nhttps://www.chicagotribune.com/2026/04/17/editorial-elwood-will-county-jb-pritzker-ceja-clean-energy-law/ \n27 See, e.g., Cordova Energy Company LLC, 194 FERC 61,108 (2026) (authorizing a 611.2 MW natural-gas fueled, \ncombined-cycle electric generating facility located in PJM to sell its capacity to an affiliate in MISO during the \n2028/2029 Delivery Year after already receiving approvals for similar sales during the 2027/2028 Delivery Year); \nDairyland Power Coop., 194 FERC ¶ 61,133, at P 5 (2026) (explaining that Dairyland acquired PJM units for the \npurpose of exporting energy and capacity to fulfill Dairyland’s capacity obligations to its distribution cooperative \nmembers located in MISO)."},{"page":85,"startToken":29116,"endToken":29556,"text":"24 \n \n49. To the extent that existing resources take these pathways out of the market in response to the \nerosion of the RPM, PJM risks additional resource adequacy shortfalls going forward caused by \nresource exit.  While PJM is proposing a discriminatory pathway for new resources to enter in \nresponse to large load growth, it does not have a similar discriminatory pathway for new resources \nto enter in response to resource adequacy needs caused by other reasons such as the exit of existing \nresources.  But due to the continued erosion in investor confidence in the RPM caused by its \nproposal in this proceeding coupled with the other recent and pending actions detailed above, PJM \nis likely to find the investors in new capacity to be unresponsive to signals for new entry via the \nRPM, with capital staying on the sideline and waiting for PJM to crack and implement some new \ndiscriminatory pathway for new entrants, such as a reprise of the RBP. \n50. The endpoint for PJM is a market that is continually in a spiraling crisis.  Ongoing \ninterventions drive resource exit and eliminate the RPM as a viable pathway for new resource \nentry, which drives new resource shortfalls which beget further intervention, further eroding \nconfidence in the market.  This outcome will erode reliability over the long run.  It will erode \nreliability because ad hoc interventions are a poor solution to resolving resource adequacy \nshortfalls.  They are slow to implement, frequently involve substituting inferior alternatives (such \nas RMR resources or IRAS curtailment) for real capacity, carry the risk of unforeseen or \nunintended consequences compared to the tried-and-true design of the market, and are often \nsubject to ongoing legal risk.  Repeated reliance on these measures raises the risk that something \nwill go wrong – IRAS loads do not curtail as expected, non-Capacity Performance compliant RMR \nresources fail to perform as hoped, RBP resources are delayed, either or both is thrown out on legal \nreview – with ongoing elevated physical resource adequacy risk for all customers being the \nultimate consequence. \n51. While repeated interventions to depress market prices for existing resources and restrict \npayment of prices at the level needed for new entry solely to new entrant resources may appear to \nlower consumer costs, over time as the need for such interventions continually repeats and existing \nresources exit the market, any apparent consumer cost savings will decline and ultimately reverse.  \nA core feature of this type of world is ongoing market exit of relatively low-cost existing resources \nthat are nonetheless needed for maintaining resource adequacy.  Under the emerging paradigm, \nthe only viable way to replace these lost existing resources is to engage in further discriminatory"},{"page":86,"startToken":29556,"endToken":29954,"text":"25 \n \ninterventions to procure additional new resources at high cost.  This is a bad trade for consumers, \nand one that will come to predominate in the world towards which PJM is trending. \n52. The forces moving PJM in the direction of the Credibility Trap have been operating for \nseveral years now and some of the interventions driving it have already occurred.  And PJM’s \ncredibility as a steward of a stable, non-discriminatory, investable market for capacity has already \nbeen badly damaged.  Put simply, PJM is already deeply mired in the Credibility Trap.  Without \nmodification, the IRAS proposal will drive substantial further market erosion for the reasons \ndiscussed above which will further undermine resource adequacy and increase costs in PJM.  This \nis particularly the case because the IRAS proposal will become a permanent part of the tariff and \neven if its implementation is suspended due to changing market conditions it can be repeatedly re-\nactivated later if market conditions again become tight.  Thus, the IRAS proposal is a permanent \n“heads I win, tails you lose” policy from the perspective of existing resources. \n53. But strong, prompt intervention by the Commission in the proceeding could put PJM on a \npath to ultimately escaping the Credibility Trap.  The modifications I discuss in other sections of \nthis affidavit – namely moving IRAS curtailments back in the curtailment order and reflecting \nthem in energy prices and reflecting all new large load in demand – are necessary to this but not \nsufficient in my view.  As discussed above, the BYONC mechanism is ultimately highly corrosive \nto markets and is a major contributor to the confluence of factors driving PJM towards the spiral \nof crisis.  Ideally the Commission should direct PJM to remove the BYONC mechanism from its \nproposal.  If the Commission declines to recommend a full removal of the BYONC mechanism \nfrom PJM’s proposal, it should consider mechanisms that limit its impact on the broader market, \nsuch as requiring resources entering the market under BYONC arrangements to comply with the \nMinimum Offer Price Rule which would preserve a new entry price signal for the broader RPM \nmarket.  The issues discussed in the PJM White Paper are broad and not limited only to the IRAS \nproposal, but strong action by the Commission to preserve markets in this proceeding will send a \nstrong signal to investors that markets remain viable over the long term. \n54. This concludes my affidavit."},{"page":87,"startToken":29954,"endToken":29954,"text":""},{"page":88,"startToken":29954,"endToken":29960,"text":"26 \n \n \n \n \n \n \n \n \n \nAttachment A to Patterson Affidavit"},{"page":89,"startToken":29960,"endToken":30172,"text":"27 \n \nAaron T. Patterson Testimony and Expert Reports \nDate \nOn Behalf Of \nCommission/Court \nSubject Matter \nDocket/Case Number \nDec-25 \nConstellation Energy FERC \nAffidavit – Proposal for \nEnhanced Reliability \nBackstop Mechanism \nRM26-4-000 \nEL25-49-000 \nAD24-11-000 \nEL25-20-000 \nDec-25 \nConstellation Energy Illinois Commer \nCommission \nRebuttal Testimony \nResponding to Joint NGO \nBring Your Own Generation \nProposal \n25-0680 \nOct-25 \nConstellation Energy Illinois Commerce \nCommission \nRebuttal Testimony \nResponding to Joint NGO \nBring Your Own Generation \nProposal \n25-0679 and 25-0677 \nApr-25 \nConstellation Energy FERC \nAffidavit – Resource \nAdequacy Issues in PJM \nEL25-49-000 \nAD24-11-000 \nEL25-20-000 \nJan-25 \nConstellation Energy FERC \nAffidavit – Treatment of RMR \nResources in PJM Capacity \nMarket \nER25-682-000 \nFeb-24 \nNuclear Energy \nInstitute \nU.S. Department of \nthe Treasury \nExpert Report (with Frank \nHuntowski and John \nHutchinson) – “Assessing the \nIncrementality Requirement \nof Treasury’s Proposed 45V \nRegulations” \nREG-117631-23 \nDec-23 \nConstellation Energy FERC \nReply Affidavit – PJM \nCapacity Market Reforms \nER24-99-000 and ER24-98-000 \nNov-23 \nConstellation Energy FERC \nAffidavit – Market Monitor \nComplaint regarding PJM \nCapacity Market \nEL24-12-000 \nNov-23 \nConstellation Energy FERC \nAffidavit – PJM Capacity \nMarket Reforms \nER24-99-000 and ER24-98-000 \nNov-22 \nConstellation Energy FERC \nJoint Affidavit (with Michael \nM. Schnitzer) – New England \nWinter Gas-Electric Forum \nAD22-9-000 \nJune-21 \nExelon Corporation \nand PSEG \nCompanies \nFERC \nReply Affidavit – PJM \nCapacity Market Seller Offer \nCap \nEL-19-63-000 \nMay-21 \nExelon Corporation \nand PSEG \nCompanies \nFERC \nAffidavit – PJM Capacity \nMarket Seller Offer Cap \nEL19-63-000"},{"page":90,"startToken":30172,"endToken":30255,"text":"28 \n \nAaron T. Patterson Testimony and Expert Reports \nDate \nOn Behalf Of \nCommission/Court \nSubject Matter \nDocket/Case Number \nNov-20 \nExelon Corporation \nFERC \nDeclaration (with Michael M. \nSchnitzer) – NYISO Capacity \nMarket Buyer Side Mitigation \nEL21-07-000 \nNov-19 \nExelon Corporation \nState of New York \nPublic Service \nCommission \nExpert Report – “Impact of \nCarbon Pricing on Potential \nExpanded Buyer-Side \nMitigation in the NYISO \nMarkets” \n19-E-0530 \nDec-17 \nExelon Corporation \nPublic Utility \nCommission of Texas \nExpert Report (with David \nColeman) – “Economic \nEquilibrium and Reliability in \nERCOT” \nProject No. 47199"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":154,"startToken":0,"endToken":924},{"p":4,"at":154,"title":"BACKGROUND","method":"printed heading","endPage":9,"endAt":29,"startToken":924,"endToken":2489},{"p":9,"at":29,"title":"I. PJM’s Proposal Is Beyond The Commission’s Jurisdictional Reach","method":"printed heading","endPage":9,"endAt":97,"startToken":2489,"endToken":2498},{"p":9,"at":97,"title":"A. The Commission’s Jurisdiction Is Subject To Strict Statutory Limits","method":"printed heading","endPage":13,"endAt":254,"startToken":2498,"endToken":3974},{"p":13,"at":254,"title":"B. The Proposal Exceeds The Statutory Limits On The Commission’s","method":"printed heading","endPage":26,"endAt":1424,"startToken":3974,"endToken":8795},{"p":26,"at":1424,"title":"C. The Proposal Exceeds The Statutory Limits On The Commission’s","method":"printed heading","endPage":27,"endAt":1679,"startToken":8795,"endToken":9151},{"p":27,"at":1679,"title":"D. The Authorities On Which PJM Relies Do Not Support Jurisdiction Here","method":"printed heading","endPage":29,"endAt":251,"startToken":9151,"endToken":9546},{"p":29,"at":251,"title":"II. The Commission Would Unduly Discriminate Based On Load Size, Load Date, And","method":"printed heading","endPage":29,"endAt":659,"startToken":9546,"endToken":9607},{"p":29,"at":659,"title":"A. The Commission Must Reject The Proposal Unless PJM Shows That The","method":"printed heading","endPage":31,"endAt":382,"startToken":9607,"endToken":10210},{"p":31,"at":382,"title":"B. PJM’s Proposal Unduly Discriminates Based On Load Size And Load Date","method":"printed heading","endPage":37,"endAt":539,"startToken":10210,"endToken":12306},{"p":37,"at":539,"title":"C. PJM’s Proposal Unduly Discriminates Based On Resource Vintage","method":"printed heading","endPage":41,"endAt":6,"startToken":12306,"endToken":13647},{"p":41,"at":6,"title":"III. The Commission Must Reject PJM’s Proposal Because Market Design Flaws Make","method":"printed heading","endPage":42,"endAt":6,"startToken":13647,"endToken":13964},{"p":42,"at":6,"title":"A. PJM’s Proposal To Curtail New Large Load Prior To Calling On Emergency","method":"printed heading","endPage":46,"endAt":6,"startToken":13964,"endToken":15185},{"p":46,"at":6,"title":"B. PJM’s Proposal To Exclude New Large Load Without Sufficient BYONC","method":"printed heading","endPage":53,"endAt":6,"startToken":15185,"endToken":17505},{"p":53,"at":6,"title":"IV. If the Commission Nonetheless Were To Accept PJM’s Unlawful Proposal, It Should","method":"printed heading","endPage":53,"endAt":1166,"startToken":17505,"endToken":17676},{"p":53,"at":1166,"title":"A. If Accepted, The Proposal Should Be Modified To Allow Any Qualifying New","method":"printed heading","endPage":55,"endAt":180,"startToken":17676,"endToken":18121},{"p":55,"at":180,"title":"B. If Accepted, The Proposal Should Be Modified To Specify That BYONC","method":"printed heading","endPage":56,"endAt":916,"startToken":18121,"endToken":18624},{"p":56,"at":916,"title":"C. If Accepted, The Proposal Should Be Modified To Include Incremental","method":"printed heading","endPage":57,"endAt":1359,"startToken":18624,"endToken":18971},{"p":57,"at":1359,"title":"V. Conclusion","method":"printed heading","endPage":59,"endAt":4,"startToken":18971,"endToken":19179},{"p":59,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":62,"endAt":5,"startToken":19179,"endToken":19315},{"p":62,"at":5,"title":"I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT","method":"printed heading","endPage":62,"endAt":62,"startToken":19315,"endToken":19322},{"p":62,"at":62,"title":"A. QUALIFICATIONS","method":"printed heading","endPage":62,"endAt":1275,"startToken":19322,"endToken":19511},{"p":62,"at":1275,"title":"B. BACKGROUND AND PURPOSE OF AFFIDAVIT","method":"printed heading","endPage":63,"endAt":1554,"startToken":19511,"endToken":19941},{"p":63,"at":1554,"title":"C. SUMMARY OF CONCLUSIONS","method":"printed heading","endPage":65,"endAt":5,"startToken":19941,"endToken":20536},{"p":65,"at":5,"title":"II. IRAS LOAD SHOULD BE CURTAILED AFTER DEPLOYMENT OF DEMAND RESPONSE AND OTHER","method":"printed heading","endPage":65,"endAt":185,"startToken":20536,"endToken":20564},{"p":65,"at":185,"title":"A. DURING EMERGENCY OPERATIONS, RTOS SHOULD DEPLOY THE","method":"printed heading","endPage":67,"endAt":5,"startToken":20564,"endToken":21422},{"p":67,"at":5,"title":"B. CURTAILMENT OF IRAS LOAD IS LIKELY TO BE MORE EXPENSIVE THAN","method":"printed heading","endPage":72,"endAt":1064,"startToken":21422,"endToken":23814},{"p":72,"at":1064,"title":"C. THE COST OF CURTAILING IRAS LOAD SHOULD BE REFLECTED IN","method":"printed heading","endPage":75,"endAt":6,"startToken":23814,"endToken":24890},{"p":75,"at":6,"title":"III. PJM’S PROPOSAL TO EXCLUDE NEW LARGE LOADS FROM RPM DEMAND UNLESS THEY","method":"printed heading","endPage":80,"endAt":1039,"startToken":24890,"endToken":27268},{"p":80,"at":1039,"title":"IV. IRAS IS THE LATEST IN A SERIES OF RECENTLY-IMPLEMENTED OR PENDING ACTIONS BY","method":"printed heading","endPage":90,"endAt":635,"startToken":27268,"endToken":30255}]}