{"document":{"slug":"rec-20260903-5204","title":"Comments and Limited Protest of Southern Maryland Electric Cooperative, Inc. regarding PJM Interconnection, L.L.C.’s 08/13/2026 filing","issued":"2026-09-03","accession":"20260903-5204","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Southern Maryland Electric Cooperative, Inc.","kind":"protest","file":"sources/filings/text/20260903-5204_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5204","tier":"record","sha256":"18555bdf4e3ab0598a0a4e1968a1405d15b2a9d54ff76c842341d37a87219949","pages":15,"tokens":4119,"emptyPages":[],"textThemes":["registry","adequacy","flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":279,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n) \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \n \n \n) \n \nCOMMENTS AND LIMITED PROTEST OF \nSOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC.  \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (the “Commission”)1 and in accordance with the Commission’s \nCombined Notice of Filings notice issued August 13, 2026, Southern Maryland Electric \nCooperative, Inc. (“SMECO”)2 respectfully submits this Comments and Limited Protest regarding \nthe filing that PJM Interconnection, L.L.C. (“PJM”) submitted in the above-captioned docket on \nAugust 13, 2026 (the “IRAS Filing”).3 \nPJM proposes revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the \nReliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a new \n“Interim Resource Adequacy Service” (“IRAS”) and an associated “Large Load Registry.”  As \nproposed by PJM, IRAS is a supplemental capacity product through which Eligible New Large \nLoads may be directed by the Electric Distributor to reduce their load in response to an Interim \nResource Adequacy Service Action called by PJM.4  \n \n1 18 C.F.R. § 385.211 (2025). \n2SMECO is an electric distribution cooperative organized under the laws of the State of Maryland and is an “Electric \nDistributor,” as that term is defined in the PJM Amended and Restated Operating Agreement (“Operating \nAgreement” or “OA”), serving retail customers in Southern Maryland. In this proceeding, SMECO submitted, and \nthe Commission accepted a (doc-less) motion to intervene on August 25, 2026.  \n3Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Transmittal Letter of \nPJM Interconnection, L.L.C., Docket No. ER26-3515-000 (August 13, 2026) (“IRAS Filing”). \n4IRAS Filing at 74."},{"page":2,"startToken":279,"endToken":563,"text":"2 \nSpecifically, beginning with the 2027/2028 Delivery Year, IRAS would allow New Large \nLoads to interconnect without first securing capacity to cover their full demand, subject to a \ncondition: PJM may direct the Electric Distributor serving such a load to reduce an aggregate \nquantity of that load -- ahead of PJM’s existing Pre-Emergency Load Management Reductions -- \nwhen PJM determines that available real-time supply may be insufficient to maintain required \nreserves.5 \nSMECO’s comments and limited protest address certain aspects of the IRAS Filing, \nincluding whether the real-time Interim Resource Adequacy Service Action mechanism that Mr. \nChristopher Pilong’s affidavit describes will operate as PJM intends without exposing Electric \nDistributors’ core native load to curtailment, and further aspects in which Electric Distributors are \nassigned new operational, data-reporting, compensation-administration responsibilities and \nexposure to payments and default allocations for payments owed by other entities under PJM’s \nproposed billing indemnification provision. \nI. INTRODUCTION AND SUMMARY \nPJM’s IRAS proposal responds to the same capacity shortfall underlying PJM’s separate \nReliability Backstop Procurement (“RBP”) filing in Docket No. ER26-3380 – namely, that the \n2028/2029 Delivery Year Base Residual Auction cleared 6,831.3 MW short of the PJM Region \nReliability Requirement, a shortfall PJM attributes in substantial part to the rapid interconnection \nof large loads, including data centers.6 Where the RBP is a one-time capacity procurement, IRAS \nis a standing framework – i.e., it permits New Large Loads to connect to the PJM system ahead of \n \n5IRAS Filing at 74–77.  \n6IRAS Filing at 21 (describing the 2028/2029 Delivery Year Base Residual Auction shortfall); see also Reliability \nBackstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-\n3380-000, PJM Transmittal Letter at 2 (July 31, 2026)."},{"page":3,"startToken":563,"endToken":859,"text":"3 \nsecuring their own capacity, in exchange for exposing the uncovered portion of that load to \ncurtailment before PJM calls on Pre-Emergency Load Management Reductions.7  \nHowever, the IRAS Filing assigns Electric Distributors a series of new duties -- to execute \nIRAS Action directives, to help build and validate a data registry, to coordinate retail deployment \nof load reductions, and to implement a wholesale compensation program -- while leaving several \ndesign questions either unresolved or deferred to future PJM Manual revisions.  SMECO focuses \non the following issues: \n• New duties that proposed Tariff, Attachment DD-4 impose on Electric Distributors, \ncertain of go beyond the metering, data-reporting, and physical emergency-response \nfunctions historically assigned to Electric Distributors under the PJM Operating \nAgreement (“OA”). \n• A real-time Interim Resource Adequacy Service Action that directs an Electric \nDistributor to reduce its full, pre-assigned aggregate MW quantity without regard to \nwhether the underlying New Large Load is actually energized and taking service, risking \ncurtailment of the Electric Distributor’s existing, non-Large-Load native customers. \n• A billing indemnification provision8 that assigns Electric Distributors all of the risk that \nanother entity -- potentially an LSE with which the Electric Distributor has no affiliation \n-- fails to pay IRAS compensation it owes, with no PJM-level credit support of any kind. \n• Mechanics of the proposed Large Load Registry’s data-reporting mandate on Electric \nDistributors, that PJM proposes to defer to PJM Manual revisions that have not yet been \ndrafted; PJM’s proposal also identifies no mechanism for Electric Distributors to recover \nthe costs of Large Load Registry compliance. \nII. BACKGROUND \nPJM submitted the IRAS Filing on August 13, 2026, requesting that the Commission act \nby no later than October 12, 2026, so that PJM may begin implementing the Large Load Registry \n \n7IRAS Filing at 74–77. \n8 Proposed Tariff, Attachment DD-4, section X(b)(iii)"},{"page":4,"startToken":859,"endToken":1209,"text":"4 \nand the other proposed Tariff and RAA revisions on that date. IRAS itself would not become \navailable until the 2027/2028 Delivery Year, beginning June 1, 2027.9 \nPJM proposes to define “Large Load” as end-use customer load with a cumulative peak of \n50 MW or greater at a single electrical site, including affiliated load facilities within a one-mile \nradius under specified configurations.10 A “New Large Load” is a Large Load (or incremental load \nat an existing site) that enters service after June 1, 2027,11 and an “Eligible New Large Load” is a \nNew Large Load that has not entered into a “Bring Your Own New Capacity” (“BYONC”) \narrangement or has not been allocated UCAP MW through the RBP.12 \nIRAS is triggered when PJM determines that available economic real-time supply may not \nbe sufficient to maintain required reserves or applicable Interconnection Reliability Operating \nLimits.13 In that circumstance, PJM may issue an “Interim Resource Adequacy Service Action” \ndirecting the affected Electric Distributor to reduce an aggregate MW quantity of load -- based on \nthe zone/area’s pre-Delivery Year IRAS obligation -- before calling on existing Pre-Emergency \nLoad Management Reduction Actions.14  \nNotably, PJM will not itself identify which specific New Large Loads must reduce load; \nthat determination is left to the Electric Distributor, who in coordination with the relevant state \nand/or Electric Retail Regulatory Authority (“RERRA”), LSEs, and LSE customers, make that \n \n9IRAS Filing at 121-122. \n10IRAS Filing at 31 (quoting proposed RAA, Definitions — Large Load). \n11IRAS Filing at 1, FN 2 (quoting proposed Tariff, Definitions — New Large Load): New Large Load shall mean \nend-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) incremental \nload in-service after June 1, 2027, that increases the existing end-use customer load at a single electrical site that, \nprior to such incremental load, did not previously meet the definition of Large Load. \n12IRAS Filing at 38–41. \n13IRAS Filing at 74–75 (quoting proposed Tariff, Attachment DD-4, section I(b)). \n14IRAS Filing at 81-84; Affidavit of Christopher Pilong at para 52."},{"page":5,"startToken":1209,"endToken":1491,"text":"5 \ndetermination.15 PJM emphasizes that “an Interim Resource Adequacy Service Action will not be \nspecific as to which New Large Loads would need to be reduced; rather, it will be based on the \naggregate MW of reduction available from the Eligible New Large Loads in the zone/area.” 16 \nCompensation for IRAS load reductions is set at a wholesale rate of up to 50% of the \nexisting Non-Performance Charge Rate, but the rate can be reduced -- including to zero -- if the \nEligible New Large Load elects a lower or no payment in its retail rate.17 How that wholesale rate \nreaches an Eligible New Large Load, and how (or whether) it is funded at the retail level, is left to \nthe Electric Distributor, in conjunction with the applicable state authority or RERRA.18 \nTo administer both IRAS and the Large Load Registry, PJM’s proposal assigns Electric \nDistributors four (4) duties under proposed Tariff, Attachment DD-4, section III:  \n• Executing PJM’s Interim Resource Adequacy Service Action directives;  \n• Coordinating with PJM on Large Load Registry development, including by providing “any \ninformation or data the Electric Distributor believes appropriate to facilitate an accurate \nLarge Load Registry;”19  \n• Coordinating with the relevant state(s) or RERRA(s), LSEs, and LSE customers to support \n“transparent, effective, and orderly deployment” of IRAS;20 and  \n• Implementing the IRAS compensation program.21 \n \nRemainder of Page Intentionally Blank \n \n \n15IRAS Filing at 83. \n16IRAS Filing at 83-84.  \n17IRAS Filing at 101-102. \n18IRAS Filing at 104–107. \n19IRAS Filing at 26 (quoting proposed Tariff, Attachment DD-4, section III(b)). \n20IRAS Filing at 27 (quoting proposed Tariff, Attachment DD-4, section III(c)). \n21IRAS Filing at 27 (quoting proposed Tariff, Attachment DD-4, section III(d))."},{"page":6,"startToken":1491,"endToken":1910,"text":"6 \nIII. COMMENTS. \nA. PJM’s IRAS Proposal Assigns Significant New Electric Distributor Responsibilities. \nIn its IRAS Filing, Proposed Tariff, Attachment DD-4, section III requires that Electric \nDistributors “shall” fulfill four tasks: \n1. Execute IRAS Load Reductions. An Electric Distributor must “execute the Office of the \nInterconnection’s directives to implement Interim Resource Adequacy Service Actions.”22  \nSMECO does not object to this task, which is a natural extension of the Electric Distributor’s \nexisting Emergency-response role. \n2. Build and validate the Large Load Registry. An Electric Distributor must “provide PJM \nwith any information or data the Electric Distributor believes appropriate to facilitate an \naccurate Large Load Registry, including applicable state or RERRA retail tariff or contractual \nobligations,” and coordinate with PJM and the applicable Transmission Owner to “check the \nvalidity of the information provided.”23  \nThis task goes beyond OA section 11.3.3(h)’s data-reporting obligation, which speaks to data \n“necessary or appropriate to implement or administer” the OA and RAA themselves -- not to \nserving as a validation source for a registry whose contents is built on information originating \nwith LSEs or Large Loads that the Electric Distributor does not necessarily control.24 \n3. Identify which retail customers to curtail. An Electric Distributor must “coordinate, as \nappropriate, with the relevant state(s) or RERRA(s), individual [LSEs], and customers served \nby the [LSEs] in its zone/area to support transparent, effective, and orderly deployment” of \nIRAS.25 PJM characterizes this function as “memorializing” existing practice, under which \nElectric Distributors already determine, consistent with state programs, which loads to reduce \nin response to a PJM directive.26 \nWhile PJM OA sections 11.3.3(c) and (e) require an Electric Distributor to maintain load-\nshedding capability and to “[s]hed connected load … and take such other coordination actions \nas may be necessary in accordance with the directions of the Office of the Interconnection in \nEmergencies” -- an operational, physical-curtailment obligation27, PJM’s description of the \ncoordination duty as a “memorialization” of past practice does not change that Electric \n \n22IRAS Filing at 26 (quoting proposed Tariff, Attachment DD-4, section III(a)). \n23IRAS Filing at 26, 43 (quoting proposed Tariff, Attachment DD-4, section III(b); proposed RAA, Schedule 11, \nsection B.1(c)). \n24IRAS Filing at 36–37 (describing the LSE as the party with the initial obligation to submit Large Load Registry \ndata, with the Electric Distributor providing supplemental information). \n25IRAS Filing at 27 (quoting proposed Tariff, Attachment DD-4, section III(c)). \n26IRAS Filing at 27. \n27OA sections 11.3.3(c), (e)."},{"page":7,"startToken":1910,"endToken":2206,"text":"7 \nDistributors are, for the first time, being asked to administer eligibility and curtailment-priority \ndeterminations under an entirely new service category. \n4. Implement the IRAS compensation program. An Electric Distributor must “implement \n[a] compensation program consistent with Tariff, Attachment DD-4, section X.”28 It requires \nthe Electric Distributor to administer, collect for, and disburse a PJM wholesale-rate-linked \npayment obligation.  \nIV. LIMITED PROTEST. \nB. PJM’s Real-Time Interim Resource Adequacy Service Action Mechanism Does Not \nConfirm That the New Large Load Underlying an Electric Distributor’s Assigned \nObligation Is Actually Energized or Online, Risking Curtailment of Core Native Load. \nThe Affidavit of Christopher Pilong, submitted in support of the IRAS Filing, confirms \nthat the “[i]dentification of an IRAS requirement for each Electric Distributor’s zone/area \nestablishes the reliability obligation applicable to affected load,”29 and that “the IRAS requirement \nestablishes an operational reliability resource available to PJM, which can be called upon when \nactual system conditions indicate that the reliability need addressed by the IRAS requirement is \nmaterializing.”30  \nNothing in Mr. Pilong’s affidavit, however, ties PJM’s actual exercise of that authority in \nreal time to whether the New Large Load generating the obligation, in fact, is energized and taking \nservice. To the contrary, Mr. Pilong describes an Interim Resource Adequacy Service Action as a \ndirective to reduce a fixed, pre-set quantity of load at the Electric Distributor zone/area level, \ndetermined without regard to real-time large-load operating status.   \nSpecifically, the MW quantity of IRAS assigned to a given zone/area is fixed “prior to the \nstart of each Delivery Year,” and thereafter is simply the figure “utilized by PJM Dispatch in their \n \n28IRAS Filing at 27 (quoting proposed Tariff, Attachment DD-4, section III(d)). \n29 Affidavit of Christopher Pilong para 21. \n30Affidavit of Christopher Pilong para  22."},{"page":8,"startToken":2206,"endToken":2496,"text":"8 \nsystem projections, alerts and actions.”31 When PJM later calls an actual Interim Resource \nAdequacy Service Action, Mr. Pilong explains that PJM Dispatchers “will direct Electric \nDistributors to implement reductions in load up to, and capped at, the pre-Delivery Year IRAS \nobligations they were assigned” -- the pre-set figure, not a real-time measure of the underlying \nload’s actual consumption -- and that PJM “will not direct specific New Large Loads to reduce \nload” but instead “will only direct load reduction of an aggregate MW IRAS within the zone or \narea.”32 The affidavit describes PJM Dispatchers calling, in an RTO-wide emergency, “for some \nor all Electric Distributors to reduce load across the PJM RTO Region” based on “the maximum \nIRAS amounts assigned to each Electric Distributor zone/area” -- again with no reference to \nwhether the New Large Load behind that assignment is actually in service.33  \nThis is not a remote hypothetical. The New Large Loads whose lack of BYONC makes \nthem “Eligible” for IRAS treatment in the first place -- because, as described above, they have not \nsecured a BYONC arrangement and have not been allocated sufficient RBP UCAP MW34 -- are, \nas a structural matter, disproportionately likely to be projects still working through \ninterconnection, construction, or commissioning, rather than loads already drawing their full \nexpected demand, if any demand at all based upon the state of project development.  \nMr. Pilong’s affidavit also confirms that an Interim Resource Adequacy Service Action \n“prioritizes load reduction from those Electric Distributor zones/areas where New Large Loads \nhave not brought their own new capacity and do not have Allocated Reliability Backstop \n \n31Affidavit of Christopher Pilong para 28. \n32Affidavit of Christopher Pilong para 42. \n33Affidavit of Christopher Pilong para 43. \n34IRAS Filing at 38–41, 69."},{"page":9,"startToken":2496,"endToken":2777,"text":"9 \nProcurement Unforced Capacity Megawatts … sufficient to cover their capacity needs” -- the same \nunder-covered load that defines Eligible New Large Load status in the first place.35  \nAnd, because an Interim Resource Adequacy Service Action need not be preceded by any \nday-ahead alert -- Mr. Pilong acknowledges that “it is not a requirement that an Interim Resource \nAdequacy Service Alert be issued prior to an Interim Resource Adequacy Service Action”36 -- an \nElectric Distributor may have no advance opportunity to flag that its assigned New Large Load is \nnot yet in service before PJM’s Action issues. \nIf an Electric Distributor’s assigned New Large Load has not yet been energized -- or has \nonly begun a ramp or testing period well short of its expected draw -- at the time PJM issues an \nInterim Resource Adequacy Service Action, the Electric Distributor will nonetheless receive a \ndirective to reduce its full pre-Delivery Year MW quantity. Because that New Large Load is not \nconsuming power to reduce, and because the Interim Resource Adequacy Service Action is \ndirected to the Electric Distributor’s zone/area as a whole rather than to any specific load, the \nElectric Distributor’s only means of complying would be to curtail its core, non-Large-Load native \ncustomers.  \nThat outcome is the opposite of what IRAS is meant to achieve and would adversely impact \nSMECO’s ability to provide safe and reliable service on its electric distribution system to its \ncustomer-members. SMECO respectfully requests that the Commission direct PJM to clarify:  \n1. \nWhether an Electric Distributor’s obligation under an Interim Resource Adequacy \nService Action is capped by the New Large Load MW actually energized and taking \n \n35Affidavit of Christopher Pilong para 41. \n36Affidavit of Christopher Pilong para 34."},{"page":10,"startToken":2777,"endToken":3118,"text":"10 \nservice in its zone/area at the time of the Action, rather than by the full pre-Delivery \nYear assigned quantity;  \n2. \nIf clarification point #1 above is not capped as described, what safeguard, if any, \nprevents an Electric Distributor from being directed to reduce more load than its \ninterconnected, energized New Large Load represents, such that the Electric \nDistributor would be required to curtail core native load to comply; and  \n3. \nWhether PJM will commit to adjusting/suspending an Electric Distributor’s \nassigned IRAS obligation when the underlying New Large Load’s in-service date \nis delayed beyond what PJM assumed in setting the zone/area’s pre-Delivery Year \nquantity. \nC. The IRAS Filing’s Billing Indemnification Provision Shifts Compensation Default Risk \nto Electric Distributors, Including for Payments Owed by Other Entities. \nThe PJM Filing proposes “IRAS Compensation”, in which “Electric Distributors bear the \nresponsibility to implement the compensation scheme for New Large Loads that provide the IRAS \nload reduction service.”37   As noted above, PJM is proposing a rate for IRAS that is equal to 50% \nof the Non-Performance Charge Rate. Given that the current RTO-wide Non-Performance Charge \nRate is approximately $2,278/MWh (for the 2027/2028 Delivery Year), a new large load that did \nnot arrange for new capacity would be compensated for curtailing at a rate of over $1,100/MWh.  \nHowever, proposed Tariff, Attachment DD-4, section X(b)(iii) provides that “neither PJM nor the \nPJM membership, generally, is financially responsible for any potential defaults that may arise in \nassociation with the billing of” IRAS compensation.”38 Under this provision, if a state-approved \nrate requires collection of IRAS compensation from other LSEs, and an LSE does not pay as \nrequired -- “whether billed directly by the Electric Distributor or by PJM upon request of the \nElectric Distributor” -- “the default will not pass to the PJM membership,” and instead “any default \nshall be assessed to the Electric Distributor.”39 \n \n37 IRAS Filing at 101. \n38IRAS Filing at 108 (quoting proposed Tariff, Attachment DD-4, section X(b)(iii)). \n39IRAS Filing at 108–109."},{"page":11,"startToken":3118,"endToken":3454,"text":"11 \nPJM acknowledges that “in restructured states, the LSE may be an independent entity, not \naffiliated with the Electric Distributor.”40 Where that is so, an Electric Distributor directed to bill \n(or to request that PJM bill) another LSE for IRAS compensation would bear the full risk of that \nunaffiliated LSE’s non-payment, notwithstanding that the Electric Distributor has no ownership \nrelationship, and potentially no pre-existing commercial or credit relationship, with the paying \nLSE. PJM’s proposal includes no mechanism -- no collateral requirement or no PJM-administered \nmutualization -- to protect the Electric Distributor against that exposure. SMECO respectfully \nrequests that the Commission direct PJM to revise section X(b)(iii) to limit an Electric \nDistributor’s exposure to such circumstances. \nD. The Large Load Registry Rests on Key Details That PJM Proposes to Develop Only \nAfter the Registry Takes Effect, With No Identified Cost-Recovery Mechanism. \nProposed RAA, Schedule 11, section B.1(b) directs PJM to obtain Large Load Registry \ninformation from Electric Distributors, and proposed Tariff, Attachment DD-4, section III(b) \nrequires an Electric Distributor to supply “any information or data the Electric Distributor believes \nappropriate to facilitate an accurate Large Load Registry, including applicable state or RERRA \nretail tariff or contractual obligations.”41  PJM’s proposes that its Large Load Registry will contain \nthe following information about each Large Load in the PJM Region: \n• Eligible Customer/Network Customer for Large Load;  \n• Description of Large Load;  \n• Location(s) (Control Zone, Electric Distributor zone/area, where a zone/area is an area \nwithin a Zone for which the relevant Electric Distributor specifies a separate Obligation \nPeak Load MW value.  A zone/area is a service area of an Electric Distributor that is a \nseparately identifiable, geographic area bounded by wholesale metering); \n• In-service date for each increment of load;  \n• Peak shaving adjustment value pursuant to a state program codified in state law and \nwhether and how it meets the requirements of Tariff, Attachment DD-2;  \n \n40IRAS Filing at 105, FN 281. \n41IRAS Filing at 26 (quoting proposed Tariff, Attachment DD-4, section III(b)."},{"page":12,"startToken":3454,"endToken":3809,"text":"12 \n• Delivery point / Point(s) of interconnection (include all if more than one);  \n• Peak load quantity (MW) and ramp schedule, if applicable;  \n• Telemetry specifications;  \n• BYONC quantity (MW) and ramp schedule, if applicable;  \n• Allocated RBP UCAP MW quantity (MW), if applicable; \n• Backup generation (MW), including fuel type and relevant permitting limitations;  \n• Contracts or service agreements between the Large Load and the LSE;  \n• Points of contact at the applicable Transmission Owner, Electric Distributor, and Load \nServing Entity;  \n• EMS B1/B2/B3 name (for the applicable Transmission Owner, Electric Distributor); and  \nAdditional details and contents as necessary, in accordance with the PJM Manuals. 42 \nThe IRAS Filing, however, defers the mechanics of this mandate to PJM Manual revisions \nthat have not yet been reviewed. For example, among other items deferred to later development, \nPJM states that it “intends to develop provisions in its Manuals to implement the Large Load \nRegistry, as needed, including details about who may access the information and specific \nsafeguards in place to maintain the confidentiality of certain data.”43 \nElectric Distributors are thus asked to commit to an obligation whose scope, format, and \nconfidentiality protections will not be defined until after the Tariff and RAA revisions PJM \nproposes in the IRAS filing take effect.44 This timing is compounded by a liability concern PJM \nraises.  That is, submitters of Large Load Registry information are subject to the Commission’s \nprohibition on untrue statements or material omissions under FPA Section 222 and 18 C.F.R. Part \n1c, backed by civil penalties that can exceed $1.5 million per violation per day, and that “Sellers” \nadditionally owe a duty of candor to the Commission and to PJM under 18 C.F.R. § 35.41(b).45  \n \n42IRAS Filing at 37. \n43IRAS Filing at 43. \n44IRAS Filing at 121–122 (requesting an October 12, 2026 effective date for the Large Load Registry rules). \n45IRAS Filing at 44–45, citing FPA section 222, 16 U.S.C. § 824v; 18 C.F.R. §§ 1c.1(a), 1c.2(a), 35.36(a)(1), \n35.41(b); Civil Monetary Penalty Inflation Adjustments, Order No. 906, 190 FERC ¶ 61,006 (2025)."},{"page":13,"startToken":3809,"endToken":4009,"text":"13 \nHowever, much of the underlying data an Electric Distributor is asked to relay into the \nLarge Load Registry (see list above), will originate with the LSE serving the Large Load or with \nthe Large Load itself, neither of which the Electric Distributor necessarily controls or can \nindependently verify.46 PJM’s IRAS Filing does not clarify the scope of an Electric Distributor’s \npotential exposure under the above-noted anti-fraud and candor provisions for registry information \nit receives from, and relays on behalf of, third parties.  \nFinally, the IRAS Filing identifies no mechanism through which an Electric Distributor may \nrecover the costs (administrative and systems) of complying with the Large Load Registry’s data-\nsupply, validation, and coordination duties. SMECO respectfully requests that the Commission \ndirect PJM to (i) file the Manual provisions implementing the Large Load Registry’s data formats, \none-mile-site methodology, and confidentiality safeguards for review before -- not after -- the \nLarge Load Registry becomes effective; (ii) clarify the scope of an Electric Distributor’s potential \nliability for registry information sourced from LSEs or Large Loads; and (iii) identify a mechanism \nfor Electric Distributors to recover the reasonable costs of Large Load Registry compliance. \n \nRemainder of Page Intentionally Blank \n \n \n \n \n \n46IRAS Filing at 36–41."},{"page":14,"startToken":4009,"endToken":4071,"text":"14 \nV. CONCLUSION \nSMECO respectfully requests that the Commission consider SMECO’s Comments and \nLimited Protest in acting on PJM’s IRAS Filing. \nRespectfully submitted, \nDamon L. Krieger \nSenior Vice President, Legal and Strategy, and \nGeneral Counsel \nSouthern Maryland Electric Cooperative, Inc. \n15035 Burnt Store Road \nP.O. Box 1937 \nHughesville, MD 20637-1937 \n301.274.4323 \nDamon.Krieger@SMECO.coop \nDated: September 3, 2026."},{"page":15,"startToken":4071,"endToken":4119,"text":"15 \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served a copy of the foregoing document upon each \nparty on the official service list compiled by the Secretary of the Federal Energy Regulatory \nCommission in this proceeding. \n \n \n \nDated: September 3, 2026. \n \n \n \n \n \n \n \n /s/ _____ \nJohn S. Rohrbach"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1085,"startToken":0,"endToken":425},{"p":2,"at":1085,"title":"I. INTRODUCTION AND SUMMARY","method":"printed heading","endPage":3,"endAt":1787,"startToken":425,"endToken":812},{"p":3,"at":1787,"title":"II. BACKGROUND","method":"printed heading","endPage":6,"endAt":3,"startToken":812,"endToken":1492},{"p":6,"at":3,"title":"III. COMMENTS.","method":"printed heading","endPage":6,"endAt":19,"startToken":1492,"endToken":1494},{"p":6,"at":19,"title":"A. PJM’s IRAS Proposal Assigns Significant New Electric Distributor Responsibilities.","method":"printed heading","endPage":7,"endAt":456,"startToken":1494,"endToken":1969},{"p":7,"at":456,"title":"IV. LIMITED PROTEST.","method":"printed heading","endPage":7,"endAt":478,"startToken":1969,"endToken":1972},{"p":7,"at":478,"title":"B. PJM’s Real-Time Interim Resource Adequacy Service Action Mechanism Does Not","method":"printed heading","endPage":10,"endAt":694,"startToken":1972,"endToken":2884},{"p":10,"at":694,"title":"C. The IRAS Filing’s Billing Indemnification Provision Shifts Compensation Default Risk","method":"printed heading","endPage":11,"endAt":819,"startToken":2884,"endToken":3234},{"p":11,"at":819,"title":"D. The Large Load Registry Rests on Key Details That PJM Proposes to Develop Only","method":"printed heading","endPage":14,"endAt":4,"startToken":3234,"endToken":4010},{"p":14,"at":4,"title":"V. CONCLUSION","method":"printed heading","endPage":15,"endAt":6,"startToken":4010,"endToken":4072},{"p":15,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":15,"endAt":323,"startToken":4072,"endToken":4119}]}