{"document":{"slug":"rec-20260903-5207","title":"Limited Protest and Comments of FirstEnergy Service Company et al. in response to PJM Interconnection, L.L.C.’s 08/13/2026 filing to establish Interim…","issued":"2026-09-03","accession":"20260903-5207","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"FirstEnergy Service CompanyOhio Edison CompanyThe Cleveland Electric Illuminating Company ,The Toledo Edison Company ,FirstEnergy Pennsylvania Electric Company ,Jersey Central Power & Light Company ,Monongahela Power Company ,The Potomac Edison Company ,","kind":"protest","file":"sources/filings/text/20260903-5207_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5207","tier":"record","sha256":"9c13eea24f1e3d9e860394c3c555bc0b2da1da57a025cd6b64871e666cc1163b","pages":18,"tokens":5618,"emptyPages":[],"textThemes":["flex","retail","adequacy","registry"]},"pages":[{"page":1,"startToken":0,"endToken":286,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION  \n \nPJM Interconnection, L.L.C.   \n    ) \n \nDocket No. ER26-3515-000 \n \n \n \n \n \nLIMITED PROTEST AND COMMENTS OF  \nFIRSTENERGY SERVICE COMPANY \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or “Commission”),1 FirstEnergy Service Company, as agent for \nits affiliates (“FirstEnergy”),2 respectfully submits this Limited Protest and Comments in response \nto PJM Interconnection, L.L.C.’s (“PJM”) August 13, 2026 filing, proposing to establish an \nInterim Resource Adequacy Service (“IRAS”) mechanism.3 \nIn the Statement of Principles Regarding PJM (“Statement of Principles”), the National \nEnergy Dominance Council and 13 of the Governors of the PJM States joined together and \nidentified that there would be a class of new data centers that have not self-procured capacity or \nagreed to be curtailable.4  Under the Statement of Principles, this class of new data centers was to \nbe excluded from PJM’s procurement of new Capacity Resources.  PJM’s IRAS Proposal purports \nto outline how service is to be provided at the wholesale level to this class of data centers; the \nheadline being that these new data centers either must bring their own new capacity (“BYONC”) \nor be curtailable. \n \n1  \n18 C.F.R. § 385.211 (2025). \n2  \nFirstEnergy’s affiliates include Ohio Edison Company, The Cleveland Electric Illuminating Company, The \nToledo Edison Company, FirstEnergy Pennsylvania Electric Company, Jersey Central Power & Light Company, \nMonongahela Power Company, and The Potomac Edison Company. \n3  \nDocket No. ER26-3515, PJM, Proposal to Establish Interim Resource Adequacy Service and a Large Load \nRegistry to Address System Reliability (“PJM IRAS Proposal”). \n4  \nStatement \nof \nPrinciples \nRegarding \nPJM, \n1st \nand \n3rd \nbullets \n(1/16/26), \navailable \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm."},{"page":2,"startToken":286,"endToken":738,"text":"2 \nFirstEnergy agrees that new data centers that are not included within the scope of a PJM \ncapacity procurement must either bring their own new capacity or be curtailable.  Unfortunately, \nfundamental elements of PJM’s IRAS Proposal are fatally flawed and as a result these elements \ncannot be approved consistent with section 205 of the Federal Power Act (“FPA”).   \nSection 205 of the FPA provides that the Commission can accept PJM’s RPM proposal \nonly if it is just and reasonable and not unduly discriminatory or preferential.5  The filing utility—\nPJM—bears the burden of proof to demonstrate its proposal meets these FPA requirements.6  The \nCommission may accept PJM’s proposal only if there is sufficient evidence in the record to show \nPJM has carried its section 205 burden of proof.7  The Commission will reject any proposal that \nfalls outside the zone of reasonableness—i.e., does not result in just and reasonable rates in \naccordance with section 205.8  Moreover, even if a rate falls within the zone of reasonableness, it \nmay nevertheless violate section 205 due to being unduly discriminatory or preferential.9 \nIn these comments, FirstEnergy demonstrates that PJM’s IRAS Proposal does not meet the \nFPA section 205 “just and reasonable” standard because: \n1. PJM unlawfully is attempting to set retail rates by proposing that new data centers that are \nto be curtailable under the IRAS Proposal are to be paid to curtail; \n2. PJM is discriminating against new generation that aligns itself with a new data center by \nrequiring such new generation to participate in the RPM auctions for 10 years; \n \n5  \n16 U.S.C. § 824d(a)-(b). \n6  \nConstellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022); NorthWestern Corp. v. \nFERC, 884 F.3d 1176, 1182-83 (D.C. Cir. 2018); Midcontinent Indep. Sys. Operator, Inc., 194 FERC ¶ 61,050, at P \n23 (2026); Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC ¶ 61,236, at P 7 (2018). \n7  \n884 F.3d at 1182-84; Winnfield v. FERC, 744 F.2d 871, 876-77 (D.C. Cir. 1984); NorthWestern Corp., 147 \nFERC ¶ 61,049, at P 48 (2014). \n8  \nIndep. Power Producers of N.Y., Inc. v. FERC, 2022 U.S. App. LEXIS 22081, at * 6, 2022 WL 3210362 \n(D.C. Cir. Aug. 9, 2022) (citing Me. Pub. Utils. Comm'n v. FERC, 520 F.3d 464, 471 (D.C. Cir. 2008), rev'd on other \ngrounds, 558 U.S. 165 (2010); FCC v. Prometheus Radio Project, 141 S. Ct. 1150, 1158 (2021)). \n9  \nAla. Elec. Coop, Inc. v. FERC, 684 F.2d 20, 27 (D.C. Cir. 1982) (citing U.S. v. Cent. Ill. R.R., 263 U.S. 515, \n524 (1924))."},{"page":3,"startToken":738,"endToken":1056,"text":"3 \n3. PJM fails to align the timing of its IRAS Proposal with applicable Commission guidance; \nand \n4. Various of the implementing details are beyond the scope of the Statement of Principles \nand are unnecessary and/or inconsistent with other elements of the Commission’s \ndeveloping data center policies and directives, and thus must be dropped from PJM’s \neventual compliance filing. \nLIMITED PROTEST AND COMMENTS \nI. \nPJM is unlawfully attempting to set retail rates by proposing that new data centers that \nare to be curtailable under the IRAS Proposal are to be paid to curtail. \nAs the Commission is aware, its ratemaking jurisdiction is limited to interstate transmission \nand wholesale power sales.10  States regulate retail rates for retail customers.  And new data centers \nare retail customers.   \nThese broad principles notwithstanding, PJM has filed a tariff that calls for retail payments \nto be made when new data centers are curtailed.11  PJM even goes so far as to propose a retail rate \nthat is to be paid to the curtailing data center; although PJM leaves final determination of the \npayment amount in the hands of the jurisdictional state.12 \nThere is no basis under federal law for PJM to propose this rate.  PJM’s IRAS Proposal is \ncareful to exclude curtailable new data centers from its “Reliability Pricing Model” capacity \nprocurement.13  In fact, such loads are not participating directly in any PJM power market.  This \nis because they are retail loads.  It is true that Load-Serving Entities may buy power at wholesale \nfor resale for end-use consumption by a new data center.  But this does not mean that a curtailable \nnew data center is participating directly in PJM’s power markets.  As such, these loads do not \n \n10  \n16 U.S.C. §§ 824, 824d, 824e. \n11  \nPJM IRAS Proposal, Filing Letter, pp. 101, et seq., and the proposed tariff amendments described therein. \n12  \nId., p. 102. \n13  \nId., p. 55."},{"page":4,"startToken":1056,"endToken":1383,"text":"4 \nresemble “demand response” as that product is defined in the PJM tariffs or in applicable state \nretail programs.   \nThere is no policy guidance that calls PJM to create a Commission-jurisdictional \ncompensation mechanism for new data center loads that are to be curtailable.  As noted above, the \nStatement of Principles contemplates that certain new data centers will be curtailable.  But the \nStatement of Principles does not call for PJM to create a compensation mechanism to pay for such \nresources during periods of curtailment.  And PJM points to no other policy guidance that compels \ncreation of a rate that provides payments to the new data centers – that are retail customers – that \nare required to curtail during periods of capacity shortfalls. \nThe unlawful nature of PJM’s proposal is demonstrated by PJM’s implicit recognition that \nthe jurisdictional state authority must set the amount of the final payment.14  That PJM is calling \nfor states and LSEs to identify the other retail customers that are to fund such payments again \nreflects the fact that PJM’s proposal is about retail rates, even if it is dressed up as purported \namendments to a Commission-jurisdictional tariff.   \nThe tariff amendments that are embodied in PJM’s IRAS Proposal do not reflect the \njurisdictional boundary between the Commission and the states.  Indeed, the states must retain \ncontrol over determining the need for new power generation facilities, the economic feasibility of \nsuch facilities, and the rates and services to be provided by suppliers of the same.15  The \nCommission’s role is limited to regulating wholesale power sales.16  That is, the Commission can \nregulate a wholesale power market, as it does with PJM and the other RTOs.  But the Commission \ncannot direct a utility to build new generation, and it cannot establish retail rate recovery that can \n \n14  \nPJM IRAS Proposal, Filing Letter, p. 104. \n15  \nSee, e.g., Hughes v Talen, 136 S.Ct. 1288 at 1292 (US 2016). \n16  \n16 U.S.C. 824(b)(1)."},{"page":5,"startToken":1383,"endToken":1717,"text":"5 \npay for new generation.  And, just as FERC cannot establish a retail rate to pay for new generation, \nFERC cannot establish a retail rate that pays a new data center to curtail when there is not sufficient \ngeneration capacity available to serve that customer.  These functions are reserved for the states. \nMoreover, beyond the jurisdictional issues, the concept of compensating new large loads \nto curtail in the IRAS Proposal is deficient from a policy perspective and is contrary to the intent \nof the Statement of Principles which is to protect customers from the costs associated with \nintegrating large loads.  However, the IRAS Proposal, as designed, will in fact unjustly raise costs \nto retail customers with no corresponding benefits, and rewards imprudent owners of new large \nload facilities for their failure to procure new capacity to serve their own load.  PJM attempts to \nsmooth over this dynamic by pointing to the Ratepayer Protection Pledge as a mechanism to avoid \npassing costs associated with the IRAS Proposal on to retail customers.  The Ratepayer Protection \nPledge, however, is not a binding legal document and would not prevent new large loads from \nseeking compensation pursuant to the IRAS Proposal mechanisms. \nThus, for these reasons, the Commission must reject PJM’s attempt to create a retail rate \nas part of the IRAS Proposal. \nII. \nThe IRAS Proposal includes no justification for requiring BYONC generation \nresources to participate in RPM for 10 years, and the Commission should require \nPJM to drop this requirement. \nThere is no basis for PJM to create a minimum 10-year term for participation in the \nannual RPM auction for new BYONC resources.17  Although it is not spelled out, if a data center \naligns itself with a new generation resource, it is reasonable to assume that the data center has \nsigned a contract that is the basis for financing the new resources.  That is, the funding for a new \n \n17  \nPJM IRAS Proposal, Filing Letter, p. 55 and et seq. (and the tariff amendments described therein)."},{"page":6,"startToken":1717,"endToken":2041,"text":"6 \nBYONC generation resource should be understood to come from the commercial arrangements \nbetween the new data center and the generation resource.   \nIt is axiomatic that marginal-price market models do not pay for new capital investment \nin high cost-of-capital fields; an outcome that is reflected by the fact that marginal-price design \nRPM has brought very little significant new dispatchable generation in PJM.  The new data \ncenter, and not PJM’s RPM program, will be funding the capital investment in the new resource.  \nAs such, there is no need, or reason, to compel the new generation resources to be in the RPM \nauction for 10 years. \nIII. \nPJM is discriminating against new generation that aligns itself with a new data \ncenter by proscribing the opportunity for that resource to serve as a Fixed Resource \nRequirement generator. \nPJM proposes that new BYONC resources must participate in RPM.18  That is, PJM is \nforcing new Capacity Resources that are aligned with new data centers into the RPM market. \nThis is unduly discriminatory and preferential as it treats data centers and data center-\naligned new resources differently from new loads and generation that otherwise have the option to \nopt into a full or partial Fixed Resource Requirement (FRR). \nSection B of Schedule 8.1 of the PJM Reliability Assurance Agreement (RAA) sets forth \nthe terms under which a certain load may “opt out” of the RPM program by demonstrating that it \nis eligible for the FRR program.19  An eligible LSE must demonstrate that all or part of its load \nfalls within the RAA’s FRR Service Area definition (capable of being metered separately from \nother load), and that it has procured eligible Capacity Resources to cover that load and the FRR-\ndefined associated resource adequacy reserve requirement.  Importantly, because they are in an \n \n18  \nPJM IRAS Proposal, Filing Letter, p. 55 and et seq. (and the tariff amendments described therein). \n19  \nPJM Reliability Assurance Agreement, Schedule 8.1, B."},{"page":7,"startToken":2041,"endToken":2372,"text":"7 \nFRR “alternative,” eligible loads, and the associated generation, are not subject to the annual RPM \nauction. \nFirstEnergy agrees with PJM that new data centers can be established as a new class of \ncustomers that are subject to different capacity rules than other loads.20  However, there is no basis \nto obligate a new data center, and the new generation resources that have been procured to supply \nthat data center, to participate in the annual RPM auctions.  On the contrary, PJM’s IRAS proposal \ncontemplates that new data centers with associated new Capacity Resources in existing FRR areas \nwill be excluded from the RPM auction.  But PJM does not afford the opportunity for a new load \nwith associated new generation that is not in an existing FRR area to take advantage of the FRR \nopportunity. \nIf new data centers and associated new Capacity Resources in existing FRR areas are \nexempted from the RPM auction, then there is no basis to force new Capacity Resources that are \nnot in an existing FRR area to participate in the RPM auction.  On the contrary, given the vagaries \nof the RPM construct, prudent data center developers and associated developers of generation \nresources have every reason to demand that they be allowed to take advantage of the FRR \nalternative, and be afforded the opportunity to do so.  Requiring participation in the RPM auction, \nas PJM so proposes, is unduly discriminatory and preferential. 21 \nIV. \nPJM fails to align the timing of the IRAS Proposal with applicable Commission \nguidance. \nThe Statement of Principles provides policy guidance about the timing of the programs \ncontemplated therein.  Specifically, the Statement of Principles provides that PJM is to conduct a \n \n20  \nSee PJM IRAS Proposal, Filing Letter, p. 94 and et seq. (and the tariff amendments described therein). \n21  \n16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., \n263 U.S. at 524)."},{"page":8,"startToken":2372,"endToken":2710,"text":"8 \nReliability Backstop [Procurement] to procure new Capacity Resources for new data centers that \nhave not self-procured or agreed to be curtailable.22  Importantly, the policy guidance issued to \nPJM is to make changes for “new” data centers.  Existing data centers implicitly are grandfathered. \nPJM’s IRAS Proposal purports to apply to new data centers that go into service after June \n1, 2027.23  However, there could be a difference between “new” data centers and data centers that \ngo into service after June 1, 2027.  Specifically, it is possible that a developer of a data center may \nhave signed a construction agreement for new transmission network facilities before January 16, \n2026 and that due to the process of construction the data center may not go into service until after \nJune 1, 2027.  This customer is not “new” within the scope of the Statement of Principles and \nshould be grandfathered.  Importantly, the fact that these customers are not “new” within the \ncontemplated scope of the agreement could mean that attempting to apply the IRAS Proposal to \nthem could violate the filed rate doctrine because to do so would undermine preexisting \ncommercial relationships by attempting to allocate capacity market outcomes to data centers who \npossibly have already signed FERC-jurisdictional contracts based on a pre-IRAS Proposal \nunderstanding of the market. \nRelevant here is that PJM makes no effort to demonstrate that its proposal, at least for the \ncustomers described in the prior paragraph, is consistent with relevant Commission guidance.  \nSpecifically, in its June 18, 2026 Order to Show Cause, the Commission identified that certain \ndata centers were, as of the date of the Order, working with transmission owners and other relevant \nentities to take service from the transmission system.24  The Commission further identified that \nthere is a need to protect existing commercial arrangements, that stakeholders needed to ensure \n \n22  \nStatement of Principles, 3rd bullet. \n23  \nPJM IRAS Proposal, Filing Letter, p. 38 (and the tariff amendments described therein). \n24  \nPJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 105."},{"page":9,"startToken":2710,"endToken":3009,"text":"9 \nminimal disruption to existing commercial arrangements, and that stakeholders were to \nthoughtfully develop proposals to establish a reasonable amount of time to finalize agreements \nthat are nearing completion as of the date when tariff amendments were filed for Commission \napproval.25 \nPJM’s “one size fits all” IRAS Proposal does not protect against disruption to existing \ncommercial arrangements, and it makes no effort to establish a reasonable time to finalize \nagreements that are nearing completion as of the date when the IRAS Proposal was filed.  That is, \nPJM failed to align the timing of the IRAS Proposal with the Commission’s guidance about \nexisting and nearly final commercial arrangements.  As such, the Commission should reject PJM’s \n“one size fits all” date of “enters service after June 1, 2027,” and instead direct PJM to develop an \nIRAS Proposal effective date that does not disrupt existing commercial arrangements and that \nprovides sufficient notice so that stakeholders can complete contracting processes that are “in \nflight” as to the date of PJM’s future compliance filing. \nV. \nVarious of the implementing details are beyond the scope of the Statement of \nPrinciples and are unnecessary and/or inconsistent with other elements of the \nCommission’s developing data center policies and directives, and thus must be \ndropped from PJM’s eventual compliance filing. \nCertain aspects of PJM’s IRAS Proposal are not consistent with the express or implied \npolicy guidance that is provided in the Statement of Principles or other applicable Commission \nguidance.  As such, these details do not clear the “just and reasonable” legal standard for evaluating \ntariff amendments.  As outlined in the following sections, the Commission should require PJM to \naddress these instances by submitting further amendments in order to bring these instances into \nharmony with the Statement of Principles and the other applicable Commission guidance.   \n \n25  \nId."},{"page":10,"startToken":3009,"endToken":3330,"text":"10 \nA. The definition of “Large Load” should be adjusted, either to take the minimum \nmegawatt threshold to 200 MW, or to limit the definition to new data centers. \n \nAs relevant here, PJM proposes to define Large Loads as an end-use customer that has a \ncumulative peak of 50MW or greater.26  This definition will capture new data centers.  But it will \nalso capture small and medium-sized manufacturing facilities.   \n \nThe scope of the Statement of Principles document, which is the policy guidance that \nshould control for review of PJM’s IRAS proposal, is limited to new data centers.27  And for good \ncause.  It is true that similar energy infrastructure must be constructed without regard to whether \nthe new facility is a data center or a manufacturing facility.  But that is where the similarity ends.  \nManufacturing facilities generate numerous upstream, local and downstream investment and jobs; \nwhereas data centers do not.  That is, manufacturing facilities generate significant upstream, local \nand downstream benefits for workers, their communities, and the states that comprise PJM; \nwhereas the economic benefits of data centers are different and more limited. \nThere are material differences between a new data center and a manufacturing facility.  \nFirst, a new data center will generate many jobs during initial construction; but very few full-time \njobs post construction, whereas a new manufacturing facility will generate many permanent full-\ntime jobs.  Next, once it is up and running, the new data center will consume enormous amounts \nof energy, and that’s it.  In contrast, a new manufacturing facility will consume raw and somewhat \nprocessed materials; the extraction/processing/supply of such also will generate many full-time \njobs.  Importantly, each full-time job that is supported directly or indirectly by a manufacturing \nfacility will support a family.  And families own homes, pay taxes, and participate in communities. \n \n26  \nPJM IRAS Proposal, Filing Letter, p. 31, and the proposed tariff amendments described therein. \n27  \nStatement of Principles, 3rd bullet."},{"page":11,"startToken":3330,"endToken":3671,"text":"11 \n \nThe differences are not limited to jobs.  For example, data centers likely can be curtailed \non short notice with little consequence.  But there are consequences for curtailing manufacturing \nfacilities on short notice, including at least: upstream and downstream supply chain disruption; \nwork stoppages for affected workers; lost inventory that is stranded in the manufacturing process; \ndamage to manufacturing equipment; and cleaning and restarting of manufacturing equipment.   \n \nPJM is unable to demonstrate that it clears the FPA section 205 hurdle for including \nmanufacturing facilities within the scope of the IRAS proposal.  This is because it is unjust and \nunreasonable to include manufacturing facilities within scope.  Manufacturing facilities are not \nlike data centers, and they also are not within the scope of the Statement of Principles guidance.  \nAnd imposing what amounts to a “tax” on future operations will likely have the unintended \nconsequence of driving investment and jobs out of PJM and into regions of the country that are \nmore welcoming; that is, including manufacturing facilities within the scope of the IRAS proposal \nis unduly discriminatory and preferential28 against manufacturing facilities that are attempting to \nlocate or expand in PJM as compared to other regions.  As such, the Commission should direct \nPJM to either raise the MW threshold for IRAS applicability (to 200 MW) or refine the Large Load \ndefinition to limit the rule to new data centers. \nB. The criteria for the Large Load registry must match the criteria that are to be set \nforth in the pro forma agreement that is described in the Commission’s June 18, \n2026 Order to Show Cause.   \n \nThe Commission’s June 18, 2026 Order to Show Cause included a preliminary finding that \nPJM’s tariff appears to be unjust and unreasonable because it lacks a pro forma agreement that \nitemizes the terms and requirements under which a new data center would take transmission \n \n28  \n16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. \nR.R., 263 U.S. at 524)."},{"page":12,"startToken":3671,"endToken":3995,"text":"12 \nservice.29  Importantly, PJM and the Transmission Owners are to submit a compliance filing that, \namong other things, provides the pro forma agreement anticipated in the Order to Show Cause.30 \n \nIn the IRAS Proposal, PJM outlines the data that data centers must submit to be included \nin a contemplated “Registry.”31  FirstEnergy does not object to many of these criteria, but notes \nthat the criteria should not be finalized until the pro forma agreement and “registry” that are \ncontemplated in the Order to Show Cause are finalized. \nC. PJM should clarify that the Data Center, and not the Load-Serving Entity, is \nresponsible for certain compliance obligations.   \n \nPJM’s IRAS Proposal is filled with terms, requirements, obligations, and conditions that \nattach to data centers under the IRAS.  But, from time to time, PJM attempts to place some of these \nconditions on Load-Serving Entities.  For example, the IRAS Proposal provides that LSEs must \nbring new capacity or be subject to load reductions.32 \n \nPJM, no doubt, intended confusion concerning this aspect of the IRAS Proposal.  However, \nPJM’s language is confusing.  Sometimes the terms, requirements, obligations, and conditions are \ndescribed as pertaining to the new data center.  And, as noted, at other times, PJM suggests that \nthey pertain to the LSE. \n \nAssuming that at some future time some form of PJM’s IRAS Proposal is approved, the \nCommission can remedy this deficiency by directing PJM to clarify which entity holds the \nobligations.  For example, PJM could create new classes of LSEs and Electric Distribution \n \n29  \nSupra, n. 24 at P 65. \n30  \nFERC Docket No. EL26-67, PJM, Motion of PJM, fn 28 (PJM working with Transmission Owners on \ncompliance filing) (July 28, 2026); id., Letter Order, 196 FERC ¶ 61,129 (2026). \n31  \nPJM IRAS Proposal, Filing Letter, pp. 36 and et seq. (and the proposed tariff amendments described therein). \n32  \nPJM IRAS Proposal, Filing Letter, pp. 49 and et seq. (and the proposed tariff amendments described therein)."},{"page":13,"startToken":3995,"endToken":4275,"text":"13 \nCompanies – e.g., Data Center-Related LSEs/EDCs – and clarifying that the obligations attach to \nthese classes of entities. \nD. PJM should clarify that “Energy Resources” can be “new” Capacity Resources for \npurposes of evaluating a Data Center’s compliance with the proposed Bring Your \nOwn New Capacity option for removal from IRAS.   \n \nPJM proposes that new data centers can remove themselves – in whole or part – from the \nIRAS if the new data center brings new capacity.  PJM goes on, however, to clarify that a new \nCapacity Resource cannot be existing generation that is “repackaged.”33 \n \nIt is clear that PJM is attempting to ensure that existing Capacity Resources are not \nremoved from the Reliability Pricing Model markets and then paired with a new data center so that \nthe new data center can be removed from the IRAS.  However, there is a class of generating \nresources that currently are not Capacity Resources.  Specifically, PJM’s Open Access \nTransmission Tariff defines an “Energy Resource” as a Generating Facility that is not a Capacity \nResource.34  Energy Resources do not have RPM obligations, and receive no RPM revenues.  \nInstead, Energy Resources typically limit their power market participation to selling energy and \nancillary services into PJM’s day-ahead and real-time markets.  Because such resources are not \ncommitted to the RPM market, they are not Capacity Resources. \n \nThe Commission should direct PJM to allow Energy Resources to qualify as “new \ncapacity” for purposes of evaluating whether a data center can be removed from IRAS.  There is \nno basis to exclude Energy Resources.  Excluding such resources would be unduly discriminatory \n \n33  \nId. at p. 50 (and the tariff provisions described therein). \n34  \nPJM Open Access Transmission Tariff, definitions."},{"page":14,"startToken":4275,"endToken":4648,"text":"14 \nand preferential35 in that it would prohibit Energy Resources from entering the capacity market as \nsupply for the new data centers that wish to bring their own new capacity. \nE. There is no justification for dropping the IRAS rules if PJM has sufficient capacity \nto meet the RPM requirement for three consecutive years.   \nPJM proposes that the IRAS rules will not apply if PJM has sufficient capacity to meet the \nRPM requirement for three consecutive years.36  This proposal, however, is unjust and \nunreasonable as it would allow data center loads that are “new” after the termination of the IRAS \nrules to enter with the expectation of firm capacity supply.  There is no basis to expect that such \nfirm supply will exist.  PJM itself admits that its current capacity resource shortfall is at least 6,831 \nMW.37  And the Statement of Principles notes that PJM must procure new Capacity Resources to \nserve new data centers that do not self-supply or agree to be curtailable.38  The Statement of \nPrinciples does not authorize PJM to allow new data centers to enter the market when there is not \nsufficient supply.  And new data centers now range from hundreds to more than a thousand \nmegawatts of demand.39  This is not the incremental load growth for which the RPM construct was \ndesigned.  The mere fact that the RPM market has cleared for three consecutive years does not \nmean that there is enough “headroom” to absorb hundreds or possibly thousands of new megawatts \nof new load.  Moreover, this proposal is unjust and unreasonable in that it allows “new” data \ncenters that enter the market after termination of the IRAS rules to ride on the capacity that is being \n \n35  \n16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., \n263 U.S. at 524). \n36  \nPJM IRAS Proposal, Filing Letter, p. 52 and et seq. (and the tariff amendments described therein) \n37  \nFERC Docket No. ER25-3380, PJM, RBP Filing Letter, p. 31. \n38  \nStatement of Principles, 3rd bullet. \n39  \nSee Data Centers and Their Energy Consumption, Library of Congress (2026), available \nhttps://www.congress.gov/crs-product/R48646."},{"page":15,"startToken":4648,"endToken":5016,"text":"15 \npaid for by other customers.  In other words, this proposal is unduly discriminatory and preferential \nin favor of the new “free riding” data centers.40 \nF. There is no justification for requiring BYONC generation resources to participate \nin RPM for 10 years, and the Commission should require PJM to drop this \nrequirement.   \n \nThere is no basis for PJM to create a minimum 10-year term for participation in the annual \nRPM auction for new BYONC resources.41  Although it is not spelled out, as the impetus for \nfunding a new BYONC resource should be understood to come from the commercial arrangements \nbetween the new data center and the generation resource.  It is axiomatic that marginal-price \nmarkets models do not pay for new capital investment in high cost-of-capital fields; an outcome \nthat is reflected by the fact that marginal-price design RPM has brought very little significant new \ndispatchable generation in PJM.  The new data center, and not PJM’s RPM program, will be \nfunding the capital investment in the new resource.  If there is to be a minimum term, it should be \nset at a minimum term for the new data center to be removed from the IRAS program, and not on \nthe basis that the data center brought new generation.   \nG. PJM must provide additional clarification regarding the new data centers that \nqualify for reduced IRAS due to being allocated a share of the Reliability Backstop \nProcurement megawatts.   \nPJM proposes that a new data center that could be subject to the IRAS can have its IRAS \nobligations reduced or eliminated by virtue of being allocated a share of the new Capacity \nResources that are to be procured through PJM’s proposed “Reliability Backstop Procurement” \n(RBP).42  Given, however, that the RBP capacity is to be allocated to data center loads that were \n \n40  \n16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., \n263 U.S. at 524). \n41  \nPJM IRAS Proposal, Filing Letter, p. 55 and et seq. (and the tariff amendments described therein). \n42  \nPJM IRAS Proposal, Filing Letter, p. 67 and et seq. (and the tariff provisions described therein)."},{"page":16,"startToken":5016,"endToken":5346,"text":"16 \nincluded in forecasts from 2025 that are the basis for the RBP cost allocation,43 PJM should clarify \nthat a new data center can have its IRAS obligation reduced or eliminated only if the data center \nwas included in the 2025 forecast that is the basis of the RBP procurement.  To do otherwise would \nbe unduly discriminatory and preferential to other similarly situated data centers that retain IRAS \nobligations.44 \nH. IRAS obligations must be allocated to data centers that did not agree to be \ncurtailable.   \nPJM proposes to reallocate IRAS curtailment obligations annually.45  That is, PJM \nproposes to reallocate curtailment obligations annually based on the level of the capacity shortfall \nfor a given region.  As capacity shortfalls ebb and flow, PJM will reallocate curtailment \nobligations.  The proposal is unduly discriminatory and preferential as it could allow new data \ncenters that did not bring their own generation to avoid curtailment based on market activity of \nother market participants.   \nThe Statement of Principles, which is the policy guidance that should control for review of \nPJM’s IRAS proposal, provides that new data centers either must participate in the RBP, or bring \ntheir own generation, or agree to be curtailable.46  It does not allow a data center to exit a \ncurtailment obligation because, through the activity of some other market participant, the region \nin which the data center is not located no longer is net-short of capacity.  And, under PJM’s \nproposal, the “net short” conditions will change because either other loads exited the region or \nbecause unaffiliated new Capacity Resources entered the region. \n \n43  \nFERC Docket No. ER25-3380, PJM, Filing Letter, p. 103. \n44  \n16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. R.R., \n263 U.S. at 524). \n45  \nPJM IRAS Proposal, Filing Letter, p. 70 and et seq. (and the tariff provisions described therein). \n46  \nStatement of Principles, 3rd bullet."},{"page":17,"startToken":5346,"endToken":5565,"text":"17 \nIn short, PJM is proposing to allow certain data centers to benefit from actions of \nunaffiliated third parties.  This is the definition of undue discrimination and preferential \ntreatment;47 especially as compared to the other new data centers that will remain subject to the \nIRAS requirement.  The policy guidance provided in the Statement of Principles is clear - if a new \ndata center is not subject to the RBP, and does not bring its own new capacity, then it is curtailable.  \nThe Commission should direct PJM to drop this unjust and unreasonable proposal as part of PJM’s \ncompliance filing. \nIII. \nCONCLUSION \nFirstEnergy respectfully requests that the Commission consider the foregoing comments \nand protest in its consideration of PJM’s IRAS Proposal, and direct PJM to amend its proposal in \na manner that corrects the issues as discussed above and to submit a compliance filing within a \nreasonable timeframe. \n \n \n \n \n \n \nRespectfully submitted, \n/s/___Evan K. Dean_____________ \nMorgan Parke  \nVice President - Associate General Counsel \nEvan K. Dean  \nManaging Counsel \nFirstEnergy Service Company  \n341 White Pond Drive  \nAkron, Ohio 44320  \n(330) 942-2519  \nedean@firstenergycorp.com \n \nCounsel for FirstEnergy Service Company \n \n \n47  \n16 U.S.C. § 824d(a)-(b); see also Ala. Elec. Coop, Inc. v. FERC, 684 F.2d at 27 (citing U.S. v. Cent. Ill. \nR.R., 263 U.S. at 524)."},{"page":18,"startToken":5565,"endToken":5618,"text":"CERTIFICATE OF SERVICE \nI certify that I have served the foregoing document on each person designated on the official \nservice list compiled by the Secretary of the Commission in this docket. \n \n \n \nRespectfully submitted,  \nEvan K. Dean______________ \nEvan K. Dean \nManaging Counsel \nedean@firstenergycorp.com \nCounsel for FirstEnergy Service Company \n \nDate: September 3, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":417,"startToken":0,"endToken":802},{"p":3,"at":417,"title":"I. PJM is unlawfully attempting to set retail rates by proposing that new data centers that","method":"printed heading","endPage":5,"endAt":1368,"startToken":802,"endToken":1601},{"p":5,"at":1368,"title":"II. The IRAS Proposal includes no justification for requiring BYONC generation","method":"printed heading","endPage":6,"endAt":648,"startToken":1601,"endToken":1821},{"p":6,"at":648,"title":"III. PJM is discriminating against new generation that aligns itself with a new data","method":"printed heading","endPage":7,"endAt":1442,"startToken":1821,"endToken":2278},{"p":7,"at":1442,"title":"IV. PJM fails to align the timing of the IRAS Proposal with applicable Commission","method":"printed heading","endPage":9,"endAt":1112,"startToken":2278,"endToken":2880},{"p":9,"at":1112,"title":"V. Various of the implementing details are beyond the scope of the Statement of","method":"printed heading","endPage":10,"endAt":4,"startToken":2880,"endToken":3010},{"p":10,"at":4,"title":"A. The definition of “Large Load” should be adjusted, either to take the minimum","method":"printed heading","endPage":11,"endAt":1506,"startToken":3010,"endToken":3557},{"p":11,"at":1506,"title":"B. The criteria for the Large Load registry must match the criteria that are to be set","method":"printed heading","endPage":12,"endAt":542,"startToken":3557,"endToken":3760},{"p":12,"at":542,"title":"C. PJM should clarify that the Data Center, and not the Load-Serving Entity, is","method":"printed heading","endPage":13,"endAt":129,"startToken":3760,"endToken":4014},{"p":13,"at":129,"title":"D. PJM should clarify that “Energy Resources” can be “new” Capacity Resources for","method":"printed heading","endPage":14,"endAt":180,"startToken":4014,"endToken":4305},{"p":14,"at":180,"title":"E. There is no justification for dropping the IRAS rules if PJM has sufficient capacity","method":"printed heading","endPage":15,"endAt":158,"startToken":4305,"endToken":4674},{"p":15,"at":158,"title":"F. There is no justification for requiring BYONC generation resources to participate","method":"printed heading","endPage":15,"endAt":1249,"startToken":4674,"endToken":4857},{"p":15,"at":1249,"title":"G. PJM must provide additional clarification regarding the new data centers that","method":"printed heading","endPage":16,"endAt":422,"startToken":4857,"endToken":5087},{"p":16,"at":422,"title":"H. IRAS obligations must be allocated to data centers that did not agree to be","method":"printed heading","endPage":17,"endAt":605,"startToken":5087,"endToken":5445},{"p":17,"at":605,"title":"III. CONCLUSION","method":"printed heading","endPage":18,"endAt":0,"startToken":5445,"endToken":5565},{"p":18,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":18,"endAt":378,"startToken":5565,"endToken":5618}]}