{"document":{"slug":"rec-20260903-5209","title":"Comments of Calibrant Energy requesting clarifications of PJM Interconnection, L.L.C.’s proposal filed on 08/13/2026","issued":"2026-09-03","accession":"20260903-5209","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Calibrant Energy","kind":"rehearing request","file":"sources/filings/text/20260903-5209_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5209","tier":"record","sha256":"a84228e4004e6a8e512b52f2a9ccabe5f0856b9c887a931554e1d49983afc097","pages":13,"tokens":3640,"emptyPages":[],"textThemes":["colo","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":333,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n) \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \n) \n \nCOMMENTS OF CALIBRANT ENERGY \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (Commission) \nRules of Practice and Procedure,1 Calibrant Energy (Calibrant) respectfully submits these \ncomments requesting clarifications of PJM Interconnection, LLC’s (PJM) proposed revisions to \nits Open Access Transmission Tariff (Tariff) and the Reliability Assurance Agreement Among \nLoad Serving Entities (RAA) to establish Interim Resource Adequacy Service (IRAS) rules and \nprocedures.2 Calibrant seeks only a narrow subset of clarifications to provide the regulatory \ncertainty needed to ensure that the IRAS proposal incentivizes the entry of any and all resources \nthat are able to help address PJM’s resource adequacy challenges.  \nCalibrant develops energy generation and storage assets throughout the United States, \nincluding in the PJM footprint. Calibrant participated in PJM’s stakeholder process to ensure that \n \n1 18 C.F.R. § 385.211. \n2 Throughout these comments, Calibrant requests that aspects of PJM’s filing be clarified to \naddress ambiguities in the proposed Tariff and RAA revisions, so as to provide greater clarity to \nmarket participants. As explained herein, Calibrant understands these requests to be consistent \nwith the policy direction intended by PJM and communicated to stakeholders in the PJM \nstakeholder process. Calibrant believes that these clarifications can be made by PJM directly, in \nthis docket or otherwise, and respectfully submits that such sua sponte clarification would be the \nmost straightforward and efficient option. However, to the extent PJM determines that sua sponte \nclarification is not practicable, or otherwise does not affirmatively provide such clarification, \nCalibrant directs its requests to the Commission on the grounds that, as further discussed in these \ncomments, the PJM proposal risks unjustness, unreasonableness, and undue discrimination \nabsent the requested clarifications. To that end, Calibrant notes that PJM “consents to the \nCommission’s exercise of authority to modify and/or sever any element of the proposed Tariff \nand RAA language to the extent necessary and permitted.” Transmittal Letter at 9."},{"page":2,"startToken":333,"endToken":581,"text":"2 \nbehind-the-meter energy storage projects (with or without generation)—which are new “steel-in-\nthe-ground” assets capable of reliably serving the long-term capacity needs of the region with a \nfaster development timeline than front-of-the-meter new capacity resources—are fully eligible to \nprovide Bring Your Own New Capacity (BYONC) by supporting Demand Resource \nparticipation.  \nCalibrant supports PJM’s proposal to allow loads to avoid IRAS exposure via Demand \nResource BYONC. Calibrant appreciates PJM’s engagement during the stakeholder process and \nPJM’s recognition of the potential for behind-the-meter projects to help address the region’s \nresource adequacy challenges. Inclusion of Demand Resource BYONC eligibility is fundamental \nto the IRAS proposal’s ability to incent bilateral contracting to bring new capacity online in a \nnon-discriminatory manner. To ensure that PJM’s proposal incents as much entry of new capacity \non the system as possible, however, Calibrant seeks clarification of several aspects of PJM’s \nproposal, which, as drafted, increase contracting risk and would accordingly discourage \ninvestment. Specifically, Calibrant requests clarification that: \n• Incremental Demand Resource capacity at sites that are currently providing or \nhave previously provided capacity, enabled by registration of new on-site \ngeneration or storage installations, is eligible to provide BYONC; \n• New Large Loads and the BYONC that they contract with satisfy their obligations \nunder the IRAS framework by providing capacity for the 10-year duration of the \nBYONC’s Reliability Pricing Model (RPM) obligations; \n• The demonstrations over the 10-year period that Demand Resources providing \nBYONC are required to make need only be made on an installed capacity (ICAP) \nbasis."},{"page":3,"startToken":581,"endToken":859,"text":"3 \nProviding these clarifications will increase regulatory certainty for potential developers, thereby \nfacilitating greater BYONC participation and reducing the need for involuntary IRAS \ncurtailment. They will also ensure comparable treatment across similarly situated resource types, \nincentivizing the entry of any and all resources that are able to help address PJM’s resource \nadequacy challenges. \nCalibrant also recognizes that PJM’s IRAS framework contemplates continued \ncoordination with the states to ensure faithful, effective, cost-minimizing implementation. In \nparticular, clear and consistent retail tariff treatment, which resides within the clear jurisdiction \nof the states, is paramount to reducing contracting risk between New Large Loads and potential \nBYONC developers, thereby encouraging entry of new capacity onto the system to address \nresource adequacy challenges. Calibrant stands ready to support those efforts.  \nI. \nREQUIRED CLARIFICATIONS \nA. \nCalibrant requests clarification that incremental Demand Resource capacity \nat prior-participating locations may provide BYONC. \nPJM proposes to allow Demand Resources or DER Capacity Aggregation Resources to \nserve as BYONC under two circumstances: (1) the Demand Resource or DER Capacity \nAggregation Resource is composed of locations that did not previously support a Capacity \nResource (or participate as Peak Shaving Adjustment or Price Responsive Demand), or (2) the \nDemand Resource or DER Capacity Aggregation Resource is composed of “any location not \nregistered in or prior to the 2026/2027 Delivery Year at which an incremental amount at that \nlocation is the result of the registration of new generation or storage assets at the location” (at \nleast until the capacity market restabilizes, resetting the deadline from which prior-participation \nis measured).3 This second participation pathway is not clear. In order to give this provision \n \n3 Proposed Attach. DD-4 § VI(b)(ii) (emphasis added)."},{"page":4,"startToken":859,"endToken":1153,"text":"4 \nindependent effect and based on PJM’s position in stakeholder discussions, Calibrant believes \nthat PJM intended this provision to allow prior-participating Demand Resources and Distributed \nEnergy Resource (DER) Capacity Aggregation Resource to offer incremental BYONC capacity \nwhere enabled by registration of new generation or storage resources at the location. Clarifying \nthis intent will incent the new entry of reliable capacity supported by new behind-the-meter \nresources and avoid otherwise unnecessary involuntary curtailment exposure. In addition, \nCalibrant requests clarification that the “incremental amount” of Demand Resource capacity \nsupported by installation of new behind-the-meter resources will be measured against the \nDemand Resource’s most recent participation level.  \nAbsent such clarification, PJM’s proposed second qualification pathway for Demand \nResources is confusing.4 It is not clear how new generation or storage could provide incremental \ncapacity at a location that has never before participated. “Incremental” usually would imply \nadditional capacity on top of existing capacity. Otherwise, it would just be new Demand \nResource or DER capacity, not incremental capacity. Moreover, such new Demand Resource or \nDER capacity can already participate under PJM’s other proposed participation pathways for \nlocations that have not previously participated in the PJM capacity construct—whether or not \nsupported by new generation or storage. To give the incremental participation provision \nindependent meaning, it must allow for some form of participation that adds to the other option, \ni.e., at some locations that have participated in the RPM in prior Delivery Years. Thus, the most \nnatural reading of the language is that the limit on prior year registration is a bar on BYONC \nqualification only to the extent underlying storage and generation assets previously supported the \nregistration (i.e., where such storage and generation is not new). Where the storage and \n \n4 See id. § VI(b)(ii)(1)."},{"page":5,"startToken":1153,"endToken":1372,"text":"5 \ngeneration enable incremental, previously-unregistered capacity, such capacity should be clearly \neligible to serve as Demand Resource BYONC. \nStakeholder conversations with PJM staff and PJM’s marked tariff redline included as \nAttachment A to its filing help to square this circle. In discussions with Calibrant, PJM staff \nexplained that it intended to allow Demand Resources at locations that had previously \nparticipated in the PJM capacity market if new behind-the-meter generation or storage \ninvestments enable additional incremental Demand Resource capability. PJM’s marked tariff \nredline suggests potential confusion as to how best to provide for this result: the redlines, which \nare supplied in two different colors, suggest that a second author may have revised this proposal \nfrom a requirement that Demand Resource BYONC could “be composed of, or reliant on, any \nlocation registered in the 2026/2027 Delivery Year at which an incremental amount at that \nlocation is the result of the registration of new generation or storage assets at the location” to one \nwhere Demand Resource or DER BYONC may only be composed of “any location not \nregistered in or prior to the 2026/2027 Delivery Year . . . .”5\n \n \n5 PJM Transmittal, Attachment A, Revisions to the PJM Open Access Transmission Tariff and \nResource Adequacy Agreement (Marked/Redline Format), at Proposed Attach. DD-4 § \nVI(b)(ii)(1) (pdf page 100) (emphasis added)."},{"page":6,"startToken":1372,"endToken":1729,"text":"6 \nCalibrant respectfully asks for clarification that this insertion is not intended to prohibit \nDemand Resources that previously participated in the RPM from providing BYONC by \ninstalling reliable, steel-in-the-ground behind-the-meter storage or generation resources to enable \nadditional demand flexibility. Clarifying proposed Tariff Attachment DD-4 section VI(b)(ii)(1) in \nthis way will allow existing large commercial and industrial customers that have previously \nprovided Demand Resource capacity but that can increase their capabilities by installing new \nbehind-the-meter resources to be part of the solution to PJM’s historic resource adequacy \nchallenges. Such an all-hands-on-deck approach is consistent with PJM’s goals in the IRAS \nfiling of encouraging New Large Loads to cover their needs by bringing their own new capacity \nto the market.  \nTo the extent necessary, Calibrant requests that the Commission direct PJM to revise its \nproposed Tariff to provide this clarification on the basis that the provision as drafted is (1) unjust \nand unreasonable because it is unclear6 and (2) unduly discriminatory or preferential because it \nwould exclude resources that are similarly situated to new front-of-meter generation and storage \nassets in their ability to allow New Large Loads to mitigate the region’s resource adequacy crisis \nby bringing their own new capacity. The Commission could require such modifications while \naccepting the remainder of PJM’s proposal given PJM’s express notice “that it consents to the \n \n6 See Boston Edison Co., 98 FERC ¶ 61,292, at P 21 (2002) (The Commission “has an interest in \nensuring that tariffs clearly, completely and unambiguously identify services, rates and terms and \nconditions. The Commission thus frequently rejects proposed tariff language as unclear”); \ncf. Dominion Energy Mktg., Inc., 155 FERC ¶ 61,121, at P 21 (2016) (“We find that the lack of \nclarity regarding the process for new incremental capacity and existing capacity at the same \nresource to participate in the [Forward Capacity Auction] fails to provide reasonable notice to \nmarket participants of the requirements, and is therefore, unjust and unreasonable.”); see \nalso PJM Interconnection, 137 FERC ¶ 61,108 (2011); Entergy Serv. Co., 106 FERC ¶ 61,039 \n(2004); Toledo Edison Co., 78 FERC ¶ 61,013 (1997); Detroit Edison Co., 77 FERC ¶ 61,279 \n(1996)."},{"page":7,"startToken":1729,"endToken":2023,"text":"7 \nCommission’s exercise of authority to modify and/or sever any element of the proposed Tariff \nand RAA language to the extent necessary and permitted . . . where such modification and/or \nseverance is consistent with PJM’s overarching objectives in this filing.”7 Allowing incremental \nDemand Resource capacity to qualify as BYONC where facilitated by new generation or storage \nassets at locations that have previously registered would further PJM’s broader objectives by \nencouraging steel-in-the-ground investments to increase the amount of capacity that existing \nDemand Resources can reliably provide, reducing the need for involuntary curtailment. \nIn addition, Calibrant requests clarification of how PJM will determine the baseline \nagainst which it will measure the “incremental amount” of Demand Resource capacity that a \nbehind-the-meter investment allows at a prior-participating location if that Demand Resource’s \nparticipation has decreased from prior levels. Calibrant believes that this provision should be \nread to allow a prior-participating Demand Resource that has since deactivated, reduced its \nparticipation, or experienced UCAP degradation to provide capacity incremental to its most \nrecent level of participation by installing new behind-the-meter resources. Measuring \nincremental additions in this way would produce a result similar to PJM’s proposal to allow \nrepowered generation facilities to provide BYONC8 because it would allow a Demand Resource \nthat “deactivated” to provide BYONC in the full amount of its capacity enabled by new behind-\nthe-meter assets, like the BYONC eligibility of a repowered generator that is credited for \nBYONC purposes based on its full capacity value and not only for capability above its prior \ncapacity. For example, take a load that previously provided 50 MW of Demand Resource \ncapacity but then withdrew from capacity market participation, providing 0 MW in the most \n \n7 Transmittal Letter at 9.  \n8 See Proposed Tariff, Attach. DD-4, § VI(b)(i)(4)."},{"page":8,"startToken":2023,"endToken":2345,"text":"8 \nrecent Delivery Year. If that load then registered a new behind-the-meter battery to provide 100 \nMW of Demand Resource capacity, PJM should treat the Demand Resource as providing 100 \nMW of incremental capacity and therefore 100 MW of BYONC—like the storage asset would be \ntreated if interconnecting in front of the meter—rather than only 50 MW of incremental capacity.  \nMeasuring the incremental amount of capacity enabled by behind-the-meter investments \nfrom the most recent non-participation baseline will provide a clearer incentive to invest in \nbehind-the-meter projects and renew participation, reducing the need for involuntary curtailment. \nCrediting incremental contributions enabled by behind-the-meter investments only to the extent \nthat they exceed the maximum amount previously offered would conversely substantially mute \nexisting and deactivated Demand Resources’ incentives to invest in this needed capacity.  \nB. \nCalibrant requests clarification that a New Large Load and BYONC’s \nobligations under the IRAS program extend at most only through the required 10 \nyears of RPM participation. \nPJM proposes to require that “BYONC that is in an arrangement with a New Large Load \nmust remain in such arrangement with that New Large Load unless and until the New Large \nLoad is permanently out-of-service.”9 Calibrant seeks clarification, based on PJM’s statements in \nits transmittal letter and other parts of the proposed Tariff, that this tariff proposal is meant only \nto prohibit BYONC transferability and not to suggest that a BYONC must remain in service for \nthe life of the New Large Load that it serves.  \nPJM explains in its transmittal that it proposes to require a BYONC to remain in an \narrangement with its New Large Load for the life of the load to effectuate its “propos[al] that \nonce the subject of an arrangement[,] BYONC cannot change to a different New Large Load—\ni.e., BYONC is non-transferable.”10 That is, proposed Tariff Attachment DD-4 section VII(e) is \n \n9 Id. § VII(e). \n10 Transmittal Letter at 64."},{"page":9,"startToken":2345,"endToken":2653,"text":"9 \nmeant only to prohibit a BYONC resource from later serving another New Large Load, and not \nto require a BYONC serving a New Large Load to remain in service for the lifetime of the \nload—a requirement that no new resource could reasonably commit to.  \nUnder this reading, the term through which the BYONC is responsible to cover the New \nLarge Load’s registered peak load instead extends only to, at maximum, the 10-year period \nduring which the BYONC is subject to capacity must-offer requirements under proposed Tariff \nAttachment DD-4 section VIII(b).11 This reading accommodates PJM’s express \nacknowledgement in its proposed Tariff that sellers of Demand Resources and DER Capacity \nAggregation Resources BYONC may replace their BYONC capacity with other qualifying \nBYONC for the remainder of the original BYONC’s 10-year RPM Auction participation \ncommitment.12 Replacing a resource for RPM purposes would not be reconcilable with a reading \nof proposed Tariff Attachment DD-4 section VII(e) that requires a given BYONC to remain in an \narrangement with the New Large Load for the life of the load unless the load has retired \nunusually early. \nCalibrant therefore respectfully requests clarification that a BYONC’s duty to remain in \nservice under the proposed Tariff extends only to the duration of its RPM must-offer \nresponsibilities. Put differently, “once BYONC is in an arrangement with a New Large Load”—\nand BYONC completes its RPM must-offer obligations under proposed Tariff Attachment DD-4, \nsection VIII, “the New Large Load gets the benefit of ‘bringing’ this new capacity to the system \nand permanently reduces its availability to provide Interim Resource Adequacy Service by the \n \n11 Proposed Tariff, Attach. DD-4 § VIII(b); see also id. §§ VIII(e) & (f) (referencing Attach. DD-\n4 § IV(b)(iii)) (relieving BYONC their must-offer obligations if the RPM clears sufficient \ncapacity for three consecutive Delivery Years). \n12 Id. § VIII(e)."},{"page":10,"startToken":2653,"endToken":3000,"text":"10 \nICAP equivalent of the BYONC.”13 This time-bounded, 10-year RPM must-offer requirement \nwas established in the stakeholder process as a practical solution to allow for commercially \nworkable bilateral contracting. While Calibrant intends to operate its behind-the-meter assets \nsupporting load response for their 20+ year useful lives, Calibrant cannot commit its assets to \noperate for the duration that the load it serves remains in service. This clarification is therefore \nneeded to provide regulatory certainty that a New Large Load must only contract with a BYONC \nresource for a definite term to procure protection from IRAS curtailment exposure, as opposed to \npotential indefinite exposure that could last decades and would create substantial risk for \ndevelopers. To the extent that the Commission believes that PJM must clarify its proposed Tariff \nlanguage to make clear that proposed Tariff Attachment DD-4 section VII(e) only prohibits \ntransferring a BYONC and does not require the BYONC to remain in operation for the life of the \nload, Calibrant requests that the Commission find PJM’s proposal unjust and unreasonable given \nits conflict with the provision allowing Demand Resource and DER BYONC to be replaced in \nthe RPM and direct PJM to clarify the language on compliance.14 \nC. \nCalibrant requests clarification that a Demand Resource’s 10-year \ndemonstration obligation applies on an ICAP basis and, for New Large Load \nDemand Resource, does not apply in Year 1. \nPJM proposes to require Demand Resources to demonstrate their availability each year \nduring a 10-year period. For the avoidance of doubt, Calibrant requests confirmation that these \ndemonstrations are to be made on an ICAP, rather than Unforced Capacity (UCAP), basis. In \n \n13 Transmittal Letter at 64-65.  \n14 See id. at 9 (consenting “to the Commission’s exercise of authority to modify . . . any element \nof the proposed Tariff and RAA language to the extent necessary and permitted under FPA \nsection 205 and NRG Power Marketing, LLC v. FERC, where such modification and/or \nseverance is consistent with PJM’s overarching objectives.” (citation omitted)); see also sources \ncited in supra n.6, in which the Commission rejected confusing or unclear tariff proposals."},{"page":11,"startToken":3000,"endToken":3378,"text":"11 \naddition, Calibrant requests confirmation that New Large Load Demand Resources are not \nrequired to make such an installed capacity demonstration in year 1. \nPJM proposes that a Demand Resource’s or DER Capacity Aggregation Resource’s \nAccredited UCAP shall be the Accredited UCAP for the RPM Auction in which the BYONC \ncleared for the initial Delivery Year that the BYONC is in an arrangement with the New Large \nLoad.15 Further, PJM proposes to require that the Demand Resource’s or DER Capacity \nAggregation Resource’s “Accredited UCAP . . . must be demonstrated each year for a 10-year \nperiod using the Demand Response or DER Capacity Aggregation Resources installed capacity \nfor the first Delivery Year after the BYONC is in an arrangement with the New Large Load.”16 \nCalibrant reads this requirement to require a Demand Resource to demonstrate its \nongoing BYONC eligibility in the Accredited UCAP amount of the first Delivery Year that it \ncontracts with the New Large Load using its ICAP rather than its UCAP. This reading is \nconsistent with conversations with PJM staff in the stakeholder process. It also parallels the \nrequirements that front-of-meter assets face in being subject to an RPM must offer requirement \nunder the proposed Tariff and Tariff Attachment DD § 6.6, which requires all of the installed \ncapacity of existing generation resources to be offered in all RPM Auctions for each Delivery \nYear.17 Calibrant requests this confirmation for the avoidance of doubt given potential confusion \n \n15 Proposed Tariff, Attach. DD-4 § VII(i)(ii). \n16 Id. (emphasis added). \n17 Proposed Attach. DD-4 § VIII(b) (“All BYONC in an arrangement with a New Large Load \nmust be offered into the RPM Auctions as Capacity Resources consistent with and pursuant to \nthe capacity must-offer requirements and exceptions set forth in Tariff, Attachment DD, sections \n6.6 and 6.6A.”); OATT ATT DD.6.6, OATT ATTACHMENT DD.6.6 Offer Requirement for \nCapacity Resour (3.0.0), § 6.6(a) (“To avoid application of subsection (h) below, all of the \ninstalled capacity of all Existing Generation Capacity Resources located in the PJM Region shall \nbe offered by the Capacity Market Seller that owns or controls all or part of such resource (which \nmay include submission as Self-Supply) in all RPM Auctions for each Delivery Year” (emphasis \nadded))."},{"page":12,"startToken":3378,"endToken":3580,"text":"12 \nin the proposed tariff as written stemming from the requirement to demonstrate the Accredited \nUCAP using “installed capacity.” This clarification will provide regulatory certainty to Demand \nResource and DER Capacity Aggregation Resource developers that their BYONC eligibility will \nnot degrade in subsequent Delivery Years, creating uncertainty that would otherwise discourage \nbilateral contracting of new demand side and distributed BYONC. \nIn addition, PJM proposes that, “For Demand Resources or DER Capacity Aggregation \nResources that are also the actual New Large Load, there is no demonstration required for the \ninitial Delivery Year only to not be an Eligible New Large Load.”18 Calibrant requests \nconfirmation that this means that a New Large Load that serves as its own BYONC by \nregistering as a Demand Resource is not required to make an installed capacity demonstration in \nthe first Delivery Year that it is participating as a Demand Resource, and is only required to make \nthe demonstration in years 2-10.  \n \n \n \nRespectfully submitted, \n/s/ Kim Smaczniak \nKim Smaczniak \nMiles Farmer \nAvi Zevin \nNathan Lobel \nRoselle LLP \n300 New Jersey Ave. NW, Suite 300 \nWashington, DC 20001 \nmiles.farmer@rosellellp.com \navi.zevin@rosellellp.com \nnathan.lobel@rosellellp.com \n \n \n \n18 Proposed Tariff, Attach. DD-4 § VII(i)(ii)."},{"page":13,"startToken":3580,"endToken":3640,"text":"13 \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Commission in this \nproceeding. \n \nDated: September 3, 2026 \n/s/ Nathan Lobel \nNathan Lobel \nRoselle LLP \n300 New Jersey Ave. NW, Suite 300 \nWashington, DC 20001 \nnathan.lobel@rosellellp.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":945,"startToken":0,"endToken":705},{"p":3,"at":945,"title":"I. REQUIRED CLARIFICATIONS","method":"printed heading","endPage":3,"endAt":974,"startToken":705,"endToken":708},{"p":3,"at":974,"title":"A. Calibrant requests clarification that incremental Demand Resource capacity","method":"printed heading","endPage":8,"endAt":936,"startToken":708,"endToken":2155},{"p":8,"at":936,"title":"B. Calibrant requests clarification that a New Large Load and BYONC’s","method":"printed heading","endPage":10,"endAt":1302,"startToken":2155,"endToken":2853},{"p":10,"at":1302,"title":"C. Calibrant requests clarification that a Demand Resource’s 10-year","method":"printed heading","endPage":13,"endAt":4,"startToken":2853,"endToken":3581},{"p":13,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":379,"startToken":3581,"endToken":3640}]}