{"document":{"slug":"rec-20260903-5219","title":"Protest of America's Power re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service","issued":"2026-09-03","accession":"20260903-5219","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"America's Power","kind":"protest","file":"sources/filings/text/20260903-5219_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5219","tier":"record","sha256":"3200942b73b9634537d2bbc39f9d1ebe605008e3b5c07927c9f9db6fa67d98ec","pages":22,"tokens":5770,"emptyPages":[],"textThemes":["adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":247,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \n)          \n)         Docket No. ER26-3515-000 \n) \n) \n \nPROTEST OF AMERICA’S POWER \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 America’s Power2 protests the unjust, \nunreasonable and unduly discriminatory Interim Resource Adequacy Service (“IRAS”) \nproposal filed by PJM Interconnection, L.L.C. (“PJM”) because it discriminates against \nexisting generation, will suppress capacity market price signals, and threatens to accelerate \nthe retirement of resources that remain essential to system reliability. \nPJM’s IRAS proposal creates a new source of capacity demand through its Bring Your \nOwn New Capacity (“BYONC”) arrangements with New Large Loads, while categorically \nexcluding existing generation from serving that demand.  At the same time, PJM would \nsuppress Reliability Pricing Model (“RPM”) clearing prices by removing demand from the \nVariable Resource Requirement (“VRR”) Curve and requiring BYONC resources to submit \n$0/MW-Day offers for ten years.  The approximately 38,000 MW of coal-fueled generation \n \n1 18 C.F.R. § 385.211. \n2 America’s Power is a trade association with members that participate in the electric power \ngeneration supply chain, including in the PJM region.  America’s Power advocates on behalf of the U.S. \nelectric generation coal fleet and its supply chain, including coal producers, transportation \ncompanies, and equipment manufacturers.  The nation’s fleet of more than 400 coal-fueled \ngenerating units located across 37 states provides affordable, reliable, dispatchable and energy-\nsecure electricity on a 24/7 basis."},{"page":2,"startToken":247,"endToken":577,"text":"Page | 2  \n \nwithin PJM3 would therefore be denied access to this new revenue opportunity while also \nfacing reduced revenues in RPM—the only capacity market available to them.  The resulting \nloss of revenue would be consequential because capacity payments represent roughly 25% \nto 45% of total revenue for PJM coal-fueled generators.4   \nThe most obvious and predictable result is increased financial pressure to retire \nmore coal-fueled generation.  For perspective, almost 10,500 MW of coal-fueled capacity in \nPJM have announced plans to retire over the next five years.5 (This would add to the \napproximately 46,500 MW that have already retired since 2011.6)  Without IRAS, these \nretirement plans might be reversed.  With IRAS, reversals are less likely, and the prospect of \nso-far unannounced retirements increases.  Ironically, these retirements are the principal \nnear-term threat to resource adequacy and the very condition PJM asserts its filing is \nintended to address.  The IRAS Proposal thus purports to remedy a capacity shortfall by \nundermining the economics of the fleet that currently provides capacity, especially coal \nunits that have on-site fuel supply that provides critical reliability benefits during extreme \nweather conditions.  PJM offers no support for excluding such resources from the opportunity \nto serve Large Load because it submitted no analysis of the filing’s market effects. \n \n3 See Monitoring Analytics, LLC, Independent Market Monitor for PJM, 2025 State of the Market Report \nfor PJM, Section 12 at 711 (Mar. 12, 2026)(“PJM IMM 2025 Report”), 2025 Annual State of the Market \nReport for PJM. \n4 See id., Section 7 at 421(capacity market revenue as % of new entrant net revenue); id. at 443 (Table \n7-39, net revenue by quartile for coal-fueled units), 2025 Annual State of the Market Report for PJM. \n5 Energy Ventures Analysis maintains a data base that tracks announced coal retirements.  These \nannounced retirements are based on Integrated Resource Plans, consent agreements, and press \nreleases.  As such, announced retirements are subject to change. \n6 PJM IMM 2025 Report at 711."},{"page":3,"startToken":577,"endToken":848,"text":"Page | 3  \n \nAccordingly, the Commission should find that PJM has not shown its IRAS proposal \nto be just, reasonable and not unduly discriminatory, and reject PJM’s filing. \nI. \nTHE PJM IRAS PROPOSAL \nPJM filed its IRAS proposal with the Commission on August 13, 2026, following its July \n31, 20267 companion filing regarding its Reliability Backstop Procurement (“RBP”).8 The IRAS \nproposal is intended to address new “Large Load” additions—principally data centers—that \ninterconnect with the grid without first securing sufficient capacity to support their load.9   \nPursuant to the IRAS Proposal, a New Large Load that does not provide its own \nqualifying capacity would be required to take IRAS.10 IRAS would make the load subject to \ncurtailment during grid emergencies arising from resource inadequacy, subject to a \nmaximum compensation rate of 50% of the Non-Performance Charge Rate.11 BYONC is the \nmechanism through which a New Large Load may reduce or eliminate its IRAS exposure by \nsecuring qualifying new capacity.12 IRAS will be available starting with the 2027/2028 Delivery \nyear, i.e., starting June 1, 2027.13 \n \n7 PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim resource \nAdequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515-000 \n(filed Aug. 13, 2026)(“IRAS Proposal”). \n8 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy \nConcerns Stemming from Large Loads, Docket No. ER26-3380-000 (filed Jul. 31, 2026)(“RBP \nProposal”). \n9 IRAS Proposal at 6. \n10 See id. at 23. \n11 See id. at 22, 102. \n12 See id. at 23. \n13 See id. at 61."},{"page":4,"startToken":848,"endToken":1098,"text":"Page | 4  \n \nPJM defines BYONC as a quantity of capacity that permits  a New Large Load to satisfy \nits obligation through contracts with one or more resources.14 The contracted capacity, \nhowever, must constitute an actual addition to PJM’s supply.15 Eligible resources may \ninclude new generation, uprates, surplus interconnection service, repowered resources, \nfuel conversions, and storage.16 A load may use a combination of BYONC, allocated RBP \nUCAP, and IRAS to satisfy its capacity-related needs, but it cannot use existing capacity.17 \nBYONC directs new capacity into bilateral, load-specific arrangements rather than \nthe competitive RPM auction.  Thus, new supply may obtain long-term, load-specific revenue \noutside the RPM auction, while existing resources remain dependent on RPM revenues – \nwhich are critically important to the financial viability of the coal fleet − and are fully exposed \nto auction-clearing dynamics.  Existing generators have no comparable mechanism through \nwhich to capture the value associated with serving new load. \nFurther, beginning with the 2029/2030 Delivery Year, PJM proposes to exclude from \nthe VRR Curve the MW associated with New Large Loads that neither have BYONC \narrangements nor allocated RBP UCAP MW, to the extent those MW exceed the New Large \nLoad included in the 2028/2029 Delivery Year load forecast.18 Under the proposal, the \ndemand curve would subtract that amount of excluded New Large Load from the PJM Region \n \n14 See id. at 51. \n15 See id. at 52. \n16 See id. at 52-53. \n17 See id. at 51. \n18 See id. at 109-10."},{"page":5,"startToken":1098,"endToken":1300,"text":"Page | 5  \n \nReliability Requirement.19 In practical effect, PJM would not procure incremental RPM \ncapacity for those loads.  Instead, the loads would be required to secure qualifying capacity \nthrough BYONC or remain subject to IRAS.20  This exclusion directly reduces the reliability \nrequirement—and therefore the quantity of capacity procured—in future Base Residual \nAuctions (“BRAs”).21 Although PJM characterizes this structure as consistent with its \nRatepayer Protection Pledge,22 the same design that avoids charging ratepayers for capacity \nassociated with unbacked New Large Load also removes a material source of capacity \ndemand from the market on which existing generators depend. \nII. \nPROTEST \nA. \nPJM’s IRAS Proposal is Unjust and Unreasonable and Unduly \nDiscriminates Against Existing Generators \n \n1. \nThe Exclusion of Existing Capacity from Serving Large Load is \nUnsupported \nUnder the proposed IRAS construct, a Large Load may avoid interruption only by \nsecuring capacity from new resources, while otherwise available capacity from existing \ngeneration is excluded from serving that purpose.  Only “new” capacity may qualify as \nBYONC.  Capacity already on the system as of May 31, 2027, is categorically ineligible, as are \n \n19 See id. at 117-18. \n20 See id. at 110-11. \n21 See id. at 23-24. \n22 See id. at 109-12."},{"page":6,"startToken":1300,"endToken":1565,"text":"Page | 6  \n \nMW previously included in an FRR Capacity Plan.23 Eligible BYONC capacity is limited to new \nconstruction, uprates, Surplus Interconnection Service, repowering of resources \ndeactivated before April 10, 2026, and efficiency-driven fuel conversions.24   \nThis distinction between new and existing capacity is unsupported.  A MW of \naccredited capacity from existing generation is indistinguishable, for resource adequacy \npurposes, from a MW of accredited capacity from new generation.  Both count toward the \nReliability Requirement, are accredited under the same methodology, and assume the same \nCapacity Performance obligations and exposure to non-performance charges.  At the time \ncapacity is delivered, the PJM Tariff recognizes no difference between them. \nPJM’s own authority confirms this conclusion.  PJM cites a D.C. Circuit case for the \nproposition that the Tariff “defines a Capacity Resource as the amount of net MW committed \nfrom one or many generating units, not a physical facility.”25 If a Capacity Resource is defined \nby committed MW rather than by the particular facility supplying them, PJM has no principled \nbasis to discriminate between capacity based on whether the facility that produces the \ncapacity is new or existing. \n \n23 See id. at 52.  The FRR Capacity Plan is “a long-term plan for the commitment of Capacity \nResources and Price Responsive Demand to satisfy the capacity obligations of a Party that has \nelected the FRR Alternative, as more fully set forth in the Reliability Assurance Agreement.”  PJM \nReliability Assurance Agreement, Definitions. \n24 IRAS Proposal at 53-54. \n25 IRAS Proposal at 51 & n.137 (citing Energy Harbor, LLC v. FERC, 143 F.4th 388, 394 (D.C. Cir. 2025))."},{"page":7,"startToken":1565,"endToken":1858,"text":"Page | 7  \n \nA public utility may not confer an undue preference or establish an unreasonable \ndifference in rates or service among similarly situated customers or suppliers.26 The relevant \ninquiry is whether the entities receiving different treatment are similarly situated and, if so, \nwhether the distinction is supported by a legitimate, non-discriminatory basis.  PJM has \nprovided no legitimate, non-discriminatory basis for the distinction between new and \nexisting generation.  PJM's discrimination analysis rests on New Large Loads being a \n\"separate, unique class\"27 justifying different treatment.  This is not legitimate.  A BYONC \ngeneration resource and an existing coal unit, for example, both physically provide the same \ncapacity product such that they are similarly situated.  PJM's core discrimination defense, \nnamely that New Large Loads \"caused\" the shortfall and so can be treated differently,28 \nmisses the mark.  If cost-causation justifies putting the burden of the shortfall on New Large \nLoads through IRAS curtailment, existing generators who did not cause the shortfall should \nnot simultaneously absorb the adverse market consequence through exclusion from serving \nthat demand and resulting in suppressed prices, as discussed further below.  A mechanism \ndesigned to accommodate the entities that caused a shortfall should not discriminate \nagainst those similarly situated entities that did not.29   \n \n26 16 U.S.C. § 824d(b); City of Lincoln v. FERC, 89 F.4th 926, 935 (D.C. Cir. 2024) (citing Mo. River Energy \nServs. v. FERC, 918 F.3d 954, 958 (D.C. Cir. 2019)). \n27 IRAS Proposal at 104. \n28 Id. at 50, 52, 98-99. \n29 Consol. Edison Co. of New York, Inc. v. FERC, 45 F.4th 265, 282 (D.C. Cir. 2022)(finding undue \ndiscrimination where threshold “unduly discriminates against small zones, which must absorb higher \ncost allocations after large zones are exempted.”)."},{"page":8,"startToken":1858,"endToken":2148,"text":"Page | 8  \n \n2. \nPJM’s Own Eligibility Categories Refute the New-Versus-Existing \nRationale \n \nPJM’s distinction between new and existing capacity turns solely on an arbitrary date.  \nThat cutoff produces a perverse result.  For example, a unit that announced its deactivation \non April 9, 2026, and is retained or returned to service through a BYONC contract may qualify \nas new supply, while an otherwise identical unit that announced deactivation on April 11, \n2026, and is retained through an identical contract may not.   \nTo illustrate the perverse consequences of PJM’s eligibility cutoff further, consider \nthat whether a unit announced retirement on April 9, 2026, or April 11, 2026, it confronts the \nsame underlying environmental, economic, and operational pressures.  Those pressures \naffect the coal fleet broadly; they do not depend on the date of a particular retirement \nannouncement.  PJM therefore has no principled basis to extend April 10 treatment to one \nsubset of at-risk coal resources while denying it to otherwise similarly situated units.  \nPreventing the retirement of an existing resource contributes to resource adequacy no less \nthan returning a retired resource to service.  The same treatment should be available to all \ncoal units, and PJM offers no reasoned explanation for this distinction. \nIn addition, PJM’s reasoning for the BYONC qualifying criteria that it is designed to \nstimulate incremental supply ignores the fact that more than 200 GW of proposed new \ngeneration qualified for study in PJM’s Cycle 01 without its IRAS Proposal.30  This underscores \nthat PJM need not exclude existing generation from the capacity market to encourage \n \n30 PJM Inside Lines, Over 700 New Generation Projects Accepted Into First Cycle of Reformed \nInterconnection Process (Aug. 3, 2026), Over 700 New Generation Projects Accepted Into First Cycle \nof Reformed Interconnection Process | PJM Inside Lines."},{"page":9,"startToken":2148,"endToken":2447,"text":"Page | 9  \n \nincremental supply, because the current market already is attracting substantial proposed \nnew generation.   \nMoreover, the IRAS filing defines a Large Load as an end-use customer or aggregated \nsite with peak demand of at least 50 MW, consistent with the Commission’s show cause \norder.31 But PJM does not explain why a 50-MW load is too large to be served through the RPM \nconstruct, while a slightly smaller load may rely on that same market.  Ten 50-MW data \ncenters and one 500-MW data center impose the same aggregate 500-MW demand on the \nsystem.  Nothing about the size of an individual customer’s facility establishes that the \ncustomer must procure a dedicated new power plant rather than rely on the capacity market. \nSince RPM’s inception, PJM has relied on the capacity market to procure resources \nneeded to serve load growth.  The IRAS Proposal departs from that approach by treating the \naddition of a 50-MW customer as sufficient reason to exclude its demand from RPM unless \nthe customer brings qualifying new supply or receives RBP UCAP.  PJM has not shown why \nRPM is adequate to serve additional load below that threshold, but inadequate to serve the \nsame quantity of incremental demand once it is concentrated at a single customer site. \n3. \nThe Discrimination is Permanent and Eventually Universal \nThe discrimination is not temporary or self-limiting.  New generation that contracts \nwith a Large Load today will become “existing” generation in subsequent years.  If PJM \nsatisfies its Reliability Requirement for three consecutive Delivery Years but subsequently \nexperiences another shortfall, the proposal would reset the “new/existing” capacity baseline \nto the capacity then in existence.  A resource that qualified as BYONC during the initial cycle \n \n31 IRAS Proposal at 32 (citing PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 58 (2026))."},{"page":10,"startToken":2447,"endToken":2699,"text":"Page | 10  \n \nwould consequently be ineligible to qualify in a subsequent cycle.32  When PJM forecasts \ninsufficient capacity in later years, that same resource, which previously was considered \nnew, may no longer qualify to support a Large Load under the IRAS framework.  Thus, over \ntime, every resource will fall on the disfavored side of the eligibility line.  The proposal \ntherefore establishes a recurring preference for new capacity, with no identified end date or \nlimiting principle.   \n4. \nThe Derivative Discrimination is that Existing Capacity is Worth \nLess to a New Large Load \nThe exclusion does more than deny existing generators access to the BYONC market; \nit affirmatively diminishes the value of their capacity.  Large Loads that contract with existing \nresources would remain subject to curtailment, making those resources a less attractive \ncontractual option than new generation regardless of their comparable reliability value.  An \nironic consequence of PJM’s IRAS Proposal is that a Large Load that co-locates with an \nexisting generator may reduce the need for transmission upgrades, yet would receive no \nBYONC credit merely because the supporting capacity is existing.  The Large Load would \ntherefore remain subject to IRAS curtailment notwithstanding the potential transmission and \nreliability benefits of the arrangement.  This outcome would discourage efficient bilateral \ncontracting, distort Large Load procurement decisions, and deny existing resources a \nmeaningful opportunity to compete to serve Large Load demand.  As a result, the IRAS \nProposal causes existing capacity to command a lower price than new capacity for the same \nphysical product. \n \n32 See id. at 52-55."},{"page":11,"startToken":2699,"endToken":2943,"text":"Page | 11  \n \n In doing so, PJM sends precisely the wrong investment and retirement signal.  By \ndiminishing the value of existing capacity, PJM would increase pressure on existing baseload \nresources to retire, especially coal units that have on-site fuel supply that provides critical \nreliability benefits during extreme weather conditions.  These resources are not easily \nreplaced.  At a time when PJM faces increasing reliability risks, as it has made clear,33 its tariff \nshould preserve, rather than undermine, the economic viability of dependable existing \nresources. \nB. \nPJM’s Proposal Results in Price Suppression \n1. \nRemoving Demand from the PJM Capacity Forecast Results in \nPrice Suppression \nPJM’s proposal promotes  artificial capacity price suppression.  Although Large Load \ndemand is increasing, PJM proposes to exclude that demand from its capacity forecast.  As \na result, PJM would procure less supply than it otherwise would to meet the region’s actual \nresource-adequacy needs.  Reducing the demand forecast in this manner and lowering the \nquantity of capacity procured artificially depresses auction clearing prices.  Those \nsuppressed prices will distort the market signals needed to encourage market participants—\nincluding existing coal generators—to remain available and invest in continued operation.  \nThe distorted market signals will affect new resources too.  To the extent those new \nresources do not participate in the RBP central procurement or serve as RBP offset MW \nthrough bilateral arrangements with data centers, those resources likewise would depend \non RPM price signals to support investment and entry.    \n \n33 Id. at 6, 13-14, 18, 21."},{"page":12,"startToken":2943,"endToken":3230,"text":"Page | 12  \n \nFurther, the IRAS Proposal creates asymmetric treatment between incumbent \nresources and new BYONC resources.  It suppresses RPM prices while imposing the cost of \nnew supply on New Large Loads through bilateral arrangements.  A New Large Load that \nprocures BYONC would pay the resource’s actual cost through a load-specific contract—\npotentially at a level comparable to the $555/MW-Day figure identified in PJM’s RBP filing—\nwhile the resource would be required to offer into RPM as a $0/MW-Day price taker. \nPJM’s ramping treatment magnifies that effect.34 Where a Large Load ramps up over \ntime but contracts for a generator sized to meet its eventual load, PJM would include the \nportion of the Large Load then supported by BYONC in the applicable RPM load forecast.  At \nthe same time, PJM would permit the generator’s full accredited capacity to be offered into \nthat auction as a price taker.  Capacity intended to serve the Large Load’s future growth \nwould therefore be offered at $0/MW-Day  before the corresponding future load is reflected \nin the demand curve.  The result is an imbalance: the auction receives the full quantity of \nzero-priced BYONC supply, while its demand curve reflects only the then-current, supported \nportion of the ramping Large Load. \nThis effect is compounded by PJM’s broader exclusion of incremental New Large \nLoad that is not supported by BYONC or allocated RBP UCAP.  Existing generators receive no \ncomparable load-specific contracting or cost-recovery mechanism.  They must compete in \nan RPM market facing both excluded incremental demand and an expanding volume of zero-\npriced capacity whose costs are recovered outside the auction.  The proposal therefore does \nmore than treat new and existing resources differently; it shifts new-resource cost recovery \n \n34 Id. at 115-16."},{"page":13,"startToken":3230,"endToken":3464,"text":"Page | 13  \n \nto bilateral contracts while placing downward pressure on the RPM revenues available to \nexisting resources.  As a result, newcomers get price insurance; incumbents get price \nsuppression.   \n2. \nThe Resulting Price Suppression Threatens to Accelerate \nGeneration Retirement \nThis resulting price suppression is likely to further the retirement of existing \ngeneration and reduce the capacity available to support reliability.  Deactivation decisions \nrespond to expected net revenue.  Reduced expected revenue accelerates those decisions.  \nThat result is particularly untenable given PJM’s own reliability assessments identifying a \ncapacity shortfall.  Accelerated retirement of accredited capacity is the principal near-term \nthreat to resource adequacy — the condition PJM says the filing exists to address.35  PJM \ncannot reasonably respond to a growing reliability need by excluding increasing Large Load \ndemand from its procurement requirement and, in turn, weakening the incentives to existing \ngeneration needed to meet that demand. \nAs an example, under the BYONC/RBP gating criteria, a coal plant that retires and is \nlater repowered can requalify as \"new\" capacity — eligible for price-taker guaranteed \nclearing or a 15-year RBP contract.  The same plant, if it simply keeps running as existing \ncapacity, gets no such treatment and faces a suppressed clearing price.  PJM’s IRAS \nProposal construct, therefore, economically rewards retirement-and-reentry over continued \noperation — the opposite of what a resource-adequacy-focused filing should incentivize, \nespecially given PJM's own acknowledgment that thermal retirements are a major driver of \n \n35 IRAS Proposal at 6."},{"page":14,"startToken":3464,"endToken":3751,"text":"Page | 14  \n \nthe shortfall.36 \nPJM has separately extended the capacity must-offer requirement to all available \nExisting Capacity Resources.37 Thus, existing generators are required to offer it in.  Combined \nwith the VRR exclusion suppressing clearing prices, existing generators (particularly higher-\nmarginal-cost coal units) could be forced to operate — or stay available — at prices below \nwhat are needed to justify continued investment in the plant, with no legal ability to exit the \nmarket other than through full deactivation.   \nCapacity revenue is often the difference between viability and retirement for aging \nthermal units, especially coal, whose energy-market margins have compressed as gas and \nrenewables have grown.  By excluding uncovered New Large Load MW from the demand \ncurve, PJM is shrinking the measured reliability requirement even though the physical load is \nreal and growing.  A lower demand curve clears at a lower price.  Every existing generator — \nnot just the ones connected to New Large Loads — receives less capacity revenue than the \ntrue system need would otherwise support, at precisely the moment when load growth \nshould be pushing prices up and signaling \"build/retain more capacity.\" \n \n36 See, e.g., Written Testimony of Manu Asthana, President and CEO, PJM Interconnection, Keeping \nthe Lights On: Examining the State of Regional Reliability at 4, Hearing Before the Subcomm. on Energy, \nH. Comm. on Energy & Commerce, 119th Cong. (Mar. 25, 2025), https://www.pjm.com/-\n/media/DotCom/library/reports-notices/testimony/2025/20250325-asthana-testimony-us-house-\nsubcommittee-on-energy.pdf (“the pace of retirements of existing dispatchable fossil-based \nresources, largely due to state and federal policies, is clearly outpacing the rate of construction of new \nresources”). \n37 RBP Proposal at 23-24 (citing PJM Interconnection, L.L.C., 190 FERC ¶ 61,117, order on reh'g, 191 \nFERC ¶ 61,221 (2025))."},{"page":15,"startToken":3751,"endToken":3915,"text":"Page | 15  \n \nThe recent National Coal Council (“NCC”) report highlights the need to retain existing \ngeneration resources such as coal given the rapid demand growth resulting from data \ncenters.38  The NCC Report states: \nAfter nearly 15 years of flat electricity demand, the grid must now support \nrapid growth from data centers, AI, manufacturing, electrification, and \nbroader economic activity.  Despite this demand growth, dispatchable \ncapacity remains at risk of retirement, with financial pressures expected to \nincrease to the extent new loads are encouraged or required to obtain their \nelectricity from only new generation resources.  For net capacity increases to \noccur, existing generation resources must be retained even as new resources \nare added to the grid.  Retaining and operating the existing coal fleet through \nat least the 2040s remain one of the most cost-effective pathways to \nmaintain grid reliability.39 \n \n38 National Coal Council, Maximizing the Value of the U.S. Coal Fleet at 5 (Jul. 2026), FINAL-\nNCC_Maximizing-Value-of-US-Coal-Fleet.pdf (“NCC Report”). \n39 Id."},{"page":16,"startToken":3915,"endToken":4474,"text":"Page | 16  \n \n3. \nThe IRAS Proposal is Inconsistent with Commission Precedent \nRecognizing the Importance of Appropriate Price Signals and \nPJM Provides no Evidence to Justify that Departure \nCommission and court precedent recognize the need for appropriate price signals.40 \nPJM has not justified treating a failure to clear the full Reliability Requirement in a \nparticular auction as requiring the permanent exclusion of otherwise forecasted new load \n \n40 See, e.g., Sw. Power Pool, Inc., 191 FERC ¶ 61,214 at P 45 (2025)(“because these out-of-market \nactions and resulting uplift costs are not reflected in market prices, those costs and the reasons for \nincurring them are inherently less transparent, which limits the ability of competitive electric markets \nto send appropriate price signals to compensate and encourage investment in resource attributes \nthat respond to system needs.”); PJM Interconnection, L.L.C., 173 FERC ¶ 61,23 at P 67 (2020)(stating \nthat “the Commission has required the RTOs to implement scarcity pricing, finding that RTO market \ndesigns were unjust and unreasonable if energy prices failed to reflect shortages in reserves”); Uplift \nCost Allocation and Transparency in Markets Operated by Regional Transmission Organizations and \nIndependent System Operators, Order No. 844, 163 FERC ¶ 61,041 at P 3 (2018)(finding RTO practices \nthat mask system conditions impede market participants’ ability to value resources or evaluate the \nneed for new investment and are unjust and unreasonable); FERC v. Elec. Power Supply Ass'n, 577 \nU.S. 260, 269 (2016), as revised (Jan. 28, 2016)(“[a]s in any market, when wholesale buyers’ demand \nfor electricity increases, the price they must pay rises correspondingly”); Offer Caps in Markets \nOperated by Regional Transmission Organizations and Independent System Operators, Order No. 831, \n157 FERC ¶ 61,115 at PP 34-41 (2016)(finding energy price cap can impair price formation because \ninefficient price signals can harm reliability and can inhibit performance and investment), order on \nreh’g and clarification 161 FERC ¶ 61,156 (2017); Settlement Intervals and Shortage Pricing in Markets \nOperated by Regional Transmission Organizations and Independent System Operators, Order No. 825, \n155 FERC ¶ 61,276 at PP 1-2 (2016) (requiring shortage pricing in energy and operating reserves \nmarkets to reflect value of the service and noting that a failure to properly price a service results in a \n“distort[ion] [of] price signals and [a] fail[ure] to provide appropriate signals for resources to respond \nto the actual operating needs of the market”); id. at P 163 (finding “that the shortage pricing \nrequirement will help ensure that prices rise sufficiently and appropriately to allow supply to meet \ndemand during an operating reserve shortage, and thus will more accurately reflect the value a \nresource provides”); Wholesale Competition in Regions with Organized Electric Markets, Order No. \n719, 125 FERC ¶ 61,071 at P 192 (2008) (finding that rules “that do not allow for prices to rise \nsufficiently during an operating reserve shortage to allow supply to meet demand are unjust, \nunreasonable, and may be unduly discriminatory”), order on reh’g, Order No. 719-A, 128 FERC ¶ \n61,059, order on clarification, Order No. 719-B, 129 FERC ¶ 61,252 (2009); id. rules that do not allow \nprices to rise during a shortage “may not produce prices that accurately reflect the value of energy \nand, by failing to do so, may harm reliability, inhibit demand response, deter entry of demand response \nand generation resources, and thwart innovation”)."},{"page":17,"startToken":4474,"endToken":4838,"text":"Page | 17  \n \nfrom RPM.  PJM is presently approximately 6,800 MW short of its Reliability Requirement,41 \nbut PJM has not demonstrated that any auction shortfall necessarily translates into an \ninability to serve all load reliably.  If anticipated data-center load does not materialize, the \nactual shortfall may be materially smaller.  In that circumstance, RPM could procure \ncapacity to serve additional New Large Load that PJM’s proposal instead excludes.  Yet PJM \nwould keep that load outside RPM until the market clears the Reliability Requirement for \nthree consecutive Delivery Years. \nPJM’s recent operating experience underscores the need for such analysis.  During \nthe 2026/2027 summer, PJM reportedly served load reliably despite a 90/10 peak-load \noutcome, greater-than-expected unit outages, and an RPM auction that had cleared slightly \nshort of the Reliability Requirement.42 That experience does not establish that shortages are \nimmaterial, but it does call into question PJM’s apparent premise that any auction shortfall \nrequires excluding all future Large Load above 50 MW from the ordinary capacity-market \nframework.  PJM has provided no evidence showing the point at which the size of an \nindividual load makes RPM incapable of serving that load without a dedicated new \ngenerating resource.  PJM further has provided no evidence of how large and persistent an \n \n41 In the 2028/2029 BRA, PJM cleared 6,831 MW short of its Reliability Requirement.  PJM itself \nacknowledged, however, that this shortfall does not necessarily mean the system will be unable to \nserve load reliably during the Delivery Year.  See PJM News Release, PJM Capacity Auction Procures \n138,318 MW of Generation Resources as Work Continues To Address Growing Electricity Demand at \n1 (Jul. 14, 2026),20260714-pjm-capacity-auction-procures-138318-mw-of-generation-resources.pdf. \n42 During the July 2026 heat event, PJM maintained reliable operations while serving a record \npreliminary peak load of 168,158 MW—near its 90/10 summer forecast of 169,128 MW—and \nmanaging forced generation outages of 18,100 to 19,400 MW, compared with a 12,800 MW average \nfor the ten highest summer-peak days in the prior three years.  See PJM Inside Lines, PJM Serves Load \nThrough Record-Breaking July Heat (Jul. 14, 2026), PJM Hot Weather Operations Update – July 14, 2026 \n| PJM Inside Lines."},{"page":18,"startToken":4838,"endToken":5108,"text":"Page | 18  \n \nRPM shortfall must be before PJM may exclude otherwise forecasted New Large Load from \nRPM and instead procure supply through out-of-market arrangements.  Absent evidence, the \nproposal merely substitutes an indefinite market-exclusion regime for the established RPM \nmechanism with no specific reasoning tying it to the 50-MW  load size threshold. \nPJM supports its filing merely with a single affidavit from an operations witness, which \naddresses emergency procedures and dispatch sequencing.43 It presents no testimony from \nan economist or market-design witness; no quantification of the demand-curve exclusion’s \neffect on capacity clearing prices; no analysis of the effect of ten years of mandated $0/MW \noffers; no loss-of-load-expectation study; and no estimate of the capacity volume that would \nbe excluded.  PJM’s entire showing on price effects consists of a single sentence.   \nInstead of respecting the long-established Commission and Court precedent that \ncompetitive markets must allow prices to reflect market fundamentals, such that prices \nshould rise in the face of growing demand and tight supply in order to retain and attract \nneeded supply, PJM’s IRAS Proposal results in price suppression. \nC. \nPJM’s Proposal Results in a Negative Impact on Reliability \nThe negative impact of PJM’s IRAS Proposal on reliability is significant.  Treating load \nas if it is not on the system by excluding it from the demand curve and replacing this through \na load-reduction mechanism only will further increase pressure to retire coal and other \nthermal generation, diminish critical reliability attributes like fuel security, create financial \nuncertainty for the coal supply chain and decrease available capacity necessary for \nreliability.   \n \n43 See IRAS Proposal at 76 (referring to Affidavit of Christopher Pilong)."},{"page":19,"startToken":5108,"endToken":5414,"text":"Page | 19  \n \nThe nation’s coal fleet provides essential reliability services, helps moderate \nelectricity prices, provides energy security, promotes resilience during extreme \nweather, and can provide substantial amounts of dependable and affordable \nelectricity.44  Many existing generators—whether coal-fueled or other generators—\ngenerate substantially less power than they are capable of generating.  The average \ncapacity factor for the coal fleet was 49% last year,45 which means there is considerable \nunderutilized generating capacity available to serve Large Loads.  To illustrate the \namount of underutilized capacity, the nation’s coal fleet totals some 172,000 MW of \ncapacity.46  Retaining existing coal generation facilities is a more cost-effective and \ntimely means of supporting grid reliability.  The NCC Report states that “[r]etaining and \noperating the existing coal fleet through at least the 2040s remain one of the most cost-\neffective pathways to maintain grid reliability.”47  It also makes clear that “[p]reserving \nand modernizing existing coal power plants is generally less expensive than replacing \n \n44 NCC Report at 17 ( “Coal power plants provide reliability and fuel security for the electricity grid.”); \nid. at 18 (“[c]oal power plants contribute to the stability of the electricity grid because they are \ndispatchable – meaning that grid operators can dispatch the power plant (increase or decrease \ngeneration) when needed to match customer demand for electricity.”); id. (“Coal power plants also \nprovide critical on-site fuel security by maintaining large stockpiles of coal at the plants.  This provides \nreliability in the event that fuel deliveries are interrupted due to adverse weather conditions or \ntransportation problems.”). \n45 See EIA Electric Power Monthly, Electric Power Monthly - U.S. Energy Information \nAdministration (EIA) (2025 coal capacity factor). \n46 Id. \n47 NCC Report at 5 (“Retaining and operating the existing coal fleet through at least the 2040s remain \none of the most cost-effective pathways to maintain grid reliability.”)."},{"page":20,"startToken":5414,"endToken":5675,"text":"Page | 20  \n \nthem with new capacity, which can take several years to build.”48 \nDespite this, PJM proposes to exclude existing generation, including coal units, \nfrom serving the increasing Large Load demand with no justification.  Section 205 of the \nFPA requires that the public utility proposing tariff revisions bears the burden of proof to \ndemonstrate that the changes are just and reasonable and not unduly discriminatory.49  PJM \nhas not supported its proposed exclusion of generating resources that have needed \nreliability attributes and that are critical to resource adequacy.  PJM’s IRAS Proposal departs \nfrom precedent and threatens to undermine, rather than advance, system reliability.50  The \nCommission rejects filings where, as here, the filing public utility has failed to meet its \nburden of proof, and therefore, should reject PJM’s IRAS Proposal. \n \n \n \n48 Id.; id. at 25 (“the current development pipeline is not capable of replacing retiring coal-fueled \ncapacity quickly enough to meet rapidly increasing electricity demand.  Existing coal power plants \nalready have interconnection rights, transmission access, fuel supply logistics, operating workforces, \nand on site infrastructure in place.”). \n49 16 U.S.C. § 824d(a)(“[a]ll rates and charges made, demanded, or received by any public utility for or \nin connection with the transmission or sale of electric energy . . . shall be just and reasonable.”). \n50 PJM Interconnection, L.L.C., 186 FERC ¶ 61,097 at p 126 (2024), reh’g denied, PJM Interconnection, \nL.L.C., 187 FERC ¶ 62,016 (2024); PJM Interconnection, L.L.C., 180 FERC ¶ 61,089 at P 6 (2022), order \ndenying reh’g 181 FERC ¶ 61,191 (2022)."},{"page":21,"startToken":5675,"endToken":5727,"text":"Page | 21  \n \nIII. \nCONCLUSION \nWHEREFORE, for the reasons explained fully herein, America’s Power requests that \nthe Commission reject PJM’s unjust, unreasonable and unduly discriminatory IRAS \nProposal.   \nRespectfully submitted,\n \n \n \nMichelle Bloodworth \nPresident and CEO \nAmerica’s Power \n1010 N. Glebe Road \nSuite 640  \nArlington, VA 22201 \n(202) 459-4803 \nmbloodworth@americaspower.org \nSeptember 3, 2026"},{"page":22,"startToken":5727,"endToken":5770,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, D.C. this 3rd  day September, 2026. \n \n \n \n \n \n \n     Michelle Bloodworth"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":175,"startToken":0,"endToken":604},{"p":3,"at":175,"title":"I. THE PJM IRAS PROPOSAL","method":"printed heading","endPage":5,"endAt":698,"startToken":604,"endToken":1199},{"p":5,"at":698,"title":"II. PROTEST","method":"printed heading","endPage":5,"endAt":712,"startToken":1199,"endToken":1201},{"p":5,"at":712,"title":"A. PJM’s IRAS Proposal is Unjust and Unreasonable and Unduly","method":"printed heading","endPage":11,"endAt":578,"startToken":1201,"endToken":2782},{"p":11,"at":578,"title":"B. PJM’s Proposal Results in Price Suppression","method":"printed heading","endPage":14,"endAt":1438,"startToken":2782,"endToken":3679},{"p":14,"at":1438,"title":"H. Comm. on Energy & Commerce, 119th Cong. (Mar. 25, 2025), https://www.pjm.com/-","method":"printed heading","endPage":18,"endAt":1232,"startToken":3679,"endToken":5017},{"p":18,"at":1232,"title":"C. PJM’s Proposal Results in a Negative Impact on Reliability","method":"printed heading","endPage":21,"endAt":14,"startToken":5017,"endToken":5677},{"p":21,"at":14,"title":"III. CONCLUSION","method":"printed heading","endPage":22,"endAt":0,"startToken":5677,"endToken":5727},{"p":22,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":22,"endAt":291,"startToken":5727,"endToken":5770}]}