{"document":{"slug":"rec-20260903-5224","title":"Comments and Limited Protests of Ohio Energy Leadership Council in response to the Interim Resource Adequacy Service and Large Load Registry proposed by PJM…","issued":"2026-09-03","accession":"20260903-5224","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Ohio Energy Leadership Council","kind":"protest","file":"sources/filings/text/20260903-5224_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5224","tier":"record","sha256":"c11081e82db91eda9ba5349a42c9640caf7d9ddcd287458ef5070aa0b01c11ae","pages":19,"tokens":4428,"emptyPages":[],"textThemes":["flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":265,"text":"UNITED STATES OF AMERICA \nBEFORE THE FEDERAL ENERGY REGULATORY COMMISSION  \n \n \nPJM Interconnection, L.L.C. \n  \n \n) \n) \n) \n \n \nDocket No. ER26-3515-000 \n \n \n \nCOMMENTS AND LIMITED PROTESTS OF OHIO ENERGY LEADERSHIP COUNCIL \n \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (the “Commission”), Ohio Energy Leadership Council (“OELC”) \nrespectfully submits these comments and limited protests in response to the Interim Resource \nAdequacy Service (“IRAS”) and Large Load Registry proposed in this proceeding by PJM \nInterconnection, L.L.C. (“PJM”). \nI. \nSUMMARY OF COMMENTS AND LIMITED PROTESTS. \nOELC supports the objective of maintaining resource adequacy and recognizes that new \nlarge loads should bear responsibility for the incremental resource-adequacy needs their additions \ncreate. OELC also recognizes the value of an interim conditional service option that allows \nqualifying new large loads to connect subject to curtailment when system conditions require it. \nBut the Commission should not allow PJM’s proposal to shift to existing customers the risks and \ncosts associated with its proposal in this case. Accordingly, OELC respectfully requests that the \nCommission condition any acceptance of PJM’s IRAS proposal on the following: \n1. \nEstablish a separate, protective threshold for non-data-center customers. A non-data-\ncenter customer—including but not limited to traditional manufacturing, steelmaking, \nchemical, industrial, educational, institutional, and retail customers—should be treated as \na Large Load only if its Peak Load Contribution (“PLC”) is at least 150 MW. The lower \n50 MW threshold should not apply to non-data-center customers. \n2. \nPreserve the intended sequential load-reduction order if PJM accepts New Large \nLoad demand response as BYONC. PJM’s proposal may permit New Large Load to"},{"page":2,"startToken":265,"endToken":601,"text":"2 \n \nreduce its IRAS responsibility by registering its own load as a new Demand Resource or \nas part of a new DER Capacity Aggregation Resource. OELC does not oppose this proposal \nprovided that curtailment sequencing should be preserved such that such new demand \nresources offered by the New Large Load should be curtailed before PJM calls on existing \nDemand Resources and existing DER Capacity Aggregation Resources as part of Pre-\nEmergency and Emergency Load Management Reduction Actions. \n3. \nEnsure IRAS compensation is reasonable and just while preserving cost recovery \nquestions to the appropriate state commissions. While OELC does not oppose \nappropriate compensation for IRAS curtailments, the Commission should ensure the \ncompensation regime is just and reasonable and that the framework leaves to the \nappropriate state commissions how such costs are recovered from the local utilities and \ntheir customers. \nThese protections are necessary for the proposal to satisfy the Federal Power Act’s just-\nand-reasonable standard. Section 205 requires that all Commission-jurisdictional rates, charges, \npractices, and classifications be just and reasonable. PJM bears the burden to demonstrate that each \nproposed IRAS condition, including its BYONC eligibility, load-reduction sequencing, and \ncompensation provisions, satisfies that standard. \nII. \nOELC’S INTEREST AND EXPERIENCE. \n \nOELC is a not-for-profit trade association that represents its members’ interests in utility \nand ratemaking matters in Ohio. Managing the cost and availability of energy is a crucial \ncomponent of success for many businesses, and OELC advocates for competitive, reasonable, and \ntransparent laws, policies, and utility rates through effective lobbying and legal advocacy. OELC’s \nwork is directed to ensuring Ohio remains an attractive place for businesses and enterprises to \nremain, grow, invest, and create jobs. \nFor more than 30 years, OELC has helped its members understand and manage their \nelectric and natural gas supply costs. OELC and its members have direct, long-standing experience \nwith the practical effects of utility tariffs, rate design, energy legislation, and regulatory policy on \nOhio businesses that must manage significant energy consumption and exposure to volatile energy \ncosts. OELC’s members include energy-intensive manufacturing, industrial, educational,"},{"page":3,"startToken":601,"endToken":895,"text":"3 \n \ninstitutional, and retail business customers in Ohio. Collectively, OELC’s members annually \nconsume many billions of kilowatt-hours of electricity and are major contributors to Ohio’s \neconomy and employment sector. For OELC’s members, electricity is not a discretionary \npurchase; it is a material production input, a prerequisite to continuous operations, and a major \ncomponent of the delivered cost of goods and services. \nThrough its dedicated lobbying and regulatory advisors, OELC actively participates in \nlegislative matters affecting Ohio energy and utility policy and participates in matters before the \nPublic Utilities Commission of Ohio (“PUCO”). That work includes electric distribution-rate \nproceedings for Ohio electric utilities and other PUCO proceedings affecting member utility rates \nand issues. OELC is therefore well positioned to explain how PJM’s IRAS proposal will affect \nOhio end-use customers and the competitiveness of Ohio’s industrial economy.  \nA reliable and reasonably priced electric system is essential to OELC’s members. OELC \ntherefore supports measures that maintain system reliability and allocate the responsibility for new \nload fairly. The Commission should ensure that the IRAS construct does not allow new load to \nobtain preferential treatment in emergency curtailment or to impose on existing customers the cost \nof compensating that new load for complying with the conditions of its earlier, conditional service. \nIII. \nPJM SHOULD ADOPT A SEPARATE 150 MW THRESHOLD FOR NON-DATA-\nCENTER CUSTOMERS BASED ON PLC VALUES. \nPJM proposes to define a Large Load as an end-use customer load with a cumulative peak \nload of 50 MW or greater at a single electrical site.1 OELC does not oppose a definition that \nidentifies the extraordinary new load additions producing the resource-adequacy concerns \nunderlying IRAS. But PJM should not apply a uniform 50 MW threshold that treats traditional, \n \n1 Application, FERC Docket No. ER26-3515-000 (August 13, 2026) at 31-32."},{"page":4,"startToken":895,"endToken":1165,"text":"4 \n \nenergy-intensive, non-data-center customers as similarly situated to data centers or apply that \nthreshold without considering the materially different characteristics of these customer classes. \nLarge non-data center loads include manufacturers, steel mills, chemical facilities, \nuniversities, and retailers, among others. Traditional industrial facilities are foundational to \ndomestic supply chains. They supply critical domestically produced materials and products used \nin infrastructure, transportation, construction, energy systems, agriculture, health care, and \nnational-defense-related production. A durable national-security and national economic strategy \nrequire that these industries have access to reliable and reasonably priced power. Reliability and \naffordability are complementary objectives, not competing ones.  \nThe Commission need not choose between supporting data-center growth and supporting \ndomestic industry. It can do both by applying a definition that targets the new load that creates the \nIRAS regime requirement while maintaining reliable service to the traditional industrial base. The \nApplication itself describes specific characteristics of new data-center load that support \ndifferentiated treatment. PJM states that an “unprecedented surge in data center load” has arrived \nfaster than new supply can come online; the speed of connecting these loads has created a \n“fundamental misalignment between demand and supply cycles,” resulting in significant resource-\nadequacy stress.2 PJM likewise cites data centers’ incomparably large energy demands, rapid \nenergization, and unique collective potential to affect grid reliability and raise rates for other \ncustomers.3 PJM’s Application also identifies data-center growth as the predominant source of the \nnear-term load-growth problem. PJM forecasts 32 GW of peak-load growth between 2024 and \n2030, of which 30 GW is projected to come from data centers.4 \n \n2 Application at 21. \n3 Application at 96-97. \n4 Application at 13."},{"page":5,"startToken":1165,"endToken":1443,"text":"5 \n \nIn this context, penalizing existing manufacturers for energy intensity simply weakens the \nvery industrial capacity on which the nation depends, while doing little to improve the signal sent \nto the new load that drives the need for additional capacity. Energy prices are already a decisive \ncomponent of manufacturing competitiveness. Capacity charges and other demand-related costs \nare not absorbed in a vacuum. They increase the delivered energy cost of production, reduce \noperating margins, constrain capital spending, and affect decisions about production volumes, \nfacility expansions, and employment. OELC’s members compete not only with other domestic \nfacilities but with international producers that may operate under materially different energy, \nregulatory, labor, and capital-cost conditions.  \nThe Commission should not introduce a new cost burden on domestic manufacturing at \nthis critical time in our nation’s economy. The likely effect of an overbroad 50 MW threshold is \nnot confined to the affected bill. Energy-intensive manufacturers transmit higher production costs \nthrough supply chains, or they absorb them by reducing investment, output, or employment. \nNeither outcome advances reliability, affordability, or economic resilience. Moreover, traditional \nenergy-intensive customers often operate equipment and facilities with which utilities are familiar, \npromoting more accurate load forecasting and system planning for traditional loads. In the current \ninflation-sensitive environment, the Commission should avoid a tariff design that may add \navoidable cost pressure to domestically produced materials and the goods made from them.  \nA tailored distinction between data center and non-data center load is neither unduly \ndiscriminatory nor preferential. That distinction has already been implemented in Ohio where the \nPublic Utilities Commission of Ohio has found a reasonable basis for treating data centers \ndifferently where their unique, concentrated load characteristics and system impacts distinguish"},{"page":6,"startToken":1443,"endToken":1799,"text":"6 \n \nthem from other large-load customers.5 The Federal Power Act does not require PJM to disregard \nmaterial differences among load categories. Rather, a just-and-reasonable tariff should recognize \nthe materially different characteristics of data centers and avoid placing traditional manufacturing \nand industrial customers in the IRAS category solely because they exceed an undifferentiated 50 \nMW threshold.  \nOELC therefore requests that the Commission direct PJM to establish a separate 150 MW \nthreshold for non-data-center customers. A 50 MW threshold that indiscriminately includes every \ncustomer category is overinclusive. It risks imposing undue IRAS-related obligations on \ntraditional industries based on electricity intensity alone, rather than on a demonstrated causal \nnexus between incremental demand and the specific reliability concern the IRAS proposal is \ndesigned to address. Additionally, the non-data center 150 MW threshold should be calculated \nbased on the customer’s system-peak PLC, rather than a non-data center customer’s highest \ndemand during any hour of the year. Capacity-related classifications should be based on capacity-\nrelated data—demand when the PJM system is under peak conditions—not an isolated \nnoncoincident operating maximum. A threshold must do more than identify customers that use a \nmeaningful amount of electricity. It must identify customers whose incremental system-peak \ndemand creates the need for the specific capacity procurement and associated charges. \n \n5 See, e.g., Opinion & Order, PUCO Case No. 24-508-EL-ATA (July 9, 2025) at 76-78 (“unlike non-data center \nload, which comprises a diverse group of customer end uses, data center load cannot be naturally hedged by other \nindustries in AEP Ohio’s service territory…Thus, we recognize that data center customers pose a different type of \nrisk, as well as an increased amount of risk”); Opinion and Order, Case No. 25-392-EL-AIR (April 1, 2026) at 65-66 \n(approving settlement separating data centers into their own rate class in future case); Finding and Order, PUCO \nCase No. 26-113-EL-ATA (August 5, 2026) at 12 (“Limiting the Interim Relief to customers subject to the DCT is \nconsistent with the existing regulatory framework in the state of Ohio and continues to be narrowly tailored for \ncustomers that present unique load characteristics and system impacts that distinguish them from other large load \ncustomers.”)."},{"page":7,"startToken":1799,"endToken":2098,"text":"7 \n \nThat is because capacity procurement exists to ensure that sufficient resources are available \nwhen the PJM system faces its highest coincident peak demand. The relevant question, therefore, \nis not whether a particular customer ever reached a high demand level in an isolated hour. It is \nwhether the customer materially contributes to the regional peak conditions that establish the \nsystem’s capacity need. A customer-specific annual maximum can occur in a season, hour, or \noperating condition that does not coincide with the PJM system peak. It may reflect a one-time \nproduction event, an outage recovery, a weather-related operational adjustment, commissioning \nactivity, or another idiosyncratic event with no meaningful relationship to the capacity issues in \nPJM that its IRAS proposal attempts to address. Using that noncoincident maximum would \noverstate the customer’s capacity responsibility and produce classifications untethered from the \nneed for incremental capacity. \nBy contrast, system-peak PLC is a familiar and objective planning construct used by PJM \nfor many years. It measures demand when capacity is most needed by the region. PJM itself relies \non load adjustments and capacity-obligation concepts that are intended to assign changes in \nforecasted load to the zone or area where they occur. The Large Load definition should employ \nthe same fundamental principle: identify load by its contribution to the relevant system condition, \nrather than by an isolated and potentially unrepresentative maximum peak demand. \nIf a customer can be classified as a Large Load based on its highest demand at any time in \na year, a single non-coincident operating hour could trigger long-lived tariff consequences. That \napproach would be unpredictable, hard to audit, and unfair to customers with variable \nmanufacturing processes. It could also perversely encourage customers to alter operations during \nindividual high-demand hours without reducing their contribution to system peaks, thereby \nproducing no genuine reliability benefit."},{"page":8,"startToken":2098,"endToken":2444,"text":"8 \n \nThe Commission should thus reject a methodology that conflates a facility’s maximum \noperating demand with its system-relevant contribution to capacity requirements. A capacity-\nrelated classification must be based on capacity-related data. Accordingly, the Commission should \ndirect PJM to revise its proposed tariff language to resolve at a minimum the following issues: \n1. \nEstablish a separate, protective 150 MW threshold for non-data-center customers. A \nnon-data-center customer—including but not limited to traditional manufacturing, \nsteelmaking, chemical, industrial, educational, institutional, and retail customers—should \nbe treated as a Large Load only if its PLC is at least 150 MW. The lower 50 MW threshold \nshould not apply to non-data-center customers. \n2. \nUse of PLC Values. Identify the precise PJM peak-hour set and the period used to calculate \nthe customer’s peak load for purposes of defining a “Large Load Customer,” including the \nprocess for publishing those hours and correcting data errors. OELC recommends that PJM \nbe directed to use the existing PLC methodology; an annual maximum, an unannounced \nad hoc interval, or a noncoincident peak should not be used. \n3. \nNet-load treatment. Specify the treatment of behind-the-meter generation, demand \nresponse, energy storage, and other load-management arrangements, including the data \nnecessary to verify net system contribution. \n4. \nCustomer notice and verification. Provide customers with advance notice of proposed \nclassification, their underlying interval data and calculated PLC, a reasonable time to \ncorrect errors, and a transparent mechanism for challenging a classification before charges \ntake effect. \n5. \nTemporal nexus to new load. For purposes of the IRAS, require PJM and the relevant \nelectric distributor to demonstrate that the customer’s qualifying PLC reflects new or \nincremental load relative to the forecast or baseline used to establish the relevant target. \nExisting load should not be reclassified solely because it is large. \nThese elements are indispensable. Without them, manufacturing customers cannot forecast \ntheir exposure, evaluate the accuracy of their bills, or meaningfully participate in any state retail-\ncost-allocation proceeding. Ambiguity in the definition and measurement of load invites \ninconsistent results, disputes, and cost shifting—the opposite of the transparent and reasonable \ntariff administration OELC seeks."},{"page":9,"startToken":2444,"endToken":2732,"text":"9 \n \nIV. \nTHE SEQUENTIAL LOAD-REDUCTION STACK PROPOSED BY PJM SHOULD \nBE PRESERVED EVEN IF NEW LARGE LOAD USES DEMAND RESPONSE AS \nBYONC. \nPJM’s application explains that its emergency procedures use sequential load reduction. \nSites registered in the PJM demand-response program as Demand Resources may be called to \nreduce load in Pre-Emergency and Emergency Load Management Reduction Actions before firm \nexports are reduced in a Maximum Generation Emergency. PJM proposes to add IRAS as a \ncategory of load reduction that precedes Demand Resources and DER Capacity Aggregation \nResources in that sequence.6 That sequencing is integral to the proposed incentive structure. PJM \nexplains that placing IRAS after Pre-Emergency Load Management would reduce the incentive \nfor New Large Loads to bring new capacity because the new loads would instead be insulated by \nDemand Resource capacity products.7  \nOELC recommends that the Commission approve the curtailment sequencing proposed by \nPJM in this case. This is particularly important because PJM’s proposal may permit New Large \nLoad to rely on demand response resources to meet BYONC requirements. A New Large Load \nthat has not brought new generation could, in theory, register as a Demand Resource, avoid the \nearlier IRAS tranche, and move into the later Demand Resource tranche. It could improve its \nposition in the sequential load-dump stack through a contractual arrangement rather than through \nthe procurement of distinct incremental supply. The question is not whether Demand Resources \nprovide reliability value. Properly structured and verifiable demand response can provide \nsubstantial benefits to the system, including demand resources offered by New Large Load. Rather, \nthe question is whether a New Large Load’s participation in Demand Response should change the \ncurtailment priority proposed by PJM under IRAS.  \n \n6 Application at 101.  \n7 Application at 80."},{"page":10,"startToken":2732,"endToken":3022,"text":"10 \n \nThis tension can be resolved by creating a new category of Demand Resources consisting \nof New Large Load that elects to utilize its own curtailment capability as BYONC. The \nCommission should, therefore, direct PJM to revise its proposed tariff to provide that, to the extent \nNew Large Load utilizes new Demand Resources or new DER Capacity Aggregation Resources \nto satisfy the BYONC requirements, for purposes of load-curtailment sequencing those resources \nshould be curtailed before other PJM demand-response resources. This conditional acceptance of \nPJM’s proposal would help maintain power availability for traditional manufacturers and industrial \ncustomers as grid conditions become constrained by the increasing load brought about by \nincreasing data center demand in PJM. \nV. \nTHE COMMISSION SHOULD ENSURE ANY IRAS COMPENSATION IS JUST \nAND REASONABLE AND RESERVE RETAIL COST RECOVERY QUESTIONS \nFOR THE STATE COMMISSIONS. \nFinally, the Commission should fully evaluate whether PJM’s proposal to offer \ncompensation at fifty (50) percent of the Non-Performance Charge Rate is just and reasonable.8 \nUnder PJM’s IRAS proposal, a New Large Load’s obligation to curtail when required to protect \nreliability is a condition of receiving earlier service. PJM’s own framework is premised on \nallowing qualifying large loads to connect subject to operational controls, including curtailment \nduring specified system conditions, in order to protect customers from potential outages.9 The \nCommission should carefully evaluate the appropriate compensation scheme for New Large Loads \nthat are complying with an IRAS curtailment condition that permits such New Large Loads to \nconnect and energize earlier than the grid may otherwise permit.  \nFurther, OELC respectfully submits that the Commission should avoid approving a \nstructure whereby existing industrial and manufacturing customers will subsidize any such \n \n8 Proposed Tariff, Attachment DD-4, § X(a); Application at 102. \n9 Application at 15-16."},{"page":11,"startToken":3022,"endToken":3205,"text":"11 \n \ncurtailment credits or payments. Instead, the Commission should reserve for the relevant state \nauthorities or commissions with jurisdiction over retail terms and conditions of service how such \ncompensation obligations are ultimately recovered from retail customers. \nVI. \nCONCLUSION AND REQUEST FOR RELIEF. \nOELC does not oppose new load connecting to the PJM system or the development of \nmechanisms that protect reliability while such load is integrated. To the contrary, reliable service \nis essential to OELC’s members and to Ohio’s manufacturing and industrial economy. OELC’s \nconcern is that the IRAS framework must not threaten domestic manufacturing and should \npreserve an appropriate allocation of responsibility. Accordingly, OELC respectfully requests that \nthe Commission condition its approval of PJM’s tariff on the adoption of the recommendations set \nforth in these comments and limited protests. \nDate: September 3, 2026 \nRespectfully submitted, \n \n \n \n \n/s/ David F. Proaño \n \n         \n \nDavid F. Proaño (Counsel of Record) \n \nBenjamin A. Kurtz \n \nBAKER & HOSTETLER LLP  \n \n127 Public Square, Suite 2000 \n \nCleveland, OH 44114 \n \n216-621-0200 / Fax 216-696-0740 \n \nEmail: dproano@bakerlaw.com  \n \nEmail: bkurtz@bakerlaw.com  \n \n \n*Willing to Accept Service by Email*  \n \n \nCOUNSEL FOR OHIO ENERGY  \n \nLEADERSHIP COUNCIL"},{"page":12,"startToken":3205,"endToken":3382,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that on this third day of September 2026, I served the foregoing document by \nelectronic means on each person listed on the Federal Energy Regulatory Commission’s official \nservice list in Docket No. ER26-3515-000.  \n \n \n \nchum@wrightlaw.com; \ncollins@wrightlaw.com; \ncraig.glazer@pjm.com; \nmark.stanisz@pjm.com; \njesse.jacobe@pjm.com; \nneil@persistenceanalyticsgroup.com; \nSuzette.Krausen@monitoringanalytics.com; \njeffrey.mayes@monitoringanalytics.com; \nJoseph.Bowring@monitoringanalytics.com; \ndmabry@mwn.com; \nsbruce@mcneeslaw.com; \nlhuff@mwn.com; \nNancyB@epsa.org; \nblipman@rpa.nj.gov; \ndwand@rpa.nj.gov; \nrglover@rpa.nj.gov; \ndlayugan@rpa.nj.gov; \nmorris.schreim@maryland.gov; \njoey.chen@maryland.gov; \nRansom.Davis@Maryland.gov; \ndslifer@gtpowergroup.com; \ngthomas@gtpowergroup.com; \nlaurac@chappelleconsulting.net; \nscott.metzger@ilag.gov; \nkimberly.janas@ilag.gov; \nandrew.obeso@ilag.gov; \nsusan.satter@ilag.gov; \naleksandar.mitreski@brookfieldrenewable.com; \nnathalie.godard@brookfieldrenewable.com; \nOBustami@mintz.com; \nsshparber@mintz.com; \nemily.starobin@huschblackwell.com; \nlinda.walsh@huschblackwell.com; \nemmanix.simon@edf-re.com; \ntemujin.roach@edf-re.com; \npaul.youchak@bpu.nj.gov; \nsteven.chaplar@law.njoag.gov;"},{"page":13,"startToken":3382,"endToken":3554,"text":"2 \n \nIan.Oxenham@bpu.nj.gov; \njordan.mitchell@law.njoag.gov; \nMahala.Lahvis@bpu.nj.gov; \nelizabeth.vanwinkle@law.njoag.gov; \nairi.kogishi@bpu.nj.gov; \namanda.lescano@bpu.nj.gov; \ntimothy.randazzo@bpu.nj.gov; \nalexander.cary@bpu.nj.gov; \nmichael.youth@ncemcs.com; \nrelliott@mccarter.com; \ncharlie.bayless@ncemcs.com; \nataylor@mccarter.com; \nsbeeny@mccarter.com; \nppolacek@ctenterprises.org; \nppolacek@ctenterprises.org; \nFrank.Swigonski@vistracorp.com; \narnie.quinn@vistracorp.com; \nandrew.weinstein@vistracorp.com; \ntoba.pearlman@illinois.gov; \nChristine.Ericson@illinois.gov; \njudith.judson@calibrantenergy.com; \nmichael.west@ky.gov; \nthomas.lacy@ky.gov; \nclbumgarner@aep.com; \njccrespo@aep.com; \ntlaios@aep.com; \nlturner@aep.com; \ntslocum@citizen.org; \ngabe@verrusdata.com; \nckennedy@duqlight.com; \nmbrechlin@duqlight.com; \nmelatieh@paoca.org; \njharmar@paoca.org; \ncmarquis@advancedenergyunited.org; \nkkoenig@advancedenergyunited.org; \nmhaugh@advancedenergyunited.org; \njgordon@advancedenergyunited.org; \nmalfano@seia.org; \nmona.tierney-lloyd@enel.com; \njuan.diaz9@enel.com; \nFERCe-filings1@Constellation.com; \ncarrie.allen@constellation.com; \njohn.white@constellation.com; \nerik.heinle@constellation.com; \nadrien.ford@constellation.com; \ndenise.cronin@ekpc.coop;"},{"page":14,"startToken":3554,"endToken":3713,"text":"3 \n \nanasantana@eversheds-sutherland.com; \nAllisonSalvia@eversheds-sutherland.com; \nDanielFrank@eversheds-sutherland.com; \nkellycuthbertson@eversheds-sutherland.com; \nwilliam.fields@maryland.gov; \nmichael.sammartino@maryland.gov; \nphilip.sussler@maryland.gov; \njordan.kwok@exeloncorp.com; \nalejandro.bautista@exeloncorp.com; \ncarlos.isaac@exeloncorp.com; \ndpierpont@lspower.com; \ncsummers@citizensutilityboard.org; \nedebellis@citizensutilityboard.org; \nRobert.Gardinor@pseg.com; \nViet.Ngo@pseg.com; \nRobert.Gardinor@pseg.com; \nViet.Ngo@pseg.com; \nRobert.Gardinor@pseg.com; \nViet.Ngo@pseg.com; \nRobert.Gardinor@pseg.com; \nViet.Ngo@pseg.com; \njcliatt@thompsoncoburn.com; \naclair@thompsoncoburn.com; \nleetwood@eei.org; \nkhuyler@eei.org; \nAmber.Thornhill@nationalgrid.com; \nhugheys@michigan.gov; \nClarkA55@michigan.gov; \nmolly.suda@duke-energy.com; \nmolly.suda@duke-energy.com; \nmolly.suda@duke-energy.com; \nmolly.suda@duke-energy.com; \nkhelfrich@ohioec.org; \nlkaleps@ohioec.org; \ngrant.glazer@mn8energy.com; \ncaplan@acore.org; \nhushijima@jpowerusa.com; \nBerthiaumeS@Coned.com; \nsavagep@coned.com; \nhaggartr@coned.com; \nAlvarezh@coned.com; \ncmcgeady@equinix.com; \nahaubenstock@equinix.com; \nkribrown@pa.gov; \nebarnes@pa.gov; \ntiftran@pa.gov;"},{"page":15,"startToken":3713,"endToken":3872,"text":"4 \n \njames.g.davis@dominionenergy.com; \nwesley.walker@dominionenergy.com; \nJRohrbach@acespower.com; \nDamon.Krieger@SMECO.coop; \nEugene.Bradford@smeco.coop; \nfrederick.ochsenhirt@scc.virginia.gov; \nradkins@psc.state.wv.us; \nalan.trotta@uinet.com; \nnoelle.kinsch@avangrid.com; \nkevin.kilgallen@avangrid.com; \nleonard.rodriguez@avangrid.com; \nptoulme@novec.com; \narobbins@washingtonenergylaw.com; \nrsweeney@novec.com; \ndroby@washingtonenergylaw.com; \ntsteiger@washingtonenergylaw.com; \npcolvin@washingtonenergylaw.com; \nkabreu@voltus.co; \ntfodor@imea.org; \ndchung@imea.org; \njeffrey.levine@engie.com; \nsarah.bresolin@engie.com; \nanna.bautista@delaware.gov; \ndavid.crumplar@delaware.gov; \nben@opsi.us; \nellen@opsi.us; \nferccompliance@invenergy.com; \ntoconnor@crowell.com; \nnluckey@invenergy.com; \nferccompliance@invenergy.com; \ntoconnor@crowell.com; \nnluckey@invenergy.com; \nferccompliance@invenergy.com; \ntoconnor@crowell.com; \nnluckey@invenergy.com; \nbshpall@wsgr.com; \nbriangeorge@google.com; \neomsavage@google.com; \nmchristiansen@wsgr.com; \nmbloodworth@americaspower.org; \nzina@basepowercompany.com; \nahosea@basepowercompany.com; \nmadeline@basepowercompany.com; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com;"},{"page":16,"startToken":3872,"endToken":4057,"text":"5 \n \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com;"},{"page":17,"startToken":4057,"endToken":4220,"text":"6 \n \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \nmichael.yuffee@bakerbotts.com; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nBRIANNA.ANDERSON@NRG.COM; \njoe.bower@bakerbotts.com; \ncortney.slager@nrg.com; \nmichael.yuffee@bakerbotts.com; \nBRIANNA.ANDERSON@NRG.COM; \nbwhite@cleanpower.org; \nmgarber@mcneeslaw.com; \njustin.vickers@sierraclub.org; \nerilling@cpv.com; \nmlitchfield@cpv.com; \nedean@firstenergycorp.com; \nmparke@firstenergycorp.com; \nedean@firstenergycorp.com; \nmparke@firstenergycorp.com; \nedean@firstenergycorp.com; \nmparke@firstenergycorp.com; \nedean@firstenergycorp.com; \nmparke@firstenergycorp.com; \nedean@firstenergycorp.com; \nmparke@firstenergycorp.com; \nedean@firstenergycorp.com; \nmparke@firstenergycorp.com; \nedean@firstenergycorp.com; \nmparke@firstenergycorp.com; \nedean@firstenergycorp.com; \nmparke@firstenergycorp.com; \nshaun@shaunneal.com; \nmax@nicholasneal.com;"},{"page":18,"startToken":4220,"endToken":4390,"text":"7 \n \ndgoulet@mccarter.com; \nangela.obrien@occ.ohio.gov; \njohn.mccaffrey@stinson.com; \nlmcalister@amppartners.org; \nghull@amppartners.org; \ncnorton@amppartners.org; \nnwallace@elpc.org; \nkduffley@naruc.org; \njramsay@naruc.org; \nclangree@nrdc.org; \nScott.Strauss@spiegelmcd.com; \npeter.hopkins@spiegelmcd.com; \njeffrey.schwarz@spiegelmcd.com; \nlauren.springett@spiegelmcd.com; \nbkurtz@bakerlaw.com; \ndproano@bakerlaw.com; \nScott.Strauss@spiegelmcd.com; \npeter.hopkins@spiegelmcd.com; \njeffrey.schwarz@spiegelmcd.com; \nlauren.springett@spiegelmcd.com; \nScott.Strauss@spiegelmcd.com; \npeter.hopkins@spiegelmcd.com; \njeffrey.schwarz@spiegelmcd.com; \nlauren.springett@spiegelmcd.com; \nScott.Strauss@spiegelmcd.com; \npeter.hopkins@spiegelmcd.com; \njeffrey.schwarz@spiegelmcd.com; \nlauren.springett@spiegelmcd.com; \nScott.Strauss@spiegelmcd.com; \npeter.hopkins@spiegelmcd.com; \njeffrey.schwarz@spiegelmcd.com; \nlauren.springett@spiegelmcd.com; \nkimberly.frank@klgates.com; \nthomas.devita@klgates.com; \nSMNadel@pplweb.com; \ncharlie.iannello@igs.com; \newhittle@nixonpeabody.com; \nbdunning@progressivereform.org; \nsarah.parrot@puco.ohio.gov; \nthomas.lindgren@ohioattorneygeneral.gov; \nbecca.smith@sunrun.com; \narielhorowitz@anthropic.com; \nbreiter@akingump.com; \nshug@akingump.com; \nmorgan@datacentercoalition.org; \nandrew.devore@kirkland.com;"},{"page":19,"startToken":4390,"endToken":4428,"text":"8 \n \njohn.decker@kirkland.com; \ncassidy.hall@kirkland.com; \nJennifer.Mansh@talenenergy.com; \nsco@vitol.com; \nbja@vcrenewables.com; \nenc@vitol.com; \nenc@vitol.com; \nsco@vitol.com; \n \n \n \n \n \n \n/s/ David F. Proaño \n \n         \n \n \nDavid F. Proaño   \n \n \nCounsel of Record"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":608,"startToken":0,"endToken":82},{"p":1,"at":608,"title":"I. SUMMARY OF COMMENTS AND LIMITED PROTESTS.","method":"printed heading","endPage":2,"endAt":1357,"startToken":82,"endToken":457},{"p":2,"at":1357,"title":"II. OELC’S INTEREST AND EXPERIENCE.","method":"printed heading","endPage":3,"endAt":1471,"startToken":457,"endToken":807},{"p":3,"at":1471,"title":"III. PJM SHOULD ADOPT A SEPARATE 150 MW THRESHOLD FOR NON-DATA-","method":"printed heading","endPage":9,"endAt":5,"startToken":807,"endToken":2445},{"p":9,"at":5,"title":"IV. THE SEQUENTIAL LOAD-REDUCTION STACK PROPOSED BY PJM SHOULD","method":"printed heading","endPage":10,"endAt":792,"startToken":2445,"endToken":2846},{"p":10,"at":792,"title":"V. THE COMMISSION SHOULD ENSURE ANY IRAS COMPENSATION IS JUST","method":"printed heading","endPage":11,"endAt":275,"startToken":2846,"endToken":3058},{"p":11,"at":275,"title":"VI. CONCLUSION AND REQUEST FOR RELIEF.","method":"printed heading","endPage":12,"endAt":0,"startToken":3058,"endToken":3205},{"p":12,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":19,"endAt":269,"startToken":3205,"endToken":4428}]}