{"document":{"slug":"rec-20260903-5229","title":"Limited Protest of East Kentucky Power Cooperative, Inc. to PJM Interconnection, L.L.C.’s 08/13/2026 proposed revisions to the Open Access Transmission…","issued":"2026-09-03","accession":"20260903-5229","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"East Kentucky Power Cooperative, Inc.","kind":"protest","file":"sources/filings/text/20260903-5229_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5229","tier":"record","sha256":"db798fa4f084c5255161fd50d2fd65d3fccfcc1819d0ae7fce3b5679e8af9696","pages":71,"tokens":20861,"emptyPages":[],"textThemes":["flex","adequacy","registry","study"]},"pages":[{"page":1,"startToken":0,"endToken":284,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n) \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \n \n \n) \n \nLIMITED PROTEST OF \nEAST KENTUCKY POWER COOPERATIVE, INC.  \n \nPursuant to Rule 211 of the Commission’s Rules of Practice and Procedure1 and the \nCommission’s August 13, 2026 “Combined Notice of Filings #2,” East Kentucky Power \nCooperative, Inc. (“EKPC”)2 hereby submits this limited protest of the August 13, 2026 filing3 of \nPJM Interconnection, L.L.C. (“PJM”) proposing revisions to its Open Access Transmission Tariff \n(“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to \nestablish an Interim Resource Adequacy Service (“IRAS”). Under its IRAS Proposal, PJM would \nbe authorized to direct Electric Distributors to implement load curtailments as a new emergency \nprocedure step subject to North American Electric Reliability Corporation (“NERC”) compliance \nand provide compensation to the load that is curtailed. To support IRAS, PJM is also proposing in \nthe IRAS Proposal new definitions for Large Load, New Large Load, and Eligible New Large \nLoad; the creation of a Large Load Registry; and the exclusion of New Large Loads from the \nVariable Resource Requirement (“VRR”) curve starting in the 2029/2030 Delivery Year. \nEKPC shares the concern that PJM is attempting to address through the establishment of \nan IRAS-type service, and supports the curtailing of data center load that connects without it or its \n \n1 18 C.F.R. § 385.211 (2026). \n2 EKPC filed a doc-less motion to intervene in this proceeding on August 18, 2026. \n3 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, “Proposal of PJM Interconnection, L.L.C. to Establish \nInterim Resource Adequacy Service and a Large Load Registry to Address System Reliability” (filed Aug. 13, 2026) \n(“PJM IRAS Filing”)."},{"page":2,"startToken":284,"endToken":567,"text":"2 \nLoad Serving Entity (“LSE”) securing sufficient Capacity Resources. However, PJM’s IRAS, as \nproposed, is not the solution. PJM’s IRAS Proposal includes provisions that are not just and \nreasonable and could result in the curtailment of load that is supported by capacity resources and \ntherefore not contributing to the resource adequacy concerns that the IRAS Proposal is intended \nto address. Moreover, PJM requiring other loads in the zone not contributing to the need for IRAS \nto pay for the IRAS curtailments is not just and reasonable. Finally, PJM’s proposal discriminates \nbetween similarly situated load based solely on whether its LSE satisfies its capacity obligation \nthrough Reliability Pricing Model (“RPM”) auctions or the Fixed Resource Requirement (“FRR”) \nalternative; the IRAS Proposal compounds the problem by adopting an additional requirement for \nFRR Capacity Plans that creates ambiguity and may disadvantage entities that elect FRR in the \nfuture. \nFor these reasons, and as discussed herein, the Commission should reject several elements \nof PJM’s proposed Tariff and RAA revisions and require appropriate clarifications and revisions \nto the IRAS Proposal in order to avoid unjust and unreasonable or unduly discriminatory results. \nI. \nBackground \nA. IRAS Overview \nAs proposed by PJM, IRAS is a supplemental reliability mechanism that addresses the \nundisciplined connection of New Large Loads without sufficient capacity being available in the \nPJM Region. As explained by PJM, IRAS permits New Large Loads to connect to the PJM system \nwhile managing the capacity shortfall that confronts the PJM Region through targeted, emergency \nload reductions and incentives for self-supply of new capacity.4 Fundamentally, as explained by \nPJM, “IRAS will enable PJM to prioritize load reduction in zones/areas where New Large Loads \n \n4 PJM IRAS Filing at 22."},{"page":3,"startToken":567,"endToken":871,"text":"3 \nhave not brought their own new capacity or had their capacity needs covered through the \nReliability Backstop Procurement (‘RBP’),” and New Large Loads can avoid IRAS “by bringing \nnew capacity to the system.”5 IRAS will “in Delivery Years when RPM Auctions have failed to \nsecure sufficient capacity, under the proposed IRAS framework, [give] the ability to manage real-\ntime operational issues resulting from such shortages through Interim Resource Adequacy Service \nAction.”6 The PJM IRAS Proposal is being driven by an acute and worsening resource adequacy \ncrisis in the PJM Region, and, as noted by PJM, the IRAS Filing is “is just one part of a multi-\npronged, ongoing effort by PJM to respond to the challenges stemming from the influx of Large \nLoads into the PJM Region.”7 \nPJM explains that, as part of its IRAS Proposal, it is proposing “three foundational \nrevisions” in the IRAS Filing. First, PJM is proposing a load reduction mechanism, which \n“clarif[ies] a Load Serving Entity’s (‘LSE’) obligation to bring new capacity in an amount that \nequals or exceeds its New Large Loads’ peak load or be subject to load reduction requests during \nEmergencies prior to Pre-Emergency Load Management Response.”8 As PJM notes, this “lays the \nfoundation for the IRAS paradigm in PJM.”9 Second, PJM is proposing to establish a Large Load \nRegistry, which will be “a database of information pertaining to Large Loads that will be \nestablished and maintained by PJM.”10 Third, PJM has proposed that certain New Large Loads \n(defined below) will be excluded from the VRR Curve beginning with the 2029/2030 Delivery \n \n5 PJM IRAS Filing at 1-2. \n6 PJM IRAS Filing at 6. \n7 PJM IRAS Filing at 12. \n8 PJM IRAS Filing at 4. \n9 PJM IRAS Filing at 4. \n10 PJM IRAS Filing at 5."},{"page":4,"startToken":871,"endToken":1115,"text":"4 \nYear “to protect residential customers from capacity price.”11 PJM claims that its IRAS Proposal \nis “consistent with the Statement of Principles Regarding PJM issued on January 16, 2026, by the \nNational Energy Dominance Council (‘NEDC’) and the 13 governors of the PJM states, and the \nRatepayer Protection Pledge.”12 \n1. IRAS Load Reduction Mechanism \nIRAS is a load reduction service, which PJM claims is the “foundation” for IRAS, and will \nbe available starting with the 2027/2028 Delivery Year.13 PJM may invoke an IRAS Action when \nit determines that available economic real-time supply may be insufficient to maintain reserves, \nmeet applicable Reserve Requirements and Interconnection Reliability Operating Limits \n(“IROLs”), or prevent cascading outages.14 Load reductions under IRAS would be called before \nPre-Emergency Load Management Reductions.15 PJM would direct only aggregate MW quantities \nof load reduction to the relevant Electric Distributor zone or area; PJM would not identify specific \nend-use customers for curtailment.16 Electric Distributors, in coordination with state authorities \nand Relevant Electric Retail Regulatory Authorities (“RERRAs”), would determine which retail \nloads are ultimately reduced, consistent with state-approved curtailment programs.17 As explained \nby PJM, this framework reflects a cooperative-federalism model designed to respect the \n \n11 PJM IRAS Filing at 5. \n12 PJM IRAS Filing at 6. \n13 PJM IRAS Filing at 7. \n14 PJM IRAS Filing at 2, 75. \n15 PJM IRAS Filing at 82, 94-95. \n16 PJM IRAS Filing at 86. \n17 PJM IRAS Filing at 87."},{"page":5,"startToken":1115,"endToken":1433,"text":"5 \njurisdictional divide between federal wholesale authority and state retail authority under the \nFederal Power Act (“FPA”).18 \n2. Large Load Registry \nPJM proposes to establish a centralized registry of Large Loads in the PJM Region, \nmaintained by PJM and updated periodically.19 The registry would collect detailed information \nincluding, among other items, peak load quantities, in-service dates, Bring Your Own New \nCapacity (“BYONC”) quantities, backup generation, points of interconnection, and relevant \ncontracts.20 Information would be available – subject to confidentiality protections under \nOperating Agreement, section 18.17 – to authorized state public service commissions, \nTransmission Owners, Electric Distributors, LSEs, the Market Monitoring Unit, and the \nCommission, with aggregated data posted publicly by zone/area.21 PJM claims that the registry \nreceived strong stakeholder support: 82% of 66 respondents in a July 16, 2026 poll agreed that a \nlarge-load registration requirement was necessary, and seven of ten stakeholder proposals included \na registry concept.22 Notably, however, several stakeholder respondents to the poll indicated that \nsupport for a registry concept was framed around imposing the Connect and Manage (now called \nIRAS) obligation on the LSE, not the use of the registry as PJM has adopted in the IRAS. In the \nuse of a registry that PJM has proposed in IRAS, the obligation is imposed on the Electric \n \n18 PJM IRAS Filing at 86. \n19 PJM IRAS Filing at 22. \n20 PJM IRAS Filing at 37. \n21 PJM IRAS Filing at 37-38. \n22 PJM IRAS Filing at 30. EKPC takes issue with PJM’s characterization of support for a large load registry as \nsupporting what PJM proposed in the IRAS Filing. EKPC agrees that there is significant stakeholder support for a \nregistry. But the registry as proposed by PJM is not reflective of the characteristics of the registries included in the \nother stakeholder proposals. Therefore, PJM is overstating the stakeholder support for the Large Load Registry it has \nproposed in this proceeding."},{"page":6,"startToken":1433,"endToken":1805,"text":"6 \nDistributor to interpret the registry and or seek guidance from a RERRA to determine which loads \nit must curtail.23 \n3. New Large Load Definitions \nPJM proposes to define “Large Load” as “end-use customer(s) load that has a cumulative \npeak load of 50 megawatts or greater at a single electrical site behind one or more points of \ninterconnection, where for configurations involving multiple affiliated load facilities or multiple \npoints of interconnection with affiliated load facilities behind them, all affiliated load facilities \nwithin a one-mile radius will be considered a single electrical site as further described in the PJM \nManuals.”24 “New Large Load” is defined separately as “an end-use customer load that is either \n(a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after \nJune 1, 2027, that increases the existing end-use customer load at a single electrical site that, prior \nto such incremental load, did not previously meet the definition of Large Load.”25 Last, “Eligible \nNew Large Load” is defined as “a New Large Load eligible to provide Interim Resource Adequacy \nService in accordance with Tariff, Attachment DD-4, section V.”26 \n \n23 PJM Interconnection, L.L.C., CIFP – Reliability Backstop Procurement/Connect & Manage Summarized Poll \nResults, at 33, https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/postings/cifp-poll-results-with-\ncomments.pdf. (Stakeholder respondents noted that “[a] registry is necessary for both the Reliability Backstop \nProcurement and for the Connect & Manage framework to ensure costs and curtailments are assigned appropriately. \nConsistent with the Statement of Principles, a registry will ensure that new Large Load customers (cost causers), \nthrough the LSEs that serve them, are appropriately assigned the cost of capacity procured through the Reliability \nBackstop Procurement (RBP) mechanism. Absent a registry, it is unclear how other end-use consumers could be \ninsulated from these costs. . . . Additionally, it is unclear how, absent a registry, a Connect & Manage framework \ncould be implemented in a way that protects other end-use consumers from being curtailed in response to a PJM \nConnect & Manage event.”). \n24 PJM IRAS Filing at 31 (quoting Proposed RAA, Definitions – Large Load). \n25 PJM IRAS Filing at 38 (quoting Proposed Tariff, Definitions – New Large Load). \n26 See Proposed Tariff, Definitions – Eligible New Large Load."},{"page":7,"startToken":1805,"endToken":2083,"text":"7 \n4. Bring Your Own New Capacity (“BYONC”) \nNew Large Loads may avoid or reduce their IRAS exposure by contracting with qualifying \nnew capacity. BYONC is defined as new megawatts of Unforced Capacity (“UCAP”) that meet \nspecified “gating criteria” to ensure that the capacity is genuinely new – including new-build \ngeneration, qualifying uprates, repowered deactivated resources, qualifying fuel conversions, and \ncertain new demand-side resources.27 To ensure that the capacity benefits are durable, BYONC \nmust participate as a price taker ($0/MW offer) in RPM Auctions for ten consecutive Delivery \nYears, subject to all capacity market rules.28 A New Large Load’s potential IRAS obligation is \ninversely proportional to the amount of BYONC and Allocated RBP UCAP MW it has secured.29 \n5. VRR Curve Exclusion \nBeginning with the 2029/2030 Delivery Year, PJM proposes to exclude incremental New \nLarge Loads from the VRR Curve to the extent that they do not have sufficient BYONC or \nAllocated RBP UCAP MW arrangements.30 Once a New Large Load’s associated BYONC is \noffered into the applicable RPM Auction, the corresponding load would be reflected in the demand \ncurve.31 This measure is intended to protect residential customers from capacity price increases \nattributable to large-load additions that have not secured their own capacity.32 It also has the effect \nof limiting BYONC to only those resources that clear simultaneously with the New Large Load. \n \n27 PJM IRAS Filing at 53-54. \n28 PJM IRAS Filing at 56-57. \n29 PJM IRAS Filing at 23. \n30 PJM IRAS Filing at 23-24. \n31 PJM IRAS Filing at 23-24. \n32 PJM IRAS Filing at 5-6. Without the proposed exclusion, demand would be greater, driving up capacity prices."},{"page":8,"startToken":2083,"endToken":2338,"text":"8 \nB. The Stakeholder Process and Joint EDC Proposal \nPJM’s IRAS Proposal emerged from several overlapping stakeholder and PJM Board-\ndriven processes. On January 16, 2026, the PJM Board issued a letter outlining a multi-pronged \napproach to addressing large-load resource adequacy challenges, including a backstop \nprocurement and cost-allocation mechanisms.33 On March 25, 2026, the Board directed formation \nof the Connect and Manage Senior Task Force to develop a framework for connecting large loads \nsubject to operational controls.34 The PJM Board initiated a Critical Issue Fast Path (“CIFP”) \nstakeholder process on April 8, 2026, initially focused on the RBP, the scope of which was later \nexpanded to include the IRAS framework, concluding that the “substantive link” between RBP \nand IRAS warranted a single process.35 The expanded CIFP concluded on June 30, 2026.36 \nStakeholders submitted advisory votes on eleven proposals addressing the concepts embodied in \nIRAS; none achieved the requisite two-thirds support.37 \nDespite this outcome, the PJM Board concluded that the deteriorating resource adequacy \noutlook required timely action.38 On July 27, 2026, the Board issued a decisional letter directing \nPJM to file the IRAS Proposal as presented.39 The IRAS Proposal is therefore a PJM Board-\ndirected filing, not a stakeholder-endorsed compromise.40 \n \n33 PJM IRAS Filing at 15. \n34 PJM IRAS Filing at 15-16. \n35 PJM IRAS Filing at 16. \n36 PJM IRAS Filing at 16. \n37 PJM IRAS Filing at 16. \n38 PJM IRAS Filing at 16-17. \n39 PJM IRAS Filing at 16-18. \n40 PJM IRAS Filing at 16."},{"page":9,"startToken":2338,"endToken":2664,"text":"9 \nEKPC was a co-sponsor of a Connect & Manage proposal (the “Joint EDC Proposal”) that \nreceived 50% stakeholder support.41 The Joint EDC Proposal recognized that “[i]f LSEs take on a \nretail obligation to supply Large Loads, as defined by the PJM Tariff, without sufficient capacity \nresources to serve them, they impose risk onto the PJM region. It is appropriate to place rules upon \nsuch entities to mitigate that unreasonable risk to others.”42 The Joint EDC Proposal featured some \nof the same concepts as PJM’s IRAS Proposal, including a large load registry, a definition of “New \nLarge Load,” and BYONC resources and determinations.43 But, how the Joint EDC Proposal \nproposed to implement these concepts differed in significant ways from PJM’s IRAS Proposal. \nII. \nLimited Protest \nA. Introduction \nPJM claims that IRAS is necessary “to mitigate the potential reliability risks associated \nwith resource adequacy” and is a “mechanism to support reliability while allowing New Large \nLoads to connect even when new capacity supply lags behind load growth.”44 EKPC shares PJM’s \nconcern about resource adequacy and the reliability challenges facing the PJM Region, supports \nmeasures that maintain resource adequacy, and recognizes the urgency of PJM’s reliability \nconcerns. EKPC even supports the idea of an IRAS-type service as evidenced by its sponsorship \nof the Joint EDC Proposal. However, as filed, the PJM IRAS Proposal imposes unreasonable \ncurtailment risk on loads not contributing to the resource adequacy concepts underpinning the \n \n41 In addition to EKPC, the Joint EDCs included: Buckeye Power, Dominion Energy, Duquesne Light Company, \nExelon, Old Dominion Electric Cooperative, PPL Electric Utilities Corp., Southern Maryland Electric Cooperative, \nDuke Energy Ohio, and Duke Energy Kentucky. See PJM Critical Issue Fast Path – Reliability Backstop Procurement \n/ Connect & Manage, Joint EDCs Connect & Manage CIFP Package (June 30, 2026), https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mc/2026/20260630-special/item-01f---1-joint-edcs---cm---\nexecutive-summary.pdf (“Joint EDC Proposal Summary”). \n42 Id. \n43 Id. \n44 PJM IRAS Filing at 13-14."},{"page":10,"startToken":2664,"endToken":2969,"text":"10 \nproposal, and establishes unduly discriminatory treatment of similarly situated load. As a result, \ncertain elements of the IRAS Proposal are not consistent with requirements of the FPA. \nKey elements of the IRAS Proposal are unjust and unreasonable. First, the IRAS \nProposal is unjust and unreasonable because it fails to recognize an LSE’s existing supply portfolio \nin determining whether load will be subject to IRAS. If an RPM Self-Supply LSE has sufficient \nresources – either owned or secured through bilateral contracts, whether “new” or existing – to \nmeet the demand of its load, that load should not risk being subject to the IRAS requirements, \nincluding in particular curtailment. Snapping a line between what is “new” versus “existing” and \nignoring certain resources voids the value that loads relying upon those resources otherwise should \nbe able to derive. It unreasonably subjects loads that were not contributing to the need for IRAS \nto curtailment obligations. \nSecond, similarly, PJM has proposed that a BYONC resource must be committed in an \nRPM Auction at the same time the New Large Load is included in the RPM Auction in order to \noffset IRAS exposure. This requirement creates the potential for disconnects between the \ncommercial operation date of a BYONC resource, the timeline for the conducting of an RPM \nAuction, and full Delivery Year commitment required by RPM Auctions. These potential \ndisconnects mean that an LSE may have brought real capacity to the system yet the associated load \nremains exposed to IRAS. As explained in the Affidavit of Marc Montalvo, as a result of PJM’s \nproposal, resources with similar reliability characteristics may receive different treatment under \nIRAS.45 This fundamentally undermines the resource adequacy incentives that PJM intends to \ncreate with IRAS and penalizes loads that did not contribute to the need for IRAS. \n \n45 Attachment 1, Affidavit of Marc D. Montalvo (“Montalvo Affidavit”)."},{"page":11,"startToken":2969,"endToken":3293,"text":"11 \nThird, it is unreasonable to require specific capacity resources to be devoted to the service \nof specific end-consumer large loads. Yet that is what PJM’s IRAS Proposal does since curtailment \nexposure may depend on whether UCAP MW from BYONC receives recognition for satisfying \nthe peak load contribution of a specific Large Load and is tagged to that load through the in-service \nlifespan of that specific Large Load.46 As a result, PJM’s IRAS Proposal ignores prudent portfolio \nplanning and the standard practice of Self-Supply LSEs specifically to develop and manage \nresources on a system-wide basis (i.e., for the entirety of their load obligation, not matching \nspecific resources to specific loads). Mr. Montalvo explains that the “resource-to-load attribution” \nrequired by IRAS is contrary to “longstanding utility planning and operating practice.”47 \nFourth, as proposed, the strict BYONC recognition rules create an unreasonable restriction \non an LSE’s ability to adjust its portfolio. Under PJM’s proposal, BYONC is non-transferable,48 \nand a BYONC arrangement with New Large Load is permanent “unless and until the New Large \nLoad is permanently out-of-service.”49 This restriction does not seem to account for the fact that \nan LSE may serve multiple loads, and an LSE should have the flexibility it needs to adjust its \nportfolio to cover its load obligation, including transferring BYONC.50 \nFifth, PJM has not provided sufficient justification for its broad proposed definition of New \nLarge Load. For example, PJM’s proposed definition of New Large Load “encompass[es] all end-\nuse customer(s) load that meet the [certain] requirements.”51 It thus includes commercial and \n \n46 See Proposed Tariff, Attachment DD-4, sections VII(g) and VII(e). BYONC must remain tied to load until \npermanently out of service.  \n47 Montalvo Affidavit at PP 29-30. \n48 PJM IRAS Filing at 65. \n49 PJM IRAS Filing at 64-65; Proposed Tariff, Attachment DD-4, section VII(e)). \n50 See Montalvo Affidavit at P 28.  \n51 PJM IRAS Filing at 35."},{"page":12,"startToken":3293,"endToken":3635,"text":"12 \nindustrial load. However, all of the explanation of the need for IRAS is based on data center load, \nyet without justification PJM sweeps new industrial and manufacturing consumers into its \ndefinition.52 \nAdditionally, EKPC seeks clarification as to how PJM intends to measure the MW quantity \nit will direct an Electric Distributor to curtail in an IRAS Action. This clarification is necessary to \neliminate a potential unjust and unreasonable result. Specifically, EKPC seeks to avoid PJM \ndirecting an Electric Distributor to drop a specified amount of MW based on registered peak loads \nof New Large Loads that exceeds the amount of actual New Large Load demand in real time. Such \na directive from PJM would result in the Electric Distributor having to drop existing customer load \nthat is not New Large Load. PJM proposes to determine the zonal allocation of IRAS based on the \n“total Final RBP Target MW across all zone/areas.”53 Not only does determining the zonal \nallocation of IRAS pursuant to this proposal fail to account for whether the Large Load included \nin the forecast used in the RPM Auctions, which formed the basis for PJM’s shortfall calculation \nsetting the RBP Target, actually came to fruition, it also fails to take into consideration whether \nthat load is actually on line in real-time when PJM is making the decision to issues an IRAS \ncurtailment directive. Thus, the directive could be expecting an Electric Distributor to curtail an \namount of load that is not only larger than the actual Large Load in the zone but also larger than \nthe amount of Large Load actually taking service at that moment. Such a directive would create a \nconundrum for an Electric Distributor in which it must abide by the Operating Instruction or face \npotential NERC compliance consequences. This introduces uncertainty as to whether an Electric \nDistributor will need to shed other load beyond the Large Load that IRAS was intended to address. \n \n52 Montalvo Affidavit at P 32. \n53 PJM IRAS Filing at 68; Proposed Tariff, Attachment DD-4, section IX(a)."},{"page":13,"startToken":3635,"endToken":3924,"text":"13 \nPJM has failed to show that compensating IRAS is just and reasonable. PJM has also \nnot sufficiently demonstrated that compensating IRAS curtailment is warranted. PJM has not \nshown why the IRAS curtailment consequence should be converted into a compensable wholesale \nservice funded by other load.  \nCertain elements of the IRAS Proposal are unduly discriminatory. Certain aspects of \nthe IRAS Proposal are unduly discriminatory because they create an unjustified distinction among \nentities that have taken similar resource adequacy actions. As proposed, New Large Loads within \nan FRR Service Area cannot be Eligible New Large Loads. In contrast, an RPM Capacity Market \nLSE that has likewise prudently planned to serve its load does not receive comparable treatment \nunder the proposed IRAS framework. As explained in Mr. Montalvo’s Affidavit, this raises \ncomparability concerns54 and results in undue discrimination between similarly situated \nparticipants in the PJM market.  \nLast, the proposal also creates ambiguity for, and potentially disadvantages, entities that \nmay elect FRR in the future because it introduces new restrictions on the use of existing generation \nin an FRR Capacity Plan. PJM’s proposal fails to account for the fact that IRAS may not be in \nplace in the future, but this restriction on an FRR Capacity Plan would remain. \nIn conclusion, PJM’s IRAS Proposal attempts to address a legitimate resource adequacy \nneed. Key revisions and clarifications, however, are required in order to ensure PJM addresses the \nresource adequacy need in a just and reasonable and not unduly discriminatory fashion. Therefore, \nfor the reasons discussed herein, the Commission should reject certain provisions of the IRAS \nProposal and require appropriate revisions and clarifications to address the proposal elements that \nwould create unjust and unreasonable and unduly discriminatory results.  \n \n54 Montalvo Affidavit at PP 40-41."},{"page":14,"startToken":3924,"endToken":4360,"text":"14 \nB. Elements of PJM’s IRAS Proposal Are Not Just and Reasonable. \nUnder Section 205 of the FPA, 16 U.S.C. § 824d, all rates and charges made by a public \nutility for the transmission or wholesale sale of electric energy subject to the Commission’s \njurisdiction, and all rules and regulations affecting such rates or charges, “shall be just and \nreasonable.”55 A rate or charge that is not just and reasonable “is hereby declared to be unlawful.”56 \nSection 205(b) further prohibits any public utility from making or granting “any undue preference \nor advantage to any person or subject any person to any undue prejudice or disadvantage.”57 The \nburden of proof is on the filing utility to make an affirmative evidentiary showing that the proposed \nrates, terms, and conditions satisfy the statutory standard.58 General assertions and policy \naspirations are insufficient, and PJM has failed to meet this burden with respect to certain aspects \nof the  IRAS Proposal. \n1. Subjecting LSEs with Sufficient Existing Resources to Cover New Large \nLoad to IRAS is Unjust and Unreasonable. \nPJM’s IRAS Proposal requires all loads satisfying the broad definition of “New Large \nLoads” to be subject to IRAS if new capacity resources are not secured for the load-serving \nobligation associated with the New Large Load.59 As proposed, LSEs serving New Large Loads \nthat have prudently planned their (existing) resource portfolios cannot avoid being subject to IRAS \n \n5516 U.S.C. § 824d(a). \n56 16 U.S.C. § 824d(a). \n5716 U.S.C. § 824d(b). \n58 18 C.F.R. § 35.13 (any public utility filing a rate change must submit detailed data and statements to “sustain the \nburden of proof under the Federal Power Act of establishing that the rate increase is just and reasonable”). See also \n16 U.S.C. § 824d(e) (“[a]t any hearing involving a rate or charge sought to be increased, the burden of proof to show \nthat the increased rate or charge is just and reasonable shall be upon the public utility.”). \n59 Proposed RAA, section 7.8 (“Effective June 1, 2027, each LSE that desires to provide Network Transmission \nService to support New Large Loads must designate one or more Generation Capacity Resources or Capacity Storage \nResources that had not cleared an RPM Auction as Network Resource(s) in a cumulative amount that equals or exceeds \nthe LSE’s New Large Load’s peak load (in MW) as reported in the Large Load Registry pursuant to RAA, Schedule \n11 or such New Large Load may be subject to load reduction requests during Emergencies prior to Pre-Emergency \nLoad Management Response.”)."},{"page":15,"startToken":4360,"endToken":4684,"text":"15 \nwithout additional, new capacity resources. PJM does not propose to evaluate whether an LSE’s \nsupply resource portfolio is sufficient to satisfy aggregate load and reliability requirements. As \nexplained by Mr. Montalvo, PJM does not address whether the LSE is causing the resource \nadequacy concern that IRAS is intended to address.60 However, it is not just and reasonable to \nsubject to IRAS curtailment the load of an LSE that has prudently planned its power supply \nportfolio to include sufficient resources to meet its load-serving obligations, including for New \nLarge Load. \nOne foundational point of the IRAS Proposal is that PJM requires that “the capacity must \nbe new”61 to exempt New Large Load from IRAS. As PJM explains, “new” capacity is “capacity \nadded to the system starting with the 2027/2028 BRA,” subject to certain gating criteria. As a \nresult, according to PJM’s IRAS Proposal, “capacity already on the system would not fall within \nthe definition of BYONC.”62 Additionally, PJM restricts from BYONC eligibility any UCAP MW \nthat cleared in an RPM Auction before establishing an arrangement with New Large Load that \nhave been reported to PJM.63 Because of the requirement that only new capacity can be used by a \nNew Large Load to avoid IRAS and that the New Large Load would have entered into contracts \nbefore the capacity clears an RPM auction, PJM’s IRAS Proposal essentially ignores the existing \nsupply portfolio of an LSE. PJM fails to recognize the value of existing resources to an LSE \nparticipating in the RPM with sufficient existing capacity to cover its aggregate load obligations, \nincluding New Large Loads. Ms. Tucker explains the consequence of failing to recognize the value \nof EKPC’s existing portfolio of resources “To the extent that the load EKPC is obligated to serve \n \n60 Montalvo Affidavit at P 23. \n61 PJM IRAS Filing at 52. \n62 PJM IRAS Filing at 52. \n63 Proposed Tariff, Attachment DD, section VI (a)(iii)."},{"page":16,"startToken":4684,"endToken":5036,"text":"16 \ncan be satisfied with EKPC’s portfolio of resources, it should not be subject to IRAS curtailment \nexposure. To do otherwise would ignore the significant investment that such loads have made to \nsecuring reliability.”64 \nFundamentally, the concern for portfolio-length LSEs is that PJM does not appear to \nprovide an offset for an LSE that has existing or planned portfolio length sufficient to cover some \nor all of the load growth associated with a New Large Load, unless that capacity satisfies BYONC \nrules or is reflected through RBP UCAP MW (i.e., both of which are limited to new capacity \nresources). Allowing such recognition of existing resources would not be “repackaging” of \ncapacity as PJM has characterized it.65 An LSE should retain the economic and reliability benefits \nof its supply portfolio without having to unnecessarily be subject to curtailment or to procure \nadditional resources that may not be needed just to meet PJM’s definition of “new.” As a result, \nEKPC is concerned that PJM’s IRAS Proposal may run afoul of Kentucky Public Service \nCommission precedent and the settlement this Commission approved conditioning EKPC’s \nintegration into PJM.66 \nBecause PJM’s IRAS Proposal fails to recognize the value of prudent planning, disregards \nthe reliability and economic value of an integrated, existing power supply portfolio, and potentially \nsubjects to curtailment load that is not causing the reliability concern that IRAS is intended to \naddress, the IRAS Proposal as filed by PJM is unjust and unreasonable. The Commission should \n \n64 Attachment 2, Affidavit of Julia J. Tucker at P 12 (“Tucker Affidavit”) \n65 PJM IRAS Filing at 23. \n66 See KRS 278.214 (A utility “shall not curtail or interrupt retail electric service within its certified territory … except \nfor customers who have agreed to receive interruptible service, until after service has been interrupted to all other \ncustomers whose interruption may relieve the emergency or other event.”). See also Application of East Kentucky \nPower Cooperative, Inc. to Transfer Functional Control of Certain Transmission Facilities to PJM Interconnection, \nLLC, Case No. 2012-00169 (Application Dated May 3, 2012); EKPC Integration Order (Ky. P.S.C. December 20, \n2012)."},{"page":17,"startToken":5036,"endToken":5353,"text":"17 \nnot accept it without changes by PJM to expressly recognize LSEs’ existing supply in their \nportfolios to serve New Large Load and consequently not be subject to IRAS. \n2. PJM Has Created an Unjust and Unreasonable Timing Issue by \nRestricting BYONC to Capacity that Has Cleared an RPM Capacity \nMarket Auction. \nAs proposed by PJM, for BYONC to “address the capacity needs of New Large Loads,” it \nmust be a Capacity Resource.67 A BYONC resource must have participated in an RPM Capacity \nAuction before the BYONC value may reduce IRAS exposure.68 PJM justifies this requirement by \nstating that it is necessary to make sure that the capacity benefits of BYONC are “real and lasting,” \nand to make sure that all entities are aware of “the rules and obligations that accompany \narrangements between the UCAP of their resource and New Large Loads.”69 PJM justifies the \nrequirement that BYONC participate as a Capacity Resource on the ground that it will ensure that \nthe LSE will not sell capacity attributes outside of the PJM market.70 \nEKPC does not take issue with requiring resources that offset an IRAS obligation to take \non obligations similar to those of an RPM committed capacity resource. However, explicitly tying \nthe BYONC eligibility to RPM commitment goes further than necessary. In many instances, the \ntiming of the RPM Base Residual Auction (“BRA”) or Incremental Auction (“IA”) will be \nsufficient to allow a resource to receive an RPM Capacity Auction commitment. However, the \nrequirement that the BYONC resource must be committed in an RPM Capacity Auction in order \nto be BYONC and thereby reduce IRAS curtailment risk is unreasonably restrictive. Specifically, \nthere can be a mismatch between the infrequent conduct of the IA and the in-service date of \n \n67 PJM IRAS Filing at 55. \n68 PJM IRAS Filing at 55. \n69 PJM IRAS Filing at 55-56. \n70 PJM IRAS Filing at 56."},{"page":18,"startToken":5353,"endToken":5700,"text":"18 \nplanned resources. And resources have Commercial Operation Dates (“COD”) mid-Delivery Year, \nwhich would make them ineligible for RPM commitment the Delivery Year in which they come \non-line and provide operational reliability services to the PJM Region. Mr. Montalvo observed, \n“A resource may therefore enter service, contribute to reliability, and support load without \nreceiving BYONC recognition if its commercial operation date does not align with PJM’s \nqualification and auction schedule.”71 \nThe Joint EDC Proposal addressed this timing concern by allowing resources whose COD \nwould not have enabled them to participate in the 3rd IA of the Delivery Year associated with the \nnew Large Load ramping or achieving full operation to still be considered BYONC until its first \nopportunity to participate in a BRA and obtain an RPM commitment.72 Under the Joint EDC \nProposal, to be eligible, the resource would have had to meet several criteria including: (1) it must \nbe online, (2) it must not take on capacity obligations outside of the PJM Region, and (3) it must \noffer into the Day Ahead energy market commensurate with the Large Load’s schedule for \nramping and achieving full operation.73 This approach would have effectively made the BYONC \nresource comparable to an RPM committed Capacity Resource. PJM could have adopted such an \napproach. \nThe impact of PJM’s restrictive approach on Self-Supply LSEs like EKPC is particularly \nnoteworthy.74 Self-Supply LSEs have committed capital, incurred development costs, and \n \n71 Montalvo Affidavit at P 25. \n72 See Joint EDC Proposal Summary. \n73 See id. \n74 Self-Supply is defined in the PJM Tariff as “Capacity Resources secured by a [LSE], by ownership or contract, \noutside a Reliability Pricing Model Auction, and used to meet obligations under this Attachment or the [RAA] through \nsubmission in a Base Residual Auction or an Incremental Auction of a Sell Offer indicating such Market Seller’s \nintent that such Capacity Resource be Self-Supply. Self-Supply may be either committed regardless of clearing price \nor submitted as a Sell Offer with a price bid. A [LSE’s] Sell Offer with a price bid for an owned or contracted Capacity"},{"page":19,"startToken":5700,"endToken":6073,"text":"19 \nassumed development risk to develop new resources to serve existing and New Large Load. Yet, \nunder PJM’s IRAS Proposal, if any such resource does not meet the RPM Capacity Auction timing \nrequirement, or otherwise comes on-line mid-Delivery Year, an LSE would not get recognition for \nbringing a resource to the system that is contributing to reliability and resource adequacy.75 In fact, \ninstead of receiving a benefit for bringing a new resource to the PJM system, a Self-Supply LSE \nwould continue to face a curtailment risk in addition to having to incur the cost of the resource.76 \nAnd worse, other loads served by such a Self-Supply LSE may be asked to pay for those \ncurtailments pursuant to PJM’s proposed IRAS compensation structure. This result cannot be just \nand reasonable. \nIf a resource reaches commercial operation after the relevant RPM opportunity, or cannot \nalign with a full Delivery Year commitment, an LSE may have brought real capacity to the system \nwhile the associated load remains exposed to IRAS. As explained by Mr. Montalvo, resources with \nsimilar reliability characteristics may receive different treatment under IRAS. A resource that \nsatisfies RPM qualification requirements and secures a capacity commitment may qualify as \nBYONC and reduce or eliminate IRAS exposure.77 However, a resource that enters service shortly \nafter the applicable milestone may receive no BYONC recognition during that Delivery Year \ndespite providing comparable reliability benefits.78 Associated load may therefore “remain subject \nto curtailment because of PJM's administrative qualification and recognition timeline rather than \n \nResource shall not be deemed “Self-Supply,” unless it is designated as Self-Supply and used by the LSE to meet \nobligations under this Attachment or the [RAA].” PJM Tariff, Definitions – Self-Supply. \n75 See Montalvo Affidavit at PP 26-27 in which Mr. Montalvo provides the example of EKPC’s Liberty RICE project, \nwhich has an expected COD of mid-delivery year and had not advanced sufficiently through the interconnection \nprocess to qualify as a Planned Capacity Resource for 2027/2028 or 2028/2029 Delivery Years. See also Tucker \nAffidavit at PP 13-16 in which Ms. Tucker describes the status of the Cooper CCGT and Liberty RICE projects. \n76 Montalvo Affidavit at P 27. \n77 Montalvo Affidavit at P 25. \n78 Montalvo Affidavit at P 27."},{"page":20,"startToken":6073,"endToken":6408,"text":"20 \na shortage of available capacity.”79 PJM says that the objective is to “incent” new capacity. But, \nas proposed, the revised Tariff would fail to recognize new capacity that is real, available, and not \ncommitted outside PJM merely because RPM timing does not line up with the resource’s COD or \nthe New Large Load’s ramp schedule. As a result, IRAS penalizes load not causing the reliability \nconcern IRAS seeks to address. This result cannot be just and reasonable. Therefore, the \nCommission should not accept PJM’s IRAS Proposal unless it is revised to ensure that the timing \ncommitments associated with becoming a capacity resource do not unreasonably restrict the ability \nof a new resource to offset IRAS exposure. \n3. PJM’s IRAS Proposal Unreasonably Requires Specific Capacity \nResources to be Devoted to Specific End-Consumer Large Loads. \nThe fundamental structure of PJM’s IRAS Proposal pushes Large Loads and their LSEs \ntoward tagging specific resources to specific end consumer loads rather than utilizing portfolio \nplanning, which has characterized utility planning for over 100 years. IRAS is framed as a service \nfor New Large Loads that are not in arrangements with new capacity additions. \nPJM is requiring information about “BYONC quantity (MW) and ramp schedule” “related \nto each Large Load served” by the LSE.80 Only New Large Loads that have no (or insufficient) \noffsetting BYONC or Allocated RBP UCAP MW are subject to IRAS. Each New Large Load’s \nregistered peak load is reduced by recognized BYONC and Allocated RBP UCAP MW which \nreduces its IRAS curtailment obligation.81 Similarly, an LSE seeking Network Integration \nTransmission Service to support New Large Loads is required to designate new resources in an \namount equal to or greater than the New Large Load’s peak load, or face IRAS exposure.82 The \n \n79 Montalvo Affidavit at P 27. \n80 Proposed RAA Sch.11, B.1(a). \n81 PJM IRAS Filing at 69, n.183 (citing Proposed Tariff, Attachment DD-4, section V(b)). \n82 PJM IRAS Filing at 49; Proposed RAA, section 7.8."},{"page":21,"startToken":6408,"endToken":6798,"text":"21 \nresult is that a New Large Load can avoid or reduce IRAS exposure only to the extent PJM \nrecognizes specific capacity coverage for individual retail loads. \nAs proposed, IRAS exposure may rely on whether there is specific resource-to-Load \nattribution rather than portfolio sufficiency. This is unduly restrictive on Self-Supply LSEs, like \nEKPC, that are subject to state regulation and integrated resource planning (“IRP”) requirements. \nIn many instances, LSEs like EKPC do not enter into bilateral contracts with generation supply \nthat identify the specific end consumer they are intended to serve. For example, PJM’s proposal \nsubjects any incremental growth that causes a load to exceed 50 MW to IRAS which could result \nin industrial and manufacturing load growth becoming subject to IRAS. An LSE like EKPC plans \nfor such growth using a portfolio of supplies and does not devote a new generation resource or \nbilateral contract to individual end consumers.83 To the extent a bilateral contract were to provide \nthe new capacity, PJM’s IRAS Proposal also has the potential consequence of restricting \ncommercial contracting, which is generally something the Commission will avoid,84 because \ncontracts will have to link resources to specific end-use consumers.85 Certainly PJM should not \nintend through IRAS to upend portfolio planning, regulatory processes and commercial \ncontracting. \n \n83 Similarly, EKPC’s Data Center Tariff allows EKPC to use its portfolio planning approach to satisfy data center load \nsized under 250 MW; larger data centers are required to have designated resources. Even there the requirement does \nnot restrict the larger data centers to be tagged to specific resources with restrictions on the ability to replace designated \nresources. See Tucker Affidavit at PP 17-18. \n84 See e.g., Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1, 554 U.S. 527, 578 (2008) (“[The Commission] \nmay abrogate a valid contract only if it harms the public interest”); Sw. Power Pool, Inc., 144 FERC ¶ 61,059, P 128 \n(2013) (“[A]ll such provisions in bilateral power sales contracts freely negotiated at arm's length between sophisticated \nparties generally would establish contract rates and would come within the [Mobile-Sierra] presumption”).  \n85 See Tucker Affidavit at PP 17-18 in which she describes EKPC’s Data Center Tariff and how the requirement for \nlarger data centers to have designated resources does not “tie” the resource to a particular load as IRAS contemplates."},{"page":22,"startToken":6798,"endToken":7071,"text":"22 \nTaking a “portfolio-based approach reflects longstanding utility planning and operating \npractice.”86 As Mr. Montalvo explains, “Resource adequacy studies, integrated resource plans, \nreserve margin analyses, and reliability assessments evaluate whether aggregate resource \ncapability can satisfy aggregate load obligations. RPM applies a similar framework. Reserve \nmargin requirements, capacity obligations, and resource adequacy assessments do not require \npermanent assignments between individual resources and individual customers.”87 The relevant \ninquiry is whether aggregate resources satisfy aggregate reliability requirements. For example, \nwith respect to EKPC specifically: \nAs a state-regulated generation and transmission cooperative and self-\nsupply LSE, EKPC develops and manages resources to satisfy aggregate \nload obligations and reliability requirements. When evaluating load growth, \nincluding growth from Large Loads, EKPC assesses effects on demand \nforecasts, reserve margin requirements, operational requirements, reliability \nobjectives, and long-term resource plans. Resource development decisions \naddress system requirements rather than the needs of a specific customer or \nload increment. EKPC evaluates generation additions based on their \ncontribution to resource adequacy, reliability performance, operational \nflexibility, fuel diversity, production costs, and other planning objectives. \nA single resource may support load growth of multiple customers across \ncustomer classes, maintain reserve margins, replace aging resources, \nimprove operational flexibility, reduce reliability risk, and strengthen \nportfolio diversity. EKPC therefore evaluates resource additions based on \ntheir contribution to the overall portfolio.88  \nIn order to meet its load serving obligation, EKPC “actively plans its supply portfolio.”89 As Ms. \nTucker notes, “EKPC builds out its portfolio of resources to satisfy the aggregate of its forecasted \n \n86 Montalvo Affidavit at P 30. \n87 Montalvo Affidavit at P 30. \n88 Montalvo Affidavit at P 28. \n89 Tucker Affidavit at P 13."},{"page":23,"startToken":7071,"endToken":7394,"text":"23 \nload needs. EKPC does not tie specific resources in its portfolio to specific Owner Members or to \nany individual end-consumers served by its Owner Members.”90 \nMoreover, the implication of PJM requiring BYONC to be devoted to specific loads while \nalso not accommodating BYONC replacement could leave a load subject to curtailment risk should \nthe initially designated BYONC cease to be able to satisfy the full BYONC 10-year commitment. \nIt is unclear whether the New Large Load is fully excused in such circumstances or whether the \nload becomes subject to IRAS curtailment obligations again.91 \nRestricting an LSE’s ability to prudently plan to serve its aggregate load obligation with a \nportfolio of resources potentially unjustifiably subjects its load to curtailment risk by virtue of \nbeing unable to tag specific resources to specific load. This unreasonably restrictive approach \nshould be rejected by the Commission. \n4. It Is Unjust and Unreasonable to Strictly Restrict the Transferability of \nBYONC. \nPJM has proposed that “once the subject of an arrangement BYONC cannot change to a \ndifferent New Large Load – i.e., BYONC is non-transferable.”92 According to PJM, the restriction \nthat the BYONC arrangement is permanent is “necessary and consistent with PJM’s overall \nscheme.”93 And, “BYONC that is in an arrangement with a New Large Load must remain in such \nan arrangement with that New Large Load unless and until the New Large Load is permanently \nout-of-service.”94 What PJM’s IRAS Proposal does not seem to account for is that an LSE may \n \n90 Tucker Affidavit at P 12. \n91 Proposed Tariff, Attachment DD-4, V(c) (“For purposes of removing its eligibility to provide Interim Resource \nAdequacy Service, a New Large Load may enter into arrangements with BYONC . . . .” The Tariff is silent on \ntreatment if a BYONC resource becomes unavailable.  \n92 PJM IRAS Filing at 64. \n93 PJM IRAS Filing at 65. \n94 PJM IRAS Filing at 64-65; Proposed Tariff, Attachment DD-4, section VII(e))."},{"page":24,"startToken":7394,"endToken":7715,"text":"24 \nserve multiple loads, and an LSE should have the flexibility it needs to adjust its portfolio to cover \nits aggregate load obligation. One Large Load not growing to the size initially anticipated should \nnot restrict the ability of an LSE to apply BYONC to offset the IRAS curtailment obligation of \nanother New Large Load. To do otherwise penalizes an LSE that secures a portfolio of resources \nto serve its aggregate load obligation. As proposed, PJM’s transferability restriction on BYONC \nis unjust and unreasonable and therefore should be rejected. \nPJM indicates that BYONC is UCAP and is comprised of MW, not physical resources.95 \nPJM explains that this is reasonable because “[t]his is consistent with how Capacity Resources \nunder PJM’s capacity market design are also MW and not the underlying physical resource that \nsupports a Capacity Resource. RPM Auctions clear MW of UCAP; that is the traded product. Thus, \nin the same vein, BYONC is designed to offset the capacity needed presented by the New Large \nLoad.”96 Because PJM defines BYONC as UCAP MW rather than as an indivisible physical \nresource, the Tariff already contemplates some fungibility. On this same basis, UCAP MW not \nneeded to supply one New Large Load should be allowed to offset the BYONC of another New \nLarge Load. \nAdditionally, PJM accommodates flexibility for BYONC resources to parse their UCAP \nMW across multiple New Large Loads. And PJM allows New Large Loads to oversize their \nBYONC.97 PJM explains, “New Large Load that has plans for expanding in the future may go \nahead and lock in BYONC for such planned growth before the growth occurs.”98 However, should \na New Large Load not need some of the UCAP MW, the New Large Load (or its LSE) has no \n \n95 PJM IRAS Filing at 51. \n96 PJM IRAS Filing at 51 (internal citations omitted). \n97 PJM IRAS Filing at 64. \n98 PJM IRAS Filing at 64."},{"page":25,"startToken":7715,"endToken":8052,"text":"25 \nability to transfer it to another load that remains subject to IRAS. This is particularly problematic \nfor an LSE that would have paid for the resource but is unable to utilize it to avoid the need to \ncurtail other load it serves. LSEs use a portfolio of resources to satisfy load obligations. LSEs \nshould be permitted to adjust allocations and assignments as necessary from year to year. \nFurthermore, should the LSE not need the resource, it should not be forced to continue to incur \ncosts that it otherwise could offset by transferring the resource to another LSE who might need it. \nSuch LSEs would be punished for acting prudently to get ahead of load growth and not leaning on \nthe PJM Region to meet its load obligations. \nPJM offers no justification for this mismatch where a New Large Load (or its LSE) can \noversize its BYONC commitment but unused UCAP MW cannot be transferred as BYONC from \none New Large Load (or LSE) to another, should it not be needed. This aspect of PJM’s proposal \nis unduly restrictive and therefore not just and reasonable. \n5. PJM’s Definitions of Large Load and New Large Load Are Unreasonably \nBroad. \nPJM has proposed to define Large Load as “end-use customer(s) load that has a cumulative \npeak load of 50 [MW] or greater at a single electrical site behind one or more points of \ninterconnection, where for configurations involving multiple affiliated load facilities or multiple \npoints of interconnection with affiliated load facilities behind them, all affiliated load facilities \nwithin a one-mile radius will be considered a single electrical site as further described in the PJM \nManuals.”99 And New Large Load is defined, in part, as “end-use customer load that is either (a) \na Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June \n1, 2027, that increases the existing end-use customer load at a single electrical site that, prior to \n \n99 PJM IRAS Filing at 31; Proposed RAA, Definitions – Large Load."},{"page":26,"startToken":8052,"endToken":8473,"text":"26 \nsuch incremental load, did not previously meet the definition of Large Load.”100 A manufacturing \nfacility in Kentucky that is less than 50 MW today may become subject to IRAS if its incremental \nload growth increases its size beyond 50 MW.101 The entire incremental growth, not just that which \nexceeded 50 MW, apparently is subject to IRAS.102 PJM’s proposed definitions, however, go \nbeyond the scope of PJM’s purported driver of its IRAS Proposal.103 Even PJM in its transmittal \nletter recognizes that the resource adequacy concerns motivating IRAS are “due to a confluence \nof various factors, particularly the ‘unprecedented surge in data center load’ at a faster pace than \nnew supply can come online.”104 \nBut despite all of the explanation of the need for IRAS being driven by data center load, \nwithout sufficient justification PJM sweeps incremental growth and new economic development \nfrom industrial and manufacturing consumers into its definition of Large Load and New Large \nLoad.105 But manufacturing and industrial expansions do not present the same timing, \nconcentration, or operational risks as data centers. Such broad definitions of Large Load and New \nLarge Load – and the concomitant consequence of potentially subjecting the load to curtailment – \n \n100 Proposed RAA, Definitions – New Large Load. \n101 See Montalvo Affidavit at P 32. \n102 See PJM Interconnection, L.L.C., CIFP Framework for Service During Period of Insufficient Resource Adequacy \n– PJM Proposal, Executive Summary, (July 31, 2026), https://www.pjm.com/-/media/DotCom/committees-\ngroups/cifp-rbp/2026/20260731/20260731-item-02b---cifp-framework-for-service-during-periods-of-insufficient-\nresource-adequacy---executive-summary---redline.pdf (“This includes incremental load that causes an existing load \nto meet the Large Load definition when it had not previously met this threshold (e.g., if a 30 MW load ramps to \nbecome a 60 MW load, then the 30 MW of new load would be considered new Large Load megawatt)”). \n103 See PJM IRAS Filing at 31 (citing PJM Interconnection, L.L.C., “Order to Show Cause,” 195 FERC ¶ 61,211, P \n58 (2026)). \n104 PJM IRAS Filing at 21 (citing 2027/2028 Base Residual Auction Reserve Target Shortfall Report, PJM \nInterconnection, L.L.C., 1 (Feb. 9, 2026), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-\ninfo/2027-2028/2027-2028-bra-reserve-target-shortfall-report.pdf [https://perma.cc/TA3Y-95AX]). See, e.g., PJM \nInterconnection, L.L.C., Board Decisional Letter on Critical Issue Fast Path – Large Load Additions (Aug. 5, 2025) \n(“Recent increases in large load additions, mainly from data centers, present both opportunities and challenges for the \nregional grid.”). \n105 See PJM IRAS Filing at 35."},{"page":27,"startToken":8473,"endToken":8812,"text":"27 \nmay divert economic development away from Kentucky and other PJM states, and that could result \nin diverting jobs from the PJM region. PJM has not adequately supported applying the same \nextraordinary curtailment and compensation framework to every form of qualifying large-load \ngrowth. Therefore, PJM’s proposed definitions of Large Load and New Large Load are not just \nand reasonable and the Commission should not accept them unless and until they are revised. \n6. PJM’s Determination of Zonal IRAS Allocation May Unreasonably \nSubject Non-IRAS Loads to Curtailment. \nPJM proposes to determine a zone’s final allocation of IRAS based on the “total Final RBP \nTarget MW across all zone/areas.”106 This proposal raises several concerns that must be addressed \nin order to avoid an unjust and unreasonable result. First, allocating IRAS based on the “total Final \nRBP Target MW across all zones/areas” fails to account for whether the Large Load, which was \nassumed in the forecast that was used in the RPM Auctions that formed the basis for PJM’s \nshortfall calculation that set the RBP Target, came to fruition. Second, PJM’s proposal does not \ntake into consideration whether the Large Load assumed in the forecast is actually online in the \nreal-time space in which PJM is making the decision to issue an IRAS curtailment directive. Thus, \nPJM’s IRAS Action could be a direction to an Electric Distributor to curtail an amount of load that \nis larger than the actual Large Load in the zone or an amount larger than the actual Large Load on-\nline in real time. An Electric Distributor must abide by the Operating Instruction or face potential \nNERC compliance consequences. This could result in an Electric Distributor being required to \nshed other load beyond the load for which IRAS was intended to target.107  \nAs Mr. Montalvo explains, \n \n106 PJM IRAS Filing at 68.  \n107 Mr. Montalvo also addresses a related concern in that PJM’s proposal does not clearly establish how it will evaluate \ncompliance with an IRAS Action directive.  See Montalvo Affidavit at P 16."},{"page":28,"startToken":8812,"endToken":9145,"text":"28 \nan Electric Distributor may need to exercise judgment when PJM \ndirects a load reduction that exceeds the amount of Eligible New \nLarge Load available for curtailment. Because PJM characterizes an \nIRAS Action as a NERC Operating Instruction (Proposed Tariff, \nAttachment DD-4, Section III(a)), an Electric Distributor may be \nexpected to comply even when the sufficient IRAS-targeted load \nunavailable. In those circumstances, the Electric Distributor could \nface a choice between failing to satisfy PJM’s instruction or \nextending curtailments beyond the loads that the IRAS framework \nis intended to address. If the requested reduction exceeds the amount \nof IRAS-curtailable New Large Load that is online and available, \nfirm end-use customers that are not taking IRAS service may \nnonetheless be curtailed. This ambiguity creates implementation \nrisk and may result in curtailment impacts that extend beyond the \nscope of the underlying IRAS obligation.108 \n \nClearly, this cannot be the result that PJM would desire. Moreover, it is a result that does not \nprovide PJM operations with an accurate understanding of how real-time actions would aid in \nalleviating emergency conditions. Thus, EKPC requests that PJM provide clarification and \nappropriate revisions to its proposal to address this potentially unjust and unreasonable result.  \n7. SPP’s CHILL Precedent Is Materially Different from IRAS. \nPJM justifies the IRAS Proposal, in part, by pointing to the Commission’s approval of the \nSouthwest Power Pool, Inc. (“SPP”) Conditional High Impact Large Load Service (“CHILLS”) \nconstruct.109 However, PJM’s IRAS Proposal is materially different. The Commission accepted \nSPP’s CHILL as a non-firm transmission service that allows certain large loads accelerated access \nfor a limited period while preserving curtailment authority until sufficient designated resources or \nnetwork upgrades are in place.110 IRAS is not simply a distinct conditional transmission product; \nit is an integrated load-reduction, compensation, BYONC and RBP Offset recognition, and VRR \nCurve adjustment mechanism. The Commission’s acceptance of CHILLS, which is time-limited \n \n108 Montalvo Affidavit at P 14.  \n109 PRM IRAS Filing at 97. \n110 Sw. Power Pool, 195 FERC ¶ 61,196 (2026)."},{"page":29,"startToken":9145,"endToken":9448,"text":"29 \nconditional transmission service, does not establish that PJM’s broader IRAS design is just and \nreasonable.111 CHILLS does not create curtailment risk for entities that did not contribute to the \nresource adequacy problem facing the region (as IRAS creates for entities in the PJM region). Nor \ndid CHILLS create an unduly discriminatory treatment between similarly situated load. \nC. PJM Has Failed to Demonstrate that Compensating IRAS Curtailment Is \nWarranted. \nUnder PJM’s IRAS Proposal, load reductions provided under IRAS will be compensated \nat a rate equal to 50% of the applicable Non-Performance Charge Rate.112 Specifically, PJM \nproposes to “extend the rate applicable for Pre-Emergency Load Response nonperformance (and \nconversely for bonus payments) – 50% of the Non-Performance Charge Rate – as the maximum \nrate for IRAS performance.”113 PJM’s justification for this approach is based in part on the fact \nthat the Commission recently accepted this rate.114 However, the Commission’s acceptance of a \n50 percent Non-Performance Charge Rate for demand-response performance or non-performance \ndoes not by itself justify paying New Large Loads for IRAS curtailment. Demand response \ncompensation generally rests on a defined resource obligation and wholesale market impact. IRAS \ncurtailment, by contrast, is triggered by PJM’s conclusion that a class of load lacks recognized \ncapacity coverage. PJM must justify IRAS compensation on its own terms, and PJM has failed to \ndo so. \nAs explained by Mr. Montalvo \nIRAS applies to New Large Loads that have not secured qualifying \nBYONC resources or sufficient [RBP] capacity. Exposure to \ncurtailment therefore reflects the absence of qualifying capacity \n \n111 Indeed, PJM states that IRAS will remain in the Tariff even if the current capacity shortfall driven by data center \ngrowth is resolved. See PJM IRAS Filing at 93. In that regard, it is not time limited. \n112 PJM IRAS Filing at 102. \n113 Id. \n114 Id."},{"page":30,"startToken":9448,"endToken":9721,"text":"30 \nsupport. Under those circumstances, curtailment does not constitute \na distinct reliability service. Instead, curtailment reflects the \nreliability consequences associated with receiving service without \nobtaining the resources needed to support firm resource adequacy \ntreatment.115  \n \nTherefore, curtailment is a “condition of service rather than a compensable reliability product.”116 \nOn this point, Mr. Montalvo compares IRAS compensation with the compensation structure for \nfirm and non-firm transmission service. As Mr. Montalvo explains, “Both classes of customers \nreceive transmission service, but non-firm customers accept interruption during periods of system \nconstraint rather than pay for transmission upgrades. Transmission providers generally do not \ncompensate non-firm transmission customers when interrupted because curtailment is an inherent \ncharacteristic of the service being provided.”117 The same should be the case with the curtailment \nservice PJM is proposed through IRAS. \n \nMr. Montalvo additionally observes that the compensation level proposed would be at a \nlevel “broadly comparable to recent capacity-market prices, and potentially higher than revenues \nreceived by Demand Response resources committed through the RPM Capacity Market to take on \nan obligation to curtail…”118 As such, the compensation “may reduce the economic consequence \nof remaining subject to IRAS and thereby weaken the incentive for New Large Loads to secure \nqualifying capacity resources.”119 Moreover, PJM’s proposal to not include New Large Load in \nthe Variable Resource Requirement yet require such loads to be included in the zonal allocation \nof RPM costs may “lessen the apparent capacity-cost impact on other customers without \n \n115 Montalvo Affidavit at P 42. \n116 Montalvo Affidavit at P 42. \n117 Montalvo Affidavit at P 43. \n118 Montalvo Affidavit at P 15. \n119 Montalvo Affidavit at P 15."},{"page":31,"startToken":9721,"endToken":10023,"text":"31 \nstrengthening the incentive to develop or procure the resources needed to serve that New Large \nLoad reliably.”120 \nAs Mr. Montalvo notes, “[r]esource adequacy frameworks generally function most \neffectively when market participants bear the costs associated with the reliability risks they \ncreate.”121 That is not the scenario PJM is creating with its IRAS Proposal. As discussed above, \nrequiring the other load of LSEs, like EKPC, to pay for curtailments that otherwise would have \nbeen avoided if PJM were to (1) recognize the existing length in a supply portfolio, and (2) correct \nthe potential timing mismatch in new generation COD and the start of a Delivery Year, is overly \npunitive. It also is not aligned with the intended incentives underlying IRAS – to encourage prudent \nresource planning. PJM has effectively weakened the incentives to develop, procure, or contract \nfor qualifying capacity resources because compensation for IRAS curtailments “reduce[s] the \neconomic consequence of remaining subject to IRAS.”122 \nMoreover, PJM requiring the other load in the zone to fund the compensation penalizes \nsuch loads that are not contributing to the resource adequacy insufficiency that PJM is proposing \nto address with IRAS. Granting an opportunity for New Large Loads to waive the compensation \ndoes not address the underlying inequity in the proposal. It is seemingly inconsistent with the \nCommission’s jurisdiction that a RERRA could determine the applicability of a PJM Tariff \nprovision and decide that the other load does not need to make the payment PJM proposed to \ncompensate New Large Loads that are curtailed by an Electric Distributor upon PJM’s direction.  \nFurthermore, this required compensation runs afoul of Kentucky Public Service \nCommission precedent and the settlement conditions approved by this Commission upon which \n \n120 Montalvo Affidavit at P 18. \n121 Montalvo Affidavit at P 49.  \n122 Montalvo Affidavit at P 46."},{"page":32,"startToken":10023,"endToken":10513,"text":"32 \nEKPC (and the other Kentucky utilities) integrated into PJM.  The Kentucky Public Service \nCommission specifically reserved jurisdiction over all demand-side management programs \ninvolving retail loads, such as demand response programs, and, as a condition of the integrations \nof Kentucky’s three utilities that are members of PJM, required PJM to consent to this \nreservation.123 As a result, PJM may not offer load interruption programs to retail consumers \nwithout the utilities’ consent, which in turn requires the approval of the Kentucky Public Service \nCommission.124 To go a step further, the Kentucky Public Service Commission conditioned the \noriginal integration approval order upon this Commission’s acknowledgement of the reservation \nof jurisdiction over demand-side management programs in Kentucky and this Commission \nacknowledged the reservation.125 When energy efficiency resource aggregators sought to \naggregate load in Kentucky to bid into PJM’s capacity market, the Kentucky Public Service \nCommission issued an order that such actions violated its jurisdiction,126 which this Commission \nacknowledged.127 \n \n123 In the Matter of the Application of Kentucky Power Company d/b/a American Electric Power, for Approval, to the \nExtent Necessary, to Transfer Functional Control of Transmission Facilities Located in Kentucky to PJM \nInterconnection, L.LC. Pursuant to KRS 278.218, Order, Case No. 2002-00475, (Ky. P.S.C. May 19, 2004); In the \nMatter of the Application of Duke Energy Kentucky, Inc. for Approval to Transfer Functional Control of its \nTransmission Assets from the Midwest Independent System Operator to the PJM Interconnection Regional \nTransmission Organization and Request for Expedited Treatment, Order, Case No. 2010-00203, (Ky. P.S.C. Dec. 22, \n2010); Letter from Terry Boston to Jeff Derouen, Case No. 2010-00203, Post-Case Correspondence File (Ky. P.S.C. \nJan. 11, 2011); Application of East Kentucky Power Cooperative, Inc. to Transfer Functional Control of Certain \nTransmission Facilities to PJM Interconnection, LLC, Order, Case No. 2012-00169 (Ky. P.S.C. Dec. 20, 2012). \n124 As a “load reduction service” in which load is curtailed and, according to PJM’s proposal, compensated, IRAS \nwould be a load interruption program subject in Kentucky to the Kentucky Public Service Commission’s jurisdiction. \nSection 278.285 of the Kentucky statutes grants the Kentucky Commission authority to “determine the reasonableness \nof demand-side management plans proposed by any utility under its jurisdiction.”  And Section 278.010 of the \nKentucky statutes defines “demand-side management” as “any conservation, load management, or other utility \nactivity intended to influence the level or pattern of customer usage or demand, including home energy assistance \nprograms” (emphasis added).  \n125 In the Matter of New PJM Companies and PJM Interconnection, LLC, 107 FERC ¶ 61,272, P 4 (2004). \n126 In the Matter of the Application of East Kentucky Power Cooperative, Inc. for a Declaratory Order Confirming \nthe Effect of Kentucky Law and Commission Precedent on Retail Electric Customers’ Participation in Wholesale \nElectric Markets, Order, Case No. 2017-00129 (Ky. P.S.C June 6, 2017). \n127 Advanced Energy Economy, 161 FERC ¶ 61,245, PP 66-69 (2017)."},{"page":33,"startToken":10513,"endToken":10866,"text":"33 \nBecause PJM has failed to provide sufficient justification for treating IRAS as a reliability \nservice rather than a condition of service, and failed to justify why other loads not contributing to \nthe need for IRAS curtailments should pay for the curtailments, PJM’s proposed IRAS \ncompensation has not been shown to be just and reasonable and should be rejected.  \nD. PJM’s Proposed Treatment of New Large Loads Served by FRR Entities Is \nPreferential and Unduly Discriminatory; And PJM has Not Sufficiently \nSupported the Blanket Exception from IRAS for Load Served by FRR Entities. \nPJM’s IRAS Proposal’s treatment of FRR entities and its allowance for the use of an FRR \nentity’s portfolio of resources to demonstrate resource adequacy raises comparability concerns and \nunduly discriminates against RPM Capacity Market LSEs. As proposed, no new large loads in \nFRR Service Areas are “Eligible New Large Loads.”128 Therefore, the New Large Loads in FRR \nService Areas are not eligible for IRAS. PJM’s rationale is that an FRR Entity is responsible for \nsecuring new generation to supply new large load.129 However, it is possible for an FRR Entity to \nhave an insufficient FRR Plan. PJM is not proposing any restrictions on such an entity; rather it is \nproposing a blanket exception from IRAS for FRR loads. It is unduly discriminatory to allow an \nFRR Entity that potentially could have an insufficient FRR Plan to avoid IRAS while load of a \nSelf-Supply Entity participating in the RPM Capacity Market would be subject to IRAS. The Joint \nEDC Proposal addressed this concern by including the caveat that “Load that is part of a [FRR] \nAlternative Capacity Plan is excluded from Connect and Manage [i.e., now IRAS] only to the \nextent the FRR plan is sufficient.”130 PJM could have adopted a similar caveat to its FRR exclusion \nin its IRAS Proposal as well. \n \n128 PJM IRAS Filing at 73 (quoting Proposed Tariff, Attachment DD-4, section V(a)) (“New Large Loads that are \nlocated within an FRR Service Area cannot be Eligible New Large Loads.”)). \n129 PJM IRAS Filing at 73. \n130 See Joint EDC Proposal at 3."},{"page":34,"startToken":10866,"endToken":11167,"text":"34 \nAs explained by Mr. Montalvo, although FRR Entities and Self-Supply Entities “pursu[e] \nthe same reliability objective,”131 PJM’s IRAS Proposal nevertheless subjects FRR Entities and \nSelf-Supply Entities to different requirements “based solely on the framework through which PJM \nrecognizes resource adequacy.”132 The IRAS Proposal fails to “explain why a portfolio-based \ndemonstration suffices within the FRR construct but not within the self-supply construct. Given \nthe similarities in the planning, procurement, and portfolio management functions performed by \nthese entities, the record provides little basis for this distinction.”133 Effectively an FRR Entity is \nable to use its portfolio of supply to cover all its load, including shifting the supply in its portfolio \nto cover the capacity needs of other loads without the same restrictions that PJM has proposed \nwith respect to BYONC. LSEs participating in RPM cannot do so. Such disparate treatment of \nsimilarly situated entities is unduly discriminatory. \nAn FRR entity may use a portfolio of resources to satisfy its FRR Capacity Plan \nrequirements with no requirement to tie the resources to specific loads or restrictions on replacing \ncapacity resources or transferring capacity resources. By contrast, an RPM LSE that has prudently \ndeveloped, retained, or contracted for sufficient resources to serve all or part of its incremental \nload would not receive comparable treatment. If PJM recognizes resource adequacy actions taken \nunder the FRR construct for purposes of avoiding IRAS exposure, principles of comparability \nrequire that it similarly recognize owned resources, bilateral contracts, and comparable resource \ncommitments maintained by RPM LSEs when determining IRAS curtailment. PJM offers no \nexplanation as to why LSEs that similarly have existing resources paid for by the load they serve \nshould be exposed to curtailment under IRAS. \n \n131 Montalvo Affidavit at P 40. \n132 Montalvo Affidavit at P 40. \n133 Montalvo Affidavit at P 40."},{"page":35,"startToken":11167,"endToken":11592,"text":"35 \nMoreover, although PJM imposes a restriction on an FRR Entity’s inclusion of Existing \nGeneration Capacity Resources in its FRR Capacity Plan,134 it does not require the FRR Capacity \nPlan to be sufficient. There are no conditions on the IRAS exception. PJM has not provided any \nsupport for the reasonableness of the blanket exception for FRR load. \nRPM Capacity Market LSEs that have sufficient capacity, whether owned or contracted \nfor, are similarly situated to FRR entities. Yet as proposed, only RPM Capacity Market LSEs have \nexposure under IRAS. And FRR Entities that do not have sufficient FRR Capacity Plans would be \nexempt from IRAS. These distinctions, without justification, are unduly discriminatory.135 \nTherefore, the Commission should not accept PJM’s IRAS Proposal unless it is revised to confirm \nthat FRR Entities are only exempt from IRAS to the extent the FRR plan is sufficient. \nE. PJM’s Proposed Revisions to FRR Rules Creates Ambiguity and Disadvantage \nEntities that May Elect FRR in the Future. \nPJM has proposed an additional requirement be placed on FRR Capacity Plans. PJM is \nproposing that “[a]n FRR Entity may not include in its FRR Capacity Plan any MW quantity of \nExisting Generation Capacity Resource in excess of what such FRR Entity owned or contracted \nby such FRR Entity Prior to June 1, 2027, to serve New Large Loads.”136 EKPC supports \nconstraining the FRR Capacity Plans’ reliance on existing capacity resources to the extent that the \n \n134 RAA Schedule 8.1, Section D. \n135 City of Anaheim, Opinion No. 483, 113 FERC ¶ 61,091, P 130 (2005) (“Discrimination is undue when there is a \ndifference in rates or services among similarly situated customers that is not justified by some legitimate factor.”); \nPacifiCorp Elec. Operations, 54 FERC ¶ 61,296, 61,855 (“undue discrimination can occur only when two similarly \nsituated customers are treated differently, and there is no justification for the differing treatment”); Puget Sound \nEnergy, Inc. v. All Jurisdictional Sellers of Energy, Opinion No. 537, 151 FERC ¶ 61,173, P 43, n.105 (quoting Energy \nTransfer, 120 FERC ¶ 61,086, P 169), rev’d on other grounds, 157 FERC ¶ 61,026 (2016) (“It is well established that \na finding of undue discrimination requires a showing that ‘(1) two classes of customers are treated differently; and (2) \nthe two classes of customers are similarly situated.’”); Midwest Indep. Transmission Sys. Operator, Inc., 155 FERC ¶ \n61,082, P 31 (2016) (“there is no undue discrimination or preference because we have identified appropriate reasons \nfor it”). \n136 Proposed RAA, Schedule 8.1, D (1.1)."},{"page":36,"startToken":11592,"endToken":11781,"text":"36 \nFRR entity would be pulling resources from RPM while the IRAS rules are in effect. However, to \nthe extent that IRAS is not needed, this language unduly restricts an FRR Capacity Plan. Such a \nrestriction not only limits cost-effective options for load subject to FRR, but it also unnecessarily \neliminates a financial option for capacity resources because they cannot be used by an FRR entity \nto satisfy an FRR Capacity Plan. PJM’s proposed language is broader than necessary to address \nthe narrow reliability issue it intends to resolve. As drafted, PJM’s new restrictions create \nambiguity for current FRR Entities and disadvantage any entity that may decide to elect FRR in \nthe future. Therefore, this broad language is not just and reasonable and the Commission should \nnot accept it unless the IRAS Proposal is revised to address these concerns. \nIII. \nConclusion \nWherefore, East Kentucky Power Cooperative, Inc. respectfully requests, as detailed \nabove, that the Commission reject certain elements of PJM’s IRAS Proposal as unjust and \nunreasonable or unduly discriminatory and require appropriate revisions or clarifications to those \nelements in order to avoid unjust and unreasonable or unduly discriminatory results."},{"page":37,"startToken":11781,"endToken":11882,"text":"37 \n \nRespectfully submitted, \n \n \nDenise R. Foster Cronin \nChief Compliance Officer and Senior Vice \nPresident \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTel.: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \n \nOn Behalf of \nEast Kentucky Power Cooperative, Inc. \n \n/s/ Daniel E. Frank \n \n \nDaniel E. Frank \nAllison E. S. Salvia  \nKelly A. Cuthbertson \nAdriana J. Santana \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTel.: 202-383-0100 \nEmail: danielfrank@eversheds-sutherland.com \nallisonsalvia@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \nanasantana@eversheds-sutherland.com \n \nCounsel for \nEast Kentucky Power Cooperative, Inc. \n \n \n \n \nDated: September 3, 2026"},{"page":38,"startToken":11882,"endToken":11888,"text":"Attachment 1 \nAffidavit of Marc Montalvo"},{"page":39,"startToken":11888,"endToken":12143,"text":"1 \n \nAFFIDAVIT OF MARC D. MONTALVO \nON BEHALF OF \nEAST KENTUCY POWER COOPERATIVE, INC. \n  \nIntroduction \n1. My name is Marc D. Montalvo. I am President and Managing Principal of Daymark Energy \nAdvisors (“Daymark”). My business address is 370 Main Street, Worcester, Massachusetts \n01608. Daymark is a consultancy that provides transmission planning, economic analysis, \nand strategic advisory services to the electric power industry. Daymark is part of the Xodus \nGroup. \n2. I work with industry and policymakers to design regulatory and market structures that enable \nthe efficient development and deployment of energy infrastructure. My principal practice \nareas are competitive power markets, strategic planning, risk management, and capital \nbudgeting and investment analysis. I have worked on capacity market design issues on behalf \nof clients in PJM Interconnection, L.L.C. (“PJM”), New York Independent System Operator, \nInc. (“NYISO”), ISO-New England, Inc. (“ISO-NE”), and Midcontinent Independent System \nOperator (“MISO”). My clients include developers, utilities, and government agencies across \nNorth America, and I have appeared as an expert before the Federal Energy Regulatory \nCommission (“FERC” or the “Commission”), Canadian provincial regulators, and state \nregulatory agencies. Prior to joining Daymark, I worked ten years at ISO-NE where I held \nthe positions of Director of Market Development, Director of Internal Market Monitoring: \nInvestigation and Market Assessment, and Director of Enterprise Risk Management. Prior to \nISO-NE, I was a managing consultant with La Capra Associates. I began my career at New \nEngland Power Co. I taught courses in finance and business analytics at Clark University’s \nSchool of Management from 2016 to 2020."},{"page":40,"startToken":12143,"endToken":12384,"text":"2 \n \n3. I advised East Kentucky Power Cooperative, Inc. (“EKPC”) on the development of workable \nreliability backstop and connect and manage mechanisms during the PJM stakeholder \nprocess that culminated in PJM’s filings in docket nos. ER26-3380-000 and ER26-3515-000. \nIn this docket, I have been asked by EKPC to evaluate PJM’s proposed Interim Resource \nAdequacy Service (“IRAS”) framework, including proposed Tariff, Attachment DD-4 and \nrelated revisions to the Reliability Assurance Agreement (“RAA”), and its implications for \nutilities developing and maintaining resources to serve growing electric demand, including \nLarge Loads.  \n4. My findings are based upon my review of the PJM IRAS proposal, the Joint Electric \nDistribution Company (“EDC Joint”) proposal, which I helped develop and was submitted \ninto the PJM stakeholder process, project development information provided by EKPC, and \nmy professional experience evaluating electric utility planning, generation investment \ndecisions, resource adequacy frameworks, and capacity market design. \nSummary of findings \n5. My findings are as follows: \na. IRAS may require customer curtailments even when sufficient resources are available to \nserve load because PJM’s eligibility determination is governed by administrative gates \nrather than actual resource in-service dates and operational availability. Consequently, \ncustomers may be curtailed despite the resolution of the underlying reliability concern. \nb. IRAS may assign curtailment obligations to Load Serving Entities (“LSEs”) whose loads \ndo not contribute to the resource adequacy deficiency because PJM will propose to link \nspecific resources to specific large loads rather than assess the adequacy of an LSE’s"},{"page":41,"startToken":12384,"endToken":12634,"text":"3 \n \noverall resource portfolio. Consequently, LSEs with sufficient aggregate capacity \npositions may nevertheless face curtailment risk. \nc. IRAS applies different standards to similarly situated LSEs by permitting FRR entities to \ndemonstrate resource adequacy on a portfolio basis while imposing resource-specific \nqualification and resource-specific requirements on self-supplying RPM participants. \nConsequently, loads served by self-supply LSEs may face curtailment exposure that \ncomparable FRR-served LSEs do not. \nd. PJM’s proposal to compensate large loads curtailed under IRAS may weaken incentives \nto develop, retain, or procure qualifying resources – particularly demand response -- and \nmay shift costs onto end-use customers. Consequently, the proposal risks increasing \nreliance on curtailment while doing little to improve the long-term resource adequacy \nchallenges it is intended to address. \nBackground \n6. As a preliminary matter, it is important to distinguish amongst the various entities and \ncustomers referenced in this affidavit. LSEs provide electric supply service to end-use \ncustomers. Under the RAA, LSEs are Customers of PJM and take service under PJM’s Open \nAccess Transmission Tariff (“OATT”). By contrast, Large Loads are customers of LSEs and, \nunless they independently qualify and register as an LSE, are not Customers of PJM. Electric \nDistribution Companies (“EDCs”) provide distribution service to end-use customers and are \nlikewise not Customers of PJM. Some EDCs also serve as Electric Distributors, which as \ndescribed in PJM manuals, perform certain administrative functions, including meter reading \nfor the determination of LSE Peak Load Contributions used in Reliability Pricing Model \n(“RPM”) settlements, as well as the collection and reporting of load forecast data."},{"page":42,"startToken":12634,"endToken":12944,"text":"4 \n \nThroughout this affidavit, I use these terms with care. The term “Customer,” when \ncapitalized and used independently, refers to an LSE that is a PJM Customer. The term \n“customer,” when not capitalized, or when used in conjunction with terms such as “load \ncustomer” or “end-use customer,” refers to a retail supply customer of an LSE or a \ndistribution customer of an EDC. \n7. On August 13, 2026, PJM filed revisions to its Open Access Transmission Tariff and \nReliability Assurance Agreement that would establish an IRAS framework and related \nprovisions governing New Large Loads.1 The proposal would take effect in the 2027/2028 \nDelivery Year. It addresses large load registration, capacity coverage requirements, \nemergency load reduction procedures, and the treatment of incremental large loads within \nPJM’s resource adequacy framework and capacity market, including proposed Tariff, \nAttachment DD-4 and proposed RAA section 7.8.2 \n8. IRAS is a load-reduction framework available during specified reliability conditions. PJM \ndescribes IRAS in its proposed tariff as a “load reduction service” and in its transmittal letter \ncharacterizes IRAS as a “new supplemental capacity product” through which New Large \nLoads provide load reduction capability to help PJM manage resource adequacy shortfalls.3 \n9. IRAS would allow PJM to direct zonal load reductions before Pre-Emergency Load \nManagement when PJM determines that available economic real-time supply may be \ninsufficient to satisfy reserve requirements, maintain Interconnection Reliability Operating \n \n1 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry \nto Address System Reliability,  Docket No. ER26-3515-000 (filed Aug. 13, 2026). \n2 PJM Interconnection, L.L.C., Proposed Reliability Assurance Agreement § 7.8, Docket No. ER26-3515-000 (filed \nAug. 13, 2026). \n3 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry \nto Address System Reliability, Docket No. ER26-3515-000, at 22 (filed Aug. 13, 2026)."},{"page":43,"startToken":12944,"endToken":13212,"text":"5 \n \nLimits (“IROLs”), or prevent cascading outages.4 PJM proposes to deploy IRAS before Pre-\nEmergency Load Management actions, generally during Energy Emergency Alert Level 1 \n(“EEA1”) conditions, while retaining discretion to implement other emergency actions \nnecessary to maintain reliability. \n10. PJM proposes to create and administer a Large Load Registry.5 The registry would contain \ninformation on Large Loads, including location, in-service date, peak demand, load-growth \nschedule, telemetry specifications, backup generation, interconnection status, and capacity \narrangements. PJM would use the registry to identify New Large Loads, determine available \nIRAS curtailment amounts, track Large Load specific capacity arrangements (not LSE \narrangements), and calculate IRAS obligations by Electric Distributor zone or area. With \nIRAS PJM puts the load serving obligation on LSEs but requires the Bring Your Own New \nCapacity (“BYONC”) arrangements to be tied to specific load customers. The proposal \ndefines a Large Load as an end-use customer load with a cumulative peak demand of at least \n50 MW at a single electrical site, including certain affiliated facilities located within a one-\nmile radius. \n11. The proposal would establish a BYONC framework under Tariff, Attachment DD-4 sections \nVI through VIII. Qualifying BYONC capacity would offset a New Large Load’s capacity \nrequirement and reduce potential IRAS exposure. Eligible resources include specified \ngeneration, storage, incremental capacity additions, repowered resources, and demand-side \nresources. The proposal establishes reporting, validation, and maintenance requirements for \n \n4 PJM Interconnection, L.L.C., Proposed Tariff, Attachment DD-4 § I, Docket No. ER26-3515-000 (filed Aug. 13, \n2026). \n5 PJM Interconnection, L.L.C., Proposed Reliability Assurance Agreement, Schedule 11 § B, Docket No. ER26-\n3515-000 (filed Aug. 13, 2026)."},{"page":44,"startToken":13212,"endToken":13553,"text":"6 \n \nBYONC arrangements and requires BYONC resources to clear as Capacity Resources in the \nRPM. PJM does not permit replacement of BYONC generation or storage resources but does \nallow Demand Response and DER Aggregations to replace their BYONC commitments. \n12. The proposed Tariff, Attachment DD-4 sections IV and V establish procedures for \ndetermining and allocating IRAS obligations. For each Delivery Year, PJM would determine \nif a capacity shortfall exists and then calculate the load-reductions required to address that \nshortfall. New Large Loads are subject to curtailment under IRAS if qualifying BYONC \narrangements or allocated Reliability Backstop Procurement (“RBP”) Unforced Capacity \n(“UCAP”) do not offset their registered peak load.6  \n13. The proposal excludes New Large Loads located in Fixed Resource Requirement (“FRR”) \nservice areas from IRAS.7 FRR entities would instead satisfy resource adequacy \nrequirements through their FRR Capacity Plans. Nonetheless, while FRR entities remain \nexempt from IRAS, PJM recognizes that large load growth raises resource adequacy \nconsiderations that warrant incremental capacity support.8  \n14. PJM does not propose to identify individual load customers for curtailment. Instead, PJM \nwould determine a zonal or area-wide megawatt reduction and issue a curtailment directive \nto the applicable Electric Distributor. The proposal relies on forecasted load-growth \nallocations to establish zonal responsibilities and on Electric Distributor and state processes \n \n6 PJM Interconnection, L.L.C., Proposed Tariff, Attachment DD-4 § IX, Docket No. ER26-3515-000 (filed Aug. 13, \n2026). See PJM Interconnection, L.L.C., Protest of East Kentucky Power Cooperative, Inc., Docket No. ER26-3380-\n000, at 19 (filed Aug. 21, 2026) (noting uncertainty regarding how load growth between Delivery Years over the 15-\nyear RBP horizon will be handled and how LSE obligations may change from Delivery Year to Delivery Year, \ncreating uncertainty regarding the amount of load that may remain exposed to IRAS curtailment). \n7 PJM Interconnection, L.L.C., Proposed Tariff, Attachment DD-4 § V, Docket No. ER26-3515-000 (filed Aug. 13, \n2026). \n8 PJM Interconnection, L.L.C., Proposed Reliability Assurance Agreement, Schedule 8.1 § D.1.1, Docket No. ER26-\n3515-000 (filed Aug. 13, 2026)."},{"page":45,"startToken":13553,"endToken":13904,"text":"7 \n \nto implement curtailments at the end-use customer level. However, the proposal does not \nclearly explain how a zone-level curtailment obligation should be implemented during an \nactual IRAS event. As a result, an Electric Distributor may need to exercise judgment when \nPJM directs a load reduction that exceeds the amount of Eligible New Large Load available \nfor curtailment. Because PJM characterizes an IRAS Action as a NERC Operating \nInstruction (Proposed Tariff, Attachment DD-4, Section III(a)), an Electric Distributor may \nbe expected to comply even when sufficient IRAS-targeted load is unavailable. In those \ncircumstances, the Electric Distributor could face a choice between failing to satisfy PJM’s \ninstruction or extending curtailments beyond the loads that the IRAS framework is intended \nto address. If the requested reduction exceeds the amount of IRAS-curtailable New Large \nLoad that is online and available, firm end-use customers that are not taking IRAS service \nmay nonetheless be curtailed. This ambiguity creates implementation risk and may result in \ncurtailment impacts that extend beyond the scope of the underlying IRAS obligation. \n15. PJM proposes compensating New Large Loads curtailed under IRAS (see Tariff, Attachment \nDD-4 section X) at a rate equal to 50 percent of the applicable Non-Performance Charge \nRate, subject to modification or waiver through retail arrangements. Given PJM’s proposed \ncompensation formula and the CONE values reflected in PJM’s proposed tariff revisions, the \nIRAS compensation rate could be approximately $307/MW-day on an RTO-wide basis.9 \nWhile the precise rate will vary depending on the final tariff calculation and applicable \n \n9 This estimate is an RTO-wide approximation based on values in PJM’s filing. The estimate is calculated as follows: \nPJM's proposed 2028/2029 and subsequent Delivery Year CONE values are $218,000/MW-year for CONE Area 1, \n$222,000/MW-year for CONE Area 2, $215,000/MW-year for CONE Area 3, $216,000/MW-year for CONE Area 4, \nand $248,000/MW-year for CONE Area 5. The simple average is $223,800/MW-year. Dividing by 365 produces \napproximately $613.15/MW-day, and applying PJM's proposed 50 percent IRAS compensation factor produces \napproximately $306.58/MW-day, rounded to $307/MW-day."},{"page":46,"startToken":13904,"endToken":14175,"text":"8 \n \nlocation, the likely compensation level is substantial and contrary to reason. A New Large \nLoad that does not secure qualifying BYONC or sufficient RBP capacity takes IRAS service \nto gain conditional market access. Under PJM’s proposal, that same load could receive \ncompensation broadly comparable to recent capacity-market prices, and potentially higher \nthan revenues available to Demand Response resources committed through the RPM \nCapacity Market to take on the obligation to curtail in response to PJM emergency directives. \nThis compensation scheme may reduce the economic consequence of remaining subject to \nIRAS and thereby weaken the incentive for New Large Loads to secure qualifying capacity \nresources. \n16. The proposal does not clearly establish how PJM will evaluate compliance with an IRAS \nAction after issuing a zonal or area-wide curtailment directive to an Electric Distributor. \nUnder this construct, PJM may evaluate compliance based on whether the Electric \nDistributor achieved the aggregate megawatt reduction specified in the directive, rather than \non whether specific New Large Loads subject to IRAS were curtailed. If compliance is \nmeasured solely by reference to the aggregate load reduction achieved, the proposal does not \nensure that curtailment responsibility remains aligned with the New Large Loads or LSEs \nwhose insufficient capacity position gave rise to the IRAS obligation. As a result, non- IRAS \nloads could be curtailed while PJM nevertheless deems the Electric Distributor’s response \ncompliant. By contrast, the EDC Joint Proposal would have evaluated obligations on an LSE-\nspecific or load-specific basis, preserving a clearer connection among the load creating the \nreliability need, the entity responsible for that load, and the operational consequences \nimposed when sufficient capacity is not provided."},{"page":47,"startToken":14175,"endToken":14465,"text":"9 \n \n17. The proposal would revise the RPM Variable Resource Requirement (“VRR”) Curve \nbeginning with the 2029/2030 Delivery Year. Incremental New Large Loads not supported by \nqualifying BYONC arrangements or allocated RBP capacity would be excluded from RPM \ndemand. Once a New Large Load secures qualifying BYONC resources or allocated RBP \ncapacity, both the load and the associated resource would appear in RPM demand and supply \ncurves. The proposal also establishes procedures governing excluded load quantities and their \nincorporation into VRR calculations and auction parameters. \n18. Although the proposal does not directly address cost allocation, New Large Loads subject to \nIRAS may affect RPM cost-allocation outcomes. These loads remain part of zonal load \nresponsibility even as portions of the RPM demand construct exclude them. To the extent that \nexcluding IRAS-exposed New Large Load from RPM demand reduces RPM charges for \nother customers in the zone, that effect is merely a short-term cost-allocation consequence. It \ndoes not address whether the proposal creates appropriate incentives for the New Large Load \nor its serving LSE to secure qualifying capacity. If a New Large Load remains outside the \nRPM demand construct while receiving service and curtailment compensation, the proposal \nmay lessen the apparent capacity-cost impact on other customers without strengthening the \nincentive to develop or procure the resources needed to serve that New Large Load reliably. \nAs a result, the proposal risks weakening, rather than reinforcing, the long-term resource \nadequacy signals that RPM is intended to provide. \n19. The proposal conditions BYONC recognition on specified RPM qualification, participation, \nand compliance requirements. The proposal also evaluates resource adequacy by associating \nspecific capacity resources and their accredited UCAP values with individual Large Loads. \nUnder this framework, BYONC treatment depends on whether a resource satisfies the"},{"page":48,"startToken":14465,"endToken":14707,"text":"10 \n \nproposal’s RPM-related requirements and can be attributed to a particular Large Load. \nBecause those requirements operate within PJM’s existing RPM framework, the timing of \ncommercial operation, qualification, auction participation, and capacity recognition may \naffect when a resource is recognized for BYONC purposes. As a result, the determination of \nwhether a Large Load is subject to IRAS depends on both the status of the associated \nresource within the RPM construct and the resource-to-load associations established under \nthe proposal.  \nDiscussion \nResource adequacy is a forward-looking investment and planning function \n20. Resource adequacy planning ensures that sufficient resources will be available to serve \nforecast load and maintain reliability standards. Because generation resources often require \nyears to permit, finance, construct and interconnect, utilities and other load-serving entities \nmake resource development and procurement decisions well before a resource enters service. \nReliability outcomes depend on investment decisions, contractual commitments, and \ndevelopment activities that occur years before commercial operation. \n21. Utilities routinely commit capital and organizational resources to projects long before those \nprojects satisfy market qualification requirements. Site acquisition, permitting, equipment \nprocurement, financing, engineering, construction, and interconnection activities all occur \nduring the development process. These actions represent material commitments that \ndetermine whether a resource ultimately reaches commercial operation. As a result, resource \ncommitment and market qualification represent distinct milestones. Resource commitment \nreflects a decision to develop or procure a resource to meet future system needs, whereas \nmarket qualification determines whether PJM recognizes that resource under its tariff for"},{"page":49,"startToken":14707,"endToken":14985,"text":"11 \n \nparticipation in a particular PJM-administered market. The requirements for market \nqualification vary across PJM markets and are distinct from the decision to commit a \nresource. For example, a resource may enter service during a Delivery Year and provide \nenergy and ancillary services to the grid, yet not have cleared as a capacity resource in an \nRPM auction for that Delivery Year. \n22. Practically, resource adequacy is enhanced when investment and development decisions \nresult in resources entering service and becoming available to support system reliability. \nUnder the proposed IRAS framework, New Large Loads remain subject to curtailment until \nPJM recognizes associated BYONC resources. However, rather than linking BYONC \nrecognition to a resource’s operational in-service date and its contribution to resource \nadequacy, PJM conditions recognition on compliance with specified RPM qualification and \nparticipation requirements. As a result, differences between RPM administrative timelines \nand resource in-service schedules may directly affect whether a New Large Load remains \nsubject to curtailment under IRAS during a Delivery Year.  \nIRAS can expose load to curtailment because BYONC eligibility depends on RPM \ncommitment timing rather than an assessment of an LSE’s overall resource position \n23. Under the proposed IRAS framework evaluates resource adequacy through the association of \nspecific capacity resources with specific New Large Loads and does not assess whether an \nLSE’s overall resource portfolio is sufficient to satisfy its aggregate load and reliability \nobligations. In particular, the proposal does not evaluate whether an LSE has existing or \ncommitted portfolio resources exceeding its projected obligations that are available to \nsupport incremental load growth. Nor does it assess whether the LSE’s load growth \nmaterially contributes to the resource adequacy concern that IRAS is intended to address."},{"page":50,"startToken":14985,"endToken":15249,"text":"12 \n \nInstead, a New Large Load served by an RPM-participating LSE remains subject to IRAS \ncurtailment unless sufficient BYONC resources are specifically attributed to that load. As a \nresult, a New Large Load may remain subject to IRAS even when the serving LSE has \nadequate portfolio resources to support the associated load and reliability requirements. \n24. LSEs, particularly self-supply entities, typically make resource investment and procurement \ndecisions on a portfolio basis. Through integrated resource planning and related planning \nprocesses, they evaluate forecast demand, reserve margin requirements, resource retirements, \nportfolio performance, fuel diversity, and long-term reliability needs. Those decisions often \noccur before individual load additions fully materialize and are intended to ensure that \nsufficient resources are available to serve aggregate load. As a result, a self-supply LSE may \nmaintain existing or committed portfolio length that is available to support new load growth \neven though PJM’s proposal would not recognize that capacity for IRAS purposes unless it \nqualifies through the specific BYONC or RBP pathways and is attributed to a particular New \nLarge Load. Consequently, an LSE may face IRAS curtailment exposure despite maintaining \nsufficient resources to support its overall load obligations and resource adequacy \nrequirements. \nIRAS can expose load to curtailment because BYONC eligibility depends on RPM \ncommitments rather than resource availability  \n25. Under the proposal, a New Large Load’s exposure to IRAS depends in significant part on \nwhether supporting resources receive BYONC recognition. A resource must obtain an RPM \ncapacity commitment to qualify as BYONC and reduce or eliminate IRAS exposure \nProposed Tariff, Attachment DD-4, section VIII requires BYONC to be committed in an"},{"page":51,"startToken":15249,"endToken":15560,"text":"13 \n \nRPM auction to be a Capacity Resource.10 A resource may therefore enter service, contribute \nto reliability, and support load without receiving BYONC recognition if its commercial \noperation date does not align with PJM’s qualification and auction schedule. \n26. EKPC’s Liberty RICE project illustrates the interaction between resource development \nschedules and RPM qualification requirements. The project could not participate in the \napplicable capacity auction for either of the 2027/28 or 2028/29 Delivery Years because it \nhad not advanced sufficiently through the interconnection process to qualify as a Planned \nCapacity Resource. Its projected December 2028 in-service date further illustrates the \nmismatch between resource development schedules and PJM’s Delivery Year construct. As a \nresult, the project may be online, producing energy, and supporting reliability during the \n2028/2029 Delivery Year while remaining ineligible for BYONC recognition and unable to \noffset IRAS curtailment exposure.  \n27. PJM’s publicly posted queue information underscores that the Liberty RICE timing issue is \nnot unique. PJM’s Service Request Status materials identify generation projects with \nprojected commercial operation and in-service dates throughout the calendar year, rather than \nuniformly on June 1, the start of a PJM Delivery Year.11 This outcome is not surprising. \nGeneration projects reach commercial operation based on permitting, financing, engineering, \nequipment delivery, construction, testing, interconnection, and operational-readiness \n \n10 PJM Interconnection, L.L.C., Proposed Tariff, Attachment DD-4 § VI- VIII, Docket No. ER26-3515-000 (filed \nAug. 13, 2026). \n11 See PJM Interconnection, L.L.C., Service Requests, https://www.pjm.com/planning/service-requests (providing \npublic service-request status information for generation interconnection requests and projects under construction/in \nservice); PJM Interconnection, L.L.C., PJM Announces Application Deadline for First Cycle of New Interconnection \nProcess (Aug. 22, 2025) (stating that approximately 46 GW of interconnection projects had signed agreements to \nconnect to the grid and identifying permitting, siting, and supply-chain challenges as factors affecting project \ndevelopment)."},{"page":52,"startToken":15560,"endToken":15827,"text":"14 \n \nmilestones, none of which necessarily align with PJM’s annual capacity-market schedule or \nDelivery Year construct. By conditioning BYONC recognition under IRAS on RPM \nqualification, commitment, and administrative timing requirements, the proposal may not \nrecognize resources that are online and contributing to reliability during a Delivery Year \nsolely because their in-service dates do not align with the RPM calendar. As a result, \ncurtailment exposure may continue even after the underlying resource adequacy concern has \nbeen addressed. The associated load may remain subject to curtailment because of PJM’s \nadministrative qualification and recognition timeline rather than a shortage of available \ncapacity. This outcome is difficult to reconcile with PJM’s stated objective of encouraging \nnew capacity additions because it places continued curtailment risk on an LSE that has \ninvested in and developed resources that are available to support reliability but do not align \nwith PJM’s auction and qualification schedule. \nIRAS relies on resource-to-Load attribution rather than portfolio sufficiency \n28. As a state-regulated generation and transmission cooperative and self-supply LSE, EKPC \ndevelops and manages resources to satisfy aggregate load obligations and reliability \nrequirements. When evaluating load growth, including growth from large loads, EKPC \nassesses effects on demand forecasts, reserve margin requirements, operational requirements, \nreliability objectives, and long-term resource plans. Resource development decisions address \nsystem requirements rather than the needs of a specific customer or load increment. EKPC \nevaluates generation additions based on their contribution to resource adequacy, reliability \nperformance, operational flexibility, fuel diversity, production costs, and other planning \nobjectives. A single resource may support load growth of multiple customers across customer \nclasses, maintain reserve margins, replace aging resources, improve operational flexibility,"},{"page":53,"startToken":15827,"endToken":16055,"text":"15 \n \nreduce reliability risk, and strengthen portfolio diversity. The resource adequacy value of that \nresource does not disappear because PJM’s IRAS proposal recognizes only capacity fitting \nspecified BYONC or RBP pathways. \n29. The same principle governs electric service. Customers receive service from an integrated \nresource portfolio. Reliability depends on portfolio adequacy even when planning or \ncontractual arrangements associate specific resources with specific customers, resource \nadequacy depends on the capability and sufficiency of the overall portfolio. \n30. This portfolio-based approach reflects longstanding utility planning and operating practice. \nResource adequacy studies, integrated resource plans, reserve margin analyses, and reliability \nassessments evaluate whether aggregate resource capability can satisfy the aggregate load \nobligations. RPM implicitly applies a similar framework. Reserve margin requirements, \ncapacity obligations, and resource adequacy assessments do not require permanent \nassignments between individual resources and individual customers.  \n31. IRAS, however, requires one-to-one linking of resources and large loads. Under proposed \nTariff, Attachment DD-4 section V, curtailment exposure turns on whether a New Large \nLoad’s registered peak load is offset by recognized BYONC arrangements or allocated RBP \nUCAP MW. Under sections VI through IX, that recognition depends on PJM’s prescribed \nresource-specific pathways rather than a broader demonstration of portfolio sufficiency. This \ndistinction is particularly important for self-supply entities as resource additions often \nadvance multiple planning objectives simultaneously and strengthen the overall portfolio. \nThe IRAS framework does not recognize this planning reality."},{"page":54,"startToken":16055,"endToken":16363,"text":"16 \n \n32. This issue is not limited to data-center load. PJM’s proposed Large Load definition could \nalso apply to new industrial or manufacturing loads that exceed the proposed 50 MW \nthreshold, even when those loads are planned for and served through an LSE’s existing \nresource portfolio rather than a dedicated resource. For example, EKPC’s retail tariff requires \ndatacenter loads greater than 250 MW to provide dedicated generation, while smaller \ndatacenter and manufacturing loads generally will be served from EKPC’s portfolio \nresources. The IRAS framework therefore risks treating ordinary portfolio-supported load \ngrowth as though it lacks capacity support because the resources serving that load are not \nlinked to a specific large-load customer through the BYONC construct. \n33. Because IRAS does not evaluate whether an LSE possesses sufficient aggregate resources to \nsatisfy its capacity obligation, the proposal may classify load as creating a resource adequacy \ndeficiency even when the LSE’s portfolio contains adequate capacity. Consequently, LSEs \nwhose load is supported by sufficient resources may improperly receive curtailment \ninstructions. \nA Portfolio-Based Alternative Was Available Through the EDC Joint Proposal \n34. The EDC Joint Proposal adopted a different framework.12 It allowed portfolios of resources \nto support portfolios of Large Loads. That approach reflects how self-supply entities plan for \nand satisfy resource adequacy obligations. Utilities typically meet those obligations through \nintegrated portfolios rather than direct assignments between individual resources and \n \n12 Joint Proposal of the PJM Electric Distribution Companies, including Buckeye Power, Dominion Energy, \nDuquesne Light Company, East Kentucky Power Cooperative, Exelon, Old Dominion Electric Cooperative, PPL \nElectric Utilities Corp., Southern Maryland Electric Cooperative, Duke Energy Ohio, Duke Energy Kentucky \n(“EDC Joint Proposal”); see PJM Critical Issue Fast Path – Reliability Backstop Procurement / Connect & Manage, \nJoint EDCs & Data Center Coalition Reliability Backstop Procurement Package (June 30, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02f---joint-\nedcs-and-data-center-coalition---rbp---executive-summary.pdf."},{"page":55,"startToken":16363,"endToken":16631,"text":"17 \n \nindividual customers. It also avoids treating prudent portfolio length as irrelevant simply \nbecause the capacity was not newly assigned to a particular end-use customer under PJM’s \nBYONC construct. \n35. Resource-to-load attribution may simplify IRAS administration. However, to the extent PJM \ndoes not recognize an LSE’s actual portfolio position, the proposal may impose curtailment \nrisk on load that is not contributing to the asserted resource adequacy concern. In those \ncircumstances, the proposal may weaken the connection between responsibility for the \nreliability need and the operational consequences imposed under the IRAS framework. \nInconsistency between portfolio treatment of FRR entities and self-supply LSEs; \npreferential treatment of load subject to FRR  \n36. The proposed treatment of New Large Load in FRR service areas differs from the treatment \napplied to similarly situated load served by self-supply LSEs participating in RPM. Under \nproposed Tariff, Attachment DD-4, section V(a), New Large Loads located within an FRR \nService Area do not qualify as Eligible New Large Loads and therefore are not subject to \nIRAS. The FRR entity instead must satisfy the resource adequacy requirements associated \nwith that load through its FRR Capacity Plan and supporting resource portfolio, consistent \nwith proposed RAA Schedule 8.1, section D.1.1. Resource adequacy therefore rests on a \nportfolio-level demonstration within the FRR construct. The Joint EDC Proposal followed a \nsimilar approach by allowing portfolios of resources to support portfolios of Large Loads. \n37. FRR entities and self-supplying LSEs share the same resource adequacy objective. Both must \nmaintain sufficient resources to serve forecast load and satisfy applicable reliability \nrequirements. Although the administrative frameworks differ, both approaches rely on"},{"page":56,"startToken":16631,"endToken":16875,"text":"18 \n \nplanning, acquiring, and managing resource portfolios that support aggregate load \nobligations. \n38. The proposal nevertheless applies different standards for demonstrating resource adequacy. \nAn FRR entity may support load growth through a portfolio-level demonstration reflected in \nits FRR Capacity Plan. A self-supplying LSE participating in RPM, by contrast, must satisfy \nresource-specific BYONC qualification requirements and assign qualifying resources to \nspecific New Large Loads. As a result, an FRR entity may demonstrate resource adequacy \nthrough the sufficiency of its overall portfolio, while a self-supplying LSE must establish \ncompliance on a resource-by-resource basis even when its portfolio contains adequate \ncapacity to serve the new load. \n39. No difference in resource adequacy outcomes supports this distinction. FRR entities and self-\nsupply LSEs face the same obligation to maintain adequate resources and ensure reliable \nservice. The distinction instead reflects the way PJM recognizes resource adequacy. In that \nrespect, the proposal creates disparate treatment. First, PJM accepts a portfolio-level \ndemonstration of resource adequacy for FRR entities while requiring self-supplying RPM \nparticipants to satisfy qualification and attribution requirements for individual resources. \nSecond, PJM excludes FRR load from IRAS without requiring a demonstration that the \napplicable FRR Capacity Plan contains sufficient capacity to support the associated New \nLarge Load. Contrarywise, the Joint EDC Proposal addressed this issue by conditioning the \nexclusion on a demonstration that the FRR Capacity Plan contained adequate capacity to \nserve the load. That approach maintained a direct connection between the exemption and the \nunderlying resource adequacy objective."},{"page":57,"startToken":16875,"endToken":17138,"text":"19 \n \n40. The proposal therefore applies different requirements to entities pursuing the same reliability \nobjective based solely on the framework through which PJM recognizes resource adequacy. \nThe filing does not explain why a portfolio-based demonstration suffices within the FRR \nconstruct but not within the self-supply construct. Given the similarities in the planning, \nprocurement, and portfolio management functions performed by these entities, the record \nprovides little basis for this distinction. \n41. As a practical matter, the proposal permits FRR-served load growth to avoid IRAS exposure \nthrough a portfolio-based demonstration of adequacy while subjecting comparable load \nserved by self-supplying RPM participants to curtailment risk unless PJM’s resource-specific \nattribution requirements are satisfied. The result is disparate curtailment exposure for \ncustomers whose loads are supported by similarly adequate resource portfolios. \nPJM does not demonstrate that compensating IRAS curtailments is warranted \n42. PJM proposes to compensate load reductions provided under IRAS at a rate equal to 50% of \nthe applicable Non-Performance Charge Rate under proposed Tariff, Attachment DD-4 \nsection X. IRAS applies to New Large Loads that have not secured qualifying BYONC \nresources or sufficient RBP capacity. PJM characterizes IRAS curtailments as a reliability \nservice and proposes compensation on that basis. However, the filing does not establish that \nIRAS curtailments provide a reliability service comparable to other compensated reliability \nresources.  \n43. The proposal can be understood as permitting New Large Loads to receive service prior to \nsecuring sufficient recognized capacity support, in which case curtailment represents a \ncondition associated with that available-system-capacity-contingent service arrangement. \nIndeed, PJM seems to acknowledge the purpose of IRAS in the proposed RAA revisions:"},{"page":58,"startToken":17138,"endToken":17397,"text":"20 \n \n“load reductions requested by the Office of Interconnection to maintain system reliability for \nthe purpose of supporting the integration of New Large Load to the PJM Region that have \nnot entered into an arrangement with new capacity additions to the PJM Region. [RAA, \nSchedule 11, B (3)]” This treatment is analogous to the distinction between firm and non-\nfirm transmission service. Both classes of customers receive transmission service, but non-\nfirm customers accept interruption during periods of system constraint rather than pay for \ntransmission upgrades. Transmission providers generally do not compensate non-firm \ntransmission customers when interrupted because curtailment is an inherent characteristic of \nthe service being provided. A similar construct logically applies to New Large Loads that \nhave not secured qualifying capacity resources. Such loads receive service subject to \ninterruption during specified reliability conditions without creating a separate entitlement to \ncompensation. Curtailment under those circumstances is more appropriately viewed as a \ncondition of service rather than a compensable reliability product. \n44. The proposed compensation mechanism may also affect incentives. Based on PJM’s \nproposed compensation formula and the CONE values reflected in PJM’s proposed tariff \nrevisions, the IRAS compensation rate could be approximately $307/MW-day on an \nindicative RTO-wide basis. 13 While the precise applicable rate may vary depending on the \nfinal tariff calculation and applicable location, the estimate demonstrates that the proposed \ncompensation level is substantial.  \n45. The proposed compensation creates a potential perverse incentive. A New Large Load that \nhas not secured qualifying BYONC or sufficient RBP capacity remains subject to IRAS \n \n13 See supra note 9."},{"page":59,"startToken":17397,"endToken":17677,"text":"21 \n \nbecause it has not demonstrated recognized capacity support. Yet that same load could \nreceive compensation for curtailments at a level broadly comparable to recent capacity-\nmarket prices and, in some circumstances, greater than revenues earned by resources that \nundertake direct resource adequacy obligations. The filing does not explain why load that has \nnot secured recognized capacity support should receive compensation comparable to \nresources that commit capacity and assume associated performance obligations. Absent such \na distinction, the proposal may reduce the relative advantage of securing qualifying capacity, \nweaken incentives for timely resource development or procurement, and increase reliance on \ncurtailment as a substitute for capacity solutions. Compensation at that level may reduce the \neconomic consequence of remaining subject to IRAS and thereby weaken incentives for New \nLarge Loads or their serving LSEs to secure qualifying capacity resources. \n46. Additional concerns arise from the interaction between IRAS and RPM. New Large Loads \nthat remain subject to IRAS are excluded from the RPM demand curve unless they secure \nqualifying BYONC resources or allocated RBP capacity. As a result, those loads do not \ncontribute to the RPM demand signal that would otherwise support additional capacity \nprocurement. At the same time, the proposal would permit an IRAS-exposed New Large \nLoad to receive compensation when curtailed even though the load remains outside the RPM \ndemand construct. The filing does not explain why that outcome is necessary to maintain \nreliability or promote efficient resource adequacy outcomes. The proposal therefore relies on \nBYONC development, RBP allocations, and curtailment exposure rather than RPM \nprocurement to address the resource adequacy implications of New Large Load growth. The \nfiling provides limited discussion of how this treatment affects investment incentives, cost"},{"page":60,"startToken":17677,"endToken":17937,"text":"22 \n \ncausation, and the relationship between resource adequacy beneficiaries and resource \nprocurement obligations. \n47. The proposal also creates an unusual disparity when compared to RPM Demand Response. \nDemand Response participates in RPM as a capacity resource. Curtailment Service Providers \naggregate customer load-reduction capability, offer that capability into the capacity market, \nassume capacity-performance obligations, and manage customer curtailments in exchange for \nRPM revenues. By contrast, a New Large Load subject to IRAS has not secured qualifying \nBYONC or sufficient RBP capacity and has not undertaken an RPM capacity obligation. \nNevertheless, PJM’s proposal could provide compensation at levels comparable to, or \npotentially greater than, the revenues earned by some Demand Response resources that have \nassumed those obligations. The filing does not explain why load that remains subject to \nIRAS should receive compensation comparable to resources that actively participate in RPM \nand bear resource adequacy responsibilities. That disparity may distort incentives between \nmarket participants, diminish the value of assuming RPM obligations, and discourage \nparticipation through mechanisms designed to procure and maintain capacity resources. \n48. By allowing a New Large Load to continue receiving service while remaining subject to \ncompensated curtailment, the proposal reduces the relative benefit of obtaining qualifying \ncapacity support. To the extent market participants view compensated curtailment as an \nacceptable alternative to resource procurement, the proposal may encourage reliance on load \nreductions rather than investment in the resources needed to address long-term resource \nadequacy needs. \n49. The compensation structure also raises cost-causation concerns. If PJM recovers IRAS \ncompensation through charges assessed to other load in the affected zone or area, customers"},{"page":61,"startToken":17937,"endToken":18182,"text":"23 \n \nthat did not contribute to the underlying resource adequacy concern may fund payments to \nload that remained subject to IRAS because it lacked recognized capacity support. That result \nis difficult to reconcile with a resource adequacy framework intended to assign responsibility \nto the load additions driving the need for the mechanism. Resource adequacy frameworks \ngenerally function most effectively when market participants bear the costs associated with \nthe reliability risks they create. PJM states that compensation may be waived or modified \nthrough retail arrangements, but the proposed tariff nevertheless establishes a default federal \ncompensation rate. The filing does not explain why, absent such a waiver or alternative retail \ntreatment, other customers should fund these payments or how that outcome is consistent \nwith principles of cost causation and the stated objective of protecting existing ratepayers \nfrom costs associated with New Large Load growth. If those costs are shifted to other \ncustomers, the proposal could socialize costs associated with New Large Load development, \nweaken accountability for capacity procurement decisions, and undermine the cost-allocation \nprinciples that IRAS purports to advance. \nConclusion \n50. The proposed IRAS framework may result in load curtailments even when sufficient \nresources are available to support reliability because PJM conditions BYONC recognition on \nqualification and timing requirements rather than actual resource availability. \n51. The proposal evaluates resource adequacy through resource-to-load attribution instead of \nassessing the sufficiency of an LSE’s overall resource portfolio. As a result, customers \nsupported by adequate portfolios may nevertheless face curtailment exposure."},{"page":62,"startToken":18182,"endToken":18380,"text":"24 \n \n52. The proposal applies different standards to FRR entities and self-supplying RPM participants \neven though both pursue the same resource adequacy objective through portfolio planning \nand resource procurement. \n53. By compensating curtailments associated with insufficient recognized capacity support, the \nproposal may weaken incentives to develop or procure qualifying resources, shift costs to \nother customers, and increase reliance on curtailment as a substitute for capacity solutions. \n54. The proposal also does not adequately address the risk that a real-time IRAS directive could \nexceed the amount of IRAS load online and available for curtailment within the applicable \nElectric Distributor zone or area. Nor does the filing justify assigning IRAS compensation \ncosts to load that did not contribute to the resource adequacy concern the mechanism is \ndesigned to address. As a result, the proposal may shift the consequences of insufficient \nrecognized capacity support, whether in the form of curtailment obligations, compensation \ncosts, or residual reliability risks, to customers and LSEs that did not create the underlying \nresource adequacy issue. These implementation, cost-causation, and accountability concerns \nunderscore the disconnect between the parties responsible for the resource adequacy concern \nand the entities that may bear its consequences. \n55. This ends my affidavit."},{"page":63,"startToken":18380,"endToken":18415,"text":"VERIFICATION OF AFFIDAVIT \n \nPursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the foregoing \nAffidavit is true and correct. \n \nExecuted September 3, 2026. \n \nBy: _____________________________ \n       Marc D. Montalvo"},{"page":64,"startToken":18415,"endToken":18421,"text":"Attachment 2 \n \nAffidavit of Julie Tucker"},{"page":65,"startToken":18421,"endToken":18703,"text":"1 \n \nAFFIDAVIT OF JULIA J. TUCKER \nON BEHALF OF \nEAST KENTUCY POWER COOPERATIVE, INC.  \n \nI. \nIntroduction \n1. My name is Julia J. Tucker.  I am the Vice President of Power Supply and Planning for East \nKentucky Power Cooperative, Inc. (“EKPC”).  My business address is 4775 Lexington Road, \nWinchester, Kentucky 40391.  \n2. I have a Bachelor’s degree in Electrical Engineering from the University of Kentucky.  I am a \nlicensed Professional Engineer, Registration Number 15532, in the state of Kentucky. I have \nworked for EKPC for the past 20 years.    \n3. I oversee EKPC’s Power Supply Planning, Load Forecasting, Market Operations Center, Fuels \nProcurement, Demand Side Management, Distributed Energy Resources and development of \nRenewable Energy Projects.  \n4. EKPC is a not-for-profit, member-owned generation and transmission cooperative located in \nWinchester, Kentucky. EKPC provides electricity to 16 owner-member distribution \ncooperatives (owner-members) with over 570,000 retail consumers (approximately 1.2 million \nmember population) at homes, farms, and businesses in 89 counties in Kentucky and 4 counties \nin Tennessee. EKPC does not directly serve any retail consumers. Owner members served by \nEKPC include: \n• Big Sandy RECC  \n• Jackson Energy Cooperative \n• Blue Grass Energy Cooperative  \n• Licking Valley RECC \n• Clark Energy Cooperative  \n• Nolin RECC \n• Cumberland Valley Electric  \n• Owen Electric Cooperative  \n• Farmers RECC  \n• Salt River Electric Cooperative \n• Fleming-Mason Energy Cooperative  \n• Shelby Energy Cooperative \n• Grayson RECC  \n• South Kentucky RECC \n• Inter-County Energy Cooperative \n• Taylor County RECC \n \nII. \nPurpose \n5. The purpose of my affidavit is to explain EKPC’s role as a Load Serving Entity (“LSE”) under \nthe PJM Interconnection, L.L.C. (“PJM”) Reliability Assurance Agreement Among Load \nServing Entities (“RAA”) and how EKPC utilizes a portfolio of Self-Supply resources in the \nReliability Pricing Model (“RPM”) Capacity Market. Additionally, I will describe the"},{"page":66,"startToken":18703,"endToken":19254,"text":"2 \n \nobligation we will impose on any new data center load we may become obligated to serve \npursuant to our Kentucky Public Service Commission approved Data Center Tariff. In doing \nso, I offer support for the concerns EKPC raised in its Protest of PJM’s proposal to establish \nan Interim Resource Adequacy Service (“IRAS”). Specifically, I highlight how PJM’s Bring \nYour Own New Capacity (“BYONC”) eligibility requirements conflict with our long-standing \nportfolio approach to supplying our Owner Members’ capacity requirements as well as with \nthe obligation we would impose on data centers under our Data Center Tariff.   The result is \nthat PJM would ignore the important reliability contribution of resources within our portfolio, \nand resources currently under development to be added to our portfolio, to offset any \ncurtailment obligation it would impose under IRAS.  To avoid the curtailment risk, EKPC \nwould need to incur cost in addition to the significant costs we are bearing to support the \ndevelopment of these additional important reliability resources to avoid leaning on the PJM \nregion for power supply.   \nIII. \nEKPC’s LSE Role and Proactive Planning For and Use of Self-Supply Resources \n6. Under the PJM Open Access Transmission Tariff (“PJM Tariff”), Self-Supply means, \n“Capacity Resources secured by a Load-Serving Entity, by ownership or contract, outside a \nReliability Pricing Model Auction, and used to meet obligations under this Attachment or the \nReliability Assurance Agreement through submission in a  Base Residual Auction or an \nIncremental Auction of a Sell Offer. . . .”1 \n7.  EKPC satisfies the capacity obligation associated with it acting as agent for its 16 owner \nmember distribution cooperatives for purposes of satisfying all Load Serving Entity \nrequirements in PJM.  EKPC has a full-requirements contract with its owner members, \nobligating it to satisfy their load serving obligations under Kentucky law.  As such, in order to \nsatisfy the load serving obligations of its owner members, EKPC is a signatory to the PJM \nOperating Agreement, Reliability Assurance Agreement (RAA) and PJM Tariff. \n8. Focusing specifically on the resource adequacy requirements associated with serving our \nowner members’ load, EKPC has elected to satisfy the RAA obligations by participating in the \nRPM Capacity Market.  EKPC both owns generation capacity resources and has capacity \nresources under contract, as well as administers demand response programs that are eligible \ndemand response capacity resources in the RPM Capacity Market. \n9. EKPC offers all of its owned generation, capacity resources under contract, and demand \nresponse products into the RPM Capacity Market. It designates these resources as “Self-\nSupply”.  In turn, EKPC pays the resulting price from the combination of the BRA and IAs for \na Delivery Year.  EKPC offers in sufficient Self-Supply to cover its load obligation.  \n10. In total, EKPC owns and operates approximately 2,963 MW of net summer generating capacity \nand 3,265 MW of net winter generating capacity. EKPC owns and operates coal-fired \ngeneration at the John S. Cooper Station in Pulaski County, Kentucky (341 MW) and the Hugh \nL. Spurlock Station (1,346 MW) in Mason County, Kentucky. EKPC also owns and operates \nnatural gas-fired generation at the J. K. Smith Station in Clark County, Kentucky (753 MW \n(summer)/989 MW (winter)) and the Bluegrass Generating Station in Oldham County, \nKentucky (501 MW (summer)/567 MW (winter)), landfill gas-to-energy facilities in Boone \n \n1 PJM Open Access Transmission Tariff, Definitions, Section 1."},{"page":67,"startToken":19254,"endToken":19855,"text":"3 \n \nCounty, Greenup County, Hardin County, Pendleton County and Barren County (13.8 MW \ntotal), and a Community Solar facility (8.5 MW) in Clark County, Kentucky. Finally, EKPC \npurchases hydropower from the Southeastern Power Administration at Laurel Dam in Laurel \nCounty, Kentucky (70 MW), and the Cumberland River system of dams in Kentucky and \nTennessee (100 MW). EKPC also has 200 MWs of interruptible load and approximately 28 \nMWs in peak reduction mechanisms.  \n11. EKPC constantly strives to anticipate the challenges it may face over both the near and long-\nterm. As part of this process, EKPC regularly conducts and reviews load and pricing forecasts, \nprepares for environmental regulation developments, and evaluates the impact various factors \nmay have on the Cooperative’s existing generation portfolio and overall financial stability. \nFuture power supply needs analysis occurs both during and between EKPC’s Integrated \nResource Plan (“IRP”) filings with the KY PSC.  EKPC plans for growth in residential, \nindustrial and commercial load. Only with respect to data center load growth does EKPC apply \nan additional consideration to its power supply planning described below. \n12. EKPC builds out its portfolio of resources to satisfy the aggregate of its forecasted load needs. \nEKPC does not tie specific resources in its portfolio to specific Owner Members or to any \nindividual end-consumers served by its Owner Members. The portfolio includes a range of \nresource types to meet the energy and capacity needs of the aggregate load. To tie specific \nresources to individual loads as PJM’s IRAS proposal effectively requires would undermine \nthe efficiency gained by portfolio planning.  Forecasted growth of industrial and manufacturing \nload is included in the portfolio planning as well. Such loads could grow to a size to be included \nin PJM’s proposed definition of New Large Load and be subject to IRAS exposure. EKPC \nwould be unable to tie specific resources to individual loads to make a BYONC demonstration. \nMoreover, EKPC has planned for some measure of load growth in its existing portfolio of \nresources. To the extent that the load EKPC is obligated to serve can be satisfied with EKPC’s \nportfolio of resources, it should not be subject to IRAS curtailment exposure.  To do otherwise \nwould ignore the significant investment that such loads have made to securing reliability.  \n13. In so doing, EKPC actively plans its supply portfolio to manage its load serving obligation.  In \nresponse to EKPC’s forecast of changes in its peak load requirements, EKPC filed with, and \nreceived approval from, the KY PSC three Certificates of Public Convenience and Necessity \n(“CPCNs”) in PSC Case Nos. 2024-001291, 2024-003102 and 2024-003703, seeking \nCommission approval to build new generation assets known as Cooperative Solar Fayette (40 \nMW), Cooperative Solar Marion (96 MW), Star Hill Farms solar (0.5 MW), Liberty RICE \n(214 MW) and Cooper CCGT (745 MW), along with the natural gas co-fire conversion of \nEKPC’s existing coal-fired generating units including Spurlock Units 1 through 4 and Cooper \nUnit 2.  \n14. Both the Cooper CCGT and the Liberty RICE are in interconnection queues and currently \nbeing studied by PJM for reliable interconnection to the grid.  The Cooper CCGT plant would \nbe capable of producing up to 745 MW on a dependable and dispatchable basis. The plant \nwould have two natural gas fired combustion turbines, two heat recovery steam generators \n(“HRSG”) and one steam turbine. Its expected Commercial Operation Date (“COD”) is \nDecember 2030.  Liberty proposed project is a 217.6 gross MW RICE facility consisting of \ntwelve (12) Engine/Generator Sets (“Gensets”) with each Genset capable of producing \neighteen (18.132) gross MW. The total expected net capacity available from the facility is"},{"page":68,"startToken":19855,"endToken":20499,"text":"4 \n \nexpected to be 214 net MW.  The Gensets are designed to operate on both natural gas and on \nultra-low sulfur diesel as a backup fuel source. EKPC anticipates COD of December 2028 for \nthe Liberty RICE units. \n15. The Cooper CCGT had been selected as part of the Reliability Resource Initiative that inserted \nprojects into Transition Cycle #2. PJM’s analysis is not yet complete so the Cooper CCGT does \nnot yet have Generation Interconnection Agreement.  Due to its mid-Delivery Year COD, \nEKPC will not be able to offer it into the 2030/2031 Delivery Year RPM BRA.  The first \nDelivery Year in which EKPC could offer the Cooper CCGT to be committed in an RPB BRA \nwould be 2031/32.  Thus, for approximately 6 months, the Cooper CCGT would be on-line \nand providing reliability benefits to the grid but unable to offset PJM’s IRAS curtailment \nobligation. PJM’s IRAS proposal requires a BYONC resource to be committed in an RPM \nAuction to offset the IRAS curtailment obligation. Indeed, consistent with its power supply \nplan, EKPC would offer the Cooper CCGT into the energy and ancillary service markets at the \nearliest opportunity despite not having a capacity obligation requiring it to do so yet that \ncontribution to reliability would be ignored until it is formally committed to the region through \nan RPM Auction.  The Cooper CCGT is an important part of the portfolio of resources EKPC’s \nOwner Members are investing in to reliably meet their power supply needs and avoid leaning \non the PJM market.    Yet, those served by EKPC’s Owner Members would be exposed to \ncurtailment risk despite their significant investment in reliability. \n16. The Liberty RICE had not been selected as part of the Reliability Resource Initiative and is not \nbeing studied in Transition Cycle #2 along with the Cooper CCGT. Instead, it is being studied \nin New Cycle #1 that just began in spring of 2026.  Despite Liberty RICE’s expected COD of \nDecember 2028, it was not eligible to offer into the 2028/29 Delivery Year BRA both because \nit had not progressed sufficiently through the interconnection study process and because it has \na mid-Delivery Year COD and cannot be committed for a full Delivery Year. The first full \nDelivery Year in which Liberty RICE would be operational and able to be committed in an \nRPM Auction would be 2029/2030 Delivery Year.  Thus, for approximately 6 months, the \nLiberty RICE would be on-line and providing reliability benefits but unable to offset PJM’s \nIRAS curtailment obligation. As noted above, PJM’s IRAS proposal requires a BYONC \nresource to be committed in an RPM Auction to offset the IRAS curtailment obligation.  \nIndeed, as noted above, consistent with its power supply plan, EKPC would offer the Liberty \nRICE into the energy and ancillary service markets at the earliest opportunity despite not \nhaving a capacity obligation requiring it to do so.  The Liberty RICE is an important part of \nthe portfolio of resources EKPC’s Owner Members are investing in to reliably meet their power \nsupply needs and not lean on the PJM market.  Yet, those served by EKPC’s Owner Members \nwould be exposed to curtailment risk despite their significant investment in reliability. \nIV. \nEKPC’s Data Center Tariff and Obligation To Adjust Power Supply Plan \n17. In October, 2025, the KY PSC approved EKPC’s Data Center Tariff which applies data centers \nthat satisfy two criteria: load size (15 megawatts (\"MWs\") or greater) and load factor (60% or \ngreater).   The over-arching goal of the Rate DCP Tariff is to minimize - and if possible \neliminate - cross-subsidization of data center load and non-data center load.  The proposed \nRate DCP Tariff acknowledges that large data center loads could exceed EKPC's existing \nportfolio of generation resources. Accordingly, the Rate DCP Tariff includes a requirement that \nEKPC will work with a data center to develop and implement a power supply plan to support"},{"page":69,"startToken":20499,"endToken":20778,"text":"5 \n \nthe customer’s load with: “Dedicated Resources” supplied by EKPC or the data center; \nbilateral power and capacity purchases; or a combination of these resources. For those data \ncenter loads exceeding 250 MWs, one or more Dedicated Resources will be required as part of \nthe power supply plan. The Dedicated Resource in EKPC’s data center tariff is an important \nsystem resource planning requirement, but the Dedicated Resource is not “tied” to a particular \nload as IRAS contemplates. At this time, EKPC has not executed a contract to serve a new data \ncenter; however, there are several actively negotiating terms and conditions of service utilizing \nour Data Center Tariff framework. The IRAS proposal filed by PJM has created a significant \nheadwind to data center investments because it fails to give credit to loads for existing \nresources that are under contract. \n18. EKPC’s focus on data centers differs from PJM’s more expansive definition of Large Load that \nincludes industrial and manufacturing loads.  As noted above, EKPC plans for the growth of \nindustrial and manufacturing loads as part of its ongoing forecasting and planning efforts.  To \nthe extent a data center is under 250 MW, EKPC would ensure its load requirements would be \nsatisfied as part of EKPC’s forecasting and portfolio planning efforts. However, data center \nloads greater than 250 MW would require “Dedicated Resources.”  This not does mean that \nEKPC deviates from a portfolio approach, but rather that EKPC ensures there are sufficient \nresources to satisfy the data center load and places additional financial obligations directly on \nthe data centers to ensure that other loads are protected from costs associated with supplying \ntheir needs. \nV. \nConclusion \n19. This concludes my affidavit."},{"page":70,"startToken":20778,"endToken":20813,"text":"VERIFICATION OF AFFIDAVIT \n \nPursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the foregoing \nAffidavit is true and correct. \n \nExecuted September 3, 2026. \n \nBy: _____________________________ \n       Julia J. Tucker"},{"page":71,"startToken":20813,"endToken":20861,"text":"Certificate of Service \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, DC this 3rd day of September, 2026. \n/s/ Kelly A. Cuthbertson \n \nKelly A. Cuthbertson"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1265,"startToken":0,"endToken":470},{"p":2,"at":1265,"title":"I. Background","method":"printed heading","endPage":2,"endAt":1281,"startToken":470,"endToken":472},{"p":2,"at":1281,"title":"A. IRAS Overview","method":"printed heading","endPage":8,"endAt":3,"startToken":472,"endToken":2084},{"p":8,"at":3,"title":"B. The Stakeholder Process and Joint EDC Proposal","method":"printed heading","endPage":9,"endAt":770,"startToken":2084,"endToken":2463},{"p":9,"at":770,"title":"II. Limited Protest","method":"printed heading","endPage":9,"endAt":792,"startToken":2463,"endToken":2466},{"p":9,"at":792,"title":"A. Introduction","method":"printed heading","endPage":14,"endAt":4,"startToken":2466,"endToken":3925},{"p":14,"at":4,"title":"B. Elements of PJM’s IRAS Proposal Are Not Just and Reasonable.","method":"printed heading","endPage":29,"endAt":387,"startToken":3925,"endToken":9203},{"p":29,"at":387,"title":"C. PJM Has Failed to Demonstrate that Compensating IRAS Curtailment Is","method":"printed heading","endPage":33,"endAt":371,"startToken":9203,"endToken":10572},{"p":33,"at":371,"title":"D. PJM’s Proposed Treatment of New Large Loads Served by FRR Entities Is","method":"printed heading","endPage":35,"endAt":909,"startToken":10572,"endToken":11311},{"p":35,"at":909,"title":"E. PJM’s Proposed Revisions to FRR Rules Creates Ambiguity and Disadvantage","method":"printed heading","endPage":36,"endAt":860,"startToken":11311,"endToken":11731},{"p":36,"at":860,"title":"III. Conclusion","method":"printed heading","endPage":39,"endAt":91,"startToken":11731,"endToken":11902},{"p":39,"at":91,"title":"Introduction","method":"printed heading","endPage":41,"endAt":913,"startToken":11902,"endToken":12501},{"p":41,"at":913,"title":"Background","method":"printed heading","endPage":48,"endAt":555,"startToken":12501,"endToken":14543},{"p":48,"at":555,"title":"Discussion","method":"printed heading","endPage":61,"endAt":1249,"startToken":14543,"endToken":18114},{"p":61,"at":1249,"title":"Conclusion","method":"printed heading","endPage":65,"endAt":90,"startToken":18114,"endToken":18435},{"p":65,"at":90,"title":"I. Introduction","method":"printed heading","endPage":65,"endAt":1658,"startToken":18435,"endToken":18646},{"p":65,"at":1658,"title":"II. Purpose","method":"printed heading","endPage":66,"endAt":1130,"startToken":18646,"endToken":18876},{"p":66,"at":1130,"title":"III. EKPC’s LSE Role and Proactive Planning For and Use of Self-Supply Resources","method":"printed heading","endPage":68,"endAt":3217,"startToken":18876,"endToken":20385},{"p":68,"at":3217,"title":"IV. EKPC’s Data Center Tariff and Obligation To Adjust Power Supply Plan","method":"printed heading","endPage":69,"endAt":1741,"startToken":20385,"endToken":20771},{"p":69,"at":1741,"title":"V. Conclusion","method":"printed heading","endPage":71,"endAt":0,"startToken":20771,"endToken":20813},{"p":71,"at":0,"title":"Certificate of Service","method":"printed heading","endPage":71,"endAt":305,"startToken":20813,"endToken":20861}]}