{"document":{"slug":"rec-20260903-5230","title":"Comments and Request for Clarification of American Electric Power Service Corporation re PJM Interconnection, LLC’s proposed revisions to the PJM Open…","issued":"2026-09-03","accession":"20260903-5230","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"American Electric Power Corporation","kind":"rehearing request","file":"sources/filings/text/20260903-5230_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5230","tier":"record","sha256":"52564462eb45671889fcaaeb461deec17e01dc2951c5f5c5e9e9acb0ed3b2596","pages":19,"tokens":5125,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":220,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \n \nCOMMENTS AND REQUEST FOR CLARIFICATION \nOF AMERICAN ELECTRIC POWER SERVICE CORPORATION \n \nAmerican Electric Power Service Corporation, on behalf of its affiliates \nAppalachian Power Company, Indiana Michigan Power Company, Kentucky Power \nCompany, Kingsport Power Company, Ohio Power Company, and Wheeling Power \nCompany (collectively, “AEP”), submits the following comments to and request for \nclarification of PJM Interconnection, LLC’s (“PJM’s”) proposed tariff revisions to the PJM \nOpen Access Transmission Tariff (“PJM Tariff”) and Reliability Assurance Agreement \nAmong Load Serving Entities (“RAA”) proposed in the above-captioned docket to \nestablish Interim Resource Adequacy Service (“IRAS”) effective October 12, 2026 (the \n“IRAS Proposal”).1 \nI. \nEXECUTIVE SUMMARY \nAEP recognizes that PJM faces a significant tightening of its Reliability Pricing \nModel (“RPM”) capacity market in recent years and subsequent resource adequacy \nshortfalls, and supports PJM taking action to mitigate the associated reliability risks.  AEP \nseeks narrow clarifications on certain aspects of the IRAS Proposal that impose \n \n1 PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim Res. Adequacy \nServ. and A Large Load Registry to Address Sys. Reliability, Docket No. ER26-3515 (filed Aug. 13, 2026) \n(“IRAS Proposal”).  AEP filed a doc-less motion to intervene in the captioned docket on August 17, 2026."},{"page":2,"startToken":220,"endToken":520,"text":"2 \nrequirements on entities that utilize the Fixed Resource Requirement Alternative (“FRR”) \nto satisfy their obligations under the RAA to commit Unforced Capacity to ensure reliable \nservice to FRR loads in the PJM Region.2  \nMost of AEP’s affiliate load serving entities (“LSEs”) in the PJM Region use the \nFRR Alternative.  While IRAS itself does not apply to loads in FRR service areas, the \nIRAS Proposal includes a rule that restricts FRR Entities from utilizing Existing \nGeneration Capacity Resources to meet the capacity obligations of New Large Load within \nFRR service areas unless the Existing Generation Capacity Resource is procured prior to a \nset date.3  The goal of this restriction is to ensure that FRR Entities cannot poach capacity \nfrom the RPM market during periods of capacity shortfall.4  \nConsistent with that goal, AEP requests a few points of clarification to ensure that \nthe IRAS Proposal does not discriminate between FRR load and RPM load in its efforts to \nmitigate reliability risk during capacity shortfall periods in the RPM market.  First, as \ndescribed in section III.B, the IRAS Proposal allows for IRAS to be active during periods \nof RPM capacity shortfall and to go dormant during periods of sufficient capacity in RPM.5  \nAEP seeks clarification that when IRAS goes dormant, the IRAS Proposal’s restrictions on \nFRR entities also go inactive.6  Second, the IRAS Proposal allows for IRAS to reactivate \n \n2 Proposed RAA, Schedule 8.1, section D.1.  These comments solely address the aspects of the IRAS \nProposal that affect FRR Entities and should not be construed as an endorsement of any specific provision \nof the IRAS Proposal applicable to RPM load. \n3 Id. section D.1.1. \n4 PJM Transmittal Letter at 73-74. \n5 See infra section III.B. \n6 See infra section IV.A."},{"page":3,"startToken":520,"endToken":738,"text":"3 \nafter a dormant period when PJM is again facing an RPM capacity shortfall.7  When IRAS \nreactivates, it redefines the load that IRAS can restrict based on a new in-service date—\nonly Large Loads that go into service after the new in-service date will be subject to IRAS.8  \nAEP seeks clarification that when IRAS reactivates, the restrictions on using Existing \nGeneration Capacity Resources also reset to an updated cutoff date.9  Finally, when IRAS \nreactivates, the reactivation determination is made just a few months before the service \nbecomes active again.10  For FRR Entities, the effect is an extremely short timeline to \ncomply with the IRAS Proposal’s restrictions on FRR Capacity Plans.11  AEP seeks \nclarification that there will be a buffer period for FRR Entities to develop compliant FRR \nCapacity Plans upon IRAS reactivation.12  If these clarifications are not made and the IRAS \nProposal is implemented, the proposal will be unjust, unreasonable, and unduly \ndiscriminatory.  Accordingly, absent the clarifications that AEP seeks, the Commission \nshould condition any approval of the IRAS on fixing these issues consistent with the \ncomments below.13   \n \n7 See infra section III.B. \n8 Id. \n9 See infra section IV.B. \n10 See infra section III.C; section IV.C. \n11 See infra section IV.C. \n12 Id. \n13 Id."},{"page":4,"startToken":738,"endToken":957,"text":"4 \nII. \nCORRESPONDENCE AND COMMUNICATIONS \nCorrespondence regarding this filing should be sent to the following individuals, \nwho should be placed on the official service list in this proceeding:14 \nJohn C. Crespo \nSenior Legal Counsel \nAmerican Electric Power Service \nCorporation \n1 Riverside Plaza \nColumbus, OH  43215 \n(614) 716-3727 \njccrespo@aep.com  \n \nWilliam M. Keyser \nMegan McDowell \nSteptoe LLP \n1330 Connecticut Avenue, NW \nWashington, DC  20036 \n202-429-8186 \nwkeyser@steptoe.com \nmmcdowell@steptoe.com  \n \nIII. \nBACKGROUND \nA. \nAEP \nAmerican Electric Power Company, Inc. is one of the largest investor-owned \nelectric public utility holding companies in the United States.  Its electric utility companies \nprovide generation, transmission, and distribution services to more than five million \ncustomers in Arkansas, Indiana, Kentucky, Louisiana, Michigan, Ohio, Oklahoma, \nTennessee, Texas, Virginia, and West Virginia.  It also partially owns entities that own \ntransmission facilities in states outside of its service territories. \nAmerican Electric Power Company, Inc.’s affiliates Appalachian Power Company, \nIndiana Michigan Power Company, Kentucky Power Company, Kingsport Power \nCompany, Ohio Power Company, and Wheeling Power Company are load serving entities \n(“LSEs”) in PJM.  Accordingly, American Electric Power Service Corporation is a party \n \n14 AEP respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) (2026) to allow more than two individuals \nto be designated for service on the official service list in this proceeding."},{"page":5,"startToken":957,"endToken":1253,"text":"5 \nto PJM’s Reliability Assurance Agreement on behalf of these LSE affiliates.  Of these \noperating companies, Appalachian Power Company, Indiana Michigan Power Company, \nKentucky Power Company, and Wheeling Power Company are FRR Entities, meaning they \nutilize the FRR Alternative under the RAA to satisfy their RAA obligations to commit \nUnforced Capacity to ensure reliable service to loads in the PJM Region.  Thus, as FRR \nEntities, these companies do not satisfy their capacity obligations through the RPM and its \nauctions.  Rather, they supply their capacity needs from owned or contracted capacity \nresources and provide FRR Capacity Plans in advance of each Delivery Year \ndemonstrating that they have sufficient Unforced Capacity to serve their load obligations, \nincluding satisfying the applicable reserve margin requirements. \nB. \nIRAS \nIRAS is a proposed service that will allow for Large Loads15 to interconnect in PJM \nwithout bringing their own capacity, on the condition that “they must reduce their load or \nswitch to on-site backup resources under specific, limited emergency conditions.”16  New \nLarge Loads17 can avoid being subject to IRAS reductions by bringing their own new \ncapacity or procuring capacity through the Reliability Backstop Procurement.   \n \n15 Proposed RAA, Article 1 – Definitions (defining Large Load):   \n“Large Load” shall mean end-use customer(s) load that has a cumulative peak load of 50 \nmegawatts or greater at a single electrical site behind one or more points of interconnection, \nwhere for configurations involving multiple affiliated load facilities or multiple points of \ninterconnection with affiliated load facilities behind them, all affiliated load facilities \nwithin a one-mile radius will be considered a single electrical site as further described in \nthe PJM Manuals.   \n16 PJM Transmittal Letter at 39 (footnote omitted). \n17 See infra section III.C.1, reproducing proposed definition of New Large Load in the Proposed PJM Tariff."},{"page":6,"startToken":1253,"endToken":1582,"text":"6 \nIRAS will only apply during multi-year periods where there are insufficient \nresources to reliably meet demand in real time operations, as defined in the proposed tariff \nchanges.18  During those periods, IRAS will enable PJM to reduce loads in zones/areas \nwhere New Large Loads have not otherwise covered their capacity needs (the New Large \nLoads that can be reduced under IRAS are considered “Eligible New Large Loads”19).  The \nIRAS Proposal sets these “active” IRAS periods based on RPM auction results:  (1) IRAS \nbegins as active in the coming 2027/2028 delivery year, (2) if three consecutive years pass \nwhere the RPM auction clears sufficient capacity to meet the capacity requirement,20 IRAS \ngoes dormant, (3) then, if the RPM auction fails to clear sufficient capacity for the third \nincremental auction in advance of a delivery year,21 IRAS reactivates for the upcoming \ndelivery year.  Upon reactivation, IRAS stays active until the capacity market meets \nconditions to go dormant, as set forth in proposed Attachment DD-4, section IV(b)(iii). \nThe IRAS Proposal uses the proposed definition of New Large Load as the \nmechanism to deactivate and reactivate IRAS.  IRAS obligations can only apply to eligible \nNew Large Load.22  New Large Load is initially defined as Large Load with an in-service \n \n18 PJM Transmittal Letter at 1, 39-40. \n19 “Eligible New Large Loads shall mean a New Large Load eligible to provide Interim Resource Adequacy \nService in accordance with Tariff, Attachment DD-4, section V.”  Proposed PJM Tariff, Definitions \n(defining Eligible New Large Loads); see Proposed PJM Tariff, Attachment DD-4, section V(b). \n20 The IRAS Proposal details the conditions for IRAS dormancy in proposed Attachment DD-4, section \nIV(b)(iii).  \n21 The IRAS Proposal details the conditions for IRAS reactivation in proposed Attachment DD-4, section \nIV(b)(iii). \n22 See infra section III.C.1, reproducing proposed definition of New Large Load in the Proposed PJM Tariff; \nsee PJM Transmittal Letter at 40-41, 69 (footnotes omitted)."},{"page":7,"startToken":1582,"endToken":1858,"text":"7 \ndate after June 1, 2027.23  After three consecutive years of sufficient capacity clearing the \nRPM auction,24 the relevant in-service date for the definition of New Large Load resets.  It \nbecomes June 1 of the next delivery year where sufficient capacity does not clear the RPM \nauction.25  Thus, there can be a time period where there is no load that meets the definition \nof New Large Load, because the relevant in-service date for the definition of New Large \nLoad is not June 1, 2027, and has not yet reset to a new date.  Under these circumstances, \nIRAS is effectively dormant because there is no defined load for the service to apply to. \nIRAS will apply to New Large Loads that satisfy their capacity requirements via the \nRPM auction process and PJM is not proposing to extend IRAS to New Large Loads \nlocated in FRR Service Areas.26  However, the IRAS Proposal does require that in an FRR \nEntity’s FRR Capacity Plan, any capacity planned to serve New Large Load must be owned \nor contracted by the FRR Entity prior to a specified date:  June 1, 2027.  For ease of \nreference, these comments will refer to this rule, which the IRAS Proposal proposes to \neffectuate via revisions to the RAA Schedule 8.1, section D.1.1, as the “FRR Capacity \nRule.” \n \n23 Id. at 38-40, 72 (footnotes omitted). \n24 As detailed in proposed Attachment DD-4, section IV(b)(iii).  \n25 See section III.C.1, reproducing proposed definition of New Large Load in the Proposed PJM Tariff; see \nProposed PJM Tariff, Attachment DD-4, section IV(b)(iii). \n26 PJM Transmittal Letter at 73."},{"page":8,"startToken":1858,"endToken":2231,"text":"8 \nC. \nAEP’s Comments Focus on Three Proposed Amendments in the IRAS \nProposal \nAEP’s comments and request for clarification of the IRAS Proposal focus on three \nspecific proposed amendments to PJM’s governing documents:  the definition of New \nLarge Load to be included in the PJM Tariff, section IV(b)(iii) of the new Attachment \nDD-4 to the PJM Tariff (which is referenced by the New Large Load definition and \nregulates when that definition is dormant and active), and the revised language in the RAA, \nSchedule 8.1, section D.1.1., which forms the FRR Capacity Rule.  These proposed \namendments are reproduced below for ease of reference: \n1. \nPJM Tariff Definitions, Definition of New Large Load \n“New Large Load” shall mean end-use customer load that is either (a) a Large \nLoad that goes into service after June 1, 2027, or (b) incremental load in-\nservice after June 1, 2027, that increases the existing end-use customer load \nat a single electrical site that, prior to such incremental load, did not \npreviously meet the definition of Large Load.  However, to the extent three \nconsecutive Delivery Years meet the requirements of Tariff, Attachment DD-\n4, section IV(b)(iii), then New Large Load shall mean end-use customer load \nthat is either (a) a Large Load that goes into service after June 1 of the first \nDelivery Year for which the requirements of Tariff, Attachment DD-4, \nsection IV(b)(iii) are not met or (b) incremental load in-service after June 1 \nof the first Delivery Year for which the requirements of Tariff, Attachment \nDD-4, section IV(b)(iii) are not met that increases the existing end-use \ncustomer load at a single electrical site that, prior to such incremental load, \ndid not previously meet the definition of Large Load. \n2. \nPJM Tariff Attachment DD-4, section IV(b)(iii) \nIn the event ([the amount of Capacity Resources committed for a given \nDelivery Year (as determined after the Third Incremental Auction) equals or \nexceeds the PJM Region Reliability Requirement determined prior to the \nThird Incremental Auction] divided by the Pool-wide Accredited UCAP \nFactor), then the Office of the Interconnection does not need any Eligible \nNew Large Loads to be available to provide Interim Resource Adequacy \nService for that Delivery Year."},{"page":9,"startToken":2231,"endToken":2604,"text":"9 \n3. \nThe FRR Capacity Rule:  RAA Schedule 8.1, section D.1.1 \nAn FRR Entity may not include in its FRR Capacity Plan any MW quantity \nof Existing Generation Capacity Resource27 in excess of what such FRR \nEntity owned or contracted by such FRR Entity prior to June 1, 2027, to serve \nNew Large Load. \nIV. \nCOMMENTS \nA. \nPJM Should Clarify that FRR Requirements Are Intended to Mirror \nthe RPM Requirement Such That When IRAS is Dormant, the FRR \nCapacity Rule is Also Dormant. \nThe IRAS Proposal provides a mechanism for IRAS to deactivate after three \nconsecutive years of sufficient capacity clearing the RPM auction, as described above in \nsection III.B.  PJM should clarify that the FRR Capacity Rule likewise deactivates when \nIRAS deactivates.  Since both the IRAS deactivation mechanism and the FRR Capacity \nRule hinge on the definition of New Large Load, it should be evident that the FRR Capacity \nRule is inactive when IRAS is inactive.  Nonetheless, an explicit clarification will ensure \nthat no future FRR load is subject to capacity restrictions above and beyond those for RPM \nload. \n \n27 See RAA, Article 1 – Definitions (defining Existing Generation Capacity Resource):   \n“Existing Generation Capacity Resource” shall mean, for purposes of the must-offer \nrequirement and mitigation of offers for any RPM Auction for a Delivery Year, a \nGeneration Capacity Resource that, as of the date on which bidding commences for such \nauction:  (a) is in service; or (b) is not yet in service, but has cleared any RPM Auction for \nany prior Delivery Year.  A Generation Capacity Resource shall be deemed to be in service \nif interconnection service has ever commenced (for resources located in the PJM Region), \nor if it is physically and electrically interconnected to an external Control Area and is in \nfull commercial operation (for resources not located in the PJM Region).  The additional \nmegawatts of a Generation Capacity Resource that is being, or has been, modified to \nincrease the number of megawatts of available installed capacity thereof shall not be \ndeemed to be an Existing Generation Capacity Resource until such time as those megawatts \n(a) are in service; or (b) are not yet in service, but have cleared any RPM Auction for any \nprior Delivery Year."},{"page":10,"startToken":2604,"endToken":2909,"text":"10 \nThe IRAS Proposal defines New Large Load as Large Load that goes into service \nafter June 1, 2027.  However, once system conditions are met such that IRAS is no longer \nnecessary, IRAS is deactivated.  When this happens, the definition of New Large Load \nbecomes Large Load that goes into service after June 1 of the next Delivery Year that PJM \nfaces capacity scarcity and IRAS must be reactivated.28  \nUnder the proposed FRR Capacity Rule, “An FRR Entity may not include in its \nFRR Capacity Plan any MW quantity of Existing Generation Capacity Resource in excess \nof what such FRR Entity owned or contracted by such FRR Entity prior to June 1, 2027, \nto serve New Large Load.”  The final clause “to serve New Large Load” clearly modifies \nthe entire sentence.  The inclusion of this phrase demonstrates that the FRR Capacity Rule \nshould be read to only apply to New Large Load as it is defined at that time.  Accordingly, \nwhen IRAS is inactive, no new load will meet the definition of New Large Load.  In this \ncircumstance, the FRR Capacity Rule would also effectively be inactive because there \nwould be no identifiable New Large Load for the rule to apply to.   \nAlthough it is possible to determine via the proposed PJM Tariff and RAA \namendment language that the FRR Capacity Rule is effectively dormant at the same time \nthat IRAS is dormant, the Commission should clarify that this is the case to avoid any \nconfusion in the future.  Without clarification that the FRR Capacity Rule goes dormant \nsimultaneous with IRAS, this aspect of the IRAS Proposal is unjust, unreasonable, and \nunduly discriminatory because it could be used to treat RPM load and FRR load differently \n \n28 See proposed definition of New Large Load; see proposed PJM Tariff, Attachment DD-4, section \nIV(b)(iii)."},{"page":11,"startToken":2909,"endToken":3185,"text":"11 \nwithout justification.  The FRR Capacity Rule, as described further below in section IV.B, \nis aimed at protecting the RPM market during periods of capacity scarcity in that market.  \nPJM does not explain why the rule would continue to apply to FRR when capacity is not \nscarce.  Accordingly, PJM should clarify that AEP’s understanding of the rule is correct or \nthe Commission should find the rule unjust and unreasonable and require PJM to modify \nit on compliance.   \nB. \nPJM Should Clarify that When the Relevant In-Service Date for the \nDefinition of New Large Load Resets, the Capacity Procurement \nDeadline under the FRR Capacity Rule Also Resets. \nThe fixed date of June 1, 2027 in the FRR Capacity Rule is inconsistent with the \nflexible in-service date in the proposed definition of New Large Load.  PJM should clarify \nthat when the in-service date for New Large Load resets, the procurement deadline for \nExisting Generation Capacity Resources under the FRR Capacity Rule likewise resets. \nPJM’s transmittal letter describes that the FRR Capacity Rule is proposed to ensure \nthat “FRR Entities (or their New Large Loads) bring new capacity to the system to meet \nthe New Large Loads’ resource adequacy needs, and precludes FRR Entities from \nsatisfying load growth from New Large Loads with existing Capacity Resources that could \npotentially be lured from the RPM Auctions (and further exacerbating the shortage \nconditions in the capacity market).”29  Thus, the rationale for the FRR Capacity Rule \nappears to be to establish an obligation for FRR Entities that parallels the IRAS Proposal’s \nincentives for RPM load to bring its own new capacity.   \n \n29 PJM Transmittal Letter at 73-74 (alteration in original)."},{"page":12,"startToken":3185,"endToken":3445,"text":"12 \nUnder the FRR Capacity Rule as drafted, however, an FRR Entity cannot use \nExisting Generation Capacity Resources that were procured after June 1, 2027 to serve \nNew Large Load even when IRAS goes dormant and then reactivates.  Thus, as written, \nthe FRR Capacity Rule creates a likely scenario where in future years, if IRAS reactivates \nafter a period of dormancy and the relevant in-service date for the definition of New Large \nLoad has been reset, FRR Entities are still restricted from using Existing Generation \nCapacity Resources to satisfy New Large Load capacity requirements unless those Existing \nGeneration Capacity Resources were procured prior to June 1, 2027.  This outcome is \ninconsistent with the intent of the IRAS rule and, if left unclarified, would put FRR Entities \nat a clear disadvantage to entities participating in the RPM.   \nAccordingly, PJM should clarify that if the in-service date for New Large Load \nresets to June 1 of a future year, the cutoff date for procuring Existing Generation Capacity \nResources under the FRR Capacity Rule also resets.  If the issue is not clarified, the IRAS \nProposal will be unjust, unreasonable and unduly discriminatory with respect to the FRR \nCapacity Rule.  It will restrict FRR Entities to a greater extent than it would restrict RPM \nload.  Furthermore, such an inconsistent approach would thwart the aligned, parallel \napproach to FRR and RPM large load capacity that PJM describes in its transmittal letter \nas the justification for the novel restriction on the historic ability of FRR Entities to plan \nholistically for the capacity needs of their loads."},{"page":13,"startToken":3445,"endToken":3779,"text":"13 \nC. \nPJM Should Clarify How FRR Entities Can Comply with Their \nObligations Under the FRR Capacity Rule After IRAS is Reactivated. \nPJM should clarify that an FRR Entity can comply with the FRR Capacity Rule \nduring years where IRAS is reactivated because the IRAS Proposal, as written, does not \nappear to provide sufficient notice for an FRR Entity to develop a compliant FRR Capacity \nPlan to provide for New Large Loads in reactivation years. \nUnder the IRAS Proposal, if IRAS goes dormant, the determination of whether \nIRAS reactivates in a future delivery year is made pursuant to outcome of the final RPM \nauction for that delivery year, the Third Incremental Auction.30  This auction occurs only \nthree to four months before the start of the delivery year.31  As described above in section \nIV.A, the mechanism for IRAS to go dormant and to reactivate is the definition of New \nLarge Load and, because the FRR Capacity Rule hinges on its applicability to New Large \nLoad, the FRR Capacity Rule should go dormant and reactivate at the same time as IRAS.32  \nThus, in a year where IRAS reactivates, the FRR Capacity Rule should also reactivate.   \nHowever, as drafted, the FRR Capacity Rule appears to leave FRR Entities with \nonly three to four months to ensure that their FRR Capacity Plan to serve New Large Load \ncomplies with the rule.  This timeline will be difficult, if not impossible, for FRR Entities \nto comply with because FRR Capacity Plans take years to develop.  FRR Entities must first \nsubmit their FRR Capacity Plan for a delivery year at least one month before the Base \n \n30 Proposed PJM Tariff, Attachment DD-4, section IV(b)(iii). \n31 PJM Interconnection, L.L.C., PJM Manual 18:  PJM Capacity Mkt., § 5.2, at 122 (rev. 62 Dec. 17, 2025), \nhttps://www.pjm.com/-/media/DotCom/documents/manuals/m18.ashx.  \n32 As explained in section IV.A, FERC should clarify that this is the correct interpretation of the IRAS \nProposal."},{"page":14,"startToken":3779,"endToken":4039,"text":"14 \nResidual Auction for that delivery year, which occurs three years before the delivery year \ncommences.33  The FRR Capacity Plan is then extended and updated annually.34  Compared \nto the usual multi-year timeline to develop an FRR Capacity Plan, three to four months is \nunrealistically short and would put FRR Entities at a severe disadvantage to RPM \ncustomers, who are able to comply with IRAS requirements on a shorter time frame.   \nRPM load can comply with the IRAS Proposal requirements on a short time frame \nbecause they can comply either by (1) bringing their own new capacity or Reliability \nBackstop Procurement capacity, or by (2) being subject to IRAS reductions.  FRR load, \nhowever, can only comply with the IRAS proposal by providing sufficient capacity, \nbecause FRR load is not subject to IRAS.  FRR Entities are therefore disadvantaged by \narbitrarily being placed in jeopardy of noncompliance as a result of the IRAS rules in \nreactivation years.  \nAlso, if the issue described in section IV.B above is not clarified and the FRR \nCapacity Rule restricts the use of Existing Generation Capacity Resources to only the \nresources procured before June 1, 2027, this will exacerbate the detrimental effects of the \nunreasonably short timeline for FRR Entities to develop a compliant FRR Capacity Plan, \nbecause they will be further restricted as to which capacity resources can be used to meet \nthe capacity requirements of New Large Load.  \n \n33 Proposed RAA, Schedule 8.1, section D.1; PJM Manual 18, § 5.2, at 121.  \n34 Proposed RAA, Schedule 8.1, section D.1."},{"page":15,"startToken":4039,"endToken":4374,"text":"15 \nTo address these time constraints, PJM should clarify that upon reactivation, there \nis a one-year delay for the FRR Capacity Rule.  For example:  assume the IRAS is dormant \nentering 2035 for the prior delivery year but the Third Incremental Auction that occurs in \nFebruary 2035 does not meet the conditions of Attachment DD-4, section IV(b)(iii) (i.e., \ndoes not clear sufficient capacity).  Under the IRAS Proposal, this would reactivate IRAS \nfor the upcoming 2035/2036 delivery year and the definition of New Large Load would \nemploy an in-service date of June 1, 2035.  Accordingly, under the IRAS Proposal, the \nFRR Capacity Rule would apply to New Large Load—that is, Large Load that goes into \nservice after June 1, 2035.  Thus, under the FRR Capacity Rule, an FRR Entity would not \nbe able to include in its FRR Capacity Plan any MW quantity of Existing Generation \nCapacity Resource in excess of what such FRR Entity owned or contracted by such FRR \nEntity prior to June 1, 2035, to serve New Large Load.35  This essentially gives the FRR \nEntity a short, three to four month period to contract with necessary supply to serve New \nLarge Load.  This is simply not a reasonable amount of time to do so and puts FRR at a \nsignificant disadvantage to the rest of the PJM market.  Accordingly, in this example, FRR \nEntities should not have to comply with the FRR Capacity Rule until the start of the \n2036/2037 delivery year, and should have an additional year to procure the necessary \nExisting Generation Capacity Resources to serve New Large Load.  This will provide \napproximately sixteen months for FRR Entities to develop a compliant capacity plan for \n \n35 This statement assumes the requested clarification in section IV.B is accepted and the cutoff date becomes \nflexible, no longer fixed at June 1, 2027, but that the cutoff date is the same date as the IRAS reactivation \ndate instead of providing a one-year delay as this section requests."},{"page":16,"startToken":4374,"endToken":4727,"text":"16 \nNew Large Load (which would still, in this example, be Large Load with an in-service date \nof June 1, 2035 or later).  The FRR Capacity Rule would restrict FRR Entities from using \nExisting Generation Capacity Resources that the FRR Entity procured after June 1, 2036, \nand would still provide the safeguards contemplated by the IRAS proposal at that time.  \nThus, upon reactivation, the FRR Capacity Rule would recognize that compliance with the \nrule reasonably requires more time than compliance with IRAS.  \n1. \nThis Issue Compounds if the FRR Capacity Rule Cutoff Date for \nExisting Generation Capacity Resources Remains Fixed at June \n1, 2027. \nIf the issue described in section IV.B above is not clarified, and the FRR Capacity \nRule restricts the use of Existing Generation Capacity Resources to only such resources \nprocured before June 1, 2027—even far into the future after a period of IRAS dormancy—\nthen an FRR Entity may have already included Existing Generation Capacity Resources in \ntheir FRR Capacity Plan before it is determined that IRAS is reactivating for the upcoming \ndelivery year.  During IRAS dormancy, an FRR Capacity Plan may be submitted prior to \nthe Base Residual Auction (three years prior to the delivery year),36 and such a plan may \nutilize Existing Generation Capacity Resource that the FRR Entity procured after June 1, \n2027 to fulfill the capacity requirements of upcoming Large Load additions that will, if \nIRAS is reactivated after the Third Incremental Auction, be deemed New Large Load.37  In \n \n36 PJM Manual 18 § 5.2, at 121. \n37 This also raises a potential conflict with the Takings Clause of the Fifth Amendment, because FRR \nEntities would be restricted from utilizing their investment in the Existing Generation Capacity Resources \nthey procured after June 1, 2027, with the reasonable expectation of using the procured capacity in their \nFRR Capacity Plan to serve upcoming large load additions.  The Takings Clause of the Fifth Amendment \nprovides that “private property [shall not] be taken for public use, without just compensation.”  Regulatory \ntakings occur where the government “imposes regulations that restrict an owner’s ability to use his own"},{"page":17,"startToken":4727,"endToken":4997,"text":"17 \nsuch a situation, the FRR Entity would be out of compliance with the FRR Capacity Rule \nas soon as IRAS (and the FRR Capacity Rule) is reactivated.  This is clearly not the intent \nof the IRAS proposal.  At a minimum, this issue should be addressed by clarifying the \nproposal is intended to operate as discussed in section IV.B and providing that FRR \nCapacity Rule’s cutoff date for procuring Existing Generation Capacity Resources resets \nalong with the in-service date for New Large Load. \n2. \nIf PJM does not clarify this issue, the IRAS Proposal is unjust \nand unreasonable. \nIf PJM does not clarify that FRR Entities can comply with the FRR Capacity Rule \nin delivery years where IRAS reactivates after a dormant period, the IRAS Proposal is \nunjust, unreasonable and unduly discriminatory because it places FRR Entities at a \nsignificant disadvantage, as discussed above.   \nV. \nCONCLUSION \nAEP respectfully requests that PJM clarify under its IRAS Proposal:  (1) that the \nFRR Capacity Rule will go dormant when IRAS goes dormant, (2) that the cutoff for \nprocuring Existing Generation Capacity Resources under the FRR Capacity Rule will reset \nwhen the New Large Load in-service date resets, and (3) that FRR Entities can comply \nwith the FRR Capacity Rule in years when the rule “reactivates” following a period of \nIRAS being dormant. \n \nproperty” but goes too far.  Cedar Point Nursery v. Hassid, 594 U.S. 139, 148 (2021).  A key consideration \nin evaluating whether a regulatory taking has occurred is the regulation’s interference with reasonable \ninvestment-backed expectations.  Penn Central Transportation Co. v. New York City, 438 U. S. 104, 124-\n125 (1982)."},{"page":18,"startToken":4997,"endToken":5054,"text":"18 \n \n \n \nJohn C. Crespo \nSenior Legal Counsel \nAmerican Electric Power Service \nCorporation \n1 Riverside Plaza \nColumbus, OH  43215 \n(614) 716-3727 \njccrespo@aep.com  \n \nRespectfully submitted, \n \n/s/ William M. Keyser \nWilliam M. Keyser \nMegan McDowell \nSteptoe LLP \n1330 Connecticut Avenue, NW \nWashington, DC  20036 \n202-429-8186 \nwkeyser@steptoe.com \nmmcdowell@steptoe.com  \n \nCounsel for AEP\n \n \nDated:  September 3, 2026"},{"page":19,"startToken":5054,"endToken":5125,"text":"19 \nCERTIFICATE OF SERVICE \n \nPursuant to Rule 2010, 18 C.F.R. § 385.2010, I hereby certify that I have this day \ncaused the foregoing document to be served upon each person designated on the official \nservice list compiled by the Secretary in this proceeding. \n \nDated at Washington, D.C. on this 3rd day of September, 2026. \n \n \n \n \n \n \n/s/ Jeannette Crooks \nJeannette Crooks \nSteptoe LLP \n1330 Connecticut Avenue, NW \nWashington, DC 20036"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":899,"startToken":0,"endToken":117},{"p":1,"at":899,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":4,"endAt":3,"startToken":117,"endToken":739},{"p":4,"at":3,"title":"II. CORRESPONDENCE AND COMMUNICATIONS","method":"printed heading","endPage":4,"endAt":521,"startToken":739,"endToken":810},{"p":4,"at":521,"title":"III. BACKGROUND","method":"printed heading","endPage":5,"endAt":841,"startToken":810,"endToken":1078},{"p":5,"at":841,"title":"B. IRAS","method":"printed heading","endPage":8,"endAt":3,"startToken":1078,"endToken":1859},{"p":8,"at":3,"title":"C. AEP’s Comments Focus on Three Proposed Amendments in the IRAS","method":"printed heading","endPage":9,"endAt":303,"startToken":1859,"endToken":2288},{"p":9,"at":303,"title":"IV. COMMENTS","method":"printed heading","endPage":9,"endAt":318,"startToken":2288,"endToken":2290},{"p":9,"at":318,"title":"A. PJM Should Clarify that FRR Requirements Are Intended to Mirror","method":"printed heading","endPage":11,"endAt":476,"startToken":2290,"endToken":2987},{"p":11,"at":476,"title":"B. PJM Should Clarify that When the Relevant In-Service Date for the","method":"printed heading","endPage":13,"endAt":4,"startToken":2987,"endToken":3446},{"p":13,"at":4,"title":"C. PJM Should Clarify How FRR Entities Can Comply with Their","method":"printed heading","endPage":17,"endAt":887,"startToken":3446,"endToken":4872},{"p":17,"at":887,"title":"V. CONCLUSION","method":"printed heading","endPage":19,"endAt":4,"startToken":4872,"endToken":5055},{"p":19,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":19,"endAt":441,"startToken":5055,"endToken":5125}]}