{"document":{"slug":"rec-20260903-5231","title":"Comments of the PJM Industrial Customer Coalition in response to the Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service…","issued":"2026-09-03","accession":"20260903-5231","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"PJM Industrial Customer Coalition","kind":"comments","file":"sources/filings/text/20260903-5231_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5231","tier":"record","sha256":"3ba7c5f8041b27cd0aa1cce98ea18d38ec81563fd01580f442dfca657c84815b","pages":16,"tokens":4550,"emptyPages":[],"textThemes":["registry","retail","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":252,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.  \n \n \n: \n \nDocket No. ER26-3515-000 \n \nCOMMENTS OF  \nTHE PJM INDUSTRIAL CUSTOMER COALITION \n \nThe PJM Industrial Customer Coalition (“PJMICC” or “Coalition”) respectfully submits \nthese Comments in response to the Proposal of PJM Interconnection, L.L.C. to Establish Interim \nResource Adequacy Service and A Large Load Registry to Address System Reliability (“IRAS \nFiling”), which was filed at the Federal Energy Regulatory Commission (“FERC” or \n“Commission”) in the above-referenced docket.1 PJMICC is a coalition of energy-intensive \nindustrial and institutional customers in the PJM Interconnection, L.L.C. (“PJM”) region and is \nactive in PJM’s governance and stakeholder processes.  \nAs energy-intensive retail customers, PJMICC’s members are directly and substantially \naffected by the rules governing the PJM grid and its markets, including PJM’s rules to \naccommodate new large load growth. In PJMICC’s view, the rules to accommodate new large load \ngrowth must be fair to existing customers but also crafted to support the economic growth of the \nregion. To that end, PJMICC offers the following Comments for Commission consideration. \nI. \nBACKGROUND \nOn August 13, 2026, PJM filed the IRAS Filing with the Commission. Also on August 13, \n2026, FERC issued a Combined Notice of Filings, setting a comment deadline of September 3, \n2026. PJMICC filed a doc-less Motion to Intervene on August 14, 2026.  \n \n1 PJM Interconnection L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry \nto Address System Reliability, Docket No. ER26-3515-000 (Aug. 13, 2026) (“IRAS Filing”)."},{"page":2,"startToken":252,"endToken":628,"text":"2 \n \nPJM’s IRAS Filing proposes revisions to the Reliability Assurance Agreement Among \nLoad Serving Entities (“RAA”) and the PJM Open Access Transmission Tariff (“Tariff”) to \nestablish the Interim Resource Adequacy Service (“IRAS”). PJM’s IRAS proposal broadly \nconsists of five parts. First, PJM proposes to clarify a Load Serving Entity’s (“LSE”) obligation to \nbring in new capacity that is equal to or greater than a New Large Load’s2 peak load, or else be \nsubject to load reduction requests during emergencies.3 Second, PJM seeks to create and maintain \na Large Load Registry that will list existing Large Loads on the system and New Large Loads that \nplan to interconnect in the future.4 Third, PJM proposes an IRAS product, which it describes as “a \nnew supplemental capacity product through which New Large Loads provide a load reduction \nservice” – put simply, IRAS is a curtailment tool for deployment by PJM to manage resource \nadequacy shortfalls “that would otherwise drive shedding of native loads.”5 Fourth, PJM proposes \nthe Bring Your Own New Capacity (“BYONC”) concept as a “category of new capacity eligible \nto address New Large Load capacity needs.”6 Specifically, BYONC is an incentive intended to \naddress new capacity needs by reducing a New Large Load’s potential IRAS requirement in \nlockstep with the new capacity the New Large Load secures itself. Finally, PJM proposes to \nexclude New Large Loads from the Variable Resource Requirement (“VRR”) Curve in future \nReliability Pricing Model (“RPM”) Auctions, to the extent they lack sufficient BYONC \nprovisions. PJM states that the “rest of PJM’s load should not be exposed to the price impacts \n \n2 New Large Load is defined, for purposes of the initial IRAS implementation, as “end-use customer load that is either \n(a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June 1, 2027, that \nincreases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not \npreviously meet the definition of Large Load.” IRAS Filing, Attachment A. If IRAS is activated in the future, the \ndefinition specifies different dates. \n3 IRAS Filing at 4. This load reduction request would occur prior to Pre-Emergency Load Management Response. \n4 Id. at 22. \n5 Id. \n6Id. at 23."},{"page":3,"startToken":628,"endToken":862,"text":"3 \n \ncaused by those New Large Loads’ procurement of their capacity needs through the RPM \nAuctions.”7 \nII. \nINTRODUCTION & EXECUTIVE SUMMARY \nPJMICC is a coalition representing industrial consumers, institutional customers, and other \nlarge electricity users in the PJM Region. Coalition member organizations require significant \nvolumes of electricity and natural gas to support their operations—they include manufacturers of \npaper, cement, chemicals, metals, pharmaceutical products, and consumer goods; institutional \ncustomers such as hospitals and universities; and other large energy users. Coalition members \nrepresent the backbone of American manufacturing and core services that support the United \nStates’ competitive strength in a global economy. They are anchor employers across the PJM \nRegion, supporting the regional economy with good-paying jobs and domestic production of goods \nand services. \nFor decades, PJMICC members and other similarly-situated retail customers have \ncontributed to system reliability and invested in resource adequacy by participation in PJM’s \ncapacity market, development of behind-the-meter generation, bilateral power purchase \nagreements, or supporting cost-of-service regulated generation. Many Coalition members have \nalso made long-term investments in their on-site electrical infrastructure, strengthening the grid. \nHowever, PJMICC is concerned that large retail customers who have contributed to resource \nadequacy for many years may be required to bear costs triggered by the rapid growth of new large-\nload customers. For American industry, institutions, and other traditional energy users to thrive, \ntheir costs must be just, reasonable, and consistent with cost-causation principles. \n \n7 Id."},{"page":4,"startToken":862,"endToken":1324,"text":"4 \n \nTo that end, the Coalition responds to the IRAS Filing with these Comments. Its \nrecommendations can be summarized as follows: \n First, existing large loads should be excluded from the Large Load Registry. The \nregistry’s purpose is to track new large loads driving new system costs, not existing \ncustomers already integrated into the grid and reflected in historical forecasts. If existing \nloads are included for informational purposes, they must be clearly exempted from all \nIRAS operational obligations — including curtailment, BYONC requirements, and RPM \nauction adjustments — and any collected data must be subject to robust confidentiality \nprotections. \n Second, ordinary load fluctuations should not subject existing customers to IRAS. \nPJM’s definition of “new” vs. “existing” Large Load must distinguish between genuine \nnew load growth and normal operational variation at existing facilities. The baseline \nmeasurement should not confuse normal business operational fluctuations as being new \nload growth associated with business expansions, triggering IRAS for customers that have \neffectively been operating as existing Large Loads.  \n Third, incremental expansions should trigger IRAS obligations only for the net new \nMW above 50 MW. As a threshold matter, it must be noted that very little evidence has \nbeen presented that 50 MW is an appropriate bright-line trigger for the obligations set forth \nby PJM’s instant filing.  Many of the new computational loads are significantly in excess \nof 50 MW, whereas 50 MW is not unusual for an industrial or institutional facility.  When \nan existing Large Load facility expands, only load growth over 50 MW from the baseline \nshould be subject to IRAS. (That is, a 50 MW facility should not be subjected to IRAS \nuntil it expands beyond 100 MW.) PJM should adopt bright-line, easy-to-implement \ngrandfathering rules for pre-expansion load, clear methodologies for measuring \nincremental growth, and anti-gaming provisions, while avoiding a framework that chills \nlegitimate phased and planned development. \n Fourth, IRAS participants should not receive compensation that shifts costs to other \nratepayers. Compensating new large loads for IRAS curtailment — and recovering those \ncosts broadly through retail rates — directly contradicts the Ratepayer Protection Pledge’s \ncommitment that new computational loads will not increase electricity costs for other \nconsumers. If any compensation is provided, it should be funded by the new large-load \ncustomer base itself; States must retain full discretion to set the rate at zero without risking \na violation of the filed rate doctrine. \n Finally, PJM’s “peak load” measurement in the New Large Load definition should \nalign with FERC-approved retail BTMG rules. Load netted against on-site generation \nunder BTMG should be measured in a similar manner for IRAS purposes, providing \ncertainty to retail customers who have invested in resource adequacy through retail BTMG. \n \nPJMICC respectfully requests that the Commission consider these Comments in its review \nof the IRAS Filing. Each of these points is set forth in greater detail below."},{"page":5,"startToken":1324,"endToken":1659,"text":"5 \n \nIII. \nCOMMENTS \nA. \nExisting Large Loads Should Be Excluded from the Large Load Registry. \nPJM explains in the IRAS Filing that the Large Load Registry (“Registry”) will contain \ninformation about Large Loads in the PJM Region that will “facilitate the transparent \nimplementation of IRAS and assist the Commission and states in monitoring whether loads are, in \nfact adhering to the Ratepayer Protection Pledge (“Pledge”) commitment to ‘build, bring, or buy \nthe new generation resources and electricity needed to satisfy their new energy demands.’”8 \nSpecifically, PJM will use the Large Load Registry to identify and quantify New Large Loads by \nzone or area and “allocate IRAS responsibility to each zone/area accordingly,” beginning with the \nDelivery Year starting June 1, 2027.9 \nPJMICC does not object to the need to track New Large Loads with IRAS responsibility. \nHowever, PJMICC disagrees with PJM’s decision to place all Large Loads—including Existing \nLarge Loads—into the Registry, for the following reasons.  \ni. First, the Primary Purpose of the Registry Is To Facilitate IRAS, Which \nDoes Not Apply to Existing Large Loads. \nExisting users, including large industrial and commercial users, have historically paid for \nthe generation, transmission, and distribution infrastructure they use. Existing large users are not \nthe source of the new costs driving the need for IRAS and, by extension, a Large Load Registry. \nThis cost causation principle, which is a foundational element of utility rate design, requires that \ncosts be allocated to the customers who cause them. Existing large retail customers are not driving \nnew infrastructure costs and should not be subjected to new tracking and potential curtailment \n \n8 IRAS Filing at 28 (quoting The White House, Ratepayer Protection Pledge (Mar. 4, 2026), available at \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/). PJM further notes that “‘add[ing] more \ncapacity that serves the broader public by increasing supply’ in order to protect ‘Americans from higher prices’” is \npart of the commitment of the Pledge. Id. (quoting Ratepayer Protection Pledge). \n9 IRAS Filing at 28-29."},{"page":6,"startToken":1659,"endToken":1949,"text":"6 \n \nobligations designed to address the consequences of new entrants seeking service before they can \nbe reliably accommodated. Therefore, existing large users should not be subject to exposure on \nthe proposed Large Load Registry. \nii. The Large Load Registry Imposes New Privacy Concerns Upon Existing \nLarge Load Customers, Without Adequate Justification. \nThe Large Load Registry proposes collecting substantial operational data, raising new \nprivacy concerns for existing customers who should not be subject to the IRAS. Data such as \ncustomer identity, location, in-service date, delivery point, load quantity, and backup generation \ndetails represent confidential information that existing customers have never been required to \nreport in this manner. For energy-intensive industries, such as steel, air separation, paper, and \nconsumer goods manufacturers, knowledge of load size, location, Demand Response (“DR”) \nparticipation, and LSE relationships enables competitors (including international competitors) to \ninfer critical operational intelligence. For example, publicly disclosing which DR programs a steel \nmill participates in would provide competitors with insights into its operations and cost structure. \nFurther, in restructured states, a customer’s supplier relationship is typically confidential, and \npublic disclosure of retail customers’ LSEs could affect the functioning of retail markets.  \nState-regulated utilities—with whom large retail customers have a direct relationship—\nalready have much or all of this information, but it is often subject to state confidentiality rules. \nThese customers’ local utilities understand the critical sensitivity of this information. It is carefully \nguarded by American industry. \nWhile PJM may argue that including existing loads helps improve overall forecast \naccuracy, the forecasting problem driving this initiative is new load growth, not existing load that \nis already captured in historical data. To the extent that existing loads are included for \ninformational purposes, the Commission should require PJM to limit the information collected to"},{"page":7,"startToken":1949,"endToken":2250,"text":"7 \n \nwhat is necessary for loads that are not subject to IRAS. Additionally, non-IRAS load should be \nclearly exempted from any operational obligations tied to the Registry, including IRAS curtailment \npriorities, BYONC requirements, and RPM auction demand curve adjustments. \niii. Additional Substantive and Due Process Protections Are Needed If Existing \nLarge Loads Are Included in the Registry.  \nPJMICC firmly argues that under no circumstances should existing Large Loads be subject \nto IRAS curtailment obligations, which, by PJM’s own design, apply only to New Large Loads \nthat do not bring their own capacity. However, the Registry, as proposed, does not contain \nprovisions that ensure IRAS load is not conflated with existing load. If Existing Large Loads are \nincluded in the Registry, the Commission should require PJM to incorporate additional \nclassification or disclosures within the Registry to ensure that IRAS is not assigned to loads that \nare merely experiencing year-over-year normal operation fluctuations. Additionally, Registry \ndeterminations, as currently proposed, lack clear customer notice, correction, and appeal \nprocedures. Per the filing, PJM may validate information with Transmission Owners and Electric \nDistributors, request additional information, and “consult” with the Large Load, but the Tariff does \nnot establish a customer right to notice, review, correction, hearing, or appeal before classification \nand eligible New Large Load amounts become operative. Unremedied errors concerning peak \nload, in-service date, affiliation, site boundaries, BYONC, or Reliability Backstop Procurement \n(“RBP”) allocation can directly change curtailment exposure and capacity treatment. The IRAS \nFiling also invokes significant enforcement consequences for false or incomplete information \nwithout providing a corresponding safe harbor for good faith estimates or corrections. This is \nconcerning for existing customers, some of whom operate complex configurations with multiple \nfacilities, generation integrated with industrial processes, and other nuances that may make \nreporting obligations less than straightforward. Any such process should also minimize the"},{"page":8,"startToken":2250,"endToken":2507,"text":"8 \n \ncompliance risks for retail customers that are otherwise, in many cases, not directly involved in \nthe PJM wholesale market. \nFurther, any Registry data collected from existing customers must be subject to robust \nconfidentiality protection. The Registry may include site descriptions, locations, in-service \nschedules, peak loads, telemetry, backup generation and permitting limits, contracts or service \nagreements, and contact information. As explained above, this is highly sensitive competitive \nintelligence for many retail customers. Additionally, the disclosure of this information creates \ncybersecurity and commercial information risks. While the Registry is intended to administer \nIRAS transparently, it must not pose operational or competitive risks due to inadequate \nconfidentiality safeguards. PJMICC respectfully requests that the Commission require PJM to \nimplement appropriate safeguards, privacy restrictions, due process, and, for non-IRAS load, limit \nthe amount of data required for the Registry.  \nB. \nOrdinary Load Fluctuations Should Not Subject Existing Retail Customers to \nIRAS. \nAs PJM states in the IRAS Filing, IRAS is designed as a “supplemental capacity product \nthrough which New Large Loads provide a load reduction service.”10 PJM drafted the IRAS Filing, \nincluding the proposed definition of New Large Load, to address resource adequacy challenges on \nthe grid primarily driven by large load growth.  \nPJMICC agrees with the focus on new and expanding load (to the extent not otherwise \nconsidered to be “organic” load growth). However, the Coalition is concerned that, under the \nproposed definition of New Large Load, existing Large Load customers may be mistakenly \ndeemed New Large Load solely due to ordinary load fluctuations.  \n \n10 IRAS Filing at 22."},{"page":9,"startToken":2507,"endToken":2838,"text":"9 \n \nOrdinary load fluctuations can occur for a manufacturer, for example, during a slower \nproduction year or when weather patterns are milder than usual. To use a simple illustration, \nconsider a customer facility whose peak load this Delivery Year is 48 MW but whose peak load \nwas 54 MW in the prior two Delivery Years. If, in the next Delivery Year, this customer’s peak \nload returns to 54 MW, PJM may deem it to have 6 MW of load growth. Under the New Large \nLoad definition, it is unclear if PJM would deem the entire facility as “New Large Load” or only \na part of it. Either way, the customer facility is merely returning to its typical historical levels after \na slow business cycle year (such as after COVID). It would not make sense to impose 6 MW (or \n54 MW, if PJM fails to recognize only the incremental increase) of IRAS and Registry obligations \non a customer facility that has been paying to support resource adequacy for years, if not decades. \nThis is an important issue for several reasons. First, the point of IRAS is not to burden \nexisting customers – even existing Large Load customers – with issues that are caused by rapid \nnew load growth. Second, it is important to be clear as to the rules of the road, so energy-intensive \nbusinesses can continue to do the work it does every day without worrying about triggering \nadditional obligations (that are designed to accommodate the new, super-sized large load growth). \nThird, incremental modernization or electrification at facilities should not create new obligations \nfor existing loads. \nTo address this issue, PJMICC offers the following recommendation: the Commission \nshould require PJM to establish a “baseline” load value for existing Large Load customers based \non historic usage.  Any value established for a customer should accommodate, if not facilitate, \nexisting Large Load customers’ ability to respond to changing grid and resource adequacy \nconditions, such as, for example, moving away from “peak management” strategies toward new"},{"page":10,"startToken":2838,"endToken":3166,"text":"10 \n \n“Demand Response” offerings. Additionally, PJM should allow an existing retail customer to \ndemonstrate to PJM that load growth is actually a normal fluctuation. \nC. \nIncremental Expansions Should Trigger IRAS Obligations Only for the Net \nNew MW Above 50 MW. \nAnother concern for existing industrial and institutional customers is what the process \nlooks like for incremental load growth—for example, when a university adds a new building or a \nfactory adds a production line.  \nCurrently, the proposed definition of New Large Load includes (a) “a Large Load that goes \ninto service after June 1, 2027” or (b) “incremental load in-service after June 1, 2027, that increases \nthe existing end-use customer load at a single electrical site, that, prior to such incremental load, \ndid not previously meet the definition of Large Load.” Presumably, this would mean that a 45 MW \nfacility that undergoes a 10 MW expansion would be deemed New Large Load.  \nThis approach fundamentally puts existing large loads at a competitive disadvantage. If a \nnew facility can be built at 20 MW without triggering IRAS obligations, surely a 50 MW facility \nthat has been paying into the system for decades should be able to expand to 70 MW (an equivalent \n20 MW update) on a similar basis. To obligate the latter to IRAS, but not the former, would be \nunduly discriminatory against existing customers.  \nUnfortunately, PJM’s proposal does not clearly address how such incremental expansions \nshould be treated. First, as a threshold matter, PJM must be clear that only incremental expansion \nshould be classified as New Large Load. The proposed definition of New Large Load includes \n“incremental load in-service after June 1, 2027, that increases the existing end-use customer load \nat a single electrical site that, prior to such incremental load, did not previously meet the definition \nof Large Load.” While this appears to address incremental growth of existing retail customers \nwhose “baseline” is under 50 MW and that then expand, the definition does not expressly address"},{"page":11,"startToken":3166,"endToken":3492,"text":"11 \n \nsituations where an existing Large Load (already >50 MW) expands. PJM should calculate a \n“baseline” peak load (as discussed above) for each Large Load so that it is clear when there has \nbeen real growth at a customer location and should then explain that only the incremental MW \nbecomes “New Large Load.”  \nSecond, the Commission should order PJM to require that, for existing Large Load \ncustomers, only the incremental growth above and beyond 50 MW of net new load should be \nclassified as new load. This approach is the clearest and least discriminatory, as it avoids putting \nexisting retail customers who have paid for capacity at a competitive disadvantage. Without \nclarification that an existing facility may add up to 50 MW of expansion without triggering IRAS \nobligations, there is a distinct risk of chilling legitimate expansions. Treating the entire facility as \na New Large Load upon expansion could discourage rational, phased development at existing \nfacilities. \nIn summary, PJM should establish clear rules for phased expansions, including the \nfollowing: \n A methodology for measuring both “baseline” peak load and incremental load growth at \nexisting facilities. \n A bright-line rule that the pre-expansion load quantity is grandfathered and not subject to \nIRAS. The load would be treated as a New Large Load only after 50 MW is added to the \ncustomer’s baseline load. \n Provisions addressing the timing of registration obligations for expansions (i.e., \nregistration should be required only when the incremental expansion is contracted or \ncommitted, not when the original facility was interconnected). Additionally, PJM should \naddress the potential for gaming (e.g., a customer structuring multiple sub-50 MW facilities \nwithin a one-mile radius to avoid the threshold) while still protecting legitimate existing \nmultiple sub-50 MW operations within one-mile from being swept into the Large Load \nframework. \nThese updates to PJM’s proposal would provide significant protections for existing retail \ncustomers and avoid stifling economic investment by American manufacturing, education and \nmedical institutions, and other existing large retail customers."},{"page":12,"startToken":3492,"endToken":3776,"text":"12 \n \nD. \nIRAS Participants Should Not Receive Compensation That Shifts Costs to \nOther Ratepayers \nPJM proposes that New Large Loads subject to IRAS curtailment during grid emergencies \nwould receive wholesale compensation at a maximum rate equal to 50% of the Non-Performance \nCharge Rate.11 PJM also proposes that Large Loads may waive such compensation consistent with \nany Large Loads’ signing of the Pledge.12 \nPJM does not propose a specific cost recovery mechanism for IRAS compensation, stating \nthat cost recovery “will be left to the Electric Distributors that directed the specific load reductions \nto implement IRAS, consistent with their state-approved program.”13 PJM states that “[w]hether a \nspecific New Large Load may be entitled to compensation for provision of IRAS will be \ndetermined by state authorities under state law….”14 \nUnfortunately, PJM’s approach is flawed. By establishing a FERC-jurisdictional payment \nobligation to IRAS load, PJM creates tensions with the Pledge and the filed rate doctrine and will \nmake it particularly difficult for States to protect existing customers from having to pay IRAS \ncustomers for their reductions. \ni. PJM’s Proposed Compensation Is Inconsistent with the Ratepayer \nProtection Pledge. \nThe Ratepayer Protection Pledge (“Pledge”) Proclamation, issued by the President on \nMarch 4, 2026, provides that “data centers’ energy needs will not increase household electricity \ncosts for American citizens” and that data center companies “will build, bring, or buy the new \ngeneration resources and electricity needed to satisfy their energy demands, and pay for all new \npower delivery infrastructure upgrades.”15 The Pledge itself states that “Companies will build, \n \n11 IRAS Filing at 102. \n12 Id. at 17, 102. \n13 Id. at 106. \n14 Id. \n15 Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026)."},{"page":13,"startToken":3776,"endToken":4095,"text":"13 \n \nbring, or buy the new generation resources and electricity needed to satisfy their new energy \ndemands, paying the full cost of those resources whether by building, or buying from, new or \notherwise additive power plants.”16 \nAt heart, the Pledge’s commitment is to consumer protection. The Pledge contemplates \nthat data centers bear their own costs, not receive payments from the system after failing to bring \ntheir own capacity. The Pledge’s framework is premised on data centers paying their own way. If \nnew data center loads that do not bring their own capacity receive IRAS compensation recovered \nthrough retail rates, that cost is shifted to other ratepayers—directly contradicting the Pledge’s \ncommitment that data centers will not increase electricity costs for other consumers. In fact, the \nrisk that these costs are shifted to large retail, industrial, and institutional customers is heightened, \nbecause many States are focused primarily on preventing cost shifts to residential customers. \nHowever, curtailment of IRAS load should not be compensated by other ratepayers (whether \nresidential, small commercial, or industrial/institutional); rather, it is the condition upon which a \nNew Large Load can begin taking service sooner without bringing matching capacity to the \nsystem.  \nii. PJM’s Approach to IRAS Compensation Creates Filed Rate Doctrine and \nConsumer Protection Risks for States. \nOnce FERC approves a wholesale rate—such as the maximum IRAS compensation rate—\nit is difficult for States to set rates inconsistent with FERC-jurisdictional rates. As a legal matter, \nStates may not undermine FERC-jurisdictional rates.17 However, States are also limited, as a \npractical matter of rate setting, in allocating rates in a manner inconsistent with the underlying \n \n16 The White House, Ratepayer Protection Pledge (Mar. 4, 2026), available at \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.  \n17 See, e.g., Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953 (1986); Mississippi Power & Light Co. v. \nMississippi ex rel. Moore, 487 U.S. 354 (1988)."},{"page":14,"startToken":4095,"endToken":4382,"text":"14 \n \nwholesale costs. Consequently, if FERC approves a maximum wholesale compensation rate for \nIRAS, states may be constrained in their ability to decline to pass through those costs or to set \nretail rates that nullify the compensation. Although PJM characterizes IRAS compensation as \nsubject to state discretion, a FERC-approved wholesale rate may create a federal floor that states \ncannot easily undercut. Additionally, this creates tension with state consumer protection efforts. A \nFERC-approved IRAS compensation rate could interfere with these state-level consumer \nprotection measures.  Acknowledging the exigent circumstances that exist, PJMICC offers that a \nreasonable alternative may be for PJM’s Tariff to remain silent on IRAS compensation and allow \nstates to consider programmatic approaches to compensation for any IRAS curtailments.   \nE. \nPJM’s Definition of New Large Load Should Track with PJM’s BTMG Rules. \nIn the IRAS Filing, PJM mentions co-located load, but it does not explain how Behind-\nthe-Meter Generation (“BTMG”) rules interact with IRAS obligations.18 In PJM’s Co-Located \nLoad proceeding before the FERC, the Commission has ordered PJM to maintain Behind-the-\nMeter Generation (“BTMG”) rules for retail BTMG up to 50 MW.19 The Commission should \nrequire PJM to clarify that its measurement of “peak load” in the proposed definition of New \nLarge Load should track with retail BTMG rules approved by the Commission. For example, if \nan 80 MW load with 50 MW of generation is tagged at 30 MW pursuant to retail BTMG rules, it \nshould be considered 30 MW for purposes of IRAS, as well. This approach will provide certainty \nand consistency to retail customers who have invested in resource adequacy through retail \nBTMG. \n \n \n \n \n18 See IRAS Filing at 36. \n19 195 FERC ¶ 61,209 (Order entered Jun. 18, 2026) at PP 207-220."},{"page":15,"startToken":4382,"endToken":4483,"text":"15 \n \nIV. \nCONCLUSION \nPJMICC respectfully urges the Commission to require PJM to implement the safeguards \nand clarifications described above in its IRAS proposal. These measures would go a long way to \nensuring the IRAS program is just and reasonable and that existing retail customers are protected, \nconsistent with the Ratepayer Protection Pledge. \nRespectfully submitted, \nBy: \n/s/ Susan E. Bruce \n \n \n \nSusan E. Bruce \nKenneth R. Stark \nMatthew L. Garber \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: sbruce@mcneeslaw.com \n \n kstark@mcneeslaw.com \n \n mgarber@mcneeslaw.com \n \nCounsel to the PJM Industrial Customer Coalition \n \nDated: September 3, 2026"},{"page":16,"startToken":4483,"endToken":4550,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served, via first-class mail, electronic transmission, or \nhand-delivery, the foregoing upon each person designated on the official service list compiled by \nthe Secretary in this proceeding. \n \nDated this 3rd day of September, 2026. \n \n/s/ Susan E. Bruce \n \n \n \nSusan E. Bruce \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: sbruce@mcneeslaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1241,"startToken":0,"endToken":177},{"p":1,"at":1241,"title":"I. BACKGROUND","method":"printed heading","endPage":3,"endAt":104,"startToken":177,"endToken":645},{"p":3,"at":104,"title":"II. INTRODUCTION & EXECUTIVE SUMMARY","method":"printed heading","endPage":5,"endAt":5,"startToken":645,"endToken":1325},{"p":5,"at":5,"title":"III. COMMENTS","method":"printed heading","endPage":5,"endAt":21,"startToken":1325,"endToken":1327},{"p":5,"at":21,"title":"A. Existing Large Loads Should Be Excluded from the Large Load Registry.","method":"printed heading","endPage":8,"endAt":1028,"startToken":1327,"endToken":2385},{"p":8,"at":1028,"title":"B. Ordinary Load Fluctuations Should Not Subject Existing Retail Customers to","method":"printed heading","endPage":10,"endAt":169,"startToken":2385,"endToken":2862},{"p":10,"at":169,"title":"C. Incremental Expansions Should Trigger IRAS Obligations Only for the Net","method":"printed heading","endPage":12,"endAt":6,"startToken":2862,"endToken":3493},{"p":12,"at":6,"title":"D. IRAS Participants Should Not Receive Compensation That Shifts Costs to","method":"printed heading","endPage":14,"endAt":858,"startToken":3493,"endToken":4214},{"p":14,"at":858,"title":"E. PJM’s Definition of New Large Load Should Track with PJM’s BTMG Rules.","method":"printed heading","endPage":15,"endAt":6,"startToken":4214,"endToken":4383},{"p":15,"at":6,"title":"IV. CONCLUSION","method":"printed heading","endPage":16,"endAt":0,"startToken":4383,"endToken":4483},{"p":16,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":16,"endAt":461,"startToken":4483,"endToken":4550}]}