{"document":{"slug":"rec-20260903-5232","title":"Motion to Intervene and Comments of Appalachian Voices in support of PJM Interconnection, L.L.C.’s proposed revisions to Reliability Assurance Agreement…","issued":"2026-09-03","accession":"20260903-5232","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Appalachian Voices","kind":"comments","file":"sources/filings/text/20260903-5232_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5232","tier":"record","sha256":"18281543087275f4ef767582111200b766e5cf26fdce6a662a1cd45dbaca8753","pages":14,"tokens":4187,"emptyPages":[],"textThemes":["adequacy","retail","registry"]},"pages":[{"page":1,"startToken":0,"endToken":273,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.  \n)  \nDocket No. ER26-3515-000  \n \nMOTION TO INTERVENE AND COMMENTS \nOF APPALACHIAN VOICES \n \nPursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (the \nCommission) Rules of Practice and Procedure,1 Appalachian Voices submits this motion to \nintervene and comments supporting PJM Interconnection, L.L.C.’s (PJM) proposed revisions to \nits Reliability Assurance Agreement Among Load Serving Entities and the PJM Open Access \nTransmission Tariff to establish Interim Resource Adequacy Service (IRAS), filed on August 13, \n2026, in the above-captioned proceeding (IRAS Proposal).2   \nPJM’s IRAS Proposal is an ambitious, yet narrowly tailored solution to address the \nprimary issue facing the region:  the outsized and unprecedent development of large loads and \nthe unsustainable bill impacts they have created for residential ratepayers.  Appalachian Voices \njoined the Limited Protest of Public Interest Organizations—which supports PJM’s proposal \nwith four modifications—yet writes separately to highlight the IRAS Proposal’s impact on \nVirginia, the birthplace of the data center boom, and address associated legal issues under the \nFederal Power Act.  By applying only to Load Serving Entities serving New Large Loads, whose \nsize and operational attributes create unique concerns for the bulk transmission system and \nresource adequacy, PJM’s IRAS Proposal does not unduly discriminate.  Nor does it \ninappropriately cross jurisdictional lines, but will instead complement efforts already underway \nto address large load integration in Virginia.  \n \n1 18 C.F.R. §§ 385.212, 385.214 (2025).  \n2 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry \nto Address System Reliability (filed Aug. 13, 2026) (IRAS Proposal)."},{"page":2,"startToken":273,"endToken":537,"text":"2 \n \nI. \nMOTION TO INTERVENE  \nAppalachian Voices moves to intervene in this proceeding.  Appalachian Voices is a non-\nprofit organization dedicated to bringing people together to protect the land, air, and water of \nCentral and Southern Appalachia and advance a just transition to an equitable clean energy \neconomy.  Appalachian Voices strives to shift to clean, 21st-century energy sources, including \nenergy efficiency and low-emitting power sources, and stand up to monopoly utility practices \nthat put profits over people.  Its ultimate goal is to establish economic solutions that create \ncommunity wealth and sustain Appalachia’s mountains, forests, and waters.  \nAppalachian Voices has a substantial number of dues-paying members living in the PJM \nfootprint, primarily in Virginia and North Carolina.  The outcome of this proceeding will impact \nthe reliability of PJM’s system during constrained periods, the procurement of generation to \nsupply large loads, and capacity costs that feed into retail rates.  Accordingly, Appalachian \nVoices has a substantial interest in this proceeding that cannot be adequately represented by any \nother party.  Further, by virtue of its organizational mission, Appalachian Voices’ participation in \nthis proceeding is in the public interest.  Pursuant to Rule 214 of the Commission’s Rules of \nPractice and Procedure,3 Appalachian Voices respectfully requests that the Commission grant it \nfull rights associated with party status in this proceeding.   \nII. \nCOMMENTS  \nA. The Commission Should Accept PJM’s IRAS Proposal to Help Ensure that New \nLarge Loads Pay their Fair Share of Capacity Costs and Bear Appropriate \nReliability Burdens. \n \n1. The IRAS Proposal Can Enable More Equitable Cost Allocation for Virginia \nRatepayers. \n \n \n3 18 C.F.R. § 385.214."},{"page":3,"startToken":537,"endToken":993,"text":"3 \n \nVirginia originated the data center boom and remains its epicenter.  As of late 2024, it \nwas home to thirteen percent of global data center capacity and twenty-five percent of data \ncenter capacity in the Americas.4  This trend only projects to accelerate.5  The heavy \nconcentration of data center load in the state places significant demand on its electric grid.  \nDominion Energy Virginia (Dominion), a vertically integrated utility and PJM Transmission \nOwner, has asserted that “no other utility in the country has the magnitude of high load demand \nthat Virginia is facing.”6  The utility has argued that the “scale, density of data center \ndevelopment, and load that [Dominion] must support significantly outpace[s]” other markets, \nmaking it a “uniquely concentrated and capital-intensive environment.”7  State and federal \npolicies are only just now starting to catch up to the drastic changes that data centers have \nimposed on the state’s electric power system.     \nTraditional approaches to wholesale and retail cost allocation have had the effect of \nsocializing the cost of procuring capacity for large loads across the broader customer base.  As a \nvertically integrated utility subject to state integrated resource planning requirements, Dominion \nowns or contracts for the majority of the generating capacity needed to meet its native load \nrequirements, including New Large Load customers.8  It procures the remaining increment that it \n \n4 Joint Legislative Audit and Review Commission, Report to the Governor and the General Assembly of Virginia \nData Centers in Virginia, at 1 (2024), https://rga.lis.virginia.gov/Published/2025/RD206/PDF.  \n5 PJM Interconnection, L.L.C., Total Demand Request for Large Load Adjustment, “2026 DEMAND Requests” Tab \nat cells E36, I36, https://www.pjm.com/-/media/DotCom/committees-\ngroups/subcommittees/las/2025/20250916/20250916-post-meeting---informational-only---large-load-adjustment-\nrequests.xlsx (showing requested large load adjustments to PJM load forecast of Load Serving Entities in the DOM \nZone of 7,219.6 MW for 2026, which more than doubles to 14,604.4 MW for 2030); PJM Interconnection, L.L.C., \n2026 PJM Load Forecast Report, at 34 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-\nnotices/load-forecast/2026-load-report.pdf (showing updated load forecast for DOM zone through 2045). \n6 Rebuttal Testimony of J. Scott Gaskill, Va. State Corp. Comm’n, Case No. PUR-2025-00058, at 17:3-4 (filed Sept. \n10, 2025), https://www.scc.virginia.gov/docketsearch/DOCS/88v001!.PDF.  \n7 Rebuttal Testimony of Stan Blackwell, Va. State Corp. Comm’n, Case No. PUR-2025-00058, at 24:6-10 (filed \nSept. 11, 2025), https://www.scc.virginia.gov/docketsearch/DOCS/88v301!.PDF.  \n8 Direct Testimony of William A. Coyle, Va. State Corp. Comm’n, Case No. PUR-2025-00058, at 4:5-12 (filed Mar. \n31, 2025), https://www.scc.virginia.gov/docketsearch/DOCS/84s901!.PDF (Coyle Test.)."},{"page":4,"startToken":993,"endToken":1337,"text":"4 \n \ncannot self-supply from PJM’s Base Residual Auction (BRA).9  While this arrangement may act \nas a hedge against BRA clearing prices for most of Dominion’s capacity requirements, \nDominion’s retail customers still must cover the capital costs of Dominion’s generation holdings \nthrough base retail rates.  And as Dominion pursues significant buildout of new generating \ncapacity to meet its burgeoning large load growth,10 residential customers will necessarily bear \nthe cost burden of those new facilities.  Further, as described below, BRA clearing prices have \nskyrocketed in recent years due to large load growth, particularly in the DOM zone that covers \nDominion’s territory.11  When Dominion does not have sufficient self-supply capacity to serve \nits native load, that load must pay the BRA prices associated with covering the shortfall.12 \nThe IRAS Proposal could help to alleviate these cost burdens on Virginia ratepayers in at \nleast three ways.   \nFirst, by requiring Load Serving Entities to “bring new capacity in an amount that equals \nor exceeds its New Large Loads’ peak load or be subject to load reduction requests,”13 the IRAS \nProposal dictates that Dominion procure capacity dedicated to serving discrete New Large \nLoads.  Absent explicit matching of this new capacity with one or more New Large Loads, \nDominion’s load will face curtailment exposure.  This connect-the-dots requirement will enable \nthe Virginia State Corporation Commission (SCC) to identify generation capacity costs caused \nby New Large Loads and allocate those costs accordingly.  In other words, the IRAS Proposal \nshould prevent Dominion from continuing to commingle capacity costs caused by New Large \n \n9 See id. \n10 See Shannon Heckt, “Dominion long-range projections show major energy growth, what it takes to fully comply \nwith VCEA,” Virginia Mercury, (Oct. 22, 2025), https://virginiamercury.com/2025/10/22/dominion-long-range-\nprojections-show-major-energy-growth-what-it-takes-to-fully-comply-with-vcea/.  \n11 See Coyle Test. at 7:16-8:8:9 (describing BRA clearing prices in DOM zone before application of price collar, \nDominion’s then net-short capacity status, and an expected $202 million in BRA capacity costs to customers for the \n2025/2026 delivery year). \n12 See id. \n13 IRAS Proposal, Transmittal at 3-4."},{"page":5,"startToken":1337,"endToken":1664,"text":"5 \n \nLoads in the same rate base that underlies residential customer rates, thereby protecting those \ncustomers from bearing such costs.   \nSecond, the IRAS Proposal creates a Large Load Registry that will provide the SCC and \nother regulatory entities greater visibility into the New Large Loads seeking service in a given \nElectric Distributor footprint.14  The Large Load Registry will identify, among other things, the \nspecific Bring Your Own New Capacity associated with the New Large Load.15  This will \nsimilarly provide the transparency needed to appropriately allocate capacity costs in retail rates \nand effectuate the Ratepayer Protection Pledge signed by Dominion and most data center \ndevelopers.16  It also mirrors the obligation and intended effect of the Commission’s Show Cause \ndirective that PJM identify network upgrade costs caused by large loads so that state regulators \nmay account for that information when allocating costs at the retail level.17    \nThird, by excluding New Large Load that does not bring its own capacity from the \nVariable Resource Requirement curve in future Reliability Pricing Model (RPM) auctions,18 the \nIRAS Proposal will protect Virginia residential customers from excessive PJM-derived capacity \ncosts going forward. This will impact both (1) Dominion customers who must cover the RPM \ncosts for the increment of capacity obligations that Dominion does not self-supply, and \n(2) customers of the state’s electric cooperatives, which rely more heavily on RPM auctions for \ntheir capacity needs.      \n \n14 See id. at 5. \n15 See id. at 37. \n16 See Ratepayer Protection Pledge, The White House (Mar. 4, 2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/; President Trump’s Ratepayer Protection \nPledge Secures American AI Dominance, Protects Consumers, \nThe White House (July 23, 2026), https://www.whitehouse.gov/releases/2026/07/president-trumpsratepayer- \nprotection-pledge-secures-american-ai-dominance-protects-consumers/; Data centers pay their way. Ratepayers pay \ntheirs., The White House, https://www.whitehouse.gov/ratepayer-protection-pledge/.  \n17 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at PP 71, 73 (2026). \n18 See IRAS Proposal, Transmittal at 23-24."},{"page":6,"startToken":1664,"endToken":2027,"text":"6 \n \nTogether, these aspects of the IRAS Proposal better enable the SCC and the state’s \ncooperative utilities to quarantine capacity costs needed to serve New Large Load growth from \nthe bills of residential retail customers. \n2. PJM’s Solution Is Narrowly Tailored to Maintain Reliability and Ensure that \nNew Large Loads Pay their Fair Share of Capacity Costs. \n \nWithout appropriate protective measures, large loads will continue to jeopardize \nreliability and affordability in the PJM region.  PJM’s RPM, the mechanism created to enable the \ndelivery of reliable capacity to PJM’s system, has failed to procure enough capacity to meet \nPJM’s reliability requirement two years in a row.  The BRA for the 2027/2028 Delivery Year \ncleared 6,623 MW short of the PJM Region Reliability Requirement and at the price cap of \n$333.44/MW-day.19  The BRA for the 2028/2029 Delivery Year, held this summer, cleared \n6,831.3 MW short and also hit the market price cap of $325/MW-day.20  Large load development \nis the principal cause for PJM’s market clearing short and reaching the price cap.21   \nSubjecting Load Serving Entities that serve New Large Loads and have not arranged for \ntheir required capacity to IRAS appropriately balances two competing concerns.  On one hand, \nthe IRAS Proposal appropriately protects regular ratepayers from reliability and cost impacts \ncaused by New Large Loads.  As the primary drivers of the capacity shortfall, large loads and the \nLoad Serving Entities that procure capacity on their behalf should be responsible for securing \nand paying for sufficient capacity to meet their demand.  To the extent New Large Loads and/or \ntheir Load Serving Entities are unable to bring sufficient capacity online in time to meet their \ndemand, it is just and reasonable to keep those New Large Loads out of the capacity market and \n \n19 See id. at 14.  \n20 See id.  \n21 Monitoring Analytics, LLC, State of the Market Report for PJM, Volume 2: Detailed Analysis, at 43 (Mar. 12, \n2026) (“The current conditions are not the result of organic load growth.  The current conditions in the capacity \nmarket are almost entirely the result of large load additions from data centers, both historical and forecast.”)."},{"page":7,"startToken":2027,"endToken":2328,"text":"7 \n \nsubject their Load Serving Entity to IRAS.  Doing so will insulate regular customers from load \nshed events that would not likely to occur but for the addition of power-hungry New Large \nLoads.  On the other hand, New Large Loads seek speed to power.  PJM’s IRAS Proposal offers \na viable path for New Large Loads to come online faster than the generation needed to meet their \ndemand and will only subject those New Large Loads to load reduction requests during \nEmergencies prior to Pre-Emergency Load Management Response.22  This properly places the \nresponsibility for resolving challenges related to the capacity market shortfalls with New Large \nLoads and their Load Serving Entities without imposing undue burden on those entities.   \nB. The IRAS Proposal Reflects an Appropriate Exercise of Jurisdiction under the \nFederal Power Act and Will Complement Virginia’s Efforts to Integrate Large \nLoads. \n \nPJM’s proposal also respects jurisdictional boundaries and initiatives underway in the \nstates seeking to address the challenges that large load integration presents.  The Federal Power \nAct grants the Commission jurisdiction over “the transmission of electric energy in interstate \ncommerce and the sale of electric energy at wholesale in interstate commerce[.]”23  The states \nmaintain jurisdiction over “facilities used for the generation of electric energy or over facilities \nused in local distribution[.]”24  The Federal Power Act also reserves for the states jurisdiction \nover retail sales, i.e., sales to end-use customers.25 \nThe IRAS Proposal represents a proper exercise of the Commission’s authority over the \ninterstate transmission system.  Order No. 2000 establishes Regional Transmission \nOrganizations’ (RTO) authority over transmission operations, which obligates RTOs like PJM to \n \n22 IRAS Proposal, Transmittal at 4.  \n23 16 U.S.C. § 825 (b)(1).  \n24 Id. \n25 Id. (“The provisions of this subchapter . . . shall not apply to any other sale of electric energy[.]”)."},{"page":8,"startToken":2328,"endToken":2650,"text":"8 \n \noperate as security coordinator for the region.26   PJM’s role as security coordinator requires it to \nmonitor real-time system conditions and to “direct[] actions to maintain reliability, including \nfirm load shedding.”27  PJM’s proposal to direct Electric Distributors to shed load falls squarely \nwithin PJM’s authority to operate the transmission system and coordinate relief procedures.  \nNor does PJM’s IRAS Proposal tread on state authority over retail sales.  Although PJM \nproposes to issue load reduction directives to Electric Distributors, PJM defers to the Electric \nDistributors and the relevant states to resolve how to prioritize load reductions in their service \nterritories.28  PJM’s IRAS Proposal neither mandates nor prohibits load shed of specific end-use \ncustomers, but rather mandates that Electric Distributors shed an aggregate number of megawatts \nthat matches the capacity of Eligible New Large Loads.29  That Electric Distributors should \ndirect curtailment of New Large Loads is an expectation, not a PJM requirement.  Ultimately, the \nElectric Distributor, working in conjunction with the relevant state regulator, must develop and \nexecute the appropriate retail load curtailment protocols.  Tying the megawatt quantity to be shed \nto New Large Loads is matter of reliability and cost causation.  New Large Loads have caused \nthe capacity shortfall in PJM; it would be unjust and unreasonable to shed residential load due to \ninsufficient capacity to meet New Large Load demand.   \n \nThe Commission also has authority over generation facilities to the extent those facilities \nare needed to ensure transmission system reliability.30  As an operator of the bulk-power system, \nwhich includes “electric energy from generation facilities needed to maintain transmission \nsystem reliability[,]”31 PJM has an obligation to comply with reliability standards set pursuant to \n \n26 Regional Transmission Organizations, Order No. 2000, 89 FERC ¶ 61,285, at 278 (1999).  \n27 Id. \n28 See IRAS Proposal, Transmittal at 82.  \n29 See id. at 6. \n30 16 U.S.C. § 824o. \n31 16 U.S.C. § 824o (a)(1)(B), (b)(1)."},{"page":9,"startToken":2650,"endToken":2998,"text":"9 \n \nsection 215 of the Federal Power Act.  Combined with PJM’s authority as security coordinator \nfor the region, the responsibility to maintain system reliability enables PJM to condition \ntransmission service during times of system stress on either the New Large Load or the Load \nServing Entity that serves it securing sufficient capacity to meet the large load’s demand.  If PJM \nwere to require that the New Large Load or Load Serving Entity select a certain resource type to \ncover the New Large Load’s demand, that would intrude on state authority, but that is not what \nPJM has proposed.  \nIndeed, PJM’s IRAS Proposal enables effective cooperative federalism by \ncomplementing efforts in Virginia to ensure orderly integration of large loads.  The SCC has \napproved tariff changes proposed by Dominion and Appalachian Power Company to address \nlarge loads, both of which define large loads and require collateral, minimum contract terms, and \nminimum demand charges.32  These tariff changes operate within the state’s jurisdiction over \nretail sales and aim to ensure that large loads pay for stranded costs associated with generation, \ntransmission, and distribution costs should the large load not materialize.  PJM’s IRAS Proposal, \nby contrast, operates within the Commission’s jurisdiction over transmission service and bulk \npower system reliability33 to provide for interim service to the extent that New Large Loads and \ntheir Load Serving Entities in Virginia cannot secure sufficient capacity to meet their need by the \ndesired in-service date.  It does so without jeopardizing transmission system reliability or \nsaddling regular ratepayers with the costs of securing capacity to integrate New Large Loads.    \n \n32 Application of Virginia Electric and Power Company, Final Order, Va. State Corp. Comm’n, Case No. PUR-2025-\n00058, at 24-26 (Nov. 25, 2025); Petition of Appalachian Power Company, Final Order, Va. State Corp. Comm’n, \nCase No. PUR-2025-00057, at 2 (June 1, 2026).  \n33 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at PP 85-87 (requiring PJM to extend new transmission services \nto eligible customers taking service on behalf of large loads or show cause as to why the tariff is just and reasonable \nwithout such a provision)."},{"page":10,"startToken":2998,"endToken":3331,"text":"10 \n \nC. The IRAS Proposal Does Not Unduly Discriminate.   \nPJM’s IRAS Proposal is not unduly discriminatory because any such differentiation \namong capacity buyers is warranted by the size, operational characteristics, and grid impacts \ncaused by New Large Load.  The United States Court of Appeals for the District of Columbia \nCircuit (D.C. Circuit) has held that discrimination is undue only if differently treated entities are \n“similarly situated,”34 such that “there is no reason for the difference.”35  There is no undue \ndiscrimination where the Commission articulates relevant, significant facts to provide a rational \nbasis for treating two entities differently,36 and the Commission has “wide discretion . . . to \ndetermine what constitute[s]” undue discrimination.37   \nThe D.C. Circuit has specifically held that utilities may discriminate between two entities \ndue to capacity constraints.  In Complex Consolidated Edison Company v. FERC, the \nCommission upheld differential treatment of two natural gas pipeline customers on this basis.  \nThe Commission found in the underlying order that, without the pipeline company’s disparate \ntreatment of two different customers, one customer “could pull enough gas off the system to \nleave inadequate quantities available to meet other customers’” needs.38  The D.C. Circuit \naffirmed the Commission’s decision, stating that “the Commission gave an adequate explanation \nof how it reached its conclusion that there was no undue discrimination[.]”39  Further, the court \nfound that “a rational, non-discriminatory basis existed for the difference in situation, namely \noperational constraints.”40 \n \n34 State Corp. Comm’n v. FERC, 876 F.3d 332, 335 (D.C. Cir. 2017).  \n35 Transmission Access Policy Study Grp. v. FERC, 225 F.3d 667, 721 (D.C. Cir. 2000). \n36 Complex Consol. Edison Co. of N.Y., Inc. v. FERC, 165 F.3d 992, 1013 (D.C. Cir. 1999) (citations omitted).  \n37 Transmission Access Policy Study Grp., 225 F.3d at 721.  \n38 Tenn. Gas Pipeline Co., 76 FERC ¶ 61,022, at 61,138 (1996).  \n39 Complex Consol. Edison Co. of N.Y., 165 F.3d at 1013.  \n40 Id."},{"page":11,"startToken":3331,"endToken":3684,"text":"11 \n \nA similar principle underlies the treatment at issue here.  PJM expects to experience 29.7 \ngigawatts of load growth between 2025 and 2030.41  According to the Independent Market \nMonitor for PJM, “[d]ata center load growth is the primary reason for recent and expected \ncapacity market conditions, including total forecast load growth, the tight supply and demand \nbalance, and high prices[.]”42  Accordingly, it is reasonable to assume that any requirement to \nmeet 100 percent of data center demand 100 percent of the time would jeopardize PJM’s ability \nto meet the demand of existing residential customers, given the current capacity constraints.  For \nthis reason, a policy that requires only Load Serving Entities serving New Large Loads to match \nthis demand with sufficient capacity or for the New Large Loads themselves to bring their own \nnew capacity or be subject to IRAS, is not undue discrimination.  Here, the distinction between \nNew Large Loads and existing load is based on legitimate operational constraints in PJM created \nby a sudden and unprecedented influx of large load demand.  Managing these operational \nconstraints therefore provides a rational basis for differential treatment between Load Serving \nEntities serving New Large Loads relative to all other load.   \nThe D.C. Circuit has also found that public utilities may discriminate between two \nentities based on different customer characteristics.  In Cities of Bethany, et al. v. FERC, the \nD.C. Circuit upheld the Commission’s approval of separate customer categories where two \nentities “have different customer profiles and load characteristics[.]”43  PJM’s IRAS Proposal \nlikewise applies differential treatment to Load Serving Entities serving New Large Loads \ncompared to all other load based on different customer profiles and load characteristics.  As \n \n41 John D. Wilson, et al., Grid Strategies, Power Demand Forecasts Revised Up for Third Year Running, Led by Data \nCenters, at 33 (Nov. 2025), https://gridstrategiesllc.com/wp-content/uploads/Grid-Strategies-National-Load-Growth-\nReport-2025.pdf.  \n42 The Independent Market Monitor for PJM, Analysis of 2026/2027 RPM Base Residual Auction Part A, at 1 (Oct. \n1, 2025). \n43 Cities of Bethany, et al. v. FERC, 727 F.2d 1131, 1138 (D.C. Cir. 1984)."},{"page":12,"startToken":3684,"endToken":4037,"text":"12 \n \ncompared to existing residential and commercial customers, large loads have significantly higher \ndemand requirements.  PJM’s IRAS Proposal classifies New Large Loads as those requiring 50 \nMW or more,44 but large loads can require several hundred or even a thousand megawatts.45  \nMoreover, many large loads have high load factors that far exceed the average load factor of \nresidential customers.  As such, large loads both demand significant amounts of power and run \nconstantly, which differs markedly from traditional load profiles.  As the Commission has \nacknowledged, “integrating large loads poses specific challenges to transmission system \noperation given their size, operational behavior, and unique potential to impact the transmission \nsystem.”46  Therefore, categorizing and treating Load Serving Entities that serve New Large \nLoads separately from existing load is not unduly discriminatory.  \nIn fact, imposing a single rate regime covering service to both traditional load and New \nLarge Loads may itself be unduly discriminatory.  In Alabama Electric Co-op., Inc. v. FERC, the \nD.C. Circuit held that a single rate design that places on one group of customers “charges which \nare higher than necessary to recover the costs of servicing that group” may be unlawfully \ndiscriminatory.47  The court explained that a reasonable rate scheme “should produce revenues \nfrom each class of customers which match, as closely as practicable, the cost to serve each class \nor individual customer.”48  The rapid influx of large load demand is the principal driver of the \ngeneration capacity shortfall and price spikes in the PJM region,49 causing residential and \ncommercial customers to pay more than the costs required to service their own needs.  To \nameliorate this unduly discriminatory rate regime, PJM has appropriately proposed differential \n \n44 See IRAS Proposal, Transmittal at 32.  \n45 Congressional Research Service, Data Centers and Their Energy Consumption: Frequently Asked Questions, at 3 \n(May 12, 2026), https://www.congress.gov/crs_external_products/R/PDF/R48646/R48646.8.pdf.   \n46 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 58.  \n47 Ala. Elec. Co-op., Inc. v. FERC, 684 F.2d 20, 27-28 (D.C. Cir. 1982).  \n48 Id. at 29. \n49 Id."},{"page":13,"startToken":4037,"endToken":4128,"text":"13 \n \ntreatment for Load Serving Entities serving New Large Loads to help ensure that existing \ncustomers are not shouldering Commission-jurisdictional costs to serve New Large Loads.  \nIII. \nCONCLUSION  \nFor the foregoing reasons, Appalachian Voices respectfully requests that the Commission \napprove PJM’s IRAS Proposal.   \n \nRespectfully submitted,  \n/s/ Nicholas J. Guidi \nNicholas J. Guidi \nSenior Attorney \nnguidi@selc.org \n \n/s/ Katherine L. Rogers  \nKatherine L. Rogers  \nAssociate Attorney \nkrogers@selc.org \n \nSouthern Environmental Law Center \n500 New Jersey Ave. NW, Suite 600 \nWashington, DC 20001 \n \nCounsel for Appalachian Voices  \n \n \n \n \n Dated: September 3, 2026"},{"page":14,"startToken":4128,"endToken":4187,"text":"CERTIFICATE OF SERVICE \nPursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure, I hereby \ncertify that I have this day served a copy of the foregoing on all persons designated on the \nofficial service list compiled by the Secretary in this proceeding.  \nDated this 3rd day of September 2026.  \n \n/s/ Nicholas J. Guidi  \nNicholas J. Guidi"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":274},{"p":2,"at":5,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":2,"endAt":1501,"startToken":274,"endToken":488},{"p":2,"at":1501,"title":"II. COMMENTS","method":"printed heading","endPage":2,"endAt":1517,"startToken":488,"endToken":490},{"p":2,"at":1517,"title":"A. The Commission Should Accept PJM’s IRAS Proposal to Help Ensure that New","method":"printed heading","endPage":7,"endAt":747,"startToken":490,"endToken":2145},{"p":7,"at":747,"title":"B. The IRAS Proposal Reflects an Appropriate Exercise of Jurisdiction under the","method":"printed heading","endPage":10,"endAt":6,"startToken":2145,"endToken":2999},{"p":10,"at":6,"title":"C. The IRAS Proposal Does Not Unduly Discriminate.","method":"printed heading","endPage":13,"endAt":186,"startToken":2999,"endToken":4063},{"p":13,"at":186,"title":"III. CONCLUSION","method":"printed heading","endPage":14,"endAt":0,"startToken":4063,"endToken":4128},{"p":14,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":14,"endAt":356,"startToken":4128,"endToken":4187}]}