{"document":{"slug":"rec-20260903-5233","title":"Protest of Google LLC regarding PJM Interconnection, L.L.C.’s Interim Resource Adequacy Service and Large Load Registry proposal","issued":"2026-09-03","accession":"20260903-5233","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Google LLC","kind":"protest","file":"sources/filings/text/20260903-5233_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5233","tier":"record","sha256":"81292f60c4a218be51cc9be8bb53b8e88ce1efb7355c33bf5aa76b3738c5e9a1","pages":27,"tokens":8313,"emptyPages":[],"textThemes":["flex","retail","adequacy","registry"]},"pages":[{"page":1,"startToken":0,"endToken":228,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n) \n) \n \nDocket No. ER26-3515-000 \n \nPROTEST OF GOOGLE LLC \n \n \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 Google LLC (“Google”) hereby submits this protest \nregarding PJM Interconnection, L.L.C.’s (“PJM”) Interim Resource Adequacy Service (“IRAS”) \nand Large Load Registry proposal. \nGoogle’s concerns with IRAS center on the proposed mechanism, not the underlying \nobjectives. Specifically, Google agrees that New Large Loads that do not bring sufficient new \ncapacity to offset their expected demand should be subject to curtailment prior to other firm \nwholesale customers during tight system conditions, ensuring service to residential and other \ncommercial customers remains reliable.  Consistent with this principle, a longstanding and \nfoundational pillar of Google’s energy procurement philosophy has been that Google should \nenable sufficient new capacity to meet its energy demand.    \nIRAS would stymie that goal.  It would inject fresh uncertainty into PJM, threatening \ndesperately needed investments to build out the region’s generation fleet.  The fundamental flaw \nin IRAS is PJM’s proposal to assign general curtailment obligations to Electric Distributors \n(“EDs”) with New Large Loads that do not bring new capacity, despite lacking jurisdiction over \nhow EDs execute those curtailments..  Consequently, in the event of a shortage, New Large Loads \n \n1 18 C.F.R. § 385.211 (2026)."},{"page":2,"startToken":228,"endToken":540,"text":"-2- \nthat bring new capacity—and spend billions of dollars doing so—could still be curtailed before \nthose that do not.  PJM cannot resolve this basic misalignment because curtailment priority among \nend users is a quintessential retail ratemaking question that only states have the authority to \nimplement under the Federal Power Act (“FPA”).   \nNevertheless, because of that misalignment, IRAS creates a clear risk that New Large \nLoads that invest billions of dollars to bring their own new capacity—i.e., the purported means of \navoiding curtailment under IRAS——will, in fact, not avoid it.  By penalizing the very behavior \nit seeks to incentivize, IRAS directly undercuts its own foundational premise. That regulatory \ndisconnect makes it extremely risky for Google and similarly situated customers to invest in new \nPJM capacity unless and until states enact prompt laws or regulations establishing consistent \ncurtailment protections.  Ultimately, the result of IRAS will be less investment in new capacity in \nPJM—the exact opposite of what the region needs. Accordingly, the Commission should \nemphatically reject a proposal that would actively deter the capacity investments PJM so urgently \nneeds.    \nIn addition, IRAS violates the FPA in several different respects. It exceeds the \nCommission’s jurisdiction, it is unduly discriminatory, and it is unjust and unreasonable.  Any of \nthose significant shortcomings would be sufficient, on its own, to overturn a Commission approval \non appeal.  The long shadow of uncertainty caused by litigation over a program with such obvious \nshortcomings will further sap the confidence necessary for companies like Google to deploy the \ncapital needed to develop the gigawatts (“GW”) of new generation that PJM demands.   \nIRAS is a deeply flawed approach in light of the many, superior ways of addressing the \nconcerns that motivated PJM to pursue IRAS in the first place.  Specifically, because the \ncurtailment issue is a quintessential question of state law, PJM should pursue an actual program"},{"page":3,"startToken":540,"endToken":843,"text":"-3- \nof “cooperative federalism” through which it uses its position as operator of the wholesale market \nto empower the states to effectuate curtailment priorities that meet their public policy priorities, \nincluding, for example, a preference for New Large Loads that bring their own new capacity.  This \nwould avoid the legal risk and uncertainty that would throttle investment in new generation \ncapacity while providing a clear path to pursuing the goals purportedly underlying this proceeding.  \nMoreover, there are several additional options, such as demand response reforms, to unlock the \nflexibility that data centers and other large loads can provide under the appropriate circumstances \nthat could further improve PJM’s capacity position without the problems that IRAS presents.  \nAccordingly, for the reasons that follow, the Commission should accept the Large Load Registry \n(the only legally defensible part of PJM’s proposal), while rejecting IRAS and directing PJM onto \na different, more sustainable path that will actually improve resource adequacy in the region to the \nbenefit of all stakeholders, including retail customers.  \nI. \nWHO WE ARE \nGoogle’s mission is to organize the world’s information and make it universally accessible \nand useful.  AI is critical to that mission.  Data centers are the infrastructure that make AI possible, \nand electricity is the fuel that powers them.  To serve Google’s customers, data center \ninfrastructure consumes a large amount of electricity and requires reliable electric service to \noperate.  As Google’s business grows, so too does its demand for reliable, affordable, and clean \nelectricity. \nII. \nPROTEST \nA. IRAS Will Not Incentivize New Large Loads to Bring Their Own New Capacity \nGoogle agrees with the principle that ostensibly underlies IRAS.  Namely, New Large \nLoads that connect to the transmission system should be incentivized to bring new capacity to the \nregion to cure resource adequacy shortcomings; those that do not should be curtailed at the"},{"page":4,"startToken":843,"endToken":1218,"text":"-4- \nappropriate time.  If the Commission agrees with that principle, it should reject IRAS.  That is \nbecause PJM legally cannot ensure that New Large Loads that utilize the Bring Your Own New \nCapacity (“BYONC”) pathway will receive firm service and not be curtailed, as PJM itself \nacknowledges.2  Instead, it is the states that have “‘exclusive jurisdiction’ . . . to ensure that the \nappropriate retail customers, i.e., New Large Loads, including data centers—and not residential \ncustomers or small industrial customers—are reduced when system conditions call for PJM to \nrequire load reductions.”3  PJM is explicit that it has no authority to ensure that New Large Loads \nget the purported benefit of the IRAS “bargain” (firm service), explaining that it is “leaving it to \n[EDs], in coordination with the appropriate states and/or [Relevant Electric Retail Regulatory \nAuthorities, (“RERRAs”)], [Load Serving Entities, (“LSEs”)], and LSE customers to determine \nwhich loads should ultimately reduce subject to IRAS.”4 \nStates might curtail loads in the order that PJM envisions, but there is no guarantee.   A \nstate could create its own retail curtailment scheme that reflects entirely different considerations \nthan IRAS.  For example, a state could establish a curtailment priority that gives effect only to new \ncapacity within the state or that meets certain other limiting characteristics.  Or, alternatively, a \nstate may curtail a New Large Load that brings new capacity in favor of other retail customers, \nincluding data centers, that are deemed too important to be curtailed.  In short, it is impossible to \n \n2 Compare PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim \nResource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515, at 2 \n(filed Aug. 13, 2026) (“Transmittal”)Transmittal at 2 (“New Large Loads can avoid this condition on taking \ntransmission service by bringing new capacity to the system.”), with Transmittal at 87 (“[W]hile PJM will determine \nthe quantity of MW that load in a zone/area will need to be reduced by to maintain system reliability in the PJM \nRegion, states may determine—under their own laws, policies, and definition of what constitutes ‘large load’—which \nresources will be called on to reduce load.”). \n3Id. at 90-91 \n4 Id. at 92."},{"page":5,"startToken":1218,"endToken":1523,"text":"-5- \nknow whether the states will implement IRAS as PJM expects because “the curtailment protocol \nwas not developed with [relevant state actors’] input.”5   \nAs a result, IRAS severely undermines any incentive to invest in new generation.  If entities \nare going to spend billions of dollars to offset curtailment risk by bringing their own new capacity, \nand improve the region’s resource adequacy shortfall, they need some assurance that they will, in \nfact, receive firm service and will not be curtailed whenever conditions are tight.  To be clear:  \nGoogle is prepared to invest the billions of dollars necessary to ensure that its New Large Loads \nbring adequate new capacity.  Maintaining regional resource adequacy has been and remains a \nlongstanding and foundational pillar of Google’s energy procurement philosophy. 6  But Google \ncannot responsibly do so without some assurance that it will receive firm retail service in exchange \nfor those investments, particularly where PJM’s proposal threatens to unwind firm service for \nfacilities that have already executed firm Energy Service Agreements (“ESAs”).  Without that \nassurance—which, again, PJM is legally precluded from providing—BYONC is a gamble, not an \ninvestment. \nAnd that is not the only source of uncertainty inherent in IRAS.  As explained below, IRAS \nhas several glaring legal flaws.  As PJM’s own staff recognized when it recommended against \npursuing the previous—albeit substantially similar—iteration of IRAS, the inevitable litigation \nthat follows such a legally infirm proposal will be significant and ultimately undermine the \n \n5 PJM Interconnection, L.L.C., Answer of the Pennsylvania Public Utility Commission in support of the \nOrganization of PJM States, Inc.’s motion for extension of time, Docket No. ER26-3515-000, at 2 (filed on Sep. 1, \n2026). \n6 See, e.g., Google, The Clean Transition Tariff, https://www.gstatic.com/marketing-\ncms/1f/d3/00f64e2c4f4f92e8e34ed8ef1e2c/clean-transition-tariff-ctt.pdf (last visited Sept. 1, 2026)."},{"page":6,"startToken":1523,"endToken":1898,"text":"-6- \nprogram’s ability to achieve its purported objectives.7  Inevitable litigation coupled with IRAS’s \nobvious legal flaws will cast a pall of uncertainty over the contracting for and development of new \ncapacity in PJM for as long as this proceeding and the resulting appeals continue.  The best thing \nthat the Commission could do to create certainty and facilitate investment in new long-term \ncapacity is to reject IRAS emphatically (while accepting the Large Load Registry) and have PJM \npromptly produce a proposal that complies with the FPA.   Anything short of that will only deepen \nthe current resource adequacy insecurity in PJM.    \nPJM’s attempt to justify IRAS with analogies to various constructs that the Commission \nhas accepted cannot bear the weight PJM puts on them.  For example, the Southwest Power Pool’s \n(“SPP”) “large load integration construct”—which includes SPP’s High Impact Large Load \nGeneration Assessment (“HILLGA”)8—is an inapt comparison that only highlights IRAS’s faulty \npremise.  Under HILLGA, new generation paired with an electrically proximate large load can opt \nto interconnect to SPP’s system on an expedited basis in exchange for interconnection service that \nis limited in ways explicitly spelled out in the SPP tariff.9  And because SPP has authority over \ngenerator interconnection in the region, it can actually deliver the promised benefits of HILLGA.  \nIn this way, entities considering deploying capital in SPP know exactly what they are getting if \nthey participate in HILLGA, which is essential for unlocking investment on the scale needed to \nbolster resource adequacy.  IRAS does not offer comparable predictability because PJM has no \nauthority over which retail loads are curtailed.10  As noted above, this means that large loads in \n \n7 See PJM Interconnection, L.L.C., CIFP Connect & Manage: PJM Stage 4 Proposal Executive Summary \n(June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-\nitem-02a---pjm-stage-4-proposal---connect-and-manage---executive-summary.pdf. \n8 Transmittal at 21-22 n. 64 (citing Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026)). \n9 Sw. Power Pool, Inc., 194 FERC ¶ 61,031 at P 8. \n10 See Transmittal at 85 (“[T]oday Electric Distributors select, consistent with their state programs, which \nloads to reduce in response to a PJM load reduction directive. . . . PJM is not looking to change any existing approach."},{"page":7,"startToken":1898,"endToken":2188,"text":"-7- \nPJM could invest billions of dollars to develop new generation only to be curtailed by an ED that \nhas no obligation to prioritize service to New Large Loads that bring their own new capacity.   \n Google has already committed to “build, bring, or buy the new generation resources and \nelectricity needed to satisfy their new energy demands, paying the full cost of those resources \nwhether by building, or buying from, new or otherwise additive power plants.”11  And it is not \nalone.  Indeed, there is no shortage of offtakers willing to enter long-term contracts for new \ncapacity, provided that they have certainty over the benefits that they will receive in return.  PJM \nshould focus on providing that certainty rather than undermining the otherwise favorable \ninvestment conditions for companies that stand ready to make the commitments that will actually \nbring new capacity to the region.    \nB. IRAS Violates the FPA \nIRAS is also illegal for three independent reasons.  First, it aims at and targets the retail \nsphere, in violation of the FPA’s division of jurisdiction.  Second, it is unduly discriminatory \nbecause it treats entities that are functionally identical for the purposes of the wholesale market \ndifferently without any legally relevant basis for doing so.  Suffice it to say, discrimination on the \nbasis of legally irrelevant characteristics can never be “due.”  Finally, it is unjust and unreasonable \nbecause PJM would charge customers for capacity that it never intends to procure or that those \ncustomers, by design, can never use.   \n \nCurrently, the manner in which an Electric Distributor reduces load is a function of their state-approved contracts and \nstate-approved curtailment and load reduction plans.”). \n11 The White House, Ratepayer Protection Pledge (Mar. 4, 2026), https://www.whitehouse.gov/releases/20\n26/03/ratepayer-protection-pledge/."},{"page":8,"startToken":2188,"endToken":2488,"text":"-8- \n1. IRAS Exceeds the Commission’s Jurisdiction \nIRAS exceeds the Commission’s jurisdiction because it targets particular retail \ncustomers: “New Large Loads.”  FPA Section 201(b) “‘limit[s] FERC’s sale jurisdiction to that \nat wholesale,’ reserving regulatory authority over retail sales (as well as intrastate wholesale \nsales) to the States.”12  “FERC cannot take an action transgressing that limit no matter how \ndirect, or dramatic, its impact on wholesale rates.”13  To respect that limit, FERC and entities like \nPJM are prohibited from taking actions that “aim[]” at or “target” particular retail consumers or \nthe retail market generally.14  Instead, as relevant here, a Commission order adheres to the FPA’s \njurisdictional divide only where “every aspect of the regulatory plan happens exclusively on the \nwholesale market and governs exclusively that market’s rules.”15  \nIRAS violates that principle.  FERC cannot approve tariff provisions where retail \nconsumers are the “target at which [those tariff provisions] aim.” 16  IRAS breaks that rule \nbecause it targets retail customers by assigning the wholesale curtailment obligation based on the \nsize (i.e., more than 50 MW) and vintage (i.e., in-service  date and ramp rate) of the relevant \nretail customers.17  In so doing, the proposal makes the characteristics of the retail customer, not \nthat of the ED, LSE, or Eligible Customer, or any other Commission-jurisdictional entity or \ntransaction, the basis for imposing a curtailment obligation.  It thus explicitly determines the \n \n12 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 279 (2016) (“EPSA”) (quoting New York v. FERC, 535 \nU.S. 1, 6 (2002)). \n13 Id. at 280. \n14 Id. at 282 (quoting Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015) “Oneok”)). \n15 Id. \n16 Oneok, 575 U.S. at 385; see EPSA, 577 U.S. at 282. \n17 Transmittal at 6."},{"page":9,"startToken":2488,"endToken":2926,"text":"-9- \nquality of wholesale service based on the characteristics of retail customers, and, as explained \nbelow, that is no accident or side effect of IRAS; it is the entire reason we are here. 18   \nCompare that “target[ing]” of individual retail customers to what PJM is not doing.  \nAlthough PJM suggests that the policy problem it is trying to solve is capacity shortages driven by \nnew load growth,19 under IRAS, PJM would not determine an ED’s curtailment obligations based \non its rate of load growth.  Consider a hypothetical where one ED’s annual load grows by 200 MW \nthrough ten separate 20 MW industrial facilities, while another ED’s load grows by only 100 MW \ndriven by one single data center.  Assume none of the loads bring their own new capacity.  The \nfirst ED would not be subject to curtailment while the second ED would, despite having half the \nload growth of the first.  That differential treatment confirms that it is not the ED’s load growth \nthat is the focus of IRAS, but rather the specific retail customers that make up that load growth \nthat matters. To put it mildly, this is not a regulation where “every aspect of the regulatory plan \nhappens exclusively on the wholesale market and governs exclusively that market’s rules.” 20   \nRather, IRAS is unlawfully “tethered” to the retail markets and specific retail consumers21—most \nprominently, new data centers.22   \n \n18 Cf. Corner Post, Inc. v. Bd. of Governors of Fed. Rsrv. Sys., 603 U.S. 799, 815 (2024) (“As this Court has \nrepeatedly stated, the text of a law controls over purported legislative intentions unmoored from any statutory text.”); \nKeister v. AARP Benefits Comm., 410 F. Supp. 3d 244, 257 (D.D.C. 2019) (“[I]t is well established that extrinsic \nevidence may not be relied upon to show the subjective intent of the parties absent ambiguity in the contract’s \nlanguage.” (cleaned up)). \n19 See, e.g., Transmittal at 99, 124. \n20 EPSA, 577 U.S. at 282.   \n21 Cf. Hughes v. Talen Energy, Mktg. LLC, 578 U.S. 150, 166 (2016) (state’s action to encourage \ndevelopment of certain generation resources cannot be tethered to the resource’s wholesale market participation).   \n22 PJM’s own transmittal letter confirms that the target of IRAS is specific retail customers.  See, e.g., \nTransmittal at 17 (explaining that, as directed by the PJM Board, one of the elements of PJM’s proposal is that “IRAS \nwill be applicable to ‘[N]ew Large Loads that, as of June 1, 2027, do not bring sufficient capacity to serve their \nresource adequacy needs and cannot otherwise be served at the 1-in-10 reliability standard[.]”)."},{"page":10,"startToken":2926,"endToken":3282,"text":"-10- \n PJM’s arguments to the contrary are barred by governing Supreme Court precedent.  \nPJM briefly claims that, as in EPSA, the policy question at issue is one the FPA’s drafters “could \nnot have anticipated.”23  But novel circumstances are not an excuse to rewrite a statute.24  PJM \ndoes not and cannot even assert that it satisfies EPSA’s requirement that the regulation \n“addresses—and addresses only—transactions occurring on the wholesale market.”25     \nNor does it help that, after determining that an ED must “reduce load by a certain MW \nquantity” based on the characteristics of its retail customers, PJM then leaves it to the ED and state \nto implement the reduction across its customers.26  Although PJM attempting to direct reductions \non a customer-by-customer basis would provide another reason why IRAS is unlawful, the fact \nthat things could be more jurisdictionally infirm does not immunize PJM’s already-unlawful \nproposal to condition curtailment obligations on retail customer characteristics, rather than \nconsumer-neutral load and capacity considerations.  The plan still targets and is tethered to specific \nretail consumers and thus exceeds PJM’s jurisdiction.27     \nSimilarly, it is no answer for PJM to assert that IRAS’s targeting of data centers is justified \nbecause they make up the vast majority of load growth.  While that is true, the fact that certain \nretail customers are having an outsized effect on the wholesale market does not give the \nCommission license to target those customers any more than it gives it license to target “markets \nin all electricity’s inputs—steel, fuel, and labor most prominent among them—[based on how they] \n \n23 Transmittal at 91.   \n24 Cf. Oklahoma v. Castro-Huerta, 597 U.S. 629, 649 (2022) (refusing to “rewrite a constitutionally valid \nstatutory text under the banner of speculation about what Congress might have done had it faced a question that ... it \nnever faced”). \n25 EPSA, 577 U.S. at 282; see Transmittal at 91 (drawing comparison to EPSA as to whether the policy need \nwas anticipated, but not whether the regulation only addresses wholesale transactions). \n26 Transmittal at 92. \n27 Oneok, 575 U.S. at 385; see EPSA, 577 U.S. at 282."},{"page":11,"startToken":3282,"endToken":3603,"text":"-11- \naffect generators’ supply of power.”28  Rather, as discussed above, the Commission must restrict \nits program of regulation to the wholesale market, no matter how significantly certain retail \ncustomers’ demand might affect that market and make retail regulation a tempting target for the \nCommission.     \nFinally, although PJM characterizes its proposal as “a product of cooperative federalism,” \nit is, in fact, quite the opposite.  Cooperative federalism is rooted in the concept that the federal \nentity need not, and should not, exercise the full extent of its authority when addressing issues \nthat affect both federal and state interests.  For example, in EPSA, while the Commission claimed \nthat it could negate state decisions prohibiting retail consumers from making wholesale demand \nresponse bids, it “chose not to do so in recognition of the linkage between wholesale and retail \nmarkets and the States’ role in overseeing retail sales.”  That was a scheme of cooperative \nfederalism in “which the States retain[ed] the last word.”  Here, by contrast, PJM has created a \nscheme that it lacks the authority to carry out and so it has, instead, unilaterally foisted onto the \nstates the responsibility for implementing IRAS without consulting with them on the program’s \ndesign.29  The principle of cooperative federalism does not describe a program that would have \nthe federal government exceed its authority and then leave it to the states to resolve the resulting \ncomplexities.   \n2. IRAS Is Unduly Discriminatory \nIRAS is unduly discriminatory for similar reasons.  The FPA categorically prohibits \nundue discrimination, which occurs when similarly situated entities are treated differently \n \n28 EPSA, 577 U.S. at 277-78. \n29 See PJM Interconnection, Answer of the Pennsylvania Public Utility Commission in support of the \nOrganization of PJM States, Inc.’s motion for extension of time, Docket No. ER26-3515-000, at 2 (filed on Sep. 1, \n2026) (“The curtailment protocol was not developed with PA PUC’s input, and it may impinge upon our jurisdiction \nover retail rates.”)."},{"page":12,"startToken":3603,"endToken":3914,"text":"-12- \nwithout good reason.30 When evaluating whether resources are similarly situated, it is not enough \nfor those resources to be different in any respect; rather, they must be different with respect to \nthe inquiry at hand.31  As explained above, the only differences between EDs that receive \ncurtailment orders under IRAS and those that do not are the characteristics of their retail \ncustomers, which are outside Commission jurisdiction and thus legally irrelevant to the question \nof whether two entities are similarly situated for the purposes of the FPA.  Receiving differing \nlevels of Commission-jurisdictional service based on legally irrelevant differences is unduly \ndiscriminatory.  \nBut even if PJM could consider the characteristics of retail customers when making \ncurtailment decisions, IRAS would still be unduly discriminatory because it discriminates \namongst EDs for reasons that have nothing to do with the resource adequacy concerns PJM is \ntrying to address.   \nFirst, under IRAS, PJM would issue curtailment directives to EDs based on the size of \nindividual new loads rather than the aggregate amount of new demand in a zone.  It is the \naggregate growth that causes a resource adequacy challenge, not the load growth of only a subset \nof customers.  To slightly revise the example from the previous section, if a hypothetical ED’s \nload grows by 200 MW due to ten 20 MW loads, it would have no curtailment exposure under \nIRAS.  If another hypothetical ED’s load grows by 200 MW based on a single data center, all the \nincremental load would be subject to IRAS despite having identical load growth to the first ED.  \nPJM has not explained how such disparate treatment can be justified under the FPA. \n \n30 Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th 265, 282 (D.C. Cir. 2022). \n31 See Xcel Energy Servs., Inc. v. FERC, 41 F.4th 548, 559-60 (D.C. Cir. 2022)."},{"page":13,"startToken":3914,"endToken":4236,"text":"-13- \nIn addition, IRAS is unduly discriminatory because of the manner in which it treats New \nLarge Loads differently than existing large loads.  One MW of load contributes identically to a \nreliability requirement shortfall regardless of its in-service date. Analogous D.C. Circuit and \nFERC precedent calls for treating new and continuing customers alike.32 Nevertheless, PJM \ndefines a “New Large Load” as having an in-service (or incremental-ramp) date after June 1, \n2027.  This means that a 500 MW load interconnected in the first half of 2027 would not trigger \na curtailment directive to its ED, but a 500 MW load interconnected in the second half of the \nyear would.  This would be true even though the earlier-in-time load contributes equally to any \nresource adequacy shortfall as the later-in-time load.  PJM, which bears the burden for justifying \nits section 205 proposal, has not explained why large loads that interconnect after June 1, 2027, \nwarrant differential treatment from those that interconnect before that date, which is reason alone \nto reject PJM’s filing. \n3. IRAS Is Unjust and Unreasonable \nLast but not least, IRAS is also unjust and unreasonable for two independent reasons.  \nFirst, PJM is proposing to charge customers for a service that it never intends to procure.  \nSpecifically, PJM proposes to exclude from the Variable Resource Requirement Curve (i.e., the \ncapacity market demand curve) New Large Loads that do not bring their own new capacity, \nmeaning that it would, by definition, not procure capacity to serve them, even if that capacity is \navailable.  Nevertheless, PJM proposes to charge the LSEs that will service those same New \nLarge Loads for a share of the capacity (even though none of that capacity will have been \nprocured for them).  Being forced to pay money for nothing is not just and reasonable or \nconsistent with cost causation.  \n \n32 See BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014)."},{"page":14,"startToken":4236,"endToken":4655,"text":"-14- \nPJM justifies this novel intervention in the interaction of supply and demand by arguing \nthat it would help ensure that residential and other existing commercial customers’ rates do not \nincrease when New Large Loads connect to the grid.33  To be clear:  Google supports that aim \nunequivocally.  That is why Google signed the Ratepayer Protection Pledge and, as explained \nabove, Google is firmly committed to procuring new capacity sufficient to cover its demand. 34  \nBut breaking supply and demand fundamentals by ignoring the demand that PJM itself \nexpects to materialize is not a reasonable way to further that critical goal.  Most obviously, it \nviolates the FPA’s cost causation principle, which provides that the costs allocated to an entity \nmust be “roughly commensurate” to the benefits it receives.35    Cost causation and the statutory \nrequirement to roughly equate benefits and costs does not permit PJM to assign costs to entities \nthat are structurally precluded from receiving the corresponding benefits.   The fact that New \nLarge Loads that are curtailed under IRAS might36 receive a credit in their retail rates certainly \ncannot retroactively undo PJM’s decision to forgo procuring capacity, but then still charge \ncustomers as if it had, in fact, procured capacity to serve them.   \nIn addition, ignoring demand to make the market clear is yet another significant intrusion \ninto the market fundamentals and resulting price signals that, in theory, are the reason the \n \n33 Transmittal at 23-24. \n34Amanda Peterson Corio, Supporting the White House Ratepayer Protection Pledge: Google's Approach \nfor Responsible Energy Growth, Google: The Keyword (Mar. 4, 2026), https://blog.google/innovation-and-\nai/infrastructure-and-cloud/global-network/affordability-pledge-responsible-energy-growth/.  \n35 See Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022); Long Island \nPower Auth. v. FERC, 27 F.4th 705, 714-15 (D.C. Cir. 2022); Neb. Pub. Power Dist. v. FERC, 957 F.3d 932, 939-41 \n(8th Cir. 2020); Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1260-62 (D.C. Cir. 2018); K N Energy, Inc. v. \nFERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992). \n36 There is no guarantee that New Large Loads that are curtailed under IRAS will be compensated for those \ncurtailments, because “how the compensation scheme will work in practice relies on application of state retail law. \nWhether a specific New Large Load may be entitled to compensation for provision of IRAS will be determined by \nstate authorities under state law or [Relevant Electric Retail Regulatory Authorities] as may be applicable.”  \nTransmittal at 106 (footnote omitted))."},{"page":15,"startToken":4655,"endToken":4973,"text":"-15- \nReliability Pricing Model (“RPM”) exists.37 In the very short term, PJM’s proposed capacity \nmarket may help achieve the laudable goal of insulating residential and other existing retail \ncustomers from the price effects of large load additions—a goal that, as noted, Google firmly \nsupports.  But it does so only by further balkanizing the market and turning it into a construct \nthat bears ever-less connection to the economic forces it is supposed to harness.  Nominal \nreliance on a market-based construct that is in reality untethered to market forces is a recipe for \nprolonging PJM’s current resource adequacy crisis or ending up in another one in the future. \n And that is exactly what IRAS would do by removing known, forecasted demand from \nthe RPM with the explicit goal of reducing resource procurement and resulting capacity prices.   \nPJM would, once again, be muting the demand signal and forcing capacity prices to a level that \nis lower than what is needed to attract investment in new generation.  That, in turn, threatens the \nregion’s long-term resource adequacy and is inconsistent with PJM’s own statement that the \nRPM should “reflect actual supply and demand fundamentals.”38 \nSecond, IRAS would require EDs with New Large Loads that do not bring their own new \ncapacity to contribute to the cost of new demand response capacity resources, but curtail the \nassociated EDs before those demand response resources are dispatched.   In other words, under \nIRAS, New Large Loads would pay for demand response resources to serve as capacity and yet, \nwhen system conditions warrant it, those New Large Loads would be curtailed before demand \nresponse resources are ever dispatched.  This defies basic logic: no one would buy an umbrella \non the condition that it must be surrendered the moment it rains, yet that is precisely what PJM \ndemands here. \n \n37 Id. at 115 (indicating that the RPM should “reflect actual supply and demand fundamentals”). \n38 Id."},{"page":16,"startToken":4973,"endToken":5271,"text":"-16- \nGoogle reiterates that it is committed to bringing new capacity and supporting legal and \ndurable solutions for ensuring that large loads do not raise rates or undermine service for \nresidential customers and other existing customers.  Google strongly supports competitive \nwholesale markets and believes that they are a highly effective means of developing new supply \nwhile protecting customers from unnecessary costs.  But functioning markets require adherence \nto market fundamentals.  A market design that, like IRAS, undermines the basic principles on \nwhich markets depend is neither just and reasonable nor a viable tool for ensuring resource \nadequacy, reliability and affordability.   \nC. A Lawful and Durable Framework Can Protect Residential Customers While \nPreserving Incentives for Large Loads to Bring New Capacity \nAccepting IRAS would be an egregious misstep because there are ample alternative \navenues through which PJM, in cooperation with the States, could facilitate the goals underlying \nIRAS, rather than impede them.   \nFirst, with the appropriate data management and confidentiality guarantees, the \nCommission should accept PJM’s proposed Large Load Registry as it would provide much needed \ntransparency without the jurisdictional concerns inherent in IRAS.  Second, PJM should reform its \nwholesale demand response rules39 to unlock the flexibility that large loads are capable of \nproviding.  As explained below, Google has been a pioneer in unlocking data centers’ latent \nflexibility.  And Google has consistently advocated for demand response reforms at PJM to make \ndata center-driven demand response a pillar of the solution to the resource adequacy challenges \nassociated with rapid load growth.  Breaking down the barriers to demand response supplied by \ndata centers would go a long way to resolving the resource adequacy challenge that motivated PJM \n \n39 Which, unlike the retail customers that are the target of IRAS, is a matter within the Commission’s \nexclusive jurisdiction.  EPSA, 577 U.S. 260."},{"page":17,"startToken":5271,"endToken":5603,"text":"-17- \nto pursue IRAS in the first place.  Finally, PJM should (on its own or at the direction of the \nCommission) develop a method for facilitating state interruptible load tariffs.  As explained above, \nthe question of which retail customers should reduce their demand in the face of a resource \nadequacy shortfall is fundamentally a retail ratemaking question that only the states can address. 40   \nRather than pursuing a convoluted methodology like IRAS in an effort to circumvent that basic \njurisdictional fact, PJM should embrace it.  In so doing, it could implement an actual “program of \ncooperative federalism” in which the states design the interruptible load tariffs and PJM provides \nthe wholesale-market support that it is uniquely positioned to administer.   \nThe Data Center Coalition has already presented PJM with such a durable State Opt-In \nframework coupled with immediate improvements to existing emergency load-shed procedures.41   \nBelow, Google offers principles that should guide the Commission and PJM on the path to \nensuring that the region maintains resource adequacy and reliability in the face of rising demand.  \n1. The Commission Should Accept the Large Load Registry, Which Will \nFacilitate Cooperative Federalism \nAs a threshold matter, the Commission should accept the Large Load Registry.  The \nRegistry is a common-sense mechanism for providing both PJM and states with the information \nthey need to carry out their respective responsibilities related to resource adequacy and reliability \nand, as it is informational in nature, it does not present the same jurisdictional concerns as the rest \nof the IRAS filing.  For PJM in particular, the Large Load Registry would be an important step \ntowards improving the region’s load forecast, which will help ensure that the region is procuring \n \n40 Supra § II.B.1.  \n41 Letter from Kelsey Bagot, Chair, Va. State Corp. Comm’n & Josh Levi, President & CEO, Data Center \nCoal., to Paula Conboy, PJM Bd. of Managers & David Mills, President & CEO, PJM Interconnection, L.L.C. (June \n2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260630-va-scc-\nand-data-center-coalition-letter-re-cifp-connect-manage-reliability-backstop-procurement.pdf."},{"page":18,"startToken":5603,"endToken":5990,"text":"-18- \nthe appropriate quantities of capacity and making the appropriate long-term investments in \ntransmission infrastructure, including through PJM’s regional transmission planning process.   \nAlthough PJM has taken steps over the last year to improve its load forecasting,42  more is needed, \nand the Large Load Registry would be a meaningful step in that regard.  In addition, the \ntransparency the Registry would provide aligns directly with the transparency measures that the \nCommission required in the PJM Show Cause Order, allowing states greater visibility into the \nlarge load matters affecting their jurisdictions.    \nThe Commission has the authority to accept only the Large Load Registry.  PJM has \nconsented to severing “any element of the proposed Tariff and RAA language to the extent \nnecessary and permitted under FPA section 205 and NRG Power Marketing, LLC v. FERC, where \nsuch modification and/or severance is consistent with PJM’s overarching objectives in this \nfiling.”43   For the reasons explained above, accepting the Large Load Registry and severing the \nremainder of the proposal would be consistent with PJM’s goals of improving resource adequacy \nin the region while ensuring that service to existing residential customers remains reliable.44   And \ndoing so is consistent with the Commission’s “passive and reactive” role under section 205 of the \nFPA45 and its authority to accept in part and reject in part a filing, provided that it does not create \na whole new rate.46   \n \n42 See, e.g., Reliability Technical Conference, Pre-Technical Conference Remarks of Jason Connell, Vice \nPresident, Planning, PJM Interconnection, L.L.C., Docket No. AD25-8-000 Attach. 1 (filed Oct. 17, 2025) \n(summarizing PJM’s recent load forecasting processes and enhancements).  \n43 Transmittal at 9 (footnote omitted).  \n44 Id. at 59 (“The purpose of the BYONC construct is to incent New Large Loads to facilitate the development \nof new capacity so that the PJM Region has sufficient capacity to maintain reliability without entering into a capacity \nshortage and/or having to shed existing native load customers.”).  \n45 NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114 (D.C. Cir. 2017). \n46 See, e.g., See El Paso Nat. Gas Co., L.L.C. v. FERC, 966 F.3d 842, 863 (D.C. Cir. 2020) (discussing the \nanalogous Section 4 of the Natural Gas Act and explaining that “FERC can alter a proposed rate and remain in a"},{"page":19,"startToken":5990,"endToken":6292,"text":"-19- \n2. PJM Should Reform Demand Response to Unlock the Resource Adequacy \nValue of Large Loads and Other Flexible Demand \nBefore implementing unprecedented and unworkable new curtailment regimes like IRAS, \nPJM should focus on making the most of the flexibility that can be provided through more familiar \nand jurisdictionally sound avenues, such as wholesale market demand response.   \nPJM’s current demand response regime sidelines significant quantities of flexible load.  \nThat is because it presents them with a stark choice: either be available to curtail at any time, with \nno limits on how long curtailments can last or receive no capacity value for the more limited \nflexibility they can reliably provide.  But demand response rules in PJM do not need to be an all-\nor-nothing proposition.  Instead, PJM should establish bounded demand response products with \ndefined availability parameters and accredit those products to reflect participating loads’ marginal \ncontribution to reliability.  Doing so could unlock substantial new demand-side capability. \nReforming demand response is a commonsense path to ensuring that existing residential \nand other existing retail customers continue to receive reliable service.  During the CIFP process, \nPJM expressed concern that dispatching demand response more frequently to address the \nreliability effects of load growth could lead to demand response attrition.  But if some existing \nresources cannot perform under PJM’s current availability requirements when called upon, the \nanswer is not to develop an unworkable and illegal curtailment scheme for involuntarily curtailing \ncertain large loads—i.e., IRAS.  Rather, PJM should create demand response products that require \nloads to curtail less frequently in exchange for a lower capacity value, which would facilitate \nvoluntary curtailments and unlock the capacity needed to maintain resource adequacy.    \n \nSection 4 proceeding as long as its change represents at least partial approval of the change for which the pipeline \nitself petitioned” (internal quotation marks omitted))."},{"page":20,"startToken":6292,"endToken":6598,"text":"-20- \nGoogle has been a pioneer among data centers in developing the capability to reduce \ndemand, particularly for Artificial Intelligence (“AI”) and Machine Learning (“ML”) workloads, \nin response to stressed grid conditions.47  Earlier this year, Google announced 1 GW of executed \ncontracts for demand response capability with utility partners across the United States, including \nPJM member utility Indiana Michigan Power.48 These executed agreements represent \ncontractually obligated data center demand-side capacity commitments to reduce demand during \ndefined stressed system conditions. \nYet PJM’s current rules regarding demand response make it difficult—and, in many cases, \nimpossible—for entities that own and operate large loads to realize the potential flexibility that it \ncan provide the grid.  This problem is not unique to data centers. Many commercial and industrial \ncustomers can reduce demand for defined periods or under defined conditions but cannot commit \nto effectively unbounded interruptions without jeopardizing their underlying operations or \ncustomer commitments. For data centers, most capacity is used to support enterprise and other \ncloud-based functions that demand high up times and predictable compute availability.  For those \nfunctions, suddenly dropping offline in response to high power prices simply is not an option.  The \nprospect of unpredictable and uncapped curtailment events for data centers when the services they \nprovide are most in demand is not a way to unlock the flexibility that they can provide.  The same \nbasic constraint applies across industries: flexibility can be valuable even if it is not unlimited.  \nDemand response rules that require effectively unbounded availability risk leaving substantial \n \n47 Michael Terrell, How We’re Making Data Centers More Flexible to Benefit Power Grids, Google: The \nKeyword (Aug. 4, 2025), https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/how-were-\nmaking-data-centers-more-flexible-to-benefit-power-grids/.   \n48 Michael Terrell, A New Milestone for Smart, Affordable Electricity Growth, Google: The Keyword (Mar. \n19, 2026), https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/demand-response-data-\ncenter-milestone/."},{"page":21,"startToken":6598,"endToken":6898,"text":"-21- \nflexibility on the sidelines rather than capturing the reliability value these customers can actually \nprovide.  \nTo unlock this flexibility, PJM should supplement its existing demand response offerings \nwith a bounded product that allows loads to commit to defined availability parameters, such as \nmaximum hours per year, maximum hours per event, and maximum event frequency. Existing \nDemand Resources that can meet PJM’s broader availability requirements should remain able to \ndo so and receive the corresponding capacity value. But other loads may be able to provide \nsubstantial reliability value under more limited parameters.  For Google, defined parameters would \nallow it to translate load-reduction obligations to PJM into predictable service-level commitments \nto customers that rely on its infrastructure, rather than exposing those customers to effectively \nunbounded interruption risk. Providing both bounded and unbounded options would allow PJM to \ncapture a broader range of load flexibility, with each resource accredited based on the reliability \nvalue of the commitment it actually makes.   \nIn addition, PJM should make a firm service level construct explicitly available as an option \nfor resources participating in a bounded demand response product. A firm service level would \nallow a participating load to make a clear, measurable commitment to reduce consumption to a \nspecified level when called upon, rather than measuring performance against a baseline established \nmonths or years in advance. This approach can be particularly valuable for rapidly growing loads \nundergoing multi-year ramps, for which historical or projected baselines may not accurately reflect \nactual consumption at the time of an event. PJM’s existing tariff and Business Practice Manuals \nalready provide for a firm service level construct, but Google understands that its use has been \nlimited to date. Google recognizes and agrees that resources electing more limited availability \nparameters, such as a cap on hours, should receive correspondingly lower accreditation than"},{"page":22,"startToken":6898,"endToken":7243,"text":"-22- \nresources committing to broader availability. But within those defined parameters, the resource \nwould make a firm capacity commitment and be fully accountable for performing when called. \nThe result would be accreditation that reflects the reliability contribution the resource can actually \nand reliably provide, while expanding the pool of demand-side resources available to PJM.  \nGoogle has pushed hard for rules that put these principles into practice in order to maximize \nthe flexibility that data centers can provide to the grid.  At the outset of the first Critical Issues Fast \nPath to address Large Load Additions (“CIFP”) in August of 2025, Google “encourage[d] the \nBoard and PJM to pursue reforms to existing [demand response] rules that enable any flexible \nload, particularly from data center loads, to participate in PJM’s markets.”49   Similarly, Google \nsubsequently joined Amazon, Calpine, Constellation, Microsoft, and Talen on a joint proposal that, \namong other things, would have created two new limited demand response products better aligned \nwith the operational capabilities of data centers.50   And as a member of the Data Center Coalition, \nGoogle supported the CIFP proposal of the Data Center Coalition, Governors, Exelon, and PPL, \nwhich introduced a new, voluntary flexible demand response product that would allow load to \noffer to be flexible in a range of options for a limited number of hours each day, for a total of 24 \nto 240 total hours each year.51 Those approaches offered legally durable pathways for unlocking \n \n49 PJM Interconnection, L.L.C., Critical Issue Fast Path – Large Load Additions: Stakeholder Comments \n(Aug. 28, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/postings/20250828-stakeholder-\ncomments-cifp-lla.pdf.  \n50 Amazon, Calpine, Constellation, Google, Microsoft & Talen, Joint Stakeholder Package: PJM CIFP – \nLarge Load Additions, Stage 4 (Nov. 19, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nlla/2025/20251119/20251119-item-02c---joint-stakeholder-package--executive-summary.pdf.  \n51 Governors, Data Center Coalition, Exelon Corp. & PPL Corp., Joint Proposal for CIFP LLA: Load \nForecasting, \nEnhanced \nDemand \nFlexibility, \nBYOG \n(Nov. \n19, \n2025), \nhttps://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-lla/2025/20251119/20251119-item-02d---data-center-coalition-governors-\nexelon-and-ppl-package---executive-summary.pdf."},{"page":23,"startToken":7243,"endToken":7583,"text":"-23- \nlarge quantities of additional capacity, especially from the data center driven load growth causing \nPJM to pursue measures like IRAS in the first place.   \n3. The Commission Should Order PJM to Create a Program of Genuine \nCooperative Federalism that Relies Upon State-Approved Interruptible Load \nTariffs \nAs explained above, the question at the heart of this proceeding—which retail customers \nshould be disconnected from the grid in the event demand exceeds supply—is one that is within \nexclusive state jurisdiction.  On that point, Google agrees with PJM.52   Rather than fight that fact \nor attempt to bootstrap its way into regulating matters under exclusive state jurisdiction, PJM \nshould embrace the limits of the FPA and develop an actual “program of cooperative federalism” \nthat supports states in pursuing the goals that purportedly underlie IRAS.  To do so, PJM should \nestablish protocols pursuant to which it would send a signal under certain, defined conditions to \ndisconnect retail customers that take service under state interruptible large load tariffs pursuant to \nthe rules and priorities established under those tariffs.   \nThose tariffs could resemble the model state interruptible tariff that the Virginia State \nCorporation Commission and the Data Center Coalition have committed to develop.53   The key \nfeatures should include customer eligibility and classification criteria, the circumstances and \nprocedures for interruption, applicable service rights and obligations, and other associated tariff \nprovisions.  And, in particular, states could establish service arrangements under which New Large \n \n52 Transmittal at 90-91 (“At bottom, ‘exclusive jurisdiction’ rests with the states to ensure that the appropriate \nretail customers, i.e., New Large Loads, including data centers—and not residential customers or small industrial \ncustomers—are reduced when system conditions call for PJM to require load reductions according to IRAS.” (footnote \nomitted)).  \n53 Letter from Kelsey Bagot, Chair, Va. State Corp. Comm’n & Josh Levi, President & CEO, Data Center \nCoal., to Paula Conboy, Chair, PJM Bd. of Managers & David Mills, President & CEO, PJM Interconnection, L.L.C. \n(June 30, 2026),  https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260630-\nva-scc-and-data-center-coalition-letter-re-cifp-connect-manage-reliability-backstop-procurement.pdf."},{"page":24,"startToken":7583,"endToken":7887,"text":"-24- \nLoads that bring sufficient new capacity, consistent with PJM’s definition of BYONC, receive \nfirm service while those that do not are subject to interruption.   \nA program structured in this way would provide a durable and effective path to realize the \ngoals underlying IRAS without the self-defeating uncertainty that IRAS would create.  PJM would \ndetermine whether and where load reductions are necessary to maintain bulk-system reliability; \nStates and EDs would establish the rules determining which retail customers are subject to \ninterruption and the priority among those customers.  In that way, an approach along these lines \ncould function similarly to IRAS with one notable exception:  Because these state tariffs would \nactually establish the curtailment priority—something that IRAS cannot do, as explained above—\nthey would provide the certainty needed for companies like Google to make the multi-billion dollar \ncommitments necessary to develop needed new capacity.  In addition, because an approach along \nthese lines would rely on curtailment priorities memorialized by states, it would address the undue \ndiscrimination created by determining the quality of wholesale service based on the legally \nirrelevant characteristics of retail customers.  By addressing these legal flaws, an approach along \nthese lines would also help to address the uncertainty created by the considerable litigation risk \nthat IRAS creates—i.e., the risk that led PJM’s own staff to recommend against it in the first \nplace.54     \nIn addition, to complement this approach, PJM could consider reforms to its manual load \ndump procedures to reflect the specific reliability challenges of certain large loads under stressed \ngrid conditions.  Today, under PJM’s emergency procedures, if it determines that load must be \n \n54 See PJM Interconnection, L.L.C., CIFP Connect & Manage: PJM Stage 4 Proposal Executive Summary \n(June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-\nitem-02a---pjm-stage-4-proposal---connect-and-manage---executive-summary.pdf."},{"page":25,"startToken":7887,"endToken":8185,"text":"-25- \nshed for reliability reasons, it issues a broad load-shed directive that is allocated across all affected \nEDs.55   But, because large loads are concentrated in certain parts of PJM, that approach can require \nEDs with little or no large load to shed residential customers even when substantial large-load \nreductions are available elsewhere.  Google believes that is an inequitable outcome and PJM \nshould develop practices to avoid it, if at all possible.  One potential approach is to establish a new \nphase of manual load dump whereby PJM would first call upon large loads enrolled in an initial \nload-shed phase before issuing a broader load shed directive.  PJM would only issue its broader \nload-shed directive if the load reductions from the initial load shed phase were insufficient to \nmitigate system conditions.  States, working with their EDs, would identify which customers to \ninclude as eligible for curtailment under this initial load dump phase.  Customers could also be \npermitted to participate voluntarily under state law, and Google would commit to participating in \nsuch a process to identify those conditions and circumstances.  An approach along these lines \nwould insulate residential and other customers from reliability risk associated with large-load \ngrowth, while still respecting jurisdictional bounds.  \nIII. \nCONCLUSION \nIRAS would undermine its own aims.  Instead of enhancing resource adequacy, it would \nperpetuate uncertainty and stymie the investment necessary to develop new capacity in PJM.   The \nCommission must put PJM on a better course.  It should focus on unlocking the flexibility that \ndata centers can provide while developing an actual program of cooperative federalism that would \ncreate the conditions necessary for companies like Google to make the multi-billion investments \nneeded to ensure resource adequacy, both in the near term and the long run.   \n[Signatures on next page] \n \n55 See PJM Manual 13, section 5."},{"page":26,"startToken":8185,"endToken":8253,"text":"-26- \n \nRespectfully submitted, \n \n \n/s/ Brian George \nBrian George \nSr. Lead, US Energy Markets  \nElizabeth Savage \nStrategic Negotiator \nGoogle LLC \n655 New York Ave., NW \nWashington, DC 20001 \n(202) 999-0990 \nbriangeorge@google.com  \neomsavage@google.com    \n \n \n \nMatthew Christiansen \nBryan Shpall \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006 \n(617) 598-7871 \nmchristiansen@wsgr.com \nbshpall@wsgr.com   \n \nCounsel for Google LLC \n \n \n \nDated:  September 3, 2026"},{"page":27,"startToken":8253,"endToken":8313,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \n \nDated:  September 3, 2026 \nWashington, DC \n \n \n/s/ Bryan Shpall \nBryan Shpall \nWilson Sonsini Goodrich & Rosati1700 K \nStreet NW \nFifth Floor \nWashington, DC 20006 \nbshpall@wsgr.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":1148,"startToken":0,"endToken":707},{"p":3,"at":1148,"title":"I. WHO WE ARE","method":"printed heading","endPage":3,"endAt":1660,"startToken":707,"endToken":784},{"p":3,"at":1660,"title":"II. PROTEST","method":"printed heading","endPage":3,"endAt":1674,"startToken":784,"endToken":786},{"p":3,"at":1674,"title":"A. IRAS Will Not Incentivize New Large Loads to Bring Their Own New Capacity","method":"printed heading","endPage":7,"endAt":906,"startToken":786,"endToken":2042},{"p":7,"at":906,"title":"B. IRAS Violates the FPA","method":"printed heading","endPage":25,"endAt":1343,"startToken":2042,"endToken":8088},{"p":25,"at":1343,"title":"III. CONCLUSION","method":"printed heading","endPage":27,"endAt":0,"startToken":8088,"endToken":8253},{"p":27,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":27,"endAt":404,"startToken":8253,"endToken":8313}]}